You are on page 1of 80

BREAEMAR

OFFSHORE

Offshore Lifting for Subsea Equipment


Muhammad
Naval Architect

Braemar Technical Services Offshore


16th September 2014

BREAEMAR
OFFSHORE

Content
General
Light lift
Heavy lift

Lifting Capacity Checks


Rule/Code (DNV-RP-H103)
Lifting Through Wave Zone
Deepwater Lowering Operation
Landing on Seabed and Retrieval

Practice in Offshore Industries


16 September 2014

Offshore Lifting for Subsea Equipment

BREAEMAR
OFFSHORE

General

Equipment : Crane, Crane Vessel, Transport Vessel, Lifted Object


Main consideration:
Clearence :

Between lifted object and crane boom


Between crane boom and any other object/structure
Between the lifted object and any other object/structure
Between the underside of the lifted object and grillage or seafastening
Bottom of crane vessel and the seabed (at shallow water)

16 September 2014

Offshore Lifting for Subsea Equipment

BREAEMAR
OFFSHORE

General
Light Lift
Heavy Lift
Lift off the Object

16 September 2014

Offshore Lifting for Subsea Equipment

BREAEMAR
OFFSHORE

General
Light Lift
Crane Tip Motion

Crane boom assumed to be stiff, therefore crane tip motion can


be determined from wave induced rigid body motion.
Surge, sway & heave = RAO of the vessel in 6 DOF (at COG)
Response amplitude (ct), velocity (Vct), eigenperiod (T0r)
o Analytical solution
o Equation are available at DNV-RP-H103 Chapter 9.

16 September 2014

Offshore Lifting for Subsea Equipment

BREAEMAR
OFFSHORE

General
Light Lift
Hydrodynamic Interaction
For the case of:

A. The presence of other fixed or floating structure in the


vicinity of the vessel Recalculate RAO of the vessel:
B. Lifting from or to transport vessel/barge recalculate RAO
for both vessel (coupled 12 DOF)

16 September 2014

Offshore Lifting for Subsea Equipment

BREAEMAR
OFFSHORE

General
Heavy Lift

Equipment: Semi-submersible Crane Vessel (SSCV) & computer


controlled ballast system

Lift-off operation for bow-mounted crane:


Pre-trimmed to stern up
Pre-hoist operation:
transferrinig 80% of the load from the barge to the SSCV
The barge and SSCV oscilate together as a almost rigid system
in vertical direction
Ballast operation to reverse the trim
Load is lifted 4-5 m within 90 second 5 cm/s
16 September 2014

Offshore Lifting for Subsea Equipment

BREAEMAR
OFFSHORE

General
Heavy Lift
Motion analysis

12 DOF ( 6 DOF from SSCV + 6 DOF from the barge)


After lift-off : 18 DOF (6DOF extra from the object)
Lifted object + SSCV + Barge coupled each other
Horizontal motion of lifted object critical

Time domain analysis

16 September 2014

Offshore Lifting for Subsea Equipment

BREAEMAR
OFFSHORE

General
Heavy Lift

Motion analysis- Coupled Dynamic Motioin


Neglect rotation motion of lifted object 12 DOF become 9 DOF

Mass matrix, spring matrix and response motion analysis refer


to part 9.3.3
16 September 2014

Offshore Lifting for Subsea Equipment

BREAEMAR
OFFSHORE

General
Lift off The Object

Side-by-side position: relative motion between the crane hook and


the barge

Feasibility of lift-off operation:


The hoisting speed of the crane (depends on the weight of the object to be
lifted, a lower limit is usually taken to be in the order of 0.1 m/s).
The combined motion characteristics of the barge and the crane vessel.
The weather condition, combined with the orientation of the two vessels.

Probability of barge hitting lifted object : analytical solution.


available at part 9.5.2

16 September 2014

Offshore Lifting for Subsea Equipment

10

BREAEMAR
OFFSHORE

Content
General
Light lift
Heavy lift

Lifting Capacity Checks


Rule/Code (DNV-RP-H103)
Lifting Through Wave Zone
Deepwater Lowering Operation
Landing on Seabed and Retrieval

Practice in Offshore Industries


16 September 2014

Offshore Lifting for Subsea Equipment

11

Lifting Capacity Checks

BREAEMAR
OFFSHORE

Reference : (DNV Rules for Marine Operation 1996, Pt. 2 Ch. 5)

Dynamic loads, lift in air


Crane Capacity
Rigging capacity (slings, shackles, etc.)
Structural steel capacity
(lifted object, lifting points, spreader bars, etc.)

