You are on page 1of 99

TABLE OF CONTENTS 1. 2. INTRODUCTION ...................................................................................................... 8 GENERAL ................................................................................................................ 9 2.1 2.2 2.3 2.4 2.

5
AXES CONVENTION ........................................................................................ 9 DEFINITIONS, DENSITY AND UNITS ................................................................... 9 DEFINITION OF TERMS .................................................................................. 11 ABBREVIATIONS .......................................................................................... 14 GENERAL CONDITIONS ................................................................................. 15

2.5.1 2.5.2 2.5.3 2.5.4 2.5.5 2.5.6 2.6

Design responsibilities ............................................................. 15 Plans and specifications........................................................... 15 Materials, workmanship and Barge care ................................. 16 Weight control ........................................................................... 21 Technical drawings and documents ........................................ 22 Spare parts................................................................................. 23 TESTS AND TRIALS ...................................................................................... 23 2.6.1 General ....................................................................................... 23 2.6.2 Shore tests ................................................................................. 24 2.6.3 Sea trials..................................................................................... 26
CLASSIFICATION ......................................................................................... 27 REGULATIONS, RECOMMENDATIONS AND STANDARDS.................................... 27 FLAG STATE ............................................................................................... 28 CERTIFICATES............................................................................................. 28

3.

CLASSIFICATION, REGULATIONS AND FLAG STATE ..................................... 27 3.1 3.2 3.3 3.4

3.4.1 3.4.2 4. 4.1 4.2 4.3 4.4 4.5 4.6 4.7 5. 5.1 5.2 6. 6.1

Plans, Notices ............................................................................ 29 Registration................................................................................ 29

DESIGN REQUIREMENTS .................................................................................... 30


DESIGN TEMPERATURES .............................................................................. 30 NAVIGATION RANGE .................................................................................... 30 AUTONOMY ................................................................................................. 30 LAUNCH OPERATIONAL CONDITION ............................................................... 30 LOAD OUT OPERATION CONDITIONS .............................................................. 31 TRANSPORT CONDITIONS ............................................................................. 31 DESIGN LOADS............................................................................................ 32

BARGE DESCRIPTION ......................................................................................... 33


MAIN DIMENSIONS ....................................................................................... 33 GENERAL DESCRIPTION ............................................................................... 33

CONSTRUCTION................................................................................................... 36
HULL.......................................................................................................... 36 6.1.1 General ....................................................................................... 36 6.1.2 Main subdivision ....................................................................... 36 Page 3 6.1.3 Material ....................................................................................... 37

STILL IN PROGRESS 1/28/2005 3:26 PM

6.2

6.3

System of construction............................................................. 37 Bilge keels.................................................................................. 37 Skegs .......................................................................................... 38 Shell ............................................................................................ 38 Seawater inlet chests ................................................................ 38 Bulkheads .................................................................................. 38 Tanks .......................................................................................... 39 Main deck ................................................................................... 39 Hawse pipe................................................................................. 39 Built in foundations ................................................................... 40 Local strengthening for jacket protrusion............................... 40 SUPERSTRUCTURES .................................................................................... 40 6.2.1 Barge access ............................................................................. 40 6.2.2 Ventilation deckhouse............................................................... 40 6.2.3 Coamings ................................................................................... 41 HULL EQUIPMENT AND OUTFITTING ............................................................... 41 6.3.1 Barges name, Port of registry and Draught marks................ 41 6.3.2 Watertight doors........................................................................ 42 6.3.3 Masts .......................................................................................... 42 6.3.4 Hatches....................................................................................... 42 6.3.5 Chain locker ............................................................................... 43 6.3.6 Railings and walkways.............................................................. 43 6.3.7 Ladders and stairs..................................................................... 43 6.3.8 Built on foundations.................................................................. 44 6.3.9 Manholes and covers ................................................................ 44 6.3.10 Hoisting beams and lifting eyes............................................... 44 6.3.11 Raised floor................................................................................ 45 6.3.12 Ventilation caps ......................................................................... 45 6.3.13 Bollards and chocks.................................................................. 45 6.3.14 Fendering ................................................................................... 45 6.3.15 Towing appliances .................................................................... 45
GENERAL ................................................................................................... 46 SKIDDING MECHANISM ................................................................................. 46

6.1.4 6.1.5 6.1.6 6.1.7 6.1.8 6.1.9 6.1.10 6.1.11 6.1.12 6.1.13 6.1.14

7.

LAUNCHING AND LOAD OUT SYSTEM .............................................................. 46 7.1 7.2

7.2.1 7.2.2 7.3 7.4 7.5 7.6 7.7 8. 8.1 8.2 8.3

Skidding units............................................................................ 46 Diesel HPU ................................................................................. 47 SKID TRACKS .............................................................................................. 48 ROCKER ARM .............................................................................................. 50 ROCKER LOCKING DEVICES .......................................................................... 50 HINGE POINTS ............................................................................................. 51 ROCKER BUFFERING.................................................................................... 51
GENERAL ................................................................................................... 52 MAIN GENERATOR SETS ............................................................................... 52 AUXILIARY GENERATOR SET ......................................................................... 53
Page 4

POWER GENERATION ......................................................................................... 52

STILL IN PROGRESS 1/28/2005 3:26 PM

9.

BARGE OUTFITTING ............................................................................................ 54 9.1


MOORING ARRANGEMENT ............................................................................ 54

9.1.1 9.1.2 9.1.3 9.1.4 9.2

9.3 10. 11. 10.1 11.1 11.2 11.3 11.4

General ....................................................................................... 54 Temporary mooring................................................................... 54 Quayside mooring ..................................................................... 55 Load out mooring ...................................................................... 55 TOWING ARRANGEMENT .............................................................................. 55 9.2.1 General ....................................................................................... 55 9.2.2 Towing gear ............................................................................... 56 9.2.3 Emergency Towing Gear........................................................... 56 WINDLASS .................................................................................................. 57
GENERAL ................................................................................................... 58

OFFICE, CONTROL ROOM AND SWITCHBOARD ROOM.................................. 58 MARINE SYSTEMS ............................................................................................... 59


GENERAL ................................................................................................... 59 BALLAST SYSTEM ....................................................................................... 59 STRIPPING SYSTEM ..................................................................................... 61 BILGE SYSTEM ............................................................................................ 62

11.5 11.6 11.7

11.8 11.9

11.10 11.11 11.12 11.13

11.14 11.15 11.16

11.4.1 Main bilge system...................................................................... 63 11.4.2 Bilge stripping system .............................................................. 63 11.4.3 Bilge water separator ................................................................ 64 FIRE WATER EXTINGUISHING SYSTEM ............................................................ 64 FIXED CO2 FIRE EXTINGUISHING SYSTEM ........................................................ 65 TANK AIR VENT SYSTEM & SOUNDING PIPES .................................................. 65 11.7.1 Tank air vent system ................................................................. 65 11.7.2 Sounding pipes.......................................................................... 66 POTABLE WATER / HOT WATER..................................................................... 66 SEAWATER/ FRESHWATER COOLING SYSTEMS ............................................... 67 11.9.1 Main diesel generator sets........................................................ 68 11.9.2 Auxiliary diesel generator set................................................... 68 11.9.3 Auxiliaries .................................................................................. 68 COMPRESSED AIR SYSTEM ........................................................................... 69 FUEL OIL SYSTEM ........................................................................................ 70 LUBRICATING OIL SYSTEM ............................................................................ 71 VENTILATION AND AIR CONDITIONING SYSTEMS .............................................. 71 11.13.1 Pump room and pipe tunnel ..................................................... 72 11.13.2 Engine room............................................................................... 72 11.13.3 CO2-room.................................................................................... 72 11.13.4 Spare parts room ....................................................................... 72 11.13.5 Control room and office ............................................................ 73 GREY WATER SYSTEM.................................................................................. 73 DIESEL ENGINE EXHAUST GAS LINES ............................................................. 74 PIPING AND VALVE SPECIFICATION ................................................................ 74
Page 5

STILL IN PROGRESS 1/28/2005 3:26 PM

12.

SAFETY SYSTEMS ............................................................................................... 75 12.1


FIRE FIGHTING EQUIPMENT ........................................................................... 75

12.1.1 12.1.2 12.1.3 12.1.4 12.2 12.3 12.4 13. 13.1 13.2

Fixed CO2 system ...................................................................... 75 Loose equipment ....................................................................... 75 Deck wash .................................................................................. 75 Insulation.................................................................................... 75 FIRE DETECTION SYSTEM ............................................................................. 75 FIRE AND GENERAL ALARM SYSTEM .............................................................. 76 LIFE SAVING EQUIPMENT .............................................................................. 76
GENERAL ................................................................................................... 78 SWITCHBOARD/ MCC ................................................................................... 78

ELECTRICAL SYSTEM ......................................................................................... 78

13.3 13.4 13.5 13.6 13.7

13.8 13.9 13.10

13.11 14. 14.1 14.2

13.2.1 Switchboard S-C4101 ................................................................ 78 13.2.2 Distribution Panel S-C4601....................................................... 79 TRANSFORMERS ......................................................................................... 79 380V AC MOTORS ..................................................................................... 79 AC MOTOR STARTERS ................................................................................ 80 CABLES ..................................................................................................... 80 LIGHTING AND SMALL POWER ....................................................................... 81 13.7.1 Lighting ...................................................................................... 81 13.7.2 Emergency lighting ................................................................... 81 13.7.3 Navigation lighting .................................................................... 81 13.7.4 Small power ............................................................................... 82 BATTERY SYSTEM ....................................................................................... 82 SHORE SUPPLY ........................................................................................... 82 CONTROL AND ALARM SYSTEMS ................................................................... 83 13.10.1 General ....................................................................................... 83 13.10.2 Alarm & Monitoring System...................................................... 83 13.10.3 Control System .......................................................................... 83 INTERNAL COMMUNICATION EQUIPMENT........................................................ 84
GENERAL ................................................................................................... 85 PAINT SYSTEM ............................................................................................ 85

PRESERVATION SYSTEM.................................................................................... 85

14.2.1 General ....................................................................................... 85 14.2.2 Surface preparation................................................................... 85 14.2.3 Under water part (Bottom and side shell up to 5 meter waterline) ................................................................................................ 85 14.2.4 Side shell above water (from 5 meter waterline) and rocker arm 86 14.2.5 Decks; exposed and interior..................................................... 86 14.2.6 Walls and underside decks; pump rooms, engine room and pipe tunnel segments ............................................................................ 86 14.2.7 Tanks .......................................................................................... 86 14.2.8 Ballast Tanks ............................................................................. 86 Page 6

STILL IN PROGRESS 1/28/2005 3:26 PM

14.3 14.4 14.5 14.6 15. 15.1 15.2

14.2.9 Void spaces................................................................................ 86 14.2.10 Office, control room and switchboard room ........................... 86 14.2.11 Outfitting .................................................................................... 86 14.2.12 Miscellaneous steel ................................................................... 87 INSPECTION AND TESTING ............................................................................ 87 GALVANIZING .............................................................................................. 87 INTERNAL CATHODIC PROTECTION ................................................................ 88 EXTERNAL CATHODIC PROTECTION ............................................................... 88
MAINTENANCE EQUIPMENT ........................................................................... 89 HOISTING EQUIPMENT .................................................................................. 89

BARGE MAINTENANCE ....................................................................................... 89

LIST OF APPENDICES APPENDIX I APPENDIX II APPENDIX III DOCUMENT LIST OWNER FURNISHED EQUIPMENT LIST VENDOR LIST

Page 7

STILL IN PROGRESS 1/28/2005 3:26 PM

1.

INTRODUCTION A has requested B to perform a concept and a basic design for a steel jacket launch barge. The barge will be designed as an unmanned, non-propelled steel deck barge for launching jackets up to 30,000 t. Load out and launching operations will be performed in the X area. In addition to launching operations the barge will be used as transportation barge for miscellaneous items, such as topsides and process equipment. It is the intention of this specification to provide a description, covering the design and technical requirements for the building, outfitting, testing and delivery of the Barge. The specified data shall be verified by the Yard during the Detailed Design Stage. Reference is made to drawing 0240 DNC 01 001 Barge General Arrangement Plan.

Page 8

STILL IN PROGRESS 1/28/2005 3:26 PM

2. 2.1

GENERAL AXES CONVENTION The axes convention used in the project is presented in Figure 2.1.

z y

x
PS

x
SB

Figure 2.1 axes convention The origin of the system is as follows: at APP: X positive to bow at CL : Y positive to PS at BL : Z positive upwards 2.2 DEFINITIONS, DENSITY AND UNITS The units as used in this document are summarized in Table 2.1. Table 2.1 definitions and units unit description kn knot

definition SI 0.514

m/s

Table 2.2 density description Seawater Lubrication Oil Marine Gas Oil

definition 1.025 0.90 0.89

t/m3 t/m3 t/m3

Page 9

STILL IN PROGRESS 1/28/2005 3:26 PM

The SI metric system shall be used as the primary means to describe physical quantities. Common commercial designations, when used in a descriptive manner not involving calculations, may be expressed in the customary units. The following SI units, SI derived units and permissible non-SI units should be used in all drawings, specifications, etc. Length Time meter millimeter second minute hour day year degree Celsius cubic meter liter square meter kilogram metric ton (1,000 kg) radian degree minute second meters per second Watt radians per second meters per square second Newton kilogram meter per square second load per unit length bar Pascal Stress deck load per square meter kilogram per cubic meter metric ton per cubic meter cubic meter per kilogram cubic meter per second cubic meter per minute cubic meter per hour Ampere Volt VoltAmpere Herz meter water column m mm s min h d y C m3 l m kg t rad or deg ' " m/s W rad/s m/s N kgm/s t/ m bar Pa N/mm2 t/ m2 kg/m3 t/ m3 m3/kg m3/s m3/min m3/h A V VA Hz mWc
Page 10

Temperature Volume Area Mass Plane angle

Speed (velocity) Power Angular velocity Acceleration Force Pressure

Density Specific volume Rate of flow Electric current Electric voltage Electric power Frequency Suction head

STILL IN PROGRESS 1/28/2005 3:26 PM

2.3

DEFINITION OF TERMS The following terms appearing in this specification shall be understood as stated here after: Barge: The unmanned, non self-propelled launch barge, of which the design, technical requirements and construction details are defined in this specification and the accompanying plans.

Design: The present specifications and accompanying plans and documents representing this design. The design shall be approved by Classification Society, China Classification Society. Basic Design: Preparation of specifications and plans/drawings outlining the design and in sufficient detail to gain Class Approval. In terms of structural plans, for example, this relates to determination of the main scantlings. Detailed Design: Development of Basic Design into specifications, plans/ drawings that are Class approved enabling production of Barge. In terms of structural plans, for example, this relates to the development of fabrication shop drawings. Yard: The company (Shipyard) to whom the building contract shall be awarded and who shall have responsibility for detailed design, construction, procurement, outfitting, testing and delivery of Barge, including all subcontracted work. Subcontractor: Any person or company engaged by Yard or a Subcontractor of any tier to execute a part of the work on behalf of Yard including any nominated, designated, named or preferred Subcontractor or supplier. Including those companies providing the Owner Furnished Equipment (OFE).

Page 11

STILL IN PROGRESS 1/28/2005 3:26 PM

Class: The Bureau under whose Rules, Regulations and Inspection the Barge shall be constructed and fitted out namely: CHINA CLASSIFICATION SOCIETY (CCS). Use of the word Class in this document implies the mentioned Classification Society. Authorities: The Shipping Inspection Bureau of the Country of Registry under whose Laws and Regulations Barge shall be registered, namely: CHINA CLASSIFICATION SOCIETY (CCS). Inspector: (Owner's Representative): Any person or persons or organization designated by Owner and to whom the authority and responsibility have been given to represent Owner in dealing with Yard for the purpose of fulfillment of the building contract. Manufacturer/Vendor: Vendor is any firm or agent who manufactures or sells various materials, equipment and/or services used for the purpose of fulfillment of the building contract. Owners Furnished Equipment (OFE): OFE are all materials, equipment or services that will be supplied by Owner to Yard. OFE is listed in "Owner Furnished Equipment List, Appendix II of this specification, which will be part of the building contract. All items not mentioned in the list, but necessary for the proper functioning of Barge, will be provided by Yard. Install: Where the term "install" is used in relation to any material, equipment or coating, it will mean that those materials, equipment or coatings will be received, checked, stored, insured, handled, mounted on Barge and connected and tested by Yard, regardless whether the mentioned materials or equipment are supplied by Owner or by Yard. Installation shall specifically take into account: (but not limited to) Configuration, weight, dynamic loading of the materials or equipment Recommendations from Manufacturer Access for operation and maintenance Provision of Services, e.g., Ventilation, heating, cooling if required Power supply, drainage etc. as required.

Page 12

STILL IN PROGRESS 1/28/2005 3:26 PM

Provide or Supply: Where the term "provide" or supply is used in relation to any materials or equipment, it will mean that those materials or equipment will be delivered by Yard, except for OFE (as listed in Appendix II), and installed in accordance with the fore-mentioned definition. Use of this term also applies to resources as far as necessary to comply with Yard's obligations. Foundation: Where the term "foundation" is used, in relation to any equipment to be installed in Barge, it will mean that Yard shall design, provide and install the necessary material to properly seat the equipment in Barge, including all and any work needed to transfer the static and dynamic loads into Barges structure and comply with the requirements of vibration suppression and equipment manufacturers. Main Deck: Where the term main deck is used it shall refer to the continuous deck at 14.25 m above base line and assigned as the freeboard deck. ITT Invitation To Tender issued by Owner.

Page 13

STILL IN PROGRESS 1/28/2005 3:26 PM

2.4

ABBREVIATIONS ABS APP BL BOJ CR CCS CL COG DNV ER FPP GA HPU JLB LCG LSW MBL MCR MGO MOU NDT OFE PA PS PPM RPM SB SWL TCG TOJ UPS VCG WB American Bureau of Shipping Aft Perpendicular Baseline Bottom of Jacket Control Room China Classification Society Centerline Center of Gravity Det Norske Veritas Engine Room Forward Perpendicular General Arrangement Hydraulic Power Unit (or Pack) Jacket Launch Barge Longitudinal Center of Gravity Lightship Weight Maximum Breaking Load Maximum Continuous Rating Marine Gas Oil Mobile Offshore Unit Non Destructive Testing Owner Furnished Equipment Public Address Portside Parts per million Revolutions Per Minute Starboard Safe Working Load Transverse Center of Gravity Top of Jacket Uninterrupted Power Supply Vertical Center of Gravity Water Ballast

Page 14

STILL IN PROGRESS 1/28/2005 3:26 PM

2.5 2.5.1

GENERAL CONDITIONS Design responsibilities The selected Yard shall have full responsibility for the Barge and its performance.

