Installation and Commissioning
Preparation Guide _R1.0
ZTE CORPORATION
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
ZXG10 iBSC
Engineering Installation and Commissioning Preparation Guide
* * * *
Planned by: GSM Product Support Dept, ZTE Wireless Network Service Center
Compiled by: Liu Guanghua
Reviewed by: Chen Qi
* * * *
ZTE Corporation
Address: ZTE Plaza, South Keji Rd., Hi-tech Industrial Park, Shenzhen, P.R. China, 518057
Technical Support Website:http://tsm.zte.com.cn
Hotline of Customer Support Center: (86-755) 26770800
800-830-1118
ii
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
Legal Information
All rights reserved. No part of this documentation may be excerpted,
reproduced, translated, annotated or duplicated, in any form or by any means
without the prior written permission of ZTE Corporation.
and
are the registered trade marks of ZTE Corporation. The names
and logos of ZTE products are proprietary logos or registered trade marks. The
names of other products and companies mentioned in this manual may be
proprietary to their owners respectively. Without the prior written permission of
ZTE or the owners of third-party trade marks or trade names, this manual does
not grant the reader any permission or right to use any marker appeared in the
manual.
The actual product may differ from what is described in this standard due to
frequent update of ZTE products and fast development of technologies. Please
contact the local ZTE office for the latest updating information of the product.
information,
please
visit
our
website:
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
Preface
Dear users, thank you for using ZXG10 iBSC Base Station Controller. To
further improve our cooperation and put the equipment into operation in time,
according to users requirement, ZTE has compiled this guide to help user to
complete the preparations before the engineering installation. We hope user
can make the preparations as required in this guide before ZTE technicians
arrive at commissioning site so that the equipment can be smoothly
commissioned and cut over into operation quickly during engineering
implementation, so as to create good social and economical benefit.
Before making preparations for engineering installation, user need make
clear the following matters:
1. If user has met any problem during the preparation for engineering
installation, user can contact ZTE regional office to obtain support at any
time. ZTE has the obligation to provide the corresponding help.
2. After completing all preparation work for engineering installation, please
contact the local regional office of ZTE (in the local province or region) in
time so that ZTE can assign corresponding engineering technicians to
implement the engineering installation.
3. If specific engineering installation has been implemented when project
preparations have not been completed for some reasons, user will be
responsible for the unfinished preparations specified in Installation
Preparations Guide.
4. If specific engineering installation has been implemented when project
preparations have not been completed due to some reason, and if the
project cannot be carried on due to incomplete preparation, ZTE
engineers have the right to stop the installation for further negotiation and
better arrangements before going back to the project.
To make it convenient for user to contact ZTE, please confirm the following
contents:
Address of ZTE local office (for maintenance) ___________________
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
No.
of
ZTE
person
in
charge
(PIC)
for
project_________________
ii
this
Content
1
Installation Flow...................................................................................................................1-1
Environment.........................................................................................................................2-1
2.1
2.1.2
2.1.3
Lightning-Protection Design..........................................................................................2-3
2.1.4
2.1.5
Grounding Inspection.....................................................................................................2-9
2.1.6
2.1.7
Power System.................................................................................................................2-9
2.1.8
Transmission.................................................................................................................2-11
2.1.9
2.1.10
2.1.11
2.2
Other Preparations................................................................................................................2-11
2.2.1
Personnel Preparation...................................................................................................2-11
2.2.2
2.2.3
Vehicle Preparation......................................................................................................2-12
Auxiliary Equipment Preparation......................................................................................3-1
3.1
4
4.1
Training Personnel.................................................................................................................4-1
1 Installation Flow
The installation flow of ZTE shall be implemented since the conclusion of the contract and it will not be changed
to the maintenance flow until it passes the final acceptance. The main process of the installation is as follows:
Contract intention,
contract starts
ZTE organizes
production and delivery
The goods
arrive on the site
Upon completion of system installation and debugging, both parties organize the
preliminary system acceptance, and put the system under trial run after cutover
2 Environment
2.1 Equipment Room Environment
As for the equipment room to install iBSC, check the following items before
installation: equipment room structure, indoor environment, power supply,
grounding and auxiliary equipment.
The construction for the equipment room and corridors is completed and
internal walls are completely dry.
2.
3.
4.
The main doors of the equipment room should be wide ( 1.8m) enough
and high ( 2.2m) enough for the equipment. In addition, locks and keys
should be provided for equipment room.
