Contractor Concessionair
BAR BENDING SCHEDULE FOR PILE
NAME OF WORK : Moradabad - Bareilly expressway project, Reach - 2
LOCATION : MIRGANJ LEVEL CROSSING CHAINAGE: 216+696 STRUCTURE TYPE: ROB
DRAWING REFERENCE NO. : BSEC-ZL-MBRP/216.695/SUB/SD-202 DEPTH: 22.050 mtr. DIA OF PILE: 1.200 mtr.
Regular Pile - 4 & 6 Pile group
Bar Std. Bend Length of Spacing No. of Total Unit
Shape of the Bar Dia Spacing M1 M2 Weight Remarks
no. correction bar Length Bars length Weight)