ECSS-Q-ST-70C

6 March 2009

Space product assurance


Materials, mechanical parts and processes

ECSS Secretariat ESA-ESTEC Requirements & Standards Division Noordwijk, The Netherlands

ECSSQST70C 6March2009

Foreword This Standard is one of the series of ECSS Standards intended to be applied together for the management, engineering and product assurance in space projects and applications. ECSS is a cooperative effort of the European Space Agency, national space agencies and European industry associations for the purpose of developing and maintaining common standards. Requirements in this Standard are defined in terms of what shall be accomplished, rather than in terms of how to organize and perform the necessary work. This allows existing organizational structures and methods to be applied where they are effective, and for the structures and methods to evolve as necessary without rewritingthestandards. This Standard has been prepared by the ECSS Executive Secretariat endorsed by the document and disciplinefocalpointandapprovedbytheECSSTechnicalAuthority.

Disclaimer ECSSdoesnotprovideanywarrantywhatsoever,whetherexpressed,implied,orstatutory,including, butnotlimitedto,anywarrantyofmerchantabilityorfitnessforaparticularpurposeoranywarranty that the contents of the item are errorfree. In no respect shall ECSS incur any liability for any damages, including, but not limited to, direct, indirect, special, or consequential damages arising out of, resulting from, or in any way connected to the use of this Standard, whether or not based upon warranty, business agreement, tort, or otherwise; whether or not injury was sustained by persons or property or otherwise; and whether or not loss was sustained from, or arose out of, the results of, the item,oranyservicesthatmaybeprovidedbyECSS.

Publishedby:

Copyright:

ESARequirementsandStandardsDivision ESTEC, P.O. Box 299, 2200 AG Noordwijk The Netherlands 2009 by the European Space Agency for the members of ECSS

ECSSQST70C 6March2009

Change log

ECSSQ70A 19April1996 ECSSQ70B 14December2004 ECSSQST70C 6March2009

Firstissue Secondissue Thirdissue ThemainchangesbetweenECSSQ70Bandthecurrentversionarethe following: RevisingECSSQST70accordingtoECSSdraftingrulesandnew template. Reorganizationofthecontenttoseparatedescriptivetextand requirements,andcreationofDRD.

ECSSQST70C 6March2009

Table of contents

Change log .................................................................................................................3 1 Scope.......................................................................................................................9 2 Normative references ...........................................................................................10 3 Terms, definitions and abbreviated terms..........................................................12
3.1 3.2 3.3 Terms from other standards .....................................................................................12 Terms specific to the present standard ....................................................................12 Abbreviated terms .................................................................................................... 13

4 General requirements...........................................................................................15
4.1 MMPP management requirements........................................................................... 15 4.1.1 4.1.2 4.1.3 4.2 4.2.1 4.2.2 4.2.3 4.2.4 4.3 4.4 4.5 4.6 Overview.....................................................................................................15 MMPP plan .................................................................................................15 Customer reviews....................................................................................... 18 Overview.....................................................................................................19 Establishing and processing of lists............................................................ 19 Management of the lists .............................................................................20 Supplier role and responsibilities................................................................ 20

Management and consolidation of the activities....................................................... 19

Technical constraints................................................................................................21 Cleanliness and contamination control..................................................................... 21 Safety hazardous parts and materials ...................................................................... 22 Optical, mechanical or electrical GSE hardware ...................................................... 22

5 Materials control...................................................................................................23
5.1 Technical criteria for selection of materials .............................................................. 23 5.1.1 5.1.2 5.1.3 5.1.4 5.1.5 Overview.....................................................................................................23 Temperature ...............................................................................................23 Thermal cycling ..........................................................................................23 Vacuum ......................................................................................................23 Offgassing and toxicity ............................................................................... 24 4

ECSSQST70C 6March2009 5.1.6 5.1.7 5.1.8 5.1.9 5.1.10 5.1.11 5.1.12 5.1.13 5.1.14 5.1.15 5.1.16 5.1.17 5.2 5.2.1 5.2.2 5.3 5.4 Flammability ...............................................................................................24 Radiation ....................................................................................................24 Electrical charge and discharge ................................................................. 24 Corrosion ....................................................................................................24 Stress-corrosion ......................................................................................... 24 Fluid compatibility .......................................................................................24 Galvanic compatibility................................................................................. 25 Atomic oxygen ............................................................................................25 Micrometeoroids and debris ....................................................................... 25 Moisture absorption and desorption ........................................................... 25 Mechanical contact surface effects (cold welding, fretting, wear) .............. 27 Life..............................................................................................................27 General.......................................................................................................27 Constraints .................................................................................................27

Selection...................................................................................................................27

Declared materials list (DML) ...................................................................................28 Criticality analysis .....................................................................................................28 5.4.1 5.4.2 Overview.....................................................................................................28 Requirements .............................................................................................28 General.......................................................................................................28 Evaluation phase ........................................................................................ 29 Validation phase .........................................................................................29 Approval phase...........................................................................................29 Deviation request........................................................................................29 Procurement specifications ........................................................................ 30 Incoming inspection procedure................................................................... 30 Validation status of materials......................................................................30 Traceability of materials.............................................................................. 30 Packaging, storage, removal from storage................................................. 31 Limited-life materials before implementation .............................................. 31 Limited-life materials after implementation ................................................. 31 Materials nonconformances and alerts....................................................... 31 Health and safety........................................................................................ 31

5.5

Evaluation and validation phases ............................................................................. 28 5.5.1 5.5.2 5.5.3 5.5.4 5.5.5

5.6

Procurement of materials .........................................................................................30 5.6.1 5.6.2

5.7

Use of materials .......................................................................................................30 5.7.1 5.7.2 5.7.3 5.7.4 5.7.5 5.7.6 5.7.7

6 Mechanical parts control .....................................................................................32

ECSSQST70C 6March2009 6.1 6.2 6.3 6.4 Selection of mechanical parts ..................................................................................32 Selection...................................................................................................................32 Declared mechanical parts list (DMPL) ....................................................................32 Criticality analysis .....................................................................................................32 6.4.1 6.4.2 6.5 6.5.1 6.5.2 6.5.3 6.5.4 6.5.5 6.6 6.6.1 6.6.2 6.6.3 6.6.4 6.7 6.7.1 6.7.2 6.7.3 6.7.4 6.7.5 Overview.....................................................................................................32 Requirements .............................................................................................33 General.......................................................................................................33 Evaluation phase ........................................................................................ 33 Qualification phase .....................................................................................34 Approval phase...........................................................................................34 Deviation request........................................................................................34 General.......................................................................................................34 Procurement specification .......................................................................... 34 Source inspection .......................................................................................35 Incoming inspection procedure................................................................... 35 Qualification status of parts ........................................................................35 Traceability of parts .................................................................................... 35 Packaging, storage, removal from storage................................................. 35 Limited-life parts or parts subject to wearout................................................. 36 Parts nonconformance and alerts...............................................................36

Evaluation and qualification phases ......................................................................... 33

Procurement of mechanical parts............................................................................. 34

Use of mechanical parts ...........................................................................................35

7 Process control ....................................................................................................37


7.1 7.2 7.3 7.4 7.5 Specifications or procedures .................................................................................... 37 Associated materials and mechanical parts ............................................................. 37 Selection...................................................................................................................37 Declared processes list (DPL) .................................................................................. 38 Criticality analysis .....................................................................................................38 7.5.1 7.5.2 7.6 7.6.1 7.6.2 7.6.3 7.6.4 7.6.5 Overview.....................................................................................................38 Requirements .............................................................................................38 General.......................................................................................................38 Evaluation phase ........................................................................................ 39 Verification phase .......................................................................................39 Approval phase...........................................................................................39 Deviation request........................................................................................39

Evaluation and verification phase............................................................................. 38

ECSSQST70C 6March2009 7.7 Use of a process ......................................................................................................40 7.7.1 7.7.2 7.7.3 7.7.4 7.7.5 7.7.6 7.7.7 Verification status of a process................................................................... 40 Re-verification of a process ........................................................................ 40 Implementation of a process ......................................................................40 Traceability of processes............................................................................40 Process nonconformances and alerts ........................................................ 41 Mandatory inspection points (MIP) ............................................................. 41 Packaging, storage, removal from storage................................................. 41

Annex A (normative) Declared materials list (DML) - DRD...................................42 Annex B (normative) Declared mechanical parts list (DMPL) - DRD...................49 Annex C (normative) Declared process list (DPL) - DRD .....................................55 Annex D (normative) Request for approval (RFA) - DRD .....................................60 Annex E (informative) Relationship between materials, mechanical parts, processes activities and programme phases ...................................................64
E.1 E.2 E.3 E.4 Feasibility phase (phase A) ...................................................................................... 64 Preliminary definition phase (phase B)..................................................................... 64 Detailed definition and production phase (phase C or D) .............................................. 64 Utilization phase (phase E) ......................................................................................65

Annex F (informative) MMPP documents delivery with respect to milestones............................................................................................................66 Bibliography.............................................................................................................68 Figures
Figure 4-1: Materials, mechanical parts and processes flow chart ........................................ 16 Figure A-1 : Example of a realized DML ................................................................................ 48 Figure B-1 : Example of a realized DMPL .............................................................................. 54 Figure C-1 : Example of realized DPL....................................................................................59 Figure D-1 : Example of RFA (Page 1 of 2) ...........................................................................62 Figure D-1 : Example of RFA (Page 2 of 2) ...........................................................................63

Tables
Table 4-1: Steps to be taken to get approval for materials, mechanical parts and processes (MMPP) .............................................................................................. 18 Table 5-1 Compatible couples for bimetallic contacts ............................................................ 26 Table A-1 : Material group numbers.......................................................................................43

ECSSQST70C 6March2009 Table A-2 : Environmental code .............................................................................................45 Table A-3 : Size code ............................................................................................................. 46 Table A-4 : Approval status ....................................................................................................47 Table B-1 : Mechanical part group numbers .......................................................................... 50 Table B-2 : Environmental code .............................................................................................51 Table B-3 : Approval status ....................................................................................................53 Table C-1 : Process group numbers ...................................................................................... 56 Table C-2 : Approval status....................................................................................................58 Table F-1 : MMPP documents delivery w.r.t. milestones ....................................................... 67

ECSSQST70C 6March2009

1 Scope
The purpose of this Standard is to define the requirements and statements applicable to materials, mechanical parts and processes to satisfy the mission performancerequirements. ThisStandardalsodefinesthedocumentationrequirementsandtheprocedures relevant to obtaining approval for the use of materials, mechanical parts and processesinthefabricationofspacesystemsandassociatedequipment. ThisStandardcoversthefollowing: management, including organization, reviews, acceptance status and documentationcontrol; selectioncriteriaandrules; evaluation,validationandqualification,orverificationtesting; procurementandreceivinginspection; utilizationcriteriaandrules.