2.5.2

Plans and specifications Plans and documents associated with this specification are listed in Appendix I. It shall be Yard's obligation to verify that construction, materials and equipment purchased by Yard will be compatible with the design embodied in these plans and specifications. If this is not the case, the plans and/or specifications are to be changed at Yard's cost and Yard is to obtain Class approval, if necessary. In case of discrepancy between technical documents Yard shall notify Owner in writing for interpretation and direction. Yard shall develop and is responsible to develop the Detailed Design on the basis of Basic Design supplied by Owner: Owner will supply plans and documents approved by Class corresponding to Basic Design. It shall be Yard's obligation to follow the Rules and Regulations listed in this Specification. In case of conflict between applicable Rules, Regulations and Conventions and Basic Design as submitted by Owner, Yard shall notify Owner in writing. The conflict will be treated in accordance with the Contract, and Yard shall accordingly supply the equipment and/or systems as derived from detailed engineering. Should any part of the technical documents be in error or in conflict with any applicable rule or regulation, it shall be Yard's obligation to follow the concerning Rules and Regulations after notifying Owner in writing. In case the technical documents have identified functional requirements, but some items or provisions have not been mentioned explicitly, it is Yard's responsibility to identify and supply these missing items and/or provisions at expense of Yard. If some items are specified several times in the specifications they shall only be provided in the quantity as needed. When and where special manufacture or trade names are mentioned it is understood that Yard has the option to use equivalent equipment, but not before written approval has been obtained from Owner, on any proposed alternative.

Page 15

STILL IN PROGRESS 1/28/2005 3:26 PM

2.5.3

Materials, workmanship and Barge care Yard binds himself to execute all the work according to the best practice of his industry to meet Contract requirements using the best method to ensure that Barge will be conform to the intended design. Maintenance of high standards of workmanship is also Yard's responsibility. Yard shall be responsible for the performance of the Contract. Yard will do so in accordance with the intent of these specifications, including associated plans, despite any mistake, omission, discrepancy or lack of clarity in these specifications which should reasonably be apparent to an experienced Yard, upon a careful and critical study. This will also include those parts, which have not or can not be clarified by Owner at Yard's request prior to the starting of Contract. Yard shall be fully responsible for the Barge from signing of contract to final delivery upon satisfactory completion of all work, which forms part of this contract. Whilst in the hands of Yard Barges hull is to be earthed to a suitable point ashore, whether docked or afloat. Yard will be responsible for the safe shifting, anchoring, mooring and docking of Barge and the supply of all the necessary facilities, services and equipment. Any associated cost will be to Yards account as part of the tendered Lump Sum Price. Equipment and Materials Any license-built equipment shall conform to the original, including the latest improvements transferred by the original manufacturer at the starting date of the building contract. Yard shall fulfill all responsibilities of any nature relating to the licenses, patents and rights covering Barge design, construction and equipment (restricted to Yard's supply). Any machinery or equipment will be of standard-produced type, unless otherwise specified. Before ordering any major item, material, machinery or equipment, Yard shall forward to Owner a written purchase specification for approval. Owner will return such specification as detailed in 2.5.2, bearing Owner's approval and/or remarks. Failing this, Yard may consider the Specification to be approved and place a purchase order after notifying Owner. In any case, one copy of each purchase order without price shall be submitted to Owner for his information. Materials, fittings, furnishing equipment and outfit shall be new, undamaged and of first class marine offshore industrial quality as far as applicable.

Page 16

STILL IN PROGRESS 1/28/2005 3:26 PM

All structural steel used for construction of Barge and machinery, including possible forgings and castings, shall be of shipbuilding and marine engineering quality, tested, inspected and certified as and when required by Classification Society and shall be physically and chemically in conformity with such requirements. All steel shall be free from cracks, lamination and similar defects. All structural steel plate and sections will be shot blasted and shop primed prior to any fabrication. Timber shall be well seasoned, pressure impregnated, dried and reasonably free from knots. All materials used in construction of Barge shall be acceptable to Inspector, Class or any other prevailing regulation. Asbestos shall not be used. All equipment and major components shall carry permanent identification stamped-in, cast-on or engraved plate, showing manufacturer's name or trade name, model, serial number, size and type rating. Where this identification is obscured Yard shall supply additional engraved plates of a standard design repeating this information, and permanently affix these plates in a clearly visible location. Yard shall also permanently affix instruction plates engraved in both Chinese and English in all cases where original instruction plates have been obscured, have a text other than Chinese or English, have been omitted or give inadequate instruction for the service intended. In addition safety notices and notices pertaining to the well being of the crew must be provided in both Chinese and English text. Instruments, gauges and metering devices must be supplied with all components calibrated in metric SI units. Bolts, studs, nuts, capnuts, pins, hingepins, screws, hooks, etc. subject to corrosion, sticking or freezing in damp or exposed locations, shall be of stainless steel of a quality compatible with service conditions except where specifications state otherwise. Exposed threads from studded bolts shall be protected with capnuts to prevent damage to the threads. Square threads may be approved for transport screws, but Whitworth threads shall not be used in any part of the construction. Stainless steel fittings, if fitted, shall be electrically isolated from steel parts. Isolation shall be achieved by means of nylon strips or equivalent fitted between faces, nylon ferrules between rivets or bolts, to Inspector's approval.
Page 17

STILL IN PROGRESS 1/28/2005 3:26 PM

Yard shall keep records of type, serial number and/or other identification of all material, equipment and component parts which shall be used in the construction or outfitting of Barge as part of Yard's contractual obligations. Where Yard specifies equipment, proof of after sales spares and service facilities must be submitted to Owner for approval. This also applies to equipment items, which are offered as alternatives to those quoted within this specification as being Owners preferred supply. Cleaning and preservation Yard is to operate a clean ship policy. This assumes a state of general cleanliness will be maintained on decks and in internal compartments, including those that are to be permanently covered or which may become inaccessible. Rubbish and debris from work in hand are to be regularly removed. Oil or other liquid spillages shall be dealt with promptly in an approved manner. Yard shall ensure machinery, equipment, assemblies, sub-assemblies, components, pipe work and tanks are cleaned and preserved as appropriate during all stages of manufacture, storage and trials until delivery to Owner. Main and auxiliary engines, electrical and electronic equipment shall be protected in the period between shop tests and sea trials by vapor phase inhibitors or other method of inhibiting corrosion approved by manufacturers, Owner and engine manufacturer. Machinery compartments and bilges shall be cleaned prior to sea trials and prior to delivery. Barge is to be thoroughly cleaned to the satisfaction of Owner of all dirt and debris prior to delivery to Owner. Yard will also bear the cost of the extermination of any insect or rodent infestation on completion of Contract. Care is to be taken that no mechanical damage occurs to grit blasted areas on weather decks, when moving machinery or equipment. Prior to any grit blasting taking place, Yard is to ensure that the area and its surroundings are free from flammable vapors or gases which may be ignited by sparks generated by the blasting process. Protection All vulnerable equipment, such as winches and hydraulic rams, and adjacent surfaces not subject to blasting, are to be protected from damage and the ingress of grit and blast debris.
Page 18

STILL IN PROGRESS 1/28/2005 3:26 PM

In general special attention shall be given to protect equipment against sand ingress e.g. when sealings are considered. Yard shall undertake precautions to protect all finished flooring, sheeting, control boards, cables, piping with valves, instruments and other exposed equipment against damage. During cold and/or wet weather and high humidity, Yard shall provide suitable protection, heating and ventilation as required to prevent deterioration of equipment and component parts. All materials intended for or allocated to the building of the Barge shall be properly stored and protected from the environment, immediately upon arrival at Yard's site. Safety precautions It is the responsibility of Yard to have an effective safety organization. Yard's safety representative(s) must liaise and discuss with Owners representative at a properly convened meeting as soon as possible before work commences at Yards works and draw up an agreed and clear ship/shore emergency plan. Suitable Barge and tank access procedures to be established and agreed by Owner and Yard. Maintenance of watertight integrity and maintenance of safe moorings is the responsibility of Yard throughout Contract period. For any hot work (whether gas free or not) Yard is to provide a fire watch with the necessary instructions and equipment to prevent the outbreak of fire and to contain any resultant combustion. On completion of work the fire watch is to remain at the work site long enough to ensure that the area has reduced to a safe temperature. Yard is responsible for the safe isolation and connection of fluid and electrical systems. This is to be achieved using lock off or tag out system to ensure that the isolation and de-isolation of systems is under positive control. Yard is to take all necessary precautions to prevent contamination of any spaces, pipe lines, pumps or other equipment by any liquids or gases that might be contained anywhere on the Barge. Yard is to restore at its own expense any space and all equipment contained therein to its original condition should any contamination occur. No transfers of fuel or water ballast will be performed during the building period without discussion and agreement between Yard and Owner. Fuel or water ballast shall not be transferred by means of any of Barges pumps, systems or pipelines while hot work is being performed on the deck, on the shell or internally in way of fuel oil tanks. If fuel or ballast is transferred within Barge then all Page 19 relevant

STILL IN PROGRESS 1/28/2005 3:26 PM

tanks and systems shall be restored to a certified gas free condition prior to work in them or adjacent to them being recommenced. It shall be the responsibility of Yard to maintain all certified gas free spaces in a gas free condition. It shall be the responsibility of Yard to organize and undertake the safe and environmentally acceptable removal of all redundant materials from Barge in accordance with all the applicable rules and regulations. Welding All welding shall at least be in accordance with the requirements of Class. Welding shall be performed only by personnel who have successfully passed Class qualification tests for the type of welding they will be doing and have been regularly employed on such work for a minimum period of six months. Individual operator's certificates shall be made available by Yard for inspection and approval by Owner. It shall be Owner's prerogative to request the removal from the work of any welder that is not producing work of the required quality in Owner or Class opinion. All welding shall be double continuous fillet in all areas unless noted otherwise and shall include all void spaces adjacent to the sea. Full penetration or partial penetration welds are to be provided where required and in accordance with Designer or Class requirements. For all manual and machine welding, only electrodes on the "Approved Electrodes" listing, as issued by Class, and suitable for the particular application intended shall be used. A planned program of NDT shall be carried out at Yard's expense and the results made available to Owner for approval. The program for NDT shall be approved by Owner and be in compliance with Class Standards. Additional NDT testing is required for all high stress areas. In addition to Class requirements, pipe work fabrication/inspection shall be in accordance with Owners pipe work specifications. Yard shall submit to Owner details of proposed welding sequences and procedures for approval. Special attention shall be paid to minimization of distortion and residual stresses due to welding. All plate edge preparation shall be in accordance with Class requirements and all materials shall be free from rust, grease, slag or other harmful material at the weld joint. Proper precautions shall be taken to ensure that all welding is carried out under Page 20 conditions where the welding site is protected against the detoriating effects of

STILL IN PROGRESS 1/28/2005 3:26 PM

moisture, wind and severe cold. Yard will be expected to use the appropriate welding materials and welding procedures to match the steel to be welded. Pre-heat, post-heat or special grade of steel requirements for any part of Barge structure, shall be strictly complied with by Yard throughout the work. Operators of automatic welding machines shall have available for inspection by Owner a valid welding procedure for all plate thickness being assembled. Manual welding shall be down-hand welding where possible and sections shall be turned accordingly. All welding showing excessive irregularity, excessive convexity or concavity, "endcraters" or other defects out with acceptance criteria shall be rejected and shall be corrected in a satisfactory manner to Yard's account. Yard shall provide an adequate number of trained and qualified welding supervisors so that welding operations can be properly surveyed at all times, including night work. Lugs temporarily welded for positioning or mounting of permanent parts shall be carefully removed by flame cutting or gouging, re-welding if necessary and flush grinding followed by appropriate NDT to verify soundness of affected area. Exposed parts of finished products or installed equipment shall be adequately protected from damage. 2.5.4 Weight control Yard shall set up a procedure for weight control for approval by Owner so that at the latest 45 days after acceptance of tender by Owner, Yard will be able to provide an estimate of Barges lightship weight and Center of Gravity (COG). For this Yard shall receive from Owner a list of weights of Owner Furnished Equipment. The first weight estimates shall be compared with the result of the Basic Engineering and will be used as reference for the execution of the project. During the construction of Barge, Yard will update the weight control and COG continuously for: Installed equipment, systems and structure to Barge Installed steel sections, blocks and outfitting Design changes, if any Yard shall issue a monthly report of the lightship weight and COG. In case of a significant shift in lightweight or COG from reference values, Yard shall notify Page 21 Owner immediately.

STILL IN PROGRESS 1/28/2005 3:26 PM

Weight control will end with deadweight survey and an inclining experiment to confirm lightship weight and COG, as per section 2.6. 2.5.5 Technical drawings and documents Before construction commences, all drawings and/or calculations according to agreed list are to be submitted to Owner for approval. Number of drawings should be 5 copies (2 to site office and 3 for forwarding to Owner). Owner shall return one of every received drawing and/or calculation within 14 days from date of receipt (a maximum of 10 working days). Yard will incorporate all remarks on the drawings made by Owner prior to commencement of the work. All changes in construction or equipment as a result of Owner's remarks are to be carried out when received within the 14 days limitation as stated above. Yard at no expense to Owner will manage all drawings and/or calculations and documents, which require approval from CCS or a Regulatory Authority. Approval from Owner will not relieve Yard from the responsibility to satisfy any Regulatory Authority or Class, unless specifically agreed upon. Documentation standard to be equivalent to that for Mobile Offshore Unit (IMO MOU Code 89). Yard shall supply six (6) hard copies and one set of diskettes, CD or any other data carrier to be agreed between Owner and Yard of all drawings of Barge "asbuilt", to Owner. Six (6) complete sets of documentation and instruction books covering all Yardsupplied equipment shall be handed over to Owner on delivery of the Barge. Furthermore a complete list of all supplied equipment and machinery items of the Barge, including recommended lists of spare parts for 2-years of operation and all piping installed in Barge shall be handed over in triplicate as well. A preliminary stability booklet, complying with all the requirements to the approval of all relevant regulatory bodies, is to be submitted in triplicate by Yard to Owner for their approval, at least three months before delivery of Barge. Results of the inclination experiment are to be included in the comprehensive trim and stability booklet, complying with all the requirements to the approval of all relevant Regulatory Bodies, for use by ship's officers with two copies for Owner.

Page 22

STILL IN PROGRESS 1/28/2005 3:26 PM

Yard shall prepare an Operation Manual for Marine Equipment and Operations parts thereof in accordance with MOU CODE 89 including maintenance guide and shall incorporate Owner's part for any OFE in the deliverance of a comprehensive Operation Manual for submission to Class for approval. The Yard shall provide six (6) hard copies plus one (1) electronic copy to Owner on delivery. 2.5.6 Spare parts Spare parts and maintenance tools based on Manufacturer's recommendations and as recommended by Class and as agreed with Owners will be supplied by Yard. In addition Yard shall supply to Owner, manufacturer's recommended spare parts lists for 2 years of continuous operations in due time to ensure the delivery of such parts prior to Barge delivery. All spare parts shall be properly protected against physical decay, corrosion and mechanical damage. They shall be clearly marked and adequately identified so that replacements can be ordered without difficulty. Yard shall complete storage spaces on Barge in time to enable the positioning, labeling and listing of all spare parts (Yard- and Owner-supplied) prior to Barge delivery. Yard shall be responsible for handling and storage aboard Barge of all spare parts and all tools furnished by Owner as well as pieces and supplies. Yard shall transfer any spares and tools received with equipment ordered by Yard to Owner. 2.6 2.6.1 TESTS AND TRIALS General Before Barge delivery to Owner all work performed by Yard shall be thoroughly tried out and tested to the satisfaction of Owner, Class and other regulatory bodies. If any of the tests and trials does not demonstrate proper working and compliance with the specifications to the satisfaction of Owner and/or Class, the tests and trials shall be re-run at no additional cost to Owner until proper working and compliance with the specifications is obtained to the satisfaction of above mentioned parties. Before conducting a test Yard shall give a minimum of 48 hours notice in writing to Owner of the time, date and place and type of test. If the test is delayed by Yard then the test will be required to be re-scheduled with the required 48 hour notice.
Page 23 Owner shall have the right to inspect or witness the testing of any part of the work

STILL IN PROGRESS 1/28/2005 3:26 PM

under Contract at any place where materials or part of the work is located or in preparation. Yard shall keep a record of all tests and trials, whether performed by him or by Manufacturer's representative, and shall be responsible for recording all data such as temperatures, pressures, etc. at all stages. Yard shall obtain from manufacturers all readings and data of various tests performed prior to installation, and these shall be forwarded to Owner. Yard shall forward the following test results to Owner: a. Manufacturer's test reports of all engines and machinery carried out before installation b. Reports of all results obtained during shore trials c. Reports of all results obtained during sea trials Yard shall prepare a comprehensive program for tests and trials and submit it to Owner and CCS for approval, one month before the planned start of the tests and trials. Yard shall prepare a specification and planning for incorporation of tests and commissioning of both OFE and Yard furnished equipment. Machinery and equipment tests shall be conducted at full load where practicable and these tests shall include OFE. Before Barge is delivered to Owner the following tests and trials shall take place: Shore tests Sea trials Yard shall be responsible for the preparation and fulfillment of the shore tests and sea trials. All materials, labor, tools, instruments, services, fuel, oils, glycol etc, as may be necessary to conduct these tests and trials, shall be furnished by Yard without charge to the Owner. All tests and trials including the tests of Owners Furnished Equipment to be for Yards account, unless otherwise specified. 2.6.2 Shore tests All work accomplished under this Specification including Barge main structure, main machinery, auxiliary machinery, piping, electrical, automation/control, ventilation and other systems shall be thoroughly tested during shore tests in order to demonstrate proper workmanship and suitability for the intended service in accordance with CCS Class requirement and as stated elsewhere. Testing program shall involve at least, but not limited to, the following tests:
Page 24

STILL IN PROGRESS 1/28/2005 3:26 PM

NDT testing of all welded structures, repairs or modifications and pressure piping in accordance with requirements and the Owner Piping Specification. X-ray tests of important welded seams (Owner and/or his supervisor can require up to 100 photos in excess to those required by Classification Society) Hydrostatic testing of all tanks, cofferdams, piping systems etc Operational tests for doors, access hatches, anchor winch, retrieval winch, ventilator enclosures, capstans and flaps Operational tests for all watertight closures and transits Operational tests for fire water and CO2 systems Operational and load test diesel generator units Operational tests for all control and alarm systems Operational tests for all piping systems Operational tests for valve remote control panel, emergency stop and closing plant Operational test of remote tank level indication plant Operational test of ventilation and noise level protocol Operational tests for water- and electrical heating systems, incl. lay-up condition Protocol of electro magnetic disturbance measurements Protocol of air gap measurements in generators after installation Operational tests for the whole electric plant including tests with parallel running generator, reverse power, under voltage, overspeed, etc. Operational tests for skidding systems Operational tests for the ballasting and shipping systems Shore supply

Where all these tests cannot be successfully completed in harbor due to physical limitations, then the tests are to be performed during sea trials and shall be added to those described in section 2.6.3. All tanks forming an integral part of the hull shall be tested by water pressure in accordance with the requirements of Class. Adjacent compartments shall not be tested simultaneously. The ballast system shall be used during the ballast tests to demonstrate satisfactory operation. All piping will be pressure tested. Pipes for lubricating oil, fuel oil, hydraulic oils, water and air, will be cleaned according to Manufacturers and/or Owners requirements and yard standard for pre and post pressure testing. All pipeline systems and associated valves, and ventilation systems to be fully tested. The electrical system will be tested for several loading conditions including single and parallel running of the generators. 100% load and overload will be tested to the satisfaction of Class. Before testing the total electric plant will be megger tested and figures will be presented to Owner.
Page 25

STILL IN PROGRESS 1/28/2005 3:26 PM

During the shore tests, when Barge is essentially complete, an inclining experiment shall be conducted at the minimum possible draft in accordance with the regulatory bodies' rules to establish Barges LSW and COG. 2.6.3 Sea trials When Barge is near delivery and is suitably equipped, sea trials shall be conducted to fulfill Class, regulatory bodies' and Owner's requirements. Yard is to prepare a loading condition and a sea trial program, which is to be submitted to Owner for their approval. In addition to the standard tests, required by Class and Flag State, Owner will require at least the following tests to be carried out in deep water. Anchoring test Machinery control tests including test for unmanned machinery Ballasting sequences Fuel consumption will during all trials be recorded as a function of produced power and as a function of time during the trials. This to enable Owner to determine fuel consumption on a daily basis. Yard shall submit to Owner and Class the proposed location for the sea trials for approval.

