Professional Documents
Culture Documents
DEPARTMENT OF ECONOMICS
PRESENTED BY:
MOHAMMED JUMAI
CHAPTER ONE
INTRODUCTION
In the contemporary world, reading and quest for knowledge are essential elements of
man’s survival. So far as knowledge acquisition is concerned, man cannot depart from
reading and making research. The central mission of a library is to collect, organize,
preserve, and provide access to knowledge and information. In fulfilling this mission,
libraries preserve a valuable record of culture that can be passed down to succeeding
generations. Libraries are an essential link in this communication between the past, present,
and future. Whether the cultural record is contained in books or in electronic formats,
libraries ensure that the record is preserved and made available for later use. Libraries
provide people with access to the information they need to work, play, learn, and govern.
Books, journals, Internet and other articles serve as reading materials and are usually kept
on personal shelves. They can also be found in community libraries in most villages and
towns. All schools have some form of libraries whether small or large for pupils and students
to have access to reading materials. University of Ghana has its own library, Balme Library,
where the whole student population goes to do research on their academic work. With the
increase in student population there was the need for departmental library in all the
departments and the Economics department was no exception. At the time of the university
college, there was a political science department comprising of both political science and
economics studies. In 1963, the political science section was separated from Economics
department and at this time collection of reference materials were kept in a room which
was later developed into a library. The initial development came about through exchange
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
research programmers who came as visiting lecturers and on return donated their research
materials to the library. The Economics departmental library was formally established in
1969 to help solicit for and make available educational reading materials for students and
lecturers of the department. In 1994, the African Economic Research Consortium introduced
University of Ghana, Legon. Part of the program package was rehabilitation of the library as
well as computer room. Later in 1998, when the Economic Policy Management (EPM)
program was introduced by the African Capacity Building Foundation (ACBF) and the World
Initially, it was made to accommodate students at all levels of the department. Later, due to
the increasing number of students in the department yearly there was a high pressure on
the existing facility. As a result, the levels 100 and 200 students were exempted from using
the library. The average number of students using the library now is one thousand (1000)
but the library can only take a sitting capacity of forty (40) students which is inadequate. The
Economic Policy Management (EPM) program also has a library with a sitting capacity of
thirty (30) students. The two libraries, if joined together will still not be sufficient for
Although the Economics departmental library is still serving the department, it is saddled
with the following problems:
The library is now under serious pressure by undergraduates, post-graduates, lecturers and
researchers. There has neither been any renovation nor expansion of any sort for about 16
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
years now, despite the increase in the total population of the department. The location of
the existing library makes it impossible for an expansion.
The library has only one computer which initially was to be used for book searches but now
used only by the librarian for the internet searches and the likes. There is none for students
to use for their research. Comparing the departmental library to that of other departments
the Economics departmental is lacking behind and has nothing to write home about.
The current state of furniture in the library is very poor, the library lacks good quality chairs
and tables with such trends as making noise as well as broken and they are quite
uncomfortable and inappropriate for study. Also Shelves are not adequate for effective
There is no ventilation because of the air conditioners, which are presently not in use. The
only source of air in the library is two ceiling fans which is medically not advisable since the
stillness of the place can lead to the attraction of several diseases. Proper lights are required
Time allocated for the use of the library is inadequate for effective academic work
For excellent academic work, references given by lecturers should be considered and not
only relying on the notes taken in class. There is therefore the need for the library to be
Economics as a discipline is a social science which needs to stand the test of time. The
recommended readings are not found in the library. This discourages students from using
the library.
The aim of this project is to do a cost benefit analysis of constructing a new library for the
department which will consist of three sections; a. archive, b. Automated Information and
The broad objective of this project is to promote the taste for modernity to raise the
department to the international level where students’ academic needs can be catered for
maintenance, possible source of finance and sustainability if our study proves the viability of
the project.
The Economic Policy Management (EPM) building has a stretch of land towards the
Volta Hall Car Park which can be used for this project. The project upon completion
Students of the department will have a conducive library for effective academic
work in order to produce more and better economist for the country.
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
Be able to allow the lower levels 100 and 200 to use the facility to develop their
Help reduce stress among students in order to increase the number of females
offering the course at first and second degree. By this the department will be able to
It will contain both the Economics department and the Economic Policy
Management department libraries which will enhance research work and proper
1.5 METHODOLOGY
information is basically going to be both primary and secondary. The primary data will
be sourced from the contractors, quantity surveyors and the Physical Development and
The secondary data will be sourced ethnohistorically from University of Ghana annual
reports. The key methodologies, which will be employed, involve face to face interviews.
