You are on page 1of 8

PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)

COMMITTED
Asof30September2014
Committed/
Indicative

NameoftheProject

Project
Proponent

Location

COAL

SouthLuzon
135MWPutingBato
Committed CoalFiredPowerPlant ThermalEnergy
Corp.(SLTEC)
PhaseI

Brgy.Puting
BatoWest,
Calaca,
Batangas

Southwest
LuzonPower
2X150MWSLPGC
Brgy.San
Generation
Committed CoalFiredPowerPlant
Rafael,Calaca,
Corporation
PhaseI
Batangas
(Project
Company)

SouthLuzon
135MWPutingBato
Committed CoalFiredPowerPlant ThermalEnergy
Corp.(SLTEC)
PhaseII

Brgy.Puting
BatoWest,
Calaca,
Batangas

Rated
Capacity
(MW)
1,372.00

135

300

135

ProjectStatus

TargetTesting&
Commissioning

FinancialArrangementSecuredon28October2014;
GISapprovedbyNGCPon17May2013;
StartedConstructiononDecember2011;
ConstructionDuration32Months;
230kVSalongSwitchingStationownedbyNGCPistiedupwithSLTEC;230kVSalongSwitchingStationenergizedBay1;
Alltestaremadeforthe230kVswitchyard;Generatorisforfinalalignment;Allmaterialsfortheprojectisforinstallation;Hydrotestandthermalinsulationinboilercompleted;Ongoing
airductingandinsulationforESP;
May2014
EPCworksasof31August201498.88%completed;
ConstructionProgress:Commissioingofinstalledequipments;Ongoingcommissioningofsteamblowing,watertreatmentandsaltwaterintake;Allmaterialsneedareinstalled;Ongoing
airductingandinsulationforESP;
AshManagementFacilityCompletion30April2014;
GroundbreakingFebruary2012;
ProjectcostisPhp12.9B

FinancialArrangementSecuredon24February2012(60%Loan/40%Equity);
GISapprovedbyNGCPon8November2011;
AwaitingfortheapprovalofNGCPfortheDasmariasCalacaReinforcementandrightofwayforthetransmissionlines;
Hydrotestingfortheboiler25April2014;
Embeddedplateforturbine,readyforinstallationUnit1;
CompleteSeawaterIntakeJune2014;
OngoinginstallationforpanelsUnitII;
ExpectedtocompleteCoalyardoperationbyMidMay2014;
UnitI&II
230kVSwitchyardsteelsuperstructureissubstantiallycompleted;
December2014
Ongoingnegotiationswithprospectiveofftakes(DUsandthosecurrentlywithPSAsandcontestablemarketunderOpenAccessRegime;
SiteMobilization/CommencementofConstructiononMay2012;
ProjectProgressasof31August201486.7%;
CompletedSteamTurbineBedPlateLocatingUnitII;CompletedBoilerTestHydroTestUnitII;OngoinginstallatonofCWPiping;OngoingCentralControlRoomCivilWorks;Assemblyand
alignmentofturbneonSeptember2014;Ongoingerection/assemblyofgantrysteelstructure(beamandcolumns)andequipmentpedestalsteelstructure;DCSCabinetUnit1tobe
energizedbytheendofAugust2014;
GroundbreakingMay2012;
ProjectcostforPhaseIisPhp20.4B
y
;
GISapprovedbyNGCPon17May2013;
StartedConstructiononAugust2013;
ConstructionDuration28Months;
DeliveredBoilerStreamDrum22April2014;DeliveryofTurbine2ndweekofSeptember2014;
EPCworksasof31August2014:64.05%completed;
TurbineGenerationHouseOngoingconstruction;
BoilerStructure:OngoingConstruction;
Coalyard98%completed(asofAugust2014);OngoingConstruction;Downcomerpipesinstalled;AwaitingforESPstructure;ChimneyFoundtion3.7m;
MaterialReceivingFacility99.59%completed;
GroundbreakingTargetDateAugust2013;
ProjectcostisPhp9.6B

June2015

Target
Commercial
Operation

October2014

Unit1March
2015

Unit2
June2015;

November2015

PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)
COMMITTED
Asof30September2014
Committed/
Indicative