TherelationshipbetweenactivitiesandprogrammephasesisdefinedinAnnexE. The provisions of this Standard apply to all actors involved at all levels in the production of space systems. These can include manned and unmanned spacecraft, launchers, satellites, payloads, experiments, electrical ground support equipment, mechanical ground support equipment, and their correspondingorganizations. Thisstandardmaybetailoredforthespecificcharacteristicsandconstraintsofa spaceprojectinconformancewithECSSSST00.

ECSSQST70C 6March2009

2 Normative references
The following normative documents contain provisions which, through reference in this text, constitute provisions of this ECSS Standard. For dated references,subsequentamendmentsto,orrevisionsofanyofthesepublications do not apply. However, parties to agreements based on this ECSS Standard are encouragedtoinvestigatethepossibilityofapplyingthemostrecenteditionsof the normative documents indicated below. For undated references the latest editionofthepublicationreferredtoapplies. ECSSSST0001 ECSSEST2006 ECSSQST10 ECSSQST1004 ECSSQST1009 ECSSQST20 ECSSQST40 ECSSQST7001 ECSSQST7002 ECSSQST7004 ECSSsystemGlossaryofterms SpaceengineeringSpacecraftcharging SpaceproductassuranceProductassurance management SpaceproductassuranceCriticalitemcontrol SpaceproductassuranceNonconformancecontrol system SpaceproductassuranceQualityassurance SpaceproductassuranceSafety SpaceproductassuranceCleanlinessand contaminationandcontrol SpaceproductassuranceThermalvacuum outgassingtestforthescreeningofspacematerials SpaceproductassuranceThermaltestingforthe evaluationofspacematerials,processes,mechanical partsandassemblies SpaceproductassuranceParticleandUVradiation testingofspacematerials SpaceproductassuranceFlammabilitytestingfor thescreeningofspacematerials SpaceproductassuranceControloflimited shelflifematerials SpaceproductassuranceDeterminationof offgassingproductsfrommaterialsandassembled articlestobeusedinamannedspacevehiclecrew compartment

ECSSQST7006 ECSSQST7021 ECSSQST7022 ECSSQST7029

10

ECSSQST70C 6March2009
ECSSQST7036 ECSSQST7037 ECSSQST7071 SpaceproductassuranceMaterialselectionfor controllingstresscorrosioncracking SpaceproductassuranceDeterminationofthe susceptibilityofmetalstostresscorrosioncracking SpaceproductassuranceDataforselectionofspace materialsandprocesses

11

ECSSQST70C 6March2009

3 Terms, definitions and abbreviated terms

3.1

Terms from other standards


ForthepurposeofthisStandard,thetermsanddefinitionsfromECSSSST0001 apply,inparticularforthefollowingterms: material mechanicalpart

3.2

Terms specific to the present standard


3.2.1 critical mechanical part
mechanical part that requires specific attention or control due to fracture mechanics aspects and limitedlife aspects, or with which the supplier has no previousexperienceofusingthemechanicalpartinthespecificapplicationand environment or that are new or nonqualified, or that has caused problems duringprevioususethatremainunresolved

3.2.2

critical process

process new to an individual company or nonverified for the application in questionorhascausedproblemsduringprevioususethatremainunresolved

3.2.3

critical material

material that is new to an individual company or nonvalidated for the particular application and environment, or that has caused problems during previoususethatremainunresolved

3.2.4

part

mechanicalpart(see3.1)

3.2.5

process

set of interrelated resources and activities which transforms a material or semifinishedproductintoasemifinishedproductorfinalproduct

12

ECSSQST70C 6March2009 3.2.6 request for approval (RFA)

document with which the supplier or user asks the competent body for permissiontouseacriticalmaterial,partorprocess

3.2.7

special process

process where quality cannot be completely ensured by inspection of the end articleonly

3.3

Abbreviated terms
For the purpose of this Standard, the abbreviated terms from ECSSSST0001 andthefollowingapply:

Abbreviation AA AOCS ATOX AISI CDA CDR CFRP CI DML DMPL DPL DRD EEE ESA GOX GSE LEO LOX MAPTIS MIP MMPP NASA NCR NRB PA

Meaning
AluminiumAssociation attitudeandorbitcontrolsystem atomicoxygen AmericanIronandSteelInstitute CopperDevelopmentAssociation criticaldesignreview carbonfibrereinforcedpolymer configurationitemnumber(asperprojectdefinition) declaredmateriallist declaredmechanicalpartlist declaredprocesslist documentrequirementsdefinition electrical,electronicandelectromechanical EuropeanSpaceAgency gaseousoxygen groundsupportequipment lowEarthorbit liquidoxygen MaterialsandProcessesTechnicalInformationSystem mandatoryinspectionpoint Materials,mechanicalpartsandprocesses NationalAeronauticsandSpaceAdministration nonconformancereport nonconformancereviewboard productassurance

13

ECSSQST70C 6March2009 PDR PID PMP QR QRR RFA SCC


preliminarydesignreview processidentificationdocument parts,materials,processes qualificationreview qualificationreviewreport requestforapproval stresscorrosioncracking

14

ECSSQST70C 6March2009

4 General requirements

4.1

MMPP management requirements


4.1.1 Overview

ThegeneralMMPPactivitywithintheframeworkofaprojectissummarizedin Figure41.

4.1.2
a.

MMPP plan

The supplier shall prepare, maintain and implement a MMPP plan, as part of the overall PA plan in conformance to ECSSQST10 and this Standardorasaseparatedocument. TheMMPPplanshallbesubmittedtothecustomerforapproval.

b.

15

ECSSQST70C 6March2009
Functional and technical specifications Project list and incident databank Risk and contamination analysis Results of previous uses

Start

Identification of needs

Selection Preliminary lists No

Criticality analysis

Critical?

Yes

Evaluation necessary? No

Yes

Conform to requirements? No

Yes

Validation or qualification or verification programme Test Programme

Evaluation and validation or qualification or verification programme

Test Programme

Deviation RFA first Issue

RFA first Issue

PDR
Accept? No Yes New test? Test results No Validation or qualification or verification programme Test results No Accept? Yes Deviation No Yes No

Accept? Yes

Evaluation tests

Accept? Yes

New selection? No

Yes

RFA final issue

New test? No

Yes No Accept? Validation or qualification or verification programme Yes

No Accept? Yes

New selection?

Yes Test results

No New test? Deviation RFA final issue No

Yes

New selection? No Accept? Yes Accept? Yes Deviation No No

Yes

No Accept? Yes

CDR

as-designed lists

To P a rt 2

F ro m P a rt 2 (N RB d e c i s io n )

Figure41:Materials,mechanicalpartsandprocessesflowchart

16

ECSSQST70C 6March2009
F ro m P a rt 1 To P a rt 1

Procurement of materials

Procurement of mechanical parts

Packing, storage

Removal from storage, conformity check with requirements

No Accept? Yes

Implementation of processes

No Accept? Yes Yes NCR Inspection NRB No Use

No Accept? Yes

Utilization

No Accept? Yes -

as-built lists

QR
end

Figure41:Materials,mechanicalpartsandprocessesflowchart(Continued)

17

ECSSQST70C 6March2009

Table41:Stepstobetakentogetapprovalformaterials,mechanicalpartsand processes(MMPP)
Materials Phase Step Comments
Criticalmaterials aretested,e.g. outgassing,SCC, flammability. CriticalAnalysis 1 2 Evaluation (usuallybytest methodsdefined byECSS standards) 1 2

Mechanicalparts Step Comments


1

Processes Step Comments


Criticalprocessesare evaluatedbytesting technology samplesincluding all,forexample, electrical interconnection processesand painting,adhesive bonding. Verificationtests usuallydefinedin ECSSstandards

Mechanicalpartsare 2 testedby,for example,vibration, thermalanalysis, offgassingandlife test.

Verification

Notapplicable

Notapplicable

Validation Qualification Approval


Note Note Note

Notapplicable 3

Notapplicable Notapplicable ByRFA(AnnexD)or DPL

Notapplicable

ByRFA(AnnexD) orDML

ByRFA(AnnexD)or DMPL/DPL

NOTE 1 Project approval is always by means of the request for approval (RFA) form and the projects declared materials list (DML), declared mechanical parts list (DMPL) and declared processes list (DPL). NOTE 2 The details for approvals of MMPP lists are contained in this Standard. NOTE 3 To summarize: In addition: Materials are validated. Mechanical parts are qualified. Processes are verified. Skills training schools are ESA-certified. Outside test or evaluation laboratories are certified by agency or company audits. Operators and inspectors for special and critical processes are trained, certified and monitored.

4.1.3
a.

Customer reviews

To obtain the validation status for materials and qualification status for parts and verification status for processes, the MMPP manager shall presenttothecustomerthoseactivitieswhichwereperformedinorderto complywiththisStandardtogetherwithresultsobtained. The MMPP manager shall organize technical review meetings with his suppliersatalllevels.

b.

18

ECSSQST70C 6March2009

4.2

Management and consolidation of the activities


4.2.1 Overview

The relationship between materials and processes activities and programme phasesisshowninAnnexE.

4.2.2
a.

Establishing and processing of lists

Eachsupplierandsubsuppliershallestablish,collect,reviewanddeliver the declared materials, mechanical parts and processes lists including all theitemsintendedforuseintheflightequipment. Thelistsshallreflectthecurrentdesignatthetimeofissue. These lists shall contain the materials, mechanical parts and processes usedinthecurrentdesigninorderto: 1. 2. 3. demonstratecompliancewithallrequirementsoftheprogramme; verifytheresultsofequipmentsupplieractivities; control and monitor the status of materials, mechanical parts and processesinaccordancewithprogrammemilestones. NOTE SeeAnnexF.

b. c.

d.

Thefollowingconstraintsshouldapply: 1. maximum use of the materials and processes described in approved data sources and items already approved on similar projects; NOTE 2. For approved data sources see for example ECSSQST7071.

useofprojectrelatedpreferredlists,ifavailable.

e.

Thefollowingconstraintsshallbetakenintoaccount: 1. 2. requirementsoriginatingfromtheinitialtechnicalspecification; programmaticprojectrequirementsandconditions;

f.

Ananalysisofthecriticalityofthesepreliminarylistsshall,afterchecking the conformity of the materials, mechanical parts and processes, against all the project requirements, allow them to be classified into three categories: 1. 2. Critical items, subject to evaluation, validation, qualification, or verificationprogrammes. Itemsthatarenotcriticalbutwhichdonotconformtooneormore project requirements (a justified deviation request should be draftedforthiscategory). Noncriticalitems.

3. g.

For critical items a request for approval shall be submitted in conformancewithAnnexD.

19

ECSSQST70C 6March2009

4.2.3
a. b. c. d.

