Professional Documents
Culture Documents
Problem I
1. Input Measure - Percentage of Completion Method (Cost to Cost Method)
2008:
Contract price
P 1,800,000
Actual costs to date
P 450,000
Estimated costs to complete
1,200,000
Total estimated project costs
1,650,000
Estimated total gross profit
150,000
Percentage of completion:
P450,000 / P,1650,000
27.27%
Gross profit recognized
P 40,905
2009:
Contract price
P 1,800,000
Costs incurred:
2008
2009
P 450,00
1,100,000
Total cost
Total gross profit
Recognized in 2008
Recognized in 2009
2. Input Measure - Cost Recovery Method
2008: (all costs not yet recovered)
2009:
Contract price
Costs incurred:
Total cost
Total gross profit
1,550,000
250,000
40,905
P 209,095
P -01,800,00
2008
2009
P 450,000
1,100,000
1,550,000
P 250,000
Problem II
1. Input Measure - Percentage of Completion Method (Cost to cost Method)
Years
Gross Profit (or Loss)
Supporting computations
recognized
2008
P 2 million
(P108 90) x (P30/P90) = P6 million
2009
( P18 million)
Total loss is (P108 120) = (P12 million)
To date, P6 million was recorded:
therefore, (P12 million) P6 million =
(P18 million) in 2009
2010
P 10 million
Total loss is P 108 110) = (P2 million)
To date, (P 12 million was recorded:
therefore, ( P2 million) (P12 million)
= P10 million in 2010
2009
2010
(P 12 million)
P 10 million
Supporting computations
( P108 90) = P18 anticipated gross
profit, so no need to recognized a
gross loss
Total loss is ( P108 120) = (12 million)
Total loss is (P108- 110) ( P2 million)
To date, ( P12 million was recorded:
therefore, ( P2 million) ( P12 million)
= P10 million in 2010
Problem III
1. Journal Entries
a. Input Measure Percentage of completion (cost-to-cost method)
The following analysis is to determine the percentage of completion:
Contract price:
Initial amount of contract...
Variation..
Total contract price..
Costs incurred each year
Add: Costs incurred in prior years.
Actual costs incurred to date (1)..
Add: Estimated costs to complete..
Total estimated costs (3)..
Estimated gross profit
Percentage of completion (1) / (3)
20x3
20x4
20x5
P528,000
_______P528,000
P 126,048
_______P126,048
_358,752
P484,800
P 43,200
26%
P528,000
__12,000
P540,000
*P244,032
_126,048
*P370,080
_121,920
P492,000
P 48,000
**74%
P528,000
__12,000
P540,000
P121,920
_370,080
P492,000
_______P492,000
P 48,000
100%
The revenue, expenses (costs) and profit will be recognized in profit or loss as follows:
20x3
Revenue (P528,000 x 26%)
Costs/Expenses (P484,800 x 26%)
Gross Profit (P43,200 x 26%)
To date
P 137,280
126,048
P 11,232
Recognized in
prior years
-
Recognized in
current year
P 137,280
126,048
P 11,232
20x4
Revenue (P540,000 x 74%)
Costs/Expenses (P492,000 x 74%)
Gross Profit (P48,000 x 74%)
To date
P 399,600
_364,080
P 35,520
Recognized in
prior years
P 137,280
_126,048
P 11,232
Recognized in
current year
P 262,320
238,032
P 24,288
20x5
Revenue (P540,000 x 100%)
Costs/Expenses (P492,000 x 100%)
Gross Profit (P48,000 x 100%)
To date
P 540,000
_492,000
P 48,000
Recognized in
prior years
P 399,600
_364,080
P 35,520
Recognized in
current year
P 140,400
_127,920
P 12,480
Alternatively, the gross profit recognized each year may also be computed as follows:
20x3
Contract price:
20x4
20x5
P528,000
_______P528,000
P126,048
_______P126,048
_358,752
P484,800
P 43,200
____26%
P 11,232
_______P 11,232
P
0
P528,000
__12,000
P540,000
P240,032
_126,048
P370,080
_121,920
P492,000
P 48,000
____74%
P 35,520
___11,232
P 24,288
P
0
P528,000
12,000
P540,000
P121,920
_370,080
P492,000
_______P492,000
P 48,000
___100%
P 48,000
__35,520
P 12,480
P 48,000
126,048
232,032
6,000
126,048
144,000
3. To record collections:
Cash.....
