You are on page 1of 12

RESUMEN VALORIZACIN DEL AVANCE FSICO DE OBRA

PROYECTO : URBANIZACIN E INFRAESTRUCTURA


OBRA

PERODO VALORIZADO

: MAYO DE 2007

UBICACIN : CIUDAD UNIVERSITARIA

: CONST. E IMPLE. DEL PAB. DE AULAS, SS.HH MOD. Y ADM. DE LA FAC. DE CIENCIAS DE LA EDUCACION

PRESUPUESTO DE

: MATERIALES, MANO DE OBRA Y E

AREA

: GENERAL

FECHA DE ENTREGA

SUBPROY

: MODULO "B" PABELLON AULAS

A
ID
RT
A
P

1
2
3

D E S C R I P C I N

ESCALERA AL PUENTE CRUCE


PUENTE CRUCE ENTRE PAB. DE AULAS
RAMPA Y PUENTE CRUCE A ADM

COSTO DIRECTO

AD
ID
UN

METRADO

PRESUPUESTO BASE
P.UNITARIO

P.PARCIAL

AVANCE ACUMULADO
ANTERIOR
METRADO

IMPORTE

AVANCE ACTUAL
DEL MES
%

METRADO

IMPORTE

AVANCE ACUMULADO
TOTAL
%

METRADO

IMPORTE

34,781.84
291,837.45
20,369.91

104,053.46
13,299.06
5,576.89

299.16%
4.56%
27.38%

104,053.46
5,425.23
653.54

299.16%
1.86%
3.21%

208,106.920
18,724.293
6,230.43

598.32%
6.42%
30.59%

346,989.20

122,929.41

35.43%

110,132.23

31.74%

233,061.64

67.17%

MANO DE OBRA Y EQUIPOS

SALDO POR VALORIZAR


METRADO

IMPORTE

-173,325.07
273,113.13
14,139.49

-498.321%
93.584%
69.414%

113,927.54

32.83%

VALORIZACIN DEL AVANCE FSICO DE OBRA


PROYECTO
OBRA

: URBANIZACIN E INFRAESTRUCTURA
: ESCALERA, RAMPA Y PUENTE

PERODO VALORIZADO

: MAYO DE 2007

UBICACIN
AREA

: CIUDAD UNIVERSITARIA
: GENERAL

PRESUPUESTO DE
FECHA DE ENTREGA

: MATERIALES, MANO DE OBRA


:

