You are on page 1of 110

HMWSSB

Godavari pipe line Project

DATAS MS PIPES CSSR -2010-11 (April 2009)


Cement
5400.00
M.S.Plates
44000.00
6mm M.S. Rods
39000
Manufacturing, supplying, delivery at site and laying of 600 mm internal dia (after inlining) MS pipes with 16 mm thick mild steel
plates IS:2062-1992, with three run arc welding in 5 m or suitable lengths to suite the site conditions and as directed by the
departmental officers and inlining the fabricated pipes with CM(1:2) prop 15 mm thick duly fixing 4 nos of 6mm dia MS rings at
each end of the pipe and out coating the pipe with CM(1:3) prop 30mm thick by shortcreting or guniting duly providing
wiremesh of size 50x50x3 mm including cost of steel plates and all other required materials and including all taxes and duties
,hoisting , and carefully lowering the pipes in to the ready made trenches or keeping in position on pedastals or supports and
laying them true to the alignment and gradient and perfect lining by jacking and jointing with three line arc welding and lining
and out coating fielded welded joints including hydraulic testing to a factory test pressure of 18kg/cm2 and field test pressure
of 12 kg/cm2.
Wt.of MS plate16mm thick for 1 Rmt of pipe:
3.142
0.646
1
16
7.85 254.93 Kgs
Add 10% towards wastage =
2.55
Kgs
257.48
Say
257.00 Kgs
Cost of16mm thick MS plate/Rmt
257 x
44000 /- MT
Rs.
11308.00
Rate of MS Plates Rs. 35000/- Per MT
Cost of fabrication charges
254.93 x
18000 /- MT
Rs.
4588.74
Inlining15mm thick in CM (1:2) prop required for 1 Rmt.
3.142 x 0.615x0.015 x 1.0
=
0.03
Cum.
Add 10% for wastage
=
0.003
Cum.
0.033
Cum.
Cost of CM (1:2) prop.
#REF!
x
0.03
Cum.
Rs.
#REF!
per Cum
Outcoating with CM (1:3) prop. required for 1 Rmt.
3.142 x 0.692x0.03 x 1.0
=
0.07
Cum.
Add 10% for wastage
=
0.01
Cum.
0.08
Cum.
Cost of CM (1:3) prop.
#REF!
x
0.08
Cum.
Rs.
#REF!
per Cum
MS rods 6mm dia at 4 Nos. each side
4 x 3.1415 x0.728 x 0.22 Kg
2.01 Kg
2.01
Kgs
Cost of 6mm MS rods inclg. fabrication @ 39000.00 /MT x
2.01
Kgs
Rs.
78.39
Cement and Steel rate as per G.O.Rt.No.1166, Dt. 31.07.2008 of
Transport, Road & Buildings (R.I) Dept.

600
MS
pipe
for
speci
als

(a)
(b)
(c)

(d)

(e)

(f) Wire mesh of size 50mm x 50mm x 3mm.


Area of mesh: 3.142 x 0.692 x 1.0=
Cost of wire mesh @
(g) Guniting Charges:
Inlining: 3.142 x 0.615 x 1.0
=
Outcoating: 3.142 x 0.692x 1.0)
=

2.17 Sqm
50 /Sqm

Cost of guniting @
81 /Sqm x
(h) Transportation Charges @ Rs.575=00 / MT
Weight of MS plate
=
Wt. of CM (1:2) + (1:3)
0.11
=
Cost of Transportation @ Rs.575=00 / 1 MT
(i) Lowering, laying, jointing and testing
Total:
(k) Add for sundries
Total:
Rs.

#REF!

2.17

1.93
2.17
4.1
4.1

Sqm.
Sqm.
Sqm.
Sqm

257

Kgs.

231
488

Kgs.
Kgs.
280

Sqm

/Rmt

Rs.

108.50

Rs.

332.10

Rs.
Rs.
Rs.
Rs.
Rs.

280.60
280.00
#REF!
0.87
#REF! / Rmt

Rmt

300
MS
pipe
for
speci
als

Manufacturing, supplying, delivery at site and laying of 300 mm internal dia (after inlining) MS pipes with 16 mm thick mild steel
plates IS:2062-1992, with three run arc welding in 5 m or suitable lengths to suite the site conditions and as directed by the
departmental officers and inlining the fabricated pipes with CM(1:2) prop 15 mm thick duly fixing 4 nos of 6mm dia MS rings at
each end of the pipe and out coating the pipe with CM(1:3) prop 30mm thick by shortcreting or guniting duly providing
wiremesh of size 50x50x3 mm including cost of steel plates and all other required materials and including all taxes and duties
,hoisting , and carefully lowering the pipes in to the ready made trenches or keeping in position on pedastals or supports and
laying them true to the alignment and gradient and perfect lining by jacking and jointing with three line arc welding and lining
and out coating fielded welded joints including hydraulic testing to a factory test pressure of 18kg/cm2 and field test pressure
of 12 kg/cm2.
Wt.of MS plate16mm thick for 1 Rmt of pipe:
3.142
0.346
1
16
7.85 136.54 Kgs
Add 10% towards wastage =
1.37
Kgs
137.91
Say
138.00 Kgs
(a) Cost of16mm thick MS plate/Rmt
138 x
44000 /- MT
Rs.
6072.00
Rate of MS Plates Rs. 35000/- Per MT

MS pipe data

aarvee associates

HMWSSB

Godavari pipe line Project

DATAS MS PIPES CSSR -2010-11 (April 2009)


(b) Cost of fabrication charges
136.54 x
18000 /- MT
(c) Inlining15mm thick in CM (1:2) prop required for 1 Rmt.
3.142 x 0.315x0.015 x 1.0
=
0.01
Cum.
Add 10% for wastage
=
0.001
Cum.
0.011
Cum.
Cost of CM (1:2) prop.
#REF!
x
0.01
Cum.
per Cum
(d) Outcoating with CM (1:3) prop. required for 1 Rmt.
3.142 x 0.392x0.03 x 1.0
=
0.04
Cum.
Add 10% for wastage
=
0.00
Cum.
0.04
Cum.
Cost of CM (1:3) prop.
#REF!
x
0.04
Cum.
per Cum
(e) MS rods 6mm dia at 4 Nos. each side
4 x 3.1415 x0.428 x 0.22 Kg
1.18 Kg
1.18
Kgs
Cost of 6mm MS rods inclg. fabrication @ 39000.00 /MT x
1.18
Kgs
(f) Wire mesh of size 50mm x 50mm x 3mm.
Area of mesh: 3.142 x 0.392 x 1.0=
Cost of wire mesh @
(g) Guniting Charges:
Inlining: 3.142 x 0.315 x 1.0
=
Outcoating: 3.142 x 0.392x 1.0)
=

1.23 Sqm
50 /Sqm

Cost of guniting @
81 /Sqm x
(h) Transportation Charges @ Rs.575=00 / MT
Weight of MS plate
=
Wt. of CM (1:2) + (1:3)
0.06
=

1.23

0.99
1.23
2.22
2.22

Sqm.
Sqm.
Sqm.
Sqm

138

Kgs.

115.5
253.5

Kgs.
Kgs.

Cost of Transportation @ Rs.575=00 / 1 MT


(i) Lowering, laying, jointing and testing
Total:
(k) Add for sundries
Total:
Rs.
200
MS
pipe
for
speci
als

(a)
(b)
(c)

(d)

(e)

#REF!

/Rmt

2457.72

Rs.

#REF!

Rs.

#REF!

Rs.

46.02

Rs.

61.50

Rs.

179.82

Rs.
Rs.
Rs.
Rs.
Rs.

145.76
280.00
#REF!
4.32
#REF! / Rmt

Rmt

Manufacturing, supplying, delivery at site and laying of 200 mm internal dia (after inlining) MS pipes with 16 mm thick mild steel
plates IS:2062-1992, with three run arc welding in 5 m or suitable lengths to suite the site conditions and as directed by the
departmental officers and inlining the fabricated pipes with CM(1:2) prop 15 mm thick duly fixing 4 nos of 6mm dia MS rings at
each end of the pipe and out coating the pipe with CM(1:3) prop 30mm thick by shortcreting or guniting duly providing
wiremesh of size 50x50x3 mm including cost of steel plates and all other required materials and including all taxes and duties
,hoisting , and carefully lowering the pipes in to the ready made trenches or keeping in position on pedastals or supports and
laying them true to the alignment and gradient and perfect lining by jacking and jointing with three line arc welding and lining
and out coating fielded welded joints including hydraulic testing to a factory test pressure of 20kg/cm2 and field test pressure
of 13 kg/cm2.
Wt.of MS plate16mm thick for 1 Rmt of pipe:
3.142
0.246
1
16
7.85
97.08
Kgs
Add 10% towards wastage =
0.97
Kgs
98.05
Say
98.00
Kgs
Cost of16mm thick MS plate/Rmt
98 x
44000 /- MT
Rs.
4312.00
Rate of MS Plates Rs. 35000/- Per MT
Cost of fabrication charges
97.08 x
18000 /- MT
Rs.
1747.44
Inlining15mm thick in CM (1:2) prop required for 1 Rmt.
3.142 x 0.215x0.015 x 1.0
=
0.01
Cum.
Add 10% for wastage
=
0.001
Cum.
0.011
Cum.
Cost of CM (1:2) prop.
#REF!
x
0.01
Cum.
Rs.
#REF!
per Cum
Outcoating with CM (1:3) prop. required for 1 Rmt.
3.142 x 0.292x0.03 x 1.0
=
0.03
Cum.
Add 10% for wastage
=
0.00
Cum.
0.03
Cum.
Cost of CM (1:3) prop.
#REF!
x
0.03
Cum.
Rs.
#REF!
per Cum
MS rods 6mm dia at 4 Nos. each side
4 x 3.1415 x0.328 x 0.22 Kg
0.91 Kg
0.91
Kgs
Cost of 6mm MS rods inclg. fabrication @ 39000.00 /MT x
0.91
Kgs
Rs.
35.49

(f) Wire mesh of size 50mm x 50mm x 3mm.


Area of mesh: 3.142 x 0.292 x 1.0=
Cost of wire mesh @

MS pipe data

280

Sqm

Rs.

0.92 Sqm
50 /Sqm

0.92

Sqm

Rs.

46.00

aarvee associates

HMWSSB

Godavari pipe line Project

DATAS MS PIPES CSSR -2010-11 (April 2009)


(g) Guniting Charges:
Inlining: 3.142 x 0.215 x 1.0
Outcoating: 3.142 x 0.292x 1.0)

=
=

Cost of guniting @
81 /Sqm x
(h) Transportation Charges @ Rs.575=00 / MT
Weight of MS plate
=
Wt. of CM (1:2) + (1:3)
0.04
=

0.68
0.92
1.6
1.6

Sqm.
Sqm.
Sqm.
Sqm

98

Kgs.

92.4
190.4

Kgs.
Kgs.

Cost of Transportation @ Rs.575=00 / 1 MT


(i) Lowering, laying, jointing and testing
Total:
(k) Add for sundries
Total:
Rs.
150
MS
pipe
for
speci
als

(a)
(b)
(c)

(d)

(e)

280

#REF!

129.60

Rs.
Rs.
Rs.
Rs.
Rs.

109.48
280.00
#REF!
0.29
#REF! / Rmt

Rmt

Manufacturing, supplying, delivery at site and laying of 150 mm internal dia (after inlining) MS pipes with 16 mm thick mild steel
plates IS:2062-1992, with three run arc welding in 5 m or suitable lengths to suite the site conditions and as directed by the
departmental officers and inlining the fabricated pipes with CM(1:2) prop 15 mm thick duly fixing 4 nos of 6mm dia MS rings at
each end of the pipe and out coating the pipe with CM(1:3) prop 30mm thick by shortcreting or guniting duly providing
wiremesh of size 50x50x3 mm including cost of steel plates and all other required materials and including all taxes and duties
,hoisting , and carefully lowering the pipes in to the ready made trenches or keeping in position on pedastals or supports and
laying them true to the alignment and gradient and perfect lining by jacking and jointing with three line arc welding and lining
and out coating fielded welded joints including hydraulic testing to a factory test pressure of 20kg/cm2 and field test pressure
of 13 kg/cm2.
Wt.of MS plate16mm thick for 1 Rmt of pipe:
3.142
0.196
1
16
7.85
77.35
Kgs
Add 10% towards wastage =
0.77
Kgs
78.12
Say
78.00
Kgs
Cost of16mm thick MS plate/Rmt
78 x
44000 /- MT
Rs.
3432.00
Rate of MS Plates Rs. 35000/- Per MT
Cost of fabrication charges
77.35 x
18000 /- MT
Rs.
1392.30
Inlining15mm thick in CM (1:2) prop required for 1 Rmt.
3.142 x 0.165x0.015 x 1.0
=
0.01
Cum.
Add 10% for wastage
=
0.001
Cum.
0.011
Cum.
Cost of CM (1:2) prop.
#REF!
x
0.01
Cum.
Rs.
#REF!
per Cum
Outcoating with CM (1:3) prop. required for 1 Rmt.
3.142 x 0.242x0.03 x 1.0
=
0.02
Cum.
Add 10% for wastage
=
0.00
Cum.
0.02
Cum.
Cost of CM (1:3) prop.
#REF!
x
0.02
Cum.
Rs.
#REF!
per Cum
MS rods 6mm dia at 4 Nos. each side
4 x 3.1415 x0.278 x 0.22 Kg
0.77 Kg
0.77
Kgs
Cost of 6mm MS rods inclg. fabrication @ 39000.00 /MT x
0.77
Kgs
Rs.
30.03

(f) Wire mesh of size 50mm x 50mm x 3mm.


Area of mesh: 3.142 x 0.242 x 1.0=
Cost of wire mesh @
(g) Guniting Charges:
Inlining: 3.142 x 0.165 x 1.0
=
Outcoating: 3.142 x 0.242x 1.0)
=

0.76 Sqm
50 /Sqm

Cost of guniting @
81 /Sqm x
(h) Transportation Charges @ Rs.575=00 / MT
Weight of MS plate
=
Wt. of CM (1:2) + (1:3)
0.03
=
Cost of Transportation @ Rs.575=00 / 1 MT
(i) Lowering, laying, jointing and testing
Total:
(k) Add for sundries
Total:
Rs.

MS pipe data

/Rmt

Rs.

#REF!

0.76

0.52
0.76
1.28
1.28

Sqm.
Sqm.
Sqm.
Sqm

78

Kgs.

69.3
147.3

Kgs.
Kgs.
280

Sqm

/Rmt

Rs.

38.00

Rs.

103.68

Rs.
Rs.
Rs.
Rs.
Rs.

84.70
280.00
#REF!
2.74
#REF! / Rmt

Rmt

aarvee associates

HMWSSB

Godavari pipe line Project

100
MS
pipe
for
speci
als

(a)
(b)
(c)

(d)

(e)

DATAS MS PIPES CSSR -2010-11 (April 2009)


Manufacturing, supplying, delivery at site and laying of 100 mm internal dia (after inlining) MS pipes with 8 mm thick mild steel
plates IS:2062-1992, with three run arc welding in 5 m or suitable lengths to suite the site conditions and as directed by the
departmental officers and inlining the fabricated pipes with CM(1:2) prop 12 mm thick duly fixing 4 nos of 6mm dia MS rings at
each end of the pipe and out coating the pipe with CM(1:3) prop 20mm thick by shortcreting or guniting duly providing
wiremesh of size 50x50x3 mm including cost of steel plates and all other required materials and including all taxes and duties
,hoisting , and carefully lowering the pipes in to the ready made trenches or keeping in position on pedastals or supports and
laying them true to the alignment and gradient and perfect lining by jacking and jointing with three line arc welding and lining
and out coating fielded welded joints including hydraulic testing to a factory test pressure of 23kg/cm2 and field test pressure
of 16 kg/cm2.
Wt.of MS plate8mm thick for 1 Rmt of pipe:
3.142
0.132
1
8
7.85
26.05
Kgs
Add 10% towards wastage =
0.26
Kgs
26.31
Say
26.00
Kgs
Cost of8mm thick MS plate/Rmt
26 x
44000 /- MT
Rs.
1144.00
Rate of MS Plates Rs. 35000/- Per MT
Cost of fabrication charges
26.05 x
18000 /- MT
Rs.
468.90
Inlining12mm thick in CM (1:2) prop required for 1 Rmt.
3.142 x 0.112x0.012 x 1.0
=
0.00
Cum.
Add 10% for wastage
=
0.000
Cum.
0.000
Cum.
Cost of CM (1:2) prop.
#REF!
x
0.00
Cum.
Rs.
#REF!
per Cum
Outcoating with CM (1:3) prop. required for 1 Rmt.
3.142 x 0.16x0.02 x 1.0
=
0.01
Cum.
Add 10% for wastage
=
0.00
Cum.
0.01
Cum.
Cost of CM (1:3) prop.
#REF!
x
0.01
Cum.
Rs.
#REF!
per Cum
MS rods 6mm dia at 4 Nos. each side
4 x 3.1415 x0.186 x 0.22 Kg
0.51 Kg
0.51
Kgs
Cost of 6mm MS rods inclg. fabrication @ 39000.00 /MT x
0.51
Kgs
Rs.
19.89

(f) Wire mesh of size 50mm x 50mm x 3mm.


Area of mesh: 3.142 x 0.16 x 1.0=
Cost of wire mesh @
(g) Guniting Charges:
Inlining: 3.142 x 0.112 x 1.0
=
Outcoating: 3.142 x 0.16x 1.0)
=

0.5 Sqm
50 /Sqm

Cost of guniting @
81 /Sqm x
(h) Transportation Charges @ Rs.575=00 / MT
Weight of MS plate
=
Wt. of CM (1:2) + (1:3)
0.01
=
Cost of Transportation @ Rs.575=00 / 1 MT
(i) Lowering, laying, jointing and testing
Total:
(k) Add for sundries
Total:
Rs.

MS pipe data

#REF!

0.50

0.35
0.5
0.85
0.85

Sqm.
Sqm.
Sqm.
Sqm

26

Kgs.

23.1
49.1

Kgs.
Kgs.
280

Sqm

/Rmt

Rs.

25.00

Rs.

68.85

Rs.
Rs.
Rs.
Rs.
Rs.

28.23
280.00
#REF!
1.97
#REF! / Rmt

Rmt

aarvee associates

HMWSSB

Godavari pipe line Project

Water Supply Sluice Valves Rates as per CSSR- 2010-11


1

Sluice Vaves for 100mm up to 400mm dia


Manufacture, Supply and delivery of DI D/F Gate Valves of (Soft Seated) Resilient seated soft sealing gate
valves (Sluice valves) with body bonnet of ductile cast iron of grade GGG40/ SG 400/12 or equivalent grade as
per I.S.3896-part2-1985 and subsequent revisions, wedge fully rubber lined with EPDM and seals of NBR and the valves
should be of vaccum tight and 100% leak proof with face to face dimensions as per BS5163-89/IS14846-2000/DIN 3202 F
4. All the valves should be with Electrostatic powder coating both inside and outside pocket less body passage.Drilled as
per IS:1538/ISO including all other required materials, testing charges, inclusive of all taxes and duties, transportation to
work site, loading, unloading and hoisting and carefully lowering the valves into trenches / chambers, laying true to
alignment and gradient and perfect lining and jointing including cost of tail pieces, carbon steel nuts, bolts, and rubber
gaskets with 6mm thick packing including field hydraulic testing to a required pressure and including all duties taxes etc.,
complete for finished item of work.
600 mm dia
1 No

1 No
2 No

PN 10 & PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%
Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV
Jointing the valves

421512 /each
34732.59
18249.78
21075.6

421512
34732.59
18249.78
21075.6

/each

69379.80

2751.49 /each
3028.22 /each

Sundries
Rate Rs.
400 mm dia
1 No

1 No
2 No

PN 10 & PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%
Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV

179166 Each
14763.28
7757.17
8958.3

Jointing the valves

Rate Rs.

1 No
2 No

PN 10 & PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%
Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV

170823 Each
14075.82
7395.95
8541.15

870.42 /each
992.55 /each

Jointing the valves

Rate Rs.

1 No
2 No

PN 10 & PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%
Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV

56420 Each
4649.01
2442.76
2821

Jointing the valves

Rate Rs.

1 No

Valves data

PN 10 & PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%
Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV

170823
14075.82
7395.95
8541.15

870.42
1985.11
231808.47
0.53
231809.00 /1 No.

56420
4649.01
2442.76
2821
9286.59

515.40 /each
684.69 /each

Sundries

200 mm dia
1 No

1068.68
3095.99
244299.6838
0.32
244300.00 /1 No.

28117.03

Sundries

300 mm dia
1 No

179166
14763.28
7757.17
8958.3
29490.26

1068.68 /each
1547.99 /each

Sundries

350 mm dia
1 No

2751.49
6056.45
573757.7075
0.29
573758.00 /1 No.

26954 Each
2221.01
1167.00
1347.7

515.40
1369.37
77504.13
0.87
77505.00 /1 No.

26954
2221.01
1167.00
1347.7
4436.56

254.74 /each

254.74

aarvee associates

HMWSSB

Godavari pipe line Project

2 No

446.84 /each

Jointing the valves


Sundries

Rate Rs.
150 mm dia
1 No

1 No
2 No

PN 10 & PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%
Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV
Jointing the valves

16220 Each
1336.53
702.26
811

Rate Rs.

1 No
2 No

PN 10 & PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%
Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV

10301 Each
848.80
445.99
515.05

Jointing the valves

Rate Rs.

10301
848.80
445.99
515.05

91.10
503.37
14400.83731
0.16
14401.00 /1 No.

Manufacture, Supply and delivery of DI D/F Butterfly Valves of PN-16 with GGG40/SG 400/12 or Equivalent grade as per
I.S.3896-part 2-1985 and subsequent revisions, Double eccentrically Disc., with renewable soft seal on the disc and Body
seat face of stainless steel/nickel weld overlay with powder or liquid Expoxy coating with minimum thickness of 250 microns
applied on both body and disc inside and outside. Face to face dimensions as per AWWA C 504:80 or BS 5155 or
IS:13095. Drilled as per IS:1538.Including all other required materials, testing charges, inclusive of all taxes and duties,
transportation to work site, loading, unloading and hoisting and carefully lowering the valves into trenches / chambers,
laying true to alignment and gradient and perfect lining and jointing including cost of carbon steel nuts, bolts, and rubber
gaskets packing including field hydraulic testing to a required pressure etc., complete for finished item of work.

1500
1 No

1 No
2 No

PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%
Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV
Jointing the valves

2482376.00 Each
204547.78
107476.95
124118.8

Rate Rs.
1400
1 No

1 No

PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%
Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV
Jointing the valves

2751.49 /each

2751.49

0.00 /each

0.00

/1 No.

2081819.00 Each
171541.89
90134.44
104090.95

Rate Rs.

2751.49

0.00 /each

0.00

/1 No.

968651.00 Each
79816.84
41938.71

2081819
171541.89
90134.44
104090.95

2751.49 /each

Sundries

PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%

3329863.76
0.24
3329864.00 /1 No.

342662.08

2 No

1200
1 No

2482376
204547.78
107476.95
124118.8
408592.73

Sundries

Valves data

154.41
815.65
22709.62283
0.38
22710.00 /1 No.

1695.52
91.10 /each
251.69 /each

Sundries

16220
1336.53
702.26
811
2669.77

154.41 /each
407.83 /each

Sundries

100 mm dia
1 No

893.68
37274.69566
0.30
37275.00 /1 No.

2792999.84
0.16
2793000.00 /1 No.

968651
79816.84
41938.71

aarvee associates

HMWSSB

Godavari pipe line Project

1 No

Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV
Jointing the valves

48432.55

48432.55
159437.47

2 No

2751.49 /each

2751.49

0.00 /each

0.00

Sundries
Rate Rs.
1000
1 No

1 No

PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%
Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV
Jointing the valves

/1 No.

722935.00 Each
59569.84

2751.49 /each

2751.49

0.00 /each

0.00

Sundries
Rate Rs.

1 No

PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%
Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV
Jointing the valves

/1 No.

459560.00 Each
37867.74

Rate Rs.

2 No

PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%

2751.49

0.00 /each

0.00

Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV,item-16, pg no.42

618696.74
0.26
618697.00 /1 No.

290909
23970.90
12595.20
14545.45
47882.88

2751.49 /each
3028.22 /each

2751.49
6056.45
398711.3634
0.64

Sundries

Valves data

/1 No.

290909 Each
23970.90

Jointing the valves

459560
37867.74
19897.11
22978

2751.49 /each

Sundries

1 No

971696.5292
0.47
971697.00 /1 No.

75642.40

2 No

600 mm dia
1 No

722935
59569.84
31300.19
36146.75
118993.25

2 No

800
1 No

1301028.072
0.93
1301029.00 /1 No.

aarvee associates

HMWSSB

Godavari pipe line Project

Rate Rs.
500 mm dia
1 No

1 No
2 No

PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%

398712.00 /1 No.

185564 Each
15290.47

Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV,item-16, pg no.42

9278.2
30543.36
1619.95 /each
2166.26 /each

Jointing the valves

Rate Rs.

1 No
2 No

PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%

160710 Each
13242.50

Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV,item-16, pg no.42
Jointing the valves

26452.45
1068.68

1547.99 /each

3095.99
219563.228
0.77
219564.00 /1 No.

1 No
2 No

101331 Each
8349.67

Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV,item-16, pg no.42

16678.82
515.40 /each

Rate Rs.

1 No
2 No

PN 16
PN 16
Add CED 8.24%
CST/ VAT @ 4%

73100 Each
6023.44

Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV,item-16, pg no.42
Jointing the valves

12032.07
254.74

446.84 /each

893.68
99123.87674
0.12
99124.00 /1 No.

1 No
2 No

65006 Each
5356.49

Add Transportation @ 5%
Add 14% towards overhead
charges on cost of material
Lowering charges of SV,item-16, pg no.42

Sundries
Rate Rs.

Valves data

65006
5356.49
2814.50
3250.3
10699.82

154.41 /each
407.83 /each

Jointing the valves

73100
6023.44
3164.94

254.74 /each

Rate Rs.
PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%

1369.37

3655

Sundries

150 mm dia
1 No

515.40

137698.0501
0.95
137699.00 /1 No.

Sundries

200 mm dia
1 No

101331
8349.67
4387.23
5066.55

684.69 /each

Jointing the valves

160710
13242.50
6958.10

1068.68 /each

Rate Rs.
PN 16
Cost of Sluice Valve
Add CED 8.24%
CST/ VAT @ 4%

4332.53

8035.5

Sundries

300 mm dia
1 No

1619.95

254662.6883
0.31
254663.00 /1 No.

Sundries

400 mm dia
1 No

185564
15290.47
8034.18

154.41
815.65
88097.18
0.82
88098.00 /1 No.

aarvee associates

HMWSSB

Godavari pipe line Project

Air valves
Manufacture, Supply and Delivery of CI D/F Kinetic Air valve as per IS: 14845 Heavy duty with isolating valve bevel
gear operated as per IS 14846 including conveyance of valves and accessories including loading at factory and
unloading, stacking at site of work, Central Excise duty and sales tax etc, complete.

