You are on page 1of 1

MODIFY EXISTING GRAPHIC ANNUNICATOR! TO REFLECT CONDITIONS AT THE COMPLETION!

OF CONSTRUCTION

NEW LOCATION OF FLOOR MOUNTED ! 20 TON LIEBERT DS UNIT! EXTEND EXISTING REFRIGERENT, ! COLD WATER AND CONDENSATE ! PIPING AS REQUIRED! PROVIDE TOP MOUNTED! RETURN AIR SCOOP

NEW 2" SANITARY LINE TO MAIN, ! FOR CONTINUATION AND EXACT LOCATION ! SEE CIVIL ENGINEER SITE PLAN, ! MAINTAIN A MINIMUM OF 3'-6" COVER.

DEMOLITION NOTES
1.! EQUIPMENT INDICATED IN A DASHED LINE IS ! EXISTING TO BE REMOVED.! !! 2.! EQUIPMENT INDICATED IN A SOLID LINE IS ! EXISTING TO REMAIN OR BE RELOCATED.! !! 3.! WORK SHALL BE COMPLETED IN ACCORDANCE ! WITH THE PHASING SCHEDULE DEVELOPED BY ! THE GENERAL CONTRACTOR/CONSTRUCTION ! MANAGER.! !! 4.! WORK OUTSIDE THE DESIGNATED PHASE ZONES ! MAY BE REQUIRED TO BE COMPLETED DURING ! EARLY PHASES OF THE PROJECT. THE ! ELECTRICAL CONTRACTOR IS RESPONSIBLE FOR ! IDENTIFYING THAT WORK, COORDINATING WITH ! THE OWNER AND GENERAL ! CONTRACTOR/CONSTRUCTION MANAGER AND ! PROVIDING THAT WORK IN A TIMELY MANNER.! !! 5.! PRIOR TO START OF DEMOLITION, COORDINATE ! EXACT SCOPE AND EXTENT OF WORK WITH ! CONSTRUCTION MANAGER AND OWNERS ! REPRESENTITIVE.! !! 6.! WHERE EXISTING FACILITIES ARE BEING ALTERED, ! DISCONNECT AND REMOVE OR RELOCATE ALL ! EXISTING ELECTRICAL WORK THAT INTERFERES ! WITH OR IS NECESSARY BECAUSE OF NEW ! CONSTRUCTION AS SPECIFIED, SHOWN OR ! REQUIRED.! !! 7.! WHERE SPECIFIED OR REQUIRED, EXTEND ! EXISTING SYSTEMS OR TIE INTO SAME TO ! PROVIDE A COMPLETE COORDINATED ! MECHANICAL AND FIRE PROTECTIONSYSTEM TO ! SATISFACTION OF OWNER AND ARCHITECT.! !! 8.! PROVIDE ALL WORK NECESSARY TO PERMIT ! OPERATION OF ALL EXISTING SYSTEMS DURING ! THE CONSTRUCTION PERIOD. ! !! 9.! EXISTING EQUIPMENT OR SYSTEMS DAMAGED DURING CONSTRUCTION SHALL BE REPAIRED AND/OR REPLACED BY THE CONTRACTOR TO THE SATISFACTION OF THE ARCHITECT AND OWNER.!

(EX) FM200 EMERG. SHUTDOWN SW.

REMOVE OLD BUILDING FM200! BYPASS KEY SWITCHES. SINGLE! SWITCH TO REMAIN EXISTING FM 200 TANKS! TO BE REMOVED MODIFY OR REPLACE EXISTING ! FM200 CONTROL PANEL AS REQUIRED! DUE TO RENOVATION! MODIFY OR PREPLACE FM200 SYSTEM PIPING, ! CEILINGS HEADS, RAISED FLOOR HEADS, DETECTORS,! ETC AS REQUIRED TO PROVIDE A SINGLE BUILDING! PROTECTION SYSTEM EXISTING GRADE MOUNTED ! PACKAGED UNITS! TO BE REMOVED! REMOVE EXISTING DUCTWORK ! THERMSTATS AND CEILING ! DIFFUSERS AND GRILLES

S 1
CONNECT TO EXISTING! COLD WATER MAIN 1" BELOW RAISED FLOOR SK1 3/4"

