You are on page 1of 267

Thursday,

March 15, 2007

Part II

Department of
Energy
Federal Energy Regulatory Commission

18 CFR Parts 35 and 37


Preventing Undue Discrimination and
Preference in Transmission Service; Final
Rule
sroberts on PROD1PC70 with RULES

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00001 Fmt 4717 Sfmt 4717 E:\FR\FM\15MRR2.SGM 15MRR2
12266 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

DEPARTMENT OF ENERGY regulations and the pro forma open FOR FURTHER INFORMATION CONTACT:
access transmission tariff adopted in Daniel Hedberg (Technical Information),
Federal Energy Regulatory Order Nos. 888 and 889 to ensure that Office of Energy Markets and Reliability,
Commission transmission services are provided on a Federal Energy Regulatory Commission,
basis that is just, reasonable and not 888 First Street, NE., Washington, DC
18 CFR Parts 35 and 37 unduly discriminatory or preferential. 20426, (202) 502–6243.
The final rule is designed to: Strengthen
[Docket Nos. RM05–17–000 and RM05–25–
the pro forma open-access transmission W. Mason Emnett (Legal Information),
000; Order No. 890] Office of the General Counsel—Energy
tariff, or OATT, to ensure that it
achieves its original purpose of Markets, Federal Energy Regulatory
Preventing Undue Discrimination and
remedying undue discrimination; Commission, 888 First Street, NE.,
Preference in Transmission Service
provide greater specificity to reduce Washington, DC 20426, (202) 502–6540.
Issued February 16, 2007. opportunities for undue discrimination Kathleen Barrón (Legal Information),
AGENCY: Federal Energy Regulatory and facilitate the Commission’s Office of the General Counsel—Energy
Commission, DOE. enforcement; and increase transparency Markets, Federal Energy Regulatory
ACTION: Final rule.
in the rules applicable to planning and Commission, 888 First Street, NE.,
use of the transmission system. Washington, DC 20426, (202) 502–6461.
SUMMARY: The Federal Energy EFFECTIVE DATE: This rule will become
Regulatory Commission is amending the effective May 14, 2007. SUPPLEMENTARY INFORMATION:

Paragraph
Table of Contents Nos.

I. Introduction ........................................................................................................................................................................................... 1
II. Background ........................................................................................................................................................................................... 9
A. Historical Antecedent .................................................................................................................................................................. 9
B. Order No. 888 and Subsequent Reforms ..................................................................................................................................... 14
C. EPAct 2005 and Recent Developments ....................................................................................................................................... 22
III. Need for Reform of Order No. 888 .................................................................................................................................................... 26
A. Opportunities for Undue Discrimination Continue to Exist ..................................................................................................... 26
B. Lack of Transparency Undermines Confidence in Open Access and Impedes Enforcement of Open Access Requirements 44
C. Congestion and Inadequate Infrastructure Development Impede Customers’ Use of the Grid ............................................... 52
D. A Consistent Method of Measuring ATC Is Needed .................................................................................................................. 62
E. Discriminatory Pricing of Imbalances .......................................................................................................................................... 70
F. Redispatch/Conditional Firm ....................................................................................................................................................... 73
G. EPAct 2005 Emphasized Certain Policies and Priorities for the Commission ......................................................................... 79
IV. Summary, Scope and Applicability of the Final Rule ..................................................................................................................... 82
A. Summary of Reforms .................................................................................................................................................................... 83
B. Core Elements of Order No. 888 That Are Retained .................................................................................................................. 91
1. Federal/State Jurisdiction ...................................................................................................................................................... 92
2. Native Load Protection .......................................................................................................................................................... 95
3. The Types of Transmission Services Offered ...................................................................................................................... 110
4. Functional Unbundling ......................................................................................................................................................... 117
C. Applicability of the Final Rule .................................................................................................................................................... 124
1. Non-ISO/RTO Public Utility Transmission Providers ......................................................................................................... 124
2. ISO and RTO Public Utility Transmission Providers and Transmission Owner Members of ISOs and RTOs ............... 143
3. Non-Public Utility Transmission Providers/Reciprocity ..................................................................................................... 162
V. Reforms of the OATT .......................................................................................................................................................................... 193
A. Consistency and Transparency of ATC Calculations ................................................................................................................. 193
B. Coordinated, Open and Transparent Planning ........................................................................................................................... 418
C. Transmission Pricing .................................................................................................................................................................... 603
1. General .................................................................................................................................................................................... 603
2. Energy and Generation Imbalances ....................................................................................................................................... 627
3. Credits for Network Customers ............................................................................................................................................. 729
4. Capacity Reassignment .......................................................................................................................................................... 778
5. ‘‘Operational’’ Penalties ......................................................................................................................................................... 826
a. Unreserved Use Penalties ............................................................................................................................................... 826
b. Distribution of Operational Penalties ............................................................................................................................ 850
c. Applicability of Operational Penalties Proposal to RTOs and Other Independent or Non-Profit Entities ............... 866
6. ‘‘Higher of’’ Pricing Policy .................................................................................................................................................... 870
7. Other Ancillary Services ....................................................................................................................................................... 886
D. Non-Rate Terms and Conditions ................................................................................................................................................. 901
1. Modifications to Long-Term Firm Point-to-Point Service ................................................................................................... 901
a. Planning Redispatch and Conditional Firm Options ................................................................................................... 901
b. Proposals for Transparent Redispatch ........................................................................................................................... 1095
c. Other Requested Service Modifications ........................................................................................................................ 1165
2. Hourly Firm Service .............................................................................................................................................................. 1177
3. Rollover Rights ....................................................................................................................................................................... 1214
4. Modification of Receipt or Delivery Points .......................................................................................................................... 1268
sroberts on PROD1PC70 with RULES

5. Acquisition of Transmission Service .................................................................................................................................... 1296


a. Processing of Service Requests ...................................................................................................................................... 1296
b. Reservation Priority ........................................................................................................................................................ 1394
6. Designation of Network Resources ....................................................................................................................................... 1432
a. Qualification as a Network Resource ............................................................................................................................. 1432

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00002 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12267

Paragraph
Table of Contents Nos.

b. Documentation for Network Resources ......................................................................................................................... 1507


c. Undesignation of Network Resources ............................................................................................................................ 1534
7. Clarifications Related to Network Service ............................................................................................................................ 1592
a. Secondary Network Service ........................................................................................................................................... 1592
b. Behind the Meter Generation ......................................................................................................................................... 1614
8. Transmission Curtailments .................................................................................................................................................... 1620
9. Standardization of Rules and Practices ................................................................................................................................ 1633
a. Business Practices ........................................................................................................................................................... 1633
b. Liability and Indemnification ........................................................................................................................................ 1662
10. OATT Definitions ................................................................................................................................................................ 1678
E. Enforcement .................................................................................................................................................................................. 1714
1. General Policy ........................................................................................................................................................................ 1715
2. Civil Penalties ........................................................................................................................................................................ 1724
VI. Information Collection Statement ...................................................................................................................................................... 1752
VII. Environmental Analysis .................................................................................................................................................................... 1758
VIII. Regulatory Flexibility Act Analysis ................................................................................................................................................ 1759
IX. Document Availability ....................................................................................................................................................................... 1760
X. Effective Date and Congressional Notification ................................................................................................................................... 1763
Appendix A: Summary of Compliance Filing Requirements
Appendix B: Commenting Party Acronyms
Appendix C: Pro Forma Open Access Transmission Tariff

Before Commissioners: Joseph T. 2. First, the Final Rule will increase function under the pro forma OATT
Kelliher, Chairman; Suedeen G. nondiscriminatory access to the grid by because it is the means by which
Kelly, Marc Spitzer, Philip D. eliminating the wide discretion that customers consider and access new
Moeller, and Jon Wellinghoff. transmission providers currently have sources of energy and have an
in calculating available transfer opportunity to explore the feasibility of
I. Introduction capability (ATC).3 The calculation of non-transmission alternatives. Despite
1. This Final Rule addresses and ATC is one of the most critical functions this, the existing pro forma OATT
remedies opportunities for undue under the OATT because it determines provides limited guidance regarding
discrimination under the pro forma whether transmission customers can how transmission customers are treated
Open Access Transmission Tariff access alternative power supplies. in the planning process and provides
(OATT) adopted in 1996 by Order No. Despite this, the existing OATT does not them very little information on how
888.1 This landmark rulemaking prescribe how ATC should be calculated transmission plans are developed. These
fostered greater competition in because the Commission sought to rely deficiencies are serious, given the
wholesale power markets by reducing on voluntary efforts by the industry to substantial need for new infrastructure
barriers to entry in the provision of develop consistent methods of ATC in this Nation.4 We act today to remedy
transmission service. In the ten years calculation. This voluntary industry these deficiencies by requiring
since Order No. 888, however, the effort has not proven successful. The transmission providers to open their
Commission has found that the OATT Commission therefore acts today to transmission planning process to
contains flaws that undermine realizing require public utilities, working through customers, coordinate with customers
its core objective of remedying undue the North American Electric Reliability regarding future system plans, and share
discrimination. In the Notice of Corporation (NERC), to develop necessary planning information with
Proposed Rulemaking (NOPR) issued on consistent methodologies for ATC customers.
May 19, 2006, the Commission calculation and to publish those 4. Third, the Final Rule will also
proposed to remedy those flaws.2 After methodologies to increase transparency. increase the efficient utilization of
receiving approximately 6,500 pages of This important reform will eliminate the
comments from close to 300 parties, we wide discretion that exists today in 4 Congress placed special emphasis on the

calculating ATC and ensure that development of transmission infrastructure,


now take final action. We highlight including the consideration of advanced
below the most critical reforms being customers are treated fairly in seeking transmission technologies, in the Energy Policy Act
adopted today. alternative power supplies. of 2005 (EPAct 2005). See Pub. L. 109–58, 119 Stat.
3. Second, the Final Rule will 594 (to be codified in scattered titles of the U.S.C.).
increase the ability of customers to The Commission has taken steps to implement that
1 Promoting Wholesale Competition Through
goal in numerous contexts, including recent
Open Access Non-discriminatory Transmission access new generating resources and rulemaking proceedings that address the promotion
Services by Public Utilities; Recovery of Stranded promote efficient utilization of of transmission investment through pricing reform
Costs by Public Utilities and Transmitting Utilities, transmission by requiring an open, and the siting of certain transmission facilities. See
Order No. 888, 61 FR 21540 (May 10, 1996), FERC transparent, and coordinated Promoting Transmission Investment through
Stats. & Regs. § 31,036 (1996), order on reh’g, Order Pricing Reform, Order No. 679, 71 FR 43294 (Jul.
No. 888–A, 62 FR 12274 (Mar. 14, 1997), FERC
transmission planning process.
31, 2006), FERC Stats. & Regs. § 31,222 (2006), order
Stats. & Regs. § 31,048 (1997), order on reh’g, Order Transmission planning is a critical on reh’g, Order No. 679–A, 72 FR 1152 (Jan. 10,
No. 888–B, 81 FERC § 61,248 (1997), order on reh’g, 2007), FERC Stats. & Regs. § 31,236 (2007), reh’g
Order No. 888–C, 82 FERC § 61,046 (1998), aff’d in 3 The Commission used the term ‘‘Available pending; Regulations for Filing Applications for
relevant part sub nom. Transmission Access Policy Transmission Capability’’ in Order No. 888 to Permits to Site Interstate Electric Transmission
Study Group v. FERC, 225 F.3d 667 (D.C. Cir. 2000) describe the amount of additional capability Facilities, Order No. 689, 71 FR 69440 (Dec. 1,
sroberts on PROD1PC70 with RULES

(TAPS v. FERC), aff’d sub nom. New York v. FERC, available in the transmission network to 2006), FERC Stats. & Regs. § 31,234 (2006), reh’g
535 U.S. 1 (2002). accommodate additional requests for transmission pending. As discussed herein, several actions taken
2 Preventing Undue Discrimination and services. To be consistent with the term generally in this Final Rule also relate to the need for
Preference in Transmission Service, Notice of accepted throughout the industry, the Commission investments in transmission infrastructure and are
Proposed Rulemaking, 71 FR 32,636 (Jun. 6, 2006), revises the pro forma OATT to adopt the term consistent with the Commission’s responsibilities
FERC Stats. & Regs. § 32,603 (2006). ‘‘Available Transfer Capability.’’ under EPAct 2005.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00003 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12268 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

transmission by eliminating artificial past ten years and clarify others that and investor-owned utilities connected
barriers to use of the grid. The existing have proven ambiguous. For example, to each utility’s transmission system.
pro forma OATT allows a transmission we reform our rollover rights policy to Each system covered a limited service
provider to deny a request for long-term ensure that the rights and obligations of area, which was defined by the retail
point-to-point service if the request rollover customers are consistent with franchise decisions of State regulatory
cannot be satisfied in only one hour of the resulting obligations of transmission agencies. This structure of separate
the requested term. This practice providers to plan and upgrade the systems arose naturally primarily due to
discourages the efficient use of the system to accommodate rollovers. We cost and the technological limitations
existing grid and precludes access to remove the price cap on reassigned on the distance over which electricity
alternative power supplies. We reform capacity because it is not necessary to could be transmitted.
this practice by requiring that a remedy market power and doing so will 11. A number of statutory, economic,
conditional firm option be offered to otherwise increase the efficient use of and technological developments in the
customers seeking long-term point-to- existing capacity. We increase the 1970s led to an increase in coordinated
point service, i.e., conditional firm efficient use of existing capacity by operations and competition. Among
service. We also modify the redispatch providing a priority to certain ‘‘pre- those was the passage of the Public
obligations of transmission providers to confirmed’’ requests for service. We Utility Regulatory Policies Act of 1978
increase the efficient utilization of the increase certainty by providing greater (PURPA),6 which was designed to
grid, while also ensuring that reliability clarity regarding the wholesale contracts lessen dependence on foreign fossil
to native load customers is maintained. that qualify as network resources. We fuels by encouraging the development of
5. Fourth, by adopting these and other also adopt numerous clarifications that alternative generation sources and
reforms, the Final Rule facilitates the should assist transmission providers imposing a mandatory purchase
use of clean energy resources such as and customers in implementing and obligation on utilities for generation
wind power. Conditional firm service is using the pro forma OATT from such sources. PURPA also enabled
particularly important to wind resources 8. Our actions in this proceeding have the Commission to order wheeling of
that can provide significant economic been informed to a great extent by the electricity under limited
and environmental value even if comments received in response to our circumstances.7 The rapid expansion
curtailed under limited circumstances. notices of inquiry in the above- and performance of the independent
Open and coordinated transmission captioned dockets and the subsequent power industry following the enactment
planning will enhance the ability of NOPR.5 We appreciate the time and of PURPA demonstrated that traditional,
customers to access clean energy thoughtfulness of all sectors of the vertically integrated public utilities
resources as part of their future resource industry in preparing comments. We need not be the only sources of reliable
portfolio. The Final Rule also benefits have found them very informative and power. During this period, the profile of
clean energy resources by reforming useful in reaching our decisions in this generation investment began to change,
energy and generator imbalance charges. Final Rule. and a market for non-traditional power
These reforms are particularly important supply beyond the purchases required
to intermittent resources such as wind II. Background by PURPA began to emerge. The
power because these resources have A. Historical Antecedent economic and technological changes in
limited ability to control their output the transmission and generation sectors
and, hence, must be assured that 9. In the NOPR, the Commission helped encourage many new entrants in
imbalance charges are no more than explained the historical background that the generating markets that could sell
required to provide appropriate led up to the issuance of Order No. 888, electric energy profitably with smaller
incentives for prudent behavior. and the initiation of this rulemaking scale technology at a lower price than
6. Fifth, the Final Rule will strengthen proceeding. We repeat that history here many utilities selling from their existing
compliance and enforcement efforts. We to place in context the actions we take generation facilities at rates reflecting
are increasing the transparency of pro today. cost. However, it became increasingly
forma OATT administration, thereby 10. In the first few decades after clear that the potential consumer
increasing the ability of customers and enactment of the Federal Power Act benefits that could be derived from
our Office of Enforcement to detect (FPA) in 1935, the industry was these technological advances could be
undue discrimination. We are adopting characterized mostly by self-sufficient, realized only if more efficient generating
operational penalties for clear violations vertically integrated electric utilities, in plants could obtain access to the
of an OATT, thereby enhancing which generation, transmission, and regional transmission grids. Because
compliance while also reducing the distribution facilities were owned by a many traditional vertically integrated
burdens on our Office of Enforcement. single entity and sold as part of a utilities still did not provide open
We are also increasing the clarity of bundled service to wholesale and retail access to third parties and favored their
many other OATT requirements, customers. Most electric utilities built own generation if and when they
thereby facilitating compliance by their own power plants and
transmission providers with our transmission systems, entered into 6 Pub. L. 95–617, 92 Stat. 3117 (1978) (codified

regulations. This Final Rule thus reflects interconnection and coordination in U.S.C. titles 15, 16, 26, 30, 42, and 43).
7 Section 211 of the FPA, 16 U.S.C. 824j. In earlier
the close integration of our Office of arrangements with neighboring utilities,
years, a few customers were able to obtain access
Enforcement into policy development at and entered into long-term contracts to as a result of litigation, beginning with the U.S.
the Commission. Several of the reforms make wholesale requirements sales Supreme Court’s decision in Otter Tail Power
we adopt today are informed by our (bundled sales of generation and Company v. United States, 410 U.S. 366 (1973).
Additionally, some customers gained access by
experience with OATT administration transmission) to municipal, cooperative, virtue of Nuclear Regulatory Commission license
through oversight, audits, and conditions and voluntary preference power
sroberts on PROD1PC70 with RULES

investigations performed by the Office 5 Preventing Undue Discrimination and


transmission arrangements associated with Federal
of Enforcement. Preference in Transmission Services, Notice of power marketing agencies. See, e.g., Consumers
Inquiry, 112 FERC ¶ 61,299 (2005) (NOI); Power Co., 6 NRC 887, 1036–44 (1977); Toledo
7. Finally, we modify and improve Information Requirements for Available Transfer Edison Co., 10 NRC 265, 327–34 (1979); Florida
several provisions of the pro forma Capability, Notice of Inquiry, 111 FERC ¶ 61,274 Municipal Power Agency v. Florida Power and Light
OATT using our experience over the (2005) (ATC NOI). Co., 839 F. Supp. 1563 (M.D. Fla. 1993).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00004 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12269

provided transmission access to third of delivery. As these early tariffs were transmission services. This meant
parties, access to cheaper, more efficient offered only by transmission providers public utilities had to take transmission
generation sources remained limited. that volunteered to provide service to service (including ancillary services) for
12. The Commission encouraged the third parties, they resulted in a their own new wholesale sales and
development of independent power patchwork of open access that was not purchases of electric energy under the
producers (IPPs), as well as emerging sufficient to facilitate wholesale open access tariffs, and to separately
power marketers, by authorizing market- generation markets. state their rates for wholesale
based rates for their power sales on a 13. In response to the competitive generation, transmission and ancillary
case-by-case basis, and by encouraging developments following PURPA, and services.13 Each public utility was
more widely available transmission the fact that limited transmission access required to file the pro forma OATT
access on a case-by-case basis. Market- and significant regulatory barriers included in Order No. 888 without any
based rates helped to develop continued to constrain the development deviation (except a limited number of
competitive bulk power markets by of generation by independent power terms and conditions that reflect
allowing generating utilities to move producers, Congress enacted Title VII of regional practices).14 After the
more quickly and flexibly to take the Energy Policy Act of 1992 (EPAct effectiveness of their OATTs, public
advantage of short-term or even long- 1992).10 EPAct 1992 reduced regulatory utilities were allowed to file, pursuant
term market opportunities than those barriers to entry by creating a class of to section 205 of the FPA, deviations
utilities operating under traditional ‘‘Exempt Wholesale Generators’’ that that were consistent with or superior to
cost-of-service tariffs. In approving these were exempt from the requirements of the pro forma OATT’s terms and
market-based rates, the Commission the Public Utility Holding Company Act conditions. Because certain owners,
required that the seller and its affiliates of 1935.11 EPAct 1992 also expanded controllers or operators of interstate
lack market power or mitigate any the Commission’s authority to approve transmission facilities were not subject
market power that they may have had.8 applications for transmission services to the Commission’s jurisdiction under
The major concern of the Commission under sections 211 and 212 of the sections 205 and 206 and thus were not
was whether the seller or its affiliates FPA.12 Though the Commission subject to Order No. 888, the
could limit competition and thereby aggressively implemented expanded Commission adopted a reciprocity
drive up prices. A key inquiry became section 211, it ultimately concluded that provision in the pro forma OATT that
whether the seller or its affiliates owned the procedural limitations in section conditions the use by a non-public
or controlled transmission facilities in 211 thwarted the Commission’s ability utility of a public utility’s open access
the relevant service area and therefore, to effectively eliminate undue services on an agreement to offer non-
by denying access or imposing discrimination in the provision of discriminatory transmission services in
discriminatory terms or conditions on transmission service. return.
transmission service, could foreclose 15. In addition to imposing the
B. Order No. 888 and Subsequent
other generators from competing. functional unbundling requirement, the
Reforms
Beginning in the late 1980s, in order to Commission also encouraged broader
mitigate their market power to meet the 14. In April 1996, as part of its reforms through the formation of
Commission’s conditions, public statutory obligation under sections 205 independent system operators (ISOs).
utilities seeking Commission and 206 of the FPA to remedy undue The Commission stated that ISOs can
authorization for blanket approval of discrimination, the Commission provide significant benefits such as
market-based rates for generation adopted Order No. 888 prohibiting enhancing regional efficiencies and
services under section 205 of the FPA public utilities from using their further remedying undue
filed ‘‘open access’’ transmission tariffs monopoly power over transmission to discrimination.15 While the
of general applicability.9 The unduly discriminate against others. In Commission declined to mandate ISOs,
Commission also approved proposed that order, the Commission required all it set forth eleven principles for
mergers under section 203 of the FPA public utilities that own, control or assessing ISO proposals submitted to
on the condition that the merging operate facilities used for transmitting the Commission.16
companies remedy anticompetitive electric energy in interstate commerce to 16. Order No. 888 also clarified the
effects potentially caused by the merger file open access non-discriminatory Commission’s interpretation of the
by filing ‘‘open access’’ tariffs. The early transmission tariffs that contained Federal and State jurisdictional
tariffs submitted in market-based rate minimum terms and conditions of non- boundaries over transmission and local
proceedings under section 205 and discriminatory service. It also obligated distribution. While Order No. 888
merger proceedings under section 203 such public utilities to ‘‘functionally reaffirmed that the Commission has
did not, however, provide access to the unbundle’’ their generation and exclusive jurisdiction over the rates,
transmission system that was 13 This is known as ‘‘functional unbundling’’
10 Pub. L. 102–486, 106 Stat. 2776 (1992)
comparable to the service the (codified at, among other places, 15 U.S.C. 79z–5a because the transmission element of a wholesale
transmission providers used for their and 16 U.S.C. 796 (22–25), 824j–l). sale is separated or unbundled from the generation
own purposes. Rather, they typically 11 15 U.S.C. 79a, repealed by EPAct 2005 sec. element of that sale, although the public utility may
made available only point-to-point 1263; see Repeal of the Public Utility Holding provide both functions. See infra section IV.B.4 of
Company Act of 1935 and Enactment of the Public this Final Rule.
transmission service, i.e., service from a 14 See Order No. 888 at 31,769–70 (noting that the
Utility Holding Company Act of 2005, Order No.
single point of receipt to a single point 667, 70 FR 75592 (Dec. 20, 2005), FERC Stats. & pro forma OATT expressly identified certain non-
Regs. ¶ 31,197 (2005), order on reh’g, Order No. rate terms and conditions, such as the time
8 See, e.g., Dartmouth Power Associates Limited 667–A, 71 FR 28446 (May 16, 2006), FERC Stats. deadlines for determining available transfer
Partnership, 53 FERC ¶ 61,117 (1990); & Regs. ¶ 31,213 (2006), order on reh’g, Order No. capability in section 18.4 or scheduling changes in
Commonwealth Atlantic Limited Partnership, 51 667–B, 71 FERC 42750 (Jul. 28, 2006), FERC Stats. sections 13.8 and 14.6, that may be modified to
sroberts on PROD1PC70 with RULES

FERC ¶ 61,368 (1990); Doswell Limited Partnership, & Regs. ¶ 31,224 (2006), reh’g pending. account for regional practices if such practices are
50 FERC ¶ 61,251 (1990); Citizens Power & Light 12 16 U.S.C. 824j (authorizing the Commission to reasonable, generally accepted in the region, and
Co., 48 FERC ¶ 61,210 (1989); Ocean State Power, require transmission utilities to provide service in consistently adhered to by the transmission
44 FERC ¶ 61,261 (1988); and Orange and Rockland certain circumstances); 16 U.S.C. 824k (establishing provider).
Utilities, Inc., 42 FERC ¶ 61,012 (1988). rates for service provided pursuant to an order 15 Order No. 888 at 31,655.
9 See Order No. 888 at 31,644 n.52. under section 211). 16 Id. at 31,730–32.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00005 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12270 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

terms, and conditions of unbundled ‘‘current industry practices, standards eliminate any residual discrimination in
retail transmission in interstate and criteria’’ and to describe their transmission services that can occur
commerce by public utilities, it methodology in their tariffs.21 The when the operation of the transmission
nevertheless recognized the legitimate Commission noted that the requirement system remains in the control of a
concerns of State regulatory authorities that transmission providers purchase vertically integrated utility. The
regarding the transmission component only ATC that is posted as available Commission found that RTOs would
of bundled retail sales. The Commission ‘‘should create an adequate incentive for increase the efficiency of wholesale
therefore declined to extend its them to calculate ATC and TTC as markets by eliminating pancaked rates,
unbundling requirement to the accurately and as uniformly as internalizing parallel flow, managing
transmission component of bundled possible.’’ 22 congestion efficiently, and operating
retail sales. On appeal, the U.S. 19. The electric industry continued to markets for energy, capacity and
Supreme Court affirmed this element of undergo economic and regulatory ancillary services. The Commission
Order No. 888, finding that the changes in the years following the established an open, collaborative
Commission made a statutorily issuance of Order No. 888. Retail access process that relied on voluntary regional
permissible choice.17 was adopted by approximately 25 states participation to design RTOs tailored to
17. The same day it issued Order No. in the late 1990s.23 This State the specific needs of each region. The
888, the Commission issued a restructuring activity spurred significant Commission noted, however, that ‘‘[i]f
companion order, Order No. 889,18 changes at the wholesale level as well the industry fails to form RTOs under
addressing the separation of vertically by encouraging or requiring the this approach, the Commission will
integrated utilities’ transmission and divestiture of generation plants by reconsider what further regulatory steps
merchant functions, the information traditional electric utilities and the are in the public interest.’’26
transmission providers were required to development of ISOs that could manage 21. Following Order No. 2000, RTOs
make public, and the electronic means short-term energy markets necessary to were approved in several regions of the
they were required to use to do so. support retail access. At the same time, country including the Northeast (PJM;
Order No. 889 imposed Standards of there was a significant increase in the ISO New England),27 the Midwest
Conduct governing the separation of, number of mergers between traditional (MISO) and the South (SPP). In most
and communications between, the electric utilities and between electric cases, RTOs have assumed
utility’s transmission and wholesale utilities and gas pipeline companies, responsibility for calculating ATC
power functions, to prevent the utility and large increases in the number of across the footprint of the RTO, as well
from giving its merchant arm power marketers and independent as the planning and expansion of the
preferential access to transmission generation facility developers entering transmission grid, at least for facilities
information. All public utilities that the marketplace. Trade in bulk power necessary for maintaining system
owned, controlled or operated facilities markets increased significantly and the reliability. However, large areas of the
used in the transmission of electric Nation’s transmission grid was used Nation have not developed RTOs using
energy in interstate commerce were more heavily and in new ways as the voluntary structure adopted by the
required to create or participate in an customers took advantage of the pro Commission in Order No. 2000.
Open Access Same-Time Information forma OATT and purchased power from Moreover, transmission customers have
System (OASIS) that was to provide competitive sellers. complained that even in RTO markets
existing and potential transmission 20. In the wake of these changes, in
there are instances when comparable
customers the same access to December 1999, the Commission
transmission service is not provided,
transmission information. adopted Order No. 2000.24 That
particularly in the area of transmission
18. Among the information public rulemaking recognized that Order No.
planning.
utilities were required to post on their 888 set the foundation upon which
OASIS was the transmission provider’s competitive electric markets could C. EPAct 2005 and Recent
calculation of ATC. Though the develop, but did not eliminate the Developments
Commission acknowledged that before- potential to engage in undue 22. Enacted on August 8, 2005, EPAct
the-fact measurement of the availability discrimination and preference in the added a number of new authorities and
of transmission service is ‘‘difficult,’’ it provision of transmission service.25 The priorities for the Commission and
concluded that it was important to give rulemaking also recognized that Order emphasized certain of its existing
potential transmission customers ‘‘an No. 888 did not address the regional obligations. Among other things, EPAct
easy-to-understand indicator of service nature of the grid, including the 2005 recognized the importance of
availability.’’ 19 Because formal methods treatment of parallel flows, pancaked adequate transmission infrastructure
did not then exist to calculate ATC and rates, and congestion management. development and its role in facilitating
total transfer capability (TTC), the Thus, the Commission encouraged the the development of competitive
Commission encouraged industry efforts creation of RTOs to address important wholesale markets. The Congressional
to develop consistent methods for operational and reliability issues and directives in EPAct 2005 are intended to
calculating ATC and TTC.20 Order No. reverse the decline in transmission
21 Id.
889 ultimately required transmission 22 Id. infrastructure investment. For example,
providers to base their calculations on 23 See Energy Information Administration, Retail Congress required the Commission to
Unbundling—U.S. Summary (2005), http://www. adopt a rule establishing incentive
17 New York v. FERC, 535 U.S. 1 (2002). eia.doe.gov/oil_gas/natural_gas/restructure/state/ ratemaking for transmission
18 Open Access Same-Time Information System us.html. infrastructure to help promote reliability
(Formerly Real-Time Information Networks) and 24 Regional Transmission Organizations, Order
Standards of Conduct, Order No. 889, 61 FR 21737 No. 2000, 65 FR 809 (Jan. 6, 2000), FERC Stats. &
and reduce congestion.28 Congress also
sroberts on PROD1PC70 with RULES

(May 10, 1996), FERC Stats. & Regs. ¶ 31,035 (1996), Regs. ¶ 31,089 (1999), order on reh’g, Order No.
order on reh’g, Order No. 889–A, FERC Stats. & 2000–A, 65 FR 12088 (Mar. 8, 2000), FERC Stats. 26 Id.at 30,993.
Regs. ¶ 31,049 (1997), order on reh’g, Order No. & Regs. ¶ 31,092 (2000), aff’d sub nom. Public 27 A list of commenter acronyms can be found in
889–B, 81 FERC ¶ 61,253 (1997). Utility District No. 1 of Snohomish County, Appendix B.
19 Order No. 889 at 31,605. Washington v. FERC, 272 F.3d 607 (D.C. Cir. 2001). 28 EPAct 2005 sec. 1241 (to be codified at section
20 Id. at 31,607. 25 Order No. 2000 at 31,015. 219 of the FPA, 16 U.S.C. 824s).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00006 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12271

directed the Commission to encourage 23. Recognizing the need for reform of clarity in the obligations of transmission
the deployment of advanced Order No. 888 in light of the providers and customers alike. We turn
technologies.29 Congress further Commission’s continuing concern next to a more complete explanation of
directed the Commission to ‘‘exercise its regarding whether the pro forma OATT this need for reform.
authority’’ under EPAct 2005 ‘‘in a adequately remedies undue
manner that facilitates the planning and discrimination, the Commission issued III. Need for Reform of Order No. 888
expansion of transmission facilities to an NOI on September 16, 2005 36 A. Opportunities for Undue
meet the reasonable needs of load- seeking comments on appropriate Discrimination Continue To Exist
serving entities.’’30 Congress also gave reforms of the Order No. 888 pro forma
the Commission certain ‘‘backstop’’ OATT. In the NOI, the Commission 26. Although Order No. 888 has been
transmission siting authority, and expressed its preliminary view that successful in many important respects,
authorized the creation of interstate reforms to the pro forma OATT and the need for reform of the Order No. 888
compacts establishing transmission public utilities’ OATTs are necessary to pro forma OATT has been apparent for
siting agencies.31 EPAct 2005 also avoid undue discrimination or some time. In 1999, the Commission
authorized the Commission to require preference in the provision of held, in adopting Order No. 2000, that
unregulated transmitting utilities transmission service. The NOI sought the pro forma OATT could not fully
(except for certain small entities) to comments on how best to accomplish remedy undue discrimination because
provide access to their transmission the Commission’s goals, specifically transmission providers retained both the
facilities on a comparable basis.32 with respect to enhancements that are incentive and the ability to discriminate
Congress further ordered the needed to (1) Remedy any unduly against third parties, particularly in
Department of Energy (DOE) to study discriminatory or preferential areas where the pro forma OATT left the
the benefits of economic dispatch and application of the pro forma OATT or transmission provider with significant
required the Commission to convene (2) improve the clarity of the Order No. discretion.39 The Commission made a
regional joint boards to develop a report 888 pro forma OATT and the individual
similar finding in Order No. 2003,40
to Congress containing public utility tariffs in order to more
holding that opportunities for undue
recommendations for the use of security readily identify violations and facilitate
discrimination continue to exist in areas
constrained economic dispatch within compliance.
each region.33 Congress also directed the 24. The Commission received over where the pro forma OATT leaves
Commission to facilitate price 4,000 pages of initial and reply transmission providers with substantial
transparency in markets for the sale and comments on the NOI. Based on these discretion.41 The NOPR reaffirmed these
transmission of electric energy in comments, the comments submitted in findings, preliminarily concluding that
interstate commerce, having due regard response to the ATC NOI,37 our opportunities for undue discrimination
for the public interest, the integrity of experience in implementing Order No. continue to exist in the provision of
those markets, fair competition, and the 888, and the changes in the industry open access transmission service. The
protection of consumers, and it since we adopted it, the Commission Commission therefore proposed a
authorized the Commission to prescribe proposed to reform the pro forma OATT number of reforms to the pro forma
rules to provide for the dissemination of in a number of ways. The Commission OATT to address the opportunities and
information about the availability and issued the NOPR on May 19, 2006 incentives transmission providers have
price of wholesale electric energy and proposing a number of reforms aimed at to unduly discriminate.
transmission service.34 Finally, remedying undue discrimination in the
Comments
Congress emphasized compliance with provision of open access transmission
the Commission’s regulations, adopting service and improving the clarity of the 27. Many commenters agree with the
and increasing the civil and criminal pro forma OATT and the individual Commission that reforms to the pro
penalties for violations of Commission- tariffs of transmission providers in order forma OATT are needed because there
administered statutes and regulations.35 to more readily identify violations and continue to be both the opportunity and
facilitate compliance. The Commission incentive for transmission providers to
29 EPAct 2005 sec. 1223 (to be codified at 42 received over 5,700 pages of initial and engage in undue discrimination.42
U.S.C. 16422). Indeed, Congress provided specific reply comments in response. In
guidance as to the types of advanced technologies
response to comments on the particular 28. Several commenters offered
that should be encouraged in infrastructure examples of their experiences with
improvements to include, among others, optimized issue of redispatch and conditional firm
transmission line configurations (including service (discussed in more detail transmission providers, where they
multiple phased transmission lines), controllable below), the Commission issued a Notice believe transmission providers have
load, distributed generation (including PV, fuel acted in an unduly discriminatory
cells, and microturbines), and enhanced power of Request for Supplemental Comments
device monitoring. Id. on November 15, 2006,38 that resulted
30 EPAct 2005 sec. 1233(a) (to be codified at in receipt of an additional 750 pages of 39 Order No. 2000 at 31,105.
section 217(b)(4) of the FPA, 16 U.S.C. 824q). comments. 40 See Standardization of Generator
31 EPAct 2005 sec. 1221(a) (to be codified at
25. Based on this voluminous record, Interconnection Agreements and Procedures, Order
section 216 of the FPA, 16 U.S.C. 824p). No. 2003, 68 FR 49845 (Aug. 19, 2003), FERC Stats.
32 EPAct 2005 sec. 1231 (to be codified at section
the Commission concludes that reform & Regs. ¶ 31,146 at P 11–12 (2003), order on reh’g,
211A of the FPA, 16 U.S.C. 824j–1) of the pro forma OATT and associated Order No. 2003–A, 69 FR 15932 (Mar. 26, 2004),
33 EPAct 2005 sec. 1234 (to be codified at 42 amendments to its regulations are FERC Stats. & Regs. ¶ 31,160 (2004), order on reh’g,
U.S.C. 16432); EPAct 2005 sec. 1298 (to be codified necessary to reduce the potential for Order No. 2003–B, 70 FR 265 (Jan. 4, 2005), FERC
at section 223 of the FPA, 16 U.S.C. 824w). EPAct Stats. & Regs. ¶ 31,171 (2004), order on reh’g, Order
undue discrimination and provide No. 2003–C, 70 FR 37,661 (Jun. 30, 2005), FERC
2005 sec. 1234(b) defined economic dispatch as
‘‘the operation of generation facilities to produce Stats. & Regs. ¶ 31,190 (2005), aff’d sub nom.
energy at the lowest cost to reliably serve sec. 1284(e) (to be codified at section 316A of the National Association of Regulatory Utility
sroberts on PROD1PC70 with RULES

consumers, recognizing any operational limits of FPA, 16 U.S.C. 825o–1). Commissioners v. FERC, No. 04–1148, 2007 U.S.
generation and transmission facilities.’’ 36 See supra note 5. App. LEXIS 626 (D.C. Cir. Jan. 12, 2007).
34 EPAct 2005 sec. 1281 (to be codified at section 37 Id. 41 Order No. 2003 at P 11–12.

220 of the FPA, 16 U.S.C. 824t). 38 Preventing Undue Discrimination and 42 E.g., APPA, EPSA, East Texas Cooperatives,
35 EPAct 2005 sec. 1284(d) (to be codified at Preference in Transmission Service, 117 FERC Fayetteville, NRG, Occidental, TAPS, TDU Systems,
section 316 of the FPA, 16 U.S.C. 825o); EPAct 2005 ¶ 61,185 (2006). Williams, Entegra Reply, and NRECA Reply.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00007 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12272 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

fashion.43 Constellation claims that on been largely mitigated by current transmission customers’ lack of
multiple occasions it has been denied a regulatory policies and changes in the understanding of the OATT
transmission request when the industry. EEI explains that, unlike the requirements, and the data available on
transmission provider’s OASIS indicates situation that existed when the OASIS.45
that ATC is available, but Constellation Commission enacted Order No. 888, 34. New Mexico Attorney General
had no effective and timely way to much of the country’s transmission argues that the traditional State-
challenge that determination because of facilities are now under the control of regulated, vertically-integrated cost-of-
the ATC ‘‘black box.’’ Constellation RTOs and ISOs. In addition, EEI states, service world is not in need of reform.
states that given that its needs for other transmission providers have Contrary to the ‘‘conspiracy theorists’’
transmission service are often near-term transferred (or are in the process of who argue that utilities have an
or immediate—e.g., to facilitate a load- transferring) the administration of their incentive to engage in undue
serving obligation or wholesale OATTs and OASIS functions to discrimination and preference in
transaction that must be consummated independent transmission service transmission services, New Mexico
quickly—seeking redress at the coordinators. Even among the Attorney General asserts that utilities
Commission for improperly denied transmission providers who have taken have an incentive to maximize
service generally is not time- or cost- neither of those steps, EEI argues that throughput and revenue between State-
effective. Instead, Constellation asserts, the open access requirements of Order level rate cases because incremental
it is often forced to accept the No. 888 and the Standards of Conduct transmission revenue is not deducted
determination of the transmission of Order Nos. 889 and 2004 have largely from the State-jurisdictional retail
provider that ATC is not available (even eliminated the ability of transmission revenues between rate cases. Similarly,
though its OASIS may indicate providers to engage in undue Southern, in its reply comments, asserts
otherwise) and seek alternate discrimination in the provision of that broad claims of undue
transmission paths and/or products to transmission service.44 In addition, EEI discrimination fail to take into
consummate its transaction. states, the Commission’s expanded civil consideration that vertically-integrated
29. Powerex also describes instances penalty authority added to the FPA by utilities have more of an incentive to act
where a transmission provider has EPAct 2005 gives the Commission a appropriately than do independent
granted short-term firm point-to-point powerful tool that will further eliminate utilities because the former have more
transmission service requests to any remaining incentive of transmission to lose (e.g., loss of market-based rates,
transmission customers who have been providers to engage in undue state prudence reviews of costs, etc.) if
allowed to remain in the queue, even discrimination in the provision of they are found to have engaged in
when zero ATC is posted, in the hopes transmission service. Therefore, EEI wrong-doing. Southern states that any
that a transmission provider’s OASIS asserts, any modifications to the OATT OATT revisions ultimately adopted by
site wrongly indicates zero ATC or will should be narrowly tailored to address the Commission must be reasonably
soon be updated. Powerex asserts that the perceptions of residual undue tailored to address an identified
such practices clog the short-term point- discrimination. To the extent that such problem or to provide a specific
to-point transmission queue with perceptions exist, however, Community improvement.
multiple requests and result in Power Alliance states that, in the 35. Other commenters argue that the
duplicative requests for service that absence of concrete record evidence, Commission’s focus should be on
reflect customers’ attempts to secure they are just that—perceptions. transmission providers in non-organized
service, rather than the actual quantity 32. Although Duke strongly supports, markets, arguing that remaining
of service needed. Moreover, Powerex as a policy matter, OATT reforms that concerns about undue discrimination
argues, transmission provider discretion will eliminate the perception that undue have already been addressed in the
in this area and the lack of transparency discrimination is possible and/or likely, world of ISOs and RTOs.46 According to
raise customer concerns about Duke argues that the FPA does not ISO/RTO Council, this proceeding
preferential treatment. provide the Commission the authority to provides an opportunity for the
30. Occidental claims that it has first- remedy mere ‘‘opportunities’’ to Commission to harmonize the worlds of
hand experience with a vertically discriminate. Duke states that, in some organized and non-organized markets in
integrated transmission provider that, cases, the Commission is attempting to a manner that encourages competition,
despite having an OATT, appears to remedy an opportunity for undue promotes non-discriminatory access,
have persistently used its transmission discrimination that does not exist or is and maximizes the flow of electricity
system to preferentially benefit its proposing to impose a remedy that does across various ISO/RTO and non-ISO/
merchant function. Similarly, Williams not actually remedy the perceived RTO regions. ISO/RTO Council states
alleges that its interests have been opportunity. Duke notes, however, that that, in the existing regulatory
consistently and significantly some OATT terms and conditions are environment, a utility that is not a
compromised by the discretion afforded subject to multiple interpretations and member of an ISO or RTO can sell into,
transmission providers in the argues that the Commission can, and or purchase from, an ISO or RTO market
interpretation of the OATT and the lack should, justify the OATT reforms even though the non-ISO/RTO utility
of transparency in requesting, proposed in the NOPR as reforms operates under tariff rules that are less
scheduling and interrupting of needed to provide clarity to existing open and transparent, particularly in
transmission service. policies. terms of access to generation resources
31. Other commenters, however, 33. With regard to specific allegations
and pricing/system information, than
argue that the Commission’s proposed made by commenters, several
their competitors that belong to an ISO
reforms are based on unsupported transmission providers respond that the
or RTO. Such asymmetry, ISO/RTO
allegations of undue discrimination. EEI examples given by transmission
Council argues, operates as an
sroberts on PROD1PC70 with RULES

maintains that any opportunities to customers do not illustrate instances of


engage in undue discrimination have undue discrimination. Rather, they 45 See, e.g., Entergy Reply, Progress Energy Reply,
assert, these examples demonstrate the and Southern Reply.
43 See, e.g., Dow, Fayetteville, Occidental, and 46 E.g., Indicated New York Transmission

Williams. 44 See also Southern Reply. Owners, ISO/RTO Council, and Northeast Utilities.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00008 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12273

impediment to fair and non- to deny transmission or to offer Order No. 888 at 31,669. Through this
discriminatory transmission access and transmission on a basis that is inferior Final Rule, the Commission exercises
management of grid congestion. to that which they provide to that remedial authority again to limit
36. ISO/RTO Council states that its themselves.47 Such an incentive can further opportunities for undue
members do not seek to impose their lead to unduly discriminatory behavior discrimination, by minimizing areas of
market designs on the rest of the nation. against third parties, particularly if discretion, addressing ambiguities and
At the same time, ISO/RTO Council public utilities have unnecessarily clarifying various aspects of the pro
argues that meaningful reform should broad discretion in the application of forma OATT.
ensure a level of transparency (of both their tariffs. This discretion also can 41. We disagree with commenters
price and the dispatch utilized by non- create problems for transmission who assert that the Commission is
ISO/RTO vertically-integrated entities) providers seeking to comply with our relying on unsubstantiated allegations of
in regions without an ISO or RTO that regulations in good faith because so discriminatory conduct to justify OATT
can assist the flow of electricity and many issues are left for their reform. The courts have made clear that
enhance reliability and planning in both interpretation, thereby increasing the the Commission need not make specific
ISO/RTO and non-ISO/RTO regions. possibility of disputes with factual findings of discrimination in
37. Exelon urges the Commission to transmission customers and order to promulgate a generic rule to
hold the transmission providers outside enforcement actions by the eliminate undue discrimination.52 In
ISOs or RTOs to the same standard of Commission.48 Transmission customers AGD, the court explained that the
non-discrimination that exists within also have found ways to use the tariffs promulgation of generic rate criteria
those organizations. Further, MISO/PJM to their own advantage, particularly in involves the determination of policy
States argue that in order to achieve the scheduling and queuing processes.49 goals and the selection of the means to
some level of independence in non-RTO achieve them and that courts do not
regions, non-independent transmission 40. As some commenters note,
opportunities for undue discrimination insist on empirical data for every
providers should be encouraged to turn proposition upon which the selection
over operational control of their persist, particularly in areas where the
pro forma OATT leaves the depends: ‘‘[a]gencies do not need to
transmission systems to an independent conduct experiments in order to rely on
coordinator of transmission whose transmission provider with substantial
discretion. The Commission has a the prediction that an unsupported
functions would include security stone will fall.’’ 53 During this multi-year
coordination, determination of ATC, responsibility under section 206 of the
FPA to remedy undue discrimination. proceeding, the Commission has
granting of transmission service and received many comments arguing that
oversight for transmission planning. Indeed, the court concluded in
Associated Gas Distributors v. FERC,50 commenters have either experienced or
38. Finally, EPSA suggests that the perceived that they have experienced
Commission establish a one-year review that, like the Natural Gas Act,51 the FPA
‘‘fairly bristles’’ with concern over unduly discriminatory conduct by
period for the reformed pro forma
undue discrimination. Based on AGD, transmission providers. Even
OATT. EPSA urges the Commission to
the Commission determined in Order transmission providers have
revisit this Final Rule after one year of
No. 888 that: acknowledged that there is a continuing
operation under the reformed pro forma
The Commission has a mandate under perception that there is the opportunity
OATT to ensure that the revisions
sections 205 and 206 of the FPA to ensure for them to unduly discriminate against
adopted here do, in fact, protect against
that, with respect to any transmission in their competitors and, accordingly, they
non-discriminatory or preferential
interstate commerce or any sale of electric state their support for our reform
behavior by transmission providers.
energy for resale in interstate commerce by effort.54 Moreover, it is undisputed that
NRECA responds that, after this a public utility, no person is subject to any the existing pro forma OATT provides
comprehensive rulemaking process, undue prejudice or disadvantage. We must wide discretion in implementing some
there is simply no need for another determine whether any rule, regulation, of its basic requirements, such as the
major look at the OATT in one year. practice or contract affecting rates for such
assessment of whether sufficient ATC
Moreover, NRECA states, one year is transmission or sale for resale is unduly
discriminatory or preferential, and must exists to grant third party access to the
likely too short a period for the
prevent those contracts and practices that do grid and the manner in which new
Commission and industry participants
not meet this standard. * * * AGD facilities are planned to satisfy third
to fully appreciate all of the
demonstrates that our remedial power is very party needs. This wide discretion, when
consequences of those elements of
broad and includes the ability to order coupled with a transmission provider’s
OATT reform resulting from this industry-wide non-discriminatory open incentive to discriminate, creates
proceeding. At the same time, NRECA access as a remedy for undue discrimination. opportunities for discrimination under
agrees that the Commission should
the pro forma OATT. We have an
carefully monitor implementation of the 47 Order No. 888 at 31,682. obligation under section 206 to remedy
reformed OATT. This monitoring, 48 See, e.g., Order No. 2003 at P 11–12. that discrimination.
NRECA states, must be an ongoing 49 See, e.g., Potomac Economics, Ltd., 2004 State
42. It is thus clear to us that,
process and cannot wait a year to begin. of the Market Report: Midwest ISO at 30–31, 34–35
(Jun. 2005), http://www.midwestmarket.org/ notwithstanding the Commission’s
Commission Determination publish/Document/2b8a32_103ef711180_-7bf20a efforts in Order No. 888, opportunities
39. The Commission concludes that 48324a/2004%20MISO%20SOM%20Report.pdf? to engage in undue discrimination can
action=download&_property=Attachment and will persist unless the existing pro
reforms are needed to address (explaining that the queuing process, by giving
deficiencies in the pro forma OATT that customers the opportunity to submit multiple forma OATT is reformed. We therefore
have become apparent since 1996, by requests for service, provides a low- or no-cost exercise our broad remedial authority
limiting remaining opportunities for option that restricts other customers’ access to today to limit these remaining
congested interfaces, and the scheduling process, by
sroberts on PROD1PC70 with RULES

undue discrimination. As the allowing customers to leave transmission requests 52 TAPS v. FERC, 225 F.3d at 667, 688; National
Commission found in Order No. 888, it unconfirmed, provides a free option that may invite
Fuel Gas Supply Corp. v. FERC, 468 F.3d 831 (D.C.
is in the economic self-interest of hoarding or result in underutilized capacity).
Cir. 2006) (National Fuel).
transmission monopolists, particularly 50 824 F.2d 981 (D.C. Cir. 1987) (AGD). 53 824 F.2d at 1008.

those with high-cost generation assets, 51 15 U.S.C. 717. 54 See, e.g., Duke and EEI.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00009 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12274 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

opportunities for undue discrimination. discrimination and makes it more depend on their transmission providers’
The Commission concludes that any difficult to detect. The Commission systems for the vital services they need
additional costs incurred by reasoned that this lack of sufficient to serve their loads. APPA argues that
transmission providers to implement transparency was caused in part by the Commission not only has an
the reforms required in this Final Rule inadequate compliance with the existing obligation to act to remedy undue
are fully justified by the need to ensure OASIS regulations and in part by discrimination when it sees it, but also
open, transparent and non- inadequate transparency requirements. has an affirmative duty to look for it.
discriminatory access to transmission The Commission stated that the According to APPA, the Commission
service. We also believe it is appropriate proposed reforms were intended to must continue to actively regulate the
to adopt these reforms by rulemaking, address both elements of the problem in transmission services that public utility
rather than rely on complaints filed by an effort to increase confidence in open transmission providers offer, even if full
transmission customers or other parties. access tariffs and to facilitate transparency is achieved through the
Case-by-case application of the reforms compliance with the Commission’s revisions to the OATT implemented in
adopted in this Final Rule would be regulations and its enforcement of them. the instant docket.
inappropriate since the most
Comments 48. EPSA agrees that greater
fundamental problems addressed here
arise from deficiencies in the pro forma 46. Williams states that its interests transparency will help enable market
OATT itself, not simply the have been consistently and significantly participants and the Commission to
implementation of the pro forma OATT compromised by the discretion afforded monitor and audit the behavior of
by a few transmission providers. Also, transmission providers in the transmission providers. EPSA states that
we decline to establish a one-year interpretation of the OATT and the lack the several ‘‘black boxes’’ shielding
review period for the reformed pro of transparency in requesting, discriminatory transmission service
forma OATT, as EPSA recommends. scheduling and interrupting of over the past ten years must be opened.
The Commission will continue to transmission service. According to However, EPSA argues, there must be
actively monitor compliance with its Williams, simply being told that service meaningful clarity and obligations set
orders and, as necessary, institute is being curtailed for reliability out in the rules and OATT
further proceedings to meet its statutory purposes under opaque local requirements—transparency simply for
obligation to remedy undue procedures, in the absence of a NERC the sake of knowing why transmission
discrimination. Transmission Loading Relief (TLR) service has been denied only
43. The Commission will not catalog event, leaves market participants illuminates a ‘‘bridge to nowhere’’ and
each and every basis for its reform of the suffering the consequences without fails to satisfy the Federal Power Act.
pro forma OATT in this section. Rather, knowing on what basis the decision was 49. Entergy also supports the
we identify the bases for some of the reached, and without assurance that the Commission’s efforts to provide greater
most fundamental reforms herein and, decision was made in a non- clarity in the rights and obligations of
in addition, we explain in each discriminatory manner. Ultimately, transmission providers and
individual section of the Final Rule the Williams adds, the lack of transparency transmission customers under the
inadequacies of the existing pro forma and latitude taken by the transmission OATT. According to Entergy, many of
OATT provisions being addressed there provider to determine which requests the improvements proposed by the
and the reasons why our reforms are for service are confirmed or denied and Commission will reduce the likelihood
necessary to remedy undue which are curtailed or interrupted in of disputes and promote greater
discrimination or otherwise provide for real time frustrates the Commission’s confidence on the part of customers that
rates, terms and conditions of service goal of preventing undue discrimination
they are being treated fairly. Entergy
under the pro forma OATT that are just and preference in the provision of
states that, while it recognizes that the
and reasonable. transmission service. Furthermore,
lack of clarity makes it difficult for the
Williams states, the same lack of
B. Lack of Transparency Undermines Commission to detect instances of non-
transparency exists around the opaque
Confidence in Open Access and compliance by transmission providers,
processes utilized, assumptions made,
Impedes Enforcement of Open Access Entergy also believes that this lack of
and basis on which the results of
Requirements clarity often makes it easier for
transmission planning studies are
44. Following the issuance of the NOI, transmission customers to convert every
conducted to grant or deny requests for
the Commission received a number of practice or policy into a claim of
service.
comments asserting that increased 47. APPA agrees that additional discrimination or other misconduct.
transparency would aid transmission transparency in the administration of 50. Although not convinced that there
customers in their participation in the public utility transmission providers’ is a compelling need for increased
wholesale market. A common theme in OATTs will be of material assistance to transparency since transmission
the comments was that a lack of both the Commission and transmission providers are already required to
transparency could lead to claims of customers. However, APPA argues that disclose voluminous amounts of
discrimination and could make such the Commission must go beyond information, Southern states that it
claims more difficult to resolve. increasing transparency in the recognizes that some reforms in the
Commenters urged the Commission to administration of public utility availability of information may be
improve transparency in a number of transmission providers’ OATTs. advantageous. However, Southern
areas, particularly the evaluation of ATC According to APPA, more transparency asserts, providing additional
and the planning of the transmission will not change the basic industry transparency must not simply impose
system, as well as the processing of paradigm with transmission customers additional reporting requirements; any
sroberts on PROD1PC70 with RULES

transmission service requests and depending on monopoly transmission such transparency-related reforms
studies. providers for service. In APPA’s view, should be made after taking into
45. In the NOPR, the Commission customers are often reluctant to file consideration the extent and type of
agreed that a lack of transparency both complaints or bring problems to the data and information that is already
increases the potential for undue Commission’s attention because they provided.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00010 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12275

Commission Determination unlikely to occur, except by the a legal duty to expand its transmission
51. The Commission concludes that transmission provider or its affiliate on system accordingly. Southern notes that
inadequate transparency requirements, a ‘‘sole source’’ or ‘‘no bid’’ basis it alone has invested $3.2 billion in
combined with inadequate compliance (despite Federal and State policies to transmission over the past decade and
with existing OASIS regulations, the contrary), if unaffiliated suppliers plans to invest another $2.8 billion over
cannot effectively and efficiently obtain the next five years (2006–2010).
increases the opportunities for undue
transmission service. EPSA argues that 56. Community Power Alliance also
discrimination under the pro forma
failure to boldly reform the argues that the Commission’s own June
OATT and makes instances of undue 2005 ‘‘State of the Markets Report’’
Commission’s open access transmission
discrimination more difficult to detect. contradicts the Commission’s assertion
rules at this critical juncture would
We find that the reforms we adopt in that vertically-integrated utilities do not
effectively hand an undeserved victory
this Final Rule will improve have the proper incentives to expand
to the very transmission providers who,
transparency in the OATT, reduce the grid. Community Power Alliance
by the Commission’s own findings, have
opportunities for undue discrimination, contends that this report shows that the
the motive and the opportunity to
and increase our ability to detect undue amount of transmission investments
discriminate. International
discrimination. Transmission argues that tariff reform is made in the non-RTO regions, where
C. Congestion and Inadequate no substitute for prudent investment in vertically-integrated utilities typically
Infrastructure Development Impede the transmission infrastructure needed operate, substantially exceeds the
Customers’ Use of the Grid to increase the underlying physical amount of transmission investments
capability of the transmission system. made in RTO regions.
52. The Commission noted in the 54. On the other hand, some
NOPR that the ability and incentive to Commission Determination
commenters dispute the Commission’s
discriminate increases as the assertion in the NOPR that vertically- 57. The Commission concludes that
transmission system becomes more integrated utilities operating in non- reforms are needed to ensure that
congested. The Commission observed RTO regions have an incentive to transmission infrastructure is evaluated,
that the pro forma OATT contained only discriminate and, therefore, are not and if needed, constructed on a
minimal requirements regarding adequately expanding the transmission nondiscriminatory basis and is
transmission planning, which have grid to accommodate new entry by more otherwise sufficient to support reliable
proven to be inadequate as the Nation efficient competitors. New Mexico and economic service to all eligible
faces insufficient transmission Attorney General argues that vertically- customers. As noted above, vertically-
investment in many areas. The integrated utilities operating under the integrated utilities do not have an
Commission preliminarily concluded traditional rate-base, rate-of-return incentive to expand the grid to
that the inadequacy of the existing model of regulation in fact have been accommodate new entries or to facilitate
obligation to conduct transmission historically criticized for having the dispatch of more efficient
system planning, coupled with the lack incentives to overbuild. New Mexico competitors. Despite this, the existing
of transparency surrounding system Attorney General asserts that most pro forma OATT contains very few
planning generally, required reform of transmission projects are in reality requirements regarding how
the pro forma OATT to ensure that derailed by strong ‘‘NIMBY’’ opposition transmission planning should be
transmission infrastructure is to the actual siting of transmission lines. conducted to ensure that undue
constructed on a nondiscriminatory Another countervailing factor to the discrimination does not occur.
basis and is otherwise sufficient to utility’s incentive to overbuild, in New 58. Our concern over this flaw is
support reliable and economic service to Mexico Attorney General’s view, is the heightened by the critical need for new
all eligible customers. The Commission fact that State regulators attempt to limit transmission infrastructure in this
therefore proposed to require public capacity investment to reasonable levels Nation. As the Commission explained in
utilities to engage in an open and only necessary to serve native load. the NOPR, transmission capacity is
transparent planning process at both the 55. Southern states that the being constructed at a much slower rate
local and regional levels. Commission’s assertion in the NOPR than the rate of increase in customer
that vertically-integrated utilities do not demand, with transmission capacity per
Comments MW of peak demand declining at an
have an incentive to expand the grid
53. APPA agrees that the lack of overlooks the fact that many such average rate of 2.1 percent per year
adequate transmission infrastructure is utilities are under State legal duties to during the period 1992 to 2002.55 The
one of the core problems facing the procure generation supplies through projections suggest that this trend will
electric utility industry. APPA supports open, non-discriminatory requests for continue through 2012.56 As a result,
revisions to the pro forma OATT to proposals, with the winners of those there has been a significant decrease in
enhance and improve transmission requests for proposals often being transmission capacity relative to load in
planning on both an individual system competitors of the vertically-integrated every NERC region.57 In light of this
and regional basis. Several commenters utility. Southern maintains that the trend, there is a compelling need to
go further, arguing that the proposed winning competitive generation is then build new transmission and respond to
reforms are insufficient and urging the integrated into the host utility’s increasing demand through other
Commission to more strongly encourage transmission system and dispatch, and
infrastructure development. EPSA the transmission system is expanded to 55 Eric Hirst, U.S. Transmission Capacity: Present

Status and Future Prospects (Aug. 2004), http://


asserts that successful implementation ensure the deliverability of this www.eei.org/industry_issues/energy_infrastructure/
of the Congressional policy in favor of competitive generation. Furthermore, transmission/USTransCapacity10–18–04.pdf
wholesale competition and State Southern states, a competitive generator (Present Status and Future Prospects).
sroberts on PROD1PC70 with RULES

policies in favor of competitive can also have the output of its generator 56 Present Status and Future Prospects at v.
57 Brendan Kirby (Oak Ridge National Laboratory,
procurement is frustrated by the lack of planned into the transmission
U.S. Department of Energy), Barriers to
sufficient open access to the provider’s system if it takes long-term Transmission Investment, Technical Conference
transmission grid. According to EPSA, firm service under the OATT, with the Presentation, (Docket No. AD05–5–000) (April 22,
new power plant investment is highly transmission provider then being under 2005).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00011 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12276 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

means. EEI estimates that capital the overall savings of wholesale did not standardize the methodology for
spending must increase by 25 percent, electricity markets that lowered calculating ATC, nor did it impose any
from $4 billion annually to $5 billion consumers’ electricity bills by nearly specific requirements regarding the
annually, to ensure system reliability $13 billion annually, interregional disclosure of the methodologies used by
and to accommodate wholesale electric transmission congestion cost consumers each transmission provider.63 As a
markets.58 The legacy systems hundreds of millions of dollars result, there are a variety of ATC
constructed by vertically-integrated annually. DOE concluded that relieving calculation methodologies in use today
utilities prior to the adoption of Order bottlenecks in these four regions alone and very few clear rules governing their
No. 888 support ‘‘only limited amounts could save consumers about $500 use. Moreover, there is often very little
of inter-regional power flows and million annually.61 In 2006, DOE transparency about the nature of these
transactions. Thus, existing systems released another study identifying two calculations, given that many
cannot fully support all of society’s areas of the country with severe existing transmission providers have filed only
goals for a modern electric-power or growing congestion problems: the summary explanations of their ATC
system.’’ 59 Atlantic coastal area from metropolitan methodologies in Attachment C to their
59. Expansion of the transmission New York southward through Northern OATTs.
system, as well as more efficient use of Virginia, and Southern California.62 63. In the NOPR, the Commission
the grid, will alleviate the growth of 61. The decline in transmission noted that, although the industry has
congestion in most regions of the investment and increase in transmission sought to pursue greater consistency in
country. Transmission congestion has congestion underscore our concerns ATC calculations through existing
created fairly small local load pockets in over inadequate planning provisions of NERC processes, these efforts to date
primarily urban areas, e.g., New York the existing pro forma OATT. The have been largely unsuccessful. The
City, Long Island, Boston, parts of existing pro forma OATT, as indicated Commission expressed its preliminary
Connecticut, and the San Francisco Bay above, contains very little specificity determination that the lack of a
Area. Other load pocket concerns have regarding how transmission planning consistent, industry-wide methodology
arisen in parts of northern Virginia, and should be conducted, how customers’ for calculating ATC gives transmission
various load centers in SPP. Still other needs are incorporated into that process, providers the ability and the
constraints are more regional in scope: and what information is publicly opportunity to unduly discriminate
from the Midwest to the Mid-Atlantic, available regarding the transmission against third parties. The Commission
from the Midwest to TVA, into and providers’ assumptions, criteria and therefore proposed a number of reforms
within California, from TVA and data used in the planning process. to the process of calculating ATC to
Southern into Entergy, from Mid- These inadequacies are sufficiently provide clarity and transparency to
America Interconnected Network into severe, standing alone, to merit reform users of the grid.
Wisconsin-Upper Michigan Systems, of the OATT. However, they are of even Comments
and into Florida. greater concern given the current state
60. Transmission congestion can have of the transmission grid. With 64. As discussed further in section
significant cost impacts on consumers. inadequate levels of investment in the V.A below, most commenters support
In 2002, DOE issued a study estimating grid and increasing transmission the Commission’s goal of requiring
the costs of congestion in four U.S. greater consistency in the manner in
congestion, customers’ ability to access
regions: California, PJM, New York and which ATC is calculated and additional
alternatives to the transmission
New England.60 DOE found that, despite transparency of ATC calculations.
provider’s resources is limited. It is
Commenters generally favor the
therefore imperative for the Commission
58 Energy Policy Act of 2005: Hearings before the Commission’s proposal to increase
to ensure that the planning process
Subcommittee on Energy and Air Quality of the consistency in the calculation of ATC,
under each transmission provider’s
House Committee on Energy and Commerce, 109th including consistent definitions of its
Congress, First Sess. (2005) (Prepared statement of OATT is sufficient to prevent undue
components, data inputs, modeling
Thomas R. Kuhn, President of EEI). discrimination and transparent enough
59 Present Status and Future Prospects at v. assumptions, and data exchange and
to detect any remaining instances of
60 U.S. Department of Energy, National coordination protocols. For example,
undue discrimination. We have done so
Transmission Grid Study at 11, 16–17 (May 2002), Exelon argues that each ATC component
in the reforms adopted and explained in
available at http://www.ferc.gov/industries/electric/ should be used in the same manner for
indus-act/transmission-grid.pdf. To conduct this section V.B.
all purposes (e.g., granting transmission
study, DOE estimated the benefits of interregional
wholesale power markets using the Policy Office D. A Consistent Method of Measuring service to third parties or for the
Electricity Modeling System (POEMS). POEMS is a ATC Is Needed transmission provider’s own network
national energy model designed specifically to
62. Another area in which load). Some commenters assert that
examine the impacts of electricity restructuring. industry-wide standardization of ATC
The model includes economic, regional, and transmission providers have significant
temporal detail that is needed to analyze the discretion under the pro forma OATT is calculation might not be possible and
economics of interregional trade. In the first step of the calculation of ATC. While Order No. that the Commission should consider
the study, DOE used POEMS to examine the cost
888 obligated each public utility to interconnection-wide, regional or even
reductions that would occur if increased electricity sub-regional standardization. Others
transfers across congested paths were allowed in calculate the amount of transfer
these four regions, assuming generators bid their capability on its system available for suggest allowing flexibility in order to
marginal costs. Under this assumption, consumer sale to third parties, the Commission capture differences in system operation,
costs declined by $157 million per year. In the usage, market operations and topology.
second step, DOE calculated the increase in 65. At the technical conference
congestion costs under the assumption that bid their marginal operating cost) during these
generators bid above their marginal operating costs periods, congestion costs nearly double to $300 organized in this proceeding on October
when supplies are tight and additional electricity million. 12, 2006 (October 12 Technical
sroberts on PROD1PC70 with RULES

61 Id. at xi and ii.


cannot be imported. The price spikes were assumed Conference), the entire panel agreed that
to occur during hours when at least one 62 U.S. Department of Energy, National Electric
definitions must be consistent and a
transmission link into a sub-region was congested Transmission Congestion Study, Executive
and demand was greater than 90 percent of peak Summary at 2 (August 2006), available at http:// panelist representing Constellation
demand. When prices spike an additional $50 per www.ferc.gov/industries/electric/indus-act/doe-
MWh (above the price predicted when generators congestion-study-2006.pdf. 63 Order No. 888 at 31,794 n.610.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00012 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12277

asserted that broad differences in the transmission capacity is congested, this related to the actual costs incurred by
core definitions of the ATC calculation lack of consistency, coupled with a lack transmission providers. They also argue
are neither rational nor explainable.64 of transparency, is of heightened that the inconsistency between these
NERC, however, recognized that the importance and has led to recurring charges in different control areas is
goal of achieving consistency may not disputes over whether the transmission unnecessary, and that other means of
mean that a single ATC methodology is provider is exercising its discretion to compensating the transmission
required.65 NERC explained that discriminate against its competitors. provider, such as return-in-kind, should
consistency can be achieved with a This discretion also hampers the be considered. Generators likewise
limited number of methodologies if the detection of undue discrimination and, complain that generator imbalance
requirements of those methodologies are thereby, undermines the Commission’s charges are excessive, that transmission
properly coordinated and ability to enforce the general providers refuse to credit generators
communicated. requirement in Order No. 888 that with the revenues resulting from
66. Numerous commenters support transmission service be provided on a imbalance penalties that are collected,
the Commission’s proposals to increase not unduly discriminatory basis. and that transmission providers prevent
transparency in the manner in which 69. As discussed more fully below in unaffiliated generators from purchasing
transmission providers derive ATC, section V.AIII.D, this Final Rule adopts or self-supplying generator imbalance
including greater OASIS posting. a number of reforms that address the services. In addition, owners of
Commenters opposing the transparency- potential for remaining undue intermittent resources complain that
related reforms focus on the discrimination in the determination of generator imbalance charges, which are
Commission’s proposal to require the ATC by requiring consistency in how imposed to provide an incentive for
posting of narratives on OASIS ATC is evaluated, as well as providing generators to schedule accurately, are
explaining reasons for changes in greater transparency about how a inappropriate given their lack of control
monthly and yearly ATC values on transmission provider calculates and and ability to cure deviations.
constrained paths. They argue that such allocates ATC.
a requirement would be too burdensome Commission Determination
E. Discriminatory Pricing of Imbalances 72. The Commission agrees that
and would not provide customers with
any significant new information. 70. Order No. 888 focused primarily imbalance charges should provide
67. Several commenters believe that on the adoption of non-rate terms and appropriate incentives to keep
making substantial ATC calculation and conditions of service, rather than schedules accurate without being
modeling data transparent will instituting broad reform of the excessive. We also find that consistency
compromise Critical Energy Commission’s transmission pricing in imbalance charges, both between and
Infrastructure Information (CEII) but policies. Consistent with this focus, the among energy and generator imbalances,
provide suggestions for resolving the Commission did not propose broad is preferable to the wide variety of
issue. Others express concern that the transmission pricing reform in the imbalance provisions in place today. All
data required for posting on OASIS is NOPR, but rather focused on instances imbalances have the same net effect on
not CEII but commercially sensitive. where current pricing practices under the transmission system in that they
Finally, commenters provide the pro forma OATT may no longer be require other generation to be ramped
suggestions regarding the requirement to sufficient to remedy undue up or down to compensate for the
post metrics on OASIS related to the discrimination or ensure just and imbalance. As such, the Commission
provision of transmission service under reasonable rates. One significant reform adopts two pro forma OATT provisions
the pro forma OATT, including various proposed in the NOPR related to charges (Schedule 4 for energy imbalances and
additional metrics the Commission for imbalance energy. The Commission Schedule 9 for generator imbalances)
should consider. Others state that this preliminarily found that the existing based on a tiered structure similar to the
information is already available on policies provide wide discretion in the imbalance provision used by
OASIS. development of these charges and hence Bonneville, as described further below.
the potential for undue discrimination. Such an approach recognizes the link
Commission Determination The Commission therefore proposed between escalating deviations and
68. We find that the lack of a certain principles to remedy that potential reliability impacts on the
consistent and transparent methodology potential and sought comment on system while keeping imbalance charges
for calculating ATC gives transmission whether a specific imbalance pricing closely related to incremental costs. The
providers the ability and opportunity to method would be appropriate. Commission finds, however, that
unduly discriminate in the provision of intermittent resources should be exempt
open access transmission service. There Comments
from the highest-tier deviation band. We
are few clear rules respecting ATC 71. In general, transmission customers also require transmission providers to
calculation, and transmission providers complain about the level and scope of credit to all non-offending transmission
retain unnecessarily broad discretion in energy and generator imbalance charges customers the revenues they collect in
this area. This resulting discretion is a that are levied under the pro forma excess of incremental costs.
significant problem because calculation OATT and under individual
of ATC, which varies greatly depending interconnection agreements.66 F. Redispatch/Conditional Firm
on the criteria and assumptions used, Customers complain that energy 73. In the NOPR, the Commission
may allow the transmission provider to imbalance charges are excessive and not examined whether existing methods for
discriminate in subtle ways against its evaluating requests for long-term firm
66 Energy imbalance charges, including penalties
competitors. On systems where point-to-point service continue to be
on some systems, are imposed on a transmission
customer when the amount of energy scheduled for just and reasonable. When a
sroberts on PROD1PC70 with RULES

64 Transcript of October 12 Technical Conference


delivery to the transmission grid does not equal the transmission provider considers a new
at 149–50, available at Preventing Undue amount of energy withdrawn by that customer. resource to serve native load, the
Discrimination and Preference in Transmission Generator imbalance charges are levied on
Service, Technical Conference (Docket No. RM05– generators for deviations between the amount of
transmission provider does not
25–000). energy they schedule and the amount they actually eliminate an otherwise economic option
65 Id. at 125–50. deliver to the grid. because the resource may not be

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00013 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12278 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

deliverable during a few hours of the network service and provide G. EPAct 2005 Emphasized Certain
year. For transmission customers, disincentives for transmission Policies and Priorities for the
however, the transmission provider investment. Several commenters state Commission
evaluates whether service can be that these services would make 79. Finally, we note that the reforms
granted in every hour of the year that is curtailments of existing firm service adopted in this proceeding are
modeled and, if not, it informs the more likely and limit opportunities for consistent with the policies and
customer that service cannot be use of secondary network service, priorities embodied in EPAct 2005, in
provided out of existing transfer thereby harming native load protections which Congress emphasized many of
capability. Only if the transmission and reducing reliability, contrary to FPA the same principles reflected in this
customer agrees to pay for facilities sections 215 and 217 respectively. Final Rule. First, in EPAct 2005,
studies does the transmission provider While it recognizes that conditional firm Congress placed special emphasis on
evaluate redispatch options, including service has been successful in parts of the development of transmission
whether they are less expensive than the infrastructure. Congress required the
the Western Interconnection, NRECA
upgrade costs. The Commission Commission to adopt a rule establishing
contends that a mandate would
therefore proposed to reform the incentive-based rates for new
existing pro forma OATT planning undermine responsible planning and
expansion of the transmission grid by transmission infrastructure investment.
redispatch 67 obligation, or, in the The stated purpose of new FPA section
alternative, to add a conditional firm harnessing the transmission provider’s
planning and dispatch functions to 219 is to benefit ‘‘consumers by
service to the pro forma OATT. As ensuring reliability and reducing the
proposed by the Commission, frame elaborate service conditions for
conditional firm service. cost of delivered power by reducing
conditional firm would have been a transmission congestion.’’ 68 Among
long-term service allowing the 77. Several commenters argue that, if other steps, FPA section 219 requires
transmission provider to give a lower the services are required, the the Commission to ‘‘(1) Promote reliable
curtailment priority than firm to the Commission should ensure that and economically efficient transmission
transmission customer during a pre- reliability is not adversely affected. and generation of electricity by
specified number of hours. Others urge the Commission to make the promoting capital investment in the
Comments new services an interim option until enlargement, improvement,
transmission upgrades are in place to maintenance, and operation of all
74. Some commenters support the
provide firm service. Some commenters facilities for the transmission of electric
inclusion of both a modified planning
believe planning redispatch and energy in interstate commerce,
redispatch obligation and a conditional
conditional firm customers should bear regardless of the ownership of the
firm service in the pro forma OATT,
the actual costs of the services received, facilities; (2) provide a return on equity
stating that both are required to remedy
including costs associated with system that attracts new investment in
undue discrimination and provide for
operational changes needed to transmission facilities (including related
comparable transmission service. These
accommodate the services. A few transmission technologies); [and] (3)
commenters urge the Commission to
commenters believe that the encourage deployment of transmission
require transmission providers to offer
Commission should allow for regional technologies and other measures to
planning redispatch and conditional
differences in development of the new increase the capacity and efficiency of
firm service and allow customers to
services. existing transmission facilities and
choose the option that best suits their
improve the operation of the
physical, commercial and economic
Commission Determination facilities.’’ 69 In addition, Congress
circumstances.
75. Others opine that conditional firm directed the Commission to encourage
78. The Commission believes it is the deployment of advanced
service may be simpler and less costly necessary to modify the manner in
to implement. These commenters prefer transmission technologies.70 Congress
which transmission providers assess also gave the Commission certain
the development of conditional firm point-to-point service requests to
service over the modifications to the ‘‘backstop’’ transmission siting
eliminate the potential for undue authority, and authorized the creation of
planning redispatch service because of
discrimination in transmission service. interstate compacts establishing
the complexities surrounding redispatch
We find that both techniques—planning transmission siting agencies.71 Finally,
costs and protocols. For example,
redispatch and conditional firm the Commission was directed to
Entergy believes conditional firm
service—are currently used under exercise its authority under EPAct 2005
service can provide benefits to
certain circumstances by transmission ‘‘in a manner that facilitates the
transmission customers without unfairly
providers to serve native load and, planning and expansion of transmission
socializing costs to native load and
therefore, that transmission customers facilities to meet the reasonable needs of
network customers of the transmission
should have comparable services in load-serving entities to satisfy the
provider.
76. On the other hand, many order to avoid undue discrimination,
68 EPAct 2005 sec. 1241 (to be codified at section
commenters argue that the Commission facilitate the provision of long-term
219 of the FPA, 16 U.S.C. 824s). The Commission
should not require either option because transmission service and provide has issued a Final Rule implementing such an
the services are unnecessary, customers with greater flexibility in incentive rate program. See Order Nos. 679 and
operationally unworkable, and legally choosing resources to meet their needs. 679–A.
69 FPA Sec. 219(b)(1).
unjustified, or because they would harm We expect that both options will help
70 EPAct 2005 sec. 1223 (to be codified at 42
reliability and the quality of existing integrate new generation more quickly. U.S.C. 16442).
This can be particularly beneficial to 71 EPAct 2005 sec. 1221(a) (to be codified at
sroberts on PROD1PC70 with RULES

67 Although pro forma OATT section 13.5 refers renewable generation resources, such as section 216 of the FPA, 16 U.S.C. 824p). The
to ‘‘redispatch,’’ we refer to it here as ‘‘planning wind, that can be constructed more Commission implemented new regulations in
redispatch’’ to distinguish it from the reliability accordance with this section to establish filing
redispatch provisions in the network integration
quickly than the transmission upgrades requirements and procedures for entities seeking to
transmission service sections of the pro forma necessary to deliver their power on a construct electric transmission facilities in Order
OATT. See infra notes 552 and 557. firm basis over the long-run. No. 689.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00014 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12279

service obligations of the load-serving authority carries with it the and ISOs, we amend the pro forma
entities, and enables load-serving responsibility to ensure that OATT to require coordinated, open, and
entities to secure firm transmission enforcement is firm but fair and that our transparent transmission planning on
rights * * * on a long-term basis for rules are as clear as practicable to both a sub-regional and regional level.
long-term power supply arrangements facilitate compliance.75 We conclude To implement this remedy, we adopt
made, or planned, to meet such that this Final Rule is fully consistent the eight planning principles proposed
needs.’’ 72 Although these provisions with these principles because it clarifies in the NOPR, as well as one additional
have been, or will be, addressed our rules, in many areas, which will principle, that each public utility
primarily in other proceedings, we facilitate compliance by transmission transmission provider will be required
conclude that the Final Rule is providers. to follow. We recognize that many
consistent with these provisions regions have made significant progress
IV. Summary, Scope and Applicability
because it supports improvements in in recent years in creating greater
of the Final Rule
infrastructure by reforming the openness and transparency in
transmission planning process to ensure 82. This section provides a summary transmission planning and believe our
that it is open, transparent and of the major components of the Final proposed reforms will build upon,
nondiscriminatory. Rule, a description of the core elements strengthen, and improve this progress to
80. Second, Congress emphasized the of Order No. 888 that we retain, and a reform transmission planning.
need for greater transparency in discussion of the applicability of the 85. Transmission Pricing Reforms.
electricity markets, including proposed rule to various entities. Consistent with the focus of Order No.
transmission service. EPAct 2005 added A. Summary of Reforms 888 on the non-rate terms and
section 220 to the FPA, which requires conditions of open access, the
the Commission to facilitate ‘‘price 83. Consistency and transparency of Commission does not initiate broad
transparency in markets for the sale and ATC calculations. The Commission reform of transmission pricing policy
transmission of electric energy in affirms the finding in the NOPR that the through this Final Rule. However, we
interstate commerce, having due regard lack of a consistent, industry-wide have identified several pricing rules that
for the public interest, the integrity of methodology for calculating ATC, and are part and parcel of OATT service that
[that market], fair competition, and the the lack of adequate transparency in merit reform.
protection of consumers.’’ 73 The ATC calculations, increases the • Energy and Generator Imbalance
Commission was authorized to potential for undue discrimination and Charges. We find that energy and
‘‘prescribe such rules as the also makes undue discrimination more generator imbalance charges we have
Commission determines necessary and difficult to detect. The lack of consistent previously accepted are excessive, too
appropriate to carry out the purposes standards can facilitate undue varied, and otherwise unrelated to the
of’’ FPA section 220. Those rules ‘‘shall discrimination by giving a transmission cost of providing the service and,
provide for the dissemination, on a provider the discretion, and hence the therefore, we reform energy and
timely basis, of information about the ability and opportunity, to favor itself generator imbalance pricing. We adopt
availability and prices of wholesale and its affiliates over third parties in tiered pro forma OATT energy and
electric energy and transmission service how it calculates and allocates ATC. In generator imbalance provisions similar
to the Commission, State commissions, this Final Rule, we give the industry to those in use by Bonneville and
buyers and sellers of wholesale electric specific guidance regarding the exempt intermittent resources from the
energy, users of transmission services, calculation of ATC and establish a firm highest deviation band. In these new
and the public.’’ This Final Rule deadline to develop certain provisions, imbalance charges are based
similarly will promote greater requirements to make more consistent on incremental cost and escalate as the
transparency in the provision of the ATC calculation process and the imbalance increases. Any deviations
transmission service in many important process of exchanging data between from these provisions must be
areas, including ATC calculation and transmission providers about ATC. In consistent with or superior to the pro
transmission planning. addition, we amend pro forma OATT forma OATT as modified by this Final
81. Finally, Congress emphasized requirements as well as our OASIS Rule and must meet the following
compliance with the Commission’s regulations to increase the transparency criteria: the charges must (1) Be related
regulations, increasing the civil and in how ATC is calculated. to the cost of correcting the imbalance,
criminal penalties for violations of 84. Requirement for coordinated, (2) be tailored to encourage accurate
Commission-administered statutes and open and transparent transmission scheduling behavior, such as by
regulations.74 This new authority planning. The Commission also affirms increasing the percentage of the adder as
buttresses the Commission’s efforts to the finding in the NOPR that Order No. the deviations become larger, and (3)
enforce public utility OATTs and the 888 does not contain sufficient account for the special circumstances
regulations requiring transmission protections to guard against undue presented by intermittent generators,
information to be posted on OASIS. As discrimination in transmission system such as by waiving the higher ends of
we explained in the Policy Statement on planning. Without adequate the deviation penalties.
Enforcement, however, this new coordination and open participation, • Capacity Reassignment Pricing. We
market participants have minimal input find that the existing cap on the
72 EPAct 2005 sec. 1233(a) (to be codified at or insight into whether a particular reassignment of point-to-point service is
section 217(b)(4) of the FPA, 16 U.S.C. 824q). The transmission plan treats all loads and no longer just and reasonable and,
Commission implemented FPA section 217(b)(4) in generators comparably. To ensure that
Long-Term Firm Transmission Rights in Organized
therefore, we eliminate the cap. We
Electricity Markets, Order No. 681, 71 FR 43564
truly comparable transmission service is believe that removing the cap will
(Aug. 1, 2006), FERC Stats. & Regs. ¶ 31,226 (2006), provided by all public utility eliminate an unnecessary impediment
sroberts on PROD1PC70 with RULES

order on reh’g, Order No. 681–A, 117 FERC ¶ 61,201 transmission providers, including RTOs to the resale of capacity, which in turn
(2006), reh’g pending.
73 EPAct 2005 sec. 1281 (to be codified at 16
should increase utilization of the grid
75 Enforcement of Statutes, Orders, Rules and
U.S.C. 824t). Regulations, Policy Statement on Enforcement, 113
and otherwise ensure that point-to-point
74 EPAct 2005 sec. 1284(e)(1) (to be codified at FERC ¶ 61,068 (2005) (Policy Statement on service is just, reasonable, and not
section 316(A) of the FPA, 16 U.S.C. 825o–1). Enforcement). unduly discriminatory.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00015 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12280 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

• Crediting of Customer-Owned timelines and modifies the minimum metrics related to their completion of
Facilities. We retain most elements of term of the rollover rights to five years, studies required under the pro forma
our existing policy respecting the rather than the current minimum term OATT. We note that the Commission
crediting of customer-owned facilities, of one year. The Commission also will continue to audit compliance with
including the requirement that such requires that a transmission customer the pro forma OATT, and toward that
facilities meet the integration standard. eligible for rollover rights provide notice end require transmission information
However, we eliminate the requirement of whether or not it will exercise its kept on OASIS to be retained for audit
that new facilities can receive credits right of first refusal to renew the purposes for five years. Finally, we
only if they are ‘‘jointly planned’’ contract no less than one year before the adopt a number of reforms to
because this requirement provides a expiration date of the transmission operational penalties assessed under the
disincentive to coordinated planning. service agreement, rather than within pro forma OATT, including so-called
Rather, we provide that such new the current 60-day period. ‘‘over-use’’ penalties and the treatment
facilities are eligible for credits if such 88. Increases in transparency to of operational penalty revenues
facilities are integrated into the lessen the opportunities to discriminate collected from transmission providers
operations of the transmission and reduce transaction costs. In and their affiliates.
provider’s facilities. Customer-owned addition to the increased transparency 90. Miscellaneous OATT
facilities shall be presumed to be we require regarding the calculation of improvements. Finally, we implement a
integrated if those facilities, if owned by ATC and transmission planning, we number of improvements to the terms
the transmission provider, would be increase the transparency of and conditions of the pro forma OATT
eligible for inclusion in the transmission transmission service provided under the to incorporate the lessons learned over
provider’s annual transmission revenue pro forma OATT in several other the past ten years. We briefly note these
requirement. respects. For example, we require below:
86. Improvements to Point-to-Point transmission providers and their • Designation of network resources.
Service. The Commission concludes that network customers to use the We provide clarification regarding the
the existing methods for evaluating transmission providers’ OASIS to types of agreements that may be
requests for long-term firm point-to- request designation of a new network designated as network resources, the
point service are no longer just, resource and to terminate the process for verifying whether
reasonable, and not unduly designation of an existing network agreements meet the requirements in the
discriminatory. The existing pro forma resource. In addition, we require pro forma OATT, and the requirement
OATT allows the transmission provider transmission providers to modify their for transmission providers to designate
to deny a request for long-term point-to- OASIS so that requests to designate and and undesignate network resources. We
point service if that service is not terminate a network resource can be also require customers to submit an
available in a single hour of the period queried, allowing all parties access to attestation with each application to
studied. We find that this approach is such information. We also require designate a new network resource.
not comparable because, when a transmission providers to post a list of • Reservation priorities. We change
transmission provider considers a new their current designated network the priority rules to give certain priority
resource to serve native load, the resources and all network customers’ to pre-confirmed transmission service
transmission provider does not current designated network resources on requests submitted in the same time
eliminate an otherwise economic option their OASIS. Finally, we require period. We also add price as a tie-
because the resource may not be transmission providers to post on breaker in determining reservation
deliverable in a few hours of the year. OASIS all their business rules, practices queue priority when the transmission
To remedy this problem, the and standards that relate to transmission provider is willing to discount
Commission adopts a ‘‘conditional services provided under the pro forma transmission service.
firm’’ component to long-term point-to- OATT. • Clarifications related to network
point service that addresses the 89. Strengthening enforcement of the service. We provide clarification related
situation where firm service can be pro forma OATT. The reforms adopted to use of network service on an ‘‘as
provided for most, but not all, hours of in this Final Rule provide greater clarity available basis’’ and to ‘‘redirects’’ of
the period requested. We also reform the in the terms and conditions of the pro network service.
existing requirements for the provision forma OATT, resolving ambiguities in
B. Core Elements of Order No. 888 That
of redispatch service to ensure that they the existing pro forma OATT that have
Are Retained
are of greater use to transmission made undue discrimination easier to
customers and more consistent with accomplish and more difficult to detect. 91. Although we are adopting many
reliability planning and operation of the Our new civil penalty authority under important reforms to Order No. 888 and
system. EPAct 2005 gives us ample power to the pro forma OATT in this Final Rule,
87. Reform of rollover rights. The remedy tariff violations, but it also we emphasize that many of the core
Commission concludes that section 2.2 places upon us an increased elements of Order No. 888 are retained.
of the pro forma OATT, which grants an responsibility to make the rules as clear As the Commission noted in the NOPR,
ongoing right to transmission customers as possible. We fulfill that responsibility many of these core elements enjoy broad
to renew or ‘‘roll over’’ their contracts, in the Final Rule by providing greater support from many sectors of the
should be reformed. The current clarity where appropriate to several industry. A variety of commenters—in
rollover rights do not provide critical OATT provisions. We also adopt response to the NOI issued earlier in
consistency between the rights of a number of posting and reporting this proceeding and again in response to
rollover customers and the resulting requirements that will provide the the NOPR—have urged the Commission
obligations of transmission providers to Commission and market participants to focus on meaningful incremental
sroberts on PROD1PC70 with RULES

plan and upgrade the system to with information about each reforms to the pro forma OATT, rather
accommodate rollovers. The transmission provider’s performance of than on industry restructuring. We share
Commission therefore amends section pro forma OATT obligations. For the view that Order No. 888 can be
2.2 to ensure greater consistency with example, we require transmission strengthened without discarding its
transmission planning and construction providers to post specific performance fundamental structure. We discuss

