This document provides comments on drawing MD1-0-V-111-01-00001 for a steam turbine mechanical outline. It assigns the status of "Approved with Comments". Seven comments are provided: 1) The drawing is for information only, not approval. 2) The number of nozzles for the 16th stage extraction shown does not match another drawing and needs correction. 3) Refer to another drawing for sectional views. 4) Submit missing lifting arrangement drawings. 5) Mark locations of bearings, turning gear, shaft driven pumps, rupture diaphragms. 6) Confirm exact or maximum weights for lifting capacity considerations. 7) Confirm if a dimension shown represents minimum height clearances.
This document provides comments on drawing MD1-0-V-111-01-00001 for a steam turbine mechanical outline. It assigns the status of "Approved with Comments". Seven comments are provided: 1) The drawing is for information only, not approval. 2) The number of nozzles for the 16th stage extraction shown does not match another drawing and needs correction. 3) Refer to another drawing for sectional views. 4) Submit missing lifting arrangement drawings. 5) Mark locations of bearings, turning gear, shaft driven pumps, rupture diaphragms. 6) Confirm exact or maximum weights for lifting capacity considerations. 7) Confirm if a dimension shown represents minimum height clearances.
This document provides comments on drawing MD1-0-V-111-01-00001 for a steam turbine mechanical outline. It assigns the status of "Approved with Comments". Seven comments are provided: 1) The drawing is for information only, not approval. 2) The number of nozzles for the 16th stage extraction shown does not match another drawing and needs correction. 3) Refer to another drawing for sectional views. 4) Submit missing lifting arrangement drawings. 5) Mark locations of bearings, turning gear, shaft driven pumps, rupture diaphragms. 6) Confirm exact or maximum weights for lifting capacity considerations. 7) Confirm if a dimension shown represents minimum height clearances.
APPROVED WITH COMMENTS AC Approved Subject to Incorporation of comments RETURNED FOR CORRECTION RT Insufficient Information/ Detail Resubmit for Approval REJECTED RJ Complete redesign required RECEIVED FOR INFORMATION I Returned without comments RECEIVED FOR INFORMATION IC Returned with comments any obligations covered under contract Engineer: Discipline: Date: Note: Approval or comments does not relieve the Contractor of Pyry Energy TWO(2) X 500MW MONG DUONG 1 THERMAL POWER PLANT Soumen Mitra Senior Mec Engineer 30-May-12 Pyry Comment Two(2) x 500MW Mong Duong 1 Thermal Power Plant Project
Dwg. / Doc. Title Steam Turbine Mechanical Outline(1/2)
Dwg. / Doc. No. MD1-0-V-111-01-00001 HDEC DT No. MD1-HDH-EVN-X-119 Submitted Date Rev. A Pyry TR No. Received Date New HDEC DT No. Re-Submitted Date Status Approved with Comments
Page 1 / 1 No. Pyrys Comments Contractors Reply / Action 1 This drawing is treated for information, not for approval
2 Number of nozzles for the 16 th stage extraction shown as 4 on the table in this drawing (for nozzle E3) does not match the drawing MD1-0- V-111-01-00002 (shown as 2 nos. Nozzles on that drawing). Check and correct as required.
3 Refer drawing MD1-0-V-111-01-00002 on this drawing for sectional views.
4. Submit the lifting arrangement drawings MD1-0- V-111-01-00004 to 00007 mentioned as reference on this drawing
5. Mark the location of bearings, turning gear, shaft driven pumps, rupture diaphragms, etc on the outline drawing
6. The component weights are mentioned as +/- 10%. Confirm either the exact weight in the next revision or mention the not to exceed weights for consideration in lifting capacities
7. Confirm whether the Dimension E shown on the drawing is meant to be the minimum height clearances on the components