You are on page 1of 7

Ki ng Khal i d Uni versi ty Mal e Academi c Campus

COLLEGE OF COMPUTER SCIENCE (MC04)


BILL No. 2
DIVISION 2 - SITE CONSTRUCTION
EXCAVATION AND EARTHWORK
Excavation over site generallyin reducing levels commencing fromexisting grades and excavation including hauling to stockpile about the site or disposal tip as required, temporaryearthworksupports, dewatering, compacting bases, special contouring, clearing of deleterious materials all as deemed necessaryas shown on drawings and as per specification section 02200
01 Existing ground levels to formation subgrade of beds, pavements, landscaping and the like 64.70 M3 467 30,214.90 467 - - - 0.00
Filling over site in making up levels generallyincluding hauling fromstockpile or the like, compaction, embankments, special contouring, clearing of deleterious materials all as as shown on drawings and as per specification section 02200
- - - - 0.00
01 Selected fill fromexcavations or imported fill material (as per Engineer' s approved) in building up levels to formation subgrade of beds, pavements, landscaping and the like 40.93 M3 9,682 396,284.26 9,682 - - - 0.00
Workon proposed structural built-up areas frompart of the Workpertaining to respective building or structure as measured elsewhere. NOTE - - - - 0.00
- - - - 0.00
CONCRETE WORK - - - - 0.00
Plain insitu concrete, 20 Mpa, type V as per specifications section 03300 - - - - 0.00
01 Blinding beds, 100 mmthick 462.14 M3 39 18,023.46 23 7,394.24 - - -7,394.24
Insitu reinforced concrete 30 Mpa type V cement including steel base plates, dowel bars, grouting, formworkand steel reinforcement conforming to ASTM A615 and A185 in:
- - - - 0.00
02 Footing 1,394.34 M3 96 133,856.64 101 - 5.00 6,971.70 6,971.70
03 Tie beams 1,727.08 M3 75 129,531.00 75 - - - 0.00
04 Columns pedestals 1,742.93 M3 18 31,372.74 20 - 2.00 3,485.86 3,485.86
Insitu reinforced concrete 30 Mpa type I cement including steel base plates, dowel bars, grouting, formworkand steel reinforcement conforming to ASTM A615 and A185 in:
- - - - 0.00
01 Columns 1,584.48 M3 79 125,173.92 79 - - - 0.00
02 Beams 1,727.08 M3 224 386,865.92 224 - - - 0.00
03 Suspended slabs (solid slabs) 1,307.20 M3 185 241,832.00 185 - - - 0.00
Damp-proofing - - - - 0.00
04 Bituminous paint onto surfaces of concrete in contact with soil 9.24 M2 988 9,129.12 988 - - - 0.00
PAVINGAND SURFACING - - - - 0.00
01 Asphalt pavement detail A on drawing XL31.as per specification section 02510 244.27 M2 4,230 1,033,262.10 4,180 12,213.50 - - -12,213.50
02
Drystreambed covered with rockand gravel gropings including compacted earth and 100 mmthickmortar bed as per detail 8 shown on drawng XL-32 and specification section
396.12 M2 16 6,337.92 10 2,376.72 - - -2,376.72
03 Cast-in-place concrete paving with brick edge and band as per detail-F2, drawing XL-31 and specification section 02500 290.49 M2 424 123,167.76 678 - 254.00 73,784.46 73,784.46 818.237
04 Cast-in-place concrete paving as per detail-F13, drawing XL-31 and specification section 02500 290.49 M2 2,484 721,577.16 2,503 - 19.00 5,519.31 5,519.31 2553.227
PAVINGAND SURFACING - - - - 0.00
01 Granite paving detail C7 on drawing XL31 963.89 M2 957 922,442.73 960 - 3.00 2,891.67 2,891.67
02 Granite paving detail C14 on drawing XL31 963.89 M2 192 185,066.88 178 13,494.46 - - -13,494.46
03 Granite paving pattern polished finish detail C15 on drawing XL31 963.89 M2 108 104,100.12 107 963.89 - - -963.89
STONE STEPS - - - - 0.00
04 Stone capped steps as detail 2 on drawing XL-32 633.79 M 76 48,168.04 85 - 9.00 5,704.11 5,704.11
WOODEN BRIDGE - - - - 0.00
