Chap 6: Production
Activity Control

Dipak Ramchandra Sutar

Chapter 6 Production Activity Control


Introduction

Production activity control (PAC) is responsible for executing the master production schedule and
the material requirements plan. At the same time, it must make good use of labor and machines,
minimize work-in-process inventory, and maintain customer service.

The material requirements plan authorizes PAC: to release work orders to the shop for manufacturing,
to take control of work orders and make sure they are completed on time, to be responsible for the
immediate detailed planning of the flow of orders through manufacturing, and to manage day-to-day
activity and provide the necessary support. The activities of the PAC system can be classified into
planning, implementation, and control functions.

The flow of work through each work center must be planned. PAC must ensure that the required
resources are available to manufacture the components as needed and develop a load profile for each
work center to ensure the timely completion of orders by the scheduled date.

Next we implement the plan. PAC will gather the information needed by the shop floor to
make the product and release orders to the shop floor as authorized by the material
requirements plan (dispatching).

Monitor the process and determine the necessary corrective action. PAC will rank the shop
orders in desired priority sequence by work center and establish a dispatch list, track actual
performance to plan and take corrective action by replanning, rescheduling, or adjusting
capacity to meet delivery.

Understand the characteristics and differences between flow, intermittent and project
manufacturing.

National Institute of Industrial Engineering | Chap 6: Production activity


control

Data Requirements

To plan the processing of materials through manufacturing, PAC must have the following
information: What and how much to produce. When parts are needed so the completion date can be
met. What operations are required to make the product and how long the operations will take. What
the available capacities of the various work centers are.

PAC must have data, usually stored in databases, to drive the information systems. These database
files are of two types, planning and control.

The four planning files needed are the item master file, product structure file (bill of material file),
routing file and work center file. The item master file contains all of the pertinent data related to
each part number. The product structure or BOM file contains single-level BOMs listing
components and quantities needed to assemble a parent. It forms a basis for a pick list. A routing
exists for each part number and consists of a series of operations and instructions required to make
the item. The work center master file collects relevant data on a work center.

The two control files are the shop order master file and the shop order detail file. Each active
manufacturing order has a record in the shop order master file to monitor production performance for
each shop order. The shop order detail file contains the performance record for each operation.

Order Preparation

Once authorization to process an order has been received, PAC is responsible for planning and
preparing its release to the shop floor. The order should be reviewed to be sure that the necessary
resources are available. Material and capacity availability must be checked. Checking capacity
availability is a two-step process. First, the order must be scheduled to see when the capacity is
needed, and second, the load on work centers must be checked in that period.

Scheduling

The objective of scheduling is to meet delivery dates and to make the best use of manufacturing
resources. It involves establishing start and finish dates for each operation required to complete an
National Institute of Industrial Engineering | Chap 6: Production activity
control

item. To develop a reliable schedule, the planner must have information on routing, required and
available capacity, competing jobs, and manufacturing lead times at each work center involved.

Manufacturing lead-time is the time normally required to produce an item in a typical lot quantity
and consists of five elements queue, setup, run and wait. The largest of the five elements is queue
time. PAC is responsible for managing the queue by regulating the flow of work into and out of work
centers. PAC must manage both the input of orders to the production process and the available
capacity to control queue and work-in-process.

Cycle time (throughput time) is the length of time from when material enters a production facility
or operation until it exits.

Forward scheduling assumes that material procurement and operation scheduling for a component
start when the order is received, whatever the due date, and that operations are scheduled forward
from this date. The result is completion before the due date, which usually results in a buildup of
inventory.

Backward scheduling schedules the last operation on the routing first and is scheduled for
completion at the due date. Previous operations are scheduled back from the last operation.

Infinite loading assumes infinite capacity will be available.

Finite loading assumes there is a defined limit to available capacity at any workstation.

In operation overlapping, the next operation is allowed to begin before the entire lot is completed
on the previous operation. This reduces the total manufacturing lead times because the second
operation starts before the first operation finishes all the parts in the order. Increased costs are
possible from move costs and the impact of queue and lead-time for other orders.

Operation splitting is the process of splitting orders into two or more lots and run simultaneously on
two or more machines.