Size

Basic
cost

Conveyance
charges @ 10%
on basic cost of
valves

CED @
8.24%

Sales Tax
@ 4.0%

VAT @ 4%

Total Cost

40mm
50mm
80mm
100mm
150mm
200mm

7881
9197
12116
16689
32883
49036

788.1
919.7
1211.6
1668.9
3288.3
4903.6

714.33
833.62
1098.19
1512.69
2980.52
4444.62

375.34
438.01
577.03
794.82
1566.07
2335.37

390.35
11389.00
15003.00
20666.00
40718.00
60720.00

10149.12
22777.33
30005.83
41331.41
81435.89
121439.59

ARI makeHigh Flow Combination Air Release Valve Model D-070- PN 16


Supply and Delivery of ARI High Flow Combination Air Release Valves without float, with body
made with Ductile Iron and operating valve body with Reinforced Nylon, Rolling Seal of
E.P.D.M.Rubber, Clamping Stem with Reinforced Nylon, Polypropylene drainage Elbow,
operating assembly made with Elastomer,reinforced Nylon and Stainless Steel and Base with
ductile Iron, O-Ring seal with BUNA-N, Steel Zinc Cobalt Coated Bolts& nuts. Discharges high
air flow rates upto 160 m3/h, one size orifice for a wide pressure range (PN 16).The nozzle
made with bronze and fixing as per the directions of the departmental authorities

Size

80mm
100mm
150mm
200mm

Basic Import Duties at


VAT ON
CST @ 2%
cost
25%
@ 12.5%
59000
74000
134000
203000

14750
18500
33500
50750

1180.00
1480.00
2680.00
4060.00

7375.00
9250.00
16750.00
25375.00

Total

82305.00
103230.00
186930.00
283185.00

ARI make Surge suppression Air Valve: Model D-060 HFNS - PN 16 Bar
Supply and Delivery of ARI High Flow Combination Air Release Valves without float, with body
made with Ductile Iron ASTM A 536 and operating valve body with Reinforced Nylon, Rolling
Seal of E.P.D.M.Rubber, Clamping Stem with Reinforced Nylon, Foamed Polypropylene Float,
Base with Brass ASTM B124, O-Ring seal with BUNA-N, with Automatic Orifice area of 12mm2
,for a wide pressure range (PN 16).The nozzle seat made with bronze ASTM B-62 C 83600 and
fixing as per the directions of the departmental authorities

Size
50mm
80mm
100mm
150mm
200mm
250mm

Air valves data

Basic
cost
59000
76000
102000
182000
304000
677000

Import Duties at
VAT ON
CST @ 2%
25%
@ 12.5%
14750
19000
25500
45500
76000
169250

1180.00
1520.00
2040.00
3640.00
6080.00
13540.00

7375.00
9500.00
12750.00
22750.00
38000.00
84625.00

Total
82305.00
106020.00
142290.00
253890.00
424080.00
944415.00

aarvee associates

HMWSSB

Godavari pipe line Project

GUNTUR MUNICIPAL CORPORATION


DATA FOR THE YEAR 2010-11

1)

Anchoring MS pipes to cement concrete saddle with 100mm wide x 10mm thick mild steel restraining strap including cost and conveyance of
MS plates all taxes and duties, labour charges for cutting, bending and fixing straps in position in concrete by 2600mm long, stainless steel
grade hook (j) bolts, including cost of bolts as shown in the specification drawings and as directed by departmental officers etc., complete for
finished item of work
100 mx 10mm Strap
Cost of anchoring bolts and nuts
Fabrication charges

7.85
44000
1.2
44000
18000

Labour charges for fixing etc;


Add for sundries
Total:

Kg/RM
/MT x
Kg/RM
/MT x
/MT x

2.6
20.41

20.41
Kgs

2.6
3.12
3.12

Rs.

898.04

Rs.
Rs.

137.28
56.16

3.12
Kgs
Kgs

7.0 /Kg

Rs.
Rs.
Rs.

21.84
1.68
1115.00 /each

Rs. 1115.00 /each


Manufacturing ,Supplying and erection of air valve guard cabins of size 1.2x1.2x1.2 m made with 6 nos vertical and 6 nos horizontal MS angles
of size 70x70x6 mm and 10mm size MS square bars fixed at 5 cm c/c with door and locking arrangements as per approved drawing and as
directed by the departmental officers and painting both sides with anti corrosive paint two coats over one coat of primary coat including cost
2)
of all materials , fabrication ,welding , transportation to site, all taxes and duties,fixing in position duly embodying in CC(1:2:4) prop , and all
other incidental and operational charges etc complete for finished item of work.
Cost of MS angle = 6x1.2mx6.38 Kgx4x2
Cost of 10mm size MS square rods = (1.2/0.05)x2x4
Cost of locking system =

Fabrication charges
Cost of CC (1:2:4) = 4x0.6mx 0.6mx0.6
Labour charges for fixing etc;
Add for sundries
Total:

Say
44000 /MT x
11600 /MT x
0.864 Cum

367.488
192
10
569.488
570
1035
570.00
0.00

Kg/each
Kg/each
Kg/each
Kgs
Kgs
/Cum

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

25080.00
6612.00
0.00
200.00
8.00
31900.00 /each

Rs. 31900.00 /each


Manufacturing ,Supplying and erection of air valve guard cabins of size 1.8x1.8x1.8 m made with 8 nos vertical and 8 nos horizontal MS angles
of size 70x70x6 mm and 10mm size MS square bars fixed at 5 cm c/c with door and locking arrangements as per approved drawing and as
directed by the departmental officers and painting both sides with anti corrosive paint two coats over one coat of primary coat including cost
2)
of all materials , fabrication ,welding , transportation to site, all taxes and duties,fixing in position duly embodying in CC(1:2:4) prop , and all
other incidental and operational charges etc complete for finished item of work.
Cost of MS angle = 8x1.8mx6.38 Kgx4x2
Cost of 10mm size MS square rods = (1.8/0.05)x2x4
Cost of locking system =

Fabrication charges
Cost of CC (1:2:4) = 4x0.6mx 0.6mx0.6
Labour charges for fixing etc;
Add for sundries
Total:

Say
44000 /MT x
11600 /MT x
0.864 Cum

734.976
288
10
1032.976
1035
1035
1035.00
4031.75

Kg/each
Kg/each
Kg/each
Kgs
Kgs
/Cum

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

45540.00
12006.00
3483.44
200.00
0.62
61230.06 /each

Rs. 61240.00 /each

Data

10

aarvee associates

Godavari pipe line project

GUNTUR MUNICIPAL CORPORATION


Basic Cost Of Materials
As Per S.S.R for the Year 2011-2012
Sl.No.
I
1
II
2
3
4
5
6
7
8
9
10
11
12
13

16
III
13
14
15
17
18
19
20
21
22
23
24
25
26
V
27
28
29
30
31

input

Description of item
Basic cost of Materials
Municipal area allowance
Basic cost of Materials
20mm HBG SS5 M.C
12mm HBG SS5 M.C
10mm HBG SS5 M.C
6mm HBG SS5 M.C
40mm HBG SS5 M.C
Sand for mortar
Sand for Filling
Gravel
Bricks Second Class
Cement
Reinforcement Fe 415 Grade
MS Plates
Binding wire
Water
Crusher stone dust 2.36mm and below
Seignorage Charges
Building Stone, Rough Stone & Road Metal
Gravel, Morram & Earth
Ordinary Sand For Mortar & Filling
Bricks
Loading, Unloading & Stacking Charges
a) Metal
Loading
Unloading
b) Earth, Sand & Gravel
Loading
Unloading
c) Bricks
Loading
Unloading
d) Steel
Loading
Unloading
Labour Charges
Mason/Brick layer I class, Blacksmith, blaster
Mason / Brick layer II class, Chisseler, Hammerman
Heavy Mazdoor
Light mazdoor
Labour charges for fabrication of Reinforcement

Ref. Pg.
No.

S.S. item
no.

Rate

unit

25%
245 M-053
1175.00
245 M-052
980.00
245 M-051
820.00
244 M-050
655.00
245 M-055
745.00
243
M-005
325.00
243
M-004
250.00
243
M-008
80.00
10 BMT-A.01
3100.00
11
5
5400.00
13
62
42000.00
As per revised rate(23-05-11)
44000.00
11
3
55.00
250
M-189
77.00
26 M-022
415.00

1 cum
1 cum
1 cum
1 cum
1 cum
1 cum
1 cum
1 cum
1000 Nos.
1 M.T
1 M.T
1 M.T
Kg
KL
1 Cum

50.00
22.00
40.00
38.50

1 Cum
1 Cum
1 Cum
1000 Nos.

323 cl. b
323 cl. b

23.20 cum
11.60 cum

323 cl. b
323 cl. b

11.60 cum
5.80 cum

323 cl. b
323 cl. b

31.90 1000 Nos


31.90 1000 Nos

323 cl. b
323 cl. b

45.80 tonne
45.80 tonne

229
230
230
230

11
35
3
4

285.00
260.00
215.00
215.00
18.00

each
each
each
each
1 kg

11 of 110

Godavari pipe line project

Palasa Kasibugga Municipality


LEAD STATE MENT for 2011 -12
Materials

1
2
3
4
5
6
10
11

20mm HBG SS5 M.C


12mm HBG SS5 M.C
10mm HBG SS5 M.C
6mm HBG SS5 M.C
40mm HBG SS5 M C
Fine aggregate ( Sand )
Sand for Filling
Quarry dust/rubbish
Crusher stone dust 2.36mm
and below

I
I
I
I
I
I
I
I

I cum

8.00

13

Gravel

I cum

14
15
16

Bricks Second Class


1000 Nos.
Cement
1 M.T
Reinforcement Fe 415 Grade
1 M.T

12

Unit

Lead in
KM.

Sl.No.

cum
cum
cum
cum
cum
cum
cum
cum

Initial Cost Basic Rate

Conveya
nce
Total cost
charges

1175.00
980.00
820.00
655.00
745.00
325.00
250.00
80.00

1175.00
980.00
820.00
655.00
745.00
325.00
250.00
80.00

44.50
44.50
44.50
44.50
44.50
624.90
92.00
92.00

1219.50
1024.50
864.50
699.50
789.50
949.90
342.00
172.00

415.00

415.00

92.00

507.00

80.00

80.00

92.00

172.00

-----

3100.00
5400.00
42000.00

3100.00
5400.00
42000.00

0.00
0.00
0.00

3100.00
5400.00
42000.00

3
3
3
3
3
71.00
8.00
8.00

Certified that the leads are taken and correct to the best of my knowledge

lead

12 of 110

RCC valve chambers


Sl.
No.
1

Description

Supply & delivery of HYSD Fe415 grade


reinforcement steel including cost and
conveyance to site & labour charges, cutting,
bending, fabrication, binding of reinforcement,
including cost of binding wire etc., complete as
per SS but excluding all taxes & duties.
Refilling of trenches for pipe line with excavated
earth (other than sand) including watering and
tamping etc, complete.
Manufacture, Supply, Delivery and fabrication
of MS frame and cover, at site with MS joists
and MS chequerred plate including cost of
material, machine cutting charges, fixing in
opening , suitable to the size of the opening etc,
complete as per the directions of the
departmental authorities.
Add CED @ 10.30%on Rs. 7850
Add CST/VAT @ 4% (on basic cost of FRC
frame and CED)
Add for sundries
Sub-Total

Per

3.0m x 3.0m x3.0m

2.40m x 2.40m x2.40m

1.80m x 1.80m
x1.80m
Qty
Amount

Qty

Amount

Qty

Amount

Cum

57.60

#REF!

34.68

#REF!

18.82

#REF!

Cum

2.40

1216.80

1.73

879.14

1.18

596.23

Cum

2.89

9714.05

2.05

6888.63

1.35

4547.57

Cum

#REF!

#REF!

4.54
1.73
0.30
1.43

#REF!

#REF!

7.78
2.70
0.43
2.27

#REF!

Cum

11.88
3.89
0.97
2.92

53.49

Kgs.

1109.70

59356.59

753.30

40293.16

447.30

23925.57

159.32

Cum

13.43

2139.92

9.30

1481.31

5.92

943.14

7850

No

1.00

7850.00

1.00

7850.00

1.00

7850.00

Earthwork excavation and depositing on bank


in all type of soils like black cotton soils, red
earth and ordinary gravel, hard gravally soils,
#REF!
soft disintegrated rock like shales, ordinary
gravel, stoney earth and earth mixed with fair
sized boulders etc.
Supply, collection , stacking & filling of stone
dust including cost & conveyance of all
507.00
materials & labour charges, seignorage charges,
filling tamping charges etc complete as per S.S.
VCC (1:4:8) using 40 mm (SS-5) graded HBG
metal and OPC including cost & conveyance of
all materials, labour charges, centering,
3363.59
machinery, laying in position, vibration, curing
for 7 days and all incidental charges etc.
complete for levelling course
RCC in M 30 Grade design mix using 20mm
down graded SS-5 HBG m/c metal , coarse and
fine aggregates conforming to IS: 383, as per
mix design for Fair degree of quality control)
including cost and conveyance of all materials,
machinery, all labour char
(a) for side walls
#REF!
(b) for cover slabs
Deduct for openings in cover slab
Total quantity of cover slab
#REF!

Grand Total

RCC valve chamber

Rate

#REF!

808.55

808.55

808.55

346.34

346.34

346.34

#REF!
#REF!

#REF!
#REF!

#REF!
#REF!

#REF!
#REF!

#REF!
#REF!

#REF!
#REF!

13 of 110

Data for DI Pipes


Cenrtifugally Cast( Spun) Ductile Iron Pressure Pipes for Water, Gas and Sewerage with Socket Spigot Ends confirming to IS: 8329/2000 in Standard Working lengths of 4.0m,5.0m,5.50m & 6.0m for Push-On -Joint ( Rubber Gasket
D Jointing) with cement mortor lining insode the pipes with out side zinc coating , inclusive of all taxes of Excise Duty, CST, Transportation etc complete
Price of Pig Iron (present), R2

Rs 28000

Price of Pig Iron (as per SSR), R1


Distance from factory to site

Rs 27750
325
Kms

S.No

Dia of
Pipe

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

100
150
200
250
300
350
400
450
500
600
700
750
800
900
1000

Basic Rate as per


SSR (P1)
K7
K9
830
987
1151
1461
1602
1951
2148
2560
2759
3242
3470
4042
4211
4872
5063
5829
6033
6781
8026
8944
10383
11559
11632
12972
12857
14314
15686
17456
18596
20696

Lining
Barrel Thickness
K7
K9
Thickness
5.0
6.0
3
5.0
6.0
3
5.0
6.3
3
5.3
6.8
3
5.6
7.2
3
6.0
7.7
5
6.3
8.1
5
6.6
8.6
5
7.0
9.0
5
7.7
9.9
5
9.0
10.8
6
9.7
11.3
6
10.4
11.7
6
11.2
12.6
6
12.0
13.5
6

Weight of Pipe Increase/ Decrease of


(M) in kgs
rate
K7
K9
K7
K9
13.69
16.57
3.29
3.98
19.86
23.97
3.29
3.98
26.02
32.99
3.29
3.98
34.16
44.08
3.29
3.98
43.04
55.62
3.29
3.98
54.16
69.83
3.29
3.98
64.69
83.53
3.29
3.98
75.96
99.40
3.29
3.98
89.26
115.21
3.29
3.98
117.31
151.37
3.29
3.98
160.05
192.54
3.29
3.98
184.63
215.53
3.29
3.98
210.96
237.70
3.29
3.98
255.03
287.34
3.29
3.98
303.08
341.46
3.29
3.98

Revised Rate of Pipe


(P2)
K7
K9
833.29
990.98
1154.29
1464.98
1605.29
1954.98
2151.29
2563.98
2762.29
3245.98
3473.29
4045.98
4214.29
4875.98
5066.29
5832.98
6036.29
6784.98
8029.29
8947.98
10386.29 11562.98
11635.29 12975.98
12860.29 14317.98
15689.29 17459.98
18599.29 20699.98

CED @10.30%
Sales Tax @ 4.0%
K7
K9
K7
K9
85.83
102.071 36.76
43.72
118.89
150.893 50.93
64.63
165.34
201.363 70.83
86.25
221.58
264.09 94.91
113.12
284.52
334.336 121.87
143.21
357.75
416.736 153.24
178.51
434.07
502.226 185.93
215.13
521.83
600.797 223.52
257.35
621.74
698.853 266.32
299.35
827.02
921.642 354.25
394.78
1069.79
1190.99 458.24
510.16
1198.43
1336.53 513.35
572.50
1324.61
1474.75 567.40
631.71
1616.00
1798.38 692.21
770.33
1915.73
2132.1 820.60
913.28

Conveyance
charges
K7
K9
65.00
65.00
97.50
97.50
97.50
97.50
130.00
130.00
195.00
195.00
227.50
260.00
260.00
292.50
325.00
357.50
390.00
422.50
552.50
552.50
812.50
812.50
975.00
975.00
1657.50 1657.50
1657.50 1657.50
1657.50 1657.50

Data for DI Pipes


cket Spigot Ends confirming to IS: 8329/2000 in Standard Working lengths of 4.0m,5.0m,5.50m & 6.0m for Push-On -Joint ( Rubber Gasket
all taxes of Excise Duty, CST, Transportation etc complete

Total Cost of Pipe


per Rm
K7
K9
1020.88 1201.77
1421.60 1778.01
1938.95 2340.09
2597.78 3071.19
3363.67 3918.53
4211.78 4901.22
5094.29 5885.83
6136.64 7048.63
7314.34 8205.68
9763.05 10816.90
12726.82 14076.62
14322.07 15860.00
16409.79 18081.94
19654.99 21686.19
22993.11 25402.86

Data for Rubber Gaskets suitabe for C.I/ D.I/ S/S Pipes
Manufacture as per BIS:12820/89 with S.B.R. Quality Rubber confirming to BIS:5382/85, supply and delivery
of Rbber Gaskets suitable for CI, DI, S/S pipes any where in A.P. for destination departmental stores including
cost of material, loading, incidental, handling with companys standard packing, transportation, unloading &
stacking including Central Excise Duty, Sales Tax, Octroi and other Govt. levies etc complete

S.No

Dia of
Pipe

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

100
150
200
250
300
350
400
450
500
600
700
750
800
900
1000

Basic Rate as per


SSR (P1)
K7
K9
74
74
107
107
131
131
145
145
222
222
281
281
306
306
330
330
458
458
542
542
721
721
800
800
959
959
1158
1158
1267
1267

CED @10.30%
K7
K9
7.62
7.62
11.02
11.02
13.49
13.49
14.94
14.94
22.87
22.87
28.94
28.94
31.52
31.52
33.99
33.99
47.17
47.17
55.83
55.83
74.26
74.26
82.40
82.40
98.78
98.78
119.27
119.27
130.50
130.50

Sales Tax @4.0%


K7
K9
3.26
3.26
4.72
4.72
5.78
5.78
6.40
6.40
9.79
9.79
12.40
12.40
13.50
13.50
14.56
14.56
20.21
20.21
23.91
23.91
31.81
31.81
35.30
35.30
42.31
42.31
51.09
51.09
55.90
55.90

Total Cost of Pipe


per Rm
K7
K9
84.89
84.89
122.74
122.74
150.27
150.27
166.33
166.33
254.66
254.66
322.34
322.34
351.02
351.02
378.55
378.55
525.38
525.38
621.74
621.74
827.07
827.07
917.70
917.70
1100.09 1100.09
1328.36 1328.36
1453.40 1453.40

Data for Cast(spun) Ductile Iron Fittings


Centrifugally Cast(spun) Ductile Iron fittings confirming to IS: 9523/2000 having dimensions as per table,
including all taxes such as CED, CST, VAT and transportation to site of work complete as the directions of the
Departmental authorities.
Unit
Rate as per SSR

Kg

For all specials upto 500mm Dia For all specials above 500mm Dia
88.00

98.00

CED@ 8.24%

7.25

8.08

CST @4%

3.52

3.92

8.80
107.57

9.80
119.80

Transportation
Total

Data for Cast Iron Pipes & Fittings


Manufacture, supply and delivery of Cast Iron Pipes and fittings (spls) confirming to IS: 7181/1986,5531/1988,
3950/1979 and CID joints confirming toIS:8794/1988 at site of work any where in A.P., including loading,
unloading, transportation to site of work staking at site transit risk and package, including all Taxes and duties.
Unit
Rate as per SSR

Kg

For all CI Pipes & specials specials


58.00

CED@ 8.24%

4.78

CST @4%
Total

2.32
65.10

Data for Butterfly Valves


Manufacture, Supply and delivery of CI D/F Butterfly Valves manually gear operated confirming to IS 13095/1991 including all taxes and duties, transportation to work site, loading, unloading and hoisting
and carefully lowering the valves into trenches / chambers, laying true to alignment and gradient and perfect lining and jointing including cost of tail pieces, carbon steel nuts, bolts, and rubber gaskets
with 6mm thick packing including field hydraulic testing to a required pressure and including all duties taxes etc., complete for finished item of work.

Dia of Basic Rate as per


S.No Pipe
SSR (P1)
PN - 10 PN - 16

CED @8.240%
PN - 10
PN - 16

Sales Tax @4.0%


PN - 10
PN - 16

Transportation @ 5%
PN - 10
PN - 16

Add 14% towards


overhead charges on
cost of material
PN - 10
PN - 16

Lowering charges
of SV
PN - 10
PN - 16

Jointing of Sluice
valves
PN - 10
PN - 16

Total Cost of Pipe per


Rm
PN - 10
PN - 16

300

36722

41969

3025.89

3458.25

1589.92

1817.09

1836.10

2098.45

5141.08

5875.66

515.40

515.40

131.30

131.30

48961.69

55865.15

350

56822

64939

4682.13

5350.97

2460.17

2811.60

2841.10

3246.95

7955.08

9091.46

870.42

870.42

155.03

155.03

75785.92

86465.43

400

68033

77751

5605.92

6406.68

2945.56

3366.31

3401.65

3887.55

9524.62

10885.14

1068.68

1068.68

169.49

169.49

90748.92

103534.85

450

79489

90845

6549.89

7485.63

3441.56

3933.23

3974.45

4542.25

11128.46

12718.30

1397.51

1397.51

193.86

193.86

106174.73

121115.77

500

93726

107127

7723.02

8827.26

4057.96

4638.17

4686.30

5356.35

13121.64

14997.78

1619.95

1619.95

211.41

211.41

125146.28

142777.92

600

110343

126107

9092.26

10391.22

4777.41

5459.93

5517.15

6305.35

15448.02

17654.98

2751.49

2751.49

246.51

246.51

148175.85

168916.48

700

165613

189272

13646.51 15596.01

7170.38

8194.72

8280.65

9463.60

23185.82

26498.08

281.61

281.61

218177.97

249306.02

750

195200

223085

16084.48 18382.20

8451.38

9658.69

9760.00

11154.25

27328.00

31231.90

292.34

292.34

257116.20

293804.38

800

207905

237607

17131.37 19578.82

9001.45

10287.43

10395.25

11880.35

29106.70

33264.98

463.44

463.44

274003.22

313082.02

10

900

259760

296868

21404.22 24461.92

11246.57

12853.20

12988.00

14843.40

36366.40

41561.52

532.69

532.69

342297.88

391120.73

11

1000

334565

382360

27568.16 31506.46

14485.33

16554.66

16728.25

19118.00

46839.10

53530.40

584.60

584.60

440770.43

503654.12

12

1100

441591

504674

36387.10 41585.14

19119.12

21850.37

22079.55

25233.70

61822.74

70654.36

580999.51

663997.56

13

1200

518251

592286

42703.88 48804.37

22438.20

25643.61

25912.55

29614.30

72555.14

82920.04

681860.77

779268.32

14

1300

731853

836404

60304.69 68919.69

31686.31

36212.95

36592.65

41820.20

102459.42

117096.56

962896.06 1100453.40

15

1400

829922

948482

68385.57 78154.92

35932.30

41065.48

41496.10

47424.10

116189.08

132787.48

1091925.06 1247913.97

16

1500

946920 1082195 78026.21 89172.87

40997.85

46854.71

47346.00

54109.75

132568.80

151507.30

1245858.86 1423839.63

17

1600 1230294 1406050 101376.23 ######## 53266.81

60876.34

61514.70

70302.50

172241.16

196847.00

1618692.89 1849934.36

18

1800 1398328 1598088 115222.23 ######## 60542.01

69190.82

69916.40

79904.40

195765.92

223732.32

1839774.56 2102597.99

19

2000 1883693 2152792 155216.30 ######## 81556.37

93207.28

94184.65 107639.60 263717.02

301390.88

2478367.35 2832419.82

Data for DI D/F Butterfly Valves

Manufacture, Supply and delivery of DI D/F Butterfly Valves with GGG40/SG 400/12 or Equivalent grade as per I.S.3896-part 2-1985 and subsequent revisions, Double eccentrically Disc., with
renewable soft seal on the disc and Body seat face of stainless steel/nickel weld overlay with powder or liquid Expoxy coating with minimum thickness of 250 microns applied on both body and disc inside
and outside. Face to face dimensions as per AWWA C 504:80 or BS 5155 or IS:13095. Drilled as per IS:1538.Including all other required materials, testing charges, inclusive of all taxes and duties,
transportation to work site, loading, unloading and hoisting and carefully lowering the valves into trenches / chambers, laying true to alignment and gradient and perfect lining and jointing including cost of
carbon steel nuts, bolts, and rubber gaskets packing including field hydraulic testing to a required pressure etc., complete for finished item of work.

S.No

Dia of Basic Rate as per


Pipe
SSR (P1)
PN - 10 PN - 16

CED @8.240%
PN - 10
PN - 16

Sales Tax @4.0%


PN - 10
PN - 16

Transportation @ 5%
PN - 10
PN - 16

150

65006

65006

5356.49

5356.49

2814.50

2814.50

3250.30

3250.30

200

70802

73100

5834.08

6023.44

3065.44

3164.94

3540.10

250

82494

84892

6797.51

6995.10

3571.66

3675.48

4124.70

300

98433

101331

8110.88

8349.67

4261.76

4387.23

350

112623

122866

9280.14

10124.16

4876.13

400

141850

160710

11688.44 13242.50

6141.54

450

155726

172835

12831.82 14241.60

500

157207

185564

12953.86 15290.47

Add 14% towards


overhead charges on
PN - 10
PN - 16

Lowering charges
of SV
PN - 10
PN - 16

Jointing of Sluice
valves
PN - 10
PN - 16

Total Cost of Valve per


Each
PN - 10
PN - 16

9100.84

9100.84

154.41

154.41

251.69

251.69

85934.23

85934.23

3655.00

9912.28

10234.00

254.74

254.74

407.83

407.83

93816.48

96839.95

4244.60

11549.16

11884.88

362.02

362.02

446.84

446.84

109345.88

112500.92

4921.65

5066.55

13780.62

14186.34

515.40

515.40

654.11

654.11

130677.42

134490.30

5319.61

5631.15

6143.30

15767.22

17201.24

870.42

870.42

684.69

684.69

149732.74

163209.41

6958.10

7092.50

8035.50

19859.00

22499.40

1068.68

1068.68

992.55

992.55

188692.71

213506.74

6742.31

7483.06

7786.30

8641.75

21801.64

24196.90

1397.51

1397.51

1547.99

1547.99

207833.58

230343.82

6806.43

8034.18

7860.35

9278.20

22008.98

25978.96

1619.95

1619.95

1914.91

1914.91

210371.48

247680.67

600

206041

290909

16977.78 23970.90

8920.75

12595.20

10302.05

14545.45

28845.74

40727.26

2751.49

2751.49

2166.26

2166.26

276005.08

387665.56

10

700

406760

429196

33517.02 35365.75

17611.08

18582.47

20338.00

21459.80

56946.40

60087.44

2751.49

2751.49

3028.22

3028.22

540952.22

570471.18

11

800

440977

459560

36336.50 37867.74

19092.54

19897.11

22048.85

22978.00

61736.78

64338.40

2751.49

2751.49

3028.22

3028.22

585971.39

610420.97

12

900

576712

576712

47521.07 47521.07

24969.32

24969.32

28835.60

28835.60

80739.68

80739.68

2751.49

2751.49

3028.22

3028.22

764557.39

764557.39

13

1000

722935

722935

59569.84 59569.84

31300.19

31300.19

36146.75

36146.75

101210.90

101210.90

2751.49

2751.49

3028.22

3028.22

956942.40

956942.40

14

1100

831375

68505.30

35995.21

0.00

41568.75

0.00

116392.50

0.00

2751.49

2751.49

3028.22

3028.22 1099616.48

15

1200

968651

968651

41938.71

41938.71

48432.55

48432.55

135611.14

135611.14

2751.49

2751.49

3028.22

3028.22 1280229.96 1280229.96

16

1400 2081819 2081819 171541.89 ######## 90134.44

90134.44 104090.95 104090.95 291454.66

291454.66

2751.49

2751.49

3028.22

3028.22 2744820.65 2744820.65

17

1600 2482376 2482376 204547.78 ######## 107476.95 107476.95 124118.80 124118.80 347532.64

347532.64

2751.49

2751.49

3028.22

3028.22 3271831.89 3271831.89

18

1800 3044778 3044778 250889.71 ######## 131826.71 131826.71 152238.90 152238.90 426268.92

426268.92

2751.49

2751.49

3028.22

3028.22 4011781.95 4011781.95

19

2000 5201268 5201268 428584.48 ######## 225194.10 225194.10 260063.40 260063.40 728177.52

728177.52

2751.49

2751.49

3028.22

3028.22 6849067.22 6849067.22

20

2200 7509052 7509052 618745.88 ######## 325111.92 325111.92 375452.60 375452.60 1051267.28 #########

2751.49

2751.49

3028.22

3028.22 9885409.40 9885409.40

0.00

79816.84 79816.84

5779.72

PHE-LCIF-2A

2A

Sub Analysis : (Basic Data)


OBSERVED DATA FOR TESTING OF 450
MM DIA PSC MAIN : Pumping main to
Hydralic field test pressure including

(Length = 500 Mts) taking out put /


500 Mts.Labour
Unit = 1 Rmt.
Fitters (2 x 3 days)
Fitters I Class
Fitters II Class
Machinery
Hire chargers for Hydralic field test
pressure testing including transportation of
water @ Rs. 1200/- (1000+200) / day

localmarket
pg. 98
localmarket
pg. 207

Materials
Pressure guage
3/4" G.I. Pipe (20 mm)
Specials
Dummies
Diesel (2 Lts. / Hr) 30 Hrs.
(T) Total Rate per 500 Mts.
(r) Rate per 1 Rmt for 450 mm dia

day
day

3.00
3.00

days

3.00

285.00
260.00

855.00
780.00

1200.00

3600.00

Nos
RM
Ls
No.