Management of the lists

ThesuppliershalldocumentallmaterialsintheDeclaredmaterialslistin conformancewithAnnexA. The supplier shall document all mechanical parts in the Declared mechanicalpartslistinconformancewithAnnexB. The supplier shall document all processes in the Declared process list in conformancewithAnnexC. The supplier shall process the lists of lower level suppliers to ensure exchangeabililty, searchability, sortability, storability and retrievability forthatsetoflists,beforesubmittingittothecustomer. Theselistsshallbeupdatedduringthecourseoftheproject. The preliminary lists shall include the items from suppliers preliminary needs. NOTE They are used to identify critical items (availableforthePDR).

e. f.

g. h.

The asdesigned lists shall include the items from the baselines various designfiles(availablefortheCDR). Any change after CDR or QR shall be reflected in the list and shall be in accordancewithFigure41(Part2). NOTE1 The MMPP manager is responsible within the programme to ensure that all the information needed is given and that the approval status is consistent with technical and scheduling objectivesanddataisexchangeable. NOTE2 Where no project requirements exist for a separate DMPL, the mechanical parts can be enteredintoaseparatesectionoftheDML. NOTE3 The materials of, for example, screws and nuts that are made up of a few materials can be listed in the DMPL. The materials (metals and plastics) of complex parts can be listed in the DML with, for example, outgassing, toxicity, flammability, corrosion and stress corrosion valuesandreferencetotheDMPLitem.

4.2.4
a. 1. 2. 3. b.

Supplier role and responsibilities


obtainingthecorrectandcompletelistsfromlowerlevelsuppliers; providingprovisionaland,later,definitiveapprovalforeachlist; submitting the project declaredlistsforapproval prior to initiation ofthehardwarephase(beforecriticaldesignreview).

Thesuppliershallperformthefollowingtasks:

The lists established by the suppliers shall include all the information describedinthisStandard.

20

ECSSQST70C 6March2009
c. d. Amendments to the lists shall be implemented only through established changeprocedures. The following documentation shall be delivered to the customer upon request: 1. 2. 3. e. RFA(referenceandissue); evaluationreports; deviationrequests.

The material, mechanical parts or process justification files shall be made available to the customer upon request either on the supplier site, or by anyotherprocessagreedbybothparties. NOTE Forexample,bynondisclosureagreement.

4.3

Technical constraints
a. b. Partsandmaterialsshallsatisfythemissionsfunctionalconstraints. Parts and materials shall satisfy both ground environment constraints andflightconstraints. NOTE Examplesare: Ground environment constraints: manufacture, tests, storage, maintenance, transportandintegration Flightconstraints:launchandorbit. c. d. The technical criteria from clause 5.1 shall be taken into account, accordingtothemission. The estimated availability of the parts and products obtained from materials and processes used shall be compatible with the final systems lifecycle(tests,storageandmission).

4.4

Cleanliness and contamination control


a. Thesuppliershallestablishandmaintainacontaminationandcleanliness controlprogrammeincluding,asaminimum: 1. 2. b. cleaningprocedures,and cleanlinessmonitoringproceduresormethods.

The risks of chemical or particle pollution generated by parts, materials or processes used shall be identified and reduced in accordance with missionrequirements(cleanlinessorcontaminationanalysis). For cleanliness or contaminationcritical applications, a requirement specification (chemical and particle) and a specific cleanliness control plan and shall be established in conformance with Annex A (CRS DRD) andAnnexB(C&CCPDRD)ofECSSQST7001.

c.

21

ECSSQST70C 6March2009

4.5

Safety hazardous parts and materials


a. Parts and materials with hazardous characteristics shall be identified, managedandprocessedinconformancewithECSSQST40.

4.6

Optical, mechanical or electrical GSE hardware


a. When optical, mechanical or electrical GSE materials are used in thermal vacuum or interfacing with flight hardware, possible degradation shall betakenintoaccount. NOTE For example, contamination, surface degradation, electromechanical and chemical effects.

22

ECSSQST70C 6March2009

5 Materials control

5.1

Technical criteria for selection of materials


5.1.1 Overview

The following requirements apply when the environmental conditions of the mission require their application. The specific requirements, test methods and acceptorrejectcriteriaarepresentedintheECSSQST70seriesofdocuments.

5.1.2
a.

Temperature

Material properties shall be compatible with the thermal environment to whichtheyareexposed.

5.1.3
a. b.

Thermal cycling

Materials subject to thermal cycling shall be assessed for their ability to withstandinducedthermalstress. The following materials shall be tested in conformance with ECSSQST 7004: 1. Materialssusceptibletothermalvacuumeffect. NOTE 2. For a nonexhaustive list of such materials, see ECSSQST7004Clause1.

Materials of unknown characteristics in respect to thermal vacuum.

c.

Materials subject to thermal cycling other than those covered by 5.1.3b, shallbetestedinaccordancewithaprocedureapprovedbythecustomer.

5.1.4
a. b.

Vacuum

MaterialsselectionshallbemadeinconformancewithECSSQST7071. OutgassingtestsshallbecarriedoutinconformancewithECSSQST7002. NOTE The need for retest of materials used for an extended period of time at a temperature higher than 50 C should be mutually agreed withthecustomer.

23

ECSSQST70C 6March2009

5.1.5
a.

Offgassing and toxicity

Spacecraft and associated equipment shall be manufactured from materials and by processes that do not cause a hazard to personnel or hardware,whetheronthegroundorinspace. ECSSQST7029 shall apply for the characterization of offgassing products. NOTE MAPTISandMILHDBK454testmethodisnot spacerelevant.

b.

5.1.6
a.

Flammability

The materials flammability resistance shall be evaluated in conformance with ECSSQST7021 for the most hazardous environment envisaged fortheiruse. NOTE ForNASASTSpayloadsseeNASASTD6001.

5.1.7
a.

Radiation

Materials used on the spacecraft external surfaces shall be assessed in conformancewithECSSQST7006inordertodeterminetheirresistance totheradiationdosageexpectedduringthemission.

5.1.8
a.

Electrical charge and discharge

External surfaces of the spacecraft shall be sufficiently conductive, interconnected and grounded to the spacecraft structure to avoid the buildupofdifferentialchargesinconformancewithECSSEST2006.

5.1.9
a.

Corrosion

For all materials that come into contact with atmospheric gases, cleaning fluidsorotherchemicals,itshallbedemonstratedthatthedegradationof properties during their anticipated servicelife is acceptable in terms of theperformanceandintegrityrequirements.

5.1.10
a. b.

Stress-corrosion

Materials used for structural and loadbearing applications (subject to tensilestress)shallbechoseninconformancewithECSSQST7036. AnymaterialnotcoveredbystandardECSSQST7036shallbetestedin conformancewithECSSQST7037.

5.1.11
a.

Fluid compatibility

Materials within the system exposed to liquid oxygen (LOX), gaseous oxygen (GOX) or other reactive fluids, both directly and as a result of single point failures when failure propagation effects cause hazardous

24

ECSSQST70C 6March2009
operation of interfacing hardware shall be compatible with that fluid in theirapplication. b. The possibility of hydrogen embrittlement occurring during component manufacture or use shall be assessed, and an material evaluation be undertaken,includingtheassessmentofadequateprotectionandcontrol.

5.1.12
a.

Galvanic compatibility

When bimetallic contacts are used, the choice of the pair of metallic materialsusedshallbeagreedwiththecustomer. NOTE Thisalsoincludesmetaltoconductive fibrereinforcedmaterialscontacts.

b. c.

GalvaniccompatibilitiesshallbeselectedinconformancewithTable51. Materials not listed in Table 51 shall be evaluated in a flightsimulated configuration using an accelerated environment to be agreed by the customer.

5.1.13
a.

Atomic oxygen

All materials considered for use on the external surfaces of spacecraft intendedforuseinLowEarthOrbit(LEO)altitudes(between200kmand 700km)shallbeevaluatedfortheirresistancetoatomicoxygen(ATOX). Testproceduresshallbesubjecttotheapprovalofthecustomer.

b.

5.1.14
a. 1. 2.

Micrometeoroids and debris


bereviewedandassessedonacasebycasebasis,and their use comply with safety evaluation and assessment results concerningdesignandapplicationcriteriaordetails.

Theeffectofimpactsbymicrometeoroidsanddebrisonmaterialsshall

5.1.15
a.

Moisture absorption and desorption

Precautions shall be taken to avoid moisture absorption during manufacture and storage of CFRPtype materials in conformance with ECSSQST7001andECSSQST7022.

25

ECSSQST70C 6March2009

Table51Compatiblecouplesforbimetalliccontacts
Gunmetal(CuZn10alloy),Pbronzes, Snbronzes CuproNickel,Albronzes,Sibronzes Gold,Platinum,Carbon,Rhodium Steel(carbon,lowalloy),Castiron Puremetalsandalloysin alphabeticalorder (includingcarbon) AluminiumCopperalloys Al(pure),AlZincalloys

Stainlesssteel18/8(300series)

Nickel,Monel,Inconel, Nickel/Molybdenumalloys

SnPballoys(all),Tin,Lead

Stainlesssteel13Cr(400series)

TitaniumandTialloys 2 3 2 1 0 0 0 0 0 3 1 0 3 0 0 0

Castiron(austenic)

Copper,Brasses

Magnesium

AluminiumCopperalloys Al(pure) AlZincalloys Cadmium Castiron(austenic) Chromium Copper,Brasses CuproNickel Albronzes Sibronzes Gold Platinum, Carbon Rhodium Gunmetal(CuZn10alloy) Pbronzes Snbronzes Magnesium Nickel Monel Inconel Nickel/Molybdenumalloys Silver SnPballoys(all) Tin,Lead Stainlesssteel18/8 (300series) Stainlesssteel13Cr (400series) Steel(carbon,lowalloy) Castiron TitaniumandTialloys Zinc Beryllium Key:

1 1

3 3 2

3 3 2 1

3 3 2 1 1

3 3 2 1 0 0

3 3 2 2 0 2 2

3 3 2 1 1 0 0

2 2 1 3 3 3 3

2 3 2 1 1 1 1

Silver

3 3 2 2 0 1 1

1 2 0 1 2 2 2

2 3 1 1 0 1 2

2 3 1 1 0 1 1

3 3 2 2 2 3 3

3 2

2 2

3 1

3 0

3 2

0 1

0 1 1

3 1 3 3

0 Canbeusedwithoutrestriction. 1 Canbeusedinanoncontrolledenvironment(e.g.assemblyareaandgeneralnoncleanroomenvironment). 2 Canbeusedinacleanroomenvironment. 3 Needsspecificmeasurestoavoidgalvaniccorrosionwhenthesecombinationsareselected.

26

Zinc,Beryllium 2 2 2 3 3 3 3 3 3 3 3 3 1 3 3 3 3

Chromium

Cadmium

ECSSQST70C 6March2009

5.1.16
a.