SUBPROYECTO

: ESCALERA AL PUENTE CRUCE

A
ID
RT
PA

AD
ID
UN METRADO

D E S C R I P C I N

01.00

TRABAJOS PRELIMINARES

01.01

LIMPIEZA DE TERRENO MANUAL

M2

23.04

01.02

TRAZO Y REPLANTEO

M2

23.04

02.00

MOVIMIENTO DE TIERRAS

02.01

CORTE SUPERFICIAL MANUAL HASTA 0.10 MT

M2

13.82

02.03

EXCAVACIONES

AVANCE ACUMULADO
ANTERIOR

PRESUPUESTO BASE
P.UNITARIO

AVANCE ACTUAL
DEL MES

AVANCE ACUMULADO
TOTAL

P.PARCIAL

METRADO

IMPORTE

METRADO

IMPORTE

METRADO

IMPORTE

2.15

49.54

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

5.48

126.26

1.00

5.48

4.34%

1.00

5.48

4.34%

2.00

10.96

1.71

23.63

4.00

6.84

28.94%

4.00

6.84

28.94%

8.00

13.68

0.00

EXCAVACION MANUAL EN ZAPATAS TERRENO CALICHE

M3

69.00

54.52

3,761.88

6.00

327.12

8.70%

6.00

327.12

8.70%

12.00

654.24

02.05

ACARREO DE MATERIAL EXCEDENTE HASTA UNA DISTANCIA PROMEDIO P

M3

82.80

14.54

1,203.91

7.00

101.78

8.45%

7.00

101.78

8.45%

14.00

203.56

02.06

REFINE, NIVELACION Y COMPACTACION CON EQUIPO LIVIANO

M2

23.04

5.54

127.64

8.00

44.32

34.72%

8.00

44.32

34.72%

16.00

88.64

03.00

CONCRETO SIMPLE

03.02

SOLADO PARA ZAPATAS DE 3" MEZCLA 1:12 CEMENTO-HORMIGON

M2

4.85

29.52

143.17

12.00

354.24

247.42%

12.00

354.24

247.42%

24.00

708.48

04.00

CONCRETO ARMADO

04.01

ZAPATAS
327.57

949.95

17.00

5,568.69

586.21%

17.00

5,568.69

586.21%

34.00

11,137.38

4.73

544.90

18.00

85.14

15.63%

18.00

85.14

15.63%

36.00

170.28

02.03.02

04.01.01

CONCRETO EN ZAPATAS F'C= 210 KG/CM2

M3

2.9

04.01.02

ACERO PARA ZAPATAS GRADO 60

KG

115.2

04.02

PLACAS

04.02.01

CONCRETO EN PLACAS F'C= 210 KG/CM2

M3

9.33

369.18

3,444.45

21.00

7,752.78

225.08%

21.00

7,752.78

225.08%

42.00

15,505.56

04.02.02

ENCOFRADO Y DESENCOFRADO EN PLACAS

M2

81.78

34.98

2,860.66

22.00

769.56

26.90%

22.00

769.56

26.90%

44.00

1,539.12

04.02.03

ACERO GRADO 60 EN PLACAS

KG

897.03

4.72

4,233.98

23.00

108.56

2.56%

23.00

108.56

2.56%

46.00

217.12

04.03

VIGAS

04.03.01

CONCRETO EN VIGAS F'C=210 KG/CM2

M3

236.10

26.00

8,896.42

3768.12%

26.00

8,896.42

3768.12%

52.00

17,792.84

04.03.02

ENCOFRADO Y DESENCOFRADO CARAVISTA EN VIGAS

M2

1.65

65.87

108.69

27.00

1,778.49

1636.36%

27.00

1,778.49

1636.36%

54.00

3,556.98

04.03.03

ACERO GRADO 60 EN VIGAS

KG

141.66

4.72

668.64

28.00

132.16

19.77%

28.00

132.16

19.77%

56.00

264.32

2,211.39

31.00

11,444.58

517.53%

31.00

11,444.58

517.53%

62.00

22,889.16

517.31

32.00

1,204.80

232.90%

32.00

1,204.80

232.90%

64.00

2,409.60

04.06

0.69

342.17

GRADERIAS

04.07.01

CONCRETO F'C= 210 KG/CM2 EN GRADERIAS REFORZADAS

M3

5.99

369.18

04.07.02

ENCOFRADO Y DESENCOFRADO P/GRADA Y/O PISO

M2

13.74

37.65

04.07.03

ACERO ESTRUCTURAL TRABAJADO PARA ESCALERAS

KG

702.99

4.68

3,289.99

33.00

154.44

4.69%

33.00

154.44

4.69%

66.00

308.88

04.08.00

LOSAS MACIZAS

04.08.01

CONCRETO EN LOSA MACIZA F'C=210 KG/CM2

M3

5.55

328.25

1,821.79

36.00

11,817.00

