You are on page 1of 381

Chapter 08 - Flexible Budgets and Performance Analysis

Chapter 08 Flexible Budgets and Performance Analysis


True / False Questions

1. The main difference between a flexible budget and a static budget is that a flexible budget does not contain fixed costs. True False

2. A problem with directly comparing a static planning budget to actual costs is that this comparison fails to distinguish between differences in costs that are due to changes in activity and differences that are due to how well costs were controlled. True False

3. A planning budget is prepared before the period begins and is valid for only the planned level of activity. True False

4. A flexible budget is an estimate of what revenues and costs should have been, given the level of activity that had been planned for the period. True False

5. An unfavorable activity variance for a cost indicates that spending was higher than it should have been for the actual level of activity for the period. True False

6. The activity variance for revenue is unfavorable if the actual revenue for the period is less than the revenue in the static planning budget. True False

8-1

Chapter 08 - Flexible Budgets and Performance Analysis

7. The revenue and spending variances are the differences between the static planning budget and the flexible budget. True False

8. A revenue variance is unfavorable if the actual revenue is less than what the revenue should have been for the actual level of activity for the period. True False

9. When the activity measure is the number of units sold, the revenue variance is unfavorable if the average actual selling price is less than expected. True False

10. A favorable spending variance occurs when the actual cost is less than the amount of that cost in the flexible budget. True False

11. A flexible budget performance report should contain fixed as well as variable and mixed costs. True False

12. It may be easier to control fixed costs than variable costs. True False

13. A static planning budget is suitable for planning and for evaluating how well costs are controlled. True False

8-2

Chapter 08 - Flexible Budgets and Performance Analysis

14. If the actual level of activity is 4% less than planned, then the costs in the static budget should be reduced by 4% before comparing them to actual costs. True False

15. If the actual level of activity is 4% more than planned, then the fixed costs in the static budget should be increased by 4% before comparing them to actual costs. True False

Multiple Choice Questions

16. A flexible budget: A. classifies budget requests by activity and estimates the benefits arising from each activity. B. presents a statement of expectations for a period of time but does not present a firm commitment. C. presents the plan for only one level of activity and does not adjust to changes in the level of activity. D. presents the plan for a range of activity so that the plan can be adjusted for changes in activity levels.

17. A flexible budget is a budget that: A. is updated with actual costs as they occur during the period. B. is updated to reflect the actual level of activity during the period. C. is prepared using a computer spreadsheet application. D. contains only variable production costs.

18. Which of the following comparisons best isolates the impact that changes in prices of inputs and outputs have on performance? A. static planning budget and flexible budget B. static planning budget and actual results C. flexible budget and actual results D. master budget and static planning budget

8-3

Chapter 08 - Flexible Budgets and Performance Analysis

19. Marchi Family Inn is a bed and breakfast establishment in a converted 100-year-old mansion. The Inn's guests appreciate its gourmet breakfasts and individually decorated rooms. The Inn's overhead budget for the most recent month appears below:

The Inn's variable overhead costs are driven by the number of guests. What would be the total budgeted overhead cost for a month if the activity level is 70 guests? A. $42,460.00 B. $6,620.00 C. $7,086.15 D. $6,580.00

8-4

Chapter 08 - Flexible Budgets and Performance Analysis

20. Barringer Manufacturing Corporation has prepared the following overhead budget for next month.

The company's variable overhead costs are driven by machine-hours. What would be the total budgeted overhead cost for next month if the activity level is 7,900 machine-hours rather than 7,800 machine-hours? A. $110,710.00 B. $109,620.00 C. $110,868.00 D. $111,025.38

8-5

Chapter 08 - Flexible Budgets and Performance Analysis

21. Placek Hospital bases its budgets on patient-visits. The hospital's static budget for October appears below:

The total overhead cost at an activity level of 7,700 patient-visits per month should be: A. $129,550 B. $121,720 C. $129,100 D. $137,830

22. Dike Hotel bases its budgets on guest-days. The hotel's static budget for June appears below:

The total overhead cost at an activity level of 8,400 guest-days per month should be: A. $159,440 B. $149,650 C. $160,430 D. $172,200

8-6

Chapter 08 - Flexible Budgets and Performance Analysis

23. Blackwelder Snow Removal's cost formula for its vehicle operating cost is $1,240 per month plus $348 per snow-day. For the month of December, the company planned for activity of 12 snow-days, but the actual level of activity was 14 snow-days. The actual vehicle operating cost for the month was $6,330. The vehicle operating cost in the planning budget for December would be closest to: A. $5,426 B. $6,112 C. $5,416 D. $6,330

24. Ofarrell Snow Removal's cost formula for its vehicle operating cost is $1,840 per month plus $377 per snow-day. For the month of November, the company planned for activity of 14 snow-days, but the actual level of activity was 19 snow-days. The actual vehicle operating cost for the month was $9,280. The vehicle operating cost in the flexible budget for November would be closest to: A. $9,003 B. $7,118 C. $9,280 D. $9,660

25. Guilbault Midwifery's cost formula for its wages and salaries is $2,340 per month plus $154 per birth. For the month of June, the company planned for activity of 115 births, but the actual level of activity was 112 births. The actual wages and salaries for the month was $19,530. The wages and salaries in the planning budget for June would be closest to: A. $19,530 B. $19,588 C. $20,053 D. $20,050

8-7

Chapter 08 - Flexible Budgets and Performance Analysis

26. Dewberry Midwifery's cost formula for its wages and salaries is $1,960 per month plus $429 per birth. For the month of December, the company planned for activity of 128 births, but the actual level of activity was 130 births. The actual wages and salaries for the month was $56,020. The wages and salaries in the flexible budget for December would be closest to: A. $57,761 B. $57,730 C. $56,020 D. $56,872

27. Entler Framing's cost formula for its supplies cost is $2,250 per month plus $16 per frame. For the month of June, the company planned for activity of 502 frames, but the actual level of activity was 497 frames. The actual supplies cost for the month was $10,580. The supplies cost in the planning budget for June would be closest to: A. $10,580 B. $10,282 C. $10,686 D. $10,202

28. Rising Framing's cost formula for its supplies cost is $2,210 per month plus $10 per frame. For the month of January, the company planned for activity of 710 frames, but the actual level of activity was 705 frames. The actual supplies cost for the month was $9,500. The supplies cost in the flexible budget for January would be closest to: A. $9,260 B. $9,244 C. $9,500 D. $9,310

8-8

Chapter 08 - Flexible Budgets and Performance Analysis

29. Naval Catering uses two measures of activity, jobs and meals, in the cost formulas in its budgets and performance reports. The cost formula for catering supplies is $430 per month plus $99 per job plus $10 per meal. A typical job involves serving a number of meals to guests at a corporate function or at a host's home. The company expected its activity in March to be 12 jobs and 126 meals, but the actual activity was 9 jobs and 124 meals. The actual cost for catering supplies in March was $2,550. The catering supplies in the planning budget for March would be closest to: A. $3,400 B. $2,561 C. $2,550 D. $2,878

30. Johannsen Catering uses two measures of activity, jobs and meals, in the cost formulas in its budgets and performance reports. The cost formula for catering supplies is $310 per month plus $103 per job plus $23 per meal. A typical job involves serving a number of meals to guests at a corporate function or at a host's home. The company expected its activity in February to be 28 jobs and 187 meals, but the actual activity was 26 jobs and 192 meals. The actual cost for catering supplies in February was $7,620. The catering supplies in the flexible budget for February would be closest to: A. $7,495 B. $7,404 C. $7,620 D. $6,960

31. Venanzi Air uses two measures of activity, flights and passengers, in the cost formulas in its budgets and performance reports. The cost formula for plane operating costs is $40,720 per month plus $2,646 per flight plus $11 per passenger. The company expected its activity in September to be 62 flights and 288 passengers, but the actual activity was 64 flights and 289 passengers. The actual cost for plane operating costs in September was $214,430. The activity variance for plane operating costs in September would be closest to: A. $6,490 U B. $5,303 F C. $6,490 F D. $5,303 U

8-9

Chapter 08 - Flexible Budgets and Performance Analysis

32. Kimbril Catering uses two measures of activity, jobs and meals, in the cost formulas in its budgets and performance reports. The cost formula for catering supplies is $530 per month plus $91 per job plus $12 per meal. A typical job involves serving a number of meals to guests at a corporate function or at a host's home. The company expected its activity in January to be 27 jobs and 174 meals, but the actual activity was 31 jobs and 173 meals. The actual cost for catering supplies in January was $5,330. The activity variance for catering supplies in January would be closest to: A. $255 F B. $255 U C. $352 F D. $352 U

33. Portsche Snow Removal's cost formula for its vehicle operating cost is $2,310 per month plus $317 per snow-day. For the month of November, the company planned for activity of 18 snow-days, but the actual level of activity was 20 snow-days. The actual vehicle operating cost for the month was $8,730. The activity variance for vehicle operating cost in November would be closest to: A. $714 U B. $714 F C. $634 F D. $634 U

34. Reuer Midwifery's cost formula for its wages and salaries is $2,900 per month plus $475 per birth. For the month of March, the company planned for activity of 116 births, but the actual level of activity was 117 births. The actual wages and salaries for the month was $56,270. The activity variance for wages and salaries in March would be closest to: A. $1,730 U B. $475 F C. $475 U D. $1,730 F

8-10

Chapter 08 - Flexible Budgets and Performance Analysis

35. Embertson Framing's cost formula for its supplies cost is $1,350 per month plus $16 per frame. For the month of June, the company planned for activity of 816 frames, but the actual level of activity was 812 frames. The actual supplies cost for the month was $14,680. The activity variance for supplies cost in June would be closest to: A. $64 U B. $274 U C. $64 F D. $274 F

36. Lapinsky Air uses two measures of activity, flights and passengers, in the cost formulas in its budgets and performance reports. The cost formula for plane operating costs is $31,400 per month plus $2,148 per flight plus $7 per passenger. The company expected its activity in April to be 89 flights and 261 passengers, but the actual activity was 84 flights and 260 passengers. The actual cost for plane operating costs in April was $204,810. The spending variance for plane operating costs in April would be closest to: A. $8,842 U B. $19,589 F C. $19,589 U D. $8,842 F

37. Posson Catering uses two measures of activity, jobs and meals, in the cost formulas in its budgets and performance reports. The cost formula for catering supplies is $210 per month plus $96 per job plus $20 per meal. A typical job involves serving a number of meals to guests at a corporate function or at a host's home. The company expected its activity in March to be 20 jobs and 162 meals, but the actual activity was 17 jobs and 164 meals. The actual cost for catering supplies in March was $4,990. The spending variance for catering supplies in March would be closest to: A. $380 F B. $132 U C. $132 F D. $380 U

8-11

Chapter 08 - Flexible Budgets and Performance Analysis

38. Dunklin Medical Clinic measures its activity in terms of patient-visits. Last month, the budgeted level of activity was 1,620 patient-visits and the actual level of activity was 1,540 patient-visits. The cost formula for administrative expenses is $3.20 per patient-visit plus $14,300 per month. The actual administrative expense was $21,050. In the clinic's flexible budget performance report for last month, the spending variance for administrative expenses was: A. $118 F B. $256 F C. $1,566 U D. $1,822 U

39. Brattain Tile Installation Corporation measures its activity in terms of square feet of tile installed. Last month, the budgeted level of activity was 1,230 square feet and the actual level of activity was 1,140 square feet. The company's owner budgets for supply costs, a variable cost, at $2.10 per square foot. The actual supply cost last month was $3,260. In the company's flexible budget performance report for last month, what would have been the spending variance for supply costs? A. $257 F B. $866 U C. $677 U D. $189 F

40. Cahalane Natural Dying Corporation measures its activity in terms of skeins of yarn dyed. Last month, the budgeted level of activity was 11,600 skeins and the actual level of activity was 12,000 skeins. The company's owner budgets for dye costs, a variable cost, at $0.31 per skein. The actual dye cost last month was $3,540. In the company's flexible budget performance report for last month, what would have been the spending variance for dye costs? A. $118 U B. $124 U C. $56 F D. $180 F

8-12

Chapter 08 - Flexible Budgets and Performance Analysis

41. Gladstone Footwear Corporation's flexible budget cost formula for supplies, a variable cost, is $2.83 per unit of output. The company's flexible budget performance report for last month showed a $9,555 unfavorable spending variance for supplies. During that month, 19,500 units were produced. Budgeted activity for the month had been 19,300 units. The actual cost per unit for indirect materials must have been closest to: A. $3.32 B. $3.81 C. $2.83 D. $3.85

42. Velten Corporation's flexible budget performance report for last month shows that actual indirect materials cost, a variable cost, was $45,198 and that the spending variance for indirect materials cost was $9,114 favorable. During that month, the company worked 18,600 machine-hours. Budgeted activity for the month had been 19,000 machine-hours. The cost formula per machine-hour for indirect materials cost must have been closest to: A. $1.90 B. $2.86 C. $1.94 D. $2.92

43. Lesinski Snow Removal's cost formula for its vehicle operating cost is $1,770 per month plus $483 per snow-day. For the month of February, the company planned for activity of 19 snow-days, but the actual level of activity was 24 snow-days. The actual vehicle operating cost for the month was $13,070. The spending variance for vehicle operating cost in February would be closest to: A. $2,123 U B. $292 F C. $2,123 F D. $292 U

8-13

Chapter 08 - Flexible Budgets and Performance Analysis

44. Harville Midwifery's cost formula for its wages and salaries is $1,610 per month plus $199 per birth. For the month of March, the company planned for activity of 118 births, but the actual level of activity was 122 births. The actual wages and salaries for the month was $25,430. The spending variance for wages and salaries in March would be closest to: A. $458 F B. $338 U C. $458 U D. $338 F

45. Olivier Framing's cost formula for its supplies cost is $2,870 per month plus $16 per frame. For the month of January, the company planned for activity of 533 frames, but the actual level of activity was 534 frames. The actual supplies cost for the month was $11,080. The spending variance for supplies cost in January would be closest to: A. $334 U B. $334 F C. $318 U D. $318 F

46. Elizarraras Air uses two measures of activity, flights and passengers, in the cost formulas in its budgets and performance reports. The cost formula for plane operating costs is $39,820 per month plus $2,938 per flight plus $8 per passenger. The company expected its activity in June to be 64 flights and 229 passengers, but the actual activity was 66 flights and 225 passengers. The actual cost for plane operating costs in June was $234,570. The plane operating costs in the planning budget for June would be closest to: A. $229,684 B. $227,462 C. $234,570 D. $235,528

8-14

Chapter 08 - Flexible Budgets and Performance Analysis

47. Niforos Air uses two measures of activity, flights and passengers, in the cost formulas in its budgets and performance reports. The cost formula for plane operating costs is $41,380 per month plus $2,282 per flight plus $14 per passenger. The company expected its activity in August to be 77 flights and 264 passengers, but the actual activity was 78 flights and 261 passengers. The actual cost for plane operating costs in August was $216,740. The plane operating costs in the flexible budget for August would be closest to: A. $220,790 B. $223,030 C. $223,657 D. $216,740

Pollica Corporation's cost formula for its selling and administrative expense is $11,400 per month plus $94 per unit. For the month of March, the company planned for activity of 5,700 units, but the actual level of activity was 5,660 units. The actual selling and administrative expense for the month was $522,860.

48. The selling and administrative expense in the planning budget for March would be closest to: A. $522,860 B. $547,200 C. $543,440 D. $526,555

49. The selling and administrative expense in the flexible budget for March would be closest to: A. $547,200 B. $522,860 C. $543,360 D. $543,440

50. The activity variance for selling and administrative expense in March would be closest to: A. $24,340 F B. $24,340 U C. $3,760 U D. $3,760 F

8-15

Chapter 08 - Flexible Budgets and Performance Analysis

51. The spending variance for selling and administrative expense in March would be closest to: A. $20,580 F B. $24,340 U C. $24,340 F D. $20,580 U

Kuczenski Corporation's cost formula for its manufacturing overhead is $45,700 per month plus $53 per machine-hour. For the month of March, the company planned for activity of 6,200 machine-hours, but the actual level of activity was 6,150 machine-hours. The actual manufacturing overhead for the month was $373,630.

52. The manufacturing overhead in the planning budget for March would be closest to: A. $373,630 B. $371,650 C. $376,668 D. $374,300

53. The manufacturing overhead in the flexible budget for March would be closest to: A. $371,650 B. $371,281 C. $373,630 D. $374,300

54. The activity variance for manufacturing overhead in March would be closest to: A. $670 U B. $670 F C. $2,650 F D. $2,650 U

8-16

Chapter 08 - Flexible Budgets and Performance Analysis

55. The spending variance for manufacturing overhead in March would be closest to: A. $670 F B. $1,980 U C. $1,980 F D. $670 U

Kaaihue Detailing's cost formula for its materials and supplies is $2,750 per month plus $17 per vehicle. For the month of April, the company planned for activity of 95 vehicles, but the actual level of activity was 135 vehicles. The actual materials and supplies for the month was $4,850.

56. The materials and supplies in the planning budget for April would be closest to: A. $4,850 B. $5,045 C. $3,413 D. $4,365

57. The materials and supplies in the flexible budget for April would be closest to: A. $6,203 B. $4,850 C. $4,365 D. $5,045

58. The activity variance for materials and supplies in April would be closest to: A. $680 U B. $485 F C. $680 F D. $485 U

8-17

Chapter 08 - Flexible Budgets and Performance Analysis

59. The spending variance for materials and supplies in April would be closest to: A. $195 F B. $485 F C. $195 U D. $485 U

Deleston Boat Wash's cost formula for its cleaning equipment and supplies is $2,150 per month plus $21 per boat. For the month of September, the company planned for activity of 79 boats, but the actual level of activity was 39 boats. The actual cleaning equipment and supplies for the month was $3,110.

60. The cleaning equipment and supplies in the planning budget for September would be closest to: A. $3,110 B. $6,300 C. $2,969 D. $3,809

61. The cleaning equipment and supplies in the flexible budget for September would be closest to: A. $1,880 B. $3,110 C. $3,809 D. $2,969

62. The activity variance for cleaning equipment and supplies in September would be closest to: A. $840 F B. $699 F C. $699 U D. $840 U

8-18

Chapter 08 - Flexible Budgets and Performance Analysis

63. The spending variance for cleaning equipment and supplies in September would be closest to: A. $699 F B. $699 U C. $141 F D. $141 U

Werber Clinic uses client-visits as its measure of activity. During January, the clinic budgeted for 2,700 client-visits, but its actual level of activity was 2,730 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for January:

64. The activity variance for personnel expenses in January would be closest to: A. $661 U B. $261 U C. $261 F D. $661 F

8-19

Chapter 08 - Flexible Budgets and Performance Analysis

65. The activity variance for administrative expenses in January would be closest to: A. $12 F B. $8 F C. $12 U D. $8 U

66. The activity variance for net operating income in January would be closest to: A. $2,019 U B. $2,019 F C. $489 F D. $489 U

Feiner Clinic uses client-visits as its measure of activity. During December, the clinic budgeted for 2,200 client-visits, but its actual level of activity was 2,220 client-visits. The clinic has provided the following data concerning the formulas to be used in its budgeting:

67. The activity variance for personnel expenses in December would be closest to: A. $4,024 F B. $466 F C. $466 U D. $4,024 U

8-20

Chapter 08 - Flexible Budgets and Performance Analysis

68. The activity variance for administrative expenses in December would be closest to: A. $8 F B. $162 F C. $162 U D. $8 U

69. The activity variance for net operating income in December would be closest to: A. $690 U B. $9,670 U C. $690 F D. $9,670 F

Grundhoefer Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During April, the kennel budgeted for 2,000 tenant-days, but its actual level of activity was 1,990 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for April:

8-21

Chapter 08 - Flexible Budgets and Performance Analysis

70. The activity variance for wages and salaries in April would be closest to: A. $66 F B. $564 U C. $564 F D. $66 U

71. The activity variance for administrative expenses in April would be closest to: A. $1 F B. $79 F C. $79 U D. $1 U

72. The activity variance for net operating income in April would be closest to: A. $141 U B. $2,651 U C. $2,651 F D. $141 F

Gorley Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During February, the kennel budgeted for 3,900 tenantdays, but its actual level of activity was 3,940 tenant-days. The kennel has provided the following data concerning the formulas to be used in its budgeting:

8-22

Chapter 08 - Flexible Budgets and Performance Analysis

73. The activity variance for wages and salaries in February would be closest to: A. $1,152 U B. $1,152 F C. $292 U D. $292 F

74. The activity variance for administrative expenses in February would be closest to: A. $18 U B. $12 U C. $18 F D. $12 F

75. The activity variance for net operating income in February would be closest to: A. $368 F B. $368 U C. $632 F D. $632 U

8-23

Chapter 08 - Flexible Budgets and Performance Analysis

Enriques Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During February, the company budgeted for 5,000 units, but its actual level of activity was 4,990 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for February:

76. The activity variance for direct labor in February would be closest to: A. $61 U B. $1,081 U C. $61 F D. $1,081 F

77. The activity variance for selling and administrative expenses in February would be closest to: A. $1,308 F B. $1,308 U C. $2 U D. $2 F

8-24

Chapter 08 - Flexible Budgets and Performance Analysis

78. The activity variance for net operating income in February would be closest to: A. $2,716 F B. $2,716 U C. $176 U D. $176 F

Palczewski Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During December, the company budgeted for 5,000 units, but its actual level of activity was 4,980 units. The company has provided the following data concerning the formulas to be used in its budgeting:

79. The activity variance for direct labor in December would be closest to: A. $180 U B. $70 F C. $70 U D. $180 F

80. The activity variance for selling and administrative expenses in December would be closest to: A. $14 U B. $14 F C. $1,206 F D. $1,206 U

