NCT BACK-UP PROJECT, CHITTAGONG Work Program,2nd June, 2011

S.l. No. Description


1 2 3 4 5 6 Segment 1A Segment 2A (part) Segment 1 (part) Segment 4 (part) Culvert (road)

Work Program of 2nd June, 2011


Sand dumping and sand bagging of preloading 300mm Sand Blanket filling Clearing & Grubbing. Clearing & Grubbing. Concrete pouring of 2nd wall

Achievement of 1st May, 2011


Sand dumping and sand bagging of preloading in progress 300mm Sand Blanket filling in progress Clearing & Grubbing in progress. Clearing & Grubbing in progress. Concrete pouring of 1st wall Executed Shuttering Executed Soling Executed Rebar fabrication in progress

Remarks

Open Deep Drain(CH 600-650) Concrete pouring of wall (2nd lift) Open Deep Drain(CH 520-535) CC Casting

Culvert (rail)

Rebar fabrication Earth Excavation

8 9 10 11

RCC pipe Shore Pile Interlocking Block Dismantling work

Concrete pouring Shutter making & Rebar fabrication ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

Concrete pouring in progress

ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program,7th June, 2011

S.l. No. Description


1 2 3 4 5 6 7 Segment 1A Segment 2A (part) Segment 1 (part) Segment 4 (part) Culvert (road)

Work Program of 7th June, 2011


Sand dumping and sand bagging of preloading 300mm Sand Blanket filling Clearing & Grubbing. Clearing & Grubbing. Shuttering of 2nd lift

Achievement of 6th June, 2011


Sand dumping and sand bagging of preloading in progress 300mm Sand Blanket filling in progress Clearing & Grubbing in progress. Clearing & Grubbing in progress. Rebar fabrication in 2nd lift Shuttering Executed Rebar fabrication in progress Earth Excavation in progress Concrete pouring in progress Shutter making & Rebar fabrication in progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

Open Deep Drain(CH 520-535) Concrete Pouring of 2nd lift Culvert (rail) Rebar fabrication Earth Excavation

8 9 10 11

RCC pipe Shore Pile Interlocking Block Dismantling work

Concrete pouring Shutter making & Rebar fabrication ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program,8th June, 2011

S.l. No. Description


1 Segment 1A

Work Program of 8th June, 2011


Sand dumping and sand bagging of preloading Regular Settlement Record of Preloading

Achievement of 7th June, 2011


Sand dumping and sand bagging of preloading in progress Settlement Record in progress 300mm Sand Blanket filling in progress Clearing & Grubbing in progress. Clearing & Grubbing in progress. Shuttering Executed Rebar fabrication in progress Earth Excavation in progress Concrete pouring in progress Shutter making & Rebar fabrication in progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

2 3 4 5 6

Segment 2A (part) Segment 1 (part) Segment 4 (part)

300mm Sand Blanket filling Clearing & Grubbing. Clearing & Grubbing.

Open Deep Drain(CH 520-535) Concrete Pouring of 2nd lift Culvert (rail) Rebar fabrication Earth Excavation

7 8 9 10

RCC pipe Shore Pile Interlocking Block Dismantling work

Concrete pouring Shutter making & Rebar fabrication ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program, 11th June, 2011

S.l. No. Description


1 Segment 1A

Work Program of 11th June, 2011


Sand dumping and sand bagging of preloading Regular Settlement Record of Preloading

Achievement of 10th June, 2011


Sand dumping and sand bagging of preloading in progress Settlement Record in progress 300mm Sand Blanket filling in progress Clearing & Grubbing in progress. Clearing & Grubbing in progress. Shuttering Executed Concrete pouring of wall 2nd lift Rebar fabrication in progress Earth Excavation in progress Concrete pouring in progress Shutter making & Rebar fabrication in progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

2 3 4 5 6 7

Segment 2A (part) Segment 1 (part) Segment 4 (part)

300mm Sand Blanket filling Clearing & Grubbing. Clearing & Grubbing.

Open Deep Drain (CH 520-535) Concrete Pouring of 1st lift Culvert (Roadl) Culvert (rail) Wall 2nd lift Rebar fabrication Earth Excavation

8 9 10 11

RCC pipe Shore Pile Interlocking Block Dismantling work

Concrete pouring Shutter making & Rebar fabrication ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program, 12th June, 2011


S.l. No. Description
1 Segment 1A

Work Program of 12th June, 2011


Sand dumping and sand bagging of preloading Regular Settlement Record of Preloading

Achievement of 11th June, 2011


Sand dumping and sand bagging of preloading in progress Settlement Record in progress 300mm Sand Blanket filling in progress Clearing & Grubbing in progress. Clearing & Grubbing in progress. Shuttering Executed Concrete pouring of wall 2nd lift Rebar fabrication in progress Earth Excavation in progress Concrete pouring in progress Shutter making & Rebar fabrication in progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

2 3 4 5 6 7

Segment 2A (part) Segment 1 (part) Segment 4 (part)

300mm Sand Blanket filling Clearing & Grubbing. Clearing & Grubbing.