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00016 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12281

below the core elements that are being Order No. 888. NARUC urges the contract or service agreement for firm
retained and the comments received on Commission to clarify that its planning transmission service or rights in effect
these points. proposals will not reopen or attempt to as of the date of enactment of EPAct
change the jurisdictional split over 2005.87 In the NOPR, the Commission
1. Federal/State Jurisdiction
transmission facilities delineated in concluded that the protection of native
92. In Order No. 888, the Commission Order No. 888. load embodied in Order No. 888 is
stated that it has exclusive jurisdiction consistent with FPA section 217, and
over the rates, terms, and conditions of Commission Determination reaffirmed its commitment to the
unbundled retail transmission in 94. The Commission will retain the protection of native load.
interstate commerce.76 Though the existing jurisdictional divide that was
Commission adopted a test for Comments
established in Order No. 888, which has
determining what constitute been affirmed by the U.S. Supreme 97. Several commenters agree with
Commission-jurisdictional transmission Court and accepted by the industry and the Commission’s preliminary
facilities and what constitute State- State regulatory authorities.82 We also conclusion that the protection of native
jurisdictional local distribution facilities reiterate our recognition of the need for load embodied in Order No. 888 is
in situations involving unbundled heightened cooperation between Federal consistent with FPA section 217 and
wholesale wheeling and unbundled and State regulators in areas where there support the Commission’s continued
retail wheeling,77 the Commission are overlapping Federal and State policy commitment to the protection of native
stated that it generally would defer to concerns. As explained in greater detail load.88 While APPA 89 and TAPS
determinations by State regulatory in the planning section below, and in generally agree with the Commission
authorities concerning where to draw response to NARUC’s concern, the that the overall OATT regime is
the jurisdictional line under that test.78 planning reforms adopted in the Final consistent with section 217, they urge
The Commission declined to assert Rule contemplate coordinated and open the Commission to maintain and
jurisdiction over bundled retail transmission planning, but do not reinforce the comparability requirement.
transmission, reasoning that ‘‘when reopen or otherwise change the existing APPA urges the Commission to broaden
transmission is sold at retail as part and jurisdictional divide for transmission its preliminary conclusion in the NOPR
parcel of the delivered product called facilities. and conclude instead that the protection
electric energy, the transaction is a sale of native load and the provision of fully
of electric energy at retail.’’ 79 The U.S. 2. Native Load Protection comparable transmission service to
Supreme Court affirmed the 95. In Order No. 888, the Commission other LSEs with long-term service
Commission’s decision to assert did not require transmission providers obligations, as embodied in Order No.
jurisdiction over unbundled but not to unbundle transmission service to 888, are consistent with FPA section
bundled retail transmission, finding that their retail native load. The Commission 217. TAPS also supports the
the Commission made a statutorily also did not require that bundled retail Commission’s reading of FPA section
permissible choice.80 In the NOPR, the service be taken under the terms of the 217 as consistent with the Order No.
Commission proposed to retain the pro forma OATT.83 Moreover, the 888 pro forma OATT’s ‘‘native load’’
jurisdictional divide established in Commission allowed a transmission priority, recognizing that FPA section
Order No. 888. provider to reserve, in its calculation of 217 reinforces the OATT’s commitment
ATC, transmission capacity necessary to to comparable treatment of all LSEs—
Comments
accommodate native load growth e.g., transmission providers and
93. Several commenters support the reasonably forecasted in its planning network customers.
Commission’s proposal to retain the horizon.84 Order No. 888 also granted a 98. Other commenters dispute the
existing jurisdictional divide.81 Though Commission’s preliminary conclusion
rollover right to existing firm service
APPA concludes that the most politic that the native load protection
customers,85 but allowed transmission
course at this juncture is to leave the embodied in Order No. 888 is consistent
providers to restrict that rollover right if
current jurisdictional boundaries in with FPA section 217.90 Many
the capacity was reasonably forecasted
place and develop cooperative commenters argue that FPA section 217
as needed to serve native load
mechanisms in each region to protects all load, not just native load.91
customers, as long as that restriction
coordinate Federal policy Constellation states that the
was set forth in the customer’s initial
implementation with the relevant State Commission must recognize that there
service contract.86
regulators, APPA notes that there is are other market participants besides the
96. Congress, in section 1233 of EPAct
disagreement among its members about transmission providers themselves that
2005, added section 217 to the FPA,
whether the current jurisdictional lines are LSEs under FPA section 217. Under
entitled ‘‘Native Load Service
are properly drawn. APPA explains that the definition of LSEs in FPA section
Obligation,’’ which addresses
a substantial number of its members
transmission rights held by load-serving
believe that all interstate transmission 87 16 U.S.C. 217(f).
entities (LSEs). FPA section 217 allows
services (both retail and wholesale) 88 E.g., Ameren, E.ON, Tacoma, Arkansas
should be provided under one LSEs to use their own and contracted- Commission, EPSA, Southern, and TAPS.
consistent set of tariff terms and for transmission capacity to deliver 89 APPA argues that the proposed definition of

conditions. Other APPA members, energy as required to meet their service native load customers in section 1.21 is not
obligations, without being subject to technically consistent with FPA section 217
however, believe that the Commission because FPA section 217 does not distinguish
made the proper jurisdictional call in charges of unlawful discrimination. The among the types of power supply arrangements that
provision makes clear, however, that an LSE must have to enjoy the protection of FPA
76 Order this requirement does not abrogate any section 217. Nevertheless, APPA states that it
No. 888 at 31,781. would not be fruitful to reopen the entire OATT
sroberts on PROD1PC70 with RULES

77 Id. at 31,771 (setting forth the seven-factor test). framework to address this technical (but very
78 Id. at 31,781. 82 See New York v. FERC, 535 U.S. at 28. important) definitional difference.
79 Id. 83 Order No. 888 at 31,745. 90 E.g., Arkansas Municipal, Constellation, Duke,
80 See New York v. FERC, 535 U.S. at 28. 84 Id. at 31,694.
Salt River, and South Carolina E&G.
81 E.g., Ameren, APPA, North Carolina 85 Id.; see pro forma OATT section 2.2. 91 E.g., Constellation, EPSA, and South Carolina

Commission Reply, PNM–TNMP, and Southern. 86 Order No. 888–A at 30,198. E&G.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00017 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12282 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

217, EPSA argues that many entities an ongoing long-term firm contract, Commission to comply with the
other than traditional, vertically- while the transmission needs of mandate of Northern States Power Co. v.
integrated utilities are in the business of merchants are, by comparison, short- FERC,92 which South Carolina E&G
serving load. The statute, EPSA asserts, term and speculative. asserts held that the Commission had
applies to any native load service 102. Several commenters urge the exceeded its authority in rejecting a
obligation, whether that obligation is Commission to revisit various aspects of vertically-integrated transmission
served by a competitive supplier, an the reforms proposed in the NOPR in provider’s proposal to modify section
affiliate of the transmission provider, or order to enhance the protection of 13.6 of the OATT to give a higher
by the transmission provider itself. Salt native load. For example, some curtailment priority to native load.
River contends that FPA section 217 is commenters urge the Commission to According to South Carolina E&G, the
self-implementing, though it urges the modify the rollover proposal in the Commission has responded by applying
Commission to act to remove NOPR. Salt River argues that the the court’s decision narrowly, but FPA
impediments to the full exercise of Commission’s regulations must include section 217 requires the Commission to
rights granted to LSEs. a clear provision for a transmission change that position and recognize the
99. Constellation argues that the owner anticipating, or unexpectedly primacy of service to native load in
Commission should require native load facing, load growth to recapture section 13.6 of the OATT. In its reply
and OATT customers to take service capacity temporarily made available to comments, Progress Energy supports the
under the same terms and conditions the wholesale market. Arkansas comments of South Carolina E&G and
because experience has proven that Commission disagrees with the states that the Commission must
discrimination has occurred as a result Commission’s proposal to require a affirmatively recognize the priority of
of having two different sets of rules transmission provider to compete for service to LSEs in the application of the
applicable to transmission customers. transmission capacity rather than curtailment priorities in section 13.6 of
EPSA urges the Commission to further reclaim it through its rights to reserve the OATT.
clarify that the transmission provider capacity for future load growth. The 104. Duke argues that several of the
has an affirmative obligation to serve proposal is inequitable, Arkansas Commission’s proposed reforms—such
native load in a non-discriminatory Commission argues, because native load as hourly firm service, redispatch, and
manner. According to EPSA, section 217 customers have historically paid for conditional firm service—actually
supports the Commission’s paramount most of the transmission providers’ reduce the protection afforded native/
statutory mission of ensuring non- assets and will continue to do so in the network load. Salt River suggests that
discrimination and makes clear that a future. Because of this, Arkansas the Commission should modify its ATC
transmission provider, when utilizing Commission asserts, native load proposal to bring the Commission’s
transmission capacity or rights reserved customers should be given preference in native load priority policies in line with
to serve native load, must ‘‘put its the reservation of transmission capacity. FPA section 217. Salt River asserts that,
blinders on’’ to ensure that the load’s In response to Arkansas Commission’s in calculating ATC, the transmission
needs are being met in the most position, MDEA urges the Commission provider must be able to exercise
economical way available, whether that to make clear, consistent with the reasonable professional judgment as to
decision means the deployment of its comparability principle adopted in the amount of transmission that must be
own affiliated generation, or the Order No. 888 and reaffirmed in the reserved to meet native load service
deployment of available non-utility NOPR, and with FPA section 217, that obligations; the Commission should not
alternatives. any reservation of rights or preference get into the business of dictating
100. Arkansas Municipal asserts that available to a transmission provider’s forecasting methodology. Salt River
FPA section 217 recognizes the need to native load customers must be available proposes that a native load forecast that
give priority to LSEs in certain to network customer loads as well. is used by an LSE as the basis for
situations, such as when the South Carolina E&G argues that the committing capital for generation
transmission grid may be constrained Commission’s interpretation of expansion or procurement should be
and one group of customers may be ‘‘reasonably forecasted’’ capacity under presumed to be valid for purposes of
denied service at the expense of other section 2.2 of the pro forma OATT has establishing available capacity. EPSA,
customers. Arkansas Municipal states been effectively impossible to meet and, however, argues that, unless and until
that a priority list could be instituted in therefore, the Commission should now the Commission mandates a hard and
this reform proceeding that places LSEs provide clear standards for evaluation of enforceable definition of ATC,
at the top of the list in competing native load protecting rollover transmission-owning utilities that also
requests for transmission service when restrictions. A clear standard, South own affiliated generation will continue
not all requests could be granted or Carolina E&G states, would have the to hide behind the native load service
honored by the transmission provider. Commission consider rollover obligation as an excuse for being unable
101. New Mexico Attorney General restrictions in light of a utility’s to find ATC for any but self-serving
argues that native load is fundamentally transmission planning process. On purposes.
different than merchant load and reply, Progress Energy supports South 105. EPSA also argues that the
therefore, in the planning process, the Carolina E&G’s comments. Progress Commission must ensure that
needs of merchants should not be Energy urges the Commission to revisit transmission owners’ planning
treated comparably with the needs of the rollover rights policy to develop a accommodates all supply options. EPSA
New Mexico utilities’ native loads. New policy by which an LSE may be assured urges the Commission to clarify that
Mexico Attorney General asserts that of future transmission service for transmission capacity reserved for
New Mexico utilities have a statutory reasonably forecasted native load native load is to be made available
obligation to serve retail load while growth. (including for study and other purposes)
sroberts on PROD1PC70 with RULES

merchants are free to come and go with 103. South Carolina E&G also asks the to competitive suppliers who wish to
cycles inherent in wholesale markets. Commission to revise section 13.6 of the
According to New Mexico Attorney pro forma OATT, regarding curtailment 92 176 F.3d 1090, 1096 (8th Cir. 1999), cert.
General, the transmission requirements of firm point-to-point transmission denied sub nom. Enron Power Marketing, Inc. v.
of the utilities’ native loads amount to service. South Carolina E&G urges the Northern States Power Co., 528 U.S. 1182 (2000).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00018 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12283

serve native load as allowed by State proposed by commenters are not 3. The Types of Transmission Services
law. According to EPSA, all generation necessary at this time to remedy undue Offered
assets ultimately serve load and the pro discrimination. We conclude that the
forma OATT should be clarified to 110. In Order No. 888, the
native load priority established in Order
ensure that the transmission system is Commission required all public utilities
No. 888 continues to strike the
available on a non-discriminatory basis to offer, on a non-discriminatory, open-
appropriate balance between the
now and in the future to ensure that access basis, firm network service and
transmission provider’s need to meet its firm and non-firm point-to-point
load is optimally served—regardless of native load obligations and the need of
which generation resources are serving service. In the NOPR, the Commission
other entities to obtain service from the proposed to retain these services and
that load. In its reply comments, EPSA
transmission provider to meet their own did not propose to require transmission
also challenges the initial comments of
obligations. providers to adopt a network contract
New Mexico Attorney General, which
EPSA argues incorrectly interpret FPA 108. In response to comments demand service, either as a replacement
section 217 as drawing a distinction regarding reforms needed to ATC for network or point-to-point service or
between the types of generation that calculation and transmission planning as a third category of service under the
serve load. EPSA argues that the statute to bring the native load priority policies OATT.
protects the customer load that all in line with FPA section 217, we believe Comments
suppliers would seek to serve regardless that the Commission’s reforms in this
of the source. Final Rule appropriately reflect the 111. Several commenters support the
106. APPA agrees with the transmission provider’s obligation to Commission’s proposal to retain the
Commission’s response in the NOPR to serve native load. As discussed more current services in the pro forma OATT
Metropolitan Water District that the fully in the ATC and planning sections and to not adopt contract demand
specific issues related to an RTO’s below, the processes we adopt herein service.95 While APPA supports the
provision of long-term transmission Commission’s proposal, it states that the
are open, transparent and non-
rights are better left to the rulemaking in Commission should remain open to
discriminatory and assume that the
Docket Nos. RM06–8–000 and AD05–7– individual public utility transmission
000, and the proceedings in each RTO transmission provider is meeting its
obligations, including its native load provider’s proposals to add ‘‘hybrid’’
region to implement the Final Rule service to the base network and point-
issued in those dockets on July 20, 2006. service obligation. We disagree with
to-point services.
APPA notes, however, that the Duke’s assertion that the reforms
proposed in the NOPR will result in a 112. Other commenters, such as AMP-
Commission has not proposed in this
reduction of the protection afforded Ohio and Nevada Companies, argue that
docket to exempt RTOs from the
native or network load. Not only have the Commission should require all
provisions of the NOPR. Rather, APPA
we reaffirmed the fundamental transmission providers to offer network
notes, departures from the pro forma
protections for native load contained in contract demand service. Nevada
OATT, including departures in RTO
Order No. 888, but we have modified, Companies argue that the Commission’s
OATTs, must be justified under the
where appropriate, the pro forma OATT network designation process can
‘‘consistent with or superior to’’
substantially interfere with State
standard. APPA argues that the to ensure that a transmission provider’s
jurisdiction over resource acquisition,
Commission should apply this standard obligations can be met consistent with
to long-term transmission rights, as well especially for transmission providers
maintaining the reliability to existing
as to the other terms and conditions of that are required to purchase substantial
customers, including native load. For
OATT transmission service that RTOs amounts of power to serve their retail
example, we are eliminating the current customers instead of relying primarily
provide. requirement to provide planning on their own generation. Nevada
Commission Determination redispatch over long periods of time Companies reason that allowing
(e.g., 10–30 years) because it is transmission providers to move to a
107. In Order No. 888, the
unnecessary to remedy undue contract demand-based network service
Commission gave public utilities the
discrimination and can create problems would remove them from the dilemma
right to reserve existing transmission
capacity needed for native load growth in forecasting system conditions of being forced to make resource
reasonably forecasted within the consistent with maintaining reliability procurement decisions that are
utility’s current planning horizon. The to native load customers.93 inconsistent with State requirements.
Commission also allowed transmission 109. With regard to APPA’s comments On reply, MidAmerican, Newmont
providers to restrict rollover rights regarding long-term transmission rights Mining, and Utah Municipals oppose
based on reasonably forecasted need at in organized markets, we note that the the suggestion that the contract demand
the time the contract is executed. We Commission has issued its Final Rule in service should be made a mandatory
continue to believe these protections for Docket Nos. RM06–8–000 and AD05–7– service offering in the pro forma OATT.
native load are appropriate and do not 000.94 As discussed more fully in the In its reply comments, Newmont Mining
eliminate them in this Final Rule, as applicability section of this rulemaking, states that, if the Commission is
suggested by some commenters. We also and in response to APPA’s comments, inclined to provide some relief to allow
believe that the protection of native load we reiterate that any departures from Nevada Companies to comply with both
embodied in Order No. 888, as the pro forma OATT proposed by an the pro forma OATT and their State-
enhanced by the reforms adopted in this ISO or an RTO must be ‘‘consistent with approved resource plans, that relief
Final Rule, is consistent with FPA should come only after an investigation
or superior to’’ the pro forma OATT in
section 217, which protects the of how similar problems are handled on
this Final Rule.
sroberts on PROD1PC70 with RULES

transmission rights of entities with other systems and should be a narrowly


service obligations to end-users or a 93 Proposals related to other reforms, such as
and carefully monitored exception to
distribution utility, to the extent curtailments and rollovers, are discussed in the
the resource designation requirements.
required to meet their service sections below dealing with each of those issues.
obligations. The additional reforms 94 See supra note 72. 95 E.g., MISO/PJM States, TVA, and Southern.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00019 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12284 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

113. Alberta Intervenors argue that point-to-point services by the network 4. Functional Unbundling
undue discrimination is most likely to customer to exclude its use for 117. In Order No. 888, the
occur in situations where there is a ‘‘parking’’ and ‘‘hubbing.’’ Commission chose to mandate
single or dominant network customer 114. MidAmerican states that in the functional, rather than corporate (in
and that customer either has a dual Western Interconnection, a utility’s which a public utility’s transmission
mandate for serving the network loads are not necessarily located within and generation assets would be placed
customers or that customer has a ‘‘free a confined geographical boundary in separate corporate entities),
option’’ for procuring transmission.96 served by a single transmission owner. unbundling of transmission and
Alberta Intervenors recommend that the generation services. The Commission
In these cases, MidAmerican argues,
Commission implement standardized explained that functional unbundling
neither network nor point-to-point
rules with respect to the ‘‘free option’’ has three components:
service under the current pro forma
concept while offering regional 1. A public utility must take
OATT is suitable to serve those loads.
flexibility to ensure the objectives of transmission services (including
open access and the absence of undue To remedy these shortcomings in
standard OATT service, MidAmerican ancillary services) for all of its new
discrimination continue to be advanced. wholesale sales and purchases of energy
Alberta Intervenors also argue that, states that the Commission should
require the incorporation of dynamic under the same tariff of general
despite the Commission’s proposal to applicability as do others;
address undue discrimination against scheduling and long-term, seasonally-
2. A public utility must state separate
transmission customers in attempting to shaped, firm point-to-point as new
rates for wholesale generation,
redirect to new receipt and delivery service offerings under the pro forma
transmission, and ancillary services;
points, undue discrimination remains a OATT. 3. A public utility must rely on the
concern since network customers retain Commission Determination same electronic information network
a flexibility of receipt and delivery that its transmission customers rely on
points that is not granted to third party 115. The Commission will not alter to obtain information about its
point-to-point customers. This the types of services that we required in transmission system when buying or
flexibility provided to the network Order No. 888. We continue to believe selling power.99
customer allows the use of the system that network and point-to-point services 118. In the years following Order No.
for activities known as ‘‘parking’’ 97 and are the appropriate base-line service 888, a number of public utilities
‘‘hubbing.’’ 98 Alberta Intervenors urge offerings in the OATT, and we will not nonetheless underwent corporate
the Commission to eliminate this unfair mandate that transmission providers unbundling. Many of these entities did
competitive advantage under the OATT adopt new service offerings such as so as a result of State-mandated
by making a common service available network contract demand service. restructuring laws. Others did so for
to all participants rather than differing Although the Commission has accepted corporate or tax reasons. Some entities
service for network customers, or forms of network contract demand divested all of their generation assets to
alternatively, by restricting the use of service proposed by individual a non-affiliate, while others simply
transmission providers, and the service restructured internally to place the
96 Alberta Intervenors assert that the purchase of
may provide benefits to certain generation assets in a different corporate
point-to-point service by dominant network subsidiary than the transmission assets.
customers results in an equal and offsetting customers, we do not believe the service
reduction to the network customer’s network is necessary to remedy undue There remain, however, a significant
charges, resulting in a net cost of zero. They state discrimination. For example, the service number of vertically-integrated public
that point-to-point service is a net cost to all utilities that operate under the
competitors except the dominant network customer.
would require a departure from full
Thus, they argue, a dominant network customer can load-ratio pricing for network functional unbundling approach.
buy point-to-point service for an extended period customers, which may not be warranted 119. In the NOPR, we proposed to
and use this service for a limited number of hours to the extent the transmission provider preserve the functional unbundling
at little (or no) net cost compared to not purchasing
plans its system to serve all native load. approach adopted in Order No. 888,
point-to-point service for an extended period. In rather than impose a corporate or
Alberta Intervenors’ view, this ‘‘free option’’ However, while the Commission
provides network customers with a competitive concludes that it will not require all structural unbundling requirement.
advantage when reserving point-to-point service
transmission providers to offer this While the Commission expressed its
because it enables the network customers to over- continued support for voluntary efforts
consume or buy excess point-to-point service than service, in response to the arguments
they would if the true net cost were reflected. raised by commenters such as AMP- to adopt structural changes (such as
Alberta Intervenors contend that such over- Ohio and Nevada Companies, we transmission-only companies, RTOs, or
consumption reduces access to point-to-point
reiterate that the Commission already other reforms), the Commission found
service for other customers. that the more intrusive and costly
97 Alberta Intervenors define ‘‘parking’’ as a has accepted forms of network contract
network customer reserving point-to-point service demand service and will continue to corporate unbundling was not necessary
using a network load point of delivery to purchase entertain such proposals on a voluntary at this time. The Commission also
energy that it intends to sell but where no buyer has
basis from transmission providers. declined to mandate an independent
been identified at the time of the reservation. The transmission coordinator for all
energy notionally reduces network load. Once a 116. The Commission also is not
buyer is found, the network customer completes the
transmission providers. Though the
sale by delivering the energy from freed-up
persuaded by Alberta Intervenors’ and Commission has previously found that
generation at a generation point of receipt to a MidAmerican’s arguments in support of such entities may be appropriate in
buyer’s point of delivery. further alternative services under the certain circumstances and we support
98 Alberta Intervenors define ‘‘hubbing’’ as a
pro forma OATT. As with network voluntary efforts to rely on them,100 the
practice very similar to ‘‘parking,’’ but involving contract demand service, transmission
multiple buyers and sellers. The network customer
can reserve point-to-point transmission to purchase providers may propose such services if 99 Order No. 888 at 31,654.
sroberts on PROD1PC70 with RULES

energy from multiple sellers and to sell energy to appropriate for their region. We do not 100 See Duke Power, 113 FERC ¶ 61,288 (2005);
multiple buyers by creating a hub within its believe mandating that such services be MidAmerican Energy Co., 113 FERC ¶ 61,274
network load. Alberta Intervenors explain that this (2005); see also Entergy Services, Inc., 110 FERC
allows the network customer to organize purchases
provided by all transmission providers 61,295 (2005), order on clarification, 111 FERC
and sales by physically matching the requirements is necessary at this time to prevent ¶ 61,222 (2005), order conditionally approving
of multiple buyers and sellers. undue discrimination. filing, 115 FERC ¶ 61,095 (2006).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00020 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12285

Commission concluded that there was marketing functions.103 These rules such transmission providers to submit
not a sufficient basis for requiring them require that employees engaged in FPA section 206 compliance filings,
as a generic remedy for undue transmission functions operate within 60 days after the publication of
discrimination. separately from employees of energy the Final Rule in the Federal Register,
affiliates and marketing affiliates. A that contain the non-rate terms and
Comments number of information sharing conditions set forth in the Final Rule.
120. Commenters generally support restrictions also apply, which prohibit The Commission also acknowledged
the Commission’s proposal to retain transmission providers from allowing that certain non-rate terms and
functional unbundling.101 APPA also employees of their energy and conditions, such as Attachment C
supports the Commission’s decision not marketing affiliates to obtain access to (relating to the transmission provider’s
to mandate an independent transmission or customer information, ATC calculation methodology) and
transmission coordinator for all public except via OASIS. Attachment K (relating to the
utility transmission providers. 123. The Commission aggressively transmission provider’s transmission
Similarly, Tacoma supports the enforces the Standards of Conduct and, planning process), may require more
Commission’s decision to continue to as referenced by APPA, cooperates with than 60 days to prepare and sought
view participation in an RTO or ISO as State regulators to ensure that the comment on an appropriate time period
voluntary actions. While PJM and EPSA functional unbundling regime is in which to require the submission of
would prefer a structural remedy, they sufficient to prevent undue these attachments.
generally support the Commission’s discrimination. The Commission’s 125. Following their FPA section 206
proposal to retain functional Office of Enforcement is well-suited to compliance filings, the Commission
unbundling. However, EPSA states that investigate potential violations of the proposed that transmission providers
given the Commission’s proposal to Standards of Conduct and to propose could submit filings under FPA section
continue to rely on functional remedies, including structural remedies 205 proposing rates for the services
unbundling, it is critical, particularly in if necessary, to ensure that the provided for in the tariff, as well as non-
those areas without organized markets, separation of functions and information rate terms and conditions that differ
that OATT rules regarding unbundled restrictions are fully implemented. We from those set forth in the Final Rule if
transmission service be clear, believe that the increased clarity and those provisions are ‘‘consistent with or
transparent, consistent, and rigorously transparency adopted in other parts of superior to’’ the pro forma OATT.
enforced. APPA states that it will be this Final Rule, when coupled with the
Comments
Standards of Conduct rules and our
vital to obtain the cooperation of State 126. Several commenters ask the
rigorous enforcement program, will
regulators in each region where the Commission to clarify and/or revise the
ensure that the functional unbundling
OATT reforms will be implemented to proposal for dealing with previously-
requirement will serve its original
ensure that the current functional approved provisions that depart from
purpose.
unbundling regime in fact is sufficient the existing (Order No. 888) pro forma
to do the job. C. Applicability of the Final Rule OATT. APPA contends that after this
121. E.ON and TVA express concern 1. Non-ISO/RTO Public Utility multi-phase rulemaking (NOI/NOPR/
that the Commission may yet choose a Transmission Providers Final Rule) to revise the OATT, the
structural remedy. E.ON urges the Commission should hold those public
Commission to look at the full depth 124. In the NOPR, the Commission
utility transmission providers that
and breadth of its existing powers to proposed to apply the Final Rule to all
propose non-rate terms and conditions
monitor and fully redress any abuses in public utility transmission providers,
differing from the new pro forma OATT
including those that are approved ISOs
the allocation of transmission services to a high standard of proof under the
and RTOs. With respect to non-ISO/
before considering structural ‘‘consistent with or superior to’’
RTO transmission providers, the
unbundling. Similarly, TVA notes that standard. According to APPA, any non-
Commission proposed to require all
the Commission already has the option rate term and condition that differs from
to impose a structural remedy on a case- 103 The rules were first established in Order No.
the revised pro forma OATT should be
by-case basis.102 889. See Order No. 889 at 31,595. The Standards ‘‘additive’’ in nature (for example, a new
of Conduct rules were later replaced by a broader service offering, such as network
Commission Determination set of rules adopted in Order No. 2004, which were contract demand service) or should
subsequently vacated in part by the United States
122. The Commission will, as Court of Appeals pending remand proceedings
propose substantive improvements in
proposed in the NOPR, continue to before the Commission. See Standards of Conduct transmission service to customers.
require functional—rather than for Transmission Providers, Order No. 2004, 68 FR APPA argues that a public utility
corporate or structural—unbundling. As 69134 (Dec. 11, 2003), FERC Stats. & Regs. ¶ 31,155 transmission provider should not be
(2003), order on reh’g, Order No. 2004–A, 69 FR
explained in the NOPR, for public 23562 (Apr. 29, 2004), FERC Stats. & Regs. ¶ 31,161
able to make an FPA section 206
utilities that keep transmission and (2004), order on reh’g, Order No. 2004–B, 69 FR compliance filing to implement the pro
generation assets in the same corporate 48371 (Aug. 10, 2004), FERC Stats. & Regs. ¶ 31,166 forma OATT and then ‘‘water down’’ its
(2004), order on reh’g, Order No. 2004–C, 70 FR 284 new OATT through an FPA section 205
entity, the Commission has strict (Jan. 4, 2005), FERC Stats. & Regs. ¶ 31,172 (2005),
Standards of Conduct that require the order on reh’g, Order No. 2004–D, 110 FERC filing that degrades its transmission
separation of the utilities’ transmission ¶ 61,320 (2005), vacated, National Fuel, 468 F.3d service offerings or diminishes the
system operations and wholesale 831. The Commission has issued an interim rule quality of that service.
promulgating temporary regulations consistent with 127. In its reply comments, APPA
the Court’s decision and initiated a further
101 E.g., Santee Cooper, LPPC, TVA, Tacoma,
rulemaking to propose permanent regulations. See
recommends that the Commission
Southern, MISO Transmission Owners, and E.ON. Standards of Conduct for Transmission Providers, require non-ISO/RTO transmission
sroberts on PROD1PC70 with RULES

102 Some commenters argue that adoption of the Order No. 690, 72 FR 2427 (Jan. 19, 2007), FERC providers to file the new pro forma
‘‘open dispatch’’ proposals raised by commenters Stats. & Regs. ¶ 31,327 (2007); Standards of Conduct OATT set out in the Final Rule and add
such as Chandley-Hogan and PJM would constitute for Transmission Providers, Notice of Proposed
a departure from functional unbundling. We Rulemaking, 72 FR 3958 (Jan. 29, 2007), FERC Stats.
in redline—either in that filing, or a
discuss the ‘‘open dispatch’’ and similar proposals & Regs. ¶ 32,611 (2007) (Standards of Conduct companion one—all previously
in section V.C below. NOPR). approved transmission provider-specific

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00021 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12286 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

provisions. APPA states that transmission providers to propose their confusion and to enhance coordination
transmission providers should then own imbalance pricing methodology as within the ISOs and RTOs. To the extent
explain whether they propose to include long as the proposed generator that public utility transmission owners
these provisions in their revised OATTs, imbalance charges are consistent with or whose transmission facilities are under
why they propose to retain or delete superior to the generator imbalance the control of RTOs and ISOs have filing
these provisions, and whether they provisions ultimately adopted in the rights under the RTO or ISO tariffs, EEI
believe these provisions are ‘‘affected by OATT. asks that such public utility
the revisions adopted in the Final 130. On reply, NRECA opposes EEI’s transmission owners be required to
Rule.’’ compliance proposal. NRECA states that submit any necessary tariff filings
128. In contrast, Duke and EEI ask the the Commission should retain the two- within 90 days after the effective date of
Commission to clarify that transmission phased compliance procedure proposed the Final Rule, rather than the currently-
providers with previously-approved in the NOPR because it strikes a fair proposed 60 days. National Grid
departures from the OATT that are not balance by providing transmission suggests that the Commission establish
related to the reforms adopted in this providers the opportunity to suggest a single deadline for ISOs/RTOs and
Final Rule will not be required to changes to their pro forma OATTs their transmission-owning members, set
rejustify these provisions in their FPA under FPA section 205, while allowing at six months from the date of
section 206 compliance filings. They transmission customers and others the publication of the Final Rule.
also ask that transmission providers not opportunity to argue that the deviations 134. TDU Systems recommend that
be required first to adopt all of the from the new pro forma OATT are the Commission adopt a staggered filing
provisions of the revised pro forma neither consistent with nor superior to approach for the compliance filings (i.e.,
OATT and then make an FPA section the pro forma OATT. have transmission providers come in at
205 filing to refile a departure 131. NRECA acknowledges that there different times based on criteria chosen
previously approved by the will be a burden on the transmission by the Commission, such as
Commission. They recommend that provider to prepare a compliance filing; alphabetically or by size). TDU Systems
existing, approved departures from the however, it urges the Commission to argue that this would ensure that
pro forma OATT that are not affected in retain its proposal and require transmission customers are not forced to
a substantive way by the changes to the transmission providers to identify those review all of their transmission
pro forma OATT should be included in terms and conditions that differ from providers’ filings at the same time.
the initial FPA section 206 filing.104 On the pro forma OATT. NRECA agrees
that, if a term or condition unrelated to Commission Determination
reply, Indianapolis Power agrees with
Duke and EEI and urges the Commission any modification of the pro forma 135. The Commission adopts the two-
to consider the unwieldy and cost OATT in the instant rulemaking has tiered implementation process proposed
prohibitive nature of a process that already been found to be consistent with in the NOPR, with certain clarifications
would require transmission providers to or superior to the existing Order No. 888 and modifications, as discussed below.
demonstrate that previously-accepted pro forma OATT, it likely continues to As the Commission proposed in the
elements of their OATTs are acceptable. be consistent with or superior to the NOPR, all transmission providers that
129. Duke and EEI, in their reply revised pro forma OATT term or have not been approved as ISOs or
comments, argue that APPA’s approach condition. NRECA argues, however, that RTOs, and whose transmission facilities
would be inefficient and would cause a a public utility transmission provider are not under the control of an ISO or
substantial disruption to transmission should still be required in a compliance RTO, are required to submit FPA section
service because both transmission filing to identify these deviations from 206 compliance filings that contain the
providers and transmission customers the revised pro forma OATT and, revised non-rate terms and conditions
would be required to abandon tariff ultimately, to justify them in the event set forth in the Final Rule, within 60
provisions that the Commission has that they are fairly contested. Otherwise, days after the publication of the Final
previously found to be consistent with NRECA contends, the Commission and Rule in the Federal Register.105
or superior to the pro forma OATT and industry lose the consistency and However, this filing only need to
that are regularly being used. For related advantages the pro forma OATT contain the revised provisions adopted
example, Duke notes, Duke Carolina has seeks to provide. in the Final Rule, rather than the
an Attachment K that covers the 132. Several commenters addressed transmission provider’s entire pro forma
Independent Entity that will oversee the the deadlines proposed in the NOPR. OATT.106 After the submission of their
provision of transmission service by APPA suggests that the Commission set
Duke. Duke asserts that a literal a 60 or 90-day deadline for those 105 The Commission clarifies that existing waivers

interpretation of the NOPR proposal provisions the transmission provider of the obligation to file an OATT or otherwise offer
open access transmission service in accordance
would mean that it would have to delete can complete itself and a 120 or 180-day with Order No. 888 shall remain in place. The
this attachment and replace its entire deadline for those provisions and reforms to the pro forma OATT adopted in this
OATT with the revised pro forma OATT attachments that will require the Final Rule therefore do not apply to transmission
and then refile its entire Independent transmission provider to incorporate providers with such waivers, although we expect
those transmission providers to participate in the
Entity proposal with its FPA section 205 regional practices and protocols, such as regional planning processes in place in their
filing. Similarly, Entergy states that it Attachments C and K. Tacoma proposes regions, as discussed in more detail in section V.B.
currently has a pro forma Generator 180 days for transmission providers to Whether an existing waiver of OATT requirements
Imbalance Agreement in place that was submit Attachments C and K. PGP should be revoked will be considered on a case-by-
case basis in light of the circumstances surrounding
agreed to by the IPPs on its system and recommends that transmission the particular transmission provider.
accepted by the Commission. Entergy providers be given one year to file 106 As explained below, the Commission is not
urges the Commission to permit Attachment K. requiring transmission providers to submit in their
sroberts on PROD1PC70 with RULES

133. EEI and National Grid urge the compliance filing tariff sheets associated with
104 Duke and EEI propose that a utility would
Commission to align the compliance provisions of the pro forma OATT that have not
redline its compliance filing OATT against the been modified in this proceeding. To the extent,
revised pro forma OATT so that the Commission
filing deadlines for ISOs and RTOs and however, a transmission provider desires to refile
can readily identify the ‘‘already-approved’’ their transmission-owning members in its entire OATT in order to simplify pagination or
differences. order to eliminate any potential other tariff designation issues associated with

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00022 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12287

FPA section 206 compliance filings, standard is appropriate when reviewing modifications required under the Final
these transmission providers may variations from the pro forma OATT Rule, i.e., modifications related to tariff
submit FPA section 205 filings and reject APPA’s proposal to adopt a provisions that did not implicate
proposing rates for the services higher burden of proof. previously-approved variations.
provided for in the tariff, as well as non- 138. The two-tiered compliance 140. As the Commission
rate terms and conditions that differ process adopted above will allow acknowledged in the NOPR, certain
from those set forth in the Final Rule if transmission providers with previously- non-rate terms and conditions, such as
those provisions are ‘‘consistent with or approved variations an opportunity to Attachment C (relating to the
superior to’’ the pro forma OATT. show that their existing deviations transmission provider’s ATC calculation
136. The Commission recognizes that, continue to be consistent with or methodology) and Attachment K
since the issuance of Order No. 888, superior to the pro forma OATT as (relating to the transmission provider’s
some non-ISO/RTO transmission modified in the Final Rule. However, transmission planning process) may
providers have received approval from the Commission recognizes that it may require more than 60 days to prepare.
the Commission to adopt variations cause disruption for some transmission Accordingly, we will require non-ISO/
from the non-rate terms and conditions providers that wish to continue to rely RTO transmission providers to file their
of the pro forma OATT that are on previously-approved variations Attachment C within 180 days after the
consistent with or superior to the Order during the compliance process. The publication of the Final Rule in the
No. 888 pro forma OATT. Under the Commission therefore offers an optional Federal Register and their -Attachment
compliance procedure adopted above, implementation process for non-ISO/ K (or the transmission providers’
those variations that are not affected in RTO transmission providers seeking equivalent thereof) within 210 days after
a substantive manner by the reforms to approval of previously-approved the publication of the Final Rule in the
the pro forma OATT adopted in this variations. Federal Register. A summary of the
Final Rule may remain in place. We 139. Transmission providers that have more significant filing requirements
disagree with the implementation not been approved as ISOs or RTOs and established in this Final Rule is
procedures proposed by APPA, which whose transmission facilities are not provided in Appendix A.108
would require non-ISO/RTO under the control of an ISO or RTO may 141. Other reforms adopted in the
transmission providers with provisions submit an FPA section 205 filing, within Final Rule will involve coordination
in their OATTs that depart from the pro 30 days after the publication of the Final with the North American Energy
forma OATT, but which are not Rule in the Federal Register, seeking a Standards Board (NAESB) to establish
substantively affected by the reforms in determination that a previously- OASIS functionality or uniform
this NOPR, to make a filing that approved variation from the Order No. business practices. The Commission
explains whether and why they would 888 pro forma OATT that has been requests that NAESB file a status report
retain or delete these provisions. We see substantively affected by the reforms within 90 days of publication of the
no need to require non-ISO/RTO adopted in this Final Rule continues to Final Rule in the Federal Register that
transmission providers to ‘‘rejustify’’ be consistent with or superior to the contains a work plan for development of
such provisions if they are not revised pro forma OATT adopted such OASIS functionality and business
substantively affected by the reforms in here.107 Each applicant should request practices. This work plan should
this Final Rule, given that the that the proposed tariff provisions be indicate, for each reform, what actions
Commission has already found these made effective as of the date of the are necessary and an estimate of the
provisions to be consistent with or transmission provider’s section 206 timeframe for completing those actions.
superior to terms and conditions set compliance filing, to be submitted Pending resolution of these issues with
forth in the pro forma OATT that within 60 days after the publication of NAESB, the Commission requires that
remain unchanged, and the Commission the Final Rule in the Federal Register each transmission provider develop its
has not otherwise found these (as provided above). As a condition of own OASIS functionality or business
provisions to be unjust and that request, however, the transmission practice necessary to implement each
unreasonable. provider should state that the such reform within 90 days of
137. In other circumstances, however, Commission has 90 days following the publication of the Final Rule in the
non-ISO/RTO transmission providers date of submission of the filing to act Federal Register, unless a different
may have provisions in their existing under section 205. In other words, the compliance requirement is otherwise
OATTs that the Commission deemed to Commission is offering this optional specified in this Final Rule. Upon
be consistent with or superior to terms implementation process to applicants review of this work plan, the
and conditions of the Order No. 888 pro that allow the Commission 90 days to Commission will issue an order
forma OATT that are being modified by act on the filing. This procedure will establishing further compliance
the Final Rule. Such transmission streamline the compliance process by deadlines as necessary.
providers must demonstrate that these allowing existing variations from terms 142. We are not persuaded to adopt a
previously-approved variations and conditions of the pro forma OATT staggered compliance filing approach in
continue to be consistent with or that have been modified by the Final this proceeding as TDU Systems
superior to the pro forma OATT as Rule to remain in effect until further suggest. However, we will align the
modified by the Final Rule. We Commission action, while also compliance filing deadlines for ISOs
continue to believe that use of the providing the Commission with and RTOs and their transmission-
‘‘consistent with or superior to’’ adequate time to act on the filings. The
subsequent section 206 compliance 108 For further information related to the Final

implementing the modifications required under the filing would then contain tariff sheets Rule, such as electronic versions of the pro forma
Final Rule, it may do so. We note that such a filing OATT showing tariff changes adopted in the Final
necessary to implement the remaining
sroberts on PROD1PC70 with RULES

is a compliance filing and, therefore, the only Rule in redline/strikeout format, and further
deviations in this filing should be the revised information regarding docketing of compliance
provisions in this Final Rule. If a transmission 107 Transmission providers must provide citations filings and specific filing instructions, please visit
provider wishes to propose different terms and to the Commission orders where the variation was our Web site at the following location http://
conditions, it must make a separate FPA section 205 accepted by the Commission as consistent with or www.ferc.gov/industries/electric/indus-act/oatt-
filing. superior to the pro forma OATT. reform.asp.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00023 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12288 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

owning members in order to eliminate access transmission service, including revised pro forma OATT; and
any potential confusion and to enhance the planning requirements. APPA justifications that support excluding
coordination within the ISOs and RTOs. asserts that in their filings, RTOs should revisions of the provisions that the ISO
Thus, we will require public utility be required to show how their or RTO believes are not consistent with
transmission owners whose transmission service packages, or superior to the revised pro forma
transmission facilities are under the including features such as long term OATT. EEI also interprets the NOPR
control of RTOs and ISOs to make any transmission rights, ancillary services, proposal to mean that an ISO or RTO
necessary tariff filings required to and treatment of losses, are consistent immediately may make a separate filing
comply with the Final Rule within 210 with or superior to the newly revised proposing further modifications,
days after the publication of the Final pro forma OATT. Moreover, APPA including revisions to the newly-
Rule in the Federal Register. argues, the Commission should not effective provisions of the pro forma
allow RTOs to use their avowed OATT, that are consistent with or
2. ISO and RTO Public Utility
independence as a justification for superior to the just-filed modifications.
Transmission Providers and 147. SPP urges the Commission to
transmission services that in fact do not
Transmission Owner Members of ISOs affirm that ISOs and RTOs will not be
meet the consistent with or superior to
and RTOs required to rejustify their previously-
standard.109
143. With respect to an ISO or RTO 145. On the other hand, numerous approved non-pro forma tariff
public utility transmission provider, the commenters argue that the proposed provisions, but rather only the new or
Commission recognized in the NOPR compliance process is burdensome and revised tariff provisions expressly
that such an entity may already have could require ISOs and RTOs to have to prescribed in the Final Rule. In its reply
tariff terms and conditions that are relitigate already-approved OATT comments, SPP notes that the terms and
superior to the pro forma OATT. The provisions. The ISOs and RTOs conditions of its OATT are interrelated
Commission also noted that the purpose generally argue that, given the nature of and work together to achieve a system
of this rulemaking is not to redesign the services they offer, many of the of administration that fosters open and
approved, fully-functioning RTO or ISO proposed revisions do not apply to their transparent transmission service and
markets. Thus, the Commission OATTs. Many commenters urge the function as an integrated whole.
proposed to require ISO and RTO Commission to adopt a more limited Therefore, SPP asserts, the modification
transmission providers to submit FPA compliance filing process. Some of one provision of its OATT will
section 206 compliance filings, within commenters, for example, argue that the impact several other provisions and the
90 days after the publication of the Final Commission should only require ISOs process of rejustifying one aspect of the
Rule in the Federal Register, that and RTOs to submit compliance filings tariff likewise will implicate other terms
contain the non-rate terms and that are limited to the specific pro forma and conditions.
conditions set forth in the Final Rule or tariff revisions set forth in the Final 148. Indianapolis Power argues that
that demonstrate that their existing tariff Rule. Duke argues that ISOs and RTOs tariff changes resulting from this
provisions are consistent with or should only be required to make a single rulemaking should be included only
superior to the revised provisions to the filing that revises their OATTs in a with the support of the ISO and RTO
pro forma OATT. The Commission also manner that takes into account the members who bear the costs and are in
proposed to allow ISO and RTO nature of the OATT service provided by the best position to judge the benefits.
transmission providers, after making that ISO or RTO and whether a reform 149. On reply, ISO/RTO Council
their FPA section 206 compliance adopted in the Final Rule is relevant to generally argues that there is no factual
filings, to submit filings under FPA the ISO’s or RTO’s OATT. EEI urges the or legal support for the ISO/RTO
section 205 proposing rates for the Commission to require ISOs and RTOs compliance procedures advocated by
services provided for in their tariffs, as to adopt only those OATT reforms that commenters such as APPA. ISO/RTO
well as non-rate terms and conditions are necessary to improve the quality of Council states that the OATTs of ISOs
that differ from their existing tariffs and transmission service that is provided by and RTOs were developed through
those set forth in the Final Rule if those an ISO or RTO. EEI adds that those who extensive stakeholder procedures and
provisions are consistent with or protest an ISO’s or RTO’s assertion that subject to the Commission’s filing,
superior to the pro forma OATT. The an existing provision is consistent with notice, comment, and approval
Commission did not address the specific or superior to the revised pro forma processes under FPA section 205. ISO/
obligations of transmission owning OATT should have the burden to RTO Council asserts that to adopt the
members of ISOs and RTOs. demonstrate otherwise. The ISOs and post-hoc, open-ended review advocated
RTOs similarly argue that, absent a by these parties would give disgruntled
Comments participants a ‘‘second bite’’ at legally
specific demonstration that an ISO’s or
144. Several commenters support RTO’s OATT provisions are unjust and effective OATT terms and would
applying the revised pro forma OATT to unreasonable, the compliance filing undermine the very stakeholder and
ISOs and RTOs and requiring ISOs and requirements should not apply to ISOs regulatory processes by which ISOs and
RTOs to justify any variations and RTOs. RTOs were established. MISO in
therefrom. MidAmerican argues that 146. EEI urges the Commission to particular argues that APPA’s proposal
universal application of the revised pro clarify that the 90-day filing should ignores that ISO and RTO tariffs have
forma OATT is important because not include the following materials: already been determined to be just and
every ISO or RTO transmission provider Revisions of tariff provisions that reasonable and consistent with or
has existing tariff terms and conditions conform to the revisions in the pro superior to the Order No. 888 pro forma
that are consistent with or superior to forma OATT that are appropriate, given OATT, is profoundly inconsistent with
the OATT. Old Dominion also supports the ISO or RTO’s market structure; the Commission’s policy of encouraging
sroberts on PROD1PC70 with RULES

the Commission’s compliance proposals statements supporting the provisions of RTOs as an option to ensure non-
for ISOs and RTOs. NRECA similarly the tariff that the ISO or RTO believes discriminatory open access transmission
states that RTOs, ISOs and ITCs should are consistent with or superior to the service, and is impracticable unless the
not be automatically exempt from any intent is to grind RTO markets to a halt.
aspect of the rules governing open 109 See also CMUA Reply. MISO states that each RTO tariff has

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00024 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12289

dozens, or perhaps hundreds, of comments, CMUA and APPA oppose transmission service, since the purpose
Commission-approved deviations and, this request for clarification. CMUA of this rulemaking is to prevent undue
in its view, reopening these issues argues that CAISO’s failure to provide discrimination in the provision of
would not be in the public interest and any long-term transmission service transmission service.
would consume enormous resources of renders its transmission service 155. To whatever extent the
both the RTOs and the Commission. markedly inferior to the firm Commission elects to exempt RTOs and
150. Southern, in its reply comments, transmission service under the pro ISOs from certain aspects of the pro
argues that ISOs and RTOs are forma OATT. CMUA maintains that, forma OATT, E.ON asserts that the same
essentially requesting to be exempted instead of affirmatively embracing its consideration should be given to
from the requirements of this obligation to show that its transmission utilities that have entered into
proceeding. Southern states that all service offering, once supplemented arrangements with alternative,
transmission service revisions/reforms with long-term transmission rights that Commission-approved, independent
adopted in this proceeding should apply fully comply with all seven guidelines transmission organizations. In their
uniformly to all transmission providers, set out in Order No. 681, will meet the reply comments, TDU Systems oppose
including ISOs and RTOs. Southern ‘‘consistent with or superior to’’ this proposal arguing that these
contends that ISOs and RTOs are standard of Order No. 888, CAISO alternative constructs may not meet the
increasingly subject to complaints instead asks to be exempted from any independence criteria of Order Nos. 888
alleging discriminatory treatment and such requirement. and 2000.
asserts that the highly partisan attacks 153. Xcel and Indicated New York 156. Several commenters urge the
made by several RTOs against vertically- Transmission Owners assert that the Commission to extend the proposed 90-
integrated utilities further calls into Commission should allow regional day deadline for ISOs and RTOs to
question whether ISOs and RTOs are variations to the extent that ISOs/RTOs submit their compliance filings. EEI
not susceptible to taking discriminatory can demonstrate that their OATT recommends that the Commission
actions. In addition, Southern argues, provisions meet the objectives of the clarify that it will grant an extension of
such exemptions would likely result in Final Rule. Xcel argues that the time if the stakeholder process prevents
seams issues. consistent with or superior to standard an ISO or RTO from obtaining
151. Some commenters state that the may be too narrow because some stakeholder approval of tariff changes
Commission should identify the specific changes to the OATT made by ISOs/ within the 90-day deadline. SPP
reforms it will apply to RTOs and ISOs RTOs are not as much ‘‘superior’’ or requests a minimum of 120 days for
and provide more general guidance as to ‘‘consistent with,’’ as they are simply compliance. National Grid and MISO (in
how it intends to apply the consistent necessary because the tariff is regional. its reply comments) propose that the
with or superior to standard to ISO/RTO Indicated New York Transmission Commission establish a single deadline
tariff provisions. National Grid asserts Owners argue that the Commission for ISOs/RTOs and their transmission-
that the Commission properly identified should not impose a consistent with or owning members set at six months from
these provisions in the NOPR when the superior to standard generally reserved the date of publication of the Final Rule.
Commission concluded that there may for transmission providers that are not Commission Determination
be elements of the proposed reforms members of an ISO/RTO. Indicated New
that are superior to what currently exist York Transmission Owners assert that, 157. The Commission adopts the
in some RTOs or ISOs, e.g., to the extent that certain improvements compliance procedures proposed in the
transparency, data exchange, or could or should be made to the ISO/ NOPR, with certain revisions and
planning. MISO/PJM States identify six RTO OATTs, the Final Rule should clarifications. We will require ISO and
areas as potentially applicable to RTOs: permit the necessary flexibility for each RTO transmission providers to submit
Hourly firm transmission service; ISO/RTO to propose and adopt such FPA section 206 compliance filings,
obligation to expand capacity; joint changes through their stakeholder within 210 days after the publication of
ownership; reservation priority; governance processes, in order to the Final Rule in the Federal Register,
ancillary services; and pro forma OATT address the unique market features and that contain the non-rate terms and
definitions. MISO/PJM States also circumstances of each region. conditions set forth in the Final Rule or
identify eleven areas as not applicable 154. PJM urges the Commission to that demonstrate that their existing tariff
to RTOs: Undue discrimination include an ‘‘independent entity provisions are consistent with or
generally; transmission pricing; variation’’ standard similar to that used superior to the revised provisions of the
remedies, penalties and enforcement; in Order No. 2003, which permitted an pro forma OATT. As with non-ISO/RTO
changes in receipt and delivery points RTO to adopt interconnection transmission providers, however, we
(redirects); rollover rights; rules, procedures that are responsive to will not require ISO and RTO
standards and practices governing the specific regional needs. NRECA transmission providers to ‘‘rejustify’’
provision of transmission service; joint responds that the Commission should existing provisions in their OATTs that
transmission planning; tariff compliance not entertain PJM’s request. While PJM’s are not affected in a substantive manner
review; hoarding of transmission requested standard may have made by the revisions to the pro forma OATT
capacity; curtailments; and ancillary sense in the context of generator in the Final Rule. As we explained
services. APPA, in its reply comments, interconnections, NRECA contends that above, we find that such a process is
opposes granting a blanket exemption it is inapposite to reform of the OATT. unnecessary, given that we have already
for ISOs and RTOs from any portion of NRECA states that ISOs and RTOs found these provisions to be consistent
the compliance filing requirement. should not be allowed to keep on file with or superior to the Order No. 888
152. CAISO urges the Commission to tariff provisions that possess the pro forma OATT and these provisions
clarify how it should provide for potential to allow for undue are not substantively affected by the
sroberts on PROD1PC70 with RULES

changes in the Final Rule to discrimination, even if the entity reforms we adopt today.
transmission services that it does not publishing the tariff is ostensibly 158. We also recognize, as we did in
provide or which are clearly independent of market participants and the NOPR, that some of the changes
incompatible with the transmission even if the proposed reforms do not adopted in the Final Rule may not be as
service model it employs. In their reply directly improve the ‘‘quality of’’ relevant to ISO/RTO transmission

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00025 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12290 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

providers as they are to non- under the control of RTOs or ISOs to a bilateral agreement that satisfies its
independent transmission providers. make any necessary tariff filings reciprocity obligation. Finally, the non-
For example, many ISOs and RTOs use required to comply with the Final Rule public utility may seek a waiver of the
bid-based locational markets and within 210 days after the publication of reciprocity condition from the public
financial rights to address transmission the Final Rule in the Federal Register. utility.112
congestion, rather than the first-come, A summary of the more significant filing 164. In EPAct 2005, Congress
first-served physical rights model set requirements established in this Final authorized, but did not require, the
forth in the pro forma OATT. As we Rule is provided in Appendix A.110 Commission to order non-public
indicated in the NOPR, nothing in this utilities (or ‘‘unregulated transmitting
3. Non-Public Utility Transmission utilities’’) to provide transmission
rulemaking is intended to upset the
Providers/Reciprocity services under a new section 211A in
market designs used by existing ISOs
and RTOs. We also recognize that ISOs 162. In Order No. 888, the Part II of the FPA. This section states in
and RTOs may well have adopted Commission conditioned non-public part that the Commission ‘‘may, by rule
practices that are already consistent utilities’ use of public utility open or order, require an unregulated
with or superior to the reforms adopted access services on an agreement to offer transmitting utility to provide
here. For example, ISOs and RTOs tend comparable transmission services in transmission services’’ at rates that are
to have transmission planning processes return.111 The Commission found that, comparable to those it charges itself and
that are significantly more open and while it did not have the authority to under terms and conditions (unrelated
transparent than the processes used by require non-public utilities to make to rates) that are comparable to those it
non-independent transmission their systems generally available, it did applies to itself, and that are not unduly
providers. We encourage ISOs and RTOs have the ability and the obligation to discriminatory or preferential. The
to meet with their stakeholders to ensure that open access transmission is language does not limit the Commission
discuss whether any improvements are as widely available as possible and that to ordering transmission services only to
necessary to comply with the Final Order No. 888 did not result in a the public utility from whom the non-
Rule. competitive disadvantage to public public utility takes transmission
159. We reject Indianapolis Power’s utilities. services, but rather permits the
proposal to require tariff changes 163. Under the reciprocity provision Commission to order the non-public
resulting from this rulemaking only in section 6 of the pro forma OATT, if utility to provide ‘‘open access’’
with the support of the ISO and RTO a public utility seeks transmission transmission service, i.e., service to all
members who may bear the costs service from a non-public utility to eligible customers.
associated with the revision. which it provides open access 165. In the NOPR, the Commission
Indianapolis Power effectively asks that transmission service, the non-public proposed to retain the current
we allow ISO and RTO members to veto utility that owns, controls, or operates reciprocity language in the pro forma
our decisions here, which is contrary to transmission facilities must provide OATT, as well as Order No. 888’s three
our duty to prevent undue comparable transmission service that it alternative provisions for satisfying the
discrimination in the provision of is capable of providing on its own reciprocity condition, i.e.: A non-public
transmission service. system. Under the pro forma OATT, a utility that owns, controls, or operates
160. Regarding CAISO’s request for public utility may refuse to provide transmission and seeks transmission
clarification of how it should address open access transmission service to a service from a public utility must either
changes in the Final Rule to non-public utility if the non-public satisfy its reciprocity obligation under a
transmission services that it does not utility refuses to reciprocate. A non- bilateral agreement, seek a waiver of the
provide or which are incompatible with public utility may satisfy the reciprocity OATT reciprocity condition from the
its service model, we reiterate that condition in one of three ways. First, it public utility, or file a safe harbor tariff
CAISO—like any other ISO or RTO—has may provide service under a tariff that with the Commission.113
the opportunity to demonstrate that a has been approved by the Commission 166. The Commission did not propose
variation from the tariff revisions under the voluntary ‘‘safe harbor’’ a generic rule to implement the new
adopted in the Final Rule satisfies the provision. A non-public utility using FPA section 211A.114 Rather, the
consistent with or superior to standard. this alternative submits a reciprocity Commission proposed to apply its
We do not believe that the adoption of tariff to the Commission seeking a provisions on a case-by-case basis, such
an ‘‘independent entity variation,’’ declaratory order that the proposed as when a public utility seeks service
proposed by PJM, or a regional variation reciprocity tariff substantially conforms
standard, proposed by Xcel and to, or is superior to, the pro forma 112 See Order No. 888–A at 30,285–86.
113 For non-public utilities that choose to use the
Indicated New York Transmission OATT. The non-public utility then must
safe harbor tariff, the Commission noted in the
Owners, would be appropriate. Again, offer service under its reciprocity tariff NOPR that the existing safe harbor provisions
the Commission finds that the reforms to any public utility whose transmission would need to be substantially conforming or
adopted in this Final Rule are necessary service the non-public utility seeks to superior to the new pro forma OATT. A non-public
to prevent undue discrimination in the use. Second, the non-public utility may utility that already has a safe harbor tariff would
therefore be required to amend its tariff so that its
provision of transmission service and provide service to a public utility under provisions substantially conform or are superior to
any transmission provider, including an the new pro forma OATT if it wishes to continue
ISO or RTO, must demonstrate that 110 For further information related to the Final to qualify for safe harbor treatment. As the
variations from the tariff modifications Rule, such as electronic versions of the pro forma Commission stated in Order No. 888–A, a non-
OATT showing tariff changes adopted in the Final public utility may limit the use of its voluntarily
required here satisfy the consistent with Rule in redline/strikeout format, and further offered safe harbor reciprocity tariff only to those
or superior to standard. information regarding docketing of compliance transmission providers from whom the non-public
161. As discussed above, however, we filings and specific filing instructions, please visit utility obtains open access service, as long as the
sroberts on PROD1PC70 with RULES

will align the compliance filing our Web site at the following location http:// tariff otherwise substantially conforms to the pro
deadlines for ISOs and RTOs and their www.ferc.gov/industries/electric/indus-act/oatt- forma OATT. See Order No. 888–A at 30,289.
reform.asp. 114 The Commission noted in the NOPR that LPPC
transmission-owning members and 111 These entities are not FPA public utilities and has committed to voluntary compliance with a set
require public utility transmission therefore are not subject to the Commission’s of guidelines for the provision of comparable
owners whose transmission facilities are jurisdiction under sections 205 and 206 of the FPA. service under FPA section 211A.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00026 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12291

from an unregulated transmitting utility guidelines for the provision of to provide comparable service would
that has not requested service under the comparable open access service, which create a ‘‘patchwork of open and
public utility’s OATT and the it contends will provide a significant closed’’ unregulated transmitting
reciprocity obligation therefore does not degree of standardization for such utilities, just like the patchwork of open
apply. The Commission stated that such service. Thus, LPPC believes that and closed jurisdictional transmission
a customer may file an application with generic action under section 211A is not systems the Commission sought to
the Commission seeking an order necessary. In addition, LPPC asserts that eliminate when it issued Order No. 888.
compelling the unregulated transmitting there is no evidence on record of undue Calpine also states that its comments on
utility to provide transmission service discrimination by a nonjurisdictional the NOI in this proceeding provide
that meets the standards of FPA section entity that would justify the several examples of the kinds of
211A. The Commission further Commission reversing the NOPR problems it has experienced in seeking
proposed to amend its regulations to decision to act on a case-by-case basis transmission service from unregulated
make clear that an applicant in an FPA under FPA section 211A.116 transmitting utilities in a variety of
section 211A proceeding against a non- 170. On the other hand, several regions and across multiple
public utility that has submitted an commenters urge the Commission to transmission systems.
acceptable safe harbor tariff has the implement FPA section 211A on a
burden of proof to show why service generic basis.117 AWEA argues that 173. California Commission argues
under the safe harbor tariff is not reciprocity tariffs do not subject the that FPA section 211A gives the
sufficient and why an FPA section 211A nonpublic utilities to Commission Commission the authority to require
order should be granted. In addition, the enforcement as would an OATT previously nonjurisdictional entities to
Commission stated in the NOPR its established under FPA section 211A. file tariffs with the Commission that
expectation that unregulated AWEA urges the Commission to would be subject to the due process and
transmission providers would proceed on a generic basis to ensure that the ‘‘just and reasonable’’ requirements
participate in the proposed open and nonjurisdictional utilities comply with of the FPA. California Commission
transparent regional planning processes the reformed OATT under exactly the urges the Commission to actively
and noted that, if there were complaints same terms and conditions as explore a set of mandatory actions that
about such participation, they would jurisdictional utilities. On reply, the Commission may impose on
also be addressed on a case-by-case however, APPA argues that the nonjurisdictional entities and states
basis. comparability standard does not mean that, if the Commission is reluctant to
167. The NOPR proposed to retain the that unregulated transmitting utilities do so in this proceeding, it should
existing reciprocity policy as applied to must comply with the reformed OATT initiate a new rulemaking to consider
foreign utilities doing business in the under exactly the same terms and such rules. California Commission
United States, which we adopted conditions as jurisdictional entities. asserts that there are a number of sound
pursuant to sections 205 and 206 of the 171. In its reply comments, EEI states policy reasons for taking generic action
FPA. By maintaining the same that, while LPPC’s voluntary proposal is to address the mandate of FPA section
reciprocity requirement for these foreign a step in the right direction, LPPC’s 211A. First, it argues that Commission
utilities as for domestic, non-public proposal does not go far enough to action would prevent the balkanization
utilities, the Commission stated that it assure that reciprocal transmission
would ensure that foreign entities will of the grid that can result if a
service is provided in a non- nonjurisdictional transmission owner
continue to be treated no less favorably discriminatory manner. EEI asserts that
than domestic, non-public utilities. refuses to participate in an RTO or ISO
LPPC’s proposal still gives the whose service area surrounds,
Comments individual non-public utility encompasses, or overlaps it. Second,
168. The majority of the commenters transmission provider the discretion to California Commission argues that
support the Commission’s decisions to decide what is or is not comparable and Congress has given the Commission
retain the reciprocity provision and to not unduly discriminatory. Moreover, explicit authority to require previously
adopt a case-by-case approach to FPA EEI notes, LPPC does not represent the nonjurisdictional entities to provide
section 211A.115 These commenters universe of non-public utility transmission service on a non-
reason that there is no evidence of a transmission providers, rather only 24 preferential and non-discriminatory
general problem of non-public utilities of the largest governmentally-owned basis. Finally, California Commission
failing to provide transmission service transmission providers.
asserts, the Commission would be able
172. Some commenters argue that the
and that, for the most part, non-public to squarely address generic seams issues
case-by-case approach proposed in the
utilities already provide transmission on created by the existence of control areas
NOPR does not satisfy the Commission’s
an as-available basis under comparable operated by previously unregulated
stated goal of remedying undue
terms, regardless of whether a tariff is transmission owners and the ability of
discrimination and its intent to provide
on file with the Commission. In such entities to ‘‘free ride’’ on the
transparent, consistent and clear rules
addition, Santa Clara and TANC state systems and open access requirements
for use of the nation’s transmission
that the Commission’s proposal of the jurisdictional entities.
grid.118 Calpine contends that the
apparently respects the
administrative burden of monitoring 174. In its reply comments, CMUA
nonjurisdictional status of public
and administering customer complaints contests California Commission’s
power.
169. LPPC reiterates its prior offer of or processing applications that seek to assertion that those outside CAISO
voluntary compliance with a set of compel unregulated transmitting operations are ‘‘free riders.’’ CMUA
utilities in different parts of the country notes that its members post their excess
transmission capacity on wesTTrans (an
sroberts on PROD1PC70 with RULES

115 E.g., APPA, Bonneville, LPPC, Newfoundland,


116 See also Public Power Council Reply and
NRECA, PGP, Sacramento, Salt River, Santa Clara, OASIS site serving the Western
Santee Cooper, Seattle, TANC, TAPS, TVA, Sacramento Reply.
117 E.g., AWEA, California Commission, Calpine,
Interconnection) thus making it
Tacoma, WAPA, CMUA Reply, East Texas
Cooperatives Reply, Lassen Reply, and Public EEI, MidAmerican, San Diego G&E, and Xcel. available to third parties, and that its
Power Council Reply. 118 E.g., Calpine, MidAmerican, and Xcel. members outside the CAISO also pay a

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00027 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12292 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

host of CAISO fees.119 CMUA states that of the pro forma OATT to reflect the LPPC argues, it would make sense for
it does not contest that there are comparability standards now contained the Commission to entertain requests for
‘‘seams’’ between organized markets and in FPA section 211A. LPPC states that, partial waiver.
neighbors, but it asserts that this docket with the implementation of FPA section 180. If the Commission does not
is not the place for this discussion and 211A, it is appropriate to revise the pro reconsider its proposal not to act
FPA section 211A is not the remedy. In forma OATT language in order to reflect generically under FPA section 211A,
its reply comments, APPA also urges the the unregulated utility’s obligation ‘‘to EEI contends that there are other actions
Commission to reject California provide transmission service the Commission should take. In order to
Commission’s proposal. APPA argues comparable to the service the customer facilitate full compliance with the
that section 211A was not intended, nor provides itself’’ as the ‘‘quid pro quo’’ reciprocity obligation, EEI urges the
could the Commission use it, to require for receiving reciprocal service. LPPC Commission at least to clarify and
nonjurisdictional transmission also argues that, with respect to the strengthen the obligations of non-public
providers to participate in an RTO and, existing safe harbor option, the utility transmission providers under the
therefore, California Commission’s Commission should revise its test for reciprocity provision,121 exercise
proposal exceeds the Commission’s evaluating a safe harbor OATT from one oversight and monitor their compliance
authority under section 211A.120 which asks whether the proposal is with the reciprocity obligation, and
175. EPSA, in its reply comments, equivalent or superior to the pro forma require them to provide greater
disagrees with commenters who appear OATT, to one which asks whether the transparency of the transmission
to believe that nonjurisdictional service provided under the proposed services and the terms and conditions of
transmitting utilities will not have to OATT is comparable to the service that service they offer so that those seeking
take any steps to comply with a final the unregulated utility provides itself. transmission service under the
order in this rulemaking. EPSA states 178. EPSA replies that LPPC’s reciprocity provision are able to
that its understanding is that the suggestion to revise the language of determine whether they are complying
Commission’s principle of reciprocity section 6 ironically would require with their reciprocity obligation.
would apply to any changes in the pro nonjurisdictional transmitting utilities 181. With respect to the reciprocity
forma OATT adopted in the Final Rule. to offer third party customers provision in the pro forma OATT, EEI
Accordingly, both jurisdictional and transmission services that are requests that the Commission update it
nonjurisdictional transmitting utilities comparable to network transmission by including reference to transmission
that adopted the Order No. 888 pro service, which is a higher quality of service by ISOs and RTOs. EEI asks that
forma OATT would have to make transmission service than the revised the reciprocity provision be modified to
compliance filings. In addition, EPSA OATT and which is unlikely to be provide that, if an ISO or RTO is the
argues that nonjurisdictional supported by nonjurisdictional transmission provider, the reciprocity
transmitting utilities that previously transmitting utilities. EPSA states that it obligation is owed to all members of the
received an Order No. 888 waiver or believes that FPA section 211A requires ISO or RTO. EEI notes, however, that
that wish to request such a waiver a nonjurisdictional transmitting utility even this action would not require non-
should have an affirmative duty to file to provide transmission service (at its public utility transmission providers to
a request for a waiver. In the event that interfaces with jurisdictional public provide transmission services to other
a nonjurisdictional entity wishes to file utilities and internal sources) that is entities who are eligible customers
a bilateral contract, EPSA contends that comparable to the service it is taking at under the ISO or RTO OATT and who
it should be required to file a interfaces or internal sources. EPSA are not transmission providers, such as
‘‘reciprocity’’ contract pursuant to FPA therefore argues that the appropriate independent generators. EEI asserts that
section 205. If a nonjurisdictional standard for determining whether a non-public utility transmission
transmitting utility does not adopt a nonjurisdictional transmitting utility’s providers may discriminate against
revised pro forma OATT as a ‘‘safe tariff is comparable is whether the certain transmission customers unless
harbor,’’ EPSA argues the Commission’s nonjurisdictional utility’s tariff is ‘‘equal the reciprocity obligation is expanded.
standard of review should be whether or superior’’ to the revised pro forma Sempra Global also asks the
the nonjurisdictional transmitting OATT. Commission to clarify that the right to
utility’s alternative tariff is ‘‘equal or 179. LPPC also argues that the two seek transmission service from an
superior to’’ a revised pro forma OATT. categorical exemptions from FPA unregulated transmitting utility
176. EPSA, in its reply comments, section 211A articulated in FPA section pursuant to FPA section 211A is
supports implementing the rate 211A(c)(3) (based on size and the value available to any entity that qualifies as
provisions of FPA section 211A in a of the unregulated system to the an eligible customer under the
proceeding separate from this particular integrated grid) should not be exclusive. Commission’s pro forma OATT.
proceeding. EPSA states that such a Rather, LPPC contends that the two 182. EEI acknowledges that the
proceeding could take a generic exemptions should guide the Commission declined in Order No. 888–
approach, in that nonjurisdictional Commission in considering similar A to expand the reciprocity provision
transmitting utilities could be required requests for exemption. For example, beyond the specific transmission
to set transmission rates for third-party LPPC argues that relatively small provider from which the transmission
transmission services that are computed utilities, which nevertheless exceed an customer takes service on the ground
using rate determinants that are express threshold, should be permitted that requiring ‘‘non-public utilities to
comparable to the determinants that the to demonstrate that their systems are offer transmission service to entities
non-public utility uses to calculate simply too small, and that their facilities other than public utility transmission
transmission rates for its native load. are not sufficiently strategic, to call for providers increases the chances that
177. With regard to specific full inclusion in the FPA section 211A they could lose tax-exempt status.’’ 122
sroberts on PROD1PC70 with RULES

reciprocity obligations, LPPC argues that regime. Similarly, LPPC states that, in However, EEI states, in 2002, the
the Commission should revise section 6 certain public systems, only some
discrete portions of the system would 121 Xcel and MidAmerican support EEI’s proposal
119 See also APPA Reply. fairly be considered part of the on this issue.
120 See also CMUA Reply and Santa Clara Reply. integrated system. In these cases as well, 122 Citing Order No. 888–A at 30,287.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00028 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12293

Department of the Treasury adopted transmission system, which is not the pro forma tariff to apply this
final regulations that in effect provide situation under the current reciprocity information reporting requirement to
that providing open access transmission requirement. Consequently, the those large non-public utility
does not constitute private use.123 Canadian Electricity Association asserts, transmission providers that are not
Therefore, EEI argues, this reason for EEI’s proposal would allow the exempted by section 211A(c).129
limiting the services provided under the Commission to fully impose open access 189. On reply, several commenters
reciprocity obligation is no longer requirements in Canada and would oppose EEI’s transparency proposal.
applicable.124 violate the principles of comity and Among other things, they argue that
183. Moreover, EEI argues, as undermine Canadian jurisdictional EEI’s proposal is unnecessary and
originally established in Order Nos. 888 sovereignty. duplicative of information that is
and 888–A, the Commission stated that 186. The Canadian Electricity already publicly available—e.g., the
it was ‘‘conditioning the use of public Association also repeats its earlier non-public utility’s Web site, the
utility open access tariffs, by all arguments made in response to the NOI Commission’s Web site, or in some
customers including non-public that, to the extent the Commission instances a regional entity’s Web site
utilities, on an agreement to offer adopts the comparability standard in (such as the wesTTrans OASIS).130
comparable (not unduly discriminatory FPA section 211A for non-public APPA further notes that LPPC has
services) in return.’’ 125 However, EEI utilities, the Commission must apply proposed that the terms and conditions
states, the reciprocity provision of the the same changes to Canadian utilities. in non-public utility transmission
pro forma OATT refers to ‘‘similar terms 187. EEI also urges the Commission to provider’s tariffs would be publicly
and conditions’’ but does not make clear take certain steps to increase available on the individual utility’s or a
what they should be ‘‘similar’’ to. EEI transparency and accountability in regional entity’s Web site. In addition,
argues that the term ‘‘similar’’ does not complying with the reciprocity NRECA asserts that, absent waivers, any
necessarily encompass the requirement requirement.126 For example, EEI states, non-public utility transmission provider
that is part of comparability that the the Commission could include on its that has adopted a ‘‘safe-harbor’’ tariff
services provided be ‘‘not unduly Web site a list of all non-public utility has adopted all of the OATT, OASIS,
discriminatory’’ as Order Nos. 888 and transmission providers that have and Standards of Conduct requirements
888–A require. EEI proposes that the pro Commission-approved safe harbor that apply to public utilities. NRECA
forma OATT be amended to refer to reciprocity tariffs. According to EEI, and TANC both assert that the
‘‘comparable terms and conditions’’ such a list of entities would facilitate Commission does not have similar
rather than ‘‘similar’’ to align it with use of their transmission systems, informational filing requirements for
Order Nos. 888 and 888–A. Finally, EEI provide transparency, and provide public utilities. Furthermore, TANC
also states that the Commission should recognition to these entities for their argues that it would be a waste of
also reaffirm that the reciprocity voluntary efforts in accomplishing these Commission resources to compile a list
obligation is binding on Canadian goals.127 of all non-public utility transmission
utilities. 188. EEI requests that the Commission providers that have Commission-
184. On reply, APPA urges the also establish minimal transparency approved safe harbor tariffs. TANC also
Commission to reject EEI’s proposed requirements for non-public utility argues that to provide such an
expansion of the reciprocity provision. transmission providers.128 EEI asserts information filing would be unduly
APPA notes that EEI’s proposed that the Commission has ample burdensome and a waste of
application of the reforms to all non- authority under FPA section 211A and nonjurisdictional utility transmission
public utility transmission providers under the reciprocity provision of the provider time and limited resources.
would potentially include a broader
universe of public power entities than 126 According to EEI, the new authority granted to Commission Determination
those subject to FPA section 211A. the Commission under EPAct 2005 section 1281 190. The Commission retains the
(new FPA section 220) (Electricity Market
Moreover, APPA argues, many of the Transparency Rules), which applies to all ‘‘market
reciprocity language in the Order No.
goals that EEI claims it wishes to participants,’’ provides another basis for requiring 888 pro forma OATT, but updates it to
accomplish would be accomplished greater transparency under the pro forma OATT by include references to ISOs and RTOs, as
even if the Commission takes no action. non-public utility transmission providers. EEI suggested by EEI. We also modify the
185. In its reply comments, the argues that the Commission could rely on this new
authority to require greater transparency in
reciprocity provision to provide that, if
Canadian Electricity Association urges transmission service provided under the reciprocity an ISO or RTO is the transmission
the Commission to reject EEI’s proposal obligation. provider, the reciprocity obligation is
to strengthen the reciprocity obligation 127 EEI notes that, in the NOPR, the Commission
owed to all members of that ISO or RTO.
so as to require the offering of referenced voluntary guidelines being developed by We concur with EEI’s assessment that
members of the LPPC. EEI believes this is a step in
transmission service to all eligible the right direction and looks forward to the such modifications will more accurately
customers. The Canadian Electricity opportunity to provide input on the proposed reflect the current state of the industry.
Association argues that the effect of guidelines. In EEI’s view, however, if any LPPC However, we will not adopt EEI’s
EEI’s proposal would be to enable a member wishes to use these guidelines as a safe proposal to extend the reciprocity
generator generating power in Canada to harbor tariff, it must meet the safe harbor standard
that the terms of service must be ‘‘substantially obligation to all eligible customers or
obtain access on a Canadian utility’s conforming or superior to’’ the revised OATT. The
reciprocity obligation requires that the terms and 129 Section 211A authorizes the Commission to
123 Treas. Reg. § 1.141–7(g). conditions of service be comparable to those that require certain unregulated transmitting utilities to
124 EEI asserts that the Commission also has the the non-public utility transmission provider applies provide transmission services at rates that are
authority to make this change under FPA section to itself and not be unduly discriminatory. comparable to those that the unregulated
211A, which provides that the Commission may not 128 EEI states that this informational filing should transmitting utilities charges itself and on terms and
require a State or municipality to take action under include information such as: whether or not they conditions (not related to rates) that are comparable
sroberts on PROD1PC70 with RULES

that section that would violate a private utility bond have a reciprocity or other tariff and how it can be to those under which the unregulated transmitting
rule. If a non-public utility transmission provider is obtained, whether they have an OASIS and location utility provides transmission services to itself and
concerned about the impact on the tax-exempt URL, whether they have standards of conduct and that are not unduly discriminatory or preferential.
status of its bonds, EEI suggests that it could seek where they are posted, whether they have posted 130 E.g., APPA Reply, CMUA Reply, LPPC Reply,
a waiver from the Commission. business practices, their contact for regional Lassen Reply, NRECA Reply, Sacramento Reply,
125 Citing Order No. 888–A at 30,285. transmission planning, and their ATC methodology. and TANC Reply.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00029 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12294 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

LPPC’s proposal to revise the pro forma be granted.132 Further, as we indicate a transmission provider may not know
OATT language regarding below, we restate our expectation that of its neighbors’ system conditions
comparability. We are not persuaded unregulated transmission providers will affecting its own ATC values. As a result
that either proposal is necessary at this participate in the open and transparent of this reliability impact, the
time to prevent undue discrimination regional planning processes ordered Commission observed that the proposed
absent a complaint. below and note that, if there are ATC reforms are also supported by FPA
191. We will also retain Order No. complaints about such participation or section 215(d)(5), through which the
888’s three alternative provisions for the lack thereof, we will address them Commission has the authority to direct
satisfying the reciprocity condition, i.e.: on a case-by-case basis. the ERO to submit a reliability standard
A non-public utility that owns, controls, that the Commission considers
V. Reforms of the OATT
or operates transmission and seeks appropriate to implement FPA section
transmission service from a public A. Consistency and Transparency of 215.
utility must either satisfy its reciprocity ATC Calculations 196. In light of these concerns, we
obligation under a bilateral agreement, 193. In the NOPR, the Commission direct public utilities, working through
seek a waiver of the OATT reciprocity proposed to take action under FPA NERC reliability standards and NAESB
condition from the public utility, or file section 206 to remedy undue business practices development
a safe harbor tariff with the discrimination in the provision of processes, to produce workable
Commission. Thus, for non-public transmission service. The Commission solutions to complex and contentious
utilities that choose to use the safe recognized that while Order Nos. 888 issues surrounding improving the
harbor tariff, its provisions must be and 889 require transmission providers consistency and transparency of ATC
substantially conforming or superior to to offer and post any available transfer calculations. We are directing our
the revised pro forma OATT in this capability (ATC) on their OASIS, and guidance to public utilities and require
Final Rule. A non-public utility that file the methodology they use to that they implement our direction by
already has a safe harbor tariff must calculate ATC as Attachment C to their working with NERC to develop
amend its tariff so that its provisions OATTs, the industry has not developed reliability standards that accomplish the
substantially conform or are superior to a consistent methodology for evaluating ATC reforms required in this
the revised pro forma OATT if it wishes ATC nor have transmission providers rulemaking. We will coordinate our
to continue to qualify for safe harbor adequately made their ATC calculation directives here with the ATC-related
treatment. As the Commission stated in methodology transparent. This reliability standards that are pending in
Order No. 888–A, a non-public utility inconsistency and lack of transparency Docket No. RM06–16–000.134 The
may limit the use of its voluntarily creates the potential for undue specifics of our findings with respect to
offered safe harbor reciprocity tariff only discrimination in the provision of open ATC reform are discussed below.
to those transmission providers from access transmission service. 1. Consistency
whom the non-public utility obtains 194. In the NOPR, the Commission
197. In order to address the potential
open access service, as long as the tariff proposed to address this potential for
for remaining undue discrimination in
otherwise substantially conforms to the undue discrimination by requiring
the determination of ATC, the
pro forma OATT.131 We reiterate that industry-wide consistency and
Commission proposed to require
these reciprocity requirements apply transparency of all components of the
industry-wide consistency of certain
equally to all non-public utility ATC calculation methodology and
definitions, data, and modeling
transmission providers, including those certain definitions, data, and modeling
assumptions of the ATC calculation.
located in foreign countries. assumptions. The Commission proposed
192. As the Commission proposed in to provide guidance regarding aspects of a. Necessary Degree of Consistency
the NOPR, we will not adopt a generic ATC calculations that should be more NOPR Proposal
rule to implement the new FPA section consistent and proposed to direct public
utilities, working through NERC 133 and 198. In the NOPR, the Commission
211A. Rather, we will apply its recognized that transmission providers
provisions on a case-by-case basis, such NAESB, to revise reliability standards
and business practices that are relevant use several basic types of ATC
as when a public utility seeks service calculation methodologies (with various
from an unregulated transmitting utility to ATC calculations. The Commission
also proposed to require increased detail permutations), and did not propose to
that has not requested service under the require a single ATC calculation
public utility’s OATT and the in Attachment C of each transmission
provider’s OATT and proposed methodology to be applied by all
reciprocity obligation therefore does not transmission providers. However, the
apply. A potential customer may file an amending the OASIS regulations to
require increased transparency. Commission proposed to achieve greater
application with the Commission consistency in ATC calculations by
seeking an order compelling the Although commenters challenged
aspects of this proposed remedy, no directing the development of consistent
unregulated transmitting utility to definitions of the ATC components,135
provide transmission service that meets commenters challenged the underlying
finding that ATC reform is necessary to as well as consistent data inputs,
the standards of FPA section 211A. We modeling assumptions, and data
adopt the NOPR proposal to amend our remedy undue discrimination in the
regulations to make clear that an provision of transmission service. 134 We note that many of the ATC-related

applicant in an FPA section 211A 195. The Commission also indicated reliability standards filed in Docket No. RM06–16–
proceeding against a non-public utility that the lack of consistent, industry- 000 were not addressed by the NOPR in that
that has submitted an acceptable safe wide ATC calculation standards poses a proceeding, pending the submittal of additional
threat to the reliable operation of the information. See Mandatory Reliability Standards
harbor tariff shall have the burden of for the Bulk-Power System, 71 FR 64770 (Nov. 3,
bulk-power system, particularly because
sroberts on PROD1PC70 with RULES

proof to show why service under the 2006), FERC Stats. & Regs. ¶ 32,608 at Appendix A
safe harbor tariff is not sufficient and (2006) (Reliability Standards NOPR).
132 See revised 18 CFR 35.28(e)(1)(ii). 135 The ATC components are total transfer
why an FPA section 211A order should 133 All references to NERC in the context of capability (TTC), existing transmission
developing reliability standards are to NERC as the commitments (ETC), capacity benefit margin (CBM),
131 See Order No. 888–A at 30,289. Electric Reliability Organization (ERO). and transmission reserve margin (TRM).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00030 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12295

exchange and coordination protocols. industry-wide standard for the to maximize confidence in standards
The Commission also required each calculation of ATC and emphasizes that and system use, and maintain
transmission provider using an a consistent and transparent approach to reliability. In its reply comments,
Available Flowgate Capacity (AFC) evaluating ATC and ATC/AFC modeling Exelon disagrees with EEI and states
methodology to explain its definition of assumptions is a prerequisite to the that there are no regional differences
AFC, its calculation methodology and elimination of the broad discretion within the individual interconnections
assumptions, and its process for afforded transmission providers and, that would justify differences in the
converting AFC into ATC. with it, the subtle discrimination application of ATC calculations.
practiced against customers. 204. Exelon states that ATC
Comments 201. Southern suggests that the basic definitions must be consistent so that
199. While the majority of ATC calculation should be defined for the various ATC components such as
commenters 136 support the NOPR’s both firm and non-firm ATC TRM have the identical meaning for all
proposal to increase consistency in the calculations and also proposes that the industry participants. In addition,
calculation of ATC, several caution the following basic formulas be used: ATC Exelon argues that each ATC component
Commission to allow flexibility 137 in (firm) = TTC ¥ Firm Commitments or (ETC, TRM, and CBM) must be used in
order to capture differences in system ETC ¥ TRM ¥ CBM; and ATC (non- the same manner for all purposes (e.g.,
operations,138 usage, market firm) = TTC ¥ Firm and Nonfirm granting transmission service to third
operations,139 and topology. Many Commitments + Postbacks of Redirected parties or for the transmission
assert that industry-wide and Unscheduled provider’s own network load).
standardization of the ATC calculation Service ¥ TRM ¥ CBM. In addition, 205. At the October 12 Technical
might not be possible and suggest that TDU Systems requests that the Conference, NERC recognized that the
the Commission consider Commission require standardization of goal of achieving consistency may not
interconnection-wide,140 regional,141 or methods for calculating AFC and mean that a single ATC methodology is
even sub-regional standardization. require NERC to create a formal required.145 NERC explained that
NARUC urges the Commission to definition of AFC. consistency can be achieved with a
facilitate State commission participation 202. PNM–TNMP and Bonneville limited number of methodologies if the
in efforts to reform ATC methodologies express concerns with imposing an requirements of those methodologies are
and calculations on a regional or sub- industry-wide standardized ATC properly coordinated and
regional basis. Conversely, several methodology, arguing that there are too communicated. NERC stated that the
commenters suggest that, if the many variables in the way systems are Standard Drafting Team modifying the
Commission considers allowing use of operated. In its reply comments, PNM– modeling, data, and analysis (MOD)
different ATC calculations, it must TNMP adds that NERC’s ATC standards146 relevant to ATC is
impose a heavy burden on any entity calculation method should take into developing a standard applicable to
seeking to justify a departure from the consideration the need for regional three ATC calculation methodologies:
interconnection-wide or regional ATC variation, and focus on consistency in the rated system path methodology
standard.142 definitions and data inputs. (contract path), the network response
200. Constellation proposes that the WestConnect participants caution that methodology (network ATC), and the
Final Rule establish a rebuttable the replacement of the contract path network response flowgate methodology
presumption that the basic ATC ATC approach used in the Western (network AFC). NERC and the other
calculation formula 143 set forth in Electricity Coordinating Council panelists agreed that the two network
NERC’s current ATC definition be (WECC) with a flowgate methodology methodologies are very similar in
identical within a region and that each could seriously disrupt transmission technique. NERC argued that the
element of the calculation have the service in the Western Interconnection. ultimate goal of ATC-related reforms
same meaning for all transmission 203. PGP states that, although regional should be to standardize definitions.
providers. Williams requests on reply and sub-regional consistency is a good The entire panel agreed that definitions
that the Commission establish an idea, there is no need for the must be consistent and a panelist
Commission to require ‘‘consistent’’ representing Constellation asserted that
136 E.g., Alcoa, Alliance, Ameren, Arkansas ATC methodologies; rather, the broad differences in the core definitions
Commission, Arkansas Municipal, AWEA, Duke, emphasis should be on transparency of of the ATC calculation are neither
E.ON, EEI, ELCON, EPSA, Exelon, LDWP, rational nor explainable.147
MidAmerican, NRECA, NPPD, NERC, Occidental,
the methodologies, inputs, calculations
Powerex, PJM, PPL, Progress Energy, Project for and outputs. Other commenters agree 206. New Mexico Attorney General
Sustainable FERC Energy Policy, Santee Cooper, that the Commission should not require recommends that the Commission allow
Southern, Suez Energy NA, SPP, TAPS, TVA, TDU overall standardization of ATC a utility to waive the requirement to
Systems, TranServ, Tacoma, TANC, WECC, make certain elements of ATC more
WestConnect, and Xcel.
calculations, but instead permit regional
137 E.g. Allegheny, Entergy, Indianapolis Power, differences with respect to certain consistent if the utility can show that it
North Carolina Agencies, and NARUC. aspects of the calculation of ATC.144 EEI is making adequate progress towards
138 E.g. Bonneville, Northwest IOUs, and argues that standardization of ATC developing consistent and transparent
NorthWestern. methodologies would require ATC calculations at the sub-regional
139 E.g. CAISO.
transmission systems to adopt a ‘‘lowest level.
140 E.g. Ameren and Tacoma.
141 E.g. APPA, Barrick Reply, Duke, EEI, Imperial,
common denominator’’ standard in Commission Determination
International Transmission, LDWP, NARUC, order to ensure that system reliability is
not compromised, which would result 207. The Commission adopts the
Nevada Companies, New York Commission,
NRECA, MidAmerican, Occidental Reply, Pinnacle, in a reduction in ATC. EEI suggests that NOPR proposal to require industry-wide
PNM-TNMP, Public Power Council, CREPC, Salt the Commission should direct NERC to
sroberts on PROD1PC70 with RULES

River, Seattle, South Carolina E&G Reply, SPP 145 Transcript of October 12 Technical Conference

Reply, Utah Municipals, and WPS Companies develop ATC calculation standards that at 125–150.
Reply. incorporate regional variations in order 146 MOD standards refers to Modeling, Data, and
142 E.g. TDU Systems and East Texas Cooperatives Analysis Reliability Standards.
Reply. 144 E.g., EEI Reply, NARUC Reply, and Powerex 147 Transcript of October 12 Technical Conference
143 E.g., ATC = TTC ¥ (ETC + CBM + TRM). Reply. at 149–160.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00031 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12296 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

consistency of all ATC components and processes developed for collection of results. It is therefore not necessary to
certain definitions, data, and modeling input data related to transmission require a single industry-wide ATC
assumptions. The Commission also will provider’s own system conditions as calculation methodology. The
require each transmission provider to well as relevant data that model Commission instead concludes that use
include in Attachment C to its OATT neighboring systems’ conditions. We of the ATC calculation methodologies
detailed descriptions for calculating therefore find that it is not the included in reliability standards
both firm and non-firm ATC, consistent methodologies for calculating ATC currently being developed by NERC is
with the requirements of this Final Rule. themselves that create the opportunity acceptable.
The purpose of increasing the for undue discrimination. Instead, we 211. As TDU Systems note, there is
consistency and transparency of ATC find that the potential for undue neither a definition of AFC in NERC’s
calculations is to reduce the potential discrimination stems from two main Glossary nor an existing reliability
for undue discrimination in the sources: standard that discusses the AFC
provision of transmission service, (1) Variability in the calculation of the method. In order to achieve consistency
specifically by reducing the opportunity components that are used to determine in each component of the ATC
for transmission providers to exercise ATC and (2) the lack of a detailed calculation (discussed below), we direct
excessive discretion. We find that the description of the ATC calculation public utilities, working through NERC,
amount of discretion in the existing methodology and the underlying to develop an AFC definition and
ATC calculation methodologies gives assumptions used by the transmission requirements used to identify a
transmission providers the ability and provider.148 The combination of a lack particular set of transmission facilities
opportunity to unduly discriminate of consistency of the components of the as a flowgate. However, we remind
against third parties. In order to ATC calculation coupled with the lack transmission providers that our
minimize this discretion, the Final Rule of transparency leaves customers and regulations require the posting of ATC
requires that all ATC components (i.e., regulators unable to verify ATC values associated with a particular path,
TTC, ETC, CBM, and TRM) and certain calculations and may allow not AFC values associated with a
data inputs, data exchange, and transmission providers to calculate ATC flowgate. Transmission providers using
assumptions be consistent and that the in different ways for different an AFC methodology must therefore
number of industry-wide ATC customers. convert flowgate (AFC) values into path
calculation formulas be few in number, 210. Accordingly, we conclude that (ATC) values for OASIS posting. In
transparent and produce equivalent industry-wide consistency of all ATC order to have consistent posting of the
results. The Commission finds that components (TTC, ETC, CBM, and ATC, TTC, CBM, and TRM values on
these reforms will facilitate TRM) and certain data inputs and OASIS, we direct public utilities,
development of a more coherent and exchange, modeling assumptions, working through NERC, to develop in
uniform determination of ATC. calculation frequency, and coordination the MOD–001 standard a rule to convert
208. We reject requests to establish a of data relevant for the calculation of AFC into ATC values to be used by
single methodology for calculating ATC, ATC will reduce the opportunities for transmission providers that currently
however, for several reasons. It is not the exercise of discretion that may lead use the flowgate methodology.
our intent to require transmission to undue discrimination against 212. The Commission also believes
providers to incur the expense of unaffiliated transmission customers. that further clarification is necessary
developing and adopting a new one- The Commission understands that regarding the calculation algorithms for
size-fits-all software package to firm and non-firm ATC.150 Currently,
NERC currently is developing standards
calculate ATC. We also see little benefit NERC has no standards for calculating
for three ATC calculation methodologies
in requiring a ‘‘lowest common non-firm ATC. We find that the same
(contract or rating path ATC, network
denominator’’ ATC calculator. While a potential for discrimination exists for
ATC, and network AFC).149 If all of the
uniform methodology may result in all non-firm transmission service as for
ATC components and certain data
transmission providers calculating ATC firm service and that greater uniformity
inputs and assumptions are consistent,
in an identical manner, it would also in both firm and non-firm ATC
the three ATC calculation
likely lead to software implementation calculations will substantially reduce
methodologies being finalized by NERC
costs in excess of the resulting benefits. the remaining potential for undue
through the reliability standards
More importantly, we find that the discrimination. Therefore, we direct
potential for discrimination does not lie development process will produce
predictable and sufficiently accurate, public utilities, working through NERC,
primarily in the choice of an ATC to modify related ATC standards by
calculation methodology, but rather in consistent, equivalent, and replicable
implementing the following principles
the consistent application of its 148 For example, utilities A and B would agree for firm and non-firm ATC calculations:
components. that ATC is derived by reducing TTC by the sum (1) For firm ATC calculations, the
209. All ATC calculation of ETC, CBM and TRM, but utility A may define transmission provider shall account
methodologies derive ATC by modeling ETC to include set-asides for contingencies while
only for firm commitments; and (2) for
the system to establish TTC, expressed utility B may not.
149 See Transcript of October 12, 2006 Technical non-firm ATC calculations, the
in terms of contract paths or flowgates,
conference at 125. Thee three methodologies are
and reducing that figure by existing different computational processes to determine a 150 The NERC ATC definition does not
transmission commitments (i.e., ETC), a transmission system’s ATC. The first, contract path, differentiate firm and non-firm ATC from a high
margin that recognizes uncertainties examines TTC for every A-to-B path on the system level generic ATC definition: ‘‘A measure of the
with transfer capability (i.e., TRM), and in concert with all others, reduces ATC by path for transfer capability remaining in the physical
ETC, TRM, and CBM, as appropriate, and produces transmission network for further commercial
a margin that allows for meeting ATC for each path. The second method, net work activity over and above already committed uses. It
generation reliability criteria (i.e., CBM). ATC, uses a simulator to look not at each path, but is defined as Total Transfer Capability less existing
sroberts on PROD1PC70 with RULES

These calculation methodologies are each transmission element (line, substation, etc.,), transmission commitments (including retail
developed based on physical and rule first contingency simulations to establish customer service), less a Capacity Benefit Margin,
ATC on a network basis. The third method, network less a Transmission Reliability Margin.’’ See North
characteristics of the transmission AFC, uses a simulator to examine critical flowgates American Electric Reliability Corporation, Glossary
provider’s transmission system, over a wider area, then requires a second step to of Terms Used in Reliability Standards (February 7,
historical modeling practices, and convert AFC values to particular path ATC values. 2006).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00032 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12297

transmission provider shall account for guidance to NERC and/or NAESB.152 strongly oppose a flexible deadline, and
both firm and non-firm commitments, NRECA suggests that the Commission urge the Commission to establish a firm
postbacks of redirected services, require NERC and NAESB to file the deadline that must be met.156
unscheduled service, and counterflows. results of their processes with the 218. At the October 12 Technical
We understand that these principles are Commission, give all interested parties Conference, NERC informed
currently followed by most transmission an opportunity to comment on the participants that a great deal of progress
providers and believe they should be proposals, and exercise its independent has been made since the proposed
clearly set forth in the ATC-related authority to review, and if necessary, standards developed by the NERC
reliability standards. As described remand the issues or proposals back to
Standard Committee in February 2006
below, each transmission provider’s NERC and NAESB.
were generated to address the
Attachment C must include a detailed 216. Occidental states on reply that it
recommendations made by the Long-
formula for both firm and non-firm does not oppose NERC having a role in
Term AFC/ATC Task Force.157
ATC, consistent with the modified ATC- developing the basic requirements and
However, NERC indicates that a
related reliability standards. standards for ATC. However, Occidental
also urges the Commission to adopt a significant amount of work remains
213. We deny New Mexico Attorney
process similar to that employed in before the standard revisions are
General’s request to grant waiver of the
ATC consistency requirements to developing the Standards for Business considered complete. Since NERC
utilities that can show that they are Practices and Communication Protocols would like to finalize its revised
making adequate progress toward for Public Utilities, which were standards for submittal to the
developing consistent and transparent incorporated by reference into the pro Commission for the summer of 2007,
ATC calculations at the sub-regional forma OATT.153 There, the Commission NERC has established an aggressive
level. While we certainly encourage allowed NAESB’s Wholesale Electric schedule of meetings for drafting which
regional consistency with respect to the Quadrant to develop, with widespread will be coordinated with NAESB.
ATC calculation methodology, we are industry input, business practice 219. PJM outlines several guidelines it
not requiring consistency; therefore a standards that the Commission then suggests the Commission should give to
waiver is not necessary. As discussed in reviewed, adopted and required public NERC and NAESB regarding the
more detail below, any request for utilities to include in their OATTs by standards development process and
waiver from these ATC calculation reference.154 Occidental claims that this recommends that Commission staff
requirements must take place through process would ensure industry input in participate in the standards
the NERC reliability standards the development of the methodology for development process. Williams and
development process as a request for a ATC calculations, as well as EPSA likewise request that the
regional difference, since the ATC Commission review and approval of the Commission provide clear guidance to
requirements will be determined methodology. NAESB to assure efficiency and
through the NERC reliability standards. 217. Several commenters raise timeliness of the process.
concerns that six months may not be 220. Some commenters prefer
b. Process To Achieve Consistency
sufficient time to develop ATC-related engagement of a fully independent
NOPR Proposal reliability standards and business organization to develop standards and
214. In the NOPR, the Commission practices.155 Exelon, MidAmerican and
practices related to ATC.158 EPSA
expressed confidence that the existing NARUC propose that the Commission
strongly urges the Commission to
NERC and NAESB processes were well- grant NERC one year from the date of
require all transmission providers
suited to achieving greater consistency the Final Rule to develop the necessary
outside of RTO areas to contract with an
in ATC calculations. The Commission reliability standards. NARUC agrees
independent entity to develop and/or
therefore proposed to require public with one year, but requests flexibility to
monitor ATC calculations. Although
utilities, working through NERC and assure that the NERC and NAESB
TDU Systems agree with EPSA that
NAESB, to revise the reliability processes can be adequately completed.
vertically-integrated transmission
standards and business practices NERC also states that it expects the
providers that are not subject to the
relating to ATC, consistent with the standards development process, already
independent oversight of an ISO/RTO
guidance provided in the Final Rule, underway, to be finalized with
standards submitted to the Commission retain inherent incentives to
within 180 days after the publication of discriminate against competitors, they
the Final Rule in the Federal Register. prior to the summer of 2007. LPPC
recommends that, within six months of contend that the benefit of independent
Comments the issuance of the Final Rule, NERC be oversight of ATC calculations must be
required to submit a progress report weighed against the cost of that
215. Many commenters support the oversight. Alcoa suggests engaging the
Commission’s proposal directing NERC addressing the status and a work plan
for conclusion within the ensuing six Institute of Electrical and Electronics
and NAESB to develop reliability Engineers (IEEE) instead of the
standards and business practices months. NRECA proposes that the
Commission closely monitor the NERC Commission’s proposal to use NERC
addressing ATC.151 In addition, several and NAESB. APPA opposes that
commenters urge the Commission to be and NAESB process. Some commenters
position. New York Commission
more precise in differentiating between 152 E.g., proposes that regional reliability
EPSA and Williams.
policy and business standards, and urge 153 Citing organizations, rather than NERC,
Standards for Business Practices and
the Commission to provide more Communication Protocols for Pub. Utils., Order No. complete this task and that the ATC
676, 71 FR 26199 (May 4, 2006), FERC Stats. & Regs. calculators be closely coordinated by
151 E.g., Allegheny, APPA, Arkansas Commission, ¶ 31,216 (2006), order on reh’g, Order No. 676–A,
sroberts on PROD1PC70 with RULES

Bonneville, CAISO, Constellation, E.ON, EEI, 116 FERC ¶ 61,255 (2006).


