You are on page 1of 44

PIPING STRESS ANALYSIS

BY CAESAR-II SOFTWARE
FDC PIPING
CAESAR MODELING
ANALYSIS
REPORT
WHAT MAKES PIPING CRITICAL?
Temperature
Pressure
Occasional loads (Seismic & Wind)
Dynamics of the flowing fluid
FDC PIPING
WHAT CAUSES STRESS IN THE
PIPE?
Live and Dead load (Piping component, Insulation,
Flowing medium etc.).
Line pressure
Restraining of pipe expansion or Temperature gradient
Discharge reaction (E.g. Relief valves)
Seismic / Wind load
Dynamics of flowing fluid.
FDC PIPING
Cont.
WHY STRESS ANALYSIS IS TO BE
DONE?
To ensure that all stresses in the piping system are within
allowable limits.
To limit the loads on the equipment nozzle.
To limit the thermal displacement and sagging
To limit the loads on the supporting structures &flanged
joints.
To avoid excessive piping vibration
FDC
PIPING
WORK FLOW DIAGRAM FOR
STRESS GROUP
Piping Team
Process Dept.
Stress Analysis
Team
Stress Analysis
Report
Civil Dept.
Mechanical
Dept.
Site/ Field
Instrumentation
Dept.
P&ID
LDT
Soi l
Characteristi cs
Ci vil and
Structural
Support loadi ngs
Supports Loadings
for pi pe support
selection, pipe
displ acements at
operating temp.
SAQ,
al ongwith
Stress
Isometrics
and other
data
Equipment
G.A.'s
Cleat Loads, Nozzl e
loads i f more than
allowables
Fabri cation
and Erection
Isometric
Spring, SPS,
Specials data
sheets, Site problem
resolutions, Audit
Reports
Instrument data
INPUT FOR STRESS
ANALYSIS
Stress Isometrics
LDT / P&ID
Equipment G.A.Drawing
Instrument(e.g.PSV/control valve) data sheet
FDC PIPING
SOFTWARE USED
CAESAR II 4.5
Piping Stress Analysis Software
FDC PIPING
In-house software (Tracking system)
SATS
SSTS
CAESAR CONVERT
MODELLING
Piping Components
Piping
Equipments
Restraints
FDC PIPING
Cont.
FDC PIPING
Cont.
NODE SKETCH
STRESS ISO MARKUP
Caesar Modelling
CAESAR INPUT SPREADSHEET
Batch Run
Allowable
Stress At
Hot
Condition
Allowable Stress At Cold Condition
Start Run
Material Selection
Geometry
RESTRAINT MODELLING
SPRING MODELLING
CONSTANT SPRING
INPUT SPREADSHEET
FORCE MODELLING
BEND MODELLING
SEISMIC FORCE INPUT
PROCEDURE FOR PUMP LINE ANALYSIS
PROCEDURE FOR PUMP LINE ANALYSIS

REQUIRED DOCUMENTS
? Pump line ISO, Pump vendor drg, allowable nozzle Load, P& ID, and LDT. In the
absence of allowable load in vendor drg, twice of API-610 values are used. CAESAR axis
system should match with vendor drg or API-610 for comparing nozzle allowable loads and
moments.
PUMP MODELING IN CAESAR-II
Most commonly used centrifugal pumps are:
1. End suction Top discharge
2. Top suction Top discharge
3. Side suction Side discharge
For above mentioned pumps detail modeling procedure in CAESAR-II is discussed as
below
1. End suction Top discharge
Referring to Fig.1, node marking 1-2 shows nozzle flange with given flange rating
as rigid element. Node 2-3 shows nozzle standby with pipe element (dia equal to pump
impeller dia and thickness equal to pipe wall thickness) as rigid element with zero weight
from flange welding joint to pump impeller center line.
Restraints
1) The pipe flange to be get anchored as C- Node with pump flange to get
nozzle load due to piping reaction. This load value should be less than allowable values.
2) Rigid element at Impeller C/L to be get anchored i.e. anchor at node3.