DW 1

3"VENT UP ! THRU ROOF


A 4 300

HCU 1
ON ROOF
A 4 300

(EX) 1.5 TON ! SPLIT SYSTEM

WHERE EXISTING FIRE PROTECTION SYSTEM! PIPING IS TO REMAIN, RELOCATE AS REQUIRED! BY INSTALLATION OF NEW CABLE TRAY SYSTEMS

UNLESS OTHERWISE NOTED,! DISONNECT AND REMOVE ALL! MECHAINCAL, PLUMBING AND! FIRE PROTECTION SYSTEMS! FROM RENOVATION AREA

(EX) 1.5 TON ! SPLIT SYSTEM 3/4" BELOW! RAISED FLOOR EXISTING FLOOR MOUNTED ! LIEBERT DS UNIT! TO BE REMOVED! REMOVE EXISTING PIPING,! DUCTWORK AND CEILING! GRILLES

NEW EXHAUST ! DUCT UP! THROUGH ROOF, ! DUCT TO BE FULL ! SIZE OF OPENING. ! TERMINATE DUCT ! HIGH IN BATTERY ! ROOM WITH MESH ! SCREEN

DCU 1
ON ROOF

REFRIGERENT LINES TO PENETRATE EXTERIOR! WALL, RUN UP EXTERIOR WALL AND ALONG ROOF! TO OUTDOOR UNIT. MAXIMUM LENGTH AND! MINIMUM SIZE PER MANUFACTURERS REQUIREMENTS! (TYPICAL)

DCU 2
ON ROOF

DAC 1

EXISTING FLOOR MOUNTED ! 20 TON LIEBERT DS! UNIT TO BE RELOCATED! EXTEND EXISTING PIPING! AND CONTROL WIRING AS REQUIRED

EXISTING CONDENSER! TO BE REMOVED

EXISTING FM 200 TANKS! TO BE REMOVED

PROVIDE A HYDROGEN DETECTION AND! MONITORING SYSTEM. SYSTEM SHALL COVER! ENTIRE BATTERY ROOM.! THE MONITOR SHALL ALERT ON TWO LEVELS. ! THE FIRST SHALL SHALL CONTACT COMCAST ! WHEN THE HYDROGEN LEVEL IN THE BATTERY! ROOM REACHES 1 PERCENT. THE SECOND LEVEL ! SHALL SEND A SECOND SIGNAL TO COMCAST ! WHEN THE HYDROGEN LEVEL REACHES 2 PERCENT ! AND SHALL ENERGIZE EF-1 TO EVACUATE THE ! BATTERY ROOM.!

DCU 3
ON ROOF

DAC 2

48"x20" INTAKE LOUVER MOUNTED LOW IN EXISTING WALL. PROVIDE SECURITY BARS AND MOTOR OPERATED DAMPER INTERLOCKED WITH EF-1. PROVIDE CUTTING AND PATCHING AS REQUIRED

