You are on page 1of 41

Diseo de Zapata Aislada

Datos
Columna (bxt)
25
Carga muerta
5
Carga viva
6
F'c
210
Fy
4,200
0.8
t
Pz (%)
10%

A.

x
40
Tn
Tn
Kg/cm2
Kg/cm2
2
Kg/cm

(cm)

t
4
3
2
1

Pz
4%
6%
8%
10%

Dimensionamiento en Planta:

P=
Pz =

11
2.5

Tn
Tn

Az =

t
B

Az = 150

B.

cm

16,875

A=
B=

137 cm. 150 cm


122 cm. 135 cm

m=
n=

55
55

135

cm
cm
20,250

cm2

Dimensionamiento en Elevacin:
B.1 Cortante por Punzonamiento:
Presin real del suelo:

Wu =

Vc=
Vc=

1.4

WD

+
Az

1.7

Wu [(AxB) - (b+d)(t+d)]
2d(b+t+2d)

WL

Si: d

0.5

2
0.85 Kg/cm

m=
d=

27.5 cm
40 cm (Asumir)

2
1.102 Kg/cm

Esfuerzos Permisibles:

2 =

20

(Seleccionar el menor)

V uc=
V uc=
V uc=
V uc=

13.55 Kg/cm2

0.27 (2 + 4 / c) f'c =

14.97 Kg/cm

1.1 f'c =

2
13.55 Kg/cm

0.27 (2d/bo + 2 ) f'c =

2
15.83 Kg/cm

>

Vc

Ok!

bo =

290

B.1 Cortante por Flexin:

Vc=

Wu (m-d)
d

Vc=

0.32 Kg/cm

V uc=

0.53 f'c

V uc=

6.528 Kg/cm2

>

Vc

Ok!
h=

C.

50

cm

rea de Acero:

Mu1 =

Wu A m2
2

Mu1 =

192,704

Si: a

0.1

As1 =

Mu
fy (d-a/2)

a=

As fy
0.85 f'c b

Si: a =

d, a =

Kg-cm
4

cm
As1 = 1.342 cm2

a=

0.21 cm

As1 = 1.278 cm2

0.21 cm

As min = 0.0018 A h = 13.50 cm2

>
7

As1 = 1.278 cm2

5/8 "

5/8

Usar Asmin
13.86 cm2
Ok!

Mu2 =

Wu B m2
2

Mu2 =

173,433
Si: a =

"

@ 22.17 cm

Kg-cm
0.25 cm
B

As2 =

Mu
fy (d-a/2)

a=

As fy
0.85 f'c b

As2 = 1.151 cm2

a=

As min = 0.0018 B h = 12.15 cm2

0.20 cm

>
6

As2 = 1.151 cm2

5/8 "

5/8

Usar Asmin
11.88 cm2
Corregir!

"

@ 23.6 cm

D.

Verificacin :
D.1 Verificacin por Adherencia:
Ld =

47.5 cm

0.06 Av fy
f'c
0.006 dv fy

=
=

34.42 cm

<

Ld

Adecuado por adherencia

40.01 cm

<

Ld

Adecuado por adherencia

30 cm

<

Ld

Adecuado por adherencia

D.2 Verificacin por Transferencia de Esfuerzos:


fa =
fau =

Pu
bxt

17.2 Kg/cm2

0.85 f'c A2/A1 =


fa =

2
303.5 Kg/cm

17.2 Kg/cm2

<

fau =

303.5 Kg/cm2

Conforme!

D.3 Verificacin Peso Estimado de Zapata:


Pz =

A x B x h x 2400 =

2,430

Kg

<

Pz est.

2.5

Tn

Conforme!

