Fencing mesh should be properly fixed with the supports and to be painted
Danger Boards mentioned respective voltage Min 4 No's in Local language,English&Hindi should be placed on the yard fencing Transformer should be cleaned and the transformer oil temp.Sensor should be inserted into the tank
All the earthing strips should be painted (Body earthing - Green , Neutral earthing Black, L.A Earthing - Red) All the earthing pits should be covered with chamber along with the cover , Also Naming , earthing value and Date of earthing value checked to be mentioned 408, 352, 411, 494
10
Cement waste inside the earth pit chambers should be removed and it should be filled with river/wet sand
11
Cable trench from the panel room to transformer should be sealed properly
12
Sheath to be provided between cable and cable clamp at the transformer LV cable termination
13
14
15
16
17
Insulation mats should be provided in front and back side of the control panel and front of APFC Proper cable tray should be provided up to panel for the cable in the panel room (generator Cables) and also from tower to panel room
18
All the bottom control panel should be connected to body earthing properly
21
Done in all locations. SF 494 some additional materails are kept by M/s RRB energy Ltd.(like Transformers , Tower structres ) and for same they are sending request letter to our office. Remaining all locations are OK. Done in all locations. M/s Comment :Not possible once the nacelle erection. M/s AIPL Reply : Accepted and Withdrawn from the Pending List Done in all locations.
22
Extra materials kept inside the our site premises should be cleared off
24
25
"SUN PHARMA" the name should written on the Nacelle same as RRB name (second side of Nacelle)
26
27
C02 Fire Extinguisher shall be fix on the panel room in side on wall.
28
fire Extinguising bucket stand with 2no. Of buckets Shall be provided out side of the Yard SF Number , Owner Name with logo , location and commissioned date shall be written with colour paint on the out side wall of the panel room entrence Boundary of our land demarkation shall be provided with the Granite stone in every 2mtr , which is height of 2ft and painting & numbering shall be made on the stones.
31 32 33 34
one of 33/22 KV Insulation Gloves shall be kept in every Panel Room. total land should be properly levelled 100mm thick & 1mtr width plenth PCC shall be provided around the Yard & Panel room 100mm thick PCC shall be provided in side area of Tower foundations and 100mm thick & 1mtr wedth pleth PCC shall be provided around the Tower with combining foundations. 100mm thick & 3Mtr width PCC shall be provided from the front of panel room to entrence of our land permises with attched with public road.
Done in all locations. Done in all locations. Done in all locations. Done in all locations.
35
36
Done
37
408
ACB Panel and control panel should be aligned properly without any gap between those and seal the all panel hole properly. Panel cable sealing should be provided
Done
38
Done
39 352 40
All evacuation line poles should be straight and stay wire support should be provided required locations.
Done
Done
41
Done
43
494
panel base frame should be painted and proper alignment should be made
done