You are on page 1of 71

A PRACTICAL SUMMER

TRAINING REPORT

ON

DELHI TRANSCO LIMITED

(220 KV GRID SUBSTATION AT SARITA VIHAR)

NATIONAL POWER TRAINING INSTITUTE (NR)


BADARPUR, NEW DELHI

UNDER THE GUIDANCE OF


MR. RAM SINGH (A.M.)
MR. HANS KUMAR (J.E.)

SUBMITTED BY:
AVNISH KUMAR KATIYAR
B.TECH. POWER ENGINEERING (6th SEM.)
ROLL NO. 02315303710

ACKNOWLEDGEMENT
I am highly indebted to Mr. Ram Singh (Asst. Manager, 220 KV DTL S/S Sarita Vihar)
for their valuable support without which the project could have not been worked out the
way it has. I am very much thankful to Mr. Hans Kumar (J.E. 220 KV DTL S/S Sarita
Vihar) who helped me immensely in understanding the basics and complexities of along
with additions that made the quality of report better.
I would also like to extend a note of thanks to all other employees of Delhi Transco
Limited who helped me directly or indirectly in successful completion of my project.
Last but not the least, I would like to thank my parents & all my fellow trainees who
have been a constant source of encouragement & inspiration during my studies & have
always provided me support in every walk of life.

AVNISH KUMAR KATIYAR

CONTENT
1. Introduction
1.1 Introduction to Delhi Transco Limited
1.2 DTL Network
1.3 Grid Diagram of Delhi
2. Introduction to Substation
3. 220/66/11 KV Substation Sarita Vihar
3.1 Single Line Diagram
3.2 Description of SLD
3.3 Parts of Substation
3.4 Equipments used in Substation
4. Description of Substation Equipments
4.1 Transmission Lines
4.2 Bus Bar
4.3 Isolators
4.4 Transformers
4.4.1 Introduction
4.4.2 Power transformer
4.4.3 Parts of Power Transformer
4.4.4 Transformer Cooling
4.4.5 Protection devices
4.4.6 Maintenance
4.4.7 Technical Specifications
4.5 Instrument Transformer
4.5.1 Current Transformer (CT)
4.5.2 Potential transformer (PT)
4.5.3 Capacitor Voltage Transformer (CVT)
4.6 Circuit Breaker (CB)
4.6.1 Types of CB
4.6.2 Technical Specification
4.7 Capacitor Bank
4.8 Insulator
4.9 Wave Trap
5. Protection System
5.1 Over Voltage Protection
5.1.1 Ground Wire

5.1.2 Earth Screen


5.1.3 Lightning insulator
5.2 Over Current protection
5.3 Earth fault protection
5.4 Primary and back up protection
5.5 Relays
5.6 Fuses
5.7 Earthing System
6.
7.
8.
9.

Control Room
Battery Room
PLCC and SCADA System
Operation and maintenance of Substation
9.1 Introduction
9.2 Maintenance activity
9.3 Maintenance Schedule
9.4 Maintenance Schedule Table of
9.4.1 Oil filled power transformer
9.4.2 SF6 Circuit Breaker
9.4.3 Relays and protection circuit
9.4.4 Arrestors
9.4.5 Transmission lines
9.5 Thermo Scanning
10. General Safety Precautions
11. Conclusion
References

1. INTRODUCTION
1.1 AN INTRODUCTION TO DELHI TRANSCO LIMITED
Delhi Transco Limited, a successor company of erstwhile Delhi Vidhyut board, came
into existence on 1st July 2002, as a State Transmission Utility of the National Capital.
After unbundling of DVB the distribution sector has been handed over to private
companies while the generation and transmission are still with the government. Over
the years, DTL has evolved as a most dynamic performer, keeping pace with the
manifold challenges that confront the ever increasing demand-supply power situation
and
achieving
functional
superiority
on
all
fronts.
Being the capital of India and the hub of commercial activities in the Northern Region,
coupled with the prosperity of population, the load requirement of Delhi has been
growing at a much faster pace. Added to that, being the focus of socio-economic and
political life of India, Delhi is assuming increasing eminence among the great cities of
the world. Plus the vgision-2021, aiming to make Delhi global Metro politic and world
class city demand greater infrastructure to enrich many services of infrastructure
development. DTL has been responsibly playing its role in establishing. Upgrading,
operating and maintaining the EHV (Extra High Voltage) network. DTL has also been
assigned the responsibility of running the State load Dispatch Centre (SLDC) which is
an apex body to ensure integrated operations of power system in Delhi. Delhi Transco
is also committed to promote energy conservation not only in its own establishments but
also in the entire Delhi. The company has done a lot to educate and sensitize the
general public about the need of energy conservation. Transmission loss level has been
reduced from 3.84 per cent in 200-203 to 1.38 per cent in 2009-10, which is one of the
lowest transmission loss level in the country. To ensure adequate and efficient power
supply. DTL has been continuously upgrading its biggest achievement has been its
ability to handle the highest ever peak demand of 4720 MW in July 2010. The total
availability of its transmission system stood 98.78%. The modern technologies are
being implemented in DTL by way of constructing GIS sub stations and laying XLPE
220 KV cable by employing cable link techniques and would be the largest network of
its kind in India.

1.2

DTL NETWORK

It contains the line diagram of the DTL network which connects all the networks of the 5
DISCOMs working in the Delhi region.

1.3

GRID DIAGRAM OF DELHI

2. INTRODUCTION TO SUBSTATION
Electrical power is generated, transmitted in the form of alternating current. The electric
power produced at the power stations is delivered to the consumers through a large network
of transmission & distribution. The transmission network is inevitable long and high power
lines are necessary to maintain a huge block of power source of generation to the load
centers to inter connected Power house for increased reliability of supply greater.
An electrical substation is a part of an electricity generation, transmission and distribution
system where voltage is transformed from high to low or in reverse using transformers. It
also serves as a point of connection between various power system elements such as
transmission lines, transformers, generators and loads. To allow for flexibility in connecting
the elements, circuit breakers are used as high power switches. Electric power may flow
through several substations between generating plant and consumer, and may be changed
in voltage in several steps. There are different kinds of substation such as
Transmission substation, distribution substation, collector substation, switching substation
and some other types of substation. The general functions of a substation may include:

Voltage transformation
Connection point for transmission lines
Switchyard for network configuration
Monitoring point for control center
Protection of power lines and apparatus
Communication with other substations and regional control center

Making an analogy with the human body, the role of substation in the power system to
address the above mentioned issues is pivotal: the substations are the center of the
nervous, immune, musculoskeletal and cardiovascular subsystems of the entire power
system body. The nervous subsystem role of the substation is to allow the central system
to sense the operating states, view status of the equipment, and make assessments of the
system criticality. The immune subsystem role is to develop self-defense means and
sustain self healing strategies. The musculoskeletal subsystem role is to maintain the
system topology, switch the equipment state and restore the power flows. The
cardiovascular subsystem role is to sustain normal power flow and control the
synchronization.
The substation includes the primary equipment (such as circuit breakers, transformers,
instrument transformers, etc.) and the secondary equipment (monitoring, control and
protection devices) which are installed in control house.
In the primary side, a large number of breakers and disconnectors are used in order to allow
for maintenance and repair with a minimum of interruption, which occupy large space. Oilinsulated transformers are used to step-up or step-down the voltage level for purposes
needed. Oil-insulated transformers usually have big size and have potential explosion
problems. In addition, the maintenance is also elaborate and the noise of those transformers
is also a big issue. The breakers also need an insulation media which may be oil, gas, or air.
Conventional current and potential transformers (CTs and VTs) are used to convert the
primary current and voltage to an operation range (0-5A and 115V) for metering and
protection. The CT saturation and open secondary CT circuit safety issue are primarily of
concern in such devices.

All interfaces between primary and secondary equipment are connected by hard-wired
cabling. Different length and types cables are bundled as shown in Fig.1.2, which makes it
labor intensive for future maintenance and modification. In addition, due to the large number
of wires in a highly electromechanically polluted substation switchyard environment, the
wiring may experience significant electromagnetic interference (both conducted and
radiated).

3. 220/66/11 KV GRID SUBSTATION AT SARITA VIHAR:


The 220 KV Grid Substation at Sarita Vihar is a Air Insulated Outdoor Substation.
This is
220/66/11 KV Substation.There are four 220 KV incoming feeders for this substation coming
from:
1. Pragati Powers
2. Power Grid
3. BTPS CKT. No. 1
4. BTPS CKT. No. 2

3.1

SINGLE LINE DIAGRAM

3.2

DESCRIPTION ABOUT SINGLE LINE DIAGRAM

Figure attached shows key diagram of a typical 220/66/11 KV Sarita Vihar Grid Substation.
The diagram of this grid station is explained as under:1) There are Four 220 KV incoming lines as one circuit from Pargati powers, one circuit
from Power Grid and two circuits from BTPS. These four incoming lines are
connected to the double bus bar system through a number of equipments. All these
lines can be loaded simultaneously to share the grid station load. The four lines
arrangement increases the reliability of the system. In case there is a breakdown of
one incoming line, the continuity of supply can be maintained by the other lines.
2) As in the single line diagram the each incoming is connected to the bus bar in a
sequence with a number of equipments. The equipments between the incoming lines
and the line bus bar is connected in a defined sequence as following:
I.

Line lightning Arrestor

II.

Line capacitive voltage transformer (CVT).

III.

Line Isolator

IV.

Line Current Transformer

V.

Line Circuit Breaker

3) The Substation has double bus bar system, one main bus bar and the other spare
bus bar. The incoming can be connected to either bus bar with the help of an
arrangement of circuit breaker and isolators called Bus Coupler. The advantage of
double bus bar system is that if repair is to be carried on one bus bar, the supply
need not to be interrupted as the entire load can be transferred to the other bus.
4) Each line bus bar is connected with Potential Transformer (PT) to measure the bus
bar voltage.
5) There is an arrangement in to step down the incoming 220 KV supply to 66 KV by
two transformer banks with capacity each of 100 MVA. The transformer bank can be
connected to either of the line bus bar through the bus changer Isolator connected
between the two buses. The 100 MVA Transformer is connected to line bus bar
through a number of equipments in as following defined sequence:
I.

Isolator arrangement

II.

Circuit Breaker

III.

Current transformer

IV.

Isolator arrangement

V.

Lightning Arrestor (LA) and then

VI.

100 MVA transformer

6) The 100 MVA transformer steps down the 220 KV incoming to 66 KV and this output
is connected to second bus bar arrangements through a sequenced equipments as
follows:
I.

Lightning Arrestor (LA)

II.

Isolator arrangement

III.

Circuit breaker

IV.

Bus bar isolator

7) The second bus bar arrangement is also a two bus bar system each connected with
Potential Transformer (PT). There is again a bus coupler between the two bus bars
to couple them. Here a Capacitor Bank is provided to increase the incoming voltage if
there is any voltage drop in the incoming. It can enhance the incoming voltage by 3
to 4 KV.
8) From the 66 KV bus bar there are four outgoing circuits transmitting power at 66KV
to:
I.

Mathura road circuit no.1

II.

Mathura road circuit no. 2

III.

DMRC circuit no. 1

IV.

DMRC circuit No. 2

And there are two circuits for 66/11 KV transmission. These two 66 kV incomers from
the 66 KV bus bar is fed to the two Transformers of 20 MVA each.
9) The 20 MVA transformer steps down 66 KV into 11 KV and this 11 KV is supplied to
a number of sub circuits from the 11 kV bus bar. The 11 KV bus bar is also
connected with a capacitor bank of 5 MVAR

PARTS OF SUBSTATION

3.3

The substation can be broadly divided into two parts:

220 kV outdoor yards.