05 Wooden bridge including all associated works as shown on drawings and specification 174,850.01 No. 2 349,700.02 2 - - - 0.00
Randomstone paving - - - - 0.00
01 Randomstone paving as per detail E10 shown on drawing XL-31 and specification section 02515 237.67 M2 844 200,593.48 570 65,121.58 - - -65,121.58 543.943
SEATING - - - - 0.00
02 Reinforced concrete seats including all associated works as per detail 4 drawing XL-32 713.02 M 71 50,624.42 39 22,816.64 - - -22,816.64
03 Wooden seats with concrete base including all associated works as per detail 6 drawing XL-32 1,109.14 No. 22 24,401.08 22 - - - 0.00
CURBS AND EDGING - - - - 0.00
01 Precast concrete road curb as per detail 1 drawing XL-32 71.30 M 974 69,446.20 2,018 - 1,044.00 74,437.20 74,437.20
02 Concrete mowing as per detail 5 drawing XL-32 71.30 M 24 1,711.20 23 71.30 - - -71.30
Sundries - - - - 0.00
03
Reflective thermoplastic proprietarypaint marking to driveways and parking areas including lane strips, directional arrows, scripts and the like complete per drawings and specifications section 02580
ITEM - - - - 0.00
- - - - 0.00
RETAININGWALL - - - - 0.00
Retaining walls comprising RC walls and foundation, blinding bed including excavation, backfilling, water proofing and moisture protection , finishes as shown on drawing and specification
- - - - 0.00
01 Retaining wall as required height 554.57 M 140 77,639.80 151 - 11.00 6,100.27 6,100.27 150.807
Stone faced planter retaining wall - - - - 0.00
02 Stone faced planter wall as detail 3 on drawing XL-32 1,056.32 M 220 232,390.40 283 - 63.00 66,548.16 66,548.16 271.947
Rockformation & boulder - - - - 0.00
Rockoutcrop landscaping comprising rockboulders and gravel mulching to suit location as required to simulate naturallyoccurring rockformations as per detail 9, drawing XL-32 as per specification section 02870
- - - - 0.00
01
(Boulder Schedule) 1M2 =15% 0.25 M3 =40% 0.25M3 =45%
ITEM - - - - 0.00
Tree pit surround - - - - 0.00
02 Formation of tree/palmpit surround concrete edge pavers, on cement mortar setting bed as detail 7, drawing XL-32 4,225.28 No. 3 12,675.84 3 - - - 0.00
- - - - 0.00
LANDSCAPING - - - - 0.00
Trees including pit excavation, stakes and ties, soil planting mix, mulching, filter membrane and drainage layer all as details and planting schedule on drawing and specification section 02900
- - - - 0.00
01 T/Cv 468.74 No. 14 6,562.36 13 468.74 - - -468.74
02 T/Aa 448.94 No. 14 6,285.16 11 1,346.82 - - -1,346.82
03 T/Fs 438.37 No. 5 2,191.85 5 - - - 0.00
04 T/Pa 359.15 No. 10 3,591.50 10 - - - 0.00
05 T/Ao 429.13 No. 6 2,574.78 6 - - - 0.00
Shrubs and ground cover including planting, site excavation as required, soil planting mix, mulching, filter membrane and drainage layer all as per details and planting schedule on drawings as per specification section 02900
- - - - 0.00
01 S/Aw 96.39 No. 13 1,253.07 13 - - - 0.00
02 S/Cn 151.85 No. 80 12,148.00 84 - 4.00 607.40 607.40
03 S/Gj 109.59 No. 26 2,849.34 26 - - - 0.00
04 S/Ji 126.76 No. 16 2,028.16 16 - - - 0.00
Shrubs and ground cover including planting, site excavation as required, soil planting mix, mulching, filter membrane and drainage layer all as per details and planting schedule on drawings as per specification section 02900
- - - - 0.00
01 S/Js 102.99 No. 22 2,265.78 22 - - - 0.00
02 S/Ah 349.91 No. 7 2,449.37 7 - - - 0.00
03 S/Li 153.17 No. 13 1,991.21 13 - - - 0.00
04 S/Cg 153.17 No. 3 459.51 3 - - - 0.00
Shrubs and ground cover including planting, site excavation as required, soil planting mix, mulching, filter membrane and drainage layer all as per details and planting schedule on drawings as per specification section 02900