NameoftheProject

AndaPower
Corporation's82MW
Committed CiculatingFluidized
BedCoalFiredPower
Plant

Project
Proponent

Location

AndaPower
Corporation

Brgy.
Bundagul,
Mabalacat,
Pampanga

SMC
300MWLimayPower
Consolidated
Committed PlantProjectPhaseI
Power
(2x150MW)
Corporation

Brgy.Lamao,
Limay,Bataan

Pagbilao
PowerStation,
1x420MWPagbilao
PagbilaoEnergy
Nrgy.Ibabang
Committed CoalFiredThermal
Corporation
Polo,Pagbilao,
PowerPlant
Quezon

Rated
Capacity
(MW)

ProjectStatus

TargetTesting&
Commissioning

Target
Commercial
Operation

82

FinancialArrangementSecured;
Ongoingnegotiationswithofftakers;
AwaitingforthereviewreportofNGCPoftheSIS(Unit1tobeincludedinthesimulationintheSIS);
CommencementofConstruction:March2014;
TotalProjectCost$196,246,837.63;

June2015

300

FinancialArrangementSecured(65%Loan/35%Equity);
EnvironmentalImpactAssessmentcompleted;TopographicandHydrographiccompleted;SoilInvestigationcompleted;
GIS/SISsubmittedlast12July2013,underreviewofNGCP;
Sitedevelopmentintermsofphysicalaccomplishmentasof26September2014is74.14%;ConstructionActivitiesofUnit1&22x150MWPowerPlant2.30%;DesignandConstructionof
PierandJettyStructureis67.59%;EngineeringDesign&ManufacturingofParts71.49%;AshDumpDesignandConstruction100%;
FacilityStudyalreadysenttoNGCPforreview;
EPCwasexecutedinJanuary2013;
ECCwasissuedonSeptember2013;
ConstructionoftheProjecthasbeenunderwaysinceJanuary2014
SECissuedlast19August2011;
Landacquisitioncompleted;
Ongoingelectricpowersupplycontractnegotiationwithprospectiveofftakers(DUs);
ClearancetoUnderatakeGISfromDOEissuedon13February2013;
Projectcostis$622.15M/Php25.508B

Unit1150MW
Unit1150MW
May2016
March2016
Unit2150MW
Unit2150MW
September2016
July2016

420

FinancialArrangementSecuredwithvariouslenderson30July2014;Allconditionsprecedenthavebeenfulfilled/satisfied;Firstandseconddrawdownscompleted;
EstimatedNetCapacity:400MW;
FeasibilityStudycompleted;
MarketingofGeneratingCapacities:Contractwithofftakerscompleted,Suppyagreementexecuted;
Permits&OtherRegulatoryRequirements:EnvironmentalComplianceCertificatewasissuedon18June2013;SecuredendorsementfromSangguniangBarangayofIbabangPolo,
SangguniangBayanofPagbilao,SangguniangPanlalawiganofQuezon;
InfinalnegotiationswithNPC,PSALM,TeaMEnergyCorporationandThermaLuzon,Inc.tocolocatetheplantintheexistingPagbilaoPowerStation;MarketingofGeneratingCapacities:
50%oftheplant'scapabilitywillbesoldtoThermaLuzinInc.andother50%willbesoldtoTeaM(Phils.)EnergyCorporation;
ConstructionContractsforPlant&Equipment:Completedandexecuted;NoticetoProceedandCommencementNoticeissuedtoEPCContractor;DownPaymentalreadyreleasedtoEPC
contractor;
TargetCommencementofEPCandConstruction:30May2014;
GroundBreakingDate:23July2014
EstimatedProjectCost:US$1,000,000,000.00

BetweenMayto
November2017
November2017

October2015

PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)
COMMITTED
Asof30September2014
Committed/
Indicative

NameoftheProject

Project
Proponent

Location

NATURALGAS

Committed

Pagbilao600MW
CombinedCycleGas
FiredPowerPlant
Proposed3x200MW
CCGTPowerPlant

Committed

100MWSanGabriel
AvionProject

1x450SanGabriel
Committed PowerPlant
(PhaseII)

Brgy.Ibabang
Polo,Grande
EnergyWorld
Island,
Corporation
Pagbilao,
Quezon

PrimeMeridian
PowerGen
Corporation
(Project
Company)
FirstGen
Corporation

FirstNatGas
PowerCorp.