0.5

1.5

5/8 "

@ 0.22 m

5/8 "

@ 0.24 m

1.35

1.5

DNI

Diseo de Zapata Aislada


Datos
Columna (bxt)
25
Carga muerta
2
Carga viva
2
F'c
210
Fy
4,200
0.8
t
Pz (%)
10%

A.

x
40
Tn
Tn
Kg/cm2
Kg/cm2
2
Kg/cm

(cm)

t
4
3
2
1

Pz
4%
6%
8%
10%

Dimensionamiento en Planta:

P=
Pz =

4
2

Tn
Tn

Az =

t
B

Az = 110

B.

cm

7,500

A=
B=

94
79

cm. 110 cm
cm. 95 cm

m=
n=

35
35

cm
cm

95

10,450

cm2

Dimensionamiento en Elevacin:
B.1 Cortante por Punzonamiento:
Presin real del suelo:

Wu =

Vc=
Vc=

1.4

WD

+
Az

1.7

Wu [(AxB) - (b+d)(t+d)]
2d(b+t+2d)

WL

Si: d

0.5

2
0.59 Kg/cm

m=
d=

17.5 cm
40 cm (Asumir)

2
0.269 Kg/cm

Esfuerzos Permisibles:

2 =

30

(Seleccionar el menor)

V uc=
V uc=
V uc=
V uc=

13.55 Kg/cm2

0.27 (2 + 4 / c) f'c =

14.97 Kg/cm

1.1 f'c =

2
13.55 Kg/cm

0.27 (2d/bo + 2 ) f'c =

2
20.41 Kg/cm

>

Vc

Ok!

bo =

290

B.1 Cortante por Flexin:

Vc=

Wu (m-d)
d

Vc=

-0.07 Kg/cm

V uc=

0.53 f'c

V uc=

6.528 Kg/cm2

>

Vc

Ok!
h=

C.

50

cm

rea de Acero:

Mu1 =

Wu A m2
2

Mu1 =

39,974

Si: a

0.1

As1 =

Mu
fy (d-a/2)

a=

As fy
0.85 f'c b

Si: a =

d, a =

Kg-cm
4

As1 = 0.278 cm2

a=

0.06 cm

As1 = 0.265 cm2

0.06 cm

As min = 0.0018 A h =

cm

9.90 cm2

>
6

As1 = 0.265 cm2

5/8 "

5/8

Usar Asmin
11.88 cm2
Ok!

Mu2 =

Wu B m2
2

Mu2 =

34,523
Si: a =

"

@ 18.6 cm

Kg-cm
0.25 cm
B

As2 =

Mu
fy (d-a/2)

a=

As fy
0.85 f'c b

As min = 0.0018 B h =

As2 = 0.229 cm2

a=

8.55 cm2

0.06 cm

>
6

As2 = 0.229 cm2

5/8 "

5/8

Usar Asmin
11.88 cm2
Ok!

"

@ 15.6 cm

D.

Verificacin :
D.1 Verificacin por Adherencia:
Ld =

27.5 cm

0.06 Av fy
f'c
0.006 dv fy

=
=

34.42 cm

>

Ld

No es adecuado por adherencia

40.01 cm

>

Ld

No es adecuado por adherencia

30 cm

>

Ld

No es adecuado por adherencia

D.2 Verificacin por Transferencia de Esfuerzos:


fa =
fau =

Pu
bxt

6.2 Kg/cm2

0.85 f'c A2/A1 =


fa =

2
303.5 Kg/cm

6.2 Kg/cm2

<

fau =

303.5 Kg/cm2

Conforme!

D.3 Verificacin Peso Estimado de Zapata:


Pz =

A x B x h x 2400 =

1,254

Kg

<

Pz est.

Tn

Conforme!

0.5

1.1

5/8 "

@ 0.19 m

5/8 "

@ 0.16 m

0.95

1.1

DNI

Diseo de Zapatas Combinadas


Datos
Col. 1 (bxt)
Col. 2 (bxt)
PD 1
PL 1
PD 2
PL 2
F'c
Fy

25
25
3
2
3
2
210
4,200
0.8

t
Pz (%)
S

A.

x
x

40
40

(cm)
(cm)

Tn
Tn
Tn
Tn
2
Kg/cm
2
Kg/cm
Kg/cm2

t
4
3
2
1
(Kg/cm2)

10.0%

1.95 m.

Pz
4%
6%
8%
10%

Dimensionamiento en Planta:

Pz =

P=
Pz =

B C1 b

C2

Az =
b

10
3

Tn
Tn

16,250

cm2

M : R.X' = P2.S
X' = 0.98 m.

S
P1

P2

R
x'
L/2

B.

