INSPECTION REQUEST FORM FOR PILING WORKS (DRIVEN PILE)

Unless otherwise approved,this inspection request form shall be submitted during the daily morning meeting among LTA,Contractor and QP(S) Contractor: Project: SAMWOH CORPORATION PTE LTD SK E & C To: LTA

NO:

ER296-CONSTRUCTION AND COMPLECTION OF SENTOSA GATEWAY TUNNEL FROM TELOK BLANGAH ROAD TO KEPPEL ROAD / KAMPONG BAHRU ROAD/ LOWER DELTA ROAD AND ASSOCIATED ROAD WIDENING WORKS INTERCHANGE

Date: Time:

The work described below has been inspected by our Site Engineer and is complete and ready for your inspection. A checklist is attached overleaf. Location Checked and Requested By: Chainage Activity Drawings Used for Construction Other Description Contractor's PM Name & Signature

The meeting noted that the information provided by the Contractor is adequate/not adequate*. QP(S) may proceed work approved to start:__________________ Request Rejected work completed on:________________________

INITIAL INSPECTION DECISION BY QP(S)


We have inspected the above referenced works and found them acceptable. You may proceed. However, please return the completed checklist upon completion of the remaining work. You cannot proceed. Please carry out corrective works as noted on the checklist and submit a fresh request for inspection. Other comments:

RTO/RE Name & Signature/ Date

FINAL INSPECTION DECISION BY QP(S)


__________________________________ QP(S) Name& Signature/Date

work approved to start:_______________

work completed on:_______________________

LTA The above process for request for inspection of work by Contractor and approval by Qp(S) is noted. __________________________________ LTA's Representative/date/time

CHECKLIST FOR PILING WORKS (DRIVEN PILE) NO:


Date,Time:
S/No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

Location:
Description of Works Check setting out Check pegged position of individual pile Check services plan Locate services with cable detector and digging trial trench Check mill certificate Check whether coating on pile is required Check set specified

Chainage:
Checked by Contractor Confirmed by QP(S)

Check certificate of fitness of piling machine and service crane Check certificate of crane operator Check piling frame and crane located on firm bases Check pile dimensions Check pile defects Check verticality of piles Check welding requirement for joints and plates Check set and calculate working load Check risen piles Check eccentricity of individual pile Check cut-off level of pile Take sample for testing Check sufficient temporary traffic devices if lane closure is required Others