- - - - 0.00
01 G/Wt 14.52 No. 513 7,448.76 513 - - - 0.00
02 G/Av 17.17 No. 441 7,571.97 441 - - - 0.00
03 G/Gr(Y) 42.25 No. 301 12,717.25 301 - - - 0.00
04 G/Of 14.52 No. 894 12,980.88 894 - - - 0.00
05 G/Vp 14.52 No. 676 9,815.52 676 - - - 0.00
- - - - 0.00
DRAINAGE INSTALLATIONS - - - - 0.00
Reinforced concrete sewer manhole with standard traffic type cast-iron manhole cover and frame (heavyduty) 0.60m dia. including foundation bed and associated civil and earthworks as on drawing and as per specification section 02730
- - - - 0.00
01 Ref. SMH 15,844.80 No. 12 190,137.60 12 - - - 0.00
Reinforced concrete chemical waste neutralizing tankwith proprietarystanard cast iron manhole cover and frame including earthworks, concrete works acid resistant brick lining, limstone chips neutralizing agent as detailed on drawings and specifications
- - - - 0.00
02 Chemical waste neutralizing tank 19,806.00 No. 8 158,448.00 8 - - - 0.00
Soakawaypit including excavation in unclassified ground and filling with 100mmthickgraded and base layer 300mm thickgravel course and 300 mmthickearth fill topping all as detail on drawings
- - - - 0.00
01 Soakawaypit, 300 mmdia.,700 mmdeep 3,168.96 No. 17 53,872.32 17 - - - 0.00
Supplyand installation pipework, UPVC schedule 40, including trench work, fittings and supports as required as shown on drawings and as per specifications section 02730
- - - - 0.00
01 75 mmdia. 71.30 M 65 4,634.50 71 - 6.00 427.80 427.80
02 100 mmdia. 87.15 M 805 70,155.75 443 31,548.30 - - -31,548.30
03 200 mmdia. 174.29 M 630 109,802.70 494 23,703.44 - - -23,703.44
ACCESSORIES - - - - 0.00
04 Area drain . Ref. (AD) 462.14 No. 1 462.14 1 - - - 0.00
Supplyand installation pipework, polypropylene, including trench work, fittings and supports as required as shown on drawings and as per specifications
- - - - 0.00
01 100 mmdia. 264.08 M 55 14,524.40 174 - 119.00 31,425.52 31,425.52
ACCESSORIES - - - - 0.00
02 Ground cleanout 100 mmdia.Ref. (COTG) 462.14 No. 7 3,234.98 8 - 1.00 462.14 462.14
03 Ground cleanout 200 mmdia. Ref. (COTG) 633.79 No. 1 633.79 - 633.79 - - -633.79
Reinforced concrete lift station including concrete works waterproofing, access ladders, internal lining, proprietary galvanized steel manhole cover and frame, guide bar, lifting chain and all associated works as detailed on drawing
- - - - 0.00
01 Lift station No.(2) 63,379.20 No. 1 63,379.20 1 - - - 0.00
Constant discharge submersible pumps (one duty, one stand-by) including associated valving pipe workwithin sump pit, and accessories within sump pit chamber as described on drawings (sump pit measured separately)
- - - - 0.00
01 Ref. (SP-2) capacity7.25 m3 /h & 22.00 mPSI 79,224.00 SET 1 79,224.00 1 - - - 0.00
- - - - 0.00
POTABLE WATER SYSTEM - - - - 0.00
Supply, installation testing and commissioning potable &fire pipework, UPVC schedule 80 including, fittings and supports hot water pipes insulation , excavtion and backfilling as required shown on drawings as per specification section 02668
- - - - 0.00
01 100 mmdia. 174.29 M 30 5,228.70 30 - - - 0.00
02 150 mmdia. 253.52 M 10 2,535.20 10 - - - 0.00
Accessories - - - - 0.00
01 Supplyand install 150 mmdia. Pressure reducing valve (PRV) 6,205.88 No. 1 6,205.88 1 - - - 0.00
02 Supplyand install 150 mmdia. isolating valve 3,961.20 No. 1 3,961.20 3 - 2.00 7,922.40 7,922.40
- - - - 0.00
FIRE WATER SYSTEM - - - - 0.00
Supplyand installation pipeworkincluding fitting and support, excavation and backfilling as required as shown on drawings and as per specificatons section 15300