16 September 2014

Offshore Lifting for Subsea Equipment

12

Lifting Capacity Checks

BREAEMAR
OFFSHORE

Dynamic loads (DAF) for Lift in Air


DAF in air may be caused by e.g. variation in
hoisting speeds or motions of crane vessel and
lifted object.
The given table is applicable for offshore lift in air
in minor sea states, typically Hs <2-2.5m.
DAF must be estimated separately for lifts in air at
higher seastates and for subsea lifts !

16 September 2014

Offshore Lifting for Subsea Equipment

13

Lifting Capacity Checks

BREAEMAR
OFFSHORE

Dynamic loads (DAF) for Lift in Air

16 September 2014

Offshore Lifting for Subsea Equipment

14

Lifting Capacity Checks

BREAEMAR
OFFSHORE

Crane Capacity
DHL = DAF*(W+Wrig) + F(SPL)
W is the weight of the structure, including a weight inaccuracy factor
The DHL should be checked against available crane capacity.
The crane capacity decrease when the lifting radius increase.

16 September 2014

Offshore Lifting for Subsea Equipment

15

Lifting Capacity Checks

BREAEMAR
OFFSHORE

Rigging capacity (slings, shackles, etc.)


Sling Load
The maximum dynamic sling load, Fsling:
Fsling = DHLSKLkCoGDW / sin
Where:
SKL = Skew load factor extra loading caused by equipment and
fabrication tolerances.
kCoG = CoG factor inaccuracies in estimated position of centre of
gravity.
DW = vertical weight distribution e.g. DWA = (8/15)(7/13) in sling
A.
= sling angle from the horizontal plane.
16 September 2014

Offshore Lifting for Subsea Equipment

16

Lifting Capacity Checks

BREAEMAR
OFFSHORE

Rigging capacity (slings, shackles, etc.)


The sling capacity Minimum breaking load, MBL, is checked by:

The safety factor is minimum sf 3.0.


Safe working load, SWL, and MBL, of the shackle are checked by :

Both criteria shall be fulfilled


16 September 2014

Offshore Lifting for Subsea Equipment

17

Lifting Capacity Checks

BREAEMAR
OFFSHORE

Structural steel capacity


The load factor f = 1.3, is increased by a consequence factor, C =
1.3, so that total design factor, design , becomes:

The design load acting on the lift point becomes:


A lateral load of minimum 3% of the design load shall be included. This
load acts in the shackle bow !

16 September 2014

Offshore Lifting for Subsea Equipment

18

Lifting Capacity Checks

BREAEMAR
OFFSHORE

Structural steel capacity


Other lifting equipment:
A consequence factor of C = 1.3 should be applied on lifting yokes,
spreader bars, plateshackles, etc.

Structural strength of Lifted Object:

16 September 2014

Offshore Lifting for Subsea Equipment

19

Lifting Capacity Checks

BREAEMAR
OFFSHORE

Summary

16 September 2014

Offshore Lifting for Subsea Equipment

20

BREAEMAR
OFFSHORE

Content
General
Light lift
Heavy lift

Lifting Capacity Checks


Rule/Code (DNV-RP-H103)
Lifting Through Wave Zone
Deepwater Lowering Operation
Landing on Seabed and Retrieval

Practice in Offshore Industries


16 September 2014

Offshore Lifting for Subsea Equipment

21

BREAEMAR
OFFSHORE

Rule/Code

DNV-RP-H103 (Modelling and analysis of Marine Operation)


Lifting through wave zone
Deepwater lowering operation
Landing on seabed and retrieval

16 September 2014

Offshore Lifting for Subsea Equipment

22

BREAEMAR
OFFSHORE

Rule/Code
Lifting through wave zone
Hydrodynamic forces
General Method
Simplified Method

Stability of lifting operation


Snap forces
Moonpool operation

16 September 2014

Offshore Lifting for Subsea Equipment

23

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Hydrodynamic Forces (General Method)


General
Accurate prediction of design load during lowering/ retrieval

Loads
Weight of object, Buoyancy force, Current force, viscous drag
force: analitical solution. Equation are available in part 3.2
Inertia force due to moving object, Wave damping force, Wave
excitation force, Slamming force, vertical motion of lifted object:
numerical calculation in time domain

16 September 2014

Offshore Lifting for Subsea Equipment

24

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Hydrodynamic Forces (General Method)


Calculation methods
Simplified Method
Regular design wave approach
Shallow water effects are neglected.
Fhyd = F + Fm + Fs + Fd [N]
where : F = varying buoyancy force [N], Fm = hydrodynamic mass force
[N], Fs = slamming impact force [N], Fd = hydrodynamic drag force [N]