66 kV outdoor yards.
11 kV indoor yards.
Control room.
SCADA room
Battery room.

3.3.1 220 KV Outdoor Yard:


220 KV yard is an outdoor yard where 220 KV incoming is transformed into 66 KV and
connected to the bus bar arrangement on which four 66 KV outgoing feeder two circuit for
DMRC and two circuits for Mathura road. From the 66 KV bus bar two outgoing feeders are
given as incomer to the 66/11 KV yard. There are a number of switching, protection and
measuring equipments connected in the yard. These all equipments are controlled from the
Control Room.

Description about the 220 KV yard:


o

There are four incoming feeders of 220 KV i.e. one from Pragati Powers, one from
Maharani Bagh and two from BTPS.
Two buses named Bus-1 and Bus-2 of 220 KV each run in parallel to which all the
220 KV incoming feeders are connected and also the two 100 MVA transformers are
connected to step down 220 KV to 66 KV.

The incoming 220 KV feeder is first connected to an Oxide Film Lightening arrestor
which protect all the other equipments from Lightening and ground the lightening if
falls on the incoming feeders.

After the Lightening Arrestor a Capacitor voltage transformer is provided which


serves the function of measuring and protection.

A Wave Trap is provided to trap the waves which may be dangerous to the
instruments here in the substation.

Current transformer (CT) is connected to drive the current measuring equipment and
also for protection i.e. for measuring and protection.

Line isolator with Earth switch is provided opening the circuit in no load condition and
earth switch (E/S) is to ground the extra voltage which may be dangerous for any of
the instrument in the substation.

Circuit Breaker (SF6 CB) is connected in line to open or close the circuit in normal
and abnormal condition.

From circuit breaker the incoming feeder is connected to the 220 kv double bus bar
system through isolator arrangements so that the connection can be changed from
one bus to other bus.

The bus is connected with Potential Transformer for measuring the line voltage and
protection purpose.

A bus coupler is provided to couple the two buses for load sharing and line
protection.

The two transformer of 100 MVA, 220/66/11 KV are connected to the 220 KV bus
used to step down the voltage from 220 KV to 66 KV. This output is connected to the
66 KV bus bar.

Circuit breaker (SF-6 CB) is connected in the transformer circuit to open and close
the circuit in no load and full load condition and in normal and abnormal condition.

Horn gap lightening arrestor is provided just before and after the 100 MVA
transformers for protecting the transformer from lightening.

3.3.2
o

66KV OUTDOOR YARD

There are two incomers of 66 KV coming from 220KV yard transformers. There are
two buses of 66 KV in parallel and are connected to the 66 KV incomers through
isolator arrangements for changing the connection from one bus to another.
Here also a bus coupler is provided for coupling the buses for load sharing and
protection.

The bus is connected with three capacitor banks of 20 MVAR for power factor
improvements and for increasing the incoming low voltage by 3 to 4 KV.

Form the 66 KV bus bar six outgoing feeders are connected as one for Mathuara
road circuit no. 1, one for Mathura road circuit no 2 and two for DMRC, and two
circuits are connected to the two 20 MVA transformer.

All the circuits are connected through deferent switching, measuring and protection
equipments like Isolators, CT, Circuit Breakers, Lightening Arrestors.

Two transformers of 20 MVA each of rating 66/11 KV are connected to 66 KV bus by


bus selection Isolator.

Each bus is connected to PT for measurement of voltage in line.

CT is connected at required place for measurement of current and protection of lines.

The SF-6 CB (Circuit Breakers) is aligned in the circuit for tripping whenever any fault
occurs in the circuit.

3.3.3

11 KV INDOOR YARDS (VCB ROOM)

There are two incomers of 11 KV coming from 66 KV yard transformers of rating 20


MVA, 66/11 KV and are connected to two 11KV bus i.e. Bus no.1 and bus no.2.
The 11 KV indoor substation is having vaccum circuit breaker (VCB) in all the
outgoing feeders.
Capacitor banks of 5 MVAR are connected in each phase of the Bus bar to increase
the voltage level if there is any drop in incoming voltage.
There are 12 outgoing feeders connected to 11 KV bus. The feeders are connected
in a sequence as:
On first half bus connected feeders are:
400 KVA Local Transformer.
11 KV O/G Aali Village
11 KV O/G spare
11 KV O/G Saurav Vihar-1
11 KV O/G Indian Oil Corporation
11 KV O/G S/Stn. No. 22 Sarita ViIhar
On second half bus :

11 KV O/G S/Stn. No. 21 Sarita ViIhar


11 KV O/G Sewage Pump
11 KV O/G Jaitpur
11 KV O/G Saurav Vihar- 2
11 KV O/G American Express
11 KV O/G Spare
A bus coupler is provided between the two buses for load sharing and line protection.

o
o
o
o

3.4 EQUIPMENTS USED IN SUBSTATION:S.NO. EQUIP.


1. BUS BAR

CONS.FEATURE/LOCATION
Rigid tubular support on positions
or
Flexible ACSR bus bar
supported from two ends of strain
insulator.

FUNCTION
Receive power from
incoming
and
deliver power to
O/G ckt.

2.

SURGE
ARRESTOR

Connected B/W phase conductor Discharge


O/V
and ground first equip as seen surge to earth and
from incoming O/H line and also protect equipment.
near transformer terminal.

3.

ISOLATOR

Located each side of CB.

4.

EARTH SWITCH Mounted on frame of isolators,


(E.S.)
generally for such I/C each bus
bar.
CURRENT
Protection, measuring decided by
TRANSFORMER protective zone measurement
(C.T.)
requirements.
VOLTAGE
Electro
magnetic
capacitive
TRANSFORMER feeder side of C.B.
(V.T.)

5.

6.

Provide
isolation
from part for MTC.

Discharge voltage
on ckt to earth for
safety.
Step-down current
measurement front
and control.
Step-down current
measurement
protection
and
control.
Depend on rated voltage LV, MV, Switching
during
HV, EHV depend on quenching normal
abnormal
medium SF6 MQ, AB etc.
and S.C. current.

7.

CIRCUIT
BREAKER (C.B.)

8.

SERIES
REACTOR

Oil filled gapped core shielded, 1.


Control
low
usually unswitched.
load period voltage.
2. To compensate
shunt capacitor of
T.L during low load.

9.

SHUNT
CAPACATOR

11. TRANSFORMER

Locate at receiving STN and


DIST, substation.
Banks rated -132KV, 66KV,
400KV, 11KV switched during
heavy load.
1. Capacitor bank located at send
end or receive end of line.
2. Provided with bypass C.B and
protect spare gaps.
Oiled filed 3

12. MV/LT SW GR

Inside swgrbling.

10. SEREIS
CAPACITOR

1. comp. rex power.


2. P.F. improves.
3. VOH contran.

Used for EHV lines


to improve power
transformer.
Setup
/
down
voltage.
AC
power
to
auxiliary stnlty

13. STATION
EARTHING
SYTEM

Earth mat and earth electrode.

14. INSULATORS

Between
the
poles
and
conductors. Disc type shaped.

15. POLES

It is made by joining the heavy


materials with the help of nuts
and bolts of requirement shape
and size wherever necessary.

16. CVT

Consist of two to five windings in


parallel of line.

17. L.A.

Ring type L.A. parallel in line.

18. CONDUCTORS

A.C.R.S. is
necessary.

19. BATTERY
BANKS

Located in separate room near to To supply D.C. for


control room.
controlling
protection system
and communication
equipments.

20. CONTROL
PANEL

Associate with protection relays To


control
locate in big hall.
equipment
substations.

4.
4.1

used

wherever

For
safe
touch
potential
Equipment body
earth.

discharging
current from SA
O/H shielding and
E.S.
Does not allow the
current to pass
through it.
To
provide
necessary height to
conductor
from
which current is
flowing.
CVT are used for
line
voltmeters,
synchronoscope,
protective
relays,
tariff meter etc.
To drop the sky
lightening effect.
Transmission
current form one
place to another.

DESCRIPTION OF SUBSTATION EQUIPMENTS


TRANSMISSION LINES

all
of

In this category the EHV lines viz. extra high voltage lines of 400kv, 220kv, 132kv, and
66kv are considered. These high voltages are transmitted from one sub-station to other
sub-station through various types of conductors.
For 400 KV line: Taran, Tulla and Marculla conductor.
For 220 KV line: Zebra conductor is used composite of Aluminum strands and steel
wires.
For 66kv, 33kv lines: Panther conductors is used composite of Aluminum strands and
steel wires.
The materials used in these conductors is generally Aluminum conductor steel reinforced
(ASCSR).

4.2

BUS-BAR

It is a conductor to which a no. of circuit is connected. In 220kv Najafgarh there are two busbars running parallel to each other, one is main& other is auxiliary bus.
The purpose of using two buses is only for stand by, in each of failure of one bus we can
keep the supply continue with help of other bus using isolators.
According to bus voltage the material is used. T he most commonly used material is Al, Cu.
But Al. Is used because of its property & feature and also it is cheap.

Figure Typical representations of bus bars

PROPERTIES OF MATERIALS USED IN BUS BAR ARE AS FOLLOWS:-

PROPERTIES

COPPER

Electrical resistively at 20 deg 0.017241

ALUMINIUM
0.0288

C
Temp coeff. of resistivity

0.00411

0.00403

Softening temperature

200

180

Thermal conductivity

0.923

0.503

Melting point

1083

657

When a number of lines operating at the same voltage have to be directly connected
electrically bus-bar are used as the common electrical component. Bus-bar are copper or
aluminium bars and operate at constant voltage. The incoming and outgoing lines in a substation are connected to the bus-bars. The most commonly used bus-bar arrangements in
sub-station are:
I.
Single bus-bar arrangement.
II.
Single bus-bar system with sectionalisation.
III.
Double bus-bar arrangement
I.
SINGLE BUS-BAR SYSTEM: It consists of a single bus-bar and all the incoming and outgoing lines are connected to it.
The disadvantage of this type of system is that if repair is to be done on the bus-bar or a
fault occurs on the bus. There is a complete interruption of the supply. This arrangement is
not used for voltages exceeding 33KV.

II.

SINGLE BUS-BAR SYSTEM WITH SECTIONALISATION : -

In this arrangement the single bus-bar is divided in to sections and load is equally distributed
on all the sections. Any two sections of the bus bar connected by a circuit breakers and
isolators. It has two principle advantages. Firstly, if a fault occurs on any section of the bus
that section can be isolated with out affecting the supply from other sections. Secondly,
repairs and maintenance of any section of the bus bar can be carried out by de-energizing
that section only, eliminating the possibility of complete shutdown. This arrangement is used
for voltage upto 33KV.

III.

DOUBLE BUS-BARS SYSTEM: -

This system consists of two bus bars, a main bus bar and a spare bus bar. Each bus bar
has the capacity to take up the entire substation load. The incoming and out going lines can
be connected to either bus bar with help of bus bar coupler which consist of a circuit breaker
and isolators. Ordinarily, the incoming and outgoing lines remain connected to the main bus
bar of fault occurring on it, the continuity of supply to the circuit can be maintained by
transferring it to spare bus bar.

