Professional Documents
Culture Documents
Singal Sihombing
Abstract
In 2006, State Electricity Company of Indonesia (PLN), planned to build HVDC long
transmission lines and submarine cables interconnection of Sumatera and Jawa grid.
The aim of this interconnection is to transfer energy of IPP mine mouth coal power plant
of Musirawas and Bangko in Sumatera island, with capacity of 2x600 MW and 4x600
MW respectively, to Jawa grid as load center.
The long distance transmission system of about total 700 km and submarine cables of
50 km, named Sumatera-Jawa HVDC transmission project, transmit 3000 MW, from
the Bangko substation in South Sumatera to the load center in Jawa. It would be
expected in operation in the beginning of 2013. The system, with a transmission voltage
of ±500 kV, HVDC bipole.
Now, the design of this HVDC system still in progress, and it is expected to be finish in
the end of December 2008, devided into several contract documents packages, and
bidding process and contract sign will take place in the beginning up to end of 2009.
Introduction
The average energy growth in the Jawa system is 6% to 7% each year with 16,000 MW
as peak load, 72% as load factor and 22,000 MW of installed capacity. Considering the
maintenance schedule of the power plants, season variation, FOR (force outage rate) of
the units, also the de-rating of the units, the Jawa system needs about 2,000-3,000 MW
of additional power generation in total every year. In 2007, PLN started building a
number of coal-fired steam power plants with total generation of approximately 6,900
MW, most of which are expected to commercially operate in 2009 and 2010.
Given that, the question underlying now is how the system will be supplied for 2011 and
in the proceeding years Jawa as an island with a very density in terms of population has
a long list of issues, especially those related with land and the environment. One of the
closest related to the power system is the difficulty to acquire land in order to construct
new transmission lines and or power plants. Furthermore, issues with high pollution
rates and infrastructure insufficiency are also experienced in the Jawa Island.
Close to Jawa is the island of Sumatera, an island with a very huge coal deposit. and
The coal deposit has attracted the eyes of the investors to obtain its mining concession.
Later, these investors propose to PLN that they would build mine mouth power plants in
the area for PLN. This then resulted in the birth of two independent power plants named
Musirawas (2x600) MW and Bangko (4x600) MW. The two power plants are separated
by 200 km and are located as far as 450 km in land. To reach Jawa, the power must be
transmitted over the Sunda Strait, which is approximately 50 km wide, to the tip of the
Jawa Island.
Musirawas
(2x600) MW
HVDC 500 kV Bipole
TebingTinggi 3000 MW, 700 km
Lampung
Salira Indah
500 kV and 275 kV AC
500 kV DC
In response to the proposal from the investors, PLN decided to build a transmission
lines to transmit the power from this mine mouth power plant to the load center in the
Jawa system. This idea is foreseen to provide direct benefits for both systems as the
transmission line will interconnect Sumatera and Jawa grid, enhance both systems’
reliability, improve both systems’ security, increase economic efficiency in both systems’
operation, as well as reduce environmental impacts.
Choosing the Transmission System
In choosing the transmission system, PLN decided to transport the electricity over a
HVDC (high-voltage direct current) transmission thus creating a link between the
Sumatera and Jawa systems. The decision is made based on studies done. One of the
major justifying reasons put forward in the study is that HVDC is more economically
efficient in investment cost to transport electricity over a very long distance transmission
line compared to HVAC transmission. Also, based on the aforementioned study, it is
concluded that it is cheaper to transport electricity directly to Jawa from far-away coal
mines over a transmission line rather than transporting the coal to Jawa in order to fire
steam power plants build in the Jawa Island.
The following list is a number of quotes taken from the study to justify the HVDC as the
transportation method for transporting energy from Sumatera to Jawa:
1. Less investment
3. Lower losses
4. Better Controllability
In general, it is best to base the choosing of HVDC transmission in light of the HVAC
transmission from the technical and economic point of view, such as the following:
1. Easier controllability
Easier Controllability
An HVDC transmission line costs less than an HVAC transmission line for the same
transmission capacity for long transmission lines. However, the terminal stations are
more expensive in the HVDC case due to the fact that the stations must perform the
conversion from AC to DC and vice versa. But above a certain distance, the so-called
"break-even distance", the HVDC will always give the lowest cost.
DC Line Cost
AC Terminal Cost
Distance
Environmental benefits
One of the best things of an HVDC transmission line is that for the same voltage level
and the same power capacity, the HVDC transmission line requires a smaller right-of-
way compared to that of an HVAC transmission line. For short, a single HVDC line,
which can transport the same power as a double HVAC circuit, definitely has less right-
of-way compared to its HVAC equivalent –a double HVAC circuit.
Project Scheduling
The project schedule of the Sumatera-Jawa HVDC link is synchronized with the project
schedule of the two power plants. The power plants are planned to have their first units
COD in early 2013, one unit for each Bangko and Musirawas with similar capacities of
600 MW. Afterwards, each power plant shall have a subsequent unit COD every six
months. The HVDC transmission lines are expected to fully operate prior to the COD of
these subsequent units.
PLN has entrusted this mission to PLN Engineering as the consultant to develop the
basic engineering design of the HVDC link and package it in a form of bidding
documents. The bidding documents are expected to be finished in December 2008.
Bids will take place in 2009, continued by construction of each package of the project.
COD
PLN E Progress
Airlangga University
1. Land Survey for both HVdc and Hvac lines in both islands; Jawa and
Sumatera
5. Bid Evaluation
Summary
PLN, Perusahaan Listrik Negara, the state electricity company of Indonesia, has
decided to build HVDC link of Sumatera to Jawa. This link is meant to transmit the
power from mine mouth power plants located in South Sumatera to Jawa system. It is
expected to be in commercial operation by 2013 in order to meet the energy
consumption growth of the Jawa Island in the 2013.
References
2. HVDC, Why does the cook strait cable system use DC (Direct Current)
Transmission?
3. Siemens; Answer for Energy. HVDC – High Voltage Direct Current Power
Transmission from Siemens, Unrivaled practical experience.