154 Citing id. at P 20. 156 E.g., Utah Municipals and Entegra.
ELCON, Entergy, Exelon, FirstEnergy, LPPC,
157 Citing Long-Term AFC/ATC Task Force Final
MidAmerican, New York Commission, NERC, 155 E.g., Constellation, Duke, EEI, Exelon, LPPC,

Northeast Utilities, Project for Sustainable FERC MidAmerican, NARUC, Northwest IOUs, Public Report (Revised April 14, 2005), available at
Energy Policy, PNM–TNMP, Santa Clara, Southern, Power Council, CREPC, Southern, TDU Systems, http://www.nerc.com/∼filez/ltatf.html.
Tacoma, TransServ, and Utah Municipals. and WestConnect. 158 E.g., Alcoa, Fayetteville, and MISO.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00033 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12298 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

ISOs and RTOs.159 PJM contends on owners, they can be addressed on a are not based on physical transmission
reply that New York Commission’s case-by-case basis. reservations.162
proposal for coordination of ATC 223. With respect to a timeline for 226. MISO argues that AFC
between ISOs and RTOs has been completion, the Commission concurs calculation methodologies should be
fulfilled at least between PJM and its with NERC that a significant amount of established via the RTO stakeholder
neighbors, arguing that New York process, not NERC. In its reply
work remains to be done on ATC-related
Commission’s proposal is unnecessary comments, Exelon expresses
reliability standards development. We
and would add a layer of bureaucracy disagreement with MISO and states that
also agree with the many commenters
and cost. TAPS expresses concern with there must be one standard for ATC
who state that the NOPR’s proposed six-
the Commission proposal to use NERC calculations, not several methods based
and encourages the Commission to be month timeline is too short for such a
on the desires of different sets of
precise in its direction to NERC to complex assignment. Although NERC stakeholders. Several commenters also
accomplish the needed objective. projects that it may be able to complete believe that ISOs/RTOs should not be
the process by the summer of 2007 exempt from the requirements for
Commission Determination (which is approximately six months consistent and transparent ATC
221. The Commission directs public from the date of the Final Rule), we calculations.163
utilities, working through NERC and believe NERC should have additional 227. EEI asks the Commission to
NAESB, to modify the ATC-related flexibility with respect to its timeline. require all municipal and other non-
reliability standards and business Accordingly, we direct public utilities, public utility transmission providers to
practices in accordance with specific working through NERC, to modify the adhere to any requirement for consistent
direction provided in this Final Rule. As ATC-related reliability standards within and transparent ATC/AFC calculation.
we explain above, the development of a 270 days after the publication of the In its view, applying the ATC-related
more coherent and uniform Final Rule in the Federal Register. We reforms to these nonjurisdictional
determination of ATC across a region also direct public utilities to work entities would recognize the
will help limit the potential for undue through NAESB to develop business interconnected nature of the
discrimination in the calculation of practices that complement NERC’s new transmission grid. EEI argues that
ATC. The Commission concludes that reliability standards within 360 days greater transparency and consistency in
the NERC reliability standards after the publication of the Final Rule in the provision of transmission service
development process and the NAESB the Federal Register. Finally, we direct would be frustrated if all transmission
business practices development process NERC and NAESB to file, within 90 providers do not have to comply. Other
are the appropriate forums for days of publication of the Final Rule in commenters reply that EEI’s concerns
developing this consistency. the Federal Register, a joint status are unfounded and describe an example
222. NERC has been certified as the report on standards and business in the WECC region, where the
ERO and, as such, has been found to practices development and a work plan methodologies and practices regarding
have the ability to develop reliability for completion of this task within the ATC calculations are developed by
standards through processes with timeframe established above.160 representatives from all affected
reasonable notice and opportunity for
transmission providers, utilities, and
public comment. NERC’s processes are c. Applicability to ISOs, RTOs, and
market participants, including
open and provide due process as well as Non-Public Utility Transmission
nonjurisdictional entities.164
a balance of interests, while assuring Providers
228. LPPC contends that the NERC
independence from users and owners reliability standards related to ATC
NOPR Proposal
and operators of the bulk-power system.
calculation will already be applicable to
Moreover, NAESB has a long history of 224. The Commission did not both public and non-public utilities.
developing standard business practices specifically address the application of LPPC argues that NERC standards, when
for the electric industry, on which the the ATC-related reforms proposed in the final, will be filed with the Commission,
Commission has relied in various NOPR to ISOs and RTOs or non-public become part of the ERO’s mandatory
contexts. While other entities may bring utility transmission providers. reliability standards and will be fully
certain benefits, commenters have not
Comments applicable to otherwise
demonstrated the superiority of IEEE, a
nonjurisdictional entities. As a result,
regional reliability organization, or a
225. ISOs and RTOs believe that the the ATC standards will be applicable to
particular RTO over NERC and NAESB.
Once components of ATC are made Commission should not require and enforceable upon all transmission
consistent and ATC calculation wholesale revisions of RTO and ISO owners, whether or not the transmission
methodologies are made transparent, tariffs, even on such issues as ATC owner has an OATT.
opportunities for discretion that may standards.161 They caution that many Commission Determination
lead to undue discrimination in the regional grid operators’ tariffs contain
nonconforming provisions that were the 229. We discuss the applicability of
calculation of ATC will be sufficiently the Final Rule to ISOs and RTOs in
eliminated to invalidate the need for the product of extensive debate, litigation
and settlements. In addition, some section IV.C.2 above. With respect to the
creation of independent entities to
commenters point out that concern application of the ATC requirements of
oversee that calculation. To the extent
about ATC calculations is a non-issue in this Final Rule to municipal and other
that, even following the adoption of
many ISO/RTO regions because non-public utility transmission
these reforms, customers have
transmission services in those regions providers, we likewise note that the
complaints regarding the calculations
applicability of the rule generally to
performed by individual transmission
such entities is addressed in section
sroberts on PROD1PC70 with RULES

160 NAESB’s work plan for developing business

159 If
ISOs and RTOs cannot perform the practices related to other reforms adopted in this
162 E.g., ISO/RTO Council, ISO New England, and
coordination function, New York Commission Final Rule should be filed separately, as requested
suggests the establishment of a Transmission in Section IV.C.1. Pennsylvania Commission.
161 E.g., PJM and MISO Transmission Owners, 163 E.g., NRECA and TDU Systems.
Oversight Center to oversee the calculation of ATC
within and between ISOs and RTOs. SPP Reply. 164 E.g., Lassen and Public Power Council.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00034 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12299

IV.C.3. We note here, however, that certainty that it provides for available Comments
such entities will be required to comply capacity, suggesting that the contract
235. Entergy supports the
with reliability standards developed path paradigm facilitates long-term
development of consistent practices for
under FPA section 215. As LPPC bilateral contracting.
determining transfer capability while
acknowledges, once these reliability
Commission Determination maintaining flexibility to recognize
standards are approved they will
232. In this rulemaking, the regional and system-specific differences.
become part of the ERO’s mandatory
Commission is requiring consistency in APPA agrees that the calculation of
reliability standards and, thus, will be
applicable to and enforceable upon all the determination of ATC with the TTC/TFC is, for the most part, a regional
transmission owners, whether or not the purpose of improving a customer’s calculation. APPA states that the
transmission owner has adopted the ability to receive transmission service Western Interconnection and ERCOT
OATT. on a non-discriminatory basis. These use their own methods, which are
reforms are fully consistent with generally applied system-wide. APPA
d. Alternatives to ATC Consistency operational reality, and we decline to believes that more standardization and
Comments mandate the security constrained coordination of TTC/TFC among
economic dispatch alternative proposed transmission providers in the Eastern
230. Some commenters contend that Interconnection, where two primary
the NOPR is focused too narrowly on by Chandley-Hogan. Chandley-Hogan
argue that it would be unduly methods are used to calculate TTC or
simply improving the consistency and TFC, would be desirable because of
transparency of ATC determinations discriminatory to exclude third-party
generators from an efficient dispatch to reported loop-flow problems in the
and suggest that a focus on balancing (or Eastern Interconnection.
dispatch) services and how those are serve native load and therefore a
centralized, bid-based market is 236. In order to increase transfer
priced would allow the Commission to
required. We agree that a centralized capability from existing facilities,
avoid the pitfalls inherent in the ATC
bid-based market can benefit customers AWEA proposes that the Commission
approach.165 In their view, such an
and, over a large region, can manage direct NERC, as part of developing
approach would eliminate much of the
congestion efficiently. We do not consistent ATC standards, to investigate
difference between how third parties are
believe, however, that mandating that the impact of implementing dynamic
treated in RTO versus non-RTO systems.
result—essentially requiring that Day 2 line ratings in TTC/TFC calculations
Constellation encourages the
RTOs be adopted in every region of the and propose protocols to effectuate such
Commission to consider requiring
country—is necessary to remedy undue a program. In response to AWEA’s
transmission providers to implement
discrimination in the provision of proposal, commenters state that if the
all-inclusive, security constrained
transmission service. The concern Commission decides to provide
economic dispatch processes. In reply
raised by Chandley-Hogan is not related guidance to NERC with regard to
comments, Chandley-Hogan argue that
solely to the nondiscriminatory use of dynamic line ratings, the Commission
the Commission’s ATC-related
the transmission system. It also should encourage NERC to develop
proposals in the NOPR confuse how
implicates the purchase decisions of standards with regard to dynamic line
transmission service is actually transmission providers on behalf of ratings in the operating horizon, but not
provided in most of the United States their native load customers. These in the planning horizon.167
and, as a result, the Commission’s decisions are regulated primarily by the
analysis of perceived problems in the states and we decline to take generic Commission Determination
calculation of ATC is flawed, action in this rulemaking to reform the 237. The Commission adopts the
inconsistent with network realities and processes by which those purchases are NOPR proposal and directs public
the laws of physics, and incompatible made. utilities, working through NERC, to
with reliable operations.
231. Contrary to the above claims, e. ATC Components develop consistent practices for
some commenters find that ATC calculating TTC/TFC. We direct public
233. The next several sections address utilities, working through NERC, to
provides a functionally useful measure components of ATC that must be made
of available capacity and has certain address, through the reliability
consistent to remove the potential for standards process, any differences in
advantages over alternative models.166 undue discrimination, namely TTC/
These commenters argue that the factual developing TTC/TFC for transmission
TFC, ETC, CBM, and TRM. provided under the pro forma OATT
record does not support conclusions
that bid-based, marginal cost dispatch (1) Total Transfer Capability (TTC)/ and for transfer capability for native
by a third party is inherently more Total Flowgate Capability (TFC) load and reliability assessment studies.
efficient or inherently more likely to NOPR Proposal 238. We acknowledge that reliability
remedy undue-discrimination than the regions have historically calculated
234. The Commission proposed to transfer capability using different
OATT model, and cannot overcome the direct public utilities, working through
considerable real world obstacles to approaches, and we agree that regional
NERC, to develop consistent practices differences should be respected.168
pure economic redispatch, including for calculating total transfer/flowgate
overlapping and dynamic constraints, However, as already discussed above
capability (TTC/TFC). Although the regarding ATC, the TTC requirements
and the physical realities in the Western NERC reliability regions have
Interconnection that often limit the pool will be determined by the NERC
historically calculated transfer reliability standards and any request for
of resources that can be redispatched to capability using different approaches,
solve constraints. LPPC contends that a regional difference from the reliability
the Commission expressed its view that standards must take place through the
the principal advantage of ATC is the guidelines for a common approach to NERC process.
sroberts on PROD1PC70 with RULES

calculating transfer capability are


165 E.g., Chandley-Hogan, EPSA, PJM, San Diego
achievable. The Commission also stated
G&E, and Transparent Dispatch Advocates Reply. 167 E.g.,
MAPP and MidAmerican.
166 E.g., APPA, CMUA, CPA, Duke, EEI, Entergy, that the criteria used for identifying 168 Forexample, WECC has a documented open
LPPC, Public Power Council, Sacramento, and flowgates and determining TFC could be process for establishing TTC for the Western
WestConnect Reply. more consistent. Interconnection.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00035 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12300 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

239. With respect to AWEA’s proposal in ETC appear to be candidates for reservations that have the same point of
regarding implementing dynamic line business practices rather than reliability receipt (POR) (generator) but different
ratings in TTC/TFC calculations, the standards. point of delivery (POD) (load), for the
Commission finds that this proposal is 242. Williams proposes that ETC be same time frame, should not be modeled
outside the scope of this rulemaking as the subject of an expanded definition in the ETC calculation simultaneously if
it does not appear to relate to undue and that native load growth projections their combined reserved transmission
discrimination in transmission service be based on verifiable data provided by capacity exceeds the generator’s
and, in any event, would best be an independent source. It also states nameplate capacity at POR. This will
addressed in the first instance through that transmission providers should be prevent overly unrealistic utilization of
the NERC reliability standards required to update ATC based on each transmission capacity associated with
development process, addressing confirmed transmission service power output from a generator
reliability standards that regulate reservation (point-to-point or network, identified as a POR. We direct public
facility ratings. If AWEA desires to firm or non-firm). utilities, working through NERC, to
pursue this proposal, it should propose Commission Determination develop requirements in MOD–001 that
an appropriate dynamic line rating lay out clear instructions on how these
standard within the ERO’s reliability 243. To achieve greater consistency in reservations should be accounted. One
standards development process. ETC calculations and further reduce the approach that could be used is
potential for undue discrimination, the examining historical patterns of actual
(2) Existing Transmission Commitments Commission adopts the NOPR proposal reservation use during a particular
(ETC) and directs public utilities, working season, month, or time of day.
NOPR Proposal through NERC and NAESB, to develop
a consistent approach for determining 246. We agree with NERC that some
240. In the NOPR, the Commission the amount of transfer capability a elements of ETC are candidates for
expressed its view that the lack of transmission provider may set aside for business practices rather than reliability
consistency in modeling of existing its native load and other committed standards. Accordingly, we direct
transmission commitments (ETC) uses. We expect that NERC will address public utilities, working through
resulted in excessive discretion in ETC through the MOD–001 reliability NAESB, to develop business practices
determining how much capacity a standard rather than through a separate necessary for full implementation of the
transmission provider sets aside for reliability standard.169 By using MOD– developed MOD–001 reliability
native load, including its network 001, the ETC calculation can be adjusted standard.
customers. The Commission therefore to be applicable to each of the three 247. We decline to adopt Williams’s
proposed the development of a ATC methodologies under development proposal to require that native load
consistent methodology for determining by NERC. growth be based on the verifiable data
the capacity needed and set aside for 244. In order to provide specific provided by an independent source.
native load usage. The Commission also direction to public utilities and NERC, Through increased consistency and
proposed that accounting for we determine that ETC should be transparency of ATC determinations,
transmission reservations in an ATC/ defined to include committed uses of including requirements for posting
AFC calculation be more consistent. The the transmission system, including (1) additional data, third parties will be
Commission further proposed that Native load commitments (including able to verify the accuracy of ETC,
public utilities, working through NERC, network service), (2) grandfathered helping to eliminate opportunities for
establish and specifically identify the transmission rights, (3) appropriate undue discrimination.
reservations to be used in determining point-to-point reservations,170 (4)
ETC. rollover rights associated with long-term (3) Capacity Benefit Margin (CBM)
firm service, and (5) other uses NOPR Proposal
Comments
identified through the NERC process.
241. Entegra and PGP support ETC should not be used to set aside 248. In the NOPR, the Commission
increasing consistency in determining transfer capability for any type of proposed three options to address the
ETC. APPA agrees that it would be planning or contingency reserve, which CBM component of ATC: (1) Have NERC
helpful to standardize the method of are to be addressed through CBM and develop clear standards for how the
accounting for ETC on an TRM.171 In addition, in the short-term CBM value should be determined,
interconnection-wide basis. APPA ATC calculation, all reserved but allocated across transmission paths, and
states, however, that flexibility might be unused transfer capability (non- used; (2) charge an entity for which
required among the interconnections. scheduled) shall be released as non-firm transfer capability has been set aside to
TDU Systems requests that the ATC. meet generation reliability criteria a
Commission define with specificity the 245. We agree with TDU Systems that separate rate for this service; or (3)
types of transmission service requests or inclusion of all requests for eliminate CBM and require an entity
scheduled transmission transactions transmission service in ETC would reserving ATC to meet generation
that should be included in ETC and likely overstate usage of the system and reserve (currently through CBM) to
agrees with the Commission that understate ATC. We therefore find that designate network resources on the
inclusion of all requests for other side of the interface and make an
transmission service in ETC is likely to 169 The purpose of MOD–001 is to promote the associated transmission service
overstate usage of the system, thus consistent and uniform application of transfer reservation.
capability calculations among the transmission
understating ATC. It suggests that the system users. Comments
Commission develop a bright line 170 By ‘‘appropriate,’’ we mean that reservations
sroberts on PROD1PC70 with RULES

method for calculating ETC. NERC notes accounted for under ETC depend on the firmness 249. Numerous commenters support
that its proposed reliability standards and duration of the reservation. The specific the Commission’s proposed option one,
characteristics should be developed in the requiring NERC to develop clear
would define ETC and require reliability standard.
appropriate documentation. NERC adds, 171 TRM also includes such things as loop flow standards for how the CBM value
however, that the components included and parallel path flow. should be determined, allocated across

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00036 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12301

transmission paths, and used.172 They not all transmission providers set aside Commission Determination
believe that CBM ensures the ability to capacity through CBM for their native 256. The Commission concludes that
import needed power to support system load; to the extent that a transmission it is appropriate to allow LSEs to retain
conditions. TVA argues that option two provider does not set aside CBM, there the option of setting aside transfer
would be costly and may cause some should be no obligation to allow other capability in the form of CBM to
systems to forego CBM, thereby LSEs to do so. Duke proposes that the maintain their generation reliability
jeopardizing service to native load Commission should continue to permit requirement. We agree with commenters
customers. PJM states that option two is such flexibility. that, without CBM, LSEs would have to
irrelevant in PJM since PJM ‘‘totals’’ 253. NERC takes no position on CBM, increase their generation reserve
reservations and decides when CBM can expecting that the issue can be settled margins by contracting for generation
be used. Supporters of option one through the NERC and NAESB capacity, which may result in higher
criticize option three, elimination of Procedure for Joint Standards costs without additional reliability
CBM, as costly and a threat to Development and Coordination and benefits. We require, however, the
transmission system reliability. through other open forums. development of standards for how CBM
Southern, Progress Energy, and PJM 254. TAPS suggests that the is determined, allocated across
emphasize that, without CBM, the LSEs Commission ensure that all LSEs have transmission paths, and used in order to
would need to increase their reserve both access to CBM to meet their limit misuse of transfer capability set
margin by contracting for additional reserve-sharing needs and meaningful aside as CBM. Transmission providers
generation capacity, costing millions of input into how much CBM is reserved. also must reflect the set-aside of transfer
dollars. In addition, Ameren and TVA To do so, TAPS recommends the capability as CBM in the development
believe that CBM elimination will creation of a reserve-sharing group made
increase the likelihood of widespread of the rate for point-to-point
up of the transmission provider and transmission service to ensure
blackouts in emergency conditions. LSEs it serves. It argues that this would
250. At the October 12 Technical comparable treatment for point-to-point
remove reservation decisions from the to customers.
Conference, Exelon supported option sole discretion of the vertically-
two proposing a charge for CBM. Exelon 257. The Commission therefore
integrated transmission provider and adopts a combination of the NOPR
contended that, in a rate-making
instead have them made by the options one and two, and declines to
context, there would be an increase in
transmission provider/LSE reserve- adopt option three. First, we require
the divisor of the rate by the amount of
sharing group, subject to dispute public utilities, working through NERC
CBM set-aside which would lower the
resolution at the Commission. All LSEs and NAESB, to develop clear standards
point-to-point charge. Consequently,
would be invited to participate in the for how the CBM value shall be
those not benefiting from the CBM set-
studies as well as review the results and determined, allocated across
aside effectively would be paying a
assumptions. Moreover, once a regional transmission paths, and used. We
lower charge.
251. Constellation and Morgan planning process is established, as understand that NERC has already
Stanley support the elimination of CBM proposed in the NOPR, TAPS begun the process of modifying several
and argue that CBM and TRM are often recommends that the regional planning of the CBM-related reliability standards
used interchangeably and result in group be required to approve the CBM and that the drafting process is a joint
duplicative transmission set-asides. reservation as well. project with NAESB. Second, we require
They also argue that there is no 255. Williams suggests that a transmission providers to reflect the set-
compelling need for CBM in the current transmission provider must designate aside of transfer capability as CBM in
liquid market environment. In addition, network resources and reserve firm the development of the rate for point-to-
Morgan Stanley states that LSEs transfer capability on both sides of the point transmission service.
affiliated with the transmission provider control area transmission interface in 258. We note that there is broad
should not be allowed to use CBM for order to reserve CBM. Duke replies that, concern that eliminating CBM (option
long-term planning purposes as an although some commenters prefer three) would impose extraordinary costs
excuse to avoid undertaking needed eliminating CBM and replacing it with for meeting generation reliability
resource additions or to conceal the true additional designated network criteria, which then may lead utilities to
cost of their load serving functions. resources, CBM is the preferable option reduce their generation reliability
Furthermore, the Commission should because it is less costly. Duke further requirement to avoid the cost increase.
not be distracted by assertions that such argues that the choice is between setting We believe that the reforms reflected in
long-term arrangements are necessary aside both additional transmission and combining options one and two are
for ‘‘reliability,’’ when in fact they are generation capacity to deal with sufficient to remedy undue
simply a way to protect the economic emergencies (the additional designated discrimination and that the adverse
interests of a particular entity. network resource approach) versus effects associated with option three are
252. Duke replies that Constellation setting aside only transmission (the neither warranted nor required. We
mistakenly believes that CBM is CBM approach). Having to procure reject Morgan Stanley’s call for CBM
currently only available to a additional designated network resources elimination on the grounds that CBM is
transmission provider’s native load to keep in reserve reduces one of the acting as a disincentive to undertake
when, in fact, for those transmission main benefits of interconnected needed generation resource additions. It
providers that establish CBM, it should operations. Duke argues that eliminating would be inappropriate for the
be established for the load of all LSEs CBM would drive up costs for network Commission to restrict the ability of an
in the control area. Duke contends that customers, as they would have to LSE to determine how best to meet its
procure additional generation and generation reliability criteria.
sroberts on PROD1PC70 with RULES

172 E.g., Allegheny, Ameren, EEI, Duke, NRECA, transmission resources. EEI adds that 259. To ensure CBM is used for its
TVA, APPA, Bonneville, EPSA, FirstEnergy, such a proposal may result in increased intended purpose, CBM shall only be
Indianapolis Power, MidAmerican, Pinnacle, PJM,
PGP, PNM–TNMP, Public Power Council,
LSE reserve requirements, over-building used to allow an LSE to meet its
Sacramento, Seattle, South Carolina E&G, TANC, of generation supply, and a reduction, generation reliability criteria. Consistent
TDU Systems, and Wisconsin Electric. rather than an increase, in ATC. with Duke’s statement, we clarify that

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00037 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12302 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

each LSE within a transmission FPA section 205 rate filing as part of its supports the Commission’s proposal,
provider’s control area has the right to initial ATC-related compliance filing. pointing out that the implementation of
request the transmission provider to set These filings, which may be submitted the current NERC standards definition
aside transfer capability as CBM for the within 120 days after the publication of for TRM and CBM could result in its
LSE to meet its historical, State, RTO, or the Final Rule in the Federal Register, double-counting, which must be
regional generation reliability criteria may be limited to the rate design change eliminated. APPA members in the
requirement such as reserve margin, loss only, i.e., they will not require the Western Interconnection suggest that
of load probability (LOLP), the loss of submission of cost of service data or a regional variations be permitted. They
largest units, etc. revision to the transmission provider’s also note that the modeling methods
260. We direct public utilities, revenue requirement. used by WECC and its sub-regions may
working through NERC, to develop clear 264. With respect to TAPS’ proposal differ from those used in the Eastern
requirements for allocating CBM over that all LSEs should be allowed to use Interconnection. For example, they
transmission paths and flowgates. While CBM to meet their reserve-sharing contend that uncertainties associated
we do not mandate a particular needs, we believe that TRM is the with transmission maintenance
methodology for allocating CBM to appropriate category for that purpose, schedules that are driven by hydro-
paths and flowgates, one approach not CBM. We reject TAPS’ proposal to production curves will seasonally affect
could be based on the location of the use CBM for the LSE’s reserve-sharing TRM set-asides on certain transfer
outside resources or spot market hubs needs, but instead make TRM available paths. PJM believes that the TRM
that an LSE has historically relied on for the incremental power flows methodology should be consistent at the
during emergencies resulting from an resulting from reserve sharing, as regional reliability organization level.
energy deficiency. explained next. PJM also contends that TRM should be
261. We concur with TAPS’ proposal 265. As we are rejecting option three, coordinated, exchanged and respected
that all LSEs should have access to CBM which would have required the on external flowgates and that the
and meaningful input into how much reservation of transfer capability rather concept of a maximum TRM, by
transfer capability is set aside as CBM. than using CBM, we also reject percentage, should be adopted in the
In the transparency section below, we Williams’ proposal to require the NERC standards.
provide detailed requirements regarding reservation of transfer capability on both 268. Consistent with its position on
availability of documentation used to sides of an interface for CBM. CBM, TAPS proposes that TRM set-
determine the amount of transfer asides should be conditioned on
(4) Transmission Reserve Margin (TRM)
capability to be set aside as CBM and inclusive reserve-sharing arrangements,
the posting of CBM values and NOPR Proposal with the reservations determined by the
narratives. Access to this documentation 266. Finally, the Commission reserve-sharing group, subject to dispute
will enable LSEs to validate how much proposed the development of reliability resolution before the Commission (and,
transfer capability is set aside as CBM standards MOD–008 and MOD– eventually, approval by joint planning
on each system and provide them with 009 173that specify the uncertainties that groups).
information to question whether the set- TRM could be used to accommodate, 269. PNM–TNMP suggests that the
aside is consistent with the reliability which could include (1) Load forecast Commission consider definitions to
standards and this Final Rule. and load distribution error, (2) include the following clarification taken
262. Concerning TAPS’ proposal to variations in facility loadings, (3) from WECC procedures on ATC: ‘‘If the
remove the reservation decision from uncertainty in transmission system limitation on the use of TRM to 59
the sole discretion of transmission topology, (4) loop flow impact, (5) minutes would force a Transmission
providers, we determine that LSEs variations in generation dispatch, Provider to set aside unnecessary CBM
should be permitted to call for use of including intermittent resources, (6) on the same path as the TRM, that
CBM, if they do so pursuant to automatic sharing of reserves, and (7) Transmission Provider may utilize the
conditions established in the reliability other uncertainties identified through TRM beyond the 59 minutes.’’ 176 PNM–
standards development process. We the NERC reliability standards TNMP states that this would allow the
direct public utilities working through development process. transmission provider to maximize the
NERC to modify the CBM-related ATC by not needlessly setting aside
standards to specify the generation Comments
twice the amount of transmission (TRM
deficiency conditions during which an 267. Most commenters agree that the and CBM) than is necessary for
LSE will be allowed to use the transfer existing definitions for TRM require reliability.
capability reserved as CBM. In addition, clarification.174 Commenters also agree 270. Nevada Companies argue that no
we direct that transmission set aside as that NERC should be required to new standards are required for TRM and
CBM shall be zero in non-firm ATC develop clear standards for the that any further action would be
calculations. Finally, we order public determination of TRM, including burdensome. They explain that NERC
utilities to work with NAESB to develop specifying the criteria used in the has a well-established definition that
an OASIS mechanism that will allow for determination of TRM.175 PNM–TNMP does not require further clarification. In
auditing of CBM usage. their view, all that is required is a
263. We also require transmission 173 The MOD–008 and MOD–009 reliability
complete statement, to be posted on
providers to design their transmission standards document regional TRM methodologies
OASIS, regarding the transmission
charges to ensure that the class of and procedures for verifying TRM values.
174 E.g., Allegheny, APPA, EEI, EPSA, Exelon, provider’s application of TRM. NERC
customers not benefiting from the CBM
LPPC, MidAmerican, NRECA, Northwest IOUs,
set-aside, i.e., point-to-point customers, NorthWestern, Occidental, Pinnacle, Powerex, generation dispatch; TRM for the same scenarios;
do not pay a transmission charge that PNM–TNMP, PPL, PJM, PPM, and WestConnect. and CBM.
sroberts on PROD1PC70 with RULES

includes the cost of the CBM set-aside. 175 Exelon recommends that the following factors 176 Citing WECC Rocky Mountain Operating and

To do this, transmission providers are should be the same for the planning process and Planning Group, Determination of Available
ATC/AFC process to achieve consistency: base case Transfer Capability within the Western
required to submit redesigned flows, reservation impacts, TRM and CBM Interconnection, June 2001, page 9, http://
transmission charges that reflect the forecasted to occur simultaneously; counterflows; www.wecc.biz/modules.php?op=modload&name=
CBM set-aside through a limited issue positive impacts resulting from reservations and Downloads&file=index&req=getit&lid=1035.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00038 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12303

comments that the existing reliability percentage. This is a relatively simple for all uses. The Commission stated its
standards for TRM will be revised to method and, if adopted as the reliability view that consistency is necessary to
require clear documentation of the standard’s method, should not restrict a ensure non-discriminatory treatment by
calculation of TRM. It also adds that the transmission provider from using a eliminating a transmission provider’s
revised standard will make various TRM more sophisticated method that may ability to use discretion to the
components mandatory to achieve more allow for greater ATC without reducing disadvantage of competitors. The
consistency across methodologies. overall reliability. Commission proposed three specific
271. Santee Cooper urges the 276. Because of the operational areas for reform.
Commission to ensure that service to characteristics of the uncertainties that 279. First, the Commission proposed
native load and transmission system are to be accommodated using TRM, to require public utilities, working
reliability will not be compromised as and their aggregate impact on reliable through NERC, to modify the ATC-
the Commission seeks greater levels of operation, we require each transmission related standards to incorporate a
consistency in the calculation of ATC. It provider to calculate, and allocate on requirement for periodic validation and
states that the Commission also must be the paths and flowgates, the aggregate modification of models to ensure that
cognizant of the importance of TRM in TRM value for all LSEs within its area. they are up to date.178 The Commission
the provision of service to native load. We support NERC’s plan to revise stated that the models should be
existing reliability standards for TRM to updated and benchmarked to actual
Commission Determination
require clear documentation of the TRM events.
272. The Commission adopts the calculation, as we expect the TRM value 280. Second, the Commission
NOPR proposal and requires public to be supported and fully transparent. In proposed that, to the maximum extent
utilities, working through NERC, to addition, we require each transmission practicable, the same data must be used
complete the ongoing process of provider to make available all by the transmission provider to
modifying TRM standards MOD–008 underlying documentation, including determine short- and long-term ATC as
and MOD–009. We understand that the work papers and load flow base cases, those used in system operation and
standard drafting process is underway used to determine TRM, to any planning studies, respectively.
as a joint project with NAESB. transmission customer and LSE within 281. Third, the Commission proposed
273. The Commission also adopts the its control area, subject to a that public utilities, working through
NOPR proposal to establish standards confidentiality agreement,177 if NERC, develop assumptions for use in
specifying the appropriate uses of TRM necessary. We agree with Santee ATC determinations and that the
to guide NERC and NAESB in the Cooper’s comments that the assumptions remain consistent among
drafting process. Transmission Commission must ensure that service to transmission providers to the maximum
providers may set aside TRM for (1) native load and system reliability are extent practicable. The Commission
Load forecast and load distribution not compromised. We believe that our indicated that short- and long-term ATC
error, (2) variations in facility loadings, requirement for public utilities to work calculations should be developed using
(3) uncertainty in transmission system through NERC satisfies such concerns. consistent assumptions regarding
topology, (4) loop flow impact, (5) 277. With respect to the proposal to representative load levels, generation
variations in generation dispatch, (6) permit regional variations in the TRM dispatch, transmission reservations and
automatic sharing of reserves, and (7) calculation methodology, we reiterate counterflows, in addition to any other
other uncertainties as identified through our position stated above that any modeling assumptions identified by
the NERC reliability standards request for regional difference from the NERC. The Commission further
development process. Because load, applicable reliability standards must proposed that there should be a
facility loading and other uncertainties take place through the NERC reliability consistent approach to the modeling of
constantly deviate, we will not require standards development process. With load levels, a method established for
that TRM set aside capacity be set at respect to TAPS’ proposal regarding determining which generators should be
zero in the non-firm ATC calculation. In reserve sharing groups, we clarify that, modeled in service (including guidance
other words, we will not require transfer to the extent transfer capability is on how independent generators should
capability that is set aside as TRM to be needed for transmission of shared be considered), consistency in the
sold on a non-firm basis. We find that reserves, this is included under TRM. simulation of power flows from points
clear specification in this Final Rule of However, as noted previously in the of receipt to delivery when sources are
the permitted purposes for which CBM discussion, we are not mandating unknown, and consistency in the
entities may reserve CBM and TRM will the use of reserve sharing groups. manner in which ATC/AFC reservations
virtually eliminate double-counting of are accounted for. The Commission
TRM and CBM. f. Modeling, Assumptions and Input stated that the model for long-term ATC
274. We will not adopt PNM-TNMP’s Data should include, to the maximum extent
proposal regarding use of set aside NOPR Proposal practicable, the same assumptions
transfer capability as TRM beyond 59 regarding new transmission and
minutes, rather than converting it to 278. The Commission’s proposal with
regard to modeling, assumptions and generation facilities additions and
CBM. Our proposal is to separate retirements as those used in planning
transfer capability set asides as either data inputs was based on a principle
that there should be consistency among for expansion.
CBM or TRM without regard to duration 282. The Commission noted that the
of use of the set aside. Therefore, such transmission providers and between
what the transmission provider does for proposal is not intended to change the
a clarification is not necessary. manner in which native load is served
275. In addition, we direct public its operation and expansion planning
utilities, working through NERC, to for native load and what it does in 178 The Commission noted that this would
determining short and long-term ATC
sroberts on PROD1PC70 with RULES

establish an appropriate maximum include review of load flow base cases, short circuit
TRM. One acceptable method may be to data, transient and dynamic stability simulation
177 The agreement may appropriately restrict the data, contingency (files should contain information
use a percentage of ratings reduction, sharing of sensitive information with customer on special protection schemes and remedial action
i.e., model the system assuming all personnel that are involved only in transmission plans) subsystem and monitoring files, and
facility ratings are reduced by a specific functions, as opposed to merchant functions. production cost models.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00039 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12304 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

and sought comment on whether (and, operations and service request their boundaries.182 PJM states that such
if so, how) this proposal would affect evaluations should generally be based issues are best left to the joint
service to native load customers. on similar data and procedures, but stakeholder processes and the resulting
argues that due to changes in system joint and common market initiatives.
Comments 289. In response to the Commission’s
configuration, facilities included in
283. Commenters generally discuss transmission plans are often not needed inquiry as to how standardizing the
consistency of data, assumptions and at all and thus are not constructed. modeling assumptions and data would
modeling together so we in turn do the Therefore, Entergy proposes that the affect native load, commenters generally
same. Many commenters support the Commission allow NERC to determine state that standardization of ATC
proposals for consistency in data, the circumstances under which modeling assumptions would increase
assumptions and/or modeling.179 Others differences between models would be comparability of service to LSEs and
support flexibility or regional appropriate. enhance the ATC methodology and its
variation.180 A few commenters oppose 286. Southern asks for clarification on nondiscriminatory application to grid
specific aspects of the overall what the Commission intends by utilization.183
proposal.181 proposing that modeling assumptions be
284. TDU Systems and Sacramento Commission Determination
consistent in the context of TTC
express support for the Commission’s assessments. Southern explains that, as 290. The Commission directs public
proposal to require public utilities, the Commission has recognized, the utilities, working through NERC, to
working through NERC, to develop inevitable changes in system conditions modify the reliability standards MOD–
modeling assumptions for use in between different time horizons (e.g., 010 through MOD–025 184 to incorporate
calculating ATC that are consistent with real-time and planning and operations) a requirement for the periodic review
those used to plan the operation and would render this approach unreliable and modification of models for (1) Load
expansion of the transmission system. because load levels, dispatch flow base cases with contingency,
Xcel, however, would have the arrangements, reservations, and outages subsystem, and monitoring files, (2)
Commission go further. Xcel cannot be the same over significantly short circuit data, and (3) transient and
recommends that the Commission different time horizons. dynamic stability simulation data, in
enhance its proposal by establishing a 287. Supporting regional differences, order to ensure that they are up to date.
date certain for transmission providers Bonneville contends that calculating This means that the models should be
in the Western Interconnection to be ATC for a hydroelectric system requires updated and benchmarked to actual
required to account for impacts of loop different inputs and modeling events. We find that this requirement is
flows when processing transmission assumptions than are appropriate for essential in order to have an accurate
service requests and calculating ATC. thermal-based systems. Bonneville simulation of the performance of the
Xcel suggests that NERC be directed to explains that non-power constraints grid and from which to comparably
develop standards for evaluation of placed on hydroelectric projects that calculate ATC, therefore increasing
counterflows on ATC. EPSA offers were built for multiple uses are a major transparency and decreasing the
examples of specific data inputs that, in concern on the Bonneville system. potential for undue discrimination by
its view, should also be standardized Consequently, hydro operators are more transmission providers.
among all transmission providers, limited in their ability to use generation 291. We note that commenters
which include: Load levels and redispatch as a tool to meet long-term generally were very supportive of the
distribution studies; transmission firm load obligations. Similarly, Santee Commission’s proposals for review and
outages; generation outages; and Cooper cautions that over- update of models and for consistency of
generation dispatch. Ameren submits standardization may result in certain assumptions and data inputs. We
that any modeling of base generation parameters being misstated or received no adverse comments
dispatch must model generators, inappropriately constrained, resulting in concerning our general proposal to
including merchant generators, as they inaccurate reservations of capacity for require public utilities, working through
are expected to run. native load purposes and a potentially NERC, to modify the ATC-related
285. Williams asks the Commission to detrimental effect on the reliability of standards to incorporate a requirement
require consistency between service. It recommends that the for the periodic review and modification
transmission planning horizon and Commission direct NERC to allow of models to ensure that they are up to
procurement terms, and transparency deviations from the standard modeling date. Moreover, the need to improve the
around the long-term transmission assumptions where the need can be quality of system modeling was one of
planning assumptions. Williams states supported, with the caveat that a the U.S.-Canada Power System Task
that third-party bids to a request for utility’s modeling assumptions must be Force recommendations.185
proposals are evaluated with transparent and available for scrutiny. 292. The Commission also adopts the
transmission costs that may already be Seattle contends that modeling NOPR proposal to require transmission
included in long-term transmission assumptions should be developed at the providers to use data and modeling
plans. Thus, argues Williams, sub-regional level, consistent among assumptions for the short- and long-
procurement and long-term planning adjacent transmission providers. TVA term ATC calculations that are
assumptions are intertwined. In reply, suggests that the transmission providers consistent with that used for the
Entergy acknowledges and agrees that be allowed to retain flexibility to
182 E.g., Sacramento, Manitoba Hydro, Nevada
the models used for planning, conduct risk analyses and reflect those
Companies, and TANC.
in their modeling assumptions. 183 E.g., Sacramento.
179 E.g., APPA, Arkansas Commission, 288. Other commenters argue that 184 The MOD–010 through MOD–025 reliability
Constellation, Entegra, Exelon, EPSA, ISO/RTO modeling assumption standardization standards establish data requirements, reporting
sroberts on PROD1PC70 with RULES

Council, LDWP, MidAmerican, Municipals, should not be performed by NERC and, procedures, and system model development and
NRECA, CREPC, Sacramento, Santee Cooper, Suez validation for use in the reliability analysis of the
Energy NA, TAPS, TDU Systems, WestConnect, and
instead, should be delegated to the
interconnected transmission systems.
Williams. regional reliability organizations or 185 Final Report on the August 14, 2003 Blackout
180 E.g., Bonneville. Santee Cooper, and Entergy. RTOs, as they possess a superior in the United States and Canada: Causes and
181 E.g., PJM, EPSA, and Ameren. knowledge of the physical grid within Recommendations.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00040 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12305

planning of operations and system provide a vehicle for interested parties resources that are committed or have the
expansion, respectively, to the to gain access to planning-related legal obligation to run, as they are
maximum extent practicable. This information and to have their own plans expected to run and (2) uncommitted
includes, for example: (1) Load levels, for transmission evaluated at the same resources that are deliverable within the
(2) generation dispatch, (3) transmission time the transmission provider plans for control area, economically dispatched
and generation facilities maintenance its needs. Coupled with the as necessary to meet balancing
schedules, (4) contingency outages, (5) modifications to the ATC-related requirements.
topology, (6) transmission reservations, reliability standards that require the 297. Regarding transmission
(7) assumptions regarding transmission same data and assumptions to be used reservations modeling, we direct public
and generation facilities additions and for calculating long-term ATC as in utilities, working through NERC, to
retirements, and (8) counterflows. We system planning, these reforms are develop requirements in reliability
find that requiring consistency in the adequate to address Williams’ concern. standard MOD–001 that specify (1) A
data and modeling assumptions used for To the extent there are changes on the consistent approach on how to simulate
ATC calculations will remedy the system, these should be captured in the reservations from points of receipt to
potential for undue discrimination by regional transmission planning process points of delivery when sources and
eliminating discretion and ensuring and in the determination of ATC. We sinks are unknown and (2) how to
comparability in the manner in which a therefore reject Entergy’s proposal to model existing reservations.
transmission provider operates and allow NERC to determine the 298. In response to commenter
plans its system to serve native load and circumstances under which differences requests in favor of flexibility and
the manner in which it calculates ATC between models would be appropriate regional differences, we again require
for service to third parties. The in order to ensure comparable service that any waivers from the approved
Commission directs public utilities, for all transmission customers. NERC reliability standards must take
working through NERC, to modify ATC 295. We offer the following place through the NERC reliability
standards to achieve this consistency. clarifications. In response to Southern, standards process as a request for
293. With regard to EPSA’s request for we clarify that we require consistent use regional difference. Also, we disagree
the standardization of additional data of assumptions underlying operational with commenters who argue that
inputs, we believe they are already planning for short-term ATC and modeling assumptions should be
captured in the Commission’s proposal expansion planning for long-term ATC delegated to regional reliability
as adopted in this Final Rule. Xcel asks calculation. We also clarify that there organizations. The goal of this
the Commission to require consistency must be a consistent basis or approach rulemaking is to increase consistency in
in the determination of counterflows in to determining load levels. For example, ATC calculations and that is best
the calculation of ATC. Counterflows one approach may be for transmission accomplished through NERC, which has
are included in the list of assumptions providers to calculate load levels using established processes to address
that public utilities, working through an on- and off-peak model for each requests for regional differences from
NERC, are required to make consistent. month when evaluating yearly service the reliability standard requirements.
We believe that counterflows, if treated requests and calculating yearly ATC. We conclude that the NERC process is
inconsistently, can adversely affect The same (peak- and off-peak) or appropriate as it is open to all industry
reliability and competition, depending alternative approaches may be used for participants and, therefore, is a suitable
on how they are accounted for. monthly, weekly, daily and hourly ATC arena for establishment of common
Accordingly, we reiterate that public calculations. Regardless of the ultimate
standards for modeling assumptions.
utilities, working through NERC and choice of approach, it is imperative that
NAESB, are directed to develop an all transmission providers use the same g. ATC Calculation Frequency
approach for accounting for approach to modeling load levels to NOPR Proposal
counterflows, in the relevant ATC enable the meaningful exchange of data
standards and business practices. We among transmission providers. 299. The Commission proposed the
find unnecessary Xcel’s request that we Accordingly, we direct public utilities, development of standards requiring that
require a date certain for specific issues working through NERC, to develop the ATC calculation be performed with
in the Western Interconnection to be consistent requirements for modeling consistent frequency among
addressed. Above we require public load levels in MOD–001 for the services transmission providers. Specifically, the
utilities, working through NERC, to offered under the pro forma OATT. Commission proposed that transmitting
modify the ATC standards within 270 296. With respect to modeling of public utilities, working through NERC
days after the publication of the Final generation dispatch, we direct public and NAESB, develop standards
Rule in the Federal Register. utilities, working through NERC, to requiring that the calculation be
294. With regard to Williams’ request develop requirements in NERC’s MOD– performed by all transmission providers
that the Commission require 001 reliability standard specifying how on a consistent time interval and in a
consistency between transmission transmission providers shall determine manner that closely reflects the actual
planning horizons and procurement which generators should be modeled in topology of the system, e.g., generation
terms, we believe that such an express service, including guidance on how and transmission outages, load forecast,
requirement is neither appropriate nor independent generation should be interchange schedules, transmission
necessary. The manner in which considered. We agree with Ameren that reservations, facility ratings, and other
transmission providers procure power any modeling of base generation necessary data. The Commission also
for native load customers is generally dispatch must model generators, supported uniform updating of ATC
outside the scope of this rulemaking. including merchant generators, as they values and its components (e.g., TTC,
This notwithstanding, we note that by are expected to run. Accordingly, we ETC, CBM, and TRM).
sroberts on PROD1PC70 with RULES

this Final Rule, Williams and other direct public utilities, working through
affected market participants will have NERC, to revise reliability standard Comments
an opportunity to participate in a MOD–001 by specifying that base 300. Alcoa and Powerex emphasize
transmission provider’s coordinated, generation dispatch will model (1) All the critical need for ATC to be
regional planning process. This will designated network resources and other calculated more frequently for

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00041 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12306 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

constrained facilities. On constrained there are additional data that should be reply comments, Exelon agrees with
paths, where transmission equipment is provided, whether access to such data MISO that the various joint operating
stressed to its limits, Alcoa recommends should be limited to transmission agreements are not consistent. Exelon
that ATC be calculated on an hourly or providers, and if there are existing proposes that the NERC standards
real-time basis and be adjusted for forums by which these or similar data specify requirements for coordination
temperature extremes. Seattle comments are already shared. and the type of data that must be
that ATC should be updated on a ‘‘by exchanged and used for accurate ATC
Comments
exception’’ basis, i.e., when significant calculations. Exelon contends that
model changes or confirmations of 303. Most commenters support the having uniform standards for
service requests occur. While Commission’s proposal to establish coordination developed by NERC will
supporting the Commission proposal, rules for data exchange, but express a enhance efficiency throughout the
TAPS cautions against updating ATC/ preference for confidential data industry, particularly between and
AFC too frequently, as this may play exchange.186 NERC states that proposed among RTO and non-RTO areas.
into the hands of those who use changes to its existing modeling MidAmerican reiterates that ATC
reservation computer programs. standards would require transmission coordination remains an issue for RTOs
providers to coordinate the calculation and that any improvements in ATC
Commission Determination of TTC/ATC/AFC with others. TVA coordination resulting from this
301. The Commission adopts the emphasizes that it has already proceeding must apply to the OATTs of
NOPR proposal and requires the incorporated these principles into its RTOs and non-RTOs alike.
development of reliability standards operating processes by executing 306. NAESB states that coordination
that ensure ATC is calculated at agreements that provide for data and data exchange may require business
consistent intervals among transmission exchange and coordination with practices for existing transmission
providers. The Commission thus directs neighboring transmission systems. reservations, including counterflows,
public utilities, working through NERC 304. PJM suggests that the data ATC calculation frequency, and source/
and NAESB, to revise reliability exchange protocols be developed as sink modeling identification. Some
standard MOD–001 to require ATC to be minimum requirements and not commenters request that the
recalculated by all transmission interfere with existing protocols that Commission clarify that only
providers on a consistent time interval PJM has with neighboring control areas information necessary for purposes of
and in a manner that closely reflects the under agreements such as the MISO/ ATC modeling needs to be
actual topology of the system, e.g., PJM JOA.187 Similarly, SPP states that it exchanged.189 In particular, they
generation and transmission outages, also has developed seams coordination propose that proprietary generation or
load forecast, interchange schedules, agreements with adjoining transmission market information data that might
transmission reservations, facility providers 188 that fully meet and, in harm their competitive position should
ratings, and other necessary data. This some cases exceed, the Commission’s not be publicly disseminated since that
process must also consider whether objective of fostering greater data would not enhance the ability of
ATC should be calculated more exchanges between transmission transmission providers to accurately
frequently for constrained facilities. providers. calculate ATC.
ATC-related requirements for OASIS 305. MISO is concerned that the 307. While acknowledging these
posting are discussed below. NOPR does not address transparency confidentiality and commercial
and regional coordination issues arising sensitivity concerns, other commenters
h. Data Exchange at the seams between RTO and non-RTO recommend that the availability of
NOPR Proposal regions, particularly with respect to shared data not be limited to
ATC calculations. In MISO’s view, the transmission providers.190 For example,
302. The Commission proposed the Commission-approved joint operating TAPS explains that transmission
development through NERC of standard agreements between various ISOs and dependent utilities need an opportunity
protocols that would enable and require RTOs contain cutting edge ATC to access the data periodically as a
the exchange of data and coordination calculation methodologies, while no check on the process. To address
among transmission providers. The comparable common protocols have confidentiality or standards of conduct
Commission proposed that the evolved with non-RTO utilities. In its concerns, TAPS proposes that
following data, at a minimum, be transmission dependent utilities’ access
exchanged among transmission 186 E.g., Allegheny, Ameren, Arkansas Municipal,
to data could be achieved through an
providers for the purposes of ATC Bonneville, Constellation, CAISO, Entergy, Exelon,
employee barred from disclosing
modeling: (1) Load levels; (2) FirstEnergy, LPPC, MidAmerican, Santee Cooper,
Seattle, and TAPS. information to marketing staff or a third
transmission planned and contingency 187 Under the PJM/MISO Joint Operating party independent consultant retained
outages; (3) generation planned and Agreement (JOA) and other operating agreements by the transmission dependent utility.
contingency outages; (4) base generation modeled on that agreement, parties have developed However, APPA and Seattle urge the
dispatch; (5) existing transmission comprehensive data exchange protocols to facilitate
Commission to eliminate artificial and
reservations, including counterflows; (6) coordination and consistent AFC calculations.
Much of this data is supplied through industry institutional barriers to the exchange of
ATC recalculation frequency and times; standard sources such as NERC SDX and NERC data and information.
and (7) source/sink modeling eTags. 308. APPA and Seattle also contend
identification. The Commission 188 SPP has developed seams agreements to
that, even if data were openly available,
expressed its view that significant exchange ATC data and coordinate congestion with
non-RTO neighbors such as the Southwest Power the vast quantities of hourly data points
improvements in the communication, Administration. Further, SPP exchanges ATC/AFC are difficult to manage, process and
coordination, and exchange of data data and coordinates planning, reserve sharing, analyze using existing methods. To
sroberts on PROD1PC70 with RULES

across all transmission providers in an outage coordination, and transmission service


address this issue, APPA recommends
interconnection are needed to produce administration under a transmission coordination
agreement with Associated Electric Cooperative,
accurate determinations of ATC. The Inc. (AECI), an individual transmission provider 189 E.g., Allegheny, Constellation, and
Commission sought comment as to how situated on SPP’s border that is not a member of Indianapolis Power.
much data sharing is workable, whether SPP or any other RTO. 190 E.g., APPA, Bonneville, TAPS, and Seattle.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00042 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12307

that the Commission encourage ongoing are developed in the NERC and NAESB Commission’s proposal to require
efforts to obtain greater resolution of processes.191 detailed information in Attachment C
system-model State variables, 312. With respect to concerns regarding the transmission provider’s
contractual uses and probabilistic regarding the exchange of data that may ATC/AFC calculation methodology.193
ranges and to refine data management be a subject of confidentiality and Barrick agrees in its reply comments
and analytical methods. commercially sensitive, we only require that a thorough explanation of how ATC
information necessary for purposes of is calculated should be made readily
309. New York Commission suggests
ATC modeling to be exchanged. As available either in the transmission
having an overarching entity, such as a suggested by some commenters,
Transmission Oversight Center, that is provider’s OATT or on its OASIS,
proprietary generation or market thereby improving transparency and
responsible for calculating and information data that might harm a making it less difficult for customers to
coordinating ATC between various competitive position should not be determine whether the calculations are
ISOs/RTOs could overcome this lack of publicly disseminated, since that would unduly discriminatory. Old Dominion
data. not enhance the ability of transmission calls for greater transparency in the
Commission Determination providers to accurately calculate ATC. If details of calculating ATC, even as
any of the data are subject to applied to RTOs such as PJM because of
310. The Commission adopts the confidentiality and are commercially the relevance of ATC at the borders of
NOPR proposal and directs public sensitive, they must be disclosed in an RTO/ISO and the market impact of
utilities, working through NERC, to accordance with a confidentiality inconsistencies in definitions, data,
revise the related MOD reliability agreement. modeling assumptions and frequency of
standards to require the exchange of 2. Transparency ATC calculations. NERC states that the
data and coordination among revised NERC reliability standards will
transmission providers and, working a. OATT Transparency
address transparency.
through NAESB, to develop (1) Attachment C 315. NARUC contends that
complementary business practices. The NOPR Proposal understanding ATC calculation
following data shall, at a minimum, be methodologies and having access to the
exchanged among transmission 313. In the NOPR, the Commission
proposed to require each transmission underlying data is essential to a range of
providers for the purposes of ATC critical State commission functions and,
modeling: (1) Load levels; (2) provider to include in Attachment C of
its OATT more descriptive information therefore, greater transparency of ATC
transmission planned and contingency information will significantly enhance
concerning its ATC/AFC calculation
outages; (3) generation planned and State commissions’ abilities to fulfill
methodology. Specifically, the
contingency outages; (4) base generation Commission proposed to require the their statutory obligations. On reply,
dispatch; (5) existing transmission transmission provider to state its North Carolina Agencies agree with
reservations, including counterflows; (6) specific mathematical algorithm used to NARUC and state that efforts aimed at
ATC recalculation frequency and times; calculate firm and non-firm ATC/AFC increased transparency of ATC
and (7) source/sink modeling for its scheduling horizon, operating calculations should help uncover any
identification. The Commission horizon, and planning horizon. The actual discriminatory behavior by
concludes that the exchange of such Commission also proposed to require transmission providers, provide a
data is necessary to support the reforms transmission providers to provide a clearer standard against which to
requiring consistency in the process flow diagram that illustrates the evaluate claims of unduly
determination of ATC adopted in this various steps through which ATC/AFC discriminatory activities, and facilitate
Final Rule. As explained above, is calculated. In addition, the regional planning efforts. Entegra states
transmission providers are required to Commission proposed to require on reply that transmission providers
coordinate the calculation of TTC/TFC transmission providers to provide should be required to post narratives
and ATC/AFC with others and this definitions and explain in detail how explaining changes in models and
requires a standard means of exchanging TTC, ETC, AFC, TRM, and CBM are factors underlying ATC and AFC values,
data. calculated for both operating and which would be invaluable to the
planning horizons. Commission and customers in
311. While there is a near consensus
identifying problems that may warrant
among commenters that significant Comments enforcement actions.
improvements in the communication,
314. Most commenters support the 316. While APPA generally supports
coordination, and exchange of data Commission’s overall proposal on
across all transmission providers are the Commission’s proposal, some of
transparency in ATC calculations.192 APPA’s members along with other
needed to produce accurate Numerous commenters support the
determinations of ATC, we acknowledge commenters express concern that
the concerns of ISO/RTOs that new data 191 We are not requiring that every transmission
including all the information might be
exchange protocols may interfere with provider follow identical protocols. Rather, all too burdensome and result in numerous
the existing protocols and seams transmission providers must meet the relevant tariff changes.194 Some APPA members
coordination agreements. Although we
NERC reliability standards and NAESB business in the West also express concerns about
practices, and each entity will be subject to the competitive implications of
will not provide a blanket exemption for reliability standards compliance audits through
ISOs and RTOs from meeting or which they will have to demonstrate that they meet
or exceed the reliability standards. 193 E.g., Arkansas Municipal, Arkansas
exceeding the data exchange 192 E.g., Alberta Intervenors, AWEA, Bonneville, Commission, CAISO, Constellation, ELCON,
requirements of this Final Rule, they
sroberts on PROD1PC70 with RULES

CAISO, Constellation, Duke, East Texas Entergy, ISO New England, Morgan Stanley,
may, as explained in section IV.C.2, Cooperatives, ELCON, Entergy, Entegra, EPSA, NARUC, Nevada Companies, Occidental, PJM,
demonstrate in relevant filings that their E.ON, Exelon, MidAmerican, Morgan Stanley, Powerex, Project for Sustainable FERC Energy
Municipals, Nevada Companies, NPPD, PGP, PJM, Policy, Santee Cooper, and Suez Energy NA.
existing data exchange protocols are Powerex, CREPC, Santee Cooper, TVA, TAPS, and 194 E.g., EEI, PNM–TNMP, Sacramento, Seattle,
consistent with or superior to those that TDU Systems. and Southern.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00043 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12308 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

providing such confidential and Regarding the proposal to require a Commission Determination
sensitive information. ‘‘detailed explanation’’ of the 323. The Commission adopts the
317. EEI also notes that providing calculation of ATC, TTC, ETC, and TRM NOPR proposal to increase transparency
additional detailed information in components, ISO New England argues regarding ATC calculations by requiring
Attachment C would be duplicative and that the relevant inputs can change on each transmission provider to set forth
may result in confusion due to a daily basis because ATC for Pooled its ATC calculation methodology in its
inconsistencies between the wording of Transmission Facilities (PTF) in New OATT. Each transmission provider
the NERC and NAESB ATC documents England is a function of market must, at a minimum, include the
and each transmission provider’s conditions, as opposed to an following information in Attachment C
Attachment C. To avoid uncertainty, EEI administratively-derived calculation. In to its OATT. It must clearly identify
recommends that the Commission ISO New England’s view, the level of which of the NERC-approved
require transmission providers to detail required should reflect the methodologies it employs (e.g., contract
comply with the requirements of operation of competitive markets. MISO path, network ATC, or network AFC). It
Attachment C by referencing NERC is concerned that the NOPR does not also must provide a detailed description
reliability standards or business address transparency and regional of the specific mathematical algorithm
practices that provide the information coordination issues arising at the seams
that is called for in the Attachment. the transmission provider uses to
between market and non-market areas, calculate firm and non-firm ATC for the
MidAmerican believes that additional particularly with respect to ATC
information concerning calculating ATC scheduling horizon (same day and real-
calculations. time), operating horizon (day ahead and
and its components would best be 321. MidAmerican strongly urges the
retained in the transmission provider’s pre-schedule), and planning horizon
Commission to ensure that non-public (beyond the operating horizon). In
business practices rather than utility transmission providers adhere to
Attachment C. In its reply comments, addition, transmission providers must
the transparency requirements, since in include a process flow diagram that
Powerex suggests an alternative of the Pacific Northwest many of the
permitting transmission providers to describes the various steps that it takes
‘‘backbone’’ transmission lines are co- in performing the ATC calculation.
provide a general reference to NERC, owned by jurisdictional and
WECC, or NAESB standards and fully Furthermore, transmission providers
nonjurisdictional entities. A must set forth a definition of each ATC
outline core definitions, processes, data jurisdictional co-owner may be limited
and assumptions when deviating from component (i.e., TTC, ETC, TRM, and
in its ability to determine such CBM) and a detailed explanation of how
such standards.
parameters as TRM and CBM because it each one is derived in both the
318. Southern contends that the
may not be the line operator. LPPC, in operating and planning horizons.
transparency concerns expressed in the
NOPR are driven more by the its reply comments, believes it is Requiring transmission providers to file
complexity and volume of the data unnecessary and redundant to require a statement of their ATC calculation
involved rather than a lack of non-public utility transmission methodology along with a process flow
information. Southern suggests that providers to adopt the ATC diagram and more detailed definitions
sufficient information is readily requirements of the pro forma OATT, of ATC components in Attachment C of
available and the best course of action because the Commission recognizes in the OATT will provide greater
by the Commission would be to focus the NOPR that NERC and NAESB are transparency to transmission customers
on documenting transfer capability currently drafting standards for ATC, and assist in identifying any
methodologies available to transmission which when final will be filed with the discrepancies that may arise in ATC
customers. NRECA replies that many Commission and become part of the determinations. These new
commenters provided input into why ERO’s mandatory reliability standards requirements will assist in alleviating
more transparency is needed and and fully applicable to otherwise any appearance of discrimination in the
repeats the example provided in its NOI nonjurisdictional entities. determination of ATC.
comments of a cooperative that spent 322. Suez Energy NA contends that it 324. The Commission acknowledges
many months in discussions with a is essential that the Commission include NARUC’s comments that understanding
public utility transmission provider in an explanation of each component of ATC methodologies and the underlying
an effort to understand ATC-related the ATC calculation in Attachment C to data also will enhance State regulators’
information posted on OASIS. ensure that the transmission provider ability to meet their regulatory
319. Pinnacle contends that the incorporates NERC standards obligations. More transparent ATC
Commission’s proposal for detailed appropriately and to ensure proper calculations are critical to coordinated
information in Attachment C is only enforcement in the event that an audit regional transmission planning that
relevant in flow-based systems, pointing shows that the transmission provider ultimately will improve transmission
out that in the Western Interconnection, has employed other methods of access for customers and enhance grid
the scheduling horizon, and the calculating ATC. Suez Energy NA also reliability. Transparent ATC
operating horizon are the same and thus notes that the mathematical algorithms calculations facilitate the ability of
reporting such information is not and process flow diagrams should be market participants and regulators to
necessary. APPA and Bonneville believe provided to users of the transmission detect discrimination.
that adding such detail in Attachment C system, independent monitors, 325. We do not believe our
may only result in incremental changes transmission coordinators and requirement to include additional
and suggest that better regional regulators, even if a confidentiality information in Attachment C will be
coordination would provide greater agreement is required. APPA suggests overly burdensome or lead to an
transparency. that the Commission and regional excessive level of future tariff revisions.
sroberts on PROD1PC70 with RULES

320. Though ISO New England reliability organizations conduct Attachment C must provide an accurate
believes this proposal would not create additional audits to ensure that these documentation of processes and
an undue burden, it urges the posted practices and procedures are in procedures related to the calculation of
Commission to allow for variety in the fact being followed, and that the data ATC, not the actual mathematical
illustration of the process flow diagram. used are verifiable. algorithms themselves, which should be

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00044 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12309

posted on the transmission provider’s NERC, NAESB, and WECC.195 ATC (2) CBM Practices
Web site. These processes define service calculations have a direct and tangible NOPR Proposal
availability and, as such, must be part effect on the granting of open access
of the transmission provider’s OATT. It transmission service.196 As such, an 332. In the CBM Order, the
is entirely appropriate that, because accurate and detailed statement of the Commission required transmission
revisions to such processes impact methodology and its components that providers to post a specific narrative
transmission availability, they should be defines how the transmission provider explanation of their CBM practices.198
filed for Commission approval and determines ATC belongs in the In addition, the Commission directed
included in a transmission provider’s transmission provider’s OATT as the transmission providers to post their
OATT. We also require transmission means of holding the transmission procedures for allowing access to CBM
providers to file a revised Attachment C provider accountable for following non- during emergencies. The Commission
to incorporate any changes in NERC’s discriminatory procedures for granting further stated in the CBM Order that, if
and NAESB’s revised reliability service, not in business practices kept a utility’s practice was not to set aside
standards and business practices related by the transmission provider.197 transfer capability as CBM, it should
to ATC calculations, as requested by the However, as noted above, the actual reflect that in Attachment C.
Commission in this Final Rule. This mathematical algorithms should be 333. In the NOPR, the Commission
filing should be made within 60 days of posted on the transmission provider’s proposed to require transmission
completion of the NERC and NAESB web site, with the link noted in the providers to include this CBM narrative
processes. As we expect transmission transmission provider’s Attachment C. in Attachment C of their OATTs. In
providers to rarely change their ATC 329. We also reject Pinnacle’s addition, the Commission proposed that
calculation methodologies, we do not assertion that more detailed information transmission providers explain their
believe this requirement will trigger an in Attachment C would only apply to definition of CBM, list the databases
unacceptable level of tariff filings flow-based systems. Regardless of what used in their CBM calculations, and
modifying the Attachment C description type of ATC calculation methodology is prove that there is no double-counting
of the ATC components and processes. employed, transparency in ATC of contingency outages when
326. We agree with ISO New England performing CBM calculations.
calculations is critical to avoid undue
that the process flow diagram
discrimination when allocating Comments
requirement may be met with a variety
transmission capacity under the pro
of illustrations, so long as it is of 334. Seattle and Suez Energy NA
forma OATT.
sufficient detail to provide the support this proposal. Seattle states that
transmission customer with a 330. In response to MidAmerican’s CBM information should be specified in
reasonable understanding of the comments regarding the applicability of Attachment C in order to provide clear
transmission provider’s ATC calculation the ATC-related reforms to non-public guidance for the specific information
processes. The process flow diagram utilities, we again refer to section IV.C.3 that is posted on OASIS. Seattle and
should support the other Attachment C where we discuss this issue generally. APPA suggest that CBM should be
requirements. As noted above, we agree We note here, however, that the ERO’s verifiable and subject to audit by
with Suez Energy NA that mathematical reliability standards currently in independent parties such as regional
algorithms and process flow diagrams development before the Commission reliability organizations.
should be made available. We do not will be applicable to all users, owners 335. EEI suggests that the Commission
find that a confidentiality agreement is and operators of the bulk electric grid, revise Attachment C, section 3(f) to
generically warranted; however, we note which includes non-public utilities. replace the word ‘‘prove’’ with the word
that, a transmission provider may 331. We do not believe ATC-specific ‘‘demonstrate’’ in the requirement that
require a confidentiality agreement for tariff audits are necessary to order at the transmission provider ‘‘prove’’ that
CEII materials, consistent with our CEII this time. The Commission will it does not double count contingency
requirements, or may otherwise protect continue to provide oversight of all outages when calculating CBM, TTC
the confidentiality of proprietary tariff-related activities through its and TRM. EEI notes that the term
customer information. enforcement program. Moreover, ATC ‘‘prove’’ implies a determination on the
327. We also require transmission requirements will be part of the merits after evaluation of competing
providers to document their processes mandatory and enforceable reliability arguments and evidence. A transmission
for coordinating ATC calculations with standards and, as such, will be subject provider should be able to satisfy its
their neighboring systems. This to compliance audits through that obligations by ‘‘demonstrating’’ the
requirement is particularly important process. absence of a double count. Any
with respect to seams between market customer that wishes to challenge the
and non-market areas, as identified by 195 WECC has on file a Reliability Management
demonstration can do so, at which time
MISO, and with respect to the request System agreement under which transmission the issue of ‘‘proof’’ would arise.
of other commenters to increase regional providers agreed, through contracts, to follow
336. With regards to ‘‘double
coordination regarding ATC calculation. WSCC reliability criteria. Western Systems
Coordinating Council, 87 FERC ¶ 61,060 (1999). counting,’’ TVA references TRM and
While this Final Rule does not address 196 The Commission recognized in Order No. 889 agrees that additional explanations
all seams issues between market and that the methodology for calculating ATC and TTC regarding the calculation of TRM,
non-market areas, it does take important belongs in the tariff. Order No. 889 at 31,607. At
including methods used to avoid double
steps towards that end by improving the time, the industry represented that it was
engaged in efforts to develop uniform methods of counting contingency events, should
data exchange between transmission determining ATC. The Commission encouraged improve transparency in providing open
providers and providing increased such industry efforts and required that the tariff access transmission service. TVA points
transparency with respect to ATC include the methodology, which was to be based on
out that this is being addressed by a
sroberts on PROD1PC70 with RULES

calculation. current industry practices, standards and criteria.


197 For the same reason, the Commission NERC standards drafting team.
328. We reject proposals to address
disagrees with the assertions of Southern and EEI
the transparency of ATC methodology that more information in Attachment C would be 198 Capacity Benefit Margin in Computing
by merely referencing business practices duplicative because some ATC-related information Available Transmission Capacity, 88 FERC ¶ 61,099
and reliability standards developed by is already available elsewhere. (1999) (CBM Order).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00045 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12310 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Commission Determination ATC and TTC calculations to be paths, by requiring a posted tabulation
337. The Commission adopts the performed according to consistently of annual and monthly ATC calculation
NOPR proposal requiring additional applied methodologies referenced in the details. Great Northern suggests
information in the transmission transmission provider’s OATT and including TTC, network load for each
provider’s OATT Attachment C current industry practices, standards transmission customer, capacity
regarding its determination of CBM. and criteria. The Commission proposed reserved for each network resource,
Transmission providers must provide in that these calculations be based on the each point-to-point transmission service
Attachment C a narrative description ERO reliability standards. reservation, CBM and other deductions
detailing their CBM practices. In 342. The Commission further from TTC.
addition, a transmission provider must proposed to maintain the requirement 346. APPA members support the
explain its definition of CBM and list that transmission providers provide, on posting of ATC information, as it will
the databases used to derive its value. request, all data used to calculate ATC assist in using ATC more efficiently,
These new requirements will provide and TTC for any constrained paths. and they support the posting of system
transmission customers transparency Transmission providers also would planning studies and specific network
into the CBM component of ATC and remain required, on request, to make impact studies that the transmission
help discourage the potential for undue publicly available any system planning provider performs for its own merchant
discrimination in the calculation and studies or specific network impact function, as well as studies performed
use of CBM. studies performed for customers and to for customers. In addition, APPA
338. We adopt EEI’s proposal that the post a list of such studies on OASIS. suggests the posting of facilities studies
Commission revise Attachment C, at the time they become available,
Comments assuming that this can be done
section 3(f) to replace the word ‘‘prove’’
with the word ‘‘demonstrate.’’ The word 343. Several commenters support the consistent with CEII concerns. TAPS
‘‘demonstrate’’ more accurately proposal to post ATC-related goes further by urging the Commission
describes the showing we expect the information on OASIS.199 TDU Systems to close gaps in the current OASIS
transmission provider to make. We supports each of the Commission’s requirements by requiring posting of all
agree that the word ‘‘prove’’ implies a proposals with respect to providing studies performed for transmission
standard of proof that we did not intend easier access to data underlying ATC owners’ own transmission network
to impose. We also acknowledge TVA’s calculations and greater transparency to resource designations and other uses of
comments that the NERC standards the process. Sacramento states that the system, including facilities studies
drafting team is developing standards posting on OASIS will ensure proper as well as system impact studies,
that should address ‘‘double counting’’ public access, but will avoid the need ensuring posted study lists are updated
in ATC calculations in general. for Commission approval of an OATT contemporaneously with the availability
However, we require that the change. of new studies, and requiring retention
information in Attachment C be 344. Constellation strongly supports of studies for a minimum of five years.
sufficient to demonstrate that a the need for additional transparency, 347. Nevada Companies and TVA
transmission provider is not double stating that providing transmission support cost effective measures that
counting CBM in its ATC calculation. customers with meaningful insight into increase transparency in transmission
339. Finally, the Commission rejects the current ‘‘black box’’ determination operations and, unless the requirement
the proposal by Suez Energy NA, APPA, of ATC will help minimize the mystery becomes unduly time consuming or
and Seattle to establish formal audits of underlying many transmission provider burdensome, in general support more
CBM set asides. Requirements for CBM responses to service requests. According disclosure rather than less.
will be part of the mandatory and to Constellation, further transparency Commission Determination
enforceable reliability standards and, as will assist customers in predicting the
outcome of transmission service 348. The Commission adopts the
such, will be subject to compliance
requests and facilitate increased proposal in the NOPR to continue to
audits through that process. Moreover,
commercial activity. Constellation require transmission providers to
the Commission provides oversight of
suggests that the Commission require comply with existing ATC-related
all tariff-related activities through its
enforcement program. transmission providers to provide posting obligations as supplemented by
transmission customers, on request, this Final Rule. The Commission will
b. OASIS continue to require transmission
with specific details related to modeling
(1) ATC/TTC Posting Requirements data, modeling support information, providers, on request, to make available
modeling benchmarking and forecasting all data used to calculate ATC and TTC
NOPR Proposal for any constrained paths and any
data, and transmission service request
340. The Commission’s existing audit data. It requests that the system planning studies or specific
regulations require certain ATC-related information be in a form and format network impact studies performed for
information to be posted on each usable by the transmission customers customers. Transmission providers must
transmission provider’s OASIS and and that the Commission take steps to also continue to post a list of such
other information to be provided on ensure that transmission customers studies on OASIS.
request. To ensure that relevant 349. In addition, we agree with the
understand how ATC is calculated and
information is available on a timely requests of APPA and TAPS to require
the data inputs are used to affect those
basis to all market participants, the the additional posting of, at a minimum,
calculations.
Commission proposed in the NOPR to a listing of all system impact studies,
345. Great Northern likewise requests
amend its regulations to allow potential facilities studies, and studies performed
that the Commission enhance the
customers greater access to information for the transmission provider’s own
requirement to provide all data on
sroberts on PROD1PC70 with RULES

that will enable them to obtain service network resources and affiliated
request, specifically on constrained
on a non-discriminatory basis from any transmission customers, to be made
transmission provider. 199 E.g., APPA, Constellation, FirstEnergy, available upon request. We note that
341. The Commission noted in the Indianapolis Power, Sacramento, Suez Energy NA, appropriate procedures to accommodate
NOPR that existing regulations require TAPS, and TDU Systems. CEII concerns should be developed to

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00046 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12311

ensure eligible entities with a legitimate information. Bonneville indicates that it fact, materialized).201 The Commission
interest in transmission study data can currently posts TRM values in its therefore directed transmission
receive access to it. Also, we adopt Business Practices Forum, which is providers to periodically reevaluate
TAPS’ suggestion that the studies be useful for examining curtailment events, their generation reliability needs so as to
made available for five years to make supporting transmission planning make known the availability of CBM
the requirement consistent with data objectives, and validating posted ATC and to post on OASIS their practices in
retention requirements pertaining to values. this regard.202 In the NOPR, the
denial of service requests. 353. EPSA also recommends that the Commission proposed to incorporate
350. The Commission rejects Commission provide guidance on these requirements in the Commission’s
Constellation’s and Great Northern’s standards that should be developed to regulations and to obligate transmission
proposals to require transmission require each transmission provider to providers to reevaluate the CBM set-
providers to provide upon request or notify the Commission in writing and aside at least quarterly.
regularly post additional information post a notice on its OASIS within 24
beyond that required in the regulations Comments
hours of a transmission provider’s use of
and this Final Rule. The transmission CBM to import emergency power. EPSA 357. Some commenters support
provider is already required to make also requests that the amount of CBM quarterly reevaluation of CBM set-
available, upon request and in reserved for each interface be posted on asides.203 TAPS agrees with the need for
electronic format, all information OASIS. full transparency of CBM reservations
related to the calculation of ATC and and practices and states that, because
TTC for any constrained path. Commission Determination CBM values may differ from season to
Accordingly, we see little benefit to 354. The Commission adopts the CBM season, CBM values should be
require transmission providers to posting requirements proposed in the separately calculated for at least each
provide upon request or regularly post NOPR. In doing so, we amend our quarter. However, TAPS does not find
additional information suggested by OASIS regulations to incorporate the that it is necessary or appropriate for the
these commenters. directives established in the CBM Order. CBM values to be reevaluated quarterly,
Accordingly, we require transmission given the effort involved in collecting
(2) CBM/TRM Posting Requirements the data and performing the modeling
providers to post (and update) the CBM
NOPR Proposal amount for each path. In addition, the analysis. Rather, CBM studies should be
351. The Commission’s OASIS Commission requires transmission performed at least every other year,
regulations currently require providers to make any transfer supplemented with ‘‘off-year studies’’
transmission providers to calculate and capability set aside for CBM but unused when appropriate.
post ATC and TTC for each posted path, for such purpose available on a non-firm Commission Determination
but make no requirement for CBM and basis and to post this availability on 358. The Commission incorporates
TRM postings. In the CBM Order, OASIS. Furthermore, the Commission into its regulations the requirement in
however, the Commission required requires transmission providers to post the CBM Order for a transmission
transmission providers, with respect to (and update) the TRM values for the provider to periodically reevaluate its
each path for which the utility already paths on which the transmission transfer capability set-aside for CBM.
posts ATC, to post (and update) the provider already posts ATC, TTC, and With respect to TAPS’ concerns over the
CBM figure for that path. The CBM. effort involved in the re-evaluation
Commission also required transmission 355. We reject EPSA’s request to process, we will require CBM studies to
providers to make any transfer require transmission providers to notify be performed at least every year. This
capability set aside for CBM available the Commission in writing and post a requirement is consistent with the CBM
on a non-firm basis and to post this notice on OASIS within 24 hours of a Order, in which the Commission stated
availability on OASIS. In the NOPR, the transmission provider’s use of CBM to that the level of ATC set aside for CBM
Commission proposed to incorporate import emergency power and transfer should be reevaluated periodically to
these CBM posting requirements into its capability set aside as CBM at each of take into account more certain
regulations. The Commission also the transmission provider’s interfaces. information (such as assumptions that
proposed that transmission providers The additional transparency of CBM- may not have, in fact, materialized).204
post (and update) the TRM values for related information provided in this While changes requiring a reevaluation
the paths on which the transmission Final Rule, along with the reforms of CBM are longer-term in nature (e.g.,
provider already posts ATC, TTC, and related to consistency of CBM, will installation of a new generator or a long-
CBM. cause sufficient information to be made term outage), quarterly may be too
Comments available to customers concerning the frequent, though two years may be too
use of CBM. The use and allocation of long and may prevent a portion of the
352. Several commenters strongly
CBM and TRM will be more transparent CBM set-aside from being released as
support the Commission’s proposal to
to transmission customers, thus ATC. Moreover, annual reevaluation is
require transmission providers to post
reducing the potential for undue consistent with the current NERC
TRM and CBM.200 APPA and EPSA
discrimination. standard being developed in MOD–
agree that the posting of TRM for near
term transmission services would (3) Periodic Reevaluation of the CBM 005.205 The requirement to evaluate
provide greater assurance that ATC Set-Aside CBM at least every year also is
calculations are being performed consistent with the CBM Order in that
NOPR Proposal
according to established procedures. 201 CBM
356. In the CBM Order, the Order at 61,237.
Since transmission providers already
sroberts on PROD1PC70 with RULES

202 Id.
have this information, FirstEnergy states Commission stated that the level of ATC 203 E.g., EPSA, Sacremento, Santa Clara, Suez
that it does not appear to be unduly set aside for CBM can and should be Energy NA, and TDU Systems.
burdensome for them to post such reevaluated periodically to take into 204 CBM Order at 61,237.
account more certain information (such 205 The MOD–005 reliability standard establishes
200 E.g., Powerex, PJM, PPL, Seattle, and Pinnacle. as assumptions that may not have, in the procedure for verifying CBM values.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00047 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12312 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

the Commission directed transmission 362. A few commenters caution that traced to a specific change in the inputs.
providers to periodically reevaluate some of the data that the Commission is Alternatively, EEI suggests that
their generation reliability needs so as to requiring to be posted by transmission transmission providers could post the
make known the need for CBM and to providers is market-sensitive and, if major changes in the inputs to the TTC
post on OASIS their practices in this posted on a real-time basis, could be modeling software that are made in
regard. used by third parties to obtain an unfair connection with each updated TTC
competitive advantage.208 These posting without ascribing specific
(4) ATC/TTC Narrative Explanation
commenters propose that the inputs to specific changes in TTC and
NOPR Proposal transmission providers should be ATC values on specific lines.
359. In the NOPR, the Commission allowed a brief period of delay (e.g., one 366. Several commenters are
proposed to largely retain existing week) before posting data. Indianapolis supportive of the proposed requirement
posting requirements for unconstrained Power also advocates a delay due to the that transmission providers provide a
posted paths, but to amend the burden on transmission providers of the narrative explanation when ATC values
regulations relating to data posted for new posting. remain at zero.210 APPA suggests that if
constrained posted paths. Existing 363. Several commenters oppose the a particular interface shows an ATC of
regulations require ATC and TTC on Commission’s proposal to require that zero for a specified period, the
constrained paths to be updated when transmission providers post narratives transmission provider should provide a
(1) Transactions are reserved, (2) service on OASIS outlining reasons why narrative explanation of why this is the
ends, or (3) whenever the TTC estimate monthly and yearly ATC values on case and how its plans to address this
for the path changes by more than 10 constrained paths change.209 These problem. It also suggests that this
percent.206 In the NOPR, the commenters contend that this will cause information should be employed in the
Commission proposed to supplement undue burden on transmission transmission planning process. East
the existing regulations by requiring the providers without providing customers Texas Cooperatives, in reply comments,
transmission provider to post a brief, with any significant or new information. state that the narrative can provide
but specific, narrative explanation of the They also argue that the proposal is useful information to the transmission
reason for the change at the time a impractical and will not result in customers and State and Federal
change in monthly and yearly ATC providing transmission customers with regulators regarding specific conditions
values on a constrained path is posted. meaningful information regarding regarding ATC coordination.
The Commission sought comment on transmission service options. 367. In supplemental comments,
364. If such a requirement is adopted, NAESB states that the Commission
whether the posting of this new
MISO recommends that a threshold should specify whether it is sufficient
information would provide adequate
higher than a 10 percent change in ATC for the explanation of changes in ATC
transparency to the customer on a
be established and that the Commission or TTC values to be limited to broad
frequent enough basis without imposing
clarify what the term ‘‘specific generalized statements or whether the
an undue burden on the transmission
explanation’’ means in this context. PJM posted information should include such
provider. The Commission also sought
states that it already exceeds the information as the specific events which
comment on whether a similar narrative
Commission’s proposed requirement. gave rise to the change, the new values
should be required when ATC remains
However, if strictly applied, this for ATC at all points on the network, the
unchanged at a value of zero for some
proposal would be unduly burdensome impact of the change on transmission
specified period of time.
on PJM because it would require PJM to customers, and a detailed snapshot of
Comments post a narrative each hour. PJM asks that the conditions on the system at all
360. Some commenters support the the Commission not apply unnecessary flowgates or constrained elements when
Commission’s proposal to require and costly posting requirements on the change occurred.211
transmission providers to post more independent RTOs and ISOs. 368. Southern states that posting a
365. EEI and Southern are concerned narrative when ATC remains at zero is
detailed explanations about changes in
that monthly ATC may change in unwarranted and unnecessary, as it
ATC values on their OASIS sites.207
response to every reservation of hourly simply indicates that the market has
NAESB, TranServ, and Williams request
transmission service because a responded to market signals of ATC
that the Commission clarify the
reservation of hourly firm service on a availability and purchased all available
regulatory requirements for posting of
constrained path may reduce the capacity.
updated ATC values such as the level of
availability of monthly firm service. EEI
standardization, frequency and time of Commission Determination
contends that, if transmission providers
postings, and other requirements.
are required to post changes in TTC 369. The Commission adopts the
CAISO believes that ATC should be
instead of ATC, they would not be NOPR proposal, with the modifications
updated on a daily basis.
required to post a new narrative every discussed below, to require that the
361. Powerex and Nevada Companies
time a reservation is made, thus transmission provider post a brief, but
propose that additional disclosures be
reducing the overall burden on specific, narrative explanation of the
posted, such as data on grandfathered
transmission providers. EEI additionally reason for a change in monthly and
contracts, time-specific data relevant to
states that the reasons for changes in yearly ATC values on a constrained
transmission constraints and ATC rights
TTC and ATC values often are complex path. Rather than requiring a narrative
on posted paths, and remaining
and involve the interaction of multiple
customer rights under a reservation-
variables in the model that produces the 210 E.g., APPA, East Texas Cooperatives, Suez
based network service system. Energy NA, and TAPS.
TTC and ATC values and a specific
211 November 2, 2006, Addendum to the
change in TTC or ATC cannot easily be
sroberts on PROD1PC70 with RULES