4.3

ISOLATORS

An isolator is a disconnecting switch is used upon same given part circuit after circuit
breaker. Thus isolators surge only has preventing the voltage from being applied to same
given section of bus.
These are essentially off load devices although they are capable of dealing with small
charging currents of bus-bars and connections. The design of isolators is closely related to
the design of substations. Isolator design is considered in the following aspects:
o Space Factor
o Insulation Security
o Standardization
o Ease of Maintenance
o Cost

It is required in substation to disconnect a part of the system for general maintenance and
repairs. This is accomplished by isolators. An isolator is essentially a knife switch and is
designed to open a circuit under no load. In other words, isolator switches are operated only
when the lines in which they are connected carry no current. Isolators used in power system
are generally 3 pole isolator having three identical poles each pole consist of two or three
insulator posts mounted on a fabricate support. The fixed and moving conducting parts are
of copper or aluminium rods. During the opening operation, conducting rods swing apart and
isolation is obtained simultaneously on all 3 poles. The three poles are mechanically
interlocked which operate together by operating a common operating mechanism which may
be:
1. Electric motor mechanism.
2. Pneumatic mechanism.

ISOLATOR WITH EARTH SWITCH: The earth switch is connected between the line conductor and earth. Normally, it is opened
when the line is disconnected. The earth switch is closed so that the voltage trapped in line
is discharge to earth. There some voltage lines due to changing current. This voltage is
significant in high voltage system. Before, proceeding with the maintenance work. This
voltage is discharge to earth by closing the earth switch. Normally earth switches are
maintained on the frame of isolator.

4.4 TRANSFORMER
4.4.1

INTRODUCTION:

A transformer is a static device by means of which electric energy from one electrical
circuit to another is transferred through the medium of magnetic field and without change
in the frequency.
A high voltage is desirable for transmitting large powers in order to decrease the IR
losses and reduce the amount of conductor material. A very much lower voltage, on the
other hand s required for distribution , for various reasons connected with safety and
convenience the transformer make this easily and economically possible.
4.4.2

POWER TRANSFORMERS

Power transformer is the main and major requirement of a sub-station to step down the
supply voltage. The rating of a transformer is taken according to the load requirement.

4.4.3

Parts of power transformer:

i.
ii.

Transformer core
Windings

iii.

Tank

iv.

Conservator

v.

Breather

vi.

Bushing

vii.

Air Cell

viii.

Tap Changer and O.L.T.C.

ix.

Cooling Equipments

i.

CORE: - It not only supports the winding also provides the low
reluctance path for the magnetic circuit. It is made up of cooled rolled grain oriented
(C.R.G.O.) alloy. Steel is in the form of lamination on that the iron losses could be
avoided.

ii.

WINDING: - Windings are arranged in concentric formation


with lower voltage winding next to core. Tertiary winding is placed next to the core over
L.V. winding H.V. main winding are placed.
Various types of windings are used for coils these are as follows:a. Low voltage winding - Spiral or helical
b. High voltage winding - Partially inverted disc / layer winding.
c. Tertiary winding

- Spiral / Helical / Disc

d. Tapping winding - Inter wound spiral or helical paper covered insulated copper
strips or continuously cable are used for making winding.
iii.

TANK: - They are constructed from welded sheet steel, and


larger ones from plain boiler plates. The lids may be of cast iron, or waterproof gasket
being used at the joints. The fitting includes thermometer pockets, drain cock, rollers or
wheels for moving transformer position, eye bolts for lifting, conservators and breathers,
cooling tubes are welded in, but separate radiators are welded and afterwards bolted. On
the outside is applied with anti corrosive primer paint and final of synthetic enamel.

iv.

CONSERVATOR: - As the temp. Of oil increases or decreases


there is continuous rise and fall in volume. For this an expansion vessel (conservator) is
to transformer tank having the capacity of oil level equal to 75% of total oil.
o Conservator is provided to tank core of the expansion and contraction of oil, which
takes place during normal operation of the transformer.
o Wherever specified flexible separators or oil cell if provided in the conservator can
prevent direct contact of air with the transformer oil.
o A smaller oil expansion vassal is provided for the on load tapchanger.
o Magnetic oil level gauge is fitted on the main conservator which can give alarm / trip
in the event of the oil falling below the pre-set level due to any reason.

v.

BRAETHER:

Both transformer oil and


celluloses paper are highly
hygroscopic .Paper being
more
hygroscopic
than
mineral oil .The moisture, if
not excluded from oil surface
in conservator, this will find its
way
finally
into
paper
insulation
and
causes
reduction insulation strength
of transformer to minimize this
the conservator is allowed to
breath only through silica gel
colomin ,which absorb the
moisture in air before it enters
the conservator air surface
vi.
BUSHING: Up to a voltage of 33kv, ordinary
porcelain insulators can be used.
Above this voltage the of conductor or
oil filled terminal bushing, or a
combination of two has to be
considered .Of course, any type of
conductors can be effectively insulated
by air provided that it is at a sufficient
Distance from other conducting bodies
and sufficiently to prevent corona
phenomena.
The high voltage connections pass
from the winding to terminal bushing.
Thermal bushings up to 36kv class,
3150 Ampere are normally of plain
Porcelain and Oil communicating
type .Higher current rated bushings
and bushings of 52kv class and above
will be of oil impregnated paper
condenser type. The oil inside the condenser bushings and will not be communicating
with the oil inside the transformer oil level gauge is provided on the expansion chamber
of the condenser bushings.
Oil in the condenser bushing is hermetically selected and it should not be disturbed in
normal operation. Oil level and oil leakage may be checked regularly.

vii.

AIR CELL: -

It is a flexible rubber bag placed inside the conservator and floats on the oil surface. Air
cell inflates or deflates surface of the air cell and the inner cell of air cell is provided with
ozone resistant .The dry air is sucked and do not come in contact with oil, this eliminates
the possibility of contamination for oil filling.

viii.

TAP
CHANGER.

Tap changer are of two types:a) On-load Tap changer.


b) Off-load Tap changer.

ON LOAD TAP CHANGER: As the name implies it sets a tap for


adjusting the secondary voltage in the
condition of on load. It is generally
connected to the primary side due to
current. The tap is connected to the diverter switch of the tap changer. It may be manually
operated or motor drive unit is initiated by a push button or relay. The diverter switch diverts
the current. The break in the current prevented by transmission resistance tap changer.
On load tap changer is the device for changing the tapping connections of a winding, whilst
the transformer is connected is on load
When the transformer is connected to a system it is some time necessary to vary the voltage
on the secondary side to meet the load demands, as such transformer tap changer must be
capable to varying the turn ratio without interruption of supply. On a double wound
transformer the best position to place the tapping is at the neutral end of high voltage
winding .The positioning of the tapping on the lower voltage winding is not applied on
account of high current rating which would result.
The tapping of the windings are brought out through a terminal board to a separate oil filled
compartment, in which the on- load tap changer selector is housed. As the selector must not
break current ,a further separate oil filled compartment is provided to house the diverter
switch which breaks the load current by an interrupted arc forming carbon ,therefore the oil I
the diverter switch compartment must be prevented from missing with the oil in the main
tank.
The tap changer is operated by a motor operated driving mechanism by local or remote
control and a handle is fitted for manual operation in an emergency.
As the changing must take place on load, the contact for the tap changer are so arranged
that before one tapping is left , contact must be made with the next . This could cause a
short circuited no. of turn and large current are prevented by the use of resistor or reactors.
IV.4.4 COOLING EQUIPMENT: -

Transformer is having a single or mixed cooling of ONAN, ONAF, OFAF, and


OFAN by means of radiators, fans, pumps, & heat exchanger etc.
In Power transformer cooling are of following Types:
1. ONAN with 50% efficiency
2. ONAF with 70% efficiency
3. OFAF with 100% efficiency
o
o
o

4.4.5

For ONAN/ONAF cooling, oil flow through the winding and external cooler unit
attached to the tank by themo-Syphonic effect.
For OFAF/ODAF/OFWF cooling, the oil is directed through the winding by oil
pumps provided in the external cooler unit.
External cooler unit /units consists of passed Steel sheet radiators mounted
directly on the tank or separator cooler banks for air cooled transformer and
oil to water heat exchangers for water cooled transformer.

PROTECTIVE DEVICES:

1. Buccholtz relay
2. Pressure relief valve
3. Oil temperature indicator
4. Oil level indicator
5. Winding temperature indicator
6. Dehydrating Breather
7. Earthing Arrangements

Buccholtz
relay

1.

BUCHHOLTZ RELAY: It is used for protection of oil filled transformer from incipient faults below oil level. It is
installed between tank and conservator. In this relay two mercury contacts are provided. The
device comprises of a cast iron housing containing the hinged floats, one in upper part other
in lower part. Each float is filled with the mercury switch; leads of a switch are connected to a
terminal box for tripping.
APPLICATIONS:Double element relays can be used in detecting miner fault in a Transformer
The alarm element will operate, after a specified volume of gas has collected to give an
alarm indicator.

Examples incipient faults are:1. Shorted laminations


2. Broken-down core bolt insulation
3. Bad contacts

4. Over heating of part of winding,

2.

PRESSURE RELIEF VALVE:


In case of major faults in the transformer like short circuit in the winding .The internal P.R.V.
is build up to a very high level which may result in rapture of tank to avoid this P.R.V.
provided.
A device for avoiding high oil pressure build up inside the transformer during fault a condition
is fitted on the top of the tank. The pressure relief device allows rapid release of excessive
pressure that may be generated in the event of a serious fault.
This device is fitted with an alarm trip switch.

3.

OIL TEMPERATURE INDICATOR: It is the distance thermometer operated on principle of liquid expansion. It indicates the top
oil temp. At marshaling box. The connection between the thermometer and the dial indicator
is made by steel capillary tube. The bulb is enclosed in the pocket and the pocket is situated
on transformers hottest oil region. The pocket is to be filled with oil. It has two switches one
for alarm and other for tripping.
ALARM = 95 DEG.
TRIPPING = 110 DEG.

It is consist of a sensor bulb capillary tube and a dial thermometer the sensor bulb is fitted at
the location of hottest oil .That sensor bulb and capillary tube are fitted with evaporation
liquid. The vapor pressure varies with temperature and is transmitted to a burden tube inside
the change in pressure which is proportional to the temperature.

4.

WINDING TEMPERATURE INDICATOR: It also operates on principles of liquid expansion. It indicates the top oil temp. At marshalling
box hot spot temp. Of winding. The winding hot spot of top oil temp. Difference is simulative
by means of CT current fed to the heater coil fitted at top senses the top oil temp. Thus, its
temp. Reading is proportional to the load current and oil temp.
o
o

FANS ON =
PUMP ON =

60 deg C
75 deg C

o ALARM
= 90 deg C
o TRIP
= 100 deg C
Winding temperature relay indicates the winding temperature of the transformer and operates on
the principle of thermal imaging and it is not actual measurement.
Winding temperature indicators consist of sensor bulb placed in oil filled pocket in the
transformer tank top cover. The bulb is connected to the instrument having by means of two
flexible capillary tubes. One capillary tube is connected to the measuring below of the instrument
and the other to compensation below. The measuring system is filled with a liquid which
changes its volume with rising temperature inside the instrument is filled with a heat resistance
which is fed by a current proportionate to the current flowing through the transformer winding.
The instrument is provided with maximum temperature indicator the heating resistance is fed by
current transformer associated to the loaded winding of the transformer .The increase in the
temperature of the resistance is proportionate to that of the winding. The sensor bulb of
instrument is located in the hottest oil of the transformer the winding temperature indicates a
temperature of hottest oil plus the winding temperature rise above hot it .i.e. the hot spot
temperature.

5.

