Typical Productivity Rates (Example)

Foundations and Excavation - Basement Excavation Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 Task / Description Hydraulic Excavator, 0.3m3 bucket, Sand/Soil - Basement Works Hydraulic Excavator, 0.3m3 bucket, Gravel Beds - Basement Works Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk - Basement Works Hydraulic Excavator, 0.3m3 bucket, Hard Ground - Basement Works Hydraulic Excavator, 0.4m3 bucket, Sand/Soil - Basement Works Hydraulic Excavator, 0.4m3 bucket, Gravel Beds - Basement Works Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk - Basement Works Hydraulic Excavator, 0.4m3 bucket, Hard Ground - Basement Works Hydraulic Excavator, 0.5m3 bucket, Sand/Soil - Basement Works Hydraulic Excavator, 0.5m3 bucket, Gravel Beds - Basement Works Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk - Basement Works Hydraulic Excavator, 0.5m3 bucket, Hard Ground - Basement Works Slow 6.4 5.5 5.2 4.7 12.6 11.7 10.9 9.7 18.2 16.5 15.4 13.3 Ave 8.0 6.9 6.5 5.9 15.4 14.3 13.3 11.8 20.0 18.1 16.7 15.4 Fast 9.4 8.1 7.9 8.2 18.9 16.7 15.6 14.0 23.0 20.0 19.3 17.7 Units m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr

Foundations and Excavation - Bulk Excavation Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Excavation Bulking Factor, Gravel Excavation Bulking Factor, Clay/Chalk Excavation Bulking Factor, Boulder Clay Excavation Bulking Factor, Rock Spoil Weight, Rock Spoil Weight, Concrete Spoil Weight, Landfill/CDG Spoil Weight, Sand Rail Mounted Grab, 2.0m3 bucket 2.4min lift cycle Crane Mounted Clamshell Grab, 2.0m3 bucket 2.9min lift cycle Crane Mounted Clamshell Grab, 2.5m3 bucket 2.9min lift cycle Hydraulic Excavator, 0.3m3 bucket, Sand/Soil Hydraulic Excavator, 0.4m3 bucket, Sand/Soil Hydraulic Excavator, 0.5m3 bucket, Sand/Soil Hydraulic Excavator, 0.3m3 bucket, Gravel Beds Hydraulic Excavator, 0.4m3 bucket, Gravel Beds Hydraulic Excavator, 0.5m3 bucket, Gravel Beds Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk Hydraulic Excavator, 0.3m3 bucket, Hard Ground Hydraulic Excavator, 0.4m3 bucket, Hard Ground Hydraulic Excavator, 0.5m3 bucket, Hard Ground Task / Description Excavation Bulking Factor, Sand/Soil Slow 30.0 25.0 34.0 6.9 23.4 45.5 5.6 20.5 36.8 5.6 20.5 37.0 4.5 17.9 25.7 Ave 15.0 33.0 40.0 45.0 60.0 2.5 2.4 1.9 1.8 48.0 33.0 42.0 8.7 28.6 50.0 7.1 25.0 40.0 7.1 25.0 40.0 6.1 22.2 28.6 Fast 20.0 59.0 41.0 52.0 10.2 33.4 58.0 8.2 29.0 46.0 8.3 28.7 46.0 7.2 25.0 32.9 Units % % % % % Tonnes/m3 Tonnes/m3 Tonnes/m3 Tonnes/m3 m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr

Foundations and Excavation - Contigous Piling Sr. No. 1 Task / Description Extra Over time for bored pile build times Slow Ave 20.0 Fast Units %

Foundations and Excavation - Dewatering Sr. No. 1 2 Setup small 2 hole system Setup large 15 hole system Task / Description Slow 10.0 Ave 8.0 21.0 Fast 6.0 Units days days

Foundations and Excavation - Excavate and Remove Sr. No. 1 2 3 4 5 6 7 Task / Description Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds Excavate Spoil Heaps to Transport, 0.6m3 bucket, Clay/Chalk Excavate Spoil Heaps to Transport, 0.6m3 bucket, Boulder Clay Excavate Spoil Heaps to Transport, 1.1m3 bucket, Sand/Soil Excavate Spoil Heaps to Transport, 1.1m3 bucket, Gravel Beds Excavate Spoil Heaps to Transport, 1.1m3 bucket, Clay/Chalk Slow 14.5 15.2 12.3 11.2 25.4 25.6 22.5 Ave 20.0 20.4 18.5 16.9 30.3 31.3 27.8 Fast 25.6 25.6 23.2 21.3 35.7 37.0 33.3 Units m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr

These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to calculate their productivity depending on the resources available and conditions of work.

Typical Productivity Rates (Example)


8 9 10 11 12 Excavate Spoil Heaps to Transport, 1.1m3 bucket, Boulder Clay Load Spoil to Barge, capacity 2,000m3 Load Spoil to Barge, capacity 1,500m3 Load Spoil to Barge, capacity 1,000m3 Spoil conveyor, 600mm belt, 150m/min 18.9 24.4 8.0 6.5 5.5 260.0 30.3 m3/hr hrs hrs hrs m3/hr

Foundations and Excavation - Ground Compaction Sr. No. 1 2 3 4 5 6 Deep Vibroflot, 3m centres Vibro-Roller, Sand Vibro-Roller, Soil Vibro-Roller, Clay Vibro-Roller, Hardcore Vibro-Roller, Ash Task / Description Slow 330.0 28.5 Ave 380.0 31.2 58.8 55.6 38.4 57.8 Fast 465.0 45.2 Units m3/hr m2/hr m2/hr m2/hr m2/hr m2/hr

Foundations and Excavation - Sheet Piling Sr. No. 1 2 Task / Description Vibro/Drop Hammer, 10m deep Sand Vibro/Drop Hammer, 35m deep Sand Slow 3.5 Ave 55.0 32.0 Fast 60.0 10.5 Units m/day m/day