5.
6.
The ceiling, walls, doors, windows and floor in the equipment room are
strong enough. Measurement is taken to avoid dust. The roof should be
in good condition without leaking. Fire-proof materials must be used.
The windows should be sealed.
7.
8.
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
Generally, patterned materials should not be used for the floor. The
walls and roof should use bright and light color. In addition, the paint
should be lusterless or not contain silicide.
9.
10. The ground of the equipment room should be leveled horizontally and
clean, and the quantities, positions and sizes of the reserved hidden
pipes, ground grooves and holes should meet the technology design
requirements.
11. The anti-earthquake feature of the equipment room should meet the
following standards:
The equipment room building should be one level higher on antiearthquake respect than the civil construction.
The equipment installation (especially in the equipment room with
movable floor) should take extra anti-earthquake measures on top of
basic measures.
The space between two cabinet rows should not be less than 1m.
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
2.
The front and back side of a cabinet should be at least 1m away from
the wall.
3.
The side of a cabinet should be at least 0.8 m away from the wall.
4.
1.2m
0.8m
1.0m
Caution:
The equipment room should be far enough from high-voltage power line, strong
magnetic field, strong electric sparks, or other factors that may have potential
threat to the equipment room.
In a building which is not high, the ground of the BSS equipment should be
separate from the electrical grounding or anti-lightening grounding, and should
be away from these devices as far as possible.
The buildings structures whose height are at the minimum 15m above the
equipment room, such as the chimney and antenna, should be designed
according to the lightning-protection requirements of civil buildings and
structures.
Confidential and Proprietary Information of ZTE CORPORATION.
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
devices
should
be
protected
from
electrostatic
harm
electromagnetic interference.
Confidential and Proprietary Information of ZTE CORPORATION.
and
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
2.1.4.1
Antistatic Requirements
The equipment should be well grounded. The antistatic floorboards or the
leather floor with semi-conductive materials should be used. Copper foils
should be used for grounding at certain points (copper foils are pasted between
the cement ground and the semi-conductive floor and connected with the
grounding cable).
2.1.4.2
Dust-Proof Requirements
The equipment room should meet the following requirements:
1.
2.
Seal doors and windows. The outer window should have double-layered
glasses and be sealed, and doors should have dustproof sealing strips.
The ideal situation is a sealed equipment room with a skylight and air
filter.
2.
Keep the work clothes and slippers clean and change them frequently.
3.
4.
5.
The walls and ceiling of the equipment room must be painted or pasted
with wallpaper. Lusterless paint is recommended.
2.1.4.3
Long-term working
Short-term working
condition (Note 1)
condition (Note 2)
Short-term
working
working
condition
condition
5
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
Scope
0C~40C
-5C ~45C
20%~90%
5%~95%
Note 1: Under normal working environment of the switch, the measurement values of
temperature and humidity refer to the value measured at 2 m above the floor and
0.4 m before the equipment (measurement is done when no protective board is in
the front or at the back of the rack).
Note 2: The short-term working condition means that the continuous operation period is no
more than 48 hours for each time, and no more than 15 days in a year.
2.
Air conditioning
temperature:
18oC
28oC. 20oC
~ 25oC
is
recommended.
2.1.4.4
Noise
The environment noise of the equipment room should keep lower than 70 dB.
2.1.4.5
Lighting
Direct sunlight should be avoided.
The light should be soft with average lighting level between 150 lux and 200
lux. In an area where power-cut always happens, a light with direct current
power supply should be installed.
It is required that the storage battery room be equipped with an anti-explosion
light. The outer window should be pasted with paper or be painted to avoid
direct sunlight.
The lighting conditions of the equipment room should meet the equipment
maintenance requirements, and three sets of lighting systems including normal
lighting, spare lighting, and emergency lighting should be prepared.
2.1.4.6
Atmospheric Pressure
Working: 1.08 x 105 Pa ~ 5.1 x 104 Pa (-500 mm ~ +500 mm)
Storage: 1.08105 ~ 1.2 x 104 Pa (-500 mm ~ +1500 mm)
2.1.4.7
Air Pollution
The equipment should not be exposed to corrosive air such as hydrogen
sulfide, sulfur dioxide, oxide containing ammonia, or smog such as oil solvents,
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
Air Conditioner
To meet the temperature and humidity requirements as mentioned above, air
conditioners are needed. There should be air conditioners with humidity
adjustment function in the large equipment room, while in small equipment
rooms only ordinary cabinet or window air conditioners are needed.