Mechanical contact surface effects (cold welding, fretting, wear)

For all solid surfaces in moving contact with other solid surfaces, it shall be demonstrated that the degradation of surface properties over the completemissionisacceptablefromaperformancepointofview.

5.1.17
a.

Life

Materials shall be selected to ensure sufficient life with respect to the intendedapplication.

5.2

Selection
5.2.1
a. 1.

General
those successfully used for an identical application in other space programmes similar with respect to environment constraints and lifetimetotheproposedapplication; those for which satisfactory evaluation results are obtained on samples representative of the application with a sufficient margin asregardsconditionsofuse; thoseincludedinapproveddatasources. NOTE Forexample:ECSSQST7071,ESAandNASA databanks.

Materialsshallbechosengivingpreferencetothefollowing:

2.

3.

b.

Whether the materials are already validated or remain to be validated, theirselectionshalltakeintoaccountthefollowingcriteria: 1. 2. continuityofsupply; reproducibilityofcharacteristics.

5.2.2
a.

Constraints
NOTE This is due to the possibility of whisker growth and transformation to grey tin powder at low temperatures.

Puretinfinishwithmorethan97%purityshallnotbeused.

b.

The incoming inspection of each component batch shall include the verificationoftheterminationcomposition(toavoidassemblyofpuretin finish).

27

ECSSQST70C 6March2009

5.3

Declared materials list (DML)


a. The supplier shall establish and maintain a declared materials list in conformancewithAnnexA.

5.4

Criticality analysis
5.4.1 Overview

To conform to mission requirements, the objective of the analysis is to identify whetherfurtherdataarerequired.

5.4.2
a.

Requirements

The supplier shall analyse all the materials contained in his preliminary lists with respect to criticality and in correlation with the risk analysis performed. Any material not meeting the project requirements shall be subject to a RFDtobesubmittedtothenextcustomer. Any critical material shall be subject to a RFA to be submitted to the customer. For any material not meeting the project requirements the supplier shall submitaRFAinconformancewithAnnexD. NOTE Any material when specifically required, markinginkscanbeexcluded.

b. c. d.

5.5

Evaluation and validation phases


5.5.1
a.

General

Depending on the results of the criticality analysis, the supplier shall perform an evaluation phase before the validation phase for all critical materials with unknown characteristics (new materials) or with major changesintheuseorintheconfiguration Incaseofanextensionofanexistingapplication,theevaluationindicated in5.5.1aneednotbeperformedifsoagreedwiththecustomer. Guarantied characteristics of materials and material supplier inspection methods, together with associated documents, shall be available for review at the suppliers premises before the start of evaluation or qualificationphases.

b. c.

28

ECSSQST70C 6March2009

5.5.2
a. 1. 2. 3. 4. b.

Evaluation phase
thelimitsofuse; the materials physical, chemical or functional characteristics along withtheirvaluesandtolerances; behavioural tendencies and degradation processes depending on environmentalparameters(includingsensitivitytopollution); acceptancecriteria.

Theevaluationshallconsiderthefollowingasaminimum:

When evaluation is performed, an evaluation programme (available at PDR, according to Figure 41) shall be drawn up, implemented and an evaluation report (available before CDR, according to Figure 41 and Table41)shallbedrawnup.

5.5.3
a.

Validation phase

For all critical materials, a validation programme (available at PDR) shall be drawn up by the supplier and then implemented to check or confirm that the materials satisfy the mission requirements with appropriate marginsasnecessarytoobtainvalidationstatus. Validation status shall depend on the results obtained (validation report) andthereviewofcorrespondingdocumentation(availableatCDR).

b.

5.5.4
a.

Approval phase

The material shall not receive an approval identification in the declared material list for the project unless the requirements in 5.5.2 and 5.5.3 are satisfied. Ifapprovalisnotgranted,thesupplierinchargeoftheitemshalleither: 1. 2. 3. selectanothermaterial,or propose a modified evaluation programme and resubmit for approval,or if actions 5.5.4b.1 and 5.5.4b.2 fail to achieve positive results, initiateadeviationprocedure.

b.

5.5.5
a.

Deviation request

For materials not conforming to project requirements, whether at the end of criticality analysis or of evaluation and validation tests, the supplier shallsubmitarequestfordeviationinconformancewithECSSQST1009.

29

ECSSQST70C 6March2009

5.6

Procurement of materials
5.6.1
a.

Procurement specifications

All materials shall be procured to an internationally or nationally recognized specification or an inhouse fully configured procurement specification which defines the materials properties, the materials requirements, the test methods, the acceptance criteria for the specific applications,sourceinspection(ifany)andmaterialsupplierinspection. Wherematerialsuppliersdonotacceptspecificationsandprocurementis by means of a datasheet the supplier shall introduce internal, inhouse receipt inspection to ensure that the validation status of the material is maintainedduringthesubsequentprocurements. Materials with long lead times or long procurement delays (versus the projectschedule)shallbeidentifiedbeforetheformalsubsystemPDR. Procurement shall be thoroughly planned, documented and implemented in a timely manner to obtain reliable product assurance provisionatCDR. Backupplansshallbepreparedandinitiatedwheneverthereisevidence ofdelaysortechnicalproblems. The material requirements shall be explicitly accepted by the material supplierormanufacturer.

b.

c. d.

e. f.

5.6.2
a. b.

Incoming inspection procedure

Allmaterialsshallbesubmittedtoanincominginspection. An incoming inspection procedure shall define the inspections and tests to be carried out, particularly for materials that are known to be variable intheirfinalproperties.

5.7

Use of materials
5.7.1
a. b.

Validation status of materials

The supplier shall verify that all critical materials are validated before beingusedinthemanufactureofqualificationorflightproducts. Any modification, change of condition or configuration of application shall lead to a reevaluation in conformance with the process shown in Figure41.

5.7.2
a.

Traceability of materials

ThesuppliershallapplythetraceabilityrulesdefinedinECSSQST20to allmaterials.

30

ECSSQST70C 6March2009
b. Materials should be identified by a unique reference number, code or a lot number to provide traceability should there be an incident or nonconformance, or a need for a technical investigation following failure or damage, to reconstruct the materials history, either individually (individual traceability) or by the manufacturing lot of which it was a part(lottraceability).

5.7.3
a. b.

Packaging, storage, removal from storage

The supplier shall define provisions for packaging, storage and removal fromstorageformaterials. Measurements and inspections used to guarantee the material integrity and monitoring during storage and removal from storage shall be identified.

5.7.4
a.

Limited-life materials before implementation

The supplier shall ensure that all materials which have limitedlife characteristics have their date of manufacture (when available, otherwise date of delivery) and shelflife expiry date accurately identified and clearlymarkedoneachlotorbatch. Materials which have exceeded their shelflife expiry date may be recertified only after the physical and chemical characteristics are inspected and the parameters, subject to deterioration, are evaluated for continued acceptability according to the accept and reject criteria in conformancewithECSSQST7022.

b.

5.7.5
a.

Limited-life materials after implementation

Materialswithlimitedlifeafterimplementation(suchaspropellant)shall beidentifiedandcontrolledinconformancewithECSSQST1004. NOTE Storage and mission life are criteria for the assessmentandcontrolofthosematerials.

5.7.6
a.

Materials nonconformances and alerts

Nonconformances and alerts shall be managed in conformance with ECSSQST10.

5.7.7
a.

Health and safety

Material safety data sheet or equivalent shall be available for all materials.

31

ECSSQST70C 6March2009

6 Mechanical parts control

6.1

Selection of mechanical parts


a. The supplier shall verify that all materials and processes used in the manufactureofpartssatisfythemissiontechnicalrequirements.

6.2

Selection
a. Parts shall be chosen from those successfully used for an identical application in other space programmes similar with respect to environmentconstraintsandlifetimewheneverthosepartsexist. Type reduction actions shall be implemented at all levels of the programme. Whether the parts are already qualified or remain to be qualified, their selectionshalltakeintoaccountthefollowingcriteria: 1. 2. durabilityofsupply; reproducibilityofcharacteristics.

b. c.

6.3

Declared mechanical parts list (DMPL)


a. Thesuppliershallestablishandmaintainadeclaredmechanicalpartslist inconformancewithAnnexB.

6.4

Criticality analysis
6.4.1 Overview

To conform to mission requirements, the objective of the analysis is to identify whetherfurtherdataarerequired.

32

ECSSQST70C 6March2009

6.4.2
a.

Requirements

Thesuppliershallanalyseallthepartscontainedintheirpreliminarylists with respect to criticality and in correlation with the risk analyses performedinconformancewithECSSQST1004. Critical parts shall be identified in the DMPL and included in the critical itemslist. AnycriticalpartshallbethesubjectofaRFA.

b. c.

6.5

Evaluation and qualification phases


6.5.1
a.

General

Depending on the results of the criticality analysis, the supplier shall perform an evaluation phase before the validation phase for all critical partswithunknowncharacteristicsorwithmajorchangesintheuseorin theconfiguration. Incaseofanextensionofanexistingapplication,theevaluationindicated in6.5.1aneednotbeperformedifsoagreedwiththecustomer. Guarantied characteristics of materials and material supplier inspection methods, together with associated documents, shall be available for review at the suppliers premises before the start of evaluation or qualificationphases. NOTE Refer to Table 41 for an explanation of the stepsinvolved.

b. c.

6.5.2
a.

Evaluation phase

The evaluation shall consider the following, as a minimum, for each criticalpart: 1. 2. 3. 4. thelimitsofuse, the parts physical or functional characteristics, along with its valuesandtolerances, behavioural tendencies and degradation processes depending on environmentparameters(includingsensitivitytopollution),and acceptancecriteria.

b.

When an evaluation is performed an evaluation programme (available at PDR) shall be drawn up, implemented, and an evaluation report (availablebeforeCDR)shallbedrawnup. The behaviour of the parameters to be monitored which were also recorded during the evaluation programme tests, shall serve as a referencefortheanalysisofqualificationtestresults. NOTE Example of such behaviour is variation and changeovertime.

c.

33

ECSSQST70C 6March2009

6.5.3
a.

Qualification phase

Foreachcriticalpartaqualificationprogrammeshallbedrawnupbythe supplier (of the equipment using the critical part) and then implemented to check or confirm whether the parts satisfy mission requirements with appropriatemargins. Qualification status shall depend on the results obtained (qualification report) and the reviews of corresponding documentation (available at CDR).

b.

6.5.4
a.

Approval phase

The mechanical parts shall not receive an approval identification in the declared mechanical parts list for the project unless the requirements in 6.5.2and6.5.3aresatisfied. Ifapprovalisnotgranted,thesupplierinchargeoftheitemshalleither: 1. 2. 3. selectanothermechanicalpart,or propose a modified evaluation programme and resubmit for approval,or if actions 6.5.4b.1 and 6.5.4b.2 fail to achieve positive results, initiateadeviationprocedure.

b.