0.05
3.00

200.00
146.00

10.00
438.00

0.10

Lts.

60.00

20.00
45.00

2700.00

2.00
8385.00
16.77

(R) Rate per 1 Rmt for 10 mm dia =


(10/450) x r
Note : Proportionate Testing
Charges may be arrived, keeping
the diametre of pipe based on this
5

PHE-JCIF-5

Jointing CI pipes, fittings and valves


with flanged ends including cost of
jointing materials such as bolts,
rubber insertion, white lead including
filling with water, with lead up to 500
meters and testing to required pressure
complete. (Reference to specifications.
BIS No.3114/1994.)

80 mm dia pipe

Details of cost for 10 joints

Rates

Quantity

Amount

a)

Labour

Plumber 1st class

day

285.00

0.090

25.65

Plumber 2nd class

day

260.00

0.210

54.60

Man mazdoor

day

215.00

0.800

172.00

Sub total (a)

252.25

b) Material
Bolts and nuts 16mm dia 60mm long
Rubber insertion 5mm thick
White lead

kg
kg

106.02
87.78

6.800
2.125

720.94
186.53

Sub total (b)

907.47

c) Testing
Testing of Pipelines with required pressure
as per relevant IS Specification including
filling with water with a water lead upto 500
M, including hire charges of testing
equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

rm

27.500

Sub total (c)

81.99

81.99

(d) Total = a+b+c

1241.71
(e) Add for water charges @ 1% on
Labour & Testing Charges

3.34

(f) Total = d+e

1245.05
MAA @ 25%

63.06
183.14
1491.25

(g) Overheads & Contractors Profit


(h) Cost for 10 joints (f+g)
Rate per joint = h/10

PHE-CISP-14
(sub analysis)

2A

149.12

Sub Analysis : (Basic Data)


Labour charges for laying in position
S&S or flanged CI specials such as
Tees, bends, collars and caps etc.

10 Nos Tees of 200 x 150mm dia


Weight = 10 x 70kgs = 700 kgs
Labour
Plumber I Class
Plumber II Class
Man mazdoor
Cost for 700 kgs

day
day
day

0.465
1.094
2.480

285.00
260.00
215.00

Cost for 1 kg

PHE-CISV-15

Lowering, keeping in position and fixing CI


sluice valves (with cap/with hand wheel
and reflux valves) excluding cost of bolts,
nuts, rubber insertion, sluice valve and tail
pieces.

132.53
284.44
533.20
950.17
1.36

80 mm dia sluice valve

Rates

Details of cost for 1 No


i

Quantity

Amount

Weight =
(32.30+34.10+40)/3 =
35.47
(a) Labour charges for laying sluice
valve with cap, with hand wheel and
reflux valve
MAA @ 25%

(b) Overheads & Contractors Profit

kgs

1.36

35.470

48.15

12.04

8.43

68.61

Rate per 1 sluice valve

PHE-LRCS-6

Lowering the RCC S/S pipes carefully into


the trenches laying them true to alignment
and gradient, jointing with rubber rings and
testing including filling with water with a
water lead upto 500 meters including cost
of rubber rings as per BIS No. 783/1985

80 mm dia pipe

Unit = 1rmt
Rates

Quantity

Amount

day

285.00

0.780

222.30

day

260.00

1.800

468.00

Man mazdoor

day

215.00

5.000

1075.00

Women mazdoor (Water carrier)

day

215.00

1.300

279.50

Taking output 100rmt


i

a)

Labour

Mason 1st class


Mason 2

nd

class

Sub total (a)

2044.80

b) Material
Rubber rings conforming BIS
5382/1985

each

50.000
Sub total (b)

900.00
900.00

c) Testing
Testing of Pipelines with required pressure
as per relevant IS Specification including
filling with water with a water lead upto 500
M, including hire charges of testing
equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

rm

100.000

Sub total (c)

298.13

298.13

(d) Total = a+b+c

3242.93
(e) Add for water charges @ 1% on
Labour & Testing Charges

23.43

(f) Total = d+e

3266.36
MAA @ 25%
(g) Overheads & Contractors Profit

511.20
528.86

4306.42

(h) Cost for 100 rmt (f+g)


Rate per rmt = h/100

PHE-JCIR-4

43.06

Jointing CI, DI pipes and fittings with rubber


gasket (push-pn-joints), excluding the cost
of gasket but including all sundries, filling
with water, with a water lead up to 500
meters and testing to required pressure etc
complete. (Reference to specifications. BIS
No.3114/1994/12288/1997.)

80 mm dia pipe

Details of cost for 10 joints

Rates

Quantity

Amount

a)

Labour

Plumber 1st class

day

285.00

0.000

0.00

Plumber 2nd class

day

260.00

0.300

78.00

Man mazdoor

day

215.00

0.800

172.00

Sub total (a)

250.00

b) Material
Bolts and nuts 16mm dia 60mm long
Rubber insertion 5mm thick
White lead

kg
kg

106.02
87.78

0.000
0.000

Sub total (b)

0.00
0.00

0.00

c) Testing
Testing of Pipelines with required pressure
as per relevant IS Specification including
filling with water with a water lead upto 500
M, including hire charges of testing
equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)

rm

50.000

Sub total (c)

149.07

149.07

(d) Total = a+b+c

399.07
(e) Add for water charges @ 1% on
Labour & Testing Charges

3.99

(f) Total = d+e

403.06
MAA @ 25%
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10

62.50
65.18
530.74
53.07

100 mm dia pipe

125 mm dia pipe

150 mm dia pipe

200 mm dia pipe

250 mm dia pipe

Quantity

Amount

Quantity

Amount

Quantity

Amount

Quantity

Amount

Quantity

0.150

42.75

0.150

42.75

0.180

51.30

0.180

51.30

0.200

0.350

91.00

0.350

91.00

0.420

109.20

0.420

109.20

0.420

1.000

215.00

1.000

215.00

1.100

236.50

1.100

236.50

1.200

348.75

Sub total (a)

348.75

397.00

Sub total (a)

397.00

Sub total (a)

1441.87
222.96

13.600
3.140

1441.87
275.63

2544.48
377.45

25.200
6.160

2671.70
540.72

39.600
8.500

Sub total (a)

13.600
2.540

Sub total (a)

24.000
4.300

Sub total (b)

27.500

Sub total (c)

1664.83

Sub total (b)

1717.50

102.48

27.500

128.10

102.48

Sub total (c)

128.10

Sub total (b)

27.500

Sub total (c)

2921.93

Sub total (b)

3212.43

Sub total (b)

153.73

27.500

204.97

27.500

153.73

Sub total (c)

204.97

Sub total (c)

2116.07

2194.36

3472.66

3814.40

4.51

4.77

5.51

6.02

2120.58

2199.12

3478.17

3820.42

87.19
309.09
2516.85

87.19
320.08
2606.40

99.25
500.84
4078.25

99.25
548.75
4468.42

251.69

260.64

407.83

446.84

100 mm dia sluice valve

125 mm dia sluice valve

150 mm dia sluice valve

Quantity

Quantity

Quantity

Amount

Weight = (44.30+47+50)/3
= 47.10
47.100

63.93

Amount

Amount

Weight =
Weight = (72.50+77+90)/3
(56.30+59+70)/3 = 61.77
= 79.83
61.770

83.85

79.830

108.36

200 mm dia sluice valve

Quantity

Amount

Weight =
(121.5+128.6+145)/3 =
131.7
131.700

178.77

15.98

20.96

27.09

44.69

11.19

14.67

18.96

31.28

250 mm dia sluice valve

Quantity

Weight =
(179.9+186.6+195)/3 =
187.16
187.160

91.10

100 mm dia pipe

119.48

154.41

150 mm dia pipe

254.74

200 mm dia pipe

250 mm dia pipe

Quantity

Amount

Quantity

Amount

Quantity

Amount

Quantity

0.960

273.60

1.170

333.45

1.170

333.45

1.620

2.240

582.40

2.730

709.80

2.730

709.80

3.780

6.300

1354.50

7.800

1677.00

7.800

1677.00

10.500

1.600

344.00

1.600

344.00

1.600

344.00

2.300

3064.25

Sub total (a)

3064.25

Sub total (a)

1950.00

50.000

2250.00

50.000

Sub total (a)

50.000

2554.50

1100.00

Sub total (a)

50.000

Sub total (b)

1100.00

Sub total (b)

1950.00

Sub total (b)

2250.00

Sub total (b)

100.000

372.67

100.000

559.00

100.000

745.33

100.000

Sub total (c)

372.67

Sub total (c)

559.00

Sub total (c)

745.33

Sub total (c)

4027.17

5573.25

6059.58

36.23

38.10

4056.44

5609.48

6097.68

638.63
657.31

766.06
892.58

766.06
960.92

29.27

5352.37

7268.12

7824.67

53.52

72.68

78.25

100 mm dia pipe

125 mm dia pipe

150 mm dia pipe

200 mm dia pipe

250 mm dia pipe

Quantity

Amount

Quantity

Amount

Quantity

Amount

Quantity

Amount

Quantity

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.500

130.00

0.500

130.00

0.600

156.00

0.600

156.00

0.620

1.000

215.00

1.000

215.00

1.100

236.50

1.100

236.50

1.200

345.00

Sub total (a)

345.00

392.50

Sub total (a)

392.50

Sub total (a)

0.00
0.00

0.000
0.000

0.00
0.00

2544.48
0.00

0.000
0.000

0.00
0.00

0.000
0.000

2544.48

Sub total (b)

0.00

Sub total (b)

279.50

50.000

372.67

50.000

279.50

Sub total (c)

372.67

Sub total (c)

Sub total (a)

0.000
0.000

Sub total (a)

24.000
0.000
0.000

Sub total (b)

50.000

Sub total (c)

0.00

Sub total (b)

0.00

186.33

50.000

232.92

186.33

Sub total (c)

232.92

531.33
5.31

577.92
5.78

Sub total (b)

50.000

Sub total (c)

3216.48
6.72

765.17
7.65

536.65

583.70

3223.20

772.82

86.25
87.21
710.10

86.25
93.79
763.74

98.13
464.99
3786.31

98.13
121.93
992.88

71.01

76.37

378.63

99.29

250 mm dia pipe

300 mm dia pipe

350 mm dia pipe

400 mm dia pipe

450 mm dia pipe

Amount

Quantity

Amount

Quantity

Amount

Quantity

Amount

Quantity

Amount

57.00

0.240

68.40

0.300

85.50

0.300

85.50

0.360

102.60

109.20

0.560

145.60

0.600

156.00

0.700

182.00

0.840

218.40

258.00

1.200

258.00

1.500

322.50

1.500

322.50

1.700

365.50

424.20

Sub total (a)

472.00

Sub total (a)

564.00

Sub total (a)

590.00

Sub total (a)

686.50

4198.39
746.13

39.600
10.280

4198.39
902.38

54.400
21.260

5767.49
1866.20

98.400
22.660

10432.37
1989.09

123.000
27.640

13040.46
2426.24

4944.52

Sub total (b)

5100.77

Sub total (b)

7633.69

Sub total (b)

12421.46

Sub total (b)

15466.70

256.21

27.500

307.45

27.500

358.69

27.500

409.93

27.500

461.18

256.21

Sub total (c)

307.45

Sub total (c)

358.69

Sub total (c)

409.93

Sub total (c)

461.18

5624.93

5880.22

8556.38

13421.40

6.80

7.79

9.23

10.00

5631.73

5888.01

8565.61

13431.40

16625.85

106.05
803.29
6541.07

118.00
840.84
6846.86

141.00
1218.93
9925.53

147.50
1901.05
15479.94

171.63
2351.65
19149.12

654.11

684.69

992.55

1547.99

1914.91

250 mm dia sluice valve

Amount

Weight =
(179.9+186.6+195)/3 =
187.16
254.05

300 mm dia sluice valve

Quantity

Amount

Weight =
(242.40+257+300)/3 =
266.46
266.460

361.69

350 mm dia sluice valve

Quantity

Amount

Weight = (430+470)/2 =
450
450.000

610.82

400 mm dia sluice valve

Quantity

Amount

Weight = (525+580)/2 =
552.5
552.500

749.95

16614.37
11.48

450 mm dia sluice valve

Quantity

Amount

Weight = (635+810)/2 =
722.5
722.500

980.71

63.51

90.42

152.71

187.49

245.18

44.46

63.30

106.89

131.24

171.62

362.02

250 mm dia pipe

515.40

300 mm dia pipe

870.42

350 mm dia pipe

1068.68

400 mm dia pipe

1397.51

450 mm dia pipe

Amount

Quantity

Amount

Quantity

Amount

Quantity

Amount

Quantity

Amount

461.70

1.750

498.75

1.900

541.50

2.100

598.50

2.250

641.25

982.80

4.140

1076.40

4.500

1170.00

4.900

1274.00

5.250

1365.00

2257.50

11.600

2494.00

12.700

2730.50

13.900

2988.50

15.000

3225.00

494.50

2.300

494.50

2.400

516.00

2.900

623.50

3.300

709.50

4196.50

Sub total (a)

4563.65

Sub total (a)

4958.00

Sub total (a)

5484.50

Sub total (a)

5940.75

2800.00

40.000

3520.00

40.000

4200.00

40.000

4800.00

40.000

5440.00

2800.00

Sub total (b)

3520.00

Sub total (b)

4200.00

Sub total (b)

4800.00

Sub total (b)

5440.00

931.67

100.000

1118.00

100.000

1304.33

100.000

1490.67

100.000

1677.00

931.67

Sub total (c)

1118.00

Sub total (c)

1304.33

Sub total (c)

1490.67

Sub total (c)

1677.00

7928.17
51.28

9201.65
56.82

10462.33
62.62

11775.17
69.75

13057.75
76.18

7979.45

9258.47

10524.96

11844.92

13133.93

1049.13
1264.00

1140.91
1455.91

1239.50
1647.02

1371.13
1850.25

1485.19
2046.68

10292.57

11855.29

13411.48

15066.29

16665.79

102.93

118.55

134.11

150.66

166.66

250 mm dia pipe

300 mm dia pipe

350 mm dia pipe

400 mm dia pipe

450 mm dia pipe

Amount

Quantity

Amount

Quantity

Amount

Quantity

Amount

Quantity

Amount

0.00

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

161.20

0.800

208.00

0.900

234.00

1.000

260.00

1.200

312.00

258.00

1.200

258.00

1.500

322.50

1.500

322.50

1.700

365.50

419.20

Sub total (a)

466.00

Sub total (a)

556.50

Sub total (a)

582.50

Sub total (a)

677.50

0.00
0.00

0.000
0.000

0.00
0.00

0.000
0.000

0.00
0.00

0.000
0.000

0.00
0.00

0.000
0.000

0.00
0.00

0.00

Sub total (b)

0.00

Sub total (b)

0.00

Sub total (b)

0.00

Sub total (b)

0.00

465.83

50.000

559.00

50.000

652.17

50.000

745.33

50.000

838.50

465.83

Sub total (c)

559.00

Sub total (c)

652.17

Sub total (c)

745.33

Sub total (c)

838.50

885.03
8.85

1025.00
10.25

1208.67
12.09

1327.83
13.28

1516.00
15.16

893.88

1035.25

1220.75

1341.11

1531.16

104.80
139.82
1138.50

116.50
161.25
1313.00

139.13
190.38
1550.26

145.63
208.14
1694.88

169.38
238.07
1938.61

113.85

131.30

155.03

169.49

193.86

500 mm dia pipe

600 mm dia pipe

700 mm dia pipe

750 mm dia pipe

Quantity

Amount

Quantity

Amount

Quantity

Amount

Quantity

Amount

0.390

111.15

0.450

128.25

0.510

145.35

0.510

145.35

0.910

236.60

1.050

273.00

1.190

309.40

1.190

309.40

1.800

387.00

2.000

430.00

2.200

473.00

2.200

473.00

Sub total (a)

734.75

Sub total (a)

831.25

Sub total (a)

927.75

Sub total (a)

927.75

134.000
38.190

14206.68
3352.32

192.000
51.710

20355.84
4539.10

244.800
68.910

25953.70
6048.92

260.400
78.430

27607.61
6884.59

Sub total (b)

17559.00

Sub total (b)

24894.94

Sub total (b)

32002.62

Sub total (b)

34492.19

27.500

512.42

27.500

614.90

27.500

717.38

27.500

768.63

Sub total (c)

512.42

Sub total (c)

614.90

Sub total (c)

717.38

Sub total (c)

768.63

18806.16

26341.09

12.47

14.46

18818.64

26355.56

33664.20

36205.53

183.69
2660.33
21662.65

207.81
3718.87
30282.24

231.94
4745.46
38641.60

231.94
5101.25
41538.72

2166.26

3028.22

3864.16

4153.87

500 mm dia sluice valve

Quantity

Amount

Weight = (775+900)/2 =
837.5
837.500

1136.80

600 mm dia sluice valve

Quantity

Amount

Weight = (1220+1625)/2 =
1422.5
1422.500

1930.87

284.20

482.72

198.94

337.90

33647.75
16.45

36188.57
16.96

1619.95

500 mm dia pipe

2751.49

600 mm dia pipe

Quantity

Amount

Quantity

Amount

2.430

692.55

2.750

783.75

5.670

1474.20

6.450

1677.00

16.200

3483.00

16.300

3504.50

3.300

709.50

3.300

709.50

Sub total (a)

6359.25

Sub total (a)

6674.75

40.000

6240.00

40.000

9080.00

Sub total (b)

6240.00

Sub total (b)

9080.00

100.000

1863.33

100.000

2236.00

Sub total (c)

1863.33

Sub total (c)

2236.00

14462.58

17990.75

82.23

89.11

14544.81

18079.86

1589.81
2258.85

1668.69
2764.80

18393.47

22513.34

183.93

225.13

500 mm dia pipe

600 mm dia pipe

700 mm dia pipe

750 mm dia pipe

Quantity

Amount

Quantity

Amount

Quantity

Amount

Quantity

Amount

0.000

0.00

0.000

0.00

0.000

0.00

0.000

0.00

1.300

338.00

1.500

390.00

1.700

442.00

1.700

442.00

1.800

387.00

2.000

430.00

2.200

473.00

2.200

473.00

Sub total (a)

725.00

Sub total (a)

820.00

Sub total (a)

915.00

Sub total (a)

915.00

0.000
0.000

0.00
0.00

0.000
0.000

0.00
0.00

0.000
0.000

0.00
0.00

0.000
0.000

0.00
0.00

Sub total (b)

0.00

Sub total (b)

0.00

Sub total (b)

0.00

Sub total (b)

0.00

50.000

931.67

50.000

1118.00

50.000

1304.33

50.000

1397.50

Sub total (c)

931.67

Sub total (c)

1118.00

Sub total (c)

1304.33

Sub total (c)

1397.50

1656.67
16.57

1938.00
19.38

2219.33

2312.50

22.19

23.13

1673.23

1957.38

2241.53

2335.63

181.25
259.63
2114.11

205.00
302.73
2465.11

228.75
345.84
2816.12

228.75
359.01
2923.39

211.41

246.51

281.61

292.34

800 mm dia pipe

900 mm dia pipe

1000 mm dia pipe

Amount

Amount

Amount

43120.00

50710.00

58410.00

6036.80
0.00

7099.40
0.00

8177.40
0.00

0.00

0.00

0.00

800 mm dia pipe

900 mm dia pipe

1000 mm dia pipe

Quantity

Amount

Quantity

Amount

Quantity

Amount

2.350

669.75

2.750

783.75

3.000

855.00

4.700

1222.00

5.500

1430.00

6.000

1560.00

0.650

139.75

0.700

150.50

0.750

161.25

Sub total
(a)

2031.50

Sub total
(a)

2364.25 Sub total


(a)

2576.25

0.000
0.000

0.00
0.00

0.000
0.000

0.00
0.00

0.000
0.000

0.00
0.00

Sub total
(b)

0.00

Sub total
(b)

0.00

Sub total
(b)

0.00

50.000

1490.67

50.000

Sub total
(c)

1490.67

Sub total
(c)

50.000

1863.33

1677.00 Sub total


(c)

1863.33

1677.00

3522.17

4041.25

4439.58

35.22

40.41

44.40

3557.39

4081.66

4483.98

507.88
569.14
4634.40

591.06
654.18
5326.91

644.06
717.93
5845.97

463.44

532.69

584.60

Godavari pipe line project

GUNTUR MUNICIPAL CORPORATION


Sl. No. 26a, pg.
no. 257, bldg
SSR

Cutting BT Road Surface including stacking of excavated material for pipe line trench

10 Sqm
Add Municipal Area Allowance @20%
Sub - Total
Add overhead and contracotrs profit of 14%

20%

1 Sqmt
Sl. No. 26b, pg.
no. 258, bldg
SSR

Cutting Open CC Road Surface including stacking of excavated material for pipe line trench

1 cum
Add Municipal Area Allowance @20%
Sub - Total
Add overhead and contracotrs profit of 14%

20%

1 Cum
Sl. No. 26c, pg.
no. 258, bldg
SSR

10

596.00
119.20
715.20
100.13
815.33
81.53

1656.00
331.20
1987.20
278.21
2265.41

Cutting Open WB M including stacking of excavated material for pipe line trench

1 cum
Add Municipal Area Allowance @20%
Sub - Total
Add overhead and contracotrs profit of 14%

20%

1 Cum

204.00
40.80
244.80
34.27
279.07

15 Collection , supply & filling sand including watering, tamping, etc complete
A. MATERIALS:
Sl No
1

Particulars
Sand

Unit

Quantity

cum

1.00
0.00

Total cost of Materials


B.MACHINERY:
Sl No
1

Particulars

Unit

Quantity

NIL

UNIT :
1
Rate
in Rs.
342.00
0.00
Rs:

Rate
in Rs.

0.00
0.00
Total hire charges of machinery

C.LABOUR
Sl No
1
2

Particulars

Male
Mazdoor ( un skilled)

Unit

Quantity

day
day
Total cost of labour

0.00
0.31

Add 25% over basic rate for area allowance


Total cost of labour
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)

general data

14%

cum
Amount
in Rs.
342.00
0.00
342.00

Amount
in Rs.
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.

Amount
in Rs.
0.00 0.00
215.00 66.65
Rs: 66.65
16.66
83.31
Rs:
Rs:
Rs:
Rs:
Rs:
Rs.

342.00
0.00
83.31
425.31
59.54375

39 of 110

Godavari pipe line project

Total cost for

1.00

Rate per

cum

Rs: 484.86

cum (A+B+C+D) /1

Rs: 484.86

16 Refilling the pipe line trenches with excavated soils other than sand complying with standard
specification for finished item of work
A. MATERIALS:
Sl No
1

Particulars

Unit

Quantity

NIL

0.00
0.00
Total cost of Materials

B.MACHINERY:
Sl No
1

Particulars

Unit

Quantity

NIL

UNIT :
6
Rate
in Rs.
0.00
0.00
Rs:

Rate
in Rs.

0.00
0.00
Total hire charges of machinery

C.LABOUR
Sl No
1
2

Particulars

Male
Mazdoor ( un skilled)

Unit

Quantity

day
day
Total cost of labour

0.00
3.12

Add 25% over basic rate for area allowance


Total cost of labour

17

Amount
in Rs.
0.00 0.00
0.00 0.00
Rs: 0.00

Rate
in Rs.

Amount
in Rs.
0.00 0.00
215.00 670.80
Rs: 670.80
167.70
838.50
Rs:

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D.Add for contractor's profit and overheads on (A+B+C)
Total cost for
6.00
Rate per
cum (A+B+C+D) /6

cum
Amount
in Rs.
0.00
0.00
0.00

Rs:
Rs:
Rs:
Rs:
Rs.
Rs:
Rs:

14%
cum

0.00
0.00
838.50
838.50
117.39
955.89
159.32

Carting away the surplus excavated earth from the work site with a lead of 0.5 km beyond initial lead
including loading, unloading and conveyance but excluding stacking charges etc., complete - 1 cum
1.00
Cum
1
Cum
63.50
63.50
Sub - Total
63.50
8.89
Add overhead and contracotrs profit of 14%
72.39

18

Carting away the surplus excavated rock from the work site with a lead of 0.5 km beyond initial lead
including loading, unloading and conveyance but excluding stacking charges etc., complete - 1 cum
1.00
Cum
1
Cum
63.50
63.50
Sub - Total
63.50
8.89
Add overhead and contracotrs profit of 14%
72.39
19 laying Cement concrete ( 1: 2 : 4) graded HBG metal including cost of all materials and
labour charges etc. complete

RATE ANALYSIS

UNIT :

1.00 cum

A. MATERIALS:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

general data

Cement for mix

Coarse sand

3
4

kg

in Rs.

275.00

5.40

1485.00

cum

0.48

949.90

455.95

Coarse aggregate 40 mm

cum

0.54

789.50

426.33

Coarse aggregate 20 mm

cum

0.27

1219.50

329.27

40 of 110

Godavari pipe line project

Coarse aggregate 10 mm

Water (including curing)

cum
kl
(Included in
rate)
Rs.
(Included in
rate)
Rs.

Add seignorage charges on CA @


Add seignorage charges on FA @

0.09

864.50

77.81

1.20
material

77.00

92.40

Rs:

0.00

material

Total cost of Materials

Rs:

0.00

Rs:

2866.75

B. MACHINERY:
Sl No

Hire Charges of
Plant &
MachinaryP.No. 130 &
131

Description

Unit

Concrete mixer
10/7cft(0.2/0.8cum)capacity
Fuel / Energy charges
Needle vibrator 60 mm dia ( petrol )
Fuel / Energy charges

Hour
Hour
Hour
Hour

Quantity

0.00
0.00
0.00
0.00

Rate

Amount

in Rs.

in Rs.