Barangay
Bolbok,
Batangas

SanGabriel,
Batangas

Rated
Capacity
(MW)
1,150.00

600

100

450

ProjectStatus

FinancialArrangementSecured:Financingequitywillbe100%sourcedfromEWC;
GISfor300MWissuedbyNGCPon8August2013andrevisedon3July2013for600MW;IssuedDOEEndorsementforRevisedCapacityon3July2013;RevisedDOEclearanceforGIS
submittedtoNGCPonJanuary2014;GISfromNGCPforthe600MWwasreleasedonAugust2014;
Landisalreadysecuredwithalongleaseenteredintosince2007;
CommencementofConstruction:December2013;
Offtaker:NospecificofftakeryetbutalreadyhaveadiscussionwithFederationofPhilippineIndustries,intendedtosupplypowerintotheWholesaleElectricitySpotMarketbutisalso
opentodiscussingpotentialofftakearrangementsaswell;
PerrmitsandRegulatoryRequirements:SeveralResolutionshasbeenissuedonMay2014(SangguniangBarangayResolution,SangguniangBayanResolutionandSangguniangPanlalawigan
Resolution)interposingnoobjectionfortheconstructionofa600MWLiquifiedNaturalGas(LNG)PowerPlant;OngoingprocessingofECCforpowerplant;Ongoingprocessing
EnteredintoaSaleandPurchaseAgreementlastOctober2012withSiemensEnergyfortwo200MWgasturbinesandthefirst200MWturbineisexpectedtoarrivebySeptember2014;
LNGTankiscurrentlyat50%constructioncompletedasofAugust2014;
ProjectCost:$300M

TargetTesting&
Commissioning

January2015:1st FebruaryMarch
:1stUnit200MW,
Unit200MW,
'Dec2015:2nd 'Dec2015:2nd
Unit200MW
Unit200MW
'Dec2016:3rd 'Dec2016:3rdUnit
Unit200MW
200MW

FinancialArrangementSecured:
SecuredClearancefromDOEfortheconductofGISon21June2011;
SystemImpactStudy(SIS)wascompleted;
AmendmentofPhilippinePortsAuthority(PPA)chartertoaccomodatefortherightofwayfortheprojectsiteisstillforapprovalbytheOfficeofthePresident;Engineeringanddesignby
theContractorsisongoingfinalizationwithparallelreviewsbeingperformedbyPMPCanditsTechnicalConsultants;ExcavationandgroundpreparationworksbytheEPCcontractorare
ongoing;Procurementofplantequipmentiscontinuing,withmostofthemajorpowerplantcomponentseitherbeingmanufacturedorarescheduledfordeliverytothesite;Deliveryofthe
firstoftwo(2)GasTurbineandsomeanicillaryeuipmenthavearrivedatthePortofBatangason5October2014andareexpectedtobedeliveredtothesiteby24October2014;Shipmentof April2015
(Target
the2ndGasTurbineandancillaryequipmentisexpectedtoarriveattheprotofBatangasbytheendofOctober2014;
AlltestareconductedsuchasSeismic,GeologicalandHydrotests;
Commercial
Seven(7)polesaretobesetupforthetransmissionlines;
Operation)
SigningofContractwithMeiscorfortheconstructionoftransmissionlineApril22,2014;
CommittedArrivaloftheTurbineSeptember2014;
Offtaker:Discussionwithtargetofftakersongoing;
CommencementofConstructionwillbeonOctober2013;
ProjectcostisPhp10B

FinancialArrangementSecuredon10July2014:
SecuredClearancefromDOEfortheconductofGISon18February2013;
SISwasapprovedbyNGCPon11December2013.;
CommencementofConstruction:December2013;
Offtaker:Discussionwithtargetofftakerstargetedforthefirsthalfof2014;
ConstructionoftheProjecthasbeenprogressingwithistepreparationandfoundationworks;
ProjectcostisUS$600Million;

Target
Commercial
Operation

January2016

April2015

March2016

PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)
COMMITTED
Asof30September2014
Committed/
Indicative

NameoftheProject

Project
Proponent

Location

HYDROPOWER

Committed Sabangan

Hedcor
Sabangan,Inc.