8-25

Chapter 08 - Flexible Budgets and Performance Analysis

81. The activity variance for net operating income in December would be closest to: A. $2,372 U B. $328 F C. $2,372 F D. $328 U

Burget Clinic uses client-visits as its measure of activity. During July, the clinic budgeted for 2,100 client-visits, but its actual level of activity was 2,110 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for July:

82. The revenue variance for July would be closest to: A. $2,581 F B. $2,110 U C. $2,110 F D. $2,581 U

8-26

Chapter 08 - Flexible Budgets and Performance Analysis

83. The spending variance for medical supplies in July would be closest to: A. $580 U B. $645 U C. $645 F D. $580 F

84. The spending variance for occupancy expenses in July would be closest to: A. $265 F B. $280 U C. $280 F D. $265 U

85. The overall revenue and spending variance (i.e., the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for July would be closest to: A. $4,508 F B. $4,290 U C. $4,290 F D. $4,508 U

8-27

Chapter 08 - Flexible Budgets and Performance Analysis

Razor Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During November, the kennel budgeted for 3,000 tenant-days, but its actual level of activity was 3,010 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for November:

86. The revenue variance for November would be closest to: A. $1,607 U B. $1,910 U C. $1,607 F D. $1,910 F

87. The spending variance for expendables in November would be closest to: A. $240 F B. $354 F C. $240 U D. $354 U

8-28

Chapter 08 - Flexible Budgets and Performance Analysis

88. The spending variance for facility expenses in November would be closest to: A. $416 U B. $416 F C. $390 F D. $390 U

89. The overall revenue and spending variance (i.e., the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for November would be closest to: A. $3,520 F B. $3,428 U C. $3,520 U D. $3,428 F

Vandall Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During April, the company budgeted for 7,300 units, but its actual level of activity was 7,340 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for April:

8-29

Chapter 08 - Flexible Budgets and Performance Analysis

90. The revenue variance for April would be closest to: A. $4,274 F B. $5,690 F C. $5,690 U D. $4,274 U

91. The spending variance for direct materials in April would be closest to: A. $210 U B. $210 F C. $426 U D. $426 F

92. The spending variance for manufacturing overhead in April would be closest to: A. $1,600 U B. $1,648 F C. $1,600 F D. $1,648 U

93. The overall revenue and spending variance (i.e., the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for April would be closest to: A. $6,144 F B. $6,740 U C. $6,740 F D. $6,144 U

8-30

Chapter 08 - Flexible Budgets and Performance Analysis

Moorhouse Clinic uses client-visits as its measure of activity. During December, the clinic budgeted for 3,700 client-visits, but its actual level of activity was 3,690 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for December:

94. The personnel expenses in the planning budget for December would be closest to: A. $51,009 B. $51,147 C. $53,370 D. $53,299

95. The medical supplies in the flexible budget for December would be closest to: A. $18,150 B. $17,472 C. $17,378 D. $18,105

8-31

Chapter 08 - Flexible Budgets and Performance Analysis

96. The activity variance for personnel expenses in December would be closest to: A. $2,361 U B. $71 U C. $71 F D. $2,361 F

97. The revenue variance for December would be closest to: A. $3,680 U B. $3,429 F C. $3,429 U D. $3,680 F

98. The spending variance for medical supplies in December would be closest to: A. $680 F B. $680 U C. $725 U D. $725 F

8-32

Chapter 08 - Flexible Budgets and Performance Analysis

Cotty Clinic uses client-visits as its measure of activity. During March, the clinic budgeted for 3,000 client-visits, but its actual level of activity was 2,970 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for March:

99. The administrative expenses in the planning budget for March would be closest to: A. $6,288 B. $6,300 C. $6,418 D. $6,483

100. The occupancy expenses in the flexible budget for March would be closest to: A. $13,400 B. $12,770 C. $13,349 D. $13,029

8-33

Chapter 08 - Flexible Budgets and Performance Analysis

101. The activity variance for administrative expenses in March would be closest to: A. $118 U B. $12 F C. $118 F D. $12 U

102. The spending variance for medical supplies in March would be closest to: A. $1,050 U B. $1,050 F C. $1,263 F D. $1,263 U

Murphree Clinic uses client-visits as its measure of activity. During April, the clinic budgeted for 3,300 client-visits, but its actual level of activity was 3,350 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for April:

8-34

Chapter 08 - Flexible Budgets and Performance Analysis

103. The net operating income in the planning budget for April would be closest to: A. $14,425 B. $19,519 C. $13,550 D. $20,115

104. The net operating income in the flexible budget for April would be closest to: A. $20,115 B. $19,519 C. $14,425 D. $13,550

105. The activity variance for net operating income in April would be closest to: A. $875 F B. $6,265 F C. $875 U D. $6,265 U

106. The overall revenue and spending variance (i.e., the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for April would be closest to: A. $5,390 F B. $6,265 U C. $5,390 U D. $6,265 F

8-35

Chapter 08 - Flexible Budgets and Performance Analysis

Henkel Clinic uses client-visits as its measure of activity. During November, the clinic budgeted for 3,600 client-visits, but its actual level of activity was 3,550 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for November:

107. The personnel expenses in the planning budget for November would be closest to: A. $74,120 B. $71,432 C. $70,440 D. $74,640

108. The occupancy expenses in the flexible budget for November would be closest to: A. $14,422 B. $14,831 C. $15,325 D. $15,400

8-36

Chapter 08 - Flexible Budgets and Performance Analysis

109. The activity variance for administrative expenses in November would be closest to: A. $215 U B. $215 F C. $5 F D. $5 U

110. The spending variance for occupancy expenses in November would be closest to: A. $775 U B. $700 F C. $775 F D. $700 U

Hoeper Clinic uses client-visits as its measure of activity. During January, the clinic budgeted for 2,600 client-visits, but its actual level of activity was 2,570 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for January:

8-37

Chapter 08 - Flexible Budgets and Performance Analysis

111. The administrative expenses in the planning budget for January would be closest to: A. $5,047 B. $4,960 C. $5,106 D. $4,957

112. The medical supplies in the flexible budget for January would be closest to: A. $19,733 B. $18,932 C. $19,940 D. $19,377

113. The activity variance for personnel expenses in January would be closest to: A. $1,416 U B. $486 F C. $1,416 F D. $486 U

114. The spending variance for medical supplies in January would be closest to: A. $787 F B. $787 U C. $580 F D. $580 U

8-38

Chapter 08 - Flexible Budgets and Performance Analysis

Legard Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During January, the kennel budgeted for 2,600 tenantdays, but its actual level of activity was 2,620 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for January:

115. The wages and salaries in the planning budget for January would be closest to: A. $24,040 B. $23,755 C. $23,938 D. $24,198

116. The expendables in the flexible budget for January would be closest to: A. $35,946 B. $36,704 C. $35,680 D. $37,271

8-39

Chapter 08 - Flexible Budgets and Performance Analysis

117. The activity variance for wages and salaries in January would be closest to: A. $158 F B. $158 U C. $102 U D. $102 F

118. The revenue variance for January would be closest to: A. $750 U B. $40 U C. $40 F D. $750 F

119. The spending variance for expendables in January would be closest to: A. $1,040 F B. $1,306 F C. $1,040 U D. $1,306 U

8-40

Chapter 08 - Flexible Budgets and Performance Analysis

Drabant Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During February, the kennel budgeted for 2,000 tenant-days, but its actual level of activity was 2,040 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for February:

120. The administrative expenses in the planning budget for February would be closest to: A. $7,500 B. $7,252 C. $7,110 D. $7,512

121. The facility expenses in the flexible budget for February would be closest to: A. $13,700 B. $13,401 C. $13,788 D. $12,880

8-41

Chapter 08 - Flexible Budgets and Performance Analysis

122. The activity variance for administrative expenses in February would be closest to: A. $248 U B. $248 F C. $12 U D. $12 F

123. The spending variance for expendables in February would be closest to: A. $836 F B. $1,360 F C. $836 U D. $1,360 U

Tosta Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During May, the kennel budgeted for 2,100 tenant-days, but its actual level of activity was 2,050 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for May:

8-42

Chapter 08 - Flexible Budgets and Performance Analysis

124. The net operating income in the planning budget for May would be closest to: A. $9,140 B. $11,626 C. $12,200 D. $8,420

125. The net operating income in the flexible budget for May would be closest to: A. $9,140 B. $8,420 C. $11,626 D. $12,200

126. The activity variance for net operating income in May would be closest to: A. $2,770 U B. $720 U C. $720 F D. $2,770 F

127. The overall revenue and spending variance (i.e., the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for May would be closest to: A. $3,490 F B. $2,770 F C. $3,490 U D. $2,770 U

8-43

Chapter 08 - Flexible Budgets and Performance Analysis

Stent Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During February, the kennel budgeted for 3,000 tenantdays, but its actual level of activity was 2,950 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for February:

128. The wages and salaries in the planning budget for February would be closest to: A. $22,670 B. $24,183 C. $23,780 D. $23,000

129. The facility expenses in the flexible budget for February would be closest to: A. $16,000 B. $15,875 C. $15,738 D. $16,276

8-44

Chapter 08 - Flexible Budgets and Performance Analysis

130. The activity variance for administrative expenses in February would be closest to: A. $150 U B. $20 U C. $20 F D. $150 F

131. The spending variance for facility expenses in February would be closest to: A. $130 U B. $130 F C. $5 U D. $5 F

Rippelmeyer Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During June, the kennel budgeted for 3,600 tenant-days, but its actual level of activity was 3,550 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for June:

8-45

Chapter 08 - Flexible Budgets and Performance Analysis

132. The administrative expenses in the planning budget for June would be closest to: A. $7,996 B. $7,885 C. $7,555 D. $7,560

133. The expendables in the flexible budget for June would be closest to: A. $33,666 B. $34,270 C. $34,740 D. $34,621

134. The activity variance for wages and salaries in June would be closest to: A. $310 F B. $110 F C. $310 U D. $110 U

135. The spending variance for expendables in June would be closest to: A. $130 F B. $600 U C. $130 U D. $600 F

8-46

Chapter 08 - Flexible Budgets and Performance Analysis

Baugus Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During August, the company budgeted for 6,900 units, but its actual level of activity was 6,950 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for August:

136. The direct labor in the planning budget for August would be closest to: A. $27,760 B. $29,190 C. $27,560 D. $28,980

137. The direct materials in the flexible budget for August would be closest to: A. $127,650 B. $128,575 C. $127,581 D. $129,436

8-47

Chapter 08 - Flexible Budgets and Performance Analysis

138. The activity variance for direct labor in August would be closest to: A. $1,220 F B. $210 U C. $210 F D. $1,220 U

139. The revenue variance for August would be closest to: A. $1,450 F B. $1,450 U C. $430 F D. $430 U

140. The spending variance for direct materials in August would be closest to: A. $70 F B. $855 U C. $70 U D. $855 F

8-48

Chapter 08 - Flexible Budgets and Performance Analysis

Lampert Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During March, the company budgeted for 6,100 units, but its actual level of activity was 6,060 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for March:

141. The selling and administrative expenses in the planning budget for March would be closest to: A. $26,560 B. $27,647 C. $27,466 D. $26,536

142. The manufacturing overhead in the flexible budget for March would be closest to: A. $48,822 B. $51,384 C. $51,440 D. $49,468

8-49

Chapter 08 - Flexible Budgets and Performance Analysis

143. The activity variance for selling and administrative expenses in March would be closest to: A. $906 U B. $906 F C. $24 U D. $24 F

144. The spending variance for direct materials in March would be closest to: A. $900 F B. $900 U C. $1,376 U D. $1,376 F

Woofter Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During January, the company budgeted for 7,600 units, but its actual level of activity was 7,560 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for January:

8-50

Chapter 08 - Flexible Budgets and Performance Analysis

145. The net operating income in the planning budget for January would be closest to: A. $16,410 B. $16,238 C. $28,604 D. $29,140

146. The net operating income in the flexible budget for January would be closest to: A. $28,604 B. $16,238 C. $16,410 D. $29,140

147. The activity variance for net operating income in January would be closest to: A. $12,816 F B. $12,816 U C. $536 F D. $536 U

148. The overall revenue and spending variance (i.e., the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for January would be closest to: A. $12,816 F B. $12,280 U C. $12,816 U D. $12,280 F

8-51

Chapter 08 - Flexible Budgets and Performance Analysis

Buffaloe Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During August, the company budgeted for 5,200 units, but its actual level of activity was 5,250 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for August:

149. The direct labor in the planning budget for August would be closest to: A. $40,040 B. $41,015 C. $40,425 D. $40,624

150. The manufacturing overhead in the flexible budget for August would be closest to: A. $53,919 B. $55,525 C. $52,896 D. $55,460

8-52

Chapter 08 - Flexible Budgets and Performance Analysis

151. The activity variance for selling and administrative expenses in August would be closest to: A. $690 F B. $690 U C. $20 F D. $20 U

152. The spending variance for manufacturing overhead in August would be closest to: A. $2,055 F B. $2,055 U C. $2,120 U D. $2,120 F

Luc Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During February, the company budgeted for 5,000 units, but its actual level of activity was 4,950 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for February:

8-53

Chapter 08 - Flexible Budgets and Performance Analysis

153. The selling and administrative expenses in the planning budget for February would be closest to: A. $30,490 B. $30,495 C. $30,500 D. $30,190

154. The direct materials in the flexible budget for February would be closest to: A. $91,575 B. $95,985 C. $92,500 D. $94,075

155. The activity variance for direct labor in February would be closest to: A. $340 U B. $760 F C. $340 F D. $760 U

156. The spending variance for direct materials in February would be closest to: A. $3,450 F B. $2,525 U C. $3,450 U D. $2,525 F

8-54

Chapter 08 - Flexible Budgets and Performance Analysis

Worden Hospital bases its budgets on patient-visits. The hospital's static budget for February appears below:

157. The total variable cost at the activity level of 4,400 patient-visits per month should be: A. $85,140 B. $87,120 C. $65,120 D. $63,640

158. The total fixed cost at the activity level of 4,700 patient-visits per month should be: A. $162,620 B. $148,780 C. $93,060 D. $85,140

159. The total cost at the activity level of 4,600 patient-visits per month should be: A. $153,720 B. $148,780 C. $153,220 D. $159,160

8-55

Chapter 08 - Flexible Budgets and Performance Analysis

Dwelmont Hotel bases its budgets on guest-days. The hotel's static budget for May appears below:

160. The total variable cost at the activity level of 2,600 guest-days per month should be: A. $36,920 B. $32,660 C. $45,540 D. $51,480

161. The total fixed cost at the activity level of 2,900 guest-days per month should be: A. $78,200 B. $57,420 C. $98,600 D. $45,540

162. The total cost at the activity level of 2,800 guest-days per month should be: A. $95,200 B. $86,230 C. $85,300 D. $78,200

8-56

Chapter 08 - Flexible Budgets and Performance Analysis

Springmeyer Clinic uses client-visits as its measure of activity. During August, the clinic budgeted for 2,900 client-visits, but its actual level of activity was 2,940 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for August:

163. The personnel expenses in the planning budget for August would be closest to: A. $69,600 B. $73,800 C. $70,560 D. $73,200

164. The administrative expenses in the planning budget for August would be closest to: A. $7,594 B. $7,590 C. $7,165 D. $7,264

8-57

Chapter 08 - Flexible Budgets and Performance Analysis

165. The net operating income in the planning budget for August would be closest to: A. $15,416 B. $11,878 C. $11,557 D. $14,560

Weisgarber Clinic uses client-visits as its measure of activity. During August, the clinic budgeted for 3,900 client-visits, but its actual level of activity was 3,850 client-visits. The clinic has provided the following data concerning the formulas to be used in its budgeting for August:

166. The personnel expenses in the planning budget for August would be closest to: A. $83,940 B. $88,444 C. $83,310 D. $87,310

167. The administrative expenses in the planning budget for August would be closest to: A. $7,780 B. $8,144 C. $8,040 D. $7,770

8-58

Chapter 08 - Flexible Budgets and Performance Analysis

168. The net operating income in the planning budget for August would be closest to: A. $15,615 B. $15,217 C. $18,705 D. $19,670

Smithson Clinic uses client-visits as its measure of activity. During May, the clinic budgeted for 3,300 client-visits, but its actual level of activity was 3,270 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for May:

169. The medical supplies in the flexible budget for May would be closest to: A. $14,907 B. $15,488 C. $15,207 D. $15,030

8-59

Chapter 08 - Flexible Budgets and Performance Analysis

170. The occupancy expenses in the flexible budget for May would be closest to: A. $14,334 B. $13,840 C. $13,786 D. $14,599

171. The net operating income in the flexible budget for May would be closest to: A. $9,731 B. $9,555 C. $10,293 D. $10,770

Mah Clinic uses client-visits as its measure of activity. During April, the clinic budgeted for 3,800 client-visits, but its actual level of activity was 3,750 client-visits. The clinic has provided the following data concerning the formulas to be used in its budgeting:

172. The medical supplies in the flexible budget for April would be closest to: A. $21,340 B. $22,600 C. $22,325 D. $21,913

8-60

Chapter 08 - Flexible Budgets and Performance Analysis

173. The occupancy expenses in the flexible budget for April would be closest to: A. $15,575 B. $15,660 C. $14,975 D. $15,377

174. The net operating income in the flexible budget for April would be closest to: A. $12,550 B. $14,987 C. $13,420 D. $14,595

Lauser Clinic uses client-visits as its measure of activity. During July, the clinic budgeted for 3,700 client-visits, but its actual level of activity was 3,690 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for July:

8-61

Chapter 08 - Flexible Budgets and Performance Analysis

175. The personnel expenses in the planning budget for July would be closest to: A. $54,730 B. $54,641 C. $52,341 D. $52,483

176. The occupancy expenses in the flexible budget for July would be closest to: A. $12,466 B. $12,991 C. $12,921 D. $12,480

177. The net operating income in the flexible budget for July would be closest to: A. $17,215 B. $17,122 C. $11,140 D. $11,018

Higgenbotham Clinic uses client-visits as its measure of activity. During May, the clinic budgeted for 3,600 client-visits, but its actual level of activity was 3,580 client-visits. The clinic has provided the following data concerning the formulas to be used in its budgeting for May:

8-62

Chapter 08 - Flexible Budgets and Performance Analysis

178. The administrative expenses in the planning budget for May would be closest to: A. $5,261 B. $5,440 C. $5,232 D. $5,432

179. The net operating income in the planning budget for May would be closest to: A. $18,274 B. $13,920 C. $18,479 D. $13,616

180. The medical supplies in the flexible budget for May would be closest to: A. $20,164 B. $19,340 C. $19,941 D. $19,242

8-63

Chapter 08 - Flexible Budgets and Performance Analysis

Jauron Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During September, the kennel budgeted for 2,300 tenant-days, but its actual level of activity was 2,310 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for September:

181. The wages and salaries in the planning budget for September would be closest to: A. $13,741 B. $13,682 C. $13,781 D. $13,730

182. The administrative expenses in the planning budget for September would be closest to: A. $7,362 B. $7,181 C. $7,360 D. $7,212

8-64

Chapter 08 - Flexible Budgets and Performance Analysis

183. The net operating income in the planning budget for September would be closest to: A. $10,772 B. $6,979 C. $10,866 D. $6,870

Lutts Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During November, the kennel budgeted for 3,800 tenant-days, but its actual level of activity was 3,850 tenant-days. The kennel has provided the following data concerning the formulas to be used in its budgeting:

184. The wages and salaries in the planning budget for November would be closest to: A. $27,610 B. $27,280 C. $28,238 D. $28,610

185. The administrative expenses in the planning budget for November would be closest to: A. $7,310 B. $7,520 C. $7,540 D. $7,215

8-65

Chapter 08 - Flexible Budgets and Performance Analysis

186. The net operating income in the planning budget for November would be closest to: A. $12,720 B. $9,648 C. $9,904 D. $13,115

Swader Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During March, the kennel budgeted for 2,900 tenantdays, but its actual level of activity was 2,930 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for March:

187. The expendables in the flexible budget for March would be closest to: A. $25,905 B. $25,650 C. $27,274 D. $26,719

8-66

Chapter 08 - Flexible Budgets and Performance Analysis

188. The facility expenses in the flexible budget for March would be closest to: A. $20,700 B. $20,369 C. $20,793 D. $20,820

189. The net operating income in the flexible budget for March would be closest to: A. $12,522 B. $12,267 C. $9,414 D. $9,120

Whetstine Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During September, the kennel budgeted for 3,200 tenant-days, but its actual level of activity was 3,180 tenant-days. The kennel has provided the following data concerning the formulas to be used in its budgeting:

190. The expendables in the flexible budget for September would be closest to: A. $27,630 B. $27,864 C. $27,517 D. $27,800

8-67

Chapter 08 - Flexible Budgets and Performance Analysis

191. The facility expenses in the flexible budget for September would be closest to: A. $21,320 B. $21,238 C. $21,513 D. $21,784

192. The net operating income in the flexible budget for September would be closest to: A. $8,548 B. $4,967 C. $5,029 D. $8,720

Kalinowski Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During February, the kennel budgeted for 2,300 tenant-days, but its actual level of activity was 2,320 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for February:

8-68

Chapter 08 - Flexible Budgets and Performance Analysis

193. The wages and salaries in the planning budget for February would be closest to: A. $15,570 B. $16,197 C. $16,338 D. $15,688

194. The facility expenses in the flexible budget for February would be closest to: A. $18,680 B. $19,046 C. $19,379 D. $18,772

195. The net operating income in the flexible budget for February would be closest to: A. $10,370 B. $10,608 C. $7,642 D. $7,775

