ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

ZXG10 iBSC
Installation and Commissioning
Preparation Guide _R1.0

ZTE CORPORATION

Confidential and Proprietary Information of ZTE CORPORATION.

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

ZXG10 iBSC
Engineering Installation and Commissioning Preparation Guide

* * * *
Planned by: GSM Product Support Dept, ZTE Wireless Network Service Center
Compiled by: Liu Guanghua
Reviewed by: Chen Qi
* * * *
ZTE Corporation
Address: ZTE Plaza, South Keji Rd., Hi-tech Industrial Park, Shenzhen, P.R. China, 518057
Technical Support Website:http://tsm.zte.com.cn
Hotline of Customer Support Center: (86-755) 26770800

800-830-1118

Fax: (86-755) 26770801


* * * *

Confidential and Proprietary Information of ZTE CORPORATION.

ii

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

Legal Information
All rights reserved. No part of this documentation may be excerpted,
reproduced, translated, annotated or duplicated, in any form or by any means
without the prior written permission of ZTE Corporation.

and
are the registered trade marks of ZTE Corporation. The names
and logos of ZTE products are proprietary logos or registered trade marks. The
names of other products and companies mentioned in this manual may be
proprietary to their owners respectively. Without the prior written permission of
ZTE or the owners of third-party trade marks or trade names, this manual does
not grant the reader any permission or right to use any marker appeared in the
manual.

The product described herein conforms to the design requirements of


environment protection and human security. The storage, usage, and discard
of the product shall comply with the manual, related contract, or laws and
regulations of related countries.

The actual product may differ from what is described in this standard due to
frequent update of ZTE products and fast development of technologies. Please
contact the local ZTE office for the latest updating information of the product.

For the latest document


http://tsm.zte.com.cn

information,

please

Confidential and Proprietary Information of ZTE CORPORATION.

visit

our

website:

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

Preface
Dear users, thank you for using ZXG10 iBSC Base Station Controller. To
further improve our cooperation and put the equipment into operation in time,
according to users requirement, ZTE has compiled this guide to help user to
complete the preparations before the engineering installation. We hope user
can make the preparations as required in this guide before ZTE technicians
arrive at commissioning site so that the equipment can be smoothly
commissioned and cut over into operation quickly during engineering
implementation, so as to create good social and economical benefit.
Before making preparations for engineering installation, user need make
clear the following matters:
1. If user has met any problem during the preparation for engineering
installation, user can contact ZTE regional office to obtain support at any
time. ZTE has the obligation to provide the corresponding help.
2. After completing all preparation work for engineering installation, please
contact the local regional office of ZTE (in the local province or region) in
time so that ZTE can assign corresponding engineering technicians to
implement the engineering installation.
3. If specific engineering installation has been implemented when project
preparations have not been completed for some reasons, user will be
responsible for the unfinished preparations specified in Installation
Preparations Guide.
4. If specific engineering installation has been implemented when project
preparations have not been completed due to some reason, and if the
project cannot be carried on due to incomplete preparation, ZTE
engineers have the right to stop the installation for further negotiation and
better arrangements before going back to the project.
To make it convenient for user to contact ZTE, please confirm the following
contents:
Address of ZTE local office (for maintenance) ___________________

Confidential and Proprietary Information of ZTE CORPORATION.

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

Telephone (fax) No. of ZTE local office (for maintenance) ______


Person in charge (PIC) of ZTE local office (for maintenance) _____________
ZTE person in charge (PIC) for this project________________________
Telephone

No.

of

ZTE

person

in

charge

(PIC)

for

project_________________

Confidential and Proprietary Information of ZTE CORPORATION.

ii

this

Content
1

Installation Flow...................................................................................................................1-1

Environment.........................................................................................................................2-1
2.1

Equipment Room Environment.............................................................................................2-1


2.1.1

Equipment Room Construction......................................................................................2-1

2.1.2

Equipment Room Layout...............................................................................................2-2

