Restructured Accelerated Power Development and Reforms Program Part -B,PVVNL

DAILY PROGRESS REPORT OF DATE-23/7/13


DISCOM Activities Name of Name of Name of Circle Town/Site Circle Engineer visited Name of Designation/ Person Contact No. interacted with Contractor Activities Name of Contractor- VVIPL

Remark

Activity

Name of Town

Status as on today

Cummulative Status of work till Date

Remark

Erection work

Baghpat

No work done ,because 4 no. of manpower so work stopped by me

3 nos of 250 kva T/F insttalation with chemical earthing,150 mtr. Reconducting weasel to Dog conductor

Erection work Baghpat Bhanu Partap Singh Khekra

Baraut 1st division

pit digging

31 nos of SP-33 pole, 5 nos of SP55,5 nos of DP for 100 kva T/F

Erection work

Baraut 2nd division

7 nos, of SP-33 pole 11 kv line 300 mtr.,103 nos of pole are erected at site SP-33,23 nos DP for 100 KVA T/F.

Erection work

Khekra

250 Kva T/f are 11kv line 2.5 km,1 nos of 250 insttalation at site,no KVAT/F & 1 nos 100 KVA T/F load charging charging at no load

Restructured Accelerated Power D


Name of Circle Name of Circle Engineer Name of Town/Site visited Name of Person interacted with

DAILY PR

DISCOM Activi

Baghpat

Bhanu Partap Singh

Baghpat&Baraut

DK GARG

Accelerated Power Development and Reforms Program Part


DAILY PROGRESS REPORT OF DATE-24/7/13
DISCOM Activities Designation/Contact No. Remark Activity

Contractor Activ

Erection work

SE/94127-49205

To meet SE sir, discuss the Progressive Month target & july or August month target.Transformer location with serial No. &11kv line new or reconducting both which area progress,A summrised copy send or discuss with Executive engg.

Erection work

Erection work

Erection work

Program Part -B,PVVNL


Contractor Activities Name of Status as on today Town Name of Contractor- VVIPL Cummulative Status of work Remark till Date

3 nos of 250 kva T/F insttalation with chemical 3 span of 11kv line& 2 nos of Baghpat earthing,300 mtr. SP_55 pole are erected Reconducting weasel to Dog conductor. SP-55 pole 2nos.

Baraut 35 nos of SP-33 pole, 5 nos of 1st 4 nos of SP-33 pole are erected SP-55,5 nos of DP for 100 kva division T/F

Baraut 11 kv line 300 mtr.,103 nos of 2nd no work because labour holiday pole SP-33,23 nos DP for 100 division KVA T/F. 11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA 8 Span of Reconducting i.e. 300 Khekra T/F charging at no mtr. load.Reconducting ACSR Dog conductor 300 mtr.

Restructu
Name of Circle Name of Circle Engineer Name of Town/Site visited Name of Person interacted with

Baghpat

Bhanu Partap Singh

Baraut

Restructured Accelerated Power Development and R


DISCOM Activities Name of Person interacted with Designation/Contact No. Remark

DAILY PROGRESS REPORT OF DA

lopment and Reforms Program Part -B,PVVNL


Contractor Activities Activity Name of Town

ESS REPORT OF DATE-25/7/13

Erection work

Baghpat

Erection work

Baraut 1st division

Erection work

Baraut 2nd division

Erection work

Khekra

art -B,PVVNL
Name of Contractor- VVIPL Status as on today Cummulative Status of work till Date

ities

3 span of 11kv line

3 nos of 250 kva T/F insttalation with chemical earthing, mtr. Reconducting weasel to Dog conductor. SP-55 pole 2nos.

4 nos of SP-33 pole are erected

39 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F

5 nos. of SP-55 pole are erected

11 kv line 300 mtr.,108 nos of pole SP33,23 nos DP for 100 KVA T/F. 11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 800 mtr.