- - - - 0.00
03 250 mmdia. 1,006.14 M 15 15,092.10 15 - - - 0.00
Accessories - - - - 0.00
01 Supplyand install 250 mmdia. Backflowpreventer (BFP) 6,602.00 No. 1 6,602.00 1 - - - 0.00
02 Supplyand install 250 mmdia. Isolating valve 7,922.40 No. 1 7,922.40 1 - - - 0.00
- - - - 0.00
IRRIGATION SYSTEM - - - - 0.00
Supply, installation testing and commissioning irrigation line pipework, UPVC schedule 80, including trenching, backfill, fittings,valves and supports as required as shown on drawings and as per specifications section 02810
- - - - 0.00
01 20 mmdia. 66.02 M 55 3,631.10 - 3,631.10 - - -3,631.10
02 25 mmdia. 68.66 M 175 12,015.50 - 12,015.50 - - -12,015.50
03 32 mmdia. 72.62 M 175 12,708.50 759 - 584.00 42,410.08 42,410.08
04 40 mmdia. 100.35 M 20 2,007.00 - 2,007.00 - - -2,007.00
05 50 mmdia. 118.84 M 230 27,333.20 215 1,782.60 - - -1,782.60
Supply, installation testing and commissioning irrigation line pipework, UPVC schedule 80, including trenching, backfill, fittings,valves and supports as required as shown on drawings and as per specifications section 02810
- - - - 0.00
01 75 mmdia. 142.60 M 385 54,901.00 352 4,705.80 - - -4,705.80
Accessories - - - - 0.00
02 Supplyand installation irrigation controller as detailed on drwings and as per specifications section 02810 8,239.30 No. 1 8,239.30 1 - - - 0.00
Accessories - - - - 0.00
01 Supplyand installation bubbler for shrubs, ground cover and succulents 15.84 No. 614 9,725.76 588 411.84 - - -411.84
02 Supplyand installation bubblers for trees 15.84 No. 220 3,484.80 - 3,484.80 - - -3,484.80
Supplyand installation remote control valve assembly including piping complete with valve box, Y-strainer, accessories and all associated works as detail on drawing and as per specifications section 02810
- - - - 0.00
03 Ref. RCV 01 to 07 3,340.61 No. 7 23,384.27 7 - - - 0.00
- - - - 0.00
OUTDOOR POWER AND LIGHTINGINSTALLATION - - - - 0.00
Supplyand install outdoor power and lighting accessories including all necessaryboxes, switches, sockets and as required seal enclosures. In addition to final sub-circuits comprising cables, conduits, fittings, connections and associated works as required to suit the locations shown on drawings and as described in specifications section 16050
- - - - 0.00
01 Disconnect switch with pilot light, non-fused,16A, 3P,380V weatherproof 554.57 No. 2 1,109.14 2 - - - 0.00
02 Junction box, floor mounted, weatherproof 330.10 No. 3 990.30 3 - - - 0.00
- - - - 0.00
SITE LIGHTING - - - - 0.00
Supply, installation, testing and commissioning of outdoor lighting fixtures complete including poles, cables/wires and conduits, trenching work, foundations and all accessories as shown on drawings and as described in specifications section 16050
- - - - 0.00
01 Type (BLI) 2,535.17 No. 130 329,572.10 129 2,535.17 - - -2,535.17
02 Type (PE1) 3,301.00 No. 4 13,204.00 4 - - - 0.00
03 Type (L1) 5,228.78 No. 74 386,929.72 73 5,228.78 - - -5,228.78
04 Type (L3) 4,436.54 No. 28 124,223.12 28 - - - 0.00
SITE LIGHTING - - - - 0.00
01 Type (LP1) 3,301.00 No. 14 46,214.00 14 - - - 0.00
02 Type (ST1) 3,168.96 No. 98 310,558.08 98 - - - 0.00
03 Type (UL) 3,168.96 No. 65 205,982.40 65 - - - 0.00
04 Type (WL4) 3,168.96 No. 65 205,982.40 65 - - - 0.00
- - - - 0.00
OUTDOOR POWER AND LIGHTING - - - - 0.00
Supply, installation, testing and commissioning of control gear panel boards complete including circuit breakers, enclosures, fixings, supports and associated lighting contactors for complete installation as shown on drawings and as per specification section 16442