2.1.3

Lightning-Protection Design..........................................................................................2-3

2.1.4

Requirements for Equipment Room Environment........................................................2-4

2.1.5

Grounding Inspection.....................................................................................................2-9

2.1.6

Emergency Illumination System....................................................................................2-9

2.1.7

Power System.................................................................................................................2-9

2.1.8

Transmission.................................................................................................................2-11

2.1.9

IP Address Planning and Preparation...........................................................................2-11

2.1.10

Transportation Path to Equipment Room.....................................................................2-11

2.1.11

Equipment Temporary Storage.....................................................................................2-11

2.2

Other Preparations................................................................................................................2-11
2.2.1

Personnel Preparation...................................................................................................2-11

2.2.2

Access Pass Preparation...............................................................................................2-12

2.2.3

Vehicle Preparation......................................................................................................2-12
Auxiliary Equipment Preparation......................................................................................3-1

3.1
4

Auxiliary Equipment Preparation..........................................................................................3-1


Personnel Arrangement.......................................................................................................4-1

4.1

Training Personnel.................................................................................................................4-1

Appendix A Self-Check Table of Preparation for Engineering Installation..........................................A-1


Appendix B Physical Parameters for ZXG10 iBSC.................................................................................B-1
B.1 Physical Parameters...........................................................................................................................B-1
B.2 System Index.....................................................................................................................................B-1

1 Installation Flow
The installation flow of ZTE shall be implemented since the conclusion of the contract and it will not be changed
to the maintenance flow until it passes the final acceptance. The main process of the installation is as follows:
Contract intention,
contract starts

ZTE dispatches persons for engineering survey


Detailing and
concluding the contract
The customer starts engineering
preparations in accordance with the
Engineering Preparation Guide

The customer has


made the prepayment

ZTE organizes
production and delivery
The goods
arrive on the site

ZTE makes inspection and provides guidance to the engineering


preparations on an irregular basis, and completes the Engineering
Preparation Completion Table after this and requires for deployment

Both ZTE and the customer jointly determine


the kickoff date and the responsible persons for both parties

At the installation site, ZTE and the


customer jointly install and debug the equipment

Upon completion of system installation and debugging, both parties organize the
preliminary system acceptance, and put the system under trial run after cutover

Final system acceptance


to end the installation

It shows that the smooth commissioning of a project requires close cooperation


between user and equipment supplier (ZTE).

2 Environment
2.1 Equipment Room Environment
As for the equipment room to install iBSC, check the following items before
installation: equipment room structure, indoor environment, power supply,
grounding and auxiliary equipment.

2.1.1 Equipment Room Construction


The equipment room includes switch room, control room (generally 20m 2), and
auxiliary room (the control room and the equipment room can be combined if
conditions do not permit).
1.

The construction for the equipment room and corridors is completed and
internal walls are completely dry.

2.

The ground can support at least 450 kg/m2.

3.

The net height of the equipment room is more than 3.20 m.

4.

The main doors of the equipment room should be wide ( 1.8m) enough
and high ( 2.2m) enough for the equipment. In addition, locks and keys
should be provided for equipment room.

5.

Ventilation facilities work fine.

6.

The ceiling, walls, doors, windows and floor in the equipment room are
strong enough. Measurement is taken to avoid dust. The roof should be
in good condition without leaking. Fire-proof materials must be used.
The windows should be sealed.

7.

The grooves should be damp-proof with smooth and regular margins


and corners. The cover boards should be seamless with the floor and
the electric and power cords should be well covered.

8.

Equipment room color

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

Generally, patterned materials should not be used for the floor. The
walls and roof should use bright and light color. In addition, the paint
should be lusterless or not contain silicide.
9.