Page 26

STILL IN PROGRESS 1/28/2005 3:26 PM

3. 3.1

CLASSIFICATION, REGULATIONS AND FLAG STATE CLASSIFICATION Vessel including machinery, equipment and outfitting will be constructed under supervision of China Classification Society to obtain class notation. The barge will be classed as an unmanned, non self propelled, steel deck barge. In addition to the CCS Rules, the JLB will comply with applicable ABS Rule requirements. The class notation of the barge will be:

CSA 5/5 (LAUNCH) BARGE Ice Class B

3.2

REGULATIONS, RECOMMENDATIONS AND STANDARDS The following Rules and Regulations will be included, but not limited to: CCS Rules and Regulations for the Construction and Classification of Sea Going Ships 2001 Hull Volume 2, Part 2 Chapter 1 to chapter 4 and chapter 12 (Shell plating according chapter 2) Machinery Volume 3, Part 3 Electrical Volume 4, Part 4 Technical Regulations for Statutory Survey of Ships and Installations Non International Voyage Ships Life-saving equipment: Chapter 2, Part 4, Section 2.14(2) Stability during Launching: Chapter 7, Part 4, Section 1,2 & 3.10 ABS Rules for Building and Classing Steel Barges 2003 ABS Rules for Mobile Offshore Drilling Units for direct structural calculations CCS Guidelines for direct analysis of oil tankers January 2003 section 9, for (buckling) strength of bulkheads and decks DNV Classification note 30.1 Buckling strength analysis 1995 The International Convention on Load Lines 1966, revised by the protocol of 1988, consolidated edition 2002 International Convention on Tonnage Measurements 1967/1969 International Convention of the Prevention of Collisions at Sea 1972 incl. amendments International Convention for the Safety of Life at Sea SOLAS 1974, Protocol of 1988 including 2000 Amendments Guidelines for Safe Ocean Towing MSC/ Circ. 884 21 December 1998 Technical Regulations for statutory survey of Ocean Towing 1999, promulgated by the Register of Shipping of Peoples Republic of China
Page 27

STILL IN PROGRESS 1/28/2005 3:26 PM

3.3

International Convention of the Prevention of Pollution from Ships (MARPOL) 73/78, Consolidated Edition, IMO 1997 IMO Regulations (not limited to) IMO Resolution A.468 - XII Noise Control IMO Resolution A.749(18) Intact Stability, Pontoon Barge International Electronical Commission (IEC), Electrical Installation in Ship, Publication no. 92 IACS Recommendation 47 Shipbuilding Repair and Quality Standard ANSI Standard

FLAG STATE The flag state of the JLB will be the Peoples Republic of China.

3.4

CERTIFICATES The following certificates or provisional certificates and protocols shall be furnished at delivery of Barge: To be issued by Class / Flag Authorities and/or Regulatory Bodies (Yard to include price in Lump Sum tendered): 1. Classification certificate of Barge 2. Safety construction certificate 3. Load line certificate 4. International tonnage certificate 5. Stability compliance certificate 6. Safety equipment certificate 7. Oil record book 8. International oil pollution prevention certificate 9. Fitness for towing certificate To be issued by Yard's Vendors (for Yard's supplied equipment only): 1. Certificates of pressure Vessels, incl. relief valves, hull valves, fuel tankvalves and other as required by CCS 2. Explosion proof equipment certificates or industrial safety certificates 3. Navigation equipment certificates (compasses and lanterns) 4. Safety and marine equipment certificates 5. Towing, anchoring and mooring equipment certificates 6. Certificates of materials used in hull construction

Page 28

STILL IN PROGRESS 1/28/2005 3:26 PM

To be issued by Yard: 1. Yard's certificate of Barge 2. Protocol of delivery and acceptance 3. Protocols of tests and trials 4. Declaration of warranty 5. As-built plans, data and calculations 6. Operation manual (including lay-up and start-up instructions) 7. Inclining test report 8. Trim and stability booklet 9. Noise and vibration report 10. Safety Information and Instruction Notices 11. De-rat certificate 3.4.1 Plans, Notices Yard to provide capsulated plans for bulkhead mounting of the following plans according to Regulatory requirements : General Arrangement Fire Fighting and Safety Tank and Capacity Plan and Sounding Tables (including corrections for heel and trim) Yard to provide safety signs, notices and exit markings in accordance with Regulatory requirements.

These are all to be in the English and Chinese language. 3.4.2 Registration Registration will be dealt with by the Owner, but Yard shall provide all necessary assistance to Owner to obtain the maximum reduction for net and gross registers tonnage including deduction for permanent ballast spaces. The registered tonnage shall be engraved on the main deck.

Page 29

STILL IN PROGRESS 1/28/2005 3:26 PM

4. 4.1

DESIGN REQUIREMENTS DESIGN TEMPERATURES Ambient temperatures Water temperature Humidity -20C +45C -2C +30C 55% Relative Humidity @45C

The mechanical ventilation systems shall be designed for an outside air inlet temperature of +40C. 4.2 NAVIGATION RANGE Navigation range of the barge for transport will be unrestricted ocean service. 4.3 AUTONOMY The barge tank capacities will be suitable for a normal load out, transport and launch operation of 60 days. Tank layout will ensure power functionality for trim angles up to 10 deg by stern. 4.4 LAUNCH OPERATIONAL CONDITION The maximum (environmental) launch condition data is: Maximum jacket weight 30,000 t Maximum 30,000 t jacket VCG 33.4 m Minimum 30,000 t jacket Length 200 m Wind speed (Vw) (Surface) Current speed (Vc) 13.8 2.0 m/s kn

Associated waves: Significant wave height (Hs) Peak Period (Tp) Maximum scantling draught Maximum trim (incidental) Maximum trim (operational)

2.1 m 8.0 - 9.0 s 38.0 12.0 10.0 m at APP deg deg

The barge shall be positioned with the bow into the waves during launching operation.

Page 30

STILL IN PROGRESS 1/28/2005 3:26 PM

4.5

LOAD OUT OPERATION CONDITIONS The load out operation is limited by the following data, based on enlarged skid track height at the different quays to 3,500 mm and a JLB skid track height of 2,000 mm above main deck The following limits are applicable: Minimum water depth in a tide cycle Maximum distance quayside skid track to water level Maximum Draught Scantling Draught Allowable tide variation Maximum tide variation speed 4.7 12.3 11.75 12.25 7.1 1.0 m m m m m m/h

With the dimensions of the barge determined in the Concept Design and the above limits load out will be feasible at the two intended load out yards with the enlarged skid track heights presented in Table 4.1. The corresponding draughts of the barge are presented in the table as well. Table 4.1 yard skid track height and required draught variation Skid track height Required Draughts Chiwan 3,500 mm 8.45 11.75 m Zhan Jiang 3,500 mm 6.25 11.37 m 4.6 TRANSPORT CONDITIONS The environmental data used for motional calculation representing a 10-years storm condition in the South China Sea area is presented based on Noble Denton Guidelines for Marine Transportation; the design storm for the towage should be the 10 year return period monthly extreme storm for the towage route. Based on the above mentioned Noble Denton guideline and Global Wave Statistics of the South China Sea area (Area b2), the following conditions are applicable during transport: Significant wave height (Hs) Peak Period (Tp) Peakedness factor (g) 8.5 m 10.5-16.0 s 2.7 Barge Motion Analysis

Reference Document 0240 CNC 01 011 Transport Report

Page 31

STILL IN PROGRESS 1/28/2005 3:26 PM

4.7

DESIGN LOADS The resulting design loads derived from all operational conditions are summarized in Table 4.2. Table 4.2 Design Loads Scantling draught forward Scantling draught aft Deck load - cargo deck area Deck load - deck area forward (175 m from APP to FPP) Total Bending Moment (Rule Value - unrestricted) Rocker Arm Load Rocker Arm Load Load per unit length Skid Beam Load Pressure Skid Beam Load Load per unit length Webframe load 12.25 38.0 15.0 10.0 716,600 10,500 840 2,540 330 750 m m t/m2 t/m2 tm t t/m kPa t/m t

Page 32

STILL IN PROGRESS 1/28/2005 3:26 PM

5.

BARGE DESCRIPTION Reference is made to 0240 DNC 01 001 Barge General Arrangement Plan.

5.1

MAIN DIMENSIONS The main dimensions of the barge shall be: Length Overall (approximately) Length between Perpendiculars Breadth moulded Depth moulded Typical Transit Draught Block coefficient (approximately) Scantling Draught (forward) Design load line draft 235.00 215.00 52.50 14.25 6.50 0.96 12.25 10.45 m m m m m m m

5.2

GENERAL DESCRIPTION The Barge shall be an unmanned, non self-propelled steel deck barge designed for launching steel jackets weighing up to 30,000 t and up to 300 m total length. Besides for launching operations the barge will be used for transportation purposes with maximum cargo load capacity of 60,000 t. For launching purposes two (2) skid beams including skidding equipment as well as two rocker arms, hingeable at the stern, shall be provided. The beams and rocker arms shall be adjustable in between positions from 8 to 14 m from CL. The Barge shall be equipped with suitable towing gear, including emergency towing gear, as well equipment to handle this gear. Also a single anchor system for temporary mooring shall be provided. The Barge shall be subdivided into watertight and non-watertight compartments by means of transverse and longitudinal bulkheads. A double bottom shall be under the engine room to accommodate the fresh water cooling tank. A double bottom shall be provided under both pump rooms as well. These double bottom sections shall be void. The pump room forward shall be closed with watertight doors forward and aft and the aft pump room shall be closed with a watertight door at the forward bulkhead of the pump room.

Page 33

STILL IN PROGRESS 1/28/2005 3:26 PM

The general arrangement below main deck shall comprise: Forepeak Water ballast tank Anchor recess Anchor chain locker including access cofferdam Central store Rope store Office spaces, meeting room and changing room (upgradeable to pantry, accommodation and washing room) Control and switchboard room Battery room and electrical store Engine and Auxiliary room CO2 room Spare parts store Workshop Fresh Water cooling tank in double bottom Escape trunk (from Control Room) Various tanks, comprising Fuel Oil tanks Lube Oil tank Grey water tank Bilge water tank Sludge tank Hydraulic Oil tank Potable Water tanks Pipe tunnel (in three sections) Forward pump room Aft pump room Water ballast tanks On main deck the following shall be allocated: Towing and emergency towing arrangement including retrieval equipment Navigation lights Anchor windlass, combined with bridle retrieval winch and including warping head Skidding and Launching Equipment Life saving equipment Mooring arrangement

Page 34

STILL IN PROGRESS 1/28/2005 3:26 PM

Figure 5.1 General Arrangement Side and Top view For the General Arrangement drawings: 0240 DNC 01 001 0240 DNC 01 003 0240 DNC 01 004 0240 DNC 01 005 of the Barge reference is made to the following Barge General Arrangement Plan Barge Machinery Spaces Arrangement Barge Pump Room Aft Arrangement Barge Pump Room Forward Arrangement

Page 35

STILL IN PROGRESS 1/28/2005 3:26 PM

6. 6.1 6.1.1

CONSTRUCTION HULL General The construction plans associated with these specifications shall be approved by the Classification Society. The construction of the Barge shall be in compliance with the applicable Rules and Regulations, as set out in Section 3 of this document. Scantlings of structural members may be adapted to Yard's practice, however due consideration shall be given to the required section modulus and overall strength. It is not allowed to change the principal construction layout. The Barge shall be subdivided into watertight compartments by longitudinal and transverse watertight bulkheads.

6.1.2

Main subdivision The hull shall be divided in tank sections by eight (8) transverse watertight bulkheads. The bulkhead at frame 80 shall be a collision bulkhead. Tank lengths shall vary between 25m, 35m and 40m and forepeak tanks shall be 15m. Pump room lengths shall be 15m and machinery and service spaces area will be 25 m in length. All bulkheads shall be placed on webframe distance. Two longitudinal watertight bulkheads at 15,000 mm from CL shall run from APP to FPP. On CL a bulkhead shall be provided between frames 0 and 10 as well as frame 80 to 86 (aft tank and forepeak tank). Between frames 10 and 80 a 9,000 mm wide pipe tunnel shall be provided by means of longitudinal bulkheads at 4,500 mm from CL. Between frames 70 and 80 the machinery and service spaces shall be located, provided with a tween deck, division bulkheads and inner bottom of 1,500 mm high. Inner bottom shall be the tanktop of fresh water cooling tank. The space shall extend to the two outer bulkheads. Two (2) pump rooms shall be located in between frames 20&26 and 50&56 and shall extend to the two outer bulkheads. Large openings in the pipe tunnel bulkheads shall be provided for accessing the pump room without compromising longitudinal strength. The pump rooms shall be provided with a inner bottom of 1,500 mm height. The rest of the compartments shall function as ballast tanks. Other tanks shall be arranged in the machinery space. The main deck at 14,250 mm above base shall be the freeboard deck of the Barge.
Page 36

STILL IN PROGRESS 1/28/2005 3:26 PM

Figure 6.1 General Arrangement Subdivision 6.1.3 Material The barge shall be constructed of all welded shipbuilding quality steel in accordance with the Requirements of the Classification Society. Mild steel with yield stress of 235 N/mm2 Shall be used as far as possible. In bottom and deck higher tensile steel with yield stress of 315 N/mm2 shall be applied. In the stern section higher steel grades may be considered, however never exceeding the maximum allowed steel grade E36. The skid beams and rocker beams shall be made from steel E36 or D36. 6.1.4 System of construction A longitudinal framing system shall be applied. The longitudinal stiffeners shall be supported by transverse bulkheads and web frames. The web frames shall be supported by longitudinal bulkheads. For the stiffeners standard bulb profiles or alternatively constructed members for stiffening shall be used. Main transverse (web) frame spacing shall be 2,500 mm. Transverse bulkheads shall be stiffened vertically, with three (3) horizontal girders to support the stiffeners. 6.1.5 Bilge keels The parallel midship section part of the barge from frame 13 to frame 67 shall be fitted with bilge keels. Bilge keels shall be welded on a flat bar of 60x20 mm, web shall be 230x20 mm and at the tip a round bar of 50 mm shall be fitted.

Page 37

STILL IN PROGRESS 1/28/2005 3:26 PM

6.1.6

Skegs Two skegs underneath the bottom plating at the aft ship in line with the outside longitudinal bulkheads shall be provided.

6.1.7

Shell The plating of bottom and side shell shall be reinforced in way of openings and appendages as required by the Classification Society. Shell plating in way of the anchor shall be increased by 4mm in thickness down to the light water line.

6.1.8

Seawater inlet chests Six (6) large sea chests will be provided for supply of ballast water and will ensure a fast ballast intake during load out and launching operations. In proximity of each pump room a low and high sea chest will be provided and two low sea chests will be provided on the aft end of the pipe tunnel. Furthermore a high and low sea chest for machinery consumers will be provided as required. Each sea chest shall be provided with galvanized steel plate gratings bolted to the shell and be equipped with a compressed air and vent pipe connection.