Foundations and Excavation - Small or Deep Excavation Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 Task / Description Hydraulic Excavator, 0.3m3 bucket, Sand/Soil Hydraulic Excavator, 0.3m3 bucket, Gravel Beds Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk Hydraulic Excavator, 0.3m3 bucket, Hard Ground Hydraulic Excavator, 0.4m3 bucket, Sand/Soil Hydraulic Excavator, 0.4m3 bucket, Gravel Beds Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk Hydraulic Excavator, 0.4m3 bucket, Hard Ground Hydraulic Excavator, 0.5m3 bucket, Sand/Soil Hydraulic Excavator, 0.5m3 bucket, Gravel Beds Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk Hydraulic Excavator, 0.5m3 bucket, Hard Ground Slow 6.7 3.2 3.3 3.3 8.2 7.1 6.5 6.3 12.2 10.2 9.7 6.1 Ave 8.4 4.5 4.1 4.1 10.0 8.7 8.3 7.7 13.3 11.1 10.5 6.7 Fast 9.9 5.0 5.2 5.2 11.7 10.2 9.4 9.1 15.4 12.9 12.1 7.7 Units m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr

Foundations and Excavation - Spread and Level Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Task / Description Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 5-50m to stockpile Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 50-120m to stockpile Crawler Shovel, 0.8m3 bucket, Gravel, pushed 5-50m to stockpile Crawler Shovel, 0.8m3 bucket, Gravel, pushed 50-120m to stockpile Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 5-50m to stockpile Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 50-120m to stockpile Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 5-50m to stockpile Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 50-120m to stockpile Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 5-50m to stockpile Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 50-120m to stockpile Crawler Shovel, 1.2m3 bucket, Gravel, pushed 5-50m to stockpile Crawler Shovel, 1.2m3 bucket, Gravel, pushed 50-120m to stockpile Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 5-50m to stockpile Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 50-120m to stockpile Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 5-50m to stockpile Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 50-120m to stockpile Crawler Shovel, 0.6m3 bucket, 50-200m2, Sand/Soil Crawler Shovel, 0.6m3 bucket, over 200m2, Sand/Soil Crawler Shovel, 0.6m3 bucket, 50-200m2, Gravel Crawler Shovel, 0.6m3 bucket, over 200m2, Gravel Crawler Shovel, 0.6m3 bucket, 50-200m2, Hardcore Crawler Shovel, 0.6m3 bucket, over 200m2, Hardcore Crawler Shovel, 0.6m3 bucket, 50-200m2, Boulder Clay Slow 13.9 7.6 14.2 7.6 12.7 6.9 11.6 6.3 23.8 16.7 25.0 17.2 21.7 15.1 19.6 13.7 18.6 24.4 18.9 24.2 15.8 19.2 17.2 Ave 20.4 9.5 20.4 10.2 18.4 8.9 16.9 8.2 28.5 18.5 32.0 19.3 27.5 16.9 24.5 15.9 28.5 37.2 28.6 37.2 23.5 29.6 26.4 Fast 25.0 12.6 25.6 12.8 23.2 11.6 21.3 10.4 35.7 20.4 37.0 21.2 33.3 18.8 30.3 17.5 38.5 50.0 38.4 50.0 31.2 40.0 35.7 Units m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr

These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to calculate their productivity depending on the resources available and conditions of work.

Typical Productivity Rates (Example)


24 25 26 27 28 29 30 31 32 Crawler Shovel, 0.6m3 bucket, over 200m2, Boulder Clay Crawler Shovel, 1.2m3 bucket, 50-200m2, Sand/Soil Crawler Shovel, 1.2m3 bucket, over 200m2, Sand/Soil Crawler Shovel, 1.2m3 bucket, 50-200m2, Gravel Crawler Shovel, 1.2m3 bucket, over 200m2, Gravel Crawler Shovel, 1.2m3 bucket, 50-200m2, Hardcore Crawler Shovel, 1.2m3 bucket, over 200m2, Hardcore Crawler Shovel, 1.2m3 bucket, 50-200m2, Boulder Clay Crawler Shovel, 1.2m3 bucket, over 200m2, Boulder Clay 22.2 43.5 55.5 43.8 55.5 37.1 47.6 43.8 55.6 33.8 48.0 61.1 48.3 61.1 40.3 51.6 45.7 59.1 45.4 52.6 66.7 52.9 66.7 43.5 55.6 47.6 62.5 m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr

Architectural Builders Work and Finishes - Carpentry Carcassing Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 Task / Description Windows, Timber Frames for Bricklaying Windows, Drill, Screw & Plug extra over Door Frames, Softwood, 1.0-3.0m2 Door Frames, Softwood, 3.0-7.0m2 Door Frames, Softwood, 7.0-10.0m2 Door Frames, Hardwood, 1.0-3.0m2 Door Frames, Hardwood, 3.0-7.0m2 Door Frames, Hardwood, 7.0-10.0m2 Erect Water Tank Platform Fix Studding For Bath Cut Access Hatch Floor Joists, under 3m Floor Joists, 3.0-4.5m Floor Joists, 4.5-6.0m Ceiling Joists, under 3m Ceiling Joists, 3.0-4.5m Ceiling Joists, 4.5-6.0m Ceiling Joists, Notch to Beams Ceiling Joists, Pack Joist Ends Ceiling Joists, Nailing Joists Together Ceiling Joists, Bolting Joists Together Floor Boards, Butt Jointed Floor Boards, T&G Boards, under 75mm wide Floor Boards, T&G Boards, 75-100mm wide Floor Boards, T&G Boards, 100-125mm wide Floor Boards, T&G Boards, 125-150mm wide Plywood Sheeting, Butt Jointed, nailed Plywood Sheeting, Butt Jointed, screwed Plywood Sheeting, T&G Jointed, nailed Plywood Sheeting, T&G Jointed, screwed Chipboard Sheeting, Butt Jointed, nailed Chipboard Sheeting, Butt Jointed, screwed Chipboard Sheeting, T&G Jointed, nailed Chipboard Sheeting, T&G Jointed, screwed Slow 1.1 0.3 0.5 1.2 0.6 1.4 9.0 6.8 5.5 12.8 10.8 9.6 20.0 20.1 Ave 0.5 0.1 0.2 0.4 0.8 0.3 0.3 1.0 2.3 0.1 0.3 9.6 7.2 5.8 14.0 12.1 10.8 25.0 23.8 23.0 12.6 1.7 3.4 3.8 4.2 5.5 9.1 4.1 8.3 4.0 10.0 5.1 9.3 5.5 Fast 0.1 11.6 9.7 7.3 14.7 12.6 11.1 28.5 26.3 10.2 4.8 9.1 4.6 11.5 5.8 9.1 5.9 Units hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no no/hr hrs/m no/hr no/hr no/hr no/hr no/hr no/hr no/hr no/hr no/hr m/hr m/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