Equipment room floor


Generally, antistatic and movable floor at the height of 300mm or
330mm is recommended. The resistance value of each unit should be in
accordance with Technical Requirements for Raised Floor in Computer
Rooms. The floor boards should be tightly laid, and horizontal difference
per square meter should be no more than 2mm. If fixed floor is used,
conductive floor should be used (the resistance should be 1.0 10 7 ~
1.0 1010 ). The conductive or movable floor must be grounded and
can be connected to the grounding device with a current-control resistor
and a connection cable. The value of the current-control resistor should
be 1 M.

10. The ground of the equipment room should be leveled horizontally and
clean, and the quantities, positions and sizes of the reserved hidden
pipes, ground grooves and holes should meet the technology design
requirements.
11. The anti-earthquake feature of the equipment room should meet the
following standards:
The equipment room building should be one level higher on antiearthquake respect than the civil construction.
The equipment installation (especially in the equipment room with
movable floor) should take extra anti-earthquake measures on top of
basic measures.

2.1.2 Equipment Room Layout


Cabinets may be arranged in one or more rows (when they are placed in the
same room together with iBSC or MSC racks), depending on the size of the
room and the number of racks.
The cabinet layout inside the equipment room should be easy to use. The
following requirements should be satisfied:
1.

The space between two cabinet rows should not be less than 1m.

Confidential and Proprietary Information of ZTE CORPORATION.

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

2.

The front and back side of a cabinet should be at least 1m away from
the wall.

3.

The side of a cabinet should be at least 0.8 m away from the wall.

4.

An aisle of at least 1.2m wide should be reserved in the equipment


room, as shown in Figure 2.1-1.

1.2m

0.8m

1.0m

Figure 2.1-1 Layout of Equipment Room

2.1.3 Lightning-Protection Design


Lightning-protection and anti-electromagnetic measures should be taken in the
equipment room.

Caution:
The equipment room should be far enough from high-voltage power line, strong
magnetic field, strong electric sparks, or other factors that may have potential
threat to the equipment room.
In a building which is not high, the ground of the BSS equipment should be
separate from the electrical grounding or anti-lightening grounding, and should
be away from these devices as far as possible.
The buildings structures whose height are at the minimum 15m above the
equipment room, such as the chimney and antenna, should be designed
according to the lightning-protection requirements of civil buildings and
structures.
Confidential and Proprietary Information of ZTE CORPORATION.

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

In the design of lightning-protection, measures should be taken to guard


against direct lightning current. Protective measures should also be taken to
prevent side lightning when a high-rise building is used as the equipment room.
In the areas where lightning occurs frequently, side lightning occurs and
preventive measures should be adopted according to the actual situation. For
example, you can connect the metal windows with lightning-protection
grounding system. Also, you can set metal lightning-protection straps on outer
wall at certain interval to avoid lightning.
The following lightning-protection measures should be taken for the main
building of the equipment room: Lightning-protection strips should be used for
the part of the building that is vulnerable to lightning strokes; the objects such
as chimney and antenna should be installed with overhead protection cable or
lightning rod; the grounding device should not be longer than 30 m, made of
zinc-coated flat steel and multiple copper strands with the sectional area not
less than 40 mm x 4 mm or 95 mm2. For the telecommunication building, the
grounding resistance during the lightning should not be more than 10 . The
outdoor cables, metal pipes and other things should be well grounded outside.
Before the outdoor overhead lines are directly led into the building, a lightning
arrester should be installed at the entry point. For the chimney, antenna and
other objects, a lightning arrestor should be installed at the top. For the
buildings and structures, it is recommended to use the steel bars inside of the
structure as the grounding wire.

2.1.4 Requirements for Equipment Room Environment


1. The equipment room should be clean and free of dust, corrosive gases,
waste gases and chemical gases.
2. There should not be water pipes in the equipment room and the devices
should not be exposed to water.
3. There should not be any valves or emptying vents if there are heating
devices in the equipment room.
4. The air conditioning devices should be able to meet the temperature and
humidity requirement in the equipment room.
5. The

devices

should

be

protected

from

electrostatic

harm

electromagnetic interference.
Confidential and Proprietary Information of ZTE CORPORATION.

and

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

2.1.4.1

Antistatic Requirements
The equipment should be well grounded. The antistatic floorboards or the
leather floor with semi-conductive materials should be used. Copper foils
should be used for grounding at certain points (copper foils are pasted between
the cement ground and the semi-conductive floor and connected with the
grounding cable).