6.1.9

Bulkheads A watertight collision bulkhead shall be located at frame 80. The other watertight transverse bulkheads shall be located at: frame 10. 20, 26, 40, 50, 56, 70 and frame 80. The following subdivision shall be provided by the bulkheads: APP to fr10 (Aft peak) Ballast tanks fr10 to fr20 fr10 to fr26 fr20 to fr26 fr26 to fr40 fr40 to fr50 fr40 to fr56 fr50 to fr56 fr56 to fr70 fr70 to fr80 fr80 to FPP Ballast tanks, pipe tunnel Ballast tanks Ballast tanks, aft pump room Ballast tanks, pipe tunnel Ballast tanks, pipe tunnel Ballast tanks Ballast tanks, forward pump room Ballast tanks, pipe tunnel Ballast tanks, machinery spaces, various tanks, stores, workshop, control room and office (Fore Peak) Ballast Tanks including Chain locker
Page 38

STILL IN PROGRESS 1/28/2005 3:26 PM

For longitudinal bulkheads reference is made to section 6.1.2. 6.1.10 Tanks The arrangement of the tanks and their capacities shall be as be as indicated in the drawing 0240 DNC 03 001 Barge Tank and Capacity Plan. Drain plugs shall be provided at the bottom each tank. At least two (2) plugs shall be installed at opposite corners. Tanks shall be accessible through at least two (2) manholes with flush water tight covers and steel ladders with safety cages and platforms. All structures shall be constructed with continuous welding. Bottom and top stiffeners in tanks shall be provided with lumber holes for drainage purposes and to avoid trapping of air. 6.1.11 Main deck The main deck shall be straight over the entire length of the Barge, without sheer or camber. At the aft part of the Barge two (2) inclined deck sections shall be provided in way of the allowable rocker beam positions. Rounder corners shall be applied at sheer strake in a gun whale. The main deck shall be the freeboard deck. The main deck shall be constructed for a deck load of 15 t/m2 for the deck area from APP to frame 70. The deck load for the deck area forward of frame 70 shall be 10 t/m2. Adequate stiffening shall be arranged under and around ventilators, openings, hatches, etc. Large recesses in main deck shall be provided for accommodating the rocker arms at the stern. Recesses shall be provided for bollards and chocks as well. The main deck forward and aft shall be locally reinforced in way of the capstans, bollards, shocks, etc. 6.1.12 Hawse pipe A hawse pipe shall be provided for the anchor and shall have sufficient slope for anchor to slide out by gravity. An anchor pocket of fabricated steel construction shall be provided in the stem structure, sufficient to house the anchor leg, locking and tightening devices on the chain stopper. Plating shall be reinforced in the way of the anchor pocket and hawse pipes.

Page 39

STILL IN PROGRESS 1/28/2005 3:26 PM

6.1.13

Built in foundations Where required the decks shall be reinforced to take the loads of the equipment. The built-in foundations shall be able to withstand the forces due to Barge motions, vibrations and forces of the machinery.

6.1.14

Local strengthening for jacket protrusion To allow for protruding jackets the forepeak of the Barge shall be strengthened. Transverse bulkheads shall be added at frame 83, 84 and 85 and the plating of the longitudinal bulkheads shall be suitably increased. Reference is made to 0240 CVC 10 003 Barge Local Strength Calculation Report and 0240 DVC 01 043 Barge Transverse Sections and Bulkheads Forepeak Basic Construction Plan.

6.2 6.2.1

SUPERSTRUCTURES Barge access The barge shall be accessed through a small enclosed structure near CL, closed with a watertight door. The access housing shall be located above the machinery space and combined with a ventilation deckhouse (refer to section 6.2.2). The structure shall be 2,200 mm in height. The access superstructure shall start between frame 79 and frame 80 and be approximately 2.5 m long and 9.0 m wide. Watertight access door shall be provided at the aft side of the superstructure. A second entrance from main deck shall be provided from a small superstructure at the aft side of the machinery spaces for emergency escape.

6.2.2

Ventilation deckhouse Deckhouses shall be placed on the main deck with fan rooms to provide ventilation inlet and outlet for generator room and other spaces under the main deck and accommodate the electrical fans for mechanical ventilation. Furthermore two separate sections of the Barge access superstructure shall accommodate generator room exhausts as well. Deck houses shall be 2,200 mm in height and 5,000 mm wide. All openings shall be ventilation louvres with watertight fire covers and not be located below 900 mm from main deck. Access hatches shall be provided in roof of each deckhouse.

Page 40

STILL IN PROGRESS 1/28/2005 3:26 PM

The following fan rooms shall be provided: fr66 to fr67 ventilation exhaust for pump room and pipe tunnel fr68 to fr70 ventilation supply for pump room and pipe tunnel fr70 to fr75 - ventilation supply engine and auxiliary room, minus 1,250 mm wide emergency access and escape structure fr75 to fr76 - ventilation exhaust engine and auxiliary room fr76 to fr77 trunk for generator exhaust lines 6.2.3 Coamings Coaming shall be provided around the tank access lines at main deck, e.g. fuel oil tank lines, sludge draining, fresh water filling line. The height of coamings shall be in relation to the position of the fans, the degree of water tightness and the degree of hazardous area, according to Classification requirements, as indicated on GA. The plate thickness shall be in accordance with the Classification Society. 6.3 6.3.1 HULL EQUIPMENT AND OUTFITTING Barges name, Port of registry and Draught marks The name of the Barge shall be placed on both sides in 1,000 mm high characters and on the stern name in 450 mm high characters and port of registry in 300 mm high characters. Characters, numbers and marks in general shall be cut from 6 mm plates and welded on with continuous welding and painted in a contrasting color. Draft marks, shall be tack-welded and painted on both sides fore, aft and at mid ship of the Barge. Draft marks shall be 100 mm in height and shall be placed every 200 mm. Freeboard marks, size and location shall be according to Authorities. Yards sign with engraved yard No. and year of delivery is to be mounted on the access deckhouse. On both sides and on main deck the position of transverse bulkheads and tank markings shall be marked; frame numbers and tank numbers shall be tack welded and painted. Manhole covers shall have tack welded and painted numbering. On the bottom plating, tank plug numbers shall be tack welded.

Page 41

STILL IN PROGRESS 1/28/2005 3:26 PM

6.3.2

Watertight doors The entrances giving access to machinery space below main deck level shall be fitted with a steel watertight door of the hinged and dogged type with manual operation. Manual check valve, to verify the compartment is not flooded, shall be fitted in the watertight bulkhead next to the watertight door. Below the freeboard deck watertight closures are to be provided for every opening through any watertight boundary as indicated in the drawing 0240 DNC 03 003 Barge Watertight Subdivision Plan.

6.3.3

Masts On the bow one (1) foldable mast shall be provided. All signaling lights, day signals and Halyards as required, shall be fitted to this mast. A battery shall power the navigation lights. The mast shall be placed on a raised platform to enable passing of the bridle retrieval wire. One (1) mast shall be provided on the aft with a battery powered yellow navigation light, in accordance with CCS requirements. The mast shall be divided in two, separated by a bolt secured flanged connection. This connection provides easy removal of the mast during a launching procedure.

6.3.4

Hatches Six (6) escape hatches shall be provided as indicated on general arrangement plan, four (4) shall provide escape from pipe tunnel and pump rooms to main deck and two (2) shall provide escape from engine room to tween deck (escape trunks). All hatches shall be flush. Four (4) access hatches shall be provided as indicated on general arrangement plan for accessing the fan rooms. All access hatches shall be flush. All hatches shall be closed with watertight hatch covers with a central locking device, operated from the inside by a hand wheel. Electronic control shall be installed over the trunk for indication of closure. Bolts and wing nuts of bronze shall be provided with neoprene gaskets. All moving parts shall be bronze bushed and grease lubricated. Neoprene gaskets on cover shall be fitted after paint application. The escape hatches shall incorporate hold-back securing devices for covers in open position. Escape routes shall be arranged in all working compartments where two independent accesses cannot reasonably be fitted.

Page 42

STILL IN PROGRESS 1/28/2005 3:26 PM

Four (4) flush hatches shall be installed for lowering spare parts and equipment in the machinery spaces; two (2) in the main deck and two (2) on the tween deck in line with the hatches on main deck. Typical size shall be 2,050 x 1,050 mm, fitted with a watertight bolted steel cover. Two (2) flush hatches shall be provided of 2,300 x 1,800 mm, one above each pump room. The hatches shall be fitted with a watertight bolted steel cover. Since the engine room is protected by CO2 fire fighting system all openings on deck from baseline to engine room shall be gas-tight. 6.3.5 Chain locker A cylindrical chain locker shall be provided just forward of the collision bulkhead. The diameter of the locker shall be 3,000 mm. The chain locker shall extend to bottom with a grated floor at 1,500 mm from BL. The bilge well shall be equipped with an ejector serviced by the fire pump. A cofferdam shall be provided next to the chain locker with access ladder for maintenance. Access manhole shall be closed with watertight manhole centrally bolted cover. 6.3.6 Railings and walkways Open railing shall be provided alongside walkways and stairs. The height of the top rail shall be according to Classification and authoritys requirements and made of 50 mm OD galvanized steel tube. Two intermediate rails of 20 mm round bar shall be fitted. Railing stanchions shall be made of flat bar 60 x 19 mm welded to the deck and curtain plate. A toe plate of 150 mm high shall be provided on floors or walkways. Where removable railing work is required, the flat bar stanchions shall have 8 mm galvanized chain in between. Removable railing shall be provided around the main deck. 6.3.7 Ladders and stairs Steel stairs shall be provided from barge access superstructure to tween deck passageway with access to offices, store, control room, electrical room, battery room and CO2 room and stairs to floor in the machinery room. The stairs shall have an angle of 55 in machinery spaces and executed with anti-slip steps and 50 mm diameter galvanized steel tube handrail, according China National standard.
Page 43

STILL IN PROGRESS 1/28/2005 3:26 PM

Stairs with an angle of 55 and anti-slip steps and 50 mm diameter galvanized steel tube handrail, according China National standard shall be provided aft access as well. Steel ladders of China National standard shall be fitted in all tanks as required. Hand grips and foot rungs shall be fitted as required at entry manholes and lighting holes inside tanks. Four (4) barge access ladders shall be incorporated in the hull sides. Two (2) at SB and two (2) at PS as indicated on General Arrangement. At main deck a provision for a pilot ladder shall be fitted, both on SB as well as PS. 6.3.8 Built on foundations Built-on foundations for skid mounted deck machinery and equipment, other than jacket skid beams, shall consist of angle bars welded to deck and incorporating transverse brackets as far as necessary. 6.3.9 Manholes and covers Manholes shall be provided as indicated on General Arrangement. Each tank shall be provided with two (2) manholes in opposite corners close to the bulkheads. Manhole covers shall be watertight, flush and central bolted with a stainless steel bolt. Manhole diameter shall be 600 mm. Manholes on tank tops shall be raised. For the center tanks, access shall be provided from the pipe tunnel by means of manholes. These manholes shall be watertight and bolted peripherally. The manhole cover on the chain locker shall be watertight and bolted peripherally as well. 6.3.10 Hoisting beams and lifting eyes In the machinery space and pump rooms hoisting beams or lifting eyes in way of the following, shall be provided: Diesel generator sets E-motors Ballast Pumps Workshop area All necessary lifting eyes, pads on deck heads shall be arranged for lifting tackles over motors, pumps etc. Page 44

STILL IN PROGRESS 1/28/2005 3:26 PM

Pad eyes shall be provided over equipment exceeding 40 kg weight. Pad eyes and hoisting beams shall be marked with SWL and tested. 6.3.11 Raised floor In all areas where corrosion is prone to develop quickly, galvanized gratings shall be used throughout for raised platforms or floors. These floors shall be provided in pump rooms and pipe tunnel segments. In the machinery spaces raised floors shall consist of aluminum plating. Where required raised floors shall be surrounded with suitable handrails. 6.3.12 Ventilation caps Ballast tanks and other tanks below main deck shall be provided with tank vent check valves; valves shall be of Winel make or equivalent. All ventilation caps shall be located on main deck forward of frame 63 and positioned inside of pipe tunnel bulkheads alongside and in vicinity of the vent houses. 6.3.13 Bollards and chocks Sixteen (16) 50 t double bollards shall be provided on main deck at regular intervals as arranged on drawing 0240 DVC 15 002 Barge Equipment Fender and Bollard Arrangement. The bollards shall be installed in recesses flush with main deck except for the forward bollard. Chocks shall be provided in the recesses and on main deck for the forward bollard on SB and PS. 6.3.14 Fendering All around the Barge steel fendering shall be provided. The protection shall be installed from transom to bow. Reference is made to 0240 DVC 15 002 Barge Equipment Fender and Bollard Arrangement. 6.3.15 Towing appliances The barge shall be equipped with four (4) Smit towing brackets on the main deck forward, two (2) at PS and two (2) at SB. The bracket capacity shall be at least 300 t SWL in direction of towing chain. Necessary fairleads (pipe 600x20) shall be provided for each bracket. Fairleads shall be closed at top. Position shall be conform Class requirements. Reference is made to section 9.2.

Page 45

STILL IN PROGRESS 1/28/2005 3:26 PM

7. 7.1

LAUNCHING AND LOAD OUT SYSTEM GENERAL The barge shall be equipped with two skid beams and two rocker beams. The rocker beams shall be hinged at the stern. The position of the tracks and beams shall be adjustable to any position between 8 and 14 m from CL of the barge. Skidding will be performed by four (4) skid units, placed on separate skid rails along both sides of the skid beam. The skid rails and main skid beam are integrated into 10m single sections that can easily be handled for (re)-positioning on deck. Each skid unit typically consists of 2 hydraulic cylinders, 1 gripper unit for clamping onto the skid rail, and an interconnecting push/pull yoke. The Launch and Load Out system shall include the following: One (1) skidding mechanism, comprising four (4) skid units and one (1) HPU Two (2) skid beams built up in sections with integrated skid rails on both sides Two (2) rocker arms with integrated hinge shaft Two (2) hinge gutters, integrated in the barges stern structure Four (4) locking devices, welded onto the hinge gutters locking the hinge shaft to the barge. Two (2) rocker buffers, welded onto the barges stern The skidding mechanism shall be capable of functioning as an autonomous (stand-alone) system.

7.2

SKIDDING MECHANISM Reference is made to 0240 SMC 03 002 Launch Skidding Mechanism Specification. The diesel-hydraulic skidding mechanism shall comprise: Four (4) hydraulic skidding units One (1) diesel-hydraulic power pack Four (4) sets of hydraulic hoses, connecting the skidding units to the power pack The hydraulic skidding units shall run over separate skid rails on both sides of the skid beams.

7.2.1

Skidding units The barge is equipped with 4 skidding units of 950 ton (9,500 kN) push and pull capacity each. Each unit typically consists of 2 large hydraulic cylinders, 1 gripper unit for clamping onto the skid rail, and an interconnecting push/pull yoke. The weight of the units will be approximately 17 t each. Approximate dimensions of each unit are 6.0x1.8x0.75m Page 46

STILL IN PROGRESS 1/28/2005 3:26 PM

The hydraulic cylinders are connected to the yoke at the rod ends and to the gripper units at the bottom ends. The two cylinders in one skid unit are sized to together deliver a 950 t force both in pushing and pulling mode. The gripper unit consists of a number of hydraulic jacks, mounted vertically in a frame which envelopes the top flange of the skid rail. By powering the jacks, the unit will grip the flange tightly and thus the push/pull force can be transferred from the jacket via the skid rail to the barges deck. The yoke is a double swivel plate connected at the outer ends to the push/pull cylinder rod ends and at the center equipped with a central pin of 250 mm outer diameter. A clevis is designed accordingly. Weight of the swivel plate will be approximately 1.8 t. The swivel is equipped with bolted-on push plates for launch assistance, which must be unbolted when a pull operation is to be performed. The jacket needs to be equipped with push/pull supports to fit into this clevis or onto the push plate. Such jacket supports will be designed depending on the shape and size of the jacket and therefore be project-specific. The swivel is also equipped with a gripper for locking onto the skid rail and repositioning the main gripper section. This auxiliary gripper is smaller since it only has to clamp just enough to move the skid units own weight. The skid units shall be fully manually lever-operated from a control panel at the diesel power pack. All units can be operated together or individually. Synchronization of the units shall be manual/ visual, to keep the system as simple and straight-forward as possible. The skidding mechanism shall not be clamping right at the heaviest loaded parts of the skid beam to avoid overloading the deck frames. For the design jacket this implies that the grippers shall not clamp within the first 20 meters of the jacket and in between 30 and 55 meters. (This applies only when pulling or pushing the jacket, not when moving the skidding mechanism itself). 7.2.2 Diesel HPU The skidding mechanism is capable of functioning as an autonomous system; therefore it is provided with its own diesel-hydraulic power pack on deck. The diesel power pack runs in between both skid tracks to serve all skid units. It is mounted on rugged wheels and is driven by a hydro motor. It is possible to disconnect the power pack from the skid unit. The stability of the power pack can be maintained under the barges operating roll angles. Under transit conditions it must be stowed.
Page 47

STILL IN PROGRESS 1/28/2005 3:26 PM

The diesel engine power shall be rated at approximately 2x 500 kW. The power pack overall dimensions are approx. 6.0x3.0x1.9m and weight is approximately 10 t. Built on fuel tank shall have a capacity 300 L. The HPU shall be functional at maximum power for trim angles up to 12 deg. The HPU contains the skidding control panel, at least incorporating pressure gauges for the pressures of skid jacks, main grippers and swivel plate auxiliary grippers. Flexible hoses between the power pack and the skidding units are supplied of sufficient length for on-barge operations; length shall be approximately 95m. Per skid unit the following 6 hoses are typically supplied: 2 pcs 1 for the skid jacks 2 pcs for the main grippers 2 pcs for the auxiliary grippers in the swivel plate The hose connections shall be of the Quick-Release type. 7.3 SKID TRACKS Reference is made to 0240 DMC 03 001 Launch Skid Track Basic Construction Plan and 0240 DMC 03 002 Launch Skid Track Forward Section Structural Drawing. The skid tracks shall be executed as steel boxes with a U-shaped cross-section, opened at the bottom. They will have a typical height of 2.0 m, a width of 1.9 m at the top plate and a 2.5 m wide base. The skid beam structure is open at the bottom to allow for easy manufacturing and for weight reduction. Each skid track has two integrated but separate skid rails to accommodate the hydraulic skid units. The skid track shall run from the rocker beams at the stern towards the bow and its total length will be 190 m. The top plates of main skid beam and skid rail must be flat with a tolerance of 5 mm relative to the bottom surface. The skid system supplier may specify additional skid rail tolerances. The skid track does not cover the remaining 4 m of length at the barges bow end. This area will normally not be needed for the support of the jacket. To be able to transport protruded jackets the most forward section of the skid beam on both PS and SB side shall be strengthened in order to increase the allowable load and transfer the concentrated jacket loads into the designated strengthened area of the barge. These special skid track sections shall weigh approximately 70 t.

