You are on page 1of 23

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Division 15 - Mechanical
AIR CONDITIONING SERVICES
Unless otherwise stated, the work shall pertain to the secondarydesign, supply,
installation, testing commissioning, warranty &maintenance of the following
works. Where quantities have not beenincluded , the contractor shall indicate
the quantities as per his own take off from the Tender document.
15.1

Air Handling Units complete with all connections, valves, filters, accessories
and fittings, as per Schedule in Particular specifications.

Nos.

15.2

Fresh air handling units completed with all connections, valves, filters, heat
exchangers, heat pipes, electrical heaters, accessories and fittings as per
Particular Specification.

Nos.

15.3

15.4

Control system for the Air Conditioning system, including all control valves,
sensors motorised dampers, motorised valves, DDC controls, MCC's etc.
complete as detailed in "Schedule of Controls"of the Particular Specifications.

Item

Fan coil units completed with all connections, valves, secondary drain apns,
etc. as per "Schedule of Fan Coil Units"of the Particular Specifications.

Nos.

185

15.5

Fan Coil units (dual coil) for ICUs and recovery rooms with standby DX
condensing units including refrigerant piping and all accessories as specified
in particular specifications.

Nos.

15.6

Close circuit unit and MDF rooms with standby DX coil and condensing unit
including refrigerant piping and accessories as specified in particular
specifications.

Nos.

15.7

Fire dampers with access panels in ducts at all duct entry & exits from plant
rooms as well as fire wells/zones and motorized fire dampers and motorized
smoke dampers as shown on drawing.

Item

15.8

Volume control dampers at all branches.

Item

15.9

No.

15.9.1

FANS
Basement ventilation and exhaust fans complete with required controls and
accessories as specified.

15.9.2

No.

Extract air fans with motorized volume control damper as shown in drawings
and relevant controls as specified.

No.

15.9.3

Kitchen makeup air fans with filters as specified.

No.

15.9.4

Upblast fans as shown on the drawing and as specified

No.

15.9.5

Pressurization fans with chilled water coil and VFD with associated controls
as specified.

No.

15.9.6

Smoke extract air fans with associated controls as specified.

No.

15.1

Condensing units with refrigerant piping and all necessary controls and
accessories for operation theatre Air Handling Units.

No.

15.11

Window A/Cs (Drip free type)

Nos.

15.12

Chillers, screw compressors as specified. (25 tons each)

Nos.

15.13

3 duty/1 standby CHW primary pumps complete with all connections, valves,
test points, gauges, header and fittings and controls.

Item

15.14

2 duty/1 standby CHW secondary pumps with VFDs complete all


connections, valves, test point, gauges, header and fittings and controls.

Item

15.15

Chilled water pressurization unit set complete with pumps,pressurization


vessel, connections, valves and control panels.

Item

LS

15.16

Pump control panel

Item

LS

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Total Amount of Page


Cont. Division 15 - Mechanical
15.17

Manual chemical dosing pot

Item

LS

15.18

Smoke extract system complete with smoke extract fans, smoke curtain and
powered ventilator interfaces with building FA system as specified.

Item

LS

15.19

Chilled water piping with insulation and all accessories including isolating
valves on supply & balancing valve on return, all as specified, with hangers,
support, fittings etc 300mm dia pipe.

15.19.1
15.19.2
15.19.3
15.19.4
15.19.5
15.19.6

200mm dia pipe


150mm dia pipe
125mm dia pipe

M
M
M

LS
LS
LS

100mm dia pipe


80mm dia pipe
65mm dia pipe

M
M
M

LS
LS
LS

15.19.7
15.19.8

50mm dia pipe


40mm dia pipe

M
M

LS
LS

15.19.9

32mm dia pipe


15.19.10 25mm dia pipe

M
M

LS
LS

15.19.11 20mm dia pipe


15.19.12 15mm dia pipe
15.19.13 Isolating valve & balancing valves at all branches from main line

LS

M
Item

LS
LS

Sheet metal ductwork including accessories (dampers, splitters, flexible ducts,


plenum boxes) and fittings complete with insulation as detailed on drawings,

M2

5100

Grilles/Diffusers as per drawings including:


* Ceiling diffusers in areas with false ceiling
* Linear slot diffusers for front of house corridors
* Sidewall grilles and registers
* External louvers including sand trap louvers
* 600 x 600 Egg crate grille