Time domain analyses


3 hours simulation period for each load case.
30 minutes simulation for sensitivity analysis

CFD analysis

16 September 2014

Offshore Lifting for Subsea Equipment

25

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Hydrodynamic Forces (Simplified Method)


the Simplified Method is to give simple conservative
estimates of the forces acting on the object.
Main assumption:
the horizontal extent of the lifted object is small compared to the wave
length
the vertical motion of the object is equal the vertical crane tip motion
vertical motion of object and water dominates other motions can be
disregarded

16 September 2014

Offshore Lifting for Subsea Equipment

26

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Time Domain Analysis

16 September 2014

Offshore Lifting for Subsea Equipment

27

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Crane Tip Motion


T crane tip Tn, Simplified method is unapplicable

Heave, pitch and roll RAOs for the vessel should be combined with
crane tip position to find the vertical motion of the crane tip
If operation reference period is within 30 minutes, the most probable
largest responses may be taken as 1.80 times the significant
responses.
Unless the vessel heading is fixed, vessel response should be analysed
for wave directions at least 15 off the applied vessel heading
16 September 2014

Offshore Lifting for Subsea Equipment

28

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Wave Period


There are two alternative approaches:
1. Wave periods are included:
Analyses should cover the following zero-crossing wave period range:

A lower limit of Hmax=1.8Hs=/7 with wavelength =gTz2/2 is here used.

2. Wave period are disregarded:


Operation procedures should in this case reflect that the calculations are only
valid for waves longer than:
A lower limit of Hmax=1.8Hs=/10 with wavelength =gTz2/2 is here used.
16 September 2014

Offshore Lifting for Subsea Equipment

29

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Wave Kinematics

16 September 2014

Offshore Lifting for Subsea Equipment

30

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Hydrodynamic Forces

16 September 2014

Offshore Lifting for Subsea Equipment

31

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Hydrodynamic Forces

16 September 2014

Offshore Lifting for Subsea Equipment

32

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Hydrodynamic Forces

16 September 2014

Offshore Lifting for Subsea Equipment

33

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Added Mass

16 September 2014

Offshore Lifting for Subsea Equipment

34

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Added Mass

16 September 2014

Offshore Lifting for Subsea Equipment

35

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Added Mass

16 September 2014

Offshore Lifting for Subsea Equipment

36

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Added Mass

16 September 2014

Offshore Lifting for Subsea Equipment

37

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Added Mass

16 September 2014

Offshore Lifting for Subsea Equipment

38

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Load Cases Example

16 September 2014

Offshore Lifting for Subsea Equipment

39

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Load Cases Example

16 September 2014

Offshore Lifting for Subsea Equipment

40

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Static Weight

16 September 2014

Offshore Lifting for Subsea Equipment

41

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method DAF

16 September 2014

Offshore Lifting for Subsea Equipment

42

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method DAF

16 September 2014

Offshore Lifting for Subsea Equipment

43

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Slack Slings

16 September 2014

Offshore Lifting for Subsea Equipment

44

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Slack Slings

16 September 2014

Offshore Lifting for Subsea Equipment

45

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Summary

16 September 2014

Offshore Lifting for Subsea Equipment

46

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Simplified Method Summary


The simplified method assumes that:
Vertical motion of structure is equal to the crane tip motion.
The horizontal extension of the structure is small.
Only vertical motion is present.

More accurate calculations can be performed


applying:
Regular design wave approach (Ch. 3.4.2)
Time domain analyses
CFD analyses
16 September 2014

Offshore Lifting for Subsea Equipment

47

BREAEMAR
OFFSHORE

Rule/Code
Lifting through wave zone
Hydrodynamic forces
General Method
Simplified Method

Stability of lifting operation


Snap forces
Moonpool operation

16 September 2014

Offshore Lifting for Subsea Equipment

48

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Stability of Lifting Operation


Partly air-filled objects
lifting of objects where the buoyancy is distributed differently

If no other forces, object will rotate untill CB is above CG


Lift wire must be above CF to avoid tilting
Sling length adjustment required for horizontal landing on seabed
16 September 2014

Offshore Lifting for Subsea Equipment

49

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Stability of Lifting Operation


Effects of free water surface inside the object
GB must be large enough to give :
up-righting moment > overturning moment (by water inside the
object)

16 September 2014

Offshore Lifting for Subsea Equipment

50

BREAEMAR
OFFSHORE

Rule/Code
Lifting Through Wave Zone (DNV-RP-H103)