648.65%

36.00

11,817.00

648.65%

72.00

23,634.00

04.08.02

ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MACIZAS

M2

10.52

40.68

427.95

37.00

1,505.16

351.71%

37.00

1,505.16

351.71%

74.00

3,010.32

04.08.03

ACERO ESTRUCTURAL TRABAJADO LOSAS MACIZAS

KG

100.98

4.68

472.59

38.00

177.84

37.63%

38.00

177.84

37.63%

76.00

355.68

04.09

PLACAS PARAPETOS

04.09.01

CONCRETO EN MUROS TABIQUES Y PLACAS F'C= 210 KG/CM2

M3

1.93

369.18

712.52

41.00

15,136.38

2124.35%

41.00

15,136.38

2124.35%

82.00

30,272.76

04.09.02

ENCOFRADO Y DESENCOFRADO MUROS TABIQUES Y PLACAS

M2

35.28

27.39

966.32

42.00

1,150.38

119.05%

42.00

1,150.38

119.05%

84.00

2,300.76

A
ID
RT
PA

04.09.03

07.00
07.01.00

AD
ID
UN METRADO

D E S C R I P C I N

ACERO GRADO 60 EN MUROS TABIQUES Y PLACAS

KG

153.99

AVANCE ACUMULADO
ANTERIOR

PRESUPUESTO BASE
P.UNITARIO

AVANCE ACTUAL
DEL MES

AVANCE ACUMULADO
TOTAL

P.PARCIAL

METRADO

IMPORTE

METRADO

IMPORTE

METRADO

IMPORTE

4.72

726.83

43.00

202.96

27.92%

43.00

202.96

27.92%

86.00

405.92

27.46

REVOQUES ENLUCIDOS Y MOLDURAS


CIELORRASOS CON MEZCLA DE CEMENTO-ARENA

M2

26.42

725.49

47.00

1,290.62

177.90%

47.00

1,290.62

177.90%

94.00

2,581.24

30.00

24.56

736.80

48.00

1,178.88

160.00%

48.00

1,178.88

160.00%

96.00

2,357.76

M2

15.35

16.69

256.19

49.00

817.81

319.22%

49.00

817.81

319.22%

98.00

1,635.62

18.04

36.08

53.00

956.12

2650.00%

53.00

956.12

2650.00%

106.00

1,912.24

62.40

124.80

54.00

3,369.60

2700.00%

54.00

3,369.60

2700.00%

108.00

6,739.20

158.57

58.00

509.82

321.51%

58.00

509.82

321.51%

116.00

1,019.64

212.52

684.31

62.00

13,176.24

1925.47%

62.00

13,176.24

1925.47%

124.00

26,352.48

47.24

959.92

66.00

3,117.84

324.80%

66.00

3,117.84

324.80%

132.00

6,235.68

8.00

17.84

142.72

70.00

1,248.80

875.00%

70.00

1,248.80

875.00%

140.00

2,497.60

2.00

84.30

168.60

71.00

5,985.30

3550.00%

71.00

5,985.30

3550.00%

142.00

11,970.60

2.00

13.26

26.52

72.00

954.72

3600.00%

72.00

954.72

3600.00%

144.00

1,909.44

M2

26.42

10.39

274.50

76.00

789.64

287.66%

76.00

789.64

287.66%

152.00

1,579.28

M2

81.78

9.25

756.47

77.00

712.25

94.16%

77.00

712.25

94.16%

154.00

1,424.50

M2

6.44

15.65

100.79

78.00

1,220.70

1211.18%

78.00

1,220.70

1211.18%

156.00

2,441.40

104,053.460

299.16%

07.02

FORJADO Y REVESTIM. DE GRADAS Y ESCALERAS DE CEM. COLOREADO

07.03

REVESTIMIENTO DE DESCANSOS C/MOR.1:4 X 2CM +PULIDO 1:2 X

08.00

PISOS Y PAVIMENTOS

08.03

CONTRAPISO DE 48 MM.

M2

2.00

08.06

PISO GRES CERAMICO 10X21.5 CM. EN PASADIZOS

M2

2.00

09.00

ZOCALOS Y CONTRAZOCALOS

09.01

CONTRAZOCALO CEMENTO S/COLOREAR H = 10 CM PULIDO

10.00

CARPINTERIA DE MADERA

10.01

PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5 MM. DE CEDRO

11.00

CARPINTERIA METALICA

11.03

BARANDA DE TUBO NEGRO PASAMANO 1 1/2" INCLUYE PINTADO

13.00

CERRAJERIA

13.01

BISAGRA ALUMINIZADA CAPUCHINA DE 4" X 4"