Page 48

STILL IN PROGRESS 1/28/2005 3:26 PM

Each skid track is divided into longitudinal sections, each 9.97 m in length, in order to be able to easily move or remove the skid track sections from the Barge. In order to take up any barge deformations (hogging and sagging) a 30 mm play between adjacent sections is designed. Each section weighs approximately 57 t and is equipped with 4 hoist lugs for hoisting from a single hook in a 4-rope arrangement. For the design of the skid track it is assumed that the jacket will be equipped with a hard-wooden lining and/or other means of spreading the load to the design load level as in Section 4.7. The overall width of the skid track, together with the integrated skid rail structures and hoist lugs, will be approximately 5,800mm. The total of all skid beam sections on the barge will weigh approximately 2,170 t. The skid beams shall be manufactured out of steel D36 or equivalent. The skid tracks can be moved laterally over (part of) the width of the barge in order to be able to accommodate various widths of jackets. After moving the skid track sections, the assembled skid track must be checked for the correct horizontal alignment and shimmed for the correct vertical alignment at the position of the large web frames. A nominal shim height of 40 mm is taken into the design. After ensuring the proper alignment, the skid beams must be welded onto the deck. In case adjacent beam sections are in different loading conditions, the vertical alignment is ascertained by welding key plates onto the side plates of adjacent beams. In longitudinal direction these plates allow for 30 mm of barge deformation. Also the top plates are chamfered at the ends of the beam sections. A PTFE sliding track shall be placed at the top of the skid beam over its full length. Quality and details of the slide pads are, as well as the mating material at the jacket, very important to ensure the lowest possible friction coefficient and wear. For the mating material at the jacket hard wooden lining is assumed to result in the lowest possible friction. The PTFE pads shall typically be factorybonded to steel carrier plates that must be tack welded to the skid beams top plate. Steel guiding strips shall be installed on both sides of the PTFE track, to ensure the lateral guiding of the jackets skid shoes or lining.

Page 49

STILL IN PROGRESS 1/28/2005 3:26 PM

7.4

ROCKER ARM Reference is made to 0240 DMC 01 001 Launch Rocker Arm and Hinge Points Arrangement and 0240 DMC 02 001 Launch Rocker Arm Basic Construction Plan. The two (2) rocker arms shall be located at the stern of the launch barge. The hinge shaft center shall be positioned 1,350 mm from APP. The rocker arms can be laterally moved to follow the skid track width. The rocker arms and hinge are designed to take up the forces as derived from the launch analysis. Refer to Section 4.7 for design loads. The rocker arm shall be executed as a closed box section of 41.135 m total length and approx. 3.9 m. wide at its mid-section. The beam shall be reinforced at the mid-section where the hinge shaft will be integrated. The rocker arm shall have tapered ends in the vertical plane; at the mid-section the maximum height shall be approximately 6.4 m, while at the forward end the height shall be approximately 2.0 m. so that it aligns with the skid beams. Each rocker arm will weigh approximately 590 t, including the integrated hinge shaft. The rocker arm is entirely made from steel D36 and E36. Thick plates are inserted where necessary. Maximum used steel grade shall not exceed E36. Since the rocker arms must be adjustable in lateral position, the hinge part at the barge is executed as a half-round gutter section integrated into the barges stern structure.

7.5

ROCKER LOCKING DEVICES Reference is made to 0240 DMC 02 005 Launch Locking Mechanism Construction Plan Structural Drawing. Each rocker arm shall be laterally secured by locking devices (or retainers) on both sides. They are designed to take up any lateral and uplift forces which might occur during launching and buffering of the rocker arm. The locking devices must be welded in position onto the barges stern after proper alignment of the rocker with the skid track. The locking devices shall be constructed entirely of steel D36.

Page 50

STILL IN PROGRESS 1/28/2005 3:26 PM

7.6

HINGE POINTS Reference is made to 0240 DMC 02 002 Launch Hinge Point Basic Construction Plan. The hinge gutter on the barge is executed as a steel welded section in E36 or equivalent steel integrated into the Barge structure. The hinge structure has approximate dimensions of 13.5x2.8x3.8m and a weight of approximately 94 t each. To lubricate the hinge points the following grease shall be used: GRAFLOSCON A-G 1 ULTRA of Klber Lubrication or equivalent.

7.7

ROCKER BUFFERING Reference is made to 0240 DMC 02 004 Launch Buffer for Rocker Beam Basic Construction Plan. The rocker beams are buffered in their fully rotated positions, 85 deg rotated from their initial position. When the jacket is launched, the rockers rotate under the influence of the jackets dynamic reaction forces. The rocker is slowed down before hitting the rocker buffer by the displacement of the surrounding water. The steel buffer structure shall be designed for being welded in place onto the barges stern. The buffer structure shall be covered with a wooden lining and fenders/tires to dampen the impact. The structure has frames matching the horizontal stiffening in the barge stern in order to transfer the buffer forces correctly into the barge. The buffers shall be able to be laterally positioned in any arbitrary position in a vertical line below the rocker arms.

Page 51

STILL IN PROGRESS 1/28/2005 3:26 PM

8. 8.1

POWER GENERATION GENERAL The load capacity of the power plant shall be compatible with the actual electric power consumption of the barge. Three (3) main generator sets and one (1) auxiliary generator set shall be installed in the engine room. Electrical power generating capacity shall be installed for the following operational cases. Launch operation Load out operation All diesel engines shall run on Marine Gas Oil MGO ISO-F-DMA. Functionality of the power generation shall be ensured at trim angles up to 12 deg by stern. Reference is made to: SEC 41 002 Electrical Diesel Generators Specification SEC 41 004 Electrical Auxiliary Diesel Generator Specification

8.2

MAIN GENERATOR SETS Three (3) main generator sets shall be installed, providing a 380 V, 50 Hz power system, each comprising the following main components One (1) marine diesel engine Minimum output Speed 940 kW MCR 1,500 rpm

Each engine complete with built-on: Fuel injection pumps Speed governor Mechanical overspeed trip Turbo charging Fuel oil supply system Lubricating oil system Jacket water-cooling system Starting system

Page 52

STILL IN PROGRESS 1/28/2005 3:26 PM

One (1) Electric generator Nominal apparent power Nominal rated power Power factor (assumed) Nominal voltage Frequency Speed Insulation class Max. ambient temperature Rating Cooling Enclosure Exciter Anti-condensation heater Temperature detection

1,175 kVA 940 kW 0.8 380 V 50 Hz 1,500 rpm H 50C Continuous, S1 Air IP 23 brushless 230 V, 2 phase 2 (two) resistance temperature detectors in each stator winding.

Generator control and synchronization shall be from LV switchgear 8.3 AUXILIARY GENERATOR SET One (1) marine auxiliary set shall be installed as described below One (1) diesel engine Minimum output Accessories One (1) generator Nominal apparent power Nominal rated power Power factor (assumed) Nominal voltage Frequency Speed Insulation class Max. ambient temperature Rating Cooling Enclosure Exciter Anti-condensation heater Temperature detection 350 kW cont. same as main diesel engines. 438 kVA 350 kW 0.8 380 V, 3 phases 50 Hz 1,500 rpm H 50C Continuous, S1 Air IP 23 brushless 230 V, 2 phase 2 (two) resistance temperature detectors in each stator winding.

Page 53

STILL IN PROGRESS 1/28/2005 3:26 PM

9. 9.1 9.1.1

BARGE OUTFITTING MOORING ARRANGEMENT General The Barge shall encounter three different types of mooring during the intended utilization of the barge: Temporary mooring; mooring of the barge by means of a single anchor system after launch Quayside mooring; barge lay-up at a miscellaneous quayside, when not used Load out mooring; barge secured to the quayside longitudinally, with bow or stern, to enable load out operations. The mooring arrangement shall be in accordance with Chapter 3, Section 2 of CCS Rules for Sea Going Steel Ships Vol.2 Part 2 (2001). Reference is made to 0240 CNC 01 006 Barge Mooring Arrangement Calculation Report.

9.1.2

Temporary mooring For temporary mooring a bow anchor shall be provided. The bow anchor shall be housed in anchor pocket with air vent located on the raked bow with protected corners. An inclined hawse pipe shall be provided to lead the anchor chain to the anchor winch mounted on main deck. Just before the collision bulkhead the chain locker as defined in section 6.3.5 will be provided. All corners likely to get in contact with the chain to be suitably rounded in order to minimize chafe. Ground tackle shall comprise at least 8.7 t stockless bow anchor of normal holding power or 6.5 t anchor of high holding power, 650 m of 73 mm - U3 (OR AMS3) quality anchor chain together with necessary swivels, shackles and anchor chain stopper. The anchor must self stow and flukes and crown shall be within line of shell when stowed. All equipment shall be certified by Certification Authority. Anchor shall be lowered and hoisted by an anchor windlass mounted on deck. For the windlass specification reference is made to 9.3. Suitable cable clench, chain stopper and chain compressor shall be provided.

Page 54

STILL IN PROGRESS 1/28/2005 3:26 PM

9.1.3

Quayside mooring For general lay-up at miscellaneous quaysides four (4) capstans shall be installed on the barge, with 10 t pull capacity. The capstans shall be electrically driven and locally operated from deck. Hauling speed shall be 20 m/min. As a consequence of the launching procedure the two capstans on the aft shall be able to be submerged. The aft capstans shall be installed on recessed decks flush with main deck. The forward capstans shall be installed on main deck. Ten (10) polyester mooring lines of 200 m in length and 52 mm in diameter and 6 circumference shall be provided, with a MBL of approximately 50 t. Sixteen (16) double bollards - eight (8) on each side of the Barge - shall be provided, with 50 t safe working load capacity. The bollards shall be placed at regular intervals in recesses flush with main deck. The aft bollards shall be placed on the recessed deck with the capstans flush with main deck. The forward bollards shall be placed on main deck. Sixteen (16) Panama chocks, eight (8) on SB and eight (8) on PS shall be provided, each accompanying a double bollard. All chocks will be flush with main deck in the recesses, except for the chocks located at the forward bollards.

9.1.4

Load out mooring Two (2) Smit towing brackets on the aft deck with 200 t SWL shall be provided for securing the barge during load out. Chain tension shall be provided with winch capacity from shore. Reinforcement in way of brackets shall be provided. When secured to the quayside in load out operation over the bow, the towing appliances as specified in section 6.3.15 shall be used.

9.2 9.2.1

TOWING ARRANGEMENT General Towing and emergency towing equipment the capacities are to be in accordance with Guidelines for Safe Ocean Towing MSC/ Circ. 884 21 December 1998, and Technical Regulations for statutory survey of Ocean Towing 1999, promulgated by the Register of Shipping of Peoples Republic of China. Reference is made to 0240 CNC 01 002 Barge - Towing Resistance - Calculation Report.
Page 55

STILL IN PROGRESS 1/28/2005 3:26 PM

9.2.2

Towing gear Two (2) Bridle 87 mm studlink chains of 45 m length shall be provided. The chain shall be U3 (OR AMS3) quality and end links shall be suitable for shackles. One (1) Fore runner of 15 m shall be provided of same chain. Proof load of the chain is at least 400 t. The forerunner shall be connected to the bridle chains through a triangular plate of the same breaking strength. The plate shall be installed together with 15 m of 82 mm wire with a breaking strength of at least 450 t. All connections to be made with steel shackles, MBL 600 t. The bridle chain shall be lowered and hoisted the anchor windlass mounted on the main deck. For the windlass specification reference is made to 9.3. One (1) A frame with 25 t SWL shall be provided on the bow for retrieving towing bridle. Connection to deck shall be by means of stainless steel bolts.

9.2.3

Emergency Towing Gear The PS towing bracket shall be provided with a stud link chain cable. Chain shall be U3 (AMS3) quality, 45 m long and 87 mm diameter and suitable for shackles at both ends. An emergency towing wire shall be 210 m long with a SWL of at least 450 t, connected to the free end of the chain cable All connections shall be made with steel shackles, MBL 600 t. On the free wire end a polypropylene wire of 350 m shall be provided, with plastic buoy and pick up hook. The floating rope shall be coiled up at the aft ship, the emergency towing line (chain and wire) shall be clipped over its entire length on top of the PS gunwale or next to the bollard recesses with clips. Clips shall be provided every 2.5 m and made such, that the wire will not be damaged.

Page 56

STILL IN PROGRESS 1/28/2005 3:26 PM

9.3

WINDLASS One totally enclosed electrically driven anchor windlass shall be provided at the bow on main deck. The windlass shall be of capacity and design to allow for proper self-stowage of steel wire for bridle retrieval, chain cable lifting and warping head handling. The windlass shall be located on a suitable foundation on main deck subject to Class approval. The windlass shall be rated for at least the following capacities: chain cable lifter 30 t pulling capacity @ 10 m/min 73mm U3 (or AMS3) quality chain cable wire drum 25 t pulling capacity in 2nd layer @ 3 m/min 32 mm steel wire, storage capacity at least 100m (indicative drum size: 610mm diameter x 1,000mm in length) warping head 10 t pulling capacity @ 20 m/min warping head diameter 450mm Manual operated band brakes including manual operated spindle emergency shall be provided as well as manual dog-clutches.

Page 57

STILL IN PROGRESS 1/28/2005 3:26 PM

10. 10.1

OFFICE, CONTROL ROOM AND SWITCHBOARD ROOM GENERAL Since the barge is unmanned no accommodation shall be provided on board. For operational purposes office spaces and a control room are provided in the machinery space of the Barge. One of the office spaces shall allow for upgrade into an accommodation space, one into a pantry or kitchen and one into a sanitary space. Reference is made to the following drawing 0240 DNC 01 003 Barge Machinery Spaces Arrangement. Offices and control rooms shall have all furniture and outfit installed which is considered necessary for the functions that space is designated for. To enable a future upgrade space for four (4) double bunk beds shall be reserved in one of the office spaces. All materials, outfit and equipment used and installed in the office and control room area shall be of Marine quality and standard and shall be delivered with the required certificates. Layouts, details, materials, decorations, connections etc. shall be subject to Owner's approval prior to ordering. Non steel walls and ceilings in office spaces, control room and switchboard room shall be in accordance to the applicable Rules and Regulations (SOLAS). Outfitting in the office spaces shall at least comprise the following: kitchenette with sink hand wash basin 120 l boiler (10 kw) Refrigerator 120 liter 1 table 12 chairs benches Space and provisions for four (4) double bunk beds Computer Printer Fax machine Copy machine A separate space shall be reserved for at least two chemical toilets. This room may be refurbished as wash room in case of a future upgrade.

Page 58

STILL IN PROGRESS 1/28/2005 3:26 PM

11. 11.1

MARINE SYSTEMS GENERAL All marine auxiliary systems are sized for a power system of three (3) 965 kW main generators and one (1) auxiliary generator of 350 kW capacity.

11.2

BALLAST SYSTEM Reference is made to: 0240 DKC 02 006 Marine Ballast System Piping Diagram 0240 SKC 03 003 Marine Main Machinery Equipment Specification A complete ballast system shall be installed comprising: Four (4) ballast pumps Twenty-four (24) ballast tanks Vacuum priming unit Distribution piping system Ballast control panel The ballast pumps shall be vertical, split casing, centrifugal, electrically driven. The pumps shall each have a capacity of 3,500 m3/h at 20 mWc. The ballast pumps shall be connected to a central vacuum priming system. The vacuum system shall comprise 2 x 100% capacity vacuum pumps, cooling/sealing water tank and vacuum tank. The vacuum system shall have a capacity of 770 m3/h at 48% vacuum. The distribution piping system shall consist of four suction/discharge mains connected at the fore and aft ends such forming two ring mains. The system shall allow for: Filling ballast tanks, using the ballast pump(s) Emptying ballast tanks, using the ballast pump(s) Filling ballast tanks by gravity flow Tank to tank transfer to allow quick respond on load changes, however limited to transfer from inside to outside tanks and from PS to SB and vice versa. The suction/discharge lines from the outboard water ballast tanks shall be connected to the outsides of the ring mains and the suction/discharge lines from the inboard water ballast tanks shall be connected to the insides of the ring mains.

Page 59

STILL IN PROGRESS 1/28/2005 3:26 PM

Two (2) high seawater inlet chests shall be installed inside WB wing tank No.04 PS, just forward to the transverse bulkhead on frame 50 and inside WB tank wing tank No.06 PS, just forward to the transverse bulkhead on frame 20. At the same longitudinal position two (2) low seawater inlet chests shall be installed just outside the pump room on SB side. Between the sea chests, at PS and at SB,a crossover line shall be provided complete with isolation valves and inlet strainers. The crossover and ballast (ring) mains shall be installed at an elevation as low as possible. Therefore the crossovers shall be routed through the ballast tanks just aft of the bulkheads on frame 50 and 20. Additionally two (2) low seawater inlet chests shall be installed in the aft pipe tunnel at the aft end. From the sea chest two seawater supply lines shall be installed complete with isolation valves and inlet strainers. The supply lines shall be connected one to each ballast ring main. Two (2) ballast pumps shall be installed in the aft pump room, one at PS and one at SB side and two (2) ballast pumps shall be installed in the forward pump room in the same way. The pumps shall have connections as follows: Suction from: Sea via cross-overs Ballast (ring) mains Discharge to: Sea (SB & PS) via overboard discharge main Ballast (ring) mains via overboard discharge main Expansion joints are to be fitted in the ring mains and branches (when required) to take up expansion, hogging and sagging. The suctions in the tanks are to be provided with bell mouths and with erosion plates underneath. Valves in the ballast system shall be hydraulically actuated. Control of the valves shall be possible locally at the solenoid valve boxes and remote from the ballast control desk in the control room. In case of hydraulic power failure local manual operation of the valves shall be possible by means of a portable hand pump. Valve open/close indication shall be available locally at the valve and remote from the ballast control desk. Valves that are required for throttling shall have position indication from full open to the closed position. The hydraulic system will allow for simultaneous operation of the five largest valves with an open/close cycle speed of 30 s the greater of simultaneously operating 6 of the largest system valves. In case of hydraulic system failure the valves remain in position. A Loadmaster will be installed for monitoring of the loading conditions of the barge. Ullage/level, volume, weight, draught, trim/list, stress/stability and alarms will be made available.
Page 60

STILL IN PROGRESS 1/28/2005 3:26 PM

The tank gauging and draught measuring system will be based on pressure transmitter type sensors. Alternatively an air-bubble type system may be considered. In addition inclination meters will be provided. Start/stop of the ballast pumps shall be possible locally at the pumps and remote from the ballast control desk in the control room. Start/stop of the vacuum pumps shall be possible locally at the vacuum unit and from the ballast control desk. The control system shall allow for automatic operation. Monitoring of the suction -and discharge pressures of the ballast pumps and the vacuum tank pressure shall be possible from the ballast control desk as well as locally at the pumps. 11.3 STRIPPING SYSTEM Reference is made to: 0240 DKC 02 007 Marine Stripping System Piping Diagram 0240 SKC 03 003 Marine Main Machinery Equipment Specification In addition to the ballast system a ballast stripping system shall be installed comprising: Two (2) stripping pumps Distribution piping system The stripping pumps shall be horizontal, centrifugal, electrically driven and shall be connected to the central vacuum priming system. The pumps shall each have a capacity of 200 m3/h at 20 mWc. The stripping pumps shall be installed in the aft pump room, one at SB and one at PS. The distribution piping system shall consist of two suction/discharge mains connected at the fore and aft ends such forming a ring main. The suction/discharge lines from the PS WB-tanks are connected to one leg of the ring main and the suction/discharge lines of the SB WB-tanks are connected to the other leg of the ring man. The stripping ring main shall be installed at an elevation as low as possible. The stripping pumps shall be installed in the aft pump room, one at PS and one at SB side and shall have connections as follows: Suction from: Sea via cross-over Stripping ring main The stripping pumps shall each be provided with an emergency bilge suction.