DAC 3
NEW LOCATION OF! FLOOR MOUNTED ! 20 TON LIEBERT DS UNIT! PROVIDE TOP MOUNTED! RETURN AIR SCOOP

FIRE SUPPRESSION NOTES


1.! THE FIRE PROTECTION CONTRACTOR SHALL BE ! RESPONSIBLE FOR THE CALCULATION, DESIGN ! APPROVAL, CONFORMANCE AND OPERATION OF ! THE SUPPRESSION SYSTEMS. THE PLACEMENT ! OF THIS INFORMATION ON THE DRAWINGS IS FOR ! IDENTIFICATION ONLY.! !! 2.! THE FIRE PROTECTION CONTRACTOR IS TO ! PROVIDE THE FIRE PROTECTION SYSTEM AS ! REQUIRED. HE IS SOLELY RESPONSIBLE TO ! PROVIDE A COMPLETE WORKING FIRE ! PROTECTION SYSTEM DESIGNED AND INSTALLED ! IN ACCORDANCE WITH NFPA 13, STATE AND ! LOCAL CODES, LANDLORD REQUIREMENTS, THE ! OWNER'S INSURANCE UNDERWRITER'S ! REQUIREMENT, AND AS REQUIRED BY THE LOCAL ! FIRE MARSHALL. ! !! 3.! THE AREA WITHIN THE SCOPE OF THIS PROJECT, ! INCLUDING FLOOR SPACE, IS TO BE 100% ! PROTECTED BY THE FIRE SUPPRESSION SYSTEM.! !! 4.! THE COMPLETE INSTALLATION SHALL INCLUDE ! THE FOLLOWING: TIE-IN TO THE BUILDING FIRE ! ALARM SYSTEM; ALL PIPE, VALVES, FITTINGS, ! HEADS, DETECTORS, WIRING AND CONTROLS; ! ALL INSERTS, HANGERS AND SUPPORTS FOR PIPE ! AND EQUIPMENT. ALL HANGERS AND INSERTS ! SHALL MEET THE APPROVAL OF ALL AUTHORITIES ! HAVING JURISDICTION.! !! 5.! THE CONTRACTOR SHALL PAY FOR PERMITS, ! INSPECTIONS, TESTS AND APPROVALS RELATED ! TO THE SYSTEM AS REQUIRED BY ALL ! AUTHORITIES HAVING JURISDICTION. THIS ! INCLUDES SUPPLYING ERECTION DRAWINGS TO ! THE ARCHITECT IN ACCORDANCE WITH THE ! GENERAL CONDITIONS AND THE MECHANICAL ! TRADE REQUIREMENTS OF THE PROJECT.! !! 6.! THE FM-200 SYSTEM SHALL BE FURNISHED WITH A ! (24V) DRY CONTACT. FM-200 ALARMS SHALL BE REPEATED TO THE OWNERS MONITORING SYSTEM.!

RELOCATE EXISTING! FM200 EMERG. SHUTDOWN SW.

CCU 1
ON ROOF

DC

FM200 EMERG. SHUTDOWN SW.! TO BE REMOVED

DC

(EX) FLOOR MOUNTED! 20 TON LIEBERT DS UNIT

EXISTING 3 TON MITSUBISHI! SPLIT SYSTEM TO BE REMOVED

(EX) FLOOR MOUNTED! 20 TON LIEBERT DS UNIT

CONDENSATE LINE, RUN BELOW ! RAISED FLOOR, FROM UNIT TO ! NEW SAFEWASTE AT SINK. LINE TO! BE FULL SIZE OF UNIT OPENING

CAC 1

(EX) FM200 EMERG. SHUTDOWN SW.

(EX) 5 TON LIEBERT! THRU-WALL AC UNITS

(EX) 5 TON LIEBERT! THRU-WALL AC UNITS

(EX) CONDENSER

(EX) CONDENSER

(EX) CONDENSER

(EX) CONDENSER

(EX) CONDENSER

(EX) CONDENSER

(EX) CONDENSER

(EX) CONDENSER

DEMOLITION PLAN
1/8" = 1'-0"

MECHANICAL PLAN
1/8" = 1'-0"

FM200 GRAPHIC ANNUNICATOR ! AND CONTROL PANEL!

