1.ContractAdministrationIssues
Thefollowingkeyissuesaretobeaddressedduringtheconstructionphase.
HealthService/AgencyPM(LiaisonOfficer)
WhenaHealthserviceoragencyisthePrincipal,theyshouldappointanagencyprojectmanagerwhowillact
asaliaisonofficer.Thispersonwillbetheprincipalpointofcontactforthecontractor/builderand
Superintendentandassistinprogramming,scheduling,dealingwithissuesofmaintaininghealthservice
deliverywhereworksareoccurringincludingaccessissues,commissioning,decanting,visits,openingsand
furnitureandequipmentselection.
Forlargeand/orcomplexprojects,particularlywherefacilitieswillneedtoremainfunctioningandoccupiedby
thePrincipalduringtheconstructionperiod,theliaisonofficermayneedtobeafulltimeappointment.
ConstructionInsurance
Itisessentialthattherelevantpartiesarecoveredbyinsuranceforbuildingaspectsduringtheconstruction
process,includingexistingbuildings,theworksandpublicliability.
Normally,theDepartmentarrangesPrincipalControlledInsuranceforthebuildingworks.Thestandardformof
contractAS21241992providestheoptionforthePrincipaltotakeoutsuchinsurance.Theinsuranceis
takenoutwiththeVictorianManagedInsuranceAuthority.
NotethatDepartmentalapprovalisrequiredpriortoanycapitalprojectdeviatingfromthenormalpracticeof
usingPrincipalControlledInsurance.
ThisPrincipalControlledInsurancecoverscontractworks,andpublicliability,includingallequipmentincludedin
thecontract.Thisextendstocomponentspreparedorassembledoffsite.Howeverthecoveragedoesnot
includeareasnotdesignatedinthePrincipalControlledInsurancepolicydocument,suchasthecontractors'
plantandvehicles,asbestosremoval,majordemolition,thecontractor'sandsubcontractor'spersonnel,tools
etc.TheBuilder/ContractoristorefertothePrincipalControlledInsurancepolicyfordetails,including
excessesandclaimsetc.
ThePrincipalortheSuperintendentshouldclearlyadvisetheContractorthattheexcessunderthePrincipal
ControlledInsurancearrangementsistotheaccountoftheContractor.RefertotheConstructionInsurance
Guidelineforfurtherdetails.
ProvisionalSums&Quantities
Thefinalcostofaconstructioncontractmaybeinfluencedbyprovisionalsumsandquantities.Aprovisional
sumisanominatedamountofmoney,usuallyestimatedbyaQuantitySurveyor,wheretheexactscopeand
costofspecificworkcannotbedeterminedatthestartofthecontract,suchasforremovalofrock.
Itisincludedintheoriginalcontractsum,butismonitoredcarefullysothatthesumcanbeadjustedas
required.Theprovisionalsummaybeusedforworkcarriedoutbysubcontractorsorformaterialsand
componentstobeprovidedbysuppliers,orforscheduleofratesworks,whereanagreedpriceratehasbeen
reached(e.g.$30/sqmforplasteringexistingdamagedwalls).Theseitemsareincludedwherenofirmprice
canbeobtainedorthefullextentoftheworkcannotbedeterminedatthetimethebuildingcontractislet.
Page 1 of 10
Generated at 17-Nov-2014
22:32:43 PM
PreferredSubContractors/Suppliers
TheDepartmentPolicy
TominimiserisktothePrincipal,theDepartmentrecommendsthatallsubcontracts,includingmechanicaland
electricalthatcanoftenrepresentalmosthalfoftheprojectsbudget,betenderedasacomponentofthemain
contract.Nominatedsubcontractsarenotrecommendedastheyblurrisks,liabilitiesandresponsibilitiesand
shouldbeavoidedwhereverpossible.
ConsiderationwillnotnormallybegivenbytheDepartmentfortheinclusionofnominatedorrecommended
subcontractors/suppliers.
ArecommendationcanbemadetotheDepartmentutilisingthismethodofsubcontractinghoweveritmust
clearlydemonstratewithdocumentedreasonsshowingthattheprojectwillbenefitgreatlyandthatthe
proposalissupportedbythePrincipal/agencyandSuperintendent.Exceptionswillgenerallybeconsidered
onlyif:
l
Thereisaclearindicationthattheequipment/tradebeingspecifiedcanonlybesuppliedbythe
nominatedcompanies.
Sitespecificconsiderationssuchasintegrationofspecialistworkswithsafety/firesystems.