Item
Item
Item
Item
Item

LS
8

15.20

15.20.1
15.20.2
15.20.3
15.20.4
15.20.5
15.21

Sound attenuators for supply, extract & return air systems ductwork as
required to maintain specified NC level within all conditioned spaces.
Door louvres as required & where shown on drawings
Noise and vibration control for the following equipment including inertia
basis, vibration isolators, flexible connectors etc for
*
*
*
*

Item
Item

150

Item

LS

Air Handling Units


Chilled water pumps
Chillers
Fire pumps

15.22

Condensate drain piping for AHUs, FCUs and other A/C equipment as
required

Item

LS

15.23

Improving of power factor for all HVAC equipment and provision of UV


relays/timers as per DEWA requirements (if not corrected at MDB)

Item

LS

15.24

3rd party air balancing, chilled water balancing, testing & commissioning of
all HVAC plant, equipment & systems

Item

15.25

Chemical treatment of chilled water system including initial supply of


chemicals for warranty/maintenance period & manual chemical dosing system

LS
LS

Item

15.26

DDC controls & thermostats including BMS system as specified, complete


with required I/O's.

Item

15.27

Spare set of filters (one complete set off all filters to be handed over after
commissioning). The spare set to be used to exchange installed temporary
throw away filters during installation.

Item

15.28

Cutting, patching and other civil works related to MEP works

Item

LS

15.29

Scaffolding, hangers to support required for work execution.

Item

LS

DXB 06-13 Lotus Hotel


BOQ

LS
LS

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Item

LS

Unit Price

Total Amount

Total Amount of Page


Cont. Division 15 - Mechanical

15.30

List of spare parts, Client operator training, as built drawings, O & M


manuals, schematics, shop drawings and other such fabrication & close-out
documentation required by Client/Engineer.
Additional Items

15.31

The Tenderer is to attach this bill of quantities any additional items with
quantities, enumerated or itemised and rates which are not previously
included to complete the build-up of the lump sum tender price for this
section of the works. Should the Tenderer fail to insert any items here, it will
be deemed that his lump sum price for the tender includes all items either
shown on the drawings and described in the specification or deemed necessary
by the Tenderer to develop the drawings and specification to represent the
entire cost of the works and no subsequent claim for any additional item will
be entertained.

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Total Amount of Page


Division 15 - Mechanical

Total of HVAC System


Page 1
Page 2
Page 3
Page 4

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Total Amount of Division


WATER SERVICES

15.32

15.32.1

15.33

Unless otherwise stated, the work shall pertain to the secondary design,
supply, installation, testing, commissioning, warranty & maintenance of the
following works. Where quantities have not been included, the contractor
shall indicate the quantities as per his own take-offs from the Tender
document.
Incoming water supply connection to provisions made available in plant room,
as shown on drawing W-01.

Item

Gas fired central water heaters as per "Schedule of Water Heaters of the
Particular Specification complete with interconnecting valves, fitting and
accessories.

Nos.

L/S

15.34

Installation of sanitary fixtures, complete with all fittings, trim, accessories as


stated. Contractor to include for final flex connection, angle CP vlaves, waste
connections (where exposed etc. all as per specification requirements).

Item

15.35

Hose bibs with integral vacuum breaker & hose end adaptor

No.

15.36

Domestic Water distribution pipework complete with insulation fittings,


valves, supports and accessories as per Specifications and drawings.

15.36.1

Domestic cold water pipework complete with fittings, valves supports and
accessories as per Specifications and drawings.

Item

15.36.2

Domestic cold water & hot water PEX piping within toilets & kitchens
complete with valves, distribution boxes, headers/manifold etc.

Item

15.37

Cold water with shut off valve (Basement)

Item

15.38

Disinfection of complete water supply system

15.39

Transfer water pumps complete with all valves

Nos.

15.4

28 C Booster pumps (1 duty/1 standby assist/ 1 jockey) complete with all


valves, test points, headers, pressure gauges, pipe work, fittings, VCDs, VFD
and accessories including pressure vessel as specified.

Nos.

15.41

CWS Booster pumps (1 duty/1 standby assist/1 jockey) complete with all
valves, test points, headers, pressure gauges, pipe work, fittings, VCDs, VFD
and accessories including pressure vessel as specified.

Nos.

15.42

Hot water recirculation pump set (1 run/1 standby) with valves and
accessories and controls

15.44

Pump control panels.

item

15.45

Heat exchanger for 28C water storage for 28C water supply ass per
specifications

No.