- - - - 0.00
01 Ref. SLP1 4,753.44 No. 1 4,753.44 1 - - - 0.00
02 Ref. SLP2 4,119.65 No. 1 4,119.65 1 - - - 0.00
TOTAL BILL SUMMARY 8,349,899.22 217,956.01 328,698.08 110,742.07
8,460,641.29
NEW ITEM:
LANDSCAPING
TERRAZOWITH GRANITE BAND 1,109.14 M2 - 46.00 - 46.00 51,020.44 51,020.44
GRANITE BAND 1,003.50 M2 - 25.00 - 25.00 25,087.50 25,087.50
CONCRETE UPSTAND 1,180.44 M - 145.00 - 145.00 171,163.80 171,163.80
T/Mo 500.00 No. 2.00 - 2.00 1,000.00 1,000.00
Supply, installation testing and commissioning irrigation line pipework, UPVC schedule 80, including trenching, backfill, fittings,valves and supports as required as shown on drawings and as per specifications section 02810
- - - - 0.00
01 90 mmdia. 175.00 M - 78 - 78.00 13,650.00 13,650.00
Accessories - - - - 0.00
SOLENOID VALVE 1,000.00 No. - 7.00 - 7.00 7,000.00 7,000.00
QUICK COUPLINGVALVE 1,000.00 No. - 8.00 - 8.00 8,000.00 8,000.00
POTABLE WATER SYSTEM - - - - 0.00
Supplyand installation pipework, UPVC schedule 40, including trench work, fittings and supports as required as shown on drawings and as per specifications section 02730
- - - - 0.00
01 150 mmdia. 126.76 M - 105 - 105.00 13,309.80 13,309.80
DRAINAGE INSTALLATIONS
Supplyand installation pipework, polypropylene, including trench work, fittings and supports as required as shown on drawings and as per specifications
01 75mmdia. 264.08 M - 9 - 9.00 2,376.72 2,376.72
ACCESSORIES - - - - 0.00
01 Ground cleanout 75 mmdia.Ref. (COTG) 250.00 No. - 2 - 2.00 500.00 500.00
02 100 mmdia.Ref. (FCO) 462.14 No. 3.00 - 3.00 1,386.42 1,386.42
POTABLE WATER SYSTEM - - - - 0.00
Supply, installation testing and commissioning potable &fire pipework, UPVC schedule 80 including, fittings and supports hot water pipes insulation , excavtion and backfilling as required shown on drawings as per specification section 02668
- - - - 0.00
01 250 mmdia. 300.00 M - 2 - 2.00 600.00 600.00
TOTAL BILL SUMMARY (newitem) - - 295,094.68 295,094.68
8,755,735.97 405,836.75
REMARKS Rate Unit Quantity Amount Saving Amount
Additional Quantity
Additional Amount
Variance Amount
VARIANCE
Building Item Description
Bill of Quantity Shop
Drawing
Quantity
King Khalid University Male Academic Campus
COLLEGE OF COMPUTER SCIENCE (MC07 PART 1)
DIVISION 2 - SITE WORK
EXCAVATION AND EARTHWORK
Necessary moving or transportation about the site
excavation material including handling to temporary
stockpile or ultimate disposal off site is to be included
in the unit rate of excavation
Excavation in natural land consisting of solid rock
formation, cracked rocks, bolders and natural
contoured soil, temporary earthwork supports,
dewatering and any work below the normal water table
level as per specifications sections 02200
01
Excavation for foundations commencing from existing
grade level
64.70 M3 14,646 947,596.20 14,646.00 - - - 0.00
Backfilling - - - - 0.00
01
Approved selected imported fill material including
compaction in making up levels around and over
foundations, beds and the like as per specifications
sections 02200
40.93 M3 28,644 1,172,398.92 28,644.00 - - - 0.00
02
Approved fill material selected from excavated material
including compaction as per specification section 02200
M3 - - - - 0.00
Drainage layer - - - - 0.00
01
100 mm thick compacted coarse gravel to underside
of slabs on grade as per specification section 02200
27.73 M2 21,310 590,926.30 21,310.00 - - - 0.00
Soil treatment application for termite control - - - - 0.00
02 To subgrades of slabs and along periphery of building 7.92 M2 22,630 179,229.60 22,630.00 - - - 0.00
Thermoplastic paint for traffic marking on parking