L=
L=

2.35 m.
2.60 m. (Asumir)

B=
B=

0.63 m.
1.00 m. (Asumir)

Dimensionamiento en Elevacin:
Presin real del suelo:

Wu =
P1

P2

Corte Crtico

1.4

WD

+
L

Pu1 =
Pu2 =

8
8

1.7

WL

0.25

Tn
Tn

Diagrama de Fuerza Cortante

VA =
VB =
VC =
C

A
y

-5.3 Tn
3.8 Tn
-1.46 Tn

5.85 Tn/ml

Diagrama de Momentos Ultimos


M mx = 3.42

Tn-m

Pu2 = Wu x Y
Y = 1.30 m.
X = 1.30 m.
Mu C = 0.1827 Tn-m

Mmx = 3.42 Tn-m


Mu C = 0.183 Tn-m
Corte por Flexin:
Vu = V u . b.d
Corte Crtico: Vud = VB - Wu.d
V uc= 0.53 f'c =
si se considera:
Vud = V uc . B.d.

6.53 Kg/cm
d=
d=
h=

5.342 cm.
40.00 cm. (Asumir)
50.00 cm.

B.1 Cortante por Punzonamiento:


Esfuerzos Permisibles:

2 =

20

(Seleccionar el menor)

V uc=
V uc=
V uc=
V uc=

0.27 (2 + 4 / c) f'c =

2
14.97 Kg/cm

1.1 f'c =

2
13.55 Kg/cm
2
15.83 Kg/cm

0.27 (2d/bo + 2 ) f'c =

bo =

290

13.55 Kg/cm2

Columna Exterior:
t+d/2

V c=

Vu
bo.d

V c=

(permetro) bo=
Area =
Vu =

0.719 Kg/cm2

<

185 cm.
2
0.39 m
5,320 Kg

V uc

b+d

Ok!

Columna Exterior:
t+d

V c=

Vu
bo.d

V c=

(permetro) bo=
Area =
Vu =

0.393 Kg/cm2

Se verifica que:

<

290 cm.
2
0.52 m
4,560 Kg

V uc

Ok!

d = 40.00 cm.

y h = 50.00 cm.

b+d

C.

rea de Acero:
Tramo

Mu =

3,420

Kg-cm

Si: a

0.13 d a =

5.2

As1 =

Mu
fy (d-a/2)

a=

As fy
0.85 f'c b

As1 = 2.419 cm2

a=

14 . B.d
4,200

0.569 cm

As1 = 2.276 cm2

Si: a = 0.506 cm

As min =

cm

13.33 cm2

>
7

As1 = 2.276 cm2

5/8 "

5/8

Usar Asmin
13.86 cm2
Ok!

Mu2 =

Apoyo
Interior

183

@ 13.9 cm

Kg-cm

Si: a =

2.0

cm

As2 =

Mu
fy (d-a/2)

As2 =

0.12 cm2

a=

As fy
0.85 f'c b

a=

0.03 cm

As min =

"

14 . B.d
4,200

13.33 cm2

>
7

As2 = 0.124 cm2

5/8 "

5/8

Usar Asmin
13.86 cm2
Ok!

Acero
Transaversal
Presin Real
del Suelo

0.375

Apoyo Exterior = t1 + 0.75.d =


Apoyo Interior = t2 + 1.5.d =

@ 13.9 cm

cm.
cm.

Col. Interior
Wu =

Si: a =

B As2 =

0.375

70
100

"

a=
As min =

0.1

Mu =
cm

Pu2
B
534

Kg/ml

0.35

cm2

Kg-m

Mu
fy (d-a/2)

As2 =

As fy
0.85 f'c b

a=

14 . B.d
4,200

7,600

13.33 cm2

0.08 cm
>

As2 = 0.354 cm2

5/8 " @

Usar Asmin
14.2 cm


D.

5/8

" @ 15.00 cm

Verificacin :
D.1 Verificacin Peso Estimado de Zapata:
Pz =

L x B x h x 2.4 =

Vol. Zapat. =

3.12

Tn

>

Pz est. 3.00 Tn

1.3 m3

Corregir!