15.46

Heat exchanger for 10C water supply as per specifications

No.

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

15.47

Panel type water tanks 3 x 1.5 x 2.5mH for normal water storage including all
connections and accessories as per specifications.

Nos.

15.48

Panel type insulated water tank 3 x 1.5 x 2.5mH for 28C water storage
including all connections and accessories as per specifications

Nos.

Unit Price

Total Amount

Total Amount of Page


Division 15 - Mechanical
15.49

All shop drawings & close-out documentation including As-built drawings, O


& M manuals, schematic charts, etc.

15.5

Additional Items

15.51

Item

The Tenderer is to attach with this bill of quantities any quantities items with
quantities, enumerated or itemised and rates which are not previously
included to completethe build-up of the lump-sum tender price for this section
of the works. Should the Tenderer fail to insert any items here, it will be
deemed that his lump sum price for the tender includes all items either shown
on the drawings and described in the specification to represent the entire cost
of the works and no subsequent claim for any additional item will be
entertained.

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Total Amount of Page


Division 15 - Mechanical
WATER SERVICES
Total of Water Services
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Total Amount of Page


Division 15 - Mechanical
DRAINAGE SERVICES

15.52

Unless otherwise stated, the work shall pertain to the secondary design,
supply, installation, testing, commissioning, warranty & maintenance of the
following works. Where quantities have not been included, the contractor
shall indicate the quantities as per his own take-offs from the Tender
document:

15.53

Floor drains/clean outs/rain water outlet

No.

15.53.1

RWO

No.

15.53.2

FD-K in kitchen

No.

37

15.53.3

FD-K 1

No.

11

15.53.4

FD-P - Plant rooms

No.

14

15.53.5

FD-G - Garbaage room

No.

15.53.6

FD in toilets

No.

20

15.53.7

FD-TD Terrace Drain

No.

37

15.53.8

FT

No.

128

15.53.9

WCO with stainless steel access cover

No.

15.53.10 FCO with stainless steel access cover at floor deck.

No.

15.53.11 GT --Gulley Trap

No.

2
2

15.53.12

Manhole frames & cover for all manholes,external valve pits, gulley traps, etc.
(Civil work only by others)

Item

15.53.13

Condensate drain pipes complete with all fittings 19mm closed cell, insulation
with protective covering, accessories and supports

Item

15.53.14 CB-Catch Basin (Basement-3)

Item

15.53.15 CB-01 (Basements 1 & 2)

Item

15.53.16 Grease Trap - Type 'B"

No.

15.53.17 Oil interceptor

No.

15.53.18 Stop log for underground water tank

No.

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

15.54

Drainage piping, fitting and accessories, all as per drawings & specifications
in vertical & horizontal runs

Item

15.55

Acoustic lagging for all horizontal runs of DEWAge lines above occupied
spaces as specified.

Item

15.56

Sanitary drainage connections, soil waste & vest including final connections
to fixtures and stacks & horizontal runs at low and high level were shown for
all saanitary fixtures:

Item

15.57

MH vents pipe

Item

15.58

2 Nos. sump pit with sump pumps (SP1 to SP4)

Item

Unit Price

Total Amount

L/S

Total Amount of Division


Division 15 - Mechanical
15.59

Pressure brake MH

Item

15.60

Acoustically insulated Soil Waste pipe

Item

15.61

Sand trap

Item

15.62

Miscellaneous
DM approvals & coordination for same to obtain final permission to connect

15.63

Close-out documentation

Item
Item

DRAINAGE SERVICES
15.54

50MM WP

523

50MM VP

843

50MM KWP

20

80mm WP

320

80mm KWP

65

100mm WP

137

100mm SP

130

100mm VP

200

100mm RWP

41

150mm WP

455

150mm SP

318

150mm KWP

63

150mm RWP

105

200mm WP

114

200mm SP

117

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

150mm VP

52

FCO150mmO

No.