pavement in parking floor and sub-terrain floor as
shown on drawings and detail on G-A 902 and
specification section 02580
- - - - 0.00
01 Straight arrows 133.36 No. 58 7,734.88 58.00 - - - 0.00
02 Turning arrows 133.36 No. 14 1,867.04 14.00 - - - 0.00
03 Straight arrows& turning 133.36 M 3 400.08 3.00 - - - 0.00
04 Parking lane marking, 100 mm wide 60.74 M 531 32,252.94 552.00 - 21.00 1,275.54 1,275.54
TOTAL BILL SUMMARY 2,932,405.96 - 1,275.54 1,275.54
NEW ITEM:
- - - 0.00
- - - 0.00
- - - 0.00
- - - 0.00
- - - 0.00
- - - 0.00
- - - 0.00
TOTAL BILL SUMMARY (new item) - - - -
2,933,681.50 1,275.54
REMARKS
Rate Unit Quantity Amount Saving Amount
Additional Quantity
Additional
Amount
Variance Amount
VARIANCE
Building Item Description
Bill of Quantity
Shop Drawing
Quantity
King Khalid University Male Academic Campus
Supported Deanships (MD01)
BILL No. 2
DIVISION 10 -SPECIALTIES
TOILET AND BATH ACCESSORIES
Supply and installation of following toilet and
bath accessories as per schedule including
fixings and trims as shown on drawings and
specification section 10800 to suit locations as
required
01 Ref. FM1, Clear glass mirror on 20 mm thick
plywood backing, 960 mm high
92.43 M 136 12,570.48 157.00 - 21.00 1,941.03 1,941.03
02 Ref. FM2, Clear glass mirror with stainless steel
frame, size 400 x 600 mm
343.30 No. 1 343.30 1.00 - - - 0.00
03 Ref. FMh, Clear glass mirror with stainless steel
frame, size 400 x 600 mm (handicapped)
343.30 No. 23 7,895.90 27.00 - 4.00 1,373.20 1,373.20
Supply and installation of following toilet and
bath accessories as per schedule including
fixings and trims as shown on drawings and
specification section 10800 to suit locations as
required
- - - - 0.00
01 Ref. GB1, 32 mm dia. Satin finish stainless steel
grab bar 600 mm length
132.04 No. 39 5,149.56 50.00 - 11.00 1,452.44 1,452.44
02 Ref. GB2, 32 mm dia. Satin finish stainless steel
grab bar 1050 mm length
198.06 No. 64 12,675.84 73.00 - 9.00 1,782.54 1,782.54
03 Ref. GB3, 32 mm dia. Satin finish stainless steel
grab bar 300 mm length
105.63 No. 97 10,246.11 133.00 - 36.00 3,802.68 3,802.68
04 Ref. HD, Surface mounted push button electric
hand dryer
2,376.72 No. 55 130,719.60 77.00 - 22.00 52,287.84 52,287.84
05 Ref. PTD, Surface mounted stainless steel
paper towel dispenser
323.50 No. 39 12,616.50 53.00 - 14.00 4,529.00 4,529.00
Supply and installation of following toilet and
bath accessories as per schedule including
fixings and trims as shown on drawings and
specification section 10800 to suit locations as
required
- - - - 0.00
01 Ref. RH1, Single robe hook (high category) 79.22 No. 2 158.44 2.00 - - - 0.00
02 Ref. RH2, Single robe hook 79.22 No. 490 38,817.80 769.00 - 279.00 22,102.38 22,102.38
03 Ref. RHh, Single robe hook (handicapped ) 79.22 No. 84 6,654.48 52.00 2,535.04 - - -2,535.04
Supply and installation of following toilet and
bath accessories as per schedule including
fixings and trims as shown on drawings and
specification section 10800 to suit locations as
required
- - - - 0.00
01 Ref. SD, Wall mounted soap dispenser 151.85 No. 88 13,362.80 104.00 - 16.00 2,429.60 2,429.60
02 Ref. SDH1, Wall mounted soap dish and holder
(high category)
264.08 No. 1 264.08 1.00 - - - 0.00
03 Ref. SDH2, Wall mounted soap dish and holder 151.85 No. 23 3,492.55 23.00 - - - 0.00
04 Ref. HS1, Hand spray with flexible hose and
wall hook (high category)
290.49 No. 1 290.49 - 290.49 - - -290.49
05 Ref. HS2, Hand spray with flexible hose and
wall hook
145.24 No. 250 36,310.00 225.00 3,631.00 - - -3,631.00
Supply and installation of following toilet and