10 Span of Reconducting i.e. 500 mtr.

of Contractor- VVIPL Remark

Restructured Acc
Name of Circle Name of Name of Circle Town/Sit Engineer e visited DISCOM Activities Designat Name of Person ion/Cont Remark interacted with act No.

Baghpat

Bhanu Partap Singh

Khekra

ructured Accelerated Power Development and Reforms Prog


DAILY PROGRESS REPORT OF DATE-26/7/13
Contractor Activities Activity Name of Town

Erection work

Baghpat

Erection work

Baraut 1st division

Erection work

Baraut 2nd division

Erection work

Khekra

t and Reforms Program Part -B,PVVNL


Status as on today

RT OF DATE-26/7/13

ties

7 span of 11kv line i.e. 385 mtr.

5 nos of SP-33 pole are erected

Pit digging

4 Span of Reconducting i.e. 240 mtr.

m Part -B,PVVNL
Name of Contractor- VVIPL Cummulative Status of work till Date

3 nos of 250 kva T/F insttalation with chemical earthing,835 mtr. Reconducting weasel to Dog conductor. SP-55 pole 2nos.

43 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F

11 kv line 300 mtr.,108 nos of pole SP-33,23 nos DP for 100 KVA T/F.

11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1040mtr.

Contractor- VVIPL Remark

Restructured Accelerated
Name of Circle Name of Circle Engineer Name of Town/Site visited Name of Person interacted with

DISCOM

Baghpat

Bhanu Partap Singh

Baraut

red Accelerated Power Development and Reforms Program P


DAILY PROGRESS REPORT OF DATE-27/7/13
DISCOM Activities Designation/Contact No. Remark Activity Contractor Activities

Erection work

Erection work

Erection work

Erection work

orms Program Part -B,PVVNL


Contractor Activities Name of Town Status as on today Name of Contractor- VVIPL Cummulative Status of work till Date 3 nos of 250 kva T/F insttalation with chemical earthing,835 mtr. Reconducting weasel to Dog conductor. SP-55 pole 2nos. 43 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F

-27/7/13

Baghpat

Pit digging for Replacement pole

Baraut 1st division

no work because no laboure

Baraut 2nd division

4 nos . of SP-33 pole are erected

11 kv line 300 mtr.,112 nos of pole SP33,23 nos DP for 100 KVA T/F.

Khekra

11kv line 2.5 km,1 nos of 250 7 Span of Reconducting i.e. 400 KVAT/F & 1 nos 100 KVA T/F mtr. charging at no load.Reconducting ACSR Dog conductor 1440mtr.

Contractor- VVIPL Remark

Restructured Acce
Name of Circle Name of Name of Circle Town/Sit Engineer e visited Name of Person interacted with DISCOM Activities Designation/Cont act No.

Baghpat

Bhanu Partap Singh

Baghpat

Rvinder Singh

JE/9412749600

estructured Accelerated Power Development and Reforms P


DAILY PROGRESS REPORT OF DATE-28/7/13
DISCOM Activities Remark Activity Contractor Activities

Erection work

to meet sir at the site,site check pole are erected & some other location where pole are replaced

Erection work

Erection work

Erection work

ment and Reforms Program Part -B,PVVNL


Contractor Activities Name of Town Status as on today

PORT OF DATE-28/7/13

Baghpat

6 nos. of SP-55 pole arected

Baraut 1st division

no work because no laboure

Baraut 2nd division

no work because no laboure

Khekra

no work because laboure Sunday holiday

t -B,PVVNL
Name of Contractor- VVIPL Cummulative Status of work till Date Remark

3 nos of 250 kva T/F insttalation with chemical earthing,835 mtr. Reconducting weasel to Dog conductor. SP-55 pole 8nos.

43 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F

11 kv line 300 mtr.,108 nos of pole SP-33,23 nos DP for 100 KVA T/F.

11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1040mtr.