206 See18 CFR 37.6(b)(3)(i)(C). Testimony of Ronald M. Mucci on behalf of the


207 E.g.,
Arkansas Commission, CAISO, North American Energy Standards Board,
208 E.g., Ameren, ISO New England, Southern,
Constellation, East Texas Cooperatives, Exelon, Preventing Undue Discrimination and Preference in
FirstEnergy, LPPC, Morgan Stanley, NRECA, and NRECA. Transmission Service, Docket Nos. RM05–25–000
Pinnacle, Powerex, Santa Clara, and Suez Energy 209 E.g., Ameren, EEI, Entergy, MISO, Pinnacle, and RM05–17–000, October 12 Technical
NA. PJM, PNM–TNMP, Southern, TranServ, and TVA. Conference, pp. 2–3.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00048 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12313

when a monthly or yearly ATC value retained and made available upon Commission Determination
changes as a result of transactions being request for download for three years
reserved, service ending, or the TTC from the date when they are first posted. 376. As proposed in the NOPR, the
estimate for the path changing by more The Commission proposed to change Commission maintains the requirement
than 10 percent, we will require a the period from three to five years. that a transmission provider post the
narrative when a monthly or yearly ATC reason for a denial of service and
value changes only as a result of a 10 Comments extends from three years to five years
percent change in TTC. This will reduce the period for which transmission
374. Many commenters support providers must maintain data providing
the number of ATC changes for which posting of the reasons for denying
a narrative will be required and address reasons for denial of service. In general,
service and the 5-year retention commenters support the requirement for
concerns that the new requirement
proposal.212 TAPS supports the posting denial of service information
unduly burdens transmission providers.
proposal but suggests several and the increase in retention time to five
Any remaining burden is justified by the
benefit to transmission customers of modifications. First, it suggests that the years, indicating that such information
receiving timely information regarding Commission clarify the requirement to can be helpful to customers in their
changes in TTC that result in changes to post the reasons for denying service is awareness of actual transmission
ATC. In addition, we adopt NAESB’s triggered not only by denial of the congestion, rather than relying on
suggestion that posted information entirety of a transmission request, but to simulation models.
include the (1) Specific events which any disposition that falls short of a full
unconditional grant of the service (with 377. We also adopt TAPS’ suggestion
gave rise to the change and (2) new to expand the regulations to include
values for ATC on that path (as opposed rollover rights if applicable). Second,
TAPS recommends that the regulatory availability of information supporting
to all points on the network). the disposition of a transmission
370. We reject calls for delays prior to text of proposed section 37.6(e)(2)(ii) be
modified to make the supporting data provider’s own network resource
posting data. While commenters allege
available, upon request, to any eligible designations and to make such
the possibility of granting others a
information available to any eligible
competitive advantage through the customer rather than just to the
customer rather than just to that
release of ‘‘market-sensitive’’ data, they customers who were denied service.
customer denied service. In addition,
have proffered no evidence to support Third, it asks that the Commission
the allegation of potential harm. we clarify that a partial denial of service
expand its OASIS regulations to require
371. We do require, as suggested in triggers the requirements as well. Such
the transmission provider to maintain
the NOPR, a narrative with regard to information is consistent with the new
and make available on request the
monthly or yearly ATC values when regulations established by this Final
information supporting the disposition
ATC remains unchanged at a value of Rule and will help ensure that
(positive, negative, or in between) of its
zero for a significant period, and will set customers receive transmission service
own network resource designations and
that period at six months or longer. This that is not unduly discriminatory. The
other usage needs. East Texas
information will be valuable to development of a log of service denials,
Cooperatives suggest that the
customers and regulators in assessing full or partial, will establish an ongoing
Commission also require that
the ability of a transmission provider’s record of service requests and
transmission providers distinguish transmission provider responses
facilities to meet existing service between denials of requests for firm and
requests. The information also will demonstrating the transmission
non-firm transmission service. provider’s provision of
provide assurance to customers that the
transmission provider is diligent in 375. Some commenters urge the nondiscriminatory open access service.
regularly evaluating ATC on all paths, Commission to clearly define the scope Furthermore, repeated denials of service
monitoring persistent constraints and of any transmission service request over a particular path or flowgate will
addressing them in its planning information subject to the proposed provide an indication of congestion that
processes. five-year record retention requirement can be used in the transmission
372. Finally, we reject CAISO’s to ensure that no undue administrative planning process. In addition, we agree
suggestion that ATC be updated daily burden is placed on transmission with East Texas Cooperatives that
on a transmission provider’s OASIS site, providers.213 TVA questions the need to postings of denials of service should
because CAISO offered no justification extend the time period for an additional indicate whether the requested service
for the proposal. two years. TVA states that the benefits was firm or non-firm.
(5) Denial of Service/Records Retention of extension are not commensurate with
the increased costs, since it is unaware (6) Designation and Termination of
NOPR Proposal Network Resources
of any problems that have arisen with
373. In the NOPR, the Commission the current three-year timeline. Seattle NOPR Proposal
proposed to maintain the requirement argues on reply that the Commission
that a transmission provider post the should retain the NOPR posting 378. In the NOPR, the Commission
reason for a denial of a request for requirements in the Final Rule because proposed to require the transmission
service. The Commission also proposed information on actual transmission provider and network customers to use
to amend this provision to require a congestion can be helpful instead of sole the transmission provider’s OASIS to
transmission provider to maintain and reliance on simulation models. request designation of a new network
make available information supporting resource and to terminate the
the reason for the denial. The 212 E.g., APPA, Arkansas Commission, Arkansas designation of a network resource. This
information would be posted on OASIS
sroberts on PROD1PC70 with RULES

Commission further proposed to extend Municipal, Duke, East Texas Cooperatives, MISO,
the time period for which transmission ISO New England, Williams, Nevada Companies, for 90 days and be available for audit for
PPL, Sacremento, Sant Clara, Suez Energy NA, and a five-year period. Transmission
providers must maintain transmission TDU Systems.
service information for audit. Currently, 213 E.g., MidAmerican, PacifiCorp, PNM–TNMP,
customers therefore would be able to
regulations require that audit data be and PJM. query such requests to designate and

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00049 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12314 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

terminate a network resource.214 The 383. Great Northern supports the posting of unused transfer capability.
Commission also proposed to require proposal and requests clarification that, TDU Systems state that the requirement
the transmission provider to post on its when a network resource is to post on OASIS all transfer capability
OASIS a list of its current designated ‘‘undesignated,’’ ATC will not be set associated with transmission
network resources and all network aside in anticipation that it might be reservations not scheduled in real time
customers’ current designated network designated again as a network resource furthers not only the Commission’s
resources. The list would include the in the future. Great Northern requests goals with respect to comparability and
resource name, geographic and that the Commission confirm that new transparency of ATC calculations, but
electrical location and amount of requests to designate network resources, also the Commission’s goals in freeing
capacity of the designated network regardless of the prior designation of up access to transmission capacity for
resource. those resources, are placed at the end of transmission customers.
the transmission service queue.
Comments 384. Sacramento states that the Commission Determination
379. Several commenters support the posting requirements for network 389. We affirm our statement in the
Commission’s proposal to require resources are an unnecessary burden NOPR proposal acknowledging that
transmission providers and network and instead recommends that the transfer capability associated with
customers to use the transmission transmission provider should be transmission reservations that are not
provider’s OASIS to request or required to identify resources it is scheduled in real time is required to be
terminate designation of resources, transmitting to native load when it made available as non-firm, and posted
though some indicated that the required denies a request for transmission service on OASIS.
network resource information is from a third party.
(8) Other OASIS Issues
currently available via OASIS.215 PJM Commission Determination
supports the proposal, provided that the Comments
electrical location is based on an 385. The Commission adopts the
390. MidAmerican, PacifiCorp and
industry standard format and any NOPR proposal and requires
Pinnacle contend that the development
standard adopted by NERC takes into transmission providers and network
of the OASIS posting requirements is
consideration possible confidentiality customers to use OASIS to request
technical in nature and should be
issues when posting the geographic designation of new network resources
addressed by the NERC and NAESB
location of designated network and to terminate designation of network
processes.
resources. resources.216 This information shall be
391. NRECA recommends that the
380. APPA suggests that reservations posted on OASIS for 90 days and
Commission require public utility
related to future load growth also available for audit for a five-year period.
transmission providers to make OASIS
should be posted so that it is clear to all Transmission customers thus shall be
data available in a useable, machine-
industry participants what transmission able to query requests to designate and
readable and manipulable format to
capacity transmission providers are terminate a network resource. This
transmission customers (so they can be
reserving for load growth purposes. requirement adds valuable transparency
better prepared to make decisions about
Williams submits that the list of current without undue burden, since it is
their transmission needs) and to the
designated resources needs to indicate nothing more than maintaining a
Commission (so that it can monitor the
whether they are for native load or database of designation requests made
provision of transmission service).
network customers, or whether they are and responded to electronically. The
Similarly, Powerex states that posted
for meeting forecasted loads and system Commission orders public utilities,
data must be in sufficient detail to
emergencies. working through NAESB, to develop
permit third parties to independently
appropriate templates for OASIS.
381. TranServ supports the 386. The requests for clarifications by review and verify ATC postings and
Commission’s proposal and indicates Exelon and Great Northern will not be treatment of transmission service
that NAESB is the appropriate forum for addressed in this section. These requests.
development of standards necessary to requests are not related to OASIS 392. Utah Municipals suggest that
support posting the designation and postings, but involve changes in tariff OASIS sites be as uniform and
termination of network resources. language. They are addressed in section compatible as possible and reasonably
TranServ cautions that implementation V.D.6 of this Final Rule. user-friendly, and that certificate fees
will require a sufficient period of time for access to non-public sites be
after the practices and standards are (7) Posting of Unused Transfer evaluated for legitimacy. Arkansas
developed and suggests that changes to Capability Commission and Seattle also express
OASIS should be timed to avoid peak NOPR Proposal concern over the OASIS access
summer and winter seasons. requirements established by most
387. In the NOPR, the Commission transmission providers, which require
382. Exelon requests that the reminded transmission providers that
Commission clarify that transmission viewers to purchase certificates or
transfer capability associated with licenses for the particular computers
providers and network customers transmission reservations that is not
making firm off-system sales may from which OASIS access is sought.
scheduled in real time should be 393. Williams suggests that all
terminate designation of network included in non-firm ATC and posted
resources solely for the term of such sale transmission service-related business
on OASIS. practices and local procedures,
and not for other periods of time. During
this period of termination, the firm Comments including the exercise of discretion or
capacity is posted and made available to waiver or granting of exception, be
388. Entegra, TANC, and TDU
sroberts on PROD1PC70 with RULES

other customers. posted on the transmission provider’s


Systems emphasize the need for the
OASIS. It also suggests that real-time
214 See
18 CFR 37.6(a)(6). 216 See paragraph 1477, where further detail on data and import/export limits by
215 E.g.,
APPA, Exelon, PJM, TAPS, TranServ, and using OASIS to request designation of network constrained area should be posted on
TDU Systems. resources is provided. OASIS, along with line outages

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00050 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12315

(planned and unplanned), estimated (9) CEII process to ensure timely resolution of
return to service dates and de-rates of a NOPR Proposal ATC calculation disputes and to adopt
line. measures that ensure that CEII claims do
397. Critical Energy Infrastructure not unduly restrict information.
Commission Determination Information (CEII) is information 400. EEI and Southern caution that
concerning proposed or existing critical the release of a transmission provider’s
394. In response to NRECA and other infrastructure (physical and virtual) that explanation of methodologies, practices,
commenters regarding the availability (1) Relates to the production, and procedures in Attachment C may
and format of data available on OASIS, generation, transportation, transmission not give rise to CEII concerns, but that
we note that current regulations already or distribution of energy, (2) could be other information such as energy
require that OASIS data be made useful to a person in planning an attack infrastructure data, models and
available in a useable, machine-readable on critical infrastructure, (3) is exempt assessments do raise security and
user friendly format to transmission from mandatory disclosure under the confidentiality concerns. They propose
customers. The improvements required Freedom of Information Act, 5 U.S.C. that a transmission provider have the
in the Final Rule will enhance the level 552, and (4) does not simply give the ability to seek confidential treatment of
of detail posted on OASIS and, in turn, location of the critical infrastructure.217 such information. Allegheny proposes
transmission customers’ ability to verify Access to such transmission related that an independent third party or
the transmission provider’s treatment of information has been restricted by the Commission staff review and explain
transmission requests. Thus, to the Commission’s CEII regulations.218 ATC calculations to interested parties
extent NRECA or others desire greater 398. In the NOPR, the Commission without disclosing CEII.
recognized that the use of the existing 401. Several commenters believe that
consistency in data formats, they should
CEII processes could undermine their much of the information the
propose such revisions through the
goal of providing increased Commission proposes to require
NERC and NAESB processes. transparency to information necessary transmission providers to provide will
395. Regarding comments received to evaluate the use of the transmission not pose CEII concerns.220 However,
expressing concern about the use of system. As a result, the Commission Entergy states that some of the
certificates for OASIS access, we believe requested comment on procedures that information requires protection as
that the use of such certificates can be could be adopted by transmission proprietary information because its
appropriate. However, the Commission providers to streamline the resolution of public availability over OASIS would
reminds transmission providers that the CEII concerns and allow timely reveal commercially sensitive
cost of OASIS access, whether by disclosure of information from the information. ISO New England also
registration, certificate or other form of transmission providers to interested points out that information relevant to
license, should be limited to a nominal parties. the ATC calculation may be market-
charge, e.g., no more than $100. This Comments sensitive
nominal fee provides funding for OASIS 402. Pinnacle believes the current
399. APPA and other commenters
maintenance while assuring that all CEII process is not unduly burdensome
argue that the additional information
transmission customers and potential and urges the Commission to continue
disclosure requirements proposed in the
customers will not be denied access to apply the existing CEII procedures,
NOPR raise substantial CEII concerns,
because of excessive fees. which allow transmission customers
and request the Commission to refine its
with digital certificates or passwords to
396. With respect to Williams’ request CEII procedures to allow those with
access publicly restricted transmission
for additional OASIS postings, we agree legitimate need for the information to
information.
that such additional data would be obtain it on a timely basis.219 Bonneville
useful to transmission customers and is would like to permit public access for Commission Determination
already posted on some ISO and RTO stakeholders to review principles and 403. The Commission acknowledges
Web sites and, to a lesser extent, on the methods used in ATC calculations, but that certain data and studies required to
NERC web site (TLR data). Therefore, only permit limited access, subject to be made public under this Final Rule
we require that all transmission service- background checks and non-disclosure may contain CEII. The Commission has
related business practices and local agreements, to modeling data that may a responsibility to protect this
procedures, including waivers, should compromise infrastructure security. information. However, the Commission
be posted on or made available through APPA suggests establishing a process for agrees with APPA, Bonneville, and TDU
OASIS. With respect to real-time data advance qualification for receipt of such Systems that those with a legitimate
information by those industry need for CEII information must be able
and import/export limits by constrained
participants with rights to review to obtain it on a timely basis. The
area, estimated return-to-service dates
information on the customer side of Commission also shares EEI and
and line de-ratings, we are confident
OASIS, without giving blanket public Southern’s concerns that the data,
that most of this data is already required access. TDU Systems urge the
by this Final Rule and shall be provided models and assessments used to
Commission to adopt a streamlined calculate ATC may contain information
whenever TTC and ATC changes in
value trigger the posting of a narrative that raises security and confidentiality
217 See Critical Energy Infrastructure Information,
concerns, and ISO New England and
explanation of the causes of those Order No. 683, 71 FR 58273 (Oct. 3, 2006), FERC
Stats. & Regs. ¶ 31,228 at P 66 (2006), reh’g pending. Entergy’s concerns about commercial
changes. Moreover, the Final Rule
We note that the Commission is proposing to and market-sensitive information.
requires a broad data exchange among change the definition of CEII in a proceeding in 404. In order to provide transparency
transmission providers, including Docket No. RM06–23–000. See Critical Energy and avoid undue delays in providing
sroberts on PROD1PC70 with RULES

information on line outages and other Infrastructure Information, Notice of Proposed


Rulemaking, 71 FR 58325 (Oct. 3, 2006), FERC information to those with a legitimate
data relating to ATC calculations. Stats. & Regs. ¶ 32,607 (2006). need for it, the Commission requires
Accordingly, we will not require 218 See 18 CFR 388.112–113.

additional OASIS postings for this data. 219 E.g., MidAmerican, Sacramento, Southern, 220 E.g., Nevada Companies, East Texas

and TVA. Cooperatives, PJM, and TDU Systems.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00051 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12316 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

transmission providers to establish a showing acceptances and denials of transmission provider, because the
standard disclosure procedure for CEII transmission service requests of non- metrics can lead to incorrect
required to be disclosed by this Final affiliates and affiliates.222 However, PJM impressions. MidAmerican also states
Rule. We note that transmission and Ameren argue that the affiliate that the proposed posting would require
customers already have digital posting requirement should not apply to sophisticated analysis to yield useful
certificates or passwords to access RTOs and ISOs, because they are benefits.
publicly restricted transmission independent, have no affiliates, and lack 410. EEI is not opposed to the
information on OASIS. Transmission incentive to favor one transmission proposal to post metrics on acceptance
providers may set up an additional login customer over another. MDEA requests and denial of requests for transmission
requirement for users to view CEII clarification on how the additional service, but suggests such information is
sections of the OASIS, requiring users to posting requirements would be applied already available on OASIS and that any
acknowledge that they will be viewing under Entergy’s weekly procurement customer or the Commission staff can
CEII information. Transmission process. Entergy notes on reply that the develop its own metrics. Southern also
providers may require customers to sign Commission has already established states that this data is currently
a nondisclosure agreement at the time metrics to measure the performance of available.
that the customer obtains access to this its weekly procurement process, and the 411. Several commenters support the
portion of the OASIS. Only information creation of further metrics are beyond posting of forecast and actual daily peak
that meets the criteria for CEII, as the scope in a generic rulemaking. loads.223 Ameren states that the
defined in section 388.113 of the Entergy further points out that non- proposed requirement would produce a
Commission’s regulations,221 should be affiliated generating facilities that are useful comparison, increase
posted in this section of the OASIS. designated as network resources to serve transparency, and provide the ability to
Transmission providers will be native load also benefit from verify that an appropriate amount of
responsible for identifying CEII and transmission service obtained in this capacity is being set aside for native
facilitating access to it by appropriate manner. It suggests that NAESB is the load. E.ON states that RTO and ISO
entities, and the Commission will be best forum for considering such issues forecasts and actual data need to be
available to resolve disputes if they and developing specific procedures for posted with sufficient granularity to
arise. calculating these metrics. TranServ allow for meaningful comparison of
suggests that there are other useful control area and LSE load levels. EEI
(10) Additional Data Posting requests that the Commission clarify
metrics that NAESB should be directed
NOPR Proposal to define, such as average time to that its proposal to require the posting
405. To further reduce discretion in evaluate requests and confirm requests, of peak loads applies to system-wide
calculating ATC/AFC, the Commission and percentage of requests denied, loads and not only to the native load of
proposed that transmission providers approved and withdrawn. the transmission provider. It also seeks
post on OASIS metrics related to the 407. PJM notes its support of clarification that the differences
provision of transmission service under proposed OASIS posting reforms, but between forecast and actual system peak
their OATT. In the NOPR, the cautions that all industry groups must loads not result in any repercussions.
Commission proposed to require the have an equitable and proportionate 412. APPA members in the East
monthly posting of (1) The number of voice in NAESB if it is requested to generally favor the proposal to post the
affiliate versus non-affiliate requests for develop standards. It also expresses load information, but its members in the
transmission service that have been concern that PJM and other RTOs have West expressed concerns about the
rejected and (2) the number of affiliate established a practice of posting a competitive implications of providing
versus non-affiliate requests for significant amount of data for such data. Additional commenters
transmission service that have been participants’ use in formats and express concern about data
made. This posting would also detail applications which respective members confidentiality.224 TAPS contends that
the length of service request (e.g., short- have requested and approved through providing for data disclosure on a one-
term or long-term) and the type of stakeholder processes. day lag basis would alleviate these
service requested (e.g., firm point-to- 408. APPA points out that the data on commercial concerns, but it also
point, non-firm point-to-point or transmission denials would be useful to suggests that the Commission should
network service). The Commission the Department of Energy (DOE) in require the disclosure of projected load
sought comments regarding whether it reporting on congestion in its triennial forecast information on request to a
should require transmission providers congestion studies to be prepared under customer’s non-market employees or
to post their underlying load forecast FPA section 216(a), and that NAESB agents.
assumptions for all ATC calculations may be able to provide standard formats
Commission Determination
and, on a daily basis their actual daily for disclosure of such data. Some APPA
members express a preference for NERC 413. The Commission adopts the
peak load for the prior day. Finally, the
to develop these standards, while others proposed requirement to post on OASIS
Commission asked for comment on the
stress the need for regional variation in metrics related to the provision of
overall benefit of posting the proposed
posting requirements. transmission service under the OATT.
metrics, on potential alternative metrics,
409. Ameren questions whether the Specifically, transmission providers
and on working through NAESB to
posting requirement would serve the must post (1) The number of affiliate
develop standards for consistent
Commission’s objective of identifying versus non-affiliate requests for
methods of posting the new
undue discrimination even in cases transmission service that have been
requirements on OASIS.
where the transmission provider is not rejected and (2) the number of affiliate
Comments an RTO or other independent versus non-affiliate requests for
sroberts on PROD1PC70 with RULES

406. PJM and other commenters 222 E.g., Arkansas Commission, Constellation, 223 E.g., Ameren, Constellation, E.ON, Nevada
support the proposal to post data MidAmerican, MDEA, Morgan Stanley, Nevada Companies, NRECA, Powerex, Suez Energy NA,
Companies, NRECA, Suez Energy NA, and TAPS, TDU Systems, and TranServ.
221 18 CFR 388.113. TranServ. 224 E.g., E.ON, Entergy, LDWP, and TranServ.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00052 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12317

transmission service that have been held accountable for producing a the part of the transmission provider for
made. This posting must detail the reasonable load forecast. While we do point-to-point service is found in
length of service request (e.g., short-term not intend to penalize transmission section 15.4 of the pro forma OATT,
or long-term) and the type of service providers for failing to account for which provides that, when a
requested (e.g., firm point-to-point, non- unforeseen circumstances, we retain our transmission provider cannot
firm point-to-point or network service). ability to investigate any allegations of accommodate a request for point-to-
The Commission also will require manipulation of load forecasts, as this point transmission because of
transmission providers to post their could be used as a means of insufficient capability on its system, it
underlying load forecast assumptions inappropriately denying requested will ‘‘use due diligence to expand or
for all ATC calculations and, to post on transmission service. modify its Transmission System to
a daily basis, their actual daily peak 417. The Commission is not provide the requested Firm
load for the prior day. The Commission convinced by the views of some Transmission Service.’’ Section 15.4
directs transmission providers to work commenters that load data has goes on to provide that ‘‘the
through NAESB to develop standards competitive implications. The Transmission Provider will conform to
for consistent methods of posting the Commission notes, as PJM pointed out Good Utility Practice in determining the
new requirements on OASIS. in its comments, that many RTOs have need for new facilities and in the design
414. The Commission agrees with PJM an established practice of posting and construction of such facilities.’’ The
and Ameren that affiliate posting significant amounts of load data for transmission provider’s obligation to
requirements do not apply to RTOs and participants’ use, and this data posting upgrade or expand its system to provide
ISOs, since they do not have affiliates to has not raised competitive concerns. point-to-point service as detailed in
transact with. The Commission also
B. Coordinated, Open and Transparent section 15.4 is contingent on the
agrees with Entergy that the metrics
Planning transmission customer agreeing to
established for its weekly procurement
compensate the transmission provider
process are outside the scope of this 1. The Need for Reform for such costs pursuant to the terms of
proceeding.
415. In response to Southern’s point 418. Order No. 888 set forth certain section 27 (providing for cost
that the information necessary to minimum requirements for transmission responsibility for upgrades and/or
compute the metrics is already available system planning. For example, Order redispatch ‘‘to the extent consistent
on OASIS, while it is true that service No. 888 and the pro forma OATT with Commission policy’’).
denial information is available on require that transmission providers plan 420. In Order No. 888–A, the
OASIS for long periods, request and upgrade their transmission systems Commission encouraged utilities to
information is not. As such, a customer to provide comparable open access engage in joint planning with other
would need to continuously download transmission service for their utilities and customers and to allow
information from OASIS to record the transmission customers. With regard to affected customers to participate in
data sufficient to calculate the metrics network service, section 28.2 of the pro facilities studies to the extent
on its own. The Commission concludes forma OATT provides that the practicable. The Commission also
that it is not unduly burdensome for transmission provider ‘‘will plan, encouraged regional planning so that
transmission providers to calculate the construct, operate and maintain its the needs of all participants are
metrics required by this Final Rule. Transmission System in accordance represented in the planning process.225
416. With regard to posting of load with Good Utility Practice in order to Order No. 888–A did not, however,
forecasts and actual daily peak load, we provide the Network Customer with require that transmission providers
conclude that such postings are Network Integration Transmission coordinate with either their network or
necessary to provide transparency for Service over the Transmission point-to-point customers in
transmission customers. We agree with Provider’s Transmission System.’’ transmission planning or otherwise
E.ON that RTO and ISO load data needs Section 28.2 also provides that the publish the criteria, assumptions, or
to be posted at a sufficient granularity Transmission Provider shall, consistent data underlying their transmission
to allow for meaningful comparison of with Good Utility Practice, ‘‘endeavor to plans. The Commission also did not
control area and LSE load levels. Most construct and place into service require joint planning between
RTOs and ISOs post load data for the sufficient transfer capability to deliver transmission providers and their
entire footprint, but few post it on an the Network Customer’s Network customers or between transmission
LSE or control area basis. We therefore Resources to serve its Network Load on providers in a given region.226 The only
direct ISOs and RTOs to post load data a basis comparable to the Transmission section of the existing pro forma OATT
for the entire ISO/RTO footprint and for Provider’s delivery of its own generating that directly speaks to joint planning is
each LSE or control area footprint and purchased resources to its Native section 30.9, which provides that a
within the ISO/RTO. This will not Load Customers.’’ network customer must receive credit
create an undue burden on ISOs and 419. The pro forma OATT also
when facilities constructed by the
RTOs, since the load data for the entire requires that new facilities be
customer are jointly planned and
footprint is an aggregation of load data constructed to meet the service requests
installed in coordination with the
across the LSEs or control areas in the of long-term firm point-to-point
transmission provider.227
footprint. We also agree with EEI that customers. Section 13.5 of the pro forma
the peak load applies to system-wide OATT requires the transmission 225 See Order No. 888–A at 30,311.
load, including native load. We direct provider to consider redispatch of the 226 See id.
transmission providers to post load system to relieve any constraints that 227 Pro forma OATT section 21.2, ‘‘Coordination
forecasts and actual daily peak load for are inhibiting a transmission customer’s of Third-Party System Additions,’’ provides for
sroberts on PROD1PC70 with RULES

both system-wide load (including native point-to-point service if it is economical certain rights for transmission providers to
load) and native load, as this data will to do so; but if redispatch is not coordinate construction of facilities on their
systems associated with point-to-point customer
be useful to customers and regulators. economical, the transmission provider requests and related construction on a third-party
We deny EEI’s request for a guarantee is obligated to expand or upgrade its transmission system, but imposes no obligation on
that transmission providers will not be system. This expansion obligation on transmission providers.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00053 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12318 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

421. As the Commission stated in the transmission or to offer transmission on also is no requirement that the key
NOPR, the Nation has witnessed a a basis that is inferior to that which they assumptions and data that underlie
decline in transmission investment provide themselves.’’ 229 The court transmission plans be made available to
relative to load growth in the ten years agreed on review of Order No. 888, customers.
since Order No. 888 was issued. noting in TAPS v. FERC that ‘‘[u]tilities 425. Taken together, this lack of
Transmission capacity per MW of peak that own or control transmission coordination, openness, and
demand has declined in every NERC facilities naturally wish to maximize transparency results in opportunities for
region. Transmission constraints plague profit. The transmission-owning utilities undue discrimination in transmission
most regions of the country, as reflected thus can be expected to act in their own planning. Without adequate
in the limited amounts of ATC posted interest to maintain their monopoly and coordination and open participation,
in many regions, increased frequency of to use that position to retain or expand market participants have no means to
denied transmission requests, the market share for their own generated determine whether the plan developed
increasingly common transmission electricity, even if they do so at the by the transmission provider in
service interruptions or curtailments expense of lower-cost generation isolation is unduly discriminatory. This
and rising congestion costs in organized companies and consumers.’’ 230 The means that disputes over access and
markets.228 Supreme Court in New York v. FERC discrimination occur primarily after-the-
422. We do not believe that the similarly explained that ‘‘public utilities fact because there is insufficient
existing pro forma OATT is sufficient in retain ownership of the transmission coordination and transparency between
an era of increasing transmission lines that must be used by their transmission providers and their
congestion and the need for significant competitors to deliver electric energy to customers for purposes of planning.233
new transmission investment. We wholesale and retail customers. The The Commission has a duty to prevent
cannot rely on the self-interest of utilities’ control of transmission undue discrimination in the rates,
transmission providers to expand the facilities gives them the power either to terms, and conditions of public utility
grid in a nondiscriminatory manner. refuse to deliver energy produced by transmission service and, therefore, an
Although many transmission providers competitors or to deliver competitors’ obligation to remedy these transmission
have an incentive to expand the grid to power on terms and conditions less planning deficiencies. As we explain
meet their State-imposed obligations to favorable than those they apply to their above, our authority to remedy undue
serve, they can have a disincentive to own transmissions.’’ 231 discrimination is broad.234 In addition,
remedy transmission congestion when 424. The existing pro forma OATT new section 217 of the FPA requires the
doing so reduces the value of their does not counteract these incentives in Commission to exercise its jurisdiction
generation or otherwise stimulates new the planning area because there are no in a manner that facilitates the planning
entry or greater competition in their clear criteria regarding the transmission and expansion of transmission facilities
area. For example, a transmission provider’s planning obligation. to meet the reasonable needs of LSEs. A
provider does not have an incentive to Although the pro forma OATT contains more transparent and coordinated
relieve local congestion that restricts the a general obligation to plan for the regional planning process will further
output of a competing merchant needs of their network customers and to these priorities, as well as support the
generator if doing so will make the expand their systems to provide service DOE’s responsibilities under EPAct
transmission provider’s own generation to point-to-point customers, there is no 2005 section 1221 to study transmission
less competitive. A transmission requirement that the overall congestion and issue reports designating
provider also does not have an incentive transmission planning process be open National Interest Electric Transmission
to increase the import or export capacity to customers, competitors, and State Corridors and the Commission’s
of its transmission system if doing so commissions.232 Rather, transmission responsibilities under EPAct 2005
would allow cheaper power to displace providers may develop transmission section 1223.
its higher cost generation or otherwise plans with limited or no input from
make new entry more profitable by customers or other stakeholders. There NOPR Proposal
facilitating exports. 426. In order to provide for more
423. As the Commission explained in 229 Order No. 888 at 31,682. comparable open access transmission
Order No. 888, ‘‘[i]t is in the economic 230 225 F.3d at 684.
service, limit the potential for undue
231 535 U.S. at 8–9 (citation and footnotes
self-interest of transmission discrimination and anticompetitive
omitted).
monopolists, particularly those with 232 As discussed in more detail in the NOPR, the conduct, and satisfy its statutory
high-cost generation assets, to deny need for reform was recognized by the Consumer responsibilities under section 217 of the
Energy Council of America (CECA), a public FPA, the Commission proposed to
228 The number of TLRs has increased interest energy policy organization with a 30-year
significantly since NERC started reporting annual history of bringing stakeholders together to find amend the pro forma OATT to require
statistics. The total number of TLRs each year has solutions to contentious energy policy issues. CECA coordinated, open, and transparent
grown from under 500 in 1998 and 1999 to around launched its Transmission Infrastructure Forum in transmission planning on both a local
2000 over the last four years from 2002 to 2006. The early 2004, which published its conclusions in and regional level. Each public utility
number of TLR actions at the highest levels, January 2005 in a final report titled ‘‘Keeping the
requiring curtailment of firm transmission flows, Power Flowing: Ensuring a Strong Transmission
233 In our discussion of enforcement issues at
has also grown, from under 10 before 2001 to 70 System to Support Consumer Needs for Cost-
in 2006, averaging 55 per year from 2003 to 2006. Effectiveness, Security and Reliability’’ (CECA section V.E of this Final Rule, we note specific
Source: NERC Web site, ftp://www.nerc.com/pub/ Report). Among other things, the CECA Report situations in which transmission providers have
sys/all_updl/oc/scs/logs/trends.htm. In addition, concludes that regional transmission planning with agreed to resolve staff allegations that they engaged
congestion costs continue to be a major issue in consumer input early in the process is needed to in OATT violations involving transactions with
RTO markets. For example, congestion costs in PJM ensure the development of a robust transmission affiliates. While these specific situations may not
were $2.09 billion in calendar year 2005, which was system capable of meeting consumer needs reliably directly relate to discrimination in planning, they
a 179 percent increase over 2004. Although this and at reasonable cost over time. The CECA Report nevertheless document the continuing incentive of
sroberts on PROD1PC70 with RULES

increase resulted primarily from increases in PJM stresses that regional transmission planning must transmission providers to favor themselves and
annual billings, the congestion costs in both years address inter-regional coordination, the need for their affiliates in the provision of transmission
were approximately 9 percent of total PJM billings both reliability and economic upgrades to the service.
in both years and have ranged from 6 percent to 10 system, and critical infrastructure to support 234 See Order No. 888 at 31,669 (noting that the

percent of total billings since 2000. Source: 2005 national security and environmental concerns. See FPA ‘‘fairly bristles’’ with concern for undue
PJM State of the Markets Report, April 2006. NOPR at P 207. discrimination (citing AGD, 824 F.2d at 998).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00054 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12319

transmission provider would be transmission projects and, given that planning efforts. In its reply, WPS
required to submit, as part of its such projects can take years to opposes MISO’s proposal to be exempt
compliance filing in this proceeding, a construct, whether the planning process from the NOPR’s planning
proposal for a coordinated and regional should be required to look out at least requirements, arguing that the MISO
planning process that complies with the as far as the longest time it would take process is not open and only aggregates
following eight planning principles: to build such an upgrade in the region the plans of the transmission providers.
Coordination, openness, transparency, in question. Finally, the Commission 432. EEI takes issue with broad
information exchange, comparability, sought comment on the level of detail to statements in the NOPR that assert that
dispute resolution, regional be required in transmission providers’ transmission providers have a
participation, and congestion studies. In OATTs. disincentive to remedy transmission
the alternative, transmission providers congestion and to plan their
Comments transmission systems on a comparable
could make a compliance filing in this
proceeding describing their existing 429. Most commenters support the basis. Other individual investor-owned
coordinated and regional planning development of coordinated, open, and utilities also assert that the record does
processes and showing that they are transparent planning. While differing on not support the NOPR’s claims that a
consistent with or superior to that how they should be implemented, mandatory coordinated, open, and
required in the Final Rule. commenters express broad support for transparent planning process is
427. The Commission stated that it the eight planning principles,235 though necessary to remedy undue
expected non-public utility all RTOs and ISOs and many investor- discrimination.238 Many others,
transmission providers to participate in owned utilities believe that their however, believe the NOPR correctly
the proposed planning processes, given planning processes already comply with diagnoses the problem of
that effective regional planning cannot the proposals in the NOPR. ISO/RTO discrimination.239
occur without the participation of all Council, as well as individual RTOs and 433. Most commenters do not
transmission providers, owners, and ISOs, advance the position that RTOs question the Commission’s jurisdiction
customers. Although the Commission and ISOs already meet the planning to address the transmission planning
encouraged the use of an independent requirements in the NOPR, that there process generally. Southern, however,
third party to oversee or coordinate the has been no credible case made for argues that the Commission has no
planning process, the NOPR did not reopening their already approved general authority in this area and that
propose to require it. The Commission planning processes, and that RTOs and section 217 of the FPA does not grant
also strongly encouraged the ISOs should be exempt from complying the Commission any additional
participation of State commissions and with the NOPR’s planning principles. jurisdiction to impose a regional
other State agencies in planning 430. Some transmission providers planning requirement.240 FMPA
activities. agree that RTOs already meet the counters that the Commission has FPA
428. The Commission sought principles, and others argue against authority to cure undue discrimination
comment on several aspects of the commenters who maintain that RTOs and to ensure ‘‘just and reasonable’’
NOPR proposal. First, the Commission ‘‘rubber stamp’’ transmission provider transmission rates and terms by
inquired as to the level of flexibility plans.236 For example, MISO asserts that adopting transmission planning
each transmission provider should be it conducts an open planning process criteria.241 In their replies, APPA and
given in implementing any principles and does not ‘‘rubber stamp’’ projects. TAPS agree with the Commission that
adopted. Second, the Commission Duke concurs with MISO, stating that FPA section 217(b)(4) can be cited as
sought comment, by way of example, on there are abundant opportunities for legal support for transmission planning.
transmission planning processes that participation in the MISO planning In its reply, NRECA stresses that the
comply with the NOPR reforms in process. Xcel also replies in support of transmission planning process must
principle. Third, the Commission the MISO process. focus, consistent with FPA section
sought comment on whether there are 431. Several transmission customers, 217(b)(4), on the reasonable long-term
other principles or requirements that however, argue that current RTO needs of LSEs, not all users of the
should be adopted to support the processes are insufficient because, system as argued by EPSA and NRG.
construction of needed new among other things, they merely accept Santee Cooper urges the Commission to
infrastructure and otherwise ensure that the transmission owners’ plans and only be mindful of the limits of its
all market participants are treated on a provide for after-the-fact input, thus jurisdiction in establishing study
comparable basis. Specifically, the failing to satisfy the planning principles requirements that may delve into
Commission inquired: (a) Whether there proposed in the NOPR.237 Old generation resource adequacy or issues
should be a principle or guideline to Dominion also asserts that RTOs related to the mix of generation. Other
govern the recovery and allocation of generally approve transmission owner commenters urge the Commission not to
costs associated with funding the identified upgrades, which give them impinge on State jurisdiction.242 In its
regional planning requirement; (b) the advantage of having their own reply, LPPC emphasizes that the
whether there should be a requirement parochial plans incorporated into the Commission’s expectation that public
that, at least for large new transmission regional plan without any separate power entities will participate is
projects, there be an open season to evaluation or complete stakeholder
allow market participants to participate input. TAPS asserts that open planning 238 See, e.g., Duke and Southern.
239 See, e.g., APPA and EPSA. However, NRG and
in joint ownership of these projects; (c) should apply both to the RTO and the
Reliant believe that the planning process outside of
whether there should be a specific study underlying transmission owners’ RTOs is fundamentally flawed and cannot be
process to identify opportunities to remedied by the NOPR’s planning proposal.
enhance the grid for purposes beyond 235 The one exception is the congestion studies 240 Progress Energy also claims that the
sroberts on PROD1PC70 with RULES

maintaining reliability or reducing requirement, which is generally opposed by Commission does not have any jurisdiction to
transmission providers and supported by mandate regional planning.
current congestion; and, (d) whether customers. 241 See also TAPS Reply.
public utilities should be required to 236 E.g., Duke, Exelon, and Xcel. 242 See, e.g., Nevada Companies, New Mexico
develop cost allocation principles to 237 E.g., Indicated Parties Reply, Old Dominion, Attorney General, North Carolina Commission
address the sharing of the costs of new NRECA, and TAPS. Reply, and Southern.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00055 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12320 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

sufficient and asserts that there is no existing OATT is insufficient to address obligations included in this Final Rule
reason to take further action that might that concern. do not address whether or how
test the limits of jurisdiction under FPA 436. New section 217 of the FPA investments identified in a transmission
section 211A.243 further supports reform in this area, as plan should be compensated. Through
it reflects Congress’ intent that the the principles described below, we
434. WIRES endorses several planning
Commission utilize its powers to establish a process through which
objectives it believes to be critical to
facilitate the planning and expansion of transmission providers must coordinate
successful planning. These objectives the transmission system.245 Through with customers, neighboring
include open and transparent planning EPAct 2005 sec. 1223, Congress also transmission providers, affected State
procedures, a long-term planning directed the Commission to encourage authorities, and other stakeholders in
horizon, broad-based inclusion of the deployment of advanced order to ensure that transmission plans
reliability, economic, efficiency and transmission technologies in are not developed in an unduly
environmental considerations in infrastructure improvements, including discriminatory manner.
planning, clear conditions under which among others optimized transmission 439. As for the application of the
a transmission owner will commit to line configurations (including multiple Final Rule’s coordinated planning
build planned facilities, and provision phased transmission lines), controllable requirement to RTOs and ISOs, which
for fair and efficient allocation of the load, distributed generation (including already have a Commission-approved
costs of planned facilities. WIRES also PV, fuel cells, and microturbines), and transmission planning process on file
emphasizes the importance of enhanced power device monitoring. with us, we note that the intent of our
considering non-transmission 437. Accordingly, each public utility reform in this Final Rule is not to
alternatives, arguing that an appropriate transmission provider is required to reopen prior approvals, but rather to
grid plan must be based on an integrated submit, as part of a compliance filing in ensure that the transmission planning
view of all alternatives, including this proceeding, a proposal for a process utilized by each RTO and ISO
demand response and distributed coordinated and regional planning is consistent with or superior to the
generation. process that complies with the planning planning process adopted here. When
principles and other requirements in the Commission approved the existing
Commission Determination this Final Rule.246 In the alternative, a RTO and ISO transmission planning
435. In order to limit the transmission provider (including an processes, they were found to be
opportunities for undue discrimination RTO or an ISO, as discussed below), consistent with or superior to the
may make a compliance filing in this existing pro forma OATT. Because the
described above and in the NOPR, and
proceeding describing its existing pro forma OATT is being reformed by
to ensure that comparable transmission
coordinated and regional planning this Final Rule, it is necessary for each
service is provided by all public utility
process, including the appropriate RTO and ISO to now either reform its
transmission providers, including RTOs process or show that its planning
language in its tariff, and show that this
and ISOs, the Commission concludes process is consistent with or superior to
existing process is consistent with or
that it is necessary to amend the existing superior to the requirements in this the pro forma OATT, as modified by the
pro forma OATT to require coordinated, Final Rule. Under either of these Final Rule.
open, and transparent transmission approaches, the process must be 440. We also make clear that
planning on both a local and regional documented as an attachment to the transmission owning members of ISOs
level. We disagree with commenters transmission provider’s OATT. and RTOs must participate in the
arguing either that we lack jurisdiction 438. At the outset, we note that the planning processes adopted in this Final
to require coordinated transmission planning obligations imposed in this Rule. In order for an RTO’s or ISO’s
planning or that we have not established Final Rule do not address or dictate planning process to be open and
a basis for such a requirement. The which investments identified in a transparent, transmission customers and
Commission has broad authority to transmission plan should be undertaken stakeholders must be able to participate
remedy undue discrimination by by transmission providers. Furthermore, in each underlying transmission
ensuring that transmission providers except for the discussion below of cost owner’s planning process. This is
plan for the needs of their customers on allocation for transmission investments important because, in many cases, RTO
a comparable basis.244 That under Principle 9, the planning planning processes may focus
fundamental requirement was adopted principally on regional problems and
in Order No. 888 and the reforms 245 FPA section 217(b)(4) provides that ‘‘[t]he solutions, not local planning issues that
adopted herein should ensure that it Commission shall exercise the authority of the may be addressed by individual
Commission under [the FPA] in a manner that transmission owners. These local
will be implemented properly. Further, facilitates the planning and expansion of
we explained in detail above why transmission facilities to meet the reasonable needs
planning issues, however, may be
undue discrimination remains a concern of load-serving entities to satisfy the service critically important to transmission
in the planning area and why the obligations of the load-serving entities, and enables customers, such as those embedded
load-serving entities to secure firm transmission within the service areas of individual
rights (or equivalent tradable or financial rights) on
243 Other jurisdictional arguments primarily relate a long term basis for long term power supply
transmission owners. Consequently, the
to the question of joint ownership, in which some arrangements made, or planned, to meet such intent of the Final Rule will not be
commenters argue that the Commission lacks needs.’’ realized if only the regional planning
jurisdiction to mandate joint ownership 246 The pro forma OATT, as modified by this
process conducted by the RTOs and
arrangements. See, e.g., Duke, EEI, National Grid, Final Rule, reflects the proposed planning
Northeast Utilities, PSEG, and Southern. FMPA and
ISOs is shown to be consistent with or
requirement in sections 15.4, 16.1, 17.2(x), 28.2,
others, however, argue that the Commission does 29.2, 31.6. The planning process itself will be
superior to the Final Rule. To ensure
have the authority to order joint ownership. Joint included as Attachment K to the pro forma OATT. full compliance, individual
sroberts on PROD1PC70 with RULES

ownership will be discussed more fully below. We understand that some transmission providers transmission owners must, to the extent
244 See AGD, 824 F.2d at 1008 (Commission has may already have attachments to their OATTs that they perform transmission planning
broad discretion to promulgate generic rules to labeled with the letter ‘‘K,’’ in which case
eliminate undue discrimination without transmission providers are free to label their
within an RTO or ISO, comply with the
‘‘conduct[ing] experiments in order to rely on the planning process OATT attachment with the next Final Rule as well. Without such a
prediction that an unsupported stone will fall’’). available letter. requirement, the more regional RTO or

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00056 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12321

ISO planning process will not comply processes required by this Final Rule, 2. Planning Principles
with the requirements of the Final Rule the Commission may exercise its 444. We set forth below the planning
to the extent they incorporate and rely authority under section 211A on a case- principles that must be satisfied for a
on information prepared by underlying by-case basis. Further, we note that transmission provider’s planning
transmission owners that, in turn, have reciprocity dictates that non-public process to be considered compliant with
not complied with the Final Rule. utility transmission providers that take the Final Rule. The NOPR identified
Accordingly, as part of their compliance advantage of open access due to eight such principles, but based on the
filings in this proceeding, RTOs and improved planning should be subject to comments received the Commission
ISOs must indicate how all participating the same requirements as jurisdictional will require compliance with nine—the
transmission owners within their transmission providers. original eight plus a cost allocation
footprint will comply with the planning 442. In sum, each OATT planning principle, as described further below.
requirements of this Final Rule. While process attachment must incorporate the
we leave the mechanics of such transmission planning principles and a. Coordination
compliance to each RTO and ISO, we concepts in this Final Rule and must be 445. In the NOPR, the Commission
emphasize that the RTO’s or ISO’s filed with the Commission within 210 proposed that transmission providers
planning processes will be insufficient days after the publication of the Final must meet with all of their transmission
if its underlying transmission owners Rule in the Federal Register. customers and interconnected neighbors
are not also obligated to engage in Alternatively, RTOs, ISOs, and other to develop a transmission plan on a
transmission planning that complies transmission providers that currently nondiscriminatory basis. We sought
with Final Rule.247 have planning processes they believe comment on specific requirements for
441. The Commission also expects all comply with the Final Rule may make this coordination, such as the minimum
non-public utility transmission a filing with the Commission number of meetings to be required each
providers to participate in the planning documenting those processes in an year, the scope of the meetings, the
processes required by this Final Rule. A OATT attachment and explaining how notice requirements, the format, and any
coordinated, open, and transparent their planning processes are consistent other features deemed important by
regional planning process cannot with or superior to the planning process commenters.
succeed unless all transmission owners adopted here. Such filings must also be
submitted within 210 days after the Comments
participate. We are encouraged, based
on the representations of LPPC and publication of the Final Rule in the 446. Commenters express universal
others, that non-public utility Federal Register. support for the general concept of
transmission providers will fully 443. In order to assist transmission coordination, but differ on how specific
participate in such processes. We providers in complying with the Final the requirement should be. Several
Rule, and ensure that the planning commenters argue that the requirement
therefore do not believe it is necessary
procedures are developed with that transmission providers ‘‘must
at this time to invoke our authority
customer and stakeholder participation, meet’’ with customers and utilities is
under FPA section 211A, which gives us
the Commission will convene staff unrealistic.249 EEI requests that the
authority to require non-public utility
technical conferences in several broad Commission clarify that transmission
transmission providers to provide
regions around the country to discuss providers will be responsible for
transmission services on a comparable
regional implementation and other coordinating with customers and
and not unduly discriminatory or
compliance issues in advance of the holding meetings, but that the
preferential basis.248 If we find on the
compliance date. We extend an requirement to meet should be limited
appropriate record, however, that non-
invitation to State regulatory to making reasonable efforts to meet
public utility transmission providers are commissions to participate in these
not participating in the planning with all customers. NRECA asks on
technical conferences with our staff in reply that the Commission make clear
247 We understand that there are some
order to ensure that State concerns are that the lack of full participation by
transmission owners in RTOs or ISOs that continue fully addressed. The Commission will some nonjurisdictional utilities that take
to have OATTs on file under which they provide endeavor to hold the technical network service under the OATT should
service over certain transmission facilities that they conferences 90 to 120 days after the not excuse the transmission provider’s
did not turn over to the operational control of the publication of the Final Rule in the
RTO or ISO. Like any other transmission provider, obligation to engage in transmission
Federal Register. To facilitate these
those entities must submit a compliance filing to planning. NRECA states that inclusion
their OATTs that satisfies all requirements of this conferences, each transmission provider
in the planning process must be an
Final Rule, including the inclusion of an should, within 75 days after the
attachment governing their own planning opportunity for LSEs, not an obligation.
publication of the Final Rule in the 447. Other commenters express a
procedures. As we explain elsewhere, the
compliance filing deadline for transmission owning
Federal Register, post a ‘‘strawman’’ more general concern that the
participants in RTOs and ISOs shall be the same as proposal for compliance with each of Commission not be prescriptive with
the RTO and ISO deadline, i.e., 210 days after the planning principles adopted in the respect to meeting requirements.250 For
publication of the Final Rule in the Federal Final Rule, including a specification of
Register. example, most commenters generally
the broader region in which it will
248 FPA section 211A(b) provides, in pertinent believe the Commission should not
part, that ‘‘the Commission may, by rule or order, conduct coordinated regional planning.
prescribe rigid rules regarding the
require an unregulated transmitting utility to This strawman may be posted on the
number of meetings that must be held
provide transmission services—(1) At rates that are transmission provider’s OASIS, or its
comparable to those that the unregulated Web site if it does not have its own 249 E.g., Allegheny, Duke, EEI, International
transmitting utility charges itself; and (2) on terms
and conditions (not relating to rates) that are
OASIS (e.g., in the case of a Transmission, MidAmerican, NorthWestern, and
comparable to those under which the unregulated transmission owning member of an RTO SCE.
sroberts on PROD1PC70 with RULES

transmitting utility provides transmission services or ISO that does not have its own 250 E.g., Allegheny, APPA, Bonneville, California

to itself and that are not unduly discriminatory or OATT). We strongly urge transmission Commission, Duke, Entergy, Imperial, International
preferential.’’ The non-public utility transmission Transmission, MidAmerican, NCEMC, NC
providers referred to in this Final Rule include
providers to consult with their Transmission Planning Participants Reply,
unregulated transmitting utilities that are subject to stakeholders in the development of this NorthWestern, NRECA, Pinnacle, Progress Energy,
FPA section 211A. strawman. CREPC, Santee Cooper, SCE, TVA, and WAPA.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00057 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12322 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

each year. Xcel, however, suggests that planning models, including the to meet with customers and other
a minimum of three meetings a year assumptions and criteria that go into stakeholders that choose not to meet.
would be appropriate. Progress notes these models, and in the development of Transmission providers cannot force
that coordination in North Carolina the base case and change case for study others to meet with them. Transmission
already occurs as a result of regular purposes, particularly as to the providers are, however, required to craft
meetings throughout the year. Nevada identification and projection of loads a process that allows for a reasonable
Companies believe that meetings should and resources.254 Progress and and meaningful opportunity to meet or
be dependent on need and should not Southern, however, argue in replies that otherwise interact meaningfully. We
be programmatically established. TDU giving customers equal weight in also clarify that the coordination
Systems recommend at least monthly decision-making crosses the line from requirements imposed in this Final Rule
meetings, but stress that meetings planning to control by third parties, and are intended to address transmission
should be as frequent as is required to Southern believes this would be planning issues, and are not intended to
specify and perform the studies forming opposed by State regulators. provide a forum for ancillary issues,
the basis for the plan. NCPA believes Commission Determination such as specific siting concerns, which
that the minimum requirements are not are better addressed elsewhere. As for
as important as how they can be 451. The Commission adopts the NRECA’s concern that transmission
monitored or enforced to ensure that coordination principle proposed in the providers must plan for their
true participation indeed occurs. NOPR. Commenters overwhelmingly nonjurisdictional network customers
448. Seattle suggests 30 days notice desire flexibility as to the coordination even if they decline to fully participate
for meetings and that information principle, and as such, we will not in the planning process, a transmission
regarding meetings be posted at least prescribe the requirements for provider cannot be expected to
one week in advance. Entergy finds a coordination, such as the minimum effectively plan for a customer if that
notice requirement reasonable, and number of meetings to be required each customer declines to engage in the
other utilities suggest a 30-day year, the scope of the meetings, the planning process. Therefore, we
requirement would be appropriate.251 notice requirements, the format, and any encourage NRECA and non-public
Seattle also suggests e-mail notification other features. We will allow utilities to participate fully in the
and Salt River supports internet posting. transmission providers, with the input planning process.
With respect to details beyond of their customers and other
stakeholders, to craft coordination 454. In response to the suggestion by
frequency and notice, Entergy cautions some commenters that we require
the Commission against being too requirements that work for those
transmission providers and their transmission providers to allow
prescriptive. customers to collaboratively develop
449. On meeting scope, several customers and other stakeholders.
452. We emphasize that the purpose transmission plans with transmission
commenters request that the providers on a co-equal basis, we clarify
of the coordination requirement is to
Commission make clear that the that transmission planning is the tariff
eliminate the potential for undue
purpose of the meeting is to focus on obligation of each transmission
discrimination in planning by opening
transmission issues and not provide a provider, and the pro forma OATT
appropriate lines of communication
broad forum for other issues.252 planning process adopted in this Final
between transmission providers, their
Sacramento believes that meetings Rule is the means to see that it is carried
transmission-providing neighbors,
should be limited to sub-regional or out in a coordinated, open, and
affected State authorities, customers,
regional transmission planning and not transparent manner, in order to ensure
and other stakeholders. Rigid and
include planning to meet local that customers are treated comparably.
formal meeting procedures may be one
transmission needs. way to accomplish this goal, but there Therefore, the ultimate responsibility
450. Other commenters stress that for planning remains with transmission
may be other ways as well. For example,
joint planning requires more than just providers. With this said, we fully
a transmission provider could meet this
meeting with customers and that all intend that the planning process
requirement by facilitating the
LSEs need to be integrated into the adopted herein provide for the timely
formation of a permanent planning
planning process so that they are committee made up of itself, its and meaningful input and participation
actively developing transmission plans neighboring transmission providers, of customers into the development of
alongside transmission providers from affected State authorities, customers, transmission plans. This means that
the inception.253 This concept of and other stakeholders. Such a planning customers must be included at the early
collaborative planning is a running committee could develop its own means stages of the development of the
theme in the comments provided by of communication, which may or may transmission plan and not merely given
several public power entities, such as not emphasize formal meeting an opportunity to comment on
NRECA, TAPS, and TDU Systems. TDU procedures. We are more concerned transmission plans that were developed
Systems argue that comparability with the substance of coordination than in the first instance without their input.
requires that LSEs have equal weight in its form.
decision-making rather than provide de b. Openness
453. In response to the concerns of
facto veto authority to transmission some commenters, we clarify that 455. In the NOPR, the Commission
providers. NRECA argues in its reply transmission providers are not required proposed that transmission planning
that collaborative planning is required meetings must be open to all affected
by FPA section 217(b)(4). These 254 This collaborative approach is also generally
parties (including all transmission and
commenters assert that LSEs must be supported by East Texas Cooperatives, FMPA,
interconnection customers and State
able to participate in the development of NCEMC, NCPA, and Old Dominion. NCEMC
believes that the key to ensuring true collaboration authorities). The Commission also
sroberts on PROD1PC70 with RULES

251 E.g.,
is a voting structure, like that adopted in the North sought comment on whether there are
Nevada Companies and NorthWestern. Carolina Transmission Planning Collaborative,
252 E.g.,
any circumstances under which
Entergy, Progress Energy, SCE, and which gives all load-serving entities an equal say
Southern. in planning decisions. APPA also believes that
participation should be limited, for
253 E.g., NRECA, Seminole Reply, TAPS, and TDU giving customers a say in the outcome (e.g., through example, to address confidentiality
Systems. voting) is critical. concerns.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00058 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12323

Comments that if information is disclosed during a application of the Commission’s


456. Commenters generally agree on planning meeting and is not Standards of Conduct to planning
the need to meet with all affected simultaneously made public, then all participants, and whether and how
parties, as well as the need to limit some planning participants—including these standards should affect access to
meetings for security or confidentiality nonjurisdictional entities—should be and use of information obtained in the
reasons. Certain commenters urge the subject to the Commission’s Standards planning process, will be discussed
Commission to make clear that of Conduct. APPA understands the need below.
openness does not extend to a to ensure that non-public information
obtained during planning meetings is c. Transparency
requirement to meet with the general
public and that the meetings are for not utilized to gain an unfair advantage 461. In the NOPR, the Commission
‘‘industry and governmental in the power market; however, it proposed that transmission providers be
representatives’’ only.255 For example, believes that other means short of the required to disclose to all customers and
Southern agrees that eligible application of the Standards of Conduct other stakeholders the basic criteria,
transmission customers and State would suffice, such as requiring assumptions, and data that underlie
commissions should be allowed to simultaneous disclosure of information their transmission system plans. The
participate in the meetings, but states as a ‘‘safe harbor’’ or the use of Commission also sought comment on
that these meetings should not be open confidentiality agreements.258 whether the information provided in
to the general public to help ensure that 459. NRECA and TDU Systems argue FERC Form 715 (Form 715) is adequate
the focus is on core transmission that meetings should be open and, and, if not, what additional detail
planning and not be diverted to other joined by APPA, suggest that should be provided. In addition, the
issues. confidentiality issues can be managed Commission sought comment on the
457. Transmission providers generally with confidentiality agreements and format for disclosure, including
note that some meetings will need to be other arrangements (such as password protections to address confidentiality
limited for CEII concerns or for protected access to information). TAPS concerns.
discussion of commercially-sensitive suggests that access to data be limited to
transmission dependent utility Comments
information.256 Progress Energy states
the Commission should be flexible employees not involved in marketing or 462. Transmission providers generally
regarding the composition of meetings to an outside consultant. California agree that they should provide the basic
and openness, noting that in North Commission stresses that any advisory criteria, assumptions, and data for
Carolina meetings involving CEII are subcommittees must also be open to all planning, but argue that non-public
limited to transmission personnel and stakeholders. utility transmission providers should
non-marketing personnel of also be required to provide comparable
Commission Determination
participating LSEs, while other meetings information.259 In general, EEI believes
460. The Commission adopts the that information provided during the
in the North Carolina process are open
NOPR’s proposal and will require that planning process should be treated as
to the public. In their reply, NC
transmission planning meetings be open confidential and not disclosed to the
Transmission Planning Participants note
to all affected parties including, but not general public.
that they have been able to negotiate
limited to, all transmission and 463. Public power entities and other
confidentiality protocols agreeable to
interconnection customers, State commenters support transparency and
each of them. Duke believes that
commissions and other stakeholders. also are sensitive to confidentiality
restrictions on open meetings need to be
We recognize that it may be appropriate concerns.260 NCPA believes that the
in place when sensitive commercial
in certain circumstances, such as a failure of CAISO to release planning
information is being discussed, so that
particular meeting of a subregional data is one of the biggest failings of
personnel engaged in the merchant
group, to limit participation to a CAISO planning process. Without
function do not gain access to sensitive
relevant subset of these entities. We access to criteria, assumptions, and data
information about their competitors.
emphasize, however, that the overall inputs, NCPA argues that customers
Indianapolis Power recommends the
development of the transmission plan cannot duplicate planning results, nor
Commission keep existing restrictions
on access to planning meetings in place and the planning process must remain can they independently determine
to preserve current protections on open. We agree with the concerns of whether the assumptions are correct,
security and competitive information. some commenters that safeguards must whether the model is producing the
TVA states that it is particularly be put in place to ensure that right results, whether those results are
concerned with maintaining confidentiality and CEII concerns are being fairly applied in the choice of
confidentially and asks the Commission adequately addressed in transmission projects to be undertaken, or assess the
to defer to NERC and its Regional planning activities. Accordingly, we impacts on their own customers. APPA
Entities, which TVA says are developing will require that transmission providers, suggests that transmission providers be
procedures for planning. in consultation with affected parties, required to reduce to writing the
458. Commenters also raise issues develop mechanisms, such as methodology, criteria, and processes
regarding the application of the confidentiality agreements and they use to develop their transmission
Commission’s Standards of Conduct to password-protected access to plans, including how they treat retail
those that participate in planning information, in order to manage native loads, in order to ensure that
meetings.257 EEI, for example, believes confidentiality and CEII concerns. standards are consistently applied.
Lastly, concerns surrounding the
255 E.g.,APPA, EEI, Salt River, and Southern. 259 E.g.,
CAISO, EEI, and SCE.
256 Other commenters also recognize the need to Conduct to planning participants in their comments 260 E.g.,
APPA, California Commission, NCPA,
sroberts on PROD1PC70 with RULES

maintain confidentiality for CEII and commercially- addressing some of the other principles as well, CREPC, Salt River, and WAPA. Old Dominion,
sensitive information. E.g., Arkansas Commission, which will be discussed below, as well as however, does not believe that any of the data
AWEA, California Commission, NCPA, NRECA, addressed in the pending rulemaking in Docket No. required to be disclosed is commercially-sensitive;
CREPC, Seattle, TDU Systems, and WAPA. RM07–1–000. See Standards of Conduct NOPR. however, it does recognize that it may be CEII, in
257 Commenters raise issues with regard to the 258 See also East Texas Cooperatives Reply and which case it claims security can be maintained via
application of the Commission’s Standards of NRECA Reply. a secure OASIS site.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00059 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12324 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

CREPC points out that transparency is to be generally sufficient.262 Others demand response, and new technology
necessary if State regulatory processes believe the information in Form 715, as as part of the mix of available options
are to give deference to planning results. currently supplemented by other for incremental or interim congestion
Sacramento asserts that it may be information in the planning process, is relief until longer term solutions can be
reasonable to allow customers and adequate.263 Duke and WAPA contend developed and constructed. Fayetteville
stakeholders access to the planning that Form 715 does not contain notes its general support for a SEARUC
model or at least allow access to a sufficient information for transmission joint planning proposal, which includes
comprehensive description of the model planning, but believe that disclosure of a principle that would require the
and methodology, in order to allow further details should be left to integration of demand response in
others to closely replicate the planning stakeholders. According to planning. WIRES likewise argues that an
analysis. Sacramento is joined by NorthWestern, Form 715 contains the appropriate grid plan should be based
Imperial in referencing WECC’s on- basic data, but may not always provide on an integrated view of all alternatives,
going effort to increase planning the needed information. including demand response and
transparency. 467. ISO/RTO Council believes that distributed generation. PJM, Midwest
464. NRECA and TDU Systems, Form 715 data are generally inadequate ISO, and ISO New England emphasize
however, do not believe that a specific for planning studies, but urges the that their planning processes already
disclosure principle would be necessary Commission not to attempt to develop provide for the evaluation and
if LSEs were truly integrated into the ‘‘standardized forms’’ for these and integration of demand response
planning process. In other words, they other types of data. CAISO also cautions resources.265 Other commenters, such as
argue that if the process is truly open, against adopting a standardized form for Alcoa and Steel Manufacturer’s
then LSEs, as participants in the the collection of necessary information, Association, suggest that demand
development of the joint plan, should because standardized forms do not response resources be considered as
already have access to the inputs and necessarily provide the information substitutes for certain ancillary services.
assumptions underlying the plans and, needed by individual providers. 470. In response to its notice
in fact, should have helped develop 468. A number of other commenters convening the October 12 Technical
them. believe that Form 715 information is Conference, the Commission received
465. EEI believes that Standards of insufficient.264 APPA and TAPS point several comments addressing the role of
Conduct requirements should be placed out that Form 715 does not include all demand response in planning.
on all participants in the planning the information needed to perform a Participants in the technical conference
process whenever disclosure of load flow study, including information generally responded that demand
commercially-sensitive information is on economic dispatch and interchange, response programs are considered in
needed for planning. East Texas and also that Form 715 information is planning, particularly in the load
out of date when filed. Seattle notes that forecasts. Some observed that demand
Cooperatives argues that the Standards
typical sub-regional planning processes response has often been difficult to
of Conduct should not be generically
go into significantly greater detail than incorporate in long-term plans when it
applied to public power and that such
Form 715 and argues that Form 715 is is not dispatchable and only available in
issues should be managed with
primarily a reliability-focused report one-year increments. Participants
confidentiality agreements and case-by-
that seldom delves into economic stressed that transmission providers
case protective orders. In its reply,
analysis of congestion and transmission must have control over a resource
NRECA also asserts that, while it is
options that mitigate congestion. throughout the planning horizon if they
necessary to protect competitively-
469. Several commenters contend that are to rely on that resource in lieu of
sensitive information, there is no basis
transparency in the planning process is constructing upgrades. Some
for requiring nonjurisdictional entities
of particular interest to demand participants reported that this capability
to comply with the formal separation of
resources. New Jersey Board suggests is available from several forms of
functions requirements simply because
that each transmission provider’s demand response resources.
they have received information in the
planning process, as this is inconsistent planning process analyze whether Commission Determination
with the cooperative utility business demand resources or other solutions
could be considered as an alternative or 471. The Commission adopts the
model. Rather, NRECA believes NOPR’s proposal and will require
commercially-sensitive information can a component of new transmission lines
or upgrades. New Jersey Board states transmission providers to disclose to all
be handled in other established ways. customers and other stakeholders the
APPA also suggests that Standards of that this analysis should include both
supply-side and demand-side measures basic criteria, assumptions, and data
Conduct issues can be managed by that underlie their transmission system
providing for certain ‘‘safe harbors’’ for such as load management, new building
codes and energy efficiency standards, plans.266 In addition, transmission
participation, such as simultaneous
disclosure of information or the use of the use of distributive renewable energy
265 See also ISO/RTO Council.
an independent facilitator.261 systems, and renewable portfolio 266 Much of the information should be available
standards. Ohio Power Siting Board
466. Commenters express a range of to those engaged in transmission planning already
argues that an open, transparent, and under reliability Standards TPL–001–0 through
views on the information found in Form
inclusive regional planning process TPL–004–0 proposed in Docket RM06–16–000. See
715. MidAmerican believes Form 715 to the Reliability Standards NOPR. These standards
should include distributed generation,
be more than adequate and recommends set out detailed requirements for annual studies to
shortening or eliminating it. Other 262 E.g.,
assess the performance of the transmission system
Indianapolis Power, Southern, and Xcel. and require conducting simulation studies over a
investor-owned utilities find Form 715 263 E.g., Allegheny (with data from PJM) and five-year time horizon, with additional studies as
Nevada Companies (with data from WECC). needed for the six to ten-year horizon. The
sroberts on PROD1PC70 with RULES

261 NARUC asks the Commission to re-examine 264 E.g., APPA, California Commission, NCPA, Commission proposed that planning entities
the need for its Standards of Conduct rules CREPC, Seattle, TAPS, and TDU Systems. California conduct ‘‘studies to bracket the range of probable
concerning communications between resource and Commission and CREPC also point out that the load outcomes,’’ examining system operation under
transmission planners in light of the mitigation forecast information presently used in planning in variations in demand levels, existing and planned
provided by the open planning processes proposed the Western Interconnection is likewise facilities, reactive power resources, generation
in the NOPR. insufficient. dispatch and transaction patterns, controllable

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00060 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12325

providers will be required to reduce to 474. In Order No. 888–A, the advantage in power markets. We
writing and make available the basic Commission clarified that, under the therefore intend to balance the costs of
methodology, criteria, and processes reciprocity condition, a non-public confidentiality restrictions with the
they use to develop their transmission utility transmission provider must also importance of not allowing any entity
plans, including how they treat retail comply with the OASIS and Standards an undue competitive advantage in
native loads, in order to ensure that of Conduct requirements or obtain addressing this issue on a case-by-case
standards are consistently applied. This waiver of them.267 We reiterate that basis.
information should enable customers, non-public utility transmission 476. Although we adopt the foregoing
other stakeholders, or an independent providers should abide by the Standards protections to ensure that particular
third party to replicate the results of of Conduct with regard to managing entities do not gain an inappropriate
planning studies and thereby reduce the non-public transmission planning competitive advantage over others, we
incidence of after-the-fact disputes information obtained through the believe that transmission providers
regarding whether planning has been planning process, consistent with their should make as much transmission
conducted in an unduly discriminatory reciprocity obligations. We also note planning information publicly available
fashion. We note, however, that that, given the planning process as possible, consistent with protecting
transmission providers cannot be required by this Final Rule, it may be the confidentiality of customer
expected to fulfill these planning necessary to revisit the waivers of the information. Given that one of the
obligations unless non-public utility Standards of Conduct granted to certain primary objectives of the planning
transmission providers that participate non-public utility transmission reforms adopted herein is to allow
in the planning process make similar providers in the past. We will not do so, customers to consider future resource
information available and, for the however, on a generic basis in this options, it will be necessary for market
reasons set forth above, we fully expect proceeding. All such existing waivers participants, including the merchant
that they will do so. We believe that the thus shall remain in place. Whether an function of transmission providers, to
same safeguards developed as discussed existing waiver of the Standards of have access to basic transmission
above regarding the openness principle, Conduct should be revoked will be planning information in order to
such as confidentiality agreements and considered on a case-by-case basis in consider those options. The
password protected access to light of the circumstances surrounding simultaneous disclosure of transmission
information, will adequately protect the particular transmission provider.268 planning information can alleviate the
against inappropriate disclosure of 475. In order for the Final Rule’s Standards of Conduct concerns
confidential information or CEII. transmission planning process to be as discussed above.270
472. The Commission also requires effective as possible, we emphasize that 477. In response to commenter
that transmission providers make all transmission providers, both concerns regarding the sufficiency of
available information regarding the jurisdictional and nonjurisdictional, planning information currently
status of upgrades identified in their must be assured that the information available in the Form 715, we find that
transmission plans in addition to the they provide in that process will not be Form 715, as well as Form 714, have not
underlying plans and related studies. It used inappropriately in the wholesale provided customers and others with the
is important that the Commission, power market. While we decline to timely data needed to perform load flow
stakeholders, neighboring transmission require a third party independent studies and other analyses to ensure that
providers, and affected State authorities facilitator as discussed below, we do planning is being conducted on a
have ready access to this information in believe that utilizing an independent comparable basis. For example, while
order to facilitate coordination and entity may help parties manage we understand that certain planning
oversight. To the extent any such Standards of Conduct concerns.269 information is already provided in FERC
information is confidential or consists of Finally, we wish to emphasize that the Form No. 714 (Annual Electric Control
CEII, the transmission provider can Commission recognizes that compliance and Planning Area Report) and FERC
implement the safeguards suggested with the Standards of Conduct can Form 715 (Annual Transmission
above. impose costs on small entities, but we Planning and Evaluation Report), we
473. In response to the concerns of believe that this concern must be believe that with regard to transparency
some commenters regarding the balanced against the fact that a of data and assumptions, Forms 714 and
disclosure of information to non-public coordinated and open transmission 715 are limited in a number of ways. An
utility transmission providers, we planning process is critical to important limitation is that information
believe that simultaneous disclosure of remedying undue discrimination and is not necessarily available on a
transmission planning information meeting our Nation’s future energy consistent geographic basis. Form 715
where appropriate alleviates many of needs and that an open planning requires selected powerflow studies by
those concerns. In those instances process cannot be fully successful if
where there is non-simultaneous certain entities (whether jurisdictional 270 Transmission providers could ensure

disclosure of information, we find that or nonjurisdictional) can use the simultaneous disclosure of information through
information to obtain an undue such actions as providing all current and potential
existing reciprocity requirements ensure customers and other stakeholders equal access,
that information is not inappropriately notice, and opportunity to attend planning
267 See Order No. 888–A at 30,286.
shared with the non-public utility meetings, providing for the contemporaneous
268 We believe this same approach should also
transmission provider’s marketing availability of meeting handouts and minutes on the
apply to public utilities that have obtained waivers transmission providers’ OASIS or Internet Web
affiliate. of the Standards of Conduct. sites, and requiring that an energy affiliate or
269 The Commission will consider whether marketing affiliate employee of the transmission
loads and demand-side management, and other further changes to the Standards of Conduct would provider may not attend a meeting unless a
factors. Id. at P 1047. While we recognize that facilitate the transmission planning requirement in representative of at least one additional customer or
sroberts on PROD1PC70 with RULES

OATT planning is distinct from these proposed the Standards of Conduct NOPR initiated in Docket potential customer is present. We believe such
reliability planning standards, we expect that the No. RM07–1–000. See supra note 257. We also actions would typically constitute compliance with
key data underlying transmission planning will be intend to address the concerns of NARUC with sections 358.5(a) and (b) of the Standards of
provided in conjunction with reliability standards regard to waiving the Standards of Conduct Conduct, 18 CFR 358.5(a)–(b), dealing with
and thus should be available for transmission concerning communications between resource and information access and prohibited disclosure,
planning when those standards are finalized. transmission planners in that proceeding. respectively.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00061 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12326 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

control area, while Form 714 requires some others.273 We therefore find that, public utilities. EEI maintains that
information on control area generation where demand resources are capable of similarly-situated participants should
and load, including hourly load on a providing the functions assessed in a have comparable information, with
planning area. Since these two areas do transmission planning process, and can commercially-sensitive information
not necessarily coincide, it can be be relied upon on a long-term basis, available only to transmission function
difficult to apply the data except for the they should be permitted to participate personnel. Duke supports the
single annual or seasonal system peak. in that process on a comparable basis.274 information exchange principle in
Consequently, Form 715 is an This is consistent with EPAct 2005 general, but believes the NOPR
insufficient basis for broad transmission section 1223. envisions a wider exchange of
planning purposes and must be information on loads and resources than
d. Information Exchange
supplemented by additional is appropriate.277 Instead, Duke believes
480. In the NOPR, the Commission that planning participants should agree
assumptions and data.
proposed that network transmission on how much detail will be available.
478. Information may also be difficult customers be required to submit WAPA similarly suggests that any
to compare or apply if a region is larger information on their projected loads and criteria for information exchange should
than a single control area. Where the resources on a comparable basis (e.g., be developed by stakeholders, not the
peak periods represented in the Form planning horizon and format) as used by Commission.
715 correspond to different time periods transmission providers in planning for 482. Although commenters do not
in different control areas, separate their native load. The Commission generally disagree with a requirement
assumptions and information may be further proposed that point-to-point for point-to-point customers to submit
needed for a study encompassing customers be required to submit any projections of their needs for service,
multiple control areas. In addition, each projections they have of a need for they question the value of these
control area may include different service over that planning horizon and projections if the customers have not
criteria for including facilities in the at what receipt and delivery points. The actually requested service for these
data and additional assumptions will be Commission sought comment on projected needs.278 Nevada Companies
needed to resolve these issues as well. whether specific requirements should state that point-to-point customers
Moreover, information on the basis for be adopted for this information should provide future use forecasts and
key assumptions is limited. The Form exchange.275 The Commission also that the forecast data transferred by all
715 instructions require a description of stated that transmission providers must entities should be provided for the
transmission planning reliability criteria allow market participants the planning horizon in a uniform manner.
and assessment practices, but allow the opportunity to review and comment on 483. Southern is concerned that the
transmitting utility discretion on what is draft transmission plans. opportunity for review and comment
reported. As a result, assumptions Comments could be construed to apply to draft
regarding key inputs, such as the load interconnection, system impact, or
forecasts, are not available. Similarly, 481. Transmission providers suggest facilities studies under the transmission
that they should be responsible for provider’s OATT. Southern argues that
information regarding customer demand
developing a schedule and format for such a requirement would cause great
response is not available. Lastly, Form
submission of information and the delay and asks the Commission to
715 requires no information explaining
development of a draft plan that clarify that the transparency
the basis for generator dispatch in the
provides sufficient time for participants requirement for review and comment on
powerflow cases, nor is any economic
to review and comment before transmission plans is limited to only the
information provided. For studies of
completion of a final plan.276 EEI transmission provider’s draft of its base
system peak reliability, when all
emphasizes the importance of requiring case transmission plan.
generators are expected to be running,
comparable information from all 484. Other commenters advance a
this may not be a significant limitation.
participants in planning, including non- view that joint planning should consist
However, without some basis for
dispatching the system at other times, it of more than providing the transmission
273 See Staff Report: Assessment of Demand
becomes difficult or impossible to provider with information and then
Response & Advanced Metering at 97–100 (Docket
conduct meaningful load flow studies Number AD–06–2–000) (Demand Response Report), reviewing and commenting on the plans
for other planning purposes. Therefore, available at http://www.ferc.gov/legal/staff-reports/ it develops; rather, customers need to be
we will require the disclosure of
demand-response.pdf#xml=http:// able to actively participate in the
search.atomz.com/search/ development of the planning studies
criteria, assumptions, data, and other pdfhelper.tk?sp_o=1,100000,0.
information that underlie transmission 274 The transmission planning processes we
and transmission plans.279 APPA
plans as described above. require in this Final Rule are not intended in any likewise believes that earlier
way to infringe upon State authority with regard to involvement is needed so that projected
479. Finally, several commenters integrated resource planning. Rather, we believe needs are fully understood and
assert that demand response resources that the transparency provided under an open
accounted for in the initial development
should be considered in transmission regional transmission planning process can provide
useful information which will help states to of the plan.280 NCPA stresses that
planning.271 Some commenters note coordinate transmission and generation siting reviewing plans is meaningless if there
that certain regions currently are in the decisions, allow consideration of regional resource is no access to data on how the plan was
process of incorporating demand adequacy requirements, facilitate consideration of
demand response and load management programs
created, how economic evaluation was
response into their transmission at the State level, and address other factors states
planning processes.272 Demand wish to consider. 277 TVA states that it is unaware of any

resources currently provide ancillary 275 The Commission noted in the NOPR that for shortcomings with the existing information
services in some regions, and this network service, some of this information is already exchange process and that more specific
sroberts on PROD1PC70 with RULES

required by sections 29, 30, and 31 of the pro forma requirements may limit the ability of transmission
capability is in under development in providers to meet changing needs and processes.
OATT, but to the extent it is not, the Commission
278 E.g., APPA, Duke, and Salt River.
proposed to require customers to provide additional
271 E.g., Ohio Power Siting Board, New Jersey information as necessary for the transmission 279 E.g., NCPA and TDU Systems.