Open Deep Drain (CH 520-535) Concrete Pouring of 1st lift Culvert (Roadl) Culvert (rail) Wall 2nd lift Rebar fabrication Earth Excavation

8 9 10 11

RCC pipe Shore Pile Interlocking Block Dismantling work

Concrete pouring Shutter making & Rebar fabrication ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program, 13th June, 2011


S.l. No. Description
1 Segment 1A

Work Program of 13th June, 2011

Achievement of 12th June, 2011

Remarks

Sand dumping and sand bagging of preloading Sand dumping and sand bagging of preloading in progress Regular Settlement Record of Preloading Settlement Record in progress 300mm Sand Blanket filling in progress Clearing & Grubbing in progress. Clearing & Grubbing in progress. Concrete pouring of wall 1st lift Concrete pouring of wall 2nd lift Rebar fabrication in progress Earth Excavation finished Shutter making & Rebar fabrication ILB plant shift CC/RCC Dismantling work at Segment 3 & 4 Concrete pouring in progress Shutter making & Rebar fabrication in progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

2 3 4 5 6 7

Segment 2A (part) Segment 1 (part) Segment 4 (part)

300mm Sand Blanket filling finished Clearing & Grubbing. Clearing & Grubbing.

Open Deep Drain (CH 520-535) Shuttering of 2nd lift Culvert (Roadl) Culvert (rail) Top slab shuttering Rebar fabrication Base C.C casting

8 9 10 11

RCC pipe Shore Pile Interlocking Block Dismantling work

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program, 16th June, 2011


S.l. No. Description
1 Segment 1A

Work Program of 16th June, 2011


Sand dumping and sand bagging of preloading Regular Settlement Record of Preloading

Achievement of 15th June, 2011


Sand dumping and sand bagging of preloading in progress Settlement Record in progress 300mm Sand Blanket filling is finished Clearing & Grubbing in progress. Clearing & Grubbing in progress. Earth Excavation is finished Top slab shuttering & rebar binding in progress Rebar binding of Base in progress Shutter making & Rebar fabrication in progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

2 3 4 5 6 7 9 10 11

Segment 2A (part) Segment 1 (part) Segment 4 (part)

PVD Driving Clearing & Grubbing. Clearing & Grubbing.

Open Deep Drain (CH 520-535) Soling & CC work Culvert (Roadl) Culvert (rail) Shore Pile Interlocking Block Dismantling work Top slab shuttering & rebar binding Rebar binding of Base Shutter making & Rebar fabrication ILB plant shift CC/RCC Dismantling work at Segment 3 & 4

Project Manager NCT Back-up Project Project Builders Ltd

NCT BACK-UP PROJECT, CHITTAGONG Work Program, 21th June, 2011


S.l. No.Description
1 Segment 1A

Work Program of 21th June, 2011


Sand dumping and sand bagging of preloading Regular Settlement Record of Preloading

Achievement of 20th June, 2011


Sand dumping and sand bagging of preloading in progress Settlement Record in progress PVD Driving in progress Clearing & Grubbing in progress. Levelling & Dressing in progress Earth Excavation is finished Top slab shuttering & rebar binding in progress Rebar binding of Base in progress Concrete Pouring in Progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 in progress

Remarks

2 3 4 5 6 7 9 10 11

Segment 2A (part) Segment 1 (part) Segment 4 (part)

PVD Driving Clearing & Grubbing. Levelling & Dressing

Open Deep Drain (CH 520-535) Soling & CC work Culvert (Roadl) Culvert (rail) Shore Pile Interlocking Block Dismantling work Top slab shuttering & rebar binding Shuttering & Rebar binding of Base Shuttering & Rebar fabrication ILB plant shift CC/RCC Dismantling work at Segment 3

Project Manager NCT Back-up Project Project Builders Ltd

NCT BACK-UP PROJECT, CHITTAGONG Work Program, 22th June, 2011


S.l. No.Description
1 Segment 1A

Work Program of 22th June, 2011


Sand dumping and sand bagging of preloading Regular Settlement Record of Preloading

Achievement of 21th June, 2011


Sand dumping and sand bagging of preloading in progress Settlement Record in progress PVD Driving in progress Clearing & Grubbing in progress. Levelling & Dressing in progress Earth Excavation is finished Top slab shuttering & rebar binding in progress Rebar binding of Base in progress Concrete Pouring in Progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 in progress

Remarks

2 3 4 5 6 7 9 10 11

Segment 2A (part) Segment 1 (part) Segment 4 (part)

PVD Driving Clearing & Grubbing. Levelling & Dressing

Open Deep Drain (CH 520-535) Soling & CC work Culvert (Roadl) Culvert (rail) Shore Pile Interlocking Block Dismantling work Top slab shuttering & rebar binding Shuttering & Rebar binding of Base Shuttering & Rebar fabrication ILB plant shift CC/RCC Dismantling work at Segment 3

Project Manager NCT Back-up Project Project Builders Ltd

NCT BACK-UP PROJECT, CHITTAGONG Work Program, 23th June, 2011


S.l. No.Description
1 Segment 1A

Work Program of 23th June, 2011


Sand dumping and sand bagging of preloading Regular Settlement Record of Preloading