ContractPosition
IfapprovedbytheDepartment,theSuperintendentmayproposetonominateparticularsubcontractorsor
suppliers,wheresuchworkorproductsarerecommendedtobeincorporatedinthebuilding.However,the
Governmentsupplypolicyrequirementsmustalwaysbeconsidered.Thismeansthattheselectionand
approvalofsubcontractorsorsuppliersshouldbemadeonacontestablebasis,allpartiesaretreatedfairly
anddecisionsbebasedonusingassessmentcriteriasuchasfitforpurposeandbestvalueapplicabletoall
submissions.
TheContractormaycalltendersorobtainquotationsforsubcontractsandsupplies.Whereexistingservice
providershavesufficientexpertiseandcapacity,theyshouldbegiventheopportunitytotenderforsub
contractwork.
TheSuperintendentmakesrecommendationstotheSteeringCommittee/PCGforendorsementofthe
recommendedsubcontractor/supplier.TherecommendationisnormallybasedontheContractor's
recommendation.ThisisbecausetheContractorisultimatelyresponsibleforworkandmaterialsorproducts
ofallthesubcontractors&/orsuppliers.
Options
Thereareoptionsforengaging&appointingsubcontractors/suppliers.
l
AseparatetenderisinvitedandthesuccessfultendererisnominatedtotheBuilderforinclusioninthe
Contract.Inthisinstance,thefirmisaNominated'SubcontractortotheContractor.
Alistofapprovedsubcontractors/suppliersisincludedinthetenderdocumentsadvisingtheBuilderthat
theyareresponsibleforobtainingquotationsfromtheapprovedorequivalentfirms.Inthisinstancethe
firmisselectedbytheBuilder.
TheDepartmenthasnoobjectiontotheengagementofselectedsubcontractors/suppliers.Experiencehas
shownthattheuseofselectedsubcontractors/suppliersislesslikelytoleadtocontractualdisputes.
Page 2 of 10
Generated at 17-Nov-2014
22:32:43 PM
Payments
ContractSum
UndertheContractrequirementsofAS21241992,thePrincipalagreestopaytheContractorastated
amountorlumpsumforcompletionoftheworks,subjecttotheprovisionsofthecontract.Thislumpsumis
knownasthe'ContractSum'.
ChangestotheContractSummayoccurasaresultofvariations,arisingfromrequestsforamendments,
Page 3 of 10
Generated at 17-Nov-2014
22:32:43 PM
Variations
AvariationcanbestbedefinedasThechangeormodificationofthedesign,qualityorquantityoftheworks
ortheadditionoromissionorsubstitutionofanywork,materialsorgoods'.
VariationscanonlybeimplementediftheSuperintendentissuesaninstructioninwriting.Variationsmayoccur
becauseof:
l
l
l
CorrectionoferrorsandomissionsintheContractdocuments
Site/buildingconditionsdifferingfromthosedescribedintheContractdocuments
ChangerequestedbythePrincipal(theseshouldbekepttoanabsoluteminimum).
Somevariationsentailcostand/ortimeadjustmentstothecontract.Suchvariationsshouldbepricedbythe
Page 4 of 10
Generated at 17-Nov-2014
22:32:43 PM
ContractSumAdjustments
AContractSumadjustmentisamonetaryadjustmenttotheinitialContractSum,duringthecourseofthe
contract.
ThefinalContractSum,afterContractSumadjustment,maybeforahigherorloweramountthantheoriginal
ContractSum',dependingonthenatureoftheadjustment.
SomeContractSumadjustmentsmayoccurasaresultof:
l
l
l
l
l
l
Approvedvariations
Superintendent'sinstructions,orlackofthem
DiscrepanciesarisingfromquantitiesspecifiedinthecontractortheBillofQuantities
ChangestoAuthoritylevies
Unexpectedsiteconditions(latentconditions)or
Provisionalsumsincludedinthecontractbeinginsufficientorexcessivefortheactualcostofthechosen
productorworkactivity
Variationsmaycauseareductionorincreasetotheoriginalscopeofthecontract.
ContingencySum
Acontingencyamountshouldnormallybeallowedinthebudgetfornewandrefurbishmentworks.The
SteeringCommittee/PCGcansetaseparateamountdependingonthespecificsoftheproject.Theamount
shouldneverbedisclosedorstatedinthetenderorcontractdocumentsnorshouldthisinformationbe
providedtopartieswhomaycommunicatewiththeContractor.ThissumisavailablesolelyforthePrincipalto
managerisksandisintendedtocoverthecostofunknownsorunforseenmattersthatmayariseand
adjustmentsfordiscrepanciesinthedocuments.Theamountisnotavailableforincreasesinthescopeofthe
project.
