You are on page 1of 11

2 Probabilistic power system reliability

analysis
1

2.1 Introduction
The reliability of power systems has been studied for many years. Throughout the
years, many different methods, concepts and techniques have emerged. This chapter
gives an overview of the current state of probabilistic reliability analysis.
This chapter begins with a description of the basic concepts and methods of
probabilistic reliability analysis in sections 2.2 and 2.3. Then, section 2.4 describes
the different applications of probabilistic reliability analysis.
2.2 Basic concepts
For the reliability analysis of the power system, both deterministic and probabilistic
methods can be used. In deterministic methods, criteria are given for the occurrence
of certain events. For example, the n-1 criterion states that in system operation, a
single failure must not develop into a significant failure of the system. Such a
criterion does not say anything about the probability of occurrence of the individual
events. In probabilistic reliability analysis, these probabilities are taken into account.
In this way, situations with low probability are no longer overestimated and complex
situations that were not considered in the deterministic methods can be revealed.

The concept of system reliability is a general concept that is used to indicate the
ability of a system to fulfil its function. In probabilistic power system reliability,
reliability is divided into two main fields as shown in figure 2.1 [1]. The system
security refers to the ability of the system to respond to disturbances arising within
that system. System adequacy is the existence of sufficient facilities within the system
to fulfil its function. System security is therefore more related to system dynamics
while system adequacy is more related to the steady state of the system.

Figure 2.1: Subdivision of system reliability [2].

As the power system is a complex system, it is divided into several hierarchical
levels for reliability studies, illustrated in figure 2.2. The first level consists of the
generation system, the second level is the transmission network and the third level is
the distribution system. Most studies are mainly devoted to one hierarchical level,

1
B.W.Tuinema (PhD-researcher: Power System Reliability, b.w.tuinema@tudelft.nl)

while assumptions are made for the other hierarchical levels. In some research, an
additional hierarchical level, i.e. HL0, the availability of energy resources, is defined.

Figure 2.2: Hierarchical levels [2].
2.3 Methods for probabilistic reliability analysis
Different methods have been developed for the reliability analysis of power systems.
Some of these methods resulted from general reliability analysis or mathematics,
while other methods have been developed with the application for power systems in
mind. This section describes some of the reliability methods and indices that are used
for probabilistic reliability analysis of power systems. A more detailed description of
the different methods is given in power system reliability literature like [1] and [3].
2.3.1 Methods for components and small parts of the system
A basic reliability model is the stress-strength model as shown in figure 2.3. It
shows the probabilistic distribution of the strength of a component and the stress on
that component. The area where the stress on the component is higher than the
strength of the component is the area where failures occur. In the power system, this
model can represent the reliability of the generation system. The available capacity of
the generation system has a certain probabilistic distribution (system strength), while
the load has another distribution (system stress). When the load is higher than the
available generation capacity, system failures occur. The probability of a system
failure can be calculated with a mathematical convolution.

800 1000 1200 1400 1600 1800
0
1
2
3
4
5
x 10
-3
Stress-Strength Model
Stress Strength
Failures

Figure 2.3: Stress-Strength model.

A second model that is often used in reliability analysis is the Markov model. In its
simplest form, the Markov model consists of an UP and a DOWN state, like in figure
2.4. The Markov model gives information about the probability of the system states
(P
UP
and P
DOWN
), de failure rate () and the repair rate (). Mostly, this simple
Markov model is used to represent the failure behaviour of single components within
the system.


Figure 2.4: Simple two-state model [1].

The Markov model can be expanded with additional states like derated or
maintenance states. The Markov models of different components can be combined
into a Markov model for a small part of the system. Figure 2.5 gives an example of a
Markov model for a system that consists of two components and one additional spare.
As Markov models become complex for larger systems, Markov models are mainly
used for single components or a small group of system components.



Figure 2.5: More advanced state model.
The representation of components in the two-state Markov model results in a certain
availability (A=P
UP
) and unavailability (U=P
DOWN
). A network of components then
gives a reliability network in which the components are described by their
availability/unavailability, like in figure 2.6. With simple mathematics, the reliability
of the complete network can be calculated. This method is especially suitable for
radial networks, but can also effectively be used for other parts of the power system.
Figure 2.7 gives an example of a radial distribution network.


Figure 2.6: Series/parallel connection.

Figure 2.7: Radial distribution network.
System outages can be the result of various causes. In some systems, these various
causes can not be represented by simple reliability models. In these cases, an
investigation of the different failure modes that lead to a system failure has to be
performed. The result can then be presented as a fault tree, like done in figure 2.9 for
the typical substation configuration shown in figure 2.8. This method can effectively
be used for the study of substations, where the different failure modes of the breakers
and switches have to be analysed.


Figure 2.8: Typical substation configuration.