5/8

"

@ 0.14 m

0.50

2.60
7

1.00

2.60

5/8 "

@ 0.14 m

5/8 "

@ 0.15 m

DNI

Diseo de Zapatas Combinadas


Datos
Col. 1 (bxt)
Col. 2 (bxt)
PD 1
PL 1
PD 2
PL 2
F'c
Fy

25
25
3
3
4
4.5
210
4,200
0.8

t
Pz (%)
S

A.

x
x

40
40

(cm)
(cm)

Tn
Tn
Tn
Tn
2
Kg/cm
2
Kg/cm
Kg/cm2

t
4
3
2
1
(Kg/cm2)

10.0%

1.80 m.

Pz
4%
6%
8%
10%

Dimensionamiento en Planta:

Pz =

1.45

B C1 b

C2

P=
Pz =

14.5 Tn
3.1 Tn

Az =

22,000

cm2

M : R.X' = P2.S
X' = 1.06 m.

S
P1

P2

R
x'
L/2

B.

L=
L=

2.51 m.
2.55 m. (Asumir)

B=
B=

0.86 m.
1.00 m. (Asumir)

Dimensionamiento en Elevacin:
Presin real del suelo:

Wu =
P1

P2

Corte Crtico

1.4

WD

+
L

Pu1 =
Pu2 =

9
13

1.7

WL

0.35

Tn
Tn

Diagrama de Fuerza Cortante

VA =
VB =
VC =
C

A
y

-5.8 Tn
6.618 Tn
-3.1 Tn

8.84 Tn/ml

Diagrama de Momentos Ultimos


M mx = 3.0302 Tn-m

Pu2 = Wu x Y
Y = 1.50 m.
X = 1.05 m.
Mu C = 0.5416 Tn-m

Mmx = 3.03 Tn-m


Mu C = 0.542 Tn-m
Corte por Flexin:
Vu = V u . b.d
Corte Crtico: Vud = VB - Wu.d
V uc= 0.53 f'c =
si se considera:
Vud = V uc . B.d.

6.53 Kg/cm
d=
d=
h=

8.927 cm.
40.00 cm. (Asumir)
50.00 cm.

B.1 Cortante por Punzonamiento:


Esfuerzos Permisibles:

2 =

40

(Seleccionar el menor)

V uc=
V uc=
V uc=
V uc=

0.27 (2 + 4 / c) f'c =

2
14.97 Kg/cm

1.1 f'c =

2
13.55 Kg/cm
2
25.00 Kg/cm

0.27 (2d/bo + 2 ) f'c =

bo =

290

13.55 Kg/cm2

Columna Exterior:
t+d/2

V c=

Vu
bo.d

V c=

(permetro) bo=
Area =
Vu =

0.791 Kg/cm2

<

185 cm.
2
0.39 m
5,851 Kg

V uc

b+d

Ok!

Columna Exterior:
t+d

V c=

Vu
bo.d

V c=

(permetro) bo=
Area =
Vu =

0.746 Kg/cm2

Se verifica que:

<

290 cm.
2
0.52 m
8,652 Kg

V uc

Ok!

d = 40.00 cm.

y h = 50.00 cm.

b+d

C.

rea de Acero:
Tramo

Mu =

3,030

Kg-cm

Si: a

0.13 d a =

5.2

As1 =

Mu
fy (d-a/2)

a=

As fy
0.85 f'c b

As1 = 2.143 cm2

a=

14 . B.d
4,200

0.504 cm

As1 = 2.017 cm2

Si: a = 0.504 cm

As min =

cm

13.33 cm2

>
7

As1 = 2.017 cm2

5/8 "

5/8

Usar Asmin
13.86 cm2
Ok!

Mu2 =

Apoyo
Interior

542

@ 13.9 cm

Kg-cm

Si: a =

2.0

cm

As2 =

Mu
fy (d-a/2)

As2 =

0.37 cm2

a=

As fy
0.85 f'c b

a=

0.09 cm

As min =

"

14 . B.d
4,200

13.33 cm2

>
7

As2 = 0.367 cm2

5/8 "

5/8

Usar Asmin
13.86 cm2
Ok!

