P/F P.V.

C doors of approved quality and manufacturer i/c all fittings complete as approved and directed by the Engineer Incharge.

(Analysis for 2 x7=17.5 Sft) Cost of vinyle door Hardware/accessories Fitting Charges Carriage from market to site of work 17.5 Sft @440/Sft 450/Each door 350/Each door 300/Each door Total Add 20% Contractor profit Total Rate Per Sft Say 10620/17.5 7700/450/350/200/8820/1770/10620/606.85/Sft 600/Sft

Sub Divisional Officer Provincial Buildings Sub Division-I Sargodha

Executive Engineer Provincial Buildings Division Sargodha

ANALYSIS OF RATE
P/F Non clogging centrifugal pump 3x4 in position of centrifugal pump 0.5 cusecs coupled with electric motor 05 BHP (Siemens) made head 40 ft i/c bowl assembly impellers pump shaft top set erection of suspension clumps cable clamps sluice valves reflex valves circuit breaker etc dry running protection device complete in all respects as approved and directed by the Engineer In charge. ___________

Cost of machinery (Quotation attached)

370000/-

Cost of c conc foundation Total

5000/382000/-

Contractor profit and overhead (11%) Total Say

42020/424020/424000/-

It is certificate that the N.S item. rates as taken in the analysis which are not included in the rate are prevailing market rates and are verified for the market.

Sub-Divisional Officer,

Provincial Buildings Sub-Division No. 1, Sargodha

ANALYSIS OF RATE
P/F Water supply centrifugal pump 3x4 in position of centrifugal pump 0.5 cusecs coupled with electric motor 05 BHP (Siemens) made head 40 ft i/c bowl assembly impellers pump shaft top set erection of suspension clumps cable clamps sluice valves reflex valves circuit breaker etc dry running protection device complete in all respects as approved and directed by the Engineer In charge. ___________

Cost of machinery (Quotation attached)

325000/-

Cost of c conc foundation Total

5000/330000/-

Contractor profit and overhead (11%) Total Say

36300/366300/366000/-

It is certificate that the N.S item. rates as taken in the analysis which are not included in the rate are prevailing market rates and are verified for the market.

Sub-Divisional Officer, Provincial Buildings Sub-Division No. 1, Sargodha

ANALYSIS OF RATE
P/F Water supply Submersible turbine 0.25 cusecs as approved and directed by the Engineer In charge. ___________

Cost of machinery (Quotation attached)

1000000/-

Cost of c conc foundation Total

5000/1005000/-

Contractor profit and overhead (11%) Total Say

110000/1115000/1115000/-

It is certificate that the N.S item. rates as taken in the analysis which are not included in the rate are prevailing market rates and are verified for the market.

Sub-Divisional Officer, Provincial Buildings Sub-Division No. 1, Sargodha

ANALYSIS OF RATE
P/F of white board size 8x4 and thick made of chip board laminated with Formica i/c beading and lipping on four sides complete in all respects as approved/directed by the Engineer Incharge. ___________ Unit of Analysis Each of size 8x4

Material

Cost of Chip board (8x4)

1050/-

Cost of Formica

600/-

Cost of adhesive

300/-

Cost of beading

24Rft@20/Rft

480/-

Cost of lipping

24Rft@15/Rft

360/-

Carriage from workshop to site of work Total

500/3290/-

Laboure

Laboure for making of white board

500/-

Laboure for fixing of white board on wall i/c nailing and screwing

200/-

Total

700/-

G Total

3990/-

Contractor profit and overhead (20%) Total Say

798/4788/4788/-

It is certificate that the N.S item. rates as taken in the analysis which are not included in the rate are prevailing market rates and are verified for the market.

Sub-Divisional Officer, Provincial Buildings Sub-Division No. 1, Sargodha