Figure 2.9: Fault tree analysis.
2.3.2 Methods for larger systems
For larger systems, the combination of the states of all the different components
would lead to an extremely complicated model with a huge amount of system states.
Therefore, special reliability methods exist for larger systems. In these methods, a
selection is made of the possible system states that is assumed to be representative for
the overall reliability behaviour. The two main approaches for this are state
enumeration and Monte Carlo simulation.
In state enumeration, the states are defined according to their order of failure. This
process is illustrated in figure 2.10. The lower-order states, with less component
failures and a higher probability, are selected first. Then the higher-order states, with
more component failures and a lower probability, are selected. It is assumed that the
lowest-order states, with the highest probability, are representative for the reliability
of the system. State enumeration is mainly used in systems with low failure

probabilities and when no additional information like probability distributions or
switching sequence information is required.

Figure 2.10: State enumeration.
In a Monte Carlo simulation, the reliability of the system is determined by
performing a simulation of the system. In this simulation, different random system
states are defined. It is assumed that these random states are a sufficient representation
for the reliability of the system. In order to be representative, the simulation has to
simulate many system years. Monte Carlo simulation is mainly used in systems where
more complicated failure combinations contribute to the system reliability and when
additional information like probability distributions or switching sequence
information is required.

Figure 2.11: Monte-Carlo Simulation.
In both methods, the defined states can be studied by performing a load flow,
executing remedial actions and determining the load curtailment. From this, different
reliability indices and the reliability of the complete system can be calculated.


The methods that were described in this section can now be summarised by table 2.1.

Table 2.1: Methods for probabilistic reliability analysis
Components and small systems Large systems
Stress-strength model
representation of the failure behaviour
of components

Markov models
model of the different operating states
used for components and simple
combinations of components

Series/parallel networks
simple mathematic reliability
calculation of series/parallel
connections
especially suitable for radial
(distribution) networks

Fault tree analysis
chart of the different causes that can
lead to a contingency (partial or full
failure in the system)
especially useful for substations,
where different breaker and switch
malfunctioning can lead to system
failures
Stress-strength model
useful for the reliability of the
generation/load system

State enumeration
system states are defined in order
from lower failure order, with high
probability, to higher order, with
lower probability
used for systems with low failure
probabilities and when no
additional information like
probability distributions or
switching sequence information is
required

Monte Carlo simulation
system states are defined by a
computer simulation
used for systems where more
complicated failure combinations
contribute to the system reliability
2.3.3 Reliability indices
With the described methods, a variety of reliability indices can be calculated. For
different parts of the power system, other sets of reliability indices exist. Some
reliability indices reflect the reliability of a combined system, while others represent
the generation system, the distribution system or the reliability economics.

The most common indices that are used for the reliability of a combined system are:
LOLP (Loss Of Load Probability)
The probability of a system situation in which load curtailments exist.
LOLE (Loss Of Load Expectation)
Expectation of the amount of time with load curtailments in a period.
LOEE (Loss Of Energy Expectation)
Expectation of the amount of energy that cannot be supplied to the load.
EENS (Expected Energy Not Supplied)
Expectation of the amount of energy that cannot be supplied to the load.

Indices that are often used for the generation system are:
LOCP (Loss Of Capacity Probability)
Probability of loosing a certain generation capacity.
ESWE (Expected Surplus Wind Energy)
Expected amount of wind energy that cannot be absorbed by the system.

ELCC (Effective Load Carrying Capability)
The amount of load that can be served by a (variable) energy source, while
keeping the reliability of the system at the same level.
The generation system is often represented by the COPT (Capacity Outage
Probability Table) in which the different capacity levels of the generation system and
the corresponding probabilities are given.

Some indices that are used for the distribution system are:
SAIFI (System Average Interruption Frequency Index)
The amount of customer interruptions per customers served.
CAIDI (Customer Average Interruption Duration Index)
The average duration of a customer interruption.
ASAI (Average Service Availability Index)
Ratio of the available service duration and the demanded service duration.

For reliability economics, it is important to define the total costs and benefits of an
investment. Typically, the investment costs, the operation costs and the risk
costs/benefits are defined. For the risk benefits, the costs of interrupted energy must
be defined. A distinction can be made between the interruption of a generating facility,
an industrial and a domestic customer. Indirect costs and benefits are often not
considered.

Another reliability index that describes the reliability of a combined system is the
risk indicator. The risk is defined as the product of probability and severity. As the
significance of an event depends on both its probability of occurrence and its
consequences, this is a useful index.
2.4 Applications of probabilistic power system reliability analysis
Probabilistic reliability analysis can be used in different fields of activity in planning
and operation of the power system, as shown in figure 2.12. The main fields are asset
management, operational planning and reliability economics. These applications are
described in more detail in this section.

Figure 2.12: Applications of probabilistic power system reliability analysis.

