MCU International College 99511 Operations Management 2004 Fall Quiz #2 Y.-H. Chen, Ph.D.
Academic and Professional Conduct exam policy:
Using unauthorized notes, copying another students
work, or providing another student with answers during
an examination is a violation of the exam policy.
Exam Instruction: Close books and notes. Exam time is
60 minutes. Please write your answers clearly in
designated areas. You are allowed to use calculators
and three pages of blank paper. PDA, laptops, and other
types of computers are not allowed.


There is a total of 20 multiple-choice problems. Please write out the correct choice below each problem number.
Each problem is worth for 5 points with a total of 100 points.

1. A visual depiction of the subassemblies and components that are needed to produce and/or assemble a
product is called a(n):
A) assembly time chart
B) product structure tree
C) MRP II
D) pegging
E) Gantt chart

Answer: B Page: 578 Difficulty: Medium
2. Which one of the following most closely describes net material requirements?
A) gross requirements - amount on-hand - scheduled receipts
B) gross requirements - planned receipts
C) gross requirements - order releases + amount on-hand
D) gross requirements - planned order releases
E) gross requirements - amount on-hand + planned order releases

Answer: A Page: 581 Difficulty: Medium
3. In MRP, "scheduled receipts" are:
A) identical to "planned-order receipts"
B) identical to "planned-order releases"
C) open orders (that is, ordered before the first time bucket, but not delivered yet)
D) "net requirements"
E) available to promise inventory

Answer: C Page: 582 Difficulty: Medium
4. In MRP, the gross requirements of a given component part are calculated from:
A) net requirements + amount on-hand.
B) gross requirements of the immediate parent
C) planned orders of the end item
D) net requirements of end item
E) planned orders of the immediate parent

Answer: E Page: 582 Difficulty: Medium
5. Which of the following lot sizing methods does not attempt to balance ordering (or setup) and holding costs?
A) economic order quantity
B) economic run size
C) lot-for-lot
D) part-period
E) all of the above

Answer: C Page: 590 Difficulty: Hard
6. The multiplication process used by MRP to determine lower level requirements is called:
A) time-phasing
B) pegging
C) netting
D) projecting
E) exploding

Answer: E Page: 581 Difficulty: Medium
7. Which statement concerning MRP II is false?
A) It is basically a computerized system.
B) It can handle complex planning and scheduling quickly.
C) It involves other functional areas in the production planning process.
D) It involves capacity planning.
E) It produces a production plan which includes all resources required.

Student ID:
(NoteBoth sides of the paper have exam problems.) 2 of 3

Answer: E Page: 591 Difficulty: Medium
8. A recent effort to expand the scope of production resource planning by involving other functional areas in
the planning process has been:
A) material requirements planning
B) capacity requirements planning
C) manufacturing resources planning
D) Just-In-Time planning
E) multifunctional relationships planning

Answer: C Page: 591 Difficulty: Easy
9. A report which shows expected capacity requirements for current, planned, and expected jobs is a:
A) master production schedule
B) bill of materials report
C) inventory status report
D) MRP schedule
E) load report

Answer: E Page: 593 Difficulty: Medium
10. Which is true of a net-change system?
A) It is a batch-type system which is updated periodically.
B) It is usually run at the beginning of each month.
C) The basic production plan is modified to reflect changes as they occur.
D) It is used to authorize the execution of planned orders.
E) It indicates the amount and timing of future changes.

Answer: C Page: 588 Difficulty: Hard
11. Which of the following is the last step in the capacity/scheduling chain?
A) product planning
B) process planning
C) capacity planning
D) aggregate planning
E) scheduling

Answer: E Page: 655 Difficulty: Easy
12. Primary considerations in scheduling high volume systems involve:

I. coordinating the flow of inputs
II. overcoming the disruptions to planned outputs
III. assigning workers to work centers

A) I and III
B) I and II
C) II and III
D) I, II, and III
E) II only

Answer: B Page: 656 Difficulty: Medium
13. Finite loading, as compared to infinite loading, assumes that:
A) There are a finite number of jobs to be done.
B) Work centers can be loaded without regard to their capacity.
C) Work centers' capacity must be taken into account.
D) Work centers' capacity may be taken into account, but it's not required.
E) Loading must be completed in a finite amount of time.

Answer: C Page: 660 Difficulty: Medium
14. Based on the cost information given in the table below, which set of job-machine pairs reflects the
minimum-cost solution using the Assignment method?

Machine
A B C
Job 1 $0 0 0
2 3 6 4
3 2 4 0

A) 1-B, 2-A, 3-C
B) 1-A, 2-B, 3-C
C) 1-C, 2-A, 3-B
D) 1-B, 2-C, 3-A
Student ID:
(NoteBoth sides of the paper have exam problems.) 3 of 3

E) 1-C, 2-B, 3-A

Answer: A Page: 663 Difficulty: Hard
15. The priority rule where jobs are processed according to the smallest ratio of due date to processing time is:
A) CR
B) EEDD
C) FCFS
D) S/O
E) SPT

Answer: A Page: 666 Difficulty: Medium
16. Which of the following is not a measure for judging the effectiveness of a schedule sequence?
A) average number of jobs at the work center
B) total number of jobs at the work center
C) average completion (flow) time
D) average job tardiness
E) none of the above

Answer: B Page: 667 Difficulty: Medium
17. Average completion (flow) time for a schedule sequence at a work center is:
A) total processing time divided by the number of jobs
B) total flow time divided by the number of jobs
C) total flow time divided by total processing time
D) total processing time plus total late time divided by number of jobs
E) total flow time plus total late time divided by number of jobs

Answer: B Page: 667 Difficulty: Medium
18. The scheduling sequencing rule which always results in the lowest average completion (flow) time is the:
A) first come, first served (FCFS) rule
B) shortest processing time first (SPT) rule
C) earliest due date first (EDD) rule
D) least slack per operation first (S/O) rule
E) run until slack happens (RUSH) rule

Answer: B Page: 670 Difficulty: Medium
19. For the jobs listed below, which processing sequence would result using Johnson's Rule?

Processing time (hrs.)
Job Center 1 Center 2
a 6 11
b 12 8
c 5 9
d 10 7

A) c-a-d-b
B) b-d-a-c
C) a-b-c-d
D) d-c-b-a
E) c-a-b-d

Answer: E Page: 672 Difficulty: Medium
20. Scheduling in service systems often takes the form of:
A) appointment systems
B) reservation systems
C) (A) and (B)
D) makespan systems
E) all of the above

Answer: C Page: 676 Difficulty: Easy