Accounts receivable
120,000
20x4
127,920
6,000
121,920
244,032
240,000
144,000
156,000
240,000
228,000
120,000
126,048
11,232
20x5
156,000
192,000
228,000
238,032
24,288
137,280
192,000
127,920
12,480
262,320
140,400
540,000
540,000
P528,000
_______P528,000
P126,048
_______P126,048
____ _?
20x4
P528,000
__12,000
P540,000
P244,032
_126,048
P370,080
____ _?
20x5
P528,000
__12,000
P540,000
P121,920
_370,080
P492,000
_______-
P492,000
The revenue, expenses (costs) and profit will be recognized in profit or loss as follows:
20x3
Revenue*
Costs/Expenses
Gross Profit
* equivalent to costs incurred
To date
P 126,048
126,048
P
0
Recognized in
prior years
-
Recognized in
current year
P 126,048
126,048
P
0
20x4
Revenue*
Costs/Expenses
Gross Profit
* equivalent to costs incurred
To date
P 364,080
_364,080
P
0
Recognized in
prior years
P 126,048
126,048
P
0
Recognized in
current year
P 238,032
238,032
P
0
To date
Recognized in
prior years
Recognized in
current year
20x5
Revenue (P540,000 x 100%)
P 540,000
P 364,080
_492,000
P 48,000
P 175,200
364,080
127,920
P 48,000
Alternatively, the gross profit recognized each year may also be computed as follows:
20x3
Contract price:
Initial amount of contract.......
Variation
Total contract price
Costs incurred each year.
Add: Costs incurred in prior years..
Actual costs incurred to date ....
Add: Estimated costs to complete
Total estimated costs ....
Estimated gross profit.
Percentage of completion..
Gross profit to date.
Less: Gross profit in prior years.
Gross profit in current year...
P528,000
_______P528,000
P 126,048
_______P 126,048
____ _?
P
?
P
0
_ -___
P
0
_______P
0
20x4
20x5
P528,000
__12,000
P540,000
P244,032
_126,048
P370,080
____ _?
P
?
P
0
_ -___
P
0
_______P
0
P528,000
12,000
P540,000
P 121,920
_370,080
P492,000
_______P492,000
P 48,000
___100%
P 48,000
__
0
P 48,000
126,048
20x4
238,032
6,000
126,048
144,000
3. To record collections:
Cash.....
Accounts receivable
120,000
127,920
6,000
121,920
244,032
240,000
144,000
156,000
240,000
228,000
120,000
20x5
156,000
192,000
228,000
192,000
126,480
238,032
126,480
127,920
48,000
238,032
Current Liability:
Payables (Payments on Account)
Progress billings
Less: Construction In Progress.
Gross amount due to customers
Construction In Progress
20x3
P 24,000
175,920
540,000
540,000
20x4
P 36,000
20x5
P399,600
_384,000
P 15,600
P 6,000
P144,000
_137,280
P 6,720
Progress Billings
20x3 CI 126,048
Pr 11,232
144,000 20x3
end of x3 137,280
20x4 CI 238,032
Pr
11,232
144,000 end of x3
240,000 20x4
end of x4 399,600
20x5 CI 127,920
Pr
12,480
384,000 end of x4
156,000 20x5
540,000
540,000
540,000
540,000
20x3
P 24,000
20x4
P 36,000
P 6,000
20x5
Current Liability:
Payables (Payments on Account)
Progress billings
Less: Construction In Progress.
Gross amount due to customers
Construction In Progress
P 137,280
_144,000
P 6,720
P384,000
_364,080
P 19,920
Progress Billings
20x3 CI 126,048
Pr
0
144,000 20x3
end of x3 126,048
20x4 CI 238,032
Pr
0
144,000 end of x3
240,000 20x4
end of x4 364,080
20x5 CI 127,920
Pr
48,000
384,000 end of x4
156,000 20x5
540,000
540,000
540,000
540,000
3. Gross Profit
a. Input Measure - Percentage of Completion Method (refer to requirement 1 for detailed
computation)
Revenue
Less: Costs / Expenses...
Gross Profit.