PROCEDURE FOR PUMP LINE ANALYSIS

2. Topsuction Topdischarge&3. Sidesuction Sidedischarge


Referringto Fig.2&3, nodemarking1-2shows nozzle flangewithgivenflange ratingas rigid element. Node 2-3
showsnozzlestandbywithpipeelement (Diaequal topumpimpeller diaandthicknessequal topipewall thickness) asrigid
element withzero weight fromflangeweldingjoint to pumpimpeller center line. Node3-4shows rigidelement withzero
weight uptocenter lineof thepump.
Restraints
1) Thepipeflangetobeget anchoredasC- Nodewithpumpflangetoget nozzleloadduetopipingreaction. Thisloadvalue
shouldbelessthanallowablevalues.
2) Rigidelement at pumpC/Ltobeget anchoredi.e. anchor at node4.

PROCEDURE FOR PUMP LINE ANALYSIS


ANALYSIS
FDC PIPING
STATIC ANALYSIS
DYNAMIC ANALYSIS
TYPESOF STRESSES
FDC PIPING
PRIMARY
SECONDARY
TYPES OF LOAD
FDC PIPING
Sustain Load
Occasional Load
Thermal Load
Hydro Test Load
LOAD CASE DEFINATION
L1 WW +HP (HYD)
L2 W +T1 +P1 +H (OPE)
L3 W +T2 +P1 +H (OPE)
L4 W +P1 +H (SUS)
L5 L2 L4 (EXP)
L6 L3 L4 (EXP)
FDC PIPING
LOAD CASE DEFINATION
FDC PIPING
L1 W +T1 +P1 +H (OPE)
L2 W +P1 +H (SUS)
L3 U1 (OCC)
L4 U2 (OCC)
L5 L2 +L3 (OCC)
L6 L2 +L4 (OCC)
CAESAR LOAD CASES
DESIGN TEMP. LOAD CASE
OPERATING TEMP. LOAD CASE
PROCEDURE FOR PUMP LINE ANALYSIS
When two or more pumps are used in a systemthen fromstress analysis point of viewthe different load cases
are made. Like,
Bothpumpoperating.
One pumpoperating&one standby.
(This point to be get discussed with process, what will be the requirement, whether at anymoment onlyone
pumpwill operate, for more thantwo pumpcase)
Hot Cold analysis to be done at designandoperatingtemperature.
For the pump, which is not operating, ambient
temperatureshouldbe consideredfromTee point
Whentwo pumps are present in the system hot
cold cases can be made as below (Refer Fig. 4).
LOAD CASES FOR PUMP LINE STRESS ANALYSIS
Load cases for the pump connected lines are discussed below.
1. Hot Cold Load case:
PROCEDURE FOR PUMP LINE ANALYSIS
Case 1: When both pumps are in operating condition,
provide design and operating temperature for node 10-20-
30-40-A&20-50-60-B
Case 2: When pump Ais operating and pump Bis cold, provide
design and operating temperature for node 10-20-30-40-A and
ambient temperaturefor 20-50-60-B.
Case 3: When pump B is operating and pump A is
cold, provide design and operating temperature for
node 10-20-50-60-B and ambient temperature for 20-
30-40-A.
When three pumps are present in the system
hot cold cases can be made as below (Refer Fig. 5).
PROCEDURE FOR PUMP LINE ANALYSIS
CASE6: W+P1+T5 (OPE) Pump A at operating temp and Pump B standby.
CASE7: W+P1+T6 (OPE) Pump B at operating temp and Pump A standby.
CASE8: W+P1 (SUS)
CASE9: WNC (SUS)
CASE10: L2-L8 (EXP)
CASE11: L3-L8 (EXP)
CASE12: L4-L8 (EXP)
CASE13: L5-L8 (EXP)
CASE14: L6-L8 (EXP)
CASE15: L7-L8 (EXP)
For load case no 2, 3, 4, 5, 6,7and 8 pump nozzle load is checked and it should be within
acceptable limit as specified by vendor or API 610.
For load case no 1, 8, 10, 11,12,13,14 and 15 stress value is checked and it should be less than
allowable stress as specified by relevant code.
For load case no 9 (WNC case) deflection is checked at pipe flange for cold alignment case as
discussed in earlier topic of WNC load case.
B. Load Cases for Static Analysis (Three Pumps A, B & C)
CASE1: WW+HP (HYD)
CASE2: W+P1+T1 (OPE) Three pumps at design temperature.
CASE3: W+P1+T2 (OPE) Three pumps at operating temperature.
CASE4: W+P1+T3 (OPE) .Pump B&C at design temp and Pump A standby.
CASE5: W+P1+T4 (OPE) ..Pump A&C at design temp and Pump B standby.
CASE6: W+P1+T5 (OPE) ..Pump A&B at design temp and Pump C standby.
CASE7: W+P1+T6 (OPE) ..Pump B&C at operating temp and Pump A standby.
CASE8: W+P1+T7 (OPE) ..Pump A&C at operating temp and Pump B standby.