80mmO

110

Unit

10.755

Manhole Size 1200mm x 900mm

Unit Price

Total Amount

Grease trap type C floor mounted 800mm x 2400mm


Gutter channel 250mm width with grating cover
150mm O VP Vent cowl
100mm O VP Vent cowl
Total Amount of Division
Division 15 - Mechanical
Additional Items

15.64

The Tenderer is to attach with this bill of quantities any additional items with
quantities, enumerated or itemised and rates which are not previously
included to complete the build-up of the lump-sum tender price for this
section of the works. Should the Tenderer fail to insert any items here, it will
be deemed that his lump sum price for the tender includes all items either
shown on the drawings and described in the specification to represent the
entire cost of the works and no subsequent claim for any additional item will
be entertained.
Division 15 - Mechanical
DRAINAGE SERVICES
Total of Drainage Services
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Item

L/S

Item

20

Unit Price

Total Amount

Total Amount of Division


Division 15- Mechanical
FIRE FIGHTING SERVICES

15.65

Unless otherwise stated the work shall pertain to the secondary design,
obtaining approvals from Civil Defence, supply, installation, testing,
commissioning, warranty and maintenance of the following works: All
components to be UL listed or FM approved.

15.66

Sprinkler pipe as per NFPA 13 with threaded (up to 50mm) and victaulic end
fittings (65mm & longer)

15.67

Automatic zone control valves, flow switches, drain valves, supervisory


valves, etc. for system to comply with Civil Defence requirements.

15.68

Fire Hose reel cabinets with 30m hose 25 o, wet riser landing valve 65o &
protable extinguishers.

Item

15.69

Sprinkler for entire area as per Civil Defence requirements

Item

15.70

Protable extinguishers in plant rooms and other areas as shown. CO2 & dry
powder type as on Drawing. Generator rooms, cylinder rooms, etc.

Item

15.71

2 way breeching inlet cabinets

Item

Combined sprinkler & fire fighting pump set -- UL listed


a) Electric motor driven pump vertical turbine type
b) Diesel Engine driven pump vertical turbine type
c) Jockey pump

Item

1 set

15.72
15.72.1
15.72.2
15.72.3
15.73

With all associated valves, fuel oil tank etc and pump control panel.

15.74

FM200 system with associated controls, cylinders etc. as specified and as


shown on drawing complete with room integrity test

Item

15.75

CO2 system with controls as specified and as shown on drawing for fuel tank
room

Item

15.76

Fuel tank for fuel storage with fill line, discharge line, pumps with valves and
controls for filling of roof installed genset day tank.

Item

Additional Items

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

15.77

Description

Unit

Qty

Item

Recessed Pendant Sprinklers Head

Unit

275

Upright Sprinkler Head

Unit

245

Side Wall Sprinkler

Unit

83

4.5 Kg. CO2 Fire Extinguisher

Unit

20

4.5 Kg. Dry Powder Fire Extinguisher

Unit

13

4 Way Breeching Inlet Cabinet

Unit

The Tenderer is to attach with this bill of quantities any additional items with
quantities, enumerated or itemised and rates which are not previously
included to complete the build-up of the lump-sum tender price for this
section of the works. Should the Tenderer fail to insert any items here, it will
be deemed that his lump sum price for the tender includes all items either
shown on the drawings and described in the specification or deemed necessary
by the Tenderer to develop the drawings and specification to represent the
entire cost of the works and no subsequent claim for any additional item will
be entertained.

Unit Price

Total Amount

Total Amount of Division


Division 15 - Mechanical
Fire Fighting
15.69

15.70

15.71

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Total Amount of Division


Division 15 - Mechanical
FIRE FIGHTING SERVICES
Total of
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Total Amount of Division


Division 15 - Mechanical

15.78

LPG System
Supply, install, test & commission of LPG system comprising of:

15.79

LPG tank with all connections, valves and piping

Nos.

15.8

Vaporizer as per specifications

Nos.

15.81

Piping & fittings as per drawing

Item

15.82

Gas leakage detection system interfaced to FA system as specified

Item

15.83

As Built drawings, O & M manuals, schematics, shop drawings and other


such fabrication & close-out documentation required by Client/Engineer

Item

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Total Amount of Division


Division 15 - Mechanical
L.P.G. System
Total of LPG Systems
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Total Amount of Division


ELECTRICAL SERVICES

16.1

16.1.1

16.2

16.2.1
16.2.2
16.2.3
16.2.4
16.2.5
16.2.6
16.2.7
16.2.8
16.2.9
16.2.10
16.2.11
16.2.12
16.2.13
16.2.14
16.2.15
16.2.16
16.2.17
16.2.18
16.2.20
16.2.21

Unless otherwise stated, the work shall pertain to the secondary design,
supply, installation, testing commissioning, warranty & maintenance of the
following works. Where quantities have not been included, the contractor
shall indicate the quantities as per the Tender document.
Coordination with DEWA for the supply of power to LV panel installed under
this contract. Cable already existing from MDB to SMDB in Electrical room
as shown on the drawing.