Page 61

STILL IN PROGRESS 1/28/2005 3:26 PM

Discharge to: Sea SB and PS via overboard discharge main Stripping ring main via overboard discharge main Expansion joints are to be fitted in the ring mains to take up expansion, hogging and sagging. The suctions in the tanks are to be provided with bell mouths and with erosion plates underneath. Valves in the ballast stripping system shall be hydraulically actuated. Control of the valves shall be possible locally at the solenoid valve boxes and remote from the ballast control desk in the control room. In case of hydraulic power failure local manual operation of the valves shall be possible by means of a portable hand pump. Valve open/close indication shall be available locally at the valve and remote from the ballast control desk. Valves that are required for throttling shall have position indication from full open to the closed position. Start/stop of the stripping pumps shall be possible local at the pumps and remote from the ballast control console in the control room. Monitoring of the suction and discharge pressures of the stripping pumps shall be possible from the ballast control panel in the control room as well as locally at the pumps. 11.4 BILGE SYSTEM Reference is made to: 0240 DKC 02 005 Marine Bilge System Piping Diagram 0240 DKC 02 015 Marine Bilge Stripping System Piping Diagram 0240 SKC 03 003 Marine Main Machinery Equipment Specification A complete bilge system shall be installed comprising: Two (2) bilge pumps One (1) bilge water separator unit Two (2) bilge water stripping pumps Bilge piping system (main system) Bilge stripping piping system The system is to comply with the Classification Society and IMO MARPOL, for overboard discharges. The bilge system is to be based on a dry bilge concept with no system drains flowing into the bilge.

Page 62

STILL IN PROGRESS 1/28/2005 3:26 PM

11.4.1

Main bilge system The main bilge pumps shall be horizontal, centrifugal, electrically driven and be provided with a self priming device (air ejector). The pumps shall each have a capacity of 370 m3/h at 25 mWc. Start/stop of the bilge pumps shall be possible locally at the pumps and remote from the ballast control console in the control room. Bilge wells with a capacity of at least 0.15 m3 shall be arranged in the engine room and in the aft and forward pump rooms. The bilge wells shall be located one at each corner. A strum-box shall be applied for suctions from the bottom while a mud-box shall be applied at locations with a bilge well in a tank top. A bilge main is to be provided running over the length of the barge. Bilge suctions shall be provided from all WT compartments to the bilge main. In the aft pump rooms at PS and at SB an emergency bilge suctions shall be provided, connected to the ballast stripping pumps. In the engine room an emergency bilge suction shall be provided, connected to one of the cooling water pumps for a main diesel generator set. For the emergency bilge suctions in the engine room reference is made to 0240 DKC 02 003 Marine Seawater/Fresh water Cooling System Piping Diagram. For the emergency bilge suctions in the aft pump room reference is made to 0240 DKC 02 007 Marine Stripping System Piping Diagram. One bilge pump shall be installed in the engine room and one in the forward pump room and shall have connections as follows: Suction from: Bilge main Direct bilge suctions Discharge to: Overboard In each bilge well and in the vicinity of each strum-box a float-operated bilge highlevel alarm switch. shall be fitted The switches shall be connected to the machinery alarm and monitoring system.

11.4.2

Bilge stripping system A bilge stripping system shall be provided as a separate part of the bilge system. Start/stop of the bilge stripping pumps shall be possible locally at the pumps and remote from the ballast control console in the control room. The bilge stripping pumps shall be, piston-type, electrically driven and shall have a capacity of 2 m3/h at 45 m.
Page 63

STILL IN PROGRESS 1/28/2005 3:26 PM

The stripping system shall have its own suction main with branches from WT compartments where bilge water polluted with oil can be expected. One (1) bilge stripping pump shall be installed in the forward pump room and one (1) bilge stripping pump shall be installed in the ER. The bilge stripping pumps shall have suction connections from the bilge stripping main line and discharge to the dirty bilge water tank. A separate sludge or dirty oil pump shall be installed in the engine room. This pump shall have the same capacity and be of the same type as the bilge stripping pumps. This pump shall have a suction connection from the sludge/dirty oil tank and a discharge connection to a standard shore connection at main deck. The bilge stripping pump and the sludge pump in the engine room shall be provided with a drip tray complete with drain. The sludge tank and dirty bilge water tank are to be fitted with a float-operated high-level alarm switch. The high-level set point shall be at 80% of the tank content. Switches shall be connected to the machinery alarm and monitoring system. 11.4.3 Bilge water separator A bilge separator unit, comprising a separator vessel, a pump and a 15 ppm oil content monitor, shall be installed in the engine room. The bilge water separator shall have a capacity of at least 1 m3/h. The output oil content is to be not more than 15 ppm in accordance with IMO MARPOL requirements. The separator shall further be provided with connections for ancillary systems such as fresh water and service air. The bilge water separator unit shall be installed in the engine room and shall be provided with suction connection and return connection from/to the dirty bilge water tank and with a connection for separated oil to the double bottom sludge/dirty oil tank in the engine room. The unit shall further be provided with a clean water discharge connection to overboard (less than 15 ppm oil). 11.5 FIRE WATER EXTINGUISHING SYSTEM Reference is made to: 0240 DKC 02 005 Marine Bilge System Piping Diagram 0240 DKC 02 012 Marine Fire Water System Piping Diagram 0240 SKC 03 003 Marine Main Machinery Equipment Specification A firewater extinguishing system shall be installed comprising: Two (2) fire pumps Distribution piping system The firewater extinguishing system shall be capable supplying the water Page 64 demand

STILL IN PROGRESS 1/28/2005 3:26 PM

for two hose streams simultaneously and each provided with a 16 mm nozzle and maintaining a pressure at the hydrants of 2.7 barg. Nozzles shall be of dualpurpose type incorporating a shutoff. The fire pumps shall be capable to deliver 60 m3/h at 60 mWc for fire fighting purposes. A non-pressurized fire water main shall be installed with hydrants in the engine room, pump rooms and pipe tunnel segments. On the main deck in the vicinity of the main entrance to the engine room supply connections with two branches and an international shore connection shall be arranged. 11.6 FIXED CO2 FIRE EXTINGUISHING SYSTEM A CO2 fire extinguishing installation of the High Pressure Total Flood type shall be installed for the protection of the engine room. The system shall be in accordance with the CCS and SOLAS Rules and Regulations. The CO2 system shall be based on the following: Standard 45 kg CO2 cylinders All high-pressure components shall be located in a dedicated CO2 room. The cylinders shall be placed in suitable racks. Means shall be provided in the CO2 room for lifting/weighting of cylinders Two means of manual release of CO2 shall be provided: From inside the CO2 room From a stainless steel release panel located next to the engine room entrance Upon release a pilot line shall be pressurized with nitrogen which shall open the main valve and the valves of the CO2 cylinders after a time delay of minimum 30 seconds Opening of the CO2 release panel door shall initiate CO2 alarm inside the engine room and outside at the engine room entrance The alarm whistle shall be gas powered (CO2) From the CO2 room a distribution piping system complete with CO2 nozzles shall be installed in the engine room. 11.7 11.7.1 TANK AIR VENT SYSTEM & SOUNDING PIPES Tank air vent system Reference is made to: 0240 DKC 02 009 Marine - Air and Sounding System Piping Diagram Tank air vent pipes shall be installed for all tanks. All ballast tanks shall be
Page 65

STILL IN PROGRESS 1/28/2005 3:26 PM

provided with two vents. Tank vents lines shall be provided with automatic closing appliances (floater ball type tank vent check valves), with flame screens on oil tanks and dust screens on fresh water tanks. The height of the tank vent lines measured from the main deck to the point where water may have access shall be 760 mm. Tank vent lines shall be internally and externally galvanized except vents of oil tanks, which shall be externally galvanized only. Vent lines of water ballast tanks shall be provided with automatic drain valves (floater ball type check valves). Expansion joints are to be fitted in the ballast tanks vent lines to take up expansion, hogging and sagging. Vents shall be located at the forward side of the barge above main deck and be grouped within the inner bulkheads area of the barge. 11.7.2 Sounding pipes Sounding pipes shall be provided for all tanks and void spaces, complete with striking plates underneath and screw caps on top. Sounding pipes are to be located within the tanks they serve. Sounding pipes ending on the main deck shall be mounted flush in the deck. Fresh water tanks, potable water tanks, dirty bilge water tank and the MGO tanks shall not be equipped with sounding pipes. These tanks shall be equipped with a level gauge complete with bottom and top valves and supports. The double bottom tanks shall be fitted with short sounding pipes, ending above the floor level. These sounding pipes shall be provided with self-closing cocks and test cock. Sounding pipes shall have a nominal bore of 1 (40 mm) 11.8 POTABLE WATER / HOT WATER Reference is made to: 0240 SKC 03 003 Marine Main Machinery Equipment Specification A potable water system shall be provided to supply operating water to the bilge water separator and to supply domestic water to the sink in the office, as well as a shower on main deck.

Page 66

STILL IN PROGRESS 1/28/2005 3:26 PM

The system shall comprise: Two (2) potable water storage tanks each with a capacity of approx. 35m3. Bunker line (nominal bore of 2 ) with connections and isolation valves to the potable water tanks. Drain line (nominal bore 2) with connections and isolation valves from the potable water tanks to the bilge. Potable water hydrophore unit, capacity approx.2 m3/h @ 3.5 bar and a vessel capacity of approx. 300 liters. Active carbon filter UV filter Hot water boiler, capacity approx. 120 liter Distribution piping system The hydrophore unit shall have connections as follows: Suction from: Potable water tanks Discharge to: Bilge water separator Via active carbon filter to the hot and cold water mixer of the sink in the office Hot water boiler in the office Shower on main deck

A back flow preventer shall be provided in the supply line to the bilge water separator. From the hot water boiler a supply line shall be provided to the hot and cold water mixing tap at the sink in the office and shower on the main deck. Tank and system isolation valves/cocks shall be fitted as required. 11.9 SEAWATER/ FRESHWATER COOLING SYSTEMS Reference is made to: 0240 DKC 02 003 Marine Sea Water/ Fresh Water Cooling Water System Piping Diagram 0240 SKC 03 003 Marine Main Machinery Equipment Specification Cooling water systems shall be provided for the main diesel generator sets, auxiliary diesel generator set and for other auxiliaries, such as the AC-unit.
Page 67

STILL IN PROGRESS 1/28/2005 3:26 PM

11.9.1

Main diesel generator sets The cooling water pipe line systems for the Main diesel generator sets shall be arranged for seawater cooling drawn from the seawater cross over line, as well as from the fresh cooling water circulation tank in the double bottom. Each Main diesel generator set shall be equipped with a heat exchanger capable to match the total cooling requirements of the diesel engine. A dedicated cooling water pump, provided with a self priming device (air ejector) shall be installed for each set with a suction line from the seawater cross-over line and from the double bottom fresh cooling water circulation tank. Discharge lines to overboard (PS and SB) and to the double bottom fresh cooling water circulation tank shall be installed. Change-over valves shall be provided in the suction lines close to the cooling water pumps and in the discharge lines as close as possible to the heat exchangers, to allow cooling of the diesel engines with seawater or cooling with fresh water by circulating through the double bottom tank. Drain valves shall be installed for draining of seawater in case of changeover to freshwater cooling. Fresh cooling water suction point and discharge point shall be arranged as wide as possible from each other. (suctions aft between fr.70-71, discharges forward between fr.79-80) One of the cooling water pumps shall be provided with emergency bilge suction. A seawater inlet crossover line shall be installed, capable of drawing water from a high inlet chest sited at SB in a ballast tank and from a low inlet chest in the engine room. Sea inlet grids shall be installed in the sea chests and two strainers shall be provided in the crossover line each with two isolating valves.

11.9.2

Auxiliary diesel generator set The auxiliary diesel generator set shall be equipped with a built-on heat exchanger and a dedicated cooling water pump, provided with a self priming device (air ejector). Only freshwater cooling shall be applied for the auxiliary diesel generator set by circulation through the double bottom fresh cooling water tank. A suction line and discharge line from / to the double bottom tank shall be installed. Suction point and discharge point shall be arranged as wide as possible from each other. (suction between fr.70-71, discharge between fr.79-80)

11.9.3

Auxiliaries Two (2 x100%) cooling water pumps, provided with a self priming device (air ejector) shall be installed in the engine room for cooling of the AC-unit, compressed air after cooler and the ballast vacuum system in the pump room. A suction line from the double bottom fresh cooling water circulation tank shall be installed to the cooling water pumps and discharge lines to the consumers. Page 68 Return lines from the consumers shall be provided connected to a common line to

STILL IN PROGRESS 1/28/2005 3:26 PM

the double bottom circulation tank. Suction point and return point penetrating the double bottom, shall be arranged as wide as possible from each other. (suction between fr.70-71, discharge between fr.79-80) 11.10 COMPRESSED AIR SYSTEM Reference is made to: 0240 DKC 02 004 Marine Compressed Air System Piping Diagram 0240 SKC 03 303 Marine Main Machinery Equipment Specification A combined service and start air system shall be provided consisting of the following major components: Two(2) air compressors Two(2) air receivers One(1) after cooler One (1) dryer A complete service air piping system shall be installed throughout the barge with service connections at suitable places in the engine room, auxiliary room, workshop, pipe tunnel segments, pump room aft and forward. A service air line shall be installed to the main deck with service points for portable air tools. Service air connections shall be complete with a valve and quick type hose connector. Air connections shall also be provided to all sea inlet chests with pressure reducing station and safety valve in accordance with the CCS Rules. For charging of the freshwater hydrophore vessel an airline with hose connector shall be installed as well. Drain cocks shall be fitted at the lowest points of the system and just up stream of the pressure reducing stations. Starting air piping shall be arranged to supply air for starting of all main diesel generator sets. The diesel generator sets shall be delivered with a complete builton starting air system including a starting air motor. The piping system shall be arranged to allow both air receivers to be connected to the service air system as well as to the starting air system. Both air receivers shall be fitted with safety valve, pressure gauge, inspection openings, and automatic drain with drain line to the bilge. In the air supply for control air to the tank gauging system absorption type airdryer will be fitted. This will be located in the forward pump room. Two air compressors shall be installed to maintain a normal system pressure of Page 69

STILL IN PROGRESS 1/28/2005 3:26 PM

8.5barg in the air receivers. The pressure switch of one air compressor shall be adjusted at 8.5barg, the other one at 7.5barg. The design pressure of the piping system shall be 11barg. An after cooler shall be installed with water separator and automatic drain and drain pipe to the bilge system. 11.11 FUEL OIL SYSTEM Reference is made to: 0240 DKC 02 001 Marine - Fuel Oil System Piping Diagram 0240 SKC 03 303 Marine Main Machinery Equipment Specification A complete Marine Gas Oil (MGO) system shall be provided including filling, service, discharge and transfer arrangements. Two (2) fuel oil tanks shall be built in the engine room (structural steel tanks) with one filling line from the filling station on main deck. Vent lines to the main deck shall be provided with tank vent check valves with flame screens and gate valves to be locked in the open position. Each MGO tank shall be fitted with high and low level alarm, level gauge and a self-closing water drain valve. All suction connections shall be provided with quick closing valves on the tanks. The quick closing valves shall be operable from the main deck. High and low suctions shall be installed in the MGO tanks and connected to supply lines with strainers to the diesel engines. Return lines shall be routed from the diesel engines to the top of the tanks. Anti-siphoning holes shall be drilled in the return pipes within the tanks. A MGO transfer pump shall be installed with suction lines from both tanks and discharge manifold with pipelines to both tanks and the main deck (filling station). Local start / stop facilities shall be provided and an emergency stop from the main deck. The MGO tanks, MGO transfer pump and diesel engines shall be provided with drip trays and drain lines (1) to the sludge/dirty oil tank, located in the double bottom. For sludge/dirty oil tank refer to the Bilge Stripping System in section 11.4.2. The filling station on main deck shall be provided with drip tray and drain cock.
Page 70

STILL IN PROGRESS 1/28/2005 3:26 PM

11.12

LUBRICATING OIL SYSTEM Reference is made to: 0240 DKC 02 002 Marine Lubricating Oil System Piping Diagram 0240 SKC 03 303 Marine Main Machinery Equipment Specification A complete lubricating oil system shall be provided including filling, service and discharge arrangements. A lubricating oil storage tank shall be installed in the engine room with a filling line from the filling station on main deck. One (1) lubricating oil transfer pump shall be installed with suction strainer and suction connection from the storage tank. The transfer pump shall be provided with a discharge line to the diesel engines with hose connection for filling of the crankcases. Gravity filling of the crankcases shall also be possible. The main diesel engines shall have a built-on electrical driven pre-lube oil pump, which also can be used for draining of the crankcases to the sludge/dirty oil tank. The auxiliary diesel engine shall have a manual pre-lube oil pump for this purpose. Lubricating oil storage tank and lube oil pump shall be provided with drip trays and drain lines to the sludge/dirty oil tank, located in the double bottom. For sludge/dirty oil tank refer to the Bilge Stripping System in section 11.4.2. From each diesel a crankcase vent line shall be arranged up to above the main deck with flame screen and gate valve locked in the open position.