Acero
Transaversal
Presin Real
del Suelo

0.375

Apoyo Exterior = t1 + 0.75.d =


Apoyo Interior = t2 + 1.5.d =

@ 13.9 cm

cm.
cm.

Col. Interior
Wu =

Si: a =

B As2 =

0.375

70
100

"

a=
As min =

0.1

Mu =
cm

Pu2
B
932

Kg/ml

Kg-m

Mu
fy (d-a/2)

As2 =

As fy
0.85 f'c b

a=

14 . B.d
4,200

13,250

13.33 cm2

0.62

cm2

0.15 cm
>

As2 = 0.617 cm2

5/8 " @

Usar Asmin
14.2 cm


D.

5/8

" @ 15.00 cm

Verificacin :
D.1 Verificacin Peso Estimado de Zapata:
Pz =

L x B x h x 2.4 =

3.06

Tn

<

Pz est. 3.10 Tn

Vol. Zapat. = 1.275 m3

Conforme!

5/8

"

@ 0.14 m

0.50

2.55
7

1.00

2.55

5/8 "

@ 0.14 m

5/8 "

@ 0.15 m

DNI

Diseo de Zapatas Combinadas


Datos
Col. 1 (bxt)
Col. 2 (bxt)
PD 1
PL 1
PD 2
PL 2
F'c
Fy

25
25
4
4.5
4
2
210
4,200
0.8

t
Pz (%)
S

A.

x
x

40
40

(cm)
(cm)

Tn
Tn
Tn
Tn
2
Kg/cm
2
Kg/cm
Kg/cm2

t
4
3
2
1
(Kg/cm2)

10.0%

2.05 m.

Pz
4%
6%
8%
10%

Dimensionamiento en Planta:

Pz =

1.45

B C1 b

C2

P=
Pz =

14.5 Tn
3 Tn

Az =

21,875

cm2

M : R.X' = P2.S
X' = 0.85 m.

S
P1

P2

R
x'
L/2

B.

L=
L=

2.10 m.
2.70 m. (Asumir)

B=
B=

0.81 m.
1.00 m. (Asumir)

Dimensionamiento en Elevacin:
Presin real del suelo:

Wu =
P1

P2

Corte Crtico

1.4

WD

+
L

Pu1 =
Pu2 =

13
9

1.7

WL

0.25

Tn
Tn

Diagrama de Fuerza Cortante

VA =
VB =
VC =
C

A
y

-10.0 Tn
3.644 Tn
-2.06 Tn

8.24 Tn/ml

Diagrama de Momentos Ultimos


M mx = 8.0021 Tn-m

Pu2 = Wu x Y
Y = 1.09 m.
X = 1.61 m.
Mu C = 0.2575 Tn-m

Mmx = 8.002 Tn-m


Mu C = 0.258 Tn-m
Corte por Flexin:
Vu = V u . b.d
Corte Crtico: Vud = VB - Wu.d
V uc= 0.53 f'c =
si se considera:
Vud = V uc . B.d.

6.53 Kg/cm
d=
d=
h=

4.956 cm.
40.00 cm. (Asumir)
50.00 cm.

B.1 Cortante por Punzonamiento:


Esfuerzos Permisibles:

2 =

20

(Seleccionar el menor)

V uc=
V uc=
V uc=
V uc=

0.27 (2 + 4 / c) f'c =

2
14.97 Kg/cm

1.1 f'c =

2
13.55 Kg/cm
2
15.83 Kg/cm

0.27 (2d/bo + 2 ) f'c =

bo =

290

13.55 Kg/cm2

Columna Exterior:
t+d/2

V c=

Vu
bo.d

V c=

(permetro) bo=
185 cm.
2
Area = 0.39 m
Vu = 10,036 Kg

1.356 Kg/cm2

<

V uc

b+d

Ok!

