You are on page 1of 4

JOB SAFETY ANALYSIS FOR EXCAVATION AND BLINDING AT PH 1 & 3

COMMON COOLING SEAWATER SYSTEM PHASE 2 SEQUENCE OF BASIC ACTIVITY STEPS 1.0 Weather POTENTIAL HAZARDS 1.1 Sun Burn 1.2 Heat stress and dehydration 1.3 Dust 2.0 Excavation 2.1 Collapse of Excavation 2.2 Fall and hit 2.3 Movement of Machinery HAZARDS CONTROL 1.1.1 Adequate shelter to be provided for workers to take rest 1.2.1 Sufficient quantity of cool drinking water will be made 1.2.2 Rotation of workers will be made suitably 1.3.1 Water will be sprayed to suppress the dust and dust mask to be provided to workers 2.1.1 Sloping,shoring benching will be applied as applicable. 2.2.1 Excavated materials to be kept away from 2 meters from the edge of excavation. 2.3.1 Equipment will be equiped with Reverse alarm and revolving warning light Banks Man will be provided for heavy equipments with reflective jackets 2.4.1 Excavated area must be barricaded with crash barrier and deep excavation sign board to be displayed. 2.4.2 Proper access and egress will be kept available 2.4.3 Aluminium lader or ladder with guard to be provided excavated place for access and egress 2.5.1 Underground services to be identified and start the work RESPONSIBLE Dodsal Supervisor

Dodsal Supervisor

2.4 Deep Fall

2.5 Underground services

1 of 4

JOB SAFETY ANALYSIS FOR EXCAVATION AND BLINDING AT PH 1 & 3

COMMON COOLING SEAWATER SYSTEM PHASE 2 SEQUENCE OF BASIC ACTIVITY STEPS POTENTIAL HAZARDS HAZARDS CONTROL with trial pit method no mechanical excavation upto 3 meters
all the side.use only manual excavation.

RESPONSIBLE

3.0 Removal of excavated


materials through crane

3.1 Failure of crane, collapse and overturn

3.1.1 Crane and lifting tackles shall be certified by QP approved


3.1.2 3.1.3 third party and shall be colour coded accordingly Operators and rigger shall be certified with applicable licence by QP approved third party Crane shall be erected in a firm and level ground with outriggers fully extended with base pad Area must be barricaded with sign board of lifting is in progress to prevent any unauthorized entry Load suspended shall not swing over personnel and dont hold suspended load during break Tag line shall be used to hold the suspended load. Banksman shall be provided

Dodsal Supervisor

3.2 Fall of material and injury

3.2.1 3.2.2 3.2.3 3.2.4

4.0 Blinding / Masonary work 4.1 Fall of personel, material and injury and collapse

4.2 Equipments failure, collapse

4.1.1 Material handling and storage shall be done as per procedure. 4.1.2 Experienced and competent person shall be deployed 4.1.3 Blinding shall not be done when adverse weather condition prevails 4.1.4 House keeping to be maintained always 4.2.1 Operators of mixers, pumps and other equipments involved

Dodsal Supervisor

2 of 4

JOB SAFETY ANALYSIS FOR EXCAVATION AND BLINDING AT PH 1 & 3

COMMON COOLING SEAWATER SYSTEM PHASE 2 SEQUENCE OF BASIC ACTIVITY STEPS POTENTIAL HAZARDS and injury 4.2.2 4.2.3 4.3 Enviornmental pollution 5.0 Compaction 5.1 Equipment failure and injury 5.2 Exposure to viberation 5.3 Collapse of form work and displacement of reinforcement 5.4 Noise 6.1 Equipment failure 4.3.1 5.1.1 5.1.2 5.2.1 5.3.1 5.3.2 5.4.1 6.1.1 6.1.2 6.2.1 HAZARDS CONTROL RESPONSIBLE

6.0 Curing of concrete

6.2 Fall of personnel and injury

shall be approved with relevant licence by QP approved third party All access road leading to site shall be safe for traffic movements with necessary signage No infringing activity shall be permitted when blinding work is going on Dumping, cleaning and disposal of blinding waste to be dump at designated area only Equipment shall be maintained and inspected for its suitablity Dodsal Supervisor Experienced workers shall be deployed Workers shall be rotated suitably to avoid prolonged exposure to vibration Inspect the form work prior to compaction Compactor shall not be used along the forms to avoid damage Ear plugs shall be used to avoid exposure to noise Equipment shall be certified by QP approved third party Dodsal Supervisor Operators shall be certified with licence by QP approved third party Clear access shall be maintained at all the time and working

3 of 4

JOB SAFETY ANALYSIS FOR EXCAVATION AND BLINDING AT PH 1 & 3

COMMON COOLING SEAWATER SYSTEM PHASE 2 SEQUENCE OF BASIC ACTIVITY STEPS 7.0 Water proofing POTENTIAL HAZARDS HAZARDS CONTROL platform shall be provided Workers shall be trained for application and safe handling of the material. Water proofing material shall be stored in designated area Signage to be displayed and MSDS to be display, eye wash system also ensured Material will be stored in their designated area Barricading will be provided for open and storage area Minimise the manual handling and used equipment. RESPONSIBLE

7.1 Corrosive material

7.1.1 7.1.2 7.1.3

Dodsal Supervisor

8.0 Material handling and Storage

8.1 Slip,trip, fall and injury

8.1.1 8.1.2 8.1.3

Dodsal Supervisor

Remarks: 1- Prior to start any work it will be made sure that personnel are safety inducted. 2- Prior to start any work Tool Box Talk will be carried out. 3- Personnel will wear all applicable PPE. 4- Adequate first aid facility will be provided. 5- Adequate fire extinguishers shall be provided with every equipments. Prepared By: M P Gupta ( Civil Engineer ) Reviewed By: Solayappan ( HSE Officer )

4 of 4

You might also like