2.1.4.2

Dust-Proof Requirements
The equipment room should meet the following requirements:
1.

The concentration of dust with the diameter greater than 5m should be


lower than 18,000 granules/cm3.

2.

The dust particles should be non-conductive, non-magnetic and noncorrosive.

Recommended anti-dust measures for the equipment room:


1.

Seal doors and windows. The outer window should have double-layered
glasses and be sealed, and doors should have dustproof sealing strips.
The ideal situation is a sealed equipment room with a skylight and air
filter.

2.

Keep the work clothes and slippers clean and change them frequently.

3.

The operating equipment should be set in the outer room for


convenience.

4.

Keep indoor RH relatively high to reduce dust adherence caused by


static electricity.

5.

The walls and ceiling of the equipment room must be painted or pasted
with wallpaper. Lusterless paint is recommended.

2.1.4.3

Temperature and Humidity Requirements


Table 2.1-1 shows the requirements of temperature and humidity.
Table 2.1-1 Temperature and Humidity
Temperature (oC)
Item

Long-term working

Short-term working

condition (Note 1)

condition (Note 2)

Confidential and Proprietary Information of ZTE CORPORATION.

Relative Humidity (%)


Long-term

Short-term

working

working

condition

condition
5

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
Scope

0C~40C

-5C ~45C

20%~90%

5%~95%

Note 1: Under normal working environment of the switch, the measurement values of
temperature and humidity refer to the value measured at 2 m above the floor and
0.4 m before the equipment (measurement is done when no protective board is in
the front or at the back of the rack).
Note 2: The short-term working condition means that the continuous operation period is no
more than 48 hours for each time, and no more than 15 days in a year.

Generally, air conditioners should be equipped.


1.

Air conditioning humidity: 40% ~ 65%, 50% ~ 60% is recommended.

2.

Air conditioning

temperature:

18oC

28oC. 20oC

~ 25oC

is

recommended.
2.1.4.4

Noise
The environment noise of the equipment room should keep lower than 70 dB.

2.1.4.5

Lighting
Direct sunlight should be avoided.
The light should be soft with average lighting level between 150 lux and 200
lux. In an area where power-cut always happens, a light with direct current
power supply should be installed.
It is required that the storage battery room be equipped with an anti-explosion
light. The outer window should be pasted with paper or be painted to avoid
direct sunlight.
The lighting conditions of the equipment room should meet the equipment
maintenance requirements, and three sets of lighting systems including normal
lighting, spare lighting, and emergency lighting should be prepared.

2.1.4.6

Atmospheric Pressure
Working: 1.08 x 105 Pa ~ 5.1 x 104 Pa (-500 mm ~ +500 mm)
Storage: 1.08105 ~ 1.2 x 104 Pa (-500 mm ~ +1500 mm)

2.1.4.7

Air Pollution
The equipment should not be exposed to corrosive air such as hydrogen
sulfide, sulfur dioxide, oxide containing ammonia, or smog such as oil solvents,

Confidential and Proprietary Information of ZTE CORPORATION.

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

smoke and dust. It is prohibited to smoke in the equipment room or places


where the equipment (including the battery) is installed.
2.1.4.8

Air Conditioner
To meet the temperature and humidity requirements as mentioned above, air
conditioners are needed. There should be air conditioners with humidity
adjustment function in the large equipment room, while in small equipment
rooms only ordinary cabinet or window air conditioners are needed.
As the iBSC has built-in fans, it is unnecessary to install central air conditioning
in the equipment room. In fact, the equipment room with the central air
conditioning still needs to be equipped with independent air conditioners.
The following measures are recommended:
1.