Item

Switch Gear System


Complete with installation & termination of all outgoing cable to DBs.
MDB-1
MDB-2
MDB-3
SMDB-B3
SMDB-GF
SMDB-MF
SMDB-1F
SMDB-2F
SMDB-3F
SMDB-4F
SMDB-5F
SMDB-6F
SMDB-7F
SMDB-RF
SMDB-MDF
SMDB-CBS
SMDB-BK
SMDB-MK
ESMDB-GEN
DBs as per load schedule & drawings.

DXB 06-13 Lotus Hotel


BOQ

No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
Item

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item
16.3
16.3.1
16.3.2
16.3.3
16.4

Description
Capacitor Banks
Capacitor Bank-1
Capacitor Bank-2
Capacitor Bank-3

Unit

Qty

No.
No.
No.

1
1
1

No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
Item
No.

6
3
4
1
10
2
40
10
3
4

No.
No.
No.
No.
No.
No.
No.
No.
No.

94
25

No.

49

No.

Unit Price

Total Amount

Motor Control Centre


MCC complete with installation and termination of all outgoing cables to
equipment control devices etc.

16.4.1
16.4.2
16.4.3.
16.4.4
16.4.5
16.4.6

MCC-RF
EMCC - RF
MCC-Chiller
MCC-Pump
MCC B1
Uninterruptible power supply unit with battery

Total Amount of Page


Division 16 - Electrical
16.5
16.5.1
16.5.2
16.5.3
16.5.4
16.5.5
16.5.6
16.5.7
16.5.8
16.5.9
16.5.10
16.5.11

Load Distribution Switches


300 A TP W/P Isolator
160 A TP W/P Isolator
125 A TP W/P Isolator
100 A TP W/P Isolator
63 A TP W/P Isolator
40 A TP W/P Isolator
32 A TP W/P Isolator
25 A TP W/P Isolator
20 A TP W/P Isolator
20 A SP W/P Isolator
Control panels including starters, control devices, etc.
100 IP Isolator

16.6

Final sub-circuit and auxilliary installations


Cable and conduit in concelaed installations to the following:
16.6.1-a Socket Outlet 13A single switched socket
16.6.1-b WIP
16.6.3 Double pole switch
16.6.4 Connection point/outlet
16.6.5 13A single switched socket explosion proof
16.6.6 13A double switched socket
16.6.7 Spur outlet (W/P)
16.6.8 Lock off stop push button
16.6.9 15A socket outlet
20A DP (W/P) outlet with switch for water heater and with neon indicator
16.6.10
16.6.11
16.6.12

20A DP outlet with spur outlet and with neon indicated and marker for hand
dryer.
Connection point/outlet

DXB 06-13 Lotus Hotel


BOQ

70

46

No.
Section 01200 - BOQ
Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item
16.6.13
16.6.14
16.6.15
16.6.17
16.6.18
16.6.19
16.6.20
16.6.21
16.6.22
16.6.23
16.6.24
16.7

Description
Voice/data RJ45 outlets
Light switches complete with all accessories. IP56 for all plant rooms
Isolator (W/P) outlet with complete wiring and installation for equipment as
per drawing

Unit

Qty

Unit Price

Total Amount

No.
No.
No.

Floor box with no. 13A double socket + 2 RJ 45 socket and blank plate
compete installation and wiring.
Industrial TP and SP socket for equipment as per drawing
Lighting point
Switch point
Cable trays as required
Trunking as required
PVC ducts as required

No.
No.
No.
Item
Item
Item

Light switches complete with all accessories, brush stainless steel for
occupied areas

Item

35

No.
35

CCTV & Access Control


CCTV and Access control system complete with internal & external cameras
to be connected to, monitors located in secuirty guard room for video
monitoring of all perimeters & required internal areas. System to be
compatible with existing monitors and equipment located in existing security
guard room.

16.80

Structured Cabling System

16.8.1
16.8.2
16.8.3

Cat 6 Cable, patch panels & all and conduits in concealed and exposed
installations:
Telephone outlet RJ45
Data outlets RJ45
Main incoming connections form the existing Etisalat JRC manholes

Item

No.
No.
Item

22
20

No.

131

No.
No.
No.
No.

160
28
13
39

No.

