2.1 Failure of jack up 2.1.1 The jack up rig and associated equipments / pontoon drilling rig/ pontoon and must be certified and by QP approved third party equipments 2.1.2 Operator must have a valid license respect to the vessel and must be certified by QP approved third party 2.2 Fall of personnel and material in to sea 2.2.1 Experienced and competent workers to be deployed and they shall wear life jacket 2.2.2 Equipments, tools, casings, drill rods and materials to be secured properly to prevent rolling and falling 2.2.3 Vessel shall be equipped with rescue buoys and rope
Page : 2 of 5
Page : 3 of 5
Page : 4 of 5
Notes: 1- Prior to start any work it to be made sure that personnel are safety inducted 2- Prior to start any work Tool Box Talk to be carried out 3- Personnel shall wear all applicable PPE 4- Adequate First Aid facility to be provided Prepared By : M.P Gupta ( Civil Engineer ) Reviewed By: Solayappan ( HSE Officer )
Page : 5 of 5