44.80
61.90
6.20
18.60

0.00
0.00
0.00
0.00

Rs:

0.00

Total hire charges of Machinery


C. LABOUR:
Sl No
1
2

Description

Unit

Mason Class-I
mazdoor( unskilled)

Day
Day

Quantity
0.10
2.36

Rate

Amount

in Rs.
285.00
215.00

in Rs.
28.50
507.40

Rs:

535.90
133.98
669.88

Total cost of Labour

Add 25% over area allowance


Total cost of Labour

Rs:

ABSTRACT:
A. Cost of Materials including seignorage charges

Rs:

B. Hire charges of Machinery

Rs:

0.00

C. Cost of Labour

Rs:

669.88

Total
D. Add for contractor's profit and overheads
Rs:
on (A+B+C)

Rs:

3536.63

Total cost for

1.00 cum

Rate percum

(A+B+C+D) /1

2866.75

495.13

Rs:

4031.75

Rs.

4031.75

laying Cement concrete ( 1: 4 : 8) using 40mm nominal size graded HBG metal
including cost of all materials and labour charges etc. complete

20

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

UNIT :

1.00 cum

Particulars
Cement for mix
Coarse aggregate 40 mm
Fine aggregate
Water (including curing)

Unit

Add seignorage charges on CA @

kg
cum
cum
kl
(Included
rate)

Add seignorage charges on FA @

(Included
rate)

Quantity
162.00
0.90
0.45
1.20
in material
Rs.
in material
Rs.

Rate
in Rs.
5.40
789.50
949.90
77.00

Amount
in Rs.
874.80
710.55
427.46
92.40

Rs:

0.00

Total cost of Materials

Rs:

0.00

Rs:

2105.21

B. MACHINERY:
Sl No

Hire Charges of
Plant &
MachinaryP.No. 130 &
131

general data

1
2

Description

Unit

Concrete mixer
10/7cft(0.2/0.8cum)capacity
Hour
Fuel
/ Energy
Hour
Needle
vibratorcharges
60 mm dia ( petrol
)
Hour
Fuel / Energy charges
Hour
Total hire charges of Machinery

Quantity

1.00
1.00
1.00
1.00

Rate
in Rs.
44.80
61.90
6.20
18.60
Rs:

Amount
in Rs.
44.80
61.90
6.20
18.60
131.50

41 of 110

Godavari pipe line project

C. LABOUR:
Sl No

Hire Charges of
Plant &
MachinaryP.No. 130 &
131

Description

Unit

Quantity

1
2
3

Crew for Concrete mixer


Crew for Needle vibrator
Mason Class-I

Hour
Hour
Day

1.00
1.00
0.10

mazdoor( unskilled)
Day
Total cost of Labour

1.39

Rate
in Rs.
141.70
102.00
285.00

Amount
in Rs.
141.70
102.00
28.50

215.00
Rs:

298.85
571.05
142.76
713.81

Add 25% over area allowance


Total cost of Labour
ABSTRACT:
A. Cost of Materials including seignorage charges
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and
Rs:
overheads on (A+B+C)
Total cost for
1.00 cum
Rs:
Rate per
cum
(A+B+C+D)
Rs.

21

Rs:
Rs:
Rs:
Rs:
Rs:

2105.21
131.50
713.81
2950.52
413.07
3363.59
3363.59

Supply and delivery of Steel Reinforcement H.Y.S.D.confirming to I.S.S. including cost &
conveyance of all materials , cost of binding wire and its fabrication charges, placing in
position tying grills etc., complete.
RATE ANALYSIS
A. MATERIALS:
Sl No
Particulars
1

UNIT :

1.00 MT
Unit

Quantity

Rate

Amount

in Rs.

in Rs.

HYSD bars including 5% for overlaps&wastage


MT

1.05

42000.00

44100.00

Binding wire

6.00

55.00
Rs:

330.00
44430.00

kg
Total cost of Materials

B. MACHINERY:
Sl No

Description

Unit

Quantity

Rate

Amount

in Rs.
NIL

NIL
C. LABOUR:
Sl No

Rs:

Description

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Black smith or barbender

Day

2.000

285.00

570.00

Mazdoor

Day

6.400

215.00
Rs:

1376.00
1946.00
486.50
2432.50

Total cost of Labour

Add 25% over area allowance


Total cost of Labour
ABSTRACT:
A. Cost of Materials including seignorage charges
B. Hire charges of Machinery
C. Cost of Labour
Total
Add 1% for SUNDIRES
Total
D. Add for contractor's profit and overheads on (A+B+C)
Rs:
Total cost for
Rate per1 MT

general data

in Rs.
0.00
0.00

1.00 MT
(A+B+C+D) /1

Rs:
Rs.
Rs.

Rs:
Rs:
Rs:
Rs:
Rs:
Rs:
Rs:

44430.00
0.00
2432.50
46862.50
468.63
47331.13
6626.36
53488.86
53488.86
53.49
per kg

42 of 110

Godavari pipe line project

22 Manufacture and supply of RCC Socket and spigot pipes confirming to B.I.S 458/2003of NP3/NP2
class of following diameters including cost of all materials, all taxes and duties and transportation to
site and lowering carefully in to the trenches, laying them true to alignment and gradient, jointing with
rubber rings including cost of jointing materials, cost and conveyance of all materials, labour
charges, tools and plants for laying, jointing as per specification drawing and as directed by
departmental officers and all other incidental and operational charges etc., complete for finished
item of work.
Present cost of cement C1 =

5500.00

Present cost of steel S1 = 39000per MT

Revised cost of cement C2 =

5400.00

Revised cost of steel S2 = 42000per MT

For RCC Pipes - NP-3


class

450mm dia 500mm dia 600mm dia

Initial Cost as per SSR


Thickness of pipe as per
IS: 458/2003

150mm dia NP2

2156.00

3209.00

4222.00

399.00

75.00

75.00

85.00

95.00

25.00

4.57

5.60

8.19

15.70

0.76

Weight of cement (Wc)

89.02

97.50

131.64

192.22

9.89

R1 = (S2-S1)/1000 x Ws

13.71

16.8

24.57

47.1

2.28

R2 = (C2-C1)/1000 x Wc

-8.90

-9.75

-13.16

-19.22

-0.99

1980.81

2163.05

3220.41

4249.88

400.29

159.20
2140.01

168.40
2331.45

238.30
3458.71

426.40
4676.28

14.00
414.29

79.23
2219.24

86.52
2417.97

128.82
3587.52

170.00
4846.27

16.01
430.30

166.66
2385.90

183.93
2601.91

225.13
3812.66

225.13
5071.41

72.68
502.98

Weight of steel (Ws)

Revised cost
Conveyance Charges as
per SSR item No 7.1
Page No 60 for 50Km
Add VAT 4% under ST
on Basic Cost

lowering, laying and


Jointing of RCC pipes
(As per SSR)
Total Per Rm
23

800mm dia

1976.00

V R.C.C. M20 Grade using 20 mm HBG Down graded metal including centring charges,
laying , levelling , machine mixing but exculding cost of steel in reinforcement, etc
complete as per SS ANCHOR BLOCKS, THRUST BLOCKS AND PEDESTALS

RATE ANALYSIS

UNIT :

1.00 cum

A. MATERIALS:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.
kg

Cement for mix

Coarse aggregate 20 mm

cum

0.90

Fine aggregate

cum

0.45

949.90

427.46

Water (including curing)

1.20
material

77.00

92.40

Rs:

0.00

Add seignorage charges on CA @


Add seignorage charges on FA @

400.00

in Rs.

kl
(Included in
rate)
Rs.
(Included in
rate)
Rs.

5.40
#REF!

2160.00
#REF!

material
Rs:

Total cost of Materials

Rs:

0.00
#REF!

B. MACHINERY:
Sl No
1
Hire Charges of
Plant &
MachinaryP.No. 130 &
131

general data

Description

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Concrete mixer 10/7cft(0.2/0.8cum)capacity


Hour

1.00

44.80

44.80

Fuel / Energy charges

Hour

1.00

61.90

61.90

Needle vibrator 60 mm dia ( petrol )

Hour

1.00

6.20

6.20

Fuel / Energy charges

Hour

1.00

18.60

18.60

43 of 110

Godavari pipe line project

Pg.No75 of
PHSSR

Centering charges

Cum

1.00

539.00

539.00

Rs:

670.50

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Crew for Concrete mixer

Hour

1.000

141.70

141.70

Crew for Needle vibrator

Hour

1.000

102.00

102.00

Mason Class-I

Day

0.133

285.00

37.91

Mason Class-II

Day

0.267

260.00

69.42

mazdoor( unskilled)

Day

3.600

215.00

774.00

Rs:

1125.03
281.26
1406.28

Total cost of Labour

Add 25% over area allowance


Total cost of Labour

Rs:

ABSTRACT:
A. Cost of Materials including seignorage charges

Rs:

B. Hire charges of Machinery

Rs:

670.50

C. Cost of Labour

Rs:

1406.28

Total
D. Add for contractor's profit and overheads
on (A+B+C)
Rs:

Rs:

Total cost for

1.00 cum

Rate percum
24

(A+B+C+D)

#REF!

#REF!
#REF!

Rs:

#REF!

Rs.

#REF!

V R.C.C. M30 Grade using 20 mm HBG Down graded metal including centring charges,
laying , levelling , machine mixing but exculding cost of steel in reinforcement, etc
complete as per SS up to 150mm thick Slab
RATE ANALYSIS

UNIT :

1.00 cum

A. MATERIALS:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.
kg

Cement for mix

Coarse aggregate 20 mm

cum

0.90

Fine aggregate

cum

0.45

949.90

427.46

Water (including curing)

1.20
material

77.00

92.40

Rs:

0.00

Add seignorage charges on CA @


Add seignorage charges on FA @

441.00

in Rs.

kl
(Included in
rate)
Rs.
(Included in
rate)
Rs.

5.40
#REF!

2381.40
#REF!

material
Rs:

Total cost of Materials

Rs:

0.00
#REF!

B. MACHINERY:
Sl No

Hire Charges of
Plant &
MachinaryP.No. 130 &
131
Pg.No75 of
PHSSR

1
2

Description

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Concrete mixer
10/7cft(0.2/0.8cum)capacity

Hour

0.267

44.80

11.96

Fuel / Energy charges

Hour

0.267

61.90

16.53

Needle vibrator 60 mm dia ( petrol )

Hour

0.267

6.20

1.66

Fuel / Energy charges

Hour

0.267

18.60

4.97

Centering charges

cum

6.670

201.00

1340.67

Rs:

1375.78

Total hire charges of Machinery


C. LABOUR:
Sl No

general data

Description

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Crew for Concrete mixer

Hour

1.000

141.70

141.70

Crew for Needle vibrator

Hour

1.000

102.00

102.00

44 of 110

Godavari pipe line project

Mason Class-I

Day

0.067

285.00

Mason Class-II

Day

0.133

260.00

34.58

mazdoor( unskilled)

Day

2.500

215.00

537.50

Rs:

834.88
208.72
1043.59

Total cost of Labour

Add 25% over basic rate on labour component for muncipal area
Total cost of Labour

Rs:

19.10

ABSTRACT:
A. Cost of Materials including seignorage charges

Rs:

B. Hire charges of Machinery

Rs:

C. Cost of Labour

Rs:
Total

#REF!
1375.78
1043.59

Rs:

#REF!

D. Add for contractor's profit and overheads on (A+B+C)


Rs:
Total cost for

1.00 cum

Rate percum
25

(A+B+C+D)

#REF!

Rs:

#REF!

Rs.

#REF!

V R.C.C. M30 Grade using 20 mm HBG Down graded metal including centring charges,
laying , levelling , machine mixing but exculding cost of steel in reinforcement, etc
complete as per SS for Side walls of valve chamber
RATE ANALYSIS

UNIT :

1.00 cum

A. MATERIALS:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.
kg

Cement for mix

Coarse aggregate 20 mm

cum

0.90

Fine aggregate

cum

0.45

949.90

427.46

Water (including curing)

1.20
material

77.00

92.40

Rs:

0.00

Add seignorage charges on CA @


Add seignorage charges on FA @

441.00

in Rs.

kl
(Included in
rate)
Rs.
(Included in
rate)
Rs.

5.40
#REF!

2381.40
#REF!

material
Rs:

Total cost of Materials

Rs:

0.00
#REF!

B. MACHINERY:
Sl No

Hire Charges of
Plant &
MachinaryP.No. 130 &
131
Pg.No 45 of
PHSSR

1
2

Description

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Concrete mixer
10/7cft(0.2/0.8cum)capacity

Hour

0.267

44.80

11.96

Fuel / Energy charges

Hour

0.267

61.90

16.53

Needle vibrator 60 mm dia ( petrol )

Hour

0.267

6.20

1.66

Fuel / Energy charges

Hour

0.267

18.60

4.97

Centering charges

cum

3.330

1302.00

4335.66

Rs:

4370.77

Total hire charges of Machinery


C. LABOUR:
Sl No

Description

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Crew for Concrete mixer

Hour

1.000

141.70

141.70

Crew for Needle vibrator

Hour

1.000

102.00

102.00

Mason Class-I

Day

0.067

285.00

19.10

Mason Class-II

Day

0.133

260.00

34.58

mazdoor( unskilled)

Day

2.500

215.00

537.50

Rs:

834.88
208.72
1043.59

Total cost of Labour

Add 25% over basic rate on labour component for muncipal area
Total cost of Labour

Rs:

ABSTRACT:

general data

A. Cost of Materials including seignorage charges

Rs:

B. Hire charges of Machinery

Rs:

#REF!
4370.77

C. Cost of Labour

Rs:

1043.59

45 of 110

Godavari pipe line project

Total

Rs:

D. Add for contractor's profit and overheads on (A+B+C)


Rs:
Total cost for
Rate percum

26

Pg.No 121 of
PHSSR

27

Pg.No 121 of
PHSSR

28

(A+B+C+D)

#REF!

Rs.

#REF!

Supply and delievery of Nut,Bolts with Double washer including cost and
conveyance etc.., complete

SI No

Rate Per Kg

Total including
overheads &
contractor
profit @ 14%

1
a

2
93.00

5
106.02

Supply and delivery of rubber packing including cost and conveyance etc..,
complete

SI No

Thickness

Rate Per Kg

Total including
overheads &
contractor
profit @ 14%

1
b

2
6 mm thick

3
77.00

5
87.78

Basic
Rate

16.00

1 sqm

16.00
16.00

Laying VCC in M 30 Grade design mix using 20mm SS-5 HBG m/c metal , coarse and fine
aggregates conforming to IS: 383, and OPC (cement content between 350 to 425 kg/cum as per
IRC mix design for Fair degree of quality control), subject to recovery of difference in cost of
cement if cement content as per mix design is less than 400 kg/cum of concrete, including cost
and conveyance of all materials, machinery, all labour charges (including placing in position
expansion, contraction, construction, longitudinal joints and corner reinforcement if any but
excluding cost of joint filler, sealant and reinforcement and its fabrication ), centering,
vibration, curing for 21 days and all incidental & operational charges etc. complete conforming
to standard specification for CC Pavement more than 2m wide - 1 Cum

RATE ANALYSIS
A. MATERIALS:
Sl No
1
2
3
4

UNIT :
Particulars

Cement at 400 Kgs/cum


Coarse aggregate 25mm @
.0.60cum/cum
Coarse aggregate 12.5mm at
0.30cum/cum
Fine aggregate at 0.45cum/cum

1050.00 cum
Unit

Quantity

tonnes

414.00

Rate
in Rs.
5400.00

Amount
in Rs.
2235600.00

cum

630.00

1219.50

768285.00

cum
cum

315.00
473.00

1024.50
949.90

322717.50
449302.70

tonnes

9.45

0.00

0.00

tonnes

1.17

0.00

0.00

32mm mild steel dowel bars of


grade S-240
16mm dia deformed steel tie bars
of grade S-415

Separation membrane of
impermiable plastic sheeting 125
micron thick

sqm

3675.00

16.00

58800.00

Premoulded joint filler 25mm thick


for expansion joint
Joint sealent
Sealentsheet
primer
Plastic
1.25mm thick for
dowel bars
Curing compound

sqm
kgs
kgs
sqm
lts

16.33
875.00
116.67
46.67
1850.00

915.00
80.00
25.00
20.00
105.00

14941.95
70000.00
2916.75
933.40
194250.00

8
9
10
11
12

general data

#REF!

Rs:

Supply and placing separation membrane of impermeable plastic sheeting 125 micron thick under
pavement slab including cost and conveyance etc. complete - 1 sq.m.
sqm

29

1.00 cum

#REF!

Sl.no.828,pg
68, BMTU.03
Hire
as
perfor
local
market
as per local
market
Sl.no.15,pg
12, Irrigation

46 of 110

Godavari pipe line project

13
14

Super plastisizer admixur IS


marked as per 9103-1999 @ 0.5%
by weight of cement
Cost of water
Add seignorage charges on CA @
Add seignorage charges on FA @

kgs
kl
(Included
rate)
(Included
rate)

Sl.No70, Pg
.no13 of
111780.00 Irrigation
16632.00 works

2070.00
216.00
in material

54.00
77.00

Rs.
in material
Rs.

Rs:

0.00

Rs:

0.00

Total cost of Materials, Rs.

4246159.30

Add 1% of material cost for cost of miscellaneous materials like


tarpalin,Hessian cloth, metal cloth, cotton or compressible sponze and cradle
for dowel bars work bridges for men to approach concrete surface without
walking over it, cutting blades and bit

42461.59

B. MACHINERY:
Sl No

Description
Road sweeper at 1250 sqm per
hour

3
4

Front end loader 1cum bucket


capacity
Cement concrete batch mix plant
@ 175 cum/hr
Electric generator 250 KVA

5
6

Slip form paver with electronic


sensor
Water Tanker 6 Kl Capacity

7
8
9
10

Unit

Quantity

Rate
in Rs.

Amount
in Rs.

Hour

2.80

2000.00

5600.00

Hour

18.00

2000.00

36000.00

Hour
Hour

6.00
6.00

770.40
2500.00

4622.40 130 for Hire


15000.00

Hour
Hour

6.00
36.00

560.00
417.83

3360.00 325 for Hire


for
15041.70 Charges
Sl.no.64,pg

6.00
12.00
12.00

1467.20
400.00
146.00
Rs:

8803.20 325 for Hire


4800.00 Charges for
1752.00
94979.30

Sl.no.11,pg

Sl.no.20,pg

326 for Hire


Sl.no.1,pg

Transit truck agitator 5 cum


capacity

Hour
Concrete joint cutting machine
Hour
Texuring machine
Hour
Total hire charges of Machinery

C. LABOUR:
Sl No
1
2

Description

Unit

Quantity

Mazdoor( skilled)
Day
mazdoor( unskilled)
Day
Total cost of Labour

15.00
37.00

Rate
in Rs.
260.00
215.00
Rs:

Add 25% over area allowance


Total cost of Labour
ABSTRACT:
A. Cost of Materials including seignorage charges
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and
overheads on (A+B+C)
Rs:
Total cost for
1050.00 cum
Rs:
Rate per
cum
(A+B+C+D)/1050
Rs.

Rs:
Rs:
Rs:
Rs:
Rs:

Amount
in Rs.
3900.00
7955.00
11855.00
2963.75
14818.75

4246159.30
94979.30
14818.75
4355957.35
609834.03
4965791.38
4729.33

Manufacture as per BIS: 12592(part- 1&2), Supply & and delivery of Manhole Covers and frames with ISI marking
any where in A.P., F.O.R destination including, loading, unloading & stacking at site including Central Excise Duty,
Sales Tax, Octroi and other Govt levies etc, as applicabe - For Cover Slabs of Valve Chamber
H.D. -35 with 560mm dia clear opening
Rate as per SSR 2010-2011
Central Excise Duty @8.24%
CST @ 4%
VAT @4%

Each

Total

general data

2012.00
165.79
80.48
80.48
2338.75

47 of 110

Godavari pipe line project

25

Uprooting of CI pipes by melting lead, loosening the joints, seperating the pipes, hoisting
and keeping with in a lead of 10 m but exploding earthwork excavation and refilling

80 mm diameter

UNIT :

40.26 Rm

A. Labour:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Assistant fitter (Plumber 2nd class)

day

0.50

260.00

Man mazdoor

day

4.00

215.00

860.00

Rs:

990.00

B. MATERIAL:
Sl No

For breaking lead coulked joints, melting lead etc;


Description

Fuel wood

Kerosene oil

130.00

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

0.373

450.00

litre

0.379

25.00

167.85
9.48

Rs:

177.33

ABSTRACT:
A. Cost of labour

Rs:

B. Cost of material

Rs:

990.00
177.33

C. Cost of (A+B)

Rs:

1167.33

D. Add for contractor's profit and overheads


on (A+B)
Rs:
E. Total cost for
Rate per each Rm

163.43

40.26 Rm

Rs:

1330.75

E/40.26

Rs.

33.05

100 mm diameter

UNIT :

40.26 Rm

A. Labour:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Assistant fitter (Plumber 2nd class)

day

0.63

260.00

Man mazdoor

day

4.50

215.00

967.50

Rs:

1131.30

B. MATERIAL:
Sl No

For breaking lead coulked joints, melting lead etc;


Description

Fuel wood

Kerosene oil

163.80

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

0.466

450.00

litre

0.379

25.00

209.70
9.48

Rs:

219.18

ABSTRACT:
A. Cost of labour

Rs:

B. Cost of material

Rs:

219.18

C. Cost of (A+B)

Rs:

1350.48

D. Add for contractor's profit and overheads


on (A+B)
Rs:
E. Total cost for
Rate per each Rm
125 mm diameter

general data

1131.30

189.07

40.26 Rm

Rs:

1539.54

E/40.26

Rs.

38.24

UNIT :

40.26 Rm

48 of 110

Godavari pipe line project

A. Labour:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Assistant fitter (Plumber 2nd class)

day

0.76

260.00

197.60

Man mazdoor

day

5.00

215.00

1075.00

Rs:

1272.60

B. MATERIAL:
Sl No

For breaking lead coulked joints, melting lead etc;


Description

Fuel wood

Kerosene oil

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

0.559

450.00

litre

0.562

25.00

251.55
14.05

Rs:

265.60

ABSTRACT:
A. Cost of labour

Rs:

B. Cost of material

Rs:

1272.60
265.60

C. Cost of (A+B)

Rs:

1538.20

D. Add for contractor's profit and overheads


on (A+B)
Rs:
E. Total cost for
Rate per each Rm

215.35

40.26 Rm

Rs:

1753.55

E/40.26

Rs.

43.56

150 mm diameter

UNIT :

40.26 Rm

A. Labour:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Assistant fitter (Plumber 2nd class)

day

0.83

260.00

215.80

Man mazdoor

day

5.50

215.00

1182.50

Rs:

1398.30

B. MATERIAL:
Sl No

For breaking lead coulked joints, melting lead etc;


Description

Fuel wood

Kerosene oil

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

0.663

450.00

litre

0.568

25.00

298.35
14.20

Rs:

312.55

ABSTRACT:
A. Cost of labour

Rs:

B. Cost of material

Rs:

1398.30
312.55

C. Cost of (A+B)

Rs:

1710.85

D. Add for contractor's profit and overheads


on (A+B)
Rs:
E. Total cost for
Rate per each Rm

239.52

40.26 Rm

Rs:

1950.37

E/40.26

Rs.

48.44

200 mm diameter

UNIT :

40.26 Rm

A. Labour:
Sl No

Particulars

Quantity

Rate

Amount

in Rs.

in Rs.

Assistant fitter (Plumber 2nd class)

day

1.10

260.00

286.00

Man mazdoor

day

6.50

215.00

1397.50

Rs:

1683.50

B. MATERIAL:

general data

Unit

For breaking lead coulked joints, melting lead etc;

49 of 110

Godavari pipe line project

Sl No

Description

Fuel wood

Kerosene oil

Unit

Quantity

0.84

litre

0.757

Rate

Amount

in Rs.

in Rs.

450.00

378.00

25.00

18.93

Rs:

396.93

ABSTRACT:
A. Cost of labour

Rs:

B. Cost of material

Rs:

1683.50
396.93

C. Cost of (A+B)

Rs:

2080.43

D. Add for contractor's profit and overheads


on (A+B)
Rs:
E. Total cost for
Rate per each Rm

291.26

40.26 Rm

Rs:

2371.68

E/40.26

Rs.

58.91

250 mm diameter

UNIT :

40.26 Rm

A. Labour:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Assistant fitter (Plumber 2nd class)

day

1.30

260.00

338.00

Man mazdoor

day

7.50

215.00

1612.50

Rs:

1950.50

B. MATERIAL:
Sl No

For breaking lead coulked joints, melting lead etc;


Description

Fuel wood

Kerosene oil

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

1.026

450.00

litre

1.137

25.00

461.70
28.43

Rs:

490.13

ABSTRACT:
A. Cost of labour

Rs:

B. Cost of material

Rs:

1950.50
490.13

C. Cost of (A+B)

Rs:

2440.63

D. Add for contractor's profit and overheads


on (A+B)
Rs:
E. Total cost for
Rate per each Rm

341.69

40.26 Rm

Rs:

2782.31

E/40.26

Rs.

69.11

300 mm diameter

UNIT :

40.26 Rm

A. Labour:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Assistant fitter (Plumber 2nd class)

day

1.50

260.00

390.00

Man mazdoor

day

8.50

215.00

1827.50

Rs:

2217.50

B. MATERIAL:
Sl No

For breaking lead coulked joints, melting lead etc;


Description

Fuel wood

Kerosene oil

Unit

Quantity

1.12

litre

1.515

Rate

Amount

in Rs.

in Rs.

450.00

504.00

25.00

37.88

Rs:

541.88

ABSTRACT:
A. Cost of labour

general data

Rs:

2217.50

50 of 110

Godavari pipe line project

B. Cost of material

Rs:

541.88

C. Cost of (A+B)

Rs:

2759.38

D. Add for contractor's profit and overheads


on (A+B)
Rs:
E. Total cost for
Rate per each Rm

386.31

40.26 Rm

Rs:

3145.69

E/40.26

Rs.

78.13

350 mm diameter

UNIT :

40.26 Rm

A. Labour:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Assistant fitter (Plumber 2nd class)

day

1.75

260.00

455.00

Man mazdoor

day

9.50

215.00

2042.50

Rs:

2497.50

B. MATERIAL:
Sl No

For breaking lead coulked joints, melting lead etc;


Description

Fuel wood

Kerosene oil

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

1.231

450.00

litre

1.515

25.00

553.95
37.88

Rs:

591.83

ABSTRACT:
A. Cost of labour

Rs:

B. Cost of material

Rs:

2497.50
591.83

C. Cost of (A+B)

Rs:

3089.33

D. Add for contractor's profit and overheads


on (A+B)
Rs:
E. Total cost for
Rate per each Rm

432.51

40.26 Rm

Rs:

3521.83

E/40.26

Rs.

87.48

400 mm diameter

UNIT :

40.26 Rm

A. Labour:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Assistant fitter (Plumber 2nd class)

day

2.00

260.00

520.00

Man mazdoor

day

10.50

215.00

2257.50

Rs:

2777.50

B. MATERIAL:
Sl No

For breaking lead coulked joints, melting lead etc;


Description

Fuel wood

Kerosene oil

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

1.306

450.00

litre

1.894

25.00

587.70
47.35

Rs:

635.05

ABSTRACT:
A. Cost of labour

Rs:

B. Cost of material

Rs:

635.05

C. Cost of (A+B)

Rs:

3412.55

D. Add for contractor's profit and overheads


on (A+B)
Rs:
E. Total cost for
Rate per each Rm
450 mm diameter

general data

2777.50

477.76

40.26 Rm

Rs:

3890.31

E/40.26

Rs.