Total Amount of Page


Division 16 - Electrical
16.9
16.9.1
16.9.2
16.9.3
16.9.4
16.9.5
16.9.6
16.9.7
16.9.8
16.9.9
16.9.10
16.9.11

Fire alarm control panel complete with necessary accessories, brackets and
fittings as per drawing and specifications.
Smoke detector
Smoke detector + buzzer
Heat detector
Optical detector
Sounder/sounder W/P
Manual call point
Fire alarm repeater panel
Allow for interface fire alarm system with fire fighting
Allow for interface fire alarm system with smoke panel
Allow for interface fire alarm system with lift
Allow for interface FA system with automatic doors

Allow for interface FA system with fireman's switch.

No.
No.
No.

16.10

Central Battery system & accessories

No.

16.11

Emergency light fittings with central battery backup (1x8w)

No.

163

16.12

Exit sign light fittings with central battery backup

No.

140

No.

262

No.
No.

36
297

16.9.12

16.12.1
16.12.2
16.12.3
16.13

Normal lighting fixtures with convertible kit to feed from central battery
system on emergency condition.
Analog abbressable break glass
Ceiling speaker (surface/recessed/wall mounted type)
2x9 W surface mounted circular light fittings on staircases with central battery
backup

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item
16.14
16.14.1
16.14.2
16.14.3
16.14.4
16.14.5
16.14.5.1
16.14.5.2
16.14.6
16.14.7
16.14.8
16.14.9
16.14.10
16.14.11
16.14.12
16.14.13
16.14.14

Description
All fittings IP21 except in toilets to be IP65, external to be weather proofed
and for riser storage & preparation and within paint booth areas to be sealed
type explosion proof fittings.
4 x 18W fluorescent light with louver
4 x 18W fluorescent tube fitting HF control gear weather proof
2 x 36W fluorescent tube fitting with diffused as B type
1 x 36W fluorescent tube fitting as BB type
Down lighters (1 x 18W)
Down lighters (2 x 9W)
2 x 9 surface mounted M.T.D. circular fluorescent light with PL lamp.
Mirror lights type K
2 x 36W fluorescent explosion proof type
1 x 50W wall mounted light fittings IP65
External lights, as per drawings
Main Distribution frame (By others). Etisalat charges directly by client.
Patch panels
Telephone manholes with covers
Twin voice/data RJ45 outlets
Diesel engine generator of rating with accessories and controls and load test.

Unit

Qty

No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.
No.

33

No.

Unit Price

Total Amount

222
3
12
45
56
9
39

1
1
1

Total Amount of Page


Division 16 - Electrical
16.15
16.15.1
16.15.2
16.15.3
16.15.4

Sundries
Earthing and Bonding system of all metal structure, all panels, mechanical
plant, etc.
Lighting protection system
Other work associated with external cabling
Allow for associated ducting for electrical and LV services.

Item
Item
Item
Item

Additional Items

16.16

The tenderer is to attach with this bill of quantities any additional items with
quantities, enumerated or itemized and rates which are not previously
included to complete the build-up of the lump-sum tender price for this
section of the works. Should the Tenderer fail to insert any items here, it will
be deemed that this lump sum price for the tender includes all items either
shown on the drawings and described in the specification or deemed necessary
by the Tenderer to develop the drawings and specification to represent the
entire cost of the works and no subsequent claim for any additional item will
be entertained.

DXB 06-13 Lotus Hotel


BOQ

Item

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Total Amount of Page


Division 16 - Electrical
Total of Electrical Services
Page 1
Page 2
Page 3
Page 4
Page 5
Page 6

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Total Amount of Division

Other works associated with MEP Services


Preparation of working drawings and carrying out the secondary
design associated with the preparation of the working drawings and
material/equipment submittals

Item

Testing & Commissioning

Item

Provision of O & M manuals, As-Built drawings

Item

Insurance as per contract conditions

Item

Warranty of works

Item

Coordination with local authorities and payments


14 months operation; attendace and maintenance of all MEP
installations

Item

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Total Amount of Division

Total Amount of Division 15 - Mechanical


Total Amount of Division 16 - Electrical
Mobilization

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37

NAGA

Issue for Tender Rev (0)

Architects Designers Planners


Dubai Atlanta Alexandria Amsterdam

Item

Description

Unit

Qty

Unit Price

Total Amount

Total Lump Sum Price in AED

DXB 06-13 Lotus Hotel


BOQ

Section 01200 - BOQ


Page 37 of 37