ContingencyisakeyelementtobeestablishedandmanagedbytheSteeringCommittee/PCGtoensurethe
projectisconstructedappropriatelyandwithintheallocationprovidedbytheDepartmentofTreasury&
Finance.
TheprojectbudgetincludescontingenciesthataretobeapprovedbytheDepartmentfollowingendorsement
bytheSteeringCommittee/PCGwhoshouldassesstheneedtousethecontingenciesbasedona
recommendationfromtheSuperintendent.
WorksProgramming
TheContractorisresponsiblefortheprogrammingoftheworkstoachievecompletionwithinthecontract
period.Theconstructionprogramsequencescontractactivitiesandtrades,showingdurationsand
dependenciesandtheexpecteddatesforachievementofmilestonessuchasstructurallockup',services
Page 5 of 10
Generated at 17-Nov-2014
22:32:43 PM
ExtensionsofTime
Foravarietyofreasons,acontractormaybeunabletocompletetheWorksbythedatestipulatedinthe
contract.ThedelaysmaybeoftheContractor'smakingorattributabletocircumstancesbeyondthe
Contractor'scontrol.Whenthelatteroccurs,theContractorisentitledtoanextensionoftimetothecontract
period,asjustifiedagainsttheconstructionprogram.
Therearetwotypesofextensionsoftime.Those:
l
l
Withoutcostimplication
WithcostimplicationsthesearecalledProlongation.
Generally,extensionsoftimewouldnotleadtoanincreasedcost.Wherethedelayisduetotheactionsofthe
Principal(client)whichthereforeaffectstheprogrammedcriticalactivities,thentheContractorhasan
entitlementtoreasonablecostsfordelay..
Causesofdelaymayincludethefollowing:
WithoutCostImplicationstotheContract
l
l
l
Industrialdisputese.g.StatewideorNational
Inclementweather
Delaysinreceivingpermitsandapprovalsfromauthoritiesorutilitycompanies.
PotentialforCostImplicationstotheContract
l
l
l
DelaysbytheSuperintendentingivinginstructionsorresponsestothecontractor
Majorvariationstoconstruction,planningordesignapprovedbythePrincipal
Instructionstodeferordelayaportionorthewholeoftheworkduetooperationrequirementsofthe
HealthService/Agency.
Notethat:
l
Unexpectedsiteconditions(incertaincircumstances,costsmaybeapplicable)mayfallintoeither
category
Itisnotalwayseasytodetermineifaparticulardelaywillwarrantanextensiontothetimeofthe
contract.TheSuperintendentmayrequestthattheContractorjustifyclaimsforextensionoftime
throughthepresentationofarecent(nomorethan14daysold)criticalpathprogram/diagramforthe
contractworks.
PracticalCompletion
Theterm'PracticalCompletion'describesthestagewhen
l
l
theworkhasbeencompleted,allequipmentinstalled,testedandfoundtobeinrunningorder,
theprojectisdeemedsafeandfitforoccupationtothesatisfactionoftheSuperintendent.
Page 6 of 10
Generated at 17-Nov-2014
22:32:43 PM
thefacilityisfitforitspurpose,complieswithservicedeliveryperformancerequirements,and
thefacilitycommissioninghasbeenundertaken
operationandmaintenancemanuals,traininganddocumentationhavebeenprovided.
TheAustralianStandardcontractAS21241992providesthattheSuperintendentmayissueacertificate
statingadatethat,intheSuperintendent'sopinion,thebuildingworksarePracticallyComplete',meaning
thatallworksarecomplete,withtheexceptionofminoromissionsanddefectswhichwillnotaffecthandover
to,andoccupationby,thePrincipalandfacilityusers.Atthistimethefinalisedworksarehandedovertothe
HealthService/AgencywithnecessarydocumentationincludingaCertificateofOccupancy,operationmanuals,
warrantiesetc.
PracticalCompletiondoesnotrelievethecontractorfromtheneedtorectifyomissionsanddefectsinatimely
manner,anditisimportantthattheSuperintendentcloselymonitorsprogressonrectifyingomissionsand
defects.
ItisimportanttodetermineandadvisetheDateofPracticalCompletionforitscontractualimplications.
Othercontractualeffects,whichoccuratthetimePracticalCompletionisreached,arethe:
l
l
Beginningofthedefectsliabilityperiod
Contractualendtothecontractor'sliabilityforliquidateddamagesorthePrincipal'sliabilityfor
prolongationcosts
Partialreductionofsecurityorbankguarantee,requiredunderthecontract.
WhereaprojectcontainsSeparablePortions',applythePracticalCompletionindividuallytoeachofthe
separableportionsunderthecontract.
