You are on page 1of 2

Current Status of Electrical points discussed in Karachi office

Basic Earthing
Equipment

Earthing Material required for the structure foundation and burying in


the soil will reach Matadi probably By February 2015.

NYA

FLS

Status ?

ongoing

Bulk Material
Analyzer
2
(Handling of
Source)

We require
NYA Head Office will find out standing rules and regulation of DRC for specification
Handling, Installing and Utilizing Radioactive Transmitter and Receiver of radioactive
of Bulk Material Analyzer.
transmitter,
etc.

3 Load List

Not Finalized Yet, will be remitted as soon as prepared. Updated


preliminary load list will be sent in the end of October 2014.

Status?

Final BOQ for


Electrical
Installation Jobs
4
of Electrical
Instrumentation
and DCS/PLC

FLS will revert next week with a date for when the preliminary updated
BOQ will be delivered to NYA.

Status?

5 Vender List

ABB for MV Equipment, Siemens for LV switchgears, Distributions


transformers will be of Schneider. Detailed list will be provided soon.

OK

Sketch of Cable Gallery route from NYA Grid Station situated outside
Tunnel from NYA
boundary wall to existing MV Substation handed over to Mr. Pedersen.
6 Grid to MV
FLS will modify Cable Gallery entrance point at MV substation
Substation
accordingly.

OK

NYA suggested cable trenches in place of proposed Cable pipe Duct


Cable pipe ducts
Banks for ease of installation and proper up keep of the power and
7 banks of Crusher
control cables of crusher area. Mr. Pedersen will incorporate need
Area
changes.

OK

Type of 3 Pin
8 Power Out to be
installed

In view of French Standards Being followed in DRC French Type 3 Pin


Power Out Lets was suggested by NYA Team for Installation
throughout NYA Project.

OK

LUX Values for


9 different areas of
the NYA Project

NYA will provide DRC illumination standards for working out


Illumination Level and Number of Luminaries to be installed in different Provided to
areas of the NYA Project. FLS will send lux values to NYA for
Mr. Pedersen
confirmation.

ongoing

SEP

Type of Gas
Analyzers

Mr. Pedersen will provide technical detail of gas analyzers selected for
the NYA Project. Preliminary documentation.

Status?

SEP check

Location of
Internet Access
11
Points at NYA
Project

Mr. Pedersen will indicate on the layout drawing, areas where internet
connection will have to be provided by NYA.

Status?

SEP check

10

Process Signal,
Handling
Mr. Pedersen will provide complete detail of signal handling and
Transmission and
12
communication system (Profibus, Ethernet, Fiber Optics etc. for
Communication
DSC/PLC Department in due time.
for DSC/PLC
Department

Status?

Main Cable
13
Routing

The Cable trench design and substation design has been uploaded on
myfls. NYA will comment after detailed study these documents as
soon as the myfls account for Mr. Mazhar Ali Muhammadani
mmazhar@nya-cement.com is available.

OK

With reference to the list provided by NYC the start inrush was
discussed.
LC experience is that motors mentioned in the list require soft starters
to secure life of motors and contactors.
Motor Drives
(Start Inrush
14
Heavy start
Motors)

FLS normally start the mentioned motors direct on line. The design
secures protection of the motors and contactors.

Status?

SEP

FLS will, however, provide a soft starting device for 461.FN400.


FLS will review the remaining list (Bucket elevators and Belt conveyors
if fluid couplings applies, again, comment and respond.
Ref. Attachment # EL01.

2X 25 MVA Transformer will be installed Mr. Pedersen has some


Power Distribution questions regarding SNEL 220 kV Network and Power Transformers.
Mr. Mazhar will arrange to reply these queries

15

SLD has been discussed, FLS is still working in certain areas like Kiln
Main Transformer etc. the detail of the remaining switch gear will be communicated in
due time.
MV Switch Gear

LV switchgears will be provided by Siemens.

Distribution
transformers

Schneider

LV Switch Gear

Siemens

OK

16 Lighting Vendors

Vendors for lighting materials were discussed: Philips is preferred by


NYA.

OK

17 Control System

The Control system was presented in general terms and discussed.

OK

18

Documentation
Schedule

Specification of
19 MV cable to be
clarified.

The documentation schedule was discussed. FLS will submit the


Schedule for the release of the Electrical documentation to NYA.

Status?

SEP

The insulation of proposed cable is 8.5 / 15 KV. FLS should provide


(datasheet) clarification to NYA.

Status?