20x3
P 137,280
_126,048
P 11,232
20x4
P 262,320
_238,032
P 24,288
20x5
P 140,400
_127,920
P 12,480
b. Input Measure Cost Recovery Method (refer to requirement 1 for detailed computation)
Revenue
Less: Costs / Expenses...
Gross Profit.
20x3
P 126,048
_126,048
P
0
20x4
P 238,032
_238,032
P
0
20x5
P 175,920
_127,920
P 48,000
Problem IV
1. Anticipated/Gross Loss
a. Input Measure Percentage of Completion (Cost-to-Cost Method)
2008:
Contract price
Actual cost to date
Estimated costs to complete
Total estimated project costs
Estimated loss, recognized in 2008
P2,500,000
P1,500,000
1,200,000
2,700,000
P (200,000)
2009:
Contract price
Costs incurred:
P 2,500,000
In 2008
In 2008
P1,500,000
1,300,000
Total cost
Total loss
Recognized in 2008
Recognized in 2009
2,800,000
P (300,000)
(200,000)
P (100,000)
P( 200,000)
P (100,000)
2. Journal Entries
a. Input Measure Percentage of Completion (Cost-to-Cost Method)
2008:
Construction in progress
Various credits
1,500,000
1,500,000
Accounts receivable
Billings on construction contract
1,200,000
Cash
Accounts receivable
1,000,000
Cost of construction
Construction in progress (loss)
Revenue from long-term contracts*
2009:
Construction in progress
Various credits
1,588,889
Accounts receivable
Billings on construction contract
1,300,000
Cash
Accounts receivable
1,500,000
Cost of construction
Construction in progress (loss)
Revenue from long-term contracts**
1,211,111
2,500,000
*P2,500,000
** P2,500,000
Problem V
(P1,500,000/P2,700,000)
1,388,889
1,200,000
1,000,000
200,000
1,388,889
1,300,000
1,300,000
1,300,000
1,500,000
100,000
1,111,111
2,500,000
Item to compute
Total revenue recognized during 2009 (w):
CIP contains cost + gross profit = revenue, so w = P50
Gross profit recognized during 2009 (x): P50 P35 = P15
Billings on construction (y) : P14 + P 46 = P60
Net billings in excess of construction in progress (z): Billings of P60 CIP of
P50
Calculate the percentage of PAC that was completed during 2009:
50/150 = 33.33%
Problem VI
Item to compute
Cash collected by KP on Cincy One during 2009. (P75 billings P10 A/R)
Actual costs incurred by KP on Cincy One during 2009 (P66 CIP P22
gross pofit)
At 12/31/2009, the estimated remaining costs to complete Cincy One
(44/{44 + x})(300 {44 + x}) = 22; x = 156
The percentage of Cincy One that wa completed during 2009 100 x (44/
{44 + 156})
Problem VII
1.
Progress billings on construction contract
Less accounts receivable
Cash collected in 20x4
Answer
P50 million
P 15 million
P60million
P10 million
333.33%
Answer
P65 million
P44 million
P156 million
22%
P562,000
150,500
P411,500
2.
Gross profit from construction contract + Construction in progress = Revenue for 20x4
P301,000 + P602,000 = P903,000
P903,000/P7,525,000 = 12% Percentage completed in 20x4
P301,000/.12 = P2,508,333 Estimated income on construction contract
Problem VIII
1. Percentage of Completion Method (Cost-to-cost Approach)
20x4
Contract price ...................
P250,000
Current year costs ...............
110,000
Costs to date ....................
110,000
Estimated cost to complete .......
100,000
Estimated total cost .............
210,000
Estimated total gross profit .....
40,000
Percent complete .................
52%
Revenue to date ..................
P130,000
20x4:
Revenue
Costs (110/210 x 210)
Gross profit
20x5:
Revenue
20x5
P250,000
120,000
230,000
20,000
245,000
5,000
94%
P230,000
20x6
P250,000
15,000
245,000
0
240,000
5,000
100%
P250,000
To Date
at Dec. 31
P130,000
110,000
P 20,000
Previous
Years
Current
Year
P130,000
110,000
P 20,000
P235,000
P130,000
P105,000
20x6:
230,000
5,000
110,000
P 20,000
120,000
P(15,000)
Revenue
Costs
Gross profit
P250,000
245,000
P 5,000
P235,000
230,000
P 5,000
P 15,000
15,000
P
0
20x4
1.