Board, and WIRES. provider to develop a system plan. 280 See also Bonneville, California Commission,
272 E.g., PJM and ISO–New England. 276 E.g., EEI, Pinnacle, Salt River, and Xcel. Imperial, NCPA, and Seattle.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00062 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12327

performed, and how and why proposed that might have taken into account Mexico Attorney General asserts that
upgrades were chosen. Old Dominion reasonable projections of future system native load and non-affiliated merchants
suggests that planning information and uses that were not the subject of specific and other wholesale customers should
data be posted no less than monthly or, service requests. To the extent not be treated comparably, because
where appropriate, seasonally. TDU applicable, transmission customers also utilities have a statutory obligation to
Systems and NCEMC stress that LSEs should provide information on existing serve.
should have access to all information at and planned demand resources and 491. TDU Systems and the NRECA
the same time since if a transmission their impacts on demand and peak repeat the view that comparability
provider performs studies without demand. In addition, stakeholders cannot be achieved if the transmission
including other LSEs, it opens the door should provide proposed demand provider is the only one developing the
for providers to act on sensitive response resources if they wish to have plan, which they believe this principle
information before releasing it to other them considered in the development of contemplates. They argue instead that
LSEs. the transmission plan. LSEs should be allowed to participate
485. Some commenters advance the 488. Lastly, in response to the actively in the development of the plan
view that distributed generation and concerns of some commenters, we from the beginning and should have
other demand response resources emphasize that the transmission equal weight in decision-making. TDU
should be considered in developing a planning required by this Final Rule is Systems believes that comparability
transmission plan.281 not intended, as discussed earlier, to be does not allow for different planning
limited to the mere exchange of standards for certain customers, because
Commission Determination
information and then review of it may leave rural electric cooperatives
486. The Commission adopts the transmission provider plans after the out of the planning loop.285 TAPS also
information exchange principle as to fact. The transmission planning argues that comparability is not enough;
both network and point-to-point required by this Final Rule is intended rather, substantive goals should be
transmission customers. Accordingly, to provide transmission customers and included.286
we will require transmission providers, other stakeholders a meaningful 492. Noting that not all transmission
in consultation with their customers opportunity to engage in planning along service requests may be granted,
and other stakeholders, to develop with their transmission providers. At Southern urges the Commission to
guidelines and a schedule for the the same time, we emphasize that this clarify that the intent of this criteria is
submittal of information. In order for information exchange relates to that the transmission provider plan its
the Final Rule’s planning process to be planning, not other studies performed in system so as to be able to reliably serve
as open and transparent as possible, the response to interconnection or all of its long-term firm commitments on
information collected by transmission transmission service requests. its transmission system in accordance
providers to provide transmission
e. Comparability with its State and Federal legal
service to their native load customers
489. In the NOPR, the Commission requirements, as well as ERO Standards.
must be transparent and, to that end,
proposed that, after considering the data With regard to RTO and ISO planning,
equivalent information must be
and comments supplied by market NYAPP argues that it is not comparable
provided by transmission customers to
participants, each transmission provider for an RTO or ISO to only plan for bulk
ensure effective planning and
develop a transmission system plan that power facilities, while allowing
comparability. We clarify that the
(1) Meets the specific service requests of individual transmission owners the
information must be made available at
its transmission customers and (2) discretion to plan for lower voltage
regular intervals to be identified in
otherwise treats similarly-situated transmission facilities.
advance. Information exchanged should
customers (e.g., network and retail 493. Some commenters argue that
be a continual process, the frequency of
native load) comparably in transmission demand resources should be treated
which should be addressed in the
system planning. comparably to other resources in
transmission provider’s compliance
transmission planning.287
filing required by the Final Rule. Comments
However, we expect that the frequency Commission Determination
and planning horizon will be consistent 490. Several commenters support the
comparability principle,282 and others 494. The Commission adopts the
with ERO requirements. NOPR’s proposal as to the comparability
487. We also believe that it is state that existing processes already
follow this principle.283 EEI urges the principle and will require the
appropriate to require point-to-point
Commission to emphasize that the transmission provider, after considering
customers to submit any projections
‘‘comparability’’ principle requires the the data and comments supplied by
they have of a need for service over the
transmission provider or transmission customers and other stakeholders, to
planning horizon and at what receipt
owner to treat similarly-situated develop a transmission system plan that
and delivery points. We believe that any
participants comparably in the (1) Meets the specific service requests of
good faith projections of a need for
service, even though they may not yet development of a plan, but does not
285 See also NRECA Reply and Old Dominion.
be subject to a transmission reservation, require that all participants be treated
286 TAPS cites to its ‘‘Balanced Principles for
may be useful in transmission planning equally. Pinnacle and others support
Transmission Planning & Expansion,’’ which was
as they may, for example, provide comparable treatment of similarly- attached to its NOI comments, for a description of
situated customers and request the the following substantive goals: (1) Reliability/
planners with likely scenarios for new
Commission to confirm that native load adequacy, (2) accommodating load growth, (3)
generation development. If the point-to- preserving existing transmission rights, (4) access to
protections will be recognized in the
point customers do not submit such regional competitive generation markets, (5)
concept of comparability.284 New maintaining deliverability, (6) facilitating regional/
projections, then the transmission
sroberts on PROD1PC70 with RULES

inter-regional power transfers, and (7) integrating


provider cannot later be faulted for 282 E.g., California Commission, NCPA, CREPC, new generation into the regional grid. TAPS
failing to consider planning scenarios Salt River, Seattle, and WAPA. emphasizes that the process should anticipate
283 E.g., Duke and Imperial. needs and propose solutions before serious
281 E.g., New Jersey Board, Ohio Power Siting 284 See also MidAmerican, Progress Energy, and transmission problems emerge.
Board, and WIRES. Xcel. 287 E.g., ELCON, New Jersey Board, and WIRES.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00063 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12328 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

its transmission customers and (2) principle,290 while others believe need for an elaborate dispute resolution
otherwise treats similarly-situated existing processes, including section 12 process.
customers (e.g., network and retail of the pro forma OATT, are
Commission Determination
native load) comparably in transmission sufficient.291 Other commenters simply
system planning.288 Further, we agree urge flexibility in the development of a 501. The Commission adopts the
with commenters that customer demand dispute resolution process.292 However, NOPR’s proposal to require
resources should be considered on a maintaining that the Commission has no transmission providers to develop a
comparable basis to the service legal authority to mandate a regional dispute resolution process to manage
provided by comparable generation planning process or dispute resolution disputes that arise from the Final Rule’s
resources where appropriate. related thereto, Progress states the planning process.294 An existing dispute
495. We are specifically requiring a Commission should be flexible and resolution process may be utilized, but
comparability principle to address allow for a voluntary dispute resolution those seeking to rely on an existing
concerns, such as those raised by process.293 dispute resolution process must
commenters, that transmission 498. Southern believes that dispute specifically address how its procedures
providers continue to plan their resolution should be limited to whether will be used to address planning
transmission systems such that their a provider has complied with any disputes. The dispute resolution process
own interests are addressed without procedural requirements and not be should be available to address both
regard to, or ahead of, the interests of utilized by parties to modify a procedural and substantive planning
their customers. Comparability requires transmission plan. APPA, however, issues, as the purpose for including a
that the interests of transmission argues that such an approach would dispute resolution process is to provide
providers and their similarly-situated relegate customers to an advisory role. a means for parties to resolve all
customers be treated on a comparable EEI believes the Commission should disputes related to the Final Rule’s
basis. In response to the concerns include principles for dispute resolution planning process before turning to the
expressed by several commenters, we and should allow stakeholders in the Commission.
emphasize that similarly-situated regional planning groups to craft their 502. We emphasize that the intent of
customers must be treated on a own procedures consistent with those the dispute resolution process required
comparable basis, not that each and principles. Reflecting concerns of some here is not to address issues over which
every transmission customer should be of its members, EEI cautions against the Commission does not have
treated the same.289 mandating dispute resolution that jurisdiction, such as a transmission
includes binding resolution of whether, provider’s planning to serve its retail
f. Dispute Resolution how, where, or when to construct native load or State siting issues. As
496. In the NOPR, the Commission additional transmission facilities. discussed above, however, we do intend
proposed that transmission providers 499. Indianapolis Power believes that the planning process required by
propose a dispute resolution process, there should be a dispute resolution this Final Rule ensure comparability in
such as requiring senior executives to process in place with specific steps planning between that conducted for a
meet prior to the filing of any complaint identified, expressing reservations about transmission provider’s retail native
and using a third party neutral. The the vagueness of the current MISO load and its similarly-situated
Commission noted that the process. ATC argues that RTO plans transmission customers and, therefore,
Commission’s Dispute Resolution should recognize which entity is issues relating to such comparability
Service is available to assist ultimately accountable for building may be appropriate for the dispute
transmission providers in developing a transmission, by requiring transmission resolution process.
dispute resolution process. The customers that have a dispute with a 503. Lastly, we encourage
Commission also noted that, in addition plan first to appeal to the local transmission providers, customers, and
to informal dispute resolution, affected transmission owner to ensure both other stakeholders to utilize the
parties would have the right to file entities fully understand what is being Commission’s Dispute Resolution
complaints with the Commission under requested, before carrying the dispute Service to help develop a three step
FPA section 206. The Commission further. dispute resolution process, consisting of
sought comment on whether any 500. Consistent with its focus on negotiation, mediation, and arbitration.
specific dispute resolution processes integrated joint planning, TDU Systems Regardless of the process adopted by a
should be required. asks that the Commission clarify that a transmission provider, affected parties
dispute resolution process is not being of course would retain any rights they
Comments required as a principle as an may have under FPA section 206 to file
497. Many commenters support the acknowledgement that transmission complaints with the Commission.
proposed dispute resolution providers will retain control over the g. Regional Participation
process. As long as LSEs are an integral
288 As discussed above, we emphasize that the
part of the planning process, TDU 504. In addition to preparing a system
obligation imposed herein on transmission Systems stress that there should be no plan for its own control area on an open
providers is meant to include transmission owners and nondiscriminatory basis, the
in RTOs and ISOs that no longer have their own
OATTs, as well as non-public utility transmission
290 E.g., APPA, Bonneville, California Commission proposed in the NOPR that
providers required to comply with the Final Rule’s Commission, Imperial, and NCPA. each transmission provider be required
planning process consistent with their reciprocity 291 E.g., East Texas Cooperatives, Salt River,
to coordinate with interconnected
obligations. Seattle, TVA and WAPA. TVA points out that since systems to: (1) Share system plans to
289 Additionally, in our discussion of the planning and its principles are just now being
formed, resources would be better spent on ensure that they are simultaneously
coordination principle above, we clarify that
transmission planning is the tariff obligation of each developing platforms where interested parties could feasible and otherwise use consistent
sroberts on PROD1PC70 with RULES

transmission provider, and as such, ultimate have input into the planning process, as opposed
responsibility for planning remains with to dispute resolution. 294 We have already addressed arguments
292 E.g., Allegheny, Nevada Companies, Pinnacle,
transmission providers. Accordingly, we reject the concerning our jurisdiction to require a
arguments made by some commenters that and Southern. Xcel, however, does not believe any transmission planning process. A process for
comparability requires that customers have equal dispute resolution process is required in the OATT. resolving disputes that arise from that planning
weight in decision-making. 293 See also Duke and MidAmerican. process is a necessary incident to it.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00064 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12329

assumptions and data, and (2) identify existence of sub-regional planning must No. RM04–7–000: 298 PJM, New York,
system enhancements that could relieve not diminish the obligation to plan on New England, Midwest, SPP, Southeast,
‘‘significant and recurring’’ transmission a broader, more regional level. TDU California, Northwest, and Southwest.
congestion (defined below). The Systems also believe that more than 509. LDWP and Salt River suggest that
Commission emphasized that such coordination is required; rather, continued participation in existing
coordination should encompass as transmission providers should be regional and sub-regional groups should
broad a region as possible, given the required to conduct planning on an satisfy the expectation that municipally-
interconnected nature of the integrated basis with, at a minimum, owned transmission providers
transmission grid and the efficiency of first-tier, adjacent interconnected participate in open and transparent
addressing these issues in a single systems. If a transmission provider regional planning processes. Other
forum. The Commission also recognized refuses to do so, TDU Systems believe commenters express a similar concern
that, as in the West, it may be that should be considered an exercise of that the Commission not mandate any
appropriate to organize regional vertical market power and the procedures that would interfere with the
planning efforts on both a sub-regional transmission provider should lose its processes the West has already
and regional level. The Commission market-based rate authority. TDU established.299 New Mexico Attorney
sought comment on whether there are Systems also urge the Commission to General believes that those already
existing institutions (such as the NERC require regional planning for both engaged in a planning process should be
regional councils or sub-regional reliability and economic upgrades, in allowed a waiver.
planning groups) that are well-situated order to ensure that competitive market 510. NARUC urges the Commission to
to perform or coordinate this function. development is not retarded by clarify that planning proposals should
inappropriate seams at the borders of not interfere with or undermine existing
Comments
utility systems.296 In its reply, NRECA regional planning efforts, such as those
Regional Scope argues that regional participation must conducted by RTOs and in non-RTO
505. EEI agrees that regional planning be mandatory, because uncoordinated, areas.300 Project for Sustainable FERC
should be encouraged, but urges the unilateral planning by transmission Energy Policy recommends that the
Commission not to be prescriptive about providers severely handicaps LSEs’ Commission use the Bonneville and
the size of the regions involved. assembly of competitive power PJM planning processes as models for
According to EEI, the Commission suppliers for their customers. evaluating transmission provider
should define regional planning as compliance. Arkansas Commission
507. PJM states that transmission believes that the active involvement of
planning that involves more than one providers bordering RTOs should be
transmission provider and allow the states can be a catalyst for regional
required to participate in the RTO planning.
regions to define themselves. CAISO planning process, but MidAmerican
believes the Commission should leave 511. National Grid believes the
opposes such a requirement and principles of coordination, openness,
the determination of the sub-regional believes it already happens in MISO
and regional boundaries to transmission and transparency should extend to
anyway. MAPP also opposes such inter-regional planning and requests
providers. NC Transmission Planning mandatory participation, pointing out
Participants assert on reply that the clarification that this is the
that comparability would then require Commission’s intent for neighboring
participants in each regional process are that transmission providers in RTOs
in the best position determine the regions in a single interconnect.
participate in the planning processes of
proper scope of the planning process for non-RTO providers on their borders as Existing Institutions
their region. NRECA argues that well.297 MAPP believes that currently-
customers and other stakeholders 512. Regarding the Commission’s
existing regions should have the request for comment on whether there
should be allowed to participate in the opportunity to adjust their planning
discussion that leads to the delineation are existing institutions that are well-
processes to meet the Commission’s situated to coordinate regional
of regions. NRECA asserts that regions guidelines for regional transmission
should be large enough to minimize the participation, commenters express
planning. differing views regarding the identity of
potential for seams problems for LSEs in
multiple control areas. At a minimum, 508. Indianapolis Power emphasizes the regional coordinator and the size of
NRECA argues that the Commission that the regional scope of a transmission the region over which entities should be
should ensure that all public utility provider’s planning process should required to coordinate. Some
transmission providers coordinate with consider grid topology and historical transmission provider commenters cite
their adjoining systems to ensure that usage to avoid regions that are too broad NERC regions and regional councils as
the needs of LSEs with loads and or unwieldy. Indianapolis Power well-suited for coordinating regional
resources in different systems’ areas are believes that the current MISO region participation.301 Taking an opposite
met. may be an example of a region that is view, ISO/RTO Council maintains that
506. TDU Systems support mandatory too large, but nevertheless asserts that RTOs and ISOs are the best models for
regional planning and believe that the MISO should have the primary role in
298 See Market-Based Rates for Wholesale Sales of
Commission should specify the criteria coordination, with regional councils in
Electric Energy, Capacity and Ancillary Services by
for determining regions, rather than supporting roles. AWEA recommends Public Utilities, Notice of Proposed Rulemaking, 71
prescribe regional boundaries. In TDU nine planning regions that coincide FR 33102 (Jun. 7, 2006), FERC Stats. & Regs.
Systems’ view, ‘‘regional’’ planning at a with the nine regions being established ¶ 32,602 (2006).
minimum means something more than for Regional Triennial Reviews in the 299 E.g., California Commission, Imperial, and Salt

market-based rate rulemaking in Docket River.


planning on an individual control area 300 See also NC Transmission Planning
basis.295 TDU Systems stress that the
sroberts on PROD1PC70 with RULES

Participants Reply and North Carolina Commission


those other providers it proposes to include in its Reply. Also, in its reply, North Carolina
295 TAPS believes joint planning should include regular regional planning process. Commission urges the Commission not to be overly
296 NRECA’s comments on regional planning are prescriptive with respect to the details of regional
at least two transmission providers and be no
smaller than a State. TAPS suggests that the consistent with those of TDU Systems. transmission planning.
transmission providers’ compliance filings identify 297 See also MidAmerican Reply. 301 E.g., Allegheny, Constellation, and Duke.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00065 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12330 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

regional participation, because regional reliability and economic transmission the large, unregulated municipal
reliability organizations do not have planning. California Commission also utilities that do not participate in
mandates or authority to ensure that stresses that the processes in the West CAISO.
adequate system expansion occurs on a have resulted in transmission being
Northeast
coordinated basis. built. Utah Municipals, however, are
513. MISO is concerned the critical of the WECC process, and in 516. PJM, NYISO, and ISO New
Commission intends to shift reply, assert that the WECC process does England all have transmission planning
transmission planning responsibility not allow for effective stakeholder processes that have been approved by
from RTOs to the Regional Entities input, but merely review of the Commission. ISO/RTO Council cites
under the ERO, arguing that these transmission plans once they are billions of dollars of transmission
entities have neither a sufficient level of formed. Utah Municipals also believe investment in the Northeast as an
independence nor a track record in that sub-regional groups in its area (e.g., example of the success of these
transmission planning. TDU Systems the Southwest Transmission Expansion transmission planning processes and
suggest that RTOs, where they exist, Plan (STEP)) are more effective and argues that these processes all satisfy
should perform the regional planning urges the Commission to focus on the the Commission’s principles for
function, although in some other effective implementation of joint coordinated, open, and transparent
instances it may be the regional plans.305 planning. PJM maintains that its
reliability organizations. Although 515. Other commenters support the Regional Transmission Expansion
CAISO states that a larger regional entity sub-regional planning processes in the Planning Protocol is a successful and
with the authority to order expansion West as well, and generally believe the comprehensive regional planning
has some appeal, it contends there are Commission should look to each sub- paradigm. ISO New England also argues
too many hurdles to creating such an region’s existing processes and that its transmission planning meets the
entity in the West. TAPS suggests a institutions.306 For example, principles and further points to the
‘‘Regional Joint Planning Committee’’ commenters in the Southwest and Northeastern ISO/RTO Planning
that is not dominated by transmission California also support the sub-regional Coordination Protocol as providing
providers, which would direct the study groups located in that region (e.g., STEP coordinated planning across the entire
process and be responsible for the and the Southwest Area Transmission Northeast region.
development of uniform planning Expansion Planning group (SWAT)).307 517. Utilities in the Northeast are
criteria, assumptions for base and California Commission also supports the generally supportive of the transmission
changed cases, and transmission plans. CAISO planning process and states that planning in the Northeast RTOs.
Existing Regional Planning Processes CAISO works closely with stakeholders Designated NY Transmission Owners
to proactively identify needed, cost contend that the NYISO Comprehensive
The West Reliability Planning Process is fully
effective transmission solutions through
514. Transmission provider an open, non-discriminatory process open, coordinated, and transparent and
commenters in the West (outside that has resulted in $1.8 billion in meets or exceeds each of the eight
California) generally recommend the transmission being constructed.308 In its principles in the NOPR. PSEG believes
Western Electricity Coordinating reply, NCPA emphasizes that the the PJM planning process embodies the
Council (WECC) 302 as a successful Commission should not equate the NOPR principles. Constellation cites the
institution and an appropriate model for CAISO planning process with a planning processes in PJM and the
designating regions and developing a California-wide process, because not all NYISO as examples of planning
plan for the interconnection.303 Many transmission providers in California are processes that, while not perfect, should
public power entities and others in the members of CAISO. However, California serve as models for compliance filings
West also support WECC and suggest Commission notes that California, with by others. Old Dominion, however,
that it should be a primary focus when the support of WECC, has begun the expresses concern over continuing
deciding which institution can provide work of creating a California-wide sub- domination of transmission planning by
independent regional review and regional planning group that includes transmission owners, but nevertheless
coordination of grid planning in the commends PJM for recent efforts to
West.304 For example, California 305 Public Power Council does not support include more stakeholder input in the
Commission notes that WECC’s expansion of WECC’s role in coordinating planning planning process. National Grid is
beyond its current activities, as it believes WECC’s
Transmission Expansion Planning strength lies in the area of reliability and not
generally supportive of ISO New
Policy Committee allows for the planning and, therefore, that WECC would be best England’s planning process.
consolidated needs of all the system served by focusing on reliability and standards
enforcement, rather than as a participant (as a Northwest
operators in the Western
facilitator or otherwise) in commercial matters. 518. Several commenters in the
Interconnection to be considered in the 306 WAPA points out that certain broad functions
planning process and considers both related to planning can be coordinated at the
Northwest generally support the
regional level, but that sub-regional planning is Northwest Power Pool and the
302 In general, WECC and its sub-regional groups necessary in an expansive regional area, such as ColumbiaGrid process (which will
have adopted an overall division of labor whereby WAPA’s service territory, in order to provide focus provide for a biennial transmission
WECC has undertaken facilitation of interstate, and detail.
commercial transmission projects and the sub- 307 E.g., LDWP, New Mexico Attorney General,
expansion plan for certain entities in the
regional groups have facilitated the planning of and Salt River. LDWP also cites its involvement in Northwest).309 Also, two groups in the
their member providers. the Public Power Initiative of the West, CAISO, and Northwest are forming to address sub-
303 E.g., ColumbiaGrid, MidAmerican, Nevada the Western Arizona Transmission System group. regional planning in that region—the
Companies, NorthWestern, Pinnacle, and Xcel. 308 Anaheim believes that the CAISO process does
ColumbiaGrid group and the Northern
304 E.g., Anaheim, APPA, California Commission, not currently proactively evaluate the adequacy of
Tier Transmission Group—but it is not
sroberts on PROD1PC70 with RULES

Imperial, LDWP, NCPA, PGP, Public Power the system or itself propose projects that will
Council, CREPC, Salt River, Santa Clara, Seattle, enhance reliability or efficiency and is based
TANC, WAPA, and Western Governors. APPA entirely upon plans presented to it by transmission 309 E.g., Bonneville, ColumbiaGrid, PGP, Public

notes, however, that not all of its members that owners. It notes, however, that CAISO has proposed Power Council, and Seattle. APPA also notes its
support the WECC planning process support those reforms to address these issues. See also Anaheim members’ support for the sub-regional processes in
within California. Reply. the Northwest.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00066 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12331

yet clear how such groups intend to utility plans. Additionally, FMPA 311 for wholesale customers to access
coordinate with each other. notes that MidAmerican has recently competitive sources of supply, rather
made efforts to engage in more proactive than relying exclusively on local
Southeast planning and has offered joint generation, including resources owned
519. The public power commenters in transmission investment opportunities. by their local transmission provider.
the Southeast were not as supportive of FMPA also points to its membership in However, as discussed above, it is not
the existing regional and sub-regional CAPX 2020, a consortium of Upper in the economic self-interest of
planning processes in their region. TVA Midwest utilities, which are jointly transmission providers to expand the
and Santee Cooper generally support the studying and planning for the needs of grid to permit access to competing
process conducted by the Southeast regional transmission. However, FMPA sources of supply. A transmission
makes clear that it believes smaller provider has little incentive to upgrade
Electric Reliability Council (SERC), and
customers nevertheless need a tariff its transmission capacity with its
Santee Cooper notes that it has had a
requirement for planning to ensure that interconnected neighbors if doing so
formal joint planning process with its
their needs are addressed. would allow competing suppliers to
largest wholesale customer for more
serve the customers of the transmission
than 25 years. APPA, however, notes Florida
provider. We therefore find, as
that its members did not generally 522. While the Florida Commission discussed in greater detail above, that
endorse existing regional entities in the believes that the planning process greater coordination and openness in
Southeast. APPA states that SERC, for conducted by the Florida Reliability transmission planning is required, on
example, just ‘‘rolls up’’ the Coordinating Council (FRCC) is both a local and regional level, to
transmission plans of the transmission adequate, others, such as FMPA, do remedy undue discrimination. The
providers, and some working groups not.312 Florida Commission states that coordination of planning on a regional
currently exclude non-transmission the FRCC has instituted a transparent basis will also increase efficiency
owners.310 and inclusive planning process whereby through the coordination of
utilities, generators, and marketers transmission upgrades that have region-
North Carolina
participate in joint transmission wide benefits, as opposed to pursuing
520. NCEMC points to the North planning studies and evaluate transmission expansion on a piecemeal
Carolina Transmission Planning impediments to transfer capability and basis. The specific features of the
Collaborative (NC Transmission determine solutions to congestion in regional planning effort should take
Planning), a joint planning process with order to enhance the reliability of the account of and accommodate, where
an independent facilitator, in North FRCC system. appropriate, existing institutions, as
Carolina. NCEMC emphasizes that more Commission Determination well as physical characteristics of the
than regional coordination is required region and historical practices.
523. We adopt the NOPR’s proposal to 525. The Commission is encouraged
and that regional planning needs to be
include a regional participation that a number of voluntary coordinated
more than mere stakeholder review and
principle as a component of the Final and regional planning efforts have been
must allow for full participation of LSEs
Rule’s transmission planning process. developed throughout the country,
in planning. NCEMC stresses that
Accordingly, in addition to preparing a including those administered by RTOs
effective regional planning requires
system plan for its own control area on and ISOs and in certain sub-regions of
participation on a sufficient scale to
an open and nondiscriminatory basis, the West and Southeast. For example,
encompass all LSEs within a natural
each transmission provider will be each of the Commission-approved RTOs
market area in order to properly address
required to coordinate with in the Northeast, Midwest, and
seams issues and impacts on interconnected systems to (1) Share
neighboring systems. Fayetteville does Southwest, as well as CAISO, provide
system plans to ensure that they are for a coordinated and regional planning
not believe NC Transmission Planning simultaneously feasible and otherwise
complies with the planning principles process with stakeholder input from
use consistent assumptions and data each industry segment. There are
outlined in the NOPR. and (2) identify system enhancements several other promising efforts to
Midwest that could relieve congestion or establish voluntary coordinated and
integrate new resources (discussed regional planning efforts around the
521. MISO believes its current further below).313 country as noted in our discussion
transmission planning process 524. As discussed earlier in this Final above of existing regional planning
represents industry best practices, Rule, since the advent of open access, processes.
arguing that it is open and inclusive and power markets have become regional in 526. The Commission fully supports
provides multiple opportunities for almost every area of the country. These these existing efforts and believes some
entities to participate. MISO regional markets provide opportunities of them are consistent in significant
Transmission Owners endorse the respects with the nature of the reforms
existing MISO transmission planning 311 We note that FMPA filed joint comments on
adopted in this Final Rule. In those
process and believe that the process behalf of itself and the Midwest Municipal
Transmission Group. regions and sub-regions that already
already provides for regional planning 312 See also Seminole Reply. have adopted significant reforms, the
and an open process with stakeholder 313 As provided for above, transmission providers Commission’s planning reforms may
involvement. Ohio Power Siting Board, will be required to file a ‘‘strawman’’ proposal for require only modest changes, while
however, claims that MISO’s compliance with the Final Rule’s planning process other regions and sub-regions may need
transmission planning process should within 75 days after publication of the Final Rule
in the Federal Register that includes, among other
to undertake more significant changes to
not be regarded as best practices, stating things, a specification of the broader region in the way in which transmission currently
sroberts on PROD1PC70 with RULES

that it is not sufficiently open and which they propose to conduct coordinated is planned. The Commission will not in
transparent. It also suggests that RTOs regional planning. The Commission will then this Final Rule opine on the
merely ‘‘rubber stamp’’ investor-owned convene technical conferences in several broad
regions around the country to assist the participants
characteristics of existing regional
in developing the appropriate regional planning planning processes or their consistency
310 See also TDU Systems Reply. groups to the extent they do not already exist. with the reforms we adopt today.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00067 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12332 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Rather, each process will be addressed The Commission explained that the Duke, South Carolina E&G, and
in the context of the relevant studies should analyze and report on (1) Southern agree that separate studies of
compliance filing. In general, however, The location and magnitude of the congestion, beyond studies performed to
the Commission urges participants in congestion, (2) possible remedies for the meet service requests, should not be
existing regional planning processes to elimination of the congestion, in whole required. Rather than mandating
closely examine whether improvements or in part, (3) the associated costs of congestion studies, Southern argues that
may be implemented to ensure that each congestion, and (4) the cost associated the Commission should allow
regional planning process is fully with relieving congestion through participants to determine which types of
consistent with the requirements of this system enhancements (or other means). transmission studies have merit. Other
Final Rule. The Commission sought comment on commenters believe that, if congestion
527. Finally, the Commission how to define ‘‘significant and studies are required, they should be
acknowledges the importance of recurring’’ congestion, such as by performed at a regional level rather than
identifying the appropriate size and reference to generation redispatch, by each transmission provider
scope of the regions over which regional repeated denials of service requests, individually.317
planning will be performed. We agree zero ATC, frequent curtailments or a 532. The EEI position is
that transmission providers, customers, combination of these factors. The representative of entities calling for
affected State authorities, and other Commission noted that the required elimination of the congestion study
stakeholders should be involved in congestion studies would address both principle. EEI asserts that these studies
developing those regions. We decline to ‘‘local’’ congestion (i.e., within the in large part would be duplicative of the
mandate the geographic scope of transmission provider’s system) and studies being performed by DOE
particular planning regions at this time. congestion between control areas and pursuant to EPAct 2005.318 EEI also
The scope of a particular planning sub-regions. The Commission stated that argues that these studies would be
region should be governed by the the purpose of this requirement is to costly and time-consuming and that
integrated nature of the regional power ensure that affected market participants, transmission providers generally do not
grid and the particular reliability and State commissions, and the Commission have access to information needed for
resource issues affecting individual understand both the costs of recurring cost impact analysis and consequently
regions and sub-regions. In very large transmission congestion and the cannot assess the cost of constraints.319
regions, there may well be both sub- alternatives for relieving it. The TDU Systems assert on reply that it is
regional and regional processes. For Commission sought comment on how difficult to imagine that providers do
example, in the West there are various this information should be used by not have the information needed or
sub-regional processes in addition to a transmission providers and market means to determine the location and
WECC regional planning process. We participants to address significant and magnitude of congestion on their
believe that such an approach can work, recurring congestion. systems, since they perform this
provided that there is adequate scope to function for themselves already. TDU
the sub-regional processes and adequate Comments Systems add that customers will readily
coordination between sub-regions. We Need for Congestion Studies provide any information needed for
expect sub-regions to coordinate as congestion studies, as it is in their
necessary to share data, information and 530. The Commission’s proposal interest to do so. APPA believes that
assumptions as necessary to maintain regarding congestion studies gave rise to customers should be expressly required
reliability and allow customers to a wide range of comments. Some to produce information to help
consider resource options that span the commenters generally support requiring determine the cost of congestion (e.g.,
sub-regions. congestion studies.314 East Texas the additional cost to them of running
528. In response to the commenters Cooperatives asserts that congestion or purchasing more expensive
that indicate that regional planning studies will greatly assist in the generation). TDU Systems also argues
already occurs today as part of the development of transmission plans, that the distinction between economic
NERC planning process, we support any enable planning participants to focus on and reliability upgrades is a fiction and
such processes, but reiterate that, if they key elements of the system and assist in should be disregarded.
are to meet the requirements of the Final the preparation of the congestion 533. In the Western Interconnection,
Rule, they must be open and inclusive studies conducted by DOE. NRECA also entities maintain that WECC will be
and address both reliability and supports requiring congestion studies, performing congestion studies that
economic considerations. As we discuss but urges the Commission not to be should meet the requirement. As a
elsewhere in this section, customers prescriptive. result, they assert that this principle
must be allowed to request that 531. Other commenters recommend should not be applied to individual
economic upgrades be studied and, eliminating the requirement.315 transmission providers in the West, but
therefore, we will require transmission Southern, for example, argues that that these providers should be permitted
providers to coordinate on these issues congestion studies could be misleading to meet the principle through the
as necessary in sub-regional or regional because they can imply that all interconnection-wide congestion studies
planning processes. To the extent the congestion needs to be remedied.316 conducted by WECC. Tacoma notes that
NERC processes are not considered ColumbiaGrid is considering the
314 E.g., APPA, Arkansas Commission, California
appropriate for such economic issues,
Commission, East Texas Cooperatives, Entegra, 317 E.g., Imperial, MidAmerican, Nevada
individual regions or sub-regions may NCPA, CREPC, Southwestern Coop, TDU Systems, Companies, NorthWestern, Pinnacle, Salt River,
develop alternative processes. and WIRES. SWAT, WestConnect, and Xcel.
315 E.g., American Transmission, EEI, Progress 318 Others assert that the DOE studies will be
h. Economic Planning Studies Energy, and Southern. useful but not necessarily duplicative of the
sroberts on PROD1PC70 with RULES

529. In the NOPR, the Commission 316 Entegra, however, replied to Southern’s congestion study principle. E.g., APPA and Salt
proposed to require transmission assertion that congestion studies can be misleading, River.
stating that congestion studies did not need to be 319 Bonneville agrees that the costs of congestion
providers to prepare studies identifying misleading, and were, on the contrary, necessary for itself are not readily available to transmission
‘‘significant and recurring’’ congestion customers to assess the costs of managing versus providers and that customers are better positioned
and post such studies on their OASIS. eliminating congestion. to determine this.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00068 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12333

services it can offer in congestion congestion on the path. Additionally, primary objective in adopting this
assessment at the sub-regional level in Santa Clara emphasizes that if, principle is to ensure that the
the Northwest. Other commenters, such redispatch is necessary on an ongoing transmission planning process
as California Commission, Salt River, basis, this should be taken as an encompasses more than reliability
and Seattle, support a congestion indication that new facilities need to be considerations. Although planning to
studies requirement but believe it built. maintain reliability is a critical priority,
should not be required annually but 538. New York Commission urges the it is not the only one. Planning involves
rather biennially or triennially. Commission to utilize NYISO’s process both reliability and economic
534. In the Eastern Interconnection, for measuring historical congestion— considerations. When planning to serve
RTOs and ISOs, and entities in RTOs defined as the short-run production (i.e., native load customers, a prudent
and ISOs, believe congestion studies are dispatch) costs that could be avoided by vertically integrated transmission
not needed where LMP markets are in system enhancements, as this represents provider will plan not only to maintain
place or are satisfied by RTO or ISO the savings to society compared to the reliability, but also consider whether
studies.320 Entergy argues that the cost to society of investing in the system transmission upgrades or other
congestion studies that will be enhancement. New York Commission investments can reduce the overall costs
performed by its independent also cautions the Commission against of serving native load. Such upgrades
coordinator of transmission should meet using analyses focused on the impacts can, for example, reduce congestion
this requirement. of transmission investments on (redispatch) costs or integrate efficient
wholesale energy prices, because these new resources (including demand
Determining ‘‘Significant and energy price impacts may be temporary
Recurring’’ Congestion resources) and new or growing loads.
and offset by changes in generation Thus, to represent good utility practice
535. A variety of commenters provide investments. TDU Systems and Old and provide comparable service, the
suggestions as to what constitutes Dominion stress that in PJM significant transmission planning process under
‘‘significant and recurring’’ congestion. and recurring congestion should be the pro forma OATT must consider both
TDU Systems believe that there should based on total gross congestion and not reliability and economic considerations.
be a presumption of congestion if a the much smaller and unrealistic The purpose of this principle is to
transmission provider posts zero ATC. measure of unhedgeable congestion, as ensure that the latter is considered
TDU Systems, APPA, and Bonneville this masks the economic reality that adequately in the transmission planning
believe that other indications of congestion itself has an economic process.
significant and recurring congestion cost.321
include the need for frequent generation 539. The Organizations of MISO and 543. Some commenters argue that
redispatch, frequent curtailments for PJM States do not believe the Final Rule economic upgrades should be
reasons other than force majeure, and should address criteria for determining considered only in the context of
repeated denials of requests for firm significant and recurring congestion, but individual requests for service under the
transmission service. California should require each transmission pro forma OATT. The Commission
Commission and CREPC suggest a provider to file criteria for inclusion and disagrees. The process for addressing
similar approach based on a comparison cost responsibility for upgrades that are individual requests for service under the
of ATC and schedules with historical included in the transmission plan to pro forma OATT is adequate for
flows and an assessment of denied remedy congestion. customers who request specific
requests, but emphasize that the process 540. Seattle asserts that current transmission rights to purchase power
should be forward-looking as well. OASIS standards do not support from a particular resource in a particular
536. APPA suggests the use of metrics consistent tracking of service denials location during a defined time period.
to measure congestion (e.g., reporting on and that this inhibits the evaluation of However, it does not provide an
all congestion costs that exceed five congestion. Seattle also points out that opportunity for customers to consider
percent of base energy costs and five the costs of congestion may be difficult whether potential upgrades or other
percent of the hours in a season). to quantify because reliability dispatch investments could reduce congestion
California Commission also suggests the is a reactive tool used only after service costs or otherwise integrate new
use of metrics, but cautions that there requests have been denied and resources on an aggregated or regional
may be East-West differences. prescheduled limits imposed and, basis outside of a specific request for
Sacramento stresses that such metrics therefore, foregone transactions will not interconnection or transmission service.
should depend on whether the system be known to the transmission provider. It thus limits, for example, groups of
being studied uses LMP or physical 541. Ohio Power Siting Board asserts customers from considering more
rights. In its view, financial metrics are that distributed generation, demand comprehensive solutions to
most useful in LMP markets, while response, and new technologies should transmission congestion, including
congestion in physical markets should be available to relieve congestion until investment in demand response. It also
be determined by paths that have been longer-term solutions can be limits multiple LSEs from considering,
derated by a material percent of their implemented. on a more aggregated basis, whether
nominal rating over a certain number of particular upgrades may represent the
Commission Determination most economic means of integrating
hours in a season.
537. Santa Clara suggests that 542. The Commission adopts the new generation resources (e.g., wind
significant and recurring congestion NOPR proposal and retains a congestion resources) located in a common area
exists when congestion costs over a study principle as part of the Final that could be accessed by many
given path during the high use season Rule’s transmission planning process; customers. The Commission believes
approach or exceed the depreciation however, we modify and clarify the such coordinated studies can, for system
sroberts on PROD1PC70 with RULES

plus other fixed costs on the new principle in certain important respects planning purposes, be more beneficial
facilities that would eliminate in response to the comments received. than studies performed on a request-by-
At the outset, we wish to clarify that our request basis. We also find that they are
320 E.g., Allegheny, FirstEnergy, Indianapolis consistent with the requirement to
Power, and PSEG. 321 See also Indicated Parties Reply. provide comparable service.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00069 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12334 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Transmission providers are not limited, 546. Some commenters express resources on an aggregated or regional
in serving native load customers, to concern that this principle may result in basis without having to submit a
studying potential transmission costly congestion studies that are of specific request for service. This
upgrades only in the context of specific little interest or value to customers. Our approach ensures that the economic
requests for service under the pro forma intent is not to impose a costly study studies required under this principle are
OATT. requirement that is unrelated to the real- focused on customer needs and
544. Some transmission providers world concerns of consumers. In the concerns, not administratively
appear to object to this principle NOPR, we sought comment on whether determined metrics that may bear no
because they fear that an obligation to specific metrics (e.g., zero ATC or TLR necessary relation to those concerns.
study potential upgrades is equivalent frequency) should be used to trigger the Once such studies are requested, the
to an obligation to fund or build such congestion study requirement. After transmission provider would conduct
upgrades. We clarify that this is not the considering the comments on this topic, the studies, including appropriate
intent of this principle. There is a we do not believe that any single metric, sensitivity analyses, in a manner that is
difference between a planning process or group of metrics, is adequate for that open and coordinated with the affected
that is coordinated and open and one purpose. Relying on discrete metrics in stakeholders. The cost of the defined
that dictates construction and cost this instance would risk both over- and number of high priority studies would
responsibility. Both considerations are under-inclusiveness—i.e., triggering too be recovered as part of the overall pro
important, but, as we explain above, many studies, thereby imposing cost forma OATT cost of service.324 By
they are distinct. The purpose of this burdens on transmission providers that limiting this principle to a defined
principle is to ensure that customers are not appropriate, or triggering too few number of high priority studies
may request studies that evaluate studies, thereby omitting important annually, we are not precluding
potential upgrades or other investments studies that could help customers stakeholders from requesting additional
that could reduce congestion or identify cost-effective solutions to studies. However, to provide
integrate new resources and loads on an congestion. Additionally, we direct appropriate financial incentives, the
aggregated or regional basis (e.g., wind transmission providers, in consultation stakeholder(s) requesting these
developers), not to assign cost with their stakeholders during additional studies would be responsible
responsibility for those investments or development of their Attachment K for paying the cost of such studies.
compliance filings (as discussed above), 548. We also will modify this
otherwise determine whether they
to develop a means to allow the principle with respect to the scope of
should be implemented. The issue of
transmission provider and stakeholders the studies being performed. The
cost allocation is addressed in Principle
to cluster or batch requests for economic Commission proposed in the NOPR that
No. 9 below.
planning studies so that the the studies address ‘‘significant and
545. The Commission also disagrees recurring congestion.’’ However, the
with the contentions of certain RTOs or transmission provider may perform the
studies in the most efficient manner. We Commission also sought comment on
ISOs that they need not comply with whether, in addition, the study process
this principle. Although RTO and ISO will also require the requests for
economic planning studies, as well as should address upgrades associated
planning processes tend to be more with new generation resources and
open and coordinated than the the responses to the requests, be posted
on the transmission provider’s OASIS or provide information needed to
processes used by vertically-integrated proactively evaluate such resources. We
transmission providers, this does not Web site, subject to confidentiality
discuss the comments on this proposal
mean that RTO or ISO processes requirements.
in more detail below, but, as described
adequately address, in all 547. The Commission will modify the
therein, we agree that the study process
circumstances, investments that are principle to allow customers to choose
should incorporate such considerations.
primarily economic in nature. When the studies that are of the greatest value
We therefore modify Principle No. 8 to
many RTO and ISO planning processes to them. Specifically, we are modifying
encompass the study of upgrades to
were created, they focused primarily on the principle to require that
integrate new generation resources or
system enhancements necessary to stakeholders be given the right to
loads on an aggregated or regional basis.
maintain reliability. However, in recent request a defined number of high
This is appropriate because congestion
years, as congestion has increased and priority studies annually (e.g., five to
can limit both the efficient dispatch of
generation reserve margins have ten studies) 323 to address congestion existing generation resources as well as
declined, many RTOs and ISOs have and/or the integration of new resources inhibit the development of new supply
taken increasingly progressive steps to or loads. The intent of this approach is and demand resources. Moreover, many
identify investments that could reduce to allow customers, not the transmission regions of the country must make
congestion and/or integrate new provider, to identify those portions of investments in the near future to meet
resources. For example, we recently the transmission system where they load growth and, accordingly, studies of
approved a proposal by PJM to have encountered transmission the most economic means of making
significantly enhance its RTEP planning problems due to congestion or whether such investments are critically
process.322 We applaud these efforts as they believe upgrades and other important to consumers.
consistent with the direction of the investments may be necessary to reduce 549. By expanding the scope of this
reforms adopted herein. However, we congestion and to integrate new principle, we do not intend to supplant
decline to provide a blanket exception resources. The customers should be able the existing process for individual
for RTOs and ISOs. Each RTO or ISO to request that the transmission provider customers to integrate new resources or
must show that its planning process is study enhancements that could reduce loads through specific requests for
consistent with or superior to the such congestion or integrate new
sroberts on PROD1PC70 with RULES

requirements of the Final Rule in all 324 This cost recovery mechanism is comparable
323 The example of five to ten studies mentioned and nondiscriminatory because the transmission
respects.
in this Final Rule is merely illustrative. We provider already has the ability to include in its pro
recognize that the facts of each case will be used forma OATT rates the cost of service associated
322 See PJM Interconnection, L.L.C., 117 FERC to determine the number of high priority studies with studies performed on behalf of native load
¶ 61,218 (2006), reh’g pending. allowed under a transmission plan. customers.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00070 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12335

interconnection or transmission service as detail on congested local facilities transmission customers, however,
under the pro forma OATT. Rather, we that may limit customer supply options, support rolled-in cost recovery for
contemplate that any such studies or detail on local conditions where network upgrades.328 TDU Systems ask
conducted pursuant to this principle, as additional service could be provided the Commission to clarify that direct
explained above, would be for purposes through redispatch. Moreover, although assignment of facility upgrade costs
of planning for the alleviation of the DOE may identify areas where only applies to point-to-point service,
congestion through integration of new congestion exists or new generation may unless it is being used for the delivery
supply and demand resources into the be developed, the purpose of DOE of designated network resources to serve
regional transmission grid or expanding congestion studies is not to develop network load. If direct assignment is
the regional transmission grid in a specific transmission system plans to retained, TDU Systems suggest the
manner that can benefit large numbers remedy such congestion or integrate Commission consider standardizing
of customers, such as by evaluating such resources. The DOE studies are directly assignable facilities on a
transmission upgrades necessary to therefore not a substitute for a more regional basis and stress that the critical
connect major new areas of generation open and coordinated planning process factor is comparability. TAPS suggests
resources (such as areas that can to address specific upgrades that could ‘‘regional’’ cost-spreading for backbone
support substantial wind generation). reduce congestion or integrate new high voltage facilities and criticizes
Specific requests for service would resources and loads. We therefore participant funding because it
continue to be studied pursuant to require each transmission provider to encourages would-be beneficiaries to
existing pro forma OATT processes. comply with the revised economic wait and hope that others will step
550. With respect to studying the cost planning studies principle in this Final forward first.
of congestion, several transmission Rule both as to its own transmission 555. Old Dominion emphasizes the
providers argue that they do not have system and as to the regional planning need for cross-border transmission cost
access to information regarding process described above. allocation mechanisms. In joint projects,
generation costs either from their Salt River emphasizes that it is
merchant function or unaffiliated i. Cost Allocation for New Projects
inconsistent with an open season
customers. We agree that the 552. In the NOPR, the Commission approach to assign benefits to a party
transmission provider should be asked for comment on whether there and then assign cost responsibility
obligated to study the cost of congestion should be a requirement for public beyond what the project participant
only to the extent it has information to utilities to develop cost allocation would voluntarily assume based on the
do so. We make clear, however, that if principles to address the recovery of subscription rights received. Both
stakeholders request that a particular costs associated with new transmission Bonneville and TVA believe that cost
congested area be studied, they must projects. In particular, the Commission allocation principles should be based on
supply relevant data within their asked whether the development of a determination of beneficiaries and cost
possession to enable the transmission specific cost allocation principles would causation. New Mexico Attorney
provider to calculate the level of provide greater certainty and hence General stresses that cost recovery for
congestion costs that is occurring or is support the construction of new construction of transmission intended
likely to occur in the near future. To the infrastructure or whether cost allocation for wholesale or market transactions
extent that the transmission provider’s is better handled on a case-by-case should not be allocated to native load.
merchant function possesses such basis. NCPA states that it would expect some
information (e.g., redispatch cost Comments Commission deference to recovery of
information), it must provide that costs of projects identified in a truly
information to the extent necessary to 553. Several commenters express
collaborative process.
conduct such studies. Providing for concern that the Final Rule not reopen 556. At the October 12 Technical
confidential treatment and application cost allocation principles in RTOs and Conference, PJM stated that the
of the Standards of Conduct, as ISOs or in the OATTs of vertically Commission should provide generic
discussed above, will give assurance to integrated transmission providers.325 guidance on what would be acceptable
customers that their cost and other Duke argues that the Final Rule should regarding cost allocation, though
information will not be used not address cost allocation for new
Progress Energy did not favor putting a
improperly. To that end, we direct transmission at all, stating that
cost allocation approach in the pro
transmission providers to clearly define transmission pricing should be
forma OATT, as modified by the Final
the information sharing obligations evaluated in a separate proceeding.
Rule. National Grid expressed the view
placed on customers in the planning Other commenters agree that cost
that the Commission would need to
attachment to their pro forma OATT. allocation issues should be handled on
address cost allocation generally,
551. In response to those commenters a case-by-case basis.326
554. Some commenters urge the arguing that cost allocation solely on a
that argue that regional congestion project-by-project basis is inefficient.
studies should be sufficient, we agree Commission to define cost allocation
that regional congestion studies can be principles in this proceeding.327 For Commission Determination
used as part of regional transmission example, E.ON believes that the cost of 557. The Commission finds, after
planning processes required by this upgrades should be directly allocated to considering the comments, that it is
Final Rule. For example, to the extent parties benefiting from an expansion appropriate to include a specific
the DOE has extensively studied and proposes that the host transmission principle regarding cost allocation. The
congestion in certain broad areas, it is owner should coordinate and be manner in which the costs of new
not necessary or appropriate for responsible for obtaining funding. Many transmission are allocated is critical to
transmission providers to duplicate the development of new infrastructure.
sroberts on PROD1PC70 with RULES

325 E.g., Duke, EEI, ELCON, ISO/RTO Council,


these studies. However, regional studies Transmission providers and customers
MISO Transmission Owners, SCE, and Southern.
typically provide broad information on 326 E.g., APPA, Arkansas Commission, PGP, cannot be expected to support the
overall regional power flows and may Santee Cooper, Southwestern Coop, and
not provide sufficient detail on local Sacramento. 328 E.g., AWEA, NCEMC, NCPA, NRECA, Seattle,

system conditions and congestion, such 327 E.g., E.ON, National Grid and WIRES. and TDU Systems.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00071 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12336 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

construction of new transmission unless provide adequate incentives to construct Comments


they understand who will pay the new infrastructure than one that does 563. Overall comments on the use of
associated costs. We therefore find that, not. The states, which have primary an independent third party to oversee or
for a planning process to comply with transmission siting authority, may be coordinate the planning process range
the Final Rule, it must address the reluctant to site regional transmission from those who believe it is not needed
allocation of costs of new facilities. projects if they believe the costs are not to those who feel that it should be
558. The Commission emphasizes, being allocated fairly. Similarly, a required rather than merely encouraged.
however, that we are not modifying the proposal that allocates costs fairly to Arguing against the need for an
existing mechanisms to allocate costs participants who benefit from them is independent coordinator, South
for projects that are constructed by a more likely to support new investment Carolina E&G does not believe an
single transmission owner and billed than one that does not. Adequate independent third party is either
under existing rate structures. Our financial support for major new necessary or desirable. Arguing in favor
intent is not to upset existing cost transmission projects may not be of an independent coordinator, EPSA
allocation methods applicable to obtained unless costs are assigned fairly strongly supports independent oversight
specific requests for interconnection or to those who benefit from the project. and believes that third party oversight
transmission service under the pro 561. These factors are particularly will be necessary in non-RTO areas,
forma OATT. The cost allocation important as applied to the economic particularly where transmission
principle discussed herein is intended upgrades discussed above—e.g., providers have conducted non-
to apply to projects that do not fit under upgrades to reduce congestion or enable transparent processes.330 Most
the existing structure, such as regional groups of customers to access new commenters fall somewhere between
projects involving several transmission generation. As a general matter, we these two positions, finding potential
owners or economic projects that are believe that the beneficiaries of any benefits in independence but concurring
identified through the study process such project should agree to support the with the proposal not to mandate it.
described above, rather than through costs of such projects. However, we 564. Several public utility
individual requests for service. We will recognize that there are free rider commenters acknowledge the potential
not impose a particular allocation problems associated with new benefits of using an independent
method for such projects, but rather will transmission investment, such that coordinator and believe the Commission
permit transmission providers and customers who do not agree to support should encourage it.331 National Grid,
stakeholders to determine their own a particular project may nonetheless for example, finds it difficult to see how
specific criteria which best fit their own receive substantial benefits from it. In a non-independent transmission
experience and regional needs. The the past, different regions have provider would be able to manage
proposal should identify the types of attempted to address such issues in a confidential information in a manner
new projects that are not covered under variety of ways, such as by assigning fair to all stakeholders and recommends
existing cost allocation rules and, transmission rights only to those who finding independent administration of
therefore, would be affected by this cost financially support a project or planning ‘‘superior to’’ non-
allocation principle. spreading a portion of the cost of certain independent administration. Other
559. Although the Commission does high-voltage projects more broadly than commenters note only that
not prescribe any specific cost the immediate beneficiary/supporters of independence can be beneficial or
allocation method in the Final Rule, we the project. We believe that a range of suggest that the Commission be open to
believe some overall guidance is solutions to this problem are available. independent third parties when
appropriate. Our decisions regarding We therefore continue to believe that offered.332 Progress agrees there can be
transmission cost allocation reflect the regional solutions that garner the
premise that ‘‘[a]llocation of costs is not benefits, but does not believe an
support of stakeholders, including independent coordinator is needed to
a matter for the slide-rule. It involves affected State authorities, are preferable.
judgment on a myriad of facts. It has no ensure confidence.
Moreover, it is important that each 565. EEI argues against an
claim to an exact science.’’ 329 We region address these issues up front, at independence requirement, seeing no
therefore allow regional flexibility in least in principle, rather than having need to require non-RTO/ISO
cost allocation and, when considering a them relitigated each time a project is transmission providers to engage
dispute over cost allocation, exercise proposed. Participants seeking to independent third parties to oversee the
our judgment by weighing several support new transmission investment planning process.333 EEI believes the
factors. First, we consider whether a need some degree of certainty regarding
cost allocation proposal fairly assigns cost allocation to pursue such 330 See also AWEA, Arkansas Commission, Old
costs among participants, including investments. Dominion, and Project for Sustainable FERC Energy
those who cause them to be incurred Policy. Old Dominion stresses that even in RTOs,
and those who otherwise benefit from 3. Additional Issues Relating to the transmission owners may have the ability to
exercise market power and, therefore, the market
them. Second, we consider whether a Planning Reform monitoring unit should have the requisite
cost allocation proposal provides a. Independent Third Party Coordinator independence and authority to investigate and
adequate incentives to construct new address undue influence.
transmission. Third, we consider 562. In the NOPR, the Commission 331 E.g., National Grid, PPL, Constellation, and

whether the proposal is generally acknowledged that an independent Tacoma.


supported by State authorities and third party coordinator would provide 332 E.g., APPA, Bonneville, California

benefits for transmission planning, but Commission, Duke, Indianapolis Power, NCEMC,
participants across the region. NorthWestern, Progress Energy, CREPC,
560. These three factors are did not propose to require Sacramento, Seattle, and TDU Systems. Some
interrelated. For example, a cost independence. Noting that public power entities, such as APPA, NRECA, and
sroberts on PROD1PC70 with RULES

allocation proposal that has broad independence could take many forms, TDU Systems are concerned with ensuring that the
the Commission sought comment on the costs of an independent coordinator do not
support across a region is more likely to outweigh the benefits.
level of independence that could 333 TVA believes that the levels of independence
329 Colorado Interstate Gas Co. v. FPC, 324 U.S. provide benefits and the institutions practiced in NERC and NAESB and the
581, 589 (1945). that could offer such independence. implementation and administration of those

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00072 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12337

planning processes proposed in the meaningful concerns if a plan does not consumers, since they are charged only
NOPR are adequate without third party treat similarly-situated customers in a with regulating public utilities, and
oversight and maintains that requiring comparable manner, where planning could be conflicted and disinclined to
third party coordination could add appears to be conducted in a act in the best interests of entities not
another layer of administration, might discriminatory manner, or in other under their jurisdiction.
encroach on State authority, and could instances where the independence of 572. NARUC supports active State
create the possibility that the planning may be in question. If disputes commission participation in both RTO
transmission provider would lose do arise in these areas and cannot be and non-RTO markets.335 NARUC asks
control of the transmission plan. EEI resolved consensually, we are available that the Commission clarify that its
however also notes that the Commission to either encourage a consensual planning proposals assume that the
could require independent oversight in resolution (e.g., by use of the Dispute results of State commission planning
circumstances where a transmission Resolution Service) or resolve them decisions relating to retail load will be
planner has failed to implement the ourselves if a complaint is filed. incorporated into the planning process
principles or has engaged in undue rather than subject to further review.
b. State Commission Participation
discrimination in planning for customer
569. In the NOPR, the Commission NARUC and New Mexico Attorney
needs.
strongly encouraged the participation of General also ask for clarification that
566. The consensus at the October 12
Technical Conference was generally State commissions and other State joint planning will allow for
supportive of the potential benefits of an agencies in the coordinated planning communications between resource and
independent facilitator, but not process, particularly with regard to transmission planners for the purpose of
supportive of a mandate. There was regional planning. The Commission developing State-required resource
general support for the idea that an sought comment on how best to plans and that this will not be
independent facilitator can assist with accommodate effective State considered a violation of the Standards
handling sensitive information and participation. of Conduct. PNM–TNMP and Southern
provide confidence that analysis of support the NARUC position in their
Comments reply comments.
information would be fair, although
several participants stated that sufficient 570. All commenters addressing the 573. New York Commission wants to
trust and confidence could be obtained question of State participation agree that ensure that the Commission’s planning
without an independent facilitator. states have an important role in responsibilities cover only transmission
transmission planning, but there were that serves a bulk power system
Commission Determination only limited comments recommending function.336 Florida Commission
567. The Commission adopts the specific processes to encourage State believes that it already has direct
NOPR proposal to not require the use of participation. Supporters of State oversight of grid planning and related
an independent third party coordinator participation generally believe that it issues, through among other things its
at this time. We agree that there are can assist in obtaining siting approval participation in the FRCC planning
benefits to be gained from independent and in cost recovery. ISO/RTO Council process and review of the annual Ten
third party oversight, as cited by and individual RTOs and ISOs point to Year Site Plan. Seattle does not believe
commenters, such as the ability to their current processes for including that any additional requirements are
manage confidential information and states in their region in the planning needed for State commission
the ability to ensure equitable treatment process. Noting the local benefits that participation. Other commenters are
of all viewpoints in planning. We can derive from interstate transmission concerned that State policy goals, such
therefore encourage transmission projects, American Transmission as California’s Renewable Portfolio
providers and their customers and other supports collaborative efforts among Standard, be included in the
stakeholders to explore aspects of states such as the Organization of MISO coordinated planning required by the
planning where the use of an States. However, American Final Rule.337 NARUC and California
independent coordinator would be Transmission and other commenters Commission also discuss State staff and
beneficial and to incorporate those suggest that the Commission defer to the fiscal constraints on participation, and
aspects in their planning process states to determine how they participate California Commission suggests that the
compliance filings. in the planning process.334 Commission consider a tariff rider to
568. It is, however, possible to comply 571. Allegheny believes it should be fund State participation.
with the principles without the use of the responsibility of the transmission
an independent third party. We expect provider to maintain good Commission Determination
the transmission plans themselves to be communication with State 574. The Commission strongly
developed under an open process that commissions. Nevada Companies assert encourages State participation in the
includes coordination among each that the real question the Commission transmission planning process and
transmission provider, its customers, should be posing is how to coordinate expects that all transmission providers
other stakeholders, and its neighbors. A the State jurisdictional role in will respect states’ concerns, such as
transmission provider will need to transmission planning and construction retail resource needs, in the planning
demonstrate to us in a compliance filing and the obligations imposed by the
that the plan meets the principles, Commission on transmission providers, 335 Similar views are expressed by APPA,
including providing a dispute resolution so that the system of coordination does Arkansas Commission, Bonneville, California
process. We believe that an open, not put transmission providers in the Commission, NCEMC, NYAPP, and CREPC.
transparent planning process, with middle between conflicting State and NYAPP, however, asks the Commission to be
meaningful coordination and dispute Commission requirements. Moreover, vigilant in not allowing State commissions
sroberts on PROD1PC70 with RULES

improper control over the planning process.


resolution, will provide a sufficient Santa Clara notes that some State 336 NYAPP, on the other hand, urges the
basis for customers to identify and raise commissions do not represent all energy Commission to require planning for all transmission
facilities, not just bulk power facilities.
standards by the regional entitities (such as SERC) 334 E.g., American Transmission, Duke, and 337 E.g., AWEA, California Commission, and

are adequate and appropriate. Progress Energy. Project for Sustainable FERC Energy Policy.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00073 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12338 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

process.338 As with any other interested flexibility the transmission provider MISO shows that flexibility is needed,
stakeholder, we emphasize that should be given in implementing the citing the wide variations within the
planning must be coordinated with principles and requested examples of MISO footprint and the difficulties
relevant State regulators (including city transmission planning processes that experienced in planning for a single
councils, local siting boards, and other comply with the proposed principles. large region. MidAmerican opposes the
agencies) that wish to participate in the NRG proposal for regional modeling
Comments
transmission provider’s planning standards, as well as the AWEA
process. We will not prescribe a 577. Commenters generally favor proposal for a regional planning
particular level of State participation, flexibility and urge the Commission not protocol, as too burdensome. Exelon
but rather encourage states to determine to be too prescriptive regarding how the expresses general agreement with the
their own level of participation, planning processes must satisfy the EEI position on flexibility, but states
consistent with applicable State law.339 planning principles. Many entities in that planning processes outside RTOs
We stress that State determinations with the Western Interconnection cite the do not presently meet the NOPR’s
respect to retail load will not be second- overall WECC process as largely requirements. Exelon states planning
guessed, but that once those compliant with the principles. Nevada processes outside RTOs should follow
determinations are incorporated into the Companies notes that the WECC process the planning direction of RTOs like
transmission plan, the transmission works well under the existing pro forma PJM.
planning principles will apply (e.g., for OATT, so that few changes should be
purposes of determining whether required to implement the proposal. In Commission Determination
similarly-situated customers are treated the East, Progress Energy and Duke cite 582. Although we allow flexibility in
comparably). NC Transmission Planning as an the development of a coordinated and
575. Just as we intend to coordinate example of an effective planning regional planning process, the
with State regulators and other agencies, process that generally meets the Commission will carefully review
we also encourage those parties to principles. transmission planning compliance
collaborate amongst themselves as well, 578. Constellation agrees with filings to ensure that each planning
particularly regionally, in order to reach providing flexibility, but believes the process is consistent with the planning
agreement on how best to review and Commission should strongly encourage principles and other requirements in
approve new transmission facilities that transmission providers to model their this Final Rule. We encourage
are the product of the coordinated and compliance filings after existing transmission providers to give
regional planning process required by processes, such as those in RTOs and consideration to existing planning
this Final Rule. We intend to defer to ISOs. ISO/RTO Council and all processes, such as those already
such agreements between State individual RTOs and ISOs argue that implemented by ISOs or RTOs, or those
regulators and other agencies in a given their processes are generally compliant
proposed by AWEA, as they work with
region as appropriate. We are, moreover, and should not be disturbed.
their customers and other stakeholders
sensitive to concerns, such as Transmission providers in RTOs and
to develop a transmission planning
Allegheny’s, about the overlapping ISOs generally support this position.340
579. Some entities believe that process that complies with the Final
nature of regulatory jurisdiction over Rule. The Commission makes clear,
planning matters. We believe the flexibility should be permitted in order
to deal with regional variations, but that however, that we do not endorse any
planning principles in this Final Rule specific existing process as a model for
will help alleviate this concern by individual transmission providers
should have limited flexibility in all transmission providers.
facilitating coordination through open,
transparent planning and enhanced implementing the planning process.341 d. Recovery of Planning Costs
exchange of information. We also Some commenters simply state that
583. In the NOPR, the Commission
understand Santa Clara’s concern that regional flexibility should be permitted,
recognized that participants in the
certain State regulators do not represent without further elaboration.342 Other
planning process must be assured of
all energy consumers in some states; commenters urge the Commission to
recovery of their costs incurred in the
however, we do not believe this detracts limit both regional and local
planning process, as well as assured that
from the significant interest that State flexibility.343
580. NRG argues that system planning the costs will be borne equitably by all
regulators and other agencies have with parties benefiting from the process. The
regard to transmission planning for their models should reflect economic
dispatch to facilitate efficient utilization Commission also sought comment on
State and region. whether there should be a principle or
and also argues in favor of requirements
c. Flexibility in Implementation and for specific criteria on the treatment of requirement regarding cost recovery and
Examples of Compliant Processes system overloads and contingencies. allocation associated with funding the
576. In the NOPR, the Commission AWEA proposes a specific regional regional planning requirement.
sought comment on how much planning protocol patterned off the Comments
‘‘Collaborative Governance’’ model
584. Public utility commenters
338 As noted above, we expect the concerns of developed during mediation for the
NARUC and others that the application of the generally support the principle that
Southeast RTO in Docket No. RT01–100.
Commission’s Standards of Conduct are inhibiting costs should be borne by the
State resource planning will be addressed in the 581. In reply to commenters arguing
beneficiaries of the process. EEI agrees,
rulemaking proceeding on the Standards of Conduct in favor of less flexibility, Indianapolis
but argues that the Commission should
in Docket No. RM01–7–000. See supra note 257. Power maintains that its experience in
339 We also recognize that there are concerns not establish a specific cost basis for
about how State regulators and other agencies will 340 E.g., Allegheny, Duke, and National Grid.
recovery, and several other commenters
recover the costs associated with their participation concur.344 NorthWestern and PSEG
sroberts on PROD1PC70 with RULES

341 E.g., APPA, East Texas Cooperatives, Seattle,


in the planning process. As discussed below, we
direct transmission providers to propose a and TDU Systems. support a cost causation principle for
342 E.g., Bonneville, Salt River, PJM, and TVA.
mechanism for cost recovery in their planning
compliance filings. These proposals should include 343 E.g., Arkansas Municipal, Project for 344 E.g., Duke, Indianapolis Power, MidAmerican,

relevant cost recovery for State regulators, to the Sustainable FERC Energy Policy, and Southwestern Progress Energy, PSEG, South Carolina E&G, and
extent requested. Coop. SPP.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00074 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12339

allocation of costs of planning, and requirement and, if so, what conditions achieve economies of scale in
Southern argues that entities that or limitations should be associated with construction. In its view, the level of
request any transmission sensitivity it. transmission investment is currently
studies should bear the costs of those increasing and joint ownership should
Comments
studies. not be expected to create additional
585. There is general agreement with 588. As a general matter, a number of sources of transmission investment.
the principle that costs should be commenters believe that the planning Third, EEI contends that prospective
recoverable, and some public utilities process should include a mandate to joint owners mistakenly believe they
request that the Commission clarify that construct identified upgrades or will not be subject to the same
all planning costs not directly assigned otherwise hold transmission providers requirements as Commission-
are recoverable through transmission accountable for carrying out the plan.347 jurisdictional owners and urge the
provider transmission rates.345 Other EEI and others argue that such a Commission to make clear that both
commenters believe that the parties in mandate would go beyond planning and jurisdictional and nonjurisdictional
the planning process should determine result in providers giving up control of owners would be subject to the same
how planning costs should be allocated their systems. In their replies, LPPC and requirements for service over jointly-
and funded. APPA urges simplicity, the Sacramento assert that the decision to owned facilities. If the Commission
avoidance of double collecting (e.g., build facilities and to carry out were to order joint ownership, Duke
LSEs should not have to pay through transmission plans must rest with argues that it must condition such
both transmission rates and transmission providers and State ownership by a nonjurisdictional entity
individually) and stresses the need to authorities and that, in any event, it is on that entity filing a safe harbor OATT
assess costs based on size and assets. unclear that the Commission has the ensuring reciprocal open access by that
Other comments are consistent with authority to compel construction joint owner.
equitable allocation of planning pursuant to regional transmission plans. 590. Tacoma notes that ColumbiaGrid
costs.346 At the October 12 Technical Conference, includes a mechanism for small users to
there was considerable discussion of the participate in transmission projects in
Commission Determination the proposal it is considering for its
obligation to build and its relationship
586. We will not propose a specific to the planning process proposed in the planning process. Xcel supports
method for recovery and allocation of NOPR. adopting the open season concept as an
planning costs in this Final Rule. We 589. While not necessarily opposed to option in joint planning requirements.
recognize, however, the importance of voluntary joint ownership arrangements Though it does not completely oppose
planning cost recovery and will require in general, many commenters oppose the principle, MidAmerican sees
transmission planning processes to the idea of mandated open seasons.348 significant practical problems in
provide a mechanism for recovery of EEI provides a representative summary developing and implementing an open
costs. We direct transmission providers of the arguments of those opposed to season proposal and regards the open
to work with other participants in the open seasons. First, EEI argues that the season idea as premature. Others
planning process, as part of the Commission does not have the authority generally support allowing for open
collaborative process described above, to order joint ownership and that joint seasons and joint ownership, but also do
to develop their cost recovery proposals ownership could interfere with State not believe they should be mandated.350
in order to determine whether all siting authority. It maintains that the 591. A number of other commenters,
relevant parties, including State instances where the Commission can however, support requiring open
agencies, have the ability to recover the order transmission construction are very seasons as a method of ensuring that
costs of participating in the planning limited and do not extend to the identified upgrades are constructed.
process. Transmission providers should authority to order joint ownership.349 ELCON is strongly in favor, stating that
also consider whether mechanisms for Second, EEI argues that joint ownership open seasons for joint ownership is an
regional cost recovery may be will not provide the benefits cited by ‘‘idea whose time has come’’ and
appropriate, such as through agreements the Commission, stating that there is expressing frustration that the
(formal or informal) to incur and ample evidence that joint ownership of Commission has not already acted on
allocate costs jointly. The Commission transmission lines is not needed to this proposal. FMPA argues that joint
will consider resulting cost recovery ownership will aid in providing
proposals, including special riders to 347 E.g., APPA, East Texas Cooperatives Reply, additional capital for transmission
transmission rates, with an eye toward FMPA, NCPA, TAPS, TDU Systems, Utah projects. TDU Systems urge the
Municipals, and WIRES.
encouraging the broadest participation 348 E.g., Allegheny, American Transmission,
Commission to require transmission
in the planning process possible. Constellation, New York Transmission Owners, providers, including RTOs and ISOs, to
MidAmerican, Duke, EEI, Entergy, FirstEnergy, hold open seasons.351 Joined by
e. Open Season for Joint Ownership
MISO, National Grid, Northeast Utilities, Arkansas Commission, TDU Systems
587. In the NOPR, the Commission NorthWestern, Progress Energy, PSEG, South argue that open seasons should not be
expressed its belief that an open season Carolina E&G, SCE, Southern, SPP, Tacoma,
Tucson, and Xcel. limited to large projects. PGP supports
to allow market participants to 349 APPA, FMPA, TAPS, and TDU Systems, open seasons when providers do not
participate in joint ownership, however, point to various sources of authority on voluntarily agree to add capacity based
particularly for large new transmission which the Commission could rely to mandate open on the results of the transmission plan.
projects, could stimulate grid seasons and joint ownership, such as: To remedy
undue discrimination under FPA sections 205 and
TDU Systems cite the Neptune and
investment and ensure that all 206; to carry out FPA section 214(b)(4)’s
customers have the ability to participate requirement to facilitate the planning and 350 E.g., Bonneville, California Commission, and

in new projects on a nondiscriminatory expansion of transmission facilities to satisfy the CREPC. Bonneville stresses that any jointly-owned
sroberts on PROD1PC70 with RULES

basis. The Commission sought comment needs of load-serving entities; as a condition of facilities should have a single operator.
market-based rate authority, FPA section 203 351 Similar comments were made by APPA,
on whether to include such a approval, or transmission rate incentives under FPA Arkansas Commission, FMPA (includes a legal
section 219; and under the permitting regulations analysis in an attachment), NCPA, MISO/PJM
345 E.g., Southern and South Carolina E&G. promulgated under FPA section 216(c)(2)(B) dealing States, Santa Clara, Southwestern Coop, TANC, and
346 E.g., Bonneville, NRECA, and CREPC. with backstop siting authority. TAPS.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00075 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12340 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Cross-Sound Cable projects, where in regions facing chronic constraints. Comments


regulated utilities failed to provide We encourage joint ownership for other 596. Most transmission provider
solutions despite the need for expansion large backbone transmission upgrades commenters favor providing for study of
of the system in those regions. Seattle included in the transmission plan some grid enhancement beyond
argues that voluntary joint ownership of developed by the planning process reliability and congestion-related needs,
projects should not be contingent upon required by this Final Rule.352 but believe the Final Rule should not
an open season requirement. TANC 594. We acknowledge, however, that mandate a specific study process.
points to current joint ownership
joint ownership can increase the Various commenters argue that the
arrangements in the Western
complexity of planning and developing Commission should allow planning
Interconnection. Sacramento likewise
a transmission project and are sensitive participants to determine details such as
notes that the joint planning and
to concerns that formal open seasons the scope, number, and cost
ownership process in the Western
can add to that complexity. We responsibility for the studies.353 MISO
Interconnection has been a success, but
therefore do not mandate open season states that it is working on these issues,
asks the Commission to make clear that
procedures to allow market participants but enhancement beyond maintaining
physical rights set asides are available
to participate in joint ownership. We reliability or reducing congestion is a
in CAISO to accommodate non-LMP co-
owners. recognize that there may be reasons, complicated subject best left to each
592. On reply, EEI, Entergy, and given the complexity of the RTO or ISO to decide.
Southern repeat arguments against joint transmission grid and changing 597. Some commenters are more
ownership and open seasons. EEI conditions of supply and demand for explicit or expansive in their
replies that FMPA’s claim that joint power, why any given facility identified recommendations. CAISO recommends
ownership will result in increased in a transmission plan may not that the Commission develop a policy to
investment is not based on fact and will ultimately be constructed. encourage construction of transmission
not increase access. In its reply, TDU Consequently, our planning reforms do lines necessary to connect renewable
Systems states that joint ownership not include an obligation to construct resources,354 and Suez Energy NA
would not, as argued by EEI, infringe on each facility identified in the plan, provides similar comments about new
State siting, as states would retain this whether individually or through joint remote generation. PJM believes the
authority over the jointly-developed ownership mechanisms. At the same planning process should look at future
project. APPA also stresses that its time, the Commission agrees that joint congestion and building for resources
members have fewer difficulties ownership may be useful in certain not yet announced. The New Jersey
obtaining service where joint ownership situations and encourages transmission Board believes that demand-side
is permitted. In their replies, Lassen, providers and customers alike to management and other solutions, such
Santa Clara, and TANC argue that the consider the use of open seasons to as distributed renewable generation,
Commission should not, as suggested by realize construction of upgrades also should be considered. WIRES and
Duke, condition the participation of a identified in the planning studies. If a ELCON believe all credible proposals
nonjurisdictional entity in a jointly- transmission provider declines to should be studied. TAPS asserts that
owned project on that entity filing a safe construct an identified upgrade, we also planning should study grid
harbor OATT, as public power entities encourage customers and third parties enhancements needed for new potential
use the capacity they need and sell the to consider, either individually or resources.355 These views are consistent
rest whether or not they have a safe jointly, development and ownership of with the views of many of the
harbor OATT on file. However, TAPS a project to the extent consistent with commenters that support additional
asks on reply that access to jointly- applicable State law. study processes.356 TDU Systems,
owned facilities be available through a however, point out that planning for
f. Specific Study Processes Beyond reliability and economics should be
pro forma OATT. Participants at the
Reliability and Congestion Reduction incorporated into the open and
October 12 Technical Conference
expressed both support for joint 595. In the NOPR, the Commission inclusive planning process and,
ownership, as well as caution. National sought comment on whether there therefore, a special study process should
Grid states that it has had good success should be a specific study process to not be needed.
with joint ownership, but that jointly- identify opportunities to enhance the 598. Other commenters are opposed
owned projects are more complicated grid for purposes beyond maintaining to additional processes: South Carolina
and can take longer to develop. reliability or reducing current E&G does not see a need for additional
congestion. Such a study process could studies; Southern believes additional
Commission Determination
allow interested entities, including State study processes would be overly
593. The Commission believes there burdensome and would divert attention
resource agencies and others, to request
are benefits to joint ownership of away from the fundamentals of prudent
the transmission provider to model grid
transmission facilities, particularly large planning; and Bonneville notes that
upgrades needed to accommodate the
backbone facilities, both in terms of market participants often make requests
construction of new resources and
increasing opportunities for investment
provide information needed to
in the transmission grid, as well as 353 E.g., EEI, MISO, NorthWestern, PSEG, and
proactively evaluate such resources. The
ensuring nondiscriminatory access to Tacoma.
Commission expected that such studies 354 Related to this, California Commission asserts
the transmission grid by transmission
would not conflict with State that regional planning processes need to be closely
customers. The comments received in
prerogatives, but rather would provide linked with the resource adequacy planning
response to the NOPR support the processes and renewable energy portfolio standards
states with better information to
notion that joint ownership can provide on the State level.
evaluate all relevant resource options.
sroberts on PROD1PC70 with RULES

these benefits in many cases. For 355 EEI replies in opposition to TAPS’ assertions

example, as TDU Systems note, the that planning should address transmission for
352 As the Commission stated in Order No. 679– potential resources, arguing that such a requirement
Neptune and Cross-Sound Cable A, ‘‘[t]he Commission will look favorably on would be cost prohibitive and would harm users.
projects have resulted in significant incentive requests that include public power joint 356 E.g., APPA, Arkansas Commission, AWEA,

amounts of new transmission capacity ownership.’’ Order No. 679–A at P 102. CREPC, Sacramento, and Seattle.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00076 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12341

for expensive studies without following (c) A written description of the Systems argue that the failure to
through on them. Santee Cooper methodology, criteria, and processes eliminate pancaked rates has caused
cautions the Commission against giving used to develop transmission plans; many of the TDU Systems to spend
license to those who would attempt to (d) The method of disclosure of many millions of dollars to build
hijack the regional planning process in transmission plans and related studies transmission from generation to
order to advance a generation-related and the criteria, assumptions and data interconnect with multiple control areas
agenda, and notes that the underlying those plans and studies; in order to avoid paying multiple
Commission’s authority does not extend (e) The obligations of and methods for wheeling charges.
to generation resource adequacy. customers to submit data to the 605. Some of these commenters also
transmission provider; advocate that the Commission should
Commission Determination (f) The dispute resolution process; move towards joint rates.360 Arkansas
599. We believe that development of (g) The transmission provider’s study
Municipal Power argues that moving
a study process for identifying procedures for economic upgrades to
toward joint rates outside an RTO will
opportunities for grid enhancement address congestion or the integration of
not only eliminate competitive barriers
beyond reliability and congestion new resources; and
(h) the relevant cost allocation outside RTOs, but would reduce the
reduction has the potential to provide disincentive to formation of new and
useful information and would generally procedures or principles.
expanded RTOs. TAPS complains that
benefit development of the transmission C. Transmission Pricing the NOPR requires regional planning,
grid. We therefore will include such but has no provision requiring
study processes within the scope of 1. General
transmission providers to build facilities
Principle No. 8. In the NOPR, that 603. As the Commission explained in to support regional needs, arguing that
principle concerned only congestion Order No. 888, the pro forma OATT was joint rates would ease this problem.
studies, but, as modified above, it now designed to include primarily non-rate
TDU Systems argue, however, that any
includes studies regarding upgrades that terms and conditions of open access
joint rate methodology should not shift
could integrate new generation non-discriminatory transmission
costs to other network customers,
resources. We note that various service. Transmission providers first
especially where surcharges are sought
commenters argued for the were required to adopt the non-rate
that might open the door to potential
consideration of demand resources in terms and conditions of the pro forma
over-recovery by transmission providers
development of enhancements to the OATT and then, in a subsequent filing
transmission grid.357 As we explain as argued in the PJM/MISO proceedings.
under FPA section 205, to propose
above, consideration of such resources Old Dominion also contends that the
corresponding rates for service provided
falls within Principle No. 8, as modified Commission should add a requirement
under their OATTs. Consistent with the
by the Final Rule. focus of Order No. 888 on the non-rate in the pro forma OATT that regional
terms and conditions of open access, the transmission costs be recovered through
g. Level of Detail in the OATT a single regional transmission rate of a
Commission did not propose broad
600. In the NOPR, the Commission reform of transmission pricing policy rolled-in nature. Relative to cost
sought comment on the level of detail to through the NOPR. Rather, the recovery, Old Dominion believes that
be required to be in the transmission Commission identified in the NOPR rolled-in zonal rates work for local
provider’s OATT regarding its planning several discrete pricing rules that it facilities within a single transmission
process. considered part and parcel of OATT owner footprint, but regional rolled-in
service that merit reform, which we rates would be necessary for larger
Comments footprints.
discuss in more detail later in this
601. Several commenters argued that section. The Commission also 606. Old Dominion also contends that
the details of the planning process specifically noted in the NOPR that the the lack of periodic review by the
should be included in the transmission purpose of this rulemaking is to Commission of stated transmission rates
providers’ OATTs.358 Seattle noted that strengthen the pro forma OATT to sends a strong economic signal to
the OATT should balance the need for remedy undue discrimination and not to transmission owners to not invest in
detailed planning requirements with the create new market structures. new transmission. Old Dominion argues
need for regional processes to evolve. 604. Despite the clear scope of this that the Commission should require
Commission Determination rulemaking, several commenters periodic rate reviews at least every five
contend that broader ratemaking years or implement formula rates which
602. The Commission agrees that the would remove economic incentives for
reforms should be implemented in order
transmission planning attachment to a failing to build transmission.
to remove obstacles to achieving
transmission provider’s OATT must 607. EEI argues that the Commission
competitive markets. Various
include sufficient detail to enable should not address in this proceeding
commenters assert that rate pancaking
transmission customers to understand TDU Systems’ proposal to require
must be eliminated in this reform,
the transmission provider’s planning transmission providers to eliminate
noting that the Commission has
process. This new attachment must pancaked transmission rates in non-
recognized in the past that pancaked
therefore include: RTO regions because it involves
(a) The process for consulting with rates inhibit the development of
competitive markets.359 Arkansas complex issues that are not easily
customers and neighboring transmission
Municipal and TDU Systems contend resolved. EEI contends that transmission
providers;
that pancaked rates are particularly providers should not be required to
(b) The notice procedures and
burdensome for customers with loads eliminate multiple transmission rates
anticipated frequency of meetings or
and resources on multiple transmission across multiple systems simply to allow
planning-related communications;
sroberts on PROD1PC70 with RULES

providers systems and those that sit TDU members to avoid the economic
357 E.g., New Jersey Board, Ohio Power Siting essentially at or on the boundaries. TDU consequences of their decisions to
Board, and WIRES.
358 E.g., APPA, NRECA, Old Dominion, and 359 E.g., Arkansas Municipal, AWEA, FMPA, and 360 E.g., Arkansas Municipal, TAPS, and TDU

Seattle. APPA also suggests OASIS posting. TDU Systems. Systems.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00077 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12342 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

purchase energy from off-system accessing and closely interacting with independent entity. In its reply
resources. the system operator’s dispatch, comments, Williams supports the rules
608. Other commenters ask the including determining if transmission based dispatch service proposed by PJM
Commission to institute much broader service is available, acquiring redispatch and states that it will reduce the
market reforms in this rulemaking, service to allow its schedule to proceed opportunity for transmission providers
arguing that the Commission will not be without curtailment, and settling to levy unjust and unreasonable
able to achieve its objectives of imbalances from scheduled levels. redispatch rates.
remedying undue discrimination and Williams agrees with Chandley-Hogan 613. PJM also contends that non-RTO/
developing competitive wholesale that a system allowing non-RTO utilities ISO systems have negative impacts on
markets without a fundamental change to deny and curtail service requests RTO systems because of the respective
in market structures. Several whenever there is little ATC left and treatment of import transactions by non-
commenters advocate changing the without offering redispatch to a third RTOs/ISOs and RTOs/ISOs and the
market structure in non-RTO markets to party is completely flawed. Williams incidence of loop flows in market
allow transmission customers to access argues that these same requests would environments. PJM argues that entities
the transmission provider’s dispatch be accommodated in an RTO through scheduling flows through PJM that
and redispatch options.361 Some redispatch as long as the RTO has actually loop onto other systems
commenters 362 go further to assert that sufficient offers to arrange a security nevertheless benefit financially because
the Commission require the use of constrained economic dispatch. they collect the difference between the
locational marginal pricing (LMP) as a 611. EPSA argues on reply that an all- relatively high price at the interface
part of OATT reform. Other inclusive, ‘‘asset-blind’’ administration where the energy is scheduled to enter
commenters 363 assert that the of open dispatch is needed to fully the PJM footprint and the lower price at
Commission would not need to adopt a eliminate undue discrimination. EPSA the interface where the energy is
full RTO market design to achieve its states that security constrained dispatch scheduled to leave the PJM footprint.
more limited objectives, but contend will provide reliable operation and When energy does not flow as
that eliminating the fundamental efficient utilization of the transmission scheduled, PJM states that the otherwise
inconsistency between the OATT rules grid by promoting the use of newer, expected, beneficial impact on the
and actual operation of the grid would cleaner and less expensive power transmission constraints are not
remove a major obstacle to other plants. EPSA urges that these issues realized, resulting in price differentials
reforms. Several commenters 364 should be explored further here or in between the affected interfaces. As a
contend that requiring use of a security another policy proceeding. Project for result, PJM contends that such
constrained economic dispatch is a Sustainable FERC Energy Policy asserts scheduled transactions only contribute
needed part of this reform. that there is no assurance of non- to the FTR revenue adequacy issues PJM
609. Chandley-Hogan contend that the discriminatory access to transmission has experienced over the last 12
key element to ensuring transmission services and competitive wholesale months.
services are provided on a just, markets unless load and potential 614. PJM asserts that it is unduly
reasonable and not unduly competitors of the control area operators preferential for a non-RTO/ISO utility to
discriminatory basis is to provide open are treated comparably during dispatch. take advantage of the benefits of the
access to the security constrained Project for Sustainable FERC Energy organized markets of a bordering RTO/
economic dispatch and the associated Policy supports additional provisions to ISO without any obligation to bear any
imbalance pricing that arises from that the pro forma OATT requiring of the costs of administering those
dispatch. Chandley-Hogan state that transparency and fairness in system markets. PJM contends that it is unduly
using a security constrained economic dispatch and redispatch such as either discriminatory and an impediment to
dispatch would also substantially an ‘‘open dispatch’’ requirement or a the development of competitive markets
reduce the problems inherent in the pro rule-based framework with standards of to permit a non-RTO/ISO utility
forma OATT’s reliance on contract conduct and OASIS disclosure, as well adjacent to an RTO/ISO’s organized,
paths and ATC for transmission service as reporting and auditing requirement to transparent markets to accept the
scheduling. eliminate anticompetitive incentives. benefits of those markets and the
610. Chandley-Hogan contend that a Project for Sustainable FERC Energy regional transmission planning process
viable path to Order No. 888 reform is Policy argues that sufficient data to that sustains them, while the same
to start from the premise that open establish marginal system costs and utility relies on non-market-based
access to the dispatch (and redispatch) permit comparisons with the prices/ congestion management and limits the
and marginal cost pricing for costs of neighboring systems should be access of its competitors, including
imbalances and redispatch to disclosed on OASIS. those who are members of the relevant
accommodate transmission are keys to 612. PJM proposes open dispatch RTO/ISO, to its dispatch sequence and
getting open, non-discriminatory access consisting of control of the dispatch wholesale prices within its service area.
to transmission. Chandley-Hogan argue function by a disinterested entity and PJM asks the Commission to declare that
the institution of a spot or balancing it would not be unduly discriminatory
that dispatch is the essential
market to allow for the formation of for an RTO/ISO to include in its tariff
transmission service and providing
real-time prices. Project for Sustainable a provision that makes an external
open access to this dispatch is a path to
FERC Energy Policy encourages the system operator’s access to those
achieving open, non-discriminatory
further separation of the system markets contingent on the external
access to transmission. Chandley-Hogan
operator’s dispatch functions from its operator providing reciprocal access to
contend that a third party cannot
merchant functions, to include specific its dispatch and planning functions for
effectively access the grid without
dispatch transparency and RTO/ISO members, as well as access to
sroberts on PROD1PC70 with RULES

361 E.g.,
comparability mandates as per PJM’s the external system’s real-time marginal
Chandley-Hogan, Constellation, and PJM.
362 E.g., Morgan Stanley and Steel Manufacturers
and Transparent Dispatch Advocates’ system cost information.
Associations. request. Project for Sustainable FERC 615. Transparent Dispatch Advocates
363 E.g., Chandley-Hogan and PJM. Energy Policy supports comparable propose on reply that the Commission
364 E.g., EPSA and Chandley-Hogan. dispatch services through an require the industry to develop inter-

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00078 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12343

control area coordination agreements to entities at issue are not similarly comparability, but rather focus on what
provide for reciprocal redispatch to situated and that open dispatch they believe are mechanisms for more
alleviate constraints at specified border concerns resource procurement, an area efficient use of the grid. Overall, Entergy
flowgates. Transparent Dispatch beyond the scope of the Commission’s does not support any changes to the
Advocates argue that redispatch over a jurisdiction. Southern further argues basic nature of the services available
larger area provides transmission that the open dispatch remedy proposed under the pro forma OATT or the
providers more options to extract the by PJM and others would require radical development of real-time markets to
full efficiency of their systems by restructuring and market reforms that ensure comparable access.
allowing import/export transactions and are unfounded, lack a legal basis and 621. In its reply comments,
intra-control area flows to continue that would result in political discord. Sacramento disagrees with PJM’s claims
would otherwise be curtailed by Southern states that open dispatch that TLRs are a discriminatory
providing redispatch of generation would violate FPA section 217 by substitute for real-time redispatch and
across a border at a lower cost than threatening the ability of LSEs to PJM’s proposal to eliminate such use of
would result had the transaction been maintain access to transmission rights to TLRs in favor of an expanded redispatch
curtailed. Transparent Dispatch serve native load. In its reply comments, obligation. Sacramento argues that firm
Advocates further propose that the Entergy states that the open dispatch customers under the pro forma OATT
Commission establish principles in the proposal should be rejected because it is do not expect TLRs, while those in Day
Final Rule to guide the development of unnecessary to ensure open access 2 RTOs expect that generation will be
these coordination agreements and transmission service, is contrary to the redispatched. Sacramento adds that
require filing of the agreements within Congressional intent in passing EPAct TLRs affect all loads, but that the nature
12 months of the issuance of the Final 2005, exceeds the scope of the of firm physical rights service is that it
Rule. Transparent Dispatch Advocates Commission’s jurisdiction by overriding will not be interrupted except in very
suggest that technical conferences may State jurisdiction over sales to retail narrow defined circumstances.
need to be scheduled to address any customers, and would result in 622. Southern argues that customers
utility specific issues that arise. opposition that will delay other reforms selling between RTO and non-RTO
616. Morgan Stanley and Steel and distract the Commission with systems are treated equally since part of
Manufacturers Association contend that divisive litigation. the transaction is under an LMP
every control area should be moving 619. Sacramento states that the treatment and the other part is under
toward LMP and that facing an proposals for mandatory redispatch, the OATT treatment. In response to PJM’s
imbalance cost measured by full control of the dispatch by a allegations that loop flows are unduly
replacement value of redispatch disinterested entity, and the institution discriminatory to its customers,
measured under LMP is the correct of a spot or balancing market to allow Southern states that loop flows are
incentive to follow a schedule. Entegra for the formation of real-time prices unavoidable consequences of integrating
similarly argues that customers and would undermine customers’ objectives electrical systems and that PJM itself
State regulators would benefit from to receive uninterrupted transmission imposes loop flows on non-RTO
more transparency regarding congestion service at a predictable price and ignore systems, the effects of which are not
on the transmission system and that the transmission system operational compensated by PJM. If PJM believes
most efficient way to provide this limitations. Sacramento states that the that entities are free-riding on its system
transparency is to require transmission value of mandatory redispatch in the or manipulating its system, Southern
providers to apply LMP models to their Western Grid is limited because argues that PJM could seek to increase
systems and to post the resulting constraints often overlap and change market participation charges or file a
modeled LMPs. from thermal to voltage to stability complaint with the Commission.
617. Several commenters object to the constraints at differing load levels and Sacramento agrees that this rulemaking
proposal for a mandatory all-inclusive redispatching large amounts of is the wrong forum for resolving seams
redispatch using bid-based pricing.365 generation to relieve constraints because issues given the stated scope of the
These commenters generally argue that of the distance between loads and NOPR. Sacramento adds that border
such a proposal could not lawfully be generation cannot be achieved in the utilities do not ‘‘free ride’’ on RTO
adopted in the Final Rule because it timeframes required to maintain markets because these markets impose
dramatically departs from the scope of reliability. Sacramento is concerned that significant costs on border entities.
the NOPR. They also argue that the PJM’s proposal would cause Sacramento also disagrees that open
proposal is bad policy because there is appropriation of generation built to redispatch would resolve loop flow
no record showing that consumers serve a transmission provider’s native problems and suggests other mechanism
would benefit from the costly and load in order to effectuate third-party for addressing loop flow. Finally,
disruptive implementation required for transmission transactions, strain the Sacramento states that TLRs are an
the proposal and that adoption of the transmission provider’s grid, and cause Eastern Interconnection process that,
proposal would create controversy given additional curtailment of native load although rare, occur in RTOs and non-
that Congress and the Commission have and firm transactions when a force RTO areas.
already rejected an LMP-based model of majeure event occurs.
620. Entergy cites the approval of the Commission Determination
industry restructuring. Sacramento adds
that given the record of transmission ICT proposal as ample evidence that the 623. As the Commission explained in
investment in RTOs, open redispatch incremental approach proposed in the the NOPR, we do not intend to
might not meet the transmission NOPR is a better means of improving undertake a comprehensive overhaul of
expansion goals of the NOPR. clarity, transparency and improvements our transmission pricing policies in this
618. Southern argues on reply that in dispatch efficiency than the rulemaking. Instead, the Commission
sroberts on PROD1PC70 with RULES

there is no legal basis for claims that a Transparent Dispatch Advocates and proposed a number of specific reforms
lack of open dispatch results in undue PJM seek to mandate. Entergy states that to discrete provisions in the pro forma
discrimination. Southern states that the the arguments posed by PJM and OATT and a clarification to our ‘‘higher
Chandley-Hogan do not target of’’ policy for pricing of transmission
365 E.g., LPPC, Entergy, and Sacramento. remedying discrimination or ensuring system expansions. Given the limited

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00079 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12344 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

scope of this proceeding, we do not in the proceeding on RTO Border Utility price of energy imbalance service, the
believe it would be appropriate to adopt Issues.367 Commission explained that it
the broader ratemaking proposals intentionally did not provide detailed
2. Energy and Generation Imbalances
suggested by commenters. Issues of rate pricing requirements.376 Instead, the
pancaking, including joint rates, 627. In Order No. 888, the Commission required transmission
regional rolled-in rates and rate reviews Commission concluded that six providers to propose rates for energy
are beyond the scope of this proceeding. ancillary services must be included in imbalance service.377
an OATT.368 One of those ancillary 630. Although transmission providers
624. Similarly, the Commission made services is energy imbalance service have different energy imbalance
clear in the NOPR that the purpose of under Schedule 4 of the pro forma charges, they typically require
the proposed rule is to strengthen the OATT.369 Energy imbalance service is customers to correct energy imbalances
pro forma OATT to remedy undue provided when the transmission within the deviation band through
discrimination and not to impose any provider makes up for any difference return in kind or a financial settlement
particular market structure on the that occurs over a single hour between that requires payment for
industry. The Commission’s focus in the scheduled and the actual delivery of underdeliveries of energy equal to 100
this proceeding was and remains the energy to a load located within its percent of the transmission provider’s
development of competitive wholesale control area.370 The Commission system incremental cost for the hour the
markets through the reduction of recognized, in general, that the amount deviation occurred. For energy
barriers to entry created through the of energy taken by load in an hour is overdeliveries, the transmission
control of transmission assets. We variable and not subject to the control customer would receive a payment
continue to believe that the appropriate of either a wholesale seller or a equal to 100 percent of the transmission
focus of this rulemaking is to strengthen wholesale requirements buyer.371 provider’s decremental cost for the hour
competitive wholesale markets by 628. The Commission found that the deviation occurred.378 Outside the
adopting reforms to address remaining energy imbalance service should have deviation band, transmission providers
areas of undue discrimination and an energy deviation band appropriate either charge the transmission customer
issues of comparability rather than for load variations and a price for (1) A percentage of the utility’s system
mandating a fundamental change in the exceeding the deviation band that is cost, such as 110 percent of incremental
market structure. appropriate for excessive load costs for underscheduling or 90 percent
variations.372 The Commission of decremental costs for overscheduling
625. We therefore reject requests to
established an hourly deviation band of or (2) the greater of a percentage of
institute systems that require the real-
+/¥1.5 percent (with a minimum of 2 system costs or a fixed charge, such as
time use of regional security constrained
MW) for energy imbalance. The $100 per MWh.379
economic dispatch and LMP for
Commission explained that this 631. While the Commission found in
granting real-time transmission service
deviation band promotes good Order No. 888 that energy imbalance
and for the settlement of imbalances or
scheduling practices by transmission was an ancillary service, it also
to otherwise require transmission recognized that another imbalance may
customers, which ensures that the
providers to use LMP-based modeling. arise for differences between energy
implementation of one scheduled
We believe that LMP market designs can scheduled for delivery from a generator
transaction does not overly burden
provide significant benefits to customers another.373 and the amount of energy actually
through more efficient use of the grid, 629. With respect to compensation generated in an hour,380 commonly
but do not believe that such market associated with the hourly energy called generator imbalance. The
designs are the only way to remedy deviation band, the Commission Commission concluded, however, that a
undue discrimination or achieve explained that, for energy imbalances generator should be able to deliver its
comparability. We continue to support within the deviation band, the scheduled hourly energy with precision
regional flexibility in market transmission customer may make up the and expressed concern that allowing a
development, provided that the market difference within 30 days (or other generator to deviate from its schedule by
design implemented by the transmission reasonable period generally accepted in 1.5 percent without penalty, so long as
providers provides other transmission the region) by adjusting its energy
customers with comparable service to deliveries to eliminate the imbalance that it would allow the transmission provider and
that which the transmission providers (i.e., return energy in kind within 30 the customer to negotiate and file another deviation
provide to their own native loads and band more flexible to the customer, if the same
days).374 In addition, the Commission deviation band is made available on a not unduly
affiliates. explained that the transmission discriminatory basis. Id. at 30,232–33.
626. We also reject arguments customer must compensate the 376 Id. at 30,234

regarding seams issues creating an transmission provider for each 377 Id.

undue discrimination between market imbalance that exceeds the hourly 378 See, e.g., Arizona Public Service Co., FERC

deviation band and for accumulated Electric Tariff, Twelfth Revised Volume No. 2,
and non-market areas that must be Schedule 4 (Energy Imbalance Charge), accepted in
resolved in this proceeding. We note minor imbalances that are not made-up Arizona Public Service Co., Docket No. ER04–442–
that there are currently processes within 30 days.375 With respect to the 003 (Sep. 30, 2004) (unpublished letter order);
underway to address seams issues both Public Service Company of New Mexico, FERC
367 Id. Electric Tariff, Second Revised Volume No. 4.,
in the Eastern and Western 368 Order Schedule 4 (Energy Imbalance Charge), accepted in
No. 888 at 31,703.
Interconnections.366 We believe that 369 Id. Public Service Co. of New Mexico, Docket No.
such seams issues are beyond the scope 370 See Id. at 31,960.
ER04–416–002 (Sep. 30, 2004) (unpublished letter
of this rule and are better addressed on order).
371 Order No. 888–A at 30,230. 379 See Idaho Power Co., 102 FERC ¶ 61,351
a case-by-case basis or, as appropriate,
sroberts on PROD1PC70 with RULES

