1.

GENERAL

A. WORK CONSISTS, IN GENERAL, OF THE REMOVAL OF A


PANELBOARD, STARTERS, DISCONNECT SWITCHES,
FEEDERS, ETC., AND REPLACE WITH NEW.

B. ALL EXISTING SYSTEMS ARE TO OPERATE CONCURRENTLY


AND CONTINUOUSLY, EXCEPT AS DESCRIBED HEREIN.

C. THE WORK SCHEDULE IN OCCUPIED AREAS SHALL BE


COORDINATED AND AGREED UPON BY THE CONTRACTOR
AND BY THE CONTRACTING OFFICER'S REPRESENTATIVE,
AND SHALL BE APPROVED BY THE BUILDING MANAGER.

2. PHASING OF WORK:

A. ALL WORK WITHIN THE MECHANICAL/ELECTRICAL ROOMS


AND OUTSIDE OF THE BUILDING CAN BE PERFORMED
DURING THE NORMAL WORKING DAYS AND HOURS,
UNLESS OTHERWISE SPECIFIED.

B. USE OF NOISE PRODUCING EQUIPMENT DURING


CONSTRUCTION (CORE DRILLING, ETC.), SHALL BE LIMITED
TO AFTER HOURS (7:00 P.M. - 5:00 A.M.), AND SHALL BE
PERFORMED ON WEEKENDS.

C. ALL WORK WITHIN THE OCCUPIED AREAS SHALL BE


PERFORMED DURING THE WEEKENDS AND SHALL BE
PERFORMED AS FOLLOWS:

1) ALL WORK REQUIRED UNDER THIS CONTRACT SHALL


BE PERFORMED WHILE THE BUILDING IS FULLY
UTILIZED AND OCCUPIED. ALL WORK SHALL BE
PERFORMED SO THAT INCONVENIENCE AND
ADVERSE IMPACT TO THE BUILDING OCCUPANTS
DURING CONSTRUCTION IS MINIMAL.

2) EACH DAY AT THE START OF WORK, THE


CONTRACTOR SHALL PROTECT FURNITURE,
EQUIPMENT, FIXTURES AND APPURTENANCES WITHIN
THE WORK AREA FROM DUST AND DAMAGE.

3) AT THE END OF EACH WORK PERIOD, THE


CONTRACTOR SHALL REMOVE ALL CONSTRUCTION
MATERIALS, EQUIPMENT, TOOLS, ETC., FROM THE
AREA OF WORK, CORRIDORS, OR ANY OTHER AREAS
OF THE BUILDING NOT DESIGNATED BY THE
CONTRACTING OFFICER'S REPRESENTATIVE AS A
STORAGE AREA. THE CONTRACTOR SHALL DUST,
VACUUM AND LEAVE THE AREA, INCLUDING
CIRCULATING CORRIDORS AND ELEVATORS CLEAN,
FREE OF ANY TRASH OR DEBRIS AND DUST.

4) WORK SHALL NOT INTERFERE WITH NORMAL WORK


OF OCCUPANTS EXCEPT TO THE EXTENT DESCRIBED
HEREIN.

3. ELECTRICAL POWER INTERRUPTION:

A. SHUT DOWN OF ANY SYSTEM SHALL BE SCHEDULED AT


LEAST 14 CALENDAR DAYS WITH ADVANCE WRITTEN
NOTICE TO THE BUILDING MANAGER OR THE
CONTRACTING OFFICER'S REPRESENTATIVE.

B. Additional notes

1) Additional notes

a. Additional notes.