Snap Force
Moonpool Operation

16 September 2014

Offshore Lifting for Subsea Equipment

51

BREAEMAR
OFFSHORE

Rule/Code

DNV-RP-H103 (Modelling and analysis of Marine Operation)


Lifting through wave zone
Deepwater lowering operation
Landing on seabed and retrieval

16 September 2014

Offshore Lifting for Subsea Equipment

52

BREAEMAR
OFFSHORE

Rule/Code
Deepwater Lowering Operation
Main consideration:

Stretched length of cable


Horizontal offset
Dynamics motion of lifted object
Methods for controlling vertical motion of lifted object

Static Forces
Dynamic Forces
Heave Compensation

16 September 2014

Offshore Lifting for Subsea Equipment

53

BREAEMAR
OFFSHORE

Rule/Code
Deepwater Lowering Operation
Static Forces

Stretched length of a cable


Horizontal offset due to current
Vertical displacement
Vertical cable stiffness
Horizontal stiffness
Cable payout quasi-static loads

16 September 2014

Offshore Lifting for Subsea Equipment

54

BREAEMAR
OFFSHORE

Rule/Code
Deepwater Lowering Operation
Dynamic Forces

Dynamic drag forces


Application
Natural frequencies, straight vertical cable
Eigen periods
Longitudinal pressure waves
Response of lifted object in a straight vertical cable exposed to
forced vertical oscillations
Slack cable conditions
Horizontal motion response of lifted object in a straight vertical
cable
16 September 2014

Offshore Lifting for Subsea Equipment

55

BREAEMAR
OFFSHORE

Rule/Code
Deepwater Lowering Operation

DNV-RP-H103 chapter 5 contains a simplified method for establishing


dynamic loads and limiting weather criteria during deepwater lifting
operations.

16 September 2014

Offshore Lifting for Subsea Equipment

56

BREAEMAR
OFFSHORE

Rule/Code
Deepwater Lowering Operation

16 September 2014

Offshore Lifting for Subsea Equipment

57

BREAEMAR
OFFSHORE

Rule/Code
Deepwater Lowering Operation

16 September 2014

Offshore Lifting for Subsea Equipment

58

BREAEMAR
OFFSHORE

Rule/Code
Deepwater Lowering Operation

16 September 2014

Offshore Lifting for Subsea Equipment

59

BREAEMAR
OFFSHORE

Rule/Code
Deepwater Lowering Operation

16 September 2014

Offshore Lifting for Subsea Equipment

60

BREAEMAR
OFFSHORE

Rule/Code
Deepwater Lowering Operation

16 September 2014

Offshore Lifting for Subsea Equipment

61

BREAEMAR
OFFSHORE

Rule/Code
Deepwater Lowering Operation

16 September 2014

Offshore Lifting for Subsea Equipment

62

BREAEMAR
OFFSHORE

Rule/Code

DNV-RP-H103 (Modelling and analysis of Marine Operation)


Lifting through wave zone
Deepwater lowering operation
Landing on seabed and retrieval

16 September 2014

Offshore Lifting for Subsea Equipment

63

BREAEMAR
OFFSHORE

Rule/Code
Landing On Seabed and Retrieval
Main consideration:
Foundation failure shouldnt take place
Damage does not occur to acceleration sensitive equipment

Landing on Seabed

Landing impact problem definition


Physical parameters and effects to be considered
Iterative analysis procedure
Simplified method for foundations without skirts
Simplified method for foundations with skirts on soft soil
Application of safety factors
Calculation of skirt penetration resistance

Installation by Suction and Levelling


Retrieval Foundation
16 September 2014

Offshore Lifting for Subsea Equipment

64

BREAEMAR
OFFSHORE

Content
General
Light lift
Heavy lift

Lifting Capacity Checks


Rule/Code (DNV-RP-H103)
Lifting Through Wave Zone
Deepwater Lowering Operation
Landing on Seabed and Retrieval

Practice in Offshore Industries


16 September 2014

Offshore Lifting for Subsea Equipment

65

Practice in Industries

BREAEMAR
OFFSHORE

Case Studies:
Technip
Manifold and Spool Installation

Chevron Makassar Franklin Offshore


Suction Pile Installation

16 September 2014

Offshore Lifting for Subsea Equipment

66

Practice in Industries

BREAEMAR
OFFSHORE

Technip - Manifold and Spool Installation Preparation for Offshore Lifting


Structures

- Manifold 175 Te
- Spools (OD 4, 6, & 10)

Installation vessel

- Skandi Arctic (LOA 156.9 m)