Columna Exterior:
t+d

V c=

Vu
bo.d

V c=

(permetro) bo=
Area =
Vu =

0.406 Kg/cm2

Se verifica que:

<

290 cm.
2
0.52 m
4,715 Kg

V uc

Ok!

d = 40.00 cm.

y h = 50.00 cm.

b+d

C.

rea de Acero:
Tramo

Mu =

8,002

Kg-cm

Si: a

0.13 d a =

5.2

As1 =

Mu
fy (d-a/2)

As1 =

a=

As fy
0.85 f'c b

a=

14 . B.d
4,200

5.66 cm2

1.332 cm

As1 = 5.377 cm2

Si: a = 1.266 cm

As min =

cm

13.33 cm2

>
7

As1 = 5.377 cm2

5/8 "

5/8

Usar Asmin
13.86 cm2
Ok!

Mu2 =

Apoyo
Interior

258

@ 13.9 cm

Kg-cm

Si: a =

0.1

cm

As2 =

Mu
fy (d-a/2)

As2 =

0.17 cm2

a=

As fy
0.85 f'c b

a=

0.04 cm

As min =

"

14 . B.d
4,200

13.33 cm2

>

As2 =

0.17 cm2

Usar Asmin

5/8 "

13.86 cm2

5/8

Ok!

Acero
Transaversal
Presin Real
del Suelo

0.375

Apoyo Exterior = t1 + 0.75.d =


Apoyo Interior = t2 + 1.5.d =

@ 13.9 cm

cm.
cm.

Col. Interior
Wu =

Si: a =

B As2 =

0.375

70
100

"

a=
As min =

0.1

Mu =
cm

Pu2
B
633

Kg/ml

0.42

cm2

Kg-m

Mu
fy (d-a/2)

As2 =

As fy
0.85 f'c b

a=

14 . B.d
4,200

9,000

13.33 cm2

0.10 cm
>

As2 = 0.419 cm2

5/8 " @

Usar Asmin
14.2 cm


D.

5/8

" @ 15.00 cm

Verificacin :
D.1 Verificacin Peso Estimado de Zapata:
Pz =

L x B x h x 2.4 =

Vol. Zapat. =

3.24

Tn

>

Pz est. 3.00 Tn

1.35 m3

Corregir!

5/8

"

@ 0.14 m

0.50

2.70
7

1.00

2.70

5/8 "

@ 0.14 m

5/8 "

@ 0.15 m

DNI

Diseo de Zapatas Conectadas


Datos
Col. 1 (bxt)
Col. 2 (bxt)
PD 1
PL 1
PD 2
PL 2
F'c
Fy

50
62
70
26
120
45
210
4,200
3.16

t
Pz (%)
L

A.

x
x

50
62

(cm)
(cm)

Tn
Tn
Tn
Tn
Kg/cm2
Kg/cm2
Kg/cm2

t
4
3
2
1
(Kg/cm2)

6.0%

6.20 m.

Dimensionamiento en Planta:
P1 =
R1 =

96 Tn
115 Tn

Az =

36,456

S
t

T C1 b

C2

P1

b = 0.50

cm2
h = 0.90

B.

Pz
4%
6%
8%
10%

P2

S=
S=

1.35 m.
1.35 m. (Asumir)

h=
h=

0.89 m.
0.90 m. (Asumir)

b=
b=

0.50 m.
0.50 m. (Asumir)

Dimensionamiento en Elevacin:
Dimensionamiento de Zapata Exterior:
P1 =

96 t

Wv =
Wv = 1.08

t/m
2

RN

C.

M2 = 0
RN = 107.0 Tn
2
Az = Rn / t = 3.38 m
T=
T=

S = 1.35

0.675

1.08 Tn/m

2.51 m
2.55 m. (Asumir)

5.775

rea de Acero:
Diseo de la Viga de conexin:
P1u =125.6 t
Wvu =

P 1u = 125.6 Tn
t/m

F PD =
F PL =

1.2
1.6

Wvu =

1.30 t/m

W vu = 1.30 Tn/m
M2 = 0
R NU = 139.5 Tn
W NU = 103 Tn/m

1.35
RNU

W NU

5.775
6.20

Seccin de momento Mximo, Xo < S


Vx = (W

UN

- Wvu) Xo - P1u = 0

Xo = 1.23

<

S = 1.35

Conforme!

Mu mx = -45.9 Tn-m
d = h - 7.25

cm =

82.8

cm

As = Mu/(0.9*fy*0.9*d)
2
As = 16.30 cm
a = 7.67 cm
2
As = 15.48 cm
a = 7.29 cm
As min =

13.79 cm2

14 . B.d
4,200

<

As1 = 15.48 cm2

"

Conforme!
20.27 cm2
Ok!