Architectural Builders Work and Finishes - Carpentry Final Fixing Sr. No. 1 2 3 4 5 6 7 8 9 10 11 Windows, Softwood, 3.0-7.0m2 Windows, Softwood, 7.0-10.0m2 Windows, Hardwood, 1.0-3.0m2 Windows, Hardwood, 3.0-7.0m2 Windows, Hardwood, 7.0-10.0m2 Windows, Aluminum, 1.0-3.0m2 Windows, Aluminum, 3.0-7.0m2 Windows, Aluminum, 7.0-10.0m2 Windows, Steel, 1.0-3.0m2 Windows, Steel, 3.0-7.0m2 Windows, Steel, 7.0-10.0m2 Task / Description Slow 0.6 1.3 0.4 0.7 1.6 0.2 0.5 1.2 0.4 1.2 1.4 Ave 0.4 0.9 0.3 0.5 1.2 0.3 0.4 0.8 0.3 0.6 1.2 Fast 0.3 0.6 0.4 0.7 0.3 0.5 0.2 0.5 1.0 Units hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no

These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to calculate their productivity depending on the resources available and conditions of work.

Typical Productivity Rates (Example)


12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 Window Boards, nailed Window Boards, screwed Mouldings, Softwood, Nailed Mouldings, Softwood, Screwed Mouldings, Softwood, Gun Nailed Mouldings, Hardwood, Nailed Mouldings, Hardwood, Screwed Mouldings, Hardwood, Gun Nailed Skirting, Aluminum, Screwed 150-300mm centres Skirting, Aluminum, Screwed 300-450mm centres Skirting, Plastic, Adhesive Fixing Architrave Mouldings Architrave, Fix to Doors Door Stop Mouldings Glazed Bead Mouldings Hanging Doors, Softwood, Single Pair Butts Hanging Doors, Hardwood, Single Pair Butts Cut Mortice to Receive Lock, Softwood Cut Mortice to Receive Lock, Hardwood Cut & Fix Formica Bath Panel Kitchen Cupboards, Floor Units Kitchen Cupboards, Wall Units Kitchen Cupboards, Shelf Units Staircase, pre-made, simple, straight flight Staircase, pre-made, 2 straight flights, 1 landing Staircase, pre-made, 2 straight flights, 2 landings Staircase, Balustrades/Handrails, fix horizontal Staircase, Balustrades/Handrails, fix raking Staircase, Cut and Fix Newel to Walls Windows, Softwood, 1.0-3.0m2 Raised Flooring, metal system 9.5 10.1 15.5 1.3 1.9 1.9 3.7 1.2 0.9 0.9 0.3 0.3 0.4 6.3 4.6 8.2 3.3 2.4 8.5 7.6 4.5 8.6 12.2 1.2 16.9 18.6 0.9 1.2 0.2 0.6 0.4 0.8 0.7 0.8 1.5 2.9 6.3 0.6 0.5 0.2 0.5 0.2 0.3 8.5 5.6 11.1 5.5 3.7 11.3 18.2 25.0 20.4 0.6 0.9 0.6 0.5 0.7 1.1 2.6 0.1 0.3 0.2 hrs/m hrs/m m/hr m/hr m/hr m/hr m/hr m/hr m/hr m/hr m/hr m/hr hrs/door m/hr m/hr hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no m2/hr

Architectural Builders Work and Finishes - Ceiling Finishes Sr. No. 1 2 3 Suspended Ceilings, First Fix Suspended Ceilings, Second Fix Task / Description Suspended Ceilings, office situations Slow Ave 2.6 0.7 1.2 Fast 3.5 Units m2/hr m2/hr m2/hr

Architectural Builders Work and Finishes - Doors and Windows Sr. No. 1 2 3 4 5 Mastic Pointing to Frames Fix Metal and Timber Windows After Wall Complete Window Glazing Window Glazing, Single Glazed Units Window Glazing, Double Glazed Units Task / Description Slow Ave 9.5 2.0 1.3 2.0 1.3 Fast Units m/hr m2/hr m2/hr m2/hr m2/hr

Architectural Builders Work and Finishes - Fire Protection Sr. No. 1 2 3 Spray Protection to Steelwork Spray Protection to Steelwork Sheet Protection Task / Description Slow 2.9 Ave 5.0 1.2 3.7 Fast 4.2 Units m2/hr Tonnes/hr m2/hr

Architectural Builders Work and Finishes - Floor Finishes Sr. No. 1 2 3 4 5 6 Granolithic Flooring Terrazzo Flooring, in-situ Terrazzo Flooring, pre-cast Mosaic Tiling, 0.045x0.045m Clay, quarry Tiles, small areas, much cutting Clay, quarry Tiles, large areas, little cutting Task / Description Slow Ave 3.1 3.6 4.6 1.5 0.8 2.2 Fast 5.1 2.2 1.1 2.8 Units m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to calculate their productivity depending on the resources available and conditions of work.

