DESCRIPTION OF ITEM:

Item No. 5 Earthwork in ordinary soil for embankments lead upto 100 ft. (30 metre)
including ploughing and mixing with blade grade or disc harrow or
other suitable equipment and compaction by mechanical means at
optimum moisture content and dressing to designed section, complete
in all respects:

(i) 95% to 100% maximum modified AASHTO dry-density with vibratory roller.
Mixing, Moisterning earth to optimum moisture contant in layer etc.
complete with tractor complete with rotorator blade.

Detail Unit Rate (British System) per 1000 Cft

Qty Rate Per Unit Amount (Rs.)

Rate Analysis for 1250 Cft (65 m³)


LABOUR

1 Coolies unskilled for digging 4.00 Nos. 165.00 per day 660.00
2 Coolies unskilled for carrying 3.00 Nos. 165.00 per day 495.00
3 Dresser cooly skilled 0.125 No. 180.00 per day 22.50
4 Cooly unskilled 0.142 No. 180.00 per day 25.56

Total 1,203.06
Sundries 10.00 Percent 120.31
Total 1,323.37
Contractor's Profit & Overheads 20.00 Percent 264.67
Total Rate for 1250 Cft 1,588.04

MACHINERY (For 1000 Cft Compacted)

1 Tractor with rotarator blade 0.25 HR 901.00 per hrs. 225.25


2 Vibratory Road Roller 0.25 HR 1800.00 per hrs. 450.00

Total 675.25

ITEM RATES

Labour rate per 1000 Cft Rs. 1270.43 Say 1,270.45


Labour rate per Cum Rs. 44.87 Say 44.85

Composite rate per 1000 Cft Rs. 1945.68 Say 1,945.70


Composite rate per Cum Rs. 68.72 Say 68.70