6.5.5
a.

Deviation request

For parts not conforming to project requirements, whether at the end of criticalityanalysisorofevaluationandqualificationtests,thesuppliershall submitarequestfordeviationinconformancewithECSSQST1009.

6.6

Procurement of mechanical parts


6.6.1
a. b. c.

General

Mechanical parts with long lead times or procurement delays (versus the projectschedule)shallbeidentifiedbeforethesubsystemPDR. Procurementshallbeplanned,documentedandimplementedinatimely mannertoobtainreliableproductassuranceprovisionatCDR. Backupplansshallbepreparedandinitiatedwheneverthereisevidence ofpossibledelaysortechnicalproblems.

6.6.2
a. b.

Procurement specification

Eachpartshallbecoveredbyaprocurementspecificationorastandard. The procurement specifications shall define the part characteristics, requirements, tests methods, acceptance criteria, lot acceptance testing, sourceinspection(ifany)andmaterialsupplierinspection.

34

ECSSQST70C 6March2009
c. The procurement specifications shall be explicitly accepted by the part supplierormanufacturer.

6.6.3
a.

Source inspection

Forcomplexpartsrelatedtoaspecificprojectdevelopment,eachsupplier shall define the nature and frequency of their own source inspection points. Source inspection shall becarried out by the customer on the premises of thesupplier(partmanufacturer)inconformancewithECSSQST20.

b.

6.6.4
a. b.

Incoming inspection procedure

Eachpartorbatchofpartsshallbesubmittedtoanincominginspection. An incoming inspection procedure shall be established defining the inspectionsandteststobecarriedout.

6.7

Use of mechanical parts


6.7.1
a. b.

Qualification status of parts

The supplier shall ensure that all critical parts are qualified before being usedinthemanufactureofqualificationorflightproducts. Any modification, change in condition or configuration of application shall lead to a reevaluation in conformance with the process shown in Figure41.

6.7.2
a. b.

Traceability of parts

ThesuppliershallapplythetraceabilityrulesdefinedinECSSQST20to hisparts. Partsshouldbeidentifiedbyauniquereferencenumberorcodeandalot number to provide traceability where there is an incident or nonconformance, or for the purposes of technical investigations following failure or damage to reconstruct the parts history, either individually (individual traceability) or by the manufacturing lot it was partof(lottraceability).

6.7.3
a. b.

Packaging, storage, removal from storage

The supplier shall define provisions for packaging, storage and removal fromstorageforparts. Measurements and inspections used to guarantee the part integrity and monitoringduringstorageandremovalfromstorageshallbeidentified.

35

ECSSQST70C 6March2009

6.7.4
a.

Limited-life parts or parts subject to wearout

Limitedlife parts after implementation or subject to wear out shall be identifiedandcontrolled,takingintoaccountstorageandmissionlife. NOTE Examples of such parts are mechanisms, pyro initiatorsandOrings.

b.

Limitedlife parts shall be assessed as candidates to the critical items list inconformancewithECSSQST1004.

6.7.5
a.

Parts nonconformance and alerts

Management of nonconformances and alerts shall be in conformance withECSSQST10.

36

ECSSQST70C 6March2009

7 Process control

7.1

Specifications or procedures
a. b. Each process to be used in the manufacturing or assembly of a product shallbeidentifiedbyaspecificationorprocedure. Referenceshallbemadetoacceptandrejectcriteria.

7.2

Associated materials and mechanical parts


a. Thesuppliershallverifythatthematerialsandthemechanicalpartsused during the implementation of processes satisfy the requirements of this Standard.

7.3

Selection
a. Processes shall be chosen from those already verified according to the followingorderofpreferenceandpriority: 1. 2. those covered by space agencies or other governmental organizationcertificationforidenticalconditionsofuse; those for which satisfactory evaluation and verification results are obtained on samples representative of the application with a sufficientmarginasregardsconditionsofuse; those already successfully used by the same supplier for other spaceprogrammesinthesameconditionsofuse.

3. b.

Whether the processes are already verified or remain to be verified, their selectionshalltakeintoaccountthefollowingcriteria: 1. 2. 3. 4. reliability; inspectability; reworkabilityoftheprocessitem; reproducibility.

37

ECSSQST70C 6March2009

7.4

Declared processes list (DPL)


a. The supplier shall establish and maintain a declared processes list in conformancewithAnnexC.

7.5

Criticality analysis
7.5.1 Overview

To conform to mission requirements, the objective of the analysis is to identify whetherfurtherdataisrequired.

7.5.2
a.

Requirements

Thesuppliershallanalysealltheprocessescontainedintheirpreliminary lists with respect to criticality and in correlation with the risk analyses performed. CriticalprocessesshallbeidentifiedintheDPLandincludedinthelistof criticalitems. AnycriticalprocessshallbethesubjectofanRFA. Specialprocessesshallbeidentifiedandcontrolled. Process control shall be ensured by means of procedures or personnel certificationorinlineprocesscontrol. Wheneverfeasibleastatisticalprocessmaybecarriedout.

b. c. d. e. f.

7.6

Evaluation and verification phase


7.6.1
a.

General

Depending on the results of the criticality analysis, the supplier shall perform an evaluation phase before the validation phase for all critical processes which are new or with major changes in the use or in the configuration. Incaseofanextensionofanexistingapplication,theevaluationindicated in7.6.1aneednotbeperformedifsoagreedwiththecustomer. For confidential processes, the supplier shall prove that the process has beenverified. NOTE1 For example, by presenting a verification certificate from space agencies or other governmentalorganizationresponsibletocheck theapplicabilityofthisverification. NOTE2 Refer to Table 41 for an explanation of the stepsinvolved.

b. c.

38

ECSSQST70C 6March2009

7.6.2
a.

Evaluation phase

The evaluation shall consider the following as a minimum for each criticalprocess: 1. 2. 3. thelimitsofuse, the values, determined by test samples or technology samples, of relevantparametersandtheirtolerances,and acceptancecriteria.

b.

Whenanevaluationisperformed,thesuppliershallprovide 1. 2. anevaluationplanatPDRand anevaluationreportbeforeCDR.

7.6.3
a. b. c.

Verification phase

For each critical process, the supplier shall implement a verification programme. The verification programme shall be defined in conformance with existingECSSornationalagencystandardsofverification. The supplier shall ensure that the processes satisfy the mission requirements and that the parameters needed for the product design are definedsoastoobtainverificationstatus. Verification status shall depend on the results obtained (verification report) and the review of corresponding documentation (available at CDR).

d.

7.6.4
a.

Approval phase

The processes shall not receive an approval identification in the declared processes list unless requirements in 7.6.2 and 7.6.3 are satisfied. If approvalisnotgranted,thesupplierinchargeoftheitemshalleither 1. 2. 3. selectotherprocesses,or propose a modified evaluation programme and resubmit for approval,or if actions 7.6.4a.1 and 7.6.4a.2 fail to achieve positive results, initiateadeviationprocedure.

7.6.5
a.

Deviation request

For processes not conforming to project requirements, whether at the end of criticality analysis or of evaluation and verification tests, the supplier shallsubmitarequestfordeviationinconformancewithECSSQST1009.

39

ECSSQST70C 6March2009

7.7

Use of a process
7.7.1
a. b.

Verification status of a process

The supplier shall confirm that all critical processes have been verified beforebeingusedinthemanufactureofqualificationorflightproducts. Any modification, change of condition or configuration of application shall lead to a reevaluation in conformance with the process shown in Figure41.

7.7.2
a.

Re-verification of a process

When a process needs to be reverified, a request for approval (RFA) shall be established and a reverification programme shall be implemented. NOTE Anyprolongedstoppageinmanufacturing,any major change of the facilities or procedures or any transferof production to another entity can invalidate partially or completely the initial verificationofaprocess.

7.7.3
a.

Implementation of a process

Before implementation of a process, the supplier shall ensure that personnel are trained and that environment, means and documentation areadequate. Thisverificationshallensurethat: 1. manufacturing and quality control tools associated with the process are adequate, calibrated and properly maintained are used under appropriate environmental and cleanliness conditions, see clause4.4, personnelareproperlytrainedandcertified,and the processes specifications, manufacturing and inspection procedures and workmanship standards including clear definition ofmanufacturingoperationsandclearacceptancecriteriaexist. NOTE1 Photographically documented if possible for visual acceptance criteria at the appropriate workandinspectionstations. NOTE2 For planning of manufacturing, assembly and integration operation and inspection see ECSS QST20.

b.

2. 3.

7.7.4
a.

Traceability of processes

Traceability of processes shall be ensured in conformance with ECSSQ ST20.

40

ECSSQST70C 6March2009

7.7.5
a.

Process nonconformances and alerts

Nonconformances and alerts shall be processed in conformance with ECSSQST10.

7.7.6
a.

Mandatory inspection points (MIP)

MIPsshallbedefinedinconformancewithECSSQST20.

7.7.7
a.

Packaging, storage, removal from storage

The supplier shall define provisions for packaging, storage, and removal from storage for products or semifinished products before and after implementationofprocesses.

41

ECSSQST70C 6March2009

Annex A (normative) Declared materials list (DML) - DRD

A.1

DRD identification
A.1.1 Requirement identification and source document

ThisDRDiscalledfromECSSQST70,requirement4.2.3a.

A.1.2

Purpose and objective

ThepurposeoftheDMListohaveadetailedrecordofallthematerialsusedto producetheproductsofaprojectorprogramme. The datain the DML make possible toassess whether the materials are suitable for a specific application, at the supplier and the customer levels (in the approvalstatuscolumn). The DML is prepared for each Configuration item at the relevant stages (e.g. atthestart,PDR,CDRandQR)asdefinedintheflowchartgiveninFigure41. ThefollowingdocumentsarelinkedtotheDML: thedeclaredprocesslist(DPL); requestforapproval(RFA)materials.

A.2

Expected response
A.2.1
<1>
a. 1. 2.

Scope and content


Materialsgroups

TheDMLshallcontainthefollowingstatements: Materials are classified into 20 groups depending on their type or theirmainuse,seeTableA1. Primers are classified in the group of their associated component.

42

ECSSQST70C 6March2009
3. Where no project requirement exists for a separate DMPL, mechanical partsareentered on the DML asa separate group with thecorrespondingnumbers.

b.

If new groups are created, for a given project, these shall have numbers over21.

TableA1:Materialgroupnumbers Group number


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Description
Aluminiumandaluminiumalloys Copperandcopperalloys Nickelandnickelalloys Titaniumandtitaniumalloys Steels Stainlesssteels Fillermetals:welding,brazingsoldering Miscellaneousmetallicmaterials Opticalmaterials Adhesives,coatings,varnishes Adhesivetapes Paintsandinks Lubricants Pottingcompounds,sealants,foams Reinforcedplastics(includingPCBs) Rubbersandelastomers Thermoplastics(e.g.nonadhesivetapesandfoils[MLI]) Thermosetplastics(includingPCBs) Materialaspectsofwiresandcables Miscellaneousnonmetallicmaterials,e.g.ceramics

<2>
a.