Sabangan,
Mt.Province

Committed Inabasan

OrminPower,
Inc.

SanTeodoro,
Oriental
Mindoro

Committed Catuiran

Sta.Clara
PowerCorp.

Naujan,
Oriental
Mindoro

Oriental
Mindoro
LinaoCawayan (Upper
Committed
Electric
Cascade)
Cooperative,
Inc.

Committed Bulanao

DPJEngineers
and
Consultants

Baco,Oriental
Mindoro

Tabuk,Kalinga

Rated
Capacity
(MW)
34.30

ProjectStatus

FinancialArrangementSecured;
GroundbreakingheldonJune2013;
IssuedConfirmationofCommercialityon28August2013;
Ongoingconstruction(Preconstruction100%,Construction23.38%,Interconnection0%)completedasof30September2014;
SecuredClearancefromDOEfortheconductofGISon18June2012;

TargetTesting&
Commissioning

Target
Commercial
Operation

June2015

June2015
(TargetTesting
and
Commissioning)

10.0

FinancialArrangementSecured;
Groundbreakingheldon29July2013;
IssuedConfirmationofCommercialityon28May2013;
AlreadysecuredDENRECC,NCIPCertificate,andNWRBPermit;
SubmittedFeasibilityStudy,DetailedEngineeringDesignand5YrWorkPlan.

December2015

December2015
(TargetTesting
and
Commissioning)

8.0

FinancialArrangementSecured;
GroundbreakingheldinJanuary2013;
IssuedConfirmationofCommercialityon07February2013;
Submissionlackingrequirementse.g.permitsinprogress.

March2016

March2016
(TargetTesting
and
Commissioning)

2.1

FinancialArrangementSecured;
Ongoingconstruction;
AlreadysecuredLGUEndorsement,DENRECC,NWRBCWP,NCIPComplianceCertificate;
SubmittedFeasibilityStudyand5YrWorkPlan.FinancingfromDBP;
ProjectcostPhP293M.

March2016

March2016
(TargetTesting
and
Commissioning)

1.0

FinancialArrangementSecured;
IssuedConfirmationofCommercialityon11March2014;
AlreadysecuredNCIPclearance,DENRPermits,ESAwithKalingaApayaoElectricCooperativeInc.,LandleaseAgreement;
Ongoingconstructionofintakestructureandwithpurchaseorderfortheturbinegeneratorsystem;
SubmittedFeasibilityStudyand5YrWorkPlan.FinancingfromDBP;
ProjectcostPhP293M.

13.2

TBD

TBD

PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)
COMMITTED
Asof30September2014
Committed/
Indicative

NameoftheProject

Project
Proponent

Location

SOLAR

CaviteEconomicZone Majestics
Energy
Committed (CEZ)SolarRooftop
Corporation
PowerProject

Committed

PampangaSolar
PowerProject

Raslag
Corporation

Cavite
Economic
ZonesIandII,
Rosarioand
Gen.Trias,
Cavite

Brgy.
Suclaban,
Mexico,
Pampanga

WIND

Phase3:
Committed BanguiBayWind
PowerProject

Phase1:
Committed BurgosWindPower
Project

Rated
Capacity
(MW)
50.00

ProjectStatus

TargetTesting&
Commissioning

40

FinancialArrangementSecured100%Equity;
AwardedwithSolarEnergyServiceContract(SESCNo.201310040)on30October2013;
SecuredThirdPartySystemImpactStudy,ECC/CNCfromDENR,CNOfromNCIP,ProvincialResolutionsofSupport,CertificateofRegistrationfromPEZA,andEPCContract;
AcquiredDOECertificateofConfirmationofCommercialityon27June2013;
Completedtechnicalstudy;
Ongoingconstructionasof30September2014(PreConstruction90%complete,Construction88%complete,Interconnection85%complete;)
OngoingnegotiationforConnectionAgreementwithNGCP;
OngoingconstructionofitsBalanceofSystems(BOS);
Ongoingconstruction;