The Investment Criteria in our analysis will be Net Present Value (NPV).
It is simple to calculate
n
( Bn−Cn)
NPV =∑ −Co
k=0 ( 1+r ) t
Where:
t = Time period
NPV= 0, Inconclusive
The choice of this criterion is simply because of its compatibility with our project.
Anticipate some sort of friction from people we shall consult for information when it
comes to estimate of the proposed structure. This may be because of the busy schedule
of contractors and surveyors. Contacting them for layouts, building plans and estimates
We shall make advance placement and requests for information in order to be secured
and be ahead of time and schedule to enhance our early and effective completion of
work as planned.
Chapter one looks at the historical background of the problems, the objectives of the
Chapter two will look at the projects appraisal via technical, financial, economical, social
and institutional so as to lay the foundation for the implementation of the project.
Chapter three will focus on the identification of costs and benefits involving both the
Chapter five states the summary, conclusions and recommendations of the study.
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
CHAPTER TWO
INTRODUCTION
As the project takes shape and studies get more intensified, it is deemed appropriate that a
formal process of appraisal and detailed comprehensive preview of all aspect of the project
document or plan to assess its overall soundness and readiness for implementation. In other
words, project appraisal is the process of assessing and questioning the proposal put
Considering the felt need, identification of this project and its requirements, magnitude and
social dimensions to withstand the test of time and modernity, it would be inapt to kick-
start and reach decisions about the project without providing review of very important
aspects and relevant issues of the project which would easily affect its construction,
This chapter therefore seeks to focus on providing detailed and comprehensive analyses of
the “design” of the project in all its dimensions. Thus, our task hence will be to conduct the
Institutional Appraisal.
Technical Appraisal.
Financial Appraisal.
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
Economical Appraisal.
Social Appraisal.
It must be emphasized that project appraisal is a potent instrument for choosing the best
alternative and improving the investment process thereby imposing discipline in the
decision makers.
Institutions are established law, custom, practice and organizations that guide and influence
decisions in a community. The creation and inculcation of a viable local “institution” is very
important for long-term survival of a project. Yet it is the most difficult aspect of the project
since it depends on the understanding of the culture environment and the beliefs systems of
the inhabitants. The institutional appraisals therefore enables us to analyze and understand
not only the project per say but also its organization, management, staffing, policies, norms
as well as a whole array of government policies, laws and practices by the department that
In this view, the laws and regulations that govern building of a new structure on University
policies and management shall be followed and strictly adhered to. Also culture, norms and
practices of the Economic s department and the Economic Policy Management (EPM) shall
be given full respect. These notwithstanding any policy that require changes before the
implementation of the project shall be taken care of, prior to the implementation phase.
based on conventions and norms to a given design or at least physical look alike. The new
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
Library, proposed to be an extension of the EPM block, takes the same painting and roofing
This appraisal is meant to ensure whether the project meets the required specifications and
executed as scheduled. It concentrates on the aspects of physical scale of the project and
the appropriate technology to be used. These include either, capital or labour intensive
methods, the implementation schedule and whether the project is realistic from the
technical point of view with the possibility of achieving desired output. There will be four
main sub-analyses such as project site location and structure format consultancy services,
The site and the land earmarked for the project is the stretch of land between the Economic
Policy Management Program block and the Volta Hall Car Park. This patch of land is about
9.35meters by 17.85meters and fit for the project. The project is a two storey building which
contains three different sections. The ground floor contains the first section which is the
main reference and reading room, the first floor will contain two sections; the automated
ICT and the economic archive centers. This will comprise of a standard contemporary, multi-
purposed world class research center to withstand ''Economic Integration Drive'' on Africa
continent and the global world. A center, most welcoming all kinds of investment drive
researchers especially on the African's new challenges which required new model of all-
The two main consultancy approaches of consideration will be tradition and turnkey
approaches. The traditional approach is the tendering process of hiring contractors and sub-
contractors for each stage of the project. The second one, turnkey approach where one
contractor takes sole responsibility for the construction of the entire project, could be opted
for since time and money could be saved and the urgency and felt need of the project will
be considered. The construction companies involved in this project are TAYSEL and CHINA
The construction of the new library is estimated to last for twelve (12) months or one (1)
year. Within this period, the schedule is as follows;
Table 2.1
TIME ACTIVITY
structures.