OIL LEVEL INDICATOR :This indication is manufactured for considering Transformer Applications:
1. It can also be used as Content Gauge on other tanks where level of liquid inside the
tank in required to be indicated continuously on a dial.
2. The position of indicator on the conservator can be selected to
3. Suit site condition. Float mechanism passes through the hole in pad.
4. Indicator can be mounted in titled position towards ground (max.300degree) for easy
viewing by fixing mounting pad at desired angle.
5. One mercury switch is provided for low level alarm. The Normally Open switch closes
when oil level drops to 10mm above Empty land i.e. 75mm from bottom of
conservator.
6. Loads from mercury switch are brought into a terminal box positioned at the bottom
of indicator.

6.

DEHYDRATING BREATHER: The conservator or the air cell is connected to the outside atmosphere through the breather
(silica gel) to make sure that the air in the conservator or cell is dry. When silica is saturated
with moisture its color changes to pink. It can be made reusable by heating it at 100 deg C.
for 48 hours.

7.

EARTHING ARRANGEMENTS :a) Core Earthing


Connecting leads from core and end frame are being terminated at the top of the cover, By
connecting them to tank cover, core and frame becomes earthed .Insulation resistance
between the leads from core and end frame or between leads from core and earth point can

be checked by 500 volts megger. Leads from end frame have been brought out for proper
earthing for end frame.
b) Tank to Tank Earthing :
Tank to tank cover earthing is done by connecting copper braid between tank rim and tank
cover with the help of the bolts used to tight tank cover and tank together.
c) Earthing of Tank
For earthing of tank nut-bolts & studs are required to make perfect earthing between pads on
tank and external earthing strip.
4.4.6

Maintenance & Operation

In order to avoid fault and disturbance, it is important that a careful and regular supervision
and control of the transformer and its components is planned and carried out.
The frequency extent supervision and control is dependent on climate and environment and
service condition.

POSSIBLE LEAKAGE
After energizing of the transformer, a certain setting may appear in painting joint.
Rust damage, Touch damage up painting a regular inspection of the external surface
treatment of the reactor should be carried out. Possible rust damage is removed and the
surface treatment restarted to original state by means of primer and finish paints that are
dispatched with the transformer.
THRERMO SYPHON FILTER
Thermo siphon filter is provided on large capacity, oil filled Power Transformer for keeping
the moisture level of insulating oil at a very low level. At the time of initial erection and
commissioning of transformer, most of the moisture present in the oil is removed by not oil
circulation. The moisture absorption of oil is eliminated by direction the our breather in by the
transformer during its operation through silica gel desiccant. Air cell in conservator avoids
direct of oil with air and there by eliminating the chance of moisture absorption.
It is a well known fact that water is released to the oil for the paper insulation due to ageing
process. Thermo siphon filter helps in removing this moisture from oil. When the
Transformer is on load, the thermos phonic action of liquid causes circulation of oil through
the filter. The absorbent filled in the Thermo siphon filter absorb moisture and keep the oil
dry.
4.4.7

SPECIFICATIONS OF TRANSFORMERS

1. 100 MVA, 220/66/11KV power transformer no. 1 & no. 2 (BHEL) make.
1.Types of cooling

ONAN

ONAF

OFAF

2.Rating HV & LV (MVA)

50

70

100

3.Rating TV (MVA)

16.67

23.33

33.33

4.No load voltage HV 220


(kv)

220

220

5.No load voltage LV(kv)

66

66

66

6.Noload voltage

11

11

11

7.Line current HV(Amp)

131.37

183.92

262.74

8.Line current LV (Amp)


at 66kv

437.90

613.07

875.81

9.Line current LV (Amp)


at 33kv

875.81

1226.13

1751.62

TV 875.81

1226.13

1751.62

TV(kv)

10.Line
(Amp)

current

11. Temp. rise oil ( deg


C)

50

50

50

12. Temp. rise winding


(degC)

55

55

55

4.5. INSTRUMENT TRANSFORMER: Transformer used A.C. measurement i.e. voltages current, power and energy in conjunction
with the relevant instrument. Transformer small capacity transformer. There are two types:
1.
Current transformer.
2.
Potential transformer.
3.
Capacitor Voltage transformer.
ADVANTAGES OF INSTRUMENT TRANSFORMER:1.
2.
3.
4.
5.

The size of I.T. is reduced or say moderate because the secondary


Of C.T. is designed for 5A. And of P.T. for 110V.
The replacement of damaged instrument is easy.
Several instruments can be operated from a single I.T.
Low consumption of metering circuit.
Accessibility on H.T. is easy.

Instrument transformer is used to measure AC at generating station, station at transmission


line in conjunction with AC measuring instruments. They are classified according to the use
are referred to as current transformer (CT) & potential transformer (PT).
Functions: 1.
2.

4.5.1

They serve to extent the range of AC measuring instrument.


They serve to isolate the measuring instrument from high Voltage

CURRENT TRANSFORMER: -

High current line can be reduced to low current to measure easily with the help of normal
ammeter. To measure the very high current of the running line with out distributing it, a spilt
core type current transformer is used. It is step up transformer the primary windings consist
of thicker conductor having less number of turns. Some time, only a straight conductor also
serves the purpose of primary winding. The secondary winding is done with thicker
conductor having more number of turns.
The primary winding is connected in series with the line and the M I is connected across the
secondary of the current transformer. it should be clearly understood that the secondary
winding of the current transformer is never opened. It should be always short circuit i.e. the
secondary is open, there is no current in the secondary winding hence, the M.M.F. of
primary will not be opposed and the cares will have high flux which will cause high E.M.F.
Induced or the primary and secondary winding. This E.M.F. Is dangerous and may give
sever shock.
The secondary of the current transformer should be earthed to avoid the danger of shock to
the operator.
The current transformer is kept in category of instrument transformers. The CTs are used to
reduce / stepping down A.C. from high value to lower value for measurement / protection /
control.
A 'CT' has following essential parts: 1. Magnetic core made up of continuously wound strip nickel iron alloy of CRGO
material.
2. Winding having several turns wound on the insulated core.
3. A bar primary passing through the winding of core and terminal.
4. Insulated porcelain at primary insulator.
5. Synthetic region or oil insulation.

PROPERTIES OF CT:
o
o
o

o
o

o
o
o

The CT measures the current.


The current transformer is used with primary winding.
Connected in series with the line carrying the current to be measured and therefore
primary current is dependent upon load connected in the system.
The primary winding of a very few turns, and therefore there is no appreciation drop
across it.
The secondary winding has large no. Of turns, exact no. Being determined by the
turn ratio.
Ammeter of wattmeter current coil is connected directly across secondary winding
terminals.
Thus CT operates at secondary terminal near by being short-circuited.
One of the terminals of secondary winding is earth in order to protect instrument
and personal in the vicinity in event of insulation breakdown.

WORKING: - The CT has three coils different purposes.


a) Measurement: - The secondary given 5A / 1A current which operates the ammeter to
note the current reading
b) Protection: - The 5A / 1A current is sent to the relay and if the current exceeds this limit
then the relay operates and sends signal to the C.B. which then operates.
c) Differential
d) Spare
SPECIFICATION OF CURRENT TRANSFORMERS: Specification of 220 kV side CT
a) Standard
- IS 2705
b) Highest system voltage (kv) - 245

c)
d)
e)
f)

Insulation level (kv)


- 460/1050
Frequency
- 50 Hz
Rated primary current - 600A
ST current KA/ sec
- 27 /1

Terminals
1s1-1s2
1s1-1s2
2s1-2s2
2s1-2s2
3s1-3s2
3s1-3s2
4s1-4s2
4s1-4s2

Ratio Amp.
300/1
600/1

Rating class
5P20

VA
60

Kvp / Amp
1200V/0.04A

300/1
600/1
300/1
600/1
600/1

5P20

60

1200V/0.04A

5P20

60

1200V/0.04A

.5

60

....................

4.5.2 POTENTIAL TRANSFORMER: Similar to CT it is another type of instrument transformer. It is also known as CVT (capacitor
voltage transformer). It is used for measurement and protection. Potential transformer is
used to operate voltmeter, the potential coil of wattmeter and relay from high voltage line.
The primary oftransformer4 is connected across the line carrying the voltage to be measured
and the voltage circuit is connected across the secondary winding to measure high voltage
line.
The transformer is used to measure the high voltage known as potential transformer. The
primary of the potential transformer is having more number of turns of fine wire and
secondary is having less number of turns. The potential transformer is step down
transformer the P.W is connected across the line and S.W across the meter to measure the
line voltage. The P.W when connected to line carry some current, which produces the
magnetic flux. The S.W is linked with this flux causing the induction some voltage (generally
110V in case P.T.) this voltage defects the voltmeter or the secondary of the P.T.
The scale is directly calibrated to obtain the actual voltage. The secondary of the P.T. is
always connected to earth.
They may be of one phase or three phase. Electromagnetic P.T. In which primary and
secondary are wound on magnetic core in usual transformers.

SOME TERMS RELATED TO P.T


(a) Rated Voltage: The voltage of the P.T., which it can withstand.
(b) Rated Transformer Ratio: The ratio of rated primary voltage to the rated
secondary voltage.
(c) Rated secondary voltage: e.g. 130/ root (3) = 63.3 VAR.

4.5.3

Capacitor Voltage Transformer:-

A capacitor voltage transformer (CVT) is a transformer used in power systems to step-down


extra high voltage signals and provide low voltage signals either for measurement or to
operate a protective relay. In its most basic form the device consists of three parts: two
capacitors across which the voltage signal is split, an inductive element used to tune the
device to the supply frequency and a transformer used to isolate and further step-down the
voltage for the instrumentation or protective relay. The device has at least four terminals, a
high-voltage terminal for connection to the high voltage signal, a ground terminal and at least
one set of secondary terminals for connection to the instrumentation or protective relay.
CVTs are typically single-phase devices used for measuring voltages in excess of one
hundred kilovolts where the use of voltage transformers would be uneconomical. In practice
the first capacitor, C1, is often replaced by a stack of capacitors connected in series. This
results in a large voltage drop across the stack of capacitors that replaced the first capacitor
and a comparatively small voltage drop across the second capacitor, C 2, and hence the
secondary terminals.
CVT 220 kV rating
Type: WP-245 V
Operating voltage:

220/3 kV

Voltage factor:

1.5 V for 30 sec.

Test voltage:

460 kV

Test impedance

1050 kv peak

Ellec cap:

440010% PF of 50 H 5%

Nominal intermediate voltage

20/3 kv

Spark over voltage:

36 kv

Voltage divider ratio

220000/3 /20000/3

Total thermal burden:

1000 VA

Temperature categ:
Total weight:

4.6.

10 to 55C
900 Kg.

CIRCUIT BREAKER

A circuit breaker is equipment which can be open are closed a circuit under a normal as well
as fault condition. It is so desired that it can be operated manually or by remote control under
normal condition and automatically under fault condition. For the latter operation a relay is
used in the circuit breaker. A circuit breaker essentially consists of fixed and moving
contacts, called electrodes. Under normal operating condition, these contacts remain closed
and will not open automatically until and unless the system becomes fault. The contacts can
be opened manually or by remote control whenever desired. When a fault occurs on any part
of the system, the trip coils of the circuit breaker get energized and moving contacts are
pulled apart by some mechanism, thus opening the circuit. the basic construction of any
circuit breaker requires the separation of the contacts in any insulating fluid, when serves
two function:

It extinguishes the arc drawn between the contacts when the circuit breaker open.

It provides adequate insulation between the contacts and from each contacts to
earth. Many insulating fluids are used for arc extinction and the fluid chosen depend
upon the rating and type of the circuit breaker.