CASE9: W+P1+T8 (OPE) ..Pump A&B at operating temp and Pump C standby.
CASE10: W+P1 (SUS)
CASE11: WNC (SUS) CASE12: L2-L10 (EXP) CASE13: L3-L10 (EXP) CASE14: L4-L10 (EXP)
PROCEDURE FOR PUMP LINE
Case 1: When three pumps are in operating condition, provide design and operating temperature for
whole system.
Case 2: When pump A is cold and pump B & C are operating, provide design and operating
temperature to node 10-20-30-70-B & 20-50-60-C and ambient temperature for 30-40-80-A.
Case 3: When pump B is cold and pump A & C are operating, provi de design and operating
temperature to node 10-20-30-40-80-A & 20-50-60-C and ambient temperature for 30-70-B
Case 4: When pump C is cold and pump A & B are operating, provide design and operating
temperature to node 10-20-30-40-80-A & 30-70-B and ambient temperature for 20-50-60-C.
2. WNC (Weight No Content) Load case:
The basic philosophy for WNC is by what magnitude the piping flange displaced at the
mating point while cold alignment. For WNC case, make the pump flange anchor node free and
replace the spring support to rigid support. Go in load case spread sheet, drag the WNC from
side menu to load case row and select Sustain case . Run the case and get the displacement at
the pump nozzles, this displacement should be less than 1mm (or consult mechanical department
to get allowable deflection).
3. Load Cases in CAESAR-II for two pump connected system
Load cases for stress analysis of two pump connected piping system are discussed below.
Same philosophy is applicable for more than two pump connected system.
Abbreviation: W = Weight; T= Temperature; HP = Hydro Pressure; WW = Water Fil led Weight;
WNC = Weight No Contents; P = Design Pressure. U1 = Uniform load (NS Seismic); U2 = Uniform
load (EW Seismic);
A. Load Cases for Static Analysis (Two Pumps A & B)
CASE1: WW+HP (HYD)
CASE2: W+P1+T1 (OPE) Both pumps at design temperature.
CASE3: W+P1+T2 (OPE) Both pumps at operating temperature.
CASE4: W+P1+T3 (OPE) Pump A at design temp and Pump B standby.
CASE5: W+P1+T4 (OPE) Pump B at design temp and Pump A standby.
CAESAR OUT PUT
REPORT INTERPRETATION
Displacement
Restraints
Restraints Summary
Global Element Forces
Local Element Forces
Stresses
Sorted Stress
Code Compliance
FDC PIPING
REPORT INTERPRETATION
Hanger Table
Hanger Table W/Text
Input Echo
Miscellaneous Data
Load Case Report
Warnings
FDC PIPING
OUTPUT SHEET
REPORTING
Stress Analysis Query Front Sheet
Caesar Title Sheet
Stress Isometrics with markup
Load summary sheet
Spring / Bellow data sheet
SPS drawing
Caesar Load summary sheet
FDC PIPING
Stress Analysis Query Report
Job No. : 22960
Job Title : Jamnagar Refinary Project -
Complex : Coke Unit : 371 Title : QYI/COK
Description :
Tie-In for
Heater
Package No. : Coke-371-041-00 Rev.: 0 Caesar File name : KA041A00
Analyst : rajeshr Date of issue : 18/11/2003
Isometrics :
A15-371-
PA017, A09-
Reason for analysis :
Others
Ref. Doc. : Enclosed - Stress Isometrics - Attached sheets
Caesar Dump - Attached
Load Summary Report - Attached
Caesar front sheet - for ref. Attached
Spring Report -
Spring Datasheets -
SPS drawing -
Pump/Equipment datasheet/drawing - Attached
Copy of LDT - Attached
Stress Remarks:
Line Checked for Tie -in to the existing line.
SAQ SHEET
CAESAR DUMP
RESTRAINT OUTPUT
User is given an unlocked cell (F53) to write any special comment / note.
MAINTENANCE
EL1-EL2=1500 mm
SPRING DETAILS File name: Calc No.: Node No.:
LINE NO.: TYPE: B SIZE: FIG:
ISO OR GA NO.: BOTTOM CONNECTION NO.:
INSTALLED LOAD: KN PIPE SIZE: PIPE MATERIAL:
OPERATING LOAD: KN EL1.: EL2.: EL3.:
TEST LOAD: KN DESIGN TEMPERATURE:
o
C
TRAVEL (+UP / - DOWN): mm P/SUPP TYPE: K N/mm
TRAVEL (AXIAL): mm TRAVEL (LATERAL): mm
MANUFACTURER: MATCODE % VARIABILITY 0.6
NOTES:
Remark: FOR MAINTNANCE (Line 951-WB-012-10")