3TH-8TH ,MONTH Main structure, roofing and ceiling.
and furnishing.
10TH- 11TH MONTH Stocking with reading and research materials,
computers and other relevant materials. A
qualified and proactive librarian with
contemporary skills will be recruited.
We suggested the 12 months period interval taking cognizance of the fact that natural
causes beyond human control are inevitable. Rainfall season for instance will slow down the
pace of the work. Also we recognize that, there should be some flexibility for bureaucratic
delays in the acquisition and disbursement of fund for the project. Suppliers may also
encounter some hitches in one way or the other in delivering of materials on time.
Due to the landscape of the site, it will not be convenient to use heavy machines. Labour
intensive approach is more appropriate. Also in order not to obstruct academic work we opt
for a labour intensive. The company that wins the bidding process will be advised to use
more local laboures from the university and is environs. This will facilitate the creation of
employment for the unemployed youth in the general vicinity. These notwithstanding, the
labour intensive technical approach will be coupled with some quantum or sizable amount
With all these issues being considered, the project will expect a desirable high level of
output.
This appraisal seeks to ensure that funds for the project will be adequate enough and available to
cover the entire life span of the project. The financial plan for the construction from inception to
completion will be drawn in consultation with the appropriate entity, herein, the Development
Office of the University of Ghana. However, taking into consideration the current prices of material
equipment, labour and other utility services with the current inflation rate as at January 2010 of
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
14.78%, we expect the total cost of putting up this structure to be GHC 350,000. The details or the
breakdown of this cost will be captured in Cost Benefit Analysis in Chapter Three (3).
Our expected sources of funds for this project, in the interim, are the GETFund and The Bank of
Ghana. This not withstanding to avoid unforeseen eventualities, with regards to disappointment and
shortage of funds, we suggest that the Department should organize a fund raising dinner under the
theme “Remembrance night of past and present product of Economics Department, UG.” In
addition, the Department can establish “a Development Fund” into which both Past and Present
students of the Department contributes their tokens to provide the seed money.
Economic appraisal offers an assessment of how a project will contribute to the development
objectives. In other words, it helps to analyses the long-term effect of the project on the economy as
a whole and to see whether the objectives of the project are in line with the development plans and
objectives of the Department. As part of the developmental objectives, the Economics Department
aims at providing infrastructure necessary to improve the quality of learning and research of high
caliber, introducing new courses, improving and restructuring the course content in order to foster
the socio-economic development of the nation and possibly support the macro-economic
Obviously one of the greatest set back perhaps to realization of the above stated objectives,
is the lack of adequate educative and research facilities to promote and enhance intellectual
curiosity among students of the Department. A successful completion of this project will
help to some extent revamp the deteriorating quality and eliminate other problems since
the Library will provide not only the required reading and research materials but also the
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
comfort needed for both the individual and groups philosophizing. Undoubtedly, it is an
empirical fact that illiteracy rate is higher in less developed countries implying that
For cost benefit analysis of the project to be simple and coherent, certain economic
variables must be assumed. That; the price level be constant over the economic life of the
project to enable us eliminate the implications of price fluctuation. That; maintenance cost
be zero in the first ten (10) years and grow at 10% in every ten (10) years and that the
interest rate on which discount rate based, remain constant over the period.
The social appraisal concerned with analyses of the social impact of the project on the
department and the university community as a whole. The project is an educational facility
project's social impact travels beyond the purview of Economics and engages several
analytical techniques of other social sciences. However, for the purpose of this academic
study, we simply assess the impact of the project on the social well being of the
beneficiaries by considering the most relevant issues such as distribution of the benefit,
strengthening of research work and its coordination between various financial institution
and other key sectors of the Ghanaian economy. Also the employment creation to the folks
of the university community and its environs; may improve standard of living temporarily.
