O&M Manual Checklist for Materials, Finishes,Equipment, and

Systems
INC(OMPLETE)
or NA
DATE
Drawings: Provide with reinforced punched binder tab. Bind in with text; fold larger drawings to size of text pages.
1.4
Data: In the form of an instructional manual.
Binders: Heavy-duty commercial quality, 8-1/2 x 11 inch ring binders with hardback, cleanable, plastic covers. When multiple
binders are used, correlate data into related consistent groupings.
Cover: Each binder with typed or printed title "Operation And Maintenance Instructions"; list title of Project; identify subject
matter of contents. For Final O&M Manual, identify each Volume X of Y where it is the X
th
volume of Y total volumes in each
O&M set for the project; Identify each volume as being in Set A of B where the volume is part of the A
th
set of B total final
O&M Manual sets provided for the project.
Content: By systems; under section numbers and sequence of Table of Contents.
Tabbed flyleaf: For each separate product and system, with typed description of product and major component parts of
equipment.
Text: Manufacturer's current prepared printed data, or current data from manufacturer's website, printed on 20lb paper.
Table of Contents: Provide title of Project; names, addresses and telephone numbers of Owners Authorized Representative
and Contractor with name of responsible parties; schedule of products and systems, indexed to content of the volume.
Master Index: Provide a master index at the front of each volume which lists each volume in the total set and its major tab
numbers as necessary for a user to be able to readily locate a particular O & M instruction.
Applicable Information: For each material, finish product, equipment or system as described in paragraph 3 below. In general
the O & M Manual should include all information necessary for the operating personnel to effectively and safely operate, service
and maintain the subject product, equipment or system.
Product Data: Mark each product data sheet to clearly identify specific products and component parts, and data applicable to
the installation; delete inapplicable information.
3.1
Revise / Re-submit / Correct - Req'd _X_ Not Req'd ___
1.1
1.2
1.3
2.1
2.2
1.5
1.6
1.7
2.3
2.4
2.5
2.6
Specification#:
Description:
Submitted by:
Job #
For:
1. FORMAT
2. CONTENTS, EACH VOLUME
3. MANUAL FOR MATERIALS AND FINISHES
Drawings: Supplement product data to illustrate relations of component parts of equipment and systems, to show control and
flow diagrams. Drawings included in the O & M Manuals should be provided in 8-1/2 x 11 or 11 x 17 format as appropriate for
the content and clarity of the drawing.
Typed Text: As required, supplement Manufacturers printed product data and operation and maintenance instructions.
Provide logical sequence of instructions for each procedure, incorporating manufacturer's instructions. Make use of
manufacturers printed data and information to the maximum extent possible.
Building Products, Applied Materials, and Finishes: Include product data, manufacturers catalog cuts and data sheets with
manufacturers catalog number, construction document finish code, size, composition, and color and texture designation.
Provide information including sources, names and contact information for re-ordering custom manufactured products.
O&M Manual Checklist
O&M Manual Checklist for Materials, Finishes,Equipment, and
Systems
INC(OMPLETE)
or NA
DATE Revise / Re-submit / Correct - Req'd _X_ Not Req'd ___
Specification#:
Description:
Submitted by:
Job #
For:
Design and normal functional operating parameters (capacities, flows, temperatures, speeds, energy consumption, limits,
etc.) and manufacturer performance curves.
Seasonal changes in operational requirements and procedures.
4.1.2
4.1.3
Description of equipment and system controls with as-installed controls diagrams.
Description and as-installed schematic drawings for system controls, interface with other systems, piping, and
wiring.
Manufacturer and Installing Contractor : Contact names and telephone numbers.
Initial equipment and system settings.
Section 2 System Operation:
Preventive and Routine Maintenance (checks, adjustments, calibration, lubrication, parts replacement, etc.) procedures and
frequencies including diagrams and isometrics as necessary for clarity.
Routine testing and checkout procedures and frequencies.
Cleaning instructions.
Visual inspection parameters. Operating sound and noise warnings.
Normal range of gauge and meter readings.
Instructions for Care and Maintenance: Include manufacturer's recommendations for cleaning agents and methods,
precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance. Include
repair procedures and instructions.
Moisture-protection and Weather-exposed Products: Include product data listing applicable reference standards, chemical
composition, and details of installation. Provide recommendations for inspections, maintenance, and repair.