11.13

VENTILATION AND AIR CONDITIONING SYSTEMS Reference is made to: 0240 DKC 02 013 Marine HVAC Principle Diagram 0240 SKC 03 303 Marine Main Machinery Equipment Specification Mechanical ventilation systems shall be installed for the pump rooms, pipe tunnel segments, engine room, battery room, switchboard room and CO2-room. The control room and office shall be provided with an air conditioning system. Although the maximum ambient temperature shall be 45C, the design inlet temperature for mechanical ventilation may be taken as 40C, and engine room temperature as 50C (maximum temperature increase of 10C in ER).
Page 71

STILL IN PROGRESS 1/28/2005 3:26 PM

11.13.1

Pump room and pipe tunnel Supply ducting with axial flow fans shall be installed for air distribution through the rooms. The air inlet fans and exhaust fans shall be installed in fan rooms on main deck. Hydraulic actuated valves shall be installed in the supply duct at the watertight bulkheads between the pump rooms and pipe tunnel segments . Also for air exhaust hydraulic actuated valves shall be installed at the WT-bulkheads between the pump rooms and pipe tunnel segments. To operate the supply duct valves, the valves shall be connected to the hydraulic power system of the ballast valves. Control of the valves shall be possible locally at the solenoid boxes and remote from control room. In case of hydraulic power failure local manual operation of the valves shall be possible by means of a portable hand pump. Open/closed indication shall be available locally in the pipe tunnel and remote in the control room. Supply and exhaust fans shall be locally started and stopped and remotely from the control room.

11.13.2

Engine room Six (6 x 16.67%) supply fans shall be provided for ventilation of the engine room and shall be installed in an air inlet housing (fan room) on main deck. Air inlet housing shall be fitted with weather louvers. Supply ducting shall be installed for air distribution through the engine room. Exhaust ducting shall be provided from tween deck to main deck, terminating in an air outlet housing on main deck and fitted with weather louvers. The pressure drop across the total exhaust routing shall not exceed 50-60Pa. For air supply to the Passage on tween deck, a duct shall be branched from the engine room supply duct. Air is exhausted via the engine room outlet housing.

11.13.3

CO2-room For ventilation of the CO2-room, an exhaust fan shall be installed with ducting extended to near the tween deck. Ventilation goosenecks with gate valves shall be provided for air inlet and air outlet on main deck.

11.13.4

Spare parts room The spare part room form part of the engine room and the ventilation of these rooms shall be integrated with the engine room ventilation.

Page 72

STILL IN PROGRESS 1/28/2005 3:26 PM

11.13.5

Control room and office Control room and office shall be air-conditioned for which a self-contained AC-unit shall be installed in the control room. Conditions for design/selection of AC-unit: Summer Outside Inside Winter Outside Inside 45 C 55% R.H. 270C 50% R.H. -200C 200C

Supply ducts shall be routed from the AC-unit through the control room and to the Office for air distribution. Balancing dampers shall be fitted where necessary. Return of air from the Office to the AC-unit shall be possible through a louver in the Office wall. For fresh air supply from outside an air pipe shall be installed from the main deck and connected to the AC-unit. The pipe shall be suitable for a flow rate of approx. 700 m3/hand be provided with a goose neck and with a gate valve. An air pipe for natural exhaust shall be installed for the Office, suitable for a capacity of approx. 700m3/h and complete with goose neck and with gate valve. 11.14 GREY WATER SYSTEM Reference is made to: 0240 SKC 03 300 Marine - Main Machinery Equipment Specification Waste water from the sink in the Office shall be collected in a grey water double bottom tank, located in the engine room. A drain line with siphon shall be installed from the sink to the grey water tank. The grey water tank shall be provided with a vent pipe, level gauge, and manhole. To evacuate grey water from the tank, a centrifugal pump shall be installed in the engine room complete with suction line and stop valve, and strainer. For overboard discharge a pipe line shall be made, complete with stop-check valve. Also for discharge to the main deck a pipeline with stop valve and International shore connection shall be provided. Suction and discharge manometer shall be fitted.

Page 73

STILL IN PROGRESS 1/28/2005 3:26 PM

11.15

DIESEL ENGINE EXHAUST GAS LINES For main diesel engines and the auxiliary diesel engine, exhaust gas lines will be installed to the main deck. Each exhaust gas line will be fitted with a silencer/spark arrestor (supplied with diesel engines) and expansion bellows to suit thermal expansion. The exhaust pipe will be fitted with a flanged connection on exiting the deck house, so that the top of the line can be removed when transporting large jackets Fixed supports will be made at one side of the expansion bellows and at one side of the silencers and further sufficient number of sliding points along the lines. Each exhaust gas line will be provided with a condense-water trap, gate valve and drain line to the bilge. The exhaust pipes and silencers shall be insulated with rock wool with a thickness of 3 in the engine room and 2-thickness in the casing (from tween-deck to outside) and be lagged with stainless steel sheeting. The expansion bellows shall be insulated with removable quilted blankets.

11.16

PIPING AND VALVE SPECIFICATION For the piping and valve specification reference is made to SKC 03 004 Marine Piping and Valve Specification.

Page 74

STILL IN PROGRESS 1/28/2005 3:26 PM

12. 12.1 12.1.1

SAFETY SYSTEMS FIRE FIGHTING EQUIPMENT Fixed CO2 system Fixed CO2 fire extinguishing installations of the "Total Flood" type shall be supplied according to CCS and Authority requirements the Engine room. The specification of the fixed fire extinguishing system for the Engine Room is given in Section 11.16.

12.1.2

Loose equipment Portable fire fighting equipment shall be supplied in accordance with the requirements of the regulatory bodies. Portable refillable A, B, C dry powder and CO2 fire extinguishers shall be provided in accordance with Classification Society. All portable extinguishers shall be numbered and provided with suitable supports for installation at proposed location. Two (2) firemen suits with equipment shall be delivered according to SOLAS requirements and stowed in suitable lockers. The firemans outfit shall be with CCS type approval certificate Four (4) sets of self contained (SC BA) 30 min breathing apparatuses, Sabre Centurion brand or equal, shall be provided to Owners approval. Two (2) of these sets are to be provided in the machinery space.

12.1.3

Deck wash A deck connection for fire water/deck washing shall be provided, supplied by fire pumps. Refer to section 11.5

12.1.4

Insulation The following spaces shall be A60 insulated: Emergency access staircase at aft of machinery room Control and switchboard room CO2 room

12.2

FIRE DETECTION SYSTEM A fire detection system shall be installed, fully in compliance with the requirements of Authorities.

Page 75

STILL IN PROGRESS 1/28/2005 3:26 PM

The system shall at least perform/indicate the following: Office, switchboard room and control room heat/ thermal radiation and smoke detection Office, switchboard room and control room heat/ thermal radiation door closures activation and air conditioning intakes Engine room and pump rooms heat/ thermal radiation and smoke/ flame detection Break glass station color coding alarms System test Fuel cut-off, air intakes closing, watertight doors closing and CO2 releasing will be performed manually from the fire station outside the entrance of the ER. The system shall be an addressable type that shall give an unambiguous indication in the central control room of where the event is detected. Thermal detectors, smoke and flame detectors, and manual call points shall be provided in the office, switchboard room, control room and machinery spaces. 12.3 FIRE AND GENERAL ALARM SYSTEM A fire and general alarm system shall be provided with the main fire detection panel in the control room. A fire-fighting plan shall be displayed adjacent to the panel, showing the spaces covered. Location of fire flaps to be indicated on the plan. Switches for fire alarm and general alarm shall be provided at the exits from spaces and in pipe tunnel. Alarm bells for fire and general alarm and rotating flash lamps in machinery spaces and work areas shall be provided. 12.4 LIFE SAVING EQUIPMENT The life saving equipment shall be according to the Authoritys requirements (SOLAS) and Technical Regulations for Statutory Survey of Ships and installations Non International Voyage Ships, Section 2.14(2) of Chapter 2, Part 4. Reference is made to drawing 0240 DNC 05 001 Barge Safety and Escape Routes Plan. The life saving equipment is sized for a maximum number of 15 people on board.

Page 76

STILL IN PROGRESS 1/28/2005 3:26 PM

The following life saving appliances shall be provided as a minimum. Two (2) inflatable rafts of 15 persons capacity, one on each side Fourteen (14) pieces of life buoys Fifteen (15) lifejackets Fifteen (15) working lifejackets One (1) piece of line-throwing appliance Twelve (12) pieces of rocket parachute flare

Page 77

STILL IN PROGRESS 1/28/2005 3:26 PM

13. 13.1

ELECTRICAL SYSTEM GENERAL The electrical installation shall comply with the rules and requirements as described in Chapter 3. The Electrical equipment shall be suitable for a humid, salt laden atmosphere with vibrations and accelerations normal to a marine environment. The following electric systems shall be installed on board: 380V, 50Hz, 3ph, for main generators and Barge auxiliaries 230V, 50Hz, for small consumers, general and engine room alarms, ballast controls, navigational lighting and PA system small power VHF radio

13.2 13.2.1

SWITCHBOARD/ MCC Switchboard S-C4101 The switchboard/ MCC shall be of the dead front type, drip-proof construction, well ventilated and provided with lifting eyes. The front shall have hinged panel doors and handrails and the rear side shall have detachable panels. All parts shall be accessible for inspection, maintenance or replacement. Degree of protection shall be IP23. Oil resistant, insulating matting shall be provided in front and back of the switchboard. The switchboard shall be installed consisting of: Three incoming feeders from the diesel generator sets Four starter panels for the ballast pumps complete with auto transformers Withdrawable drawers for motor starters and consumer feeders One incoming feeder from the aux. diesel generator set for start up purpose One Bus Tie panel Shore supply incoming feeder Two 380V/ 230V transformer supply panels Synchronizing Equipment Reference is made to 0240 SEC 41 003 Electrical LV Switchgear / MCC Specification

Page 78

STILL IN PROGRESS 1/28/2005 3:26 PM

13.2.2

Distribution Panel S-C4601 The panel shall be a wall mounted distribution board. All parts shall be accessible for inspection, maintenance or replacement. Degree of protection shall be IP23. The switchboard shall contain all lighting groups and small power consumers. Reference is made to 0240 SEC 41 003 Electrical LV Switchgear / MCC Specification

13.3

TRANSFORMERS Transformers for the supply to the lighting distribution shall be cast resin type protection IP23, insulation class B or better, designed for marine service provided with natural cooling.

13.4

380V AC MOTORS All 380V AC motors shall be of the induction type with squirrel cage rotors. All motor design shall be based upon +50C ambient temperature. The insulation of all motors shall be class F, the maximum temperature rise shall be for class B insulation. If two speed motors are applied these motors shall employ a separate winding for each speed, motors with tapped windings are not acceptable. Both ends of all windings shall be brought out to the terminal box, where the star or delta connections shall be made. The enclosure for all motors shall be totally enclosed, with or without fan cooling, IP 44. For all motors on main deck minimum protection shall be IP 56. The construction of all motors shall be suitable to guarantee a proper working order up to a trim angle of 12 degrees. Motors above 5kW shall be fitted with 230V anti condensation heating elements, supplied from the motor starter control transformer when the motor is not running. Motors above 100 kW shall be fitted with thermistors embedded in the stator windings. Motors in extreme wet or cold rooms are to be provided with anti condensation heating elements. Alternatively heating arrangement via windings, using a low voltage, can be used.
Page 79

STILL IN PROGRESS 1/28/2005 3:26 PM

13.5

AC MOTOR STARTERS All motor starters shall be designed for marine application, withstanding the high moisture environment and normal shipboard vibration. All equipment in the motor starter shall be rated for a 50C ambient temperature. All AC motor starters for motors of less than 100 kW shall be of the direct online type. For motors above 100 kW an auto transformer type starter will be provided. Star-delta starters shall not be used. Generally, starters shall contain: Isolating switch with locking device Magnetic contactor with auxiliary contacts Temperature compensated, thermal overload relay, with single phasing protection Necessary control relays Set of control fuses Control circuit step down transformer Control pushbuttons start/stop Running light Power indicating light All AC motor starters shall be concentrated in the 380V Motor Control Center (MCC).

13.6

CABLES Only cables of class approved make shall be used. Three phase circuits shall generally be supplied through three core cables. Two or more identical three core cables in parallel may be used for the larger capacities. All cables shall have cores of stranded copper, with ethylene propylene rubber (EPR) or cross-linked polyethylene (XLPE) insulation. Maximum conductor temperature shall be 85C. For 380V circuits at least 600/1000 V grade cables shall be used. For 230V and lower voltage circuits 250V grade cables may be used. All cables shall have the following properties in case of fire: Halogen free Flame retarding Low smoke generation. Some cables shall have fire resistant properties in addition, e.g. for emergency lights, emergency stops and general alarms. All power cables shall be of the armored or screened type, all other cables shall Page 80

STILL IN PROGRESS 1/28/2005 3:26 PM

be of the screened type with copper wire braiding between inner and outer sheath. The minimum conductor size for power and lighting circuits shall be 2,5mm2. The maximum voltage drop from main switchboard to final consumers shall not exceed 6% of the nominal voltage. Multicore cables with more than four (4) conductors shall have one (1) spare conductor for each five (5) conductors in use. Cables shall as far as practical not be installed in areas exposed to the weather, heat dissipating surfaces or inaccessible spaces. Exposed runs, where necessary, shall be kept as short as possible. Where cables penetrate watertight bulkheads or decks, watertight stuffing tubes shall be provided. At deck penetrations kick plates shall be provided. Penetrations of multiple cables through watertight bulkheads and decks shall be made by means of multi cable transits type Brattberg, Hawke or equivalent. Additionally all accessories shall be as recommended by the cable transit manufacturer. 13.7 13.7.1 LIGHTING AND SMALL POWER Lighting The lighting shall be compensated fluorescent lighting fixtures, designed for 230V AC, 50Hz and single phase. Illumination intensity shall be in accordance with the rules, but at least as follows: Engine room, pump rooms or machinery space 200 lux Offices, switchboard room and control room 300 lux Illumination levels shall be determined by applying a maintenance factor of 75% to initial values, to allow for deterioration of lamps, reflectors, enclosures and painted surfaces. Suitable flush lights shall be provided on the deck houses. 13.7.2 Emergency lighting 30% of the total amount of light fixtures shall be fed via a separate distribution panel. The light fixtures shall be provided with battery back-up and shall be situated in emergency access routing and in areas where emergency lighting is necessary for safe disembarkation of personnel in case of total black-out or other emergency situations. 13.7.3 Navigation lighting Navigation lights following the rules shall be installed on deck. The lighting shall Page 81

STILL IN PROGRESS 1/28/2005 3:26 PM

be installed on removable masts at the front and back of the Barge, port and starboard lights to be installed at the back of the Barge. The forward lights shall have a dedicated battery placed in the battery room. The aft lights shall have a dedicated battery in a suitable battery box in the aft section of the pipe tunnel in near vicinity of the light. All batteries shall have a dedicated replacement battery situated in the battery room, charged and ready for operation. The batteries shall be charged via the battery chargers in the battery room. According CCS requirements the barge shall be provided with three ball shaped and one diamond shaped signals and one portable day communication flash light. The horizontal arc of light limited for operational ability and not under command light covered by signal shall not be more than 6 deg. The Barge shall be provided with one fore and one aft anchor light. The fore anchor light shall be 4.5 m higher than the aft light. The aft light shall be installed near the stern. In addition the navigation light system will be equipped with a photocell. 13.7.4 Small power Power supply for power operated handheld tools, hand lamps and small VHF Radio be of the double isolated type supplied via suitable marine type socket outlets approved by Class and other relevant authorities. 13.8 BATTERY SYSTEM A battery system shall be provided in a dedicated battery room complete with battery chargers and suitable battery rack to fit all required batteries. At the start of the auxiliary diesel-generator set the batteries shall be charged via two main battery chargers sized to fit the total capacity of all batteries installed comprising start batteries for the auxiliary diesel and navigational light batteries. Batteries shall be low maintenance NiCd type batteries that allow for longer periods of non-charging to operate. The batteries are sized for 60 days operation. 13.9 SHORE SUPPLY The barge will be equipped with a shore connection to feed the main switchboard with power from shore. The connection will be located at the main deck next to the entrance to the Engine Room. A manual winch with 100 meters shore power cable will be fitted on the main deck in way of the shore connection.

Page 82

STILL IN PROGRESS 1/28/2005 3:26 PM

13.10 13.10.1

CONTROL AND ALARM SYSTEMS General A detailed description of the Barge control and alarm system is given in 0240 SEC 51001 Instrumentation Control System - Specification

13.10.2

Alarm & Monitoring System The Barge shall be equipped with at least the following alarm systems: General alarm Engine alarm and monitoring Fire detection alarm Fire fighting alarm (CO2, or other) The engine room alarm and monitoring system shall comprise as a minimum the following measuring points: For each of the generator diesel engines - Lubrication oil pressure - Lubrication oil temperature - Cooling water pressure - Cooling water temperature - Overspeed - Exhaust temperature alarm Additional alarms: - Fuel Oil level alarms - Auxiliary equipment alarm points - Bilge level alarms - Escape hatch and watertight door switches - Common alarm of package units (HPU, AC) - Min 20% or 15 alarm points spare inputs and outputs, whichever is more

13.10.3

Control System The Barge shall be equipped with a manual remote control system for remote operated equipment, i.e. ballast system, fire and bilge pumps, connected to the Alarm and Monitoring System. Loading computer complete with TFT bulkhead mounted touch screen and printer shall be installed in the CR. The loading computer shall be complete with software and interface with all level measurements via the Alarm & Monitoring PLC. Package units at different locations shall be locally controlled with only a common alarm to the alarm & monitoring system, unless otherwise specified. Locally operated equipment shall have running and trip lamps fitted in the 83 Page

STILL IN PROGRESS 1/28/2005 3:26 PM

switchboard mimic with a one common alarm signal (one of any of the locally operated equipment) to the Alarm & Monitoring system. The Fire detection and alarm system shall be separate from the Alarm & Monitoring system fully complying with IMO/SOLAS regulations. Switchboard, Alarm & Monitoring system, Fire Detection and alarm system and operating console are installed in the control room. The central fire control panel with ESD panel and CO2 release shall be installed near the entrance to the machinery room on main deck. 13.11 INTERNAL COMMUNICATION EQUIPMENT The barge will be equipped with a public address system, comprising loudspeakers in the forward and aft pump room, office, engine room, deck house, workshop, pipe tunnel and a microphone station in the control room. Type and size of cables for interconnecting stations, loudspeakers and central unit will be specified by the manufacturer of the system. Power supply will be via an UPS.