The insulating fluids commonly used are :Air at atmospheric pressure

Compressed air

Ultra high vacuum

Oil which produces hydrogen for arc extinction

Sulphur hexafluoride (SF6)

4.6.1

Figure 7.2 Circuit breaker arrangements


TYPES OF CIRCUIT BREAKER

I.
SULPHUR HEXAFLURIOD (SF6 )
In such circuit breaker sulphur hexafluoride gas is used as arc quenching medium. The SF 6
is electronegative gas and has a strong tendency to absorb free electrons. The contacts of
the breaker an opened in a high pressure flow of SF 6 gas and an arc is struck between
them. The conducting free electrons in arc are rapidly captured by the gas to form relatively
immobile negative ions . This loss of conduction electrons in the arc quickly builds up
enough insulating strength.The SF6 circuit breaker has been found to be very effect able for
high power and high voltage services.SF6 has excellent insulating strength because of its
affinity for electrons i.e whenever a free electrons collides with the neutral gas molecules to
form negatives ions, the electrons is absorbed by the neutral gas molecules may occur in
two ways
SF6 + e -> SF6
SF6 + e -> SF5 + F

The negative ion formed are relatively heavier as compared to free electrons and therefore
under a given electric field the ions do not attain sufficient energy to lead cumulative
ionization in the gas.
WORKING
In closed position of the breaker, the contacts remains surrounded by SF6 gas at a pressure
of about 6KG/sq.cm. When the breaker operates, the moving contact is pulled apart and arc
is structure between the contacts. The movement of the moving contacts is synchronized
with the opening of the valve, which permits SF6 gas at 15Kg/sq.cm pressures from the
reservoir to the arc interruption chamber. The high- pressure flow of SF6 rapidly absorbs the
electrons in the arc path to form immobile negative ions, which ineffective as charge carriers.
Thus, medium between the contacts quickly built up high dielectric strength and cause the
extinction of the arc, after the breaker operates.

II.

VACCUM C IRCUIT BREAKER:

In such breakers (degree f vacuum being from 10 -7 to 10-5 tore) is used as arc quenching
medium. Since vacuum offers the high insulating strength, it has superior quenching
properties then any other medium e.g when contacts of the breaker are opened n vacuum ,
the interruption occurred first current zero with dielectric strength between the contacts
building at a rate of 1000 th of times higher then that obtained with other circuit breaker .
Thus a vacuum arc is different from the general class of low & high pressure arc . In the
vacuum arc the neutral atoms, ions and electrons do not come from the medium in which the
arc is drawn but they are obtained from the electrodes themselves by evaporating its surface
material , because of the large mean free path for the electrons , the dielectric strength of
the vacuum is a 1000 times more than when
the gas is used as the interrupting medium .
III.

MINIMUM OIL CIRCUIT BREAKER


(MOCB)
One of the important development in the
design of oil circuit breaker has been to
reduce the amount of oil needed. The other
advantages are reduction in tank size ,
reduction in total weight and reduction in
cost . It used minimum amount of oil and is
only used for arc extinguishing the current
conducting parts are insulated by porcelain
or organic insulated material. Low oil circuit
breaker employees solid materials for
insulations purpose and uses a small qty.of
oil which is just sufficient for arc
extinguishing .By using suitable arc control devices, the arc extinguishing can be further
facilitated in low circuit breaker. venting.
IV.
Air blast circuit breaker
Fast operations, suitability for repeated operation, auto reclosure, unit type multi break
constructions, simple assembly, modest maintenance are some of the main features of air
blast circuit breakers. A compressors plant necessary to maintain high air pressure in the air
receiver. The air blast circuit breakers are especially suitable for railways and arc furnaces,
where the breaker operates repeatedly. Air blast circuit breakers is used for interconnected

lines and important lines where rapid operation is desired.

Figure 7.4 Air blast circuit breaker


High pressure air at a pressure between 20 to 30 kg/ cm2 stored in the air reservoir. Air is
taken from the compressed air system. Three hollow insulator columns are mounted on the
reservoir with valves at their basis. The double arc extinguished chambers are mounted on
the top of the hollow insulator chambers. The current carrying parts connect the three arc
extinction chambers to each other in series and the pole to the neighboring equipment.
Since there exists a very high voltage between the conductor and the air reservoir, the entire
arc extinction chambers assembly is mounted on insulators.
Specifications of SF6 Circuit Breaker
1. Gas circuit breaker: high voltage side (220KV)
Type 220-SFM-40A
Voltage rating: 220kv
Rated lightening impulse withstand voltage: 1050 kVp
Rated short circuit breaker current: 40 kA
Rated operating pressure: 16.5 kg/cm2-g
Rated Gas pressure: 6 kg/cm2-g
First pole to clear factor 1.3
Rated duration of short circuit current is 40 kA for 30 sec.
Rated ling charging breaker breaking current 125 Amp
Rated voltage 245 kV
Rated frequency 50 Hz
Rated normal current 2500 Amp
Rated closing voltage: 220 V dc
Rated opening voltage 220 V dc
Total Weight with Gas: 3900 Kg.
2. Gas circuit breaker: low voltage side (66 KV)
Type 70-SFM-32B
Voltage rating: 72.5 kv
Rated lightening impulse withstand voltage: 350 kVp

Rated short circuit breaker current: 31.5 kA


Rated operating pressure: 16.5 kg/cm2-g
Rated Gas pressure: 5 kg/cm2-g
First pole to clear factor 1.3
Rated duration of short circuit current is 31.5 kA for 3 sec.
Rated ling charging breaker breaking current 125 Amp
Rated voltage 72.5 kV
Rated frequency 50 Hz
Rated normal current 2500 Amp
Rated closing voltage: 220 V dc
Rated opening voltage 220 V dc
4.7.
CAPACITOR BANK
The capacitor bank provides reactive power at grid
substation. The voltage regulation problem frequently
reduces so of circulation of reactive power.
Unlike the active power, reactive power can be
produced, transmitted and absorbed of course with in
the certain limit, which have always to be workout. At
any point in the system shunt capacitor are commonly
used in all voltage and in all size.
Capacitors are used to control the level of the voltage
supplied to the customer by reducing or eliminating the
voltage drop in the system caused by inductive
reactive loads.
An AC system cannot function with the highest transmission capability at minimum cost and
at the highest efficiency unless the reactive compensation is carefully applied. The capacitor
i.e. VAR is installed in receiving substation, load substation for fast, staples control of
reactive power compensation of voltage control .
Capacitor banks are installed following purposes:
o
o
o
o
o
o

To improve the power factor of the system & there by regulating the system voltage
Reactive power compensation
To reduce the loss
Increased voltage level at the load
Reduced system losses
Increase power factor of loading current

Fig.13.1-Capacitor Bank
Benefits of using the capacitor bank are many and the reason is that capacitor reduces the
reactive current flowing in the whole system from generator to the point of installation.
The insulator for the overhead lines provides insulation to the power

4.8
INSULATOR
The insulators are connected to the cross arm of supporting structure and the power
conductor passes through the clamp of the insulator. The insulators provide necessary
insulation between line conductors and supports and thus prevent any leakage current from
conductors to earth. In general, the insulator should have the following desirable properties:
High mechanical strength in order to withstand conductor load, wind load etc.

High electrical resistance of insulator material in order to avoid leakage


currents to earth.

High relative permittivity of insulator material in order that dielectric strength is


high.

High ratio of puncture strength to flash over.

These insulators are generally made of glazed porcelain or toughened glass. Poly come type
insulator [solid core] are also being supplied in place of hast insulators if available
indigenously. The design of the insulator is such that the stress due to contraction and
expansion in any part of the insulator does not lead to any defect. It is desirable not to allow
porcelain to come in direct contact with a hard metal screw thread.
TYPE OF INSULATORS:
1. Pin type
2. Suspension type
3. Strain insulator

PIN TYPE:
Pin type insulator consist of a single or multiple shells adapted to be mounted on a spindle to
be fixed to the cross arm of the supporting structure. When the upper most shell is wet due
to rain the lower shells are dry and provide sufficient leakage resistance these are used for
transmission and distribution of electric power at voltage up to voltage 33 KV. Beyond
operating voltage of 33 KV the pin type insulators thus become too bulky and hence
uneconomical.
SUSPENSION TYPE:
Suspension type insulators consist of a number of porcelain disc connected in series by
metal links in the form of a string. Its working voltage is 66KV. Each disc is designed for low
voltage for 11KV.

Fig.-Suspension type insulator


STRAIN INSULATOR:
The strain insulators are exactly identical in shape with the suspension insulators. These
strings are placed in the horizontal plane rather than the vertical plane. These insulators are

used where line is subjected to greater tension. For low voltage lines (< 11KV) shackle
insulator are used as strain insulator.

Fig.4.3-Strain type insulator


Post type insulator
Post insulators have metal bolt down base as
opposed to threads. Many early multipart lines
are spotted with line post insulators as
replacements. Post insulators are also used in
substations to insulate high voltage switching
gear and transformers. There is no hobby
numbering system for post insulators yet. Most
insulators are used for bus bars. Post insulators
consist of porcelain body, cast iron cap and
flanged cast iron base. The hole in the cap is the threaded so that the bus bars can be
directly to cap.

4.9
Wave Trap:
Line trap also is known as Wave trap. What it does is trapping the high frequency
communication signals sent on the line from the remote substation and diverting them to the
telecom/teleprotection panel in the substation control room (through coupling capacitor and
LMU).
It is a device used to exclude unwanted frequency components, such as noise or other
interference, of a wave. Wave trap is an instrument using for tripping of the wave. The
function of this trap is that it traps the unwanted waves. Its function is of trapping wave. Its
shape is like a drum. It is connected to the main incoming feeder so that it can trap the
waves which may be dangerous to the instruments here in the substation.
This is relevant in Power Line Carrier Communication (PLCC) systems for communication
among various substations without dependence on the telecom company network. The
signals are primarily teleportation signals and in addition, voice and data communication
signals.
The Line trap OFFERS HIGH IMPEDANCE TO THE HIGH FREQUENCY COMMUNICATION SIGNALS thus
obstructs the flow of these signals in to the substation bus bars. If there were not to be there,
then signal loss is more and communication will be ineffective/probably impossible.

Fig. -Wave Trap

5.

PROTECTION SYSTEM

INTRODUCTION: There are different schemes adopted for the protection of various equipment of power
system against Over Voltage and heavy short circuit current.
CAUSES OF OVER-VOLTAGE: The over-voltage may occur in the power system due to.
1. Internal causes
2. External causes
INTERNAL CAUSES: A.
B.
C.
D.

Switching surges
Arcing grounds
Insulation failure
Resonance

EXTERNAL CAUSES OF OVER-VOLTAGES: LIGHTNING: -

An electrical discharge in our between clouds, between the separate charge in the same
cloud or b/w cloud and earth is caused lightning.
There are two main ways in which lightning stoke can effect a line i.e.
1. Direct stroke
2. Indirect stroke

5.1

PROTECTION AGAINST OVER VOLTAGES

It has been seen that the internal causes in increase the voltages of the power system really
double to that of the normal operating voltage where as the external causes may increase
the voltage several times (of the order of 200 MV) to that of normal operating voltage of
twice the value of normal operating voltage of the system for a reasonable length of time and
to provide protective devices for the voltage having value more than this.
Those devices are known as over voltage protection devices. The common device used for
the protection of power system against overvoltages is:
1. Ground wires
2. Earth screens
3. Lightning arrestors of surge diverters

5.1.1

GROUND-WIRE: -

To protect the transmission lines against direct lightning stroke, one of more bare conductors
are run at the top f the tower known as ground wires. These wires are earthed at regular
intervals preferably at every tower. The area of cross section of ground wires is based upon
their mechanical strength rather than electrical conductivity. These should have high
mechanical strength and be-non-corrosive.
The ground wires not only take the burnt of the direct strokes but also provide a certain
amount of electrostatic screening. This reduces the voltage induce in the line conductors by
the discharge of a neighboring cloud. They also provide additional protective effect in
attenuating any travelling wave that may be set up in the lines, by acting as short circuited
secondary of the line conductors.
The main objections to the ground wires are; the additional cost and the possibility of the
wire cracking and falling on the line conductors causing a direct short-circuit.