2.
3.
4.
5.
20x5
20x6
P130,000
P100,000
P15,000
20,000
(15,000)
130,000
235,000
125,000
5,000
250,000
(15,000)
0
0
20x5
20x6
P110,000
P120,000
P20,000
5,000
110,000
230,000
125,000
(15,000)
250,000
(20,000)
0
0
Problem IX
1. Percentage of Completion Method (Cost-to-cost Approach)
Contract price
Current year costs
Costs to date
Estimated cost to complete
Estimated total cost
Estimated total gross profit
Percent complete
2005
P250,000
150,000
150,000
90,000
240,000
10,000
63%
2006
P250,000
100,000
250,000
20,000
270,000
(20,000)
93%
2007
P250,000
15,000
265,000
0
265,000
(15,000)
100%
Revenue to date
P157,500
P232,500
P250,000
2005:
Revenue ............
Costs (150/240 x 240)
Gross profit ............
2006:
Revenue ............
Costs ............
To Date
at Dec. 31
P157,500
150,000
P 7,500
Previous
Years
Current
Year
P157,500
150,000
P 7,500
P232,500
252,500
P157,500
150,000
P 75,000
102,500
2007:
P(20,000)
P 7,500
P(27,500)
Revenue ............
Costs ............
Gross profit (loss) ............
P250,000
265,000
P(15,000)
P232,500
252,500
$(20,000)
P 17,500
12,500
P 5,000
20x4
20x5
20x6
P150,000
P102,500
P12,500
7,500
(27,500)
5,000
157,500
230,000*
110,000
47,500
230,000
0
0
0
10,000
10,000
*P150,000 + 7,500 + 157,500 + 100,000 costs incurred during the year 27,500 loss
2. Cost Recovery Method
20x4
1. Construction costs (expense)
recognized during the year
2. Gross profit recognized during
the year
3. Balance in the construction in
progress account at Dec. 31
(after closing entries)
4. Balance in the progress
billings account at Dec. 31 .
5. NNet (3-4) or (4-3) due from (due to)
P150,000
0
20x5
20x6
P 80,000*
P20,000**
(20,000)
5,000
150,000
***230,000
110,000
40,000
230,000
0
0
0
P
P
6M
0
6M
P 18 M
6 M / 18M
5. b
6.
7.
CI in 2004
RGP in 20x4 (?)
End of 20x4
CI in 20x5
RGP in 20x5 (?)
Construction-In-Progress
210,000
34,000
244,000
384,000
100,000
End of 20x5
728,000
P1,200,000
x (P7,200,000 P4,800,000) = P600,000.
P4,800,000
P7,200,000 P4,875,000 =P2,325,000.
Contract Price
x: Percentage-of-completion
Recognized Revenue to date
Less: Costs incurred to date
Gross Profit to date
Less: GP in prior year
Gross profit in current year
8.
9.
P3,600,000
x (P8,400,000 P6,000,000) = P1,440,000.
P6,000,000
P8,400,000 P5,600,000 = P2,800,000.
20x4
P4,800,000
_______75%
P3,600,000
P3,400,000
P 200,000
_______-0P 200,000
Items 10 and 11
No number requirement identified, if percentage-of-completion then the answer would (a)
a
[P1,950,000 (P1,950,000 + P1,300,000)] P2,250,000 = P1,350,000
(P5,500,000 P3,350,000) P1,350,000 = P800,000.
10. Cost Recovery Method - c - P5,500,000 P3,350,000 = P2,150,000.
11. a - Gross profit is recognized in the year of sale, 20x4; therefore, in 20x6 no gross profit should
be realized.
12. c
P600,000
x (P1,500,000 P1,000,000) = P300,000
P600,000 + P400,000
(P1,500,000 P1,050,000) P300,000 = P150,000.
13. a
Contract Price
Less: Total Estimated Costs
Costs Incurred-1/10/x4 to 12/31/x5
Add: Estimated costs to complete
Less: Costs incurred to date
Multiplied by: % of completion
Gross Profit to date
Less: GP in prior year (given)
Gross profit in current year
P6,000,000
P3,600,000
1,200,000
4,800,000
P1,200,000
___3.6/4.8
P 900,000
___600,000
P 300,000
14. b
20x4: Cost to date P7,500,000 x 20%
20x5: Cost to date P8,000,000 x 60%
Cost incurred during 20x5
P1,500,000
4,800,000
P3,300,000
50,000
P260,000
P 50,000
-0P 50,000
150,000
P200,000
P60,000)
__50/200
15,000
65,000
30,000
35,000
17. d - P2,040,000 P980,000 = P1,060,000 (revenue limited to costs incurred since cost-recovery
method must be used).