PZA

13.03

CERRADURA PARA PUERTA PRINCIPAL PESADA

PZA

13.05

MANIJA DE 4" PARA PUERTA PESADA

UND

15.00

PINTURA

15.01

PINTURA LATEX EN CIELO RASO 2 MANOS

15.07

PINTURA LATEX EN MUROS Y PLACA CARAVISTA

15.08

PINTURA EN PUERTAS C/BARNIZ 2 MANOS

M2

18.04

3.22

20.32

8.79

34,781.84

104,053.460

299.16%

208,106.920

YO DE 2007

TERIALES, MANO DE OBRA Y EQUIPOS

ACUMULADO
TOTAL

SALDO POR VALORIZAR


%

METRADO

IMPORTE

0.00%
8.68%

23.04

49.54

100.00%

21.04

115.30

91.32%

57.89%

5.82

9.95

42.11%

17.39%

57.00

3,107.64

82.61%

16.91%

68.80

1,000.35

83.09%

69.44%

7.04

39.00

30.56%

494.85%

-19.15

-565.31

-394.85%

1172.41%

-31.10

-10,187.43

-1072.41%

31.25%

79.20

374.62

68.75%

450.16%

-32.67

-12,061.11

-350.16%

53.80%

37.78

1,321.54

46.20%

5.13%

851.03

4,016.86

94.87%

7536.23%

-51.31

-17,556.74

-7436.23%

3272.73%

-52.35

-3,448.29

-3172.73%

39.53%

85.66

404.32

60.47%

1035.06%

-56.01

-20,677.77

-935.06%

465.79%

-50.26

-1,892.29

-365.79%

9.39%

636.99

2,981.11

90.61%

1297.30%

-66.45

-21,812.21

-1197.30%

703.42%

-63.48

-2,582.37

-603.42%

75.26%

24.98

116.91

24.74%

4248.70%

-80.07

-29,560.24

-4148.70%

238.10%

-48.72

-1,334.44

-138.10%

ACUMULADO
TOTAL

SALDO POR VALORIZAR


%

METRADO

IMPORTE

55.85%

67.99

320.91

44.15%

355.79%

-67.58

-1,855.75

-255.79%

320.00%

-66.00

-1,620.96

-220.00%

638.44%

-82.65

-1,379.43

-538.44%

5300.00%

-104.00

-1,876.16

-5200.00%

5400.00%

-106.00

-6,614.40

-5300.00%

643.02%

-97.96

-861.07

-543.02%

3850.93%

-120.78

-25,668.17

-3750.93%

649.61%

-111.68

-5,275.76

-549.61%

1750.00%

-132.00

-2,354.88

-1650.00%

7100.00%

-140.00

-11,802.00

-7000.00%

7200.00%

-142.00

-1,882.92

-7100.00%

575.32%

-125.58

-1,304.78

-475.32%

188.31%

-72.22

-668.04

-88.31%

2422.36%

-149.56

-2,340.61

-2322.36%

598.32%

-173,325.073

-498.32%

VALORIZACIN DEL AVANCE FSICO DE OBRA


PROYECTO
OBRA
UBICACIN

: URBANIZACIN E INFRAESTRUCTURA
: CONST. E IMPLE. DEL PAB. DE AULAS, SS.HH MOD. Y ADM. DE LA FAC. DE CIENCIAS DE LA EDUCACION
: CIUDAD UNIVERSITARIA

PERODO VALORIZADO
PRESUPUESTO DE

: ABRIL DE 2007
: MATERIALES, MANO DE O

AREA

: ARQUITECTURA

FECHA DE ENTREGA

SUBPROYECTO

: MODULO "B"

A
ID
RT
PA

PRESUPUESTO
AD
ID
UN
METRADO
P.UNITARIO

D E S C R I P C I N

BASE

AVANCE ACUMULADO
ANTERIOR

P.PARCIAL

METRADO

IMPORTE

13.13

2,122.20

161.63

2,122.20

100.00%

17.08

8,723.44

390.25

6,665.47

76.41%

79.42

17.14

1,361.26

0.00

0.00

0.00%

356.64

14.55

5,189.11

0.00

0.00

M2

50.21

21.41

1,075.00

15.48

619.10

2.14

1,324.87

235.65

BRUAS E=1CM. EN PISOS Y VEREDAS

123.90

2.26

280.01

07.09.00

TARRAJEO EN CIELORRASO CON YESO

M2

657.58

30.13

08.00.00

PISOS Y PAVIMENTOS

08.01.00

SARDINELES DE CONCRETO F'C=175 KG/CM2

37.85

300.33

08.02.00

CONTRAPISO DE 2" CON CERAMICO

M2

53.82

33.32

08.03.00

CONTRAPISO DE 48 MM.

