WATER TREATMENT PLANT Sl. No.

Features Description Remarks

Water Source

Pre treatment plant

Clarified water Filtration plant

RO plant

Creek water will be pumped from creek water intake pump house to creek water reservoir in the plant of capacity 30000m ( about 7 hrs) 3 x 50 % horizontal centrifugal pumps will be provided to supply creek water to the clarifier(2 x 50%). At Clarifier Outlet TSS shall not to exceed 20 ppm stored in clarifier water tank of capacity 10000 m Four (3 working +1 standby) Pressure sand Filters (PSFs) having capacity 200m/hr (each) and Dual Media filter (DMFs), four (3 working +1 standby) nos each of capacity 200 m/hr RO plant will be of a two-pass module. (2x50%) first pass of total capacity 162 m/hr (3888 m/day), the permeate from 1st pass will be stored in a permeate storage tank of capacity 4500m. TDS shall not exceed 450 ppm/ 500 ppm (depending on sea water quality) (2x50%) second pass of total capacity 40 m/hr. The permeate water from 2nd pass RO will be stored in a DM plant feed tank of capacity 100 m. TDS shall not exceed 20 ppm (2x100%) supply pump to DM plant, consist of 2x100% capacity Ion exchange units. Two (2) No. of DM Water storage tanks of capacity 400 m each equivalent to 24 hrs requirement. Condensate Storage tank of capacity 350 m Consist of - scale Inhibitor Dosing system, Corrosion Inhibitor Dosing System, Acid dosing system, Electro chlorination plant and side stream filter. scale Inhibitor, Corrosion Inhibitor, Acid dosing and Chlorine will be done at CW Common Forebay. 1.2% of cooling water (590m3/hr tentatively) will be fed to the Side Stream Filters (3x50%) and outlet of SSF shall be 2 ppm TSS maximum. 2 x 100 % Boiler fill pumps for initial filling arrangements ( 200 m/hr & 15 kg/cm

DM plant

CW Treatment

DM Water distribution

Sl. No.

Features

Description

Remarks

Service Water System

2 x 100 % Power cycle make up pumps ( 35 m/hr) 2 x 100 % DM water transfer pumps to CCW system, Chemical dosing systemStator water cooling system, CPU unit & Regeneration facility, Hydrogen plant 2 x 100% Service water pumps (200 m /hr) shall be provided to supplied to Service water to the Overhead tank of capacity 300 m.

EXPECTED CREEK WATER ANALYSIS DURING SUMMER ( TYPICAL CREEK WATER ANALYSIS to be confirmed) NO. TEST UNIT RESULT 1 Conductivity s/cm 39000 42000 2 TDS PPM 33020 - 43446 3 pH 7.6 8.9 4 Suspended Solid mg/l 200 5 Total Hardness, as CaCO3 mg/l 6206 - 6650 6 Free CO2 mg/l 0 7 Turbidity NTU 0.5 4.1 8 Oil Content Not detectable 9 Total Sulfide, as H2S mg/l 0.97 1.38

FEED WATER ANALYSIS (DESALINATED WATER) PARAMETERS VALUE TDS < 450 PPM TSS & Turbidity < 2 units pH 6.8-7.2 Organics: Not detectable TREATED WATER GUARANTEES (FROM DM PLANT) PARAMETER VALUE i) Conductivity: 0.1 mhos/cm at 25 O C ii) Total Silica ( Reactive +Colloidal) < 0.01 ppm as SiO2 iii) PH 6.8 7.2

Sl.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14

REMINERALISED WATER QUALITY Constituent Value TDS 500 mg/l Turbidity & Suspended Solids < 2 units Taste Unobjectionable Colour Unobjectionable Iron (Fe) 0.3 mg/l Manganese (Mn) 0.1 mg/l Copper (Cu) 1 mg/l Zinc (Zn) 5 mg/l Calcium (Ca) 75 mg/l Magnesium (Mg) 50 mg/l Sulphate (SO4) 200 mg/l Chloride (Cl) 200 mg/l pH 7 to 8.5 Boron <0.4 ppm