18. a - P2,040,000 (P1,000,000 + P1,000,000) = P40,000.
19. c - (P1,000,000 + P1,000,000) (P648,000 + P1,280,000) = P72,000.
20. d
21. d
Recognized gross profit (loss) to date..
Less: Recognized gross profit in prior years.
Recognized gross profit each year..
P( 100,000)
____20,000
P (120,000)
Prior year
P7,000,000
P600,000
Current year
P7,000,000
P5,000,000
2,800,000
P7,800,000
(P 800,000)
_____100%
(P 800,000)
___600,000
(P1,400,000)
24. c
25. d
26. b
27. c
28. b
29. c
30. d
31. b
32. d
33. c
34. a
39. c
40. a
Under PFRS, the excess of Construction In Progress amounting to P2,100,000 (P2,250,000
P150,000, loss) P1,900,000, billings = P200,000 is classified as due from customers.
Under the US FASB, the excess of P200,00 is considered as an inventory account.
41. c
Costs of construction
Construction in progress
Revenue for long-term contracts
1,200,000
800,000
2,000,000
P1,200,000
800,000
P2,000,000
1,500,000
P 500,000
43. b
Costs of construction
Construction in progress
Revenue for long-term contracts
600,000
400,000
1,000,000
1,200,000
1,2000,000
Under cost recovery method, revenue should be recognized up to the extent of costs
incurred.
45. b
Costs of construction
Profit
Construction In Progress
Less: Progress billings
Excess (Due to customers)
P1,200,000
0
P1,200,000
1,500,000
P( 300,000)
46. d
Costs of construction
Construction in progress
Revenue for long-term contracts
600,000
1,200,000
1,800,000
Under the cost recovery method, record equal amounts of revenue and cost until cost
recovered, and then record gross profit. In 20x4, recorded revenue and cost of P1,200,000,
so record remaining cost of P600,000 and all gross profit of P1,200,000 in 20x5.
47. a
Contract price
Costs incurred to date
Add: Estimated cost to complete
Total estimated costs
Estimated Gross Profit (loss)
Multiply by: % of completion
Recognized Gross Profit (Loss) to date
Less: Gross Profit (Loss) in prior year
Recognized Gross Profit (Loss) in current year
% of Completion / Cost Recovery Method:
Construction in Progress
CI
CI
4,920,000
4,680,000
3,720,000
7,920,000
20x4
P 9,600,000
P 4,920,000
4,920,000
P 9,840,000
P(240,000)
100%
P (240,000)
_________
P (240,000)
20x5
P10,080,000
P 8,640,000
2,160,000
P 10,800,000
P (720,000)
100%
P (720,000)
(240,000)
P (480,000)
Progress Billings
240,000 loss
5,280,000
5,280,000
3,420,000
480,000 loss
due to customers
P780,000
8,700,000
Note: If there is an anticipated loss, the Construction-in-Progress for both methods will
exactly be the same in the year the loss was incurred.
48. d
Percentage of Completion:
Contract price..
Cost incurred each year.
Add: Cost incurred in prior year
Costs incurred to date
Add: Estimated costs to compute.
Total estimated costs.
Project 6
P500,000
P375,000
_________
P375,000
________
P375,000
Project 7
P700,000
P100,000
________
P100,000
400,000
P500,000
Project 8
P250,000
P100,000
________
P100,000
100,000
P200,000
P125,000
100%
P125,000
_________
P125,000
P200,000
20%
P 40,000
_________
P 40,000
P 50,000
50%
P 25,000
_________
P 25,000
Project 6
P500,000*
Project 7
P100,000
Project 8
P100,000
375,000
P125,000
100,000
P
0
100,000
P
0
Recognized Revenue....
Less: Costs of long-term construction
contract..
Recognized gross profit each year.
* Since the contract is completed then the full amount of P500,000 contract price should be
recognized as revenue.
Percentage of Completion
Construction in Progress
Pr. 6 - Cl.
