Presentation Title ( Arial, Font size 28 )
Date, Venue, etc..( Arial, Font size 18 ) K. K. Panda Chief CTDS, Corporate Engineering
Presentation Outline
Highlight of Indian Power Sector Installed Capacity till 11th Plan Growth of Installed Capacity Capacity Addition Target in 12th Plan Capacity Addition Challenges Fuel & Land Issues, Statutory Clearances and Financing
Manufacturers for Main Plan Equipments Manufacturing Capacity of BOP Vendors Engineering Expertise & System Integration
Construction Agencies & Critical Material Skilled Manpower for Construction / O&M Tata Powers Perspective
814
900 800 700 600 500 400 300 200 100 0 Per Capita Consumption in 1950 Per Capita Consumption in 2011 15 200000 180000 160000 140000 120000 100000 80000 60000 40000 20000 0 Installed Capacity in 1947 Installed Capacity in 2012 1362
Multi-fold increase in per capita consumption & installed capacity ..... Continued Growth
Per Capita consumption in unit / year and Installed capacity in MW
2,000
1,905
1,000
858
0 2011-2012 (Actual) 2016-2017 (Projected) Energy Demand in BU Energy Met in BU 2021-2022 (Projected)
Peak Demand in GW
54,964 MW
21,407 MW
16,422 MW
19,119 MW
21,180 MW
Total 88, 537 MW Capacity addition is targeted in 12th Plan (20122017) through conventional sources
50000
0
13703 18282 9583 1362 1713 2813 5063
1947
1950
1956
1961
1966
1969
1974
1979
1980
1985
1990
1992
1997
2002
2007
2011
2012
7
60000
50000
40000
30000
20000
10000
Resolution of above issues is critical for meeting the 12th Plan Target.
10
Toshiba-JSW
Alstom Bharat Forge Ansaldo Gammon BGR Hitachi Thermax Babcock Chinese Suppliers like Shanghai Electric, Dongfang, Harbin Korean Suppliers Russian Suppliers European & US Suppliers like Alstom, Siemens, GE
Many Indian companies through JV routes are developing manufacturing capacity in India for Main Plant Equipments
11
European, Japanese and US vendors have well established proven technology and are known for quality products. But due to high cost of manufacturing they may not be competitive in Indian market.
* BHEL and L&T-MHI plants are operational. Others will be operational in 2014
12
Additionally Chinese Suppliers have a combined manufacturing capacity in excess of 100,000MW per annum. With above manufacturing capacity of domestic and international manufacturer, supply of BTG equipments are not likely to be constraints for meeting 12th Plan Target. * BHEL and L&T-MHI plants are operational. Others will be operational in 2013, 2014
13
7 6 6 5 3 4 5 7
14
Technofab, Unitech, Agnice, Fire Pro, Thermo System, Vijay Fire, Tyco
15
16
Execution of BOP Packages with emphasis on cost, quality, safety and reliability is still a challenge for Indian Power Industry
17
For ensuring timely completion of 12th Plan Projects, large numbers of experienced professionals and consultancy organizations are required.
18
Approx 1.15 Million Ton of CRGO Steel, 70,000 Tons of Forging and Casting, 92,000 Tons Boiler Quality Plates and 6,72, 000 Tones of Tubes and Pipes will be required in 12th Plan.
19
20
21
Hydro, 447
* Gas capacity includes NG based CCPP, OCPP, NG Fired Boilers and COG/BFG Fired Boilers. ** RES includes wind and solar.
22
23
Thank You
L&T - MHI
L&T-MHI Boilers Private Limited is a Joint Venture Company between Larsen & Toubro Limited (L&T), India and Mitsubishi Heavy Industries Limited (MHI).
Manufacturing facility located at Hazira, Near Surat, Gujarat. The current installed capacity is 4000 MW per year. Major Projects under execution are: 2 x 660 MW JP Power Ventures 2 x 700 MW Nabha Power
25
Thermax - Babcock
A joint venture between Thermax Limited, Pune, India and Babcock & Wilcox Power Generation Group, Inc., USA.
26
27
28
Doosan
Manufacturing Facility Near Chennai Manufacturing facility operational. Order executed / under execution in India 5 x 800 MW Mundra UMPP Boiler Package 2 x 660 MW GMR Raipur 3 x 660 MW NTPC Sipat 5 x 800 MW NTPC Bulk Tender Boiler Package (Kudgi, Mauda)
29
Toshiba JSW
JV between Toshiba and JSW Factory located at Chennai, Tamilnadu Manufacturing of 500 1000 MW steam turbine. Order executed / under execution in India 5 x 800 MW NTPC Bulk Tender Turbine Package (Kudgi, Mauda)
30
31
240 MW Sorik Marapi Geothermal Project - Tata Power with consortium partners Origin Energy and PT Supraco. In Indonesia Under Execution.
236 MW Dugar Hydro Project Himachal Pradesh Under Planning / Development 3 x 67.5 MW Kalinganagar, Orissa Under Execution 3 x 150 MW Kalinganagar, Orissa Under Planning / Development 1980 MW Tiruldih Power Project, Jharkhand Under Planning / Development 1600 MW Coastal Maharashtra Project Dehrand Under Planning / Development Distribution Franchise for Jamshedpur Circle Under Implementation
32