372 Id.
(2003); Duke Electric Transmission FERC Electric
373 Id. at 30,232. Tariff, Third Revised Volume 4, Original Sheet No.
366 See, 374 Id. at 30,229. 120 accepted in Duke Energy Corp., Docket No.
e.g., RTO Border Utility Issues, Notice of
Technical Conference on Seams Issues for RTOs 375 Id. The Commission further stated that the pro ER04–812–001 (Jul. 2, 2004) (unpublished letter
and ISOs in the Eastern Interconnections, (Docket forma OATT permits schedule changes up to order).
No. AD06–9–000) (issued Jan. 25, 2007). twenty minutes before the hour at no charge, and 380 Order No. 888–A at 30,230.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00080 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12345

it returned the energy in kind at another charge the transmission customer for provisions must account for the special
time, would discourage good generator either hourly generator imbalances or circumstances presented by intermittent
operating practices.381 The Commission hourly energy imbalances for the same generators and their limited ability to
stated that a generator’s interconnection imbalance, but not both.387 precisely forecast or control generation
agreement with its transmission 633. A variety of different deviation levels, such as waiving the more
provider or control area operator should bands and pricing methods are on file punitive adders associated with higher
specify the requirements for the for generator imbalances. Rates for deviations.
generator to meet its schedule and any generator imbalance underdeliveries 636. The Commission noted that
consequence for persistent failure to range from the greater of $100/MWh or Bonneville has adopted an energy
meet its schedule.382 110 percent of system incremental cost imbalance pricing approach based on a
632. The Commission subsequently to the greater of $150/MWh or 200 three-tiered deviation band that appears
accepted in a number of cases percent of the incremental cost.388 workable for both energy imbalance
modifications to a transmission Generator imbalance rates for service and generation imbalance
provider’s OATT to include generator overdeliveries range from 90 percent 389 service. Under this approach,
imbalance provisions.383 Moreover, in of system decremental cost to 50 imbalances of less than or equal to 1.5
Order No. 2003–B, the Commission percent 390 of the decremental cost. percent of the scheduled energy (or two
permitted the transmission provider to megawatts, whichever is larger) would
a. Tiered Approach to Imbalance
include a provision for generator be netted on a monthly basis and settled
Penalties in the OATT
balancing service arrangements in financially at 100 percent of incremental
individual interconnection NOPR Proposal or decremental cost at the end of each
agreements.384 Further, in a NOPR 634. In the NOPR, the Commission month. Imbalances between 1.5 and 7.5
concerning generator imbalance noted that the existing energy imbalance percent of the scheduled amounts (or
provisions for intermittent resources, charges described in Order No. 2003 are two to ten megawatts, whichever is
the Commission proposed to establish a the subject of significant concern and larger) would be settled financially at 90
standardized schedule under the pro confusion in the industry. The percent of the transmission provider’s
forma OATT to address generator Commission expressed concern about system decremental cost for
imbalances created by intermittent the variety of different methodologies overscheduling imbalances that require
resources and to clarify the application used for determining imbalance charges the transmission provider to decrease
of the current energy imbalance and whether the level of the charges generation or 110 percent of the
provision of the pro forma OATT.385 In provides the proper incentive to keep incremental cost for underscheduling
particular, the Commission proposed schedules accurate without being imbalances that require increased
that generator imbalance provisions for excessive. The Commission therefore generation in the control area.
intermittent resources would reflect a proposed to modify the current pro Imbalances greater than 7.5 percent of
deviation band of +/¥10 percent (with forma OATT Schedule 4 treatment of the scheduled amounts (or 10
a minimum of 2 MW) and allow net energy imbalances and to adopt a megawatts, whichever is larger) would
hourly intermittent generator separate pro forma OATT schedule for be settled at 75 percent of the system
imbalances within the deviation band to the treatment of generator imbalances. decremental cost for overscheduling
be settled at the system incremental cost 635. The Commission proposed to imbalances or 125 percent of the
at the time of the imbalance.386 The create new energy and generator incremental cost for underscheduling
Commission also reiterated its policy imbalance schedules based on the imbalances. Intermittent resources are
that a transmission provider may only following three principles: (1) The exempt from the third-tier deviation
charges must be based on incremental band and pay the second-tier deviation
381 Id.
cost or some multiple thereof; (2) the band charges for all deviations greater
382 Id.
383 See, e.g., Niagara Mohawk Power Corp., 86
charges must provide an incentive for than the larger of 1.5 percent or two
FERC ¶ 61,009, order on reh’g, 87 FERC ¶ 61,148
accurate scheduling, such as by megawatts.
(1999) (Niagara Mohawk); PacifiCorp, 95 FERC increasing the percentage of the adder 637. The Commission sought
¶ 61,145, order on reh’g and clarification, 95 FERC above (and below) incremental cost as comment regarding whether this tiered
¶ 61,467 (2001); Alliant Energy Corporate Services, the deviations become larger; and (3) the
Inc., 93 FERC ¶ 61,340 (2000); Wolverine Power approach should be adopted for
Supply Coop., 93 FERC ¶ 61,330 (2000);
387 Under existing Commission policy, a
inclusion in the pro forma OATT for
Commonwealth Edison Co., 93 FERC ¶ 61,021 energy and generator imbalances. The
(2000); FirstEnergy Operating Cos., 93 FERC transmission provider may only charge a
¶ 61,200 (2000), order denying reh’g & granting transmission customer for the penalty percent adder Commission specifically asked whether
clarification, 94 FERC ¶ 61,184 (2001); Tampa to the incremental cost for either hourly generator this approach provides sufficient
Electric Co., 90 FERC ¶ 61,330 (2000), reh’g denied, imbalances or hourly energy imbalances for the incentives to ensure that transmission
95 FERC ¶ 61,101 (2001); Florida Power Corp., 89 same imbalance. For example, if a transmission
customer has a 100 MWh point-to-point schedule systems can be operated in a reliable
FERC ¶ 61,263 (1999); Consumers Energy Co., 87
FERC ¶ 61,170 (1999) (Consumers). in a control area, but produces 105 MWh and manner and ensure that customers are
384 Order No. 2003–B at P 74–75. consumes 105 MWh, the transmission provider may treated in a just and reasonable manner.
385 Imbalance Provisions for Intermittent charge the transmission customer 110% of its
Resources; Assessing the State of Wind Energy in incremental cost for the 5 MWh of energy Comments
Wholesale Electricity Markets, Notice of Proposed imbalance, but then must pay the transmission
customer its incremental cost for the 5 MWh 638. A number of entities generally
Rulemaking, 70 FR 21349 (Apr. 26, 2005), FERC
Stats. & Regs. ¶ 32,581 at P 9 (2005) (Imbalance generator imbalance. support a tiered approach to imbalance
Provisions Proceeding).
388 See Duke Energy Corp., Docket No. ER05–855–
penalties that progressively increases
386 The Commission defined incremental cost as 000 (Dec. 20, 2005) (unpublished letter order) the penalties for imbalances, as
‘‘the transmission provider’s actual average hourly (accepting Duke Electric Transmission’s Large
Generator Interconnection Agreement with Power implemented by Bonneville.391 These
cost of the last 10 MW dispatched to supply the
sroberts on PROD1PC70 with RULES

transmission provider’s native load, based on the Ventures Group, LLC (Duke Delegated Letter
replacement cost of fuel, unit heat rates, start-up Order)). 391 E.g., Ameren, Northwest IOUs, Progress
389 See Entergy Services, Inc., 90 FERC ¶ 61,272
costs, incremental operation and maintenance costs, Energy, Suez Energy NA, Public Power Council,
and purchased and interchange power costs and (2000) (concerning various generator imbalance Sacramento, South Carolina E&G, Pinnacle,
taxes.’’ Id. at P 9 n.17 (citing Consumers, 87 FERC agreements). Allegheny, TDU Systems, Constellation, Imperial,
¶ 61,170 at 61,179 (1999)). 390 See Duke Delegated Letter Order. and Morgan Stanley.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00081 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12346 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

commenters generally state that a that facing an imbalance cost measured of the inclusion of a generation
graduated bandwidth approach by full replacement value of redispatch imbalance OATT mechanism. TDU
recognizes the link between escalating measured under LMP would be an Systems contend that the Commission
deviations and potential reliability appropriate incentive. Morgan Stanley should require that the specific
impacts on the system. Other entities, contends that the pro forma OATT bandwidths and the basis for the
however, take issue with aspects of the should specify using opportunity cost charges be spelled out in detail in the
Commission’s proposal or propose a principles to charge for imbalance revisions to the pro forma OATT and in
different approach to resolving solutions in those areas without LMP each transmission provider’s tariff.
imbalances. For example, Entegra and come as close to mimicking the Allegheny argues that changing Energy
submits that the Commission should result under LMP as possible. In reply Imbalance Service from Schedule 4 to
require transmission providers to comments, Mark Lively suggests the Schedule 4a, adding a new Schedule 4b
establish, or permit market participants Commission make the price for for Generator Imbalance Service, and
to establish, markets or pools for the imbalances a function of the size of Area eliminating proposed Schedule 9 would
netting and settlement of imbalances. Control Error. Public Power Council call attention to the fact that a
Steel Manufacturers Association argues recommends that transmission transmission provider may only charge
for the Commission to require real-time providers not assess penalties against a transmission customer either an
balancing markets. loads or resources when their deviations hourly generator imbalance charge or an
639. Among those supporting the from the schedule help the system in a hourly energy imbalance charge, but not
Commission’s proposal, Ameren asserts given delivery hour. TDU Systems argue both for the same imbalance.
that the tiered approach properly allows that inadvertent scheduling errors that 644. Other entities contend that the
for higher penalties for imbalances that do not threaten system integrity or Commission’s imbalance proposal will
have a greater impact on the system and reliability should not be penalized not do enough to protect reliability and
thus have a greater potential to affect through charges for imbalances that prevent entities from deviating from
reliability. NorthWestern is not opposed exceed incremental cost in the upper their schedules. Entergy states that the
to the generation imbalance provisions tiers of imbalance bandwidths. Commission should recognize that a
applying to all generators, arguing that 642. Although FirstEnergy states that system with significant hydro resources,
imbalance charges must be based upon the Bonneville approach for generator such as the Bonneville system, faces
incremental cost and must provide an imbalances is appropriate, it argues that different challenges in matching
incentive for accurate scheduling. the current pro forma OATT generation and load than a system with
Morgan Stanley contends that basing the methodology for calculating and predominantly thermal generation.
imbalance charge on incremental cost assessing energy imbalances should be Unlike the fast ramping capability of
should be a bedrock principle for retained. FirstEnergy argues that it is hydro units, Entergy asserts that thermal
developing methods to financially settle more appropriate and fair to apply a units have a more limited ability to
imbalances. graduated penalty structure to adjust and compensate for imbalances.
640. Progress Energy, Sacramento, generation imbalances since greater Entergy adds that the Bonneville model
and Entergy encourage the Commission deviations usually occur from may not provide sufficient incentives in
to allow each transmission provider to generation. Ameren, however, believes those areas with large amounts of
have the flexibility to craft penalty that generators are generally better able independent generation. In reply
provisions that provide the right to control their imbalances than comments, some APPA members noted
incentives to encourage their transmission customers who take energy that wind variability may pose
transmission customers to act off of the system and that the use of a significant operational concerns that
responsibly. Grant similarly contends narrower deviation band may be could increase regulating reserve
that the transmission provider must be appropriate for generator imbalances. requirements, particularly on smaller
able to decide what to charge for Nonetheless, Ameren states that it does transmission systems.
imbalance services and must consider not oppose the Commission’s proposal 645. Steel Manufacturers Association
the incentives for resource development to use the same deviation bandwidths asks the Commission to delete any
and the potential for cross-subsidies for both energy imbalances and further reference to charges based on
paid by other customers associated with generator imbalances. some multiple of incremental costs,
such pricing. Grant argues that 643. Ameren contends that which applies to scheduling incentives,
transmission providers should have an developing standardized provisions for not cost recovery. It believes that
ability to ‘‘opt out’’ if they can generator imbalances in the OATT charges based on multiples of
demonstrate an inability to provide the would eliminate the plethora of incremental costs are not necessary and
service without creating an undue penalties that now exist. Ameren asserts do not produce rates that are just and
burden on other ratepayers. that moving to a tariff approach would reasonable. Steel Manufacturers
641. Constellation, while supporting increase transparency and would help Association asserts that balancing
the Commission’s proposal, asks that address the situation where such mechanisms based on real time market-
transmission providers be required to provisions may appear either in the clearing prices provide full
utilize a security-constrained economic relevant OATT or in specific compensation and adequate scheduling
dispatch to procure and settle interconnection agreements (at least for incentives in the organized markets and
imbalances at least cost, which would interconnection agreements entered into there is no reason to apply a deadband/
ensure that least cost is determined on as of the date of the revised tariff penalty mechanism for individual
the most efficient basis. Constellation provisions). Progress Energy and South OATT providers unless there is a
contends that imbalance charges should Carolina E&G support separate tariff (or demonstrated need, i.e., a showing that
be based on the transmission provider’s Generator Interconnection Agreement) excessive gaming by LSEs or generators
sroberts on PROD1PC70 with RULES

actual cost of meeting a positive provisions for these services, suggesting has been a problem.
imbalance or liquidating a negative that generator and energy imbalance 646. Steel Manufacturers Association
imbalance, which costs can include provisions could be tailored for also contends that the current imbalance
required ancillary services and generators and LSEs. NorthWestern mechanism is a losing proposition for
redispatch costs. Morgan Stanley states states that it has long been an advocate loads that cannot control energy

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00082 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12347

consumption to match an hourly states that using a 100 percent credit for imbalance penalties under the pro
schedule of energy deliveries, with net overgeneration would result in forma OATT.
transmission providers receiving crediting the generator more than 651. Indianapolis Power contends on
windfall revenues. It argues that the $28,500. reply that variation should be allowed
mechanism is unfair to smaller 649. WECC states that it is very to account for the individual facts and
transmission systems that are not important to differentiate between the circumstances associated with a specific
control areas (and therefore may not kind of behavior that the Commission is region as well as specific types of
settle all of their imbalances through worried about and appropriate practices
return-in-kind energy) and certain retail intermittent resources. A number of
that support system reliability. WECC is entities agree with providing flexibility
customers that take unbundled retail concerned that inflexible generator
transmission service. Steel to intermittent generators, but suggest
imbalance provisions in the pro forma
Manufacturers Association asks the different ways of doing so.392 Fertilizer
OATT may create incentives for
Commission to institute a larger Institute agrees that intermittent
generators in the West to restrict
bandwidth of, at minimum, 10 percent governor action on their generators in resources should be exempt from any
for small wholesale customers and ways that degrade system reliability. penalties beyond the 90 percent/110
discrete retail loads. It contends that WECC notes that the number of rotating percent ‘‘second tier.’’ However,
large utilities and wholesale machines connected to the grid in the Fertilizer Institute also believes that
transmission customers that acquire Eastern Interconnection is much greater intermittent resources should receive
power for many discretely operated than in the Western Interconnection, greater tolerance before they run into
loads with varying load stages and load which impacts the ability of generators the 90 percent/110 percent penalty level
factors and averaging those loads creates to respond to maintain frequency when in the first place. Fertilizer Institute
an overall predictability to load curves a system’s load-resource balance urges the Commission to relax the first-
that permits the practical use of a 1.5 changes. WECC explains that a sudden tier tolerance band from 2MW to 20MW
percent bandwidth for large utilities and change in load-resource balance of a (or 40 percent of nameplate capacity,
wholesale customers. particular magnitude (for example, the whichever is greater) for intermittent
647. Utah Municipals assert that the loss of a 1,000 MW generating plant) generators only. It asserts that this
Commission is wrong to believe that will require a proportionately greater action is consistent with the
imbalances tend to result from response from each generating unit in Commission’s recognition that
carelessness or intentional conduct the West as compared to the Eastern intermittent generators can undergo
rather than unavoidable uncertainties sudden changes of conditions for which
Interconnection. WECC contends that in
and error. Utah Municipals contend they cannot fairly be held responsible.
the West a significant frequency decline
that, while technology that permits Fertilizer Institute argues that a broader
could cause responding generators to
perfectly accurate scheduling (i.e.,
exceed a 1.5 percent deviation threshold first-tier tolerance band for these
namely the AGC equipment used by
applied under current pro forma Tariff generators will present no threat to the
control area operators) is theoretically
imbalance schedules. transmission grid, because intermittent
available, it is prohibitively expensive
for many transmission customers and 650. If the manner of implementing generation facilities are limited both in
unavailable to those who do not own generator imbalance charges in the West size and in number.
generation. Utah Municipals argue that does not consider the need for 652. Geothermal Producers supports a
financial incentives for accurate generators to respond to frequency first-tier deviation band of +/¥5 percent
scheduling do not alter scheduling deviations, WECC worries that these for intermittent resources, rather than
behavior or actual imbalances, but only charges could produce perverse the 1.5 percent threshold proposed by
result in a potential windfall for the incentives that will undermine Bonneville. Geothermal Producers
transmission provider and a potentially reliability. WECC argues that generators believes a 5 percent band is appropriate
significant competitive advantage for that use set-point controllers to override for intermittent resources, since a five
the transmission provider’s market governor action will be less likely to percent band more accurately
function, which (because of the AGC incur imbalance charges and penalties, recognizes that intermittent resources
equipment that all transmission while those with properly operating
are less capable of controlling
customers pay for through rates) will governors may be punished for
deviations from schedules than are
not be subject to the charges. Utah deviating from scheduled output to
conventional resources. For over- or
Municipals suggest that the Commission respond to system reliability needs.
under-deliveries in excess of five
limit the imbalance charges for WECC believes that this has in fact been
percent, Geothermal Producers contends
unintentional deviations by applying happening in the West and is one of the
reasons that frequency response in the that intermittent resources should be
the third deviation band only to charged no more than the control area’s
intentional imbalances. Western Interconnection has
deteriorated in recent years. WECC cost of supplying energy to correct the
648. Imperial argues that the
urges the Commission to consider how imbalance. Geothermal Producers also
Bonneville approach would not provide
generators can be given appropriate supports Bonneville’s position that
appropriate incentives for small
geothermal generating units on its incentives to meet their obligations to intermittent resources should be exempt
system to control their scheduled supply energy to load but also to from the third-tier deviation band and
output, especially if imbalances are support system reliability by effectively instead should pay the second-tier
recorded on an hourly basis rather than responding to frequency deviations. deviation band charges for all deviations
on a cumulative basis over the course of WECC explains that the Commission greater than the second-tier deviation
a month. Under the Bonneville could adopt a policy that set-point band.
sroberts on PROD1PC70 with RULES

approach, Imperial asserts that it would controllers should not be allowed to 653. Other commenters, however, do
have to pay its generators 100 percent of override governor response. WECC not support providing exceptions for
its incremental cost for overgeneration suggests that deviations from scheduled
because such imbalances are usually generator output needed to correct 392 E.g., NorthWestern, Fertilizer Institute, and

less than 2 MW in any given hour. It frequency decay could be excused from Geothermal Producers.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00083 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12348 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

intermittent resources.393 If society valuable forms, such as generation with imbalance terms in agreements with
decides to provide incentives for ocean energy or ‘‘waste heat’’ from an eligible customers prior to providing
intermittent resources, Morgan Stanley industrial process. Fertilizer Institute service. Exelon suggests that the
states that this is better done in a direct asserts that the Commission should not Commission both adopt in the pro
fashion, such as a certification program broaden the definition of intermittent forma OATT a standard imbalance
akin to resource adequacy rules that resource to encompass generators who penalty structure and direct
require LSEs to source a proportion of are not truly ‘‘intermittent’’ and should transmission providers to include the
supply from such resources. Morgan not narrow the definition to exclude same terms and conditions in their
Stanley asserts that this would motivate some intermittent generators in favor of interconnection agreements with
developers to mitigate imbalance costs others. Fertilizer Institute contends on generators. TAPS suggests on reply that
through other market or technical means reply that a generator should not have each generator could simply be required
to the full extent of the economic signal to be ‘‘weather-driven’’ to qualify as to sign a service agreement that requires
imbedded in the imbalance price and ‘‘intermittent.’’ Geothermal Producers it to comply with the generator
thereby optimize the design and supports the inclusion of geothermal imbalance provisions of the
operation of such resources. energy as an intermittent resource. transmission provider’s OATT. Unless
MidAmerican argues on reply that Geothermal Resources contends that the pro forma OATT governs both
special treatment of intermittent geothermal resources satisfy both the generator and load imbalances, TAPS
resources and loads has the effect of Commission’s proposed definition and argues that it would be impossible to
penalizing those resources and loads the EEI proposal. implement and enforce the
that have made investments to manage 656. Ameren and Entergy ask the Commission’s prohibition against
scheduling and enhance reliability. TDU Commission to clarify that it does not charging both energy and generator
Systems believe that the NOPR’s third intend to amend any existing imbalances for a single transaction.
principle, which requires transmission interconnection agreements to require 660. ICNU argues on reply that the
providers to accord special treatment to the use of any pro forma imbalance Commission should adopt less
intermittent generators, is contrary to penalties. Entergy believes that the restrictive imbalance charges for retail
the principle of comparability. present form of its Generation access customers or, at a minimum,
654. Northwest IOUs argue that the Interconnection Agreement is absolutely continue to recognize that the standard
transmission provider should have the critical to managing imbalances on its energy imbalance charge needs to be
option to elect whether to exempt system and maintaining reliability. modified to accommodate direct access
intermittent resources from the third- Entergy states that it has developed customers. ICNU asks the Commission
tier deviation band and instead charge, specialized software to monitor and to modify its proposed imbalance
in a not unduly discriminatory or manage generator imbalances and provision to reflect the unique
preferential manner, the second-tier employs six system operators (one per characteristics of direct access
deviation band charge for all deviations shift) to monitor and manage generator customers by adopting wider imbalance
greater than the larger of 1.5 percent or imbalances. bandwidths and/or waiving the more
2 megawatts. 657. Although Entergy supports the punitive adders associated with higher
655. Several commenters suggested ‘‘grandfathering’’ of existing generator deviations.
that the Commission include a imbalance arrangements, it does not 661. Several entities assert that the
definition of intermittent resource in the believe that it would be appropriate to proposed imbalance reform should not
final rule. Fertilizer Institute and South require the prospective use of a different apply to RTOs. Exelon requests that the
Carolina E&G contend that it is essential methodology while simultaneously Commission explicitly state that these
for the Commission to provide a clear maintaining the grandfathered rules do not apply in regions that have
definition of ‘‘intermittent generation’’ arrangements. Entergy contends that organized markets, such as PJM, that
or ‘‘intermittent resource’’ to avoid administering two different generator obviate the need for imbalance
disputes. Fertilizer Institute argues that imbalance arrangements would not be penalties. They contend that within
the question of whether a given consistent with the comparability organized markets, an imbalance
generator is ‘‘intermittent’’—and thereby principles of Order No. 888 and would penalty rule is not necessary, as the
entitled to the special provisions—is be difficult and costly from an independent transmission operators
likely to become a source of contention. operational perspective. have effectively addressed the concerns
Fertilizer Institute suggests that an 658. Several commenters 394 argue on that the proposed imbalance schedules
intermittent resource be defined as ‘‘an reply that it would be inappropriate for are intended to address. Indicated New
electric generator that (1) Cannot store the Commission to grandfather existing York Transmission Owners contend that
its fuel sources and (2) has limited imbalance provisions. In its reply the Commission should grant the
capability to be dispatched and to comments, Entegra argues that prior NYISO a regional variation from the
respond to changes in system demand arrangements should remain in place revised pro forma OATT with respect to
and transmission security constraints.’’ only if a transmission provider can imbalance charges. It contends that the
EEI, however, suggests that the demonstrate that its existing imbalance existing mechanisms in ISO/RTO
definition apply only to weather-driven arrangements are consistent with or markets with LMP are consistent with
units. Fertilizer Institute argues on reply superior to the provisions of the pro the Commission’s objectives in its
that restricting the definition in this way forma OATT as modified by the Final NOPR and that the Commission should
would be unduly discriminatory. Rule in this proceeding. permit a regional variation to the
Fertilizer Institute argues that the 659. EEI and Exelon contend that the NYISO. SPP states that the Commission
definition should include the most transmission provider may not be able should state that it does not intend to
common forms of intermittent to charge a generator under its OATT if affect its effort to implement a real-time
sroberts on PROD1PC70 with RULES

generation—wind and solar power—as the generator is not the transmission energy imbalance market by any final
well as the less common but equally customer and, therefore, generators rule. SPP further contends that the
should be able to include standardized Commission should clarify that its
393 E.g., Morgan Stanley, Northwest IOUs, Steel energy imbalance changes do not apply
Manufacturers Association, and TDU Systems. 394 E.g., Fertilizer Institute, Entegra, and TAPS. to ISOs and RTOs with organized

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00084 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12349

markets providing for real-time energy overscheduling imbalances that require formalizing generator imbalance
imbalance markets. SPP believes that the transmission provider to decrease provisions in the pro forma OATT will
the Commission should view the generation or 110 percent of the standardize the future treatment of such
existence of a spot energy price in incremental cost for underscheduling imbalances from the wide variety of
organized markets as superior to imbalances that require increased generator imbalance provisions that
penalties based on incremental costs or generation in the control area. exist today in various generator
some multiple thereof. Imbalances greater than 7.5 percent of interconnection agreements.
662. Entegra suggests that, since many the scheduled amounts (or 10 Standardizing generator imbalances
RTOs have (or are developing) separate megawatts, whichever is larger) will be should lessen the potential for undue
markets for commitment costs, it may settled at 75 percent of the system discrimination, increase transparency
not be necessary to incorporate such decremental cost for overscheduling and reduce confusion in the industry
costs into imbalance prices in certain imbalances or 125 percent of the that results from the current plethora of
RTO markets. Organizations of MISO incremental cost for underscheduling different approaches.
and PJM States contend that this imbalances. 668. Several commenters debate
proposed change to Schedule 4 is not 665. The Commission adopts whether the imbalance provisions
applicable in the RTO context and argue Bonneville’s tariff provisions that adopted here should be applied to
that, to the extent that the Commission’s provide that intermittent resources are energy imbalances, generation
suggestions regarding the special exempt from the third-tier deviation imbalances, or both. The Commission
circumstances presented by intermittent band and would pay the second-tier concludes that subjecting both energy
generators are applicable to RTOs, those deviation band charges for all deviations and generation imbalances to the same
issues are best addressed in a context greater than the larger of 1.5 percent or charges is appropriate. Energy and
other than the instant rulemaking two megawatts. We believe this is generation imbalances have the same
proceeding. consistent with the fact that intermittent net effects on the transmission system in
generators cannot always accurately requiring other generation to be ramped
Commission Determination
follow their schedules and that high up or down to make up for the
663. In order to increase consistency penalties will not lessen the incentive to imbalance. As such, the Commission
among transmission providers in the deviate from their schedules. will modify the current pro forma
application of imbalance charges, and to 666. Several commenters argue that OATT Schedule 4 treatment of energy
ensure that the level of the charges the Commission should adopt a imbalances and adopt a new separate
provides appropriate incentives to keep standard definition of intermittent pro forma OATT Schedule 9 for the
schedules accurate without being resource. In order to clarify application treatment of generator imbalances, each
excessive, the Commission adopts in the of imbalance charges, we define an based on the tiered structure described
pro forma OATT imbalance provisions intermittent resource for this limited above. To the extent a transmission
similar to those implemented by purpose as ‘‘an electric generator that is provider wishes to deviate from these
Bonneville. We agree with commenters not dispatchable and cannot store its revised pro forma provisions, it may
that a graduated bandwidth approach fuel source and therefore cannot demonstrate in an FPA section 205
recognizes the link between escalating respond to changes in system demand proceeding that the proposed changes
deviations and potential reliability or respond to transmission security are consistent with or superior to the
impacts on the system. Furthermore, we constraints.’’ 395 We conclude that this pro forma OATT as modified by this
conclude that these provisions adhere to definition of intermittent resource Final Rule. However, we note that
the three principles discussed in the properly limits the exemption from proposed alternative provisions must
NOPR, which we also adopt here: (1) imbalance charges, without excluding comply with the three imbalance charge
The charges must be based on certain classes of intermittent generators principles addressed in the NOPR and
incremental cost or some multiple for which the exemption is appropriate adopted in this Final Rule and be
thereof; (2) the charges must provide an (e.g., non-weather driven intermittent consistent with or superior to the
incentive for accurate scheduling, such resources). specific imbalance charges set forth in
as by increasing the percentage of the 667. The Commission believes that the pro forma OATT (and discussed
adder above (and below) incremental adopting a tiered approach for both above).
cost as the deviations become larger; energy and generation imbalances will 669. Some commenters stated that the
and (3) the provisions must account for best balance the needs of transmission Commission should require
the special circumstances presented by providers to operate their transmission transmission providers to establish, or
intermittent generators and their limited systems in a reliable manner with the permit market participants to establish,
ability to precisely forecast or control needs of transmission customers to have markets or pools for the netting and
generation levels, such as waiving the reasonable access to those systems at settlement of imbalances. As explained
more punitive adders associated with just and reasonable rates. Furthermore, previously, the purpose of this rule is to
higher deviations. we conclude that the partial exemption strengthen the pro forma OATT to
664. Specifically, imbalances of less from imbalance charges for intermittent remedy undue discrimination and not to
than or equal to 1.5 percent of the resources appropriately reflects the impose any particular market structure.
scheduled energy (or two megawatts, special circumstances faced by such If transmission providers offer to modify
whichever is larger) will be netted on a resources and, consequently, is not their OATTs to allow such pools, we
monthly basis and settled financially at unduly discriminatory. Moreover, will consider such proposals. But,
100 percent of incremental or imposing such requirements goes
decremental cost at the end of each 395 See Docket No. RM05–10–000. We note that beyond the scope of this proceeding.
month. Imbalances between 1.5 and 7.5 this definition was proposed by the Commission in The Commission therefore declines, for
sroberts on PROD1PC70 with RULES

percent of the scheduled amounts (or the NOPR on Imbalance Provisions for Intermittent all these reasons, to impose the
two to ten megawatts, whichever is Resources. See Imbalance Provisions for structural reforms requested by some
Intermittent Resources; Assessing the State of Wind
larger) will be settled financially at 90 Energy in Wholesale Electricity Markets, Notice of commenters.
percent of the transmission provider’s Proposed Rulemaking, 70 FR 21349 (Apr. 26, 2005), 670. The Commission instead adopts
system decremental cost for FERC Stats. & Regs. ¶ 32,581 (2005). the three-tiered approach in the pro

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00085 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12350 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

forma OATT. As with other reforms b. Intentional Deviations elimination of the separate penalty
adopted in this Final Rule, all NOPR Proposal structure for customers deliberately
transmission providers must submit leaning on the system. Constellation and
compliance filings containing these pro 673. In the NOPR, the Commission Grant believe that a graduated
noted that the Bonneville imbalance percentage adder/discount will provide
forma tariff provisions. Transmission
provision allows for greater charges the right incentives and disincentives
providers with previously-approved
when a customer has an ‘‘intentional without the need for an intentional
tariff provisions governing imbalances deviation.’’ 396 The Commission sought
that no longer conform to the pro forma deviation provision. If deviation costs
comment on whether the pro forma are properly calculated, Morgan Stanley
OATT, as revised in this Final Rule, OATT imbalance provision should contends that requiring those who
may seek renewed approval of those provide for similar penalties for deviate to pay the full marginal cost of
tariff deviations in accordance with the behavior that represents deliberate that deviation would result in fair
procedures described in section IV.C reliance on the transmission provider’s allocation of cost responsibility and
above, demonstrating that the generation resources, as opposed to sufficient stability of system operations
alternative imbalance charge structures scheduling errors, with such penalties as a result of both cost and risk
are consistent with or superior to the being subject to prior notice and avoidance by participants. TDU Systems
reformed pro forma OATT. With respect approval by the Commission and based argue that the Commission should
to the concerns raised by ISOs and on the facts and circumstances of the eliminate the 100 mill per kWh floor for
RTOs, we agree that LMP-based markets individual transmission provider. penalties for intentional deviations.
can provide an efficient and Comments Commission Determination
nondiscriminatory means of settling
imbalances and, as indicated in the 674. Several entities contend that 676. The Commission recognizes the
NOPR, we are not proposing to redesign higher imbalance charges and penalties need to provide transmission customers
for deliberately leaning on the grid can with the appropriate incentives not to
ISO/RTO markets in this rulemaking.
be appropriate.397 Imperial supports an intentionally dump power on the
Nevertheless, ISOs and RTOs must
imbalance provision that allows for system or lean on other generation. We
follow the procedures described in the
greater charges for persistent or do not believe, however, that separate
Applicability section for seeking patterned deviations. Pinnacle agrees penalties for intentional deviations need
approval of deviations that are that deliberate reliance on the to be generically imposed in the pro
consistent with or superior to the pro transmission provider’s generation forma OATT. The tiered imbalance
forma OATT. resources is inappropriate and could penalties adopted in this Final Rule
671. We do not, however, abrogate adversely affect the reliability of the generally provide a sufficient incentive
existing generator imbalance agreements transmission system, but they are not to engage in such behavior.
between transmission providers and unsure if such an intentional deviation Proposals to assess additional penalties
their customers. These agreements have could be proven. Imperial also expresses for intentional deviations will continue
been negotiated between willing parties, concern that the burden to prove the to be considered on a case-by-case basis,
and the Commission will not re-open intent of the generator will fall on subject to a showing that they are
them generically in this proceeding. To transmission providers and that, in necessary under the circumstances. We
the extent a particular party desires to reality, transmission providers may face note that any such tariff provisions must
amend an existing generator imbalance an uphill battle to prove a generator’s include clearly defined processes for
agreement in light of the reforms we deviation was intended. South Carolina identifying intentional deviations and
adopt in this Final Rule, that party may E&G and Imperial request that the the associated penalties.
Commission provide a specific process
exercise whatever rights it may have c. Calculation of Incremental Cost
for imposing such penalties, including
under the agreement or FPA section NOPR Proposal
what procedures should be followed if
206.
a transmission provider seeks to have 677. With respect to the pricing of
672. With regard to WECC’s the Commission impose such penalties. energy and generation imbalances, the
frequency-response concerns, we agree 675. Several entities oppose penalties Commission stated in the NOPR its
that a generator should be excused from for intentional deviations or suggest belief that charges based on incremental
imbalance penalties that occur due to modifications. Constellation supports an costs or multiples of incremental costs
directed reliability actions by generators would provide the proper incentive to
396 See 2006 Transmission and Ancillary Service
to correct frequency. It would not be keep schedules accurate without being
Rate Schedules, approved in United States Dep’t of
appropriate to assess imbalance charges Energy—Bonneville Power Administration, 112 excessive. The Commission proposed
on generator deviations that are FERC ¶ 62,258 (2005). The Bonneville tariff that incremental cost be defined to
associated with supporting system provides that ‘‘For any hour(s) that an imbalance is include both energy and
determined by [Bonneville] to be an Intentional commitment 398 costs, to the extent
reliability by responding to frequency Deviation: (1) No credit is given when energy taken
deviations as directed by the is less than the scheduled energy, (2) When energy additional commitments are needed.399
transmission provider or general taken exceeds the scheduled energy, the charge is
reliability requirements. As such, if a the greater of: (i) 125% of [Bonneville’s] highest 398 The Commission noted that ‘‘capacity

incremental cost that occurs during that day, or (ii) commitment’’ is generally defined as the generating
response from a generator (particularly 100 mills per kilowatthour.’’ An ‘‘Intentional capacity committed by a utility to provide
in the West) is required to prevent Deviation’’ is defined as ‘‘a deviation that is capability for another utility to attain its reserve
frequency decay and the corresponding persistent during multiple consecutive hours or at level. See, e.g., Central & South West Services, Inc.,
specific times of the day,’’ a ‘‘pattern of under- 48 FERC 61,197 at 61,731 n.9 (1989).
deviations from the generator’s schedule delivery or over-use of energy,’’ or ‘‘persistent over- 399 The Commission proposed defining
sroberts on PROD1PC70 with RULES

would cause additional imbalance generation or under-use during Light Load Hours, incremental cost, based on its decision in
penalties, the transmission provider particularly when the customer does not respond by Consumers, as the transmission provider’s actual
adjusting schedules for future days to correct these average hourly cost of the last 10 MW dispatched
should exempt the generator from those patterns.’’ Id. at 46. to supply the transmission provider’s native load,
penalty charges. 397 E.g., Imperial District Irrigation, Progress based on the replacement cost of fuel, unit heat
Energy and Ameren. rates, start-up costs, incremental operation and

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00086 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12351

The Commission sought comment on used by IPPs, while at the same time 683. Pinnacle and Utah Municipals
how such charges should be calculated, sending the appropriate economic signal request that the Commission allow the
as well as how they would be applied that encourages generators to match use of alternative pricing
to transmission customers. The their generation with their schedules. methodologies, such as market proxy
Commission sought further comment as 680. In its reply comments, EEI argues pricing methodology based on trading
to how additional demand and energy that a transmission provider should be hubs in or adjacent to their respective
costs, if incurred in responding to entitled to recover the cost of additional control areas, where appropriate. Utah
imbalances, such as redispatch, reserves needed to meet the increased Municipals urge the Commission to
commitment, or additional regulation reliability requirements resulting from make clear in the final rule that market-
reserves, should be appropriately the provision of the imbalance energy if based pricing may be acceptable in
reflected in the calculation of imbalance the transmission provider generates some circumstances and to amend
charges and which customers should be additional energy to compensate for a Schedule 4 of the pro forma OATT to
charged for such costs. load that schedules less energy than it ensure that imbalance charges are
takes or a generator that produces less designed not only to provide legitimate
Comments energy than it schedules. EEI further incentives for accurate scheduling, but
678. Several entities argue that contends that transmission providers also to avoid unjustified penalties
incremental pricing for both energy should be permitted to include in their (masquerading as ‘‘incentives’’), to
imbalances and generator imbalances calculation of imbalance charges any minimize the discriminatory impact of
should reflect the full incremental costs other costs associated with committing such charges, and to avoid penalizing
incurred by the transmission provider a unit that is not on-line such as behavior or results that in fact help to
(e.g., such as redispatch costs, capacity minimum run times, losses, etc. keep the system as a whole in balance.
commitment costs or additional 681. Entergy opposes a single price for 684. TDU Systems believe the
regulation reserve costs) resulting from settling over-deliveries and under- Commission should disallow recovery
the imbalance.400 Allegheny questions deliveries. For transmission providers of demand charges or capacity
whether the Consumer’s definition is who choose to base energy and commitment costs in any charges
appropriate because ‘‘the last 10 MW’’ generator imbalance charges on approved for imbalances. TAPS and
requirement is independent of the time incremental and decremental costs, TDU Systems argue that capacity
of the scheduling deviation. Allegheny Entergy requests that the Commission required to follow load is already paid
contends that the definition should be not adopt standardized definitions of for by charges for regulation and
modified such that it specifically incremental cost and decremental cost reserves under Schedules 3, 5 and 6.
addresses the incremental dispatch to in the pro forma OATT. In its reply TDU Systems also support that the
supply the transmission provider’s load comments, Entergy further argues that a Commission continue to apply its
‘‘in the hour in which the imbalance requirement that the transmission existing policy of imposing a heavy
occurs.’’ provider post incremental and burden on transmission providers to
679. Entergy argues that imbalance decremental cost information is unfair justify such demand or capacity
pricing on an hourly basis does not and harmful to the market, placing the commitment charges in the context of a
capture all of the costs and reliability transmission provider at an unfair full base rate case, and of requiring
risk to the transmission provider of competitive disadvantage in the market. transmission providers to develop
over- and under-deliveries. Entergy Duke on reply proposes that System alternative solutions for balancing
states that the real-time regulation Incremental Cost (SIC) be used to price schedules and loads.
burden imposed by IPPs is similar to the both over-deliveries and under- 685. To the extent transmission
real-time regulation burden imposed by deliveries. Duke defines SIC to mean the providers are permitted to include
loads, and loads are charged for this cost incremental expense, measured in commitment costs in negative
through a transmission provider’s dollars per megawatt hour, incurred by imbalance charges, Entegra believes that
Schedule 3 Regulation and Frequency the utility to produce or procure the additional monitoring would be needed,
Response Service. Entergy asserts that next megawatt hour (MWh) of energy, to include posting of hourly imbalance
the NOPR does not propose any after serving all of the utility’s electric charges, even if with a lag of a day or
recovery mechanism for the regulation energy and/or capacity sales. Duke so. Suez Energy NA contends that the
burden imposed by IPPs, recognizing proposes that SIC shall include but not Commission should require a
that Bonneville may not face significant be limited to: The replacement cost of transmission owner to support its
generator regulation costs due to the fuel; incremental operating and incremental cost filing on the basis of
rapid ramping rate and relatively low maintenance costs; emissions allowance Form No. 423 data and actual operations
cost of hydroelectric resources. Entergy replacement costs and other of the selected units, based on
submits that its regional experience has environmental compliance costs; the operational data as reported in utilities
demonstrated that generator regulation cost of starting and operating any Continuous Emission Monitoring
service is a necessity. Entergy states that generating units, (including costs reports.
incurred due to minimum runtimes or 686. EEI argues that since Schedule 3,
its generator regulation service recovers
loading levels); purchase and 5 and 6 charges recover the costs of
charges for the generating capacity that
interchange power costs; and all capacity based on test year data, they
Entergy must maintain on-line in order would not recover the additional costs
applicable taxes or assessments based
to respond to the moment-to-moment of reserves that transmission providers
on the revenues received or quantities
deviations between scheduled output incur to compensate for their customers’
sold.
and actual generation. Entergy explains 682. Allegheny states that the failures to match their schedules and
that the charge compensates Entergy on Commission should clarify that the their loads or generator output, and they
a cost-basis for the generation capacity
sroberts on PROD1PC70 with RULES

definition of incremental cost is equally also do not recover other commitment


applicable to intermittent generator costs such as start-up costs or minimum
maintenance costs, and purchased and interchange
power costs and taxes. imbalance service as well as non- run times. EEI argues that if
400 E.g., Allegheny, Ameren, Indicated New York intermittent generator imbalance transmission providers could not
Transmission Owners, and FirstEnergy. service. recover such costs through imbalance

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00087 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12352 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

charges, they would not be able to reserves for meeting imbalances, the whether they should be pursued under
recover them at all. transmission provider should file a rate FPA section 215 as part of the review of
schedule and demonstrate that these reliability standards.
Commission Determination
charges do not allow for double
687. The Commission concludes that Comments
recovery of such costs. To address
it is appropriate to define incremental Entergy’s concern that the real-time 694. A number of commenters
cost, for purposes of the tiered regulation burden imposed by IPPs is support continuing to allow inadvertent
imbalance provisions adopted above, as similar to the real-time regulation energy to be treated differently from
the transmission provider’s actual burden imposed by loads, we will allow energy and generator imbalances,
average hourly cost of the last 10 MW transmission providers to propose agreeing that these two types of services
dispatched to supply the transmission separate regulation charges for are not comparable.403 Allegheny argues
provider’s native load, based on the generation resources selling out of the that this historical practice makes sense
replacement cost of fuel, unit heat rates, control area and consider such because the variables germane to
start-up costs, incremental operation proposals on a case-by-case basis. We inadvertent interchange are beyond the
and maintenance costs, and purchased believe that the other demand costs of control of individual transmission
and interchange power costs and taxes, providing imbalance service are already providers and, therefore, are best
as applicable. being provided under Schedule 3, 5, addressed in the context of reliability.
688. In deriving such charges, we note and 6 charges. Entergy notes that transmission
that the Commission proposed in 691. In responding to Allegheny’s customers have some flexibility to
paragraph 244 of the NOPR that comments, we clarify that the definition mitigate the deviations between their
incremental cost be defined to include of incremental cost is equally applicable schedules and the operation of their
both additional energy and commitment to intermittent generator imbalance load in real-time, while control area
costs. The Commission also sought service as well as non-intermittent interchange imbalances may involve the
comment on how additional demand generator imbalance service. failure of control areas to match their
and energy costs, such as redispatch, 692. We do not believe it appropriate scheduled inflows and outflows due to
commitment, or additional regulation to require transmission providers to use contingencies occurring even in a third
reserves, would be appropriately market proxy pricing to calculate control area.
recovered if incurred in responding to incremental costs in the pro forma 695. Northwest IOUs argue that there
imbalances. OATT. The feasibility of using market is no reason to think that there is abuse
689. The Commission finds that it is proxies must be considered on a case- of one system leaning on another in
appropriate, through the definition of by-case basis, given the characteristics regards to inadvertent energy,
incremental cost, to allow for recovery of each market. If proposed, the proxy particularly in light of Control
of both commitment and redispatch price must represent a valid alternative Performance Standards 1 and 2 and
costs while excluding the cost recovery to the incremental cost calculation, other protocols for balancing flows
of additional regulation reserve costs. reflecting competitive, transparent and across interconnections. Public Power
Commitment and redispatch costs shall liquid conditions similar to those that Council states that in-kind return of
be accommodated as a part of the hourly would exist in the seller’s market.402 inadvertent energy between Balancing
cost of the last 10 MW dispatch and in Authorities is governed by numerous
the start up cost portion of the d. Inadvertent Energy Treatment agreements and tariffs that are designed
definition. The Commission concludes NOPR Proposal to limit the ability of one system to lean
that excluding additional regulation on another.
693. The Commission proposed in the
costs as a general matter is appropriate 696. Sacramento states that the
NOPR to continue to allow inadvertent
since much of those costs would be Commission expressed concern in other
energy to be treated differently from
demand costs.401 We believe including settings that generators may
energy and generator imbalances,
charges for unit commitment costs (e.g., intentionally undergenerate during
explaining that these two types of
start-up and minimum load costs) and high-cost hours and make it up by
service are not comparable. The
O&M costs is necessary to ensure that overgenerating during low-cost hours
Commission noted that, given the nature
both energy and generation imbalance under a return-in-kind approach.
of inadvertent energy and historical
charges reflect the full incremental costs Sacramento contends that in kind
practices, transmission providers pay
incurred by the transmission provider. means not only a return of energy, but
back inadvertent energy imbalances and
We emphasize, however, that such costs a return of energy at like times and
that the Commission has accepted this
should only be the additional costs conditions and does not believe that this
practice as just and reasonable. The
incurred by the transmission provider results in leaning. In its reply
Commission sought comment on
due to the imbalance. If applicable, comments, Exelon requests that the
whether the current return-in-kind
start-up costs should be allocated pro Commission’s imbalance penalty rules
approach to inadvertent energy
rata to the offending transmission explicitly prohibit the local utility
encourages leaning on the grid in times
customers based on cost causation Balancing Authority operator from
of shortage and, therefore, whether any
principles. relying on inadvertent energy to balance
690. If the transmission provider reforms in this area are appropriate. The
Commission asked whether pricing its affiliated generators’ schedules and
elects to have separate demand charges thus obtaining a competitive advantage.
assigned to customers for the purpose of inadvertent energy at incremental cost
(or some variant thereof) would be an 697. Other commenters disagree that
recovering the cost of holding additional inadvertent energy should continue to
appropriate disincentive and, if any
reforms in this area are appropriate, be treated differently. Exelon expresses
401 To the extent a transmission provider wishes
concern that in regions without
sroberts on PROD1PC70 with RULES

to recover costs of additional regulation reserves


associated with providing imbalance service, it 402 See RockGen Energy, LLC, 100 FERC ¶ 61,261 organized markets there is the potential
must do so via a separate FPA section 205 filing (2002) (setting for hearing, inter alia, whether
demonstrating that these costs were incurred proposed market proxy price is reliable, verifiable, 403 E.g., Entergy, Allegheny, Progress Energy,

correcting or accommodating a particular entity’s and also indicative of the prevailing price in liquid Public Power Council, South Carolina E&G, PGP,
imbalances. non-redispatch markets in the region). and Ameren.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00088 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12353

for local utility balancing authority incremental cost. FirstEnergy believes e. Netting/Crediting of Energy and
operators to seek to avoid paying that the Commission should establish a Generator Imbalances
deviation charges by favoring their own tiered penalty structure that, similar to NOPR Proposal
generators over merchant generators or the Bonneville method discussed by the
by using inadvertent energy to balance Commission, levies penalties based on 704. In the NOPR, the Commission
their schedule. Exelon argues that a the severity of the inadvertent energy sought comment on whether or not it is
balancing authority operator could violation. TDU Systems state that appropriate to allow a transmission
maintain system balance by choosing to currently there are no penalties for customer to net energy and generator
order its affiliated generators to deviate under-supply even when one control imbalances for a particular transaction
from the schedule and thereby allow its area could be deemed to be within a single control area to the extent
affiliated generator to avoid deviation they offset.404 The Commission asked
intentionally ‘‘leaning’’ on the grid to
charges that the merchant generator whether the potential to allow netting
arbitrage energy market prices; but there
could not avoid. If the local utility for offsetting imbalances contradicts the
should be.
balancing authority operator relies on principle of encouraging good
inadvertent energy to balance its 701. FirstEnergy argues that a scheduling practices. The Commission
affiliated generators’ schedules, Exelon nationwide process should be sought further comment on what would
contends it is using an option that is established by the Commission to be a reasonable percentage to net
unavailable to other generation eliminate regional differences in the without concerns that allowing such
resources and obtains a competitive treatment of inadvertent energy. netting would lead to reliability
advantage. Constellation asks the Commission to concerns from using unscheduled
698. TDU Systems argue that energy require that transmission providers transmission or would cause redispatch
imbalances and inadvertent interchange specifically separate imbalances from costs by the transmission provider.
may occur for many of the same reasons, inadvertent energy and closely track and 705. The Commission also proposed
e.g., telemetry failure, meter error, report the two. to add provisions to schedule 4—Energy
generator governor response to system Imbalance Service and schedule 9—
problems, human error, and under- or Commission Determination Generator Imbalance Service of the pro
over-supply of generation. TDU Systems 702. As stated in the NOPR, the forma OATT to reflect the Commission’s
state that deviations between load and policy that a transmission provider may
Commission finds that inadvertent
supply, whether in the form of energy only charge a transmission customer for
energy is not comparable to energy and
imbalances or inadvertent interchange, either hourly generator imbalances or
generation imbalances and, therefore,
require adjustment or compensation, but hourly energy imbalances for the same
there is no reason why the form of that we will continue to allow inadvertent
energy to be treated differently from imbalance, but not both.405 The
adjustment or compensation should be Commission explained that this policy
different among transmission users. energy and generation imbalances.
Inadvertent energy represents the only applies to a transmission customer
TDU systems explain that NERC’s Final that otherwise would be charged for
Report of the Control Area Criteria Task difference between a control area’s net
both generator imbalances and energy
Force describes inadvertent interchange actual interchange and the net
imbalances for the same imbalance
as one of the ‘‘strong incentives’’ driving scheduled interchange. It is caused by
occurring within the same control area.
the newer market participants, such as the combined effects of all the
independent generators, to become generation and loads in the control area Comments
control areas, and driving existing and generation and loads outside of the 706. A number of entities believe that
control area operators to retain their control area. Variables affecting transmission customers should be
functions. inadvertent interchange often depend permitted to net energy and generator
699. TDU Systems explain that as the on the actions or the omissions of imbalances to the extent that such
Commission acknowledged in Order No. utilities other than the individual imbalances offset.406 Ameren and
2000, for transmission providers in RTO transmission providers and are distinct FirstEnergy assert that netting better
regions, unequal access to balancing from those resulting in energy and reflects the impact of imbalances.
options can lead to unequal access in generation imbalances. Morgan Stanley argues that allowing
the quality of transmission service. TDU 703. We also note that management of such netting provides a clear
Systems oppose deferring consideration competitive benefit because it would
inadvertent energy is needed to adhere
of inadvertent interchange issues until allow competitive suppliers to offer a
to NAESB standards. Historically,
the Commission’s order in the load following service in competition
transmission providers have paid back
Mandatory Reliability Standards with the transmission provider.
rulemaking proceeding in Docket No. inadvertent interchange imbalances in
kind, which has not, as a general matter, Sacramento agrees that netting of
RM06–16–000. TDU Systems argue that offsetting imbalances should be allowed
the Commission should place energy proven to be problematic. Our primary
imbalance service on a footing as nearly concern with respect to inadvertent
404 For example, the Commission noted that a
comparable to inadvertent interchange energy is to avoid incentives that could
transmission customer scheduling 100 MWh over
as feasible by allowing like-kind degrade reliability. To date, the return- an hour, but with a load of 120 MWh, would face
exchanges of energy, at the incremental in-kind approach has proven to be an imbalance of 20 MW. The Commission
cost of their own supply portfolio, to adequate as a general matter. However, questioned whether there should be a net charge if
if there is evidence that it is no longer the customer also dispatched its generation to the
remedy imbalances in lieu of the same 120 MWh. Similarly, what if a transmission
present paradigm of punitive charges. sufficient to maintain reliability, or is customer schedules 100 MWh, but has a load of 80
700. TDU Systems also argue that the allowing certain entities to lean on the MWh and dispatches its generation to 80 MWh?
sroberts on PROD1PC70 with RULES

Commission should require grid to the detriment of other entities, 405 Imbalance Provisions Proceeding at 32,123

comparability between transmission the Commission has authority under note 19 (citing Niagara Mohawk, 86 FERC ¶ 61,009
at 61,028).
providers and transmission customers FPA section 215 to direct the ERO to 406 E.g., Ameren, FirstEnergy, Xcel, Suez Energy
by imposing charges for inadvertent develop a new or modified standard to NA, Morgan Stanley, Sacramento, TDU Systems,
interchange at the suppliers’ address the matter. and Utah Municipals.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00089 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12354 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

provided the transmission customer a single control area to the extent they associated with reliability issues and
relies on reasonable load forecasts. offset, with no requirement that the additional redispatch cost. During
707. Utah Municipals and Steel imbalances be part of a single periods when transmission constraints
Manufacturers Association argue that ‘‘transaction.’’ exist, Entergy contends that it may in
the Commission should impose charges 710. Other commenters, however, fact be ramping up some generators to
based on netted imbalances, both for contend that transmission customers respond to imbalances while ramping
each customer and across the system as should not be permitted to net energy down other generation to respond to
a whole. PGP contends that there is no and generator imbalances.407 For other imbalances at exactly the same
reason to charge for both imbalances if example, Entergy and Pinnacle believe time and, therefore, it is incorrect to
a generator overruns during the same that to permit netting of energy and assume that over-generation supplied by
hour when a load overruns, so long as generator imbalances is to undercut the one IPP accompanied by under-
the overruns cancel out within a given very purpose of the imbalance generation from another IPP, even
control area. Steel Manufacturers provisions, which is to provide simultaneously, will have no
Association contends that the adequate incentives to schedule operational effect or impose no costs on
Commission should incorporate control correctly and in accordance with good a transmission provider.
area-wide netting of imbalances to utility practice. Pinnacle asserts that, 713. Allegheny believes that allowing
ensure that penalties are only assessed depending upon the location, energy or netting of hourly deviations inside the
on significant imbalances and energy generator imbalances could create first deviation band on a monthly basis
imbalance charges do not become a reliability or economic problems for would not allow for full recovery of
windfall profit center for utilities. Utah specific areas of the system and it is imbalance costs because balances that
Municipals suggest that the Commission important that the transmission operator occur in on-peak periods cost more than
provide that all imbalances be netted for know what is happening on its system imbalances that occur during off-peak
each hour and that penalties (charges and for the customer to adhere to periods. Allegheny contends that
above or credits below actual costs) be accurate scheduling. SPP argues that deviations within the first band should
imposed only when the system as a allowing netting of imbalance energy be measured and settled financially on
whole is out of balance by more than a between generation and load would an hourly or, at least, an on-peak/off-
de minimis amount and, even then, only allow price arbitrage that would be peak basis, rather than allowing
on those customers whose imbalances unjust and unreasonable. Indicated New deviations during one part of the month
fall in the same direction as the system York Transmission Owners assert that to be offset by deviations in another part
imbalance. Utah Municipals note that positive and negative imbalances do not of the month. Indianapolis Power &
Sierra Pacific has established a similar actually offset, as the NOPR would Light Company argues that the
imbalance mechanism, which appears suggest, but rather each imbalance imbalance volume could be within the
to be working well in its control area. independently places stress on the allowed bandwidth tolerance, but still
708. TDU Systems argue that the transmission system. Duke states on be significant enough to allow for the
netting rules should be sufficiently reply that, although several commenters energy market participant to make
flexible to allow individual customers to support netting imbalances, not one money off of the price difference.
net their transactions within an hour, a entity supporting such netting has put 714. Entergy also contends that a
day, a week or a month, so long as the forth a workable proposal for how to crediting mechanism for generator
results keep the transmission provider implement such netting where multiple imbalances would be not appropriate.
economically whole. TDU Systems state generators are serving multiple loads. Entergy asserts that such a credit would
that the Commission should not impose 711. Entergy believes that result in indifference by generators by
a cap on the quantity of netting allowed independent generators must take full largely immunizing them from the costs
unless the transmission provider is able responsibility for meeting their own resulting from their imbalances and, as
to demonstrate that good system schedules, including making a consequence, produce economic
performance requires such a cap. adjustments to their schedules to inefficiencies and a potential threat to
Ameren suggests that the Commission conform them to their operation in real- system reliability. Entergy argues that
use a tiered system for determining time. Entergy argues that a netting the current method, which provides an
when imbalances can be netted, but approach, however, would provide an incentive to generators to control their
argues that a transmission customer incentive for a generator to over- own imbalances, is appropriate because
should not be allowed to net offsetting generate above its schedule if its load generators have a desire to accurately
imbalances elsewhere on the system if proves to be greater than expected in schedule to avoid imbalances. Entergy
the imbalance has the potential to have real-time. Entergy argues that allowing argues that a non-offending generator in
a significant reliability impact. the netting of these imbalances will one hour can be an offending generator
709. FirstEnergy and Utah Municipals result in the virtual elimination of in the next hour and that the credit will
contend that both point-to-point and transmission schedules. bankroll generators so that penalty
network transactions should be eligible 712. In instances in which payments in one hour will be offset and
for netting. Utah Municipals and transmission customers intentionally paid for by penalty receipts in another
NRECA in their reply comments note game the transmission system through hour.
that the Commission’s reference to ‘‘a netting, FirstEnergy contends that the
particular transaction’’ does not mesh Commission Determination
transmission provider should have the
with the needs and practices of network ability to apply punitive measures 715. The Commission recognizes that
customers, who do not attempt to match through a Commission-mandated there is a trade off between the
portions of their total hourly loads with penalty process. FirstEnergy states that competitive benefits of reducing
particular resources or ‘‘transactions.’’ there appears to be no clear cut number imbalance charges, including allowing
sroberts on PROD1PC70 with RULES

Utah Municipals argue that the which defines the boundary between transmission customers to net energy
Commission’s proposal should be ‘‘good’’ netting and ‘‘bad’’ netting and generation imbalances, and the
modified to make clear that such reliability implications of the
customers should be permitted to net 407 E.g., Entergy, Pinnacle, Indianapolis Power, transmission provider needing to plan
energy and generator imbalances within and Indicated New York Transmission Owners. to accommodate such imbalances.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00090 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12355

Allowing transmission customers to net Comments the proposed tiered charges for
imbalances would further comparability 718. Several commenters argue that imbalances, would provide better, more
between the transmission provider’s the Final Rule should address within- refined incentives for generators to more
dispatch and the transmission hour deviations that occur when closely match their scheduled deliveries
customers serving load. However, generator imbalances are calculated on and would help balancing authorities
netting and crediting could lessen the an integrated hour basis.408 If the reduce Area Control Error excursions.
incentive for accurate scheduling and generator imbalance is measured over TVA suggests generator imbalances be
resulting energy or generator imbalances an integrated hour, as is typical of the measured on ten-minute intervals rather
could create reliability or economic current practice, TVA asserts that than integrated over an hour. These ten-
issues for specific areas of the system if significant intra-hour swings may be minute imbalances would not be netted
the transmission provider cannot masked. against other imbalance intervals, so as
adequately plan for such imbalances. 719. South Carolina E&G states that to avoid the problem of encouraging
generators, unable to ramp precisely to undergeneration followed by
716. In weighing these tradeoffs, the
the 15-minute schedules, often overgeneration and vice versa. In
Commission concludes that for both addition to having generator imbalance
energy and generator imbalance services undergenerate in the initial part of the
hour, then overgenerate in later parts of charges for generation outside the
it is not appropriate to require operating bands, TVA argues that there
transmission providers to allow netting the hour, in order to integrate closer to
the schedule when settled over the should be a separate charge assessed
of imbalances outside of the tier one based on the peak generator imbalance
band. We agree that netting can cause entire hour. South Carolina E&G
contends these intentional swings between the scheduled and actual
problems because netting would lessen generation recorded instantaneously
the incentive for transmission customers burden the balancing authorities who
are charged with continuously keeping during the clock hour to provide a
to schedule accurately, and inaccurate further incentive for proper generator
schedules, in turn, could require actions Area Control Error within predefined
limits. International Transmission scheduling.
by the transmission provider even when 721. Pinnacle and Utah Municipals
the imbalances offset. Where argues that intentional swings in output
can be quite severe, imposing assert that a transmission provider
transmission constraints exist, a should only charge hourly generator
transmission customer whose load and operational strains on the system,
negatively impacting the control area’s imbalances or hourly energy imbalances
generation was on net equal could still for the same imbalance. PGP argues that
ability to meet NERC Control
have an effect on the transmission customers should pay only one charge
Performance Standards, and potentially
system if, as Entergy contends, some for the net imbalance that occurs within
jeopardizing reliability.409 Entergy
generation is ramping up to respond to a single control area, either energy or
agrees that settling hourly energy
some imbalances while other generation generation, unless congestion occurs
imbalances with generators does not
is ramping down at exactly the same inside a control area that requires
provide adequate incentives for
time. Similarly, where transmission generators to schedule and dispatch redispatch.
constraints exist, if one IPP has a accurately within the hour. Entergy Commission Determination
positive deviation from its schedule asserts that generators have imposed
while another IPP has a corresponding 722. The Commission concludes that
significant moment to moment swings
negative deviation from its schedule, the it is appropriate to maintain the status
within the hour requiring it to deploy its
transmission provider could need to quo of aggregating net generation over
regulating reserves in response. Entergy
ramp up generation in one area while the hour in the pro forma OATT.
states that it has been increasingly
simultaneously ramping down Requests by transmission providers to
difficult to meet NERC’s operating
generation in another area. Further, we adopt a shorter interval will continue to
criteria for control area performance
believe that flexible scheduling be considered on a case-by-case basis.410
without committing, and incurring the
deadlines should allow transmission The Commission acknowledges that
costs for, additional regulating reserves.
customers to change their schedules shorter intervals may be appropriate in
TVA contends that all generators should
such that their loads can be accurately particular circumstances and, for this
be required to ensure that the
met and implementation of the tiered reason, declined to use a clock-hour
instantaneous generation level equals
imbalance bands will ensure that interval in the Large Generator
the scheduled output. International
charges corresponding to imbalances are Interconnection Final Rule.411 There,
Transmission asks that the imbalance
just and reasonable. the Commission permitted use of an
provisions in the Final Rule address this
interval ‘‘consistent with the scheduling
situation by either specifying penalties
f. Intra Hour Netting requirements of the Transmission
that may be assessed for within-hour
NOPR Proposal Provider’s Commission-approved Tariff
variations or advising that transmission
and any applicable Commission-
providers may implement their own
717. Under the current pro forma approved market structure.’’ 412
penalties to the extent that within-hour
OATT, energy imbalances occur when Allowing transmission providers to
variations cause operational difficulties.
there is a difference between the continue to propose alternative intervals
720. South Carolina E&G contends
scheduled and the actual delivery of for purposes of the pro forma OATT
that allowing generator imbalance
energy to a load located within a control imbalance provisions is therefore
settlements over a shorter period, such
area aggregated over a single hour. As a appropriate provided that such
as at 15-minute intervals, together with
result, if a transmission customer is proposals are consistent with relevant
under its scheduled level for the first 408 E.g., TVA, South Carolina E&G, and market structures.
sroberts on PROD1PC70 with RULES

half of a given hour, but over its International Transmission.


409 International Transmission provides the 410 See Entergy Services, Inc., 102 FERC ¶ 61,014
schedule the second half of the hour, (2003) and Entergy Services, Inc., 111 FERC
example that a large generator with scheduled
there would be no imbalance charge. output of 100 MW for an hour might stay at zero ¶ 61,314 (2005).
The Commission did not address intra for the first 50 minutes of the hour and then 411 See Order No. 2003 at P 335.

hour netting in the NOPR. generate 600 MW during the last ten minutes. 412 See pro forma LGIA Article 4.3.1

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00091 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12356 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

g. Distribution of Penalty Revenues Commission Determination minimize any incentive on the part of
Above Incremental Cost 727. In this Final Rule, the the transmission provider to rely on
NOPR Proposal Commission has reformed existing penalty revenues rather than seeking
imbalance provisions to reduce the other methods of encouraging accurate
723. The Commission also sought scheduling. Under these circumstances,
comment in the NOPR regarding the variety of different methodologies used
for determining imbalance charges and there remains no reason to exclude the
treatment of revenues the transmission transmission provider from receiving an
provider receives above the cost of ensure that the level of the charges
provide appropriate incentives to keep appropriate share of penalty revenues.
providing the imbalance service.
schedules accurate without being 3. Credits for Network Customers
Comments excessive. We also believe that 729. In Order No. 888, the
724. Various commenters state that transmission providers should have a Commission established that network
the transmission provider should retain consistent method of treating revenues customers should be eligible for credits
any amounts above the incremental cost received through imbalance penalties or for customer-owned transmission
of providing imbalance service. Ameren charges that are in excess of incremental facilities under certain circumstances.
and Constellation argue such revenues cost. The Commission has previously Specifically, section 30.9 of the pro
should serve as a contribution towards required transmission providers with forma OATT states that a network
the fixed costs of providing this service. significant imbalance penalties to customer owning existing transmission
Entergy argues that premium charges develop a mechanism to credit penalty facilities that are integrated with the
would compensate it for the revenues to non-offending transmission transmission provider’s transmission
administrative costs of maintaining an customers.413 This was intended to system may be eligible to receive cost
organization capable of providing this remove the incentive of the credits against its transmission service
purchase and sales function and provide transmission provider to hinder the charges if the network customer can
generators with an incentive to avoid development of other imbalance demonstrate that its transmission
mismatches between scheduled services that do not rely on penalties.414 facilities are integrated into the plans or
quantities and actual deliveries to We believe it is appropriate to maintain operations of the transmission provider
Entergy. Entergy states that the the requirement that transmission to serve its power and transmission
Commission has previously recognized providers credit revenues in excess of customers. Section 30.9 also states that
that these generator imbalance charges incremental costs. Therefore, as part of new facilities are eligible for credits
are analogous to the economy power their compliance filings in this when the facilities are jointly planned
rates that have historically included a proceeding, transmission providers are and installed in coordination with the
percentage adder for out-of-pocket costs required to develop a mechanism for transmission provider.
to recover difficult-to-quantify costs. crediting such revenues to all non-
725. On the other hand, FirstEnergy offending transmission customers NOPR Proposal
states that the additional revenue (including affiliated transmission 730. In the NOPR, the Commission
derived from charges above incremental customers) and the transmission proposed severing the link in the pro
costs should be provided to generators provider on behalf of its own customers. forma OATT between joint planning
and/or customers able to regulate load Such a distribution of penalty revenues and credits for new facilities owned by
that provided the redispatch, recognizes that transmission providers network customers because such linkage
commitment, or additional regulation bear the responsibility to correct can act as a disincentive to coordinated
reserves. Utah Municipals contend that imbalances and often use their own planning. The Commission proposed
the Commission should credit revenues facilities to do so. deleting from section 30.9 the language
from charges above incremental costs to 728. We acknowledge that in the that permits transmission providers to
accurately-scheduling customers, rather CP&L decision, the Commission refuse crediting for new network
than to the transmission provider. Utah declined to allow the transmission customer-owned facilities that are not
Municipals argue that the penalty provider to allocate a share of imbalance part of its planning process, and adding
portion of incremental and decremental penalty revenues to itself as a user of the language that puts a greater emphasis on
charges and rates could be credited back transmission system on behalf retail comparability. Specifically, the
to all transmission customers who incur customers. Given the reforms to the pro Commission proposed that the network
imbalance charges and whose schedules forma OATT imbalance provisions customer shall receive credit for
fell within the first deviation band for adopted in this Final Rule, we believe transmission facilities added subsequent
that hour. Progress Energy suggests that the circumstances presented in that case to the effective date of the Final Rule in
all imbalance revenues above the cost of are no longer applicable. There, the this proceeding provided that such
providing the imbalance should be Commission based its holding on its facilities are integrated into the
distributed to all non-offending understanding that the high imbalance operations of the transmission
transmission customers, based on the penalties imposed by the transmission provider’s facilities and if the
weighted amount of each non-offending provider were an interim measure that transmission facilities were owned by
transmission customer’s usage of the were intended to be in place only until the transmission provider, they would
transmission provider’s transmission an imbalance market was developed.415 be eligible for inclusion in the
system. TAPS and TDU Systems ask on In this Final Rule, we are adopting transmission provider’s annual
reply that penalty revenues not be imbalance charges that are closely transmission revenue requirement as
earmarked for retail customers. related to incremental cost and therefore specified in Attachment H of the pro
726. Morgan Stanley believes that forma OATT.
imbalance charges should be ‘‘keep 413 See Carolina Power & Light Co., 103 FERC 731. In the NOPR, the Commission
sroberts on PROD1PC70 with RULES

whole’’ charges calculated and designed ¶ 61,209 at P 25 (2003) (CP&L); Entergy Svcs., 105 also declined to allow transmission
FERC ¶ 61,319, reh’g denied, 109 FERC ¶ 61,095 at
to reimburse whoever remedied P 65–66 (2004).
providers as part of this proceeding to
whatever problem the imbalance caused 414 See Carolina Power & Light Co., 97 FERC automatically add costs of credits to the
while leaving the transmission provider ¶ 61,048 at 61,279 (2001). transmission provider’s cost of service.
financially indifferent. 415 Id. However, the Commission stated that a

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00092 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12357

transmission provider may propose to non-productive disputation over Some argue that the test for network
add an automatic adjustment clause to whether joint planning did or should customer credits should continue to be
its rates in a filing submitted under have taken place. whether the network customer’s
section 205 of the FPA. The 734. PGP points out, however, that facilities provide capability and
Commission also explained that it credits for new facilities can only result reliability benefits to the grid—the same
would not propose to make credits from joint planning, because new standard that would apply to inclusion
generically available to point-to-point facilities must be interconnected with of the facilities in the transmission
customers that own transmission the existing grid, and planning studies provider’s cost of service if the
facilities, but clarified that if some are necessary for that to happen. transmission provider constructed the
facilities owned by a point-to-point NorthWestern requests that the facilities.419 MidAmerican states that
customer meet all the criteria for credits, Commission reconsider its proposal to further clarification of this point in the
consistent with the Commission’s allow crediting of customer-owned Final Rule would be beneficial in
statement in Order No. 888, the facilities that have not been jointly minimizing disputes over this issue.
Commission would address such planned with the transmission provider. Likewise, MidAmerican asks the
situations on a fact-specific, case-by- NorthWestern contends that allowing Commission to clarify in the Final Rule
case basis.416 the construction of network facilities that such credit can be applied only to
and making a judgment after the fact is network customers taking OATT service
a. Severance of Credits and Planning
inefficient and will result in protracted and not to transmission customers that
Comments litigation and facilities that do not serve are under non-OATT (i.e., grandfathered
732. The NOPR proposal to sever the the overall grid as efficiently as planned bundled agreements) contracts. PGP
link between transmission credits and facilities. PNM–TNMP contends that the supports the new rules for granting
joint planning by eliminating the joint- Commission’s proposed action to ‘‘sever credits to network customers, but argues
planning requirement for credits for the link’’ will excuse the network implementation details should be left
new facilities constructed by network customer from the coordinated planning up to individual transmission providers.
customers is supported by a cross- process and can only operate at cross- 738. Although several transmission
section of the industry.417 Exelon asserts purposes with the coordinated providers support the continued use of
that linking credits to network transmission planning goal that is the integration test,420 other
customers with coordinated planning addressed in the planning sections of commenters representing municipal and
simply creates an incentive for the the NOPR. public power interests ask that the
transmission provider to avoid Commission reconsider or clarify its
Commission Determination
coordinated planning with the network application.421 Some commenters argue
customers so that the provider can avoid 735. The Commission adopts the that given the Commission’s current
providing credits. In addition, the NOPR proposal to sever the link in the interpretation of ‘‘integration’’ for
criterion of ‘‘jointly planned’’ with the pro forma OATT between joint planning transmission credit purposes and the
transmission provider provides little or and credits for new facilities owned by historical application of the test,
no value for discerning what facilities network customers. The proposal retaining any integration requirement
should qualify for crediting treatment. received broad industry support, and we for existing or new facilities conflicts
Further, Exelon argues, tying credits to agree with these commenters that the with comparability or constitutes undue
joint planning is no longer necessary link between credits for new facilities discrimination.422 TDU Systems argue
because the Commission’s regional and the requirement for joint planning that the integration standard has
planning initiatives will insure that can act as a disincentive to coordinated encouraged discriminatory behavior by
most, if not all, newly constructed planning, which is contrary to the allowing transmission providers to
facilities will be jointly planned. While Commission’s original objective in charge network customers for
EEI disagrees that the joint planning adopting the provision. A transmission transmission provider facilities
provision has acted as a disincentive to provider has an incentive to deny constructed to serve the transmission
joint planning, it agrees that the coordinated planning in order to avoid provider’s native load, while refusing to
coordinated planning initiatives in the granting credits for customer-owned pay the network customer for
NOPR has made the link unnecessary. transmission facilities. comparable customer-owned
733. FMPA also argues that the link 736. We find that arguments against transmission facilities. TDU Systems
between credits and planning the proposal are largely theoretical and further argue that the integration test
discourages joint planning because do not adequately take into account the has resulted in a form of ‘‘and’’ pricing
companies can avoid transmission rate coordinated planning provisions since the TDU Systems, as network
credits, often for competitors, by simply proposed in the NOPR. The coordinated transmission service customers, remain
refusing to jointly plan. FMPA asserts planning initiatives that the obligated to pay their load ratio share of
that it makes no sense to create Commission is adopting in the Final the full transmission revenue
economic disincentives to joint Rule will ensure that most, if not all, requirement of the transmission
planning. According to these transmission facilities are planned on a provider’s system, including the cost of
commenters, transmission lines cannot coordinated basis, making it transmission facilities built to serve the
be built without some exchange of unnecessary to retain this provision of transmission provider’s own loads.
information; the joint planning link may section 30.9. 739. NRECA questions the
discourage the most productive b. The New Test to Determine Eligibility Commission’s statement in the NOPR
exchange and can create needless and for Credits that, in order to satisfy the integration
737. Comments support the test for
sroberts on PROD1PC70 with RULES

416 Order No. 888 at 31,742; Order No. 888–A at 419 E.g., Allegheny, Ameren, and MidAmerican.
30,271. new facilities proposed in the NOPR.418 420 E.g., EEI, MidAmerican, and Nevada
417 E.g., Allegheny, East Texas Cooperatives, Companies.
421 E.g., FMPA, NRECA, and TAPS.
ELCON, Exelon, FMPA, MDEA, MidAmerican, 418 E.g., Allegheny, EEI, Exelon, MISO, Nevada

MISO, Suez Energy NA, Tacoma, TAPS, and Utah Companies, South Carolina E&G, Suez Energy NA, 422 E.g., East Texas Cooperatives, NRECA, TAPS,

Municipals. and Tacoma. and TDU Systems.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00093 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12358 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

standard, a customer ‘‘must demonstrate must equally include operations that detailed inventory of the existing
that its facilities not only are integrated serve transmission providers, customers facilities owned by transmission
with the transmission provider’s system, or others. provider and network transmission
but also provide additional benefits to 742. Comments on the comparability customers that are included in their
the transmission grid in terms of component of the proposed credits test annual transmission revenue
capability and reliability and can be for new facilities range from several requirement. Network transmission
relied on by the transmission provider requesting that the Commission adopt a customers could use the inventory,
for the coordinated operation of the comparability-driven analysis 428 to one which would be updated annually, to
grid.’’ 423 According to NRECA, that asking the Commission to eliminate the assess whether they currently own
statement identifies three nominal comparability component in favor of an transmission facilities comparable to
requirements for customer facilities— integration-only analysis.429 those included in the transmission
integration, benefits and ‘‘relied 743. Some commenters argue that provider’s transmission rate base, or to
upon’’—as compared to the one nominal eligibility for credits should turn in the third-party transmission facilities for
requirement for transmission provider first instance on the comparability which credits are being provided.
facilities—integration. This is standard set forth in the NOPR, 746. MDEA argues that proposed
fundamentally inconsistent with otherwise the proposal does not section 30.9 appears contrary to
comparability, NRECA continues, as the eliminate undue discrimination.430 comparability principles by imposing a
Commission seems to recognize in its NRECA argues that this requirement standard for transmission facilities
rationale for adding the comparability does not abandon integration because owned by customers that is more
requirement to new facilities. current Commission policy requires a stringent than the one applied to the
740. NRECA further argues that the Transmission Provider’s facilities to be transmission provider’s own facilities.
NOPR failed to distinguish the proposed integrated for their cost to be rolled in In MDEA’s view, the NOPR proposal is
new standard in revised section 30.9 to the transmission provider’s annual inconsistent with prior Commission
from the Commission’s recent decision transmission revenue requirement.431 precedent to the extent comparability is
in North East Texas Electric APPA would apply an integration test not required in evaluating eligibility of
Cooperative, Inc.,424 which found only if the transmission facilities for existing facilities owned by
transmission provider facilities which the customer seeks credits are transmission providers for cost
integrated on the grounds that a found not to be eligible under this recovery.432
showing of any degree of integration is comparability standard. 747. TDU Systems ask that the
sufficient, rejected a ‘‘benefits’’ 744. TAPS states that, by eliminating Commission clarify that the
requirement, and did not consider a the integration test and simply comparability prong will be aggressively
‘‘relied upon’’ requirement. East Texas providing that customer-owned enforced. For example, TDU Systems
Cooperatives argues that the facilities would be eligible for credits to request that the Commission consider a
Commission’s decision in East Texas the extent they would be included in bright-line voltage criterion to address
Electric Cooperative, Inc. v. Central and the transmission provider’s rate base if comparability, rather than leaving it to
South West Services, Inc.,425 applied an they were owned by the transmission the transmission provider’s discretion as
integration requirement for customer provider (i.e.comparability test), the to whether the facilities would be
facility credits that was different and Commission would avoid litigation over eligible for inclusion in the transmission
stricter than the standard applied to a what (if anything) the separate provider’s annual transmission revenue
transmission provider’s facilities. ‘‘integration’’ requirement adds in the requirement.
741. Regarding the application of the proposed formulation. If the integration 748. Arguing against the use of the
integration component, FMPA argues terminology is retained in section 30.9, comparability component, Entergy
that, in order to avoid continued TAPS argues that the Commission at contends that it could cause significant
discrimination, it is important that the least should clarify that the new confusion, and should in no way change
Commission reaffirm that ‘‘additional integration test is truly different from the basic requirements needed to show
benefits to the transmission grid in the old integration test and cannot integration of network customer
terms of capability, delivery options, properly be read as limiting the facilities. According to Entergy, a
and reliability’’ 426 are benefits, comparability requirement and that the network customer should be entitled to
regardless whether the transmission Commission will not follow precedents credits only when the transmission
customers or the transmission provider developed in credits cases decided provider cannot meet the transmission
(or others) benefit. Similarly, FMPA under the original section 30.9. provider’s firm obligations without the
continues, the requirement that facilities 745. To provide a comparability customer’s transmission facilities.
must ‘‘be relied upon for the baseline and eliminate the need for an 749. On reply, MDEA states that the
coordinated operation of the grid’’ 427 integration test, APPA recommends that principle of comparability requires that
transmission providers provide a there be no distinction based on
423 NRECA further notes that proposed OATT
ownership or between existing and new
section 30.9 does not include these additional 428 E.g., APPA, FMPA, and NRECA. facilities. It further asserts that Entergy
‘‘benefits’’ and ‘‘relied upon’’ requirements. NRECA 429 Entergy.
argues that these requirements cannot be part of the attempts to draw a distinction between
430 E.g., APPA, East Texas Cooperatives, FMPA,
section 30.9, since regulatory preambles cannot and NRECA.
customer-owned transmission facilities
vary the words of the rule, citing Wyoming Outdoor 431 NRECA compares North East Texas Electric needed by the transmission provider to
Council v. U.S. Forest Service, 165 F.3d 43, 53 (D.C. meet the transmission provider’s
Cooperative, Inc., 108 FERC ¶ 61,084 (2004), reh’g
Cir. 1999) (‘‘[L]anguage in the preamble of a
regulation is not controlling over the language of
denied, 111 FERC ¶ 61,189 (2005) (finding obligations to native load and firm
transmission provider facilities integrated and transmission customers (for which
the regulation itself’’).
rolling in their cost over transmission provider
credits should be available) and
sroberts on PROD1PC70 with RULES

424 108 FERC ¶ 61,084 (2004), reh’g denied, 111


objection) with Mansfield Municipal Electric
FERC ¶ 61,189 (2005). Department v. New England Power Co., 97 FERC
425 114 FERC ¶ 61,027 at P 42 (2006), appeal
¶ 61,134 (2001), reh’g denied, 98 FERC ¶ 61,115 432 MDEA cites Florida Power and Light Co., 116
docketed, No. 06–1090 (D.C. Cir. Mar. 10, 2006). (2002) (finding transmission provider facilities not FERC ¶ 61,013 (2006), and notes that the
426 NOPR at P 256.
integrated and rolling out their cost over Commission applied principles of comparability to
427 Id. transmission provider objection). a transmission provider’s existing facilities.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00094 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12359

facilities that a network customer transmission service elsewhere on the facilities.436 Because joint planning will
decides that it needs to meet its transmission provider’s system. By no longer be required in order to obtain
obligations. Entergy argues that credits allowing the development of a more credits, we find that it is particularly
should be available only for the former liquid market for such credits, Entegra important in this context to require a
type of facility. According to MDEA, reasons, the Commission could increase showing that a network customer’s
there is no justification for the the willingness of market participants to facilities provide benefits to the
distinction Entergy seeks to draw or the fund upgrades to the transmission transmission provider’s grid, i.e., a
standard it proposes to apply. Network system. transmission customer should not be
customers pay a full load ratio share of 752. TDU Systems request that the eligible for credits for facilities that the
the embedded costs of the transmission Commission recognize that inequities network customer may use to provide
grid, based on the premise that the have occurred and, if any upgrades are service for itself but that the
entire grid is available and required to required to make network customers’ transmission provider does not need to
support network loads. In this regard, facilities comparable (or comparably use to provide transmission service to
there is no difference between Entergy’s integrated), the costs of such network any other customer. However, to ensure
native load and network customer loads. upgrades should be rolled into the comparability, a presumption of
Transmission facilities required to meet transmission providers’ rates. integration will be afforded to
network customer needs by definition transmission customer facilities if it is
are required to meet grid needs, Commission Determination shown that, if owned by the
provided that such facilities are transmission provider, such facilities
integrated with the transmission 753. The Commission declines to
adopt the credits test for new facilities would be eligible for inclusion in the
network. transmission provider’s rate base.
750. Several commenters ask the proposed in the NOPR. The intent
Commission to consider crediting underlying that proposal was to prevent c. Application of the New Test to
mechanisms other than the NOPR application of the integration test in a Existing Facilities
proposal.433 For example, Entergy and manner that exclusively benefits the
Exelon contend that new facilities transmission provider.434 After Comments
should be eligible for credit only if reviewing the comments, we conclude
755. Several commenters object to the
determined through the regional that the proposed test may not in fact
Commission’s proposal to apply the
planning process that such new accomplish this objective. The test
new comparability test in section 30.9 to
facilities are needed, i.e., that a proposed in the NOPR may not
new facilities, and not to existing
measurable system capability or effectively set forth the relationship of
facilities.437 If the Commission requires
reliability benefit is provided. In their the integration standard to the
the same integration standard for both
view, this will avoid litigation of cases comparability requirement. We
existing and new facilities, East Texas
addressing questions of integration. therefore revise the test as follows, to
Cooperatives ask us to specify which
Utah Municipals argue that the more accurately reflect the
integration standard—the pre-existing
Commission should not discount the Commission’s intent as expressed in the
integration standard, or the new
potential evidentiary value of joint NOPR: A network customer shall
standard that applies the integration
planning in assessing eligibility for receive credit for transmission facilities
standard comparably—applies and
customer credits. Taking a more added subsequent to the effective date
explain the difference and the basis for
expansive view, APPA argues that of the Final Rule if such facilities are
that choice. MDEA, FMPA and TAPS
network transmission customers also integrated into the operations of the
argue that no distinction is warranted
should be able to obtain credits for transmission provider’s facilities;
between the treatment of new and
transmission facilities they build provided however, the customer’s
pursuant to an open and collaborative transmission facilities shall be 436 The integration standard, in brief, requires that
transmission planning process in their presumed to be integrated if the to be eligible for credits under pro forma OATT
region or sub-region. This additional transmission facilities, if owned by the section 30.9, the customer must demonstrate that its
opportunity for credits, according to transmission provider, would be eligible facilities not only are integrated with the
APPA, would spur participation in the for inclusion in the transmission transmission provider’s system, but also provide
additional benefits to the transmission grid in terms
transmission planning process and provider’s annual transmission revenue of capability and reliability and can be relied on by
would be superior to litigating the requirement as specified in Attachment the transmission provider for the coordinated
proper application of the integration H of the pro forma OATT. operation of the grid. Southwest Power Pool, Inc.,
standard. 754. Under our precedent, a
108 FERC ¶ 61,078 at P 17 (2004) (citing Order No.
751. Entegra argues that the 888–A at 30,271), reh’g denied, 114 FERC ¶ 61,028
transmission provider’s facilities are (2006). This policy is premised on the principle that
Commission should make the crediting
presumed to provide benefits to the ‘‘just as the transmission provider cannot charge the
policy for network customers consistent customer for facilities not used to provide
transmission grid, whereas a
with the Commission’s policies for transmission service, the customer cannot get
transmission customer must make an credits for facilities not used by the transmission
generator interconnection facilities, and
affirmative showing that its facilities provider to provide service.’’ Id. at P 20 (citing
require credits to be available for
provide benefits in order to qualify for Order No. 888–A at 30,271 & n. 277); accord East
facilities that are integrated with the Texas Coop., Inc. v. Central & South West Services,
credits.435 Under the test we adopt in
transmission grid, without any showing Inc., 108 FERC ¶ 61,079 at P 28 (2004), reh’g denied,
this Final Rule, a transmission customer 114 FERC ¶ 61,027 (2006); Southern California
of additional benefits and irrespective of
will be required to meet the integration Edison Co., 108 FERC ¶ 61,085 at P 10 (2004);
whether the service in question is
standard under pro forma OATT section Northern States Power Co., 87 FERC ¶ 61,121 at
interconnection service, network 61,488 (1999); Florida Municipal Power Agency v.
30.9 in order to receive a credit for its
service, or point-to-point service. Florida Power & Light Co., 74 FERC ¶ 61,006 at
sroberts on PROD1PC70 with RULES

Entegra further argues that the 61,010 (1996), reh’g denied, 96 FERC ¶ 61,130 at
434 See NOPR at P 256. 61,544–45 (2001), aff’d sub nom. Florida Municipal
Commission should allow customers to 435 See Power Agency v. FERC, 315 F.3d 362 (D.C. Cir.
e.g., North East Texas Electric
sell transmission credits to obtain Cooperative, Inc., 108 FERC ¶ 61,084; East Texas 2003).
Electric Cooperative, Inc. v. Central and South West 437 E.g., APPA, FMPA, MDEA, NRECA, and
433 E.g., Entergy, Exelon, and Utah Municipals. Services, Inc., 114 FERC ¶ 61,027. TAPS.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00095 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12360 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

existing facilities and that the same who must unfairly bear the cost of automatic adjustment clause to their
standard should apply. providing the credit until the next rate rates through a rate filing with the
756. TAPS clarifies that it is not case. If the Commission does not allow Commission.440 EEI argues that if the
suggesting that the standard be applied automatic rate recovery of the concept of an automatic adjustment
retroactively to past uses, but rather incremental cost of credits, clause is just and reasonable for one
prospectively to existing facilities, with MidAmerican continues, the transmission provider, it is equally just
the key consideration being when the Commission should clarify that the and reasonable for all transmission
claim for credits is brought and not customer will not be allowed providers, and there is no need to adopt
when the facilities are constructed. transmission facility credits until the a case-by-case approach. EEI further
TAPS argues that it cannot be claimed rate adjustments are filed and accepted requests that the Commission clarify
that the revised standard should apply by the Commission. MidAmerican that its policy is to accept rate
only to new facilities because the explains that such filings would adjustments that incorporate the costs
comparability requirement is new. To examine only the new revenue that transmission providers incur to
the contrary, TAPS contends that requirements to be added and should provide credits related to customer-
comparability has been the theme and not require a general rate case for the owned facilities, provided that the rate
bedrock foundation of the Commission’s transmission provider’s entire revenue adjustment methodology is just and
transmission open-access requirement requirement. Nevada Companies reasonable. MidAmerican contends that
since its inception. likewise argues that credits should not the revenue requirement of the
757. APPA argues that the be granted to network customers if the transmission provider and those of
Commission effectively acknowledges recovery of those credits is not provided transmission customers should not be
in the NOPR that transmission providers for in the revenue requirement. co-mingled, rather, consistent with
have failed to plan new facilities jointly 761. TAPS agrees with the Commission precedent, the burden is on
with their transmission customers for Commission’s conclusion that it would the transmission-owning customer to
the last ten years under the current not be appropriate in this rulemaking to demonstrate to the Commission that its
section 30.9, but offers no redress for allow transmission providers to cost of service and revenue requirement
this past discrimination. automatically add costs of credits to used to establish the amount of the
their cost of service, and that such costs credit are just and reasonable before it
Commission Determination should continue to be evaluated as part can receive credits. As for
758. We conclude that the new test for of a regular transmission rate case (or nonjurisdictional entities, MidAmerican
determining credits will apply only to recovered through an approved formula explains that they may file for a
transmission facilities added subsequent rate). APPA expresses concern that declaratory ruling from the Commission
to the effective date of this Final Rule. transmission providers may attempt to regarding their revenue requirement.
A number of customer-owned use the Commission’s decision not to 764. Allegheny argues that if the
transmission facilities have been allow them to add the costs of credits Commission continues to deny
developed, and resulting credits associated with customer-owned transmission providers an automatic
negotiated and litigated, under the prior transmission facilities automatically to adjustment clause for these credits, it
test which the Commission determined their costs of service as a pretext for not should, at a minimum, assure
to be just and reasonable at the time.438 granting such credits in the first transmission providers that
We find no basis for revisiting the instance (at least until they decide to transmission credits will be recognized
Commission’s determinations in those file a new rate case). APPA continues as a cost of service in FPA section 205
cases in this Final Rule. On a that a transmission provider’s decision rate proceedings.
prospective basis, however, given the not to exercise the option to file under 765. Entergy argues that the
increased planning and coordination we FPA section 205 a new rate case or an Commission should recognize that any
require in the Final Rule, we believe it automatic adjustment clause should not filed agreement providing for payments
appropriate to apply the new test for serve as a reason to allow it to decline of credits would be subject to the filed-
determining credits. to provide credits. rate doctrine.
762. EEI explains that the customary
d. Cost of Customer Facilities basis for not allowing single-issue rate Commission Determination
Automatically Included in Transmission adjustments for new transmission 766. We are not persuaded to
Provider Cost of Service Without a Rate facilities is that while one aspect of the generically allow automatic recovery of
Filing transmission provider’s costs may have the costs of credits associated with
Comments increased, others may have decreased or integrated transmission facilities to the
load may have increased. This is not the transmission provider’s cost of service.
759. Several transmission providers case with respect to the inclusion of the
argue that, contrary to the Commission’s These costs typically are considered and
transmission costs related to customer- evaluated as part of a regular cost of
proposal, credits should be added owned facilities, EEI continues, since
automatically to the transmission service review process. Automatic
the existence of customer-owned recovery of the costs of credits would be
provider’s cost of service.439 facilities does not have any impact on
760. MidAmerican argues that contrary to our long-standing policy
the transmission provider’s own cost of
requiring the transmission provider to concerning single-issue rate
service. EEI concludes that a
defer including the cost of the adjustments, a policy we decline to
transmission provider should not be
transmission credit until its next filed modify here.441 Nevertheless,
forced into what is essentially re-
transmission rate case penalizes the transmission providers continue to have
justifying its transmission cost of service
transmission provider’s shareholders the option to propose an automatic
simply because a customer receives a
adjustment clause in their rates under
sroberts on PROD1PC70 with RULES

438 See East Texas Electric Cooperative v. Central


credit for the integration of its own
and South West Services, Inc., 114 FERC ¶ 61,027
facilities. 440 E.g., Allegheny, EEI, Exelon, and

(2006). 763. Some commenters also address MidAmerican.