R
Name of Circle Name of Circle Engineer Name of Town/Site visited Name of Person interacted

Baghpat

Bhanu Partap Singh

Baghpat Khekra

Restructured Accelerated Power Developme


DISCOM Activities Name of Person interacted with Designation/Contact No.

DAILY PROGRESS REPO

lerated Power Development and Reforms Program Part -B,P


DAILY PROGRESS REPORT OF DATE-30/7/13
Contractor Activities Remark Activity

ies

Erection work

Erection work

Erection work

Erection work

rogram Part -B,PVVNL


Contractor Activities Name of Town Status as on today Cummulative Status of work till Date

Name of Contractor- VV

Baghpat

5 nos of span are conducting i.e. 250 mtr.

3 nos of 250 kva T/F insttalation with chemical earthing,1085 mtr. Reconducting weasel to Dog conductor. SP-55 pole 14nos.

Baraut 1st division

6 nos SP-33 of pole are erected

49 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F

Baraut 2nd division

3 SP-33 pole are erected at 11 kv line 300 mtr.,114 nos of pole SPsite 33,23 nos DP for 100 KVA T/F.

Khekra

11kv line 2.5 km,1 nos of 250 KVAT/F 6 span ACSR Dog atre string & 1 nos 100 KVA T/F charging at no i.e. 300 mtr. 1 nos load.Reconducting ACSR Dog of SP_55 are erected conductor 1540mtr.

Name of Contractor- VVIPL Remark

Restructured
Name of Circle Name of Name of Circle Town/Sit Engineer e visited Name of Person interacted with DISCOM Activities Designation/Contact No.

Baghpat

Bhanu Partap Singh

Baghpat Khekra

Pooshp Dev G

JE/9412749592

Restructured Accelerated Power Development and Refor


Contractor Activities Remark Activity Name of Town

DAILY PROGRESS REPORT OF DATE-31/

DISCOM Activities

Erection work

Baghpat

Erection work to meet sir, discuss the AB cable laying process & populated , thief area are most pariority Erection work

Baraut 1st division

Baraut 2nd division

Erection work

Khekra

t and Reforms Program Part -B,PVVNL


Name of Contractor- VVIPL Status as on today Cummulative Status of work till Date

T OF DATE-31/7/13

r Activities

5 nos of span are conducting i.e. 280 mtr.

3 nos of 250 kva T/F insttalation with chemical earthing,1365 mtr. Reconducting weasel to Dog conductor. SP-55 pole 14nos.

2 nos SP-33 of pole are erected

51 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F

5 SP-33 pole are erected at site

11 kv line 300 mtr.,119 nos of pole SP-33,23 nos DP for 100 KVA T/F.

no work because shutdown problem,Roushting time change

11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr.

ame of Contractor- VVIPL Remark

Name of Circle

Name of Circle Engineer

Name of Town/Site visited

D Name of Person interacted

Baghpat

Bhanu Partap Singh

Baghpat

Ravinder kr.

Restructured Accelerated Power Developm


DISCOM Activities Designation/Contact No. Remark Activity

DAILY PROGRESS RE

JE/9412749600

to meet sir, check the site where pole are erected at site,some other location mid span pole are required

d Power Development and Reforms Program Part -B,PVVNL


DAILY PROGRESS REPORT OF DATE-1/8/13
Activity Contractor Activities Name of Town

Erection work

Baghpat

Erection work

Baraut 1st division

Erection work

Baraut 2nd division

Erection work

Khekra

ram Part -B,PVVNL


Status as on today

Name of Contractor- VVI Cummulative Status of work till Date 3 nos of 250 kva T/F insttalation with chemical earthing,1365 mtr. Reconducting weasel to Dog conductor. SP-55 pole 16nos.

2 SP-55 pole are erected & 1 SP-33 pole are erected

2 nos SP-33 of pole are erected ,6 span of Reconducting of 11 KV line i.e. 350 mtr.