Laboe Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During February, the kennel budgeted for 2,900 tenantdays, but its actual level of activity was 2,940 tenant-days. The kennel has provided the following data concerning the formulas to be used in its budgeting:

8-69

Chapter 08 - Flexible Budgets and Performance Analysis

196. The administrative expenses in the planning budget for February would be closest to: A. $7,814 B. $7,770 C. $7,922 D. $7,782

197. The net operating income in the planning budget for February would be closest to: A. $7,191 B. $7,391 C. $7,900 D. $8,260

198. The expendables in the flexible budget for February would be closest to: A. $26,990 B. $27,354 C. $27,021 D. $27,772

8-70

Chapter 08 - Flexible Budgets and Performance Analysis

Dantuono Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During November, the company budgeted for 7,700 units, but its actual level of activity was 7,720 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for November:

199. The direct labor in the planning budget for November would be closest to: A. $44,004 B. $42,744 C. $42,633 D. $43,890

200. The selling and administrative expenses in the planning budget for November would be closest to: A. $30,490 B. $29,974 C. $30,504 D. $29,896

8-71

Chapter 08 - Flexible Budgets and Performance Analysis

201. The net operating income in the planning budget for November would be closest to: A. $35,093 B. $29,340 C. $35,275 D. $29,604

Menson Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During December, the company budgeted for 5,800 units, but its actual level of activity was 5,830 units. The company has provided the following data concerning the formulas to be used in its budgeting:

202. The direct labor in the planning budget for December would be closest to: A. $46,057 B. $45,820 C. $43,927 D. $43,701

203. The selling and administrative expenses in the planning budget for December would be closest to: A. $24,898 B. $24,880 C. $23,988 D. $23,865

8-72

Chapter 08 - Flexible Budgets and Performance Analysis

204. The net operating income in the planning budget for December would be closest to: A. $19,788 B. $24,979 C. $19,380 D. $25,238

Nasson Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During August, the company budgeted for 6,700 units, but its actual level of activity was 6,730 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for August:

205. The direct materials in the flexible budget for August would be closest to: A. $71,020 B. $71,338 C. $72,913 D. $72,264

8-73

Chapter 08 - Flexible Budgets and Performance Analysis

206. The manufacturing overhead in the flexible budget for August would be closest to: A. $55,358 B. $55,855 C. $55,076 D. $55,040

207. The net operating income in the flexible budget for August would be closest to: A. $22,506 B. $18,317 C. $17,930 D. $22,708

Poulsen Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During July, the company budgeted for 7,300 units, but its actual level of activity was 7,270 units. The company has provided the following data concerning the formulas to be used in its budgeting:

208. The direct materials in the flexible budget for July would be closest to: A. $68,338 B. $70,298 C. $68,620 D. $70,879

8-74

Chapter 08 - Flexible Budgets and Performance Analysis

209. The manufacturing overhead in the flexible budget for July would be closest to: A. $47,190 B. $47,151 C. $45,344 D. $45,719

210. The net operating income in the flexible budget for July would be closest to: A. $9,234 B. $9,310 C. $19,262 D. $19,580

Witherington Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During June, the company budgeted for 7,800 units, but its actual level of activity was 7,850 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for June:

8-75

Chapter 08 - Flexible Budgets and Performance Analysis

211. The direct labor in the planning budget for June would be closest to: A. $32,970 B. $32,760 C. $34,310 D. $34,091

212. The manufacturing overhead in the flexible budget for June would be closest to: A. $57,435 B. $54,794 C. $57,380 D. $55,498

213. The net operating income in the flexible budget for June would be closest to: A. $34,017 B. $33,585 C. $29,520 D. $30,190

Manago Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During March, the company budgeted for 5,300 units, but its actual level of activity was 5,310 units. The company has provided the following data concerning the formulas to be used in its budgeting:

8-76

Chapter 08 - Flexible Budgets and Performance Analysis

214. The selling and administrative expenses in the planning budget for March would be closest to: A. $25,640 B. $26,199 C. $26,248 D. $25,648

215. The net operating income in the planning budget for March would be closest to: A. $11,705 B. $21,877 C. $21,710 D. $11,749

216. The direct materials in the flexible budget for March would be closest to: A. $73,278 B. $73,929 C. $73,140 D. $74,208

Bessey Hospital bases its budgets on patient-visits. The hospital's static planning budget for January appears below:

Actual results for the month were:

8-77

Chapter 08 - Flexible Budgets and Performance Analysis

217. The spending variance for supplies costs in the flexible budget performance report for the month is: A. $4,180 F B. $4,180 U C. $2,560 F D. $2,560 U

218. The spending variance for laundry costs in the flexible budget performance report for the month is: A. $730 F B. $2,470 F C. $730 U D. $2,470 U

219. The spending variance for occupancy costs in the flexible budget performance report for the month is: A. $330 F B. $2,090 F C. $330 U D. $2,090 U

8-78

Chapter 08 - Flexible Budgets and Performance Analysis

Salling Corporation bases its budgets on machine-hours. The company's static planning budget for May appears below:

Actual results for the month were:

220. The spending variance for supplies costs in the flexible budget performance report for the month should be: A. $1,340 U B. $1,340 F C. $460 U D. $460 F

221. The spending variance for power costs in the flexible budget performance report for the month should be: A. $310 U B. $310 F C. $820 U D. $820 F

8-79

Chapter 08 - Flexible Budgets and Performance Analysis

222. The spending variance for equipment depreciation in the flexible budget performance report for the month should be: A. $540 F B. $10 F C. $10 U D. $540 U

Genito Corporation's static planning budget for October appears below. The company bases its budgets on machine-hours.

In October, the actual number of machine-hours was 8,800, the actual supplies cost was $69,450, the actual power cost was $34,190, the actual salaries cost was $86,490, and the actual equipment depreciation was $37,600.

223. The spending variance for supplies cost in the flexible budget performance report for the month should be: A. $4,500 F B. $7,110 F C. $7,110 U D. $4,500 U

224. The spending variance for power cost in the flexible budget performance report for the month should be: A. $1,510 F B. $2,770 U C. $1,510 U D. $2,770 F

8-80

Chapter 08 - Flexible Budgets and Performance Analysis

225. The spending variance for equipment depreciation in the flexible budget performance report for the month should be: A. $200 U B. $1,120 F C. $200 F D. $1,120 U

Lauter Printing uses two measures of activity, press runs and book set-ups, in the cost formulas in its budgets and performance reports. The cost formula for wages and salaries is $5,300 per month plus $480 per press run plus $1,080 per book set-up. The company expected its activity in October to be 169 press runs and 64 book set-ups, but the actual activity was 167 press runs and 60 book set-ups. The actual cost for wages and salaries in October was $155,690.

226. The wages and salaries in the planning budget for October would be closest to: A. $157,555 B. $155,690 C. $150,260 D. $155,540

227. The wages and salaries in the flexible budget for October would be closest to: A. $155,540 B. $155,690 C. $150,260 D. $153,699

228. The activity variance for wages and salaries in October would be closest to: A. $5,280 U B. $150 U C. $150 F D. $5,280 F

8-81

Chapter 08 - Flexible Budgets and Performance Analysis

229. The spending variance for wages and salaries in October would be closest to: A. $5,430 U B. $150 U C. $5,430 F D. $150 F

Spraque Air uses two measures of activity, flights and passengers, in the cost formulas in its budgets and performance reports. The cost formula for plane operating costs is $40,520 per month plus $2,733 per flight plus $11 per passenger. The company expected its activity in June to be 71 flights and 207 passengers, but the actual activity was 70 flights and 205 passengers. The actual cost for plane operating costs in June was $239,580.

230. The plane operating costs in the planning budget for June would be closest to: A. $239,580 B. $236,840 C. $234,085 D. $243,003

231. The plane operating costs in the flexible budget for June would be closest to: A. $233,504 B. $234,085 C. $239,580 D. $236,840

232. The activity variance for plane operating costs in June would be closest to: A. $2,755 U B. $2,755 F C. $2,740 F D. $2,740 U

8-82

Chapter 08 - Flexible Budgets and Performance Analysis

233. The spending variance for plane operating costs in June would be closest to: A. $2,740 U B. $5,495 U C. $5,495 F D. $2,740 F

8-83

Chapter 08 - Flexible Budgets and Performance Analysis


Essay Questions

234. Immen Corporation bases its budgets on the activity measure customers served. During May, the company planned to serve 38,000 customers. The company has provided the following data concerning the formulas it uses in its budgeting:

The company has also furnished its income statement for May:

Required: Prepare a report showing the company's activity variances for May. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

8-84

Chapter 08 - Flexible Budgets and Performance Analysis

235. Faggs Corporation bases its budgets on the activity measure customers served. During December, the company planned to serve 33,000 customers, but actually served 36,000 customers. The company has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare a report showing the company's activity variances for December. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

236. Brynteson Corporation bases its budgets on the activity measure customers served. During September, the company planned to serve 24,000 customers, but actually served 19,000 customers. The company uses the following revenue and cost formulas in its budgeting, where q is the number of customers served: Revenue: $2.90q Wages and salaries: $24,700 + $0.90q Supplies: $0.40q Insurance: $4,900 Miscellaneous: $2,800 + $0.10q Required: Prepare a report showing the company's activity variances for September. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

8-85

Chapter 08 - Flexible Budgets and Performance Analysis

237. Domin Corporation bases its budgets on the activity measure customers served. During April, the company planned to serve 31,000 customers, but actually served 35,000 customers. Revenue is $4.80 per customer served. Wages and salaries are $33,000 per month plus $1.60 per customer served. Supplies are $1.00 per customer served. Insurance is $12,200 per month. Miscellaneous expenses are $7,400 per month plus $0.20 per customer served. Required: Prepare a report showing the company's activity variances for April. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

8-86

Chapter 08 - Flexible Budgets and Performance Analysis

238. Fasano Clinic bases its budgets on the activity measure patient-visits. During April, the clinic planned for 3,800 patient-visits. The clinic has provided the following data concerning the formulas it uses in its budgeting:

The clinic has also furnished its income statement for April:

Required: Prepare a report showing the clinic's activity variances for April.

8-87

Chapter 08 - Flexible Budgets and Performance Analysis

239. Mulvehill Clinic bases its budgets on the activity measure patient-visits. During June, the clinic planned for 3,000 patient-visits, but the actual level of activity was 3,400 patient-visits. The clinic has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare a report showing the clinic's activity variances for June. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

240. Mccarter Clinic bases its budgets on the activity measure patient-visits. During April, the clinic planned for 2,700 patient-visits, but its actual level of activity was 2,400 patient-visits. The clinic has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare a report showing the clinic's activity variances for April. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

8-88

Chapter 08 - Flexible Budgets and Performance Analysis

241. Delamarter Clinic bases its budgets on the activity measure patient-visits. During June, the clinic planned for 2,600 patient-visits, but its actual level of activity was 3,100 patientvisits. Revenue should be $53.40 per patient-visit. Personnel expenses should be $39,700 per month plus $12.60 per patient-visit. Medical supplies should be $1,800 per month plus $10.40 per patient-visit. Occupancy expenses should be $8,200 per month plus $2.30 per patientvisit. Administrative expenses should be $6,100 per month plus $0.20 per patient-visit. Required: Prepare a report showing the clinic's activity variances for June. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

8-89

Chapter 08 - Flexible Budgets and Performance Analysis

242. Alicuben Memorial Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for October was based on 2,200 meals, but the diner actually served 2,000 meals. The diner's director has provided the following cost formulas to use in budgets:

The director has also provided the diner's statement of actual expenses for the month:

Required: Prepare a report showing the activity variances for each of the expenses and for total expenses for October. Label each variance as favorable (F) or unfavorable (U).

8-90

Chapter 08 - Flexible Budgets and Performance Analysis

243. Aslanian Memorial Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for November was based on 2,200 meals, but the diner actually served 2,700 meals. The diner's director has provided the following cost formulas to use in budgets:

Required: Prepare a report showing the activity variances for each of the expenses and for total expenses for November. Label each variance as favorable (F) or unfavorable (U). Label each variance as favorable (F) or unfavorable (U).

8-91

Chapter 08 - Flexible Budgets and Performance Analysis

244. Mulry Urban Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for September was based on 3,000 meals, but the diner actually served 2,800 meals. The diner's director has provided the following cost data to use in the budget: groceries, $2.45 per meal; kitchen operations, $4,900 per month plus $1.65 per meal; administrative expenses, $3,600 per month plus $0.60 per meal; and fundraising expenses, $1,200 per month. The director has also provided the diner's statement of actual expenses for the month:

Required: Prepare a report showing the activity variances for each of the expenses and for total expenses for September.

8-92

Chapter 08 - Flexible Budgets and Performance Analysis

245. Flicker Urban Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for December was based on 2,400 meals, but the diner actually served 2,300 meals. The diner's director has provided the following cost data to use in the budget: groceries, $2.00 per meal; kitchen operations, $5,100 per month plus $1.85 per meal; administrative expenses, $2,900 per month plus $0.65 per meal; and fundraising expenses, $1,000 per month. Required: Prepare a report showing the activity variances for each of the expenses and for total expenses for December. Label each variance as favorable (F) or unfavorable (U).

8-93

Chapter 08 - Flexible Budgets and Performance Analysis

246. Lakey Corporation uses customers served as its measure of activity. During July, the company budgeted for 33,000 customers, but actually served 34,000 customers. The company has provided the following data concerning the formulas used in its budgeting and its actual results for July:

Required: Prepare a report showing the company's revenue and spending variances for July. Label each variance as favorable (F) or unfavorable (U).

8-94

Chapter 08 - Flexible Budgets and Performance Analysis

247. Mieras Corporation uses customers served as its measure of activity. During January, the company budgeted for 37,000 customers, but actually served 36,000 customers. The company uses the following revenue and cost formulas in its budgeting, where q is the number of customers served: Revenue: $2.80q Wages and salaries: $22,800 + $0.90q Supplies: $0.50q Insurance: $7,500 Miscellaneous: $3,800 + $0.30q The company reported the following actual results for January:

Required: Prepare a report showing the company's revenue and spending variances for January. Label each variance as favorable (F) or unfavorable (U).

8-95

Chapter 08 - Flexible Budgets and Performance Analysis

248. Fuquay Corporation uses customers served as its measure of activity. The company bases its budgets on the following information: Revenue should be $4.80 per customer served. Wages and salaries should be $26,500 per month plus $1.70 per customer served. Supplies should be $0.90 per customer served. Insurance should be $7,100 per month. Miscellaneous expenses should be $4,700 per month plus $0.20 per customer served. The company reported the following actual results for May:

Required: Prepare a report showing the company's revenue and spending variances for May. Label each variance as favorable (F) or unfavorable (U).

8-96

Chapter 08 - Flexible Budgets and Performance Analysis

249. Kary Clinic uses patient-visits as its measure of activity. During May, the clinic budgeted for 3,800 patient-visits, but its actual level of activity was 4,100 patient-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for May:

Required: Prepare a report showing the clinic's revenue and spending variances for May. Label each variance as favorable (F) or unfavorable (U).

8-97

Chapter 08 - Flexible Budgets and Performance Analysis

250. Gasco Clinic uses patient-visits as its measure of activity. During August, the clinic budgeted for 2,000 patient-visits, but its actual level of activity was 2,100 patient-visits. The clinic uses the following revenue and cost formulas in its budgeting, where q is the number of patient-visits: Revenue: $62.90q Personnel expenses: $28,500 + $20.40q Medical supplies: $1,400 + $9.90q Occupancy expenses: $8,200 + $3.30q Administrative expenses: $4,000 + $0.40q The clinic reported the following actual results for August:

Required: Prepare a report showing the clinic's revenue and spending variances for August. Label each variance as favorable (F) or unfavorable (U).

8-98

Chapter 08 - Flexible Budgets and Performance Analysis

251. Braseth Clinic uses patient-visits as its measure of activity. The clinic bases its budgets on the following information: Revenue should be $39.90 per patient-visit. Personnel expenses should be $35,400 per month plus $13.00 per patient-visit. Medical supplies should be $1,100 per month plus $4.90 per patient-visit. Occupancy expenses should be $8,400 per month plus $2.00 per patient-visit. Administrative expenses should be $4,700 per month plus $0.20 per patient-visit. The clinic reported the following actual results for January:

Required: Prepare a report showing the clinic's revenue and spending variances for January. Label each variance as favorable (F) or unfavorable (U).

8-99

Chapter 08 - Flexible Budgets and Performance Analysis

252. Villella Memorial Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for October was based on 3,800 meals. The diner's director has provided the following cost formulas to use in budgets:

The director has also provided the diner's statement of actual expenses for the month:

Required: Prepare a report showing the spending variances for each of the expenses and for total expenses for October. Label each variance as favorable (F) or unfavorable (U).

8-100

Chapter 08 - Flexible Budgets and Performance Analysis

253. Garing Urban Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for March was based on 3,600 meals. The diner's director has provided the following cost data to use in the budget: groceries, $2.20 per meal; kitchen operations, $4,300 per month plus $1.90 per meal; administrative expenses, $3,300 per month plus $0.20 per meal; and fundraising expenses, $1,000 per month. The director has also provided the diner's statement of actual expenses for the month:

Required: Prepare a report showing the diner's spending variances for each of the expenses and for total expenses for March. Label each variance as favorable (F) or unfavorable (U).

8-101

Chapter 08 - Flexible Budgets and Performance Analysis

254. Legorreta Corporation uses customers served as its measure of activity. The following report compares the planning budget to the actual operating results for the month of November:

Required: Prepare the company's flexible budget performance report for November. Label each variance as favorable (F) or unfavorable (U).

8-102

Chapter 08 - Flexible Budgets and Performance Analysis

255. Duell Clinic uses patient-visits as its measure of activity. The following report compares the planning budget to the actual operating results for the month of January:

Required: Prepare the clinic's flexible budget performance report for January. Label each variance as favorable (F) or unfavorable (U).

8-103

Chapter 08 - Flexible Budgets and Performance Analysis

256. Squillace Corporation uses customers served as its measure of activity. During October, the company budgeted for 38,000 customers, but actually served 35,000 customers. The company has provided the following data concerning the formulas used in its budgeting and its actual results for October:

Required: Prepare the company's flexible budget performance report for October. Label each variance as favorable (F) or unfavorable (U).

8-104

Chapter 08 - Flexible Budgets and Performance Analysis

257. Guy Corporation uses customers served as its measure of activity. During January, the company budgeted for 32,000 customers, but actually served 35,000 customers. The company uses the following revenue and cost formulas in its budgeting, where q is the number of customers served: Revenue: $4.20q Wages and salaries: $33,900 + $1.40q Supplies: $0.60q Insurance: $10,000 Miscellaneous: $7,000 + $0.40q The company reported the following actual results for January:

Required: Prepare the company's flexible budget performance report for January. Label each variance as favorable (F) or unfavorable (U).

8-105

Chapter 08 - Flexible Budgets and Performance Analysis

258. Cotillo Corporation uses customers served as its measure of activity. During December, the company budgeted for 29,000 customers, but actually served 27,000 customers. The company bases its budgets on the following information: Revenue should be $4.40 per customer served. Wages and salaries should be $33,300 per month plus $1.80 per customer served. Supplies should be $0.60 per customer served. Insurance should be $8,900 per month. Miscellaneous expenses should be $4,600 per month plus $0.10 per customer served. The company reported the following actual results for December:

Required: Prepare the company's flexible budget performance report for December. Label each variance as favorable (F) or unfavorable (U).

8-106

Chapter 08 - Flexible Budgets and Performance Analysis

259. Thews Clinic uses patient-visits as its measure of activity. During August, the clinic budgeted for 2,000 patient-visits, but its actual level of activity was 2,200 patient-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for August:

Required: Prepare the clinic's flexible budget performance report for August. Label each variance as favorable (F) or unfavorable (U).

8-107

Chapter 08 - Flexible Budgets and Performance Analysis

260. Mcgannon Clinic uses patient-visits as its measure of activity. During November, the clinic budgeted for 3,700 patient-visits, but its actual level of activity was 4,100 patient-visits. The clinic uses the following revenue and cost formulas in its budgeting, where q is the number of patient-visits: Revenue: $23.90q Personnel expenses: $20,800 + $7.90q Medical supplies: $800 + $3.50q Occupancy expenses: $6,100 + $1.30q Administrative expenses: $3,100 + $0.10q The clinic reported the following actual results for November:

Required: Prepare the clinic's flexible budget performance report for November. Label each variance as favorable (F) or unfavorable (U).

8-108

Chapter 08 - Flexible Budgets and Performance Analysis

261. Vernon Clinic uses patient-visits as its measure of activity. During February, the clinic budgeted for 3,100 patient-visits, but its actual level of activity was 2,800 patient-visits. The clinic bases its budgets on the following information: Revenue should be $30.20 per patientvisit. Personnel expenses should be $20,600 per month plus $9.70 per patient-visit. Medical supplies should be $1,400 per month plus $5.40 per patient-visit. Occupancy expenses should be $5,700 per month plus $1.50 per patient-visit. Administrative expenses should be $2,500 per month plus $0.30 per patient-visit. The clinic reported the following actual results for February:

Required: Prepare the clinic's flexible budget performance report for February. Label each variance as favorable (F) or unfavorable (U).

8-109

Chapter 08 - Flexible Budgets and Performance Analysis

262. Gamon Memorial Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for April was based on 3,600 meals. The diner's director has provided the following cost formulas to use in budgets:

The director has also provided the diner's statement of actual expenses for the month:

Required: Prepare a flexible budget performance report showing both the activity variances and the spending variances for each of the expenses and for total expenses for April. Label each variance as favorable (F) or unfavorable (U).