M2

719.51

08.04.00

PISO DE CERAMICO 30X30 CM. ANTIDESLIZANTE DE TRANSITO MEDIO EN SS.HH

M2

08.05.00

PISO DE CERAMICO 30X30 CM. ANTIDESLIZANTE

08.06.00

AVANCE ACTUAL
DEL MES

AVANCE ACUMULADO
TOTAL

IMPORTE

METRADO

IMPORTE

55.90

733.96

34.58%

217.53

2,856.16

120.25

2,053.92

23.54%

510.50

8,719.39

11.88

203.62

14.96%

11.88

203.62

0.00%

138.34

2,012.85

38.79%

138.34

2,012.85

331.43

30.83%

13.34

285.61

26.57%

28.82

617.04

504.29

38.06%

63.21

135.27

10.21%

298.86

639.56

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

19,812.89

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

11,367.49

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

1,793.28

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

18.04

12,979.96

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

68.79

45.19

3,108.62

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

M2

492.82

45.19

22,270.54

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

PISO DE PORCELANATO EN PASADIZOS

M2

173.94

101.25

17,611.43

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

08.07.00

PISO DE 2" CONCRETO F'C 140 KG/CM2 X 4 CM.+ PULIDO 1:2 X 1CM

M2

376.96

58.68

22,120.01

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

08.08.00

CANTONERA EN GRADAS DE ALUMNIO 1 1/2" X 1 1/2"

195.60

16.23

3,174.59

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

08.09.00

JUNTAS ASFALTICAS

67.73

4.09

277.02

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

09.00.00

ZOCALOS Y CONTRAZOCALOS

09.01.00

ZOCALO DE MAYOLICA DE COLOR DE 20 X 30 DE 1ERA

M2

161.63

59.14

9,558.80

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

09.02.00

CONTRAZOCALO CON PORCELANATO

294.70

93.71

27,616.34

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

09.03.00

CONTRAZOCALO DE CEMENTO PULIDO C/MORTERO 1:5 DE 2CM.X .20M.

34.20

6.56

224.35

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

09.04.00

CONTRAZOCALO DE CEMENTO PULIDO C/MORTERO 1:5 DE 2CM.X .30M.

59.38

7.89

468.51

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

10.00.00

CARPINTERIA DE MADERA

10.01.00

PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5 MM. DE CEDRO

M2

35.20

440.53

15,506.66

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

10.02.00

PUERTA CONTRAPLACADA 35 MM. C/TRIPLAY 4MM.+ MARCO CEDRO 2X3"

M2

15.24

254.45

3,877.82

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

10.03.00

PIZARRA ACRILICA DE 5.80 X 1.40 M

6.00

470.78

2,824.68

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

11.00.00

CARPINTERIA METALICA

11.01.00

VENTANA DE ALUMINIO 1"X4" SEGUN DISEO

M2

120.84

202.73

24,497.89

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

11.02.00

PROTECTOR DE VENTANA CON REJILA METALICA

M2

120.84

176.70

21,352.43

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

11.03.00

BARANDA DE TUBO NEGRO PASAMANO 1 1/2" INCLUYE PINTADO

272.69

48.62

13,258.19

75.60

3,675.67

27.72%

0.00

0.00

0.00%

75.60

3,675.67

13.00.00

CERRAJERIA

13.01.00

BISAGRA ALUMINIZADA CAPUCHINA DE 4" X 4"

PZA

40.00

17.84

713.60

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

13.02.00

BISAGRA ALUMINIZADA CAPUCHINA DE 3" X 3"

