SEQUANCE OF POTENTIAL HAZARD BASIC HAZARD 1.0 Utilization of survey vessel 1.1 Failure of vessel and equipment HAZARD CONTROL 1.1.1 The vessel must be certified and approved by QP approved third party 1.1.2 Operator of the vessel must have valid licence and must be certified by QP approved third party 1.1.3 Radio communication facility must be available between vessel and relevant control room at shore and one dedicated supervisor shall be monitored the activity at shore 1.1.4 Rescue team with vessel to be available to attend any undue event 1.2 Fall of material and 1.2.1 The crew members must be trained and should wear personnel in to sea life jacket 1.2.2 Paramedic to be available in the vessel 1.2.3 Equipments, tools, and materials to be secured properly to prevent falling 1.2.4 All personnel should be inducted with details of activity and sea survival training 1.2.5 Vessel shall be equipped with rescue buoys and rope RESPOSIBILITY Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor
Page : 1 of 5

JOBSAFETY ANALYSIS FOR GEOTECHENICAL INVESTIGATION


COMMON COOLING SEAWATER SYSTEM PHASE 2
SEQUANCE OF POTENTIAL HAZARD BASIC HAZARD HAZARD CONTROL 1.2.6 Good house keeping to be maintained on deck and platform all time and spillage of fuel,grease and oil to be cleaned properly and disposed 1.3 Local Marine traffic 2.0 Drilling of boreholes 1.3.1 Communication with RLIC port control room to be established prior to start of survey RESPOSIBILITY Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor

2.1 Failure of jack up 2.1.1 The jack up rig and associated equipments / pontoon drilling rig/ pontoon and must be certified and by QP approved third party equipments 2.1.2 Operator must have a valid license respect to the vessel and must be certified by QP approved third party 2.2 Fall of personnel and material in to sea 2.2.1 Experienced and competent workers to be deployed and they shall wear life jacket 2.2.2 Equipments, tools, casings, drill rods and materials to be secured properly to prevent rolling and falling 2.2.3 Vessel shall be equipped with rescue buoys and rope

Page : 2 of 5

JOBSAFETY ANALYSIS FOR GEOTECHENICAL INVESTIGATION


COMMON COOLING SEAWATER SYSTEM PHASE 2
SEQUANCE OF POTENTIAL HAZARD BASIC HAZARD HAZARD CONTROL 2.2.4 Positioning of Rig/ pontoon to be done as per the procedure with supervision 2.2.5 Erection of Rig/ pontoon shall not be done when rough sea and strong wind prevails 2.2.6 All crew members to be well conversant and adhered to Emergency Procedure which is applicable 2.3 Faliure of high pressure pump and flushing system 2.3.1 Equipments, associated tools and fittings must be checked prior to its use 2.3.2 Only trained and experienced workers shall be deployed for the task 2.3.3 The materials and fittings must be approved prior to its use 2.3.4 Defective equipments to be discarded from the service RESPOSIBILITY Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor

Page : 3 of 5

JOBSAFETY ANALYSIS FOR GEOTECHENICAL INVESTIGATION


COMMON COOLING SEAWATER SYSTEM PHASE 2
SEQUANCE OF POTENTIAL HAZARD BASIC HAZARD 3.0 Lifting of Tools and Equipments 3.1 Fall of material, collapse and injury HAZARD CONTROL 3.1.1 Crane and lifting tackles must be certified by QP approved third party 3.1.2 Operator must have a valid license and to be certified by QP approved third party 3.1.2 Rigger and signal man to be trained. They should keep a good communication with operator 3.1.3 Tag lines to be used for holding suspended load 3.1.4 Crew members shall kept minimum as required and no load should swing over personnel. 4.0 General safety 4.1 Personnel injury and health hazard 4.1.1 Each member of the crew member to be phisically fit and in good health 4.1.2 Safe entrance and exit platform with ladder to be provided for sailors. RESPOSIBILITY Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor

Page : 4 of 5

JOBSAFETY ANALYSIS FOR GEOTECHENICAL INVESTIGATION


COMMON COOLING SEAWATER SYSTEM PHASE 2
SEQUANCE OF POTENTIAL HAZARD BASIC HAZARD 4.2 Fire HAZARD CONTROL 4.2.1 Flammable materials shall not be stored in the vessel if required it shall stored in a purpose designed container 4.2.2 Appropriate fire extinguishers shall be provided in the vessel 5.0 Weather 5.1 High tide 5.2 Exposure to extreme weather 5.3 Sun Burn 5.4 Heat stress and dehydration 5.1.1 Tide table shall be evaluated before sailing 5.2.1 Weather forecast must be followed 5.3.1 Adequate shelter to be provided for workers to take rest 5.4.1 Sufficient quantity of cool drinking water to be made available RESPOSIBILITY Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor Dodsal Site Supervisor

Notes: 1- Prior to start any work it to be made sure that personnel are safety inducted 2- Prior to start any work Tool Box Talk to be carried out 3- Personnel shall wear all applicable PPE 4- Adequate First Aid facility to be provided Prepared By : M.P Gupta ( Civil Engineer ) Reviewed By: Solayappan ( HSE Officer )