53 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F, Reconducting of 11 kv line 350 mtr.

3 SP-33 pole are erected at site

11 kv line 300 mtr.,122 nos of pole SP-33,23 nos DP for 100 KVA T/F.

no work because labour holiday

11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr.

me of Contractor- VVIPL Remark

Restr
Name of Circle Name of Circle Engineer Name of Town/Site visited Name of Person

DISCO

Baghpat

Bhanu Partap Singh

Baghpat

Restructured Accelerated Power Development and R


DISCOM Activities Designation/Contact No. Remark Activity

DAILY PROGRESS REPORT OF DA

wer Development and Reforms Program Part -B,PVVNL


Activity Contractor Activities Name of Town

ILY PROGRESS REPORT OF DATE-2/8/13

Erection work

Baghpat

Erection work

Baraut 1st division

Erection work

Baraut 2nd division

Erection work

Khekra

ogram Part -B,PVVNL


Status as on today Name of Contractor- VVIPL Cummulative Status of work till Date

Reconducting of 11 KV line work 3 nos of 250 kva T/F insttalation with on progress. chemical earthing,1365 mtr. Reconducting Pit Digging for SP-55 pole weasel to Dog conductor. SP-55 pole 16nos.

Pit digging for LT line

53 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F, Reconducting of 11 kv line 350 mtr.

11 kv line 300 mtr.,122 nos of pole SP-33,23 AB cable laying 12 Span i.e. 440 mtr. nos DP for 100 KVA T/F. AB cable laying 1140 mtr. 11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr.

no work because labour holiday

Name of Contractor- VVIPL Remark

Restructured Accelerated Power Development and


DISCOM Activities Name of Circle Name of Name of Circle Town/Sit Engineer e visited Name of Person interacted with Designat ion/Cont Remark act No.

DAILY PROGRESS REPORT OF DATE-

Con

Activity

Baghpat

Bhanu Partap Singh

Baghpat

Baghpat

Bhanu Partap Singh

Baghpat

evelopment and Reforms Program Part Contractor Activities Name of Town Name of Cummul ative Status of Remark work till Date 3 nos of 250 kva T/F insttalati on with chemical earthing, 1365 mtr. Recondu cting weasel to Dog conducto r. SP-55 pole 16nos. 53 nos of SP-33 pole, 5 nos of SP55,5 nos of DP for 100 kva T/F, Recondu cting of 11 kv line 350 mtr.

S REPORT OF DATE-3/8/13

Activity

Status as on today

Erection Baghpat work

Reconducting of 11 KV line work on progress. 2 nos. SP-55 pole are erected at site

Erection work

Baraut 1st division

Reconducting of 11 KV line work on progress. 400 mtr. ACSR conductor

Erection work

Baraut 2nd division

AB cable laying 6 Span i.e. 230 mtr.

11 kv line 300 mtr.,122 nos of pole SP33,23 nos DP for 100 KVA T/F. AB cable laying 1370 mtr. 11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Rec onductin g ACSR Dog conducto r 1540mtr.

Erection work

Khekra

no work because labour holiday

Restructured Accelerated Power Development a


DAILY PROGRESS REPORT
Name of Circle Name of Name of Circle Town/Sit Engineer e visited DISCOM Activities Designat Name of Person ion/Cont Remark interacted with act No. Activity

Baghpat

Bhanu Partap Singh

Baghpat

Development and Reforms Program Part -B,PVVNL


Contractor Activities Activity Name of Town Status as on today

ROGRESS REPORT OF DATE-4/8/13

Erection Baghpat work

Reconducting of 11 KV line work on progress. 7 nos span of reconducting i.e. 370 mtr.