96.63

UNIT :

40.26 Rm

51 of 110

Godavari pipe line project

A. Labour:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Assistant fitter (Plumber 2nd class)

day

2.25

260.00

585.00

Man mazdoor

day

11.50

215.00

2472.50

Rs:

3057.50

B. MATERIAL:
Sl No

For breaking lead coulked joints, melting lead etc;


Description

Fuel wood

Kerosene oil

Unit

Quantity

1.4

litre

2.273

Rate

Amount

in Rs.

in Rs.

450.00

630.00

25.00

56.83

Rs:

686.83

ABSTRACT:
A. Cost of labour

Rs:

B. Cost of material

Rs:

3057.50
686.83

C. Cost of (A+B)

Rs:

3744.33

D. Add for contractor's profit and overheads


on (A+B)
Rs:
E. Total cost for
Rate per each Rm

524.21

40.26 Rm

Rs:

4268.53

E/40.26

Rs.

106.02

500 mm diameter

UNIT :

40.26 Rm

A. Labour:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Assistant fitter (Plumber 2nd class)

day

2.50

260.00

650.00

Man mazdoor

day

12.50

215.00

2687.50

Rs:

3337.50

B. MATERIAL:
Sl No

For breaking lead coulked joints, melting lead etc;


Description

Fuel wood

Kerosene oil

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

1.492

450.00

litre

2.652

25.00

671.40
66.30

Rs:

737.70

ABSTRACT:
A. Cost of labour

Rs:

B. Cost of material

Rs:

3337.50
737.70

C. Cost of (A+B)

Rs:

4075.20

D. Add for contractor's profit and overheads


on (A+B)
Rs:
E. Total cost for
Rate per each Rm

570.53

40.26 Rm

Rs:

4645.73

E/40.26

Rs.

115.39

600 mm diameter

UNIT :

40.26 Rm

A. Labour:
Sl No

general data

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Assistant fitter (Plumber 2nd class)

day

3.00

260.00

780.00

Man mazdoor

day

14.50

215.00

3117.50

Rs:

3897.50

52 of 110

Godavari pipe line project

B. MATERIAL:
Sl No

For breaking lead coulked joints, melting lead etc;


Description

Fuel wood

Kerosene oil

Unit

Quantity

1.58

litre

3.410

Rate

Amount

in Rs.

in Rs.

450.00

711.00

25.00

85.25

Rs:

796.25

ABSTRACT:
A. Cost of labour

Rs:

B. Cost of material

Rs:

3897.50
796.25

C. Cost of (A+B)

Rs:

4693.75

D. Add for contractor's profit and overheads


on (A+B)
Rs:
E. Total cost for
Rate per each Rm

25

657.13

40.26 Rm

Rs:

5350.88

E/40.26

Rs.

132.91

Uprooting of RCC pipes including breaking the collars, loosing the joint, scrapping the
pipe, hoisting and keeping with in a lead of 10 m but excluding earthwork excavation and
refilling
100 mm diameter

UNIT :

10.00 Rm

A. Labour:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Fitter 2nd class

day

0.10

260.00

26.00

Man mazdoor

day

0.40

215.00

86.00

Woman mazdoor

day

0.45

215.00

96.75

Rs:

208.75

ABSTRACT:
A. Cost of labour

Rs:

208.75

B. Add for contractor's profit and overheads


on (A)
Rs:
C. Total cost for

10.00 Rm

Rate per each Rm

C/10

150 mm diameter

29.23

Rs:

237.98

Rs.

23.80

UNIT :

10.00 Rm

A. Labour:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Fitter 2nd class

day

0.10

260.00

26.00

Man mazdoor

day

0.49

215.00

105.35

Woman mazdoor

day

0.56

215.00

120.40

Rs:

251.75

ABSTRACT:
A. Cost of labour

Rs:

B. Add for contractor's profit and overheads


on (A)
Rs:
C. Total cost for
Rate per each Rm
225 mm diameter

10.00 Rm
C/10
UNIT :

251.75

35.25

Rs:

287.00

Rs.

28.70
10.00 Rm

A. Labour:

general data

53 of 110

Godavari pipe line project

Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Fitter 2nd class

day

0.10

260.00

26.00

Man mazdoor

day

0.49

215.00

105.35

Woman mazdoor

day

0.67

215.00

144.05

Rs:

275.40

ABSTRACT:
A. Cost of labour

Rs:

275.40

B. Add for contractor's profit and overheads


on (A)
Rs:
C. Total cost for

10.00 Rm

Rate per each Rm

C/10

300 mm diameter

38.56

Rs:

313.96

Rs.

31.40

UNIT :

10.00 Rm

A. Labour:
Sl No

Particulars

Unit

Quantity

Rate

Amount

in Rs.

in Rs.

Fitter 2nd class

day

0.10

260.00

26.00

Man mazdoor

day

0.49

215.00

105.35

Woman mazdoor

day

0.79

215.00

169.85

Rs:

301.20

ABSTRACT:
A. Cost of labour

Rs:

B. Add for contractor's profit and overheads


on (A)
Rs:
C. Total cost for
Rate per each Rm

general data

10.00 Rm
C/10

301.20

42.17

Rs:

343.37

Rs.

34.34

54 of 110

HDPE Rates - Grade PE 80 for Water Supply Distribution System

Manufacture, supply, & delivery of HDPE pipes conforming to IS 4984 - 1995 including transportation to any where in A
duty, sales tax and specials etc, complete. (Supply upto 90mm dia in coil and above 90mm dia straight length in 6m), in
duty, sales tax and specials etc etc, complete for (PE - 80 Grade)
Old resin
rate

New resin
rate

71400

71400

Class

OD

Max thick

Min.thick

Avg thick

ID

Wt kg/mt

Pipe Rate
as per SSR

Revised
Pipe Rate

4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4

63
75
90
110
125
140
160
180
200
225
250
280
315
355
400
450
500
560

3
3.4
4.1
5
5.6
6.2
7.1
7.9
8.7
9.8
25.2
28.2
31.7
35.7
42.2
47.3
52.5
58.8

2.5
2.9
3.5
4.3
4.9
5.4
6.2
7
7.7
9.8
10.9
12.1
13.7
15.3
18
20.3
22.4
25.1

2.75
3.15
3.8
4.65
5.25
5.8
6.65
7.45
8.2
8.7
9.7
10.8
12.2
13.7
15.4
17.4
19.3
21.6

57.5
68.7
82.4
100.7
114.5
128.4
146.7
165.1
183.6
207.6
230.6
258.4
290.6
327.6
369.2
415.2
461.4
516.8

0.491
0.671
0.971
1.452
1.863
2.307
3.023
3.810
4.662
5.578
6.909
8.617
10.949
13.859
17.555
22.310
27.498
34.469

60.00
83.00
119.00
177.00
229.00
282.00
369.00
466.00
571.00
747.00
924.00
1152.00
1464.00
1765.00
2287.00
2905.00
3571.00
4404.00

60.00
83.00
119.00
177.00
229.00
282.00
369.00
466.00
571.00
747.00
924.00
1152.00
1464.00
1765.00
2287.00
2905.00
3571.00
4404.00

Manufacture, supply, & delivery of HDPE fittings conforming to IS 4984 - 1995 including transportation to anywhere in
duty, sales tax and specials etc., complete

Diameter

63
75
90
110
125
140
160
180
200
225
250
280

Pipe Ends Long Neck


Basic
Excise
Sales Tax
Rate
Duty
@ 4%
16.48%
63
10.38
2.94
75
12.36
3.49
98
16.15
4.57
135
22.25
6.29
242
39.88
11.28
245
40.38
11.42
341
56.20
15.89
484
79.76
22.55
623
102.67
29.03
714
117.67
33.27
836
137.77
38.95
935
154.09
43.56
HDPE End Caps

MS Flanges
Total

76.32
90.85
118.72
163.54
293.16
296.79
413.08
586.31
754.70
864.93
1012.72
1132.65

Diameter

63
75
90
110
125
140
160
180
200
225
250
280

Basic Rate

125
157
168
178
244
264
347
490
635
793
937
1063
HDPE Reducers

Diameter

63
75
90
110
125
140
160
180
200
225
250
280

Diameter

63
75
90
110
125
140
160
180
200
225
250
280

Basic
Rate
40
51
67
77
106
124
189
307
335
350
497
508

Basic
Rate
102
124
217
257
387
534
919
1247
1717
2437
3336
4671

Excise
Duty
16.48%
6.59
8.40
11.04
12.69
17.47
20.44
31.15
50.59
55.21
57.68
81.91
83.72

Sales Tax
@ 4%

Total

Specification

1.86
2.38
3.12
3.59
4.94
5.78
8.81
14.30
15.61
16.31
23.16
23.67

48.46
61.78
81.16
93.28
128.41
150.21
228.95
371.90
405.82
423.99
602.06
615.39

50mm x 63mm
63mm x 75mm
75mm x 90mm
90mm x 110mm
110mm x 125mm
125mm x 140mm
140mm x 160mm
160mm x 180mm
180mm x 200mm
200mm x 225mm
225mm x 250mm
250mm x 280mm

HDPE Tees
Excise
Sales Tax
Duty
@ 4%
16.48%
16.81
4.75
20.44
5.78
35.76
10.11
42.35
11.97
63.78
18.03
88.00
24.88
151.45
42.82
205.51
58.10
282.96
80.00
401.62
113.54
549.77
155.43
769.78
217.63

Basic Rate

47
67
110
152
232
320
447
619
800
982
1339
1901

HDPE Bends
Total

123.56
150.21
262.87
311.33
468.81
646.88
1113.27
1510.61
2079.96
2952.16
4041.20
5658.41

Diameter

63
75
90
110
125
140
160
180
200
225
250
280

Basic Rate

90
116
200
264
389
512
764
1097
1487
2109
2891
4168

on System

sportation to any where in AP, including excise


dia straight length in 6m), including excise

Excise
Duty
16.48%
9.89
13.68
19.61
29.17
37.74
46.47
60.81
76.80
94.10
123.11
152.28
189.85
241.27
290.87
376.90
478.74
588.50
725.78

VAT @
4.00%
2.40
3.32
4.76
7.08
9.16
11.28
14.76
18.64
22.84
29.88
36.96
46.08
58.56
70.60
91.48
116.20
142.84
176.16

Total
72.29
100.00
143.37
213.25
275.90
339.75
444.57
561.44
687.94
899.99
1113.24
1387.93
1763.83
2126.47
2755.38
3499.94
4302.34
5305.94

nsportation to anywhere in AP, including excise

MS Flanges
Excise
Sales Tax
Duty
@ 4%
16.48%
20.60
5.82
25.87
7.31
27.69
7.83
29.33
8.29
40.21
11.37
43.51
12.30
57.19
16.17
80.75
22.83
104.65
29.59
130.69
36.95
154.42
43.66
175.18
49.53
HDPE Reducers

Total

151.42
190.19
203.51
215.63
295.58
319.81
420.35
593.58
769.23
960.63
1135.07
1287.71

Excise
Duty
16.48%
7.75
11.04
18.13
25.05
38.23
52.74
73.67
102.01
131.84
161.83
220.67
313.28

Sales Tax
@ 4%

Total

2.19
3.12
5.13
7.08
10.81
14.91
20.83
28.84
37.27
45.75
62.39
88.57

56.94
81.16
133.25
184.13
281.04
387.65
541.49
749.85
969.11
1189.59
1622.05
2302.86

HDPE Bends
Excise
Sales Tax
Duty
@ 4%
16.48%
14.83
4.19
19.12
5.40
32.96
9.32
43.51
12.30
64.11
18.12
84.38
23.86
125.91
35.60
180.79
51.11
245.06
69.28
347.56
98.26
476.44
134.70
686.89
194.20

Total

109.03
140.52
242.28
319.81
471.23
620.23
925.50
1328.90
1801.34
2554.83
3502.13
5049.08

PHE-LJHE -12

Laying and jointing of HDPE pipes by


butt fusion welding as per IS:7634-PartII/1975 as amended from time to time to
the alignment and gradient and testing
the pipe line to the required pressure

63 mm dia pipe

Length = 480

a)
(i) For lowering/
sub surface
transport
(ii)Jointing

(iii) Testing

Rates

Quantity

Labour
Mazdoor

day

215.00

4.000

Fitter

day

285.00

1.000

Man mazdoor

day

215.00

2.000

Fitter

day

285.00

1.000

Man mazdoor

day

215.00

2.000

Supervisor

day

215.00

1.000
Sub total (a)

b) Machinery
Hire charges of Generator Set &
Hydraulic Testing Equipement

day

5029.60

1.000
Sub total (a)

c) Material
Kerosene
Diesel
Water for Testing

Lt
Lt

Transport

day

25.00
45.00

4.000
8.000

100.00

1.000

Lt

Sub total (b)

(d) Total = a+b+c


MAA @ 25%
(g) Overheads & Contractors Profit
(h) Total Cost (d+e+g)
Rate per Rmt

63 mm dia pipe

90 mm dia pipe

Joints = 40 Length = 432

110 mm dia pipe

160 mm dia pipe

200 mm dia pipe

Joints = 36

Length = 384

Joints = 32

Length = 303

Joints = 25

Length = 240

Amount

Quantity

Amount

Quantity

Amount

Quantity

Amount

Quantity

860.00

5.000

1075.00

6.000

1290.00

7.000

1505.00

10.000

285.00

1.000

285.00

1.000

285.00

2.000

570.00

2.000

430.00

2.000

430.00

2.000

430.00

4.000

860.00

6.000

285.00

1.000

285.00

1.000

285.00

1.000

285.00

1.000

430.00

2.000

430.00

2.000

430.00

2.000

430.00

2.000

215.00

1.000

215.00

1.000

215.00

1.000

215.00

1.000

1575.00

5029.60
5029.60

Sub total (a)

1.000
Sub total (a)

1790.00

5029.60
5029.60

Sub total (a)

1.000
Sub total (a)

2005.00

5029.60
5029.60

Sub total (a)

1.000
Sub total (a)

2935.00

5029.60

Sub total (a)

1.000

5029.60

Sub total (a)

100.00
360.00

5.000
8.000

125.00
360.00

6.000
8.000

150.00
360.00

9.000
8.000

225.00
360.00

11.000
8.000

100.00

1.000

100.00

1.000

100.00

1.000

100.00

1.000

460.00

Sub total (b)

485.00

Sub total (b)

510.00

Sub total (b)

585.00

7064.60

7304.60

7544.60

8549.60

393.75
1044.17
8502.52

447.50
1085.29
8837.39

501.25
1126.42
9172.27

733.75
1299.67
10583.02

17.71

20.46

23.89

34.93

Sub total (b)

200 mm dia pipe

250 mm dia pipe

315 mm dia pipe

355 mm dia pipe

Joints = 20

Length = 216

Joints = 18

Length = 180

Joints = 15

Length = 144

Joints = 12

Amount

Quantity

Amount

Quantity

Amount

Quantity

Amount

2150.00

11.000

2365.00

12.000

2580.00

14.000

3010.00

570.00

2.000

570.00

2.000

570.00

2.000

570.00

1290.00

6.000

1290.00

6.000

1290.00

8.000

1720.00

285.00

1.000

285.00

1.000

285.00

1.000

285.00

430.00

2.000

430.00

2.000

430.00

2.000

430.00

215.00

1.000

215.00

1.000

215.00

1.000

215.00

4010.00

5029.60

Sub total (a)

1.000

4225.00

5029.60

Sub total (a)

1.000

4440.00

5029.60

Sub total (a)

1.000

5029.60

Sub total (a)

5029.60

Sub total (a)

5029.60

Sub total (a)

275.00
360.00

13.000
8.000

325.00
360.00

15.000
8.000

375.00
360.00

16.000
8.000

100.00

1.000

100.00

1.000

100.00

1.000

635.00

Sub total (b)

685.00

Sub total (b)

735.00

5300.00

Sub total (b)

0.00

400.00
360.00

760.00

9674.60

9939.60

10204.60

6060.00

1002.50
1494.79
12171.89

1056.25
1539.42
12535.27

1110.00
1584.04
12898.64

1325.00
1033.90
8418.90

50.72

58.03

71.66

58.46

APMDP - Palasa Kasibugga

Zone I - Proposed pipelines

Abstract Estimate for Distribution network


Name of Work: Providing Distribution system with HDPE pipes including supply, delivery, laying and
jointing including all appurtenances in GJ College Zone - I Area of Palasa Kasibugga Municipality under
APMDP
S.No.
1

Description
Cutting road surface including stacking
excavated materials for pipe line trench work

Qty

HDPE Abs

Lakhs
Amount (Rs.)

of

a. Cutting open BT road surface ( as well as


Asphalt concrete upto 75mm thick including water
3126.09
bound macadam)
b. Cutting open CC road surface
234.46
c. Cutting open water bound macadam road
including soling
93.78
2

Estimate in RS #REF!
Unit
Rate

Sqm

815.33

1 Sqm

2548792.00

Cum

2265.41

1 Cum

531141.00

Cum

279.07

1 Cum

26173.00

Earth Work Excavation by Machinery in all marshy


Soils up to SDR & Stone Matric with in a radius of
5m ie., cut and Dump where the depth is less than
1.5 times the width

3563.00

Cum

#REF!

1 Cum

#REF!

Earth work excavation & depositing on bank with


initial lead of 50m and lift of 3m in all soils by
manual means, where the depth is less than 1.5
times the width

713.00

Cum

#REF!

1 Cum

#REF!

Earth work excavation & depositing on bank with


initial lead of 50m and lift of 3m in in ordinary rock
by manual means where the depth is less than 1.5
times the width for pipe line trenches

713.00

Cum

#REF!

1 Cum

#REF!

Earth work excavation & depositing on bank with


initial lead of 50m and lift of 3m in in Hard rock
(blasting prohibited) by manual means where the
depth is less than 1.5 times the width for pipe line
trenches

713.00

Cum

#REF!

1 Cum

#REF!

Uprooting of CI pipes by melting lead, loosening


the joints, seperating the pipes, hoisting and
keeping with in a lead of 10 m but exploding
earthwork excavation and refilling
For 100 mm of size CI pipes
For 125 mm of size CI pipes
For 150 mm of size CI pipes
For 200 mm of size CI pipes
For 250 mm of size CI pipes
For 300 mm of size CI pipes
For 350 mm of size CI pipes
For 400 mm of size CI pipes
For 450 mm of size CI pipes
For 500 mm of size CI pipes
For 600 mm of size CI pipes

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt

38.24
43.56
48.44
58.91
69.11
78.13
87.48
96.63
106.02
115.39
132.91

Uprooting of RCC pipes including breaking the


collars, loosing the joint, scrapping the pipe,
hoisting and keeping with in a lead of 10 m but
excluding earthwork excavation and refilling
For 100 mm of size RCC/AC/HDPE pipes
For 150 mm of size RCC/AC/HDPE pipes

0.00
0.00

Rmt
Rmt

23.80
28.70

62

1
1
1
1
1
1
1
1
1
1
1

Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

1 Rmt
1 Rmt

0.00
0.00

Aarvee Associates

APMDP - Palasa Kasibugga

S.No.

Zone I - Proposed pipelines

Description

Qty
0.00
0.00

For 225 mm of size RCC/AC/HDPE pipes


For 300 mm of size RCC/AC/HDPE pipes
8

10

11

Rmt
Rmt

31.40
34.34

Unit

Amount (Rs.)

1 Rmt
1 Rmt

0.00
0.00

Providing barricading arrangement with casurina


ballies as per the design duly excavating pits and
its removal after the function is over including the
hire charges of barricading materials as per the
schedule given by the departmental authorities
9880.00
complete - for finished item of work.

Rmt

Supply,delivery and filling with sand for pipe


bedding as per specifications and drawing including
watering, tamping, ramming and bringing to the
shape of the pipe at the bottom as directed by the
departmental
officers
including
cost
and
conveyance of sand, loading, unloading, filling,
labour charges and all other incidental and
operational charges etc,complete.

380.00

Cum

484.86

1 Cum

184246.00

Manufacture, supply & delivery of HDPE pipes (PE80 Grade)confirming to IS:4984-1995 including
transportation to any where in A.P. including
excise duty, sales tax and specials etc etc,
complete
4750.00
For 110mm dia HDPE pipes
190.00
For 160mm dia HDPE pipes
0.00
For 280mm dia HDPE pipes

Rmt
Rmt
Rmt

213.25
444.57
1387.93

1 Rmt
1 Rmt
1 Rmt

1012936.00
84469.00
0.00

4750.00
190.00
0.00

Rmt
Rmt
Rmt

23.89
34.93
58.03

1 Rmt
1 Rmt
1 Rmt

113460.00
6637.00
0.00

For 110 dia HDPE pipe line


Pipe End Long Neck
MS Fanges
End Caps
Reducers- 90mm x 110mm
Tees
Bends

950.00
48.00
48.00
19.00
48.00
95.00

Nos
Nos
Nos
Nos
Nos
Nos

163.54
215.63
93.28
184.13
311.33
319.81

1
1
1
1
1
1

each
each
each
each
each
each

155362.00
10351.00
4478.00
3499.00
14944.00
30382.00

For 160 dia HDPE pipe line


Pipe End Long Neck
MS Fanges
End Caps
Reducers -140mm x 160mm
Tees
Bends

38.00
2.00
2.00
1.00
2.00
4.00

Nos
Nos
Nos
Nos
Nos
Nos

413.08
420.35
228.95
541.49
1113.27
925.50

1
1
1
1
1
1

each
each
each
each
each
each

15698.00
841.00
458.00
542.00
2227.00
3703.00

#REF!

1 Rmt

#REF!

Laying and jointing of HDPE pipes(PE-80 Grade)


by butt fusion welding as per IS:7634-Part-II/1975
as amended from time to time to the alignment
and gradient and testing the pipe line to the
required pressure
For 110mm dia HDPE pipes
For 160mm dia HDPE pipes
For 280mm dia HDPE pipes

12

Rate

Manufacture, Supply & delivery of HDPE fittings


confirming to IS:4984-1985 including transportation
to any where in A.P, including excise duty, sales
tax and specials etc, complete

For 280 dia HDPE pipe line

HDPE Abs

63

Aarvee Associates

APMDP - Palasa Kasibugga

Description

S.No.

13

14

Zone I - Proposed pipelines

Qty

1
1
1
1
1
1

0.00
0.00
0.00
0.00
0.00
0.00

Nos
Nos
Nos
Nos
Nos
Nos

1132.65
1287.71
615.39
2302.86
5658.41
5049.08

Manufacture, Supply and delivery of DI D/F Gate


Valves (Soft Seated) Resilient seated soft sealing
gate valves (Sluice valves) with body bonnet of
ductile cast iron of grade GGG40/ SG 400/12 or
equivalent grade as per I.S.3896-part2-1985 and
subsequent revisions, wedge fully rubber lined
with EPDM food grade quality and seals of NBR
and the valves should be of vacuum tight and
100% leak proof with face to face dimensions as
per BS5163-89/IS14846-2000/DIN 3202 F 4. All
the valves should be with Electrostatic powder
coating both inside and outside pocket less body
passage.
Drilled as per IS:1538 including all taxes and duties
transportation to work site, loading, unloading and
hoisting and carefully lowering the valves into
trenches / chambers, laying true to alignment and
gradient and perfect lining and jointing including
cost of carbon steel nuts, bolts, and rubber gaskets
packing including field hydraulic testing to a
required pressure etc., complete for finished item
of work.
100 mm dia valves
150 mm dia valves
250 mm dia valves

19.00
0.76
0.00

Nos
Nos
Nos

19.00
0.76

0.00

Amount (Rs.)

each
each
each
each
each
each

0.00
0.00
0.00
0.00
0.00
0.00

14401.00
22710.00
77505.00

1 each
1 each
1 each

273619.00
17260.00
0.00

Nos
Nos

#REF!
#REF!

1 Nos
1 Nos

#REF!
#REF!

Nos

#REF!

1 Nos

#REF!

Construction of RCC valve chamber having the size


of 0.90mx 0.90m x 1.00m including cost of FRC
cover manufacture as per BIS:12592 (Part 1&2)
Supply & Delivery of manhole covers and frames
with ISI marking and frame, H.D.-20 with 560mm
dia clear opening including, loading, un-loading &
stacking at site including central excise duty, sales
tax, octroi and other Govt levies etc., as applicable

Construction of RCC valve chamber having the size


of 1.20mx 1.20m x 1.20m including cost of FRC
cover manufacture as per BIS:12592 (Part 1&2)
Supply & Delivery of manhole covers and frames
with ISI marking and frame, H.D.-20 with 560mm
dia clear opening including, loading, un-loading &
stacking at site including central excise duty, sales
tax, octroi and other Govt levies etc., as applicable
250 mm dia valves

HDPE Abs

Unit

Pipe End Long Neck


MS Fanges
End Caps
Reducers - 250mm x 280mm
Tees
Bends

100 mm dia valves


150 mm dia valves
15

Rate

64

Aarvee Associates

APMDP - Palasa Kasibugga

Zone I - Proposed pipelines

S.No.

Description

16

Refilling the pipeline trenches, sides of chambers


and thrust blocks with useful soils complying with
standard specification after the pipeline is laid,
jointed and tested as directed by the departmental
officers, including breaking clods, watering,
tamping and ramming etc., and inclusive of all
incidental and operational charges etc., complete

17

18

19

20

HDPE Abs

Qty

Carting away the surplus excavated materials i.e.,


earth from the site to a suitable distance of about
5 kms including loading, unloading, conveyance
charges and dumping the carted materials at the
contractors cost, labour charges, all leads and lifts,
all other incidental and operational charges etc
complete

Supply and delivery of HYSD bars of Fe 415 grade


of various diameters including cost and conveyance
to site, labour charges for straightening, cutting,
bending and fabrication of reinforcement including
placing in position, binding and all labour charges
and cost of binding wire for tying the rods, all leads
and lifts, tools and plants, all incidental and
operational
charges
etc.,
complete
for
reinforcement for RCC chambers, pedestals, thrust
blocks etc.

65

Unit

Amount (Rs.)

2194.98

Nos

159.32

1 Nos

349694.00

4930

Nos

72.39

1 Nos

356907.00

Cum

72.39

1 Cum

103229.00

32.00

Cum

4031.75

1 Cum

129017.00

316.20

Kg

Carting away the surplus excavated materials i.e.,


rock from the site to a suitable distance of about 5
kms including loading, unloading, conveyance
charges and dumping the carted materials at the
contractors cost, labour charges, all leads and lifts,
all other incidental and operational charges etc
1426.00
complete.
Providing RCC (1:2:4) using 20mm HBG metal
including cost and conveyance of all materials nad
labour charges for laying, curing etc complete as
per the instruction of the departmental authorities

Rate

53.49

1 Kg

16914.00

Aarvee Associates

APMDP - Palasa Kasibugga

Zone I - Proposed pipelines

S.No.

Description

21

Laying VCC in M 30 Grade design mix using 20mm


SS-5 HBG m/c metal , coarse and fine aggregates
conforming to IS: 383, and OPC (cement content
between 350 to 425 kg/cum as per IRC mix design
for Fair degree of quality control), subject to
recovery of difference in cost of cement if cement
content as per mix design is less than 400 kg/cum
of concrete, including cost and conveyance of all
materials, machinery, all labour charges (including
placing in position
expansion, contraction,
construction, longitudinal joints and corner
reinforcement if any but excluding cost of joint
filler, sealant and reinforcement and its fabrication
), centering, vibration, curing for 21 days and all
incidental & operational charges etc. complete
conforming to standard specification for CC
Pavement more than 2m wide - 1 Cum - for
Restoration of road
Provision towards CI specials for inter connection
arrangements at
junctions/reservoir/interconnections and expansion
joints as per site condition

22

23

24

Qty

937.83

Cum

988.00

Kgs

Rate

Unit

4729.33

1 Cum

65.10 1 Kg
Sub Total

Provision towards charges payable to other


departments for shifting of service lines from the
proposed alignment @ 1%
Provision towards payment of R & B road cutting
charges & Rly. Line crossings Etc.