Page 84

STILL IN PROGRESS 1/28/2005 3:26 PM

14. 14.1

PRESERVATION SYSTEM GENERAL The corrosion control system (coating and cathodic protection) of the exterior hull surfaces, interior spaces and tanks shall be defined for at least 60 months protection, without dry-docking. All steel structures, spaces, housing, equipment, piping and other steel and all inside and outside areas shall be painted in accordance with the requirements as specified in this section.

14.2 14.2.1

PAINT SYSTEM General It shall be Yard's responsibility to apply an adequate paint system for a Barge suitable for world-wide operation. Methods and conditions of application shall be strictly in compliance with the paint Manufacturer's instructions. Yard's proposal shall be submitted for approval to the Owner, prior to ordering. The paint system for the hull shall be at least equivalent to the following:

14.2.2

Surface preparation Unless indicated otherwise, all fabrication and assembly shall be complete before starting surface preparation. All surfaces to be coated shall be properly prepared according to the paint manufacturer's specifications prior to application of any paint. Surface preparation and coating shall be scheduled by Yard to best practice and to avoid (a) damage to surrounding areas/systems (b) reworking of areas. Shop primer shall be removed completely by means of blasting till ISO 8501-1, SA 2, unless it is proven to be compatible with the final system, in which case it shall be sweep blasted to at least SPSS-Ss. Rusty and bare surfaces shall be blasted to ISO SA 2.

14.2.3

Under water part (Bottom and side shell up to 5 meter waterline) 1 coat 50 DFT Epoxy Primer 2 coats 150 DFT each Free Epoxy 1 coat 80 each DFT - Tin free Anti-Fouling Long Life
Page 85

STILL IN PROGRESS 1/28/2005 3:26 PM

14.2.4

Side shell above water (from 5 meter waterline) and rocker arm 1 coat 50 DFT Epoxy Primer 2 coats 150 DFT Tar Free Epoxy

14.2.5

Decks; exposed and interior 2 coats 150 each Epoxy Mastic 1 coat 50 Epoxy Topcoat

14.2.6

Walls and underside decks; pump rooms, engine room and pipe tunnel segments 1 coat 80 DFT Sealer 1 coat 50 DFT undercoat 1 coat 50 DFT Enamel

14.2.7

Tanks Stripe coat 2 coats 200 DFT each Epoxy Mastic of light color.

14.2.8

Ballast Tanks Stripe Coat 2 coats solvent/chemical resistant Epoxy Mastic of light color 200 DFT

14.2.9

Void spaces 1 coat of Tar Free Epoxy 200 DFT

14.2.10

Office, control room and switchboard room Unexposed steel surface behind paneling or insulation: 1 coat primer 80 DFT Floors: 1 coat primer 80 DFT 2 layers marine deck paint 80 - non skid type for last coat

14.2.11

Outfitting Deck outfitting (masts, skid beams, bollard, brackets, etc) 2 coats 150 each Epoxy Mastic 1 coat 50 Polyurethane Topcoat as proposed hull topside Ventilators (inside) 2 coats 150 DFT each Epoxy Mastic Ventilation ducts (inside), non galvanized 1 coat of Primer 80

Page 86

STILL IN PROGRESS 1/28/2005 3:26 PM

Ventilation ducts (inside), galvanized No paint In general all outfitting such as doors, ladders, handrails etc. shall be painted as specified for the space in which they are located. 14.2.12 Miscellaneous steel In general all piping shall be treated with approved anti-corrosive coatings. All ballast piping, tank over-flow pipes, drain pipes, fresh and salt water pipes, air or gas lines, etc. shall be galvanized steel or approved corrosive resistant material such as PVC or copper-nickel. All bolts and nuts and other fasteners shall be cadmium plated, galvanized, or coated with an approved anti-corrosive coating. All steel wire ropes shall be drawn galvanized. This includes all wire ropes for hoists, tow lines, etc. All wire ropes shall have certificates. All light fittings for external use shall be made of aluminum or of galvanized steel. 14.3 INSPECTION AND TESTING All surfaces shall be inspected by the Yard's inspector prior to inspection by the Owner's representative. Safe and adequate staging and lighting shall be provided for inspection. Yard shall supply an inspection program. The Owner shall be represented by an inspector to ensure that the specifications for the job are complied with. All aspects of the work shall be accessible to the Owner's inspector. The inspector shall have the authority to inspect any materials, tools or equipment used in the coating procedures and surface preparation operations. He shall have the right to condemn any and all material, work or equipment, which does not comply with this specification. The test shall comprise the following: Performance test Film thickness Adherence test 14.4 GALVANIZING All equipment in connection with wood, canvas, fiber, ropes, etc. and as described in the different sections in this specification shall be heavily galvanized, Page 87 such as:

STILL IN PROGRESS 1/28/2005 3:26 PM

Lashing equipment for life rafts, foundations etc. Outside railings Protection rails Fittings for ladders and walkways Ventilation grids Raised floor plates

Furthermore, protection covers including hangers, hinges, holders for cables, ventilation ducts, pipes and similar outfit and equipment shall also be heavily galvanized, including hangers for portable fire extinguishers. 14.5 INTERNAL CATHODIC PROTECTION In addition to the specified paint system, all seawater tanks, and seawater inlet chests shall be protected by means of a suitable number of sacrificial anodes. Zinc and/or aluminum anodes shall be fitted, suitable in number and configuration for an average of 20 mA/m, giving at least 5 years protection against galvanic corrosion based on 8% bare steel. Location, size and number of anodes shall be in harmony with the paint system, according to manufacturers' recommendations and to Owner's approval. Double plates shall be mounted (continuously welded) to the plating behind the anodes. The anodes shall be fastened to the double plate in an approved manner, to allow easy replacement, to Owner's satisfaction. 14.6 EXTERNAL CATHODIC PROTECTION Yard to specify and supply sufficient sacrificial anodes for protection of hull. Zinc and/or aluminum anodes shall be fitted, suitable in number and configuration for an average of 20 mA/m, giving at least 5 years protection against galvanic corrosion based on 8% bare steel. Location, size and number of anodes shall be in harmony with the paint system, according to manufacturers' recommendations and to Owner's approval. Double plates shall be mounted (continuously welded) to the plating behind the anodes. The anodes shall be fastened to the double plate in an approved manner, to allow easy replacement, to Owner's satisfaction.
Page 88

STILL IN PROGRESS 1/28/2005 3:26 PM

15. 15.1

BARGE MAINTENANCE MAINTENANCE EQUIPMENT On the Barge various maintenance equipment shall be provided in accordance with the Owners requirements. A workshop area shall be provided with vertical drilling machines, welding transformers and grinding machines. Also a workbench, bench vice, injection nozzle test bench, steel lockers, drawers and shelves as well as all necessary tools shall be provided. The normal engine room maintenance inventory shall be installed. Deck connections for welding, air and power shall be provided.

15.2

HOISTING EQUIPMENT Hoists shall be provided as follows: For the main diesel engine generators and ballast pumps; two as per Manufacturer's specification. Hand operated trolley of 50 kN. Hand operated chain hoist with lifting capacity of 50 kN For auxiliaries: Hand-operated chain hoists with lifting capacity of 50 kN. Final arrangement of trolleys, beams and lifting equipment to be advised by Owner. Suitable hoisting equipment such as trolley, beam and lifting pad-eyes etc. shall be provided for equipment over 40 kg.

Page 89

STILL IN PROGRESS 1/28/2005 3:26 PM

APPENDIX I

DOCUMENT LIST

Page 90

STILL IN PROGRESS 1/28/2005 3:26 PM

0240 Document List

CONCEPT DESIGN S M D S C C C C C C C C 01 01 01 01 001 001 001 002 Barge Barge Barge Barge Basis of Design Conceptual Design Conceptual General Arrangement Technical Outline Report Report Plan Specification

BASIC DESIGN GENERAL DESIGN D D D D D D D D D D D D D D S C C C C N N N N N N N N N N N N N N N N N N N C C C C C C C C C C C C C C C C C C C 01 01 01 01 01 01 01 02 03 03 03 04 05 05 01 01 01 01 01 001 002 003 004 005 006 007 001 001 002 003 001 001 002 001 001 003 007 008 Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge General Arrangement General Arrangement - Elevations with Jacket Launching Machinery Spaces Plan Views Pump Room Aft Pump Room Forward Machinery Spaces Longitudinal Sections Machinery Spaces Transverse Sections Lines (Hull Shape) - Aft and Fore Body Tank and Capacity Tank Sounding Table Watertight Subdivision Deck Load Safety and Escape routes Fire Fighting Control Yard Lightship Weight Deadweight Definition Basic Design Cost Estimate Plan Plan Arrangement Arrangement Arrangement Arrangement Arrangement Plan Plan Report Plan Plan Plan Plan Specification Calculation Report Report Report Report

NAVAL ARCHITECTURAL DESIGN C C C C C C C N N N N N N N C C C C C C C 01 01 01 01 01 01 01 002 006 004 005 009 010 011 Barge Barge Barge Barge Barge Barge Barge Towing Resistance Mooring system Hydrostatic Particulars Report Loading Conditions and Intact Stability Launch Analysis Strength, Stability and Motions Load-Out Analysis Motion Analysis - transit Calculation Report Calculation Report Calculation Report Calculation Report Calculation Report Calculation Report Calculation Report
Page 91

STILL IN PROGRESS 1/28/2005 3:26 PM

D D D D D D D D D D D C C C D D D C C

V V V V V V V V V V V V V V V V V V V

C C C C C C C C C C C C C C C C C C C

01 01 02 03 01 01 01 01 01 01 01 01 01 20 01 01 01 10 20

001 002 010 020 030 040 041 042 043 050 051 001 006 001 110 111 112 003 002

HULL STRUCTURAL DESIGN: Midship Section With Sectional Barge Properties Barge Midship Section WT Bulkhead Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Barge Bottom and Side Shell plating Main deck and horizontal sections Longitudinal Sections and Bulkheads Transverse Sections and Bulkheads 01 Transverse Sections and Bulkheads 02 Transverse Sections and Bulkheads Engine Room Fore Transverse Sections and Bulkheads Forepeak Stern with reinforcements & Support structure Hinge Point Barge Integration Global Hull Scantlings & Midship sectional properties FEM Aft ship Analysis during Launching Material Weight Take Off Sea Chests Low Sea-Inlet Aft Sea Chests Low Sea-High Inlet Sea Chests Low Sea-Low Inlet Local Strength Deck Strength Information

Basic Construction Plan Basic Construction Plan Basic Construction Plan Basic Construction Plan Basic Construction Plan Basic Construction Plan Basic Construction Plan Basic Construction Plan Basic Construction Plan Basic Construction Plan Basic Construction Plan Calculation Report Report Report Basic Construction Plan Basic Construction Plan Basic Construction Plan Calculation Report Data sheet

D D D D D D D

V V V V V V V

C C C C C C C

15 15 15 15 15 15 15

001 002 003 010 020 030 040

HULL OUTFITTING: Barge Towing Gear Equipment Barge Fender and Bollard Equipment Barge Capstan and Anchor winch Equipment Barge Towing Gear Equipment Barge Fender and Bollard Equipment Barge Capstan and anchor winch Equipment Barge Watertight Hatches and manhole covers Equipment

Arrangement Arrangement Arrangement Basic Construction Plan Basic Construction Plan Basic Construction Plan Basic Construction Plan

Page 92

STILL IN PROGRESS 1/28/2005 3:26 PM

JACKET LOADING AND LAUNCHING EQUIPMENT: D D C C D S D D D D C S D D M M M M M M M M M M M M M M C C C C C C C C C C C C C C 01 02 01 01 02 02 02 02 03 03 01 03 01 01 001 001 001 002 002 001 004 005 001 002 100 002 003 060 Launch Launch Launch Launch Launch Launch Launch Launch Launch Launch Launch Launch Launch Barge Rocker arm and Hinge Points Rocker arm Rocker arm Structural Design Hinge Point Structural Design Hinge Point Hinge Point Welding Buffer for Rocker Arm Locking Mechanism Construction Plan Skid Track Skid Track Forward Section Skid Track Skidding Mechanism Skid Track Special Joints Details Arrangement Structural Drawing Calculation Report Calculation Report Structural Drawing Specification Structural Drawing Structural Drawing Structural Drawing Structural Drawing Calculation Report Specification Arrangement Plan

ELECTRICAL AND INSTRUMENTATION SYSTEM: D D D S S L C S S E E E E E E E E E C C C C C C C C C 41 41 41 41 51 41 41 41 41 200 201 100 002 001 011 020 003 004 Electrical Electrical Electrical Electrical Instrumentation Electrical Electrical Electrical Electrical Central Control Room Main Switchboard Key One-Line Diesel Generators Control System Electrical Load Analysis Preliminary Short Circuit LV Switchgear/MCC Auxiliary Diesel Generator Arrangement Arrangement Principle Diagram Specification Specification List Calculation Report Specification Specification

Page 93

STILL IN PROGRESS 1/28/2005 3:26 PM

MARINE PIPING DIAGRAMS AND SPECIFICATIONS: D D D D D D D S S C D M D D D D D K K K K K K K K K K K K K K K K K C C C C C C C C C C C C C C C C C 02 02 02 02 02 02 02 03 03 04 02 02 02 02 02 02 02 001 002 003 005 006 009 004 003 004 001 011 012 007 012 013 015 016 Marine Marine Marine Marine Marine Marine Marine Marine Marine Marine Marine Marine Marine Marine Marine Marine Marine Fuel Oil Lubricating Oil Sea Water / Fresh water Cooling System Bilge System Ballast System Air and Sounding Compressed Air System Main Machinery Equipment Pipes and Valves Marine System Weight Major Machinery Equipment Major Machinery Equipment Ballast Stripping System Fire Water System HVAC Bilge Stripping System Symbols Piping Diagram Piping Diagram Piping Diagram Piping Diagram Piping Diagram Piping Diagram Piping Diagram Specification Specification Calculation Report Equipment List Vendor List Piping Diagram Piping Diagram Principle Diagram Piping Diagram Piping Diagram

Page 94

STILL IN PROGRESS 1/28/2005 3:26 PM

APPENDIX II

OWNER FURNISHED EQUIPMENT LIST

Page 95

STILL IN PROGRESS 1/28/2005 3:26 PM

Owner furnished equipment list Skidding system as specified in document: SMC 03 002 Launch Skidding Mechanism Specification

Page 96

STILL IN PROGRESS 1/28/2005 3:26 PM

APPENDIX III

VENDOR LIST

Page 97

STILL IN PROGRESS 1/28/2005 3:26 PM

VENDOR LIST Diesel Generator sets Chong Qing Cummins Luo Yang Deutz Zhen Jiang B&W Caterpillar Detroit Diesel Cummins Auxiliary Diesel Generator set Chong Qing Cummins Luo Yang Deutz Zhen Jiang B&W Caterpillar Detroit Diesel Cummins Ballast Pumps & Ballast stripping pumps DaLian DNB TianJin CTP Taiko Shanghai Di Yi Pumpworks Hamworthy Nijhuis Pumps Allweiler Vacuum Priming Unit Da Lian DNB Tian Jin CTP Taiko Shanghai Di Yi Pumpworks Sterling Sihi Hamworthy Bilge and Fire Pumps Da Lian DNB Tian Jin CTP Taiko Shanghai Di Yi Pumpworks Hamworthy Johnson Pumps Naniwa

Page 98

STILL IN PROGRESS 1/28/2005 3:26 PM

Bilge stripping Pump / Sludge Pump Da Lian DNB Tian Jin CTP Taiko Shanghai Di Yi Pumpworks Speck Johnson Pumps Naniwa Bilge Water Separator Lu Zhou Machine Works Facet Industrial Blohm & Voss Sterling Berkefield Grey Water Pump Da Lian DNB Tian Jin CTP Taiko Shanghai Di Yi Pumpworks Hamworthy Johnson Pumps Allweiler Gas Oil Transfer Pump and Lub. Oil Transfer Pump Da Lian DNB Tian Jin CTP Taiko Shanghai Di Yi Pumpworks Kracht Johnsons Pumps Desmi Fresh Cooling Water Pumps Da Lian DNB Tian Jin CTP Taiko Shanghai Di Yi Pumpworks Hamworthy Johnson Pumps Allweiler Service Starting Air System Tian Jin Atlas Copco Nan Jing Pioneer Da Lian Sulzer Atlas Copco Ingersoll Rand Grass Air
Page 99

STILL IN PROGRESS 1/28/2005 3:26 PM

After Cooler Compressed Air System Tian Jin Atlas Copco Nan Jing Pioneer Da Lian Sulzer Atlas Copco Ingersoll Rand Grass Air Hydrophore set Da Lian DNB Tian Jin CTP Taiko Shanghai Di Yi Pumpworks Hatenboer Sterling Sihi Speck Hot Water Boiler An Qing Marine Equipment Hatenboer Vaillant A.C. Unit Carrier Transicold Daikin Heinen & Hopman Axial Supply Fans Novenco Heinen & Hopman Hi-Press Butterfly Valves for Ballast / Stripping / Bilge system BAF Nakakita Control Panel for Ballast Control & Alarm System Si Yang Electrical Equipment Factory Nan Tong nav machines Shanghai Yenke Suo Merlin Gerin ABB Tank gauging & draft measurement system Kockum Sonic Calm Nakakita

Page 100

STILL IN PROGRESS 1/28/2005 3:26 PM

Main Switchboard MCC Si Yang Electrical Equipment Factory Merlin Gerin ABB Lighting & small power distribution panel Si Yang Electrical Equipment Factory Merlin Gerin ABB Transformers Si Yang Electrical Equipment Factory Merlin Gerin ABB Anchor Winch and Retrieval Winch Rexroth Qing Jiang Machine Works Lu Zhou Machine Works Lemans Ridderinkhof Rolls Royce Plimsol Planetary Capstans (electric driven): Qing Jiang Machine Works Lu Zhou Machine Works Lemans Ridderinkhof Rolls Royce Plimsol Owner Furnished Equipment: Skidding System IHC Handling Systems Rexroth Hydraudyne Bardex

Page 101

STILL IN PROGRESS 1/28/2005 3:26 PM

You might also like