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
On the empowerment of women the female student will now have that productive capacity
to equally compete with the male counterparts in all fields of academic endeavors to ensure
Socially the project may pose some minimal level of noise making that may not disrupt
Encourage more students to specialize the discipline since all levels are now
of our macroeconomic issues and policies facing the country, West Africa and
CHAPTER THREE
Every project is implemented with one essential reason, thus to derive some benefits from
it. However, it is an inevitable fact that the implementation inextricably involves incurring
costs. These therefore are the expenditures and losses that need to be borne by society in
order to acquire a social investment project. Very often than not, these cost and benefits
travel beyond those who are directly associated with the project giving rise to what is
For a conclusion to be drawn whether a project is viable or not, there is the need to identify
and quantify these cost and benefit with their associated externalities to the project. If the
benefit generated by the project exceeds the cost, then the project is viable and worth
undertaking.
This chapter therein seeks to concentrate on identifying and quantifying these cost and
benefits. However, since cost benefit analysis is mainly applied to a public project, some
cost and benefit cannot be quantified in monetary terms and hence placing value on them
will be difficult though possible. We hereby divide the cost and benefit into real and
pecuniary. For the purpose of our study being a public project, we will perhaps ignore the
pecuniary cost and benefit since it results from redistribution effect of the concerned
project.
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
The real cost and benefits which relate to the allocative effect of the structure construction
will be grouped into direct and indirect cost and benefits, which can be further categorized
COMPUTATION OF COSTS
This cost items are those closely related to the project and easily quantifiable in monetary
units. These costs can also be classified into tangible and intangible direct costs .
These are cost elements that are closely related to the construction of the structure are
easily quantified in monetary units. These cost elements can be identified as a result of the
cash outlays involved not only the procurement of building materials and utility services but
The total direct tangible cost of the building is estimated to be GHC 350,000.This estimate is
arrived at by giving due consideration to the market value of the resources required to
construct the building of such a caliber or standard of our point of view. This way, we will
classify the various direct tangible costs as cost associated with the general conditions, the
SUBSTRUCTURE:
The various cost identified with the substructure are cost of clearing, excavation and
earthwork, form work, block and plastering work at the foundation. These costs are found in
Table 3.1.1
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
SUPERSTRUCTURE:
The various cost elements related to the building of the superstructure are among other
things; cost of concrete works, block work, roofing, carpentry and joinery works, structural
steel works and metal works. Other cost such as glazing, plumbering, electrical and
engineering installation, plaster works, ceiling, furnishing, painting and decoration cost.
FURNISHING:
The cost elements related to furnishing the library includes cost of fixing a counter, shelves,
reading desk, tables, chairs, cabinet, curtains, photocopying machines, computers, id tags
and the cost of installing computers. These costs are found in Table 3.1.2
STOCKING:
This gives the cost of books for all levels of the undergraduate course. It also includes books
for the EPM program and other postgraduate courses as well as articles, journals and
Substructure 35,841.04
Superstructure
Concrete work 65,867.60
Brick and block work 10,921.50
Roofing 8,402.38
Carpentry 7,382.00
Joinery 26,377.00
Structural steel work 8,000.00
Engineering installation 5,559.65
Plaster work and other floor wall 20,170.06
and ceiling finishing
Glazing 2,685.00
Painting and decorating 5,211.88
Total builders work 168,858.46
Contingencies 10% 16,885.85
TOTAL 185,744.31
Fixtures
Electrical installation 20,750.00
Plumbing installation 5,000.00
Air-conditioning installation 6 1,500.00
External work 3,250.00
Total fixtures 30,500.00
TOTAL SUPERSTRUCTURE 201,203.96
Other costs to be incurred are the cost of interior decorations. This covers the cost of fixing curtains,
shelves and stocking the Library. The table below shows the details at these costs.
Table 3.1.2
id tags 20 1 20
Telephone 60 2 120
Maintenance 2,000.00
GRAND TOTAL 84,780.00
STOCKING OF LIBRARY
Table 3.1.3
PRICE (GH¢)
Applied 35 5 175
Applied 35 5 175
Applied 40 5 200
Applied 40 5 200
Applied 40 5 200
Applied 40 5 200
Articles 10 20 200
Journals 10 20 200
Reports 20 10 200
These are cost elements though closely related to the project, are difficult or cannot be
NOISE POLLUTION:
The equipments, machines such as concrete mixer and earth excavators will be used, however,
less capital intensive method adopted and these machines will produce a lot of noise to disrupt
the conducive atmosphere for sound academic work in the various departments surrounding the
project site.
DUST POLLUTION:
During the excavation work, there is going to be a lot of dust pollution to the immediate
surrounding areas such as the Volta Hall Car Park. This is a cost to the owners of the vehicles.