5.1.2

EARTHING SCREEN: -

A network of copper conductors earthed at various points, and placed over and above all the
substation is known as earthing screen. It provides an electrostatic shield against external
fields and protects the system. It protects the system from direct lightning strokes but does
not provide any protection against high voltage waves which may still reach at the terminals
of equipment.

5.1.3

LIGHTNING ARESSTOR OR SURGE DIVERTER: -

The lightning arrestor or surge diverters is a device which an easy conducting path or
relatively low impedance path for the flow of current which the system voltage increases
more than the designed value and against it is original properties of an insulator at normal
voltage .
A lightning arrestor voltages as on insulator at normal voltages but provides as easy path for
the flow of current at abnormal voltages. A good lightning arrestors or surge diverter should
have the following.
(a) It should not take any current on the working voltage of the system in other words it
should act as an insulator at normal working voltages.
(b) It must provide a conducting path as and when abnormal transient voltages occur on
the system.
(c) It must be capable to carry the discharge current with out getting damage it self
under abnormal conditions.

TYPES OF LIGHNING ARRESTORS: There are many types of lightning arrestors which are used to protect the power system
against over-voltage some of them are:
1. Rod gap arrestor
2. Horn gap arrestor
3. multi gap arrestor
4. Thyrite arrestor
5. Electrolytic arrestor
6. Oxide film arrestor
7. Expulsion type arrestor
8. Value type arrestor

Lightning arresters are protective devices for limiting surge voltages due to lightning strikes
or equipment fault or other events, to prevent damage to equipment and disruption of
service. Also
called
surge
arresters.
Lightning arresters are installed
on many different pieces of
equipment such as power poles
and towers, power transformers,
circuit breakers, bus structures,
and steel superstructures in
substations.

VARIOUS OTHER KINDS OF


PROTECTION

5.2

DIRECTION OVER-CURRENT PROTECTION: -

The over-current protection can be given directional feature by adding directional overcurrent protection responds to over currents for a particular directional flow if power flow is in
the opposite directions the directional over current protection remains un-operative.
Directional over current protection comprises over current relay and power directional relay
in a single relay casing the power directional relay does not measure the power but is
arranged to respond to the directional operation of relay is used where the selectivity can be
achieved by directional relaying. The directional relay recognizes the direction in which fault
occurs relative to the location of the relay. It is set such that it actuates for fault occurring in

one directional only. It does not act for faults occurring in the other direction another
interesting example of directional protection are that of reverse power protection of
generator.

5.3

DIRECTIONAL EARTH-FAULT PROTECTION : -

In the directional over-current protection coil of relay is actuated from secondary current of
line CT. where as the current coil by residual current.
In directional over-current relays. The voltage coil is actuated by secondary of line VT. In
directional earth-fault relay, the voltage coil is actuated by the residual voltage. Direction
earth fault relay sense the direction which earth fault occurs with respect to the relay
location; and it operates for fault in a particular direction. The directional earth fault relay
(single phase unit) has two coils. The polarizing quantity is obtained either from residual
current (IRS = Ia + Ib+ Ic) or
Residual voltage (VRS = Vae + Vbe + Vce), where Vae Vbe Vce are phase voltage.
One of the coils is connected in residual current circuits. This coil gets current during earth
faults. The other coil gets residual voltage. The coil connected in potential transform
secondary circuit gives a polarizing field.

5.4

PRIMARY AND BACK UP PROTECTION: -

There are times when the primary protection may fail. This could be due to failure of CT/VT
or relays, pr failure of circuit breaker one of the possible causes of the circuit breaker failure
is the failure of the trip-battery due to inadequate maintenance.

5.5 RELAYS
A relay is a low-powered device used to activate a high-powered device. Relays are used to
trigger circuit breakers and other switches in substations and transmission and distribution
systems.
The electrical quantities which may change under fault condition are:
1. Voltage

2. Current
3. Frequency
4. Phase angle
Through the change in one or more of these quantities, the fault signals there
presence type and location to the protective relay is obtained. Moving detect the
fault, the relay operates close the trip circuit of the breaker. This result in the opening
of the breaker and disconnect the fault section.

TYPES OF RELAY
Basically relay are based on two principal:o
o
But

Electromagnetic attraction
Electromagnetic induction
different

relay

based

on

this

are

used

in

this

S/S

such

as:

Differential
relay

RES E/F +O/L


Protection relay

O/F protection +FFR


Group A trip relay

Breaker failure
relay
O/C protection
relays

CB trouble relay
Group B trip relay

DR earth switch
relay

1. Over Current Relay: - It is used in over current scheme. Over current protection is the
name given to protected relay scheme devised to rise in current in a protected circuit.
2. Differential Relay: - A differential relay is one that operates when the vector difference
of two or more quantities exceeds pre determined value.
3. Oil Surged Relay
4. Buccholtz relay
5. Gas operated relay
RELAYS OF 100 MVA AND 20 MVA TRANSFORMERS
o
o
o
o

OLTC Buccholtz relay


Main Buccholtz relay
Differential relay
Restrict earth fault relay

o Over current relay


FEEDER RELAYS:
o
o
o
o
o
o
o

Out of step blocking relay


Directional current relay
Directional earth fault relay
Fuse failure relay
Auxiliary relay type
Tripping relay
Instantaneous Earth Fault relay

Protection Relays
1. DIFFERENTIAL RELAY: -

A differential relay is the relay that operates when the vector difference of two or more
similar electrical quantities exceeds a pre determined amount. Almost every type of relay
when connected in a certain way can be made to operate as differential relay, mast of the
differential relays are of the current differential type. Fig.1 shows the over current relay
used as differential relay and operates when the currents at two points of the system are
unusual. For example of the current on at two ends of alternator, windings are unusual.
There is either a fault to earth or b/w phases. When there is continuous over current and the
current over current and the current on both sides are equal, than the relay will not sense the
fault. It will sense fault only if there is a difference of current on two sides of circuit.

A very important disadvantage in simple balance system is due to inequalities of current


transformers. Hence the differential CTs should not be erroneous or should be identical.
This disadvantage can also be overcome by using a based beam relay.
Fig : Differential Relay
2. DISTANCE RELAYS: Distance or impedance relays should have the least position spread in value of operating
impedance or reactance. Any deviation of Z from the impedance setting canal bring about
variation in the operation zone length of the relay it effects the reliability of the relay
operation and venders the co-ordination of the protection on then adjoining circuit much
more difficult. Hence for this reason the fictitious operating impedance should not exceed
impedance setting.

3. DIRECTIONAL

(OVER

CURRENT

OR

EARTH

FAULT

RELAY

:-

4.
The non directional relay can operate for fault flow in either direction. In order to achieve
operation for the fault flowing in a specific direction, it is necessary to add a directional
element to the non directional element. Such a relay which responds to fault flow in a
particular directional is called a directional relay

5. IDMT

RELAY :

The IDMT relay work on the induction principle, where an aluminum or copper disc rotates
between the poles of electromagnet and damping magnet. The fluxes induce eddy current in
the disc which interact and produce rotational torque. The disc rotates to a point where it
operates a pair of contact that breaks the circuit and removes the fault condition.

6. RESTRICTED

EARTH FAULT PROTECTION RELAY :

The REF protection method is a type of "unit protection" applied to transformers or


generators and is more sensitive than the method known as differential protection.
An REF relay works by measuring the actual current flowing to earth from the frame of the

unit. If that current exceeds a certain preset maximum value of milliamps (mA) then the relay
will
trip
to
cut
off
the
power
supply
to
the
unit.
Differential protection can also be used to protect the windings of a transformer by
comparing the current in the power supply's neutral wire with the current in the phase wire. If
the currents are equal then the differential protection relay will not operate. If there is a
current
imbalance
then
the
differential
protection
relay
operates.
REF protection is applied on transformers in order to detect ground faults on a given winding
more sensitively than differential protection.
7. TRIPPING RELAY:

Figure Tripping Relay


This type of relay is in the conjunction with main relay. When main relay sense any fault
in the system, it immediately operates the trip relay to disconnect the faulty section

AUXILIARY RELAY:

Auxiliary Relay
An auxiliary relay is used to indicate the fault by glowing bulb alert the employee.

5.6 FUSES :

Fuse is a essentially a short piece of metal ( or a fusible material ) inserted in a circuit which
melts when a predetermined value of current flows through it and thus breaks the circuits
.The protective element of the fuse is a fuse-link inserted in series with the circuit being
protected . The most generally material used for fuse element is a low melting point material
such as tin, lead or zinc .Fuses may be low voltage type or high voltage type : low voltage
can be further divided into two classes namely semi- enclosed rewire able fuse and the
cartridge type fuse.
5.7
EARTHING SYSTEM
The provision of an earthing system for an electric system is necessary by the following
reason.
In the event of over voltage on the system due to lightening discharge or other
system fault. These parts of equipment, which are normally dead, as for as voltage,
are concerned do not attain dangerously high potential.

In a three phase, circuit the neutral of the system is earthed in order to stabilize the
potential
of
circuit
with
respect
to
earth.

The resistance of earthing system is depending on:


Shape and material of earth electrode used.

Depth in the soil.

Specific resistance of soil surrounding in the neighbourhood of system electrodes.

PROCEDURE OF EARTHING:
Technical consideration the current carrying path should have enough capacity to deal with
more faults current. The resistance of earth and current path should be low enough to
prevent voltage rise between earth and neutral. The earth electrode must be driven in to the
ground to a sufficient depth to as to obtain lower value of earth resistance. To sufficient
lowered earth resistance a number of electrodes are inserted in the earth to a depth, they
are connected together to form a mesh. The resistance of earth should be for the mesh in
generally inserted in the earth at 0.5m depth the several point of mesh then connected to
earth electrode or ground conduction. The earth electrode is metal plate copper is used for
earth plate.

NEUTRAL EARTHING:
Neutral earthing of power transformer all power system operates with grounded neutral.
Grounding of neutral offers several advantages the neutral point of generator transformer is
connected to earth directly or through a reactance in some cases the neutral point is earthed
through an adjustable reactor of reactance matched with the line.
The earth fault protection is based on the method of neutral earthing.

The neutral earthing is associated switchgear.

The neutral earthing is provided for the purpose of protection arcing grounds unbalanced
voltages with respect to protection from lightening and for improvement of the system.
An earthed neutral system has the following advantages :A)
It provides a better protection against earth faults.
B)
It ensures nearly constant voltage of healthy phases because neutral point is not
shifted.
C)
This system provides a better reliability of service .
D)
It is safer for personal and equipment.
E)
It requires lesser maintenance expense as compared to the unearthed neural
(isolated system.
F)
In the system, transient voltages produced are very small.
G)
Ground fault relaying is simple . The earth may be utilized to operate protective
relays to isolate the fault.
H)
Persistent arcing ground can be eliminated by employing protective gear.