8-110

Chapter 08 - Flexible Budgets and Performance Analysis

263. Wrape Urban Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for April was based on 2,100 meals. The diner's director has provided the following cost data to use in the budget: groceries, $2.55 per meal; kitchen operations, $4,700 per month plus $1.70 per meal; administrative expenses, $3,300 per month plus $0.60 per meal; and fundraising expenses, $1,000 per month. The director has also provided the diner's statement of actual expenses for the month:

Required: Prepare a flexible budget performance report showing both the activity variances and the spending variances for each of the expenses and for total expenses for April. Label each variance as favorable (F) or unfavorable (U).

8-111

Chapter 08 - Flexible Budgets and Performance Analysis

264. Hausman Hospital bases its budgets on patient-visits. The hospital's static planning budget for October appears below:

Required: Prepare a flexible budget for 8,900 patient-visits per month.

265. Turiano Corporation bases its budgets on machine-hours. The company's static planning budget for November appears below:

Required: Prepare a flexible budget for 9,800 machine-hours per month.

8-112

Chapter 08 - Flexible Budgets and Performance Analysis

266. Therrien Corporation bases its budgets on the activity measure customers served. During September, the company plans to serve 30,000 customers. The company has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare the company's planning budget for September.

267. During March, Holston Corporation plans to serve 31,000 customers. The company uses the following revenue and cost formulas in its budgeting, where q is the number of customers served: Revenue: $4.60q Wages and salaries: $36,600 + $1.60q Supplies: $0.80q Insurance: $10,900 Miscellaneous: $8,500 + $0.20q Required: Prepare the company's planning budget for March.

8-113

Chapter 08 - Flexible Budgets and Performance Analysis

268. During August, Klinck Corporation plans to serve 33,000 customers. Revenue is $2.50 per customer served. Wages and salaries are $24,300 per month plus $0.90 per customer served. Supplies are $0.30 per customer served. Insurance is $7,100 per month. Miscellaneous expenses are $5,200 per month plus $0.10 per customer served. Required: Prepare the company's planning budget for August.

269. Novielli Corporation bases its budgets on the activity measure customers served. During November, the company planned to serve 39,000 customers, but actually served 44,000 customers. The company has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare the company's flexible budget for November based on the actual level of activity for the month.

8-114

Chapter 08 - Flexible Budgets and Performance Analysis

270. During September, Booker Corporation budgeted for 20,000 customers, but actually served 22,000 customers. The company uses the following revenue and cost formulas in its budgeting, where q is the number of customers served: Revenue: $5.50q Wages and salaries: $28,300 + $1.70q Supplies: $1.00q Insurance: $6,300 Miscellaneous: $5,400 + $0.40q Required: Prepare the company's flexible budget for September based on the actual level of activity for the month.

271. During July, Bosell Corporation budgeted for 22,000 customers, but actually served 21,000 customers. Revenue should be $6.80 per customer served. Wages and salaries should be $35,900 per month plus $2.40 per customer served. Supplies should be $1.20 per customer served. Insurance should be $12,000 per month. Miscellaneous expenses should be $6,000 per month plus $0.30 per customer served. Required: Prepare the company's flexible budget for July based on the actual level of activity for the month.

8-115

Chapter 08 - Flexible Budgets and Performance Analysis

272. Gramling Clinic bases its budgets on patient-visits. During July, the clinic plans for a level of activity of 2,500 patient-visits. The clinic has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare the clinic's planning budget for July.

273. During September, Noaks Clinic plans for an activity level of 3,300 patient-visits. The clinic uses the following revenue and cost formulas in its budgeting, where q is the number of patient-visits: Revenue: $30.50q Personnel expenses: $30,900 + $8.40q Medical supplies: $1,200 + $4.50q Occupancy expenses: $6,400 + $1.70q Administrative expenses: $3,700 + $0.10q Required: Prepare the clinic's planning budget for September.

8-116

Chapter 08 - Flexible Budgets and Performance Analysis

274. During June, Defee Clinic plans for an activity level of 3,200 patient-visits. Revenue is $50.80 per patient-visit. Personnel expenses are $35,300 per month plus $16.70 per patientvisit. Medical supplies are $1,400 per month plus $8.50 per patient-visit. Occupancy expenses are $12,500 per month plus $2.60 per patient-visit. Administrative expenses are $7,200 per month plus $0.20 per patient-visit. Required: Prepare the clinic's planning budget for June.

275. Clune Clinic bases its budgets on the activity measure patient-visits. During October, the clinic planned for an activity level of 2,100 patient-visits, but the activity level was actually 2,600 patient-visits. The clinic has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare the clinic's flexible budget for October based on the actual level of activity for the month.

8-117

Chapter 08 - Flexible Budgets and Performance Analysis

276. During October, Moceri Clinic budgeted for 3,000 patient-visits, but its actual level of activity was 3,500 patient-visits. The clinic uses the following revenue and cost formulas in its budgeting, where q is the number of patient-visits: Revenue: $41.80q Personnel expenses: $30,900 + $13.70q Medical supplies: $700 + $7.80q Occupancy expenses: $8,900 + $1.50q Administrative expenses: $3,600 + $0.20q Required: Prepare the clinic's flexible budget for October based on the actual level of activity for the month.

277. During May, Phong Clinic budgeted for 2,900 patient-visits, but its actual level of activity was 3,100 patient-visits. Revenue should be $31.30 per patient-visit. Personnel expenses should be $23,700 per month plus $8.10 per patient-visit. Medical supplies should be $700 per month plus $6.20 per patient-visit. Occupancy expenses should be $7,000 per month plus $1.50 per patient-visit. Administrative expenses should be $3,400 per month plus $0.40 per patient-visit. Required: Prepare the clinic's flexible budget for May based on the actual level of activity for the month.

8-118

Chapter 08 - Flexible Budgets and Performance Analysis

278. Vilanova Memorial Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for May is to be based on 2,700 meals. The diner's director has provided the following cost formulas to use in the budget:

Required: Prepare the diner's budget for the month of May. The budget will only contain the costs listed above; no revenues will be on the budget.

8-119

Chapter 08 - Flexible Budgets and Performance Analysis

279. Mcduffey Memorial Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for September was based on 2,900 meals, but the diner actually served 2,800 meals. The diner's director has provided the following cost formulas to use in budgets:

Required: Prepare the diner's flexible budget for the actual number of meals served in September. The budget will only contain the costs listed above; no revenues will be on the budget.

280. Korando Urban Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for June is to be based on 2,900 meals. The diner's director has provided the following cost data to use in the budget: groceries, $2.60 per meal; kitchen operations, $4,200 per month plus $1.15 per meal; administrative expenses, $2,800 per month plus $0.65 per meal; and fundraising expenses, $1,000 per month. Required: Prepare the diner's budget for the month of June. The budget will only contain the costs listed above; no revenues will be on the budget.

8-120

Chapter 08 - Flexible Budgets and Performance Analysis

281. Salvia Urban Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for May was based on 3,400 meals, but the diner actually served 3,700 meals. The diner's director has provided the following cost data to use in the budget: groceries, $2.90 per meal; kitchen operations, $4,100 per month plus $1.90 per meal; administrative expenses, $2,400 per month plus $0.20 per meal; and fundraising expenses, $1,000 per month. Required: Prepare the diner's flexible budget for the actual number of meals served in May. The budget will only contain the costs listed above; no revenues will be on the budget.

282. Alarie Tech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:

In November, the school budgeted for 1,420 students and 139 courses. The actual activity for the month was 1,220 students and 142 courses. Required: Prepare a report showing the school's activity variances for November. Label each variance as favorable (F) or unfavorable (U).

8-121

Chapter 08 - Flexible Budgets and Performance Analysis

283. Eisner Tech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:

In October, the school budgeted for 1,490 students and 85 courses. The school's income statement showing the actual results for the month appears below:

Required: Prepare a report showing the school's activity variances for October. Label each variance as favorable (F) or unfavorable (U).

8-122

Chapter 08 - Flexible Budgets and Performance Analysis

284. Bures Jeep Tours operates jeep tours in the heart of the Colorado Rockies. The company bases its budgets on two measures of activity (i.e., cost drivers), namely guests and jeeps. One vehicle used in one tour on one day counts as a jeep. Each jeep has one tour guide. The company uses the following data in its budgeting:

In April, the company budgeted for 360 guests and 134 jeeps. The actual activity for the month was 335 guests and 136 jeeps. Required: Prepare a report showing the company's activity variances for April. Label each variance as favorable (F) or unfavorable (U).

8-123

Chapter 08 - Flexible Budgets and Performance Analysis

285. Mashore Jeep Tours operates jeep tours in the heart of the Colorado Rockies. The company bases its budgets on two measures of activity (i.e., cost drivers), namely guests and jeeps. One vehicle used in one tour on one day counts as a jeep. Each jeep has one tour guide. The company uses the following data in its budgeting:

In April, the company budgeted for 495 guests and 187 jeeps. The company's income statement showing the actual results for the month appears below:

Required: Prepare a report showing the company's activity variances for April. Label each variance as favorable (F) or unfavorable (U).

8-124

Chapter 08 - Flexible Budgets and Performance Analysis

286. Ahrns Tech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:

In July, the school budgeted for 1,770 students and 148 courses. The school's income statement showing the actual results for the month appears below:

Required: Prepare a report showing the school's revenue and spending variances for July. Label each variance as favorable (F) or unfavorable (U).

8-125

Chapter 08 - Flexible Budgets and Performance Analysis

287. Ruvolo Jeep Tours operates jeep tours in the heart of the Colorado Rockies. The company bases its budgets on two measures of activity (i.e., cost drivers), namely guests and jeeps. One vehicle used in one tour on one day counts as a jeep. Each jeep has one tour guide. The company uses the following data in its budgeting:

In February, the company budgeted for 436 guests and 162 jeeps. The company's income statement showing the actual results for the month appears below:

Required: Prepare a report showing the company's revenue and spending variances for February. Label each variance as favorable (F) or unfavorable (U).

8-126

Chapter 08 - Flexible Budgets and Performance Analysis

288. Brink Tech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:

In June, the school budgeted for 1,710 students and 110 courses. The school's income statement showing the actual results for the month appears below:

Required: Prepare a flexible budget performance report showing both the school's activity variances and revenue and spending variances for June. Label each variance as favorable (F) or unfavorable (U).

8-127

Chapter 08 - Flexible Budgets and Performance Analysis

289. Palamino Jeep Tours operates jeep tours in the heart of the Colorado Rockies. The company bases its budgets on two measures of activity (i.e., cost drivers), namely guests and jeeps. One vehicle used in one tour on one day counts as a jeep. Each jeep has one tour guide. The company uses the following data in its budgeting:

In January, the company budgeted for 330 guests and 143 jeeps. The company's income statement showing the actual results for the month appears below:

Required: Prepare a flexible budget performance report showing both the company's activity variances and revenue and spending variances for January. Label each variance as favorable (F) or unfavorable (U).

8-128

Chapter 08 - Flexible Budgets and Performance Analysis

290. Alto Clinic uses patient-visits as its measure of activity. The clinic has provided the following report:

Required: Prepare the clinic's flexible budget performance report for June. Label each variance as favorable (F) or unfavorable (U).

8-129

Chapter 08 - Flexible Budgets and Performance Analysis

291. Drobot Tech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:

In November, the school budgeted for 1,470 students and 126 courses. The actual activity for the month was 1,770 students and 122 courses. Required: Prepare the school's planning budget for November.

8-130

Chapter 08 - Flexible Budgets and Performance Analysis

292. Hasselman Tech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:

In January, the school budgeted for 1,110 students and 105 courses. The actual activity for the month was 1,210 students and 103 courses. Required: Prepare the school's flexible budget for the actual level of activity in January.

8-131

Chapter 08 - Flexible Budgets and Performance Analysis

293. Lantrip Jeep Tours operates jeep tours in the heart of the Colorado Rockies. The company bases its budgets on two measures of activity (i.e., cost drivers), namely guests and jeeps. One vehicle used in one tour on one day counts as a jeep. Each jeep has one tour guide. The company uses the following data in its budgeting:

In January, the company budgeted for 356 guests and 174 jeeps. The actual activity for the month was 341 guests and 177 jeeps. Required: Prepare the company's planning budget for January.

8-132

Chapter 08 - Flexible Budgets and Performance Analysis

294. Karpin Jeep Tours operates jeep tours in the heart of the Colorado Rockies. The company bases its budgets on two measures of activity (i.e., cost drivers), namely guests and jeeps. One vehicle used in one tour on one day counts as a jeep. Each jeep has one tour guide. The company uses the following data in its budgeting:

In July, the company budgeted for 434 guests and 132 jeeps. The actual activity for the month was 459 guests and 137 jeeps. Required: Prepare the company's flexible budget for the actual level of activity in July.

8-133

Chapter 08 - Flexible Budgets and Performance Analysis

Chapter 08 Flexible Budgets and Performance Analysis Answer Key

True / False Questions

1. The main difference between a flexible budget and a static budget is that a flexible budget does not contain fixed costs. FALSE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Knowledge Learning Objective: 1 Level: Easy

2. A problem with directly comparing a static planning budget to actual costs is that this comparison fails to distinguish between differences in costs that are due to changes in activity and differences that are due to how well costs were controlled. TRUE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Knowledge Learning Objective: 1 Level: Easy

3. A planning budget is prepared before the period begins and is valid for only the planned level of activity. TRUE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Knowledge Learning Objective: 1 Level: Easy

8-134

Chapter 08 - Flexible Budgets and Performance Analysis

4. A flexible budget is an estimate of what revenues and costs should have been, given the level of activity that had been planned for the period. FALSE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Comprehension Learning Objective: 1 Level: Medium

5. An unfavorable activity variance for a cost indicates that spending was higher than it should have been for the actual level of activity for the period. FALSE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Comprehension Learning Objective: 2 Level: Medium

6. The activity variance for revenue is unfavorable if the actual revenue for the period is less than the revenue in the static planning budget. FALSE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Comprehension Learning Objective: 2 Level: Medium

8-135

Chapter 08 - Flexible Budgets and Performance Analysis

7. The revenue and spending variances are the differences between the static planning budget and the flexible budget. FALSE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Comprehension Learning Objective: 3 Level: Medium

8. A revenue variance is unfavorable if the actual revenue is less than what the revenue should have been for the actual level of activity for the period. TRUE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Knowledge Learning Objective: 3 Level: Easy

9. When the activity measure is the number of units sold, the revenue variance is unfavorable if the average actual selling price is less than expected. TRUE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Comprehension Learning Objective: 3 Level: Medium

8-136

Chapter 08 - Flexible Budgets and Performance Analysis

10. A favorable spending variance occurs when the actual cost is less than the amount of that cost in the flexible budget. TRUE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Knowledge Learning Objective: 3 Level: Easy

11. A flexible budget performance report should contain fixed as well as variable and mixed costs. TRUE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Knowledge Learning Objective: 4 Level: Easy

12. It may be easier to control fixed costs than variable costs. TRUE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Knowledge Learning Objective: 4 Level: Easy

8-137

Chapter 08 - Flexible Budgets and Performance Analysis

13. A static planning budget is suitable for planning and for evaluating how well costs are controlled. FALSE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Comprehension Learning Objective: 6 Level: Medium

14. If the actual level of activity is 4% less than planned, then the costs in the static budget should be reduced by 4% before comparing them to actual costs. FALSE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Comprehension Learning Objective: 6 Level: Easy

15. If the actual level of activity is 4% more than planned, then the fixed costs in the static budget should be increased by 4% before comparing them to actual costs. FALSE

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Comprehension Learning Objective: 6 Level: Medium

8-138

Chapter 08 - Flexible Budgets and Performance Analysis


Multiple Choice Questions

16. A flexible budget: A. classifies budget requests by activity and estimates the benefits arising from each activity. B. presents a statement of expectations for a period of time but does not present a firm commitment. C. presents the plan for only one level of activity and does not adjust to changes in the level of activity. D. presents the plan for a range of activity so that the plan can be adjusted for changes in activity levels.

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Knowledge Learning Objective: 1 Level: Easy Source: CMA, adapted

17. A flexible budget is a budget that: A. is updated with actual costs as they occur during the period. B. is updated to reflect the actual level of activity during the period. C. is prepared using a computer spreadsheet application. D. contains only variable production costs.

AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Knowledge Learning Objective: 1 Level: Easy Source: CIMA, adapted

18. Which of the following comparisons best isolates the impact that changes in prices of inputs and outputs have on performance? A. static planning budget and flexible budget B. static planning budget and actual results C. flexible budget and actual results D. master budget and static planning budget
AACSB: Reflective Thinking AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Comprehension Learning Objective: 3 Level: Easy

8-139

Chapter 08 - Flexible Budgets and Performance Analysis

19. Marchi Family Inn is a bed and breakfast establishment in a converted 100-year-old mansion. The Inn's guests appreciate its gourmet breakfasts and individually decorated rooms. The Inn's overhead budget for the most recent month appears below:

The Inn's variable overhead costs are driven by the number of guests. What would be the total budgeted overhead cost for a month if the activity level is 70 guests? A. $42,460.00 B. $6,620.00 C. $7,086.15 D. $6,580.00 Variable cost per guest = ($156 + $364) 65 guests = $8 per guest ($250 + $4,480 + $1,330) + ($8 70) = $6,620.00

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-140

Chapter 08 - Flexible Budgets and Performance Analysis

20. Barringer Manufacturing Corporation has prepared the following overhead budget for next month.

The company's variable overhead costs are driven by machine-hours. What would be the total budgeted overhead cost for next month if the activity level is 7,900 machine-hours rather than 7,800 machine-hours? A. $110,710.00 B. $109,620.00 C. $110,868.00 D. $111,025.38 Variable cost per machine-hour = ($34,320 + $50,700) 7,800 machine-hours = $10.90 per machine-hour ($10,200 + $5,600 + $8,800) + ($10.90 7,900) = $110,710.00

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-141

Chapter 08 - Flexible Budgets and Performance Analysis

21. Placek Hospital bases its budgets on patient-visits. The hospital's static budget for October appears below:

The total overhead cost at an activity level of 7,700 patient-visits per month should be: A. $129,550 B. $121,720 C. $129,100 D. $137,830 ($21,080 + $44,880) + [($2.60 + $5.60) 7,700] = $129,100

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-142

Chapter 08 - Flexible Budgets and Performance Analysis

22. Dike Hotel bases its budgets on guest-days. The hotel's static budget for June appears below:

The total overhead cost at an activity level of 8,400 guest-days per month should be: A. $159,440 B. $149,650 C. $160,430 D. $172,200 ($68,620 + $16,060) + [($6.70 + $2.20) 8,400] = $159,440

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-143

Chapter 08 - Flexible Budgets and Performance Analysis

23. Blackwelder Snow Removal's cost formula for its vehicle operating cost is $1,240 per month plus $348 per snow-day. For the month of December, the company planned for activity of 12 snow-days, but the actual level of activity was 14 snow-days. The actual vehicle operating cost for the month was $6,330. The vehicle operating cost in the planning budget for December would be closest to: A. $5,426 B. $6,112 C. $5,416 D. $6,330 $1,240 + $348 12 = $5,416

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

24. Ofarrell Snow Removal's cost formula for its vehicle operating cost is $1,840 per month plus $377 per snow-day. For the month of November, the company planned for activity of 14 snow-days, but the actual level of activity was 19 snow-days. The actual vehicle operating cost for the month was $9,280. The vehicle operating cost in the flexible budget for November would be closest to: A. $9,003 B. $7,118 C. $9,280 D. $9,660 $1,840 + $377 19 = $9,003

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-144

Chapter 08 - Flexible Budgets and Performance Analysis

25. Guilbault Midwifery's cost formula for its wages and salaries is $2,340 per month plus $154 per birth. For the month of June, the company planned for activity of 115 births, but the actual level of activity was 112 births. The actual wages and salaries for the month was $19,530. The wages and salaries in the planning budget for June would be closest to: A. $19,530 B. $19,588 C. $20,053 D. $20,050 $2,340 + $154 115 = $20,050

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

26. Dewberry Midwifery's cost formula for its wages and salaries is $1,960 per month plus $429 per birth. For the month of December, the company planned for activity of 128 births, but the actual level of activity was 130 births. The actual wages and salaries for the month was $56,020. The wages and salaries in the flexible budget for December would be closest to: A. $57,761 B. $57,730 C. $56,020 D. $56,872 $1,960 + $429 130 = $57,730

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-145

Chapter 08 - Flexible Budgets and Performance Analysis

27. Entler Framing's cost formula for its supplies cost is $2,250 per month plus $16 per frame. For the month of June, the company planned for activity of 502 frames, but the actual level of activity was 497 frames. The actual supplies cost for the month was $10,580. The supplies cost in the planning budget for June would be closest to: A. $10,580 B. $10,282 C. $10,686 D. $10,202 $2,250 + $16 502 = $10,282

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

28. Rising Framing's cost formula for its supplies cost is $2,210 per month plus $10 per frame. For the month of January, the company planned for activity of 710 frames, but the actual level of activity was 705 frames. The actual supplies cost for the month was $9,500. The supplies cost in the flexible budget for January would be closest to: A. $9,260 B. $9,244 C. $9,500 D. $9,310 $2,210 + $10 705 = $9,260

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-146

Chapter 08 - Flexible Budgets and Performance Analysis

29. Naval Catering uses two measures of activity, jobs and meals, in the cost formulas in its budgets and performance reports. The cost formula for catering supplies is $430 per month plus $99 per job plus $10 per meal. A typical job involves serving a number of meals to guests at a corporate function or at a host's home. The company expected its activity in March to be 12 jobs and 126 meals, but the actual activity was 9 jobs and 124 meals. The actual cost for catering supplies in March was $2,550. The catering supplies in the planning budget for March would be closest to: A. $3,400 B. $2,561 C. $2,550 D. $2,878 $430 + $99 12 + $10 126 = $2,878