ThePrincipalhasnocontractualrighttooccupyanypartoftheworksarea(portionofthesiteforwhichthe
contractorisgivenpossessionforthepurposeofexecutingtheconstructionworks)beforePractical
CompletionwithouttheconsentoftheContractor.TheDepartmentrequiresthatoccupationoccuronly
followingtheissueofaCertificateofOccupancy.
AfullinspectionpriortoissueofaPracticalCompletioncertificateisnecessary.Ifthefacilityisnotsuitablefor
occupancy,afollowupinspectionwillberequiredfollowingremedialworksbythecontractor.
AnomissionsanddefectslististobepreparedbytheSuperintendentandprovidedtotheContractorat
PracticalCompletion.Itshouldonlycontainminoromissions&defectsthatdonotrestrictthefacilitybeing
usedforitsintendedpurposeorrequireclosureforrestorativeworks.
LiquidatedDamages
Underthecontract,iftheContractorfailstobringtheworkstoastageofPracticalCompletionbythedue
date,(i.e.thedatestatedinthecontract,adjustedforanyagreedextensionsoftime)thenthePrincipalis
entitledtoLiquidatedDamages(LDs).TheamountofLDsissetoutinthecontractatthestartoftheproject
andmustbejustifiable(seebelow).
Itisimportantthatalltimebasedcontractualissuesrelatedtovariationstotheoriginalscopeofworksand
otherdelayshavebeenresolvedpriortotheapplicationofLDs.
LossesandcostsduetodelaycanbeclaimedattheratestatedinthecontractbytheHealthServiceor
Agency,providingthecorrectstepshavebeenfollowed.Thenominatedamountsmusthavebeenagenuine
pretenderestimateofcostsandmustbeabletobesubstantiated.Forexample,thecostofengagingan
alternativefacilitytodeliverhealthservicesorcostsassociatedwithcontinuingtousetheexistingfacilities.
Asaminimum,LDsmaybebasedonthecapitalinvestmentatthelongtermbondrate,plusanallowancefor
additionalcostsofmaintainingtheSuperintendentandotherConsultantsforanextendedperiod.
Page 7 of 10
Generated at 17-Nov-2014
22:32:43 PM
ProlongationCosts
Inthestandardcontractformthatgovernstheusuallumpsum'buildingcontract,thebuilder/contractoris
responsibleforthemajorityofrisks.However,delaysandcostsmayresultfromthePrincipal'sinstructions
causingadelay.SuchdelaysincludeadelayinmakingdecisionsorinprovidinginformationtotheContractor
ormayarisefromexcessiverequestsforvariationsandchangestobemade.
TheContractormaybeentitledtoclaimcompensationunderthecontractfordelayscausedbyothers,egthe
SuperintendentorPrincipal.Theclaimmaybeforidleequipment,staffandoverheadse.g.scaffoldingplant,
cranes,foreman'stime,officesandshedsdisruptionsoftheprogramstorageandothercosts.
TheSuperintendentistonotifythePrincipalandProjectControlGroupifsuchanissuearisesandthemajor
costimplicationsinvolved.ProlongationclaimsshouldbevaluedbytheQuantitySurveyoranddeterminedto
beclearlyjustifiablepriortoendorsementbytheSuperintendent.Departmentapprovalisrequiredofall
prolongationcostclaimspriortotheiracceptance.
SecurityandRetentionMoneys
ToensurethattheContractorperformsinaccordancewiththeContract,thePrincipalshouldrequestan
appropriateformofguaranteefromtheContractor.
Themostcommonformsofguaranteesare:
l
Security(PreferredOption)TheacceptancefromtheContractorofanunconditionalbankguarantee.
Similarformsofsecuritymaybeconsidered.Theamountisequivalenttotheamountstatedinthe
contractandisheldbythePrincipalshouldtheContractordefault.Theamountofsecurityisnormally
setbyassessingfinancialrisk.Anindustrystandardminimumis5%oftheContractSum
Thenormalpracticeisforsecurity,intheformofabankguarantee,tobeprovidedtothePrincipalfollowing
tenderacceptance,andpriortositepossessionbythecontractor.Itisheldintwoequalparts.Halfisnormally
releasedatPracticalCompletionandthebalancewhenFinalCertificateisissuedafterthedefectsliabilityperiod
hasfinished.
Thisformofguaranteeisrecommendedforallcontractsinexcessof$1Musingthestandardformavailable.