Typical Productivity Rates (Example)


7 8 9 10 11 12 13 14 15 16 17 Raised Floor System Linolium/Thermo-Plastic Flooring Thermo-Plastic Floor Tiles Wood Block Flooring, lay blocks Wood Block Flooring, sand and polish Carpeting, Underlay & Gripper Carpeting, Adhesive Fixing Carpeting, Fully Fitted Hardboard Sheeting Coverings, small areas Hardboard Sheeting Coverings, large areas Floor Sheeting Coverings, Lay Lino 2.6 3.1 3.3 1.5 3.1 5.6 3.5 2.0 3.7 6.6 9.5 5.0 5.6 2.1 6.1 4.2 2.8 4.1 7.2 10.5 m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

Architectural Builders Work and Finishes - Metal Wall Panels Sr. No. 1 2 Task / Description Sub-Frame Installation, 1.5x0.5m panels VE Panel Installation, 1.5x0.5m panels Slow 12.2 1.0 Ave 15.0 1.4 Fast 17.5 1.9 Units m2/day m2/day

Architectural Builders Work and Finishes - Metalwork Sr. No. 1 2 3 Install Metal Door and Frame Install Balustrade & Railings Install Railings to Staircases Task / Description Slow Ave 0.2 1.5 0.8 Fast Units no/hr m/hr no/day

Architectural Builders Work and Finishes - Painting Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 Prepare Walls Prepare Doors Prepare Door Frames Burn Off / Heat Strip Paintwork Internal Timber, 1 coat primer before fixing, generally Internal Timber, 1 coat primer before fixing, timber lengths Internal Timber, knot, 1 primer, stop, 1 undercoat, 1 gloss Internal Timber, touchup primer, 1 undercoat, 1 coat gloss Internal Timber, polyurethane varnish, 2 coats Internal Timber, polyurethane varnish, 3 coats Internal Timber, linseed oil to hardwood, 2 coats External Timber, windows and frames External Timber, knot, 1 primer, 2 undercoats, 1 coat gloss, External Timber, touchup primer, 2 undercoats, 1 coat gloss, External Timber, 2 coats wood preservative External Timber, 3 coats polyurethane varnish Internal Walls, 2 coats emulsion to plaster Internal Walls, 2 coats emulsion to brick/blockwork Internal Walls, 1 mist, 2 coats emulsion to plaster Internal Walls, 1 mist, 2 coats emulsion to brick/blockwork Internal Walls, 1 primer, 1 undercoat, 1 gloss to plaster Internal Walls, undercoat to door frame Internal Walls, gloss to door frame Internal Walls, undercoat to door Internal Walls, gloss to door External Walls, 2 coats sandtex to render/concrete External Walls, 2 coats sandtex to brick/blockwork External Walls, 1 sealer, 2 emulsion to render/concrete External Walls, 1 sealer, 2 emulsion to brick/blockwork Floors, epoxy paint Ceilings, emulsion paint, 2 coats Ceilings, emulsion paint, 3 coats Ceilings, textured paint Ceilings, artex finish Internal Steelwork, 1 primer, 1 undercoat, 1 gloss Task / Description Slow 1.3 Ave 14.2 12.5 25.0 1.1 6.7 20.0 1.7 3.1 3.3 2.2 3.6 2.4 1.5 2.0 4.0 2.0 8.0 6.0 6.0 4.5 2.3 20.0 16.5 7.1 6.2 2.5 2.0 2.0 1.7 2.9 6.1 5.0 4.2 4.1 2.4 Fast 2.1 3.8 Units m2/hr m2/hr m/hr m2/hr m2/hr m/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m/hr m/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to calculate their productivity depending on the resources available and conditions of work.

Typical Productivity Rates (Example)


36 37 External Steelwork, 1 primer, 2 undercoats, 1 gloss Guttering Steelwork, 1 coat primer, 2 undercoats, 1 gloss 0.9 1.7 2.5 m2/hr m/hr

Architectural Builders Work and Finishes - Partitioning Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Timber Studding Metalwork System (MF) Studding Tape, Joint Sand and Top Coat Plasterboard Skimming to Plasterboards 5mm Hardboard Paneling, excluding studding time 100mm Pine Paneling, excluding studding time Quality Hardwood Paneling, excluding studding time Fix 50mm Rocksil Insulation to cavities Fix Timber Studding and Paramount Partitions Fix Timber Studding and Demountable Partitions Fix Timber Studding and Hills Duraboard Partitions Fix Timber Studding and Gyproc Laminated Partitions Stud Partitions, Butt Jointed, nailed Stud Partitions, Butt Jointed, screwed Stud Partitions, T&G Jointed, nailed Stud Partitions, T&G Jointed, screwed Stud Partitions, Fix Sole Plates Stud Partitions, Fix Noggins Stud Partitions, Drill 25-40mm Holes Fix Toilet Partition System, Separation panels Fix Toilet Partition System, Wall Front Panels Fix Toilet Partition System, Separation Front Panels Fix Toilet Partition System, End Front Panels Fix Toilet Partition System, Hang Door to Panel Fix Toilet Partition System, Hand Door plugged to wall Fix Toilet Partition System, Fix Head Rails Task / Description Slow 5.9 1.6 1.1 5.5 0.8 0.3 2.6 0.8 3.0 2.2 5.9 3.5 2.9 2.1 Ave 6.2 2.0 1.5 6.1 3.2 1.1 0.5 17.8 3.0 1.1 3.5 2.6 7.3 4.6 3.6 2.8 11.1 16.6 28.5 0.8 0.7 0.6 0.6 0.4 0.6 0.1 Fast 6.8 2.5 2.1 6.7 3.6 1.4 0.6 20.2 3.4 1.6 3.9 2.9 9.1 5.8 4.8 3.7 Units m/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m/hr m/hr m/hr m/hr m/hr m/hr no/hr hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no hrs/no