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

30. Johannsen Catering uses two measures of activity, jobs and meals, in the cost formulas in its budgets and performance reports. The cost formula for catering supplies is $310 per month plus $103 per job plus $23 per meal. A typical job involves serving a number of meals to guests at a corporate function or at a host's home. The company expected its activity in February to be 28 jobs and 187 meals, but the actual activity was 26 jobs and 192 meals. The actual cost for catering supplies in February was $7,620. The catering supplies in the flexible budget for February would be closest to: A. $7,495 B. $7,404 C. $7,620 D. $6,960 $310 + $103 26 + $23 192 = $7,404

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-147

Chapter 08 - Flexible Budgets and Performance Analysis

31. Venanzi Air uses two measures of activity, flights and passengers, in the cost formulas in its budgets and performance reports. The cost formula for plane operating costs is $40,720 per month plus $2,646 per flight plus $11 per passenger. The company expected its activity in September to be 62 flights and 288 passengers, but the actual activity was 64 flights and 289 passengers. The actual cost for plane operating costs in September was $214,430. The activity variance for plane operating costs in September would be closest to: A. $6,490 U B. $5,303 F C. $6,490 F D. $5,303 U

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 2 Learning Objective: 5 Level: Easy

8-148

Chapter 08 - Flexible Budgets and Performance Analysis

32. Kimbril Catering uses two measures of activity, jobs and meals, in the cost formulas in its budgets and performance reports. The cost formula for catering supplies is $530 per month plus $91 per job plus $12 per meal. A typical job involves serving a number of meals to guests at a corporate function or at a host's home. The company expected its activity in January to be 27 jobs and 174 meals, but the actual activity was 31 jobs and 173 meals. The actual cost for catering supplies in January was $5,330. The activity variance for catering supplies in January would be closest to: A. $255 F B. $255 U C. $352 F D. $352 U

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 2 Learning Objective: 5 Level: Easy

8-149

Chapter 08 - Flexible Budgets and Performance Analysis

33. Portsche Snow Removal's cost formula for its vehicle operating cost is $2,310 per month plus $317 per snow-day. For the month of November, the company planned for activity of 18 snow-days, but the actual level of activity was 20 snow-days. The actual vehicle operating cost for the month was $8,730. The activity variance for vehicle operating cost in November would be closest to: A. $714 U B. $714 F C. $634 F D. $634 U

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 2 Level: Easy

8-150

Chapter 08 - Flexible Budgets and Performance Analysis

34. Reuer Midwifery's cost formula for its wages and salaries is $2,900 per month plus $475 per birth. For the month of March, the company planned for activity of 116 births, but the actual level of activity was 117 births. The actual wages and salaries for the month was $56,270. The activity variance for wages and salaries in March would be closest to: A. $1,730 U B. $475 F C. $475 U D. $1,730 F

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 2 Level: Easy

8-151

Chapter 08 - Flexible Budgets and Performance Analysis

35. Embertson Framing's cost formula for its supplies cost is $1,350 per month plus $16 per frame. For the month of June, the company planned for activity of 816 frames, but the actual level of activity was 812 frames. The actual supplies cost for the month was $14,680. The activity variance for supplies cost in June would be closest to: A. $64 U B. $274 U C. $64 F D. $274 F

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 2 Level: Easy

8-152

Chapter 08 - Flexible Budgets and Performance Analysis

36. Lapinsky Air uses two measures of activity, flights and passengers, in the cost formulas in its budgets and performance reports. The cost formula for plane operating costs is $31,400 per month plus $2,148 per flight plus $7 per passenger. The company expected its activity in April to be 89 flights and 261 passengers, but the actual activity was 84 flights and 260 passengers. The actual cost for plane operating costs in April was $204,810. The spending variance for plane operating costs in April would be closest to: A. $8,842 U B. $19,589 F C. $19,589 U D. $8,842 F

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Learning Objective: 5 Level: Easy

8-153

Chapter 08 - Flexible Budgets and Performance Analysis

37. Posson Catering uses two measures of activity, jobs and meals, in the cost formulas in its budgets and performance reports. The cost formula for catering supplies is $210 per month plus $96 per job plus $20 per meal. A typical job involves serving a number of meals to guests at a corporate function or at a host's home. The company expected its activity in March to be 20 jobs and 162 meals, but the actual activity was 17 jobs and 164 meals. The actual cost for catering supplies in March was $4,990. The spending variance for catering supplies in March would be closest to: A. $380 F B. $132 U C. $132 F D. $380 U

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Learning Objective: 5 Level: Easy

8-154

Chapter 08 - Flexible Budgets and Performance Analysis

38. Dunklin Medical Clinic measures its activity in terms of patient-visits. Last month, the budgeted level of activity was 1,620 patient-visits and the actual level of activity was 1,540 patient-visits. The cost formula for administrative expenses is $3.20 per patient-visit plus $14,300 per month. The actual administrative expense was $21,050. In the clinic's flexible budget performance report for last month, the spending variance for administrative expenses was: A. $118 F B. $256 F C. $1,566 U D. $1,822 U

Since the actual expense is more than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Medium

8-155

Chapter 08 - Flexible Budgets and Performance Analysis

39. Brattain Tile Installation Corporation measures its activity in terms of square feet of tile installed. Last month, the budgeted level of activity was 1,230 square feet and the actual level of activity was 1,140 square feet. The company's owner budgets for supply costs, a variable cost, at $2.10 per square foot. The actual supply cost last month was $3,260. In the company's flexible budget performance report for last month, what would have been the spending variance for supply costs? A. $257 F B. $866 U C. $677 U D. $189 F

Since the actual expense is more than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

8-156

Chapter 08 - Flexible Budgets and Performance Analysis

40. Cahalane Natural Dying Corporation measures its activity in terms of skeins of yarn dyed. Last month, the budgeted level of activity was 11,600 skeins and the actual level of activity was 12,000 skeins. The company's owner budgets for dye costs, a variable cost, at $0.31 per skein. The actual dye cost last month was $3,540. In the company's flexible budget performance report for last month, what would have been the spending variance for dye costs? A. $118 U B. $124 U C. $56 F D. $180 F

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

8-157

Chapter 08 - Flexible Budgets and Performance Analysis

41. Gladstone Footwear Corporation's flexible budget cost formula for supplies, a variable cost, is $2.83 per unit of output. The company's flexible budget performance report for last month showed a $9,555 unfavorable spending variance for supplies. During that month, 19,500 units were produced. Budgeted activity for the month had been 19,300 units. The actual cost per unit for indirect materials must have been closest to: A. $3.32 B. $3.81 C. $2.83 D. $3.85 Actual supplies - Flexible budget = Spending variable (U) Actual supplies - (19,500 $2.83) = $9,555 Actual supplies = $64,740 Actual cost per unit = $64,740 19,500 = $3.32

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 3 Level: Hard

42. Velten Corporation's flexible budget performance report for last month shows that actual indirect materials cost, a variable cost, was $45,198 and that the spending variance for indirect materials cost was $9,114 favorable. During that month, the company worked 18,600 machine-hours. Budgeted activity for the month had been 19,000 machine-hours. The cost formula per machine-hour for indirect materials cost must have been closest to: A. $1.90 B. $2.86 C. $1.94 D. $2.92 Flexible budget - Actual cost = Spending variance (F) Flexible budget - $45,198 = $9,114 Flexible budget = $54,312 Cost formula per machine hour = $54,312 18,600 = $2.92

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 3 Level: Hard

8-158

Chapter 08 - Flexible Budgets and Performance Analysis

43. Lesinski Snow Removal's cost formula for its vehicle operating cost is $1,770 per month plus $483 per snow-day. For the month of February, the company planned for activity of 19 snow-days, but the actual level of activity was 24 snow-days. The actual vehicle operating cost for the month was $13,070. The spending variance for vehicle operating cost in February would be closest to: A. $2,123 U B. $292 F C. $2,123 F D. $292 U

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

8-159

Chapter 08 - Flexible Budgets and Performance Analysis

44. Harville Midwifery's cost formula for its wages and salaries is $1,610 per month plus $199 per birth. For the month of March, the company planned for activity of 118 births, but the actual level of activity was 122 births. The actual wages and salaries for the month was $25,430. The spending variance for wages and salaries in March would be closest to: A. $458 F B. $338 U C. $458 U D. $338 F

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

45. Olivier Framing's cost formula for its supplies cost is $2,870 per month plus $16 per frame. For the month of January, the company planned for activity of 533 frames, but the actual level of activity was 534 frames. The actual supplies cost for the month was $11,080. The spending variance for supplies cost in January would be closest to: A. $334 U B. $334 F C. $318 U D. $318 F

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

8-160

Chapter 08 - Flexible Budgets and Performance Analysis

46. Elizarraras Air uses two measures of activity, flights and passengers, in the cost formulas in its budgets and performance reports. The cost formula for plane operating costs is $39,820 per month plus $2,938 per flight plus $8 per passenger. The company expected its activity in June to be 64 flights and 229 passengers, but the actual activity was 66 flights and 225 passengers. The actual cost for plane operating costs in June was $234,570. The plane operating costs in the planning budget for June would be closest to: A. $229,684 B. $227,462 C. $234,570 D. $235,528 $39,820 + $2,938 64 + $8 229 = $229,684

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 5 Level: Easy

47. Niforos Air uses two measures of activity, flights and passengers, in the cost formulas in its budgets and performance reports. The cost formula for plane operating costs is $41,380 per month plus $2,282 per flight plus $14 per passenger. The company expected its activity in August to be 77 flights and 264 passengers, but the actual activity was 78 flights and 261 passengers. The actual cost for plane operating costs in August was $216,740. The plane operating costs in the flexible budget for August would be closest to: A. $220,790 B. $223,030 C. $223,657 D. $216,740 $41,380 + $2,282 78 + $14 261 = $223,030

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 5 Level: Easy

8-161

Chapter 08 - Flexible Budgets and Performance Analysis

Pollica Corporation's cost formula for its selling and administrative expense is $11,400 per month plus $94 per unit. For the month of March, the company planned for activity of 5,700 units, but the actual level of activity was 5,660 units. The actual selling and administrative expense for the month was $522,860.

48. The selling and administrative expense in the planning budget for March would be closest to: A. $522,860 B. $547,200 C. $543,440 D. $526,555 $11,400 + $94 5,700 = $547,200

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

49. The selling and administrative expense in the flexible budget for March would be closest to: A. $547,200 B. $522,860 C. $543,360 D. $543,440 $11,400 + $94 5,660 = $543,440

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-162

Chapter 08 - Flexible Budgets and Performance Analysis

50. The activity variance for selling and administrative expense in March would be closest to: A. $24,340 F B. $24,340 U C. $3,760 U D. $3,760 F

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Easy

51. The spending variance for selling and administrative expense in March would be closest to: A. $20,580 F B. $24,340 U C. $24,340 F D. $20,580 U

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Easy

8-163

Chapter 08 - Flexible Budgets and Performance Analysis

Kuczenski Corporation's cost formula for its manufacturing overhead is $45,700 per month plus $53 per machine-hour. For the month of March, the company planned for activity of 6,200 machine-hours, but the actual level of activity was 6,150 machine-hours. The actual manufacturing overhead for the month was $373,630.

52. The manufacturing overhead in the planning budget for March would be closest to: A. $373,630 B. $371,650 C. $376,668 D. $374,300 $45,700 + $53 6,200 = $374,300

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

53. The manufacturing overhead in the flexible budget for March would be closest to: A. $371,650 B. $371,281 C. $373,630 D. $374,300 $45,700 + $53 6,150 = $371,650

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-164

Chapter 08 - Flexible Budgets and Performance Analysis

54. The activity variance for manufacturing overhead in March would be closest to: A. $670 U B. $670 F C. $2,650 F D. $2,650 U

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Easy

55. The spending variance for manufacturing overhead in March would be closest to: A. $670 F B. $1,980 U C. $1,980 F D. $670 U

Since the actual expense is greater than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Easy

8-165

Chapter 08 - Flexible Budgets and Performance Analysis

Kaaihue Detailing's cost formula for its materials and supplies is $2,750 per month plus $17 per vehicle. For the month of April, the company planned for activity of 95 vehicles, but the actual level of activity was 135 vehicles. The actual materials and supplies for the month was $4,850.

56. The materials and supplies in the planning budget for April would be closest to: A. $4,850 B. $5,045 C. $3,413 D. $4,365 $2,750 + $17 95 = $4,365

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

57. The materials and supplies in the flexible budget for April would be closest to: A. $6,203 B. $4,850 C. $4,365 D. $5,045 $2,750 + $17 135 = $5,045

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-166

Chapter 08 - Flexible Budgets and Performance Analysis

58. The activity variance for materials and supplies in April would be closest to: A. $680 U B. $485 F C. $680 F D. $485 U

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Easy

59. The spending variance for materials and supplies in April would be closest to: A. $195 F B. $485 F C. $195 U D. $485 U

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Easy

8-167

Chapter 08 - Flexible Budgets and Performance Analysis

Deleston Boat Wash's cost formula for its cleaning equipment and supplies is $2,150 per month plus $21 per boat. For the month of September, the company planned for activity of 79 boats, but the actual level of activity was 39 boats. The actual cleaning equipment and supplies for the month was $3,110.

60. The cleaning equipment and supplies in the planning budget for September would be closest to: A. $3,110 B. $6,300 C. $2,969 D. $3,809 $2,150 + $21 79 = $3,809

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

61. The cleaning equipment and supplies in the flexible budget for September would be closest to: A. $1,880 B. $3,110 C. $3,809 D. $2,969 $2,150 + $21 39 = $2,969

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-168

Chapter 08 - Flexible Budgets and Performance Analysis

62. The activity variance for cleaning equipment and supplies in September would be closest to: A. $840 F B. $699 F C. $699 U D. $840 U

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Easy

63. The spending variance for cleaning equipment and supplies in September would be closest to: A. $699 F B. $699 U C. $141 F D. $141 U

Since the actual expense is greater than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Easy

8-169

Chapter 08 - Flexible Budgets and Performance Analysis

Werber Clinic uses client-visits as its measure of activity. During January, the clinic budgeted for 2,700 client-visits, but its actual level of activity was 2,730 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for January:

64. The activity variance for personnel expenses in January would be closest to: A. $661 U B. $261 U C. $261 F D. $661 F

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Medium

8-170

Chapter 08 - Flexible Budgets and Performance Analysis

65. The activity variance for administrative expenses in January would be closest to: A. $12 F B. $8 F C. $12 U D. $8 U

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Medium

8-171

Chapter 08 - Flexible Budgets and Performance Analysis

66. The activity variance for net operating income in January would be closest to: A. $2,019 U B. $2,019 F C. $489 F D. $489 U

Since the flexible budget net operating income is greater than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Medium

Feiner Clinic uses client-visits as its measure of activity. During December, the clinic budgeted for 2,200 client-visits, but its actual level of activity was 2,220 client-visits. The clinic has provided the following data concerning the formulas to be used in its budgeting:

8-172

Chapter 08 - Flexible Budgets and Performance Analysis

67. The activity variance for personnel expenses in December would be closest to: A. $4,024 F B. $466 F C. $466 U D. $4,024 U

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Easy

68. The activity variance for administrative expenses in December would be closest to: A. $8 F B. $162 F C. $162 U D. $8 U

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Easy

8-173

Chapter 08 - Flexible Budgets and Performance Analysis

69. The activity variance for net operating income in December would be closest to: A. $690 U B. $9,670 U C. $690 F D. $9,670 F

Since the flexible budget net operating income is greater than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Easy

8-174

Chapter 08 - Flexible Budgets and Performance Analysis

Grundhoefer Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During April, the kennel budgeted for 2,000 tenant-days, but its actual level of activity was 1,990 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for April:

8-175

Chapter 08 - Flexible Budgets and Performance Analysis

70. The activity variance for wages and salaries in April would be closest to: A. $66 F B. $564 U C. $564 F D. $66 U

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Medium

71. The activity variance for administrative expenses in April would be closest to: A. $1 F B. $79 F C. $79 U D. $1 U

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Medium

8-176

Chapter 08 - Flexible Budgets and Performance Analysis

72. The activity variance for net operating income in April would be closest to: A. $141 U B. $2,651 U C. $2,651 F D. $141 F

Since the flexible budget net operating income is less than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Medium

Gorley Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During February, the kennel budgeted for 3,900 tenantdays, but its actual level of activity was 3,940 tenant-days. The kennel has provided the following data concerning the formulas to be used in its budgeting:

8-177

Chapter 08 - Flexible Budgets and Performance Analysis

73. The activity variance for wages and salaries in February would be closest to: A. $1,152 U B. $1,152 F C. $292 U D. $292 F

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Easy

74. The activity variance for administrative expenses in February would be closest to: A. $18 U B. $12 U C. $18 F D. $12 F

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Easy

8-178

Chapter 08 - Flexible Budgets and Performance Analysis

75. The activity variance for net operating income in February would be closest to: A. $368 F B. $368 U C. $632 F D. $632 U

Since the flexible budget net operating income is greater than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Easy

8-179

Chapter 08 - Flexible Budgets and Performance Analysis

Enriques Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During February, the company budgeted for 5,000 units, but its actual level of activity was 4,990 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for February:

8-180

Chapter 08 - Flexible Budgets and Performance Analysis

76. The activity variance for direct labor in February would be closest to: A. $61 U B. $1,081 U C. $61 F D. $1,081 F

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Medium

77. The activity variance for selling and administrative expenses in February would be closest to: A. $1,308 F B. $1,308 U C. $2 U D. $2 F

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Medium

8-181

Chapter 08 - Flexible Budgets and Performance Analysis

78. The activity variance for net operating income in February would be closest to: A. $2,716 F B. $2,716 U C. $176 U D. $176 F

Since the flexible budget net operating income is less than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Medium

Palczewski Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During December, the company budgeted for 5,000 units, but its actual level of activity was 4,980 units. The company has provided the following data concerning the formulas to be used in its budgeting:

8-182

Chapter 08 - Flexible Budgets and Performance Analysis

79. The activity variance for direct labor in December would be closest to: A. $180 U B. $70 F C. $70 U D. $180 F

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Easy

80. The activity variance for selling and administrative expenses in December would be closest to: A. $14 U B. $14 F C. $1,206 F D. $1,206 U

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Easy

8-183

Chapter 08 - Flexible Budgets and Performance Analysis

81. The activity variance for net operating income in December would be closest to: A. $2,372 U B. $328 F C. $2,372 F D. $328 U

Since the flexible budget net operating income is less than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 2 Level: Easy

8-184

Chapter 08 - Flexible Budgets and Performance Analysis

Burget Clinic uses client-visits as its measure of activity. During July, the clinic budgeted for 2,100 client-visits, but its actual level of activity was 2,110 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for July:

8-185

Chapter 08 - Flexible Budgets and Performance Analysis

82. The revenue variance for July would be closest to: A. $2,581 F B. $2,110 U C. $2,110 F D. $2,581 U

Since the actual revenue is greater than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Medium

83. The spending variance for medical supplies in July would be closest to: A. $580 U B. $645 U C. $645 F D. $580 F

Since the actual expense is greater than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Medium

8-186

Chapter 08 - Flexible Budgets and Performance Analysis

84. The spending variance for occupancy expenses in July would be closest to: A. $265 F B. $280 U C. $280 F D. $265 U

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Medium

8-187

Chapter 08 - Flexible Budgets and Performance Analysis

85. The overall revenue and spending variance (i.e., the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for July would be closest to: A. $4,508 F B. $4,290 U C. $4,290 F D. $4,508 U

Since the actual net operating income is greater than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Medium

8-188

Chapter 08 - Flexible Budgets and Performance Analysis

Razor Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During November, the kennel budgeted for 3,000 tenant-days, but its actual level of activity was 3,010 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for November:

8-189

Chapter 08 - Flexible Budgets and Performance Analysis

86. The revenue variance for November would be closest to: A. $1,607 U B. $1,910 U C. $1,607 F D. $1,910 F

Since the actual revenue is less than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Medium

87. The spending variance for expendables in November would be closest to: A. $240 F B. $354 F C. $240 U D. $354 U

Since the actual expense is greater than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Medium

8-190

Chapter 08 - Flexible Budgets and Performance Analysis

88. The spending variance for facility expenses in November would be closest to: A. $416 U B. $416 F C. $390 F D. $390 U

Since the actual expense is greater than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Medium

8-191

Chapter 08 - Flexible Budgets and Performance Analysis

89. The overall revenue and spending variance (i.e., the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for November would be closest to: A. $3,520 F B. $3,428 U C. $3,520 U D. $3,428 F

Since the actual net operating income is less than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Medium

8-192

Chapter 08 - Flexible Budgets and Performance Analysis

Vandall Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During April, the company budgeted for 7,300 units, but its actual level of activity was 7,340 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for April:

8-193

Chapter 08 - Flexible Budgets and Performance Analysis

90. The revenue variance for April would be closest to: A. $4,274 F B. $5,690 F C. $5,690 U D. $4,274 U

Since the actual revenue is less than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Medium

91. The spending variance for direct materials in April would be closest to: A. $210 U B. $210 F C. $426 U D. $426 F

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Medium

8-194

Chapter 08 - Flexible Budgets and Performance Analysis

92. The spending variance for manufacturing overhead in April would be closest to: A. $1,600 U B. $1,648 F C. $1,600 F D. $1,648 U

Since the actual expense is greater than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Medium