GO TO
SARATHI
49137
32.626 10"
F1951-951-WB012A
32.812 47637
MAINTECE
48.939
BAWB401D
CS
VS2 951-WB401-10"-EC62EM-HC25
1820
150
16
1 SS
NA -0.560
1.000
13-12-2005 Issued for Construction RVB
1.000
QUANTITY REQUIRED
1
REV. DATE
DES'N
ENGR
CHKD
BY
REVISION
PIPE SUPPORT STANDARD
VARIABLE SPRINGS
1 951Y-SPR-004 22960
REV DRAWING No J OB No
FIELD DESIGN CELL
APPD
BY
PROJ .
ENGR
CLIENT
0 01-09-2003 Issued for Construction
BOTTOM CONNECTION ''B'' TYPE HANGER
MGC RPL
SS MGC RPL RRR
6
333.2
CL
EL 1
(U/S STL.)
RELIANCE INDUSTRIES LIMITED
JAMNAGAR REFINERY PROJECT
1. All welds to be6mmCFW unless otherwisenoted.
2. All make-up components to besupplied by themanufacturer.
3. All bottomconnection material to besuited with pipematerial.
4. Elevations (EL) arein mm.
CL
CL
EL.2
SPRING DATASHEET
SPS DRAWING
BELLOW DATASHEET
Reliance Engineering Associates Private Ltd.
Load Summary Chart
Fx Fy Fz Fx Fy Fz Fx Fy Fz Fx Fy Fz Fx Fy Fz
10 -3026 -15458 -11511 -11585 -12790 -39967 -147 -14754 704 -3026 -8704 -9998 -2474 -9314 -11511
120 -283 -19172 814 -283 -13086 556 20 -17646 519 -83 -635 172 -283 -2080 556
130 -689 -11710 3445 -647 -13980 3174 299 -3528 322 -689 -11710 3445 -647 -10799 3174
140 -5500 -26565 7648 -5109 -23280 7567 -898 -21080 223 -5500 -20273 7648 -5109 -20428 7567
170 1326 -27275 6542 704 -23156 6541 1035 -21389 -427 742 -21947 6542 704 -21930 6541
210 -4914 -22514 -967 -4895 -18103 -967 -169 -17668 553 -4914 -16628 -861 -4895 -16631 -967
220 -4877 -12546 -6954 -4831 -11815 -28705 -95 -9839 -22 -4877 -9512 -6954 -4831 -9548 -6784
230 -3838 -16219 217 -3833 -13389 217 -54 -12723 4 -3838 -12808 193 -3833 -12798 217
240 9691 -15425 2121 50488 -12233 2005 -31 -12099 -1 9691 -12077 2121 9349 -12079 2005
250 3532 -15003 -4500.9 3531 -11814 -66 -18 -11768 -3530.4 3532 -11774 -60 3531 -11774 -66
260 4123 -17525 -5257.5 4123 -13755 -10608 -11 -13746 -4123.8 4123 -13745 -52 4123 -13745 -56
270 1440 -6118 -1835.4 1440 -4801 -14 -8 -4799 -1439.7 1440 -4799 -14 1440 -4799 -14
580 -6309 -3048 1893 -30719 -2294 1820 -143 -2778 -83 -6309 2 1893 -6087 -210 1820
590 1086 -3479 -323 1048 -3593 -2344 -45 -2643 29 1086 -3479 -323 1048 -3402 -288
600 713 -3097 -8 713 -2467 -1 -15 -2599 -8 707 -2356 -2 713 -2378 -1
610 998 -3515 357 992 -3094 2096 -7 -2908 2 998 -3010 357 992 -3002 350
640 745 -3056 -916.8 745 -2561 -36 1 -2548 -1 743 -2480 -34 745 -2485 -36
650 -1011.3 -3371 -1011.3 952 -2912 -2186 -839.4 -2798 -839.4 958 -2884 -334 952 -2877 -322
660 -959.4 -3198 6 728 -2439 6 1 -2658 -1 721 -2405 5 728 -2426 6
670 1084 -3614 44 1060 -3551 1916 1 -2681 3 1084 -3614 44 1060 -3534 37