Achievement of 22th June, 2011


Sand dumping and sand bagging of preloading in progress Settlement Record in progress Clearing & Grubbing in progress. Levelling & Dressing in progress Earth Excavation is finished Top slab shuttering & rebar binding finished Concrete Pouring of Base executed Concrete Pouring in Progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 in progress

Remarks

3 4 5 6 7 9 10 11

Segment 1 (part) Segment 4 (part)

Clearing & Grubbing. Levelling & Dressing

Open Deep Drain (CH 520-535) Soling & CC work Culvert (Roadl) Culvert (rail) Shore Pile Interlocking Block Dismantling work Concrete pouring of top slab Shuttering & Rebar binding of wall Shuttering & Rebar fabrication ILB plant shift CC/RCC Dismantling work at Segment 3

Project Manager NCT Back-up Project Project Builders Ltd

NCT BACK-UP PROJECT, CHITTAGONG Work Program, 25th June, 2011


S.l. No.Description
1 2 3 4 5 6 7 8 9 Segment 1A Segment 1 (part) Segment 4 (part)

Work Program of 25th June, 2011


Regular Settlement Record of Preloading Clearing & Grubbing. Levelling & Dressing

Achievement of 24th June, 2011


Settlement Record in progress Clearing & Grubbing in progress. Levelling & Dressing in progress Earth Excavation is finished Concrete pouring of slab executed

Remarks

Open Deep Drain (CH 520-535) Soling & CC work Culvert (Roadl) Culvert (rail) Shore Pile Interlocking Block Dismantling work Shuttering & Rebar binding of wall Shuttering & Rebar fabrication ILB plant shift CC/RCC Dismantling work at Segment 3

Concrete Pouring of Base executed Concrete Pouring in Progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 in progress

Project Manager NCT Back-up Project Project Builders Ltd

NCT BACK-UP PROJECT, CHITTAGONG Work Program, 26th June, 2011


S.l. No.Description
1 2 3 4 5 6 7 8 9 Segment 1A Segment 1 (part) Segment 4 (part)

Work Program of 26th June, 2011


Regular Settlement Record of Preloading Clearing & Grubbing. Levelling & Dressing

Achievement of 25th June, 2011


Settlement Record in progress Clearing & Grubbing in progress. Levelling & Dressing in progress Earth Excavation is finished Concrete pouring of slab executed

Remarks

Open Deep Drain (CH 520-535) Soling & CC work Culvert (Roadl) Culvert (rail) Shore Pile Interlocking Block Dismantling work Shuttering & Rebar binding of wall Concrete Pouring ILB plant shift CC/RCC Dismantling work at Segment 3

Concrete Pouring of Base executed Concrete Pouring in Progress ILB plant shift in progress CC/RCC Dismantling work at Segment 3 in progress

Project Manager NCT Back-up Project Project Builders Ltd

NCT BACK-UP PROJECT, CHITTAGONG Work Program, 28th June, 2011


S.l. No. Description
1 2 3 4 5 6 7 8 9 10 Segment 1A Segment 1 (part) Segment 4 (part)

Work Program of 28th June, 2011


Regular Settlement Record of Preloading Clearing & Grubbing. Sub-Grade Preparation

Achievement of 27th June, 2011


Settlement Record in progress Clearing & Grubbing in progress. Levelling & Dressing in progress Earth Excavation is finished Concrete pouring of slab executed

Remarks

Open Deep Drain (CH 520-535) Soling & CC work Culvert (Roadl) Culvert (rail) Shore Pile Interlocking Block Road Work Dismantling work Shuttering & Rebar binding of wall Concrete Pouring ILB plant shift Layout fixing of Road Type-1 CC/RCC Dismantling work at Segment 3

Concrete Pouring of Base executed Concrete Pouring in Progress ILB plant shift in progress

CC/RCC Dismantling work at Segment 3 in progress

Project Manager NCT Back-up Project Project Builders Ltd

NCT BACK-UP PROJECT, CHITTAGONG Work Program, 29th June, 2011


S.l. No. Description
1 2 3 4 5 6 7 8 9 10 Segment 1A Segment 1 (part) Segment 4 (part)

Work Program of 29th June, 2011


Regular Settlement Record of Preloading Clearing & Grubbing. Sub-Grade Preparation

Achievement of 28th June, 2011


Settlement Record in progress Clearing & Grubbing in progress. Sub-Grade preparation in progress Earth Excavation is finished Concrete pouring of slab executed

Remarks

Open Deep Drain (CH 520-535) Soling & CC work Culvert (Roadl) Culvert (rail) Shore Pile Interlocking Block Road Work Dismantling work Shuttering & Rebar binding of wall Concrete Pouring ILB plant shift Layout fixing of Road Type-1 CC/RCC Dismantling work at Segment 3

Concrete Pouring of Base executed Concrete Pouring in Progress ILB plant shift in progress

CC/RCC Dismantling work at Segment 3 in progress

Project Manager NCT Back-up Project Project Builders Ltd