You are on page 1of 3

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)

SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


PRESSURE VESSEL INSTALLATION

SATIP-D-001-01
WBS/BI/JO/NO.

PROJECT TITLE:

ITEM
NO.

1.0

PROJECT PHASE &


Activity Code

APPROVED DATE

TASK / ACTIVITY

QUALITY
PROCEDURE

QUALITY
RECORD

DISCIPLINE:

25-May-05

MECHANICAL

CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

SAUDI
ARAMCO

RH1

RH1

REMARKS

DOCUMENT REVIEW
Review of Safety Instruction Sheet (S.I.S)

SAIC-D-2001

2.1

Verification of NMRs for Vessels and


Trays

SAIC-D-2022

2.2

Visual Inspection
a) External Inspection
b) Internal Inspection

SAIC-D-2002
SAIC-D-2003

SAIC-D-2002
SAIC-D-2003

H1

H1

2.3

Ladders, platforms, and other structural


steel attachments

SAIC-D-2004

SAIC-D-2004

W1

2.4

Storage, Handling and Preservation

SAIC-D-2005

SAIC-D-2005

H1

W1

2.5

Verification and visual inspection of


Vendor Supplied electrical and
instrumentation materials

Refer to the respective SATIPs for Electrical &


Instrumentation: ( SATIP-P-113-01, P-121-01 or P-104-02,
P-515-01, J-100-01, J-200-01, J-300-01, J-400-01, J-90203)

3.1

Concrete placement

Refer to SATIP-Q-001-02

3.2

Pre-Installation inspection

SAIC-D-2006

SAIC-D-2006

H1

W1

3.3

Equipment Installation - Alignment &


Elevation Survey (Vertical Vessel &
Horizontal Vessel)

SAIC-D-2007

SAIC-D-2007
SATR-D-2001
SATR-D-2002

H1

W1

3.4

Grouting Inspection

Refer to SATIP-Q-010-01

3.5

Inspection of Ladder, platform and other


structural attachment installations.

Refer to SATIP-M-001-01

1.1
2.0

3.0

MATERIAL RECEIVING

INSTALLATION

Page 1 of 3

SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


PRESSURE VESSEL INSTALLATION

SATIP-D-001-01

PROJECT TITLE:

ITEM
NO.

APPROVED DATE

WBS/BI/JO/NO.

PROJECT PHASE &


Activity Code

TASK / ACTIVITY

QUALITY
PROCEDURE

QUALITY
RECORD

DISCIPLINE:

25-May-05

MECHANICAL

CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

SAUDI
ARAMCO

REMARKS

3.6

Inspection of Vessel Trim Installation

SAIC-D-2008

SAIC-D-2008

W1

3.7

Tray Installation

SAIC-D-2009

SAIC-D-2009

H1

W1

3.8

Tray Testing

SATR-D-2004

SATR-D-2004

H1

H1

3.9

Flange Joint- Gasket Verification & Bolt


tightening

SAIC-L-2014

SAIC-L-2014
SATR-L-2001

H1

W2

3.10

Piping inspection

Refer to SATIP-L-350-01

3.11

Steam Tracing

Refer to SATIP-L-350-06

3.12

Internal CP (galvanic) for internally coated


vessels

Refer to SATIP-X series

3.13

Lighting Installation

Refer to SATIP-P-123-02

3.14

Relief Valve Installation

Refer to SATIP-J-600-01

3.15

Grounding Installation

Refer to SATIP-P-111-01

3.16

Electrical & Instrumentation installation

Refer to the respective SATIPs for Electrical &


Instrumentation: ( SATIP-P-113-01, P-121-01 or P-121-02,
P-515-01, J-100-01, J-200-01, J-300-01, J-400-01, , J-90203)

3.17

Painting, Vessel Identification & color


Coding

Refer to SATIP-H-100-01

3.18

Insulation

Refer to SATIP-N-001-01 or SATIP-N-001-02

Page 2 of 3

See Note 1 of the General Notes , at least 10% minimum


thereafter.

SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


PRESSURE VESSEL INSTALLATION

SATIP-D-001-01

PROJECT TITLE:

ITEM
NO.

WBS/BI/JO/NO.

PROJECT PHASE &


Activity Code

QUALITY
PROCEDURE

TASK / ACTIVITY

QUALITY
RECORD

DISCIPLINE:

25-May-05

MECHANICAL

CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

REMARKS

SAUDI
ARAMCO

Fireproofing

3.19
4.0

APPROVED DATE

Refer to SATIP-B-006-01 or SATIP-B-006-02

PRE-COMMISSIONING

4.1

Vessel Closure Inspection

SATR-D-2003

4.2

Instrumentation and Electrical precommissioning

Refer to the respective SATIPs for Electrical &


Instrumentation

4.3

Tightness Test

Refer to SATIP-A-004-05

4.4

Final Inspection/Punch listing for ReInstatement (by Contractor)

4.5

Mechanical Completion Punch listing


(Final MCC or Partial MCC)

SAIC-D-2012

SATR-D-2003

SAIC-D-2012
SATR-A-2011
FEIL SA-6133

H1

H1

H1

H1

GENERAL NOTES
1

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
of Saudi Aramco participation based upon the Contractors performance.

Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.

Witness:
QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
representative is not present.

Hold:

If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

organization

QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.

LEGEND
W1

100% Witness Inspection/Test

H2

Sample Hold Point for QC Inspection or Test

RH1 100% Review and Approval of Documents

W2

Sample Witness Inspection/Test

R1

100% Review of Documents

RH2 Sample Review and Approval of Documents

H1

100% Hold Point for QC Inspection or Test

R2

Sample Review of Documents

Page 3 of 3

Surveillance

You might also like