As the iBSC has built-in fans, it is unnecessary to install central air conditioning
in the equipment room. In fact, the equipment room with the central air
conditioning still needs to be equipped with independent air conditioners.
The following measures are recommended:
1.
2.
2.1.4.9
Cabling Requirements
1.
Cables should be laid out in grooves, and such moisture-proof, rodentproof and fire-proof measures can be taken.
2.
3.
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
4.
2.1.4.10
Security Requirements
1.
2.
3.
4.
Fire Protection Distance between Civil Buildings in Code for Fire Protection
Design of Buildings stipulates that: The telecommunication buildings should be
at the highest levels of fire protection. Fire resistance in design should be at the
first level (high buildings) and second level, and fire protection distance
between them should not be less than 6m. If fire resistance in design of
adjacent buildings is at the third level and fourth level, the distance between
them should not be less than 7m.
2.1.4.11
2.1.4.12
Communication Guarantee
Toll line should be offered in the equipment room, so that the customer can
contact ZTE in a quick and timely manner during the installation and
maintenance.
2.1.4.13
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
2.
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
The backup generator should have the same voltage and frequency
requirements as the above with waveform distortion range from 5%
to 10%.
3.
4.
Requirements of UPS
5.
6.
Pay attention when handling 220V or 380V AC power voltage (if any) in
the equipment room.
7.
Electric Shock:
Upon checking the power supplies, pay attention to the switch-on status of
switches, and beware of electric shock.
2.1.8 Transmission
Make sure the transmission (between equipment and from equipment to DDF)
inside the equipment room is ok.
10
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
Item
Content
Remarks
IP address of OMP:
iBSC Installation
Server Installation
Server IP address:
11
2.
3.
4.
5.
6.
7.
Install DDF.
8.
9.
10. The related networking devices, such as switch, router and HUB should
be properly installed.
4 Personnel Arrangement
Caution:
Non-professionals should not maintain or debug the interior of any equipment
unless instructed by professionals on site.
Replacing any parts or modifying the equipment might result in unexpected
dangers. Therefore, do not replace any parts or modify the equipment unless
otherwise authorized.
To ensure your safety, please contact ZTE Corporation if you have any
problem.
Self-check Items
Minimum height from the beam: 3.2 m
2
Preparation
Pass
Fail
Pass
Fail
Wall paper pasted on the walls or flat paint not easy to pulverize
Pass
Fail
Pass
Fail
Pass
Fail
Pass
Fail
Pass
Fail
Pass
Fail
Pass
Fail
Pass
Fail
Pass
Fail
Pass
Fail
Pass
Fail
5
6
7
8
be equipped with the anti-explosion lamp with an appropriate light intensity of 150
~ 200 Lux
10
11
12
13
14
Pass
Fail
15
Pass
Fail
16
Pass
Fail
17
Pass
Fail
Pass
Fail
Pass
Fail
The working ground, protection ground and lightning protection ground of the
18
19
The grounding cables should be led to under the rack; general checking of
grounding
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
SN
Self-check Items
Preparation
20
Pass
Fail
21
Pass
Fail
22
Personnel arrangement
Pass
Fail
23
Pass
Fail
24
Illumination requirements
Pass
Fail
25
Atmospheric pressure
Pass
Fail
26
Air quality
Pass
Fail
27
Safety requirements
Pass
Fail
28
Communication guarantee
Pass
Fail
29
Emergency illumination
Pass
Fail
30
Pass
Fail
31
Pass
Fail
32
Vehicles
Pass
Fail
33
Pass
Fail
34
Cabling requirements
Pass
Fail
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
Dimension of iBSC
3.
Weight
5.
Rack dimensions
The dimensions of a single rack of ZXG10 iBSC : 2000 mm 600 mm
800 mm (H W D).
2.
Cabinet color
IBSC cabinet color: Dark blue
B.2.1.2 Equipment Weight and Bearing Requirement of Floor in the Equipment Room
1.
2.
ZXG10 iBSC Engineering Installation and Commissioning Preparation Guide Internal Use Only
Note
For more information about the equipment parameters, please refer to the
ZXG10 iBSC (V6.20.xx) Technical Manual.