439 E.g., Allegheny, EEI, MidAmerican, and the option currently open to 441 See, e.g., City of Westerville, Ohio v. Columbus

Nevada Companies. transmission providers to add an Southern Power Co., 111 FERC ¶ 61,307 (2005).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00096 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12361

FPA section 205 to address the time lag qualify. Additionally, Entegra contends cannot be integrated into CAISO’s
between incurring costs associated with that denying credits for upgrades operations unless they are under
credits and the transmission provider’s funded by point-to-point customers CAISO’s operational control, consistent
next rate case. would overlook the Commission’s past with the Commission’s prior rulings.
767. Contrary to EEI’s assertions, warnings that a customer funding any
customer credits do not warrant an 772. In Xcel’s view, an RTO has no
new facilities integrated with the grid
exception to the Commission’s general incentive to refuse to jointly plan to
should be entitled to credits because a
policy regarding single-issue rate avoid paying a credit and there is thus
transmission system ‘‘cannot be
adjustments. EEI argues that customer dismembered’’ or examined good cause to allow an RTO to deviate
credits should be treated differently piecemeal.444 from the language in the pro forma
because the existence of customer OATT relating to joint planning of new
owned facilities, in EEI’s view, does not Commission Determination facilities in order to be considered for a
have any impact on the transmission 770. The Commission adopts the facility credit. Xcel and International
providers’ own cost of service. Even if NOPR proposal not to make credits Transmission argue that RTOs should be
true, this fact would not obviate the generically available for point-to-point allowed to incorporate network
Commission’s policy. Regardless of customers that own transmission customer-owned facilities into RTO
whether the customer credit is deemed facilities. As the Commission explained rates in the same manner as if they were
to impact the transmission provider’s in the NOPR, a network customer takes constructed by a transmission owner,
own cost of service, the costs it imposes a usage-based service which integrates while ensuring against double recovery
may be offset by cost decreases in other its resources and loads and pays on the of both revenue requirements and
areas, by load growth, or both. Allowing basis of its total load on an ongoing network credits.
single-issue rate adjustments would basis. The transmission provider
enable a utility to increase the total rate includes the network customer’s Commission Determination
charged by focusing solely on a single resources and loads in its long-term
cost element, while avoiding scrutiny of 773. The Commission concludes that
planning horizon and the two parties
all other determinants of the rate. The coordinate operations of their facilities it would not be appropriate at this time
Commission has an obligation to ensure through a network operating agreement. to generically exempt all ISOs and RTOs
the justness and reasonableness of the In this way, network service is from the Final Rule requirements
total rate and it would be improper to comparable to the service that the regarding credits for network
allow a utility to raise rates by transmission provider uses to serve its transmission customers. We will
selectively focusing only on particular own retail native load, and credits for address issues relating to network
elements of its costs, while avoiding certain integrated network facilities are transmission customers credits in the
scrutiny of other rate inputs. The appropriate. The point-to-point RTO and ISO context in orders
Commission has refused to allow such customer, however, does not purchase addressing OATT reform compliance
rate treatment except in the most integration service, nor does it sign a filings submitted by each RTO and ISO.
limited of circumstances and we find no network operating agreement with the The Commission determined previously
basis for deviating from that policy in transmission provider. Because of the that the existing tariffs of certain RTOs
this context. As explained above, a inherent differences between point-to- and ISOs provide opportunities for
transmission provider that wishes to point and network service, we therefore transmission customers to receive credit
add an automatic adjustment clause to decline to require that transmission or the equivalent (e.g., Transmission
its rates may seek Commission approval providers make credits generically Congestion Contracts, Firm
for its methodology in a filing submitted available to point-to-point customers Transmission Rights or Auction
under FPA section 205. that own transmission facilities. If a Revenue Rights) for building facilities or
e. Point-to-Point Customers Not Eligible particular facility owned by a point-to- upgrades that are consistent with or
for Credits on Generic Basis point customer meets all the criteria for superior to Order No. 888
credits, we will continue to address requirements.447 Each RTO and ISO will
Comments
such situations on a fact-specific, case- have the opportunity to show on
768. Several commenters support the by-case basis consistent with the
Commission proposal to not make compliance that this continues to be the
Commission’s statement in Order No.
credits generically available to point-to- case given the reforms adopted in this
888.445
point customers that own transmission Final Rule.
facilities.442 APPA argues that if the f. RTO and ISO Issues
447 For example, NYISO’s tariff provides that a
frequency of cases seeking credits for Comments
facilities owned by point-to-point facilities study will contain a non-binding estimate
771. Several RTOs or ISOs assert that as to the feasible Transmission Congestion
customers is high, then the Commission they should not be required to comply Contracts (TCCs) resulting from the construction of
should reconsider its decision to use a with the crediting provisions because new facilities. There, upon completion of the
case-by-case approach. their respective planning processes and transmission upgrade and the first subsequent
769. Some commenters encourage the centralized TCC auction, the NYISO will determine
procedures are superior to or obviate the
Commission to clarify that point-to- the incremental TCCs associated with the upgrade.
need for those set forth in the NOPR.446
point transmission customers that pay See section 19.4 ‘‘Facilities Study Procedures’’ of
CAISO states that it does not oppose the NYISO’s tariff. Similarly, PJM’s tariff provides that
for upgrades should be compensated if
Commission’s proposal, provided that an interconnection customer that undertakes
such upgrades benefit the system.443
the Commission confirms that facilities responsibility for constructing or completing
PGP argues that customers be given network upgrades and/or local upgrades to
credits if they meet the same conditions
sroberts on PROD1PC70 with RULES

444 Citing Nevada Power Co., 101 FERC ¶ 61,036 accommodate its interconnection request will be
as network customers who would at P 8 (2002). entitled to receive the incremental Auction Revenue
445 Order No. 888 at 31,742; Order No. 888-A at Rights associated with such facilities and upgrades
442 E.g., APPA, Bonneville, EEI, Exelon, 30,271. subject to conditions. See section 46.1 ‘‘Right of
FirstEnergy, Nevada Companies, and TAPS. 446 E.g., Indicated New York Transmission Interconnection Customer to Incremental Auction
443 E.g., FirstEnergy, Seattle, and Suez Energy NA. Owners, ISO New England, PJM, and SPP. Revenue Rights’’ of PJM’s tariff.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00097 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12362 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Other issues issues and, instead, will address them opportunity costs for capacity
Comments on a case-by-case basis in response to reassigned by a customer should be
appropriate filings under FPA sections measured in a manner analogous to that
774. East Texas Cooperatives argue 205 and 206. With regard to incentives used to measure the transmission
that the Commission should clarify that for new facilities, the Commission has provider’s opportunity cost.452
a network customer is entitled to already addressed incentives for
transmission credits for its own NOPR Proposal
transmission infrastructure investment
transmission facilities and the facilities in Order No. 679.449 There the 779. In the NOPR, the Commission
of member utilities for which the Commission identified specific noted that capacity reassignment does
network customer arranges and pays for incentives that it will allow when not appear to have developed into a
network transmission services. East justified in the context of individual competitive alternative to primary
Texas Cooperatives explain that a recent proceedings. With regard to FMPA’s capacity since the issuance of Order No.
Commission decision 448 allows concerns regarding potential disputes 888. To facilitate development of this
transmission credits only for facilities over compensation for transmission market, the Commission proposed to
owned by the generation and investment by non-public utilities, we remove the price cap on capacity
transmission cooperative (G&T) and not note that section 12 of the existing pro reassignment and allow negotiated rates
for its individual members, which in its forma OATT contains dispute for transmission capacity reassigned by
view is contrary to past Commission resolution procedures. This Final Rule transmission customers. The
precedent. also requires transmission providers to Commission explained that, because the
775. FMPA asks that the Commission propose a dispute resolution process as price cap appears to have reduced
affirmatively state that it will exercise part of the coordinated planning customers’ transmission options,
its jurisdiction to ensure that public process. Additionally, the Commission’s removal of the cap may be warranted
power entities are compensated for Dispute Resolution Service is available without a market-by-market analysis.
transmission investment (including to assist in developing a dispute Due to market power concerns,
joint transmission projects) in the event resolution process, as well as the however, the Commission proposed to
of dispute with jurisdictional Commission via a formal complaint retain the price cap for capacity
transmission providers. FMPA explains filed pursuant to section 206 of the FPA. reassigned by the transmission
that the proposed revisions to section provider’s merchant function or its
30.9 may be insufficient to address all 4. Capacity Reassignment affiliates.
problems that may arise, especially in 778. In Order No. 888, the 780. The Commission proposed to
regions without an RTO or an existing Commission concluded that a monitor the market for reassigned
compensation method. NRECA asks the transmission provider’s pro forma capacity by requiring regular OASIS
Commission to prohibit RTOs and ISOs OATT must explicitly permit the postings and quarterly reports from
from using a non-public utility’s voluntary reassignment of all or part of transmission providers using
transmission facilities without a holder’s firm point-to-point capacity information submitted by reassigning
compensating the entity simply because rights to any eligible customer.450 With customers. First, the Commission
it has not joined the RTO or ISO. respect to the rate for capacity proposed retaining the existing posting
NRECA argues that comparable reassignment, the Commission and filing requirements for reassigned
treatment requires compensation for use concluded it could not permit capacity transactions to ensure that
of a transmission owner’s facilities, reassignments at market-based rates capacity is equally available to all
whether the owner is subject to because it was unable to determine that customers and to protect against undue
Commission jurisdiction or not, and the the market for reassigned capacity was discrimination and the potential
Commission should not consider a sufficiently competitive so that exercise of market power.453 Second,
transmission tariff to be just and assignors would not be able to exert the Commission asked several questions
reasonable if it allows unlawful trespass market power. Instead, the Commission regarding OASIS postings and the data
and conversion. capped the rate at the highest of (1) The that should be required in quarterly
776. TAPS asks the Commission to original transmission rate charged to the reports related to capacity
include language in section 30.9 of the purchaser (assignor), (2) the reassignments: (1) What information
pro forma OATT that affirmatively transmission provider’s maximum should be required in the quarterly
states customers’ eligibility for rate stated firm transmission rate in effect at reports and OASIS postings, i.e.,
incentives for new facilities under the time of the reassignment, or (3) the information about the capacity released,
recently established Commission policy. assignor’s own opportunity costs the original rate paid for that capacity,
TAPS further requests that the capped at the cost of expansion (price the price charged to the assignee for the
Commission guard against a cap). The Commission further explained capacity, and the term of the
transmission provider blocking such that opportunity cost pricing had been assignment; (2) whether other
incentive based credits by refusing to permitted at ‘‘the higher of embedded information was necessary for
engage in joint development of costs or legitimate and verifiable operational and reliability purposes; (3)
transmission projects with its opportunity costs, but not the sum of whether additional reports by assignors
customers. the two (i.e., ‘or’ pricing is permitted; to the transmission provider are
Commission Determination ‘and’ pricing is not).’’ 451 In Order No. necessary and, if so, what information
888–A, the Commission explained that should be reported by assignors; (4)
777. The Commission finds that there
is not enough evidence on the record to 449 Promoting Transmission Investment through 452 Order No. 888–A at 30,224.
make a generic determination on these Pricing Reform, Order No. 679, 71 FR 43294 (Jul. 453 The existing OASIS posting requirements for
sroberts on PROD1PC70 with RULES

31, 2006), FERC Stats. & Regs. ¶ 31,222 (2006), order reassigned capacity already require, if selling on
448 East Texas Electric Cooperative, Inc. v. Central on reh’g, Order No. 679–A, 72 FR 1152 (Jan. 10, OASIS, for sellers to include data elements such as
and Southwest Services, Inc., 108 FERC ¶ 61,077 at 2007), FERC Stats. & Regs. ¶ 31,236 (2007). the path name, point of receipt, point of delivery,
450 See Order No. 888 at 31,696; pro forma OATT
P 21–23 (2004), reh’g denied, 114 FERC ¶ 61,027 source, sink, capacity requested, capacity granted,
at P 43–44 (2006), appeal docketed, No. 06–1090 section 23.1. start time, stop time, and offer price. See 18 CFR
(D.C. Cir. Mar. 10, 2006) 451 Id. at 31,740. 37.6(c)(5).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00098 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12363

should the Commission establish a new transmission provider’s ability to the cap for all transmission customers if
quarterly reporting process with a new leverage its monopoly power in the transmission provider and its
form, or use the existing Electric transmission into market power in affiliates are not allowed to resell
Quarterly Report procedures; and (5) generation markets.457 Entegra further capacity at market-based rates.
how frequently should OASIS postings contends that Southern, Entergy, and 785. Several commenters argue that
be made. other transmission providers have the Commission’s justification for
monopoly power in transmission eliminating the price cap—namely,
Comments reducing the ability of non-affiliated
markets in their service territories and
Lifting the Price Cap for All without a cap would exploit that market customers to exercise market power in
Transmission Customers power in the secondary market. the secondary market through
781. Some commenters support Moreover, Entegra argues that allowing competition among releasing customers,
eliminating the price cap for transmission providers and their monitoring the market via quarterly
reassignment of transmission capacity affiliates to charge market-based rates reports, and continuing rate regulation
in the secondary market.454 For for transmission capacity in the primary of primary capacity—applies to energy
example, EPSA states that the or secondary market would exacerbate and marketing affiliates as well.460 First,
Commission is correct to recognize that the skewed incentives that already several commenters argue that the
negotiated rates are dynamic and operate to discourage construction of Standards of Conduct and existing pro
provide a market discipline on the price much needed transmission facilities in forma OATT rules ensure that
for reassigned capacity. Entegra argues many markets. transmission provider affiliates have no
that the Commission’s removal of rate 783. Many commenters contend that more ability to obtain information about
caps on releases of natural gas pipeline lifting the price cap for reassignment of the transmission system or to reserve
capacity increased available peak transmission capacity only for point-to-point transmission capacity
capacity and facilitated the movement unaffiliated transmission customers than unaffiliated customers. 461
of capacity into the hands of those that would be unreasonable.458 For example, Entergy contends that, although the
value it most highly, proving that an Entergy argues that for the wholesale Commission correctly concludes
uncapped capacity release market can markets to work all wholesale market elsewhere in the NOPR that functional
be both competitive and result in just participants, including the transmission unbundling and Standards of Conduct
and reasonable rates for customers.455 provider’s affiliated marketers, must be requirements, if properly enforced are
Exelon supports eliminating the price treated comparably under the pro forma sufficient to address affiliate abuse
cap, but asserts that, since the OATT. EEI contends that lifting the concerns, the Commission seems to
transmission customer is seeking to price cap can result in a more robust assume that those same protections
reassign the capacity, it is likely the secondary market for transmission cannot be effective where the
capacity is not useful in gaining access capacity and will reduce any risks that reassignment of transmission capacity is
to load and therefore is not very transmission customers may associate concerned.
valuable. BP Energy contends that with being required to purchase 786. Second, some commenters
transparent competition between the transmission service for five-year terms question the Commission’s assertion
transmission provider (marketing in order to obtain rollover-rights. In that permitting transmission provider’s
primary and subscribed but unutilized addition, Manitoba Hydro asserts that energy and marketing affiliates to resell
capacity) and transmission customers, changing the current one-year minimum or reassign transmission capacity would
with monitoring by the Commission and term creates additional risks for give them the ability to favor their own
prospective capacity purchasers, will transmission customers and therefore generation.462 For example, EEI
moderate if not eliminate the potential having the ability to re-sell the contends that transmission providers
exercise of market power and encourage transmission capacity at market-based have no control over the reassignment
the release of capacity that is not rates would assist transmission process, and transmission customers
otherwise used or useful. As a result, BP customers to better manage the financial have complete freedom to reassign
Energy urges the Commission to require risks involved with holding longer term transmission capacity to any customer
transmission providers to facilitate a contracts. they choose. Entergy points out that
competitive capacity reassignment 784. Some commenters support lifting under Order No. 888 the assignor of
process, similar to that used for capacity the price cap for affiliates if caps are capacity may deal directly with an
release on natural gas pipelines. removed for non-affiliates, but are only assignee and without involvement of the
782. Some commenters support the generally supportive of lifting the price transmission provider.463
proposal to retain the price cap for cap.459 If the Commission does lift the 787. Third, some commenters
transmission providers and their price cap, Southern argues that it should disagree with the Commission’s
affiliates.456 Seattle states that the also lift the price caps for the statement that lifting the price cap for
Commission is correct to continue to transmission provider and its affiliates affiliates may dampen transmission
cap prices for the transmission provider as well in order to counter efforts to investment.464 These same commenters
since the transmission provider is a corner the market and other related argue that there is no relationship
regulated monopoly. In its reply, unforeseen consequences. MidAmerican between the transmission provider’s
Entegra states that the Commission has agrees, asking the Commission to retain obligation to build transmission
found that having a pro forma OATT
mitigates but does not eliminate a 457 Citing Public Service Electric & Gas Company, 460 E.g., EEI, Entergy, MidAmerican, PNM–TNMP,

78 FERC ¶ 61,119 at 61,455 (1997) (granting market- Progress Energy, Southern, and South Carolina
454 E.g., Allegheny, AWEA, Constellation, EEI, based rate authority based in part on the adequate E&G.
461 E.g., Community Power Alliance, Entergy,
Entegra, EPSA, Exelon, Morgan Stanley, PPL, ‘‘mitigation of market power’’ as evidenced by a pro
sroberts on PROD1PC70 with RULES

Seattle, Suez Energy NA, and TranServ. forma OATT). Imperial, Manitoba Hydro, Salt River, South
455 Citing Natural Gas Pipeline Negotiated Rate 458 E.g., Community Power Alliance, EEI, Entergy, Carolina E&G, and Southern.
462 E.g., EEI, Entergy, MidAmerican, and Progress
Policies and Practices, 114 FERC ¶ 61,034 (2006) FirstEnergy, Imperial, Manitoba Hydro,
(Brownell, Comm’r concurring). MidAmerican, Progress Energy, and Salt River. Energy.
456 E.g., APPA, AWEA, NRECA, Seattle, TAPS, 459 E.g., MidAmerican, PNM–TNMP and South 463 See Order No. 888 at 31,697.

and TDU Systems. Carolina E&G. 464 E.g., EEI, MidAmerican, and Progress Energy.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00099 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12364 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

facilities to accommodate third party disadvantage.467 Community Power investment.469 If removal of the cap
requests for transmission service and Alliance argues it is unfair for the were effective in making reassignment
the ability of marketing and energy Commission to now say that their more profitable, TAPS contends it
affiliates to resell unused transmission separated marketing affiliates, which would encourage hoarding of capacity
capacity at market-based rates. For have abided by Commission rules like on key paths that would run afoul of the
example, Progress Energy and others any other market participant, cannot directive in FPA section 217(b)(4) to
contend that the transmission provider now compete on an equal footing with ensure the ability of LSEs to secure
is obligated under the pro forma OATT other participants in the secondary long-term rights for their long-term
to construct transmission facilities to market for transmission capacity. Rather power supply arrangements. Northwest
meet all requests for transmission than prohibit transmission providers’ IOUs argue that lifting the price cap
service.465 Progress Energy and EEI affiliates from reselling capacity, would encourage non-affiliated
contend that the transmission customer Manitoba Hydro suggests that a more transmission customers to buy
will decide to purchase secondary equitable approach would be for the transmission capacity at cost and resell
market transmission capacity if it meets Commission to lift the price cap for all it at market, in an effort to reduce the
the reasonable needs of customers so resold transmission capacity, except for amount of transmission capacity
long as the capacity is priced below the transmission capacity administered by available for resource development and
higher of the embedded cost of an affiliate’s transmission provider. other long-term uses. PJM argues that
transmission service or the cost of the final rule should include a
790. To the extent the Commission
expansion. EEI argues that the customer requirement that appropriate hoarding
adopts the proposed restriction on
can require the transmission provider to mitigation procedures be implemented
affiliate reassignments, MidAmerican should the price cap be removed. APPA
construct additional capacity to seeks guidance on whether the
accommodate the customer’s request for argues that, if no transmission capacity
transmission provider is expected to is available in the short run from the
service if secondary market service— assure that the assignee is a valid
whether offered by the transmission transmission provider, and an LSE
eligible customer under the pro forma needs additional capacity to serve load
provider’s marketing and energy OATT. Similarly, Southern encourages
affiliates or by a third party customer— within the next day or week, the fact
the Commission to carefully identify that the transmission provider could
is priced above the cost of expansion. In and evaluate the possible adverse effects
such situations, EEI and Progress Energy build capacity in future years at an
of lifting any reassignment price caps. incremental rate has little if any bearing
contend that the cost of expansion Southern asserts that such effects could
serves as a cap on the price at which on the price that LSE is willing to pay
include expanded involvement and for the next day, week, or month to avert
both third party customers and the influence by financial players driven
transmission provider’s marketing and a looming supply problem. TVA asserts
exclusively by profit motives and who that transportation prices rose
energy affiliates can resell transmission may not be subject to Commission
capacity. Moreover, Entergy argues that drastically during periods of high
regulation. demand or constraint after the price cap
this is the same justification that the
Commission relies upon to conclude 791. Several commenters contend that for resale of gas transmission capacity
that transmission customers would not the Commission should retain the price was removed in Order No. 637 for
hoard secondary capacity, and it is cap for the reassignment of transmission everyone except pipelines and their
arbitrary for the Commission to ignore capacity for all customers, not just affiliates. TVA states that this benefited
that principle in concluding that a affiliates of the transmission entities that could afford to hold
transmission provider would hoard provider.468 APPA argues that allowing capacity, but harmed those that had to
capacity. the resale of such a scarce and valuable buy additional capacity on a short-term
service to those who value the capacity basis.
788. Additionally, some commenters 793. Alcoa and Nevada Companies
argue that lifting the price cap for more highly is a recipe for undue
discrimination and unjust and argue that there is a significant potential
affiliates will encourage transmission for abuse in connection with the
investment.466 NorthWestern contends unreasonable transmission rates, at the
expense of end-use customers. While removal of the cap, particularly in load
that allowing transmission providers to pockets. Alcoa argues that it is not clear
collect more than their ceiling price NRECA opposes the Commission
proposal to remove the price cap, at this point that there are sufficient
when the market is willing to pay a safeguards in place to prevent and
higher price could further the NRECA would support the proposal to
retain the price caps for affiliates. monitor the exercise of market power,
Commission’s goal of encouraging something that must be assured before
transmission investment to maintain Similarly, TAPS supports the decision
not to lift the price caps for affiliates; the cap is lifted on transmission
reliability and keep pace with load capacity resale. Nevada Companies
growth. NorthWestern suggests that the however, TAPS urges the Commission
to rethink the NOPR’s proposal to contend the proposal to remove the cap
Commission could place restrictions on may actually reduce utilization of the
the proceeds in excess of the ceiling otherwise lift the price cap for non-
affiliates. grid, contrary to its intended purpose.
price such that, within some specified For example, Nevada Companies state
period, the dollars must be reinvested 792. Several commenters argue that
that transmission customers who have
into transmission facilities or be lifting the cap for any transmission
locked up capacity in constrained
refunded back to customers. customers would encourage the exercise
markets will likely wait to the very last
789. Several commenters contend that of market power, including hoarding,
minute to make that capacity available
lifting the price cap only for non- and discourage transmission
in order to drive up the price, which
affiliates could dampen participation in will often result in the capacity not
sroberts on PROD1PC70 with RULES

the secondary market and place 467 E.g., Community Power Alliance, EEI,
being utilized if transactions cannot
affiliates at a competitive FirstEnergy, Imperial, Northwest IOUs, Southern,
and TVA. occur quickly enough. Some
468 E.g., Alcoa, APPA, International Transmission,
465 E.g., EEI, Entergy and MidAmerican. Nevada Companies, NRECA, PJM, Public Power 469 E.g., APPA, Nevada Companies, Northwest
466 E.g., Entegra and NorthWestern. Council, TAPS, and WAPA. IOUs, NRECA, PJM, TAPS, and WAPA.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00100 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12365

commenters contend that, like LMP in requests that the Commission clarify higher per unit cost than the primary
organized markets, allowing price that the revised pro forma OATT does rate stated in the transmission
signals via lifting the cap may not not impose the cap on affiliates of provider’s pro forma OATT (due in part
encourage transmission investment, but transmission owners that have turned to the fact that a customer may not use
rather create entrenched interests that their transmission facilities over to an all of the capacity for which it has
profit from the existence of congestion RTO/ISO when they reassign contracted).
and oppose efforts to eliminate such transmission capacity on facilities 798. Sacramento proposes that prices
congestion through transmission operated by the RTO/ISO. While MISO for released capacity be capped at the
expansion.470 If transmission providers takes no position on whether the amortized and rate-based cost of a
are forced to purchase capacity at higher Commission should retain its cap for transmission upgrade. Seattle states that
prices on the secondary market, stand-alone transmission providers and costly redirect processes, including
Imperial argues that their native load their affiliated customers, it argues that system impact studies, may be needed
customers be harmed by such higher the cap makes no sense in the context to create a reassignment product that
prices, which may in turn hamper of capacity reassignments administered has value to other customers, given that
transmission expansion contrary to the by RTOs and ISOs. MISO observes that the point of receipt, point of delivery or
Commission’s stated goals for promoting the NOPR cites affiliate preference and both typically change in a reassignment.
transmission investment. market power concerns as the basis for While the current pro forma OATT
794. In addition, some commenters retaining the cap on reassignments by pricing model differentiates
are skeptical of the Commission’s transmission providers and their transmission rates based on term and
assertion that existing market affiliated customers, which MISO argues time of day (monthly, weekly, daily,
mechanisms are a sufficient deterrent to are not applicable in the RTO/ISO hourly), Seattle asserts that seasonal
anticompetitive behavior.471 WAPA and context. Further, MISO argues that the variations in the value of transmission
TAPS argue that, while eliminating the ownership of transmission assets in an rights offered for short-term
price cap might increase customers’ RTO/ISO is divorced from the provision reassignment are also worthy of
transmission options, the Commission of transmission service, and RTO consideration, especially in a region like
still needs to conduct case-by-case transmission owners are transmission the Northwest, where power production
market power analyses prior to lifting customers no different from any other varies seasonally.
the cap.472 As a result, WAPA argues, it customer class. 799. MISO states that it believes the
is critical for the Commission to identify 796. On the contrary, APPA notes that
Commission should further strengthen
and aggressively mitigate all the issue is whether the transmission
its pro-competitive policy by permitting
transmission market power on an ex customer holding transmission rights
RTO/ISO transmission providers to offer
ante basis, rather than utilizing an ex over a constrained path has the ability
firm point-to-point transmission service
post monitoring scheme as proposed in to exercise market power and charge
for drive-out/drive-through transactions
the NOPR. If the Commission lifts the unjust and unreasonable rates if the cap
at market-based rates, including
price cap, certain commenters argue that is lifted. APPA argues that the issue is
the same in both RTO and non-RTO ‘‘rollover’’ transactions. MISO states that
the Commission should establish the principles for allocating firm
competitive bidding transaction regions. In APPA’s view, whether the
public utility transmission provider has capacity on such interfaces should be
standards.473 For example, Seattle the same as for reassigning capacity
asserts that a standards organization joined an RTO, does not affect the
ability of its merchant affiliate to extract within an RTO: i.e., permitting
such as NAESB will need to establish customers that value the capacity more
bid/ask transaction standards and unjust and reasonable rents for the
resale of scarce transmission rights. highly to benefit from it. MISO asserts
reporting formats and the Commission that allowing market participants to
must periodically validate the Alternative Price Cap Proposals compete based strictly on price on
assumption that the secondary market is external interfaces would resolve many
workably competitive. 797. Some commenters propose
alternatives to negotiated pricing of inefficiencies stemming from the
Application of the Price Cap to transmission capacity in the secondary cumbersome queue administration
Members of ISOs/RTOs market.475 While APPA supports procedures currently used on such
795. Some commenters request retaining the current rate cap, it facilities. MISO states that the final rule
clarification that, if the Commission contends that firm point-to-point should encourage RTOs and ISOs to
retains the price cap for capacity customers should be allowed to collect introduce such competitive practices in
reassigned by affiliates, that it not apply demonstrable out-of-pocket costs in their footprints.
to entities that have turned over control addition to the maximum capped rate. 800. PGP proposes two alternative
and operation of their transmission Alcoa suggests that the Commission approaches. First, PGP proposes that the
facilities to an RTO, ISO or independent could stimulate the secondary market Commission could wait until a regional
entities.474 For example, Constellation for transmission capacity by increasing approach for pricing reassignments is
the cap and allowing parties to charge developed in those areas of the country
470 E.g., APPA, International Transmission, a percentage over the original price that still rely on reassignments of point-
NRECA, Public Power Council, and Seattle. paid. Seattle contends that the existing to-point capacity to create a secondary
471 E.g., Alcoa, APPA, Bonneville, TAPS, and
Commission policy could be market in transmission service. Second,
WAPA. incrementally modified to permit PGP proposes that any decision to
472 Citing Farmers Union Cent. Exch., Inc. v.

FERC, 734 F.2d 1486, 1508–10 (D.C. Cir. 1984)


recovery of remarketing costs and remove the price cap could be made on
(concluding that ‘‘undocumented reliance on recognize that, for many customers, the a case-by-case basis after a filing by a
market forces is insufficient to satisfy the transmission right is held at a much point-to-point customer at the
sroberts on PROD1PC70 with RULES

Commission’s regulatory responsibilities.’’); Commission, in which the applicant


California ex. Rel. Lockyer v. FERC, 383 F.3d 1006, providers of transmission service, they have no
1013 (9th Cir. 2004).
must meet standards developed by the
affiliates and likewise are not bound by the
473 E.g., BP Energy, Seattle, and TranServ. Commission’s reassignment proposal. Commission that demonstrate the lack
474 E.g., Ameren, Constellation, SPP, and 475 E.g., Alcoa, APPA, Manitoba Hydro, PGP, of market power in relevant
TranServ. ISO New England and PJM argue that, as Sacramento, and Seattle. transmission or generator markets.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00101 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12366 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

801. South Carolina E&G requests that the transmission customers should Other Issues
the Commission clarify how the cap is report on the OASIS and in the 806. Some commenters argue that
calculated if the Commission chooses to quarterly reports include: The identity price caps are not limiting capacity
retain the price cap. International of the primary market seller; the reassignment under the current pro
Transmission asserts that the identities of the secondary market seller forma OATT.481 Williams contends that
Commission should lift the price cap, and purchaser; the points of receipt and other non-price limitations on capacity
on an experimental basis, similar to the delivery; the term of reassigned service; reassignment, such as the requirement
approach followed in the natural gas the quantity of the reassigned service; that the assignee utilize the same source
industry. Similarly, WAPA recommends and the charge for the reassignment, and sink as the original customers, are
that the Commission either retain the expressed in dollars per MW-month, the real reasons there has not been more
price cap or institute a separate week, day, or hour as appropriate. Other capacity reassignment. Williams
rulemaking proceeding for the purpose commenters contend that the existing acknowledges that this bars network
of establishing detailed market analysis quarterly report is appropriate and a customers from reassigning
criteria for eliminating the price cap for new report should not be instituted.479 transmission capacity and requests that
specific transmission segments or paths. TranServ argues that the existing OASIS Commission clarify that classification of
Posting and Filing Requirements posting template query and audit a transmission customer as a network or
functions are sufficient and no new point-to-point customer does not restrict
802. Some commenters support the obligations should be required. As to
proposal to require transmission the purchase or reassignment of
frequency of OASIS postings, Seattle transmission capacity. Sacramento
providers to submit quarterly reports suggests seven days after a transaction
and make OASIS postings regarding similarly complains that one of the chief
and NorthWestern proposes that the impediments to capacity reassignment
reassignments of transmission OASIS postings be no more frequent
capacity.476 Bonneville asserts that, at a is that network integration service
than monthly. customers are not permitted either to
minimum, transmission customers
804. Other commenters raise assign their capacity or to utilize it to
should be required to provide a
confidentiality concerns or state that make off-system sales. Sacramento
downloadable file to the transmission
business practice standards for capacity contends that a point-to-point customer
provider for posting on the transmission
reassignment posting requirements may utilize otherwise unused capacity
provider’s OASIS that identifies the
would be required.480 Because these to make sales ‘‘off-system’’ to third
assignee, the amount of capacity
negotiated rates will be market parties, while network customers cannot
assigned or transferred, the date of the
sensitive, Allegheny asks the make full use of the transmission
offer of assignment, and the rate and
Commission not to require reporting capacity for which they are paying.
duration of the assignment. Other
and OASIS posting until the term of the 807. Some commenters contend that
commenters argue that transmission
reassignment has expired. NAESB states timelines for the release of capacity
customers should be given greater
that capacity reassignment, including should be clearly stated.482 APPA
reporting responsibility.477 Southern
removing the price cap and allowing argues that section 13.8 of the pro forma
contends that transmission providers
negotiated rates, could require posting OATT provides too little time for LSEs
should not be burdened with submitting
standards for OASIS sites and the attempting to make firm power supply
quarterly reports and making OASIS
addition of significant functions to arrangements to obtain even daily firm
postings based on assignment
support such postings. point-to-point service using the capacity
information provided to them by other
assignors/assignees. Rather, Southern 805. NAESB states that capacity left unscheduled by other firm point-to-
and EEI argue that assignment reassignment including removing the point customers. Powerex and SPP also
information should be filed by the price cap and allowing negotiated rates ask the Commission to set out clear
respective assignors and assignees in could require posting standards for the rules, including timelines, for releasing
connection with their Electric Quarterly OASIS site, and significant functions unused transmission capacity for non-
Report filings and not by the added to support such postings. NAESB firm use to better encourage full and
transmission provider. PNM–TNMP asserts that this will require a more economically efficient use of the
contend that the Commission should comprehensive standards solution, existing transmission grid.
prescribe specific reporting obligations which may include data aggregation by
the transmission provider, reports Commission Determination
and associated deadlines to the
assignors and reporting obligations prepared and posted quarterly including 808. To foster the development of a
should also include appropriate how the information is communicated more robust secondary market for
consequences for non-compliance on between the transmission provider and transmission capacity, the Commission
the part of the assignor. Nevada marketer for collection, submittals of concludes that it is appropriate to lift
Companies ask that a system be put in quarterly reports from the transmission the price cap for all transmission
place to charge relevant transmission provider to the Commission, changes to customers reassigning transmission
customers for the additional reporting if the OASIS S&CP, and determination of capacity. In Order No. 888, the
the transmission provider is required to informational content and design of Commission found that allowing
do the reporting, either on the OASIS or templates. NAESB states that posting is holders of firm transmission capacity
through some other mechanism. more complicated if the transmission rights to reassign capacity would help
803. Some commenters argue that provider is required to post information parties manage the financial risks
more information should be posted on given to it by a marketer on its non- associated with their long-term
OASIS beyond what was proposed in standard products and requests commitments, reduce the market power
the NOPR.478 EEI asserts that the details Commission guidance regarding posting of transmission providers by enabling
sroberts on PROD1PC70 with RULES

requirements. customers to compete, and foster


476 E.g.,Bonneville, FirstEnergy, and PJM.
477 E.g.,EEI, Entergy, Nevada Companies, PNM– 479 E.g.,PJM, PNM–TNMP, and TranServ. 481 E.g., Powerex, Sacramento, TAPS, and

TNMP, South Carolina E&G, Southern, and TVA. 480 E.g.,Allegheny, Morgan Stanley, NAESB, Williams.
478 E.g., EEI, PJM, and Seattle. Seattle, and TranServ. 482 E.g., APPA, Powerex, and SPP.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00102 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12367

efficient capacity allocation.483 Over the and reasonable. Finally, the amended firm capacity is available on a non-firm
past ten years, however, it has become rules we adopt below to govern the basis to other customers and, thus, there
clear that capacity reassignment has reassignment of capacity will increase is little practical possibility of hoarding.
failed to develop into a competitive our regulatory oversight of the Instead, the capacity reassignment
alternative to primary capacity. In secondary capacity market, allowing us provisions of the pro forma OATT
particular, the price cap has served to to effectively monitor the secondary provide an economic incentive to make
reduce customers’ transmission options capacity market. There is thus no need that capacity available to third
and impaired the development of a to retain the existing price caps on parties.488 This applies even when the
secondary market for transmission reassigned capacity for any market entity obtaining transmission capacity
capacity. In order to achieve the goals participant. under the pro forma OATT is the
originally stated in Order No. 888, we 810. Our decision to lift the price caps transmission provider.489 It is equally in
therefore lift the price cap for reassigned for capacity reassignments by all the corporate interests of a transmission
capacity. We believe this will allow transmission customers is motivated by provider and its affiliates not to over-
capacity to be allocated to those entities growing concerns regarding the decrease reserve or ‘‘hoard’’ transmission
that value it most, thereby sending more in transmission investment and the capacity. Under the pro forma OATT,
accurate price signals to identify the corresponding increase in congestion the affiliate—and therefore the upstream
appropriate location for construction of costs, as described more fully in section corporate parent of the affiliate and the
new transmission facilities to reduce III.C of this Final Rule. The Commission transmission provider—bears the cost
congestion. believes it is important to take every responsibility for transmission capacity
809. We decline to adopt the NOPR opportunity to explore more efficient that it reserves but does not use to make
proposal to retain price caps for use of the grid by industry participants, wholesale sales. If the affiliate attempts
capacity resold by a transmission whether they are affiliates of the to hoard transmission capacity, its
provider’s merchant function or its transmission provider or not. upstream corporate parent loses
affiliates.484 After reviewing the Eliminating the price cap for reassigned revenues just like the non-affiliate. Like
comments submitted in response to the capacity will provide greater flexibility any other customer, an affiliate of the
NOPR, and further considering our ten to respond to changing system transmission provider should find it in
years of experience regulating capacity conditions and alternatives for its overall corporate interest to reassign
reassignments, we conclude that customers that value the capacity more transmission capacity to others with
retaining the price caps for this portion highly. As commenters suggest, lifting higher valued uses at negotiated
of the market would continue to impair the price cap will enhance the ability of rates.490
development of the secondary market customers that reserve long-term 812. We reject the suggestion in the
and is not otherwise necessary to ensure capacity for five-year terms in order to NOPR that lifting the price caps for the
just and reasonable rates. We find there obtain rollover rights to resell that transmission providers’ merchant
are no significant market power capacity if their needs change.487 Other function or affiliates will provide
concerns to justify retaining the price customers may determine that it is more disincentives to build or expand the
caps for any transmission customer. economic to acquire reassigned capacity transmission system. Without
Indeed, the Commission did not reflecting market rates than reserve congestion, the transmission provider’s
distinguish between affiliated and non- long-term capacity. In either case, lifting rate on file will serve as the de facto
affiliated transmission customers when the price cap will help ensure that, price cap and, if congestion exists, the
it initially found in Order Nos. 888 and during peak demand periods, ‘‘incremental rate’’ reflecting the
888–A that excess capacity reserved transmission capacity will be used by transmission provider’s cost of
could be reassigned.485 The Commission those that value it the most. Establishing expanding the system should act as a
instead placed a price cap on all a competitive market for secondary price ceiling for long-term transactions.
reassignments of capacity out of a transmission capacity will thus send It would be unreasonable to expect a
concern that the entire market for more accurate price signals that promote transmission customer to pay a rate for
reassigned capacity was not sufficiently efficient use of the transmission system reassigned capacity that is higher than
competitive.486 We now find that by fostering the reassignment of unused the cost of expansion when it could
market forces, combined with the capacity. simply exercise its rights under the pro
requirements of the pro forma OATT as 811. While some commenters argue forma OATT as a cheaper alternative.
modified in this Final Rule, will limit that lifting the cap encourages the To the extent there is a lag-time between
the ability of assignors to exert market exercise of market power, including the request for new transmission service
power, including affiliates of the hoarding, and discourages transmission
transmission provider. First, investment, we find that competition 488 Order No. 888 at 31,693.
competition among reassigning among reassigning customers, 489 See Southwestern Public Service Company, 80
customers will restrict the exercise of continuing rate regulation of the FERC ¶ 61,245 at 61,905 (1997).
490 Moreover, Order No. 889 required that all
market power. Second, the continued transmission provider’s primary
public utilities establish or participate in an OASIS
regulation of rates for primary capacity capacity, and reforms to the secondary that meets certain specifications and comply with
will act as a further check to ensure capacity market adopted below, Standards of Conduct designed to prevent
rates for reassigned capacity remain just combined with enforcement employees of a public utility (or any employees of
proceedings, audits, and other its affiliates) engaged in wholesale power marketing
functions from obtaining preferential access to
483 Order No. 888 at 31,696. regulatory controls, will assure just and pertinent transmission system information. The
484 Because Order Nos. 888 and 888–A require a reasonable rates. The Commission Standards of Conduct mitigate the ability of an
separation of a public utility’s transmission discussed the possibility of transmission affiliate to hoard capacity or collect rates that are
function and its wholesale generating marketing inconsistent with market conditions. As a result, we
capacity hoarding in Order No. 888. The
sroberts on PROD1PC70 with RULES

(merchant) function, a transmission provider will are less concerned in this instance about affiliates
take service under its OATT through its merchant Commission noted that unscheduled competing on the same terms as non-affiliates. To
function or affiliate. the extent problems arise from affiliate participation
485 Order No. 888 at 31,696–97; Order No. 888– 487 As explained in section V.D.3, the Final Rule in the secondary capacity market, we will revisit
A at 30,219–25. extends from one year to five years the minimum our decision here to lift the price caps for
486 Order No. 888 at 31,697. term required to obtain a rollover right. transmission providers and their affiliates.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00103 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12368 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

and the date on which new facilities longer believe that cost-of-service that all reassignments must instead be
would be available, the adoption of regulation is necessary or appropriate accomplished by the assignee executing
conditional firm service and for secondary capacity.492 a service agreement with the
modifications to redispatch service 815. As with any innovative rate transmission provider that will govern
elsewhere in this Final Rule will program, however, the Commission will the provision of reassigned service.495
mitigate the exercise of market power monitor the secondary capacity market This will effectively return the specified
during the interim period. We believe to ensure that participants are not capacity to the transmission provider for
that the reforms to rules governing exercising market power. To enhance the purpose of reassignment to the
reassignments of capacity discussed oversight and monitoring by the assignee.496 The assignment shall be
below, along with associated reporting Commission, we adopt reforms to the only to the specified assignee, without
obligations, will adequately limit the underlying rules governing capacity any obligation that the capacity be made
ability of capacity holders to exercise reassignments. First, we require that all available to third parties, and shall not
market power in the limited sales or assignments of capacity be be subject to any queuing by the
circumstances when neither primary conducted through or otherwise posted transmission provider since the assignee
transmission capacity nor these on the transmission provider’s OASIS is merely accepting the assignor’s
additional services are available. on or before the date the reassigned already-approved service for a specified
813. Several commenters raise service commences. The Commission period.497 All of the non-rate terms and
concerns that lifting of the price ceiling thus eliminates the current ability of conditions that otherwise would apply
could lead to speculative pricing. If high transmission customers to assign the to the transmission provider’s sale of
prices occur during periods of peak transmission rights to another party transmission capacity continue to apply
demand it is a legitimate reaction to with subsequent notification to the in the case of a reassignment.498
supply and demand forces. As we transmission provider.493 The 817. Third, in addition to existing
explained in Order No. 637–A, ‘‘[a] mechanisms for negotiating a OASIS posting requirements, we require
surge in the price of candles during a reassignment remain the same. The transmission providers to aggregate and
power outage is not evidence of transmission customer may either summarize in an electronic quarterly
monopoly in the candle market.’’ 491 To request that the transmission provider report the data contained in these
the extent that capacity is not being make the capacity available on its service agreements. As proposed in the
anticompetitively withheld from the OASIS or the transmission customer NOPR, the use of quarterly reports will
market, high prices are the competitive may negotiate the terms of an assist the Commission in gathering data
responses to market conditions and assignment bilaterally. In either to ensure the effectiveness of market
should result in a more efficient instance, however, the resulting sale or forces and regulatory requirements to
allocation of capacity to those customers assignment must be posted by the mitigate the exercise of market power.
valuing it the most and a resulting transmission provider on its OASIS The Commission directs that this
expansion of transmission facilities. prior to the date the reassigned service quarterly report be submitted
814. We emphasize that we are not commences. We require transmission electronically in spreadsheet format
deregulating or otherwise adopting providers working through NAESB to
market-based rates for the provision of develop appropriate OASIS 495 The pro forma Form of Service Agreement for

transmission service under the pro functionality to allow such postings. the Resale, Reassignment or Transfer of Long-Term
forma OATT. Transmission providers Transmission providers need not Firm Point-to-Point Transmission Service is set
forth in a new Attachment A–1 to the pro forma
will continue to be obligated to make implement this new OASIS OATT.
ATC available to customers, including functionality and any related business 496 As reformed in this Final Rule, the structural
ATC associated with purchased but practices until NAESB develops mechanism for reassigning transmission capacity
unused capacity. Transmission appropriate standards. will be similar to the mechanism for releasing
providers also will continue to be 816. Second, we require that assignees pipeline capacity. While parties may be able to
negotiate the prices applicable to assigned capacity,
obligated to construct new facilities to of transmission capacity execute a the assignee will execute a service agreement
satisfy a request for service if that service agreement prior to the date on directly with the transmission provider and, thus,
request cannot be satisfied using which the reassigned service there will no longer be a need for the assigning
existing capacity. The pro forma OATT commences. Under the current pro party to have on file with the Commission a rate
schedule governing reassigned capacity. See Order
therefore does not, and will not, permit forma OATT, transmission customers No. 888 at 31,697 n. 324. The transmission
the withholding of transmission that have executed service agreements provider’s OATT will govern the reassigned service.
capacity in an effort to exercise market may negotiate and implement The assignee will pay the transmission provider for
power. Furthermore, the rates for assignments of capacity without service at the negotiated rate and the transmission
transmission service provided under the involving the transmission provider, provider will bill or credit the assignor with any the
difference between the negotiated rate and the
pro forma OATT will continue to be subject to after-the-fact reporting and assignor’s original rate. As noted above, however,
determined on a cost-of-service basis posting, provided the transmission there will be no requirement for the transmission
unless the transmission provider can customer has a market-based rate tariff provider to create an auction for reassigned
demonstrate, on a case-specific basis, on file.494 In order to increase our transmission capacity similar to the pipeline
capacity reassignment program, since the
that it lacks market power. Nothing in oversight of reassigned capacity, we find underlying price caps are being removed for electric
this Final Rule affects the obligations of transmission capacity.
transmission providers to offer service 492 Our findings here address the particular 497 To the extent the assignee desires to change

under the pro forma OATT at cost-based circumstances associated with the electric utility its points of receipt or delivery, the limitations set
industry and are not intended to suggest that forth in section 23.2 shall apply.
rates. The only reform being adopted corresponding changes should be made to the rates 498 See Commonwealth Edison Co., 78 FERC ¶
concerns the resale of capacity by for capacity release by customers of natural gas 61,312 at 62,336 (1997); Boston Edison Co., 81
transmission customers. Given that transportation capacity. Any such changes would FERC ¶ 61,372 at 62,768 (1997); Southwestern
sroberts on PROD1PC70 with RULES

traditional regulation will continue to be considered only after notice and comment and Public Service Co., 80 FERC ¶ 61,245 at 61,905
based on a record applicable to the natural gas (1997). The non-rate terms and conditions of
govern the sale of primary capacity industry. reassigned service will therefore conform to the pro
under the pro forma OATT, we no 493 See Order No. 888 at 31,697.
forma OATT. As a result, there is no requirement
494 See Order No. 888 at 31,697 n.394; Order No. to file with the Commission service agreements for
491 Order No. 637–A at 31,595. 888–A at 30,224 n.151. reassigned transmission service.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00104 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12369

consistent with the electronic filing rates for secondary capacity as part of a maintain or report this information,
system used for Electric Quarterly regulatory scheme that provides Order No. 889 made clear that all OASIS
Reports so that it is readily accessible to safeguards to ensure that rates remain users, including the transmission
the Commission and the public.499 just and reasonable.502 The court provider, pay all of the fixed costs of
818. Taken together, these reforms to affirmed the Commission’s removal of OASIS-related activities in wholesale
the rules governing reassigned capacity price ceilings for short-term capacity rates and pay usage-related variable
will increase transparency and facilitate release shippers in the natural gas costs and fees.505
our monitoring of the secondary market market established in Order Nos. 637 822. With regard to confidentiality
for transmission capacity. We do not and 637–A, recognizing that non-cost concerns, the Commission finds that the
believe it is necessary to require a factors such as the need to lift price disclosure of reassigned capacity
market power analysis as a condition to ceilings to facilitate movement of information is necessary for the
exercising the right to reassign capacity into the hands of those who Commission and market participants to
transmission capacity. Although market value it most and the negotiated rates effectively monitor transactions for
power analyses are one method for only to the secondary market undue discrimination and preference.
ensuring that market-based rates remain distinguished the case from Farmers Consistent with our determination in
just and reasonable, they are not the Union.503 The same is true here, given Order No. 2001, where similar concerns
only method.500 To achieve the the non-cost factor advantages of lifting were raised regarding disclosure of
Commission’s original goals for capacity the price cap and the use of monitoring information, we believe that disclosure
reassignment expressed in Order No. and enforcement of remedies to mitigate will promote competition and make the
888, we adopt a more flexible approach the exercise of market power. market operate more efficiently.506
in this area and rely on posting 820. The Commission directs staff to Moreover, public reports will provide
requirements and other regulatory closely monitor the reassignment- customers with a certain level of price
controls to ensure that rates for related data submitted by transmission transparency to help them make
reassigned transmission capacity remain providers in their quarterly reports to informed decisions regarding the
just and reasonable. As noted above, we identify any problems in the relative value of capacity on a particular
find that a market power analysis is not development of the secondary market path.
required because transmission providers for transmission capacity and, in 823. We decline requests to require
continue to be obligated to satisfy particular, the potential exercise of implementation of electronic auctions
requests for service—whether out of market power. We direct staff to for reassigned capacity. While such
existing capacity or new facilities—at prepare, within six months of receipt of mechanisms are in place in RTO and
cost-based rates. Transmission capacity two years of quarterly reports, a report ISO markets, we conclude that it would
therefore cannot be withheld in an effort summarizing its findings. To inform our be too great a burden to impose
to exercise market power. Moreover, the analysis, we encourage market electronic auctions on other
posting and filing requirements adopted participants to provide feedback transmission providers simply to
herein provide the Commission the regarding the development of the facilitate capacity reassignments. The
necessary information to ensure that, secondary capacity market and, in continued use of OASIS, combined with
even if an entity sought to exercise particular, to contact the Commission’s the posting and service agreement
market power in the secondary market, Enforcement Hotline 504 with any requirements adopted here, should be
such an attempt could be effectively particular concerns as this market sufficient to facilitate more efficient use
detected. develops. of the grid and mitigate the exercise of
819. We therefore disagree with 821. Although several commenters market power.
commenters who assert that lifting the argue that additional posting and filing 824. With regard to the requests that
cap on reassignment contradicts judicial requirements could be too burdensome the Commission institute alternative
and Commission precedent. In Order and costly, the Commission does not specific timelines and other rules for the
No. 637–A, the Commission explained believe this burden will be great. All reassignment of capacity rights to
at length why Farmers Union 501 and capacity reassignments must be ensure efficient use of the grid, we will
other precedent did not prevent the conducted or otherwise posted on not revise the rules set forth in the pro
Commission from adopting negotiated OASIS and each assignee will be forma OATT. We do not have sufficient
required to submit an executed service evidence in this proceeding to suggest
499 The transmission provider should identify agreement for reassigned service. The that public utilities’ existing scheduling
capacity reassignments in the Contracts tab of the transmission provider thus will have timelines generally hinder customers
EQR using the Product Type Name ‘‘CAPACITY ready access to data necessary for the
REASSIGNMENT.’’ All terms must be fully from reselling unused transmission
described and rates provided. If no Product Name OASIS postings and electronic quarterly capacity or lead to capacity
adequately captures the nature of a given aspect of transaction reports. In any event, the withholding.
the capacity reassignment, the assignor may use the Commission’s access to this data is vital 825. With regard to requests for
Product Name ‘‘OTHER,’’ but that aspect must be to ensure effective monitoring and
fully described in the Rate Description field. If that network customers to reassign
description is over 150 characters, the transmission oversight and, thus, we find that any transmission capacity, we affirm our
provider may use multiple Contract Product lines burden on the transmission provider is finding in Order Nos. 888 and 888–A
to describe it. General instructions on how to file outweighed by the need for that capacity reassignments are
the EQR may be found at http://www.ferc.gov/docs- transparency. To the extent the
filing/eqr.asp. available only to point-to-point
500 See Alternatives to Traditional Cost-of-Service
transmission provider incurs costs to customers.507 Point-to-point service
Ratemaking for Natural Gas Pipelines and under the pro forma OATT clearly sets
502 Order No. 637–A at 31,558–72.
Regulation of Negotiated Transportation Services of forth defined capacity rights and is
Natural Gas Pipelines, 74 FERC ¶ 61,076 (1996). 503 InterstateNatural Gas Association of America
therefore reassignable. In comparison,
sroberts on PROD1PC70 with RULES

501 Farmers Union Central Exchange v. FERC, 734 v. FERC, 285 F.3d 18 (D.C. Cir. 2002).
F.2d 1486, 1501 (D.C. Cir. 1984) (Farmers Union) 504 Market participants may contact the
505 Order No. 889 at 31,625.
(finding that Commission failed to justify relaxation Commission’s Enforcement Hotline via telephone
506 SeeOrder No. 2001 at P 94–129.
of cost-based regulation of oil pipeline companies (202) 502–8390, toll-free 1–888–889–8030, fax (202)
because it did not ensure rates would remain within 208–0057, or at http://www.ferc.gov/cust-protect/ 507 Order No. 888 at 31,696; Order No. 888–A at

the zone of reasonableness). enforce-hot.asp. 30, 223.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00105 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12370 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

there are no specific capacity rights (1) Unreserved Use of Transmission compensate for the customer’s failure to
associated with network service and, Service schedule sufficient energy to serve its
thus, that service is not reassignable. Comments load and do not compensate the
Network service provides a network transmission provider for the use of the
828. Several commenters express transmission system. EEI asserts that
customer with a right to integrate its
general support for the Commission’s customers that use more transmission
designated resources with its designated
proposed clarification that unreserved service than they schedule should be
loads, in a generation pattern primarily use penalties apply to any circumstance
determined by the customer. As a result, required to pay for that transmission
where a transmission customer uses service just like any other user of the
it would be difficult to determine at any transmission service that it has not system.
moment in time exactly what portion of reserved.509 Several commenters 830. Duke opposes the Commission’s
network service could be resold, support the Commission’s proposed proposed clarification and suggests that
because the network customer does not clarification, but suggest that the an effective means of deterring and
have a discrete capacity reservation and transmission provider should only punishing unreserved use of
its usage of the transmission system assess unreserved use penalties when a transmission service is to charge the
varies as it attempts to most transmission customer repeatedly uses customer for the point-to-point service
economically use its resources to meet transmission service that it has not necessary to support the transaction
its loads. To the extent an entity elects reserved.510 For instance, PNM–TNMP and, additionally, to make the customer
network service, it does so with the believes penalty assessment should be subject to a civil penalty in cases of
understanding that the service is not optional and should be imposed on intentional or repeated unreserved use.
reassignable because there are no transmission customers that do not TDU Systems argue on reply that a
specific capacity rights to reassign. change their practices regarding transmission provider should not be
transmission use and OATT compliance allowed to charge unreserved use
5. ‘‘Operational’’ Penalties after being advised of their non- penalties unless it employs software
a. Unreserved Use Penalties compliance. technology designed to identify
829. Several commenters argue that unreserved use prior to operation.
NOPR Proposal transmission customers with special 831. Several commenters suggest
circumstances should not be subject to modifications to the manner by which
826. In the NOPR, the Commission
unreserved use penalties in the same transmission providers determine when
proposed to clarify that unreserved use manner as other transmission unreserved use penalties should be
penalties apply to any circumstance customers. For instance, Seattle believes assessed. TDU Systems believes
where a transmission customer uses unreserved use penalties can result in unreserved use penalties should only be
transmission service that it has not charges that are unjust and reasonable applied with prior Commission
reserved.508 Specifically, the for intermittent resources, such as wind approval after notice and opportunity
transmission customer would be subject generators, that can not precisely for hearing in order to limit the
to an unreserved use penalty in schedule power in future periods, but transmission provider’s discretion in
circumstances where the transmission are capable of controlling output. Seattle applying such penalties. To encourage
customer has a transmission service believes that unreserved use penalties regulatory certainty, Seattle suggests
reservation, but uses transmission should not apply if the transmission that the Commission implement tariff
service in excess of its reserved provider is able to operate the provisions that state a clear basis for
capacity. A transmission customer also transmission system reliably. Seattle application of unreserved use penalties.
would be subject to an unreserved use argues that an unreserved use penalty 832. Several commenters ask that the
penalty if the transmission customer should only apply if scheduling parties Commission delete the proposed
uses transmission service where it does have failed to respond to dispatchers’ language added to section 30.4 of the
not have a transmission service orders stating that system conditions proposed revised pro forma OATT
reservation. The Commission also necessitate curtailment of output. regarding the unreserved use of a
proposed that a transmission customer Southern disagrees with Seattle and network resource beyond its designated
would not be subject to an unreserved states that, as a general principle, capacity.511 In the event the
use penalty in circumstances where the unreserved use penalties should not be Commission elects to retain this
based on whether reliability is language, these commenters ask the
transmission customer inappropriately
threatened. TDU Systems recommend Commission to clarify the language to
uses a network service reservation to
that the Commission consider treating expressly permit use of the
support an off-system sale.
inadvertent use of point-to-point undesignated portion of a remote
827. The Commission sought transmission service in excess of network resource under secondary non-
comment on whether the current policy reservations by an entity serving native firm service (as a non-network resource)
that limits unreserved use penalties to load in multiple control areas as an and to preserve the customer’s right to
twice the standard rate for the entire energy imbalance in the control area in use the undesignated portion of the
service period has resulted in penalties which the energy imbalance occurs, resource for other purposes (e.g., to
that are not just and reasonable and, if rather than an unreserved use of point- serve its load on systems other than the
so, it sought further comment regarding to-point service. In their reply host transmission provider or to make
provisions that would yield unreserved comments, EEI and PNM–TNMP off-system sales). In its reply comments,
use penalties that are just and disagree with TDU Systems. EEI argues Duke notes that the fact that a generator
reasonable. that energy imbalance charges is designated as a network resource for
compensate generators for the a network load on one system does not
sroberts on PROD1PC70 with RULES

508 In the NOPR, we referred to an unreserved use additional expense they incur to prohibit a network load on a second
penalty as an ‘‘unauthorized use penalty.’’ For the system from obtaining non-firm energy
purpose of the Final Rule, we adopt the term 509 E.g., APPA and Bonneville.
‘‘unreserved use penalty’’ as it more clearly 510 E.g., MidAmerican, Southern, and PNM– 511 E.g., APPA, TAPS, TDU Systems, and EEI

articulates the nature of the penalty. TNMP. Reply.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00106 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12371

from that same generator using point-to- pro forma OATT and will assist the assessed in a relatively straightforward
point and secondary network resource. Commission in its enforcement of the manner in most cases. As a result, there
Duke points out that the proposed OATT obligations. The unreserved use will typically be little need for the
revised section 30.4 prohibits a network penalty itself will help discourage Commission to become involved. That
customer from using its firm network disorderly use of transmission service. said, a transmission customer can
service to schedule power in excess of Charging a transmission customer for always file a complaint with the
the DNR amount. Finally, TAPS asks the just the unreserved transmission service Commission protesting an unreserved
Commission to modify the language used, as suggested by Duke, would not use penalty.
added to section 30.4 so that its terms provide a sufficient incentive to procure 837. We will not exempt any class of
are consistent with the terms used in the adequate transmission service, even transmission customer from the
rest of the pro forma OATT. with the threat of possible civil potential assessment of unreserved use
833. EEI recommends that a customer penalties. In addition, an operational penalties. We do not agree with Seattle’s
that takes unreserved transmission penalty rather than a civil penalty is a assertion that unreserved use penalties
service, but that does not have a service more appropriate default remedy, even can result in charges that are unjust and
agreement with the transmission though certain circumstances may reasonable for intermittent resources,
provider, be deemed to have consented warrant a civil penalty in addition to an such as wind generators, that can not
to the transmission provider’s filing of operational penalty. In most instances, precisely schedule power in future
a service agreement, so that the an unreserved use penalty can be periods. Unreserved use penalties are
transmission provider has a basis for applied in a relatively mechanical based on the transmission capacity
imposing both the prevailing OATT rate manner. As a result, an operational reserved rather than the transmission
and the penalty charge on the customer. penalty has a relatively low service scheduled, so an intermittent
EEI also recommends that the administrative burden and still provides resource’s inability to precisely
Commission clarify that a customer that a clear signal to transmission customers schedule power in future periods is
uses more transmission service than it regarding the cost of non-compliance.513 irrelevant, as long as the resource has
has reserved also is subject to charges We do not agree with TDU Systems’ reserved sufficient transmission
for ancillary services. proposal that a transmission provider be capacity to deliver the resource’s full
required to employ software designed to output. We also do not agree with TDU
Commission Determination
identify unreserved use if the Systems’ suggestion that unreserved use
834. The Commission adopts the of transmission service by an entity
transmission provider wants to charge
NOPR proposal that a transmission serving native load in multiple control
unreserved use penalties. As we explain
customer will be subject to unreserved areas should be treated as an energy
below, we adopt reforms in this Final
use penalties in any circumstance where imbalance in the control area in which
the transmission customer uses Rule that will reduce the level of
unreserved use penalties for instances of the energy imbalance occurs, rather than
transmission service that it has not an unreserved use of point-to-point
reserved. Specifically, a transmission inadvertent unreserved use. For
instance, we reduce the period over service. In this regard, we agree with EEI
customer will be subject to an that energy imbalance charges
unreserved use penalty in which a one-time inadvertent use will
be penalized from one month to one compensate the transmission provider
circumstances where a transmission for the additional expense it incurs to
customer has a transmission service day. We believe that this and other
compensate for a transmission
reservation, but uses transmission reforms are sufficient to address TDU
customer’s failure to schedule sufficient
service in excess of its reserved Systems’ concerns.
energy to serve its load and do not
capacity. A transmission customer also 836. We will not adopt Seattle’s
compensate the transmission provider
will be subject to an unreserved use suggestion to add provisions to the pro
for the use of the transmission system.
penalty if the transmission customer forma OATT that specify all 838. We will not limit unreserved use
uses transmission service where it does circumstances that constitute use of penalties to instances where the
not have a transmission service transmission service without a unreserved use jeopardizes the reliable
reservation, including the situations transmission service reservation. Any operation of the transmission system.
described in the Arizona Public Service list of transmission customer actions Unreserved use penalties are intended,
Company (APS) audit report.512 We note that would be deemed to constitute use in part, to give transmission customers
that the transmission provider is subject of transmission service without a an incentive to reserve and pay for the
to the same penalties when it takes transmission service reservation will appropriate level of transmission service
transmission service under its OATT. necessarily be incomplete and out-of- so that transmission service is allocated
835. Our decision to clarify the date given the dynamic manner by in an orderly fashion. A transmission
application of unreserved use penalties which trading patterns and practices customer that uses unreserved
will eliminate a potential source of evolve. We believe that Commission transmission service requires the
discretion in the implementation of the actions, such as in APS, will provide a transmission provider to take some
sufficient guide to circumstances that action to accommodate the additional
512 Arizona Public Service Co., 109 FERC ¶ 61,271 constitute use of transmission system use of the system. Some penalty is
at P 6 (2004) (APS). APS contained two findings without a transmission service warranted even in those instances when
that Commission audit staff characterized as reservation. We also reject TDU
unauthorized use of transmission service. In the the transmission provider’s
first finding, APS’s wholesale merchant function Systems’ suggestion that unreserved use accommodations are sufficient to avoid
did not request and pay for point-to-point service penalties be applied only after curtailment of transmission service to
to support some of the off-system power sales it Commission approval. As mentioned
made at trading hubs where APS system resources
other transmission customers. Absent a
were directly connected. In the second finding, APS
above, an unreserved use penalty can be penalty in all instances, transmission
sroberts on PROD1PC70 with RULES

incorrectly treated the Phoenix Valley 230kV customers would have an increased
system as a single node on its transmission system. 513 The unreserved use penalties thus work in
incentive to under-reserve transmission
As a result, off-system sales made by generators conjunction with imbalance penalties described in
connected to the Phoenix Valley system should section V.C.2 of this Final Rule to reduce incentives
service, which would lead to an
have been, but were not, supported by point-to- to take actions that impair the reliability of the increase in the likelihood that system
point service. transmission system. reliability would be impaired. In

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00107 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12372 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

addition, a transmission customer that point service. In addition, we clarify provider that inappropriately uses
uses more transmission service than it that a customer that uses more network transmission service to support
has reserved, even in periods when transmission service than it has reserved off-system sales potentially uses or
system reliability has not been is also subject to charges for ancillary acquires transmission service that
impaired, has nonetheless disturbed the services. The ancillary service charges should be allocated to other
orderly allocation of transmission will be based on just the period of transmission customers. In addition, the
service. unreserved use. For instance, if a network customer or transmission
839. In response to comments transmission customer has unreserved provider has not paid for transmission
requesting that we remove the language use during two hours on the same day, service as required. Therefore, we
added to section 30.4 of the proposed the customer must pay the ancillary conclude that a network customer or
revised pro forma OATT regarding the service charges for those two hours, transmission provider inappropriately
unreserved use of a network resource rather than for the entire day. This using network transmission service to
beyond its designated capacity, we modification is appropriate, as the support off-system sales should be
clarify our intent in modifying section transmission provider is entitled to subject to unreserved use penalties. We
30.4. The Commission has identified compensation for the ancillary services will evaluate the appropriateness of
instances when a transmission provider it provides when it provides civil penalties in addition to unreserved
has scheduled delivery of off-system transmission service. We also will use penalties on a case-by-case basis
non-designated short-term purchases modify section 3 of the pro forma OATT and will not exempt, as a matter of
using transmission capacity reserved for to reflect this rule. general policy, inadvertent use of
designated network resources.514 The network service by an LSE when it
intent of the language added to section (2) Treatment of Inappropriate Use of serves its own native load on a
30.4 of the pro forma OATT was to Network Service as an Unreserved Use neighboring system as suggested by
clarify that network customers are of Point-to-Point Transmission Service TDU Systems. A network customer or
subject to unreserved use penalties Comments transmission provider that
when they schedule delivery of off- inappropriately uses network
841. A few commenters argue that a transmission service to support off-
system non-designated purchases using transmission customer that
transmission capacity reserved for system sales also may be required to
inappropriately uses a network service disgorge unjust profits from such sales,
designated network resources. We reservation to support an off-system sale
clarify, however, that a network as the Commission may determine on a
should be subject to unreserved use case-by-case basis.
customer may use the undesignated penalties.517 Other commenters request
portion of a remote network resource to clarification or modifications to the (3) Penalty Rate for Unreserved Use of
serve network load using secondary Commission’s proposal regarding the Transmission Service
network service and may use the treatment of transmission customers
undesignated portion of the resource for Comments
that inappropriately use a network
other non-network service purposes, service reservation to support an off- 843. Transmission providers generally
such as third-party sales, as long as the system sale. TAPS asks the Commission assert that the Commission’s current
network customer acquires the to clarify that a transmission provider policy of limiting unreserved use
appropriate point-to-point transmission penalties to twice the standard rate for
that inappropriately uses network
service. Moreover, because a the entire service period has yielded just
service to support an off-system sale is
transmission provider does not have to and reasonable rates.518 EEI contends
required to pay for point-to-point
‘‘take service’’ under its own OATT for that if the customer is required to pay
service to support the off-system sale
the transmission of power that is an unreserved use charge only for the
and potentially is liable for civil
purchased on behalf of bundled retail period of unreserved use, the customer
penalties, as the Commission proposed
customers, it is free to use the would have an incentive to reserve
in the NOPR. Suez Energy NA suggests
undesignated portion of a remote service for less than its maximum
that an affiliate of the transmission
network resource to serve its bundled expected use and simply pay
provider that violates network tariff
retail customers.515 If the transmission unreserved use charges in the hours in
provisions by making unauthorized
provider desires to use a remote which it exceeds that usage. EEI
sales should also disgorge unjust profits concedes, however, that the maximum
network resource for non-native load from such sales. TDU Systems urges the
purposes, such as third-party sales, it period for which the unreserved use
Commission not to impose civil charge should be assessed is one month.
must acquire the appropriate point-to- penalties for inadvertent use of network
point transmission service.516 For example, EEI acknowledges that it
service by an LSE when it serves its own would be unreasonable to charge a
840. In order to ensure that the native load on a neighboring system.
transmission provider has a basis for customer that takes yearly service a
charging an unreserved use penalty, we Commission Determination penalty for an entire year because of, for
modify section 13.4 of the pro forma instance, a single hour of unreserved
842. The Commission declines to
OATT to provide that a customer that use. In addition, EEI suggests several
adopt the NOPR proposal to exempt a
takes unreserved point-to-point modifications to the current unreserved
network customer or transmission use penalty policy. EEI suggests the
transmission service and does not have provider that inappropriately uses
a service agreement with the Commission include, in the pro forma
network transmission service to support OATT, provisions stating that the
transmission provider is deemed to have off-system sales from unreserved use
executed the transmission provider’s penalty charge for unreserved use of
penalties. As mentioned above, one of transmission service is equal to twice
form of service agreement for point-to- the purposes of unreserved use the standard rate for transmission
sroberts on PROD1PC70 with RULES

514 See MidAmerican Energy Co., 112 FERC


penalties is to encourage orderly use service. EEI recommends that the
¶ 61,346 (2005); PacifiCorp, 118 FERC ¶ 61,026
and acquisition of transmission service. Commission establish a policy that a
(2007). A network customer or transmission
515 See Order No. 888–A at 30,216–17. 518 E.g., EEI, Bonneville, MidAmerican, Nevada
516 See id. at 30,217. 517 E.g., APPA and PNM–TNMP. Companies, and PNM–TNMP Reply.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00108 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12373

customer that uses transmission service be consistent with this Final Rule. a reasonable incentive to ensure that
without a reservation must pay a Penalty charges must be based on the transmission customers reserve the
penalty equal to twice the rate for period of unreserved use rather than the appropriate level of transmission service
transmission service for the greater of period for which service is reserved, without unduly charging a transmission
the period of unreserved use or one subject to the following principles. First, customer for inadvertent unreserved
month. the unreserved use penalty for a single use. In addition, transmission customers
844. Transmission customers hour of unreserved use will be based on will continue to be subject to civil
generally assert that unreserved use the rate for daily firm point-to-point penalties on a case-by-case basis, so
penalties should be limited to twice the service, even if the transmission attempts to game this penalty regime
standard rate for the period of provider has a rate for hourly firm could result in additional penalties
unreserved use.519 Transmission point-to-point transmission service on depending on the specific facts at issue.
customers who take this position argue file. Second, as a general rule, more than We reject the suggestion in some
that using the service period rather than one assessment for a given duration comments that the transmission
the period of unreserved use as the basis (e.g., daily) will increase the penalty provider should only assess unreserved
for the penalty charge discriminates period to the next longest duration (e.g., use penalties where a transmission
against transmission customers with weekly). The unreserved penalty charge customer repeatedly uses transmission
longer term transmission service for multiple instances of unreserved use service that it has not reserved. Rather,
reservations.520 For instance, AWEA (i.e., more than one hour) within a day we find that penalties are appropriate
believes that applying an unreserved will be based on the rate for daily firm for all unreserved uses of the system.
use penalty based on the reservation point-to-point service. The unreserved Because we are allowing penalties to be
period rather than the period of penalty charge for multiple instances of based on the period of unreserved use,
unreserved use has resulted in charges unreserved use isolated to one calendar not the reservation period, such
that are not just and reasonable. AWEA week would result in a penalty based on penalties do not unduly charge a
asserts that such a policy would also be the charge for weekly firm point-to- transmission customer for inadvertent
discriminatory because, if the customer point. The unreserved use penalty unreserved use. This penalty regime
causing the unreserved use had made a charge for multiple instances of will apply to all instances where a
shorter reservation, its penalty would be unreserved use during more than one transmission customer has an
much lower. TDU Systems argue in its week during a calendar month will be unreserved use of transmission service,
reply comments that there is little to be based on the charge for monthly firm regardless of whether the transmission
gained from charging inadvertent point-to-point.522 customer had an existing relevant
unreserved use more than twice the 847. Our determination is based, in transmission service reservation but for
standard rate for the period of part, on agreement with those a lesser amount of service.
unreserved use. commenters arguing that using the 848. A transmission provider that
845. Several commenters suggest that period for which a transmission wants to charge unreserved use
unreserved use penalty charges greater customer has reserved service rather penalties must explicitly state the
than twice the standard rate for the than the period of unreserved use as the penalty rate in its tariff. The
entire service period should be limited basis for the penalty charge Commission retains the current policy
to instances of intentional unreserved discriminates against transmission established in Allegheny that the
use.521 Nevada Companies note that customers with longer term unreserved use penalty rate may not be
transmission service reservations. We greater than twice the firm point-to-
there are some marketing entities that
are mindful, however, that basing point rate for the period of unreserved
are consistently abusing the current
unreserved use penalties on only the use, as defined above.523 We continue to
policy and recommends that the
period of unreserved use could give the believe that penalties up to twice the
Commission consider more severe
transmission customer an incentive to relevant firm point-to-point rate are just
penalties for continuous carelessness in
reserve service for less than its and reasonable, given the new
tagging or a repeated pattern of
maximum expected use and simply pay definition for the penalty period. As a
unreserved use of the transmission
unreserved use charges in the hours in result, we establish a rebuttable
system. Southern believes the
which it exceeds that usage. We believe presumption that unreserved use
transmission provider should be
the unreserved penalty regime we penalties no greater than twice the firm
permitted to charge increased
articulate in this Final Rule will provide point-to-point rate for the penalty
unreserved use penalties if a
period defined above are just and
transmission customer consistently uses 522 There are a number of possible permutations
reasonable. As we discuss above, the
transmission services it has not of these principles. For instance, a transmission transmission customer must face a
reserved. TDU Systems disagree on customer that has 25 MW of unreserved use in two
hours on one day during the first week of the month penalty in excess of the firm point-to-
reply comments, arguing that a penalty
and 50 MW of unreserved use in two hours on one point transmission service charge it
equal to twice the applicable charge is day during the last week of the month will pay an avoids through unreserved use of
sufficient to deter unreserved use of unreserved use penalty based on the rate for 25 MW transmission service or the transmission
transmission service. of daily firm point-to-point service and 50 MW of
daily firm point-to-point service. A transmission customer will have no incentive to
Commission Determination customer that has 25 MW of unreserved use on two reserve the appropriate amount of
846. We will continue giving
separate days during the first week of the month service.
and 50 MW of unreserved use in two hours on one 849. The Commission thus concludes
transmission providers discretion in day during the last week of the month will pay an
that a penalty of twice the standard rate
setting their unreserved use penalty unreserved use penalty based on the rate for 25 MW
of weekly firm point-to-point service and 50 MW is not excessively punitive, particularly
rates, although those rates will need to
of daily firm point-to-point service. A transmission given the definition of the penalty
sroberts on PROD1PC70 with RULES

customer that has 25 MW of unreserved use on two period established in this Final Rule.
519 E.g., APPA, AWEA, TAPS, and TDU Systems. separate days during the first week of the month
520 E.g., APPA, AWEA, TAPS, and TDU Systems and 50 MW of unreserved use on two separate days Without evidence to the contrary, we
Reply. during the last week of the month will pay an
521 E.g., NRECA, Nevada Companies, and unreserved use penalty on 50 MWs of monthly firm 523 Allegheny Power System, Inc., 80 FERC

Southern. point-to-point service. ¶ 61,143 at 61,545–46 (1997) (Allegheny).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00109 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12374 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

believe an unreserved use penalty equal Comments financial consequence. Southern asserts
to twice the applicable rate should 851. Transmission customers along that penalties paid by an affiliate do, in
create the appropriate incentive to with several other commenters support fact, represent a real cost to the
transmission customers to purchase the the Commission’s proposal to distribute wholesale business of that affiliated
correct amount of transmission service. operational penalties paid by the entity. In its reply comments, TDU
Nonetheless, we will allow transmission transmission provider’s merchant Systems disagrees with comments that
providers to make a filing under section function to non-offending, unaffiliated suggest that non-offending affiliates
205 of the FPA to propose an transmission customers.525 Entegra and should be allowed to receive a load ratio
unreserved use penalty in excess of Morgan Stanley advocate extending the share of penalty revenues when a
twice the relevant firm point-to-point proposal so that the transmission transmission provider or one of its
rate for pervasive unreserved use. affiliates incurs an operational penalty.
provider distributes operational
Transmission providers that propose TDU Systems argue that allowing any
penalties paid by all transmission
such a rate must establish that a higher member of the corporate family to retain
customers to non-offending unaffiliated
penalty rate is required to combat any portion of the penalty revenues
transmission customers. Entegra also
pervasive unreserved use of incurred by another member of the
notes that the Commission’s policy in
transmission. In arguing for such a corporate family will dilute the
the natural gas setting is that pipelines
higher penalty rate, the transmission incentive inherent in the Commission’s
must credit all penalty revenues back to
provider must address why the standard proposal.
non-offending shippers. Entegra argues 854. Seattle suggests that compliance
penalty rate that penalizes repeated that the precedent the Commission cited
unreserved use is not adequate to monitoring and enforcement to ensure
in proposing that operational penalties that the transmission provider
discourage repeated instances of paid by the transmission provider be appropriately assesses penalties to its
unreserved use of transmission service. distributed to non-offending, affiliates will be as important as
b. Distribution of Operational Penalties unaffiliated transmission customers correctly accounting for and distributing
applies equally to penalties paid by the revenues from penalties collected
NOPR Proposal affiliated and unaffiliated transmission from affiliates.
customers.526 855. Most commenters were
850. In the NOPR, the Commission 852. With regard to unreserved use
proposed to have the transmission supportive of the Commission’s
penalties, NRECA and TDU Systems proposal to have transmission providers
provider distribute to non-offending, argue that the Commission should
unaffiliated transmission customers notify the Commission of the amounts
encourage transmission providers to of all operational penalties they
operational penalties incurred by the supervise inadvertent unreserved use incurred during the year through either
transmission provider’s merchant and notify the customer of such an annual compliance filing or a one-
function or its affiliates.524 For those occurrence rather than rely on large time filing.528 Several commenters
transmission providers subject to unreserved use penalties. They argue it expressed a preference for a one-time
operational penalties, the Commission is better to prevent unnecessary costs filing by transmission providers.529 For
proposed to require the transmission than to approve post hoc penalties for instance, Ameren states that it prefers
provider to make an annual compliance unintentional unreserved use that could the use of a one-time filing to propose
filing to notify the Commission of the have been prevented. a mechanism through which the
amounts of such operational penalties 853. A number of transmission transmission provider would identify
incurred during the year and to propose providers oppose the portion of the non-offending, unaffiliated transmission
a method to identify non-offending, Commission’s proposal that would customers and a method by which the
unaffiliated transmission customers to prohibit their non-offending affiliates transmission provider would distribute
which the transmission provider would from receiving a portion of the the operational penalties it or its
distribute penalty amounts. In addition, operational penalties the transmission affiliates have incurred to the identified
the Commission also proposed to allow provider incurs.527 For instance, PNM– transmission customers. Ameren
a transmission provider to avoid an TNMP asserts that the Commission believes this would be less burdensome
annual compliance filing by making a should allow the transmission than an annual repeated compliance
one-time filing to propose a mechanism provider’s non-offending affiliates, filing. TDU Systems, on the other hand,
through which it would identify non- which are abiding by the same rules as prefer the Commission’s proposal to
offending, unaffiliated transmission other transmission customers in require an annual reporting of penalties
customers and a method by which it accordance with Standards of Conduct, levied and penalty revenues credited in
would distribute the operational to be eligible to receive a portion of the order to foster greater transparency on
penalties it or its affiliates have incurred operational penalties the transmission this matter. TDU Systems believe greater
to the identified transmission provider incurs. In the specific case of transparency through improved
customers. Finally, the Commission unreserved use penalties, Southern does reporting requirements would provide
proposed to prohibit transmission not support distributing penalties greater opportunities for detecting
providers from recovering for imposed on a transmission provider’s abuses by transmission providers or
ratemaking purposes or through any affiliate to other OATT customers. their affiliates, either in imposing
service or facility under the Southern argues that such a proposal is inappropriate penalties on transmission
Commission’s jurisdiction any cost it predicated upon the false assumption customers or in failing to penalize their
incurs when it or an affiliate pays an that such penalties are not of true own or their affiliates’ transgressions. In
operational penalty.
addition, TDU Systems suggest that this
525 E.g., APPA, ELCON, Entegra, TAPS, TDU
reporting requirement should include
sroberts on PROD1PC70 with RULES

524 An operational penalty explicitly defines the Systems, Sacramento, and Seattle.
charge associated with a set of pre-defined activities 526 Entegra cites Carolina Power & Light Co. and details on the amount of penalties
(e.g., unreserved use of transmission service, Florida Power Corp., 103 FERC 61,209 at P 24
completing request studies outside of the 60-day (2003) (Carolina Power & Light). 528 E.g., EEI, Suez Energy NA, Sacramento, TAPS,

due diligence deadline) that are not in compliance 527 E.g., EEI, MidAmerican, Nevada Companies, and Wisconsin Electric.
with specific provisions of the OATT. and PNM–TNMP. 529 E.g., Ameren and PNM–TNMP.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00110 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12375

levied, whether on customers or the providers to be required to distribute all penalty, while the transmission
transmission provider or its affiliates, unreserved use penalties they collect, provider distributes the revenues to
for all violations. With regard to the whether from the transmission non-offending transmission customers.
annual reporting requirements (for those provider’s merchant function or other 861. The Commission requires the
companies that do not propose a transmission customers. The penalties transmission provider to make an
standard mechanism to handle the the transmission provider pays for late annual compliance filing and to propose
distribution of penalties), Nevada studies are penalties that, by their in that filing a mechanism through
Companies suggest that a standard nature, are fully distributed only to non- which it will identify non-offending,
template be proposed so that all affiliated transmission customers. transmission customers and a method
companies are following the same Requiring the transmission provider to by which it will distribute the
reporting format. distribute the unreserved use penalty unreserved use penalties revenue it
856. Several commenters make charges that its merchant function receives to the identified transmission
recommendations that they argue will incurs will ensure that the transmission customers. This rule is consistent with
ease the administrative burden of provider faces a meaningful financial our determination regarding the
distributing operational penalties paid consequence when its merchant distribution of imbalance penalties. The
by the transmission provider to non- function incurs an operational penalty. transmission provider must also
offending, unaffiliated transmission Extending the NOPR proposal to all indicate in its compliance filing how it
customers. MidAmerican suggests that unreserved use penalty revenues the will distribute late study penalties to
excluding short-term firm and non-firm transmission provider collects unaffiliated transmission customers. In
transactions from the distribution maintains the incentive structure of the addition, the transmission provider is
methodology would avoid the need to unreserved use penalty and prevents the required to make an annual filing with
develop a costly and administratively transmission provider from retaining the Commission, described further
difficult program. TVA suggests that the revenues above those it should below, that provides information
amount of any such operational reasonably be allowed to earn.530 This regarding the penalty revenue the
penalties should simply be a credit determination is consistent with the transmission provider has received and
against the transmission provider’s Final Rule for imbalance penalties and distributed. We will not allow the
transmission revenue requirement, the Commission’s decision in Order transmission provider to make an
thereby more efficiently reducing the Nos. 637 and 637–A.531 annual filing to propose a distribution
cost of transmission service to 860. We agree with those commenters method for unreserved use and late
transmission customers. that suggest that non-offending affiliates study penalties, as proposed in the
857. Several commenters argue that of the transmission provider, including NOPR. We agree with Ameren that
the transmission provider must be made the transmission provider’s native load restricting the transmission provider to
whole before it distributes any penalty customers, should be eligible to receive proposing a distribution method
revenues. For instance, EEI supports the a portion of the unreserved use through the transmission provider’s
Commission’s proposal to the extent penalties that the transmission provider compliance filing will reduce the
penalty revenues exceed the cost of collects. Unreserved use penalties are administrative burden of distributing
transmission service. Nevada assessed against transmission customers operational penalties. We believe that
Companies assert that it is the and should, therefore, be distributed to we can accomplish the goals underlying
transmission provider’s native load that all non-offending transmission a mandatory annual filing to propose a
incurs the cost of correcting for the customers, whether affiliated with the distribution method—to detect
offending customer’s intentional transmission provider or not. Given the inappropriate penalties and failure to
deviation from schedule or for a distribution of unreserved penalties penalize the transmission provider’s
transmission customer’s self-provided articulated above, the transmission affiliates—by requiring an annual
reserves being unavailable. Therefore, provider’s corporate profit is reduced if informational filing. As suggested by
Nevada Companies contend that any one of the transmission provider’s Seattle, compliance monitoring and
penalties should be returned to the wholly-owned marketing affiliates pays enforcement by Commission staff will
native load to offset its cost of an operational penalty to the provide a measure of assurance that the
generation. transmission provider. This is so transmission provider appropriately
858. Sacramento and WPS because the corporate shareholders assesses penalties.
Companies’ reply comments support the ultimately pay the marketing affiliate’s 862. All point-to-point and network
Commission’s proposal to prohibit a transmission customers, including the
transmission provider from recovering 530 As we explain further below, the transmission transmission provider’s native load, will
any cost it incurs when it or an affiliate provider will be allowed to retain the base firm be eligible to receive a portion of the
point-to-point transmission service charge when it
pays an operational penalty through assesses an unreserved use penalty.
penalty revenues distributed by the
jurisdictional rates or services. 531 Regulation of Short-Term Natural Gas transmission provider. As a result, we
Transportation Services, and Regulation of will not adopt MidAmerican’s proposal
Commission Determination Interstate Natural Gas Transportation Services, that we exclude short-term firm and
859. The Commission agrees with Order No. 637, 65 FR 10156 (Feb. 25, 2000), FERC non-firm transmission customers to
Stats. & Regs. ¶ 31,091 at 31,309 (2000) (‘‘* * *to
those commenters recommending that effectively shift pipelines to the use of the non- reduce the burden to the transmission
we broaden the NOPR proposal, which penalty mechanisms described above to solve and provider. Given the steps we have taken
required transmission providers to prevent operational problems, it will be necessary to manage the transmission provider’s
distribute to non-offending, unaffiliated to eliminate the pipelines’ financial incentive to burden of distributing penalty revenues,
impose penalties and OFOs. Thus, the Commission
transmission customers only the is requiring pipelines to credit the revenues from
we believe it more equitable to allow all
unreserved use penalties the penalties and OFOs to shippers.’’); order on reh’g, transmission customers subject to
sroberts on PROD1PC70 with RULES

transmission provider’s merchant Order No. 637–A, 65 FR 35706 (Jun. 5, 2000), FERC operational penalties to be eligible to
function incurs. Consistent with our Stats. & Regs. ¶ 31,099 at 31,609 (2000) (‘‘The goal receive a portion of the distributed
of the Commission’s new policy on penalties is to
conclusion regarding imbalance encourage pipelines to rely less on penalties and
penalty revenues. In response to TVA’s
penalties, we conclude that it would be more on non-penalty mechanisms to manage their suggestion that the amount of any such
more appropriate for transmission systems* * *.’’). operational penalties be credited against

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00111 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12376 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

the transmission provider’s to operational penalties in section V.C.4 RTOs are subject to civil penalties in
transmission revenue requirement, we (Operational Penalties) of the NOPR. For section 0 of this Final Rule.
note that the transmission provider is the most part, the discussion in that 869. We do not agree with those
free to propose this mechanism, with section of the final rule addressed how arguing that a non-profit transmission
assurances that offending customers a transmission provider should provider should be exempt from the
will not benefit, and we will decide the distribute operational penalties it incurs requirement to distribute unreserved
appropriateness of the proposal on a when it takes transmission service use penalties it pays when taking
case-by-case basis. under its own tariff. In the section V.D.5 service under its own tariff. To the
863. We agree with those commenters (Acquisition of Transmission Service) of extent that a not-for-profit transmission
that assert that the transmission the NOPR, the Commission separately provider incurs an operational penalty
provider must be made whole before it addressed whether RTOs should pay as a result of its activities as a
distributes any penalty revenues. With operational penalties for failure to transmission customer, it is still
regard to unreserved use penalties, we complete request studies on a timely required to distribute penalties to non-
will allow the transmission provider to basis. offending customers. A non-profit
retain the base firm point-to-point transmission provider would only incur
transmission service charge, but require Comments
an operational penalty as the result of
it to distribute any revenue collected 867. Several RTOs and RTO members its wholesale marketing operations. As
above the base firm point-to-point asked that the Commission clarify that such, a non-profit transmission provider
transmission service charge. For RTOs are not subject to any operational would pay for any operational penalty
instance, if a transmission customer has penalties.532 Entergy opposes the it incurs by using the profit it has
unreserved use that results in a penalty Commission’s proposal to assess earned through its wholesale marketing
equal to twice the rate for firm weekly operational penalties against non-RTO operations.
point-to-point service, then the transmission providers, but not RTOs.
transmission provider can retain an However, if the Commission maintains 6. ‘‘Higher of’’ Pricing Policy
amount equal to the rate for firm weekly this distinction, Entergy asks that it 870. As noted in the NOPR, the
point-to-point transmissions service. A clarify that independent entities—such Commission is concerned that some
transmission provider will be required as Entergy’s Independent Coordinator of transmission providers may not be
to distribute the entire amount it pays Transmission—and the transmission applying our existing pricing policies
for completing service request studies providers that allow independent consistently and, as a result, customers
on an untimely basis. entities to process transmission service may be quoted prices that are not
864. We will not require transmission requests will have the same protection consistent with the ‘‘higher of’’
providers that make an annual from operational penalties as RTOs. PGP policy.533 The practice of quoting
compliance filing to use a standard argues that, in the case of non-profit customers an incremental rate as a lump
template, as suggested by Nevada transmission providers, requiring the sum payment is inconsistent with our
Companies. Transmission providers are transmission provider to pay ‘‘non- ratemaking policy and has the potential
in the best position to determine the offending’’ customers when the provider to discourage customers from
least burdensome way to present the incurs operational penalties is self- proceeding with service requests.534
information required. We will provide defeating, because there is no one other Under the Commission’s ‘‘higher of’’
guidance, however, on the information than the customers to bear the cost of pricing policy, when the requested
that transmission providers must the penalty. PGP cites Bonneville as an transmission service requires network
provide in their annual informational example and notes that Bonneville must upgrades, the transmission provider
filings. Transmission providers must recover all costs from its customers. should calculate a monthly incremental
provide: (1) A summary of penalty cost transmission rate using the revenue
revenue credits by transmission Commission Determination
requirement associated with the
customer, (2) total penalty revenues 868. This section of the Final Rule required upgrades and compare this to
collected from affiliates, (3) total penalty primarily addresses how transmission the monthly embedded cost
revenues collected from non-affiliates, providers should distribute operational transmission rate, including the
(4) a description of the costs incurred as penalties they incur when taking expansion costs.535 This incremental
a result of the offending behavior, and transmission service under their own rate should be established by amortizing
(5) a summary of the portion of the tariff. RTOs and independent the cost of the upgrades over the life of
unreserved penalty revenue retained by transmission coordinators do not take the contract.536
the transmission provider. transmission service, so most of the
865. Transmission providers are discussion in this section of the Final 533 In Order No. 888, the Commission stated that
prohibited from recovering for Rule is simply not applicable to either system expansions should be priced at the higher
ratemaking purposes or through any RTOs or independent transmission of the embedded cost rate (including the expansion
service under the Commission’s costs) or the incremental cost rate, consistent with
coordinators. RTOs and independent the Transmission Pricing Policy Statement. See
jurisdiction any amount it or an affiliate transmission coordinators are bound Inquiry Concerning the Commission’s Pricing Policy
pays as an operational penalty. This will however by the requirement to for Transmission Services Provided by Public
ensure that the transmission provider distribute revenues they receive when Utilities Under the Federal Power Act, Policy
faces a true financial consequence when Statement, 59 FR 55031 at 55037 (Nov. 3, 1994),
they assess operational penalties. We FERC Stats. & Regs. ¶ 31,005 at 31,146 (1994), order
it or an affiliate incurs an operational address whether RTOs or independent on reconsideration, 71 FERC ¶ 61,195 (1995)
penalty. transmission coordinators are subject to (Transmission Pricing Policy Statement).
c. Applicability of Operational Penalties operational penalties due to processing 534 Southwest Power Pool, Inc., 100 FERC

transmission service request studies on ¶ 61,096 (2002) (designing a rate to include a


Proposal to RTOs and Other
sroberts on PROD1PC70 with RULES

balloon payment is not a substitute for a properly


Independent or Non-Profit Entities an untimely basis in section V.C.5.a of designed rate).
this Final Rule. We address whether 535 Southwest Power Pool, Inc., 112 FERC
866. The Commission did not address ¶ 61,319 at P 33 (2005).
the degree to which RTOs and other 532 E.g., ISO New England, PJM, MISO, SPP, and 536 See Southwest Power Pool, Inc., 98 FERC

independent entities would be subject Ameren. ¶ 61,256 at 62,026, reh’g denied in pertinent part,

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00112 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12377

NOPR Proposal 875. Some commenters ask the 878. Great Northern requests that the
Commission to further clarify, or Commission clarify that a transmission
871. As a result of the Commission’s
establish additional requirements, customer may adjust the term of its
concerns regarding application of the
regarding incremental rates. Entegra requested transmission service contract
‘‘higher of’’ pricing policy, the
states that the incremental rate should to provide a longer period for
Commission sought comments in the amortizing the cost of necessary system
be stated as both a monthly unit rate
NOPR on whether changes to the pro upgrades once the incremental cost of
and a lump sum representing the net
forma OATT are necessary to ensure expansion is disclosed by the
present value of the upgrade costs with
that incremental cost transmission rates transmission provider, as the
all inputs and assumptions in the
are presented as monthly rates for Commission seems to suggest in the
calculation disclosed. Entegra further
service. NOPR.539 In contrast, Allegheny states
contends that the customer should be
Comments allowed to choose between paying the that the amortization period for the cost
incremental rate, the lump sum, or some of an upgrade should not exceed the
872. Several commenters agree that requested term of the contract, even if
combination of the two (e.g., to pay an
incremental cost rates must be exercise of the rollover option by the
incremental rate over some period of
expressed as monthly rates, but do not customer is anticipated because
time and then to pay the balance of the
believe that imposing this requirement transmission providers must have
upgrade costs as a lump sum). While
requires changes to the pro forma assurances of cost recovery for upgrades
Morgan Stanley supports the
OATT.537 To ensure transparency, necessitated by customer decisions.
Commission’s clarification that the
Bonneville recommends that 879. TAPS and EEI recommend that
transmission provider may not demand
transmission providers post on their the Commission modify sections 19.3
a lump sum payment as a condition of
OASIS the methodology used to and 19.4 of the pro forma OATT to
providing the requested service, it asks
calculate incremental rates. APPA specify that the transmission provider
that transmission providers not be
suggests that the Commission simply must present the incremental costs of
precluded from offering a lump sum
state in the preamble to the Final Rule transmission service on a $/MW month
payment option, or any other mutually
that the transmission provider must basis contemporaneous with providing
agreeable approach, to customers.
include a proposed incremental rate in the facilities study to the customer.
its offer of service. 876. MidAmerican, EEI and
Allegheny recommend that the TAPS further states that similar changes
873. Other commenters see no need should be made to sections 32.3 and
Commission clarify that the
for clarification at this time. Southern 32.4 of the pro forma OATT, to ensure
transmission provider is not currently
states that it is not aware of problems that network customers are not scared
limited to charging the customer the rate
regarding the calculation of incremental off by inappropriate presentations of
per MW-month specified in the facilities
rates. Southern requests that the network upgrade costs. TAPS explains
study for the entire term of service if the
Commission consider allowing that, while more complex, it believes
customer pays the incremental cost of
deviations to the Commission’s ‘‘higher that ‘‘higher of’’ pricing can work in the
the network upgrades. These
of’’ pricing policies and to allow all context of network service if applied in
commenters explain that the
transmission providers, not just RTOs, a comparable manner to the
transmission provider’s revenue
to utilize participant funding. transmission provider’s treatment of the
requirement with respect to the
MidAmerican suggests the Commission upgrades needed for service to its retail
incremental cost of network upgrades
defer consideration of possible changes native load.540
will vary over the customer’s term of
to the pro forma OATT regarding this 880. ISO New England and PJM state
service in the same way as its embedded
issue until the Commission undertakes that the Commission’s pricing concerns
cost of service will vary, including the
comprehensive transmission pricing are not present for their respective
cost of capital, operations and
reform. markets and, therefore, any rule
maintenance expense and
874. Other commenters support administrative and general expense. EEI promulgated in this proceeding should
changes to the pro forma OATT that argues that the transmission provider not apply to these RTOs.
will ensure that incremental costs are 881. TAPS argues that
should have the same right to modify a
presented as monthly rates for creditworthiness or security
rate based on incremental costs
service.538 EPSA suggests that the Final requirements associated with network
pursuant to section 205 that it has to
Rule include an example of an upgrades for a transmission customer
modify embedded cost rates and that the
appropriate monthly revenue (in sections 19.4 and 32.4 of the pro
transmission provider should be
requirement calculation and the forma OATT) must be distinguished
permitted to present an incremental cost
upgrade costs included in the monthly from the incremental cost or pricing of
rate as a formula rate.
rate. Suez Energy NA supports this the upgrade. Otherwise, the customer
877. Seattle states that incremental may mistake a demand for security for
proposed change but requests that the
costs may require more rigorous a request for upfront payment of the
transmission provider be required to
treatment than simply stating a monthly entire cost of the upgrade.
provide in a clear format the existing
rate, since the cost of expansion is very 882. In reply comments, EEI states
transmission rate, the lump sum cost of
path specific and often the expansion that it continues to support the
the upgrades, and the incremental rate.
will affect multiple beneficiaries. Commission’s proposed modification to
According to Seattle, the ‘‘higher of’’ the way in which the transmission
100 FERC ¶ 61,096 (2002) (‘‘We agree with SPP that
the amortization period for upgrade costs should
pricing policy will often hinge on
match the contract period * * * As the customer contestable assumptions regarding the 539 See NOPR at P 285 (‘‘Presenting the
is only obligated to take service for the term of the beneficiaries of discrete expansion incremental charge in the form of a monthly rate
sroberts on PROD1PC70 with RULES

contract, it is reasonable that the costs only be projects and the grey area that separates allows a customer seeking a lower rate to choose to
amortized over the term of the contract.’’). request a longer transaction term.’’).
537 E.g., APPA, Bonneville, and Public Power
reliability related aspects of new 540 Citing Midwest Indep. Transmission Sys.
Council. transmission projects from projects Operator, Inc., 109 FERC ¶ 61,085, P 57 (2004)
538 E.g., ELCON, Constellation, FirstEnergy, intended to provide commercial (applying Order 2003 crediting mechanism to
NorthWestern, PGP, TDU Systems. benefits. network customers).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00113 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12378 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

provider presents information on the as well as cost support indicating the reliability of the grid was demonstrated
incremental cost of network upgrades derivation of the rate calculation during the August 2003 Blackout, when
and asserts that nothing in the initial consistent with the cost support that the Alcoa’s smelters remained in operation
comments justifies a change in the transmission provider would provide to and facilitated the restoration of the
Commission’s policies with respect to the Commission in a section 205 rate system. Accordingly, Alcoa asks the
the pricing of transmission service. EEI filing. Because transmission providers Commission to require transmission
states that changes in transmission are required to explain the calculation providers to recognize that demand
pricing policy, such as NRECA’s of their incremental rate, we conclude response resources can be a substitute
proposal to require rolled-in pricing for that the transmission provider need not for ancillary services such as Energy
network customers and TAPS’s proposal post on its OASIS the calculation Imbalance, Operating Reserve and
to exempt network customers from methodology, as recommended by Spinning Reserve.
security for the payment of costs related Bonneville. Similarly, in response to Commission Determination
to network upgrades, are outside the TAPS’s concern about security
scope of this proceeding. payments, the transmission provider’s 888. With respect to Alcoa’s concern
explanation should allow the customer regarding a transmission customer’s
Commission Determination own use of ancillary service, we note
to clearly distinguish between any
883. In the NOPR, the Commission security requirements associated with that the existing pro forma OATT
sought comments on the narrow issue of the service and the incremental cost of requires transmission providers to
whether changes to the pro forma OATT the service. permit transmission customers to
are necessary to ensure that, consistent 885. We will not adopt Great purchase ancillary services from third
with our ‘‘higher of’’ policy, incremental Northern’s recommendation to require parties or make alternative comparable
cost transmission rates are presented as the transmission provider to permit the arrangements for the provision of all
monthly rates for service. The customer to opt for a longer contract ancillary services except for scheduling,
Commission did not propose any term (to obtain a longer amortization system control and dispatch service and
changes to the underlying pricing period and a lower rate) once the reactive supply and voltage control
policy. Commenters’ proposals to incremental cost of the upgrades has service. Regarding the sale of other
change or clarify the Commission’s been determined. The specific upgrades ancillary services including energy
transmission pricing policy are therefore required to provide transmission service imbalance, operating reserve and
outside the scope of this proceeding.541 may depend on the time period over spinning reserve by load resources, we
Other comments are directed toward the agree that such sales should be
which the service is provided; therefore,
application of our ‘‘higher of’’ policy in permitted where appropriate on a
allowing the customer to opt for a longer
individual cases. These include the comparable basis to service provided by
contract term may trigger a need for
comments of Seattle (on the need to generation resources. Comparable
additional, or different, upgrades.
accurately identify the beneficiaries of treatment of load resources is consistent
the network upgrades), TAPS (on the 7. Other Ancillary Services with Staff’s August 2006 Assessment of
use of ‘‘higher of’’ pricing in the context 886. Other than the pricing of Demand Response & Advanced
of network service), and EPSA (asking imbalances, the NOPR did not address Metering Report 543 as well as
the Commission to present an example pricing issues related to ancillary provisions of EPAct 2005.544 We note
calculation of costs and rates). We will services required under the pro forma that some RTOs and ISOs already allow
not address those comments here demand response resources to
OATT. A few commenters nonetheless
because they involve issues that are participate in certain ancillary services
proposed revisions to the pro forma
largely fact-specific that are best markets, while participation of such
OATT regarding the pricing and
addressed on a case-by-case basis. resources in other ancillary services
procurement of, and other issues related
884. Based on the remaining markets is being studied. We therefore
to, ancillary services.
comments received, the Commission modify Schedules 2, 3, 4, 5, 6, and 9 of
concludes that changes to the language a. Demand Response the pro forma OATT to indicate that
of the pro forma OATT to address this Comments Reactive Supply and Voltage Control,
matter are not needed at this time. We Regulation and Frequency Response,
believe that the existing pricing policy 887. Alcoa submits that load
resources (i.e., demand response) Energy Imbalance, Spinning Reserves,
provides sufficient information for Supplemental Reserves and Generator
transmission customers to make an should be permitted to self-supply and,
under certain circumstances, sell Imbalance Services, respectively, may
informed decision regarding a request be provided by generating units as well
for service.542 Transmission providers ancillary services to third parties. Alcoa
must continue to include a proposed states that large customers such as 543 In the Demand Response Report, staff
monthly incremental rate with their aluminum smelters are capable of recommended that federal and state regulators
offer of service whenever the providing, for themselves and third consider whether to allow appropriately designed
transmission provider proposes to parties, some ancillary services so long demand response resources to provide all ancillary
as they are not required to subrogate services including spinning reserve, regulation, and
charge the customer an incremental rate, any new frequency responsive reserves. Demand
their aluminum business functions to Response Report at 97–100.
541 Comments that fall into this category include the needs of the ancillary service 544 Section 1252 (f) of EPAct 2005 states: ‘‘It is the
those of Entegra, Suez Energy NA, Morgan Stanley, markets. In Alcoa’s view, demand policy of the United States that time-based pricing
MidAmerican, EEI (regarding the right to modify resources such as Alcoa’s smelter loads and other forms of demand response, whereby
incremental rates) and Allegheny. electricity customers are provided with electricity
542 Because the Commission declines to adopt should be appropriately compensated as price signals and the ability to benefit by
changes to the pro forma OATT regarding the providers of ancillary services, responding to them, shall be encouraged, the
sroberts on PROD1PC70 with RULES

‘‘higher of’’ pricing policy, the requests of ISO New recognizing their ability to contribute deployment of such technology and devices that
England and PJM to exempt ISOs and RTOs from significantly to the operational enable electricity customers to participate in such
tariff changes related to that policy are moot. pricing and demand response systems shall be
Procedures regarding implementation of the Final
flexibility of energy markets and the facilitated, and unnecessary barriers to demand
Rule by ISOs and RTOs are otherwise discussed in stability of the grid. Alcoa asserts that response participation in energy, capacity and
section IV.C. industrial loads’ contribution to the ancillary service markets shall be eliminated.’’