Load Leveling

National Institute of Industrial Engineering | Chap 6: Production activity


control

The load profile for a work center is constructed by calculating the standard hours of operation for
each order in each time period and adding them together by time period.

Scheduling Bottlenecks

Bottlenecks are overloaded workstations where the required capacity is greater than the available
capacity. It is a facility, function, department, or resource whose capacity is equal to or less than the
demand placed upon it.

Throughput is the total volume of production passing through a facility. Bottlenecks control the
throughput of all products.

Theory of Constraints and Drum-Buffer-Rope

The fundamental concept behind Theory of Constraints, developed by Eliyahu M. Goldratt, is that
every operation producing a product or service is a series of linked processes. Each process has a
specific capacity to produce the given defined output for the operation, and that in virtually every
case, there is one process that limits or constrains (bottleneck) the throughput from the entire
operation. Focus on balancing the flow through the shop. The time lost at a nonconstraint is a
mirage, and transfer batches do not have to be the same size as process batches.

Once constraint has been identified, there is a five-step process that is recommended to help improve
the performance of the operation. The five steps are: (1) identify the constraint, (2) exploit the
constraint, (3) subordinate everything to the constraint, (4) elevate the constraint, (5) once the
constraint is a constraint no longer, find the new one and repeat the steps.

The scheduling system for Theory of Constraints is described as Drum-Buffer-Rope. The drum of
the system refers to the drumbeat or pace of production. It represents the master schedule for the
operation, which is focused around the pace of throughput as defined by the constraint. Since it is so
important that the constraint never be starved for needed inventory, a time buffer is often
established in front of the constraint. It is called a time buffer because it represents the amount of
time that the inventory in the buffer protects the constraint from disruption. The analogy is that the
rope pulls production to the constraint for necessary processing. The primary focus of the
National Institute of Industrial Engineering | Chap 6: Production activity
control

scheduling system is on effective management of the organizations constraint to throughput and


sales.

Orders that do not have all of the necessary resources, tooling, material, and capacity, should not be
released because they only cause excess work-in-process inventory and may interrupt work on orders
that can be completed.

A shop packet accompanies a shop order release to manufacturing. This packet may include the
shop order, engineering drawings, bills of material, routing sheets, materials issue tickets or pick list,
tool requisitions, job tickets for each operation to be performed, and move tickets that authorize
movement of work between operations.

Once work orders have been issued to manufacturing, their progress has to be controlled. To control
progress, performance has to be measured and compared to what is planned. If what is actually
happening (what is measured) varies significantly from what was planned, either the plans have to be
changed or corrective action must be taken to bring performance back to plan.

PAC must balance the flow of work to and from different work centers. This is to ensure queue,
work-in-process, and lead times are controlled. The input/output control system is designed to
balance the input rate in hours with the output rate. The input rate is controlled by the release of
orders to the shop floor. The output rate is controlled by increasing or decreasing the capacity of a
work center.

To control input and output, a plan must be devised along with a method for comparing what actually
occurs against what was planned. This information is shown on an input/output report.
Cumulative variance is the difference between the total planned for a given period and the actual
total for that period (Cumulative variance = previous cumulative variance + actual planned).
Planned and actual inputs monitor the flow of work coming to the work center. Planned and actual
outputs monitor the performance of the work center. Planned and actual backlogs monitor the queue
and lead-time performance.

Operation sequencing is a technique for short-term planning of actual jobs to be run in each work
center based on capacity and priorities. Control of priorities is exercised through dispatching.
Dispatching is the function of selecting and sequencing available jobs to be run at individual work
National Institute of Industrial Engineering | Chap 6: Production activity
control

centers. The dispatch list is the instrument of priority control. Its a listing by operation of all the
jobs available to be run at a work center with the job listed in priority sequence.

The ranking of jobs for the dispatch list is created through the application of priority rules. Some
commonly used rules are: (1) first come, first served (FCFS), (2) earliest job due date (EDD), (3)
earliest operation due date (ODD), (4) shortest process time (SPT), and (5) critical ratio (CR = (due
date present date) / lead time remaining).

Reference

1. Introduction to Material management: Fifth Edition J. R. Tony Arnold, Stephen N.


Chapman,

R.V. Ramakrishnan