PZA

40.00

14.85

594.00

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

13.03.00

CERRADURA PARA PUERTA PRINCIPAL PESADA

PZA

10.00

84.57

845.70

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

13.04.00

CERRADURA PTA.BAO SEG.INT.PER.MANIJ.CERRAD.GOAL 42 NP BAO

PZA

10.00

49.72

497.20

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

13.05.00

MANIJA DE 4" PARA PUERTA PESADA

UND

10.00

13.57

135.70

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

13.06.00

MANIJA DE 3" PARA PUERTA LIVIANA

UND

10.00

11.26

112.60

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

14.00.00

VIDRIOS, CRISTALES Y SIMILARES

14.01.00

VIDRIOS SEMIDOBLES INCOLORO CRUDO

8,284.12

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

07.00.00

REVOQUES ENLUCIDOS Y MOLDURAS

07.01.00

TARRAJEO DEL TIPO RAYADO O PRIMARIO C/MORTERO 1:5

M2

161.63

07.02.00

TARRAJEO INTERIOR C/MORTERO 1:5 X1.5 CM.(INC.COLUMNAS EMPOT)

M2

510.74

07.03.00

TARRAJEO EXTERIOR C/MORTERO 1:5 X 1.5CM.(INC.COLUMNAS EMPOT)

M2

07.04.00

VESTIDURA DE DERRAMES EN PUERTAS, VENTANAS Y VANOS.

07.06.00

TARRAJEO DE SUPERFICIE DE COLUMNETAS CON CEMENTO-ARENA

07.07.00

BRUAS E=1CM. EN MUROS INT

07.08.00

UND

P2

1,362.52

6.08

METRADO

A
ID
RT
PA

PRESUPUESTO
AD
ID
UN
METRADO
P.UNITARIO

D E S C R I P C I N

BASE

AVANCE ACUMULADO
ANTERIOR

AVANCE ACTUAL
DEL MES

AVANCE ACUMULADO
TOTAL

P.PARCIAL

METRADO

IMPORTE

METRADO

IMPORTE

METRADO

IMPORTE

15.00.00

PINTURA

15.01.00

PINTURA LATEX EN CIELO RASO 2 MANOS

M2

657.58

8.84

5,813.01

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

15.02.00

PINTURA LATEX EN MUROS INTERIORES 2 MANOS

M2

679.32

7.52

5,108.49

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

15.03.00

PINTURA EN LADRILLO DE MURO CARAVISTA AL LATEX

M2

341.67

5.05

1,725.43

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

15.04.00

PINTURA LATEX EN COLUMNAS CARAVISTA

M2

275.64

7.54

2,078.33

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

15.05.00

PINTURA LATEX EN COLUMNETAS

M2

50.21

7.52

377.58

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

15.06.00

PINTURA LATEX EN VIGAS CARAVISTA

M2

393.83

8.86

3,489.33

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

15.07.00

PINTURA LATEX EN MUROS Y PLACA CARAVISTA

M2

216.54

8.68

1,879.57

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

15.08.00

PINTURA EN PUERTAS C/BARNIZ 2 MANOS

M2

84.20

19.62

1,652.00

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

15.09.00

PINTURA DE CONTRAZOCALO C/ESMALTE ECONOMICO

388.28

2.46

955.17

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

16.00.00

VARIOS

16.01.00

JUNTA DE DILATACION SISMICA

127.50

29.79

3,798.23

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

5,425.231

1.86%

COSTO DIRECTO

S/.