Additional Information Requirements: As specified in individual Specifications sections.
Section 1 System Description:
Procedures and sequence of operation for system start-up, system break-in, all modes of normal operation and normal
and emergency shutdown.
Procedures for isolating individual equipment from the system, for placing the system or individual equipment on stand-
by, for bringing individual equipment online once the system is operating and for isolating subsystems.
3.2
3.3
3.4
4.1
Description of equipment and systems and interface and interrelation with other systems and subsystems.
4.2
4.2.1
Operational log and records requirements.
Recommended safety precautions and practices during system operation, adjustments, servicing, and repair.
Section 3 System Maintenance:
4.2.8
4.2.9
4.3
4.3.1
4.3.2
4.3.3
4.2.2
4.2.3
4.1.4
4.2.4
4.2.5
4.2.6
4.2.7
4. MANUAL FOR EQUIPMENT AND SYSTEMS, cont.
4. MANUAL FOR EQUIPMENT AND SYSTEMS
4.1.1
O&M Manual Checklist
O&M Manual Checklist for Materials, Finishes,Equipment, and
Systems
INC(OMPLETE)
or NA
DATE Revise / Re-submit / Correct - Req'd _X_ Not Req'd ___
Specification#:
Description:
Submitted by:
Job #
For:
Parts Descriptions.
Manufacturers Part Number.
Shelf Life.
Recommended Quantity.
Unit Price.
Name, phone numbers and address of the parts manufacturers.
Names, phone numbers and addresses of local part suppliers.
List of all special tools and equipment (testing, measurement, and diagnostic) required to perform: equipment and system
maintenance and repair. Special tools are those non-standard tools and equipment, designed and developed by the
manufacturer or others, which are necessary to perform successful O & M of the equipment and systems. For tools and
equipment requiring calibration, information should include calibration frequency, methods and standards.
4.3.6.1
List of original manufacturers spare parts and recommended quantities to be maintained in storage for a 12-month
period. Spare parts list shall contain the following information:
4.3.4
4.3.5
4.3.6
Copies of completed operational and performance test reports.(FIELD)
Copies of pre-startup deficiency lists, start-up testing deficiency lists and operational testing deficiency lists showing
correction of all deficiencies.
Copies of all warranties.
Warranty periods and special considerations to avoid violating warranty including limitations on repairs by Owner personnel
during the warranty period.
Warranty claim procedures including required forms and contact names, addresses, phone numbers and e-mail addresses.
Section 6 Testing/Commissioning Records(for Final O&M Manual only):
4.5.1
4.5.2
4.5.3
Copies of completed pre-functional system checklists.(MFG)
Copies of factory test reports.(FACTORY)
Correction and repair procedures.
Section 5 Warranty Data(for Final O&M Manual only):
4.3.6.3
4.3.6.4
4.3.6.5
4.3.6.6
4.3.6.2
List and sources of recommended operating supplies. Lubricants, cleaning materials, etc. with addresses, contact names
and telephone numbers.
4.3.6.7
4.4
4.4.1
4.4.3
4.4.2
Troubleshooting and diagnostic guidelines and procedures.
Breakdown or malfunction conditions.
Trouble indicators.
Section 4 Trouble Analysis:
4.6.4
4.6.5 Copies of contractor's pre-turnover, interim maintenance records and reports.
4.6
4.4.4
4.6.1
4.6.2
4.6.3
4.5
O&M Manual Checklist
O&M Manual Checklist for Materials, Finishes,Equipment, and
Systems
INC(OMPLETE)
or NA
DATE Revise / Re-submit / Correct - Req'd _X_ Not Req'd ___
Specification#:
Description:
Submitted by:
Job #
For:
Preliminary O & M Manual At least ninety (90) days prior to Substantial Completion and prior to specific training for
the Owner's personnel, submit two (2) copies of preliminary O & M Manual, for Equipment and Systems and Materials and
Finishes, to the Owner's Authorized Representative(s). Include proposed: cover, binder, master index, tables of
contents,organization and format of each volume, and manufacturer's printed information, drawings, diagrams, and/or tabular
data. The Owners Authorized Representative(s) will review and return one (1) copy with comments.