Erection work

Baraut 1st division

no work labour holiday

Erection work

Baraut 2nd division

AB cable work on progress pit digging for SP-33 pole

Erection work

Khekra

no work because labour holiday

Part -B,PVVNL
Name of Contractor- VVIPL Cummulative Status of Remark work till Date 3 nos of 250 kva T/F insttalation with chemical earthing,1735 mtr. Reconducting weasel to Dog conductor. SP-55 pole 16nos. 53 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F, Reconducting of 11 kv line 350 mtr. 11 kv line 300 mtr.,122 nos of pole SP-33,23 nos DP for 100 KVA T/F. AB cable laying 1140 mtr. 11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr.

Restructured Accelerated Power D


Name of Circle Name of Circle Engineer Name of Town/Site visited DISCOM Activities Designat Name of Person ion/Cont Remark interacted with act No. Activity

DAILY PR

Baghpat

Bhanu Partap Singh

BARAUT

ated Power Development and Reforms Program Part -B,PVV


DAILY PROGRESS REPORT OF DATE-5/8/13
Contractor Activities Activity Name of Town Status as on today

Erection Baghpat work

Reconducting of 11 KV line work on progress. No work because labour holiday

Erection work

Baraut LT line work on progress 1st 12 nos. of SP-33 pole are erected at site division

Erection work

Baraut 2nd division

pit digging

Erection work

Khekra

no work because labour holiday

d Reforms Program Part -B,PVVNL


Name of Contractor- VVIPL Cummulative Status of work till Date

DATE-5/8/13

3 nos of 250 kva T/F insttalation with chemical earthing,1735 mtr. Reconducting weasel to Dog conductor. SP-55 pole 16nos.

65 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F, Reconducting of 11 kv line 350 mtr.

11 kv line 300 mtr.,122 nos of pole SP-33,23 nos DP for 100 KVA T/F. AB cable laying 1140 mtr.

11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr.

B,PVVNL
Remark

me of Contractor- VVIPL

Restructured Accelerated Po
Name of Circle Name of Name of Circle Town/Sit Engineer e visited DISCOM Activities Designat Name of Person ion/Cont Remark interacted with act No. Activity

Baghpat

Bhanu Partap Singh

BARAU T

Accelerated Power Development and Reforms Program Par


DAILY PROGRESS REPORT OF DATE-6/8/13
Contractor Activities Activity Name of Town Status as on today

Erection Baghpat work

Reconducting of 11 KV line work on progress. No work because labour holiday

Erection work

Baraut 1st division Baraut 2nd division

LT line work on progress No work because rain day

Erection work

No work because labour holiday

Erection work

Khekra

no work because labour holiday

Reforms Program Part -B,PVVNL


Name of Contractor- VVIPL Cummulative Status of work till Date

DATE-6/8/13

3 nos of 250 kva T/F insttalation with chemical earthing,1735 mtr. Reconducting weasel to Dog conductor. SP-55 pole 16nos.

65 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F, Reconducting of 11 kv line 350 mtr.

11 kv line 300 mtr.,122 nos of pole SP-33,23 nos DP for 100 KVA T/F. AB cable laying 1140 mtr. 11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr.

PVVNL
Remark

me of Contractor- VVIPL

Restructured Accelerated Power Developmen


DISCOM Activities Name of Circle Name of Circle Engineer Name of Town/Site visited Name of Person interacted with

DAILY PROGRESS REPO

Baghpat

Bhanu Partap Singh

BARAUT

wer Development and Reforms Program Part -B,PVVNL


DISCOM Activities Designation/C ontact No. Remark Activity Contractor Activities Name of Town Status as on today Reconducting of 11 KV line work on progress. No work because labour holiday New of 11 KV line work on progress. 6 Span of conductor No work because labour holiday

LY PROGRESS REPORT OF DATE-7/8/13

Erection work

Baghpat

Erection work

Baraut 1st division

Erection work

Baraut 2nd division

Erection work

Khekra

Abcable are stringing i.e. 500 mtr.