10

FinancialArrangementSecured;
AwardedwithSolarEnergyServiceContract(SESCNo.201401062)on05February2014;
SecuredECCfromDENR,MunicipalandBarangayResolutionofSupport,DARConversionofLandUsefromAgriculturaltoIndustrial,ThirdPartyDistributionImpactStudy,andownershipof
land;CompletedtheFullBlownFeasibilityStudy;
EPCContractisundernegotiation;
Ongoingconstructionasof30September2014(PreConstruction85%complete,Construction8%complete,Interconnection0%complete;
December2014
FinancialClosingisundernegotiation;
DeclarationofCommercialitysubmittedon28February2014;
AcquiredDOECertificateofConfirmationofCommercialityunderFITSystemon13June2014;
RequestforAmendmentofCoCoCfrom8MWto10MWon13August2014;
OngoingacquisitionofrelevantpermitsunderPreConstructionStageasperWorkPlan;
Filedarequestforendorsementtoavailthedutyfreeimportation;

October2014

Target
Commercial
Operation

October2014
(TargetTesting
and
Commissioning)

December2014
(TargetTesting
and
Commissioning)

317.40

NorthWind
Bangui,Ilocos
Power
Norte
Development
Corporation

EDCBurgos
WindPower
Corporation

Nagsurot
Saoit,Burgos,
IlocosNorte

18.9

87

FinancialArrangementSecuredwithaBankdated15July2013;
CoveredbyWESCNo.201307058dated26February2013;
Conducteddetailedwindresourceassessment;
Completeddetailedfeasibilitystudy;AcquiredvariousLGUpermitsandresolutionsofsupport,NCIPCertificateofNonOverlap,DENRAmendedEnvironmentalComplianceCertificateand
CAAPHeightClearancepermit;
September2014
SecuredClearancefromDOEfortheconductofGISon12February2013;
(TargetTesting
September2014
AcquiredDOECertificateofConfirmationofCommercialityon03December2013;AmendedtheCoCoCinordertorefecttheimprovedcapacityfrom18Mwto18.9MWon10September
and
2014);
Commissioning)
Ongoingconstructionasof30September2014(PreConstruction100%complete,Construction98%complete,Interconnection100%complete;
OngoingcivilworksforaccessroadsandWTGFoundations;asof30Septmber2014Completed6outof6WTGFoundations;Ongoingcompletion/acceptanceofSCADAwithNGCP;
Erected6WTG;OngoinginstallationofBalanceofPlantequipment;
AcquiredDOECertificateofConfirmationofCommercialityon03December2013
TotalprojectcostisUS$48.5Million.

FinancialArrangementSecured:Issuedcertificationdated13March2013thatEDC,itsparentcompany,hasthecapacitytofinancetheproject;100%equityfinanced;:
AwardedwithWindEnergyServiceContract(WESCNo.200909004)on14Sept2009;
Conducteddetailedwindresourceassessment;AcquiredvariousLGUpermitsandresolutionsofsupport,DENREnvironmentalComplianceCertificate,NCIPCertificateofNonOverlap,Land
LeaseAgreementwithprivatelandowners,ForestLanduseAgreementwithDENRforpublicland,DARlanduseconversionandexemptionfromCARPandCAAPHeightClearancepermit;
FinalReportofSISandConnectionAgreementwithNGCPsecured;
Supply,EPCandServiceEnergyBasedAvailabilityAgreementwiththeconsortiumofVestasandFirstBalfuorsecured;
November2014
ConductedGroundbreakingCeremonyon17Apr2013;
Ongoingconstruction;ConstructionStageasofasof30September2014(PreConstruction100%completed,Construction83%completed,Interconnection83%completed);
OngoingacquisitionofTLROW;
Completedthe29WTGfoundations;
Erectedthe29WTG;OngoingconstructionofsubstationandTL;
TotalprojectcostisUS$291Million;
AcquiredDOECertificateofConfirmationofCommercialityon16May2013;

November2014
(TargetTesting
and
Commissioning)

PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)
COMMITTED
Asof30September2014
Committed/
Indicative

Committed

NameoftheProject

CaparispisanWind
EnergyProject

Phase2:
Committed BurgosWindPower
Project

Project
Proponent

Location

Brgy.
NorthernLuzon
Caparispisan,
UPCAsia
Pagudpud,
Corporation
IlocosNorte

EDCBurgos
WindPower
Corporation

Nagsurot
Saoit,Burgos,
IlocosNorte

Rated
Capacity
(MW)

