Date:________________________________
Contractor:____________________________________________ Location: __________________________
Crane Number: _______________________ Project Title: _________________________________________
Rigging Supervisor ___________________________________ Signature______________________
Crane Operator ______________________________________Signature______________________
Activity being assessed:
LIFTING & ERECTION of FIN FAN COOLER
1. Site & Ground Preparation-Test/Certified (achieved 100% Proctor density test)
2. 180 ton mobile crane & 3rd party Inspection approval & client
3. Lifting & heavy haul of Columns from Gate3 Laydown to A00 area
4. Offloading, Rigging set up as per approved Critical Lift Plan & MS
5. Lifting & Erection Commencement.
Crane Operations (General Requirements)
Before beginning any crane operation, the supervisor and operator should complete the pre-
operation checklist.
A lift plan required as a part of this procedure must provide the following information:
No. Checked Items Remarks
Crane radius
Boom length
Safe working limits of the crane (load chart)
Weight of the load
Ground and site conditions
Placement of the crane
Swing and tail clearances
Necessary communication to be used
Explanation of hand signals
Rigging hardware
Rigging sketch for critical or hazardous lifts
Rated capacity of rigging components
Sling angles
Strain calculations
Wind velocity
Load moment indicator
Cranes shall have a valid Crane Safety inspection
sticker issued by 3
rd
party.
Crane Operator Qualifications
Special Crane Operating Procedures
Effect of Wind Speeds on Crane Operations
Overhead Power Lines
Other:
HEAVY LIFT ACTIVITY CHECKLIST
One competent person shall be placed in charge of the lift with
the responsibility of explaining in detail, the duties of all involved
in the lift before the actual lift commences. The outriggers must
be fully extended prior to the lift, and the rubber tires must be off
the ground
OPERATOR:
CURRENT SAUDI ARAB GOVERNMENT CRANE OPERATORS'
LICENSE
CURRENT TUV OPERATORS' CERTIFICATE
OUTRIGGERS:
FULLY EXTENDED
LEVEL GROUND
COMPACT SOIL
HEAVY PAD SUPPORTS
LOCKING PINS/LOCKS SET
NO HYDRAULIC LEAKS
NO DAMAGE
GOOD CONDITION
WHEELS OFF THE GROUND
OPERATION:
CURRENT CRANE SAFETY INSPECTION STICKER
CLEAR 360o VISIBILITY
NO SHADES/CURTAINS IN CAB
LOAD CHARTS IN CAB
CLEAR VISIBILITY
WIND, ABOVE 20 m/h (32 km/h), Stop Operation
DO NOT OPERATE DURING STORMS AND AT NIGHT
LIGHTNING, NO GO
BARRICADE CRANE CAB SWING AREA
TAG LINES IN USE
CLEAR OVERHEAD POWER LINES
CLEAR AREA OF PERSONNEL 1-1/2 x BOOM LENGTHS
NO LIFTS OVER WORKERS OR CRITICAL PROPERTY
TRIAL LIFT, FLOAT LOAD ONE METER OFF GROUND TO CHECK
BALANCE
CLEAR VIEW OF SIGNAL MAN (RIGGER)
DO NOT PULL LOADS WITH CRANE
LOAD RADIUS INDICATOR
MAN LIFT WORK PERMIT
HEAVY LIFT ACTIVITY CHECKLIST
ANTI-TWO BLOCK OPERATIONAL
LMI (LOAD MOMENT INDICATOR) OPERATIONAL
RIGGING:
CHECK ALL RIGGING FOR DAMAGE
CHECK BLOCK, HOOKS, etc. FOR DAMAGE
HOOK SAFETY LATCH IN PLACE
RECORD WEIGHT OF LOAD
RECORD WEIGHT OF CRANE GEAR, ADD CRANE GEAR WEIGHT
TO TOTAL WEIGHT
LIFT PLAN APPROVED
USE LOAD WEIGHT MEASURING DEVICE FOR UNKNOWN LOADS
TRAVELING:
BLOCK SECURED
TIRES PROPERLY INFLATED AND IN GOOD CONDITION
BRAKE LIGHTS, SIGNALS, MIRRORS, HORN OPERATIONAL
ROUTE PLAN CHECKED FOR FIRM GROUND, OVERHEAD AND
SIDE RESTRICTIONS
ESCORT VEHICLES REQUIRED WITH FLASHING BEACON LIGHTS
SPEED TO BE MAINTAINED FOR SAFE LIMITS (SLOW AS
POSSIBLE)
PARKING:
BOOM AND HOOK BLOCK(S) LOWERED TO TRAVEL POSITION
APPLY SWING BRAKE AND POSITIVE SWING LOCK
TIE DOWN HOOK BLOCK(S)
RETRACT STABILIZERS
RETRACT OUTRIGGERS
EXTEND STABILIZERS AND LATCH ONTO FLOAT PADS
WEIGHT OF CHASSIS OFF THE TIRES
LET ENGINE IDLE 3-5 MINUTES
REMOVE ALL FOREIGN MATERIAL FROM CAB(S)
CLOSE ALL DOORS, WINDOWS, SKYLIGHTS AND
COMPARTMENTS TURN OFF SWITCHES
STOP ENGINE