8-195

Chapter 08 - Flexible Budgets and Performance Analysis

93. The overall revenue and spending variance (i.e., the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for April would be closest to: A. $6,144 F B. $6,740 U C. $6,740 F D. $6,144 U

Since the actual net operating income is less than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 3 Level: Medium

8-196

Chapter 08 - Flexible Budgets and Performance Analysis

Moorhouse Clinic uses client-visits as its measure of activity. During December, the clinic budgeted for 3,700 client-visits, but its actual level of activity was 3,690 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for December:

94. The personnel expenses in the planning budget for December would be closest to: A. $51,009 B. $51,147 C. $53,370 D. $53,299 $27,100 + $7.10 3,700 = $53,370

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-197

Chapter 08 - Flexible Budgets and Performance Analysis

95. The medical supplies in the flexible budget for December would be closest to: A. $18,150 B. $17,472 C. $17,378 D. $18,105 $1,500 + $4.50 3,690 = $18,105

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

96. The activity variance for personnel expenses in December would be closest to: A. $2,361 U B. $71 U C. $71 F D. $2,361 F

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-198

Chapter 08 - Flexible Budgets and Performance Analysis

97. The revenue variance for December would be closest to: A. $3,680 U B. $3,429 F C. $3,429 U D. $3,680 F

Since the actual revenue is greater than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

98. The spending variance for medical supplies in December would be closest to: A. $680 F B. $680 U C. $725 U D. $725 F

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-199

Chapter 08 - Flexible Budgets and Performance Analysis

Cotty Clinic uses client-visits as its measure of activity. During March, the clinic budgeted for 3,000 client-visits, but its actual level of activity was 2,970 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for March:

99. The administrative expenses in the planning budget for March would be closest to: A. $6,288 B. $6,300 C. $6,418 D. $6,483 $5,100 + $0.40 3,000 = $6,300

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-200

Chapter 08 - Flexible Budgets and Performance Analysis

100. The occupancy expenses in the flexible budget for March would be closest to: A. $13,400 B. $12,770 C. $13,349 D. $13,029 $8,300 + $1.70 2,970 = $13,349

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

101. The activity variance for administrative expenses in March would be closest to: A. $118 U B. $12 F C. $118 F D. $12 U

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-201

Chapter 08 - Flexible Budgets and Performance Analysis

102. The spending variance for medical supplies in March would be closest to: A. $1,050 U B. $1,050 F C. $1,263 F D. $1,263 U

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-202

Chapter 08 - Flexible Budgets and Performance Analysis

Murphree Clinic uses client-visits as its measure of activity. During April, the clinic budgeted for 3,300 client-visits, but its actual level of activity was 3,350 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for April:

103. The net operating income in the planning budget for April would be closest to: A. $14,425 B. $19,519 C. $13,550 D. $20,115

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-203

Chapter 08 - Flexible Budgets and Performance Analysis

104. The net operating income in the flexible budget for April would be closest to: A. $20,115 B. $19,519 C. $14,425 D. $13,550

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

105. The activity variance for net operating income in April would be closest to: A. $875 F B. $6,265 F C. $875 U D. $6,265 U

Since the flexible budget net operating income is greater than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-204

Chapter 08 - Flexible Budgets and Performance Analysis

106. The overall revenue and spending variance (i.e., the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for April would be closest to: A. $5,390 F B. $6,265 U C. $5,390 U D. $6,265 F

Since the actual net operating income is greater than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-205

Chapter 08 - Flexible Budgets and Performance Analysis

Henkel Clinic uses client-visits as its measure of activity. During November, the clinic budgeted for 3,600 client-visits, but its actual level of activity was 3,550 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for November:

107. The personnel expenses in the planning budget for November would be closest to: A. $74,120 B. $71,432 C. $70,440 D. $74,640 $37,200 + $10.40 3,600 = $74,640

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-206

Chapter 08 - Flexible Budgets and Performance Analysis

108. The occupancy expenses in the flexible budget for November would be closest to: A. $14,422 B. $14,831 C. $15,325 D. $15,400 $10,000 + $1.50 3,550 = $15,325

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

109. The activity variance for administrative expenses in November would be closest to: A. $215 U B. $215 F C. $5 F D. $5 U

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-207

Chapter 08 - Flexible Budgets and Performance Analysis

110. The spending variance for occupancy expenses in November would be closest to: A. $775 U B. $700 F C. $775 F D. $700 U

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-208

Chapter 08 - Flexible Budgets and Performance Analysis

Hoeper Clinic uses client-visits as its measure of activity. During January, the clinic budgeted for 2,600 client-visits, but its actual level of activity was 2,570 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for January:

111. The administrative expenses in the planning budget for January would be closest to: A. $5,047 B. $4,960 C. $5,106 D. $4,957 $4,700 + $0.10 2,600 = $4,960

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-209

Chapter 08 - Flexible Budgets and Performance Analysis

112. The medical supplies in the flexible budget for January would be closest to: A. $19,733 B. $18,932 C. $19,940 D. $19,377 $2,000 + $6.90 2,570 = $19,733

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

113. The activity variance for personnel expenses in January would be closest to: A. $1,416 U B. $486 F C. $1,416 F D. $486 U

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-210

Chapter 08 - Flexible Budgets and Performance Analysis

114. The spending variance for medical supplies in January would be closest to: A. $787 F B. $787 U C. $580 F D. $580 U

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-211

Chapter 08 - Flexible Budgets and Performance Analysis

Legard Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During January, the kennel budgeted for 2,600 tenantdays, but its actual level of activity was 2,620 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for January:

115. The wages and salaries in the planning budget for January would be closest to: A. $24,040 B. $23,755 C. $23,938 D. $24,198 $3,500 + $7.90 2,600 = $24,040

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-212

Chapter 08 - Flexible Budgets and Performance Analysis

116. The expendables in the flexible budget for January would be closest to: A. $35,946 B. $36,704 C. $35,680 D. $37,271 $1,100 + $13.30 2,620 = $35,946

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

117. The activity variance for wages and salaries in January would be closest to: A. $158 F B. $158 U C. $102 U D. $102 F

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-213

Chapter 08 - Flexible Budgets and Performance Analysis

118. The revenue variance for January would be closest to: A. $750 U B. $40 U C. $40 F D. $750 F

Since the actual revenue is less than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

119. The spending variance for expendables in January would be closest to: A. $1,040 F B. $1,306 F C. $1,040 U D. $1,306 U

Since the actual expense is greater than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-214

Chapter 08 - Flexible Budgets and Performance Analysis

Drabant Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During February, the kennel budgeted for 2,000 tenant-days, but its actual level of activity was 2,040 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for February:

120. The administrative expenses in the planning budget for February would be closest to: A. $7,500 B. $7,252 C. $7,110 D. $7,512 $6,900 + $0.30 2,000 = $7,500

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-215

Chapter 08 - Flexible Budgets and Performance Analysis

121. The facility expenses in the flexible budget for February would be closest to: A. $13,700 B. $13,401 C. $13,788 D. $12,880 $9,300 + $2.20 2,040 = $13,788

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

122. The activity variance for administrative expenses in February would be closest to: A. $248 U B. $248 F C. $12 U D. $12 F

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-216

Chapter 08 - Flexible Budgets and Performance Analysis

123. The spending variance for expendables in February would be closest to: A. $836 F B. $1,360 F C. $836 U D. $1,360 U

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

Tosta Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During May, the kennel budgeted for 2,100 tenant-days, but its actual level of activity was 2,050 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for May:

8-217

Chapter 08 - Flexible Budgets and Performance Analysis

124. The net operating income in the planning budget for May would be closest to: A. $9,140 B. $11,626 C. $12,200 D. $8,420

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

125. The net operating income in the flexible budget for May would be closest to: A. $9,140 B. $8,420 C. $11,626 D. $12,200

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-218

Chapter 08 - Flexible Budgets and Performance Analysis

126. The activity variance for net operating income in May would be closest to: A. $2,770 U B. $720 U C. $720 F D. $2,770 F

Since the flexible budget net operating income is less than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-219

Chapter 08 - Flexible Budgets and Performance Analysis

127. The overall revenue and spending variance (i.e., the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for May would be closest to: A. $3,490 F B. $2,770 F C. $3,490 U D. $2,770 U

Since the actual net operating income is greater than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-220

Chapter 08 - Flexible Budgets and Performance Analysis

Stent Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During February, the kennel budgeted for 3,000 tenantdays, but its actual level of activity was 2,950 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for February:

128. The wages and salaries in the planning budget for February would be closest to: A. $22,670 B. $24,183 C. $23,780 D. $23,000 $3,200 + $6.60 3,000 = $23,000

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-221

Chapter 08 - Flexible Budgets and Performance Analysis

129. The facility expenses in the flexible budget for February would be closest to: A. $16,000 B. $15,875 C. $15,738 D. $16,276 $8,500 + $2.50 2,950 = $15,875

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

130. The activity variance for administrative expenses in February would be closest to: A. $150 U B. $20 U C. $20 F D. $150 F

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-222

Chapter 08 - Flexible Budgets and Performance Analysis

131. The spending variance for facility expenses in February would be closest to: A. $130 U B. $130 F C. $5 U D. $5 F

Since the actual expense is greater than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-223

Chapter 08 - Flexible Budgets and Performance Analysis

Rippelmeyer Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During June, the kennel budgeted for 3,600 tenant-days, but its actual level of activity was 3,550 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for June:

132. The administrative expenses in the planning budget for June would be closest to: A. $7,996 B. $7,885 C. $7,555 D. $7,560 $7,200 + $0.10 3,600 = $7,560

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-224

Chapter 08 - Flexible Budgets and Performance Analysis

133. The expendables in the flexible budget for June would be closest to: A. $33,666 B. $34,270 C. $34,740 D. $34,621 $900 + $9.40 3,550 = $34,270

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

134. The activity variance for wages and salaries in June would be closest to: A. $310 F B. $110 F C. $310 U D. $110 U

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-225

Chapter 08 - Flexible Budgets and Performance Analysis

135. The spending variance for expendables in June would be closest to: A. $130 F B. $600 U C. $130 U D. $600 F

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-226

Chapter 08 - Flexible Budgets and Performance Analysis

Baugus Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During August, the company budgeted for 6,900 units, but its actual level of activity was 6,950 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for August:

136. The direct labor in the planning budget for August would be closest to: A. $27,760 B. $29,190 C. $27,560 D. $28,980 $0 + $4.20 6,900 = $28,980

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-227

Chapter 08 - Flexible Budgets and Performance Analysis

137. The direct materials in the flexible budget for August would be closest to: A. $127,650 B. $128,575 C. $127,581 D. $129,436 $0 + $18.50 6,950 = $128,575

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

138. The activity variance for direct labor in August would be closest to: A. $1,220 F B. $210 U C. $210 F D. $1,220 U

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-228

Chapter 08 - Flexible Budgets and Performance Analysis

139. The revenue variance for August would be closest to: A. $1,450 F B. $1,450 U C. $430 F D. $430 U

Since the actual revenue is less than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

140. The spending variance for direct materials in August would be closest to: A. $70 F B. $855 U C. $70 U D. $855 F

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-229

Chapter 08 - Flexible Budgets and Performance Analysis

Lampert Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During March, the company budgeted for 6,100 units, but its actual level of activity was 6,060 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for March:

141. The selling and administrative expenses in the planning budget for March would be closest to: A. $26,560 B. $27,647 C. $27,466 D. $26,536 $22,900 + $0.60 6,100 = $26,560

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-230

Chapter 08 - Flexible Budgets and Performance Analysis

142. The manufacturing overhead in the flexible budget for March would be closest to: A. $48,822 B. $51,384 C. $51,440 D. $49,468 $42,900 + $1.40 6,060 = $51,384

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

143. The activity variance for selling and administrative expenses in March would be closest to: A. $906 U B. $906 F C. $24 U D. $24 F

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-231

Chapter 08 - Flexible Budgets and Performance Analysis

144. The spending variance for direct materials in March would be closest to: A. $900 F B. $900 U C. $1,376 U D. $1,376 F

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-232

Chapter 08 - Flexible Budgets and Performance Analysis

Woofter Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During January, the company budgeted for 7,600 units, but its actual level of activity was 7,560 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for January:

8-233

Chapter 08 - Flexible Budgets and Performance Analysis

145. The net operating income in the planning budget for January would be closest to: A. $16,410 B. $16,238 C. $28,604 D. $29,140

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

146. The net operating income in the flexible budget for January would be closest to: A. $28,604 B. $16,238 C. $16,410 D. $29,140

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-234

Chapter 08 - Flexible Budgets and Performance Analysis

147. The activity variance for net operating income in January would be closest to: A. $12,816 F B. $12,816 U C. $536 F D. $536 U

Since the flexible budget net operating income is less than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-235

Chapter 08 - Flexible Budgets and Performance Analysis

148. The overall revenue and spending variance (i.e., the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for January would be closest to: A. $12,816 F B. $12,280 U C. $12,816 U D. $12,280 F

Since the actual net operating income is less than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-236

Chapter 08 - Flexible Budgets and Performance Analysis

Buffaloe Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During August, the company budgeted for 5,200 units, but its actual level of activity was 5,250 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for August:

149. The direct labor in the planning budget for August would be closest to: A. $40,040 B. $41,015 C. $40,425 D. $40,624 $0 + $7.70 5,200 = $40,040

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-237

Chapter 08 - Flexible Budgets and Performance Analysis

150. The manufacturing overhead in the flexible budget for August would be closest to: A. $53,919 B. $55,525 C. $52,896 D. $55,460 $48,700 + $1.30 5,250 = $55,525

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

151. The activity variance for selling and administrative expenses in August would be closest to: A. $690 F B. $690 U C. $20 F D. $20 U

Since the flexible budget is greater than the planning budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-238

Chapter 08 - Flexible Budgets and Performance Analysis

152. The spending variance for manufacturing overhead in August would be closest to: A. $2,055 F B. $2,055 U C. $2,120 U D. $2,120 F

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-239

Chapter 08 - Flexible Budgets and Performance Analysis

Luc Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During February, the company budgeted for 5,000 units, but its actual level of activity was 4,950 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for February:

153. The selling and administrative expenses in the planning budget for February would be closest to: A. $30,490 B. $30,495 C. $30,500 D. $30,190 $29,500 + $0.20 5,000 = $30,500

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-240

Chapter 08 - Flexible Budgets and Performance Analysis

154. The direct materials in the flexible budget for February would be closest to: A. $91,575 B. $95,985 C. $92,500 D. $94,075 $0 + $18.50 4,950 = $91,575

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

155. The activity variance for direct labor in February would be closest to: A. $340 U B. $760 F C. $340 F D. $760 U

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

8-241

Chapter 08 - Flexible Budgets and Performance Analysis

156. The spending variance for direct materials in February would be closest to: A. $3,450 F B. $2,525 U C. $3,450 U D. $2,525 F

Since the actual expense is greater than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Learning Objective: 4 Level: Medium

Worden Hospital bases its budgets on patient-visits. The hospital's static budget for February appears below:

8-242

Chapter 08 - Flexible Budgets and Performance Analysis

157. The total variable cost at the activity level of 4,400 patient-visits per month should be: A. $85,140 B. $87,120 C. $65,120 D. $63,640 Total variable cost = ($6.10 + $8.70) 4,400 = $65,120

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

158. The total fixed cost at the activity level of 4,700 patient-visits per month should be: A. $162,620 B. $148,780 C. $93,060 D. $85,140 Total fixed cost = $33,110 + $52,030 = $85,140

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-243

Chapter 08 - Flexible Budgets and Performance Analysis

159. The total cost at the activity level of 4,600 patient-visits per month should be: A. $153,720 B. $148,780 C. $153,220 D. $159,160 Total fixed cost = $33,110 + $52,030 = $85,140 Total cost = [($6.10 + $8.70) 4,600] + $85,140 = $153,220

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

Dwelmont Hotel bases its budgets on guest-days. The hotel's static budget for May appears below:

8-244

Chapter 08 - Flexible Budgets and Performance Analysis

160. The total variable cost at the activity level of 2,600 guest-days per month should be: A. $36,920 B. $32,660 C. $45,540 D. $51,480 Total variable cost = ($8.30 + $5.90) 2,600 = $36,920

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

161. The total fixed cost at the activity level of 2,900 guest-days per month should be: A. $78,200 B. $57,420 C. $98,600 D. $45,540 Total fixed cost = $27,830 + $17,710 = $45,540

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-245

Chapter 08 - Flexible Budgets and Performance Analysis

162. The total cost at the activity level of 2,800 guest-days per month should be: A. $95,200 B. $86,230 C. $85,300 D. $78,200 Total fixed cost = $27,830 + $17,710 = $45,540 Total cost = [($8.30 + $5.90) 2,800] + $45,540 = $85,300

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

Springmeyer Clinic uses client-visits as its measure of activity. During August, the clinic budgeted for 2,900 client-visits, but its actual level of activity was 2,940 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for August:

8-246

Chapter 08 - Flexible Budgets and Performance Analysis

163. The personnel expenses in the planning budget for August would be closest to: A. $69,600 B. $73,800 C. $70,560 D. $73,200 $29,700 + $15 2,900 = $73,200

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

164. The administrative expenses in the planning budget for August would be closest to: A. $7,594 B. $7,590 C. $7,165 D. $7,264 $7,300 + $0.10 2,900 = $7,590

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-247

Chapter 08 - Flexible Budgets and Performance Analysis

165. The net operating income in the planning budget for August would be closest to: A. $15,416 B. $11,878 C. $11,557 D. $14,560

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

Weisgarber Clinic uses client-visits as its measure of activity. During August, the clinic budgeted for 3,900 client-visits, but its actual level of activity was 3,850 client-visits. The clinic has provided the following data concerning the formulas to be used in its budgeting for August:

8-248

Chapter 08 - Flexible Budgets and Performance Analysis

166. The personnel expenses in the planning budget for August would be closest to: A. $83,940 B. $88,444 C. $83,310 D. $87,310 $34,800 + $12.60 3,900 = $83,940

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

167. The administrative expenses in the planning budget for August would be closest to: A. $7,780 B. $8,144 C. $8,040 D. $7,770 $7,000 + $0.20 3,900 = $7,780

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-249

Chapter 08 - Flexible Budgets and Performance Analysis

168. The net operating income in the planning budget for August would be closest to: A. $15,615 B. $15,217 C. $18,705 D. $19,670

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

Smithson Clinic uses client-visits as its measure of activity. During May, the clinic budgeted for 3,300 client-visits, but its actual level of activity was 3,270 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for May:

8-250

Chapter 08 - Flexible Budgets and Performance Analysis

169. The medical supplies in the flexible budget for May would be closest to: A. $14,907 B. $15,488 C. $15,207 D. $15,030 $1,500 + $4.10 3,270 = $14,907

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

170. The occupancy expenses in the flexible budget for May would be closest to: A. $14,334 B. $13,840 C. $13,786 D. $14,599 $7,900 + $1.80 3,270 = $13,786

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-251

Chapter 08 - Flexible Budgets and Performance Analysis

171. The net operating income in the flexible budget for May would be closest to: A. $9,731 B. $9,555 C. $10,293 D. $10,770

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

Mah Clinic uses client-visits as its measure of activity. During April, the clinic budgeted for 3,800 client-visits, but its actual level of activity was 3,750 client-visits. The clinic has provided the following data concerning the formulas to be used in its budgeting:

8-252

Chapter 08 - Flexible Budgets and Performance Analysis

172. The medical supplies in the flexible budget for April would be closest to: A. $21,340 B. $22,600 C. $22,325 D. $21,913 $1,700 + $5.50 3,750 = $22,325

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

173. The occupancy expenses in the flexible budget for April would be closest to: A. $15,575 B. $15,660 C. $14,975 D. $15,377 $9,200 + $1.70 3,750 = $15,575

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-253

Chapter 08 - Flexible Budgets and Performance Analysis

174. The net operating income in the flexible budget for April would be closest to: A. $12,550 B. $14,987 C. $13,420 D. $14,595

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

Lauser Clinic uses client-visits as its measure of activity. During July, the clinic budgeted for 3,700 client-visits, but its actual level of activity was 3,690 client-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for July:

8-254

Chapter 08 - Flexible Budgets and Performance Analysis

175. The personnel expenses in the planning budget for July would be closest to: A. $54,730 B. $54,641 C. $52,341 D. $52,483 $21,800 + $8.90 3,700 = $54,730

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

176. The occupancy expenses in the flexible budget for July would be closest to: A. $12,466 B. $12,991 C. $12,921 D. $12,480 $7,300 + $1.40 3,690 = $12,466

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-255

Chapter 08 - Flexible Budgets and Performance Analysis

177. The net operating income in the flexible budget for July would be closest to: A. $17,215 B. $17,122 C. $11,140 D. $11,018

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

Higgenbotham Clinic uses client-visits as its measure of activity. During May, the clinic budgeted for 3,600 client-visits, but its actual level of activity was 3,580 client-visits. The clinic has provided the following data concerning the formulas to be used in its budgeting for May:

8-256

Chapter 08 - Flexible Budgets and Performance Analysis

178. The administrative expenses in the planning budget for May would be closest to: A. $5,261 B. $5,440 C. $5,232 D. $5,432 $4,000 + $0.40 3,600 = $5,440

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

179. The net operating income in the planning budget for May would be closest to: A. $18,274 B. $13,920 C. $18,479 D. $13,616

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-257

Chapter 08 - Flexible Budgets and Performance Analysis

180. The medical supplies in the flexible budget for May would be closest to: A. $20,164 B. $19,340 C. $19,941 D. $19,242 $1,700 + $4.90 3,580 = $19,242

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

Jauron Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During September, the kennel budgeted for 2,300 tenant-days, but its actual level of activity was 2,310 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for September:

