: Civil Specifications Date: March 7, 2009 Project : Cut & Bend Processing Bldg. Owner : Al Rajhi Steel DIVISION 3 CONCRETE SECTION 03300 EXPANSION AND CONSTRUCTION JOINTS SUBSECTION: INDEX PART 1 GENERAL 1.01 1.02 1.03 Description Quality Assurance Product Storage

PART 2 - PRODUCTS 2.01 2.02 Materials Mixing

PART 3 EXECUTION 1.01 Installation

PART 1 GENERAL 1.01 Description A. Description of Work Work under this Section consist of furnishing everything necessary for and incidental to the execution and completion of all concrete joint work as shown on drawings and specified herein. 1.02 Quality Assurance A. Applicable Standards Comply with Standards specified under this Section. 1.03 Product Storage A. Storage Store epoxy joint materials in a cool dry place. Replace lids tightly on partially used containers.

Saudi Designers Eng. Consultant

Division-3 - 3300

Page 1 of 3

Project Number : 3206 Document Name.: Civil Specifications Date: March 7, 2009 Project : Cut & Bend Processing Bldg. Owner : Al Rajhi Steel Part 2 - Products 2.01 Materials A. B. Expansion (Isolation) Joints: ASTM D1751. Epoxy Filler Pennwalt Corporations Pouring Grade Flexjoint or equal; color selected by Consultants Representative. C. Epoxy Primer CMCI Grade Construction Material Chemical Industries and Arabian Vermiculite Industries. 2.02 Mixing A. Epoxy Joint Filler 1. Minimum Temperature Mix only when temperature of both components are above 50 oF. 2. Procedure a) b) Minimum Temperature: Mix only when temperature of both components are above 50 oF. During warm weather (80 oF and above) do not mix more material that can be placed within 5 minutes of mixing in a cool weather (51 oF to 70 oF).

Part 3 Execution 3.01 Installation A. Expansion (Isolation) Joints Securely anchor in place preformed compressible expansion joint fillers. B. Construction and Control Joints 1. Form a key with a width of one-third the thickness of the thinner member and a depth of 50 mm unless otherwise shown. Tape a key to facilitate removal of form. Carry all reinforcements thru the joint. Do not remove key or forms until concrete has cured.

2. 3. 4.

Saudi Designers Eng. Consultants

Division-3- 3300

(Page 2 of 3)

Project Number : 3206 Document Name.: Civil Specifications Date: March 7, 2009 Project : Cut & Bend Processing Bldg. Owner : Al Rajhi Steel 5. 6. Clean key of laitance, curing compound foreign materials and protrusions of hardened concrete before casting abutting work. Epoxy Primer a) Priming is not required, if joints are clean and dry; use primer only if moisture and contaminants cannot be removed effectively. If priming is necessary, brush apply a uniform coat of primer on concrete contact surface only.

b)

7.

Epoxy Filler a) b) c) Dispense epoxy filler from plastic squeeze bottle. Fill joint in two closely succeeding pours Exercise care to prevent overfilling; remove any excess with a straight edge prior to hardening, by grinding after hardening. Fill primed joints within 4 hours of priming and while primer is still tacky; if elapsed time exceeds 4 hours, or primer is no longer tacky, re-prime. Follow additional recommendation of manufacturer.

d)

e)

Saudi Designers Eng. Consultants