66

4435295.00

64319.00
#REF!

#REF!

say

HDPE Abs

Amount (Rs.)

#REF!
#REF!
#REF!
Lakhs

Aarvee Associates

APMDP - Palasa Kasibugga

Zone I - Proposed pipelines

Detailed Estimate for Distribution network


Name of Work: Providing Distribution system with HDPE pipes including supply, delivery, laying and
jointing including all appurtenances in GJ College Zone - I Area of Palasa Kasibugga Municipality under
APMDP
Diameter
For
For
For
For

Length

110mm dia HDPE


160mm dia HDPE
225mm dia HDPE
280mm dia HDPE
Total length

pipes
pipes
pipes
pipes

Sl.
No

Description

2
Earthwork Excavation Quantity calculation
For
For
For
For

110mm
160mm
225mm
280mm

dia
dia
dia
dia

HDPE
HDPE
HDPE
HDPE

pipe
pipe
pipe
pipe

4750
190
0
0
4940

Nos

line
line
line
line

trenches
trenches
trenches
trenches

Cutting road surface including stacking of


excavated materials for pipe line trench work
a. Cutting open BT road surface ( as well as
Asphalt concrete upto 75mm thick including
water bound macadam)
b. Cutting open CC road surface
c. Cutting open water bound macadam road
including soling

Size of existing CI
pipeline
100
0
125
0
150
0
200
0
250
0
300
0
350
0
400
0
450
0
500
0
600
0

Bread Depth in
Length in th in
mts
mts
mts

Quantity

4750
190
0
0

1.14
1.22
1.31
1.40

1.26
1.31
1.38
1.43

6823
302
0
0
7125

Cum
Cum
Cum
Cum
Cum

50%

4940

1.27

3126.09

Sqm

25%

4940

1.27

0.15

234.46

Cum

10%

4940

1.27

0.15

93.78

Cum

3562.66
0.34
3563.00

Cum
Cum
Cum

712.53
0.47
713.00

Cum
Cum
Cum

712.53

Cum

0.47
713.00

Cum
Cum

1
1
1
1

x
x
x
x

Earth Work Excavation by Machinery in all


marshy Soils up to SDR & Stone Matric with in a
radius of 5m ie., cut and Dump where the depth
is less than 1.5 times the width
Quantity considered 50%
Add for undulations
Earth work excavation & depositing on bank with
initial lead of 50m and lift of 3m in all soils by
manual means, where the depth is less than
1.5 times the width
Quantity considered 10%
Add for undulations

1
1
1
1

Earth work excavation & depositing on bank with


initial lead of 50m and lift of 3m in in ordinary
rock by manual means where the depth is less
than 1.5 times the width for pipe line trenches
Considering 10% of Excavation Qty as Ordinary
rock, Rock Cutting without blasting
Add for undulations

HDPE Det

Size of Existing
RCC/AC/HDPE pipe
100
0
150
0
225
0
300
0

67

Aarvee Associates

APMDP - Palasa Kasibugga

Zone I - Proposed pipelines

Sl.
No

Description

Earth work excavation & depositing on bank with


initial lead of 50m and lift of 3m in in Hard rock
(blasting prohibited) by manual means where
the depth is less than 1.5 times the width for
pipe line trenches
Considering 10% of Excavation Qty as Hard rock,
Rock Cutting with blasting
Add for undulations

100
125
150
200
250
300
350
400
450
500
600

mm
mm
mm
mm
mm
mm
mm
mm
mm
mm
mm

size
size
size
size
size
size
size
size
size
size
size

CI
CI
CI
CI
CI
CI
CI
CI
CI
CI
CI

pipes
pipes
pipes
pipes
pipes
pipes
pipes
pipes
pipes
pipes
pipes

100
150
225
300

mm
mm
mm
mm

size
size
size
size

RCC/AC/HDPE
RCC/AC/HDPE
RCC/AC/HDPE
RCC/AC/HDPE

pipes
pipes
pipes
pipes

712.53

Cum

0.47
713.00

Cum
Cum

1
1
1
1
1
1
1
1
1
1
1

x
x
x
x
x
x
x
x
x
x
x

1
1
1
1
1
1
1
1
1
1
1

0
0
0
0
0
0
0
0
0
0
0

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt
Rmt

1
1
1
1

x
x
x
x

1
1
1
1

0
0
0
0

0.00
0.00
0.00
0.00

Rmt
Rmt
Rmt
Rmt

4940

9880

Rmt

1
1
1

x
x
x

1
1
1

4750
190
0

363.38
15.96
0.00
0.67

Cum
Cum
Cum
Cum

Supply,delivery and filling with sand for pipe


bedding as per specifications and drawing
including watering, tamping, ramming and
bringing to the shape of the pipe at the bottom
as directed by the departmental officers
including cost and conveyance of sand, loading,
unloading, filling, labour charges and all other
incidental and operational charges etc,complete.
Pipe Bedding and surrounds
For 110mm dia HDPE pipe line trenches
For 160mm dia HDPE pipe line trenches
For 280mm dia HDPE pipe line trenches
Add for slushy soils

HDPE Det

Providing barricading arrangement with casurina


ballies as per the design duly excavating pits and
its removal after the function is over including
the hire charges of barricading materials as per
the schedule given by the departmental
authorities complete - for finished item of work.
For pipe line trench on both sides

Quantity

Uprooting of RCC pipes including breaking the


collars, loosing the joint, scrapping the pipe,
hoisting and keeping with in a lead of 10 m but
excluding earthwork excavation and refilling
For
For
For
For

Bread Depth in
Length in th in
mts
mts
mts

Uprooting of CI pipes by melting lead, loosening


the joints, seperating the pipes, hoisting and
keeping with in a lead of 10 m but exploding
earthwork excavation and refilling
For
For
For
For
For
For
For
For
For
For
For

Nos

68

0.51
0.56
0.68

0.15
0.15
0.15

Aarvee Associates

APMDP - Palasa Kasibugga

Zone I - Proposed pipelines

Sl.
No

Description

Nos

Bread Depth in
Length in th in
mts
mts
mts
4

Quantity

7
380.00

Cum

10 Manufacture, supply & delivery of HDPE pipes


(PE-80 Grade)confirming to IS:4984-1995
including transportation to any where in A.P.
including excise duty, sales tax and specials etc
etc, complete
4.0 Kg/Sqcm
For 110 dia HDPE pipes
For 160 dia HDPE pipes
For 280 dia HDPE pipes

1
1
1

x
x
x

1
1
1

4750
190
0

4750
190
0

Rmt
Rmt
Rmt

11 Laying and jointing of HDPE pipes(PE-80 Grade)


by butt fusion welding as per IS:7634-PartII/1975 as amended from time to time to the
alignment and gradient and testing the pipe line
to the required pressure
For 110 dia HDPE pipes
For 160 dia HDPE pipes
For 280 dia HDPE pipes

1
1
1

x
x
x

1
1
1

4750
190
0

4750
190
0

Rmt
Rmt
Rmt

For 110 dia HDPE pipes


Pipe End Long Neck
MS Fanges
End Caps
Reducers- 90mm x 110mm
Tees
Bends

1
1
1
1
1
1

x
x
x
x
x
x

1
1
1
1
1
1

950
48
48
19
48
95

950
48
48
19
48
95

Nos
Nos
Nos
Nos
Nos
Nos

For 160 dia HDPE pipes


Pipe End Long Neck
MS Fanges
End Caps
Reducers -140mm x 160mm
Tees
Bends

1
1
1
1
1
1

x
x
x
x
x
x

1
1
1
1
1
1

38
2
2
1
2
4

38
2
2
1
2
4

Nos
Nos
Nos
Nos
Nos
Nos

For 280 dia HDPE pipes


Pipe End Long Neck
MS Fanges
End Caps
Reducers - 250mm x 280mm
Tees
Bends

1
1
1
1
1
1

x
x
x
x
x
x

1
1
1
1
1
1

0
0
0
0
0
0

0
0
0
0
0
0

Nos
Nos
Nos
Nos
Nos
Nos

12 Manufacture, Supply & delivery of HDPE fittings


confirming
to
IS:4984-1985
including
transportation to any where in A.P, including
excise duty, sales tax and specials etc, complete

HDPE Det

69

Aarvee Associates

APMDP - Palasa Kasibugga

Sl.
No

Zone I - Proposed pipelines

Description

Nos

Bread Depth in
Length in th in
mts
mts
mts
4

1
2
3
13 Manufacture, Supply and delivery of DI D/F
Gate Valves (Soft Seated) Resilient seated soft
sealing gate valves (Sluice valves) with body
bonnet of ductile cast iron of grade GGG40/ SG
400/12 or equivalent grade as per I.S.3896-part21985 and subsequent revisions, wedge fully
rubber lined with EPDM food grade quality and
seals of NBR and the valves should be of vacuum
tight and 100% leak proof with face to face
dimensions as per BS5163-89/IS14846-2000/DIN
3202 F 4. All the valves should be with
Electrostatic powder coating both inside and
outside pocket less body passage.

Quantity

Drilled as per IS:1538 including all taxes and


duties transportation to work site, loading,
unloading and hoisting and carefully lowering
the valves into trenches / chambers, laying true
to alignment and gradient and perfect lining and
jointing including cost of carbon steel nuts, bolts,
and rubber gaskets packing including field
hydraulic testing to a required pressure etc.,
complete for finished item of work.
100 mm dia valves
150 mm dia valves
250 mm dia valves

1
1
1

x
x
x

1
1
1

19
0.76
0

19
1
0

Nos
Nos
Nos

1
1

x
x

1
1

19
1

19
1

Nos
Nos

Nos

14 Construction of RCC valve chamber having the


size of 0.90mx 0.90m x 1.00m including cost
of FRC cover manufacture as per BIS:12592
(Part 1&2) Supply & Delivery of manhole covers
and frames with ISI marking and frame, H.D.-20
with 560mm dia clear opening including, loading,
un-loading & stacking at site including central
excise duty, sales tax, octroi and other Govt
levies etc., as applicable
100 mm dia valves
150 mm dia valves
15 Construction of RCC valve chamber having the
size of 1.20mx 1.20m x 1.20m including cost
of FRC cover manufacture as per BIS:12592
(Part 1&2) Supply & Delivery of manhole covers
and frames with ISI marking and frame, H.D.-20
with 560mm dia clear opening including, loading,
un-loading & stacking at site including central
excise duty, sales tax, octroi and other Govt
levies etc., as applicable
250 mm dia valves

HDPE Det

70

Aarvee Associates

APMDP - Palasa Kasibugga

Sl.
No

Zone I - Proposed pipelines

Description

1
2
16 Refilling the pipeline trenches, sides of chambers
and thrust blocks with useful soils complying
with standard specification after the pipeline is
laid, jointed and tested as directed by the
departmental officers, including breaking clods,
watering, tamping and ramming etc., and
inclusive of all incidental and operational charges
etc., complete

Nos

Bread Depth in
Length in th in
mts
mts
mts
4

Qty of earth Excavated


Deduct Qty of Road cuttings
Deduct Qty of Sand bedding
Deduct Qty of Ordinary & Hard Rcck
Deduct Pipe portion
For 110 dia HDPE pipes
For 160 dia HDPE pipes
For 225 dia HDPE pipes
For 280 dia HDPE pipes

Quantity

7125
-3454
-380
-1046
PI x ((110/1000)^2)/4 x 4750
PI x ((160/1000)^2)/4 x 190
PI x ((225/1000)^2)/4 x 0
PI x ((280/1000)^2)/4 x 0
Say

-46
-4
0
0
2195
2200

Cum

Say

7125
-2195
4930
4940

Cum

1426

Cum

17 Carting away the surplus excavated materials


i.e., earth from the site to a suitable distance of
about 5 kms including loading, unloading,
conveyance charges and dumping the carted
materials at the contractors cost, labour charges,
all leads and lifts, all other incidental and
operational charges etc complete
Qty of Earth Excavated
deduct qty of refilling

18 Carting away the surplus excavated materials


i.e., rock from the site to a suitable distance of
about 5 kms including loading, unloading,
conveyance charges and dumping the carted
materials at the contractors cost, labour charges,
all leads and lifts, all other incidental and
operational charges etc complete.
Qty of Hard Rock & Ordinary Rock
Civil Works
19 Providing RCC (1:2:4) using 20mm HBG metal
including cost and conveyance of all materials
nad labour charges for laying, curing etc
complete as per the instruction of the
departmental authorities

HDPE Det

For Pedestals

20

1.00

0.90

Deduct for pipe portion


For 110 dia HDPE pipes
For 160 dia HDPE pipes
For 225 dia HDPE pipes
For 280 dia HDPE pipes

19
1
0
0

x
x
x
x

1
1
1
1

1.00
1.00
1.00
1.00

0.01
0.02
0.04
0.06

For Anchor Blocks

10

1.00

0.90

Deduct for pipe portion


For 110 dia HDPE pipes
For 160 dia HDPE pipes
For 225 dia HDPE pipes
For 280 dia HDPE pipes

10
0
0
0

x
x
x
x

1
1
1
1

1.00
1.00
1.00
1.00

0.01
0.02
0.04
0.06

71

0.90
-

-0.18
-0.02
0.00
0.00
0.90

16.01

8.00
-0.09
-0.01
0.00
0.00

Aarvee Associates

APMDP - Palasa Kasibugga

Zone I - Proposed pipelines

Sl.
No

Description

Nos

Bread Depth in
Length in th in
mts
mts
mts
4

For Thrust Blocks

10

1.00

0.90

Deduct for pipe portion


For 110 dia HDPE pipes
For 160 dia HDPE pipes
For 225 dia HDPE pipes
For 280 dia HDPE pipes

10
0
0
0

x
x
x
x

1
1
1
1

1.00
1.00
1.00
1.00

0.01
0.02
0.04
0.06

Quantity

7
0.90

say

8.00
-0.09
-0.01
0.00
0.00
31.62
32.00 Cum

20 Supply and delivery of HYSD bars of Fe 415


grade of various diameters including cost and
conveyance to site, labour charges for
straightening, cutting, bending and fabrication of
reinforcement including placing in position,
binding and all labour charges and cost of
binding wire for tying the rods, all leads and lifts,
tools and plants, all incidental and operational
charges etc., complete for reinforcement for RCC
chambers, pedestals, thrust blocks etc.
7.90
7.90

for Thrust blocks


for Anchor blocks

20 Kg/Cum
20 Kg/Cum
say

158.10
158.10
316.20
0.32

Kg
Kg
Kg
MT

21 Laying VCC in M 30 Grade design mix using


20mm SS-5 HBG m/c metal , coarse and fine
aggregates conforming to IS: 383, and OPC
(cement content between 350 to 425 kg/cum as
per IRC mix design for Fair degree of quality
control), subject to recovery of difference in
cost of cement if cement content as per mix
design is less than 400 kg/cum of concrete,
including cost and conveyance of all materials,
machinery, all labour charges (including placing
in position expansion, contraction, construction,
longitudinal joints and corner reinforcement if
any but excluding cost of joint filler, sealant and
reinforcement and its fabrication ), centering,
vibration, curing for 21 days and all incidental &
operational charges etc. complete conforming to
standard specification for CC Pavement more
than 2m wide - 1 Cum - for Restoration of
road

22 Provision towards CI specials for inter connection


arrangements at
junctions/reservoir/interconnections and
expansion joints as per site condition

3705

988

1.27

0.2

937.83

Cum

988.00

Kgs

23 Provision towards charges payable to other


departments for shifting of service lines from the
proposed alignment @ 1%

LS

24 Provision towards payment of R & B road cutting


charges & Rly. Line crossings Etc.

LS

HDPE Det

72

Aarvee Associates

Wall
Thick
B, m D, m Footing Thick ness

L, m
Clear dimensions
3.6

3.6

3.60

0.15

0.23

Ave.Dia
2.3

Detailed estimate for


Sluice valve (2200 - 2500mm dia) chamber
Sluice Valve Chamber (3.6 x 3.6 x 3.6 m)
Sl.No.

Description

Earth work excavation & depositing on bank with


initial lead of 50m and lift of 3m in all soils by
manual means

cum

4.36

4.36

3.75

71.29

Laying Cement concrete ( 1: 4 : 8) using 40mm


nominal size graded HBG metal including cost of
all materials and labour charges etc. complete- In
foundation and Plinth

cum

4.36

4.36

0.15

2.85

V R.C.C. M30 Grade using 20 mm HBG Down


graded metal including centring charges, laying ,
levelling , machine mixing but exculding cost of
steel in reinforcement, etc complete as per SS up to
150mm thick Slab
For slab of Valve pit
Deduct for Opening

1
1

cum
cum

4.06
1.80

4.06
1.80

0.15
0.15

2.47
-0.49
1.99

Supply and delivery of Steel Reinforcement


H.Y.S.D.confirming to I.S.S. including cost &
conveyance of all materials , cost of binding wire
and its fabrication charges, placing in position tying
grills etc., complete.

kg

2
2
2

cum
cum
cum
cum

Nos. Unit L(m)

B(m)

D(m)

Quantity

1000

@ 90 kg / cum of RCC
5

V R.C.C. M30 Grade using 20 mm HBG Down


graded metal including centring charges, laying ,
levelling , machine mixing but exculding cost of
steel in reinforcement, etc complete as per SS for
Side walls of valve chamber
a) Long wall
b) Short wall
c) Deduct for pipes
Total

4.06
0.20
3.60
3.60
0.20
3.60
0.23 (pi/4)*2.3^2

5.85
5.18
1.91
9.12

V R.C.C. M30 Grade using 20 mm HBG Down


graded metal including centring charges, laying ,
levelling , machine mixing but exculding cost of
steel in reinforcement, etc complete as per SS up to
150mm thick Slab - For Cover Slabs of Valve
Chamber

No.

2.00

0.50

0.175

0.70

No.

3.83

3.83

3.6

71.29
-52.81
18.48

Collection , supply & filling sand including watering,


tamping, etc complete, plinth sites of foundation in
layers not exceeding 20cm in depth including
consolidation of each layer by ramming, watering,
lead upto 50m and lift upto 1.5m in all kinds of soil
Qty of Earth excavated
Deduct

Carting away the surplus excavated earth from the


work site with a lead of 0.5 km beyond initial lead
including loading, unloading and conveyance but
excluding stacking charges etc., complete - 1 cum
Qty. Excavated
Qty. Refilled back
Qty. to be conveyed

71.29
-18.48
52.81

L, m

Wall
Thickne
B, m D, m Footing Thick ss

3.0

3.0

3.00

0.15

0.23

Detailed estimate for


Sluice valve (1600mm to 2100m dia) chamber
Sluice Valve Chamber (3 x 3 x 3 m)
Sl.No.

Description

Earth work excavation & depositing on bank with initial

Nos. Unit L(m) B(m)

D(m)

lead of 50m and lift of 3m in all soils by manual means

cum

3.76

3.76

3.15

Laying Cement concrete ( 1: 4 : 8) using 40mm


nominal size graded HBG metal including cost of all
materials and labour charges etc. complete- In
foundation and Plinth

cum

3.76

3.76

0.15

V R.C.C. M30 Grade using 20 mm HBG Down graded


metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS up to 150mm
thick Slab
For slab of Valve pit
Deduct for Opening

1
1

cum
cum

3.46
1.80

3.46
1.80

0.15
0.15

Supply and delivery of Steel Reinforcement


H.Y.S.D.confirming to I.S.S.
including cost &
conveyance of all materials , cost of binding wire and its
fabrication charges, placing in position tying grills etc.,
complete.

kg

2
2
2

cum
cum
cum
cum

@ 80 kg / cum of RCC
5

V R.C.C. M30 Grade using 20 mm HBG Down graded


metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS for Side walls of
valve chamber
a) Long wall
b) Short wall
c) Deduct for pipes
Total

3.46
0.20
3.00
3.00
0.20
3.00
0.23 (pi/4)*1.8^2

V R.C.C. M30 Grade using 20 mm HBG Down graded


metal including centring charges, laying , levelling ,
machine mixing but exculding cost

of steel in

reinforcement, etc complete as per SS up to 150mm


thick Slab - For Cover Slabs of Valve Chamber
7

No.

0.5

0.175

No.

3.23

3.23

Collection , supply & filling sand including watering,


tamping, etc complete, plinth sites of foundation in
layers

not

exceeding

20cm

in

depth

including

consolidation of each layer by ramming, watering, lead


upto 50m and lift upto 1.5m in all kinds of soil
Qty of Earth excavated
Deduct

Carting away the surplus excavated earth from the


work site with a lead of 0.5 km beyond initial lead
including loading, unloading and conveyance but
excluding stacking charges etc., complete - 1 cum
Qty. Excavated
Qty. Refilled back
Qty. to be conveyed

Ave.Dia
1.8

L, m

B, m D, m Footing Thick

2.4

2.4

2.40

0.15

Detailed estimate for


Sluice valve (1200 - 1500mm dia) chamber
Sluice Valve Chamber (2.4 x 2.4 x 2.4 m)
Quantity

Sl.No.

Description

Earth work excavation & depositing on bank with


initial lead of 50m and lift of 3m in all soils by manual
means

cum

3.16

3.16

Laying Cement concrete ( 1: 4 : 8) using 40mm


nominal size graded HBG metal including cost of all
materials and labour charges etc. complete- In
foundation and Plinth

cum

3.16

3.16

V R.C.C. M30 Grade using 20 mm HBG Down


graded metal including centring charges, laying ,
levelling , machine mixing but exculding cost of steel
in reinforcement, etc complete as per SS up to
150mm thick Slab
For slab of Valve pit
Deduct for Opening

1
1

cum
cum

2.86
1.80

2.86
1.80

Supply and delivery of Steel Reinforcement


H.Y.S.D.confirming to I.S.S. including cost &
conveyance of all materials , cost of binding wire and
its fabrication charges, placing in position tying grills
etc., complete.

kg

2
2
2

cum
cum
cum
cum

44.53
2

2.12
3

1.80
-0.49
1.31
4

670

Nos. Unit L(m) B(m)

@ 65 kg / cum of RCC
5

4.15
3.60
1.17
6.58

V R.C.C. M30 Grade using 20 mm HBG Down


graded metal including centring charges, laying ,
levelling , machine mixing but exculding cost of steel
in reinforcement, etc complete as per SS for Side
walls of valve chamber
a) Long wall
b) Short wall
c) Deduct for pipes
Total

2.86
0.20
2.40
0.20
0.23 (pi/4)*1.3^2

0.7
7

V R.C.C. M30 Grade using 20 mm HBG Down


graded metal including centring charges, laying ,
levelling , machine mixing but exculding cost of steel
in reinforcement, etc complete as per SS up to
150mm thick Slab - For Cover Slabs of Valve
Chamber

No.

1.8

0.5

No.

2.63

2.63

Collection , supply & filling sand including watering,


tamping, etc complete, plinth sites of foundation in
layers not exceeding 20cm in depth including
consolidation of each layer by ramming, watering,
lead upto 50m and lift upto 1.5m in all kinds of soil
Qty of Earth excavated
Deduct

44.53
-31.30
13.23
8

Carting away the surplus excavated earth from the


work site with a lead of 0.5 km beyond initial lead
including loading, unloading and conveyance but

44.53
-13.23
31.30

excluding stacking charges etc., complete - 1 cum


Qty. Excavated
Qty. Refilled back
Qty. to be conveyed

Wall
Thickne
ss
0.23

D(m)

Ave.Dia
1.3

Quantity

2.55

25.46

0.15

1.50

0.15
0.15

1.23
-0.49
0.74

368

2.40
2.40
(pi/4)*1.3^2

2.75
2.30
0.61
4.44

0.175

0.63

2.4

25.46
-16.60
8.86

25.46
-8.86
16.60

Length
3.60

Bredth
3.60

Depth
3.60

Sluice valve (2200 - 2500mm dia) chamber


Sluice Valve Chamber (3.6 x 3.6 x 3.6 m)
Sl.No.
Description of work
1

Quantity

Unit

Earth work excavation & depositing on bank with initial


lead of 50m and lift of 3m in all soils by manual means
71.29 cum

#REF!

Laying Cement concrete ( 1: 4 : 8) using 40mm nominal


size graded HBG metal including cost of all materials
and labour charges etc. complete- In foundation and
Plinth

2.85 Cum

3363.59

V R.C.C. M30 Grade using 20 mm HBG Down graded


metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS up to 150mm thick
Slab

1.99 Cum

#REF!

Supply
and
delivery
of
Steel
Reinforcement
H.Y.S.D.confirming to I.S.S. including cost & conveyance
of all materials , cost of binding wire and its fabrication
charges, placing in position tying grills etc., complete.
1000 kg

Rate (Rs.)

53.49

V R.C.C. M30 Grade using 20 mm HBG Down graded


metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS for Side walls of
valve chamber

9.12 Cum

#REF!

V R.C.C. M30 Grade using 20 mm HBG Down graded


metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS up to 150mm thick
Slab - For Cover Slabs of Valve Chamber

0.70 Cum

#REF!

Collection , supply & filling sand including watering,


tamping, etc complete, plinth sites of foundation in layers
not exceeding 20cm in depth including consolidation of
each layer by ramming, watering, lead upto 50m and lift
upto 1.5m in all kinds of soil

18.48 Cum

484.86

52.81 Cum

72.39

Carting away the surplus excavated earth from the work


site with a lead of 0.5 km beyond initial lead including
loading, unloading and conveyance but excluding
stacking charges etc., complete - 1 cum
TOTAL COST

Say

Length
3.00

Bredth
3.00

Depth
3.00

Sluice valve (1600mm to 2100m dia) chamber


Sluice Valve Chamber (3 x 3 x 3 m)
Sl.No.
Amount (Rs.)

Description of work
1

Unit

Earth work excavation & depositing on bank with initial lead


of 50m and lift of 3m in all soils by manual means

#REF!

44.53 Cum
2

Laying Cement concrete ( 1: 4 : 8) using 40mm nominal size


graded HBG metal including cost of all materials and labour
charges etc. complete- In foundation and Plinth

9,591.07

2.12 Cum
3

V R.C.C. M30 Grade using 20 mm HBG Down graded metal


including centring charges, laying , levelling , machine mixing
but exculding cost of steel in reinforcement, etc complete as
per SS up to 150mm thick Slab

#REF!

1.31 Cum
4

Supply
and
delivery
of
Steel
Reinforcement
H.Y.S.D.confirming to I.S.S. including cost & conveyance of
all materials , cost of binding wire and its fabrication charges,
placing in position tying grills etc., complete.

53,464.79

670 kg
5

V R.C.C. M30 Grade using 20 mm HBG Down graded metal


including centring charges, laying , levelling , machine mixing
but exculding cost of steel in reinforcement, etc complete as
per SS for Side walls of valve chamber

#REF!

6.58 Cum
6

#REF!
7

V R.C.C. M30 Grade using 20 mm HBG Down graded metal


including centring charges, laying , levelling , machine mixing
but exculding cost of steel in reinforcement, etc complete as
per SS up to 150mm thick Slab - For Cover Slabs of Valve
Chamber

0.70 cum

Filling available excavated earth in trenches, plinth sites of


foundation in layers not exceeding 20cm in depth including
consolidation of each layer by ramming, watering, lead upto
50m and lift upto 1.5m in all kinds of soil

8,959.15

13.23 Cum
8

3,822.77
#REF!

Quantity

Conveyance
of
excavated
earth
,loose
moorum/sand/earth/surkhi/cement/stone dust/hot mix asphalt
materials etc, from the site of work to a lead of 5.0 km
including loading , unloading and levelling the soil as per the
directions of the departmental author
TOTAL COST

31.30 Cum

#REF!