81

63

ProjectStatus

TargetTesting&
Commissioning

FinancialArrangementSecured:SubmittedacertificationfromvariousBanksdated12July2011;
AwardedwithWindEnergyServiceContract(WESCNo.200909005)on14Sept2009;
Conducteddetailedwindresourceassessment;Conducteddetailedwindresourceassessment;
Completeddetailedfeasibilityatudy;AcquiredvariousLGUpermitsandresolutionsofsupport,NCIPCertificateofNonOverlapon10Apr2007,ForestLanduseAgreementwithDENRon20
May2009,DENREnvironmentalComplianceCertificateon23Jul2009,DPWHRoadRightofWayforT/Lconstruction,andCAAPHeightClearancepermit;
FinalReportofSISandConnectionAgreementwithNGCPsecuredon4Jan2011;
BOIRegisteredon23Jun2011;
November2014
AcquiredDOECertificateofConfirmationofCommercialityon2July2013;
ConstructionStageoverall80.9%asof30September2014(PreConstruction99%completed,Construction85%,Interconnection59%);OverallAccomplishments:72.92%completedas
of31August2014;
OngoingacquisitionofTLROW;Ongoingcivilworksforaccessroads;Completed16outof27WTGFoundations;
AcquiredDOECertificateofConfirmationofCommercialityon2July2013;
Erectedthe27WTG;OngoingconstructionofTLROWasperWorkPlan;
TotalprojectcostisUS$255Million..

'CoveredbyWESCNo.200909004;
FinancingArrangements:100%equityfinancedsubjectavailableinstallationtarget;
CoveredbyalllocalpermitsacquiredbythePhase1Project;
OtherrelevantstudiesandpermitssuchasSystemImpactStudyandConnectionAgreementwithNGCPandEPCContractswerecoveredbytheApproved5YearWorkPlan;
100%equityfinancedsubjecttoavailableinstallationtarget.;
AcquiredDOECertificateofConfirmationofCommercialityon03December2013;
Ongoingconstruction;ConstructionStageasof30September2014(PreConstruction100%completed,Construction80%completed,Interconnection100%completed);
OngoingcivilworksforaccessroadsandWTGfoundations;
TotalProjectCostisUS$167.58M;

December2014

Target
Commercial
Operation

November2014
(TargetTesting
and
Commissioning)

December2014
(TargetTesting
and
Commissioning)

PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)
COMMITTED
Asof30September2014
Committed/
Indicative

NameoftheProject

Phase1:
Committed PilillaWindPower
Project

Project
Proponent

Alternergy
WindOne
Corporation

Location

Rated
Capacity
(MW)

67.5

ProjectStatus
'FinancialArrangementSecuredAWOCtofinancetheimplementationoftheprojectwith100%equity;
AwardedwithWindEnergyServiceContract(WESCNo.200909018)on23Oct2009;
AcquiredvariousLGUpermitsandresolutionsofsupport,DENREnvironmentalComplianceCertificate,NCIPCertificateofNonOverlap,ContracttoBuywithprivatelandowners,and
clearancesfromDAR,NIA,LRA,HLURB,andLagunaLakeDevelopmentAuthority;
InterconnectionAgreementwithMERALCOsecuredon1Mar2012;
Regulatoryrequirements,permits,GIS,etc.werecompleted;
EPCandO&MContractwithconsortiumofNordexSEandMcConnellDonnellsecuredon11Jul2012;
SecuredClearancefromDOEfortheconductofGISon21November2011;
NGCPReviewofThirdPartySISsecuredon31Jul2012;
AcquiredDOECertificateofConfirmationofCommercialityon16May2013;
ConductedGroundbreakingCeremonyon18Jun2013;
Ongoingconstructionasof30September2014(PreConstruction100%complete,Construction5%,Interconnection0%);
Startedcivilworksonaccessroad;
AmendedtheContractAreaandassignedfullytoAWOCWESCNo.200909018AF1on27February2014;
TotalprojectcostisUS$177.9Million;

TargetTesting&
Commissioning

July2015

Target
Commercial
Operation

July2015
(TargetTesting
and
Commissioning)

PRIVATESECTORINITIATEDPOWERPROJECTS(LUZON)
COMMITTED
Asof30September2014
Committed/
Indicative

NameoftheProject

Project
Proponent

Location

BIOMASS

24MWSJCiPowerRice
HuskFiredBiomass
SanJoseCityI
powerPlantProject
Power
Committed
(Phase112MW
Corporation
Phase212MW)

12.5MWBataan2020
Committed RicehullfiredCogen
Plant

Bataan2020
Inc.