8-258

Chapter 08 - Flexible Budgets and Performance Analysis

181. The wages and salaries in the planning budget for September would be closest to: A. $13,741 B. $13,682 C. $13,781 D. $13,730 $2,000 + $5.10 2,300 = $13,730

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

182. The administrative expenses in the planning budget for September would be closest to: A. $7,362 B. $7,181 C. $7,360 D. $7,212 $6,900 + $0.20 2,300 = $7,360

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-259

Chapter 08 - Flexible Budgets and Performance Analysis

183. The net operating income in the planning budget for September would be closest to: A. $10,772 B. $6,979 C. $10,866 D. $6,870

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

Lutts Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During November, the kennel budgeted for 3,800 tenant-days, but its actual level of activity was 3,850 tenant-days. The kennel has provided the following data concerning the formulas to be used in its budgeting:

8-260

Chapter 08 - Flexible Budgets and Performance Analysis

184. The wages and salaries in the planning budget for November would be closest to: A. $27,610 B. $27,280 C. $28,238 D. $28,610 $2,200 + $6.60 3,800 = $27,280

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

185. The administrative expenses in the planning budget for November would be closest to: A. $7,310 B. $7,520 C. $7,540 D. $7,215 $6,000 + $0.40 3,800 = $7,520

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-261

Chapter 08 - Flexible Budgets and Performance Analysis

186. The net operating income in the planning budget for November would be closest to: A. $12,720 B. $9,648 C. $9,904 D. $13,115

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-262

Chapter 08 - Flexible Budgets and Performance Analysis

Swader Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During March, the kennel budgeted for 2,900 tenantdays, but its actual level of activity was 2,930 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for March:

187. The expendables in the flexible budget for March would be closest to: A. $25,905 B. $25,650 C. $27,274 D. $26,719 $1,000 + $8.50 2,930 = $25,905

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-263

Chapter 08 - Flexible Budgets and Performance Analysis

188. The facility expenses in the flexible budget for March would be closest to: A. $20,700 B. $20,369 C. $20,793 D. $20,820 $9,100 + $4 2,930 = $20,820

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

189. The net operating income in the flexible budget for March would be closest to: A. $12,522 B. $12,267 C. $9,414 D. $9,120

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-264

Chapter 08 - Flexible Budgets and Performance Analysis

Whetstine Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During September, the kennel budgeted for 3,200 tenant-days, but its actual level of activity was 3,180 tenant-days. The kennel has provided the following data concerning the formulas to be used in its budgeting:

190. The expendables in the flexible budget for September would be closest to: A. $27,630 B. $27,864 C. $27,517 D. $27,800 $600 + $8.50 3,180 = $27,630

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-265

Chapter 08 - Flexible Budgets and Performance Analysis

191. The facility expenses in the flexible budget for September would be closest to: A. $21,320 B. $21,238 C. $21,513 D. $21,784 $8,200 + $4.10 3,180 = $21,238

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

192. The net operating income in the flexible budget for September would be closest to: A. $8,548 B. $4,967 C. $5,029 D. $8,720

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-266

Chapter 08 - Flexible Budgets and Performance Analysis

Kalinowski Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During February, the kennel budgeted for 2,300 tenant-days, but its actual level of activity was 2,320 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for February:

193. The wages and salaries in the planning budget for February would be closest to: A. $15,570 B. $16,197 C. $16,338 D. $15,688 $2,000 + $5.90 2,300 = $15,570

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-267

Chapter 08 - Flexible Budgets and Performance Analysis

194. The facility expenses in the flexible budget for February would be closest to: A. $18,680 B. $19,046 C. $19,379 D. $18,772 $8,100 + $4.60 2,320 = $18,772

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

195. The net operating income in the flexible budget for February would be closest to: A. $10,370 B. $10,608 C. $7,642 D. $7,775

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-268

Chapter 08 - Flexible Budgets and Performance Analysis

Laboe Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During February, the kennel budgeted for 2,900 tenantdays, but its actual level of activity was 2,940 tenant-days. The kennel has provided the following data concerning the formulas to be used in its budgeting:

196. The administrative expenses in the planning budget for February would be closest to: A. $7,814 B. $7,770 C. $7,922 D. $7,782 $6,900 + $0.30 2,900 = $7,770

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-269

Chapter 08 - Flexible Budgets and Performance Analysis

197. The net operating income in the planning budget for February would be closest to: A. $7,191 B. $7,391 C. $7,900 D. $8,260

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

198. The expendables in the flexible budget for February would be closest to: A. $26,990 B. $27,354 C. $27,021 D. $27,772 $600 + $9.10 2,940 = $27,354

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-270

Chapter 08 - Flexible Budgets and Performance Analysis

Dantuono Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During November, the company budgeted for 7,700 units, but its actual level of activity was 7,720 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for November:

199. The direct labor in the planning budget for November would be closest to: A. $44,004 B. $42,744 C. $42,633 D. $43,890 $0 + $5.70 7,700 = $43,890

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-271

Chapter 08 - Flexible Budgets and Performance Analysis

200. The selling and administrative expenses in the planning budget for November would be closest to: A. $30,490 B. $29,974 C. $30,504 D. $29,896 $25,100 + $0.70 7,700 = $30,490

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

201. The net operating income in the planning budget for November would be closest to: A. $35,093 B. $29,340 C. $35,275 D. $29,604

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-272

Chapter 08 - Flexible Budgets and Performance Analysis

Menson Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During December, the company budgeted for 5,800 units, but its actual level of activity was 5,830 units. The company has provided the following data concerning the formulas to be used in its budgeting:

202. The direct labor in the planning budget for December would be closest to: A. $46,057 B. $45,820 C. $43,927 D. $43,701 $0 + $7.90 5,800 = $45,820

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-273

Chapter 08 - Flexible Budgets and Performance Analysis

203. The selling and administrative expenses in the planning budget for December would be closest to: A. $24,898 B. $24,880 C. $23,988 D. $23,865 $21,400 + $0.60 5,800 = $24,880

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

204. The net operating income in the planning budget for December would be closest to: A. $19,788 B. $24,979 C. $19,380 D. $25,238

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-274

Chapter 08 - Flexible Budgets and Performance Analysis

Nasson Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During August, the company budgeted for 6,700 units, but its actual level of activity was 6,730 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for August:

205. The direct materials in the flexible budget for August would be closest to: A. $71,020 B. $71,338 C. $72,913 D. $72,264 $0 + $10.60 6,730 = $71,338

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-275

Chapter 08 - Flexible Budgets and Performance Analysis

206. The manufacturing overhead in the flexible budget for August would be closest to: A. $55,358 B. $55,855 C. $55,076 D. $55,040 $47,000 + $1.20 6,730 = $55,076

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

207. The net operating income in the flexible budget for August would be closest to: A. $22,506 B. $18,317 C. $17,930 D. $22,708

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-276

Chapter 08 - Flexible Budgets and Performance Analysis

Poulsen Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During July, the company budgeted for 7,300 units, but its actual level of activity was 7,270 units. The company has provided the following data concerning the formulas to be used in its budgeting:

208. The direct materials in the flexible budget for July would be closest to: A. $68,338 B. $70,298 C. $68,620 D. $70,879 $0 + $9.40 7,270 = $68,338

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-277

Chapter 08 - Flexible Budgets and Performance Analysis

209. The manufacturing overhead in the flexible budget for July would be closest to: A. $47,190 B. $47,151 C. $45,344 D. $45,719 $37,700 + $1.30 7,270 = $47,151

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

210. The net operating income in the flexible budget for July would be closest to: A. $9,234 B. $9,310 C. $19,262 D. $19,580

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-278

Chapter 08 - Flexible Budgets and Performance Analysis

Witherington Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During June, the company budgeted for 7,800 units, but its actual level of activity was 7,850 units. The company has provided the following data concerning the formulas used in its budgeting and its actual results for June:

211. The direct labor in the planning budget for June would be closest to: A. $32,970 B. $32,760 C. $34,310 D. $34,091 $0 + $4.20 7,800 = $32,760

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-279

Chapter 08 - Flexible Budgets and Performance Analysis

212. The manufacturing overhead in the flexible budget for June would be closest to: A. $57,435 B. $54,794 C. $57,380 D. $55,498 $48,800 + $1.10 7,850 = $57,435

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

213. The net operating income in the flexible budget for June would be closest to: A. $34,017 B. $33,585 C. $29,520 D. $30,190

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Medium

8-280

Chapter 08 - Flexible Budgets and Performance Analysis

Manago Corporation manufactures and sells a single product. The company uses units as the measure of activity in its budgets and performance reports. During March, the company budgeted for 5,300 units, but its actual level of activity was 5,310 units. The company has provided the following data concerning the formulas to be used in its budgeting:

214. The selling and administrative expenses in the planning budget for March would be closest to: A. $25,640 B. $26,199 C. $26,248 D. $25,648 $21,400 + $0.80 5,300 = $25,640

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-281

Chapter 08 - Flexible Budgets and Performance Analysis

215. The net operating income in the planning budget for March would be closest to: A. $11,705 B. $21,877 C. $21,710 D. $11,749

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

216. The direct materials in the flexible budget for March would be closest to: A. $73,278 B. $73,929 C. $73,140 D. $74,208 $0 + $13.80 5,310 = $73,278

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 1 Level: Easy

8-282

Chapter 08 - Flexible Budgets and Performance Analysis

Bessey Hospital bases its budgets on patient-visits. The hospital's static planning budget for January appears below:

Actual results for the month were:

217. The spending variance for supplies costs in the flexible budget performance report for the month is: A. $4,180 F B. $4,180 U C. $2,560 F D. $2,560 U

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

8-283

Chapter 08 - Flexible Budgets and Performance Analysis

218. The spending variance for laundry costs in the flexible budget performance report for the month is: A. $730 F B. $2,470 F C. $730 U D. $2,470 U

Since the actual expense is more than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

219. The spending variance for occupancy costs in the flexible budget performance report for the month is: A. $330 F B. $2,090 F C. $330 U D. $2,090 U

Since the actual expense is more than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

8-284

Chapter 08 - Flexible Budgets and Performance Analysis

Salling Corporation bases its budgets on machine-hours. The company's static planning budget for May appears below:

Actual results for the month were:

220. The spending variance for supplies costs in the flexible budget performance report for the month should be: A. $1,340 U B. $1,340 F C. $460 U D. $460 F

Since the actual expense is more than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

8-285

Chapter 08 - Flexible Budgets and Performance Analysis

221. The spending variance for power costs in the flexible budget performance report for the month should be: A. $310 U B. $310 F C. $820 U D. $820 F

Since the actual expense is more than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

222. The spending variance for equipment depreciation in the flexible budget performance report for the month should be: A. $540 F B. $10 F C. $10 U D. $540 U

Since the actual expense is more than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

8-286

Chapter 08 - Flexible Budgets and Performance Analysis

Genito Corporation's static planning budget for October appears below. The company bases its budgets on machine-hours.

In October, the actual number of machine-hours was 8,800, the actual supplies cost was $69,450, the actual power cost was $34,190, the actual salaries cost was $86,490, and the actual equipment depreciation was $37,600.

223. The spending variance for supplies cost in the flexible budget performance report for the month should be: A. $4,500 F B. $7,110 F C. $7,110 U D. $4,500 U

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

8-287

Chapter 08 - Flexible Budgets and Performance Analysis

224. The spending variance for power cost in the flexible budget performance report for the month should be: A. $1,510 F B. $2,770 U C. $1,510 U D. $2,770 F

Since the actual expense is less than the flexible budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

225. The spending variance for equipment depreciation in the flexible budget performance report for the month should be: A. $200 U B. $1,120 F C. $200 F D. $1,120 U

Since the actual expense is more than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 3 Level: Easy

8-288

Chapter 08 - Flexible Budgets and Performance Analysis

Lauter Printing uses two measures of activity, press runs and book set-ups, in the cost formulas in its budgets and performance reports. The cost formula for wages and salaries is $5,300 per month plus $480 per press run plus $1,080 per book set-up. The company expected its activity in October to be 169 press runs and 64 book set-ups, but the actual activity was 167 press runs and 60 book set-ups. The actual cost for wages and salaries in October was $155,690.

226. The wages and salaries in the planning budget for October would be closest to: A. $157,555 B. $155,690 C. $150,260 D. $155,540 $5,300 + $480 169 + $1,080 64 = $155,540

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 5 Level: Easy

227. The wages and salaries in the flexible budget for October would be closest to: A. $155,540 B. $155,690 C. $150,260 D. $153,699 $5,300 + $480 167 + $1,080 60 = $150,260

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 5 Level: Easy

8-289

Chapter 08 - Flexible Budgets and Performance Analysis

228. The activity variance for wages and salaries in October would be closest to: A. $5,280 U B. $150 U C. $150 F D. $5,280 F

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 4 Learning Objective: 5 Level: Easy

229. The spending variance for wages and salaries in October would be closest to: A. $5,430 U B. $150 U C. $5,430 F D. $150 F

Since the actual expense is greater than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 4 Learning Objective: 5 Level: Easy

8-290

Chapter 08 - Flexible Budgets and Performance Analysis

Spraque Air uses two measures of activity, flights and passengers, in the cost formulas in its budgets and performance reports. The cost formula for plane operating costs is $40,520 per month plus $2,733 per flight plus $11 per passenger. The company expected its activity in June to be 71 flights and 207 passengers, but the actual activity was 70 flights and 205 passengers. The actual cost for plane operating costs in June was $239,580.

230. The plane operating costs in the planning budget for June would be closest to: A. $239,580 B. $236,840 C. $234,085 D. $243,003 $40,520 + $2,733 71 + $11 207 = $236,840

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 5 Level: Easy

231. The plane operating costs in the flexible budget for June would be closest to: A. $233,504 B. $234,085 C. $239,580 D. $236,840 $40,520 + $2,733 70 + $11 205 = $234,085

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 5 Level: Easy

8-291

Chapter 08 - Flexible Budgets and Performance Analysis

232. The activity variance for plane operating costs in June would be closest to: A. $2,755 U B. $2,755 F C. $2,740 F D. $2,740 U

Since the flexible budget expense is less than the planning budget, the variance is favorable (F)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 4 Learning Objective: 5 Level: Easy

233. The spending variance for plane operating costs in June would be closest to: A. $2,740 U B. $5,495 U C. $5,495 F D. $2,740 F

Since the actual expense is greater than the flexible budget, the variance is unfavorable (U)

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Application Learning Objective: 4 Learning Objective: 5 Level: Easy

8-292

Chapter 08 - Flexible Budgets and Performance Analysis


Essay Questions

234. Immen Corporation bases its budgets on the activity measure customers served. During May, the company planned to serve 38,000 customers. The company has provided the following data concerning the formulas it uses in its budgeting:

The company has also furnished its income statement for May:

Required: Prepare a report showing the company's activity variances for May. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

8-293

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 2 Level: Medium

8-294

Chapter 08 - Flexible Budgets and Performance Analysis

235. Faggs Corporation bases its budgets on the activity measure customers served. During December, the company planned to serve 33,000 customers, but actually served 36,000 customers. The company has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare a report showing the company's activity variances for December. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 2 Level: Easy

8-295

Chapter 08 - Flexible Budgets and Performance Analysis

236. Brynteson Corporation bases its budgets on the activity measure customers served. During September, the company planned to serve 24,000 customers, but actually served 19,000 customers. The company uses the following revenue and cost formulas in its budgeting, where q is the number of customers served: Revenue: $2.90q Wages and salaries: $24,700 + $0.90q Supplies: $0.40q Insurance: $4,900 Miscellaneous: $2,800 + $0.10q Required: Prepare a report showing the company's activity variances for September. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 2 Level: Easy

8-296

Chapter 08 - Flexible Budgets and Performance Analysis

237. Domin Corporation bases its budgets on the activity measure customers served. During April, the company planned to serve 31,000 customers, but actually served 35,000 customers. Revenue is $4.80 per customer served. Wages and salaries are $33,000 per month plus $1.60 per customer served. Supplies are $1.00 per customer served. Insurance is $12,200 per month. Miscellaneous expenses are $7,400 per month plus $0.20 per customer served. Required: Prepare a report showing the company's activity variances for April. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 2 Level: Easy

8-297

Chapter 08 - Flexible Budgets and Performance Analysis

238. Fasano Clinic bases its budgets on the activity measure patient-visits. During April, the clinic planned for 3,800 patient-visits. The clinic has provided the following data concerning the formulas it uses in its budgeting:

The clinic has also furnished its income statement for April:

Required: Prepare a report showing the clinic's activity variances for April.

8-298

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 2 Level: Medium

8-299

Chapter 08 - Flexible Budgets and Performance Analysis

239. Mulvehill Clinic bases its budgets on the activity measure patient-visits. During June, the clinic planned for 3,000 patient-visits, but the actual level of activity was 3,400 patient-visits. The clinic has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare a report showing the clinic's activity variances for June. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

8-300

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 2 Level: Easy

240. Mccarter Clinic bases its budgets on the activity measure patient-visits. During April, the clinic planned for 2,700 patient-visits, but its actual level of activity was 2,400 patient-visits. The clinic has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare a report showing the clinic's activity variances for April. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

8-301

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 2 Level: Easy

241. Delamarter Clinic bases its budgets on the activity measure patient-visits. During June, the clinic planned for 2,600 patient-visits, but its actual level of activity was 3,100 patientvisits. Revenue should be $53.40 per patient-visit. Personnel expenses should be $39,700 per month plus $12.60 per patient-visit. Medical supplies should be $1,800 per month plus $10.40 per patient-visit. Occupancy expenses should be $8,200 per month plus $2.30 per patientvisit. Administrative expenses should be $6,100 per month plus $0.20 per patient-visit. Required: Prepare a report showing the clinic's activity variances for June. Indicate in each case whether the variance is favorable (F) or unfavorable (U).

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 2 Level: Easy

8-302

Chapter 08 - Flexible Budgets and Performance Analysis

242. Alicuben Memorial Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for October was based on 2,200 meals, but the diner actually served 2,000 meals. The diner's director has provided the following cost formulas to use in budgets:

The director has also provided the diner's statement of actual expenses for the month:

Required: Prepare a report showing the activity variances for each of the expenses and for total expenses for October. Label each variance as favorable (F) or unfavorable (U).

8-303

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 2 Level: Medium

8-304

Chapter 08 - Flexible Budgets and Performance Analysis

243. Aslanian Memorial Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for November was based on 2,200 meals, but the diner actually served 2,700 meals. The diner's director has provided the following cost formulas to use in budgets:

Required: Prepare a report showing the activity variances for each of the expenses and for total expenses for November. Label each variance as favorable (F) or unfavorable (U). Label each variance as favorable (F) or unfavorable (U).

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 2 Level: Easy

8-305

Chapter 08 - Flexible Budgets and Performance Analysis

244. Mulry Urban Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for September was based on 3,000 meals, but the diner actually served 2,800 meals. The diner's director has provided the following cost data to use in the budget: groceries, $2.45 per meal; kitchen operations, $4,900 per month plus $1.65 per meal; administrative expenses, $3,600 per month plus $0.60 per meal; and fundraising expenses, $1,200 per month. The director has also provided the diner's statement of actual expenses for the month:

Required: Prepare a report showing the activity variances for each of the expenses and for total expenses for September.

8-306

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 2 Level: Medium

245. Flicker Urban Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for December was based on 2,400 meals, but the diner actually served 2,300 meals. The diner's director has provided the following cost data to use in the budget: groceries, $2.00 per meal; kitchen operations, $5,100 per month plus $1.85 per meal; administrative expenses, $2,900 per month plus $0.65 per meal; and fundraising expenses, $1,000 per month. Required: Prepare a report showing the activity variances for each of the expenses and for total expenses for December. Label each variance as favorable (F) or unfavorable (U).

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 2 Level: Easy

8-307

Chapter 08 - Flexible Budgets and Performance Analysis

246. Lakey Corporation uses customers served as its measure of activity. During July, the company budgeted for 33,000 customers, but actually served 34,000 customers. The company has provided the following data concerning the formulas used in its budgeting and its actual results for July:

Required: Prepare a report showing the company's revenue and spending variances for July. Label each variance as favorable (F) or unfavorable (U).

8-308

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 3 Level: Medium

8-309

Chapter 08 - Flexible Budgets and Performance Analysis

247. Mieras Corporation uses customers served as its measure of activity. During January, the company budgeted for 37,000 customers, but actually served 36,000 customers. The company uses the following revenue and cost formulas in its budgeting, where q is the number of customers served: Revenue: $2.80q Wages and salaries: $22,800 + $0.90q Supplies: $0.50q Insurance: $7,500 Miscellaneous: $3,800 + $0.30q The company reported the following actual results for January:

Required: Prepare a report showing the company's revenue and spending variances for January. Label each variance as favorable (F) or unfavorable (U).

8-310

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 3 Level: Medium

248. Fuquay Corporation uses customers served as its measure of activity. The company bases its budgets on the following information: Revenue should be $4.80 per customer served. Wages and salaries should be $26,500 per month plus $1.70 per customer served. Supplies should be $0.90 per customer served. Insurance should be $7,100 per month. Miscellaneous expenses should be $4,700 per month plus $0.20 per customer served. The company reported the following actual results for May:

Required: Prepare a report showing the company's revenue and spending variances for May. Label each variance as favorable (F) or unfavorable (U).

8-311

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 3 Level: Easy

249. Kary Clinic uses patient-visits as its measure of activity. During May, the clinic budgeted for 3,800 patient-visits, but its actual level of activity was 4,100 patient-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for May:

Required: Prepare a report showing the clinic's revenue and spending variances for May. Label each variance as favorable (F) or unfavorable (U).

