ACHE - Installation, Erection, Start Up & Commissioning Check List

S/N A 1 Description Check List for Installation and Erection Carry out the receiving inspection of air cooler items received at shop / site as per packing Check the mark numbers for identification of parts Identify and install support column, bracings, walkways, plenum, fan ring and bolted up fan rings as per approved drawing. Torquing of bolts shall be : a 4 Bolt size : Check the fan shaft. Clean the rust and apply rust prevention liquid Check the bearings. Check the installation of the fan shaft and bearings onto machinery mount Check the taper lock bush size for the fan and motor pulleys machinery mount. Check the fan blade clevis angle and verify the blade angle. Allowable blade pitch tolerance 0.5 degrees. Leading edge will down and trailing edge up. Check the fan tip clearance of the fan blades as per the API 661 6mm to 19mm max. Fan blades clevis bolt shall be tighten & confirm correct torque setting as per manufacturers data (check max.) Check the drives, belt alignment and belt tension. Refer belt tensioning procedure. Check for proper grease line fitting and the lubrication (grease) in the grease pipe line. Vent the grease pipe line and fill the grease. Grease volume for the Motors 0.6 oz Grease volume for Fan shaft bearings 1.0 oz (Approx. 5 shots from standard grease gun) Rotate the fan freely with hand and check for any proximity Check the installation of vibration switches are mounted and connected. Inspected By

2 3

10

12

13

B 1

Check List Prior to Start-up & Commissioning The header restraining bolts (painted yellow) at each end of all headers are to be removed before the cooler units are bought into operation. Before starting fan drives, check for proper assembly and alignment of all mechanical parts. Start-stop the motor momentarily to check if motor rotation is correct. Rewire if incorrect. Confirm direction to suit correct fan rotation. Rotation shall be clockwise, when view from discharge air stream. Check motor current with clip on Ammeter for all phases. Check the RPM of fan shaft using Tachometer. Run the motor in coupled condition for 30 minutes to check abnormality. Run fan/motor and inspect for excessive noise, run out, heating or vibration of any part. Check motor loading. If the starting torque trips vibration switch, allow the machine to stop. Turn the sensitivity adjustment turn clockwise. Depress the reset button and restart machine. Repeat this process until the vibration switch does not trip on start.

5 6

You might also like