SAFETY EARTHING :It is required to provide protection to the operating staff working in the yard and sub station
from any injury during fault condition by keeping the voltage gradient with
in safe limits. The above two parts have common earth mat from which flat iron risers are
taken out to connect all the non-current carrying metal parts of the equipment. At the same
time the earth mat conductor rise to voltage, which is equal to the resistance of the earth mat
multiplied by ground fault current. This difference of potential results in voltage gradients.

6. CONTROL ROOM
Control panel contain meters, control switches and recorders located in the control building,
also called the dog house. These are used to control the substation equipment to send
power from one circuit to another or to open or to shut down circuits when needed.

Fig. -Control Room


MEASURING INSTRUMENT USED:
ENERGY METER: To measure the energy transmitted energy meters are fitted to
the panel to different feeders the energy transmitted is recorded after one hour
regularly for it MWHr, meter is provided.
WATTMETERS: It is attached to each feeder to record the power exported from
GSS.
FREQUENCY METER: To measure the frequency at each feeder there is the
provision of analog or digital frequency meter.
VOLTMETER: It is provided to measure the phase to phase voltage .It is also
available in both the analog and digital frequency meter.
AMETER: It is provided to measure the line current. It is also available in both the
forms analog as well as digital.
MAXIMUM DEMAND INDICATOR: There are also mounted the control panel to
record the average power over successive predetermined period.
MVAR METER: It is to measure the reactive power of the circuit.

7. BATTERY ROOM

Battery is the heart of power system control and protection as all the power system
protection equipment and the communication equipments works on D.C supply. In the event
of failure of station supply if standby D.C supply is not available then it will be dangerous for
the breaker and other protective equipment so also the communication system will be great
hampered and during such emergency there will be no communication for help or to transmit
information to the concerned authorities and the fault would be attended very late. Thus
battery installation, its commissioning and subsequent maintenance plays very important
role.
Batteries are to be installed in a room in close vicinity of control room. This room should be
constructed in a such a way that it is well ventilated and the dimension of the room should be
such that it can easily accommodate the stands provided for supporting desired no. of cells.
There should be adequate provision for artificial lightning and the windows should be located
in such a way that direct sunlight on the cells be avoided. Exhaust fan for ventilation of
gases, when on quick charge at high rate possible.
Room temperature should be maintained b/w 20 C to 35C for getting best results. Higher
temperature reduces the capacity. Battery cells should be arranged on the stands in such a
way that each cell can be easily accessed for any maintenance purpose viz., inspection,
topping up etc.
Battery room should always be kept dry as damp room is dangerous due to possible
leakages from the battery.
Storage of the battery is the most dependable source of supply of DC power required for
closing and tripping of CB , RELAY, signaling equipment, remote control apparatus,
telephone service, SCADA, emergency light etc.
Battery room is the heart line of D.C. system. In case of failure of the A.C. system the control
system should remain operative so we use D.C. control system through DC set.
Maintenance of Battery
For effective and trouble free services of station batteries following maintenance activities
are suggested:o Battery Room and Ventilation
o Herein battery rooms door are kept closed, exhaust fan checked for air circulation,
metal structures checked for corrosion and painted if necessary.
o Base or Racks
o Wooden racks checked for cracks and deterioration, base pads for deterioration.
o Cells and Jars
o Leaky jars checked for cracks replaced if necessary, clean jars-wash covers are
wiped out. Plates inspected for signs of deterioration.
o Intercell Connectors and Terminals
o Terminals cleaned for corrosion and sulphation.
o Charge
o Output of charging equipment is adjusted for normal conditioning of battery, ampere
meter should show as fraction of ampere.
o Annual Maintenance

o
o
o

Voltage of each cell which should be b/w 2.15 to 2.2 V per cell during trickle charge is
checked.
Electrolyte
Electrolyte level and add distilled water as it is necessary, specific gravity and
electrolyte is checked. Keep the distilled water container and keep some storage of
distilled water always ready for topping.

INITIAL
GRAVITY
1 840
1 825
1 825
1 400

SP. FINAL
GRAVITY
1 190
1 400
1 190
1 190

SP. ACID QUANTITY


18
40
18
45

WATER QUANITY
87
66
86
56

TECHNICAL PARTICULARS:
1. A.C. input
2. No. of cells
3. DC output 110 cells while supplying a
load of 18 amp.

8.

415 v +10% three phase 50 c/s


110
(a)
float charger capable of floating
cells of 2.65v per cell
(b)
Boost charge 220 v load at a max.
Of charging current of 20 amp.

Power line communication & SCADA system

Delhi Transco Limited (DTL) has a very large network of high voltage transmission lines in
whole Delhi. Transmission lines transfer power from power houses to substations and from
one substation to many other substations or vice versa. Power is generated at low Voltage
(of the order of 3.3KV to 25KV) and is stepped-up to high voltage (765KV, 400KV, 220KV &
132KV) for evacuating power into the grid network through transmission lines.
Transmission of Data
Below in Figure 1, main equipment from substation/power house to its subLDC has been
shown in a very simple form.

Figure 1: Transmission of Data from substation/Power house to subLDC


Current Transformers (CTs) and Potential Transformers (PTs), installed on transmission
lines, provide inputs to transducers of SIC (Supervisory Interface & Control) & RTU (Remote
Terminal Unit) panel. Circuit breakers & isolators' status are extended up to SIC panel. If for
such extension extra potential free contacts are not available in the Control Panels, Contact
Multiplying Relays (CMRs) are used to provide potential free contacts. The output of RTU is
connected to the communication equipment, through Modem. In between substation &
subLDC, a communication link has been shown. Telephone exchanges are connected with
the communication equipment. Such communication links can be of any type. DTL has got
its own three different type of communication systems, i.e. PLCC (Power Line Carrier
Communication), microwave and fibre-optic. Modem output at receive side is connected with
the CFE (Communication End Frame). Its output is connected with data takes over. Each
RTU is automatically polled by Server of Sub LDC to obtain each data of repeats at least
once in 10 sec and is stored in the database of sub LDC. This data is processed in database
formats and is retrieved for different applications. These formats or graphics are displayed or
printed as per requirement. At sub LDC, System Control Officers use this data to monitor
and analyze position of the grid.
Communication for Power System
Following are mainly three inter-related areas of functions in DTL for management of power
system:
A) Telecommunication
B) SCADA- Supervisory Control and Data Acquisition System.
C) EMS- Energy Management System
A) TELECOMMUNICATION
There are three different types of telecommunication systems in UPPTCL i.e.
i.
ii.

Microwave Communication System,


Fibre-optic Communication System,

iii.

PLCC-Power Line Carrier Communication.

Voice Frequency (VF) channels of all these systems have been integrated/interconnected to
make a hybrid communication system. Microwave & Fibre Optic are multi-channels
communication systems and are also called 'Wideband communication system'. PLCC is
single channel communication system.
SCADA SYSTEM
In SCADA system measured values, i.e. analogue (measured value) data (MW, MVAR, V,
Hz Transformer tap position), and Open/Closed status information, i.e. digital data (Circuit
Breakers/Isolators position i.e. on/off status), are transmitted through telecommunication
channels to respective sub-LDCs. For this purpose Remote Terminal Units (RTUs) at
400KV, 220KV sub-stations have been installed. System values & status information below
66 KV have not been picked up for data transmission, except for 33KV Bus isolator position
and LV side of generators. Secondary side of Current Transformers (CT) and Potential
Transformer (PT) are connected with 'Transducers'. The output of transducers is available in
dc current form (in the range of 4mA to 20mA). Analogue to digital converter converts this
current into binary pulses. Different inputs are interleaved in a sequential form and are fed
into the CPU of the RTU. The output of RTU, containing information in the form of digital
pulses, is sent to subLDC through communication links. Depending upon the type of
communication link, the output of RTU is connected, directly or through Modem, with the
communication equipment. At subLDC end, data received from RTU is fed into the data
servers. In general, a SCADA system consists of a database, displays and supporting
programmes. In DTL, subLDCs use all major functional areas of SCADA except the
'Supervisory Control/Command' function. The brief overview of major 'functional areas' of
SCADA system is as below:
1. Communications - Sub-LDC's computer communicates with all RTU stations under
its control, through a communication system. RTU polling, message formatting,
polynomial checking and message retransmission on failure are the activities of
'Communications' functional area.
2. Data Processing - After receipt of data through communication system it is
processed. Data process function has three sub-functions i.e. (i) Measurements, (ii)
Counters and (iii) Indications.

'Measurements' retrieved from a RTU are converted to engineering units and


linearised, if necessary. The measurement are then placed in database and are
checked against various limits which if exceeded generate high or low limit alarms.

The system has been set-up to collect 'Counters' at regular intervals: typically 5 or 10
minutes. At the end of the hour the units is transferred into appropriate hour slot in a
24-hour archive/history.

'Indications' are associated with status changes and protection. For those statuses
that are not classified as 'alarms', logs the change on the appropriate printer and also
enter it into a cyclic event list. For those statuses, which are defined as an 'alarms'
and the indication goes into alarm, an entry is made into the appropriate alarm list, as
well as in the event list and an audible alarm is generated in the sub-LDC.

3. Alarm/Event Logging - The alarm and event logging facilities are used by SCADA
data processing system. Alarms are grouped into different categories and are given
different priorities. Quality codes are assigned to the recently received data for any
'limit violation' and 'status changes'. Alarms are acknowledged from single line
diagram (or alarm lists) on display terminal in LDCs.
4. Manual Entry - There is a provision of manual entry of measured values, counters
and indications for the important sub-station/powerhouse, which are uncovered by an
RTU or some problem is going on in its RTU, equipment, communication path, etc.
5. Averaging of Measured Values - As an option, the SCADA system supports
averaging of all analogue measurements. Typically, the averaging of measured
values over a period of 15 minutes is stored to provide 24 hours trend.
6. Historical Data Recording (HDR) - The HDR, i.e. 'archive', subsystem maintains a
history of selected system parameters over a period of time. These are sampled at a
pre-selected interval and are placed in historical database. At the end of the day, the
data is saved for later analysis and for report generation.
7. Interactive Database Generation - Facilities have been provided in such a way that
an off-line copy of the SCADA database can be modified allowing the addition of new
RTUs, pickup points and communication channels.
8. Supervisory Control/Remote Command - This function enables the issue of
'remote control' commands to the sub-station/powerhouse equipment e.g. circuit
breaker trip command. Though, there is provision of this function in this system, yet it
is not used in U.P. As such, related/associated equipment have not been ordered.
9. Fail-over - A 'Fail-over' subsystem is also provided to secure and maintain a
database of devices and their backups. The state of the device is maintained
indicating whether it is 'on-line' or 'failed'. There is a 'backup' system, which maintains
database on a backup computer and the system is duplicated.
SLDC Minto road has a large and active 'Mimic Board' in its Control room. This mimic board
displays single line diagram of intra State transmission system i.e. grid network of 400KV,
220KV and important 66 KV sub-stations, transmission lines, thermal powerhouses.
Outgoing feeders, shown in the mimic board, have 'achieve' (LED display) colored
indications, of three different colors, to show the range of power flow at any moment i.e.
'Normal', 'Nominal' or 'Maximum' of its line capacity. For new substations and lines, displays
in active and passive forms are required to be made in the Mimic diagram. But, Mimic Board
has a limitation that it cannot incorporate/add large volume of displays for substations/power
houses/transmission lines in 'active' form due to space constraint and congestion. Due to
this Mimic Board is going to be supplemented with a Video Projection System (VPS) at
SLDC, Minto Road in near future. Also in SLDC & subLDCs, displays of single line diagrams
of RTU sub-stations/power house are viewed on VDUs of large size (21").