Refuerzo en la carga inferior


As + =

As 3

As - As min
2

10.1 cm2
As min = 13.79 cm2

As =

>
5

As = 10.13 cm2

3/4 "

Usar Asmin
14.25 cm2
Ok!

1 "

3/4 "

Diseo por Corte:

V1u
d
V2u

V1u =

9.87 Tn

V2u =

12.16 Tn

Vn = 12.16

W NU

Usar: Estribos de Montaje

Vc =

0.53.f'c.b.d =

s 36

16.2 Tn

31.8 Tn

68.58 cm

>

Vn
Conforme!

Estribos: 3/8 " @

0.65 m

Diseo de la Zapata Exterior:


W

UN

54.7 Tn/m

0.5
1.03

Mumax = 28.74 Tn-m


si =

= fy/f'c
= 0.08

0.004

W NU

2
Mu = * f'c * b * d * * (1-0.59)

2.55

d = 38.44 cm
Usar

h=

50

cm

d = 41.55 cm

Diseo por Corte:


Vud = W NU (Lv - d)
Vud = 33.3
Tn

Vn = Vud /
Vn = 44.5 Tn
Vc =

0.53.f'c.b.d =

43.1 Tn

<

Vn
Corregir

Diseo por Flexin:


As = Mu/(0.9*fy*0.9*d)
As = 20.3 cm2
a = 3.54 cm
2
As = 19.12 cm
a = 3.33 cm
As min =

14 . B.d
4,200

18.70 cm2

<
8

As1 = 19.12 cm2


3/4 "

Conforme!
22.80 cm2
Ok!

Usar : 8

3/4"

Refuerzo Transversal
As Temp = 0.0018.b.t =

0.17 m

22.95 cm2
12

5/8 "

23.75 cm2
Ok!

Usar : 12

5/8"

0.22 m

Diseo de la Zapata Interior:


P2

P1

Wv

P2 efect. =
P2 efect. =
P2u efect. =
P2u efect. =

-P2 - P1 - WvLv + RN
-161.0 Tn
-P2u - P1u - WvuLvu + RNu
-210.4 Tn

Az = P2 efect./n
Az = 5.10 m2

RN

Usar:

2.30 x 2.30 m

Wnu = P2uefect./Az
Wnu = 39.8 Tn/m2

L
n

( 2.26 x 2.26 )m2

Lv = 0.84 m
2
Mu max = Wun Lv /2
Mu max = 32.28 Tn-m

5.29 m2 )

Usar:
h min = 0.50 m

d = 40.59 cm

Verificacin por Punzonamiento :


Vu = Pu2 efect. - Wnu (m)(n)
m = 1.66 m
n = 0.91 m
Vu = 151 Tn
Vn = Vu/
Vn = 201 Tn
bo =

4.23 m

Vc = 1.06.f'c.bo.d =
264 Tn
>
Vc =

Vn
Conforme!

Verificacin por corte:


Vud = (Wnu L)(Lv - d) =
Vud = 39.7 Tn

Vn = Vu/
53
Vn =

Tn

Vc = 0.53.f'c.b.d =
71.7 Tn
Vc =

>

Vn
Conforme!

Diseo por Flexin :


As = Mu/(0.9*fy*0.9*d)
As = 23.4 cm2
a = 2.39 cm
2
As = 21.68 cm
a = 2.22 cm
As min =

14 . B.d
4,200

31.12 cm2

>
11

As1 = 21.68 cm2

3/4 "

Usar Asmin
31.35 cm2
Ok!

Usar : 11

3/4"

As Temp = 0.0018.b.t =

0.21 m

20.7 cm2
11

5/8 "

21.77 cm2
Ok!

Usar : 11

5/8"

8 3/4 " @

0.17

0.21 m

B
h = 0.5

11 3/4" @

0.21

h = 0.50

2.55

2.30

VC - ( 0.50x 0.90)

2.30
1.35
12 5/8" @

0.22

11 5/8" @

0.21

DNI