Two AC lines or an extra generator should be used to ensure power


supply to the air conditioners.

2.

It is better to install three or at lease two air conditioners in the


equipment room, because the equipments cannot work properly or even
break down once the only air conditioner goes wrong especially in hot
weather. If two air conditioners are equipped, the situation gets better.
However, it is better to have three, especially when small-power air
conditioners are used. For example, you can switch on one of them at
cool night or in spring or autumn, and switch on two if the temperature
rises. In the daytime of hot days, we can switch on all the three air
conditioners. The above method can save energy, reduce the
continuous working hours of a single air conditioner and improve
reliability.

2.1.4.9

Cabling Requirements
1.

Cables should be laid out in grooves, and such moisture-proof, rodentproof and fire-proof measures can be taken.

2.

Cables should not be mixed with power cables in layout, so as to avoid


interferences.

3.

The operator should provide grooves for cable distribution.

Confidential and Proprietary Information of ZTE CORPORATION.

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

4.

The cabling rack should be prepared as required by the design drawing,


and the installation position of the cabling rack upon upper cabling is
generally 2.5m above the ground.

2.1.4.10

Security Requirements
1.

The equipment room should be equipped with proper fire protection


facilities as smoke sensors and temperature sensors, which should be
in good condition.

2.

The sockets with different voltages in the equipment room should be


clearly labeled.

3.

It is strictly prohibited to store flammable or explosive articles in the


equipment room.

4.

Cover the reserved holes in the floors.

Fire Protection Distance between Civil Buildings in Code for Fire Protection
Design of Buildings stipulates that: The telecommunication buildings should be
at the highest levels of fire protection. Fire resistance in design should be at the
first level (high buildings) and second level, and fire protection distance
between them should not be less than 6m. If fire resistance in design of
adjacent buildings is at the third level and fourth level, the distance between
them should not be less than 7m.
2.1.4.11

Environment Conditions for Equipment Storage


iBSC is a valuable electronic device, so the environment for its storage must be
water-proof and shock-proof.

2.1.4.12

Communication Guarantee
Toll line should be offered in the equipment room, so that the customer can
contact ZTE in a quick and timely manner during the installation and
maintenance.

2.1.4.13

Desks and Chairs


In the equipment room, workstations and printers can be placed on desks and
chairs. A desk and a chair must be available in equipment room. The table
should be about 80cm high, and the chair 40cm.

Confidential and Proprietary Information of ZTE CORPORATION.

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

2.1.5 Grounding Inspection


The grounding cables in the equipment room should be wired separately in a
radial mode or a planar mode. Prevent any closed circuit formed through the
concrete bar or the rack.
The working grounding, protection grounding, and lightning-protection
grounding of the equipment should be separate with a grounding resistance of
less than 1.
The size of the grounding cable should be determined by the maximum
current. Covered copper line is recommended, and bare copper line is
prohibited.

2.1.6 Emergency Illumination System


For the unit with frequent power off, an emergency light (DC) should be
installed.

2.1.7 Power System


It is necessary to check the following items for the power supply in the
equipment room.
1.

Requirements of DC power supply

The standard voltage of power supply for iBSC is -48V in the


equipment room, with an allowed range of -57V ~ -40V.

The noise level indices of DC power voltages should meet the


general technical specifications regulated by the former Ministry of
the Posts and Telecommunications of P. R. China.

The DC power supply should have an over-voltage/current


protection and indication system.

2.

AC power supply requirements

Three-phase power supply: 380V 10%, 50Hz 5%, waveform


distortion < 5%.

Single-phase power supply: 220V 10%, 50Hz 5%, waveform


distortion < 5%.

Confidential and Proprietary Information of ZTE CORPORATION.

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

The backup generator should have the same voltage and frequency
requirements as the above with waveform distortion range from 5%
to 10%.

3.

4.