Architectural Builders Work and Finishes - Plasterboard Sr. No. 1 2 3 4 5 Boarding to Plaster dabs Boarding to Stud-work/Metal Lathes Boarding 12mm nailed to studding Boarding 19mm nailed to studding Tape, Jointing and Sanding Task / Description Slow 3.6 4.0 Ave 4.0 5.0 12.5 16.5 0.1 Fast 5.5 6.7 Units m2/hr m2/hr m2/hr m2/hr hrs/m

Architectural Builders Work and Finishes - Restoration Works Sr. No. 1 2 3 4 5 Faade Cleaning, Water Jetting Faade Cleaning, Acid Etching Faade Cleaning, Grit Blasting Cladding Restoration, Brickwork Cladding Restoration, Stonework courses Task / Description Slow Ave 25.0 9.0 12.0 6.5 20.0 Fast Units m2/day m2/day m2/day m2/day m/day

Architectural Builders Work and Finishes - Stonework Sr. No. 1 2 3 4 5 6 7 8 9 10 Task / Description Fix 0.5m2 Stones to Metal Support Frame Fix 0.5-0.75m2 Stones to Metal Support Frame Fix 0.75-1.0m2 Stones to Metal Support Frame Fix Complex Stonework to Metal Support Frame Fix Curved Stone Cladding Fix Stone Edge Beams/Window Reveals Fix Stone Soffits Stone Floors Granite Wall Panels, First Fix Granite Wall Panels, Second Fix Slow 5.6 7.2 6.9 6.9 6.9 Ave 7.0 9.0 8.7 1.8 8.0 2.3 4.0 10.4 1.3 1.1 Fast 7.8 10.1 9.7 9.2 3.2 12.2 Units m2/day m2/day m2/day m2/day m2/day m2/day m2/day m2/day m2/hr m2/hr

These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to calculate their productivity depending on the resources available and conditions of work.

Typical Productivity Rates (Example)

Architectural Builders Work and Finishes - Wall Finishes Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Mosaic Tiling, 0.045x0.045m Clay, quarry Tiles, Window Cills, setout and level Clay, quarry Tiles, Window Cills, fix, grout and clean Ceramic Tiles 150x150mm, Ledges/Upstands Ceramic Tiles 150x150mm, Areas under 1.5m2 per room Ceramic Tiles 150x150mm, Areas of 1.5-2.5m2 per room Ceramic Tiles 150x150mm, Areas over 2.5m2 per room Ceramic Tiles 150x150mm, Extra Over for Cutting Ceramic Tiles 108x108mm, Ledges/Upstands Ceramic Tiles 108x108mm, Areas under 1.5m2 per room Ceramic Tiles 108x108mm, Areas of 1.5-2.5m2 per room Ceramic Tiles 108x108mm, Areas over 2.5m2 per room Ceramic Tiles 108x108mm, Extra Over for Cutting Ceramic Tiles, Grouting Works Task / Description Slow 20.4 0.9 1.4 1.5 1.0 1.6 1.7 2.2 Ave 1.1 55.5 1.5 27.1 1.0 1.6 1.7 41.6 62.5 1.3 1.8 1.9 125.0 2.5 Fast 1.5 32.0 1.2 1.9 2.1 1.5 2.1 2.2 2.6 Units no/hr m/hr m2/hr no/hr m2/hr m2/hr m2/hr no/hr no/hr m2/hr m2/hr m2/hr no/hr m2/hr

Architectural Builders Work and Finishes - Wallpapering Sr. No. 1 2 3 4 Fix Wallpaper and lining paper Fix Vinyl and Washable paper Fix Ceiling Lining Paper Task / Description Strip Existing Wallpaper (3 layers) & Prepare Walls Slow Ave 5.0 5.0 4.2 4.0 Fast Units m2/hr m2/hr m2/hr m2/hr

Concrete Works - Concrete Finishing Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Task / Description Surface Finishing, Steel Float By Hand Surface Finishing, Wood Float By Hand Surface Finishing, Power Float Surface Finishing, Light Brush on Trowel Surface Finishing, Brush on Trowel Margin Surface Finishing, Sprayed By Pump, expose aggregate Surface Finishing, Wire Brush, expose aggregate Making Good Walls, prepare, shutter, pour Making Good Columns, prepare, shutter, pour Making Good Sides of Beams, prepare, shutter, pour Making Good Slab Soffits, prepare, shutter, pour Making Good Bolt Holes, prepare, shutter, pour Making Good Rubdown Precast Concrete, prepare, shutter, pour Making Good Scabble 3 head brush hammer, prepare, shutter, pour Slow 9.2 11.7 13.9 55.8 28.8 65.0 15.0 14.8 30.7 Ave 13.9 17.2 20.8 90.1 48.5 95.0 25.0 5.5 2.8 2.8 4.2 16.8 18.0 59.5 Fast 25.0 29.4 37.0 170.0 85.0 145.0 30.0 8.6 6.9 7.0 5.5 25.8 73.8 Units m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr no/hr m2/hr hrs/m2

Concrete Works - Concrete Mixing Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 Concrete Weight, 1m3 Readymix Lorry, Length Readymix Lorry, Width Readymix Lorry, Height Readymix Lorry, Length Readymix Lorry, Turning Circle Readymix Lorry, Allowable Access Ramp Gradient Mixing Concrete, By Hand Mixing Concrete, Single Drum Paddle Mixer Mixing Concrete, Double Drum Paddle Mixer Mixing Concrete, Single Drum Plant Pan Mixer Mixing Concrete, Dry Mix Plant Task / Description Slow 158.0 315.0 Ave 2.4 8.3 2.5 3.7 24.4 16.4 17.0 0.3 180.0 370.0 120.0 90.0 Fast 20.0 210.0 420.0 Units Tonnes m m m Tonnes m degrees m3/hr m3/hr m3/hr m3/hr m3/hr

Concrete Works - Concrete Placement Sr. No. 1 Task / Description Placing concrete, lorry based pump Slow 30.0 Ave 40.0 Fast 50.0 Units m3/hr

These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to calculate their productivity depending on the resources available and conditions of work.