375,000 500,000 Pr. 6
Pr. 125,000
Pr. 7 Cl. 100,000
Pr.
40,000
Pr. 8. Cl
100,000
Pr. 100,000
765,000 500,000
12/31
265,000 (d)
49. a
Input Measures: Efforts-Expended Method - using timbers laid
Year 2
Timers laid Each Year
300
Add: Timbers laid in Prior Years
150
Timbers laid to date
450
Add: Additional support timbers to be laid
520
Total Estimated Timbers
970
Percentage-of-Completion
45/97
x: CONTRACT PRICE
P 800,000
Recognized Revenue to Date
P 371,134
Recognized Revenue in Prior Years
Recognized Revenue in Current Yr.
Year 3
500
450
950
-0950
100%
P 800,000
P 800,000
371,134
P 428,866
Year 2
7,500
3,000
10,500
8,200
18,700
105/187
P 800,000
P 449,198
Year 3
8,000
10,500
18,500
___-018,500
100%
P 800,000
P 800,000
449,198
P 350,802
50. b
Contract price..
Cost incurred each year.
Add: Cost incurred in prior year
Costs incurred to date
Add: Estimated costs to complete
Total estimated costs.
Estimated gross profit
Multiply by: percentage of completion.
Recognized gross profit to date
Less: Recognized gross profit in prior years
Recognized gross profit each year.
2006
P5,000,000
P 900,000
P 100,000
-0P 100,000
2007
P5,000,000
900,000
P2,550,000
1,700,000
P4,250,000
P 750,000
60%
P 450,000
100,000
P 350,000
2008
P5,000,000
P2,050,000
2,550,000
P4,600,000
-0P4,600,000
P 400,000
100%
P 400,000
450,000
P( 50,000)
P60,000,000
51,000,000
P 9,000,000
30%
P 2,700,000
_________0
P 2,700,000
P 26,000,000
2,700,000
P 28,700,000
5,000,000
P 23,700,000
53. c
Contract Price
Multiplied by: Gross Profit Rate
Estimated Gross Profit of the entire contract
Multiplied by: Percentage of Completion for first year
Gross Profit realized for current year
P100,000,000
_________25%
P 25,000,000
_________50%
P 12,500,000
Contract Price
x: Mobilization Fee
Collection in 20x4
Note: Billings for 20x4 will be collected in January 20x5.
P120,000,000
10%
P 12,000,000
54. c
55. a
Mobilization Fee: 5% x P10M
P 5.0 M
Collection on Billings:
Contract price
x: Progress billings, net of 10% and 8% (50% - 10% - 8%)
Progress billings
x: Collections net of contract retention of 10%
Collections in 20x4
P 100 M
32%
P 32 M
90%
28.8 M
P 33.8 M
4,500,000
1,350,000
_2,700,000
4,050,000
450,000
1,350/4,050
150,000
____-0150,000
3. P150,000
Contract price
Costs incurred to date
Add: Estimated cost to complete
Total estimated costs
Estimated Gross Profit (loss)
Multiplied by: % of completion
Recognized Gross Profit (Loss) to date
Less: Gross Profit (Loss) in prior year
Recognized Gross Profit (Loss) in current year
20x5
3,000,000
2,250,000
750,000
300,000
20x6
3,000,000
1,800,000
_600,000
2,400,000
600,000
1,800/2,400
450,000
_300,000
150,000
4. P80,000
Contract price
Costs incurred to date
Add: Estimated cost to complete
Total estimated costs
Estimated Gross Profit (loss)
Multiplied by: % of completion
Recognized Gross Profit (Loss) to date
Less: Gross Profit (Loss) in prior year
Recognized Gross Profit (Loss) in current year
20x5
1,600,000
240,000
_960,000
1,200,000
400,000
240/1,200
80,000
______0
80,000
5. P20,000
Contract price
Costs incurred each year
Add: Cost incurred in prior years
Costs incurred to date
Add: Estimated cost to complete
Total estimated costs
Estimated Gross Profit (loss)
Multiplied by: % of completion
Recognized Gross Profit (Loss) to date
Less: Gross Profit (Loss) in prior year
Recognized Gross Profit (Loss) in current year
20x5
1,400,000
400,000
_____-0400,000
_400,000
800,000
600,000
400/800
300,000
______0
300,000
20x6
1,400,000
400,000
400,000
800,000
200,000
1,000,000
400,000
800/1,000
320,000
300.000
20,000