LOSS OF VEGETATION:
The clearing and excavating the site will result in destruction of the vegetation of the green
These are cost elements not directly related to the library project in question; but are incurred in
order to facilitate the use of the library and help the beneficiary derive expected benefit.
Equally important, it consists of the adverse impact of the project on other people and their asset;
These costs are not directly associated with the project, but are easily computable at the market
prices in monetary terms. The indirect tangible cost is by nature costs not related to the objective of
MISELLANEOUS
Maintenance cost-Is the cost of replacing the defaulted equipments and tools used in the
construction of the library. The estimated cost for this is GHC8, 000.
Operational costs- this are daily petty cash spent during the operation of library such as
The table below gives a summary of both direct and indirect costs associated with this project.
Table 3.3
Superstructure 201,203.96
Furnishing the library 84,780.00
Benefits are returns to be derived from a project when it completed put under its intended
use.
These benefits can be directly or indirectly associated with the project and tangible or
intangible.
These benefits are those closely associated with the project. These are usually seen as the
These benefits are easily quantified in monetary units because they have market value. In
quantifying these benefits, we consider the amount of money the department will gain in
hiring the facility instead of using it for academic purposes. That is the market of the
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
benefits will be accrued in terms of the opportunity cost of using the library for academic
work. Since the library is not to be provided for commercial purposes so that the cash
The direct benefits will be ascertained by using any authorized substitute in this capacity.
Others 15 3 40 1800
Another benefit area the project can be perceived is in terms of charging fees for borrowing
of books from the library. On the assumption that the facility were to be run on commercial
basis, then people can be allowed to borrow books and for that matter have to be charged
The table below indicates the estimated number of users and the expected cash flow per
After allowing for Sundays and holidays, forty weeks per year was arrived at.
This refers to the non-quantifiable elements of the direct benefit. In this respect, the project
will help to reduce the congestion in the old economics department library which can be
converted into offices for lecturers. With increases in the student population the
The indirect benefits of the project relates mainly to the positive externalities of the ptoject.
These are benefit coming out as a result of the project that can be valued at the market
prices but are not based on the main objective of the project. One of such benefits is that
the department will have access to information technology, internet facility at the
automated computer laboratory for people to use. This in effect will serve as a source of
revenue to the department. Also clerical and computer services can be done to attract
revenue.
The table below depicts the revenue that the library generates from operating the computer
services.
s 20 2.00 40 1600.00
M Phil
Researchers 15 1.50 40 900.00
Others 15 1.00 40 600.00
GRAND TOTAL 11900.00
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
Another lucrative area under the indirect tangible benefit is where photocopy machines
would be provided in the library and can be used to make photocopies for users thereby
The table shows the computed revenue from photocopying services based on the market
In addition, the library can also derive revenue from using the computers for printing services.
As part of the project, car parking space will be provided. Our preliminary investigated have
revealed that parking a car at an approved place on campus cost a GHC 1.00 for a day. The
parking space in front of EPM building can accommodate about 15 cars at a time. Thus for
every month, the car park is expected to generate GHC 900 will amount to GHC 10,800 a
year .
The facility can attract contributions from Alumina. On average, the estimated inflow of
Other development fund raising and levies will amount to GHC 2000 per year.
Therefore, the total cash inflow per year amounts to GHC 7000.
These are benefits resulting from the project and not based on the objectives of the project
and also cannot be valued at the market prices. For example, the prestige attached to the
Economics Department of having such a magnificent library; a library that can conspicuously
enhance and facilitate opportunities for the EMP becoming a school of economic
In addition, it will attract intellectuals from all walks of life especially the third world
countries to come and research for possible economic survival since they are battling in
All these notwithstanding it also uplift the status and image of the department and give
that global appetizing recognition not to the University alone but to the entire country and
The table contains the summary of both direct and indirect benefits associated with the project.
CHAPTER FOUR
This chapter focuses on a detailed, profound and critical analysis of discounted benefits and
costs of the library in question to the students and other people of the University of Ghana.
discounting all costs and benefits by choosing a target rate of returns, also known as the
discount rate. A discount rate of 16% would be used to estimate the Net Present Value for
the 15 years life span of the project, the discount rate of 16% represents the Bank of Ghana
prime rate and this is because it is the most reliable in the country compared to the other
In this analysis procedure, a positive net present value signals project feasibility and viability
and should therefore be implemented. On the other hand, a negative net present value is
indicative of the fact that the project is not viable and therefore not worthy of being
implemented.