Typical Productivity Rates (Example)


2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Hollorib Decking, concrete topping Hollorib Decking, concrete topping, incl PowerFloat Placing Concrete, By Wheelbarrow over 1-10m Placing Concrete, By Wheelbarrow over 10-20m Placing Concrete, By Wheelbarrow over 20-50m Placing Direct From Readymix Lorry, Mass Fill Placing Direct From Readymix Lorry, 50mm Blinding Placing Direct From Readymix Lorry, Ground Beams Placing Direct From Readymix Lorry, Pile Caps Placing Direct From Readymix Lorry, Duct Walls Placing Direct From Readymix Lorry, Stub Columns Placing Direct From Readymix Lorry, Ground Slab Placing Direct From Readymix Lorry,Drains Bed and Cover Placing From Tower Crane, Pile Caps Placing From Tower Crane, Mass Fill Placing From Tower Crane, Slabs under 150mm thick Placing From Tower Crane, Slabs over 150mm thick Placing From Tower Crane, Trough/Coffered Slabs Placing From Tower Crane, Stairs and Landings Placing From Tower Crane, Blinding Placing From Tower Crane, Beams under 150mm thick Placing From Tower Crane, Beams over 150mm thick Placing From Tower Crane, Walls Placing From Tower Crane, Columns 85.0 40.0 2.1 1.5 0.8 2.8 1.5 1.0 2.1 1.2 4.0 0.9 1.2 0.9 0.6 0.8 0.5 0.6 0.6 0.4 100.0 50.0 2.3 1.8 1.1 3.1 1.3 1.5 0.8 0.4 2.3 0.9 1.4 4.5 1.3 1.5 1.1 0.7 1.0 0.6 0.8 1.1 0.5 120.0 70.0 2.5 2.1 1.5 3.3 1.6 1.7 2.3 1.1 0.6 2.6 1.0 1.6 5.5 1.7 1.8 1.2 0.9 1.1 0.8 1.0 1.5 0.6 m2/hr m2/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr m3/hr

Concrete Works - Formwork Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 Pilecaps, < 0.7m2 Pilecaps, 0.7-2.5m2 Pilecaps, 2.5-3.0m2 Pilecaps, > 3.0m2 Ground Beams, < 0.7m2 Ground Beams, 0.7-1.5m2 Ground Beams, 1.5-3.0m2 Ground Beams, 3.0-5.0m2 Elevated Plain Slab Soffit Beams, on erected falsework, width 100-200mm Beams, on erected falsework, width 200-300mm Beams, on erected falsework, width 300-500mm Beams, on erected falsework, width 500-750mm Beams, on erected falsework, width over 750mm Walls, Construct Kickers Walls, Fully Framed Formwork/Struts, 1.0-2.0m2 Walls, Fully Framed Formwork/Struts, 2.0-5.0m2 Walls, Fully Framed Formwork/Struts, over 5.0m2 Walls, StoriForm Shutters, 1.0-3.0m2 Walls, StoriForm Shutters, 3.0-5.0m2 Walls, StoriForm Shutters, 5.0-10.0m2 Walls, StoriForm Shutters, 10.0-15.0m2 Walls, StoriForm Shutters, over 15.0m2 Ground Slabs Columns, Construct Kickers, direct to slab Columns, Construct Kickers, suspended from soffit slab Columns, Square Sides, Timber Clamp/Prop, csa < 0.1m2 Columns, Square Sides, Timber Clamp/Prop, csa 0.1-0.4m2 Columns, Square Sides, Timber Clamp/Prop, csa over 0.4m2 Columns, Square Sides, Steel Forms, 1.5 x 1.5 x 9.0m high Columns, Square Sides, Steel Forms, 2.0 x 2.0 x 9.0m high Columns, Square Sides, Steel Forms, 2.0 x 4.0 x 9.0m high Columns, Round Sides, Sacrificial Plastic Mould, 3.0-4.0m dia Task / Description Slow 0.9 1.6 2.0 2.3 1.1 1.7 1.8 2.5 0.6 0.9 1.0 1.2 1.5 1.4 5.3 0.9 1.0 1.2 1.0 1.9 2.3 3.2 3.8 1.0 3.2 1.2 1.3 1.8 2.0 7.9 6.9 8.5 3.5 Ave 1.6 2.0 2.3 2.5 1.7 1.8 2.5 2.6 0.8 1.0 1.1 1.3 1.6 1.5 7.1 1.8 2.2 2.5 1.4 2.3 2.8 4.5 4.8 1.5 4.1 2.8 1.6 2.1 2.3 9.5 7.5 10.2 4.5 Fast 2.0 2.3 2.5 3.1 1.8 2.5 2.6 3.5 1.2 1.1 1.3 1.5 1.8 1.7 10.0 1.9 2.5 2.9 2.0 3.3 3.5 4.0 5.4 1.8 5.4 3.2 1.8 2.4 2.5 10.3 8.3 12.0 6.0 Units m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr no/hr no/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to calculate their productivity depending on the resources available and conditions of work.