- 400 Te box boom crane NOV
- 58 Te knuckle boom crane

Specific requirements

Presence of drill rig

Engineering tools

- Incident Analysis and Feedback (IAF)


- AutoCad
- Simulation of Marine Operation (SIMO)
Installation analyses : - Splash Zone (slack sling, crane capacity),
- Crane tip motion for landing criteria
(position, velocity & acceleration)
- Ship Maneuvering Simulator Centre (SMSC)

16 September 2014

Offshore Lifting for Subsea Equipment

67

Practice in Industries

BREAEMAR
OFFSHORE

Technip - Manifold and Spool Installation Preparation for Offshore Lifting


Equipment on
vessel

16 September 2014

For controlling the load:


- Lift-off : Endless rope taglines (riggers)
- In air : Tagging towers with winches + Crane tugger winches
- Landing : Guidewire winches + Clumpweight

Offshore Lifting for Subsea Equipment

68

Practice in Industries

BREAEMAR
OFFSHORE

Technip - Manifold and Spool Installation


Lifting offshore - Different phases of subsea lift

Toolbox talk
Seafastening
Lift-off from deck
Slewing / overboarding
Through the splash zone
Landing phase
Recovery to deck

16 September 2014

Offshore Lifting for Subsea Equipment

69

Practice in Industries

BREAEMAR
OFFSHORE

Technip - Manifold and Spool Installation


Lifting offshore - Different phases of subsea lift
Toolbox talk

16 September 2014

Installation procedure / work plan


Lift plan & rigging specifications drawing
Deck layout
Contingency operations
Experiences from load-out

Offshore Lifting for Subsea Equipment

70

Practice in Industries

BREAEMAR
OFFSHORE

Technip - Manifold and Spool Installation


Important aspects when planning and executing offshore
lifts:

Deck layout, slewing path


Winches for controlling loads in air
Crane capacity curves, also for recovery (alarm settings)
Communication with offshore personnel
Learn from mobilisation (crane settings, ballasting requirements, load
handling)
HSE Plan to avoid working at height and under suspended loads
Contingencies plan

16 September 2014

Offshore Lifting for Subsea Equipment

71

Practice in Industries

BREAEMAR
OFFSHORE

Chevron Makassar Franklin Offshore


Suction Pile Installation
Preparation for Offshore Lifting
Structures

Suction pile (to be installed)

Installation vessel

- Bourdon Oceanteam 104 (LOA 136.6 m)


- 250 MT at 10m radius (at 1.3 DAF). Located at portside
- 90 MT at 13m radius (at 1.6 DAF). Located at stern

16 September 2014

Offshore Lifting for Subsea Equipment

72

Practice in Industries

BREAEMAR
OFFSHORE

Chevron Makassar Franklin Offshore


Suction Pile Installation
Vessel Description

16 September 2014

Offshore Lifting for Subsea Equipment

73

Practice in Industries

BREAEMAR
OFFSHORE

Chevron Makassar Franklin Offshore


Suction Pile Installation
Major Equipment & Material List

16 September 2014

Offshore Lifting for Subsea Equipment

74

Practice in Industries

BREAEMAR
OFFSHORE

Chevron Makassar Franklin Offshore


Suction Pile Installation
Procedures:
Site arrival
DP and USBL preparation
Pre-check and preparation activities
As-found survey
Pre-deployment preparation
Suction pile over-boarding
Suction pile selft-penetration
Suction pile

16 September 2014

Offshore Lifting for Subsea Equipment

75

Practice in Industries

BREAEMAR
OFFSHORE

Chevron Makassar Franklin Offshore


Suction Pile Installation
Contingencies Plan:
Vessel breakdown
Equipment breakdown
Suction pile positioning and penetration

16 September 2014

Offshore Lifting for Subsea Equipment

76

Practice in Industries

BREAEMAR
OFFSHORE

Chevron Makassar Franklin Offshore


Suction Pile Installation
Several issues not covered in DNV-RP-H103:
Overpressure for retrieval (lower bound upper bound)
Refusal on penetration
Expected Self penetration

16 September 2014

Offshore Lifting for Subsea Equipment

77

Practice in Industries

BREAEMAR
OFFSHORE

When planning Marine Operations,


remember to take into account ....

16 September 2014

Offshore Lifting for Subsea Equipment

78

Practice in Industries

BREAEMAR
OFFSHORE

Easy handling...

16 September 2014

Offshore Lifting for Subsea Equipment

79

Practice in Industries

BREAEMAR
OFFSHORE

... And survey access!!

16 September 2014

Offshore Lifting for Subsea Equipment

80

You might also like