bath accessories as per schedule including
fixings and trims as shown on drawings and
specification section 10800 to suit locations as
required
- - - - 0.00
01 Ref. TPH1, Toilet paper holder (high category) 396.12 No. 6 2,376.72 6.00 - - - 0.00
02 Ref. TPH2, Toilet paper holder 198.06 No. 184 36,443.04 215.00 - 31.00 6,139.86 6,139.86
- - - - 0.00
TOILET COMPARTMENTS - - - - 0.00
Proprietary solid phenolic core toilet
compartments with high pressure melamine
matt surface, including, stainless steel pilasters,
fixings, finishings, hardware and accessories as
shown on drawings and specification section
10155
- - - - 0.00
01 Toilet partitions including doors as per drawings 2,772.84 M 432 1,197,866.88 481.00 - 49.00 135,869.16 135,869.16
- - - - 0.00
Wall and Column Guards - - - - 0.00
Rubber guards including aluminium retainer as
per detail 8 on drawing G-A902 and as per
specification section 10265
- - - - 0.00
01 Rubber guard 600 mm high 594.18 No. 501 297,684.18 692.00 - 191.00 113,488.38 113,488.38
- - - - 0.00
ALUMINUM LOUVERS - - - - 0.00
Aluminum Louvers panels including insects
mesh (where required) as per drawing G-A802
- - - - 0.00
01 Type L01 1,980.60 No. 36 71,301.60 24.00 23,767.20 - - -23,767.20
02 Type L02 1,320.40 No. 10 13,204.00 1.00 11,883.60 - - -11,883.60
03 Type L03 607.38 No. 44 26,724.72 62.00 - 18.00 10,932.84 10,932.84
- - - - 0.00
ACCESS FLOORING - - - - 0.00
Proprietary raised floor system including fixing,
and all associated works as shown on detailed
on drawing (carpet tiles measured elsewhere)
specification section 10270
- - - - 0.00
01 To suit required locations 924.28 M2 90 83,185.20 90.00 - - - 0.00
- - - - 0.00
SIGNAGE - - - - 0.00
Manufacturer's standard indoor signs, letters
and plaques including fixings, finishes,
accessories complete as per interior design
drawings MC06i901 to MC06i947 and as per
specification section 10431
- - - - 0.00
01 Refer type S01 198.06 No. 704 139,434.24 718.00 - 14.00 2,772.84 2,772.84
02 Refer type S02 198.06 No. 202 40,008.12 203.00 - 1.00 198.06 198.06
03 Refer type S03 264.08 No. 54 14,260.32 54.00 - - - 0.00
04 Refer type S04 198.06 No. 95 18,815.70 95.00 - - - 0.00
05 Refer type S05 396.12 No. 70 27,728.40 69.00 396.12 - - -396.12
06 Refer type S06 2,640.80 No. 23 60,738.40 23.00 - - - 0.00
07 Refer type S07 1,584.48 No. 32 50,703.36 32.00 - - - 0.00
Manufacturer's standard indoor signs, letters
and plaques including fixings, finishes,
accessories complete as per interior design
drawings MC06i901 to MC06i947 and as per
specification section 10431
- - - - 0.00
01 Refer type S09 396.12 No. 12 4,753.44 14.00 - 2.00 792.24 792.24
02 Refer type S10 7,262.20 No. 2 14,524.40 2.00 - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
- - - - 0.00
TOTAL BILL SUMMARY 2,391,320.65 42,503.45 361,894.09 319,390.64
NEWITEM:
Type L04 1,848.56 No. - 3.00 - 3.00 5,545.68 5,545.68
Type L05 3,036.92 No. - 5.00 - 5.00 15,184.60 15,184.60
Type L06 2,772.84 No. - 3.00 - 3.00 8,318.52 8,318.52
Type L07 2,000.00 No. - 2.00 - 2.00 4,000.00 4,000.00 PER/SQ M RATE
TYPE L; STATIONARY LOUVER (3.1X2.25) 2,092.50 No. - 2.00 - 2.00 4,185.00 4,185.00
TYPE L; STATIONARY LOUVER (4.1X2.25) 2,767.50 No. - 2.00 - 2.00 5,535.00 5,535.00
0.00
- - - 0.00
- - - 0.00
TOTAL BILL SUMMARY (new item) - - 42,768.80 42,768.80
2,753,480.09 362,159.44
REMARKS Rate Unit Quantity Amount Saving Amount Additional
Quantity
Additional
Amount
Variance Amount
VARIANCE
Building Item Description
Bill of Quantity
Shop Drawing
Quantity
King Khalid University Male Academic Campus
Supported Deanships (MD01)
BILL No. 2
DIVISION 11 -EQUIPMENT