ContentsoftheDML
The DML shall include the information stated in Figure A1, where the header information identifies the list as the declared materials list and includestheissuenumberanddateofissue,asfollows: 1. Itemnumber(applicabletoequipmentmanufacturerlevelonly) (a) This consists of the material group identifier and the user code.Ittakestheformof: <groupnumber>.<identifierwithin number>.<usercode> NOTE Forexample:11.5.1.KOF. the group>.<running

43

ECSSQST70C 6March2009
(b) Characteristicsoftheitemnumberare: Theuser,identifiedbyanagreedusercodeforthe project. Oneonlypermaterialtype. Doesnotchangeduringthelifeofthematerialslist (subitemsarepermittedwhendeemednecessary). 2. Commercialidentificationorstandardizeddesignation (a) (b) (c) Enterthecorrectandstandarddesignation,suchasthetrade nameplusnumber. If no trade name exists, enter the manufacturers name plus number. For metal alloys, the Aluminium Association (AA) system is recommended for aluminium alloys, and the American Iron andSteelInstitute(AISI)systemforsteel.Forothermetalsor alloys,themainconstituentisenteredfirstexceptinthecase ofatraditionalname. Forexample:brassorbronze.

NOTE (d)

For each material, as designated in A.2.1<2>a2(a) to(c), use a unique item number. If several lines are used for different applicationsorprocessing,addsubitemnumbers.

3.

Chemicalnatureandproducttype (a) For metallic materials, add the condition as procured if applicable. Example of such conditions are rolled and heat treatment.

NOTE (b)

Whereasemifinishedproductisprocured,givetherelevant state. Exampleofsuchstateareform,plateandsheet.

NOTE (c)

Give the thickness of the material, that can be an important parameter. Examples of chemical nature are: epoxy resin, polyurethaneadhesive,Ti6Al4V.

NOTE 4.

Procurementinformation (a) (b) Manufacturer or distributor: name of the manufacturer and nameofthedistributorifdifferent. Procurement specification: reference of the procurement specification with issue, revision and date. It may be replaced by a national or international specification or standard, if this exists, and identifies the source of procurement, if relevant. Indication of issue or date is not applicablewhendatasheetsareused

44

ECSSQST70C 6March2009
5. Processingparameters List herea summary of the process parameters applied by the user oftheprocess. NOTE E.g. mixture proportions, cure temperature, special cleaning agent, surface treatment, thermal treatment and temperature, and referencetospecificationnumber.

6.

Useandlocation (a) Use codes able to define the location of the material with respecttothe: subsystem; particularpieceofequipment(boxoritem); useoftheequipment,e.g.astructuralelement,thermal control,electricalinsulation. NOTE If the CI number is not included in the list header, then a suitable abbreviation of the relevantsubsystemisincluded.

(b) 7.

Include any restrictions that apply to the use of a particular materialinthecorrespondingcommentcolumn.

Environmentalcode TheenvironmentalcodeisdefinedusingTableA2.

TableA2:Environmentalcode Radiation/UV/ATOX(R)a
G:Geostationary L:Loworbit B:Radiationbelt I:Interplanetary P:Planetary
a

Ambience(A)
V:Vacuum H:Hermetic M:Manned E:Elevatedpressure

Temperature(T)b,c
1:0Kto100K 2:101Kto200K 3:201Kto300K

S:Outsideshadow L:Outsidelight

Forallmaterials,aletterisselectedfromthelefthandcolumn.Formaterialsonthesurfaceofthe spacecraft,theletterLorSisadded. Thermalcyclingtobeindicatedbytwovalues,e.g.3/5.

b c

RT(roomtemperature)canbeacceptedasacodebetween283K(10C)and313K(40C).

NOTE:Thematerialsthatareataboundarybetweenenvironmentsaredescribedbytwosetsofcodes.

8. Sizecode The size code is indicated by an alphanumeric combination, such asA5,V2orM3,asinTableA3.

45

ECSSQST70C 6March2009 TableA3:Sizecode Sizecode Value


0 1 2 3 4

0<AorVorM1 1<AorVorM10 10<AorVorM100 100<AorVorM1000


Visthevolume,incm3 Misthemass,ing

where: Aisthearea,incm2

9. Validation references, justification for approval and prime commentsandprimeapproval (a) Make reference to relevant test data that demonstrates the acceptability of the material under the environmental conditions and the application relevant to the particular project concerned. Specifically, in column 9.1, corrosion (CORR), stress corrosion (SCC), flammability (FLAM), offgassing (OFFG) and outgassing (OUTG) data or reportreferencesareentered. Use standard abbreviations to summarize the acceptance statusofamaterialforaparticularproperty. Use the justification for approval (column 9.2) and prime approval (column 9.3) columns for any additional informationtoobtaincustomerapproval. Standard abbreviations are used to summarize the acceptability or otherwise of a material for a specific property.Thesearedefinedfortheproject. SelectthesupplierapprovalstatuscodefromTableA4.

(b) (c)

(d)

(e) 10.

Customerapprovalstatuscodeandcomments (a) (b) SelectthiscodefromTableA4. Includeadditionalcommentswhereappropriate.

46

ECSSQST70C 6March2009 TableA4:Approvalstatus Code


A X

Description
Approved. AllmaterialsclassifiedAmaybeusedwithoutrestriction. ApprovedwithanRFA. Thesematerialsaresubjectedtoanevaluationorvalidation programme.TheRFAnumberisenteredasacomment.

Approvedwithaconcession. Thesematerialsdonotmeettherequirementsbutareusedfor functionalreasons.Theconcessionnumberisenteredasa comment.

Pendingadecision. Materialsforwhichanevaluationreportoraconcessionis waitingforthecustomersprovisionalordefinitiveapproval.

Open. Newmaterialsormaterialsforwhichinvestigationsand validationsareinprogress.

R D

Rejected. Deleted. Thisclassificationisusedforamaterialthatisnolongerused.

NOTE Ifapprovalcannotbegivenandoneoftheothercodesareentered,enter thecommentsintheappropriatecolumn.

A.2.2
a. b.

Special remarks

The change record shall list the successive issues and their release dates sincethefirstformalissueofthedocument. The change record shall include a brief description of the updates which contributedtoeachissueorrevision. NOTE This DRD recommends the format and define thecontentwithintheframeworkofaprojector aprogramme.

47

ECSSQST70C 6March2009

DECLAREDMATERIALSLIST(DML)
Programmename:ABCDEFG CIno.:12345676890 Group(Title):abcdefg Docno.:001 Issue/Revision:1/4 Date:01.10.2000 Page:1

9 1 2 3
1)Chemical nature 2)Producttype

4
1)Manufacturer/ suppliername 2)Procurement spec. Issue/RevDate

5
Summaryof process parameters

6
1)Subsystem 2)Equipment 3)Use

7
1)R 2)A 3)T

8
1)A 2)V 3)M

9.1

9.2

9.3

10
Customer approvalstatus/ comments

Itemno.and Commercial identification usercode or standardized designation

Acronym/rating/ 1)Justificationfor Prime ValidationRef. approval approval forapplicable status 2)Primecomments properties

1.2.1.TXES

AZ5GU

1)Al.Zn5.6Mg2.5 1)AlmetPechiney Cdu1.6,Cr0.3 2)CRB527 eq.AA7075 2)Plate 01/02/01.02.1996 1)DowCorning 2)E3846MC10S 02/02/1984

T7351andIridit 1)PL 14heat 2)E4package treatment 3)Structure Mixture: 10/1ing Curing: 4h/65C Resin/Cat: 100/65g 4h/40C +48h/100C 1)PCU 2)Experiment tray 3)Partpotting 1)GP 2)Platform 3)Package potting

1)LS 2)V 3)3 1)G 2)V 3)34

1) 2) 3)M3 1) 2) 3)M3

1)UsedonETS2 2)

10.1.1.ETCA DC93500

1)Silicon 2)Twoparts

1)ECSSQST7001 A 2)

11.5.1.KOF

ECCOFOAM EPH

1)Polyurethane 2)Resin/Catalyst 1202H

1)Emersonand Cuming 2)SP/FOK/05/684 03/01/25.06.1992

1)LS 2)M 3)34

1) 2)V3 3)

1)DU96352 2)Usedat T>100C (Riskofdistortion beyond)

FigureA1:ExampleofarealizedDML

48

ECSSQST70C 6March2009

Annex B (normative) Declared mechanical parts list (DMPL) DRD

B.1

DRD identification
B.1.1 Requirement identification and source document

ThisDRDiscalledfromECSSQST70,requirement4.2.3b.

B.1.2

Purpose and objective

The purpose of the DMPL is to have detailed record of all the mechanical parts usedtoproducetheproductsofaprojectorprogramme. ThedataintheDMPLmakepossibletoassesswhetherthemechanicalpartsare suitable for a specific application, at the supplier and customer levels (in the approvalstatuscolumn). TheDMPLispreparedforeachConfigurationitemattherelevantstages(e.g. Start, PDR, CDR and QRR) as defined in the flow chart given in Figure 41 of ECSSQST70. The following document is linked to the DMPL: request for approval (RFA) mechanicalparts.

B.2

Expected response
B.2.1
<1>
a.

Scope and content


Mechanicalpartsgroups

TheDMPLshallcontainthefollowingstatements: Mechanical parts are classified into 11 groups depending on their type ortheirmainuse(seeTableB1).

b.

If, for a given project it is considered necessary to create new groups, theseshallhavenumbersover61.

49

ECSSQST70C 6March2009

c.

ItemsthatappearintheEEEpartslistshouldnotberepeatedhere. NOTE For example, heaters, some valves, thermostats, relays,transformercoilsandsolenoids.

TableB1:Mechanicalpartgroupnumbers Group number


51 52 53 54 55 56 57 58 59 60 61

Description
Spacingparts(e.g.washersandspacers) Connectingparts(e.g.bolts,nuts,rivets,insertsand clips) Bearingparts(e.g.ballbearingsandneedlebearings) Separatingparts(e.g.pyrotechnics,springsandcutters) Controlparts(e.g.gears) Fluidhandlingparts(e.g.diffusers) Heatingparts Measuringinstruments(e.g.gaugesandthermocouples) Opticalpassiveequipment Magneticparts Otherparts

<2>
a.

