You are on page 1of 2

APPROVED A

Approved without exception


APPROVED WITH COMMENTS AC
Approved Subject to Incorporation of comments
RETURNED FOR CORRECTION RT
Insufficient Information/ Detail
Resubmit for Approval
REJECTED RJ
Complete redesign required
RECEIVED FOR INFORMATION I
Returned without comments
RECEIVED FOR INFORMATION IC
Returned with comments
any obligations covered under contract
Engineer:
Discipline:
Date:
Note: Approval or comments does not relieve the Contractor of
Pyry Energy
TWO(2) X 500MW
MONG DUONG 1 THERMAL POWER PLANT
David Langhorne
Senior Mec Engineer
07-Dec-12
Pyry Comment
Two(2) x 500MW Mong Duong 1 Thermal Power Plant Project

Dwg. / Doc. Title
G A Drawing BFP and
Booster Pump

Dwg. / Doc. No. MD1-0-V-121-01-00001
HDEC DT No. MD1-HDH-EVN-X-1219 Submitted Date Rev. A
Pyry TR No. Received Date
New HDEC DT No. Re-Submitted Date
Status Submitted for Information Returned with Comment

Page 1 / 1
No. Pyrys Comments Contractors Reply / Action
1 Please provide KKS identifying number for
equipment and instruments on the drawings.


2 Include a parts list for the major components
(e.g. main pump, variable speed drive etc) with
reference drawings.


3 Foundation drawings with loading data and
anchor bolt information to be provided. These
drawings shall be identified as reference
drawings.


4 Confirm that there is personnel protection for all
rotating components.


5 State what DBSE means
6 Identify the equipment on the edge of the
booster and main pump base plates at grid
reference A2, A3, C5 and C6.