6. P-0- , Under the cost recovery method, record equal amounts of revenue and cost until cost
recovered, and then record gross profit
7.P240,000 Profit
Contract price
Costs incurred each year
Add: Cost incurred in prior years
Costs incurred to date
Add: Estimated cost to complete
Total estimated costs
Estimated Gross Profit (loss)
Multiplied by: % of completion
Recognized Gross Profit (Loss) to date
Less: Gross Profit (Loss) in prior year
Recognized Gross Profit (Loss) in current year
20x5
4,000,000
960,000
_______0
960,000
3,200,000
800,000
960/3,200
240,000
_______0
240,000
8. P102,000
Contract price
Costs incurred each year
Add: Cost incurred in prior years
Costs incurred to date
Add: Estimated cost to complete
Total estimated costs
Estimated Gross Profit (loss)
Multiplied by: % of completion
Recognized Gross Profit (Loss) to date
Less: Gross Profit (Loss) in prior year
Recognized Gross Profit (Loss) in current year
20x5
850,000
238,000
_______0
238,000
357,000
595,000
255,000
238/595
102,000
_______0
102,000
9. P990,000
Contract price
Costs incurred each year
Add: Cost incurred in prior years
Costs incurred to date*
Add: Estimated cost to complete
Total estimated costs
Estimated Gross Profit (loss)
Multiplied by: % of completion
Recognized Gross Profit (Loss) to date
Less: Gross Profit (Loss) in prior year
Recognized Gross Profit (Loss) in current year
20x5
3,000,000
450,000
20x6
3,000,000
990,000
450,000
1,440,000
2,250,000
750,000
____20%
150,000
______0
150,000
2,400,000
600,000
_____60%
360,000
150.000
210,000
10. P50,000
20x5
1,500,000
465,000
_______0
465,000
1,085,000
1,550,000
( 50,000)
100%
( 50,000)
_______0
( 50,000)
Contract price
Costs incurred each year
Add: Cost incurred in prior years
Costs incurred to date
Add: Estimated cost to complete
Total estimated costs
Estimated Gross Profit (loss)
Multiplied by: % of completion
Recognized Gross Profit (Loss) to date
Less: Gross Profit (Loss) in prior year
Recognized Gross Profit (Loss) in current year
11. P625,000
Contract price
Costs incurred each year
Add: Cost incurred in prior years
Costs incurred to date
Add: Estimated cost to complete
Total estimated costs
Estimated Gross Profit (loss)
Multiplied by: % of completion
Recognized Gross Profit (Loss) to date
Less: Gross Profit (Loss) in prior year
Recognized Gross Profit (Loss) in current year
20x5
3,500,000
1,350,000
-01,350,000
1,350,000
2,700,000
800,000
-0-0-
20x6
3,500,000
1,525,000
1,350,000
2,875,000
_______0
2,875,000
625,000
___100%
625,000
_______0
625,000
12. P550
Costs Incurred.
Contract price.
Cost incurred each year..
Add: Cost incurred in prior year.
Costs incurred to date..
Add: Estimated costs to complete
Total estimated costs.
Estimated gross profit (loss)..
Multiplied by: percentage of completion..
Construction In Progress account inventory account
400
P2,750
P 400
___-0P 400
_1,600
P2,000
P 750
400/2,000
150
550
13. P1,200,000
The term completed should be cost recovery
Costs Incurred
Contract price.
Cost incurred each year..
Add: Cost incurred in prior year.
Costs incurred to date..
Add: Estimated costs to complete
Total estimated costs.
Estimated gross profit (loss)..
Multiplied by: percentage of completion..
Construction In Progress account inventory account
700,000
P2,000,000
P 700,000
______-0P 700,000
__800,000
P1,500,000
P 500,000
________0
_______0
700,000
20x5
Costs incurred
Contract price.
Cost incurred each year..
Add: Cost incurred in prior year.
Costs incurred to date..
Add: Estimated costs to complete
Total estimated costs.
Estimated gross profit (loss)..
Multiplied by: percentage of completion..