FOOD SERVICE EQUIPMENT
Supply and installation of Tearoom and cafeteria
equipments as described on drawing G-A501 and
specification section 11400
01 Ref. 003, one bowel sink 3,301.00 No. 7 23,107.00 8.00 - 1.00 3,301.00 3,301.00
02 Ref. 004, bottle type water cooler 1,452.44 No. 7 10,167.08 8.00 - 1.00 1,452.44 1,452.44
03 Ref. 005, stainless steel refrigerator under counter 9,903.00 No. 7 69,321.00 8.00 - 1.00 9,903.00 9,903.00
04 Ref. 006, water boiler 1,584.48 No. 7 11,091.36 8.00 - 1.00 1,584.48 1,584.48
05 Ref. 007, two hot plate electric range on counter 2,904.88 No. 7 20,334.16 8.00 - 1.00 2,904.88 2,904.88
06 Ref. 008, trash bin 1,320.40 No. 7 9,242.80 8.00 - 1.00 1,320.40 1,320.40
Supply and installation of Tearoom and cafeteria
equipments as described on drawing G-A501 and
specification section 11400
- - - - 0.00
01 Ref. 102, one bowel sink 3,565.08 No. 1 3,565.08 1.00 - - - 0.00
02 Ref. 103, two bowel sink 2,937.89 No. 1 2,937.89 2.00 - 1.00 2,937.89 2,937.89
03 Ref, 106, juicer extractor 3,736.73 No. 2 7,473.46 2.00 - - - 0.00
04 Ref. 107, juicer squeezer 2,376.72 No. 2 4,753.44 2.00 - - - 0.00
05 Ref. 108, juicer dispencer 8,318.52 No. 2 16,637.04 2.00 - - - 0.00
06 Ref. 109, water boiler 1,056.32 No. 2 2,112.64 2.00 - - - 0.00
Supply and installation of Tearoom and cafeteria
equipments as described on drawing G-A501 and
specification section 11400
- - - - 0.00
01 Ref. 110, sstl double door reffrigerator 4,555.38 No. 2 9,110.76 2.00 - - - 0.00
02 Ref, 111 toaster 4,555.38 No. 2 9,110.76 2.00 - - - 0.00
03 Ref, 112 microwave oven 2,838.86 No. 2 5,677.72 2.00 - - - 0.00
04 Ref. 113 coffee machine 16,967.14 No. 2 33,934.28 2.00 - - - 0.00
05 Ref. 115 ice cube 11,487.48 No. 1 11,487.48 1.00 - - - 0.00
- - - - 0.00
PARKING CONTROL EQUIPMENT - - - - 0.00
Parking control equipment as per specifications
section 11150
- - - - 0.00
01 Traffic control barrier with overall arm length 5117 mm 5,281.60 No. 2 10,563.20 4.00 - 2.00 10,563.20 10,563.20
TOTAL BILL SUMMARY 260,627.15 - 33,967.29 33,967.29
294,594.44
NEW ITEM:
- - - 0.00
Ref. 105 SALAD TABLE 19,806.00 No. - 1.00 - 1.00 19,806.00 19,806.00
Building Item Description
Bill of Quantity
Shop Drawing
Quantity
REMARKS
Rate Unit Quantity Amount Saving Amount
Additional Quantity
Additional
Amount
Variance Amount
VARIANCE
King Khalid University Male Academic Campus
Supported Deanships (MD01)
BILL No. 2
Building Item Description
Bill of Quantity
Shop Drawing
Quantity
REMARKS
Rate Unit Quantity Amount Saving Amount
Additional Quantity
Additional
Amount
Variance Amount
VARIANCE
- - - 0.00
TOTAL BILL SUMMARY (new item) - - 19,806.00 19,806.00
314,400.44 53,773.29
King Khalid University Male Academic Campus
Supported Deanships (MD01)
BILL No. 2
DIVISION 13 -SPECIAL CONSTRUCTION
INSULATED ROOMS
Supply and install nuclear physics lab comprising
integrated floor, walls and celling system including
door hardwares, finishings, fixtures, equipment and all
associated works, wiring, piping, devices etc. complete
as shown on drawing and specs
01 To suit area no ( S-101 ) 660,200.00 ITEM 1 660,200.00 1.00 - - - 0.00
TOTAL BILL SUMMARY 660,200.00 - - 0.00
660,200.00
NEW ITEM:
- - - 0.00
- - - 0.00
TOTAL BILL SUMMARY (new item) - - - -
660,200.00 -
Building Item Description
Bill of Quantity
Shop Drawing
Quantity
REMARKS
Rate Unit Quantity Amount Saving Amount
Additional Quantity
Additional
Amount
Variance Amount
VARIANCE
FM1 156.581
FM2 1
FMh 27
GB1 50
GB2 73
GB3 133
HD 77
PTD 53
RH1 2
RH2 769
RHh 52
SD 104
SDH1 1
SDH2 23
HS1 0
HS2 225
TPH1 6
TPH2 215
TOILET PART. 480.984

You might also like