680 279 -3285 -16 279 -986 7 4 -2729 -13 222 -742 6 279 -929 7
690 17 -3298 65 0 1230 1740 14 -2791 51 0 0 21 0 0 17
805 662 -12263 3619 4126 -19457 3619 -45 -8552 -192 662 -12263 3619 609 -12232 3619
875 334 -10434 -3757 334 -17659 -8978 52 -7854 164 149 -10434 -3161 334 -10185 -3757
960 2678 -2340 -532 4886 2336 -510 91 -1943 -120 2678 603 -532 2495 548 -510
985 -90 -1900 -563 -70 -2389 -481 -76 -1554 -460 -69 -1599 -475 -70 -1621 -481
990 -1484 -3195 -3820 -1291 -3833 -14357 -58 -2531 220 -1484 -3195 -3754 -1291 -3096 -3820
1000 1461 -3008 699 4403 -2397 623 18 -2517 -172 1461 -925 699 977 -1178 623
1100 746 -11349 3322 282 -10415 2670 -39 -5361 94 746 -11349 3322 282 -8949 2670
1140 -876 -17708 -5240 -734 -15470 -4307 28 -9575 -179 -876 -17708 -5240 -734 -14562 -4307
1220 -1472 -8969 -800 -1472 -6209 -638 -225 -7491 281 -965 -4179 -800 -1472 -5347 -638
1250 -1786 -7238 1407 -1392 -7528 1407 172 -6088 -65 -1786 -7151 1189 -1392 -6596 1407
1260 -2088 -8217 -1310 -1651 -8135 -1100 -55 -5653 -22 -2088 -8217 -1310 -1651 -8018 -1100
1270 168 -7976 -503 12594 -5832 -503 -38 -6698 22 0 0 0 168 -1641 -503
1299 -954 -12798 -3719 -484 -20930 -3371 130 -8447 -39 -954 -12798 -3719 -484 -11352 -3371
1410 1262 -3049 729 2191 -12199 8028 -100 -2350 -38 1262 -3049 -380 668 -2981 729
1620 1564 -8812 -535 1564 -6172 -256 234 -7358 193 1144 -4211 -535 1564 -5281 -256
1640 1896 -7262 1227 1604 -7446 1227 -168 -6108 -61 1896 -7215 1045 1604 -6733 1227
1650 2137 -8183 -1281 2044 -8373 -1281 56 -5645 -20 2137 -8183 -1209 2044 -8041 -1281
1660 -240 -7980 -493 -12267 -6298 -493 35 -6701 23 0 0 0 -240 -1521 -493
1689 955 -13120 -3818 467 -20978 -3490 -122 -8829 -38 955 -13120 -3818 467 -11736 -3490
1800 -1259 -3067 1001 -1764 -11820 8638 95 -2342 -39 -1259 -3067 89 -651 -3032 1001
3010 1246 -7833 1407 757 -11537 1401 -34 -6972 366 1246 -6263 1407 757 -5308 1401
3070 600 -2164 304 552 -2415 304 -17 -1880 -38 600 -2132 220 552 -2099 304
4050 -2495 -12491 2801 -2490 -14246 2801 -1801.8 -6006 -1802 -2495 -12206 2680 -2490 -12491 2801
4070 -248 -4676 1381 0 1316 0 -167 -3602 1068 0 0 0 0 0 0
4120 -15837 -31157 -2994 -19092 -11612 -2599 711 -23909 -1135 -15837 -4411 -2994 -9860 -8782 -2599
4150 16655 0 21194 18228 0 22805 0 0 0 16655 0 21194 10765 0 13646
4170 4653 -83854 24722 2841 -45483 12902 1619 -27407 -728 4653 -83854 24722 2841 -44038 12902
Operating
Node
Max. Static Max. Composite Occ
14-Jan-06
c:\stressout\KB038A001401141157.xls
Sustained Design
Date of Generation:
File Location:
LOAD SUMMARY SHEET
FDC PIPING
COMPLETED STRESS ISO

You might also like