Construction In Progress account inventory account
600,000
P2,000,000
P 600,000
_700,000
P1,300,000)
__800,000
P(2,100,000)
P (100,000)
________0
_(100,000)
1,200,000
15. P782,000
20x5
Costs Incurred
Contract price.
Cost incurred each year..
Add: Cost incurred in prior year.
Costs incurred to date..
Add: Estimated costs to complete
Total estimated costs.
Estimated gross profit (loss)..
Multiplied by: percentage of completion..
Construction In Progress account inventory account
238,000
P850,000
P238,000
______-0P238,000
_357,000
P595,000
P255,000
_238/595
102,000
340,000
20x6
Costs incurred
Contract price.
Cost incurred each year..
Add: Cost incurred in prior year.
Costs incurred to date..
Add: Estimated costs to complete
Total estimated costs.
Estimated gross profit (loss)..
Multiplied by: percentage of completion..
Construction In Progress account inventory account
Less: Progress billings (P260,000 + P210,000)
Construction In Progress account (net) Due from
customers
319,600
P850,000
P319,600
_238,000
P557,600
_139,400
P697,000
P153,000
_557.6/697
_122,400
782,000
470,000
312,000
16. P312,000
17. same with no.16 P312,000
18. (P9,000,000 P8,250,000) (P3,795,000 P8,250,000) = P345,000.
19.P3,795,000 + P345,000 = P4,140,000.
20. P2,750,000
P1,650,000
P5,000,000 = P2,750,000
P3,000,000
21.
22.
1,650,000
1,650,000
1,100,000
23. P875,000
Revenue
Costs
Total gross profit
Recognized in 20x5
Recognized in 20x6
Or
Total revenue
Recognized in 20x5
P5,000,000
3,025,000
1,975,000
(1,100,000)
P 875,000
P5,000,000
(2,750,000)
1,650,000
2,750,000
Recognized in 20x6
Costs in 20x6
Gross profit in 20x6
24.
25.
26.
20x5
20x6
20x7
2,250,000
(1,375,000)
P 875,000
Percentage-of-Completion
Gross Profit
P750,000a
P210,000b
P440,000c
20x5
20x6
20x7
Completed-Contract
Gross Profit
P1,400,000d
aP1,500,000
P2,000,000 =
P4,000,000
P750,000
bP2,640,000
P1,600,000 =
P4,400,000
P960,000
(750,000)
P210,000
cTotal
revenue
Total costs
Total gross profit
Recognized to date
20x7 gross profit
dTotal
revenue
Total costs
Total gross profit
P6,000,000
4,600,000
1,400,000
(960,000)
P 440,000
P6,000,000
4,600,000
P1,400,000
27. P312,500
Revenue
= [P250,000/(P250,000 + P750,000)]
P1,250,000
= P312,500
Gross profit = P312,500 P250,000 = P62,500
Construction in progress = P250,000 + P62,500 = P312,500
28. P125,000
(2)
Current Assets
Inventories
Construction in progress*
P1,000,000
Less: Partial billings**
(875,000)
Costs and recognized profit not
P 125,000
yet billed
*Revenue to date = (P250,000 +
P600,000)/(P250,000 + P600,000 +
P212,500) 1,250,000 = P1,000,000
Construction in progress = P250,000 +
P600,000 + P150,000 = P1,000,000
**Partial billings = P375,000 + P500,000 =
P875,000
29. P60,00
Revenue to date
Revenue from previous periods
Revenue for 20x7
Costs incurred in 20x7
Gross profit for 20x7
P1,250,000
_1,000,000
P 250,000
_ 190,000
P 60,000
THEORIES
1.
2.
3.
4.
5.
36.
False
True
True
False
False
6.
7.
8.
9.
10,
False
False
False
True
False
11.
12.
13.
14.
15,
False
True
False
True
False
16.
17.
18.
19.
20.
True
False
True
False
True
21.
22.
23.
24.
25.
True
False
False
False
False
26.
27.
28.
29.
30.
True
True
False
False
True
31.
32.
33.
34.
35.
37.
38.
39.
40.
False
True
True
False
False
41.
46.
51.
56.
61.
66.
42.
43.
44.
45.
47.
48.
49.
50.
52.
53.
54.
55.
b
c
b
57.
58.
59.
60.
62.
63.
64.
65.
b
a
c
d
67.
68.
69.
70.
b
c
b
c
a
c
c
d
C
False
False
True
False
True