ContentsoftheDMPL
The DMPL shall include the information in Figure B1, where the header information identifies the list as the declared mechanical parts list and includestheissuenumberanddateofissue,asfollows: 1. Itemnumber(applicableatequipmentsupplierlevelonly) (a) This consists of the mechanical part identifier and the user code.Ittakestheformof: <group number>.<identifierwithin the group>.<running number>.<usercode> NOTE (b) Forexample:7.2.1.ACSA.

Characteristicsoftheitemnumberare: Identifythesubcontractorbyanagreedusercodeforthe project. Oneonlypermechanicalparttype. Doesnotchangeduringthelifeofthemechanicalparts list.

2.

Commercialidentification (a) (b) Enter the correct and standard designation, such as trade nameplusnumber. If no trade name exists then enter the manufacturers name andnumber.

50

ECSSQST70C 6March2009

3.

Typeofpart Describethematerialandsurfacetreatment(ifapplicable).

4.

Procurementinformation (a) (b) Manufacturer or distributor: name of the manufacturer and nameofthedistributorifdifferent. Procurement specification: reference of the procurement specification with issue, revision and date. It may be replaced by a national or international specification or standard if this exists and identifies the source of procurementifrelevant.

5.

Elementaryfunction,maincharacteristics (a) (b) Enterthefunctionofthemechanicalpart. Enterthemaincharacteristicsofthemechanicalpart. For example,number of revolutions per minute foraballbearing.

NOTE 6.

Useandlocation Use codes able to define the location of the mechanical part with respecttothe: (a) (b) (c) subsystem; particularpieceofequipment(boxoritem); useoftheequipment.

7.

Environmentalcode TheenvironmentalcodeisdefinedusingTableB2.

TableB2:Environmentalcode Radiation/UV/ATOX(R)a
G:Geostationary L:Loworbit B:Radiationbelt I:Interplanetary P:Planetary
a

Ambience(A)
V:Vacuum H:Hermetic M:Manned E:Elevatedpressure

Temperature(T)b,c
1:0Kto100K 2:101Kto200K 3:201Kto300K

S:Outsideshadow L:Outsidelight

Forallmechanicalparts,aletterisselectedfromthelefthandcolumn.Formechanicalpartsonthe surfaceofthespacecraft,theletterLorSisadded. Thermalcyclingtobeindicatedbytwovalues,e.g.3/5.

b c

RT(roomtemperature)canbeacceptedasacodebetween283K(10C)and313K(40C).

8. Criticality Enter Cfor critical orN for noncritical. Ifa mechanical part is considered critical, describe the reason for the criticality and methodsofcontrol.

51

ECSSQST70C 6March2009

9.

Supplierreference,primecommentsandprimeapprovalstatus (a) Use the supplier reference, prime comments and approval columns to enter any additional information that can be necessaryinordertoobtaincustomerapproval. This information comprises reference and issue of the RFA or approval, mechanical parts justification file, evaluation reportsanddeviationrequests. Make reference to the relevant test data that demonstrates acceptability of the mechanical part under the environment conditions and the application relevant to the particular projectconcerned. Use standard abbreviations, defined by the customer, to summarize the acceptance status of a mechanical part for a particularproperty. In order to justify the use of a material for flammability resistance, list here the material thickness and height of oxygenshare. SelecttheprimeapprovalstatuscodefromTableB3.

(b)

(c)

(d)

(e)

(f) 10.

Thecustomerapprovalstatuscodeandcomments (a) (b) SelectthiscodefromTableB3. Includeadditionalcommentswhereappropriate.

52

ECSSQST70C 6March2009

TableB3:Approvalstatus Code Description


A Approved AllmechanicalpartsclassifiedAmaybeusedwithout restriction. X ApprovedwithanRFA Thesemechanicalpartsaresubjectedtoanevaluationor validationprogramme.TheRFAnumberisenteredasa comment. W Approvedwithaconcession Thesemechanicalpartsdonotmeettherequirementsbutare usedforfunctionalreasons.Theuseofsuchmechanicalpartsis approvedbythecustomer.Theconcessionnumberisenteredas acomment. P Pendingadecision Mechanicalpartsforwhichanevaluationreportoraconcession iswaitingforthecustomersprovisionalordefinitiveapproval. O Open Newmechanicalpartsormechanicalpartsforwhich investigationsandvalidationsareinprogress. R D Rejected. Deleted Thisclassificationisusedforamechanicalpartthatisnolonger used.
NOTE: Ifapprovalcannotbegivenandoneoftheothercodesareentered,enter thecommentsintheappropriatecolumn.

B.2.2
a. b.

Special remarks

The change record shall list the successive issues and their release dates sincethefirstformalissueofthedocument. This record shall include a brief description of the updates which contributedtoeachissueorrevision. NOTE This DRD recommends the format and defines thecontentwithintheframeworkofaprojector aprogramme.

53

ECSSQST70C 6March2009

DECLAREDMECHANICALPARTSLIST(DMPL)
Programmename:ABCDEFG

CIno.:12345676890 Group(Title):abcdefg

Docno.:001 Issue/Revision:1/4

Date:01.10.2000 Page:1

9 1
Itemno.and usercode

2
Commercial identification

3
Typeofpart

4
1)Procurement specification 2)Issue/Revision/ Date

5
1)Elementary function 2)Main characteristics 1)Separator ring 2)Heat conductor

6
1)Subsystem 2)Equipment 3)Use 1)TC 2)Plateinterface 3)Spacingand heatinspection 1)PTANK 2)plate 3)fixing

7
1)R 2)A 3)T 1)G 2)V 3)34

8
1)Criticality

9.1
1)Supplier Reference

9.2
Primeapproval status

10
Customer approval status/comments

2)Reasonand methodof 2)primecomments control 1)N 2) 1)Usedonall projects 2)

51.2.1.ACSA

ESA003521000 Copper/AL 120 bimetalring

1)AIEV 2)Fromcatalogue

52.2.1.ASAD

A0090TX...XA Ti6Al4V screws>M4

1)Whiteareo 2)ASNA0090 DSN2413 1)Magnetics,Data sheet 2)SP/MAGN/003 01.02/03.06.1999

1)assembly 2)

1)G 2)V 3)34 1)G 2)V

1)N 2)

1)UsedonTC2 2)

60.1.1.ACSA

42908TC/F

Ferritecores magnetic

1)Coilcoreof transformer 2)Magnetic component

1)TC 2)Southface

1)C 2)tobe qualified

1) 2)

3)Heatregulation 3)34

FigureB1:ExampleofarealizedDMPL

54

ECSSQST70C 6March2009

Annex C (normative) Declared process list (DPL) - DRD

C.1

DRD identification
C.1.1 Requirement identification and source document

ThisDRDiscalledfromECSSQST70,requirement4.2.3c.

C.1.2

Purpose and objective

The purpose of the DPL is to have a detailed record of all the processes used to producetheproductsofaprojectorprogramme. The data in the DPL make possible to assess whether the processes are suitable for a specific application, at the supplier and customer levels (in the approval statuscolumn). The DPL is prepared for each Configuration item at the relevant stages (e.g. Start, PDR, CDR and QRR) as defined in the flow chart given in Figure 41 of ECSSQST70. ThefollowingdocumentsarelinkedtotheDPL: declaredmateriallist(DPL), requestforapproval(RFA)processes.

C.2

Expected response
C.2.1
<1>
a.

Scope and content


Processgroups

TheDPLshallcontainthefollowingstatements: Processes are classified into 17 groups depending on their type or their mainuse,seeTableC1.

b.

If, for a given project it is considered necessary to create new groups, theseshallhavenumbersover17.

55

ECSSQST70C 6March2009

TableC1:Processgroupnumbers Group number


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Description
Adhesivebonding Compositemanufacture Encapsulation/moulding Painting/coating Cleaning Welding/brazing Crimping/stripping/wirewrapping Soldering Surfacetreatments Plating Machining Forming Heattreatment Specialfabrication:processesdevelopedspecificallyforthe programme Marking Miscellaneousprocesses Inspectionprocedures

<2>
a.

ContentsoftheDPL
The DPL shall include the information in Figure C1, where the header information identifies the list as the declared processes list and includes theissuenumberanddateofissue,asfollows 1. Itemnumber(applicabletoequipmentsupplierlevelonly) (a) This consists of the process identifier and the user code. It takestheformof <group number>.<identifierwithin the group>.<running number>.<usercode> NOTE (b) Forexample:1.2.1.SSEX

Characteristicsoftheitemnumberare: Identifythesubcontractorbyanagreedusercodeforthe project. Oneonlyperprocesstype. Doesnotchangeduringthelifeoftheprocesslist.

56

ECSSQST70C 6March2009

2.

Processidentification Indicate the correct and standard identification of the process, e.g. theprocessnameortitle:bonding,coatingorsoldering.

3.

Specification (a) (b) Identifythenameorabbreviationoftheprocessexecutor. Make a reference to the associated procedure, together with theissue,revisionanddate. For example, national, international, EN, ISO, ECSSorcompanyinhouse.

NOTE 4.

Processdescription Enterhereashortdescriptionoftheprocess.

5.

Useandlocation Use codes able to define the location of the process with respect to the: (a) (b) (c) subsystem, particularpieceofequipment(boxoritem), useoftheequipment. For example, a structural element, thermal control,electricalinsulation).

NOTE 6. 7.

Thiscolumnnumberisnotused. Associateditemnumbers Enter the associated material list (DML) or mechanical parts list (DMPL)withtheprocess.

8.

Criticality (a) (b) EnterCforcriticalorNfornoncritical. If a process is considered to be critical, Enter the references totherelevantRFA.

9.

Supplierreference,primecommentsandapproval (a) Use the supplier reference and approval columns to enter any additional information that can be necessary to obtain customerapproval. SelectthesupplierapprovalstatuscodefromTableC2.

(b) 10.

Thecustomerapprovalstatuscodeandcomments (a) (b) SelectthiscodefromTableC2. Includeadditionalcommentswhereappropriate.

57

ECSSQST70C 6March2009

TableC2:Approvalstatus Code Description


A X Approved AllprocessesclassifiedAmaybeusedwithoutrestriction. ApprovedwithanRFA Theseprocessesissubjectedtoanevaluationorvalidation programme.TheRFAnumberisenteredasacomment. W Approvedwithaconcession Theseprocessesdonotmeettherequirementsbutareusedfor functionalreasons.Itisimportanttoreducetheuseofsuch processestoaminimum.Alldeviationrequestsareapproved bythecustomer.Theconcessionnumberisenteredasa comment. P Pendingadecision Processesforwhichanevaluationreportoraconcessionis waitingforthecustomersprovisionalordefinitiveapproval. O Open Newprocessesorprocessesforwhichinvestigationsand validationsareinprogress. R D Rejected. Deleted Thisclassificationisusedforaprocessthatisnolongerused. Ifapprovalcannotbegivenandoneoftheothercodesareentered,enter thecommentsintheappropriatecolumn.

C.2.2
b. c.