5.1.3
5.1
5.1.1
Final O&M Manual(Draft) At least thirty (30) days prior to Substantial Completion, submit two (2) copies of corrected O&M
Manuals to the Owner's Authorized Representative(s). One (1) copy will be returned with Owner comments. Correct and revise
content of documents prior to final submittal.
Final O&M Manual Within ten (10) days after Substantial Completion, submit four (4) copies of final O&M Manual,
incorporating all review comments and corrections to Owners Authorized Representative(s).
5. SUBMITTALS
Submittals shall be made jointly to the Owners Authorized Representative(s) as described below:
5.1.2
O&M Manual Checklist
O&M Manual Checklist for Materials, Finishes,Equipment, and
Systems
INC(OMPLETE)
or NA
DATE Revise / Re-submit / Correct - Req'd _X_ Not Req'd ___
Specification#:
Description:
Submitted by:
Job #
For:
RVW DATE CORRECTED ADDITIONAL ADMINISTRATIVE COMMENTS
1 Complete all local contact information for suppliers and subcontractors
2 Missing
3 Poor quality copies / Inaccurate / Not original or factory supplied copies
4
5
6
TECHNICAL CONTENT
1 Cleaning Solvents - Materials, procedures, precautions.
2 Diagnostic Tables
3 Equipment Operation - Theory and Safety Precautions.
4 Fasteners - Torque values and grades.
5 Lubrication Specifications - MIL SPEC, Supplier, etc
6 Measuring Devices - Placement diagram.
7 Overhaul Procedures.
8 Paint Specifications - MIL SPEC, Supplier, Pantone number, etc
9 Parts Names - Consistent
10 Parts Ordering - Detailed information, Alternate parts list
11 Periodic Maintenance - Frequency and practices.
12 Software Loading and Rebooting - Procedures
13 Special Handling or Storage - Procedure/ process.
14 Special Tools - Required for service/maintenance
15 System Administration - Procedures (e.g. changing passwords adding users, etc.)
16 Task Performance - Sequential steps
17 Technical Assistance - Contacts
18 Technical Illustrations - Block diagrams, pictures, exploded views,wiring and circuit diagrams
19 Technical Values - Pressure, temperature, resistance, voltage or current values,wave forms
20 Testing Processes - After routine maintenance and overhaul.
TRAINING CONTENT
1 Breakdowns - Malfunction conditions, troubleshooting and repair procedures.
2 Equipment and System Settings - Initial.
3 Gauge and Meter readings - Normal.
4 Health and Safety - Concerns, Recommended precautions and practices.
5 Inspection Parameters - Visual, sound and noise warnings.
O&M Manual Checklist
O&M Manual Checklist for Materials, Finishes,Equipment, and
Systems
INC(OMPLETE)
or NA
DATE Revise / Re-submit / Correct - Req'd _X_ Not Req'd ___
Specification#:
Description:
Submitted by:
Job #
For:
6 Isolating Individual Equipment and Subsystems during Operations.
7 Manufacturer Contacts.
8 Operating Parameters - Design and normal functional.
9 Preventive and Routine Maintenance - Procedures and frequencies.
10 Routine Testing - Procedures and frequencies.
11 Seasonal Operations - Requirements and procedures.
12 Sources - Replacement parts, operating supplies, lubricants, and cleaning materials
13 Special Tools and Equipment.
14 System Start-up - Sequence of Operation and Emergency Shutdown.
15 Warranty Periods, Procedures, and Violations.
O&M Manual Checklist
COMMENT #
Submitted by:
Job #
For:
1. FORMAT
2. CONTENTS, EACH VOLUME
3. MANUAL FOR MATERIALS AND FINISHES
O&M Manual Checklist
COMMENT #
Submitted by:
Job #
For:
4. MANUAL FOR EQUIPMENT AND SYSTEMS, cont.
4. MANUAL FOR EQUIPMENT AND SYSTEMS
O&M Manual Checklist
COMMENT #
Submitted by:
Job #
For:
O&M Manual Checklist
COMMENT #
Submitted by:
Job #
For:
5. SUBMITTALS
O&M Manual Checklist
COMMENT #
Submitted by:
Job #
For:
O&M Manual Checklist
COMMENT #
Submitted by:
Job #
For:
O&M Manual Checklist

You might also like