Professional Documents
Culture Documents
LRTIHR N
W.
B AH R c^ rAN A C oB s K rtF) 4! ' logic. Dummy activities usedin activity to are network forcecorrect activity? precedence the of Which thefollowing tables requires useof dummy (A) Activitv Depends on A B D A .C
(B)
(c)
Activitv Depends on
D A
B,C
(D)
Activity Depends on
E F
A.B D C,E
9) /
ii
Which of^the one following statements nottrueabout concept critical is the of path analysis?
:
.
'
(A) (B)
Thestarting point critical of pathanalysisto regroup theactivities. is all path Critical is a sequence activities which of for there noscheduling is flexibitity.
(C) Each.activity network at le-ast path critical has one of activities leading from starting the vertex thefinalvertex, Utn ir.6iteO critical to This tfre path. (D) Critical analysis a technique enables to plan monitor path is that us and complex projects, thattheycanapproached caried as so and out efficiently possibfe. as I i
(D) B, D,G,H
.l
as as want Muthu hisfamily to pack fewsuitcases fromIndia, and Ona triphome parceled They have of must a possible. suitcase have mass lessthan22kg. Each bundles below: as eleven to they upthethings want takeinto Bundle A (kg) Mass B B 12
C D E F G HI J K 14666 6 1 4 8 4 4
t) .
7
to algorithm the is if are suitcasgs needed Muthu using flrst-fit Howmany pack?
(A) 4
{i
(c) 6 CI ) 1 1
5 ) :
suitcases needed Muthu using full-bin are Howmany if is the algorithm to paek?
(A) 4
(C)6
(ts) 5
6 )
cD) A
Head
10
15
19
FigureI
(A) (B)
1.days 2 days
(C) (D)
3 days 4 days
q)
in list Usequick atgorithm arrange following of numbers ascending sort to the order.
7 7
8)
10 1
(A) (B)
1 1
2
5
4t10
4
3 3
(c)
(D)
10 7
615
10 7
f f it
l7[ 61 1 0
1)
in involved a small thatare in network Figure11 showsactivities The activity time The project. activity is in minutes' \
Etr
-V
I t
,'
--T-
f'{"1
----- 1"ru lao
ll
l- .. rl
higcr-re- ll (a) for predecessors each to the complete tablebelow showtheirnmedia{e activitY. lmmediate Duration Activity tminutes) predecessors A
B
C
e
F
G H
I
5
(b) activities' and duration listthecritical the Give project
C5 rna.rtce)
rt+
C5 roar ks)
2)
limitof has. of each which a weight into are boxes to bepacked crates Eleven 40k9,threeof of of boxes weight50kg,three weight Therearethree 100kg. 20kg' 30kgandtwoofweight weight \ of the and algorithm state number crates decreasing the Apply first-fit used. ( 6 cnovt<s) showthatthere a solution is using crates. fewer
(a)
of a between group the shows roadconnections Thenetworfin Diagrarn'1 that in the represent times minutes a taxi on The villages. numbers thearcs the arcs. network by represdnted those the along roads takesto travel driver issetupreadyforanapplicationofDijkstra'sa|gorithm.
't 4 morks )
Diagram1
to for route thetaxidriver take to Applyiiit rtr"'r algorithm findtheguickest all W' Show your in in his between home uiirtg"H andhii workstation village to labels permanent to the *trking clearly, inOitite orderin which assign thenodes. "nJ these route find how briefly youwould his quickest under Explain circumstances: on H, to is driver about leave he hears theradiothatan accident As the taxi fo alltraffic of a F in occurs the centre-oiiittageis causing detay 1Aminufes that through village (20marks)