Typical Productivity Rates (Example)


34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 Columns, Round Sides, Steel Mould, 3.0-4.0m dia Columns, Sloping Column Heads, extra over rate Staircases, Stair Soffit, Sloping Staircases, Stair Soffit, Flat Landing Staircases, Wall Strings Staircases, Open Strings Staircases, Riser Boards fixed to strings Staircases, Risers fixed to Strings Waffle Flooring, 2.4m grid Shaft Slip Forming Table Form, Aluminum System, 400m2 bays Table Form, H-Frame Steel Falsework, 400m2 bays Tunnel Forms, Wall and Slab poured as one Hollorib Decking, lay deck Hollorib Decking, shear connecting studs Stop Ends, no perforations Stop Ends, minor perforations Stop Ends, dense perforations Box Outs, 0.01-0.05m2 Box Outs, over 0.05m2 Dummy Frames, under 3.0m2 Dummy Frames, over 3.0m2 5.2 0.7 0.8 0.4 0.7 1.1 2.1 1.9 2.8 1.2 0.9 7.6 3.1 4.5 3.1 6.5 2.5 0.8 0.9 0.6 0.8 2.5 2.3 1.4 300.0 3.2 3.0 15.6 43.5 29.3 3.5 1.5 1.1 8.2 3.9 6.2 3.7 7.5 3.5 1.0 1.2 2.8 2.6 1.8 500.0 3.8 3.5 17.5 47.5 31.2 4.2 1.9 1.4 9.1 4.5 7.1 4.5 m2/hr hrs/no m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr mm/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr no/hr no/hr no/hr no/hr

Concrete Works - Post Tensioning Sr. No. 1 2 Task / Description Lag for Initial Stress Tensioning after 1st bay cast Lag for Final Stress Tensioning after Initial Stress Slow Ave 48.0 120.0 Fast Units hrs hrs

Concrete Works - Pre-Cast Concrete Sr. No. 1 2 Task / Description Precast Plank and Block Flooring System, Plank Elements Precast Plank and Block Flooring System, Block Elements Slow 0.4 2.7 Ave 0.2 1.2 Fast 0.1 0.9 Units hrs/plank hrs/1000no

Concrete Works - Reinforcement Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Task / Description Slabs/Foundations, steelfixing, 6mm Slabs/Foundations, steelfixing, 8mm Slabs/Foundations, steelfixing, 10mm Slabs/Foundations, steelfixing, 12mm Slabs/Foundations, steelfixing, 16mm Slabs/Foundations, steelfixing, 20mm Slabs/Foundations, steelfixing, 25mm Slabs/Foundations, steelfixing, 32mm Slabs/Foundations, steelfixing, 40mm Slabs/Foundations, steelfixing, 50mm Beams/Columns, steelfixing, 6mm Beams/Columns, steelfixing, 8mm Beams/Columns, steelfixing, 10mm Beams/Columns, steelfixing, 12mm Beams/Columns, steelfixing, 16mm Beams/Columns, steelfixing, 20mm Beams/Columns, steelfixing, 25mm Beams/Columns, steelfixing, 32mm Beams/Columns, steelfixing, 40mm Beams/Columns, steelfixing, 50mm Walls, steelfixing, 6mm Walls, steelfixing, 8mm Walls, steelfixing, 10mm Walls, steelfixing, 12mm Walls, steelfixing, 16mm Slow 40.3 28.2 22.5 16.9 12.0 9.2 6.9 5.7 5.3 5.2 55.4 38.8 29.5 23.4 16.6 12.4 9.9 6.8 6.1 6.1 41.2 29.2 22.7 17.6 12.4 Ave 38.4 26.9 20.6 16.3 11.5 8.6 6.7 5.5 5.1 4.9 52.8 37.0 28.4 22.4 15.8 11.9 9.2 6.6 5.9 5.9 40.8 28.6 22.0 17.3 12.2 Fast 36.5 25.8 20.1 15.4 10.9 8.2 6.5 5.2 4.9 4.6 50.6 35.1 26.9 21.9 15.1 11.3 8.7 6.2 5.6 5.6 39.1 27.4 21.2 16.9 11.8 Units hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne

These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to calculate their productivity depending on the resources available and conditions of work.

Typical Productivity Rates (Example)


26 27 28 29 30 31 32 33 34 35 36 37 Walls, steelfixing, 20mm Walls, steelfixing, 25mm Walls, steelfixing, 32mm Walls, steelfixing, 40mm Walls, steelfixing, 50mm Staircases, steelfixing, 6mm Staircases, steelfixing, 8mm Staircases, steelfixing, 10mm Staircases, steelfixing, 12mm Staircases, steelfixing, 16mm Staircases, steelfixing, 20mm Staircases, steelfixing, 25mm 9.4 7.4 7.0 6.4 5.3 48.9 34.4 26.6 20.9 14.6 11.3 8.6 9.2 7.2 6.8 6.1 5.1 48.0 33.6 25.8 20.4 14.4 10.8 8.4 8.7 7.0 6.4 5.9 4.8 45.5 31.9 24.3 19.5 13.8 10.5 8.2 hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne hrs/tonne

Concrete Works - Reinforcement Ratios Sr. No. 1 2 3 4 5 6 Task / Description Pile Cap, Concrete m3 x Ratio = Rebar Tonnes Base Slab, Concrete m3 x Ratio = Rebar Tonnes Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes Platform Slab, Concrete m3 x Ratio = Rebar Tonnes Columns, Concrete m3 x Ratio = Rebar Tonnes Walls, Concrete m3 x Ratio = Rebar Tonnes Slow 15.8 14.7 Ave 14.8 13.2 20.6 15.6 18.7 15.0 Fast 14.1 25.6 28.7 Units % ratio % ratio % ratio % ratio % ratio % ratio

Construction Wet Trades - Blockwork Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 Task / Description Thermalite Blockwork, under 100mm thick Thermalite Blockwork, under 100-150mm thick Thermalite Blockwork, over 150mm thick Lightweight Concrete Blockwork, under 100mm thick Lightweight Concrete Blockwork, under 100-150mm thick Lightweight Concrete Blockwork, over 150mm thick Heavyweight Concrete Blockwork, under 100mm thick Heavyweight Concrete Blockwork, under 100-150mm thick Heavyweight Concrete Blockwork, over 150mm thick Face Finish, Raked Out Face Finish, Bag Rubbed Face Finish, Flush Pointing Slow 1.8 1.4 1.2 1.5 1.4 1.2 1.4 1.2 1.1 Ave 2.5 1.9 1.6 2.2 1.9 1.6 2.1 1.6 1.4 71.4 29.4 17.6 Fast 3.2 2.5 2.1 2.9 2.1 2.0 2.9 2.1 1.8 Units m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