291,837.45

13,299.062

4.56%

18,724.293

DEL AVANCE FSICO DE OBRA

: ABRIL DE 2007
: MATERIALES, MANO DE OBRA Y EQUIPOS

AVANCE ACUMULADO
TOTAL

SALDO POR VALORIZAR

METRADO

IMPORTE

134.58%

-55.90

-733.96

-34.58%

99.95%

0.24

4.05

0.05%

14.96%

67.54

1,157.64

85.04%

38.79%

218.30

3,176.27

61.21%

57.40%

21.39

457.96

42.60%

48.27%

320.24

685.31

51.73%

0.00%

123.90

280.01

100.00%

0.00%

657.58

19,812.89

100.00%

0.00%

37.85

11,367.49

100.00%

0.00%

53.82

1,793.28

100.00%

0.00%

719.51

12,979.96

100.00%

0.00%

68.79

3,108.62

100.00%

0.00%

492.82

22,270.54

100.00%

0.00%

173.94

17,611.43

100.00%

0.00%

376.96

22,120.01

100.00%

0.00%

195.60

3,174.59

100.00%

0.00%

67.73

277.02

100.00%

0.00%

161.63

9,558.80

100.00%

0.00%

294.70

27,616.34

100.00%

0.00%

34.20

224.35

100.00%

0.00%

59.38

468.51

100.00%

0.00%

35.20

15,506.66

100.00%

0.00%

15.24

3,877.82

100.00%

0.00%

6.00

2,824.68

100.00%

0.00%

120.84

24,497.89

100.00%

0.00%

120.84

21,352.43

100.00%

27.72%

197.09

9,582.52

72.28%

0.00%

40.00

713.60

100.00%

0.00%

40.00

594.00

100.00%

0.00%

10.00

845.70

100.00%

0.00%

10.00

497.20

100.00%

0.00%

10.00

135.70

100.00%

0.00%

10.00

112.60

100.00%

0.00%

1362.52

8,284.12

100.00%

AVANCE ACUMULADO
TOTAL

SALDO POR VALORIZAR

METRADO

IMPORTE

0.00%

657.58

5,813.01

100.00%

0.00%

679.32

5,108.49

100.00%

0.00%

341.67

1,725.43

100.00%

0.00%

275.64

2,078.33

100.00%

0.00%

50.21

377.58

100.00%

0.00%

393.83

3,489.33

100.00%

0.00%

216.54

1,879.57

100.00%

0.00%

84.20

1,652.00

100.00%

0.00%

388.28

955.17

100.00%

0.00%

127.50

3,798.23

100.00%

6.42%

273,113.130

93.58%

VALORIZACIN DEL AVANCE FSICO DE OBRA


PROYECTO
OBRA

: URBANIZACIN E INFRAESTRUCTURA
: CONST. E IMPLE. DEL PAB. DE AULAS, SS.HH MOD. Y ADM. DE LA FAC. DE CIENCIAS DE LA EDUCACION

PERODO VALORIZADO

: ABRIL DE 2007

UBICACIN

: CIUDAD UNIVERSITARIA

PRESUPUESTO DE

: MATERIALES, MANO DE OBRA Y

AREA

: INSTALACIONES SANITARIAS

FECHA DE ENTREGA

SUBPROYECTO

: MODULO "B"

RT
PA

18.01.00

A
ID

D E S C R I P C I N

ID
UN

AVANCE ACUMULADO
ANTERIOR

PRESUPUESTO BASE

AD

AVANCE ACTUAL
DEL MES

AVANCE ACUMULADO
TOTAL

METRADO

P.UNITARIO

P.PARCIAL

METRADO

IMPORTE

METRADO

IMPORTE

METRADO

IMPORTE

APARATOS Y ACCESORIOS SANITARIOS

18.01.01

INODORO MONTECARLO COLOR COMERCIAL (SIN COLOCACION)

PZA

10.00

276.00

2,760.00

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

18.01.02

LAVATORIO OVALIN MEDIANO LOSA COLOR DE SOBREPONER

PZA

12.00

230.00

2,760.00

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

18.01.03

URINARIOS DE LOZA DE PICO COLOR

PZA

6.00

145.00

870.00

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

18.01.04

COLOCACION DE APARATOS Y ACCESORIOS SANITARIOS

PZA

28.00

46.47

1,301.16

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

18.02.00

SISTEMA DE AGUA FRIA Y CONTRA INCENDIO

18.02.01

SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2"