NEW FM200! TANKS

HEAD END BUILDING FIRE PROTECTION SYSTEM SPECIFICATIONS


I. SCOPE - This specication outlines the requirements for an FM-200 total ooding re suppression system with automatic! D) Detectors - The detectors shall be spaced and installed in accordance with the manufacturers specications and within! detection and control and includes all requirements to monitor, supervise and control the system. The work described in this! the guidelines of NFPA No. 72 - 1993 edition.! specication includes all engineering, labor, materials, equipment and services necessary, and required, to complete and test the! ! suppression system.! E) Manual Release Switch - The manual release switch shall be a dual action device which provides a means of manually! ! discharging the FM-200 re suppression system when used in conjunction with the Fike Rhino Control System.! II. APPLICABLE STANDARDS AND PUBLICATIONS - The design, equipment, installation, testing and maintenance of the! ! FM-200 suppression system shall be in accordance with the applicable requirements set forth in the latest edition of the following! F) Abort Station - The Abort Station shall be the Dead Man type and shall be located next to each manual switch.! codes and standards:! ! ! G) Audible and Visual Alarms - Alarm signal devices shall operate from the FM-200 control panel.! 1) NFPA No. 2001 - Clean Agent Fire Extinguishing Systems! ! 2) NFPA No. 12 A - Halon 1301 Fire Extinguishing Systems! H) Caution/Advisory Signs - Provide signs as required to comply with NFPA 2001 and the recommendations of the FM-200! 3) NFPA No. 70 - National Electrical Code! equipment manufacturer.! 4) NFPA No. 72 - Standard for Protective Signaling! ! 5) NFPA No. 75 - Electronic Computer Systems! I) Auxiliary Panels - A Graphic Annunciator panel will be mounted adjacent to the FM-200 control panel. The graphic! 6) Factory Mutual Approval Guide! annunciator shall show a scale layout of the protected area and have indicator lamps to locate each system detector. The! 7) U.L. Listings! panel shall have a lamp test switch located on the panel face.! 8) Requirements of the Authority Having Jurisdiction (AHJ)! ! ! J) System and Control Wiring - All FM-200 system wiring shall be furnished and installed by the FM-200 system contractor.! The standards listed, as well as all other applicable codes and standards, shall be used as minimum design standards.! All wiring shall be installed in electrical metallic tubing (EMT) or conduit.! Also to be considered are the requirements of the Authority Having Jurisdiction and good engineering practices.! ! ! K) System Inspection and Checkout - After the system installation has been completed, the entire system shall be checked! III. QUALITY ASSURANCE:! out, inspected, and functionally tested by qualied trained personnel, in accordance with the manufacturers recommended! ! procedures and NFPA standards.! A. MANUFACTURER - The manufacturer of the FM-200 suppression system hardware and detection components shall have a! ! minimum of 10 years experience in the design and manufacture of similar types of suppression systems and who can refer to! L) Training Requirements - Prior to nal acceptance, the installing contractor shall provide operational training to each shift! similar installations providing satisfactory service. The name of the manufacturer, part numbers and serial numbers shall appear on! of the Owners personnel. Each training session shall include system control panel operation, manual and abort functions, trouble! all major components. All devices, components and equipment shall be the products of the same manufacturer. All devices,! procedures, auxiliary functions and emergency procedures.! components and equipment shall be new and standard products of the manufacturers latest design, suitable to perform the! ! functions intended. All devices and equipment shall be U.L. listed and/or FM approved. Locks for all cabinets shall be keyed alike.! M) Operation and Maintenance - Prior to nal acceptance, the installing contractor shall provide complete operation and! ! maintenance instruction manuals, four (4) copies for each system, to the owner. All aspects of system operation and maintenance! B. INSTALLER - The installing contractor shall be trained by the manufacturer to design, install, test and maintain FM-200 re! shall be detailed, including piping isometrics, wiring diagrams of all circuits, a written description of the system design, sequence of! suppression systems. The installing contractor shall employ a NICET certied special hazard designer, level 2 or above, who will! operation, drawing(s) illustrating control logic, and equipment used in the system. Checklists and procedures for emergency! be responsible for this project. The installing contractor shall be an experienced rm regularly engaged in the installation of! situations, trouble shooting techniques, and maintenance operations and procedures shall be included in the manual.! automatic FM-200 or similar, re suppression systems in strict accordance with NFPA standards. The installing contractor must! ! have a minimum of ve (5) years experience in the design, installation and testing of FM-200, or similar, re suppression systems.! N) As-Built Drawings - The contractor shall provide and maintain in good order a complete set of blueline prints of the contract drawings.! As the work progresses, the actual location of all work shall be clearly recorded, including all changes to the contract and equipment size and type.! A list of systems of a similar nature and scope shall be provided on request. The installing contractor shall show evidence that his! These prints shall be available at the site for inspection at all times. At the conclusion of the work, the contractor shall, at his own expense, obtain! company carries a minimum $2,000,000 liability and completed operations insurance policy. These limits shall supersede the! a set of reproducibles of the original contract drawings, and utilizing the symbols on the contract drawings, shall incorporate all "as built" data in a! general conditions of the specications. The installing contractor shall have an FM-200 recharging station. The installing contractor! clearly legible and reproducible manner. All schedules shall be corrected to indicate "as built" conditions. All revisions shall be incorporated on! shall provide proof of his ability to recharge the largest FM-200 system within 24 hours after a discharge. Include the amount of! these reproducibles including all sketches and written directives. Electronic/CADD as-built's shall be provided at the completion of the project.! FM-200 bulk storage available. The installing contractor shall be an authorized stocking distributor of the FM-200 system! Contractor shall update all affected oor plans, riser diagrams and details. Contractor shall provide to the landlord a complete updated CADD le! manufacturer so that immediate replacement parts are available from inventory. The installing contractor shall show proof of! on compact disk and 1 set of reproducibles of the updated system drawings.! emergency service available on a twenty-four hour, seven days a week basis; service personnel shall be available for emergency! ! service response at all times.! O) Acceptance Tests - At the time As-Built drawings and maintenance/operations manuals are submitted, the installing! ! contractor shall submit a Test Plan describing procedures to be used to test the FM-200 system(s). The Test Plan shall include! C. SUBMITTALS - Submit drawings, calculations and system component data sheets for approval to the Local Fire Prevent Bureau,! a step-by-step description of all tests to be performed and shall indicate the type and location of test apparatus to be employed.! Owners Insurance Underwriter and all other Authorities Having Jurisdiction between starting installation. Submit approved plans to! The tests shall demonstrate that the operational and installation requirements of this specication have been met. All tests shall! the Architect/Engineer for record.! be conducted in the presence of the Owner and shall not be conducted until the Test Plan has been approved.! ! ! IV. MATERIALS AND EQUIPMENT:! P) FM-200 System Inspections - The installing contractor shall provide two (2) inspections of each FM-200 system, installed! ! under this contract, during the one-year warranty period. The rst inspection shall be at the six month interval, and the second! A) GENERAL REQUIREMENTS - The FM-200 System materials and equipment shall be standard products of the manufacturers! inspection shall be at the twelve month intervals after system acceptance. Inspections shall be conducted in accordance with! latest design and suitable to perform the functions intended. When one or more pieces of equipment must perform the same! the manufacturers guidelines and shall comply with the recommendations of NFPA.! functions, they shall be duplicates produced by one manufacturer. All devices and equipment shall be U.L. Listed and/or F.M. approved.! ! ! Q) Warranty - All Fike FM-200 system components furnished, and installed under this contract, shall be guaranteed against! B) FM-200 Storage and Distribution - Each system shall have its own supply of FM-200 agent.! defects in design, materials and workmanship for the full warranty period which is standard with the manufacturer, but in no case! ! less than one (1) year from the date of system acceptance. C) Control Panel (VERIFY WITH OWNER) - The Control System and components shall be U.L. Listed and F.M. approved for use ! as a local re alarm system.
MODIFY OR PREPLACE FM200 SYSTEM PIPING, ! CEILINGS HEADS, RAISED FLOOR HEADS, DETECTORS,! ETC AS REQUIRED TO PROVIDE A SINGLE BUILDING! PROTECTION SYSTEM PROVIDE A NEW COMPLETE FM200 SYSTEM IN THIS AREA! CONNECT WITH REMAINDER OF BUILDING TO PROVIDE A ! SINGLE BUILDING PROTECTION SYSTEM

