SALIENT POINTS OF THE FORM OF CONTRACTS

Standard Form of Contracts for SIA and PSSCOC PM5103 Contract Management_Group 1

Salient Points of the Standard Form of Contracts for SIA and PSSCOC
Similar (S) / Different (D) S Clause (Cl) SIA PSSCOC

S/No 1.

Salient Point Access to Enter Site

SIA

PSSCOC

Architect and representative s are allowed to have access to the works, workshops or other places at all reasonable times
2. 2.1. 1

SO and any person authorised by him are allowed to have access to the works, workshops or other places at all reasonable times

Cl 9

Cl 11.4

2.2.

3. 3.1.

3.2.

Possession of Site and Commencement of Work Time of Defined on specific Defined on Commencement of date on the Letter specific date in Work of Acceptace the Appendix If commencement If commencement date is not date is not specified, it shall specified, it shall follow the date be deemed to be stated in an agreed by parties instruction writing to or reasonable that effect from SO date Possession of As defined in The portion of Appendix, possession of site by Site contractor shall the contractor is be entitled on the adjusted by the commencement works from time to date to free and time uninterrupted possession of whole area Quality of Materials and Workmanship Quality of Work Exact conformnity As described in the and Materials contract in with any accordance with description or the instructions of specification in the SO the contract Investigation of Architect may SO shall instruct to Defects give do test as may be direction/instructio specified in the n to carry out contract or any tests such place If the investigation If the test shows indicates any breach of defective works, contract by the the contractor is contractor, the test responsible to shall be borne by Page 1 of 3

S D

Cl 10.1

Cl 12.1)

Cl 10.2

Cl 12.2

Cl 11.1

Cl 10.1(a)

Cl 11.2

Cl 10.1(b)

SALIENT POINTS OF THE FORM OF CONTRACTS


Standard Form of Contracts for SIA and PSSCOC PM5103 Contract Management_Group 1
comply architects direction at his own expense and no extension of time In other cases, contractor shall have compensation and extention of time resulting from the instruction the contractor

SO may grant extention of time and certify the cost of the test/any loss incurred as a result of a test, if the test shows otherwise

Cl 10.4

3.3.

Removal of Defective Work or Reduction of Price

4. 4.1.

Archi may give direction for removal or demolition defective work or reconstruction or replacement in accordance with the contract Variations and Valuation of Additional Payments Power of Order Directions/ Instructions given by Architect

SO may instruct to demolish/reconstru ct any defect work and/or remove any materials or goods which are not in accordance with the contract

Cl 11.3

Cl 10.7

4.2. 4.3.

Definition of Variation Measurement of Variations Valuation Price

4.4.

Generally the same with PSSCOC Done by QS with presence of Contractor/ representative Used schedule of rates as price If the Contractor fail to be present, SO write to Contractor within 14 days, and shall be binding between both. In 1 month of receipt, if the contractor claim differences, other wise they both are binding

Directions/ Instructions given by SO and the contractor shall notify within 14 days Generally the same with SIA Done by SO with presence of Contractor/ representative Used quotation as price Valuation: a) Receipt of Certificates b) Submition of valuation in 30 days c) SO do valuation within 60 days d) Any disagreement shall be submit to SO in 30 days e) SO make adjustment in next payment

Cl. 12.1

Cl. 19.2

S D

Cl. 12.2 Cl 12.3

Cl. 19.1 Cl. 20.2(1)

D D

Cl 12.4 Cl 12.3

Cl 19.3 Cl 20.2

Page 2 of 3

SALIENT POINTS OF THE FORM OF CONTRACTS


Standard Form of Contracts for SIA and PSSCOC PM5103 Contract Management_Group 1

Page 3 of 3