ThebalanceofsecuritymustbereleasedontheissueoftheFinalCertificate.
l
RetentionMoneys(NonPreferredOption,butmaybeapplicabletoverysmallcontracts,generally
below$50,000.)Apercentage(upto10%)oftheamountdueoneachprogresscertificate(payment)
isretaineduntilastatedsumisreached.ThissumisasafeguardforthePrincipalshouldtheContractor
default.Itisknownastheretentionamount.Normallythetotalretentiondoesnotexceed5%ofthe
ContractSum.HalfoftheretentionisnormallyreleasedtotheContractoronissuingthenoticeof
PracticalCompletionandthebalancewhentheFinalCertificateisissued(afterthedefectsliabilityperiod
hasfinished).
DefectsLiability
ThedefectsliabilityperiodistheperiodstatedintheContractthatprovidesfortherectificationofminor
defectsand/oromissionsoritemsthatfailtoperformsuitably,thatmaybeoutstandingoroccurafter
PracticalCompletion.ThePrincipal,SuperintendentandContractorstillhaveobligationsandrightsduringthis
Page 8 of 10
Generated at 17-Nov-2014
22:32:43 PM
FinalCertification
UponcompletionoftheDefectsLiabilityperiodtheSuperintendentissuesaFinalCertificateonthebasisthat
theContractorhasrectifiedalloutstandingomissions/defectsaccordingtothecontract.Thisusuallyinvolves
afinalinspectionbyallparties.
IssuesRequiringSpecialAttention
Consultantsaretoensurethatthecontractdocumentationisclear,anddrawsattentionofcontractorsto
theseimportantphasesofprocurement.Keyissuesofconcerninclude:
l
WorkinanOperatingFacility:
Awarenessoftheimpactonhealthandrelatedservicesbeingdeliveredbyconstructionactivitiesinvolving
essentialservices,access,infectionandnoisecontroletc.isvital.Measurestomitigaterisksorreduce
negativeeffectsneedtobesetoutbythePrincipalandSuperintendentforprojectswhereconstructionwork
isbeingundertakeninanoperatingfacility.
l
CommissioningPeriod:
TheContractadministratorshouldbeawareofthenecessityofallowingfortwocommissioningperiods.
l
Period1fortheContractoranditssubcontractorstoensureoperabilityofbuildingsandservices
tocomplywiththecontract'sTechnicalPerformanceRequirements'.
Period2forthecontractortorecommissionfollowinghandovertoandoccupationbyusersof
thefacilitytoensureproperperformanceinaccordancewiththeiruserrequirements,following
occupancy.
CertificateofOccupancy:
Toobtainthiscertificatethemaintenancemanualrequirementsmustbetakenintoaccount,whichincludesthe
maintenanceofessentialservices,plusreportingandrecordingrequirements.
UndernocircumstancesisafacilitytobehandedoverwithoutanoperationmanualbeingprovidedforHealth
Service/Agencyuseaswellasallemergencybackuparrangements.
l
EnvironmentalSustainability:
Variousenvironmentalissuesmustbecontrolledandmonitoredduringconstruction,suchasuse/wasteof
water,recyclingofmaterialspowerandotherservices,dustandnoisegenerationandstormwaterrunoff
fromthesite.
Page 9 of 10
Generated at 17-Nov-2014
22:32:43 PM
Checklists
ContractAdministrationChecklist(pdf,31.1KB)
TheContractAdministrationchecklististobecompletedandsignedwitheachprojectandsenttothe
appropriateDHSProjectManager.
Examples
Thesearetheexamplesthatrelatetothecontentofthisguideline.
ExampleFiles
LetterofNominationofSuperintendent(MSWord,27.0KB)
ThisletterisatemplatethatshouldbeusedtoassistinnominatingtheSuperintendent.
MonthlyReportsSiteMinutes(MSWord,92.5KB)
SiteMinutesaretobecompletedaspartofthemonthlyreport.
ContractAdministrationCostVariationsExample(MSWord,37.0KB)
TheCostVariationsformistobecompletedasrequiredforpaymentpurposes.
ContractAdministrationProgressFinancialStatus(MSWord,23.0KB)
TheProgressFinancialStatusFormistobecompletedbytheQuantitySurveyorandsubmittedwiththe
monthlyreport.
ContractAdministrationSampleProgressClaim(MSWord,42.5KB)
TheProgressClaimformistobecompletedtoreceivepayment.
ContractAdministrationSampleVariationForm(MSWord,61.0KB)
TheVariationsformistobecompletedasrequiredforvariationpurposes.
ContractAdministrationSampleProgressCertificateForm(MSWord,23.0KB)
TheProgressCertificateFormverifiesthatworkshavebeencompletedandpaymentcanbeprocessed.
ContractAdministrationCapitalPaymentClaimForm(MSWord,181.5KB)
TheAgencycompletesthisformaspartofthepaymentprocess.