Brgy.Tulat,
SanJose,
NuevaEcija

Bataan

IsabelaBiomass
20MWRuskFired
Alicia,Isabela
Energy
Committed
BiomassPowerPlant
Corporation

12MWBiomass
Committed
PowerPlantProject

Green
Innovationsfor
NuevaEcija
Tomorrow
Corporation

Rated
Capacity
(MW)
59.73

20.00

7.50

ProjectStatus

'FinanciallyClosed;
BREOCNo.201101013;
Preconstruction(100%completedasof31August2014);
PhaseIEstimatedAccomplishmentofConstruction98%completedasof31August2014);
Remainingmajorequipmentinprogressistheinstallationoftravellinggate;Ongoing
installationsofthefeedwaterpipingsystem,chemicaldosingpipeline,threecontrol
elementsoftheboilerandotherfieldinstruments;Expectedarrivalofswitchyardison
May2014;
Interconnection(100%completedasof31August2014);
Construction(Ongoingconstructionasof30September2014PreConstruction100%;Construction98%;Interconnection100%);
PermitsobtainedECC,LGU,LandUsePermit)EPCw/EngconofSingapore;
SecuredClearancefromDOEfortheconductofGISon21July2011;
IssuedCertificateConfirmationofCommercialityon2Sept2013;
Groundbreakingon12Oct2013;
Proj.CostPhp1.234B
FinanciallyClosed;
BREOCNo.201001008;
IssuedCertificateConfirmationofCommercialityon27August2013;
100%Constructed&Operational(OperatingforOwnUse);
Interconnection80%completedasof30September2014;

Phase1
Phase1October
September2014 2014
Phase2
Phase2
December2014 December2014
(SubjecttoFIT) (SubjecttoFIT)

October2014

December2014
(TargetTesting
and
Commissioning)

March2015
(SubjecttoFIT)

10.80

FinanciallyClosed;
BREOCNo.201309037;
ProjectStatusasof30September2014:PreConstruction:79%;Construction:18%;Interconnection:0%
IssuedDeclarationofCommercialityon16June2014;
Ongoingconstruction

December2015 Jnauary2016

December2015
(TargetTesting
December2015
and
Commissioning)

18

BicolBiomass
Energy
CamarinesSur
Corporation

3.15

FinanciallyClosed;
Ongoingconstruction

0.4MWVMAgbayani
Committed RiceMillRiceHusk
FiredPowerPlant

V.M.Agbayani
RiceMill

0.28

FinanciallyClosed;
Ongoingconstruction;

TotalCommittedRatedCapacity

Target
Commercial
Operation

FinanciallyClosed;
BREOCNo.201303030;
IssuedCertificateConfirmationofCommercialityon6January2014;
Ongoingconstructionasof31August201449%completed;Preconstruction95%completed;Interconnection2%completed;
SteamTurbineGenerator(STG)forconcreting;
FuelStoragewithpartialroofing;
AwaitingpermitfromDPWHfortheconstructionofdrainagesystem;
Permitsobtained(ECC,LGUEndorsement,LandUsePermit,etc.);
SecuredClearancefromDOEfortheconductofGISon22April2013;
IssuedDeclarationofCommercialityon6January2014;
HasEPC;
ProjectStatusasof30September2014:Preconstruction:95%;Construction:49%;Interconnection2%;
SubjecttoFIT;
ProjectcostisPhp1.9B

3.5MWBicolBiomass
Committed
EnergyCorporation

Oriental
Mindoro

TargetTesting&
Commissioning

2,983.43

March2015
(SubjecttoFIT)
(TargetTesting
and
Commissioning)

You might also like