GENERAL GUIDELINES
Purpose/Scope

This work package encompasses all


requirements for installing the auxiliary
skid, to include foundation preps, setting
skid, connecting piping, ship-loose items and
grounding the skid.
Precautions
Only trained and authorized persons shall be permitted
to operate a hoist/crane. Lifting equipment shall not be
loaded beyond its rated load capacity. This includes
superimposed weight on load block or hooks and any
lifting devices such as chains and slings. If hoisting
equipment is used in placing and leveling equipment,
assure it is rated to support, as minimum, the total gross
weight of equipment to be lifted. Hoisting equipment
rated between two and four times the weight of
machinery to be lifted will provide a comfortable safety
margin.

Special Tooling - Equipment


Crane/Hoist
Hoisting Equipment
Transit and level
Shims
References
General Arrangement Main Unit xxx200
Lift Arrangement xxx225
General Arrangement Aux Skid xxx218
Isolator Details Auxiliary Skid
Isolator Installation and Commissioning Manual
Site specific sub skid engineering drawings
Suggested Manpower and Duration
1 Crane Operator
1 Rigger
1 Electrician
1 Millwright
1 Helper
Duration One day

TASK START DATE

Contractor Representative

TASK COMPLETION DATE

Customer Representative

GE Representative

Printed Name:

Printed Name:

Printed Name:

Printed Title:

Printed Title:

Printed Title:

GE Representative
Signature/Date:

Rev 0

Signature/Date:

Signature/Date:

Page 1 of 3

LM2500+ G4 LSPT Installation

IWP14

Auxiliary Skid Installation

GE ENERGY

PREREQUISITES
1.

Review drawings for isolator location

2.

Remove dust, oil, and foreign materials by sanding and/or wire brushing.

3.

Ensure all personnel are familiar with the planned lift sequence, and understand their
responsibilities.

INITIALS

DATE

NOTICE
INSTALL VIBRATION ISOLATORS IN ACCORDANCE WITH MANUFACTURERS
INSTRUCTIONS PRIOR TO SETTING THE AUXILIARY SKID. BELOW IS A GENERIC
REPRESENTATION OF A PROCEDURE FOR INSTALLING VIBRATION ISOLATORS
FOR FAMILIARIZATION PURPOSES. MANUFACTURERS RECOMMENDATION WILL
APPLY. EACH ISOLATOR HAS FOUR BOLT HOLES TO SECURE IT TO THE SHIP
BEDPLATE. FOR ALIGNMENT OF THE VIBRATION ISOLATORS, EACH ISOLATOR HAS
JACK BOLT HOLES FOR CUSTOMER-FURNISHED 5/8 JACK BOLTS THAT WILL
ADJUST THE HEIGHT, PITCH, AND ROLL.

TASKS

INITIALS

1.

Set vibration isolators true, and level shim as required. Height should be in
accordance with engineering drawings.

2.

Rig and lift the auxiliary skid. Inspect underneath and ensure there are smooth, clean
contact surfaces.

3.

Set auxiliary skid on X-Y center points

4.

Recheck levelness of vibration isolators after auxiliary skid has been set per
manufacturers instructions.

5.

Tighten securing bolts

6.

Remove jack bolts.

DATE

NOTICE
EACH VIBRATION ISOLATOR CONTAINS AN INTERNAL STOPPED STRUCTURE
INSIDE. INTERNAL STOPPED SHOULD BE SET AFTER AUXILIARY SKID HAS BEEN
SET AND ISOLATORS SECURING BOLTS TORQUED. INTERNAL STOPPED
ADJUSTMENT IS PROVIDED BY AN INTERNAL HEX-HEAD STUD.

Rev 0

Page 2 of 3

LM2500+ G4 LSPT Installation


GE ENERGY

7.

8.

IWP14

Auxiliary Skid Installation

Set internal stopper. Turn internal hex-head stud upwards (right-hand, turn counter
clockwise), until stud provides some resistance or until isolator starts to turn down,
indicating the stopped head has reached the upper limit. Next, turn stopped
adjustment hex-head nut downward (opposite direction) to provide a clearance of
6mm (approximately two turns of the nut).
Levelness of vibration isolators and internal stopper should be rechecked after ship
has been launched.

9.

Secure skid with foundation bolts and tighten nuts in accordance with engineering
drawings.

10.

Connect skid grounds.

11.

Install piping.

12.

Install remaining ship-loose items.

13.

Record date including


Equipment Installation Log
Auxiliary Skid Survey Data
Grounding Earthing Inspection

Rev 0