Length
2.4

ber

Bredth
2.4

Sluice/Scour valve (1200 - 1500mm dia) chamber


Sluice Valve Chamber (2.4 x 2.4 x 2.4 m)

Rate (Rs.)

Amount
(Rs.)

Sl.No.
Description of work
1

#REF!

25.46

1.50

#REF!
4

53.49

#REF!

#REF!
7

484.86

Supply
and
delivery
of
Steel
Reinforcement
H.Y.S.D.confirming to I.S.S. including cost & conveyance
of all materials , cost of binding wire and its fabrication
charges, placing in position tying grills etc., complete.

V R.C.C. M30 Grade using 20 mm HBG Down graded


metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS for Side walls of
valve chamber

4.44

V R.C.C. M30 Grade using 20 mm HBG Down graded


metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS up to 150mm thick
Slab - For Cover Slabs of Valve Chamber

0.63

Filling available excavated earth in trenches, plinth sites of


foundation in layers not exceeding 20cm in depth including
consolidation of each layer by ramming, watering, lead upto
50m and lift upto 1.5m in all kinds of soil

6,416.95

8.86
8

72.39

2,265.71
#REF!

0.74

368

#REF!

V R.C.C. M30 Grade using 20 mm HBG Down graded


metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS up to 150mm thick
Slab

35,847.82
5

#REF!

Laying Cement concrete ( 1: 4 : 8) using 40mm nominal


size graded HBG metal including cost of all materials and
labour charges etc. complete- In foundation and Plinth

7,132.96
3

#REF!

Earth work excavation & depositing on bank with initial lead


of 50m and lift of 3m in all soils by manual means

#REF!
2

3363.59

Quantity

Conveyance
of
excavated
earth
,loose
moorum/sand/earth/surkhi/cement/stone
dust/hot
mix
asphalt materials etc, from the site of work to a lead of 5.0
km including loading , unloading and levelling the soil as
per the directions of the departmental author
TOTAL COST

16.60

Say

#REF!

Depth
2.4

a) chamber

x 2.4 m)

Unit Rate (Rs.)

Amount
(Rs.)

Cum

#REF!

#REF!

Cum

3363.59

5,038.12

Cum

#REF!

#REF!

kg

53.49

19,699.71

Cum

#REF!

#REF!

Cum

#REF!

#REF!

Cum

484.86

4,297.15

Cum

72.39

1,201.71
#REF!

Say

#REF!

Data for MS Specials

PHED, Madhya Pradesh

DATAS FOR MS SPECIALS


MS Bends
Manufacturing supplying, delivery,hoisting, laying and testing commisioning of MS Special M.S.Barrels in 16 mm thick mild steel plates
confirming to I.S.Specifications 2062-1992 grade-`A' manufactured as per IS:3589-2001, including cost of M.S.Plate fabrication charges and
three run arc welding with inlining the fabricated pipes with CM(1:2) prop 12 mm thick duly fixing 4 nos of 6mm dia MS rings at each end of the
pipe and out coating the pipe with CM(1:3) prop 30mm thick by shortcreting or guniting or short creating duly providing wiremesh of size
50x50x3 mm including cost of all materials and all other required materials and including all taxes and duties ,hoisting , and carefully lowering
the pipes in to the ready made trenches or keeping in position on pedastals or supports and laying them true to the alignment and gradient and
perfect lining by jacking and jointing etc., including all other incidental and operational charges etc., complete.

Bends
0-30 bend
2200

M.S.Pipe after in lining length


1.74
x
Sundries & Rounding off
Rs

31-60 bend
2200

31-60 bend
400

165410.00

79524.00

M.S.Pipe after in lining length


1.74
x
Sundries & Rounding off

0.00

0.00

Rmt

Rs

Rmt

Rs

Rmt

Rs

Each

M.S.Pipe after in lining length


2.08
x
Sundries & Rounding off

0.00

0.00

Rmt

Rs

Each

M.S.Pipe after in lining length


3.00
x
Sundries & Rounding off
Rs

Rs

Each

Each

Rs
61-90 bend
400

79524.00

238572.00

Rs

Rmt

Each

M.S.Pipe after in lining length


3.00
x
Sundries & Rounding off
Rs

400

138372.00

M.S.Pipe after in lining length


2.08
x
Sundries & Rounding off
Rs

61-90 bend
2200

79524.00

0.00

0.00

Rmt

Rs

Each

138371.76
0.24
138372.00

Each

165409.92
0.08
165410.00

Each

238572.00
0.00
238572.00

Each

0.00
0.00
0.00

Each

0.00
0.00
0.00

Each

0.00
0.00
0.00

Each

Mild Steel T's


2200 x 2200 x 2200mm
MS Tee for 2200X2200X2200 mm dia after inlining main length 2.5 M Branch 1.00 M with 8 mm
thick MS plate
a) Cost of MS Tees 2200mm Main barrel
2.5
b) Cost of MS Branch 2200mm barrel
1.0
1.5
Sundries & Rounding off
Rs
318096.00
2200 x 2200 x 200mm

79524.00

Rmt

Rs.

198810.00

79524.00

Rmt

Rs.

119286.00
0.00
318096.00

Each

MS Tee for 2200X2200X200 mm dia after inlining main length 2.5 M Branch 0.75 M with 16mm
thick MS plate
a) Cost of MS Tees 2200mm Main barrel
2.5
x
79524.00 Rmt
198810.00
Rs.
b) Cost of MS Branch 200mm barrel
0.8
x
#REF!
Rmt
#REF!
1.5
Rs.
Sundries & Rounding off
#REF!
#REF!
Rs
#REF!
Each
2200 x 2200 x 600mm

Pumping Main Reach -I

89

aarvee associates pvt ltd, Hyderabad

Data for MS Specials

PHED, Madhya Pradesh

MS Tee for 2200X2200X600 mm dia after inlining main length 2.5 M Branch 0.75 M with 16mm
thick MS plate
a) Cost of MS Tees 2200mm Main barrel
2.5
x
79524.00 Rmt
198810.00
Rs.
b) Cost of MS Branch 600mm barrel
0.8
x
#REF!
Rmt
#REF!
1.5
Rs.
Sundries & Rounding off
#REF!
#REF!
Rs
#REF!
Each

Pumping Main Reach -I

90

aarvee associates pvt ltd, Hyderabad

Data for MS Specials

PHED, Madhya Pradesh

MS TAPPERS (REDUCERS)
2200 x1200 mm Dia MS Taper(Reducer)
Cost of 2200 mm dia barrel
1.0
Cost of 1200 mm dia barrel
1.0
Average rate per Rmt
Rate per 1 .5m length
Add extra welding charges
For 800 mm dia
For 600 mm dia

Rs.
Rs.

79524.00
44108.00
123632.00
61816.00

1.5

92724.00

3.142*0.8*3.28*3*12 =
3.142*0.6*3.28*3*12 =

296.81
222.60

Rs.
Rs.

296.81
222.60
0.59
93244.00

MS Tail Pieces
600 mm dia
Cost of 600mm dia MS pipe
Cost of MS Flange to suit 600 mm dia MS pipe
Add welding charges 3 x 3.142 x 2400 /25.4
Add for sundries

Pumping Main Reach -I

1
1

91

Rmt
x
No
x
222.52

10143.10
4482.00

/ Rmt
/ Rmt

Rs.
Rs.

10143.10
4482
222.52
0.38
14848.00

aarvee associates pvt ltd, Hyderabad

Data for MS Specials

PHED, Madhya Pradesh

Manufacture and Supply of following MS specials using 10mm thick MS plates conforming to IS 2062- 1992 grade 'A', with flanged
branch as per IS-7322, with 1.00m long main pipe and 0.50m long as directed by the departmental officers , including inlining true to
alingment and gradient and perfect lining by jacking and jointing with three run arc welding and inlining and outcoating of field
welded joints with cement mortar as per the above specification inclusive of cost of all jointing materials
Cost of Flanges

nominal
dia of pipe
(mm)
80
100
150
200
300
500
600
700
750
1000
2400
a)

outer
dia of
flange
(mm)

thickness (mm)

No of
holes

15
15
15
15
15
20
20
25
25
25
16

4
8
8
8
12
20
20
24
24
28
36

200
220
285
340
445
670
780
895
960
1230
2680

Cost for 2400mm dia flange


Outer dia of flange
2680 mm
Inner dia of flange
2400 mm
Thickness of flange
18.00 mm
weight of flange
(22/7)/4 x 2.68^2 x 0.018 x 7850
Deduct internal dia.
(22/7)/4 x 2.4^2 x 0.018 x 7850
add 5% wastage
total weight
cost of MS plate
165.81
machine cutting charges
Drilling holes
28
Cost of nuts and bolts including C.E.D
28
Cost of rubber insertions including C.E.D
12
Total

a)

Nos
Nos.
Kg

Cost for 2300mm dia flange


Outer dia of flange
2480 mm
Inner dia of flange
2300 mm
Thickness of flange
18.00 mm
weight of flange
(22/7)/4 x 2.48^2 x 0.018 x 7850
Deduct internal dia.
(22/7)/4 x 2.3^2 x 0.018 x 7850

b)

Pumping Main Reach -I

x
x
x

2.5
2.3
0.018
682.83
587.30
95.52
4.78
100.30
Kg
x
Nos
Nos.
Kg

Rs.

20 / No
96.90 / kg
79.57 / kg

Rs.
Rs.
Rs.
Rs

36000 / MT

Rs.

96.10

20 / No
96.90 / kg
79.57 / kg

Rs.
Rs.
Rs.
Rs

Nos
Nos.
Kg

36000 / MT

Rs.

20 / No
96.90 / kg
79.57 / kg

Rs.
Rs.
Rs.
Rs

16.09 Kg
24 Nos
24 Nos
10 Kg

92

x
x
x

0.78
0.60
0.010
37.53
22.20
15.32
0.77
16.09
x
x
x
x

3610.76
1155.52
560.00
2713.20
954.86
8994.00
/ 1 No.

m
m
m
kg
kg
kg
kg
kg
Rs.

24
28
12

5969.26
1205.76
560.00
2713.20
954.86
11403.00
/ 1 No.

m
m
m
kg
kg
kg
kg
kg

x
x
x

2.4
2.2
0.018
628.87
537.34
91.53
4.58
96.10
Kg
x

Cost for 600mm dia flange


Outer dia of flange
780 mm
Inner dia of flange
600 mm
Thickness of flange
10 mm
weight of flange
(22/7)/4 x 0.78^2 x 0.01 x 7850
Deduct internal dia.
(22/7)/4 x 0.6^2 x 0.01 x 7850
add 5% wastage
total weight
cost of MS plate
machinning charges
Drilling holes
Cost of nuts and bolts including C.E.D
Cost of rubber insertions including C.E.D
Total

36000 / MT

Rs.

Cost for 2200mm dia flange


Outer dia of flange
2380 mm
Inner dia of flange
2200 mm
Thickness of flange
18.00 mm
weight of flange
(22/7)/4 x 2.38^2 x 0.018 x 7850
Deduct internal dia.
(22/7)/4 x 2.2^2 x 0.018 x 7850
add 5% wastage
total weight
cost of MS plate
machine cutting charges
Drilling holes
Cost of nuts and bolts including C.E.D
Cost of rubber insertions including C.E.D
Total

m
m
m
kg
kg
kg
kg
kg
Rs.

add 5% wastage
total weight
cost of MS plate
100.30
machine cutting charges
Drilling holes
28
Cost of nuts and bolts including C.E.D
28
Cost of rubber insertions including C.E.D
12
Total
a)

2.7
2.4
0.018
797.40
639.48
157.92
7.90
165.81
Kg
x

3459.69
1105.28
480.00
2713.20
954.86
8713.00
/ 1 No.

m
m
m
kg
kg
kg
kg
kg
36000 / MT
20 / No
96.90 / kg
79.57 / kg

Rs.
Rs.
Rs.
Rs.
Rs.
Rs

579.13
301.44
480.00
2325.60
795.72
4482.00
/ 1 No.

aarvee associates pvt ltd, Hyderabad

Data for MS Specials

PHED, Madhya Pradesh

2)

Air Valve Guard Cabins


Manufacturing ,Supplying and erection of air valve guard cabins of size 1.8x1.8x1.8 m made with 8 nos vertical and 8 nos
horizontal MS angles of size 70x70x6 mm and 10mm size MS square bars fixed at 5 cm c/c with door and locking
arrangements as per approved drawing and as directed by the departmental officers and painting both sides with anti
corrosive paint two coats over one coat of primary coat including cost of all materials , fabrication ,welding ,
transportation to site, all taxes and duties,fixing in position duly embodying in CC(1:2:4) prop , and all other incidental
and operational charges etc complete for finished item of work.
Cost of MS angle = 8x1.8mx6.38 Kgx4x2
Cost of 10mm size MS square rods = (1.8/0.05)x2x4
Cost of locking system =

734.976
288
10
1032.976
1040
1040
1040.00
2624.00

Say
36000 /MT x
Fabrication charges
6000 /MT x
Cost of CC (1:2:4) = 4x0.6mx
0.8640.6mx0.6
Cum
Labour charges for fixing etc;
Add for sundries
Total:
Rs.
46152.00 /each

3)

Kgs
Kgs
/Cum

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

37440.00
6240.00
2267.14
200.00
4.86
46152.00 /each

Manufacturing ,Supplying and erection of air valve guard cabins of size 1.2x1.2x1.5 m made with 8 nos vertical and 8 nos
horizontal MS angles of size 75x75x6 mm and 10mm size MS square bars fixed at 5 cm c/c with door and locking
arrangements as per approved drawing and as directed by the departmental officers and painting both sides with anti
corrosive paint two coats over one coat of primary coat including cost of all materials , fabrication ,welding ,
transportation to site, all taxes and duties,fixing in position duly embodying in CC(1:2:4) prop , and all other incidental
and operational charges etc complete for finished item of work.
Cost of MS angle = 8x1.2mx6.38 Kgx4x2
Cost of 10mm size MS square rods = (1.2/0.05)x2x4
Cost of locking system =

489.984
192
10
691.984
700
700
700.00
2624.00

Say
36000 /MT x
Fabrication charges
6000 /MT x
Cost of CC (1:2:4) = 4x0.6mx
0.8640.6mx0.6
Cum
Labour charges for fixing etc;
Add for sundries
Total:
Rs.
31872.03 /each

Pumping Main Reach -I

Kg/each
Kg/each
Kg/each

93

Kg/each
Kg/each
Kg/each
Kgs
Kgs
/Cum

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

25200.00
4200.00
2267.14
200.00
4.89
31872.03 /each

aarvee associates pvt ltd, Hyderabad

MS pipes Data
Old rate (M1)

43000

New Rate (M2)

Basic rate
including
Lowering,
Basic cost
Dia of
Outcoat Weight of the transportation Increase/
Laying,
Thickness Inlining
for present
Pipe
ing
pipe per Rmt
(As per AP
Decrease
jointing,
rate
SSR item no.
testing
14, pg.no. 75)
500
8
15
30
100.17
7488
100.17
7588.17
488.00

44000.00

Sub Total
for
material

Excise
Duty
14.42%

VAT @
4.00%

Sub Total Contractors


cost per
profit @
Sundries
Rmt
10%

8076.17

1094.21

347.30

9517.68

807.62

0.699

10326.00

Total Cost
per Rmt

600

15

30

119.89

8924

119.89

9043.89

600.00

9643.89

1304.13

413.92

11361.94

964.39

0.668

12327.00

700
700

8
10

15
15

30
30

139.61
175.01

10407
13015

139.61
175.01

10546.61
13190.01

697.00
697.00

11243.61
13887.01

1520.82
1902.00

482.70
603.68

13247.13
16392.69

1124.36
1388.70

0.508
0.612

14372.00
17782.00

800
800
800

8
10
12

15
15
16

30
30
31

159.33
199.66
240.18

11941
13859
16496

159.33
199.66
240.18

12100.33
14058.66
16736.18

795.00
795.00
795.00

12895.33
14853.66
17531.18

1744.87
2027.26
2413.36

553.81
643.44
765.98

15194.01
17524.35
20710.52

1289.53
1485.37
1753.12

0.460
0.282
0.364

16484.00
19010.00
22464.00

900
900
900

8
10
12

15
15
15

30
30
30

179.05
224.31
269.76

13325
15479
17638

179.05
224.31
269.76

13504.05
15703.31
17907.76

935.00
935.00
935.00

14439.05
16638.31
18842.76

1947.28
2264.42
2582.30

618.05
718.71
819.60

17004.39
19621.43
22244.66

1443.91
1663.83
1884.28

0.707
0.738
0.064

18449.00
21286.00
24129.00

1000
1000
1000
1000

8
10
12
14

15
15
15
16

30
30
30
31

198.77
248.95
299.34
349.92

14961
17344
19651
22790

198.77
248.95
299.34
349.92

15159.77
17592.95
19950.34
23139.92

1032.00
1032.00
1032.00
1032.00

16191.77
18624.95
20982.34
24171.92

2186.04
2536.90
2876.84
3336.78

693.83
805.19
913.09
1059.07

19071.64
21967.05
24772.26
28567.76

1619.18
1862.50
2098.23
2417.19

0.182
0.451
0.503
0.047

20691.00
23830.00
26871.00
30985.00

1100
1100
1100
1100
1100

8
10
12
14
16

15
15
15
16
17

30
30
30
31
32

218.49
273.60
328.92
384.43
440.13

17688
20309
22933.0
26603.0
30286.0

218.49
273.60
328.92
384.43
440.13

17906.49
20582.60
23261.92
26987.43
30726.13

1213.00
1213.00
1213.00
1213.00
1213.00

19119.49
21795.60
24474.92
28200.43
31939.13

2582.12
2968.01
3354.37
3891.59
4430.71

819.54
942.02
1064.65
1235.16
1406.27

22521.15
25705.64
28893.94
33327.17
37776.11

1911.95
2179.56
2447.49
2820.04
3193.91

0.903
0.800
0.572
0.784
0.972

24434.00
27886.00
31342.00
36148.00
40971.00

1200
1200
1200
1200
1200
1200

8
10
12
14
16
18

15
15
15
15
16
17

30
30
30
30
31
32

238.21
298.25
358.50
418.93
479.57
540.40

20019
22868
25729
28602
32554
36518

238.21
298.25
358.50
418.93
479.57
540.40

20257.21
23166.25
26087.50
29020.93
33033.57
37058.40

1359.00
1359.00
1359.00
1359.00
1359.00
1359.00

21616.21
24525.25
27446.50
30379.93
34392.57
38417.40

2921.09
3340.57
3761.82
4184.82
4763.44
5343.82

927.13
1060.27
1193.97
1328.23
1511.88
1696.09

25464.43
28926.10
32402.28
35892.98
40667.89
45457.32

2161.62
2452.53
2744.65
3037.99
3439.26
3841.74

0.950
0.375
0.066
0.023
0.851
0.944

27627.00
31379.00
35147.00
38931.00
44108.00
49300.00

1300
1300
1300
1300
1300
1300
1300

8
10
12
14
16
18
20

15
15
15
15
15
15
15

30
30
30
30
30
30
30

257.93
322.90
388.07
453.44
519.01
584.77
650.73

21852
24934
28029
31131
34247
38409
42583

257.93
322.90
388.07
453.44
519.01
584.77
650.73

22109.93
25256.90
28417.07
31584.44
34766.01
38993.77
43233.73

1561.00
1561.00
1561.00
1561.00
1561.00
1561.00
1561.00

23670.93
26817.90
29978.07
33145.44
36327.01
40554.77
44794.73

3188.25
3642.05
4097.74
4554.48
5013.26
5622.90
6234.30

1011.93
1155.96
1300.59
1445.56
1591.17
1784.67
1978.72

27871.11
31615.91
35376.41
39145.48
42931.44
47962.34
53007.76

2367.09
2681.79
2997.81
3314.54
3632.70
4055.48
4479.47

0.802
0.305
0.784
0.979
0.860
0.181
0.767

30239.00
34298.00
38375.00
42461.00
46565.00
52018.00
57488.00

1400
1400
1400
1400
1400
1400
1400

8
10
12
14
16
18
20

15
15
15
15
15
15
15

30
30
30
30
30
30
30

277.65
347.55
417.65
487.95
558.45
629.14
700.03

23236
26551
29878
33218
36564
41000
45450

277.65
347.55
417.65
487.95
558.45
629.14
700.03

23513.65
26898.55
30295.65
33705.95
37122.45
41629.14
46150.03

1797.00
1797.00
1797.00
1797.00
1797.00
1797.00
1797.00

25310.65
28695.55
32092.65
35502.95
38919.45
43426.14
47947.03

3390.67
3878.77
4368.63
4860.40
5353.06
6002.92
6654.83

1076.17
1231.09
1386.57
1542.65
1699.02
1905.28
2112.19

29777.49
33805.41
37847.86
41906.00
45971.52
51334.35
56714.06

2531.06
2869.56
3209.27
3550.30
3891.94
4342.61
4794.70

0.449
0.030
0.878
0.701
0.530
0.040
0.236

32309.00
36675.00
41058.00
45457.00
49864.00
55677.00
61509.00

1400

22

15

30

771.12

49912

771.12

50683.12

1797.00

52480.12

7308.51

2319.67

62108.29

5248.01

0.698

67357.00

1500
1500
1500
1500
1500
1500
1500
1500
1500

8
10
12
14
16
18
20
22
24

15
15
15
15
15
15
15
15
15

30
30
30
30
30
30
30
30
30

297.37
372.20
447.23
522.46
597.89
673.51
749.33
825.35
901.56

24869
28422
31978
35550
39130
42715
47341
51979
56630

297.37
372.20
447.23
522.46
597.89
673.51
749.33
825.35
901.56

25166.37
28794.20
32425.23
36072.46
39727.89
43388.51
48090.33
52804.35
57531.56

2065.00
2065.00
2065.00
2065.00
2065.00
2065.00
2065.00
2065.00
2065.00

27231.37
30859.20
34490.23
38137.46
41792.89
45453.51
50155.33
54869.35
59596.56

3628.99
4152.12
4675.72
5201.65
5728.76
6256.62
6934.63
7614.39
8296.05

1151.81
1317.85
1484.04
1650.96
1818.27
1985.81
2201.00
2416.75
2633.10

32012.17
36329.18
40649.99
44990.07
49339.91
53695.94
59290.95
64900.48
70525.72

2723.14
3085.92
3449.02
3813.75
4179.29
4545.35
5015.53
5486.93
5959.66

0.694
0.904
0.989
0.181
0.798
0.711
0.514
0.582
0.626

34736.00
39416.00
44100.00
48804.00
53520.00
58242.00
64307.00
70388.00
76486.00

1600
1600
1600
1600
1600
1600
1600
1600
1600
1600

8
10
12
14
16
18
20
22
24
26

15
15
15
15
15
15
15
15
15
15

30
30
30
30
30
30
30
30
30
30

317.08
396.85
476.81
556.97
637.32
717.88
798.63
879.57
960.72
1042.06

26268
30034
33829
37634
41446
45266
50162
55072
59993
64925

317.08
396.85
476.81
556.97
637.32
717.88
798.63
879.57
960.72
1042.06

26585.08
30430.85
34305.81
38190.97
42083.32
45983.88
50960.63
55951.57
60953.72
65967.06

2375.00
2375.00
2375.00
2375.00
2375.00
2375.00
2375.00
2375.00
2375.00
2375.00

28960.08
32805.85
36680.81
40565.97
44458.32
48358.88
53335.63
58326.57
63328.72
68342.06

3833.57
4388.13
4946.90
5507.14
6068.42
6630.88
7348.52
8068.22
8789.53
9512.45

1216.75
1392.76
1570.11
1747.92
1926.07
2104.59
2332.37
2560.79
2789.73
3019.18

34010.40
38586.74
43197.82
47821.03
52452.81
57094.34
63016.52
68955.58
74907.98
80873.69

2896.01
3280.58
3668.08
4056.60
4445.83
4835.89
5333.56
5832.66
6332.87
6834.21

0.591
0.679
0.103
0.372
0.358
0.770
0.921
0.759
0.152
0.102

36907.00
41868.00
46866.00
51878.00
56899.00
61931.00
68351.00
74789.00
81241.00
87708.00

1700
1700
1700
1700
1700
1700
1700
1700
1700
1700
1700

8
10
12
14
16
18
20
22
24
26
28

15
15
15
15
15
15
15
15
15
15
15

30
30
30
30
30
30
30
30
30
30
30

336.80
421.50
506.39
591.48
676.76
762.25
847.93
933.80
1019.88
1106.15
1192.62

27886
31901
35927
39964
44008
48065
53261
58470
63690
68923
74167

336.80
421.50
506.39
591.48
676.76
762.25
847.93
933.80
1019.88
1106.15
1192.62

28222.80
32322.50
36433.39
40555.48
44684.76
48827.25
54108.93
59403.80
64709.88
70029.15
75359.62

2730.00
2730.00
2730.00
2730.00
2730.00
2730.00
2730.00
2730.00
2730.00
2730.00
2730.00

30952.80 4069.73 1291.70


35052.50 4660.90 1479.34
39163.39 5253.69 1667.48
43285.48 5848.10 1856.14
47414.76 6443.54 2045.13
51557.25 7040.89 2234.73
56838.93 7802.51 2476.46
62133.80 8566.03 2718.79
67439.88 9331.16 2961.64
72759.15 10098.20 3205.09
78089.62 10866.86 3449.06

36314.23
41192.74
46084.57
50989.72
55903.44
60832.86
67117.89
73418.62
79732.68
86062.45
92405.53

3095.28
3505.25
3916.34
4328.55
4741.48
5155.72
5683.89
6213.38
6743.99
7275.91
7808.96

0.486
0.012
0.094
0.732
0.086
0.416
0.217
0.995
0.329
0.639
0.505

39410.00
44698.00
50001.00
55319.00
60645.00
65989.00
72802.00
79633.00
86477.00
93339.00
100215.00

1800
1800
1800
1800
1800
1800
1800
1800
1800
1800
1800
1800

8
10
12
14
16
18
20
22
24
26
28
30

15
15
15
15
15
15
15
15
15
15
15
15

30
30
30
30
30
30
30
30
30
30
30
30

356.52
446.15
535.97
625.99
716.20
806.61
897.22
988.03
1079.03
1170.24
1261.63
1353.23

29519
33767
38028
42300
46573
50864
55162
60548
65947
71355
76777
82209

356.52
446.15
535.97
625.99
716.20
806.61
897.22
988.03
1079.03
1170.24
1261.63
1353.23

29875.52
34213.15
38563.97
42925.99
47289.20
51670.61
56059.22
61536.03
67026.03
72525.24
78038.63
83562.23

3141.00
3141.00
3141.00
3141.00
3141.00
3141.00
3141.00
3141.00
3141.00
3141.00
3141.00
3141.00

33016.52 4308.05 1367.34 38691.92


37354.15 4933.54 1565.87 43853.55
41704.97 5560.92 1765.00 49030.89
46066.99 6189.93 1964.64 54221.55
50430.20 6819.10 2164.33 59413.64
54811.61 7450.90 2364.86 64627.38
59200.22 8083.74 2565.72 69849.68
64677.03 8873.50 2816.38 76366.91
70167.03 9665.15 3067.65 82899.84
75666.24 10458.14 3319.33 89443.71
81179.63 11253.17 3571.67 96004.48
86703.23 12049.67 3824.48 102577.38

3301.65
3735.41
4170.50
4606.70
5043.02
5481.16
5920.02
6467.70
7016.70
7566.62
8117.96
8670.32

0.431
0.035
0.616
0.752
0.344
0.462
0.295
0.390
0.460
0.666
0.559
0.297

41994.00
47589.00
53202.00
58829.00
64457.00
70109.00
75770.00
82835.00
89917.00
97011.00
104123.00
111248.00