Construction Wet Trades - Brickwork Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 English Bond, 0.5 Brick thick English Bond, 1.0 Brick thick English Bond, 1.5 Brick thick English Bond, 2.0 Brick thick Flemish Bond, 0.5 Brick thick Flemish Bond, 1.0 Brick thick Flemish Bond, 1.5 Brick thick Flemish Bond, 2.0 Brick thick Flemish Garden Wall Bond, 0.5 Brick thick English Garden Wall Bond, 0.5 Brick thick Stretcher Bond, 0.5 Brick thick Building in Metal Door Frame Building in Metal Window Building in Wood Door Frame Building in Wood Window Building Brick on Edge Coping Building Brick on Edge Canted Cills Pointing to Frames Bitumen DPC, horizontal under 100mm wide Bitumen DPC, horizontal 100-255mm wide Bitumen DPC, horizontal over 255mm wide Task / Description Slow 0.7 0.6 0.4 0.3 0.8 0.6 0.3 0.3 0.8 0.8 1.0 0.5 0.6 0.4 0.6 12.4 Ave 0.8 0.8 0.5 0.4 0.9 0.7 0.8 0.4 1.2 1.0 1.3 0.5 0.5 0.3 0.5 3.7 1.8 15.4 2.9 9.1 14.3 Fast 1.1 0.9 0.6 0.5 1.2 0.9 1.0 0.5 1.4 1.3 1.6 0.3 0.4 0.2 0.4 17.8 Units m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr hrs/no hrs/no hrs/no hrs/no hrs/m hrs/m hrs/m m2/hr m2/hr m2/hr

These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to calculate their productivity depending on the resources available and conditions of work.

Typical Productivity Rates (Example)


22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 Bitumen DPC, vertical under 100mm wide Bitumen DPC, vertical100-225mm wide Bitumen DPC, vertical over 225mm wide Reinforcement ExMet, horizontal under 100mm wide Reinforcement ExMet, horizontal over 100mm wide Reinforcement ExMet, vertical under 100mm wide Reinforcement ExMet, vertical over 100mm wide Face Finish as work Proceeds, Raking Out Face Finish as work Proceeds, Flush and Rubbed Face Finish as work Proceeds, Struck Pointing Face Finish as work Proceeds, Bag Rubbed Face Finish as work Proceeds, Bucket Handle Face Finish as work Proceeds, Recessed 5-10mm Face Finish after completion, Flush and Rubbed Face Finish after completion, Struck Pointing Face Finish after completion, Bucket Handle 26.3 4.2 2.8 5.4 4.2 1.9 2.5 5.8 7.8 10.0 5.8 9.1 3.8 5.8 27.8 4.3 3.0 1.1 5.6 4.7 2.0 1.3 2.7 29.4 4.5 3.1 5.8 4.9 2.1 1.2 2.9 m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

Construction Wet Trades - Plastering Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Task / Description Browning (undercoat), Internal Walls under 2.5m high Browning (undercoat), Internal Walls over 2.5m high Browning (undercoat), Reveals and Columns less than 100mm wide Browning (undercoat), Reveals and Columns 100-200mm wide Browning (undercoat), Reveals and Columns 200-300mm wide Covings Skimming (topcoat), Internal Walls under 2.5m high Skimming (topcoat), Internal Walls over 2.5m high Skimming (topcoat), Reveals and Columns less than 100mm wide Skimming (topcoat), Reveals and Columns 100-200mm wide Skimming (topcoat), Reveals and Columns 200-300mm wide Plaster Board to Ceilings Plastering Ceilings, 1 Bonding, 1 Skimming Plastering Ceilings, Topcoat Skimming Slow 2.2 2.1 9.9 5.2 3.3 6.1 5.5 12.6 7.7 4.5 3.2 1.1 2.7 Ave 2.8 2.6 10.0 5.4 3.6 5.0 6.7 6.1 13.8 8.3 5.0 4.5 1.7 3.2 Fast 3.1 2.8 10.1 6.4 3.9 7.3 6.7 15.4 9.8 5.5 5.5 2.4 5.4 Units m2/hr m2/hr m2/hr m2/hr m2/hr m/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr

Construction Wet Trades - Rendering Sr. No. 1 2 3 4 5 Task / Description Large Wall Areas, applied in 2 coats Small Wall Areas, applied in 2 coats Narrow Widths, applied in 2 coats Columns and Beams, applied in 2 coats Staircase and Soffits, applied in 2 coats Slow Ave 2.2 1.5 1.2 1.5 1.4 Fast 2.7 1.7 1.4 1.7 Units m2/hr m2/hr m2/hr m2/hr m2/hr

Construction Wet Trades - Screeding Sr. No. 1 2 3 4 5 6 7 Task / Description Sand/Cement Floor Screed, 15-20mm thick Sand/Cement Floor Screed, 20-30mm thick Sand/Cement Floor Screed, 30-40mm thick Sand/Cement Floor Screed, 40-50mm thick Sand/Cement Floor Screed, 50-65mm thick Sand/Cement Floor Screed, 65-100mm thick Fix/Setout Screed Battens Slow 3.2 2.0 Ave 4.8 4.6 4.2 3.8 3.3 3.0 10.0 Fast 5.7 5.5 5.3 5.2 3.9 3.6 Units m2/hr m2/hr m2/hr m2/hr m2/hr m2/hr m/hr

These productivity rates are calculated based on certain set of tools, site and weather conditions and skilled resources available. Contractor to calculate their productivity depending on the resources available and conditions of work.