The NPV approach has been adopted because of the following merits it offers:
Because society places more value on the cedi today than the cedi in the near future,
The use of the NPV approach will help capture in our analysis most of the benefits
that will occur overtime so that we can avoid the temptation of rejecting the project
n
Bt−Ct
NPV=∑ (1+r )
t =0
t
Cash inflow refers to the benefits that accrue to the project and cash outflow also refers to
The total cost structure was GHC 385,000.00, comprising of GHC 247,045.00 for the
construction of the building including labour cost of GHC 10,000.00, GHC 84,780.00 for the
cost of furnishing with the facilities and GHC 5,075.00 for stocking the library with books
and other intangible cost of GHC5, 100.00 for miscellaneous cost and GHC8,000.00 for
maintenance cost. A contingency of 10% was calculated on the total amount for putting up
MAINTENANCE COST
We envisage that, there will be no maintenance cost for the first five (5) years of the
project. However, for every year in the next five (5) years an average cost of GHC
5000.00 will be estimated for maintenance with an inflationary rate of 15%. These
notwithstanding, every often and then new stock of books needed to augment or
replace the old stock. An average cost of 2% contingencies from any income to be in
OPERATIONAL COST
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
UTILITIES
These costs include the cost of electricity, water supply and clearing items. These
costs though may be embodied in a large bill of the University, for the purpose of
this project, electricity and water bill per month are expected to be GHC 100.00 and
GHC 550.00 respectively. Clearing items on the other hand, per month are expected
This cost includes wages paid to the 2 librarians that would be employed, the one working
in the library reading room and the other working in the archive and ICT section. Each of the
librarians would be paid GH¢400.00. Hence the total wages is GH¢800.00, which is also
expected to increase by 15% every year. Also, two cleaners would be employed with
The table below shows the operational costs and maintenance costs to be incurred over the
life span of the project.
TABLE 4.3
Cost/ Utilities Year Year Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
1 2
Wages/salari
es.
2librarians 9,600 11,04 12696 14,600.4 16,790.4 19,309.0 22,205.3 25,536.1
0 0 6 2 7 7
cleaners 2,880 3,312 3,808.80 4,380.12 5,037.13 5,792.69 6,661.59 7,660.82
Water bills. 1,200 1,380 1,587 1,825.05 2,098.80 2,413.62 2,775.66 3,192
Electricity 6,600 7,590 8,728.50 10,037.7 11,543.4 13,274.9 15,266.1 17,556.1
bills. 7 3 4 8 0
Clearing. 960 1,104 1,269.60 1,460.04 1,679.04 1,930.89 2,220.52 2,553.59
Maintenances ------ ------ -------- 5,000 5,750 6,612.50 7,604.37 8,745.02
TOTAL 21,24 24,42 28,089.9 37,303.3 42,898.8 49,333.7 56,733.7 65,243.8
0 6 0 8 8 1 6 2
Wages/salaries
.
2 librarians 29,366.59 33,771.58 38,837.32 44,662.92 51,362.35 59,066.70 67,926.71
2 cleaners 8,809.94 10,131.43 11,651.14 13,398.82 15,408.64 17,719.93 20,377.92
Water bills. 3670.8 4,221.42 4,854.63 5,582.82 6,420.52 7,383.59 8,491.13
Electricity bills. 20,189.51 23,217.94 26,700.63 30,705.72 35,311.15 40,607.22 46,698.30
Clearing. 2,936.62 3,377.12 3,883.69 4,466.24 5,136.18 5,906.60 6,792.59
Maintenances 10,056.77 11,565.28 13,300.08 15,295.09 17,589.35 20,227.75 23,261.91
TOTAL 75,030.1 86,284.9 99,227.6 114,111.8 131,228.6 150,912.9 173,548.56
6 5 9 4 2 1
The total benefit of the project annually is GHC 79,800.00, which increases by 15% over the
The table below shows the benefits to be generated for the lifespan of the project.
TABLE 4.4
YEAR BENEFIT
1 79,800.00
2 91,700.00
3 105,535.50
4 121,365.83
5 139,570.70
6 160,506.30
7 184,582.25
8 212,269.59
9 244,110.02
10 280,726.52
11 322835.51
12 371,260.83
13 426,949.96
14 490,992.45
15 564,641.32
TABLE 4.5.1
The cash flow is the difference between the benefits and the costs for each year.