1900
1900
1900
1900
1900
1900
1900
1900

8
10
12
14
16
18
20
22

14
15
15
15
15
15
15
15

29
30
30
30
30
30
30
30

376.24
470.80
565.55
660.49
755.64
850.98
946.52
1042.26

29966
35385
39874
44377
48890
53414
57941
63595

376.24
470.80
565.55
660.49
755.64
850.98
946.52
1042.26

30342.24
35855.80
40439.55
45037.49
49645.64
54264.98
58887.52
64637.26

3612.00
3612.00
3612.00
3612.00
3612.00
3612.00
3612.00
3612.00

33954.24
39467.80
44051.55
48649.49
53257.64
57876.98
62499.52
68249.26

3395.42
3946.78
4405.15
4864.95
5325.76
5787.70
6249.95
6824.93

0.278
0.971
0.079
0.873
0.513
0.710
0.782
0.805

43114.00
50227.00
56139.00
62071.00
68015.00
73974.00
79937.00
87354.00

4375.35
5170.41
5831.38
6494.41
7158.90
7825.01
8491.58
9320.69

1388.70
1641.05
1850.84
2061.28
2272.18
2483.60
2695.16
2958.32

39718.30
46279.25
51733.77
57205.18
62688.72
68185.59
73686.27
80528.27

1900
1900
1900
1900
1900

24
26
28
30
32

15
15
15
15
15

30
30
30
30
30

1138.19
1234.32
1330.65
1427.18
1523.90

69260
74937
80625
86325
92034

1138.19
1234.32
1330.65
1427.18
1523.90

70398.19
76171.32
81955.65
87752.18
93557.90

3612.00
3612.00
3612.00
3612.00
3612.00

74010.19
79783.32
85567.65
91364.18
97169.90

10151.42
10983.90
11818.00
12653.86
13491.05

3221.98 87383.60
3486.21 94253.44
3750.95 101136.60
4016.24 108034.28
4281.96 114942.91

7401.02
7978.33
8556.77
9136.42
9716.99

0.385
0.230
0.632
0.300
0.103

94785.00
102232.00
109694.00
117171.00
124660.00

2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000

8
10
12
14
16
18
20
22
24
26
28
30
32
34

15
15
15
15
15
15
15
15
15
15
15
15
15
15

30
30
30
30
30
30
30
30
30
30
30
30
30
30

395.96
495.44
595.13
695.00
795.08
895.35
995.82
1096.49
1197.35
1298.41
1399.67
1501.12
1602.78
1704.63

31340
37002
41728
46462
51207
55964
60723
65459
71282
77115
82962
88818
94687
100565

395.96
495.44
595.13
695.00
795.08
895.35
995.82
1096.49
1197.35
1298.41
1399.67
1501.12
1602.78
1704.63

31735.96
37497.44
42323.13
47157.00
52002.08
56859.35
61718.82
66555.49
72479.35
78413.41
84361.67
90319.12
96289.78
102269.63

4154.00
4154.00
4154.00
4154.00
4154.00
4154.00
4154.00
4154.00
4154.00
4154.00
4154.00
4154.00
4154.00
4154.00

35889.96
41651.44
46477.13
51311.00
56156.08
61013.35
65872.82
70709.49
76633.35
82567.41
88515.67
94473.12
100443.78
106423.63

4576.33
5407.13
6102.99
6800.04
7498.70
8199.12
8899.85
9597.30
10451.52
11307.21
12164.95
13024.02
13884.99
14747.28

1452.49
1716.18
1937.04
2158.28
2380.03
2602.34
2824.75
3046.11
3317.23
3588.82
3861.06
4133.73
4406.99
4680.68

41918.78
48774.76
54517.16
60269.32
66034.81
71814.81
77597.42
83352.90
90402.11
97463.45
104541.69
111630.87
118735.75
125851.58

3589.00
4165.14
4647.71
5131.10
5615.61
6101.34
6587.28
7070.95
7663.33
8256.74
8851.57
9447.31
10044.38
10642.36

0.225
0.096
0.123
0.575
0.583
0.858
0.298
0.153
0.558
0.809
0.747
0.820
0.869
0.055

45508.00
52940.00
59165.00
65401.00
71651.00
77917.00
84185.00
90424.00
98066.00
105721.00
113394.00
121079.00
128781.00
136494.00

2100
2100
2100
2100
2100
2100
2100
2100
2100
2100
2100
2100
2100
2100
2100

8
10
12
14
16
18
20
22
24
26
28
30
32
34
36

15
15
15
15
15
15
15
15
15
15
15
15
15
15
15

30
30
30
30
30
30
30
30
30
30
30
30
30
30
30

415.68
520.09
624.70
729.51
834.52
939.72
1045.12
1150.71
1256.51
1362.50
1468.69
1575.07
1681.65
1788.43
1895.41

32921
38867
43827
48784
53773
58760
63755
68764
74878
81004
87141
93287
99447
105617
111798

415.68
520.09
624.70
729.51
834.52
939.72
1045.12
1150.71
1256.51
1362.50
1468.69
1575.07
1681.65
1788.43
1895.41

33336.68
39387.09
44451.70
49513.51
54607.52
59699.72
64800.12
69914.71
76134.51
82366.50
88609.69
94862.07
101128.65
107405.43
113693.41

4778.00
4778.00
4778.00
4778.00
4778.00
4778.00
4778.00
4778.00
4778.00
4778.00
4778.00
4778.00
4778.00
4778.00
4778.00

38114.68
44165.09
49229.70
54291.51
59385.52
64477.72
69578.12
74692.71
80912.51
87144.50
93387.69
99640.07
105906.65
112183.43
118471.41

4807.15
5679.62
6409.94
7139.85
7874.40
8608.70
9344.18
10081.70
10978.60
11877.25
12777.52
13679.11
14582.75
15487.86
16394.59

1525.75
1802.67
2034.47
2266.13
2499.28
2732.34
2965.77
3199.86
3484.52
3769.75
4055.49
4341.65
4628.46
4915.73
5203.52

44447.58
51647.38
57674.11
63697.49
69759.20
75818.75
81888.07
87974.27
95375.63
102791.50
110220.69
117660.83
125117.86
132587.03
140069.52

3811.47
4416.51
4922.97
5429.15
5938.55
6447.77
6957.81
7469.27
8091.25
8714.45
9338.77
9964.01
10590.67
11218.34
11847.14

0.949
0.109
0.924
0.354
0.251
0.474
0.122
0.456
0.122
0.053
0.541
0.164
0.473
0.629
0.340

48260.00
56064.00
62598.00
69127.00
75698.00
82267.00
88846.00
95444.00
103467.00
111506.00
119560.00
127625.00
135709.00
143806.00
151917.00

2200
2200
2200
2200
2200
2200
2200
2200

8
10
12
14
16
18
20
22

15
15
15
15
15
15
15
15

30
30
30
30
30
30
30
30

435.40
544.74
654.28
764.02
873.95
984.09
1094.42
1204.94

34293
40485
45678
50877
56089
61307
66538
71780

435.40
544.74
654.28
764.02
873.95
984.09
1094.42
1204.94

34728.40
41029.74
46332.28
51641.02
56962.95
62291.09
67632.42
72984.94

5494.00
5494.00
5494.00
5494.00
5494.00
5494.00
5494.00
5494.00

40222.40 5007.84
46523.74 5916.49
51826.28 6681.12
57135.02 7446.64
62456.95 8214.06
67785.09 8982.37
73126.42 9752.59
78478.94 10524.43

1589.45
1877.85
2120.54
2363.51
2607.08
2850.94
3095.40
3340.37

46819.68
54318.08
60627.93
66945.16
73278.09
79618.40
85974.41
92343.75

4022.24
4652.37
5182.63
5713.50
6245.70
6778.51
7312.64
7847.89

0.075
0.545
0.437
0.336
0.211
0.092
0.948
0.361

50842.00
58971.00
65811.00
72659.00
79524.00
86397.00
93288.00
100192.00

Wall
Thick
B, m D, m Footing Thick ness

L, m
Clear dimensions
1.5

1.5

1.50

0.15

0.20

Ave.Dia
0.2

Detailed estimate for


Sluice valve (300 - 600mm dia) chamber
Sluice Valve Chamber (1.5 x 1.5 x 1.5 m)
Sl.No.

Description

Earth work excavation & depositing on bank with


initial lead of 50m and lift of 3m in all soils by
manual means

cum

2.20

2.20

1.65

7.99

Laying Cement concrete ( 1: 4 : 8) using 40mm


nominal size graded HBG metal including cost of
all materials and labour charges etc. complete- In
foundation and Plinth

cum

2.20

2.20

0.15

0.73

V R.C.C. M30 Grade using 20 mm HBG Down


graded metal including centring charges, laying ,
levelling , machine mixing but exculding cost of
steel in reinforcement, etc complete as per SS up to
150mm thick Slab
For slab of Valve pit
Deduct for Opening

1
1

cum
cum

1.90
1.80

1.90
1.80

0.15
0.15

0.54
-0.49
0.06

Supply and delivery of Steel Reinforcement


H.Y.S.D.confirming to I.S.S. including cost &
conveyance of all materials , cost of binding wire
and its fabrication charges, placing in position tying
grills etc., complete.

kg

2
2
2

cum
cum
cum
cum

Nos. Unit L(m)

B(m)

D(m)

Quantity

187

@ 90 kg / cum of RCC
5

V R.C.C. M30 Grade using 20 mm HBG Down


graded metal including centring charges, laying ,
levelling , machine mixing but exculding cost of
steel in reinforcement, etc complete as per SS for
Side walls of valve chamber
a) Long wall
b) Short wall
c) Deduct for pipes
Total

1.90
0.20
1.50
1.50
0.20
1.50
0.23 (pi/4)*0.2^2

1.14
0.90
0.01
2.03

Manufacture as per BIS: 12592(part- 1&2), Supply


& and delivery of Manhole Covers and frames with
ISI marking any where in A.P., F.O.R destination
including, loading, unloading & stacking at site
including Central Excise Duty, Sales Tax, Octroi
and other Govt levies etc, as applicabe - For Cover
Slabs of Valve Chamber

No.

No.

1.00

Collection , supply & filling sand including watering,


tamping, etc complete, plinth sites of foundation in
layers not exceeding 20cm in depth including
consolidation of each layer by ramming, watering,
lead upto 50m and lift upto 1.5m in all kinds of soil
Qty of Earth excavated
Deduct

1.90

1.90

1.50

7.99
-5.42
2.57

Carting away the surplus excavated earth from the


work site with a lead of 0.5 km beyond initial lead
including loading, unloading and conveyance but
excluding stacking charges etc., complete - 1 cum
Qty. Excavated
Qty. Refilled back
Qty. to be conveyed

7.99
-2.57
5.42

L, m

Wall
Thickne
B, m D, m Footing Thick ss

1.2

1.2

1.20

0.15

0.20

Detailed estimate for


Sluice valve (200mm to 250m dia) chamber
Sluice Valve Chamber (1.2 x 1.2 x 1.2 m)
Sl.No.

Description

Earth work excavation & depositing on bank with initial

Nos. Unit L(m) B(m)

D(m)

lead of 50m and lift of 3m in all soils by manual means

cum

1.90

1.90

1.35

Laying Cement concrete ( 1: 4 : 8) using 40mm


nominal size graded HBG metal including cost of all
materials and labour charges etc. complete- In
foundation and Plinth

cum

1.90

1.90

0.15

V R.C.C. M30 Grade using 20 mm HBG Down graded


metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS up to 150mm
thick Slab
For slab of Valve pit
Deduct for Opening

1
1

cum
cum

1.60
1.80

1.60
1.80

0.15
0.15

Supply and delivery of Steel Reinforcement


H.Y.S.D.confirming to I.S.S.
including cost &
conveyance of all materials , cost of binding wire and its
fabrication charges, placing in position tying grills etc.,
complete.

kg

2
2
2

cum
cum
cum
cum

@ 80 kg / cum of RCC
5

V R.C.C. M30 Grade using 20 mm HBG Down graded


metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS for Side walls of
valve chamber
a) Long wall
b) Short wall
c) Deduct for pipes
Total

1.60
0.20
1.20
1.20
0.20
1.20
0.23 (pi/4)*0.15^2

Manufacture as per BIS: 12592(part- 1&2), Supply &


and delivery of Manhole Covers and frames with ISI
marking any where in A.P., F.O.R destination including,
loading, unloading & stacking at site including Central
Excise Duty, Sales Tax, Octroi and other Govt levies
etc, as applicabe - For Cover Slabs of Valve Chamber

No.

No.

Collection , supply & filling sand including watering,


tamping, etc complete, plinth sites of foundation in
layers not exceeding 20cm in depth including
consolidation of each layer by ramming, watering, lead
upto 50m and lift upto 1.5m in all kinds of soil
Qty of Earth excavated
Deduct

Carting away the surplus excavated earth from the


work site with a lead of 0.5 km beyond initial lead
including loading, unloading and conveyance but
excluding stacking charges etc., complete - 1 cum
Qty. Excavated
Qty. Refilled back
Qty. to be conveyed

1.60

1.60

1.20

Ave.Dia
0.15

L, m

B, m D, m Footing Thick

0.9

0.9

1.00

0.15

Detailed estimate for


Sluice valve (80 - 150mm dia) chamber
Sluice Valve Chamber (0.9 x 0.9 x 1 m)
Quantity

Sl.No.

Description

Earth work excavation & depositing on bank with


initial lead of 50m and lift of 3m in all soils by manual
means

cum

1.60

1.60

Laying Cement concrete ( 1: 4 : 8) using 40mm


nominal size graded HBG metal including cost of all
materials and labour charges etc. complete- In
foundation and Plinth

cum

1.60

1.60

V R.C.C. M30 Grade using 20 mm HBG Down


graded metal including centring charges, laying ,
levelling , machine mixing but exculding cost of steel
in reinforcement, etc complete as per SS up to
150mm thick Slab
For slab of Valve pit
Deduct for Opening

1
1

cum
cum

1.25
1.80

1.25
1.80

Supply and delivery of Steel Reinforcement


H.Y.S.D.confirming to I.S.S. including cost &
conveyance of all materials , cost of binding wire and
its fabrication charges, placing in position tying grills
etc., complete.

kg

2
2
2

cum
cum
cum
cum

4.87
2

0.54
3

0.38
-0.49
-0.10
4

138

Nos. Unit L(m) B(m)

@ 65 kg / cum of RCC
5

0.77
0.58
0.01
1.34

V R.C.C. M30 Grade using 20 mm HBG Down


graded metal including centring charges, laying ,
levelling , machine mixing but exculding cost of steel
in reinforcement, etc complete as per SS for Side
walls of valve chamber
a) Long wall
b) Short wall
c) Deduct for pipes
Total

1.25
0.20
0.90
0.20
0.23 (pi/4)*0.1^2

1.00
7

4.87
-3.07
1.80

Manufacture as per BIS: 12592(part- 1&2), Supply &


and delivery of Manhole Covers and frames with ISI
marking any where in A.P., F.O.R destination
including, loading, unloading & stacking at site
including Central Excise Duty, Sales Tax, Octroi and
other Govt levies etc, as applicabe - For Cover Slabs
of Valve Chamber

Carting away the surplus excavated earth from the


work site with a lead of 0.5 km beyond initial lead
including loading, unloading and conveyance but

4.87
-1.80
3.07

No.

No.

Collection , supply & filling sand including watering,


tamping, etc complete, plinth sites of foundation in
layers not exceeding 20cm in depth including
consolidation of each layer by ramming, watering,
lead upto 50m and lift upto 1.5m in all kinds of soil
Qty of Earth excavated
Deduct

excluding stacking charges etc., complete - 1 cum


Qty. Excavated
Qty. Refilled back
Qty. to be conveyed

1.25

1.25

Wall
Thickne
ss
0.18

D(m)

Ave.Dia
0.1

Quantity

1.15

2.94

0.15

0.38

0.15
0.15

0.23
-0.49
-0.25

71

1.00
1.00
(pi/4)*0.1^2

0.50
0.36
0.00
0.86

1.00

1.00

2.94
-1.56
1.38

2.94
-1.38
1.56

Length
3.60

Bredth
3.60

Depth
3.60

Sluice valve (300 - 600mm dia) chamber


Sluice Valve Chamber (1.5 x 1.5 x 1.5 m)
Sl.No.
Description of work
1

Quantity

Unit

Rate (Rs.)

Earth work excavation & depositing on bank with initial


lead of 50m and lift of 3m in all soils by manual means

Laying Cement concrete ( 1: 4 : 8) using 40mm nominal


size graded HBG metal including cost of all materials
and labour charges etc. complete- In foundation and
Plinth
V R.C.C. M30 Grade using 20 mm HBG Down graded
metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS up to 150mm
thick Slab

7.99 cum

#REF!

0.73 Cum

3363.59

0.06 Cum
0.54

#REF!

Supply
and
delivery
of
Steel
Reinforcement
H.Y.S.D.confirming to I.S.S. including cost & conveyance
of all materials , cost of binding wire and its fabrication
charges, placing in position tying grills etc., complete.
187.29 kg

V R.C.C. M30 Grade using 20 mm HBG Down graded


metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS for Side walls of
valve chamber
Manufacture as per BIS: 12592(part- 1&2), Supply & and
delivery of Manhole Covers and frames with ISI marking
any where in A.P., F.O.R destination including, loading,
unloading & stacking at site including Central Excise
Duty, Sales Tax, Octroi and other Govt levies etc, as
applicabe - For Cover Slabs of Valve Chamber
Collection , supply & filling sand including watering,
tamping, etc complete, plinth sites of foundation in layers
not exceeding 20cm in depth including consolidation of
each layer by ramming, watering, lead upto 50m and lift
upto 1.5m in all kinds of soil

53.49

2.03 Cum

#REF!

1.00 Cum

2338.75

2.57 Cum

484.86

5.42 Cum

72.39

Carting away the surplus excavated earth from the work


site with a lead of 0.5 km beyond initial lead including
loading, unloading and conveyance but excluding
stacking charges etc., complete - 1 cum
TOTAL COST
Say

Length
3.00

Bredth
3.00

Sluice valve (200 - 250mm dia) chamber

Sl.No.
Amount (Rs.)

Description of work
1

Earth work excavation & depositing on bank with initial lead


of 50m and lift of 3m in all soils by manual means

#REF!

4.87
2

Laying Cement concrete ( 1: 4 : 8) using 40mm nominal size


graded HBG metal including cost of all materials and labour
charges etc. complete- In foundation and Plinth

2,441.97

0.54
3

V R.C.C. M30 Grade using 20 mm HBG Down graded metal


including centring charges, laying , levelling , machine
mixing but exculding cost of steel in reinforcement, etc
complete as per SS up to 150mm thick Slab

#REF!

-0.10
4

Supply
and
delivery
of
Steel
Reinforcement
H.Y.S.D.confirming to I.S.S. including cost & conveyance of
all materials , cost of binding wire and its fabrication charges,
placing in position tying grills etc., complete.

10,018.18

138
5

V R.C.C. M30 Grade using 20 mm HBG Down graded metal


including centring charges, laying , levelling , machine
mixing but exculding cost of steel in reinforcement, etc
complete as per SS for Side walls of valve chamber

#REF!

1.34
6

2,338.75
7

1,246.57
8

391.99
#REF!
#REF!

Quantity

Manufacture as per BIS: 12592(part- 1&2), Supply & and


delivery of Manhole Covers and frames with ISI marking any
where in A.P., F.O.R destination including, loading,
unloading & stacking at site including Central Excise Duty,
Sales Tax, Octroi and other Govt levies etc, as applicabe For Cover Slabs of Valve Chamber
Collection , supply & filling sand including watering, tamping,
etc complete, plinth sites of foundation in layers not
exceeding 20cm in depth including consolidation of each
layer by ramming, watering, lead upto 50m and lift upto 1.5m
in all kinds of soil
Conveyance
of
excavated
earth
,loose
moorum/sand/earth/surkhi/cement/stone
dust/hot
mix
asphalt materials etc, from the site of work to a lead of 5.0
km including loading , unloading and levelling the soil as per
the directions of the departmental author
TOTAL COST

1.00

1.80

3.07

Depth
3.00

mm dia) chamber

='Valve pit Det'!V5:AC5


Sluice Valve Chamber (2.4 x 2.4 x 2.4 m)

Unit

Rate (Rs.)

Amount
(Rs.)

Sl.No.

1
Cum

#REF!

#REF!
2

Cum

3363.59

1,821.38
3

Cum

#REF!

#REF!
4

kg

53.49

7,359.52
5

Cum

#REF!

#REF!
6

cum

2338.75

2,338.75
7

Cum

484.86

873.47
8

Cum

72.39
Say

222.38
#REF!
#REF!

Length
2.4

Bredth Depth
2.4
2.4
='Valve pit Det'!V5:AC5

Sluice Valve Chamber (2.4 x 2.4 x 2.4 m)

Description of work

Quantity Unit Rate (Rs.)

Amount
(Rs.)

Earth work excavation & depositing on bank with initial


lead of 50m and lift of 3m in all soils by manual means
2.94 Cum

#REF!

#REF!

0.38 Cum

3363.59

1,291.62

#REF!

#REF!

Laying Cement concrete ( 1: 4 : 8) using 40mm nominal


size graded HBG metal including cost of all materials and
labour charges etc. complete- In foundation and Plinth

V R.C.C. M30 Grade using 20 mm HBG Down graded


metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS up to 150mm thick
Slab

-0.25 Cum

Supply
and
delivery
of
Steel
Reinforcement
H.Y.S.D.confirming to I.S.S. including cost & conveyance
of all materials , cost of binding wire and its fabrication
charges, placing in position tying grills etc., complete.
71 kg
V R.C.C. M30 Grade using 20 mm HBG Down graded
metal including centring charges, laying , levelling ,
machine mixing but exculding cost of steel in
reinforcement, etc complete as per SS for Side walls of
valve chamber
Manufacture as per BIS: 12592(part- 1&2), Supply & and
delivery of Manhole Covers and frames with ISI marking
any where in A.P., F.O.R destination including, loading,
unloading & stacking at site including Central Excise Duty,
Sales Tax, Octroi and other Govt levies etc, as applicabe For Cover Slabs of Valve Chamber
Collection , supply & filling sand including watering,
tamping, etc complete, plinth sites of foundation in layers
not exceeding 20cm in depth including consolidation of
each layer by ramming, watering, lead upto 50m and lift
upto 1.5m in all kinds of soil
Conveyance
of
excavated
earth
,loose
moorum/sand/earth/surkhi/cement/stone
dust/hot
mix
asphalt materials etc, from the site of work to a lead of 5.0
km including loading , unloading and levelling the soil as
per the directions of the departmental author
TOTAL COST

53.49

3,792.34

0.86 Cum

#REF!

#REF!

1.00 Cum

2338.75

2,338.75

1.38 Cum

484.86

669.83

1.56 Cum

72.39

113.11
#REF!
#REF!

Say

JANGAREDDYGUDEM NAGARPANCHAYAT
Material Lead Statement for 2014-15
Sl. No.

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29

Source (name of
quarry)

Description

Unit

Cost at
source

Cost of Cement OPC


Cost of Sand for Mortor Concrete Items
Cost of Sand for Motor
Cost of Sand for filling

Local
Jalleru
Jalleru
Jalleru

1 Cum
1 Cum
1 Cum

4000.00
462.00
606.00
342.00

Aggregates 6 mm Nominal size

EGK Road

1 Cum

735.00

Aggregates 10 mm Nominal size

EGK Road

1 Cum

935.00

Aggregates 13.2/12.5 mm Nominal size

EGK Road

1 Cum

1097.00

Aggregates 20 mm Nominal size

EGK Road

1 Cum

1365.00

Aggregates 25 mm Nominal size

EGK Road

1 Cum

1313.00

Aggregates 40 mm Nominal size

EGK Road

1 Cum

845.00

Aggregates below 5.6mm

EGK Road

1 Cum

557.00

Aggregates 22.4 mm to 2.36mm

EGK Road

1 Cum

914.00

Aggregates 22.4 mm to 5.60 mm

EGK Road

1 Cum

1040.00

Aggregates 45 mm to 22.4 mm

EGK Road

1 Cum

1145.00

Aggregates 63 mm to 45 mm

EGK Road

1 Cum

662.00

Aggregates 11.2 mm to 0.09 mm

EGK Road

1 Cum

704.00

Aggregates 13.2 mm to 0.09 mm

EGK Road

1 Cum

798.00

Aggregates 13.2 mm to 5.6 mm

EGK Road

1 Cum

919.00

Aggregates 53 mm to 22.4 mm

EGK Road

1 Cum

872.00

Aggregates10 mm to 5 mm

EGK Road

1 Cum

875.00

Aggregates 25 mm to 10 mm

EGK Road

1 Cum

1129.00

Aggregates Below 5.6 mm

EGK Road

1 Cum

557.00

Cost of Gravel

janampeta

1 Cum

103.00

Cost of Stone Dust/


Quarry rubbish
Cost of Steel
Bitumen Conveyance(80/100)
Bitumen Conveyance(60/70)
Cost of Bricks
20 MM HBG Metal (Graded)

EGK Road

1 Cum.
1 Cum.
1 MT
1MT
1MT

357.00
81.00
44000
41652.88
42614.01

Local
Vizag
Vizag

0.70 cm
0.10 cm
0.10 cm
0.10 cm

20mmHBG Metal
12mmHBG Metal
10 mm HBG Metal
6 mm HBG Metal

20 MM HBG Metal (Graded

Assistant Engineer (FAC),

ANCHAYAT
2014-15
Lead in
K.M.

Deduct 14
Conveyan
%
ce
contractor
Charges
profit

Seigncharges

Total Rate.

7.00
7.00
7.00

109.30
109.30
109.30

13.42
13.42
13.42

40.00
40.00
40.00

4000.00
597.88
741.88
477.88

45.00

556.60

68.35

50.00

1273.25

45.00

556.60

68.35

50.00

1473.25

45.00

556.60

68.35

50.00

1635.25

45.00

556.60

68.35

50.00

1903.25

45.00

556.60

68.35

50.00

1851.25

45.00

556.60

68.35

50.00

1383.25

45.00

556.60

68.35

50.00

1095.25

45.00

556.60

68.35

50.00

1452.25

45.00

556.60

68.35

50.00

1578.25

45.00

556.60

68.35

50.00

1683.25

45.00

556.60

68.35

50.00

1200.25

45.00

556.60

68.35

50.00

1242.25

45.00

556.60

68.35

50.00

1336.25

45.00

556.60

68.35

50.00

1457.25

45.00

556.60

68.35

50.00

1410.25

45.00

556.60

68.35

50.00

1413.25

45.00

556.60

68.35

50.00

1667.25

45.00

556.60

68.35

50.00

1095.25

84.10

10.33

22.00

198.77

45.00
45.00

556.60
556.60

68.35
68.35

50.00
50.00

895.25
619.25
44.00
42462.88
43424.01

540
540
20mmHBG Metal
12mmHBG Metal
10 mm HBG Metal
6 mm HBG Metal

810
810

1903.25
1635.25
1473.25
1273.25
20 MM HBG Metal (Graded)

1332.27
163.52
147.32
127.32
1770.45

Commissioner,

Sand
Lead - 7 Kms
1 - 5 Kms =
84.1
6 - 7 Kms =
2 x 12.6

Aggregates
Lead - 45 Kms
1 - 5 Kms =
84.1
6 - 30 Kms=
25 x 12.6
31 - 45 Kms
=
15 x 10.5

Aggregates
Lead - 540 Kms
1 - 5 Kms =
84.1
6 - 30 Kms=
25 x 12.6
31 - 540 Kms
=
510 x 10.5

84.1
25.2
109.3

84.1
315
157.5
556.6

84.1
315
5355
5754.1

You might also like