9. Operation and Maintenance of 220KV Substation


9.1.

INTRODUCTION

Maintenance is a key activity for utilities in order to assure the proper operation of the
networks. And it implies a huge amount of human and economic resources. Saving
Maintenance costs means that it is needed to proper operation of substation
equipments. The availability of reliable and quality power has made the job of substation
more important. This can be achieved by establishing the new substation, with most
efficient and reliable equipments and taking more care in their operation and
maintenance. Maintenance may be defined as the upkeep of the substation electrical
equipment in proper working and efficient condition to derive the Reliable and efficient
operation, Optimum utilization Availability of quality power, reduced down time,
Detection of premature faults, Minimizing revenue losses etc. To meet the above
requirement, the equipment has to be checked, attended to, trouble shoots and
operated under specified conditions. A large percentage of failure of electrical
equipment are due to deterioration of insulation, loose contact, abnormal operating
condition etc. many of these failure can be anticipated by regular application of simple
tests and timely maintenance . If the fault condition leading to failure is detected in the
early stage itself, the extent of damage can be reduced and the equipment can be
reconditioned and put back in to service. Any abnormality will be followed by warming
signal like variation in sound, excess temperature, vibration, sparks, blown out fuses,
frequent trappings, tripping before full load. The detection of incipient faults in electrical
equipment depends up on use of proper diagnostic tools, its effective use, correlation
and proper interpretation of test results and observation based on experience,
manufacturers guidance etc.

9.2.

MAINTENANCE ACTIVITY

1. Corrective or breakdown maintenance: Corrective or breakdown maintenance is


carried out as and when necessary. This applies only to low value and auxiliary equipments,
breakdown of which does not affect power supply continuity.
2. Preventive maintenance: Preventive maintenance calls for advance plan is made to
carry out preventive maintenance. The advantage lies in uninterrupted power supply,
increased availability of the equipment and reduction in maintenance cost.
3. Condition based maintenance: Condition base maintenance is based on condition
assessment of the equipment by tests ON or OFF the line. This is ideal for prevention of
equipment failure and other associated consequent damages.
4. Reliability centered maintenance: Reliability centered maintenance is generally carried
out on old equipment by conducting remaining life assessment studies and based on

economics, life extension techniques are adopted without sacrificing reliability and
availability. The maintenance costs are also reduced.
5. Equipment failure analyses: Equipment failure analysis is the major responsibility of
maintenance personnel to prevent repeated failure of equipment and provide inputs foe
necessary change in design parameters, new equipment design, quality control plan,
erection and subsequent maintenance technique.
6. Techniques for reducing down time: Techniques of reducing down time play a vital role
in continuity of power supply. Hot line maintenance of one line of double circuit\ line with
other circuit in live condition, deployment of emergency restoration system etc, is few
examples.
7. Spare management: Spares management ensures availability of right spares most
frequently required and at the right location and thereby help immediate restoration of power
supply.
8. Documentation/ computerization on maintenance: The documentation is a record of
the type of maintenance activity carried out, any abnormalities noticed during checking etc,
chronologically documented and computerized for further analysis and action.

9.3.

MAINTENANCE SCHEDULE

Maintenance schedule is categorized into daily, weekly, monthly, quarterly and yearly
maintenance schedules.
Power transformer (100 MVA, 20MVA)

Check and re-condition of silica jelly.

Check the working cooling fans, pumps

Release gas from BH relay

Clean the bushing, radiator, body etc.,

Check earthing connection

Check jump connections

Check OLTC motor drive and control panel


a) Lubricate bearing and cleaning
b) Check the gear box oil level
c) Check operation of limit switch, sequence switch with transformer in off
conditions
d) Check gasket joints for oil leakage
HT Circuit breakers
Clean the porcelains
Check the connections for loose contact
Check tripping through relays
Check the wiring for loose contact
Vermin Proofing of control box

Check annunciation scheme


Lubricate moving/link mechanisms wherever recommended by manufacturer

HT: CTs, PTs & Lightning arresters.


Clean the porcelain and metal body
Check connection both primary and secondary for tightness
Check oil level
Take IR values
Check earth connection for proper contact
11 kV Switchgears
Clean the breakers, panels and bus bars thoroughly, clean insulators with
CTC or Petrol
Check II values of the bus bars and individuals, breakers between phases
and earth
Check operation of breakers on local remote through relay and corresponding
annunciation
Check and lubricate operating mechanism wherever necessary
Tighten the terminal connection of all auxiliary circuit and wiring
Check all earth connections between the panel and electrodes for tightness
and check the contact resistance of earth connection.
Check contact travel, contact erosion in VCB
Check 11 kV CTs and PTs connections
Isolator
Check jump connection and replace PG clamps, if necessary
Check the alignment of isolator
Cleaning and applying petroleum jelly to contacts
GOS-HR fuses Station yard Earthing
Check clean and grease the GOS and check contacts for erosion, clean
insulator
Check operation for proper closing of the insulator
Check the fuses and renew the same wherever HR fuses are provided
Check the earth resistance of earthing mat and all individual earthing if any,
the resistance should be within the prescribed limit, otherwise action should
be taken to Bering the same to within limit immediately as it is very important
aspect for the safety of the equipment in any station.

TABLE 9.4.1: Maintenance Schedule for Oil-Filled Power Transformers


Maintenance or Test

Recommended Interval

Review equipment ratings

5 years

Preventive maintenance

As Per manufacturers
recommendations

Transformer physical inspection

Annually

Bushings visual inspection

Quarterly and 3-5 years

Bushings - check oil level

Weekly

Bushings cleaning

3-5 years

Transformer and bushings Doble test

3-5 years (6 months to 1 year for


suspect bushings)

Transformer and bushings


infrared scan

Annually

Insulating oil - DGA, physical,


and chemical tests

Annually after first year of


operation

Leakage reactance, Turns Ratio


tests, SFRA test

If problems are indicated by other


tests

Cooling fans inspect and test

Annually

Oil pumps and motors - inspect


and test

Annually

Heat exchangers inspect

Annually

Conservator and bladder - inspect

3-5 years

Top oil and winding


thermometers

Annually inspect and infrared scan


3-5 years calibrate

Oil level indicator operation

3-5 years

Pressure relief device

Annually inspect and perform


function test 3-5 years check oil
leaks

Sudden pressure relay

Annually inspect and perform


function test 3-5 years test per
manufacturers recommendations

Buchholz relay
Inspect foundation, rails, trucks
Inspect foundation, rails, trucks

Annually inspect and perform


function test
3-5 years

TABLE 9.4.2: Maintenance Schedule of SF6 Breaker


Maintenance or Test

Recommended Interval

Review equipment rating

5 years

Preventive maintenance

Per manufacturers instruction


manuals

Record gas pressure and


temperature, compare with
tolerances

Monthly

Record operations counter

Monthly

Visual inspection

Monthly, annually,5 years

Check foundation, grounds, paint

5 years

Check external screws, bolts,


electrical terminals tight

Annually

Contact resistance test, power


factor insulation test, motion
analyzer, trip test, moisture test on
gas

5 years, if required by
manufacturer

Verify operation and calibration of


temperature and pressure switches
and gauges

5 years

Check lube points, heater


operation, tightness of terminals,
linkages screws, bolts; latch,
linkage, operating mechanism
adjustments

5 years

Overhaul breaker with new seals,


contacts, nozzles

5 years10 to 15 years or 4,000 to 10,000


operations (more frequent if high
current operation)

Overhaul disconnect, grounding,


and breaking switches

15 years or 5,000 to 10,000


operations

Gas cart maintenance

Per manufacturers instruction


manuals

TABLE 9.4.3: Maintenance Schedule for Relays and Protection Circuits


Maintenance or Test

Recommended Interval

Fault/load study and recalculate


settings

5 years

Electro-mechanical relays
Calibration and functional testing

Upon commissioning
years

Solid-state relays Calibration and


functional testing

Upon commissioning 1 year after


commissioning and every 3 years

Microprocessor relays calibration


and functional testing

Protection circuit functional test,


including lockout relays

Upon commissioning 1 year after


commissioning and every 8-10
years
Immediately upon
and/or upon any changes and every 3-6 years

Check red light lit for lockout


relay and circuit breaker coil
continuity

Daily

Lockout relays Cleaning and


lubrication

5Years

TABLE 9.4.4: Maintenance Schedule for Arresters


Maintenance or Test

Recommended
Interval

Review equipment rating

5 years

Visual inspection with binoculars

Quarterly to semiannually

Clean insulator and check


connections
3-6 years Ambient dependent

3-6 years Ambient dependent

Doble test (power frequency


dielectric loss, direct current [DC]

3-6 years Ambient dependent

insulation resistance, power factor)


Replace all silicon carbide arresters
with metal oxide varistor type

As soon as possible

Infrared scan

Annually

TABLE.9.4.5: Maintenance Schedule for Transmission Lines


Maintenance or Test
Recommended Interval
Review equipment ratings

5 years

Visual inspection with binoculars

Semi -annually

Infrared scan

Annually

9.5 THERMO SCANNING


A sub station having worth crores of rupees can be scanned in two days time for which
charges for scanning comes around Rs. 30,000. By thermo scanning any incipient fault can
be identified in its initial stages if thermo scanning is done on regular interval.
Thus damage of equipment worth of crores of rupees can be avoided and also this
technique prevents disruptions of power to
Customers in case of damage of equipment.
This is done with thermo vision camera based on FLIR system.
Thermo graphic Inspection:
During the thermo-visual inspection of sub-station equipment, several hot spots are noticed
and these spots are due to loose joints. The temperature difference between the hot spots
and normal spot is reported and this aspect indicates the severity of the fault. Four types of
fault are graded from zero to three indicating normalcy to sever fault.

GENERAL SAFETY PRECAUTION REQUIRED


(a) Dont wear loose garments; they get caught leading to accidents.
(b) Long and unruly hairs are dangerous particularly when working near
revolving part.
(c) Do not smoke near prohibited area.
(d) Keep the work area clean, dry and free of obstructions.
(e) Do not touch or operate equipment unless are authorized so.
(f) Lubricate the M/C part with both hands. Use cotton waste brush etc.
(g) Ensure all guards in position before M/C working on job.
(h) Ensure all machines control of the machine is in your access.
(i) Ensure all tools are in good conditions. Look and report any accident
hazard.
(j) For any injury whether small or big get first aid first.

CONCLUSION
It has been really a knowledgeable experience pursuing training at DTL, 220 KV Sarita Vihar
sub-station. It is beyond doubt; DTL is not only an industry in itself but also offers vocational
training to engineering graduates as well as professionals.
This phase of practical training has proved to be quiet fruitful, beneficial in every respect. It
provided an opportunity to encounter big and sophisticated equipments of the Sub-Station.
The architecture of the Sub-Station and the way various equipments are linked together to
work as a unit and methodological approach in working of whole s/s is controlled renders the
impression that engineering is not just learning the structured description and working of
various equipments, but greater part is of planning proper management.
It was definitely a knowledgeable experience and pride to be a part of 220 kv Sarita Vihar s/s
for such a short period of time.
No doubt it showed that mere theoretical and bookish knowledge need to be supplemented
with able practice knowledge. And this opportunity to gain practical knowledge, imparted by
very able personals of DTL at Srita Vihar, New Delhi was a learning experience.

You might also like