PACKAGE2:INSTALASICORIOLISDILINEXRAY

NO.

PEKERJAAN

Mulai

WAKTU
Selesai Durasi(menit)

PERALATAN

CONTINGENCY

HARIKE1
1

PEMOTONGANPIPAEXISTING10"DAN6"
1.1

SetelahJumperlinediaktifkan,Tutupblockvalve12"B2Rpadajalurpipayangi
akandidemolishdanmodifikasi.

07.00

07.10

10

Alatbantu

Apabilavalve12"passing,
makaakandipasangskillet

1.2

Tutupblockvalve10"B2R&6"B2Ryangmenujujalurpipa
PL0006A6"

07.10

07.20

10

Alatbantu

Apabilavalvepassing,
makaakandipasangskillet

1.3

Persiapkanlubanggaliandandrumpenampunguntukbuangsisafluidadi
sepanjangpipaPL0112B10"(diantarablockvalve12"/300#
dan10"B2R).Vacumfluidayangadadidrumpenampung

07.20

08.20

60

Vacumtruck

Tidakada

1.4

Persiapkandrumpenampunguntukmenampungtetesanfluidapadaspool
pipayangakandipotong

08.20

08.30

10

Potongandrumpenampung

Tidakada

1.5

Flushingjalurpipayangakandipotongdenganair.Potong
pipa10"dan6"(coolcuttingwork,4joint)denganjarak
sesuaidengangambarisometricAFC/actualspoolyangakandipasangdan
tampungtetesanfluidamenggunakandrumpenampung.
Gunakantripoddanchainblockuntukmenahankeduaujung
spool/pipayangakandipotongpadaTP038,TP037,TP39,
danTP40.

08.30

10.30

120

Gergaji,potongandrum
penampung,tripoddan
chainblock1T,airuntuk
flushing

Tidakada

1.6

Angkatdanpindahkanpotonganspool/pipabekaske
tempatyangsudahditentukanPT.PEP.Gunakantripoddan
chainblockuntukmembantuprosespemindahan

10.30

11.00

30

Tripod,chainblock1T,
alatbantudantruck

Tidakada

PEMASANGANSPOOLPIPA
2.1

Persiapkanspoolbaru8"dan6"besertagasket(SWG)dan
studbolt/nutdidekatareapenginstallan

11.00

11.30

30

Alatbantu

Tidakada

2.2

Persiapkanperlengkapanweldinghabitatuntukditempatkan
diareapadajointyangakandifieldweld

11.30

11.50

20

Alatbantudanweldinghabitat

Tidakada

2.3

Pasangweldinghabitat,pasangplug8"kemudianFWspool
no.spl001diTP038

11.50

13.50

60

mesinlas,weldinghabitat,
plug8",tripod,chainblock1T

Tidakada

2.4

Pasangweldinghabitat,pasangplug8"kemudianFWjoint
padaspoolno.spl007diTP037

13.50

14.50

60

mesinlas,weldinghabitat,
plug8",tripod,chainblock1T

Tidakada

2.5

Pasangweldinghabitat,pasangplug6"kemudianFWjoint
padaflange6"/300#diTP039

14.50

15.50

60

mesinlas,weldinghabitat,
plug8",tripod,chainblock1T

Tidakada

2.6

Pasangweldinghabitat,pasangplug6"kemudianFWjoint
padaflange6"/300#diTP040

15.50

16.50

60

mesinlas,weldinghabitat,
plug8",tripod,chainblock1T

Tidakada

2.7

Koneksikanspooldummyvalve8"B1R

16.50

17.00

10

Kunciring/pass,tripod,chain
block1T,palukuningan

Tidakada

2.8

Koneksikanspoolno.spl002

07.10

07.30

20

Kunciring/pass,tripod,chain
block1T,palukuningan

Tidakada

07.30

07.50

20

Kunciring/pass,tripod,chain

Tidakada

HARIKE2
2.9

Koneksikanspooldummystrainer

NO.

PEKERJAAN

Mulai

WAKTU
Selesai Durasi(menit)

PERALATAN

CONTINGENCY

block1T,palukuningan
2.10

Koneksikanspoolno.spl003

07.50

08.10

20

Kunciring/pass,tripod,chain
block1T,palukuningan

Tidakada

2.11

Koneksikancoriolis6"/150#

08.10

08.40

30

Kunciring/pass,tripod,chain
block1T,palukuningan

Tidakada

2.12

Koneksikanspoolno.spl004

08.40

09.00

20

Kunciring/pass,tripod,chain
block1T,palukuningan

Tidakada

2.13

Koneksikanspooldummyvalve8"B1R

09.00

09.20

20

Kunciring/pass,tripod,chain
block1T,palukuningan

Tidakada

2.14

Koneksikanspoolno.spl005

09.20

09.40

20

Kunciring/pass,tripod,chain
block1T,palukuningan

Tidakada

2.15

Koneksikanspoolno.spl006

09.40

10.00

20

Kunciring/pass,tripod,chain
block1T,palukuningan

Tidakada

2.16

Koneksikanspooldummyvalve6"B1R

10.00

10.20

20

Kunciring/pass,tripod,chain
block1T,palukuningan

Tidakada

2.17

Koneksikanspoolno.spl008

10.20

10.40

20

Kunciring/pass,tripod,chain
block1T,palukuningan

Tidakada

2.18

Koneksikanspooldummyvalve6"B1R

10.40

11.00

20

Kunciring/pass,tripod,chain
block1T,palukuningan

Tidakada

2.19

Koneksikanspooldummyvalve6"B1R

11.00

11.20

20

Kunciring/pass,tripod,chain
block1T,palukuningan

Tidakada

2.20

LakukanNDT(PT&RT)padagoldenjoint(4join)

11.20

15.20

240

Tidakada

2.21

CetakfilmdanreviewhasilNDT(RT)

15.20

07.00

900

Apabiladiperlukanrepair,
makasegeradilakukan
repairpadaesokpaginya

HARIKE3
3

PEMINDAHANJALURDARIJUMPERLINEKEPIPA10"
3.1

Jalurpipasiapdialirkanfluida.Periksa/Kencangkansemua
koneksi

08.20

08.30

10

Kunciring/pass,palu
kuningan

Tidakada

3.2

Bukablockvalve12"B2Rdan10"B2R

08.30

08.40

10

Alatbantu

Tidakada

3.3

Tutupvalve12"/300#dijalurnewbypass

08.40

08.50

10

Alatbantu

Tidakada

3.4

Bersihkanareakerjadarikotorandantools/alatbantu

08.50

09.20

30

Alatbantu

Tidakada

NOTE :

1. Manpoweryangdigunakansebanyak10orang
2. ReferensidrawingPIDDWG1007(03of11)
3. LokasipekerjaandiTerminalBalongan