Special remarks

The change record shall list the successive issues and their release dates sincethefirstformalissueofthedocument. This record shall include a brief description of the updates which contributedtoeachissueorrevision. NOTE This DRD recommends the format and define thecontentwithintheframeworkofaprojector aprogramme.

58

ECSSQST70C 6March2009

DECLAREDPROCESSLIST(DPL)
Programmename:ABCDEFG CIno.:1234567890 Group(Title):abcdefg Docno.:001 Issue/Revision:1/5 Date:14.05.2000 Page:1

9 1
Itemno.and usercode

2
Process identification

3
1)Username 2)Associated procedure issue/revision/ date

7
Associated DMLorDMPL itemnumber

8
1)Criticality 2)Reasonfor criticality

9.1
1)Supplier Reference 2)Primecomments

9.2
Primeapproval status

10
Customerapproval status/comments

Processdescription 1)Subsystem code 2)Equipment code 3)Use 1)BE3 2)C5board 3)Tofixparts

1.2.1.SSEX

Bonding

1)EREMS

Applyingaspotof gluewitha 2)E/SQ/PI/012 stainlesssteel 02/01/02.08.1984 dispenser

6.1.2.ETC

1)N 2)

1)Usedon ANTARES 2)

4.3.1.KOF

Coating

1)CERCO

Coatingby paintbrushorby 2)E/SQ/PI/023 immersioninthe 02/01/08.12.1985 resin

1)BE3 2)C1C2boards 3)Protectionof CIandEEE parts 1)BE3 2)C3 3)

2.1.1.KOF

1)N 2)

1)Usedon PASTEC, ANTARES 2)

8.3.1.KOF

Vapourphase solderingof SMDs

1)EREMS 2)E/SQ/PI/026

ECSSQST7038

15.1.1.AST

1)C 2)

1)QM/04L123/ BD/MHTable1 2)

01/02/09.09.1997

FigureC1:ExampleofrealizedDPL

59

ECSSQST70C 6March2009

Annex D (normative) Request for approval (RFA) - DRD

D.1

DRD identification
D.1.1 Requirement identification and source document

ThisDRDiscalledupfromECSSQST70,requirement5.4.2d.

D.1.2

Purpose and objective

The objective of an RFA is to enable the supplier to request from the customer permissiontouseacriticalmechanicalpart,materialorprocess. The information provided by the supplier makes possible for the customer to assess whether the critical mechanical part, material or process is suitable for a specificapplication. The RFA is prepared for each critical mechanical part, material or process at the relevantstagesasdefinedintheinflowchartgiveninFigure41ofECSSQST70. ThefollowingdocumentsarelinkedtotheRFA: declaredmechanicalpartslist; declaredmaterialslist; declaredprocesslist.

D.2

Expected response
D.2.1
a.

Scope and content

TheRFAshouldcontaintheinformationinFigureD1(pages1and2),as follows: 1. The header information, identifying the document as a request for approval together with the project logo and project name, RFA reference,issuerevisionanddate. Originator Originatorsnameandreference. 3. Location Subsystemandequipmentcodes.

2.

60

ECSSQST70C 6March2009

4.

Itemdescription Briefdescriptionoftheitem.

5.

PMPinformation TheDML,DMPLorDPLitemnumberandlistreference.

6.

Itemstatus,includingthefollowinginformation: (a) (b) (c) (d) (e) (f) (g) (h) manufacturersnameandqualificationreference; suppliersnameandqualificationstatus; productormaterialspecification; procurementspecification; processorhandlingspecification; otherrelatedprocessorhandlingspecifications; verificationorqualificationspecification; reportonverificationorqualification.

7.

ReasonforRFA EnterthereasonfortheRFA.

8.

Applicationandlocationdetails Enter here the details of the application and exact location of the item. GivethereferenceintheCIL.

9.

Evaluationandvalidationprogramme Referenceanddetailsofmaintests.

10. 11.

SubcontractorsupplierapprovalforthefirstissueoftheRFA. Customer initial decision, to be entered on first issue of the RFA providing: (a) (b) (c) thedecisionconcerningtheproposedmaterial, the requirement to perform tests (deviation request as necessary),and thedecisionconcerningtheproposedtestprogramme.

12. 13. 14. 15.

Customersandfinalcustomers(ifapplicable)signature Justification results obtained with reference to the suppliers validationreportandconclusion. SubcontractorsupplierapprovalonRFAfinalissue. FinalapprovalstatusoftheRFAbythecustomer.

D.2.2
a.

Special remarks

TheRFAshallbecompletedbythesupplier(parts1to10,13and14)and thecustomer(parts1112and15).

61

ECSSQST70C 6March2009

1 Company:

Project:

Reference:RFA Issue Revision Date


Page 1of2

Requestforapproval(RFA)
2 Originator:
Originatorreference:

3 Subsystem:
Equipment:

4 Itemdescription:

5 PMPlistitemnumber:
PMPlistreference:

6 Itemstatus
Manufacturer: Supplier: Product/materialspecification: Process/handlingspecification: Verification/qualificationspecification: Manufacturerqualificationreference: Qualificationstatus: Procurementspecification: Relatedspecification: Report:

7 ReasonforRFA
CILReference:

8 Application/locationdetails:

9 Evaluation/validationprogramme(title,reference) Tests

Plan,procedures,scheduletobeattached FigureD1:ExampleofRFA(Page1of2)

62

ECSSQST70C 6March2009

Company:

Project:

Reference:RFA Issue Revision Date


Page 2of2

Requestforapproval(RFA)
10
Supplierapprovalon RFAfirstissue
Materialsandprocesses responsible PAresponsible Projectresponsible

Comments:
Materialsandprocesses responsible

11 DecisiononRFAfirstissue:
Requestrefused: Submitdeviation: Proceedwithvalidationprogramme:

12 Decision
Customer agree/disagree Finalcustomer(if applicable) agree/disagree

PAresponsible

Projectresponsible

13 Justificationresults
Validationreport(titleandreference) Conclusion:

Validationreporttobeattached
RFAfinalissue
Materialsandprocesses responsible PAresponsible Projectresponsible

14 Supplierapprovalon

15 DecisiononRFAfinal
issue

Materialsandprocesses responsible

PAresponsible

Projectresponsible

Customer agree/disagree Higherlevelcustomers (asnecessary) agree/disagree

FigureD1:ExampleofRFA(Page2of2)

63

ECSSQST70C 6March2009

Annex E (informative) Relationship between materials, mechanical parts, processes activities and programme phases

E.1

Feasibility phase (phase A)


In phase A, the materials, mechanical parts and processes product assurance tasksarecarriedoutinorderto: a. b. c. identify main programme constraints on materials, mechanical parts and processes, definethepolicy,and plantheproductassurancetasksfortheprojectdefinitionphase.

E.2

Preliminary definition phase (phase B)


In phase B, the materials, mechanical parts and processes product assurance tasksarecarriedoutinorderto: a. b. c. defineoridentifyrequirements, identify main new items needed and plan corresponding necessary actionsforphaseC, plan the product assurance tasks for the detailed design, development, manufacturing, integration and test phase and prepare the materials, mechanicalpartsandprocessesplanaspartofthePAplan,and supportpreliminarydesignreview.

d.

E.3

Detailed definition and production phase (phase C or D)


In phase C or D, the materials, mechanical parts and processes product assurancetasksarecarriedoutinorderto: e. f. identifymaterials,mechanicalpartsandprocesses; issuepreliminarylists;

64

ECSSQST70C 6March2009

g. h. i. j. k. l. m. n. o. p. q. r.

identifycriticalitems; establishorreviewRFA; supportmandatoryinspectionpointsidentification; establishevaluationprogramme,performtestorreviewtestresults; establish validation, qualification, or verification programmes (e.g. performtestsorreviewtestresults); supportnonconformanceprocessing(NRB,failurereviewboard); establishtheasdesignedlists; supportthecriticaldesignreview; supportthequalificationreview; establishthefinalasdesigned(updated)lists; supportreleaseofmanufactureofflighthardware; supportfinalacceptancereview.

E.4

Utilization phase (phase E)


In phase E, the materials, mechanical parts and processes product assurance tasksarecarriedoutinorderto: a. b. c. supporttheseriesmanufacturingofrecurringproducts, supporttheinvestigationofoperationalphaseanomalies,and update the asflown materials lists to incorporate the new materials that have been added or changed as a result of NCR activities. In particular, the PMP lists should include the actual materials flown on manned and reusablespacecraftandtheirpayloads.

65

ECSSQST70C 6March2009

Annex F (informative) MMPP documents delivery with respect to milestones


Scope of the Table F1 is to present relation of documents associated to Parts, material and processes activities to support project review objectives as specifiedinECSSMST10. NOTE This table constitutes a first indication for the data package content at various reviews. The full content of such data package is established as part of the business agreement, which also defines the delivery of the document between reviews.

The table lists the documents necessary for the project reviews (identified by +). The various crosses in a row indicate the increased levels of maturity progressively expected versus reviews. The last cross in a row indicates that at thatreviewthedocumentisexpectedtobecompletedandfinalized. NOTE All documents, even when not marked as deliverables in Table F1 are expected to be available and maintained under configuration management as per ECSSMST40 (e.g. to allowforbacktrackingincaseofchanges).

TableF1presentsthereviewsatwhichthedifferentissuesoftheECSSQST70 andECSSQST7001documentsareexpected. NOTE Other MMPP deliverable document requirements definitions (DRDs) are contained intheECSSQST70XXdocuments.

66

ECSSQST70C 6March2009

TableF1:MMPPdocumentsdeliveryw.r.t.milestones Phase DocumentTitle


0 MDR Declaredmaterialslist (DML) Declaredmechanicalparts list(DMPL) Declaredprocesslist(DPL) Requestforapproval(RFA) CleanlinessRequirement Specifications(CRS) Cleanlinessand contaminationcontrolplan (C&CCP) A PRR SRR B PDR C CDR QR D AR ORR FRR E LRR CRR ELR ECSSQST70,AnnexA ECSSQST70,AnnexB ECSSQST70,AnnexC ECSSQST70,AnnexD ECSSQST7001,AnnexA

DRDRef.

+ + + + + +

+ + + + + +

+ + + + + +

+ + + + + +

ECSSQST7001,AnnexB

67

ECSSQST70C 6March2009

Bibliography

ECSSSST00 ECSSMST10 ECSSMST40 MILHDBK454 NASAMAPTIS NASASTD6001

ECSSsystemDescription,implementationandgeneral requirements SpaceprojectmanagementProjectplanningand implementation SpaceprojectmanagementConfigurationand informationmanagement GeneralGuidelinesforElectronicEquipment MaterialsandProcessesTechnicalInformationSystem Flammability,odour,offgassingandcompatibility requirementsandtestproceduresformaterialsin environmentsthatsupportcombustion(previously NHB80601C)