PTO

28.00

62.69

1,755.32

28.00

1,755.32

100.00%

0.00

0.00

0.00%

28.00

1,755.32

100.00%

18.02.02

RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP

18.00

12.77

229.86

5.00

63.85

27.78%

8.50

108.55

47.22%

13.50

172.40

75.00%

18.02.03

RED DE DISTRIBUCION TUBERIA DE 3/4" PVC-SAP

15.00

14.99

224.85

4.00

59.96

26.67%

0.00

0.00

0.00%

4.00

59.96

26.67%

18.02.04

VALVULAS DE COMPUERTA DE BRONCE DE 3/4"

PZA

2.00

102.07

204.14

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

18.02.05

VALVULAS DE COMPUERTA DE BRONCE DE 1/2"

PZA

6.00

82.07

492.42

0.00

0.00

0.00%

2.00

164.14

33.33%

2.00

164.14

33.33%

18.03.00

SISTEMA DE DESAGUE

18.03.01

SALIDAS DE PVC SAL PARA DESAGUE DE 4"

PTO

10.00

133.79

1,337.90

10.00

1,337.90

100.00%

0.00

0.00

0.00%

10.00

1,337.90

100.00%

18.03.02

SALIDAS DE PVC SAL PARA DESAGUE DE 2"

PTO

15.00

108.09

1,621.35

15.00

1,621.35

100.00%

0.00

0.00

0.00%

15.00

1,621.35

100.00%

18.03.03

SALIDAS DE PVC SAL PARA VENTILACION DE 2"

PTO

6.00

59.61

357.66

6.00

357.66

100.00%

0.00

0.00

0.00%

6.00

357.66

100.00%

18.03.04

TUBERIA DE PVC SAL 2"

30.00

10.52

315.60

15.00

157.80

50.00%

15.00

157.80

50.00%

30.00

315.60

100.00%

18.03.05

TUBERIA DE PVC SAL 4"

30.00

14.87

446.10

15.00

223.05

50.00%

15.00

223.05

50.00%

30.00

446.10

100.00%

18.03.06

SUMIDERO DE BRONCE 2", PROVISION Y COLOCACION

UND

8.00

81.12

648.96

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

18.03.07

REGISTROS DE BRONCE DE 4"

PZA

10.00

94.05

940.50

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

18.03.08

CAJA DE REGISTRO DE DESAGUE 12" X 24"

PZA

1.00

151.62

151.62

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

18.04.00

SISTEMA DE EVACUACION PLUVIAL

04.03.00

PROVISION E INSTALACION TUBERIA PVC-SAP C-10 D=3" P/LLUVIAS

25.50

21.44

546.72

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

05.01.00

PROVISION E INSTALACION TUBERIA PVC-SAP C-10 D=2+P/D PLUVIAL

22.50

12.18

274.05

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

06.01.00

SUMIDERO DE BRONCE 2", PROVISION Y COLOCACION P/PLUVIAL

UND

3.00

65.62

196.86

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

07.01.00

CODO DE PVC SAL SP DE 3"

UND

3.00

22.62

67.86

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

07.02.00

SOPORTE METALICO T/ABRAZADERA P/TUB. DE DIAMETRO 3"-5"

UND

48.00

10.70

513.60

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

07.03.00

COLUMENTA DE CONCRETO F'C=175 KG/CM2. 25X20

6.00

392.23

2,353.38

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

S/.

20,369.91

5,576.890

27.38%

653.535

3.21%

6,230.425

30.59%

COSTO DIRECTO

EL AVANCE FSICO DE OBRA

: MATERIALES, MANO DE OBRA Y EQUIPOS

SALDO POR VALORIZAR


METRADO

IMPORTE

10.00

2,760.00

100.00%

12.00

2,760.00

100.00%

6.00

870.00

100.00%

28.00

1,301.16

100.00%

0.00

0.00

0.00%

4.50

57.47

25.00%

11.00

164.89

73.33%

2.00

204.14

100.00%

4.00

328.28

66.67%

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

0.00

0.00

0.00%

8.00

648.96

100.00%

10.00

940.50

100.00%

1.00

151.62

100.00%

25.50

546.72

100.00%

22.50

274.05

100.00%

3.00

196.86

100.00%

3.00

67.86

100.00%

48.00

513.60

100.00%

6.00

2,353.38

100.00%

14,139.485

69.41%

You might also like