Requirements of UPS

Input voltage (V): 220V 10%

Input frequency (Hz): 50Hz 5%

Power factor: > 0.95

Output voltage: 220V 3% ~ 220V 5%

Output frequency (Hz): 50Hz ~ 60Hz

Harmonic distortion: < 5%

Output waveform: Sine wave

Working mode: Online

Dynamic response duration: < 2ms

Different sockets in the equipment room should be clearly marked to


separate power electricity from lighting electricity.

5.

There should be audible/visible alarms for under current, under voltage


and over voltage conditions.

6.

Pay attention when handling 220V or 380V AC power voltage (if any) in
the equipment room.

7.

Double check the power polarities before installation.

Electric Shock:
Upon checking the power supplies, pay attention to the switch-on status of
switches, and beware of electric shock.

2.1.8 Transmission
Make sure the transmission (between equipment and from equipment to DDF)
inside the equipment room is ok.

Confidential and Proprietary Information of ZTE CORPORATION.

10

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

2.1.9 IP Address Planning and Preparation

Item

Content

Remarks

IP address of OMP:
iBSC Installation

Internal IP address of OMCR:


External IP address of OMCR:
IP address of OMCB:

Server Installation

Server IP address:

2.1.10 Transportation Path to Equipment Room


The main doors of the equipment room should be wide ( 1.8 m) enough and
high ( 2.2 m) enough for the sake of equipment transportation. In addition,
locks and keys of the equipment room should be complete.

2.1.11 Equipment Temporary Storage


Before installation the iBSC equipment should be kept in a storage room in
good package. The storage room should be free from damage materials such
as water, vibration, fire, high temperature, corrosion, electromagnetic
interference, etc. In short, it must reach the environment requirement for
equipment room.

2.2 Other Preparations


2.2.1 Personnel Preparation
The process of project implementation is also the process of onsite training.
The maintenance people should be there during the installation.

2.2.2 Access Pass Preparation


Enough passes for the installation engineers should be prepared by the
operator during installation to ensure engineering progress.

2.2.3 Vehicle Preparation


In some case, vehicle should be provided.

Confidential and Proprietary Information of ZTE CORPORATION.

11

3 Auxiliary Equipment Preparation


3.1 Auxiliary Equipment Preparation
1.

The proper DC power supplies are ready.

2.

The optical cables are properly connected and the transmission is


checked.

3.

The maintenance console for the equipment is installed in a proper


position in accordance with room layout.

4.

The equipment room (civil construction and decoration) and its


environment should meet the requirement.

5.

-48V power cable should be laid out to the equipment.

6.

The grounding cable should be laid out to the equipment.

7.

Install DDF.

8.

A person should be available to assist the installation engineer.

9.

The safety and quality measurements on the implementation site should


meet relevant regulations.

10. The related networking devices, such as switch, router and HUB should
be properly installed.

4 Personnel Arrangement

Caution:
Non-professionals should not maintain or debug the interior of any equipment
unless instructed by professionals on site.
Replacing any parts or modifying the equipment might result in unexpected
dangers. Therefore, do not replace any parts or modify the equipment unless
otherwise authorized.
To ensure your safety, please contact ZTE Corporation if you have any
problem.

4.1 Training Personnel


The process of project implementation is also the process of onsite training, so
the operator should dispatch the personnel who may be responsible for the
future equipment room maintenance for training in the implementation;
meanwhile, the customer is required to send some special persons for
coordination for some reasons (such as different customs).