-B,PVVNL
Name of Contractor- VVIPL Cummulative Status of work till Date 3 nos of 250 kva T/F insttalation with chemical earthing,1735 mtr. Reconducting weasel to Dog 65 nos of SP33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F, 11 kv line 300 mtr.,122 nos of pole SP-33,23 nos DP for 100 KVA T/F. AB cable 11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconduc Remark

Restructured Accelerated Po
Name of Circle Name of Circle Engineer Name of Town/Site visited DISCOM Activities Designat Name of Person ion/Cont Remark interacted with act No. Activity

DA

Baghpat

Bhanu Partap Singh

celerated Power Development and Reforms Program Part -B


DAILY PROGRESS REPORT OF DATE-8/8/13
Contractor Activities Activity Name of Town Status as on today

Erection Baghpat work

Reconducting of 11 KV line work on progress. No work because labour holiday

Erection work

Baraut 1st division

New of 11 KV line work on progress. No work due to raining day.

Erection work

Baraut 2nd division

No work because labour holiday

Erection work

Khekra

No work due to raining day

orms Program Part -B,PVVNL


Name of Contractor- VVIPL Cummulative Status of work till Date

-8/8/13

3 nos of 250 kva T/F insttalation with chemical earthing,1735 mtr. Reconducting weasel to Dog conductor. SP-55 pole 16nos.

65 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F, Reconducting of 11 kv line 350 mtr.

11 kv line 300 mtr.,122 nos of pole SP-33,23 nos DP for 100 KVA T/F. AB cable laying 1140 mtr.

11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr.

VVNL
Remark

me of Contractor- VVIPL

Restructured Accelerated Pow


Name of Circle Name of Name of Circle Town/Sit Engineer e visited DISCOM Activities Designat Name of Person ion/Cont Remark interacted with act No. Activity

DAIL

Baghpat

Bhanu Partap Singh

ccelerated Power Development and Reforms Program Part DAILY PROGRESS REPORT OF DATE-9/8/13
Contractor Activities Activity Name of Town Status as on today

Erection Baghpat work

Reconducting of 11 KV line work on progress. No work because labour holiday Eid festival

Erection work

Baraut 1st division

No work because Eid festival

Erection work

Baraut 2nd division

No work because Eid festival

Erection work

Khekra

No work because Eid festival

eforms Program Part -B,PVVNL


Name of Contractor- VVIPL Cummulative Status of work till Date

TE-9/8/13

3 nos of 250 kva T/F insttalation with chemical earthing,1735 mtr. Reconducting weasel to Dog conductor. SP-55 pole 16nos.

65 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F, Reconducting of 11 kv line 350 mtr.

11 kv line 300 mtr.,122 nos of pole SP-33,23 nos DP for 100 KVA T/F. AB cable laying 1140 mtr.

11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr.

PVVNL
Remark

me of Contractor- VVIPL

Restructured Accelerated P
Name of Circle Name of Circle Engineer Name of Town/Site visited DISCOM Activities Designat Name of Person ion/Cont Remark interacted with act No.

Baghpat

Bhanu Partap Singh

BARAUT

Accelerated Power Development and Reforms Program Part


DAILY PROGRESS REPORT OF DATE-10/8/13
Contractor Activities Activity Name of Town Status as on today

Erection Baghpat work

Reconducting of 11 KV line work on progress. No work because labour holiday

Erection work

Baraut 1st division

LT line work on progress. 10 span of AB cable 95 sq mm i.e. 400 mtr.

Erection work

Baraut 2nd division

No work because labour holiday

Erection work

Khekra

Abcable are stringing i.e. 350 mtr.

ms Program Part -B,PVVNL


Name of Contractor- VVIPL Cummulative Status of work till Date

8/13

3 nos of 250 kva T/F insttalation with chemical earthing,1735 mtr. Reconducting weasel to Dog conductor. SP-55 pole 16nos.