1
t
(1+r )
Where
DECISION RULE
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
In using the NPV method as investment criterion, the decision is that a project is
worthy of embarking upon when the NPV is positive. On the other, it is not advisable
to undertake the project when the NPV is negative. By applying a discount rate of
In conclusion since NPV= 296,547.16 > 0, we undertake the project and conclude
that the project is economically, financially prudent and viably justifies the cost of its
undertaking.
Through the project implementation period we expect bank of Ghana to reduce the prime
rate, therefore we have computed a net present value in a two scenarios. One is where
prime rate falls to 13% and the other is when prime rate falls to 10%.
In both scenarios the remains positive, we undertake the project and conclude that
the project remains economically, financially prudent and viably justifies the cost of
CHAPTER FIVE
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
The final chapter of our project discusses findings from the new economics department
library project on University of Ghana campus. These findings, useful recommendations for
implementation and conclusion are made based on the results of the analyses of the project
5.1 SUMMARY
The costs and benefits analyses was carried on the new economics department library in
order to assess the viability or otherwise of the project. The main aim of building a new
library will be to construct a standard library which will be accessible to all students for
research and study. In all, the total cost of the project which includes both direct and
indirect cost amounted to GHC 385,000 comprising of Ghc350, 000 being cost of the
structure including the labour cost and contingencies was valued at GHC35, 000.
During the data collection process, interviews were conducted in which ten opinion leaders
who were at the helm of affairs regarding the construction of the new library project were
contacted. Ninety percent (90%) confirmed that the existing library was too small to
accommodate the current number of students in the department. The existing number of
Furthermore, it was found that the foreign students who come for exchange programme
complain and for that matter do not patronise the library facility. Thus, the library did not
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
meet the standard of an international library which does not speak well of the premier
University of Ghana.
In addition it was found that the library has to employ two librarians who will run shift in
Consequently, the existing library could be converted into offices for lecturers of the
undergraduate programme since some of them are left with no option than to share their
5.2 CONCLUSION
The economics department is in anticipation of a day in its life when the department will not
only be a department but an Economics School. This burning desire led to the decision by
eminent lecturers and other opinion leaders to build a bigger and standard library which will
Following the discussions of the analysis of costs and benefits in chapter 4,The cost and
benefit of the said project revealed a positive net benefit of GHC 79,800 which is indicative
of the fact that the social benefits far exceeds the social cost of the project hence its
5.3 RECOMMENDATIONS
The importance of library facilities in the total academic and socio-economic development
Ghana campus through the funding of GETFund and the Bank of Ghana is very dear to the
Based on the above the following recommendations would be made to the students, the
lecturers, the library staff, the Ghana Library Board and the government of Ghana.
First and foremost, it is recommended that construction work should begin as early as
started early with full order, monitoring and proper adherence to work schedule, so that the
building will be completed in time to confront the library problem faced by the department.
Mechanisms should be put in place to ensure early and proper disbursement of funds and
prevent possible embezzlement of the project fund. For this an ad hoc committee should be
set up to monitor the flow of funds for the project. These measures will go a long way to
ensure the project is not suspended because of inadequate funds. It is recommended that
an insurance policy should be taken against any accidents during construction. This will
researchers should take full advantage of the library to ensure effective studies in order for
Lecturers should encourage students to patronise the library by either giving them
reference or assignments which will require the usage of books from the library.
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
The Ghana library board should also conduct serious supervision work on the library staff so
that they would be duty conscious operating the library timely for the users.
Lastly the government should also be duty bound to attend to salaries and wages conditions
as soon as the need arises in order to avoid strike actions that would disrupt maximum use
of the library.
CBA OF CONSTRUCTING A NEW ECONOMICS DEPARTMENT LIBRARY
REFERENCES
2. Anthony Boardman E., David Greenberg H., Aidan Vining R. and David Weimer L.
(2001) “Cost - Benefit Analysis: concepts and practice”, Pearson prentice hall, third
edition.
3. European union, regional policy (2008) “Cost Benefit analysis of investment projects”
4. Layard Richard and Glaister Stephen. “Cost Benefit Analysis. (2003).” 2nd ed.
5. Pearce D.W and Nash C.A “The Social Appraisal of projects: A Text in Cost-Benefit”
Macmillan