Appendix A Self-Check Table of


Preparation for Engineering
Installation
Self-Check Table of Preparation for Engineering Installation
SN
1

Self-check Items
Minimum height from the beam: 3.2 m
2

Preparation
Pass

Fail

Pass

Fail

Floorboard bearing load: > 450 K/m

Wall paper pasted on the walls or flat paint not easy to pulverize

Pass

Fail

Available with an antistatic floor

Pass

Fail

Pass

Fail

Pass

Fail

Pass

Fail

Pass

Fail

Pass

Fail

Pass

Fail

Pass

Fail

Pass

Fail

Pass

Fail

5
6
7
8

Long-term working temperature range: 15 ~ 30C


Short-term working temperature range: 0 ~ 45C
Anti-electromagnetic interference; an electric field of not more than 300mV/m and
a magnetic field of less than 11Gs
The dust whose diameter is more than 5m should be less than or equal to 3
104 granules/m3 in density.
The shock-proof measure should be one degree higher than the local basic
earthquake intensity.
Illumination: Direct sunshine should be avoided. The storage battery room should

be equipped with the anti-explosion lamp with an appropriate light intensity of 150
~ 200 Lux

10
11
12
13

Fire-protection measurements meet up to China Level 2 fire-protection standard


DC voltage: Primary power supply and storage battery are in mutual hot backup,
with a working range of -41 V ~ - 57 V
Charging and Discharge voltage of storage battery, floating charge voltage: 52.8
0.5 V, discharge voltage: 43.2 V
The storage battery can switch between the charging/discharging status
automatically

14

Standby diesel generator

Pass

Fail

15

AC power voltage: 220 V 20 V

Pass

Fail

16

Available with the -48 V power cable under the rack

Pass

Fail

17

Power alarm for power-off or fault

Pass

Fail

Pass

Fail

Pass

Fail

The working ground, protection ground and lightning protection ground of the
18

equipment should be grounded separately, and the grounding resistance is


typically less than 1 .

19

The grounding cables should be led to under the rack; general checking of
grounding

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
SN

Self-check Items

Preparation

20

IP address planning and preparation

Pass

Fail

21

Equipment transportation path to the equipment room

Pass

Fail

22

Personnel arrangement

Pass

Fail

23

Temperature and humidity requirements

Pass

Fail

24

Illumination requirements

Pass

Fail

25

Atmospheric pressure

Pass

Fail

26

Air quality

Pass

Fail

27

Safety requirements

Pass

Fail

28

Communication guarantee

Pass

Fail

29

Emergency illumination

Pass

Fail

30

Temporary storage of equipment

Pass

Fail

31

Commissioning of transmission equipment

Pass

Fail

32

Vehicles

Pass

Fail

33

Equipment room construction

Pass

Fail

34

Cabling requirements

Pass

Fail

Confidential and Proprietary Information of ZTE CORPORATION.

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

Confidential and Proprietary Information of ZTE CORPORATION.

Appendix B Physical Parameters for


ZXG10 iBSC
B.1 Physical Parameters
1.

Dimension of iBSC

External Dimension of iBSC: 2000 mm 600 mm 800 mm (H W D)


2.

Power supply: -48VDC (-57V~-40V)

3.

Weight

A single ZXG10 iBSC cabinet should be no more than 360 kg.


4.

Ambient temperature: -15 C ~ + 30 C (Long term)

5.

Relative humidity: 40%~65% (Long term)

B.2 System Index


B.2.1 Physical Performance
B.2.1.1 Dimensions and Colors
1.

Rack dimensions
The dimensions of a single rack of ZXG10 iBSC : 2000 mm 600 mm
800 mm (H W D).

2.

Cabinet color
IBSC cabinet color: Dark blue

B.2.1.2 Equipment Weight and Bearing Requirement of Floor in the Equipment Room
1.

The maximum weight of a single cabinet reaches 350 kg (including a


front door, a back door and a side door).

2.

The equipment room floor is required to have the bearing capacity of


450 kg/m2.

B.2.1.3 Power Supply


Power system range:

ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only

Supply voltage: -48 VDC


DC voltage fluctuation range: -40 V ~-57 V
AC voltage fluctuation range: 10%
B.2.1.4 Power Consumption
The maximum power consumption of a single iBSC cabinet in full configuration
is 2200 W.
The maximum power consumption of double iBSC cabinets in full configuration
is 5200 W.

Note
For more information about the equipment parameters, please refer to the
ZXG10 iBSC (V6.20.xx) Technical Manual.