65 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F, Reconducting of 11 kv line 350 mtr. 95 sq mm AB cable 400 mtr. 11 kv line 300 mtr.,122 nos of pole SP-33,23 nos DP for 100 KVA T/F. AB cable laying 1140 mtr.

11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr. 95 sq mm AB cable stringing 850 mtr.

VNL
Remark

me of Contractor- VVIPL

Restructured Accelerated Po
Name of Circle Name of Name of Circle Town/Site visited Engineer DISCOM Activities Designat Name of Person ion/Cont Remark interacted with act No. Activity

DA

Baghpat

Bhanu Partap Singh

elerated Power Development and Reforms Program Part -B,


DAILY PROGRESS REPORT OF DATE-11/8/13
Contractor Activities Activity Name of Town Status as on today

Erection Baghpat work

Reconducting of 11 KV line work on progress. No work because labour holiday

Erection work

Baraut 1st division

New of 11 KV line work on progress. Material shifted to main store Baghpat

Erection work

Baraut 2nd division

No work because labour holiday

Erection work

Khekra

4 nos of SP-33 9 mtr. Pole are erected at site.

orms Program Part -B,PVVNL


Name of Contractor- VVIPL Cummulative Status of work till Date

11/8/13

3 nos of 250 kva T/F insttalation with chemical earthing,1735 mtr. Reconducting weasel to Dog conductor. SP-55 pole 16nos.

65 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F, Reconducting of 11 kv line 350 mtr.

11 kv line 300 mtr.,122 nos of pole SP-33,23 nos DP for 100 KVA T/F. AB cable laying 1140 mtr.

11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr. SP=33 pole:-14

VNL
Remark

me of Contractor- VVIPL

Name of Circle

Name of Circle Engineer

Name of Town/Site visited

Name of Person interacted with

Baghpat

Bhanu Partap Singh

Khekra Baghpat

Mr. DK Garg

Restructured Accelerated Power


Name of Person interacted with DISCOM Activities Designation/Contact No.

DAILY PR

Mr. DK Garg

SE/9412749205

tructured Accelerated Power Development and Reforms Pro


DAILY PROGRESS REPORT OF DATE-12/8/13
Remark Activity

OM Activities

Contract

Erection work

Erection work to meet sir,Discuss the status of R-APDRP work. & Photo copy of invoice Bill but the accountant Mr. Rajive are goes to meerut. Erection work

Erection work

nd Reforms Program Part -B,PVVNL


Contractor Activities Name of Town Status as on today

F DATE-12/8/13

Baghpat

No work because labour holiday

Baraut 1st division

8 nos of SP-33 pole are erected at site

Baraut 2nd division

No work because labour holiday

Khekra

500 mtr. AB cable are stringing

Name of Contractor- VVIPL Cummulative Status of work till Date

3 nos of 250 kva T/F insttalation with chemical earthing,1735 mtr. Reconducting weasel to Dog conductor. SP-55 pole 16nos.

73 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F, Reconducting of 11 kv line 350 mtr.

11 kv line 300 mtr.,122 nos of pole SP-33,23 nos DP for 100 KVA T/F. AB cable laying 3 km

11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr. SP=33 pole:-14 95 sq mmAB cable :- 2km

me of Contractor- VVIPL Remark

Name of Circle

Name of Name of Circle Town/Sit Engineer e visited

DISCOM Acti Name of Person interacted with Designation/Contact No.

Baghpat

Bhanu Partap Singh

Baraut Baghpat

Restructured Accelerated Power Dev


DISCOM Activities Remark Activity

DAILY PROGR

go SE office & send the copy of invoice bill.

Power Development and Reforms Program Part -B,PVVNL


DAILY PROGRESS REPORT OF DATE-13/8/13
Contractor Activities Activity Name of Town

Erection work

Baghpat

Erection work

Baraut 1st division

Erection work

Baraut 2nd division

Erection work

Khekra

ms Program Part -B,PVVNL


Status as on today

8/13

or Activities

8 span of Reconducting i.e. 470mtr.