2.4.1 Asset management
In asset management, three issues are important, namely expansion, maintenance
and adaptation of the power system. Based on the current situation and the expected
growth and development of the power system, asset managers have to make decisions
about which parts of the power system need to be expanded, maintained or adapted.
Not all system expansions do necessarily lead to an improvement in the system
reliability. It is possible that due to economic reasons, the power flows in the system
are redistributed after the system expansion and the effective system reliability
remains the same as before the system expansion [4].
Different development objectives can lead to different solutions. For example,
deterministic, security and probabilistic targets can all lead to different system
expansions [5]. For the deterministic target, the system must be able to supply the
maximum load level and for the security target, the system must be n- secure. The
probabilistic target states that the system must have a certain reliability level
measured in the reliability index LOLE (Loss Of Load Expectation).
As deterministic rules are strongly integrated into the system operation practice and
are still frequently used for network planning, it is often suggested that probabilistic
approaches for the planning and operation are an extension of these deterministic
rules [3]. Probabilistic system reliability is then regarded as a next selection criterion
after the deterministic n-1 rule. Economical optimization then, is the following
criterion.
Another issue in asset management is maintenance [6]. Maintenance of the
components of the power system can influence the reliability of the power system in
two different ways. First, the maintenance of components will increase the reliability
of the components and eventually also the reliability of the complete system. Second,
during maintenance, different components are taken out of the system and the
reliability of the system will decrease. This latter is more a topic of operational
planning. In most studies on maintenance, the effects of different maintenance
policies on the reliability are compared and the maintenance costs are taken into
account. Often, components are ranked on their importance for the system reliability
or the expected economic benefits.
2.4.2 Operational planning
Operational planning deals with the scheduling of the generation and the transport
of electricity in the available power system. After the liberalisation of the electricity
market, the generation and the transmission of electrical energy are uncoupled. This
has led to a situation in which the TSO (Transmission System Operator) is responsible
for the overall reliability of the power system while the producers are only responsible
for the generation of electricity [7]. To optimise their profit, generating companies
plan the generation as economically as possible.
As a deterministic rule to secure the reliability of the power system during operation,
a certain redundancy (operational reserve margin) in the generation is required. The
level of the reserve margin is often discussed and is mostly chosen as the loss of the
largest unit. The increasing amount of renewable, fluctuating sources will have an
impact on the required reserve margin [8].
An important task of operational planning is maintenance scheduling. During
maintenance, different components are taken out of the system. Consequently, the
reliability of the system will decrease and the system is more operated to its limits. It

is essential to plan the maintenance in such a way that the reliability remains at a high
level. Often, maintenance is scheduled by studying deterministic worst-case scenarios.
Probabilistic reliability analysis can give more insight into the effects of the
maintenance on the system reliability.
Probabilistic reliability analysis can play an important role in the operational
planning. The challenge is to develop a method to analyse the reliability of the system
in the actual and near-future situation. The results of the real-time analysis can help
the system operator to localise critical situations and to find possible solutions for
these situations.
2.4.3 Reliability economics
The costs are often the restricting factor for increasing the system reliability. In
many situations, an optimum between the costs and the effects on reliability has to be
found. The costs of reliability can be considered in individual situations as well as in
general.
Knowledge about reliability economics can be useful when making decisions about
possible system developments. When reliability analysis and economics are combined
in a probabilistic cost/benefit analysis, decisions can be made about what the most
optimal measures are.
It is important to study both the direct and indirect costs and benefits in a
cost/benefit study. Direct costs and benefits may be for example the project costs and
the reduction of not supplied energy. Indirect costs and benefits often consist of social
wealth, welfare or loss of comfort. These costs and benefits are more difficult to
define. A thorough study on these costs will lead to more optimal decisions.
More in general, one can also think of the real cost/worth of reliability. For what
compensation are customers willing to accept some risk and what are customers
willing to invest in a more reliable system [9]? In the liberalised market, an important
question is who should be responsible for the system reliability [7].

References

[1] R. Billinion and R. N. Allan, Reliability Evaluation of Power Systems, 2nd ed.
New York: Plenum Press, 1996.
[2] R. Billinton and R. N. Allan, "Power-system reliability in perspective,"
Electronics and Power, vol. 30, pp. 231-236, 1984.
[3] W. Li, Risk Assessment of Power Systems - Models, Methods, and
Applications. Canada: Wiliey Interscience - IEEE Press, 2005.
[4] D. S. Kirschen, "Do Investments Prevent Blackouts?," in Power Engineering
Society General Meeting, 2007. IEEE, 2007, pp. 1-5.
[5] C. Jaeseok, T. Mount, and R. Thomas, "Transmission System Expansion Plans
in View Point of Deterministic, Probabilistic and Security Reliability Criteria,"
in Second International Conference on Innovative Computing, Information
and Control, 2007. ICICIC '07, 2007, pp. 380-380.
[6] L. Bertling, "Reliability Centred Maintenance for Electric Power Distribution
Systems," Ph.D. thesis, Dept. Elect. Power Engineering, Royal Institute of
Technology, Stockholm, Sweden, 2002.
[7] C. Singh, M. Schwan, and W. Wellssow, "Reliability in Liberalized Power
Markets - From Analysis to Risk Management - Survey Paper," in 14th Power
System Computation Conference PSCC, Sevilla, 2002.
[8] A. M. L. L. da Silva, W. S. Sales, L. A. da Fonseca Manso, and R. Billinton,
"Long-Term Probabilistic Evaluation of Operating Reserve Requirements
With Renewable Sources," IEEE Transactions on Power Systems, vol. 25, pp.
106-116, 2010.
[9] R. Billinton and R. N. Allan, Reliability Evaluation of Power Systems, 2nd ed.
New York: Plenum Press, 1996.

You might also like