8-312

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 3 Level: Medium

8-313

Chapter 08 - Flexible Budgets and Performance Analysis

250. Gasco Clinic uses patient-visits as its measure of activity. During August, the clinic budgeted for 2,000 patient-visits, but its actual level of activity was 2,100 patient-visits. The clinic uses the following revenue and cost formulas in its budgeting, where q is the number of patient-visits: Revenue: $62.90q Personnel expenses: $28,500 + $20.40q Medical supplies: $1,400 + $9.90q Occupancy expenses: $8,200 + $3.30q Administrative expenses: $4,000 + $0.40q The clinic reported the following actual results for August:

Required: Prepare a report showing the clinic's revenue and spending variances for August. Label each variance as favorable (F) or unfavorable (U).

8-314

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 3 Level: Medium

8-315

Chapter 08 - Flexible Budgets and Performance Analysis

251. Braseth Clinic uses patient-visits as its measure of activity. The clinic bases its budgets on the following information: Revenue should be $39.90 per patient-visit. Personnel expenses should be $35,400 per month plus $13.00 per patient-visit. Medical supplies should be $1,100 per month plus $4.90 per patient-visit. Occupancy expenses should be $8,400 per month plus $2.00 per patient-visit. Administrative expenses should be $4,700 per month plus $0.20 per patient-visit. The clinic reported the following actual results for January:

Required: Prepare a report showing the clinic's revenue and spending variances for January. Label each variance as favorable (F) or unfavorable (U).

8-316

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 3 Level: Easy

252. Villella Memorial Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for October was based on 3,800 meals. The diner's director has provided the following cost formulas to use in budgets:

The director has also provided the diner's statement of actual expenses for the month:

Required: Prepare a report showing the spending variances for each of the expenses and for total expenses for October. Label each variance as favorable (F) or unfavorable (U).

8-317

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 3 Level: Easy

8-318

Chapter 08 - Flexible Budgets and Performance Analysis

253. Garing Urban Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for March was based on 3,600 meals. The diner's director has provided the following cost data to use in the budget: groceries, $2.20 per meal; kitchen operations, $4,300 per month plus $1.90 per meal; administrative expenses, $3,300 per month plus $0.20 per meal; and fundraising expenses, $1,000 per month. The director has also provided the diner's statement of actual expenses for the month:

Required: Prepare a report showing the diner's spending variances for each of the expenses and for total expenses for March. Label each variance as favorable (F) or unfavorable (U).

8-319

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 3 Level: Easy

254. Legorreta Corporation uses customers served as its measure of activity. The following report compares the planning budget to the actual operating results for the month of November:

Required: Prepare the company's flexible budget performance report for November. Label each variance as favorable (F) or unfavorable (U).

8-320

Chapter 08 - Flexible Budgets and Performance Analysis

8-321

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 4 Learning Objective: 6 Level: Medium

255. Duell Clinic uses patient-visits as its measure of activity. The following report compares the planning budget to the actual operating results for the month of January:

Required: Prepare the clinic's flexible budget performance report for January. Label each variance as favorable (F) or unfavorable (U).

8-322

Chapter 08 - Flexible Budgets and Performance Analysis

8-323

Chapter 08 - Flexible Budgets and Performance Analysis

8-324

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 4 Learning Objective: 6 Level: Medium

256. Squillace Corporation uses customers served as its measure of activity. During October, the company budgeted for 38,000 customers, but actually served 35,000 customers. The company has provided the following data concerning the formulas used in its budgeting and its actual results for October:

Required: Prepare the company's flexible budget performance report for October. Label each variance as favorable (F) or unfavorable (U).

8-325

Chapter 08 - Flexible Budgets and Performance Analysis

8-326

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 4 Level: Medium

257. Guy Corporation uses customers served as its measure of activity. During January, the company budgeted for 32,000 customers, but actually served 35,000 customers. The company uses the following revenue and cost formulas in its budgeting, where q is the number of customers served: Revenue: $4.20q Wages and salaries: $33,900 + $1.40q Supplies: $0.60q Insurance: $10,000 Miscellaneous: $7,000 + $0.40q The company reported the following actual results for January:

Required: Prepare the company's flexible budget performance report for January. Label each variance as favorable (F) or unfavorable (U).

8-327

Chapter 08 - Flexible Budgets and Performance Analysis

8-328

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 4 Level: Medium

258. Cotillo Corporation uses customers served as its measure of activity. During December, the company budgeted for 29,000 customers, but actually served 27,000 customers. The company bases its budgets on the following information: Revenue should be $4.40 per customer served. Wages and salaries should be $33,300 per month plus $1.80 per customer served. Supplies should be $0.60 per customer served. Insurance should be $8,900 per month. Miscellaneous expenses should be $4,600 per month plus $0.10 per customer served. The company reported the following actual results for December:

Required: Prepare the company's flexible budget performance report for December. Label each variance as favorable (F) or unfavorable (U).

8-329

Chapter 08 - Flexible Budgets and Performance Analysis

8-330

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 4 Level: Medium

259. Thews Clinic uses patient-visits as its measure of activity. During August, the clinic budgeted for 2,000 patient-visits, but its actual level of activity was 2,200 patient-visits. The clinic has provided the following data concerning the formulas used in its budgeting and its actual results for August:

Required: Prepare the clinic's flexible budget performance report for August. Label each variance as favorable (F) or unfavorable (U).

8-331

Chapter 08 - Flexible Budgets and Performance Analysis

8-332

Chapter 08 - Flexible Budgets and Performance Analysis

8-333

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 4 Level: Medium

260. Mcgannon Clinic uses patient-visits as its measure of activity. During November, the clinic budgeted for 3,700 patient-visits, but its actual level of activity was 4,100 patient-visits. The clinic uses the following revenue and cost formulas in its budgeting, where q is the number of patient-visits: Revenue: $23.90q Personnel expenses: $20,800 + $7.90q Medical supplies: $800 + $3.50q Occupancy expenses: $6,100 + $1.30q Administrative expenses: $3,100 + $0.10q The clinic reported the following actual results for November:

Required: Prepare the clinic's flexible budget performance report for November. Label each variance as favorable (F) or unfavorable (U).

8-334

Chapter 08 - Flexible Budgets and Performance Analysis

8-335

Chapter 08 - Flexible Budgets and Performance Analysis

8-336

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 4 Level: Medium

261. Vernon Clinic uses patient-visits as its measure of activity. During February, the clinic budgeted for 3,100 patient-visits, but its actual level of activity was 2,800 patient-visits. The clinic bases its budgets on the following information: Revenue should be $30.20 per patientvisit. Personnel expenses should be $20,600 per month plus $9.70 per patient-visit. Medical supplies should be $1,400 per month plus $5.40 per patient-visit. Occupancy expenses should be $5,700 per month plus $1.50 per patient-visit. Administrative expenses should be $2,500 per month plus $0.30 per patient-visit. The clinic reported the following actual results for February:

Required: Prepare the clinic's flexible budget performance report for February. Label each variance as favorable (F) or unfavorable (U).

8-337

Chapter 08 - Flexible Budgets and Performance Analysis

8-338

Chapter 08 - Flexible Budgets and Performance Analysis

8-339

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 4 Level: Medium

262. Gamon Memorial Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for April was based on 3,600 meals. The diner's director has provided the following cost formulas to use in budgets:

The director has also provided the diner's statement of actual expenses for the month:

Required: Prepare a flexible budget performance report showing both the activity variances and the spending variances for each of the expenses and for total expenses for April. Label each variance as favorable (F) or unfavorable (U).

8-340

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 4 Level: Easy

8-341

Chapter 08 - Flexible Budgets and Performance Analysis

263. Wrape Urban Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for April was based on 2,100 meals. The diner's director has provided the following cost data to use in the budget: groceries, $2.55 per meal; kitchen operations, $4,700 per month plus $1.70 per meal; administrative expenses, $3,300 per month plus $0.60 per meal; and fundraising expenses, $1,000 per month. The director has also provided the diner's statement of actual expenses for the month:

Required: Prepare a flexible budget performance report showing both the activity variances and the spending variances for each of the expenses and for total expenses for April. Label each variance as favorable (F) or unfavorable (U).

8-342

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Learning Objective: 4 Level: Easy

8-343

Chapter 08 - Flexible Budgets and Performance Analysis

264. Hausman Hospital bases its budgets on patient-visits. The hospital's static planning budget for October appears below:

Required: Prepare a flexible budget for 8,900 patient-visits per month.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-344

Chapter 08 - Flexible Budgets and Performance Analysis

265. Turiano Corporation bases its budgets on machine-hours. The company's static planning budget for November appears below:

Required: Prepare a flexible budget for 9,800 machine-hours per month.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-345

Chapter 08 - Flexible Budgets and Performance Analysis

266. Therrien Corporation bases its budgets on the activity measure customers served. During September, the company plans to serve 30,000 customers. The company has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare the company's planning budget for September.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-346

Chapter 08 - Flexible Budgets and Performance Analysis

267. During March, Holston Corporation plans to serve 31,000 customers. The company uses the following revenue and cost formulas in its budgeting, where q is the number of customers served: Revenue: $4.60q Wages and salaries: $36,600 + $1.60q Supplies: $0.80q Insurance: $10,900 Miscellaneous: $8,500 + $0.20q Required: Prepare the company's planning budget for March.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-347

Chapter 08 - Flexible Budgets and Performance Analysis

268. During August, Klinck Corporation plans to serve 33,000 customers. Revenue is $2.50 per customer served. Wages and salaries are $24,300 per month plus $0.90 per customer served. Supplies are $0.30 per customer served. Insurance is $7,100 per month. Miscellaneous expenses are $5,200 per month plus $0.10 per customer served. Required: Prepare the company's planning budget for August.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-348

Chapter 08 - Flexible Budgets and Performance Analysis

269. Novielli Corporation bases its budgets on the activity measure customers served. During November, the company planned to serve 39,000 customers, but actually served 44,000 customers. The company has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare the company's flexible budget for November based on the actual level of activity for the month.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-349

Chapter 08 - Flexible Budgets and Performance Analysis

270. During September, Booker Corporation budgeted for 20,000 customers, but actually served 22,000 customers. The company uses the following revenue and cost formulas in its budgeting, where q is the number of customers served: Revenue: $5.50q Wages and salaries: $28,300 + $1.70q Supplies: $1.00q Insurance: $6,300 Miscellaneous: $5,400 + $0.40q Required: Prepare the company's flexible budget for September based on the actual level of activity for the month.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-350

Chapter 08 - Flexible Budgets and Performance Analysis

271. During July, Bosell Corporation budgeted for 22,000 customers, but actually served 21,000 customers. Revenue should be $6.80 per customer served. Wages and salaries should be $35,900 per month plus $2.40 per customer served. Supplies should be $1.20 per customer served. Insurance should be $12,000 per month. Miscellaneous expenses should be $6,000 per month plus $0.30 per customer served. Required: Prepare the company's flexible budget for July based on the actual level of activity for the month.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-351

Chapter 08 - Flexible Budgets and Performance Analysis

272. Gramling Clinic bases its budgets on patient-visits. During July, the clinic plans for a level of activity of 2,500 patient-visits. The clinic has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare the clinic's planning budget for July.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-352

Chapter 08 - Flexible Budgets and Performance Analysis

273. During September, Noaks Clinic plans for an activity level of 3,300 patient-visits. The clinic uses the following revenue and cost formulas in its budgeting, where q is the number of patient-visits: Revenue: $30.50q Personnel expenses: $30,900 + $8.40q Medical supplies: $1,200 + $4.50q Occupancy expenses: $6,400 + $1.70q Administrative expenses: $3,700 + $0.10q Required: Prepare the clinic's planning budget for September.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-353

Chapter 08 - Flexible Budgets and Performance Analysis

274. During June, Defee Clinic plans for an activity level of 3,200 patient-visits. Revenue is $50.80 per patient-visit. Personnel expenses are $35,300 per month plus $16.70 per patientvisit. Medical supplies are $1,400 per month plus $8.50 per patient-visit. Occupancy expenses are $12,500 per month plus $2.60 per patient-visit. Administrative expenses are $7,200 per month plus $0.20 per patient-visit. Required: Prepare the clinic's planning budget for June.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-354

Chapter 08 - Flexible Budgets and Performance Analysis

275. Clune Clinic bases its budgets on the activity measure patient-visits. During October, the clinic planned for an activity level of 2,100 patient-visits, but the activity level was actually 2,600 patient-visits. The clinic has provided the following data concerning the formulas it uses in its budgeting:

Required: Prepare the clinic's flexible budget for October based on the actual level of activity for the month.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-355

Chapter 08 - Flexible Budgets and Performance Analysis

276. During October, Moceri Clinic budgeted for 3,000 patient-visits, but its actual level of activity was 3,500 patient-visits. The clinic uses the following revenue and cost formulas in its budgeting, where q is the number of patient-visits: Revenue: $41.80q Personnel expenses: $30,900 + $13.70q Medical supplies: $700 + $7.80q Occupancy expenses: $8,900 + $1.50q Administrative expenses: $3,600 + $0.20q Required: Prepare the clinic's flexible budget for October based on the actual level of activity for the month.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-356

Chapter 08 - Flexible Budgets and Performance Analysis

277. During May, Phong Clinic budgeted for 2,900 patient-visits, but its actual level of activity was 3,100 patient-visits. Revenue should be $31.30 per patient-visit. Personnel expenses should be $23,700 per month plus $8.10 per patient-visit. Medical supplies should be $700 per month plus $6.20 per patient-visit. Occupancy expenses should be $7,000 per month plus $1.50 per patient-visit. Administrative expenses should be $3,400 per month plus $0.40 per patient-visit. Required: Prepare the clinic's flexible budget for May based on the actual level of activity for the month.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-357

Chapter 08 - Flexible Budgets and Performance Analysis

278. Vilanova Memorial Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for May is to be based on 2,700 meals. The diner's director has provided the following cost formulas to use in the budget:

Required: Prepare the diner's budget for the month of May. The budget will only contain the costs listed above; no revenues will be on the budget.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-358

Chapter 08 - Flexible Budgets and Performance Analysis

279. Mcduffey Memorial Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for September was based on 2,900 meals, but the diner actually served 2,800 meals. The diner's director has provided the following cost formulas to use in budgets:

Required: Prepare the diner's flexible budget for the actual number of meals served in September. The budget will only contain the costs listed above; no revenues will be on the budget.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-359

Chapter 08 - Flexible Budgets and Performance Analysis

280. Korando Urban Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for June is to be based on 2,900 meals. The diner's director has provided the following cost data to use in the budget: groceries, $2.60 per meal; kitchen operations, $4,200 per month plus $1.15 per meal; administrative expenses, $2,800 per month plus $0.65 per meal; and fundraising expenses, $1,000 per month. Required: Prepare the diner's budget for the month of June. The budget will only contain the costs listed above; no revenues will be on the budget.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-360

Chapter 08 - Flexible Budgets and Performance Analysis

281. Salvia Urban Diner is a charity supported by donations that provides free meals to the homeless. The diner's budget for May was based on 3,400 meals, but the diner actually served 3,700 meals. The diner's director has provided the following cost data to use in the budget: groceries, $2.90 per meal; kitchen operations, $4,100 per month plus $1.90 per meal; administrative expenses, $2,400 per month plus $0.20 per meal; and fundraising expenses, $1,000 per month. Required: Prepare the diner's flexible budget for the actual number of meals served in May. The budget will only contain the costs listed above; no revenues will be on the budget.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 1 Level: Easy

8-361

Chapter 08 - Flexible Budgets and Performance Analysis

282. Alarie Tech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:

In November, the school budgeted for 1,420 students and 139 courses. The actual activity for the month was 1,220 students and 142 courses. Required: Prepare a report showing the school's activity variances for November. Label each variance as favorable (F) or unfavorable (U).

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 2 Learning Objective: 5 Level: Medium

8-362

Chapter 08 - Flexible Budgets and Performance Analysis

283. Eisner Tech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:

In October, the school budgeted for 1,490 students and 85 courses. The school's income statement showing the actual results for the month appears below:

Required: Prepare a report showing the school's activity variances for October. Label each variance as favorable (F) or unfavorable (U).

8-363

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 2 Learning Objective: 5 Level: Hard

8-364

Chapter 08 - Flexible Budgets and Performance Analysis

284. Bures Jeep Tours operates jeep tours in the heart of the Colorado Rockies. The company bases its budgets on two measures of activity (i.e., cost drivers), namely guests and jeeps. One vehicle used in one tour on one day counts as a jeep. Each jeep has one tour guide. The company uses the following data in its budgeting:

In April, the company budgeted for 360 guests and 134 jeeps. The actual activity for the month was 335 guests and 136 jeeps. Required: Prepare a report showing the company's activity variances for April. Label each variance as favorable (F) or unfavorable (U).

8-365

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 2 Learning Objective: 5 Level: Medium

285. Mashore Jeep Tours operates jeep tours in the heart of the Colorado Rockies. The company bases its budgets on two measures of activity (i.e., cost drivers), namely guests and jeeps. One vehicle used in one tour on one day counts as a jeep. Each jeep has one tour guide. The company uses the following data in its budgeting:

In April, the company budgeted for 495 guests and 187 jeeps. The company's income statement showing the actual results for the month appears below:

Required: Prepare a report showing the company's activity variances for April. Label each variance as favorable (F) or unfavorable (U).

8-366

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 2 Learning Objective: 5 Level: Hard

8-367

Chapter 08 - Flexible Budgets and Performance Analysis

286. Ahrns Tech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:

In July, the school budgeted for 1,770 students and 148 courses. The school's income statement showing the actual results for the month appears below:

Required: Prepare a report showing the school's revenue and spending variances for July. Label each variance as favorable (F) or unfavorable (U).

8-368

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 3 Learning Objective: 5 Level: Hard

8-369

Chapter 08 - Flexible Budgets and Performance Analysis

287. Ruvolo Jeep Tours operates jeep tours in the heart of the Colorado Rockies. The company bases its budgets on two measures of activity (i.e., cost drivers), namely guests and jeeps. One vehicle used in one tour on one day counts as a jeep. Each jeep has one tour guide. The company uses the following data in its budgeting:

In February, the company budgeted for 436 guests and 162 jeeps. The company's income statement showing the actual results for the month appears below:

Required: Prepare a report showing the company's revenue and spending variances for February. Label each variance as favorable (F) or unfavorable (U).

8-370

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 3 Learning Objective: 5 Level: Hard

8-371

Chapter 08 - Flexible Budgets and Performance Analysis

288. Brink Tech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:

In June, the school budgeted for 1,710 students and 110 courses. The school's income statement showing the actual results for the month appears below:

Required: Prepare a flexible budget performance report showing both the school's activity variances and revenue and spending variances for June. Label each variance as favorable (F) or unfavorable (U).

8-372

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 4 Learning Objective: 5 Level: Hard

8-373

Chapter 08 - Flexible Budgets and Performance Analysis

289. Palamino Jeep Tours operates jeep tours in the heart of the Colorado Rockies. The company bases its budgets on two measures of activity (i.e., cost drivers), namely guests and jeeps. One vehicle used in one tour on one day counts as a jeep. Each jeep has one tour guide. The company uses the following data in its budgeting:

In January, the company budgeted for 330 guests and 143 jeeps. The company's income statement showing the actual results for the month appears below:

Required: Prepare a flexible budget performance report showing both the company's activity variances and revenue and spending variances for January. Label each variance as favorable (F) or unfavorable (U).

8-374

Chapter 08 - Flexible Budgets and Performance Analysis

8-375

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 4 Learning Objective: 5 Level: Hard

290. Alto Clinic uses patient-visits as its measure of activity. The clinic has provided the following report:

Required: Prepare the clinic's flexible budget performance report for June. Label each variance as favorable (F) or unfavorable (U).

8-376

Chapter 08 - Flexible Budgets and Performance Analysis

8-377

Chapter 08 - Flexible Budgets and Performance Analysis

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 4 Learning Objective: 6 Level: Hard

291. Drobot Tech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:

In November, the school budgeted for 1,470 students and 126 courses. The actual activity for the month was 1,770 students and 122 courses. Required: Prepare the school's planning budget for November.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 5 Level: Medium

8-378

Chapter 08 - Flexible Budgets and Performance Analysis

292. Hasselman Tech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:

In January, the school budgeted for 1,110 students and 105 courses. The actual activity for the month was 1,210 students and 103 courses. Required: Prepare the school's flexible budget for the actual level of activity in January.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 5 Level: Medium

8-379

Chapter 08 - Flexible Budgets and Performance Analysis

293. Lantrip Jeep Tours operates jeep tours in the heart of the Colorado Rockies. The company bases its budgets on two measures of activity (i.e., cost drivers), namely guests and jeeps. One vehicle used in one tour on one day counts as a jeep. Each jeep has one tour guide. The company uses the following data in its budgeting:

In January, the company budgeted for 356 guests and 174 jeeps. The actual activity for the month was 341 guests and 177 jeeps. Required: Prepare the company's planning budget for January.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 5 Level: Medium

8-380

Chapter 08 - Flexible Budgets and Performance Analysis

294. Karpin Jeep Tours operates jeep tours in the heart of the Colorado Rockies. The company bases its budgets on two measures of activity (i.e., cost drivers), namely guests and jeeps. One vehicle used in one tour on one day counts as a jeep. Each jeep has one tour guide. The company uses the following data in its budgeting:

In July, the company budgeted for 434 guests and 132 jeeps. The actual activity for the month was 459 guests and 137 jeeps. Required: Prepare the company's flexible budget for the actual level of activity in July.

AACSB: Analytic AICPA BB: Critical Thinking AICPA FN: Measurement Bloom's: Analysis Learning Objective: 5 Level: Medium

8-381

You might also like