6 nos of SP-33 pole are erected at site. AB cable laying 500 mtr.

No work because labour holiday

500 mtr. AB cable are stringing

NL
Name of Contractor- VVIPL Cummulative Status of work till Date

3 nos of 250 kva T/F insttalation with chemical earthing,2205 mtr. Reconducting weasel to Dog conductor. SP-55 pole 16nos.

79 nos of SP-33 pole, 5 nos of SP-55,5 nos of DP for 100 kva T/F, Reconducting of 11 kv line 350 mtr. 95 sq mm AB cable :- 2 km

11 kv line 300 mtr.,122 nos of pole SP-33,23 nos DP for 100 KVA T/F. AB cable laying 3 km

11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr. SP=33 pole:-14 95 sq mmAB cable :- 2.5 km

me of Contractor- VVIPL Remark

Restructured Acceler
Name of Circle Name of Name of Circle Town/Sit Engineer e visited DISCOM Activities Name of Person interacted with

Baghpat

Bhanu Partap Singh

Baraut Baghpat

Mr. Arya Naresh

Restructured Accelerated Power Development and Refor


DISCOM Activities Designation/Contact No. Remark Activity

DAILY PROGRESS REPORT OF DATE-14/

Contr

JE/9412749679

to meet sir ,discuss the progress of work .

opment and Reforms Program Part -B,PVVNL


Contractor Activities Activity Name of Town Status as on today

S REPORT OF DATE-14/8/13

Erection work

Baghpat

No work because labour holiday

Erection work

Baraut 1st division

4 nos of SP-33 pole are erected at site. AB cable laying 500 mtr.

Erection work

Baraut 2nd division

No work because labour holiday

Erection work

Khekra

500 mtr. AB cable are stringing

t -B,PVVNL
Name of Contractor- VVIPL Cummulative Status of work till Remark Date

3 nos of 250 kva T/F insttalation with chemical earthing,2205 mtr. Reconducting weasel to Dog conductor. SP-55 pole 16nos.

83 nos of SP-33 pole, 5 nos of SP55,5 nos of DP for 100 kva T/F, Reconducting of 11 kv line 350 mtr. 95 sq mm AB cable :- 2.5km

11 kv line 300 mtr.,122 nos of pole SP33,23 nos DP for 100 KVA T/F. AB cable laying 3 km

11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr. SP=33 pole:-14 95 sq mmAB cable :- 3 km

Restructured Accelerated Power De


Name of Circle Name of Name of Circle Town/Sit Engineer e visited DISCOM Activities Designat Name of Person ion/Cont Remark interacted with act No. Activity

DAILY PROG

Baghpat

Bhanu Partap Singh

rated Power Development and Reforms Program Part -B,PV


DAILY PROGRESS REPORT OF DATE-15/8/13
Contractor Activities Activity Name of Town Status as on today

Erection work

Baghpat

No work because labour holiday

Erection work

Baraut 1st division

No work because labour holiday

Erection work

Baraut 2nd division

No work because labour holiday

Erection work

Khekra

Independent holiday

ogram Part -B,PVVNL


Name of Contractor- VVIPL Cummulative Status of work till Date 3 nos of 250 kva T/F insttalation with chemical earthing,2205 mtr. Reconducting weasel to Dog conductor. SP-55 pole 16nos. 79 nos of SP-33 pole, 5 nos of SP55,5 nos of DP for 100 kva T/F, Reconducting of 11 kv line 350 mtr. 95 sq mm AB cable :- 2 km 11 kv line 300 mtr.,122 nos of pole SP-33,23 nos DP for 100 KVA T/F. AB cable laying 3 km 11kv line 2.5 km,1 nos of 250 KVAT/F & 1 nos 100 KVA T/F charging at no load.Reconducting ACSR Dog conductor 1540mtr. SP=33 pole:-14 95 sq mmAB cable :- 2.5 km Remark