McClellan-Palomar Airport Feasibility Study for Potential Improvements to Runway

September 25, 2013 Agenda Item #2

September 25, 2013

Agenda Item #2

Background June 2011 Board identified need for study of runway improvements

Sept 2011 Board directed staff conduct study

September 25, 2013

Agenda Item #2

Scope of Study Determine if extension would:


improve runway safety reduce airport noise increase operational efficiency increase business prospects

Prepared in accordance with FAA requirements

September 25, 2013

Agenda Item #2

Study Findings

Recommend retaining current design standards


Increased design criteria deemed not feasible

West end safety improvements for current and future aircraft East end improvements = Increased fuel loads => longer haul
September 25, 2013 Agenda Item #2 5

West End Safety Improvements


Runway Safety Improvements:
Todays Business Jet Aircraft
Engineered Material Arresting System (EMAS) Improve grades

EMAS System Key West Florida


September 25, 2013 Agenda Item #2 6

East End Runway Extension

Landfill Remediation Stable Platform for Runway Reduce settlement by reconsolidating landfill Re-construct methane gas collection system
September 25, 2013 Agenda Item #2 7

East End Runway Extension

September 25, 2013

Agenda Item #2

East End Runway Extension


BUSINESS JET RANGE ALTERNATIVES

September 25, 2013

Agenda Item #2

East End Runway Extension


Noise Contours Comparison
Existing

Future with Alt B

September 25, 2013

Agenda Item #2

10

Estimated Construction Costs


Alternative
Alt. A Alt. B-1 Alt. B-2 West End

Alternative Description
200 ft extension with north & south taxiways 900 ft extension with north taxiway 900 ft extension with north & south taxiways West End Safety Improvements

Estimated Construction Costs


$22.5M $49.6M $69.7M $25.4M

September 25, 2013

Agenda Item #2

11

Business Case Summary Current Regional Economic Benefits


$321.4M revenues 2,215 jobs $81.3M income to workers

Regional 20 Year Forecast


With Runway Extension (Alt B 900 Extension) = additional $163.2M revenues

Benefit Cost Analysis


Alt A (200 Extension) = 1.49 Alt B (900 Extension w/ both taxiways) = 2.53
September 25, 2013 Agenda Item # 12

Report Summary

Airfield same as today (B-II)

West End Safety Improvement


$25.4M FAA Eligible as Safety Project

East End Runway Extension (Alt B 900)


100% B-II sized aircraft served $69.7M with north & south taxiways FAA Eligible as Capacity Project
September 25, 2013 Agenda Item #2 13

Airport Master Plan Update

New 20-year Master Plan In Progress

Comprehensive Planning Approach Include Runway Extension Feasibility Data

September 25, 2013

Agenda Item #2

14

Airport Master Plan Update

Master Plan
Considers runway extension in the context of long-term facility improvements Project Sequencing, Environmental, Financial Plan Public Outreach

Programmatic Environmental Impact Report (EIR)

September 25, 2013

Agenda Item #2

15

Recommendations Receive report titled Feasibility Study for Potential Improvements to McClellanPalomar Airport Proposed action of receiving report is exempt under CEQA

September 25, 2013

Agenda Item #2

16

McClellan-Palomar Airport Feasibility Study for Potential Improvements to Runway

September 25, 2013 Agenda Item #2

Preliminary Draft

Preliminary Draft

West End Safety

September 25, 2013

Agenda Item #2

Business Case
Regional Payback Period

September 25, 2013

Agenda Item #2

17

Final Study and Report

Contains findings and recommendations that are:


technically sound from an engineering perspective fiscally responsible makes good business sense eligible for funding in accordance with FAA criteria

September 25, 2013

Agenda Item #2