(EX) EXISTING FM200 EMERG. ! SHUTDOWN SWITCH RELOCATED

DC

SCALE: DATE:

MECHANICAL! FLOOR PLANS

FIRE SUPPRESSION PLAN


1/8" = 1'-0"

COMCAST EAST NORRITON RENOVATION


237 West Germantown Pike
East Norriton, PA
REVISIONS
AS NOTED 03 NOV 2011

M-1

TEL:(215)755-9318 FAX:(215)755-9319

HP 1

1812 SOUTH 22nd STREET PHILADELPHIA, PA. 19145

(EX) FLOOR MOUNTED! 20 TON LIEBERT DS UNIT

(EX) FLOOR MOUNTED! 20 TON LIEBERT DS UNIT

EF 1

BHG CONSULTING, INC.

26x6

10x12

MASSOTT

6X6 OUTSIDE AIR DUCT THROUGH WALL! WITH CAP. CONNECT TO RETURN DUCT WITH! AUTOMATIC AND MANUAL DAMPERS, INTERLOCK! AUTOMATIC DAMPER WITH UNIT

D E S I G N C O N S U L T A N T S, I N C. 1034 TWIN SILO LANE, HUNTINGDON VALLEY, PA 19006 215-325-0994 massottdesign@comcast.net

You might also like