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00114 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12379

as other non-generation resources such specific customers impose on the for reform of the methods of
as demand resources where appropriate. transmission system. Alcoa contends compensation for the provision of
that, while a particular consumer may reactive power.
b. Procurement and Pricing of Ancillary
use a considerable quantity of energy, 895. Alcoa argues that ancillary
Services Generally
the cost of serving that customer beyond services pricing should recognize the
Comments the per-unit energy cost may be much efficiency contributions made by load as
889. Steel Manufacturers Association less than it would be for other a result of their demand response
contends that the pro forma OATT’s individual customers or groups of capabilities and the contribution that
approach to other generation-based customers. load located near generators makes to
ancillary services should recognize that Commission Determination the provision of reactive power in
regional ancillary services markets do a particular. Alcoa states that the
892. The Commission recognizes that localized supply of reactive power near
better job of ensuring system reliability there can be possible economic and
and holding down ancillary services load centers can alleviate transmission
reliability benefits to larger geographic constraints and allow cheaper real
costs than ancillary services provided markets for ancillary services, as
on a control area by control area basis. power to be delivered into a load center,
suggested by Steel Manufacturers as the provision of such reactive power
Steel Manufacturers Association cites to Association. However, as stated in the
MISO and SPP reports that provide increases the available flow for real
NOPR and repeated above the purpose power between two points. Alcoa argues
evidence that ancillary services of this rulemaking is to strengthen the
provided across large geographical that the pro forma OATT should
pro forma OATT to ensure that it recognize and credit the manner in
regions are more effective and achieves its original purpose—
economical than when those services which certain loads’ location and load
remedying undue discrimination—not profile allows for the provision of
are provided by single utilities. For to create new market structures or, as
example, Steel Manufacturers reactive power and contributes to real
proposed here, to modify existing power transfer capability.
Association notes that the SPP report market structures. We do not believe
concluded that, if a single Area Control 896. Occidental objects to the existing
that altering the scope of the current
Error were used for SPP, energy used for requirement that transmission
ancillary services markets is needed to
regulation service could be reduced by customers purchase reactive power
remedy undue discrimination at this
approximately 30 percent. Steel service from the transmission provider,
time.
Manufacturers Association contends 893. Similarly, we conclude that a arguing that numerous independent
that, although ancillary services markets fundamental overhaul of the current generators provide reactive supply and
in the organized markets have proven procurement and pricing of ancillary voltage control to support transmission
successful at ensuring reliability and at services, as proposed by Occidental and service in competitive wholesale
keeping ancillary services costs low and Steel Manufacturers Association, is markets. Occidental states that the
predictable, utilities outside of the RTO beyond the scope of this proceeding.545 Commission should formalize the policy
and ISO markets continue to provide The pro forma OATT already permits of compensating generators on a
ancillary services primarily from their transmission customers to make comparable, non-discriminatory basis
own limited pools of generation alternative arrangements to satisfy for several ancillary services,
resources. certain of their ancillary services particularly providing reactive power
890. Occidental and Steel obligations. Therefore, transmission capability, by requiring changes to the
Manufacturers Association propose that customers are free to seek out pro forma OATT to mirror the changes
transmission providers should be competitive providers for those accepted by the Commission to the PJM
required, if feasible, to competitively ancillary services other than scheduling, and MISO tariffs. Occidental contends
procure ancillary service products if system control and dispatch service and that amending the pro forma OATT to
there are suppliers of such services reactive supply and voltage control formalize this policy would be
other than the vertically integrated service from third party suppliers. We consistent with the FPA and achieving
merchant function. Occidental argues also find Alcoa’s contention that the non-discriminatory access to
that such procurement will result in just transmission provider’s costs of transmission. Occidental notes that PJM
and reasonable rates for these providing ancillary services for the and MISO amended their tariffs to
generation-related ancillary services that network as a whole should not be provide equal compensation to affiliated
reflect their cost-effective market-based socialized on a MWh basis without and non-affiliated generators based on
competitive supply. In Occidental’s regard to the relative cost burden that the generation owner’s monthly revenue
view, competitive procurement of specific customers impose on the requirement for reactive supply and
ancillary services will also help assure transmission system, to be beyond the voltage control as accepted by the
non-discriminatory treatment of scope of this Final Rule. Commission. Occidental also notes that,
transmission customers since when addressing generator
transmission providers will have less c. Pricing and Procurement of Reactive interconnection agreements in Order
incentive to favor their merchant Power No. 2003–A, the Commission stated that
function in the provision of generation- Comments ‘‘if the Transmission Provider pays its
related ancillary services. Occidental own or its affiliated generators for
894. Several commenters 546 suggest
notes that such procurement should be reactive power within the established
that the Commission consider the need
conducted in a manner consistent with [power factor] range, it must also pay
reliability. 545 We note, however, that the rates charged for
[the interconnecting, independent
891. Alcoa argues that the these ancillary services must be just and reasonable generator].’’ 547
sroberts on PROD1PC70 with RULES

transmission provider’s costs of under the Commissions standard of review. Thus, 897. SPP requests that the
providing ancillary services for the if less expensive options to supply ancillary Commission reform its reactive power
services (including from demand side resources) are
network as a whole should not be available, we would expect the transmission
pricing methodology, which has grown
socialized on a MWh basis without provider to examine such options.
regard to the relative cost burden that 546 E.g., SPP, Alcoa, and Occidental. 547 See Order No. 2003–A at P 416.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00115 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12380 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

out of AEP Serv. Corp.548 SPP contends generators on a case-by-case basis based transmission providers to use, in certain
that the Commission can reduce on the circumstances presented. circumstances, to create additional
uncertainty and litigation surrounding 899. In response to SPP’s specific transmission capacity to accommodate a
the pricing of reactive power by acting proposals for the treatment of reactive request for firm transmission service.
generically in a rulemaking rather than power, we note that the Commission Specifically, the existing pro forma
causing the industry to litigate reactive recently found that it is unduly OATT requires the transmission
power pricing issues on a case-by-case discriminatory and non-comparable for provider to expand or upgrade its
basis. SPP argues that, based on its SPP to apply a ‘‘needs’’ test to reactive transmission system or, if it is more
studies, it does not expect to call upon power capability for independent power economical, plan to redispatch its
IPPs to provide reactive power; and producers to receive compensation that resources to provide requested firm
therefore, it should not be required to is not also applied to all other point-to-point service, provided
pay for reactive power. SPP questions generating plants in its vicinity.550 The redispatch does not (1) degrade or
whether paying all IPPs a reservation Commission also found that parties may impair the reliability of service to native
make a separate FPA section 205 filing load customers, network customers and
charge, regardless of any determination
with the Commission with criteria, other transmission customers taking
of need or of the location of the plant
applied comparably and prospectively, firm point-to-point service or (2)
and the locational need for reactive
that would determine which generators interfere with the transmission
power, provides the appropriate siting would receive reactive power provider’s ability to meet prior firm
incentives. SPP contends that the compensation. contractual commitments to others.553
Commission can reduce the uncertainty 900. Finally, Alcoa’s assertion that The transmission provider must first
and litigation by acting generically certain loads’ location and load profile identify planning redispatch options in
rather than causing the industry to fully allows for the provision of reactive the system impact study in conjunction
litigate these issues in numerous cases power to the transmission system is with identifying relevant system
before various courts. In addition, SPP consistent with Staff’s February 2005 constraints that impact the service
challenges whether the AEP pricing report, Principles for Efficient and request.554 When a system impact study
method for reactive power continues to Reliable Reactive Power Supply and and facilities study identify planning
be appropriate. SPP suggests the Consumption,551 as well as the above- redispatch as a more economical means
Commission consider alternative pricing cited provisions of EPAct 2005. As of relieving a transmission constraint
options, such as: Tying compensation to previously discussed, we have modified than a transmission upgrade, the
the actual provision of reactive power; Schedule 2 of the pro forma OATT to customer is obligated to pay the costs of
eliminating compensation for the allow for the provision of Reactive redispatch consistent with Commission
ninety-five percent leading/lagging band Supply and Voltage Control from policy.
contained in most interconnection demand resources where appropriate. 902. Reliability redispatch is required,
agreements, as such costs may be when feasible, to relieve system
D. Non-Rate Terms and Conditions
considered as a cost of interconnection constraints that would otherwise cause
and included in the power sales price; 1. Modifications to Long-Term Firm curtailment of the network customer or
or, allowing compensation only outside Point-to-Point Service transmission provider loads. To provide
of the band or perhaps when a sale is a. Planning Redispatch and Conditional reliability redispatch, the transmission
displaced. Firm Options provider redispatches all network
resources and transmission provider
Commission Determination 901. The current pro forma OATT resources on a least-cost basis. The
requires the transmission provider to transmission provider and network
898. In Order No. 2003 et al., the provide two types of redispatch service:
Commission found that interconnection customers each pay a load ratio share of
Planning redispatch and reliability these redispatch costs.555
customers must be treated comparably redispatch.552 Planning redispatch is a
with the transmission provider and its product that Order No. 888 required NOPR Proposal
affiliates in terms of reactive power 903. In the NOPR, the Commission
compensation. The Commission 550 See Calpine Oneta Power, L.P., 116 FERC
stated its belief that current practices for
required the transmission provider to ¶ 61,282 (2006).
evaluating long-term firm point-to-point
pay interconnecting generators for 551 See Staff Report: Principles of Efficient and
service may not be comparable to the
Reliable Reactive Power Supply and Consumption
providing reactive power within the (Docket No. AD05–1–000), available at http:// manner in which transmission service is
specified range if the transmission www.ferc.gov/EventCalendar/Files/ planned for bundled retail native load
provider so pays its own generators or 20050310144430–02–04–05-reactive-power.pdf. and may no longer be just, reasonable
those of its affiliates.549 Commenters Staff noted that in many cases load response and
load-side investment could reduce the need for and not unduly discriminatory. The
seeking reform of the methods of reactive power capability in the system and that Commission described two potential
compensation for the provision of increasing reactive power at certain locations solutions: modifications to the planning
reactive power have not demonstrated (usually near a load center) can sometimes alleviate redispatch provisions and conditional
that such reforms are needed at this transmission constraints and allow cheaper real
power to be delivered into a load pocket. See id. firm point-to-point service.556 The
time to remedy undue discrimination or at 4, 108. The report also noted that distributed Commission proposed to modify the
that the current compensation method generators have the same reactive power existing planning redispatch option by
does not provide a comparable result. characteristics as large generators, with both (1) accelerating the study of planning
Accordingly, we do not believe that producing dynamic reactive power, and that the
amount of reactive power does not necessarily
acting generically on pricing reactive decrease when voltage decreases. Id. at 27.
553 See pro forma OATT section 13.5.
power is needed at this time and we 552 In Order No. 888, the Commission referred to 554 See pro forma OATT section 19.3.
sroberts on PROD1PC70 with RULES

will continue to resolve compensation planning redispatch as economic redispatch. Here 555 See pro forma OATT sections 33.2–33.3.

issues for reactive power to qualifying we avoid the term economic redispatch because in 556 Conditional firm point-to-point service

the last ten years it has taken a different meaning (hereinafter conditional firm service) and planning
in the industry and because we will no longer redispatch point-to-point service (hereinafter
548 Opinion No. 440, 88 FERC ¶ 61,141 (1999). require that planning redispatch be capped at the planning redispatch service) are options available
549 See Order No. 2003–B at P 119. cost of expansion. under long-term firm point-to-point service.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00116 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12381

redispatch in the transmission request issues are unresolved. They state that physical, commercial and economic
study process, (2) requiring an estimate using planning redispatch to the circumstances of the request.563
of the number of hours of redispatch maximum degree feasible, while not 907. On the other hand, many
that may be required to accommodate interfering with reliability, is inherent commenters argue that the Commission
the requested service, (3) requiring a in maximizing the efficient use of the should not require either option because
preliminary estimate of the cost of transmission system and should be fully the services are unnecessary,
planning redispatch, and (4) pricing evaluated before undertaking expensive operationally unworkable, and legally
planning redispatch services to facilitate expansion of the transmission system. unjustified, or because they would harm
increased availability of the service.557 Other commenters state that conditional reliability and the quality of existing
The Commission suggested that firm service will create significant network service and provide
conditional firm service could also be complications for transmission disincentives for transmission
used to accommodate additional providers and disincentives to build investment.564 Several commenters state
transactions, defining the service as a transmission in exchange for limited that these services would make
form of firm point-to-point service that and questionable benefits for new point- curtailments of existing firm service
includes less-than-firm service in a to-point customers or LSEs.561 EEI, more likely and limit opportunities for
defined number of hours of the year Indianapolis Power and Ameren express use of secondary network service,
when firm point-to-point service is doubt that customers would agree to be thereby harming native load protections
unavailable. The Commission sought curtailed during peak usage periods. In and reducing reliability, contrary to FPA
comment on its preliminary view that response, AWEA contends that existing sections 215 and 217 respectively.565
planning redispatch is the superior resources serving load would be able to Others opposing both options put forth
option because, in part, it is comparable manage curtailment risks so long as they primarily reliability, cost causation and
to the way the transmission provider could reasonably predict the curtailed comparability arguments. For example,
plans for bundled retail native load. hours. Duke states that the two options are
904. The Commission’s October 12 906. Most independent power antithetical to reliable grid operation
Technical Conference focused, among producers and a few other entities because they would require a
other things, on issues related to the support the inclusion of both services in transmission provider to grant a long-
planning redispatch and conditional the pro forma OATT, stating that the term request with the prior knowledge
firm proposals in the NOPR. On services are required to remedy undue that it cannot be accommodated.
November 15, 2006, the Commission discrimination and provide for International Transmission states that
issued a notice (November 15 Notice) comparable transmission service.562 the grid is already operating at capacity
requesting supplemental comments on a Western Governors believe that the and that requiring the transmission
transparent redispatch proposal planning redispatch and conditional provider to accommodate additional
submitted by Transparent Dispatch firm options are important to fully use megawatt-hours of service during
Advocates (TDA proposal) and certain the existing transmission grid and to periods of system stress would increase
aspects of the conditional firm enable new intermittent generation the likelihood of system failure. While
option.558 The Commission also resources to reach markets. To build the it recognizes that conditional firm
requested comments regarding the case for transmission expansion, the service has been successful in parts of
conditional firm option, including Western Governors argue, it is important the Western Interconnection, NRECA
whether it is a complementary service to to demonstrate that the existing grid is contends a mandate would undermine
planning redispatch, whether it should being effectively utilized; approval of responsible planning and expansion of
be available for all long-term requests or both options will help make this the transmission grid by harnessing the
limited to a request where the customer necessary demonstration. EPSA and transmission provider’s planning and
agrees to pay for upgrades, potential AWEA state that, while they believe dispatch functions to frame more and
modeling problems, and requirements transmission providers should be more elaborate service conditions for
for defining the conditions under which required to offer both services, conditional firm service. APPA,
the service would be curtailable.559 conditional firm service may be simpler Southern and Progress Energy argue that
Comments and less costly to implement because it both services may require adoption of a
involves the transmission provider form of organized LMP market, an
905. Some commenters agree with the action that raises significant political
directing the customer to turn off its
Commission’s preference for opposition and would be contrary to the
resources during a contingency.
modifications to planning redispatch Commission’s commitment in the NOPR
Similarly, Bonneville suggests that
over development of conditional firm to avoid such restructuring. Similarly,
conditional firm service is a reasonable
service.560 They state that the attributes other commenters contend that the
alternative to planning redispatch where
of conditional firm service are not planning redispatch option is only
a transmission provider cannot provide
clearly defined and key implementation appropriate for transmission providers
both options. Commenters state that the
557 The Commission did not propose to modify
Commission should require who are members of an RTO, ISO or
the reliability redispatch provisions that exist in the transmission providers to offer
563 E.g., California Commission Supplemental,
network integration transmission sections of the pro conditional firm service and planning
forma OATT. Williams Supplemental, Constellation
558 The following summary reflects comments
redispatch and allow customers to Supplemental, and Barrick Supplemental.
received as initial and reply comments to the
choose the option that best suits the 564 E.g., Ameren, Duke, Entergy, Imperial,

NOPR, as well as supplemental comments received International Transmission, LPPC, Progress Energy,
in response to the November 15 Notice. Some 561 E.g., EEI, Indianapolis Power, Ameren, and Santee Cooper, Salt River, Southern, Tacoma, TDU
commenters have changed their positions over time Northwest IOUs. Systems, Community Power Alliance, Northwest
and these summaries reflect the most recent 562 E.g., EPSA, AWEA, Entegra, BP Energy, IOUs, NorthWestern, NPPD, NRECA, Public Power
sroberts on PROD1PC70 with RULES

position expressed by commenters. Newmont Mining, Sempra Global, Suez Energy NA, Council, TVA, SPP Reply, South Carolina E&G
559 Questions relating to the TDA proposal are
PPM, Utah Municipals, Williams, Morgan Stanley, Supplemental, E.ON Supplemental, MISO
discussed later in this section. PPL, Project for Sustainable FERC Energy Policy, Supplemental, and APPA Supplemental.
560 E.g., Exelon, FirstEnergy, ELCON, California Commission, CREPC, TranServ, South 565 E.g., Duke, EEI, LPPC, NRECA, NPPD, Progress

MidAmerican, Arkansas Commission, MISO, and Carolina E&G, Constellation, Barrick Supplemental, Energy, Southern, Utah Municipals Reply, and
East Texas Cooperatives. Xcel Supplemental, and Bonneville Supplemental. Duke Reply.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00117 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12382 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

who have an independent administrator should be an interim option until generation more quickly. For example,
of their transmission system.566 Some of transmission upgrades are in place to when there is a lag between the time
the commenters that urge rejection of provide firm service; and, planning that a new generation resource becomes
both options state that a properly redispatch and conditional firm operational and the time that
structured conditional firm service is customers should bear the actual costs transmission upgrades can be built to
preferable to the modified planning of the services received, including costs accommodate the resource, these
redispatch service should the associated with system operational options allow power to reach customer
Commission implement one of the changes needed to accommodate the loads at an earlier date. This can be
services.567 services.571 particularly beneficial to renewable
908. Several commenters prefer the 910. A few commenters believe that resources, such as wind, that can be
development of conditional firm service the Commission should allow for constructed more quickly than the
over the modifications to the planning regional differences in development of transmission upgrades necessary to
redispatch service because of the the new services.572 deliver their power on a firm basis over
complexities surrounding redispatch the long-run.
Commission Determination
costs and protocols.568 For example, in 913. We recognize, however, that both
supplemental comments, EEI and 911. The Commission has determined options raise reliability concerns. The
Community Power Alliance state that, that modifications to the current proposal in the NOPR for planning
while not ideal, conditional firm service planning redispatch requirement and redispatch service would require the
would provide an opportunity to meet creation of a conditional firm option are transmission provider to predict system
customers’ transmission needs and is both necessary for provision of reliable conditions for the term of the service
preferable to Transparent Dispatch and non-discriminatory point-to-point request, a task that becomes more
Advocates’ redispatch proposal.569 They transmission service. The planning difficult, and hence less accurate, with
also contend that the conditional firm redispatch and conditional firm options longer-term requests. This poses several
option would provide faster provision of represent different ways of addressing related problems. Because longer-term
service and relative certainty of timing similar problems. They can be used to forecasts are inherently uncertain and
and costs for a new customer and its remedy a system condition that occurs the further into the future the forecasts,
lenders, while ensuring reliability and infrequently and prevents the granting the less accurate they are, the provision
promoting infrastructure expansion, so of a long-term firm point-to-point of planning redispatch service can
long as transmission providers are service. These options also can be used threaten the reliability of service to
permitted to work with their customers to provide service until transmission native load unless very conservative
to devise appropriate service upgrades are completed to provide fully assumptions are used. This incentive to
parameters. Entergy believes conditional firm service. Planning redispatch use conservative assumptions to protect
firm service can provide benefits to involves an ex ante determination of native load, in turn, increases the
transmission customers without unfairly whether out-of-merit order generation likelihood that planning redispatch
socializing costs to native load and resources can be used to maintain firm service will be denied. This, in turn,
network customers of the transmission service. Conditional firm involves an ex will increase the number of disputes as
provider. Overall, a majority of ante determination of whether there are to whether the denials were
commenters express support for some limited conditions or hours under discriminatory. Such disputes would
form of conditional firm service.570 which firm service can be curtailed to pose enforcement problems because
909. Several commenters argue that, if allow firm service to be provided in all they will turn on long-term projections
the services are required, the other conditions or hours. As we regarding load growth, generation
Commission should add to the services explain below, both techniques are resource additions, etc., that by
the following requirements: The currently used under certain conditions definition involve some degree of
services should not adversely affect by transmission providers to serve subjectivity. Moreover, as we discuss
reliability and service to firm customers native load and, hence, it is necessary below, there is evidence suggesting that,
or provide unduly preferential service to to make comparable services available while transmission providers use
point-to-point customers; the services to transmission customers in order to planning redispatch to serve native
avoid undue discrimination. load, they do not use it as a long-term
566 E.g., CREPC, TVA, and East Texas 912. We therefore find these options tool to avoid future upgrades
Cooperatives. are complementary services that can indefinitely.
567 E.g., EEI, Entergy, Ameren, Progress Energy,
remedy undue discrimination, facilitate 914. In balancing the foregoing
Santee Cooper, TAPS, E.ON Supplemental, TDU the provision of long-term transmission considerations, the Commission will
Systems Supplemental, LPPC Supplemental,
Tacoma Supplemental, and PNM–TNMP service and provide customers with modify the approach proposed in the
Supplemental. greater flexibility in choosing resources NOPR in two principal respects. First,
568 E.g., Manitoba Hydro, Nevada Companies, to meet their needs. There is support in given the ability of both services to
Sacramento, Pinnacle, East Texas Cooperatives, the comments for development of some address similar problems, we have
Barrick Reply, APPA Supplemental, Community reconsidered the proposal that only one
Power Alliance Supplemental, Entergy
type of conditional firm service that
Supplemental, and TAPS Supplemental. would allow for a longer-term use of the of the options should be required. We
569 Section V.D.1.b contains a summary and in- grid when transmission is projected to find that availability of both planning
depth discussion of the TDA proposal. be unavailable for a small portion of the redispatch and conditional firm in the
570 The following entities expressed some level of
year. Additionally, we note that both short-run is necessary to ensure that
support for conditional firm service: EPSA, AWEA, competitive power suppliers have
Entegra, BP Energy, Newmont Mining, Sempra
options could help integrate new
Global, Suez Energy NA, PPM, Utah Municipals,
comparable access to the grid. As
Williams, Morgan Stanley, PPL, Project for 571 E.g., EEI, Southern, TAPS, Seattle, APPA, discussed below, we will continue to
sroberts on PROD1PC70 with RULES

Sustainable FERC Energy Policy, California LPPC Supplemental, Tacoma Supplemental and require that transmission providers offer
Commission, Western Governors, CREPC, TranServ, E.ON Supplemental. Issues related to pricing of to provide planning redispatch under
Constellation, Manitoba Hydro, Nevada Companies, planning redispatch service are addressed in
Sacramento, Pinnacle, PNM–TNMP, Bonneville, paragraphs V.D.1.a.3.c below. certain circumstances in which the
EEI, Entergy, Ameren, Progress Energy, Southern, 572 E.g., California Commission, PGP, Pinnacle, transmission providers determine that
Santee Cooper, Seattle, LPPC, Salt River, and TAPS. and Imperial. there is insufficient ATC. If customers

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00118 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12383

request study of planning redispatch, be comparable to the manner in which degree to which comparability is a
transmission providers have an transmission service is planned for problem in providing point-to-point
obligation to seriously evaluate the bundled retail native load and may no service before the Commission makes
provision of planning redispatch from longer be just, reasonable and not changes to point-to-point service.579 In
their own resources and provide unduly discriminatory.575 supplemental comments, EEI contends
customers with information on the that the record in this proceeding does
Comments
capabilities of other generators to not demonstrate that conditional firm
provide planning redispatch. If planning 918. Some commenters challenge the service is necessary to remedy undue
redispatch is unavailable from the Commission’s authority to order discrimination.
transmission provider’s resources or planning redispatch or conditional firm 919. Others assert that it is not within
inadequate to meet customers’ needs, service as a remedy for potential undue the Commission’s jurisdiction to order
transmission providers have an discrimination. EEI and others argue planning redispatch for point-to-point
independent obligation to offer that planning redispatch is not customers because this type of
conditional firm, if available, as part of necessary to eliminate actual or redispatch requires use of the
the firm point-to-point service.573 perceived undue discrimination because transmission provider’s generation
Customers will have the choice of many transmission providers do not rely resources.580 LPPC states that the
whether to request study of the planning on redispatch in planning to serve comparability principle is wrongly
redispatch option, the conditional firm native load.576 However, EEI also states applied to the use of generation by a
option or both. that when transmission providers do transmission provider. In Salt River’s
915. Second, we will not impose a incorporate redispatch into their system view, the Commission proposal sets up
planning redispatch or conditional firm planning, they do so generally only its own form of discrimination by
obligation over the long run. Such an when the cost of redispatch is lower making redispatch of the transmission
obligation is not, as described below, than the cost of network upgrades and provider’s resources mandatory while
necessary to remedy undue system reliability is not impacted. Some making redispatch of generation using
discrimination and would otherwise transmission providers state that they firm point-to-point reservations and
pose reliability problems, put the do not currently use planning generation in other control areas
transmission provider at risk for redispatch in lieu of transmission voluntary.
estimating the costs of long-term construction in order to designate their 920. Those that support development
redispatch, and undermine incentives to network resources.577 On the other of both services support the
upgrade the transmission grid. hand, Entergy and Southern state that Commission’s statement in the NOPR
Therefore, we will limit the availability they currently use or have used that ‘‘transmission owners may evaluate
of both service options so that their planning redispatch of their own transmission availability to serve long-
duration is for a time period over which resources on the same basis that they term transmission service requests in a
service can be reasonably provided allow any network customer to manner that is not comparable with the
without impairing reliability.574 This redispatch from the network customer’s method they use to evaluate
limitation scales back the existing resources. For example, Southern states transmission needs for bundled retail
planning redispatch requirement in that it has used the redispatch potential native load.’’ 581 They argue that this
section 13.5 of the pro forma OATT that of its generators during off-peak/ divergent treatment of internal
could, in practice, allow for an open- shoulder periods on an interim basis transmission needs versus external
ended obligation to provide planning until completion of transmission transmission requests is unduly
redispatch in lieu of upgrading the upgrades to designate network resources discriminatory and violates the FPA.
transmission system (e.g., involving that otherwise might be EPSA states that the fact that point-to-
forecasts up to 30 years). undeliverable.578 Entergy disagrees that point service requests can be rejected
916. We discuss in detail the there is undue discrimination because due to a few hours of predicted
comparability and reliability findings this service is not available to point-to- reliability problems in a year is
that support these decisions below. point customers, stating that network ‘‘evidence of a poor use of existing
and point-to-point service are not transmission capacity and display clear
(1) Comparability
similarly situated services. TDU discrimination against non-affiliated
NOPR Proposal generation and its customers.’’ 582
Systems state that conditional firm
917. In the NOPR, the Commission service does not ensure comparability TransAlta states that its actual
expressed its preliminary view that among types of transmission service or experience with planning redispatch in
current practices for evaluating long- between transmission providers and the Pacific Northwest demonstrates that
term firm point-to-point service may not transmission customers. NRECA and planning redispatch is used
others argue that the Commission discriminatorily to the benefit of some
573 Application of planning redispatch and
requires a better understanding of the customers and the detriment of others.
conditional firm service obligations to RTO and ISO 921. In support of conditional firm
transmission providers is discussed in section
575 The Commission did not propose to modify
service, Manitoba Hydro and Tacoma
V.D.1.a.3.B.i below. reiterate their experience that long-term
574 As explained in more detail below, we adopt the reliability redispatch provisions that exist in the
limitations that are tailored to the two types of network integration transmission sections of the pro transmission service requests are being
customers that may request the options. First, for forma OATT. denied due to constraints occurring
576 E.g., EEI, TDU Systems, NRECA, Southern,
customers that agree to support the construction of during a small percentage of the time
new transmission facilities, redispatch and and Duke Reply.
577 E.g., Southern, Duke, and Progress. Duke
within the requested period of service.
conditional firm point-to-point service will be
available as a bridge until such time as those suggests that the Commission exempt transmission
579 E.g., TDU Systems and EEI Reply.
facilities are constructed and the relevant providers from the obligation to provide redispatch
sroberts on PROD1PC70 with RULES

580 E.g., LPPC, NPPD, Progress Energy, and Salt


conditions must be specified in the initial service if they commit not to use redispatch as a planning
agreement and are not subject to change. Second, tool for native load, network customers or merchant River.
for customers that do not agree to support the functions. 581 E.g., AWEA, Utah Municipals, Project for

construction of new facilities, the transmission 578 Southern states that it offered this service on Sustainable FERC Energy Policy, EPSA, and Barrick
provider will be able to re-evaluate the conditions a comparable basis to a non-affiliated transmission Reply citing NOPR at P 300.
under which services are provided every two years. customer. 582 EPSA Reply.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00119 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12384 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

EPSA and AWEA similarly state that a raised, including arguments pertaining providers currently evaluate
transmission provider will reject a long- to the Commission’s jurisdiction over transmission availability to serve long-
term firm service request unless it can transmission provider generation term firm point-to-point transmission
satisfy every element of the request. resources, are impermissible collateral service requests in a manner that is not
Manitoba Hydro and others state that, in attacks on the current planning comparable with the method they use to
an era of transmission under- redispatch obligation in Order No. 888. evaluate their own transmission needs
investment, optimizing the capacity Entergy’s argument that planning and to integrate their resources to serve
usage is paramount to system redispatch should not be available to bundled retail native load.
reliability.583 EPSA and AWEA further point-to-point customers because they 925. Furthermore, we wish to
explain that the concept of turning off are not similarly situated to be able to emphasize that, in making these
a generator to avoid system upgrades is provide redispatch from their own units findings in support of a conditional firm
not new; Maine Independence Station thus ignores the current obligation for option, we are not relying on the
avoided expensive system upgrades by each transmission provider to provide findings to create a new service. This
installing automatic switching devices redispatch from the transmission Final Rule retains the two services
to take it offline during certain system provider’s resources, if available, in adopted in Order No. 888—point-to-
conditions. Seattle states that, according evaluating a request for long-term point- point service and network service.
to the Seams Steering Committee of the to-point service.585 Conditional firm service is not a third
Western Interconnection, utilization on 924. Additionally, information in the service, but rather represents a
most constrained paths is limited to comments counters the assertion that modification to the existing procedures
only a few hundred hours per year and, transmission providers do not use for granting long-term point-to-point
therefore, it is highly likely that service planning redispatch or service service and the curtailment priorities for
under a conditional firm product could analogous to the conditional firm option that service. The primary purpose of
be offered for even a baseload plant for their own loads. Entergy and conditional firm is to address the ‘‘all or
without significantly impacting the Southern volunteer that they have nothing’’ problem associated with the
capacity factor. Santee Cooper states planned for redispatch of their own current procedures for requesting long-
that, unlike the planning redispatch resources in order to designate network term point-to-point service. Currently, a
option, conditional firm service is resources when ATC was request can be denied because firm
presumptively within the subject matter unavailable.586 As a caveat, Southern service is unavailable in a very few
jurisdiction of the Commission. states that it has planned for the use of hours of the year. For a customer who
922. Entergy states that the most redispatch only for an interim period needs long-term point-to-point service
comparable service for long-term point- until upgrades could be constructed to to support a long-term transaction, this
to-point transmission customers is not a make the transmission service from the leaves the customer in the position of
requirement that a transmission designated resource fully firm. Entergy trying to cobble together a collection of
provider redispatch its own or network states that it offers planning redispatch shorter-term requests to effectuate its
customers’ resources to grant long-term service to network customers that plan transaction, e.g., arranging firm service
firm point-to-point transmission service. to use their own resources to provide in the periods when it is available and
The most comparable service instead is redispatch in real time. Contrary to EEI’s non-firm service in the other periods.
a service that allows the transmission assertion about the record in this Such a customer also risks interruption
provider to curtail the service granted, proceeding, commenters, such as EPSA of the non-firm portion of its service for
while permitting the point-to-point and AWEA, explain that some economic reasons, e.g., a day of non-
customer to obtain alternative, transmission providers already employ firm service for the customer combining
deliverable resources if and when such automatic devices, such as special firm and non-firm service could be
curtailments occur in real-time. protection systems (SPS), to take interrupted for another customer
resources offline during certain system seeking one month of non-firm service.
Commission Determination conditions. In a way that is analogous to We do not believe such an approach is
923. We reject arguments that the proposed conditional firm service, just and reasonable. It makes little sense
planning redispatch service is these protection schemes are used to to ask the customer to cobble together a
unnecessary to remedy undue increase native loads’ firm uses of the collection of firm and non-firm requests
discrimination as a collateral attack on transmission system until a contingency when the transmission provider has
Order No. 888. The obligation to occurs that reduces available better information about when the
provide planning redispatch was transmission.587 This information, taken service may be available or unavailable.
established in Order No. 888. The together, provides ample evidence to It is therefore appropriate to require the
modifications proposed in the NOPR support our finding that transmission transmission provider to grant the
did not increase the obligation placed service on a conditional basis, as we
on transmission providers to use their 585 See pro forma OATT section 13.5. explain further below.
generation resources to provide 586 Entergy and Southern. EEI’s comments also 926. We are however modifying the
indicate that at least a few transmission providers planning redispatch obligation, and
planning redispatch to point-to-point do rely on redispatch in planning to serve their
customers. Rather, the proposed native loads.
similarly limiting the conditional firm
modifications merely added specificity 587 SPS, also known as remedial action schemes, option, to better reflect the manner in
to the redispatch information already are used to varying degrees in every NERC which redispatch or special protections
required in a system impact study and reliability region. For example, there are about 65 schemes are used by transmission
SPS in the Western Interconnection. See Western providers, in recognition of certain
adjusted the timing of when the Electricity Coordinating Council Operating
transmission provider must study Procedures, Index, V–1 to V–5 (revised July 2,
legitimate reliability concerns and the
planning redispatch options.584 2002). There are 8 SPS used by Florida Power and inherent difficulty of long-term
sroberts on PROD1PC70 with RULES

Therefore, many of the arguments Light in FRCC. See Florida Power and Light Control projections in this area. This Final Rule
Area Readiness Audit Report, 19 (March 10–11, limits transmission providers’ planning
2004). Two SPS are used in the Southern Subregion
583 E.g., EPSA, AWEA, and Project for Sustainable
of SERC. Reliability Coordinator Readiness Audit
redispatch obligations by removing the
FERC Energy Policy. Report Southern Subregion Reliability Coordinator, current obligation to provide planning
584 See pro forma OATT section 19.3. 19 (March 27–30, 2006). redispatch for an indefinite period as

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00120 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12385

long as the redispatch is cheaper than load.588 These services do, and will evaluating planning redispatch options
the relevant transmission upgrades. We continue to, share the same priority— so that there is no reliance on
also limit the conditional firm option by the highest priority of firm service on curtailment of service. MidAmerican
linking it to the transmission upgrades the transmission provider’s system. The and Progress Energy conclude that the
or a biennial assessment of the only change, as it relates to the customer must accept the risk of
conditions. conditional firm option, is to allow the selecting planning redispatch service
927. We find such an open-ended customer to elect to have its long-term over transmission construction.
obligation to provide this service is not firm transmission service interrupted 931. Several commenters request
necessary to remedy undue under certain defined circumstances. modification of the existing planning
discrimination, nor is it consistent with This does not harm other firm redispatch provisions of the pro forma
the need to maintain system reliability. customers. Indeed, it has precisely the OATT.590 They state that the
As indicated above, transmission opposite effect: it permits an Commission should clarify that the
providers temporally limit their use of interruption to maintain firm service to current section 13.5 does not require
planning redispatch and curtailment of other customers. Moreover, we find, as planning redispatch when it would
resources and there is no evidence that indicated above, that conditional firm adversely affect system reliability or
transmission providers use these service is necessary to remedy undue service to native load, network
options on a prolonged basis, e.g., for discrimination. customers and other firm point-to-point
more than a few years, without 929. The addition of conditional firm customers or impair other contractual
upgrading their transmission systems. service therefore does not significantly obligations. Indianapolis Power states
Rather, over the long run, transmission alter the existing balance between the that the Commission should modify
providers generally will construct point-to-point and network service. section 13.5 to require all reasonable
sufficient transmission to integrate their Customers of network service retain redispatch options be examined by the
resources on a firm basis. This is flexibility that is not enjoyed by point- transmission provider.
consistent with transmission planning to-point customers. Moreover, 932. In its reply comments, Southern
requirements and the emphasis placed conditional firm does not reduce the explains that transmission providers fail
upon transmission expansion in this availability of secondary network to provide the currently required
Final Rule. The modifications to long- service or the ability of network planning redispatch service to point-to-
term point-to-point service we adopt are customers to temporarily undesignate point customers because the service is
consistent and comparable to the network resources any more than short- impractical and would harm reliability.
existing use of these options by term firm point-to-point service already Southern contends that a redispatch
transmission providers’ bundled retail reduces the availability of these network scenario identified in a transmission
native loads. Thus, the planning customer options. We therefore reject plan may not be available in real time
TDU Systems’ arguments and find that due to outages or loop flow. Southern is
redispatch and conditional firm options
the addition of conditional firm service also concerned about the complications
will be available primarily as interim
is necessary to remedy undue in planning and modeling that would
measures until transmission systems are
discrimination and will otherwise occur if the transmission provider is
upgraded to meet the transmission
increase utilization of the grid without required to redispatch multiple
service request. We believe this
impairing system reliability. resources in order to accommodate
limitation will have the added benefit of
multiple planning redispatch customers.
lessening disincentives to provide the (2) Reliability 933. Similar to their arguments in
service so that more planning redispatch
(A) Ability to Predict Redispatch favor of conditional firm, EPSA and
is offered to transmission customers by
Opportunities and System Conditions in AWEA state that planning redispatch is
transmission providers.
the Long Run necessary because a transmission
928. We disagree with TDU Systems’
provider will reject a long-term firm
statement that conditional firm service Comments service request unless it can satisfy
does not ensure comparability among
930. Some commenters state that every element of the request, even if
types of transmission service or between
redispatch, used as a planning tool reliability violations occur in only a few
transmission providers and
rather than as a short-term operational hours of the year. In its reply comments,
transmission customers. TDU Systems’
tool, is overly complex, prone to causing EEI responds that there is no evidence
assertion is unsupported by any
disputes, reduces reliability and thus to support the assertion that a
explanation or examples of how the
should not be included in the pro forma transmission provider will reject a long-
conditional firm service would degrade
OATT.589 Southern asserts that term firm service request unless it can
comparability. Nevertheless, we believe
planning redispatch should not be meet every element of that request. EEI
the argument is essentially a collateral
required where it reduces reliability by states that in such a situation the
attack on Order No. 888. Order No. 888,
reducing a utility’s reserve margin, transmission provider must offer partial
not this rulemaking, created the
shifting the operational, reliability and service, offer to perform a system impact
distinction between point-to-point
economic risks from the new customer study, and exercise due diligence in
transmission service and network
to native load, or causing a single constructing needed upgrades to
integration service. We did so to
contingency to overload the system. accommodate the request. EEI adds that
recognize the different ways in which
Additionally, Xcel states that pledging a the potential customer can also request
transmission providers typically use
network resource to support planning short-term service. Finally, EEI states
their system. The two services are not
redispatch carries a risk of penalties for that there is no evidence that
precisely the same, nor were they intend
inadequate resources in some areas. transmission providers are refusing to
to be identical. Nothing in this Final
MISO states that contingency conditions redispatch in response to customer
sroberts on PROD1PC70 with RULES

Rule changes these distinctions. Indeed,


must be considered and respected when request when redispatching resources
we are not changing the relative
would have no impact on reliability. In
priorities applicable to firm point-to- 588 See
supra section V.D.5.b.
point service, network integration 589 E.g.,
Duke, Entergy, WAPA, NRECA, NPPD, 590 E.g., EEI, Indianapolis Power, Public Power
service and service to bundled native LPPC, and Southern. Council, Southern, Seattle, Sacramento, and LPPC.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00121 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12386 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

its reply comments, MISO states that variability in water flows and the risks or costs to native load or other
denial of service complained of by interdependence of the generating units users of the system.
EPSA and AWEA is a consequence of contribute to the inability to predict 939. In its reply comments, EPSA
the customer’s economic decision not to future redispatch ability. Bonneville, further argues that the Commission
build upgrades. WAPA and Bureau of Reclamation state should place the burden of showing
934. Many transmission providers that planning redispatch can conflict unreliability in a particular instance on
assert that the costs and inequities of with federal obligations to operate the transmission provider. EPSA also
achieving the proposed planning federal dams and reservoirs in a manner argues that transmission providers
redispatch outweigh any new benefits that does not impact project purposes should not be allowed to delay service
for point-to-point customers.591 They and provide preference in the sale of through feasibility studies. EPSA
state that the Commission’s proposal is hydropower to its preference customers. contends that planning redispatch will
based on an erroneous assumption that Tacoma states that planning redispatch not delay needed system upgrades and,
redispatch is nearly always feasible; must be linked to market price indexes instead, will ensure optimized use of
instead when redispatch is most to work in a hydro-based system. Seattle the existing system that will provide
desirable, generators operating at peak states that in hydro-dominant systems additional information about the
would not be available for redispatch.592 fuel availability and fuel price risk system’s capabilities to regional
Southern also explains that problems of undermine the feasibility of providing planning initiatives. In its reply
insufficient transmission capacity long-run redispatch cost estimates that comments, Morgan Stanley states that
cannot be avoided by redispatching reasonably reflect future costs. Seattle the Commission should establish clear
generation because there is no guarantee adds on reply that planning redispatch standards as to the degree of expected
that a redispatch solution will be fails to address costs pertaining to fish reliability that appends to a firm
available during real-time operations. species preservation, recreation and transmission sale and allow
Imperial argues that the personnel and flood control impacts, increased risk of transmission providers to sell as much
modeling costs to transmission spill, or replacement power that are of the system as can be sold on a firm
providers of calculating planning associated with hydroelectricity. basis, consistent with maintaining the
redispatch costs prior to a facilities 937. Morgan Stanley argues on reply reasonable standard.
study are too excessive. Xcel concludes 940. EEI and some transmission
that the Commission should not exempt
from a NERC experiment on market providers add that the conditional firm
hydroelectric system operators from
redispatch that redispatch involving product could result in an
providing planning redispatch; instead,
non-market-based or bilateral oversubscription of a transmission
factors unique to hydroelectric systems
coordination with third parties to system in violation of NERC reliability
should be taken into account in standards that require the transmission
protect a delivery path is cumbersome, determining how much planning
inefficient, and does not promote system to be planned to meet all firm
redispatch a transmission provider can needs.595 ELCON states that conditional
reliability. provide. In supplemental comments,
935. Xcel states that its estimate of firm service may not truly support long-
PPM agrees with Morgan Stanley and term contracts for firm power but may
hours of planning redispatch is unlikely
adds that hydro-based systems, such as lead to a greater volume of short-term
to be accurate given that it uses a static
Bonneville’s, are flexible enough for a trading.
power flow that is created for a specific
transmission provider to use planning
peak hour and a specific off-peak hour Commission Determination
redispatch to create additional firm
in a given year. Commenters state that
capacity. 941. Many commenters are concerned
planning redispatch service should not
be a guaranteed service because 938. In their reply comments, Utah that the options described in the NOPR
generation or transmission availability, Municipals and EPSA state that will impair system reliability. We have
system loads, loop flows from adjoining planning redispatch would not impair taken these comments into account and
systems, weather, and fuel availability reliability because the OATT provisions have tailored the modifications to long-
all entail a component of risk that do not require transmission providers to term point-to-point service so as to not
should not be pushed back on the permit intentional overloading of lines. impair system reliability. There are two
transmission provider or its native Since transmission providers are important limitations that provide such
load.593 already required to provide planning protections. First, we make clear that
936. Operators of systems that rely redispatch now, Utah Municipals transmission providers are not required
primarily on hydroelectric resources contend that any change in the sequence to offer planning redispatch or
argue that planning redispatch should for studying the option cannot have an conditional firm service if doing so
not be considered a viable option for impact on reliability. EPSA argues that would impair system reliability.596
their systems and they should be claims of adverse reliability impacts Second, as explained above and
exempt from OATT planning redispatch should be dismissed because discussed in further detail below, we are
obligations because hydroelectric transmission providers do not make limiting the time period under which
operators are unable to make long-term these same claims when they redispatch either option is offered. We do so
commitments that a resource will be to enable transmission service to meet because forecasts of potential redispatch
available to relieve transmission their own load obligations. Utah or interruption options become more
constraints.594 Bonneville states that the Municipals state that reliability would
be most enhanced by completely 595 E.g., Ameren, Southern, and EEI.
596 A transmission provider may not be able to
591 E.g., Duke, Entergy, Imperial, International restricting access to the grid, a policy
provide conditional firm service without impairing
Transmission, Salt River, Seattle, Southern, that Utah Municipals do not the reliability of its system if it is required, for
Tacoma, Northwest IOUs, Sacramento, Progress recommend because it would be example, to manage many conditional firm point-
sroberts on PROD1PC70 with RULES

Energy, E.ON, Xcel, TVA, and EEI Reply. extraordinarily costly and promote to-point reservations across the same path. The
592 E.g., Sacramento and TVA.
discrimination. In its reply comments, ability of system operators to track, tag and manage
593 E.g., Progress Energy, E.ON, WAPA, Entergy,
curtailment of multiple conditional firm
and MidAmerican. Entegra states that customers seeking reservations is necessarily limited by time, human
594 E.g., Bonneville, Seattle, Public Power planning redispatch are not seeking to resources and other reliability-related duties of the
Council, and WAPA. shift a disproportionate share of the operators.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00122 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12387

speculative over time and to require a transmission provider should retain determining whether the service can be
transmission provider to commit for a responsibility for incorporating reliably provided.
substantial period of time, subject to the reasonable assumptions into its 947. Further we will not excuse
uncertainty inherent in such long-term transmission models so that it can transmission providers from the
projecting, has the potential to degrade manage this risk, just as it currently obligation to manage multiple planning
reliability. With these two limiting manages the prediction risk in its ATC redispatch or conditional curtailment
conditions, we find that neither the models. obligations simply because some
planning redispatch nor conditional 945. We will now turn to certain commenters express concerns about
firm option will degrade reliability and, planning and modeling impacts. While
clarifications and other issues raised by
as discussed above, that both are we do not take these concerns lightly,
the commenters. We acknowledge that
necessary to remedy undue we believe they can be managed by
planning redispatch to support annual
discrimination. transmission providers. The planning
942. We agree with a majority of service may require redispatch of
generation during the peak month or redispatch obligation has existed for ten
commenters that over the long term, years, and with it the potential for
new resources should be supported by months. Since transmission providers
plan their generation to meet their peak multiple planning redispatch requests.
sufficient transmission capacity to We have no evidence that transmission
deliver their output reliably. Imposing a native load plus reserves, the
transmission provider’s resources may, providers have been unable to manage
planning redispatch or conditional firm the process. Moreover, by scaling back
obligation over the long-run would not in some cases, be fully employed to
meet the needs of bundled retail native the time period for which transmission
be consistent with the need to increase providers must plan for provision of
the reliability of the grid or otherwise load and thus may not be available to
provide redispatch during the peak redispatch, we have greatly reduced any
necessary to remedy undue planning and modeling impacts. We
discrimination. Rather, it would tend to period.597 In such an instance, the
unavailability of such resources to believe that whatever additional work
degrade reliability over time, contrary to the options cause with regard to
the public interest and the underlying provide redispatch service will
planning and modeling, it is small and
goals of EPAct 2005. Projections of constitute a legitimate basis for denying
more than offset by the considerable
planning redispatch options and planning redispatch service. However,
value of the options which allow for
conditional firm conditions are more we will not excuse the existing
more efficient use of the transmission
accurate in the near term and, hence, obligation that requires transmission
system, expansion of long-term uses of
should facilitate the efficient use of providers to study any available
the grid and remedying of undue
existing resources without impairing planning redispatch, including
discrimination.
reliability. redispatch that might provide some but
943. We therefore impose limits on not all of the service requested. Given 948. Finally, we recognize the
the transmission provider’s current that some transmission providers have difficulty of predicting, over prolonged
planning redispatch obligations. We do acknowledged their own use of periods, whether hydroelectric
so by removing the obligation to provide planning redispatch for their network resources will be available to provide
planning redispatch for an indefinite resources,598 the service must continue redispatch. We agree with Morgan
period as long as the redispatch is less to be available to those seeking point-to- Stanley that factors unique to
expensive than the relevant point service to ensure comparability. hydroelectric systems should be taken
transmission upgrades. Section 13.5 of into account in determining how much
946. We reiterate that the planning redispatch a transmission
the pro forma OATT could, in transmission provider remains obligated
conjunction with rollover rights, allow provider can provide. For example,
to provide planning redispatch from its transmission providers operating hydro-
for an extremely long-term obligation to
resources as long as the planning based systems must predict both system
provide planning redispatch in lieu of
redispatch does not (1) degrade or load growth and water availability in
upgrading the transmission system. We
impair the reliability of service to native order to determine whether resources
find that this existing obligation may
load customers, network customers and will be available in the next few years
unreasonably harm reliability and
other transmission customers taking to provide redispatch. We acknowledge
provides incorrect incentives to delay
firm point-to-point service or (2) that certain circumstances may in fact
necessary grid expansion. We
interfere with the transmission limit long-term redispatch on these
emphasize that the obligation to provide
provider’s ability to meet prior firm systems due to increased prediction
planning redispatch applies only when
contractual commitments to others.599 risks. We reiterate, however, that all
the service can be provided reliably.
944. We also limit the time period We continue to believe these are the transmission providers, including those
over which a transmission provider appropriate exceptions and will not operating hydro-based systems, are
must predict the system conditions or adopt a broad and undefined required to make a determination,
conditional hours that would apply to reasonableness standard as suggested by regarding whether planning redispatch
customers using the conditional firm Indianapolis Power. We agree with service can be provided consistent with
option. We do so in recognition of the Southern that the transmission provider system reliability based on the specific
difficulty in attempting to forecast may consider the impact of the planning facts of a particular request for service.
curtailment options over the long-term redispatch service in reducing its The fact that hydro-based systems may
and the fact that there is no evidence reserve margin below that necessary to not be able to provide planning
that transmission providers perform maintain reliability or causing a single redispatch service under many
similar forecasts for their native load contingency to overload the system in circumstances should not necessarily
customers. We do not, however, limit the availability of conditional firm
sroberts on PROD1PC70 with RULES

597 See, e.g., Arizona Public Service Co. v. Idaho


eliminate entirely the risk of predicting service on these systems. We expect that
Power Co., 95 FERC ¶ 61,081 at 61,241 (2001)
future system conditions or shift it in (resources projected to be unavailable during
transmission providers with hydro-
whole to the requesting transmission system peak month to provide planning redispatch). based systems will focus on provision of
customer as requested by certain 598 E.g., Entergy. the conditional firm option in a manner
commenters. We believe that the 599 See also Order No. 888 at 31,739. consistent with their system conditions.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00123 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12388 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

949. We also repeat that planning that NRECA argues is protected by FPA redispatch or conditional firm option
redispatch service does not need to be section 217. would qualify as a network resource on
provided if doing so would impair the any adjoining system importing that
Commission Determination
firmness of service to existing resource.
transmission customers. For example, 952. We reiterate that transmission
providers are not required to offer (3) Implementation of Planning
pre-existing federal obligations, such as Redispatch and Conditional Firm
those described by Bonneville, WAPA planning redispatch and conditional
firm point-to-point service if doing so Options
and Bureau of Reclamation, would
qualify as the type of firm commitments would impair the reliable service to firm 956. Commenters raise various
to others that would excuse customers, including native load and concerns regarding specific
transmission providers from the network customers. The concerns of the implementation issues associated with
planning redispatch obligation to the commenters regarding the impacts on the planning redispatch and conditional
extent that redispatch impaired service native load, network and other existing firm options. We address those concerns
to these customers. firm uses are therefore misplaced. below, but first provide an overview of
953. Transmission providers are the planning redispatch and conditional
(B) Impact on Network Customers and already obligated to provide planning firm service required in this Final Rule
Native Load redispatch service pursuant to Order in order to outline the new rights and
No. 888 and thus arguments that the obligations of transmission providers
950. Several commenters argue that
planning redispatch option will harm and customers. Following this overview,
the use of planning redispatch may
existing customers is equally misplaced. we address specific comments relating
remove the ability to use reliability
Indeed, under the limitation on the to the service.
redispatch in real-time operations to
duration of planning redispatch service 957. Pursuant to the modified
respond to system contingencies, imposed in this Final Rule, transmission obligations adopted in this Final Rule,
resulting in more curtailment of providers will be able to better manage where a request for long-term point-to-
network and native load.600 In addition the risks of curtailment for current users point firm transmission service is made
to reducing availability of redispatch as of the transmission grid. This is because and cannot be satisfied out of existing
an operational tool, NRECA contends the obligation to redispatch will no capacity, the transmission provider
that planning redispatch will reduce longer be an open-ended obligation. shall, at the request of the customer and
ATC for network service and the Customers will need to commit to in the system impact study, identify (1)
incentive to build new transmission. upgrade the system or to have their the transmission upgrades necessary to
Several commenters state that planning service reassessed periodically. Both of provide the service, and (2) the options
redispatch may unfairly shift costs to these allow the transmission provider to for providing service during the period
network and native load customers.601 better plan to serve needs reliably prior to completion of those
Progress Energy argues that such a because it reduces the unknowns. With transmission upgrades. Additionally, if
mandate places the power grid in regard to NRECA’s argument that upgrades cannot be completed prior to
serious jeopardy because the system has planning redispatch will cause less expiration of the requested service term,
not been designed to handle the flexibility in real-time and more the transmission provider shall, at the
redispatch planning model. Progress potential for curtailments of network request of the customer and in the
Energy and Nevada Companies state customers and bundled retail native system impact study, identify options
that the planning redispatch option load, all sales of point-to-point service for providing the service during the
could conflict with transmission could to some extent cause more requested term. The options studied by
providers’ state resource planning curtailments of network customers and the transmission provider must include
obligations to reliably serve load at least bundled retail native load. Our decision planning redispatch and conditional
cost. Exelon replies, however, that today limits the existing planning firm options.603 The transmission
planning redispatch could increase redispatch obligation for point-to-point provider, at its discretion, may study
flexibility for network customers by service, rather than expanding it. and offer a mix of planning redispatch
increasing the availability of point-to- 954. Similarly, the conditional firm and conditional firm options for a single
point service across adjacent option does not reduce the availability service request. We provide further
transmission systems to bring of secondary network service or the detail on each required option below.
generation to network loads. ability of network customers to 958. If the transmission provider
951. Some commenters argue that the temporarily undesignate network determines that planning redispatch is
conditional firm option would adversely resources any more than short-term firm available, it shall provide the customer
impact system reliability by subjecting point-to-point service already reduces with non-binding estimates of the
firm customers to additional the availability of these network incremental costs of redispatch and
curtailments once conditional customer options. We see no reason to identify the relevant constrained
curtailment hours are exceeded.602 reject the conditional firm option so that flowgates for which redispatch will be
NRECA and Utah Municipals state that transmission providers avoid offering provided. For the conditional firm
the conditional firm service will reduce higher-quality service such as option, the transmission provider shall
the flexibility of network customers by conditional firm point-to-point service identify the conditions and hours
preventing network customers from in order to retain the ability to offer pursuant to which the service may be
using secondary network service, a right lower-quality service such as secondary curtailed, using a secondary network
network service. curtailment priority, to maintain
600 E.g., EEI, Duke, Imperial, LPPC, PNM–TNMP, 955. Finally, we believe that network reliability. Specifically, the transmission
Public Power Council, NRECA, NPPD, Southern, customers can benefit from the use of provider shall identify (1) the specific
sroberts on PROD1PC70 with RULES

and Progress Energy. the planning redispatch and conditional


601 E.g., EEI, TAPS, LDWP, MidAmerican, 603 Although partial interim service is not
firm options available in a point-to-
Southern, Community Power Alliance, and MISO addressed in this rulemaking, we note that the
Reply. point transmission service request. As OATT continues to require this service, on an as
602 E.g., Duke, LPPC, NRECA, NPPD, Progress described below, long-term point-to- available basis, if a multi-year service request is
Energy, Southern, APPA, and South Carolina E&G. point service that employs the planning denied.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00124 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12389

system condition(s) when conditional the customer along with a narrative problems that may occur if a conditional
curtailment may apply and (2) the statement describing the study and firm customer is taking long-term
annual number of hours when reasons for changes to the curtailment service and the transmission system is
conditional curtailment may apply. conditions or redispatch requirements upgraded during that service. They also
Customers agreeing to take conditional no later than 90 days prior to the date argue that the bridge product would
firm service must choose one of these for imposition of these new conditions better allow for transmission providers
options, conditions or hours. or requirements. The transmission to judge the likelihood of curtailment
959. Where the customer requests provider shall assess the conditions and avoid complicated system modeling
firm service for more than two years, but based on two years of service or the and planning issues; as well as protect
is unwilling to commit to a facilities continuation of the term of service, existing long-term transmission
study or the payment of network whichever is less. customers. Duke and Ameren state that
upgrade costs, the transmission provider 961. In situations in which the an annual re-determination of the
shall identify and provide the planning customer commits to paying the costs conditional period is necessary for a
redispatch or conditional firm options associated with upgrades necessary to bridge product. If the upgrade has not
subject to the following limitation. The provide the service on a fully firm basis, been completed within a three year
transmission provider shall have a the conditions or hours identified by the period, NRECA suggests that the
periodic right to reassess (1) the transmission provider shall remain in customer be required to make a new
planning redispatch required to keep effect until such time as the upgrades long-term firm service request so the
the service firm or (2) the conditions or have been completed. Also, for such provider can update to reflect system
hours under which the transmission customers, the service agreement shall conditions at that time.
provider may conditionally curtail the specify the upgrade costs as determined 964. Several commenters suggest that
service. This reassessment may occur through the facilities study. transmission providers should offer
every two years during the term of the conditional firm service as both a bridge
(A) Eligibility for and Timing of
service, i.e., at the end of year two, year product and as a stand-alone long-term
Planning Redispatch and Conditional
four, year six, and year eight of a ten- firm service.606 Where not used as a
Firm Options
year service. The transmission provider bridge service, several commenters state
may not implement reassessments NOPR Proposal that it should be limited to reservations
during intervening periods nor may it 962. In the NOPR, the Commission that do not have rollover rights.607 Duke
reassess the conditions in order to proposed that customers who request argues that the service duration for non-
amend the service agreement in an long-term firm point-to-point bridge service should be one year, but
intervening year should it forego any transmission service and have the with renewal rights that give the
biennial reassessment.604 service denied because of lack of ATC conditional firm customer a priority
960. The service agreement shall would be eligible to receive planning over other non-bridge conditional firm
specify the relevant congested redispatch service or, if the Commission service customers seeking capacity.
transmission facilities and whether the chose to adopt the conditional firm APPA supports one to two-year service
transmission provider will provide service option, conditional firm service. offers.
planning redispatch, a mix of planning The Commission also proposed earlier 965. In supplemental comments, EEI
redispatch and conditional firm, or evaluation of the planning redispatch supports a voluntary conditional firm
conditional firm in order to provide the option in the system impact study rather product with three types of service: A
point-to-point transmission service. For than in the facilities study. The one-year product with no rollover
the conditional firm option, customers Commission proposed that, if it were to rights; a bridge product for a term of
must choose among and the service adopt conditional firm service, the more than one year that is provided
agreement must specify either (1) evaluation of conditional firm until upgrades necessary to
specific system condition(s) during availability should occur prior to a accommodate a firm service request are
which conditional curtailment may system impact study or facilities study. completed; and a non-bridge product of
occur or (2) annual number of more than one year, with no rollover
conditional curtailment hours during Comments rights or transmission provider
which conditional curtailment may 963. If the conditional firm option is obligation to construct upgrades and
occur. We deem that any service required by the Commission, many subject to the transmission provider’s
agreement that incorporates planning commenters believe it should be a periodic review of its system capability
redispatch or conditional firm options is bridge product to span the gap between to provide such service. EEI contends
a non-conforming agreement and must when the relevant transmission service that the Commission should encourage
be filed by the transmission provider request is being studied and when the transmission providers to offer
pursuant to section 205 of the FPA. relevant upgrades become conditional firm service for more than
Additionally, transmission providers operational.605 These commenters state one year without rollover rights to a
must file with the Commission any that a bridge product is appropriate customer that is not willing to take
amendments to these service agreements because it would not depress funding service of sufficient length to allow
that result from reassessments. If a for new transmission infrastructure and recovery of upgrades costs, if such
transmission provider proposes to would better meet the NOPR’s and service can be provided without
change the redispatch or conditional Congress’ grid expansion objectives. In affecting the reliability and quality of
curtailment conditions due to a their view, use of a bridge product service to firm transmission customers.
reassessment, the transmission provider would avoid equity and free rider 966. In support of limitations on the
must provide the reassessment study to term of conditional firm service, many
605 E.g., Progress Energy Supplemental, PNM-
sroberts on PROD1PC70 with RULES

604 For 606 E.g., Bonneville Supplemental, PPL


example, if a transmission provider opts TNMP Supplemental, LPPC Supplemental, APPA
to forego the reassessment at the end of year two, Supplemental, TAPS Supplemental, TDU Systems Supplemental, EPSA and AWEA Supplemental, EEI
the transmission provider may not reassess the Supplemental, NRECA Supplemental, EEI Supplemental, Barrick Supplemental, and
conditions of the service again until the end of year Supplemental, Entergy Supplemental, Ameren Constellation Supplemental.
four of service for imposition of new conditions Supplemental, Powerex Supplemental, and MISO 607 E.g., Xcel Supplemental, Duke Supplemental,

starting in year five. Supplemental. and EEI Supplemental.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00125 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12390 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

commenters state that analyzing and forecasting the number of hours of should have the option to take short-
modeling system conditions will always conditional firm service requires great term conditional firm service that would
be more accurate in the near term than analysis. To remedy this, Bonneville remain subject to limitation and
in the long term.608 EEI and Community suggests allowing the transmission curtailment if upgrades are too
Power Alliance believe that limitations provider to make conditional firm offers expensive. Constellation proposes that
on system modeling prevent many under which the transmission provider customers taking the longer-term service
transmission providers from accurately could periodically adjust the number of should have the opportunity to show
evaluating their ability to provide conditional curtailment hours. that upgrades would not be just and
conditional firm service over long 968. In supplemental comments, reasonable given the relevant
periods. According to EEI, system Constellation proposes that the circumstances, e.g., the cost of upgrades
conditions change on both the Commission require transmission for a single service request is $300
transmission provider’s and neighboring providers to offer two types of million. If the Commission determines
systems substantially affecting the conditional firm service: service for less that the bridge requirement in a
ability of the transmission provider to than the service term eligible for particular circumstance is unjust and
provide conditional firm service and the rollover rights (e.g., five years) if unreasonable, Constellation proposes
periods such service is subject to customers do not agree to pay for that the transmission provider would
curtailment. While system loads can be transmission upgrades; and service for provide the service for the requested
predicted with a reasonable degree of five years or longer with a rebuttable term, but there would be no obligation
accuracy for more than one year, other presumption that the customer is for the transmission customer to pay for
components of the prediction model, obligated to pay for upgrades that are such upgrades, and the service would
such as transmission and generator both economic and necessary to relieve not be eligible for rollover. NRECA
outages, typically are not determined the constraint that prevents its service contends that instances in which special
more than a year in advance. For from being fully firm.609 EPSA and rules apply should be extremely rare
example, EEI states that members in the AWEA maintain that it is critical that and are best addressed by the
SERC region coordinate transmission the conditions be defined, and remain transmission provider and customers on
and generation outages in a 13-month unchanged, for the term of the service an ad hoc basis.
planning horizon. Duke states that the agreement in order to obtain financing 970. Commenters recognize that
ability to model the system varies of new projects. EPSA and AWEA also upgrades required under a bridge
significantly by region. Entergy and propose that, if the contingency is conditional firm option could create
MidAmerican believe that system removed during the life of the lumpiness problems,613 but most
modeling limitations would present customer’s conditional firm service, the commenters suggest that this problem is
serious reliability problems if service should convert to traditional not unique to the conditional firm
transmission providers were required to firm service. Williams, EPSA and option, nor can it be resolved through
offer a multi-year conditional firm AWEA argue that up-front commitment use of the option.614 These commenters
transmission product because even the to continue the conditions for the support continuation of the
most advanced modeling software entirety of a long-term service Commission’s existing policies with
cannot predict long-term conditions that agreement would take no greater risk regard to lumpiness issues, and some
may affect service. Entergy and than transmission providers take today suggest the need to address the issue as
MidAmerican propose that the in committing to other long-term firm it pertains to all upgrades in a future
Commission allow transmission transmission service. EPSA and AWEA proceeding.615 In contrast, a few
providers to update the curtailment state that limited term conditional firm commenters suggest that the
criteria for a reservation, to reflect, service should pose no problems based Commission should address the
among other things, changing load on system modeling. lumpiness issue with regard to
assumptions and forecasts over time. 969. Several commenters believe that conditional firm service. PPL, EPSA and
MidAmerican argues that without there is no need for any type of special AWEA state that the transmission
annual reevaluation there would be cost rules for conditional firm customers provider should be required to pay the
shifts to other firm customers. In its taking bridge service and required to costs of any incremental lumpiness
reply comments, MidAmerican explains pay extremely expensive upgrades.610 If
associated with upgrades and the
that this reevaluation can only occur the Commission abandons the ‘‘higher
service request. BP Energy contends that
when the actual data becomes available of’’ pricing principle for upgrades, these
any lumpy capacity needs to be resolved
for projecting potential curtailment commenters suggest that any new
on a bilateral contractual basis. Powerex
hours. pricing policies should be consistent
suggests using an ‘‘open season’’ process
967. If a transmission provider offers with cost-causation principles and not
to finance expensive and lumpy
conditional firm service based on result in any improper socialization.611
upgrades. California Commission
specified system conditions, Bonneville Other commenters argue for special
supports prorating large lumpy
states in supplemental comments that rules when upgrades are extremely
limitations on modeling do not present expensive.612 Xcel states that customers 613 In the November 15 Notice, the Commission
a problem. If, however, the service is described an example of lumpy capacity as
based on a maximum number of 609 EPSA and AWEA endorse Constellation’s
upgrades to provide a requested 100 MW of point-
conditional curtailment hours per year, approach in defining and delineating the two forms to-point service that results in 1,000 MW of
of conditional firm service. additional transmission capacity.
Bonneville believes that modeling 610 E.g., Nevada Companies Supplemental, Duke 614 E.g., EEI Supplemental, Xcel Supplemental,
presents problems in offering longer- Supplemental, Bonneville Supplemental, Powerex APPA Supplemental, Bonneville Supplemental,
term service. Bonneville states that Supplemental, BP Energy Supplemental, MISO LPPC Supplemental, NRECA Supplemental,
Supplemental, PNM–TNMP Supplemental, Entergy Progress Energy Supplemental, Duke Supplemental,
sroberts on PROD1PC70 with RULES

608 E.g., Nevada Companies Supplemental, TDU Supplemental, Community Power Alliance Ameren Supplemental, Entergy Supplemental,
Systems Supplemental, LPPC Supplemental, Supplemental, and Southern Supplemental. Community Power Alliance Supplemental, MISO
611 Proposals regarding the ‘‘higher of’’ pricing Supplemental, Williams Supplemental, and PNM-
Ameren Supplemental, Community Power Alliance
Supplemental, MISO Supplemental, PNM-TNMP policy are discussed below. TNMP Supplemental.
Supplemental, NRECA Supplemental, and Xcel 612 E.g., Xcel Supplemental, Constellation 615 E.g., LPPC Supplemental, Bonneville

Supplemental. Supplemental, and NRECA Supplemental. Supplemental, and EEI Supplemental.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00126 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12391

upgrades over a large base of new planning redispatch study provision costs of the conditional firm service to
customers, to the extent that it is non- that would slow the study process. a prohibitive level for little additional
discriminatory and fiscally sound. 974. EEI states that the vast majority benefit to the customer.
971. In supplemental comments, of facilities studies show that the
embedded cost of transmission service Commission Determination
Nevada Companies urge that the time
period of a conditional firm bridge is higher than the incremental 977. As we explain above, the
product should be left up to the amortized cost of upgrades. Thus, EEI Commission finds that both planning
discretion of each transmission argues that the Commission’s proposal redispatch and conditional firm point-
provider. They suggest that most, if not to reform planning redispatch could to-point service must be offered under
all, transmission providers should be lead to uneconomic decisions by the certain circumstances for the provision
able to offer a conditional firm service customer as well as provide of reliable and non-discriminatory
for a one-year period and most should disincentives to upgrade and expand point-to-point transmission service. We
be able to offer it for longer periods. transmission infrastructure.616 In their set forth below the parameters of this
Nevada Companies state that they reply comments, Utah Municipals service, keeping in mind the concerns
should be able to provide conditional respond that most of the time the expressed by commenters.
embedded cost of transmission is higher 978. First, the planning redispatch
firm service in their control areas for
than the costs of upgrades, adding that and conditional firm options need only
longer periods, possibly for up to five
customers find requests for a be made available to customers who
years in some circumstances and in
transmission upgrades to be a time request firm point-to-point service of
certain locations.
consuming and costly impediment to more than a year in duration. When the
972. BP Energy and Williams disagree requested firm point-to-point service is
that conditional firm service should be transmission access. Further, Utah
Municipals add that limited and not available and the customer agrees to
a bridge product. They state that such a a system impact study, the transmission
limitation would provide additional occasional redispatch or curtailment,
would be more economically efficient provider must evaluate the planning
opportunities for undue discrimination redispatch and conditional firm option
and limit competitive alternatives used than the construction of transmission
facilities most of the time. at the customer’s request. If the
to serve customer load. According to customer requests study of the planning
California Commission, conditional firm 975. Several commenters state that it
would be extremely burdensome to redispatch or conditional firm options,
service needs to be available for long- the system impact study must identify
term requests unless there exists a valid, develop, at the system impact study
stage, a reliable estimate of the number the following: (1) The system
proven reason why conditions make it constraints, identified by transmission
physically or economically impossible of hours of redispatch and the cost of
the planning redispatch.617 These facility or flowgate, causing the need for
to guarantee such service. California the system impact study; (2) additional
Commission states that some limitations commenters state that this would
require substantial investment in direct assignment facilities or network
on modeling should be accepted as upgrades required to provide the
justification for not providing probabilistic studies of equipment
availability and extensive training of requested service; (3) redispatch
conditional firm or related services only options, including an estimate of the
if such provisions for load growth are personnel and expansion of data
collection, yet still would not provide incremental costs of redispatch and the
nondiscriminatory, justified and relevant congested transmission
contractually sound. reliable estimates of the number of
hours or costs of the service. MISO facilities for which redispatch will be
973. Commenters take both sides on provided; and (4) conditional firm
states that at a minimum, this would
whether planning redispatch should be options, including the number of
require two years to implement.
evaluated before the customer is conditional curtailment hours and the
976. EEI asserts that conditional firm
obligated to incur the costs and delays specific system conditions during which
service should be determined based on
of a facilities study. EPSA argues that conditional curtailment may occur.
system impact studies and facilities
evaluation prior to a facility study meets Transmission providers may recover the
studies so that the customer can
nondiscrimination requirements given costs of studying these options through
evaluate the costs of upgrades versus the
the methods used by transmission the system impact study agreement.
lack of reliability of the conditional firm
owners to evaluate planning redispatch 979. Second, we adopt limitations on
service. EEI and others also propose that
for their own needs. In its reply the nature of the planning redispatch
conditional firm service only be
comments, Exelon supports the minor and conditional firm options to reflect
available when upgrades cannot be
changes to planning redispatch the two different types of customers that
completed during the term of service or
proposed by the Commission, including may request the service: customers who
during the period prior to completion of
the earlier study of planning redispatch support the construction of upgrades
transmission upgrades.618 In its reply
options in the system impact study, and and those who do not.
comments, Bonneville disagrees that
states that these changes will expand 980. For customers supporting the
conditional firm service should be an
choices for customers. EEI states that construction of upgrades, the planning
interim service available only when the
requiring an offer of planning redispatch redispatch or conditional firm options
customer has agreed to pay for
prior to completion of a facilities study will serve as a bridge until upgrades are
upgrades, stating that such a
would be unduly preferential to point- constructed to remedy the congested
requirement would undercut the value
to-point customers because transmission transmission facilities. For these
of conditional firm service. Bonneville
providers consider the costs of network customers, the transmission provider
adds that, for example, the costs to build
upgrades and the impacts on system must offer planning redispatch or
upgrades in order to resolve a constraint
reliability before choosing planning conditional firm service until the time
in a two-month period could raise the
sroberts on PROD1PC70 with RULES

redispatch for their native load. when the upgrades are constructed. The
Southern points to the internal 616 E.g., Xcel, PPM, and BP Energy.
conditions or redispatch applicable to
inconsistencies of the NOPR that on one 617 E.g., EEI, Southern, TVA, SPP, E.ON, and this period must be specified in the
hand seek to expedite the study process MISO. service agreement and are not subject to
and on the other hand would require a 618 E.g., APPA, PNM–TNMP, and Southern. change. We impose this requirement

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00127 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12392 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

because customers who commit to hours under which the transmission in committing to provide unconditioned
support transmission upgrades are provider may conditionally curtail the firm point-to-point transmission service
typically those financing and service. The customer will receive for a similar period. Planning for
constructing new resources. These service for the requested term unless the reliable service for existing transmission
customers require certainty both with transmission provider determines customers is a difficult process, but it is
regard to upgrade costs and, before through its biennial reassessment that much more difficult to plan over an
upgrades can be constructed, the the firm point-to-point service can no extended long-term period for reliable
redispatch requirements or curtailment longer be reliably provided. The service when the service is firm for most
conditions that may apply to their customer may also choose to terminate of the hours of the year and less firm for
service. We disagree with Williams and the service at the time of reassessment other hours. This is because many
BP Energy that requiring transmission if the service no longer meets it needs. transmission providers use annual
providers to offer this bridge product 982. We select two years as providing hourly peak load for two to 10-year
will present more opportunities for a reasonable balance between the planning purposes. They would need to
undue discrimination. As we note concerns of potential customers and substantially change their planning
above, available information on transmission providers. We recognize methods to ensure no change in service
transmission providers’ current uses of that a shorter period would increase the for a conditional firm customer that is
redispatch and curtailment plans for reliability of predictions, as sought by not expected to be served during the
their retail native load indicates that the certain transmission providers, but find peak hour. We therefore adopt a two
mechanisms are used for relatively short that a two-year period is consistent with year assessment window to provide an
periods of time until upgrades are the bridge concept, given that two years appropriate degree of flexibility for
completed to resolve the transmission is often less than the typical time to transmission providers’ planning needs.
insufficiencies. Comparable services for construct new facilities. While this is a 985. We acknowledge, however, that
long-term point-to-point customers shorter period than some transmission some commenters, such as Bonneville
should therefore be similarly limited to customers would desire, customers who and Nevada Power, state that they may
shorter time periods or otherwise linked require greater certainty over the long- be able to provide conditional firm
to transmission upgrades. term can obtain that certainty by service over a period longer than two
agreeing to support the construction of years, without the need for
981. For customers choosing not to
new facilities. In the long run, all firm reassessment. The Commission
support the construction of new transmission customers, including encourages the provision of planning
facilities, the planning redispatch or conditional firm customers, should redispatch or conditional firm service
conditional firm options also must be support the expansion of the grid to for longer periods where it is practical.
made available as a reassessment reliably serve load. In the event a transmission provider is
product, i.e., subject to certain 983. We decline to adopt any of the able to extend the assessment period,
limitations. Although many suggestions to address unique we will allow the transmission provider
transmission providers argue that circumstances that may arise in which to waive or extend its right to reassess
planning redispatch and conditional upgrades are prohibitively expensive. the availability of the option, provided
firm service should be offered only to Specifically, we will not adopt that the waiver or extension is provided
customers who seek to upgrade the grid, Constellation’s suggestion that consistently for all similarly situated
we disagree. We find that there are customers be able to rebut the service.
legitimate circumstances under which presumption that required upgrades are 986. With regard to timing of the
customers may not choose to support just and reasonable. In this Final Rule, study of planning redispatch and
system upgrades—either because the we provide customers with the option of conditional firm options, the
costs of construction are too high or obtaining planning redispatch or Commission finds that study of both
because the term of service (e.g., less conditional firm service for a long term, options is appropriate in the system
than five years) does not merit the with the ability to roll over a five-year impact study. The obligation for the
construction of additional facilities. We or longer reservation, subject to a transmission provider to study planning
will therefore make planning redispatch limitation that the underlying redispatch options in the system impact
and conditional firm service available to restrictions on the service, i.e., the phase is already present in the existing
such customers, but subject to certain conditions for redispatch or curtailment, OATT.619 The Commission clarifies in
limitations to reflect the nature of the may be reassessed by the transmission this Final Rule the specific requirements
services. Specifically, we must select a provider every two years. We believe necessary to meet this obligation.
limitation on the term for the conditions that this option is superior to that Transmission providers, when
that permit interruption or redispatch, proposed by Constellation because it requested by potential customers, must
given that, for these customers, the term will provide the customer with rollover provide non-binding estimates of the
is not circumscribed by the period rights while ensuring that transmission incremental costs of planning
during which upgrades are constructed. providers can reliably operate their redispatch and identify the relevant
We adopt two years as the appropriate transmission systems. Additionally, congested transmission facilities for
time period to allow the transmission since issues of lumpy capacity are which redispatch will be provided.
provider to reassess the conditions present in the provision of transmission Transmission providers will not be
under which planning redispatch or services generally, we will not address required to estimate the number of
conditional firm service is provided. such issues in this Final Rule as they do hours of redispatch that may be required
The transmission provider will retain not present issues unique to planning to accommodate the requested service as
the right to reassess the planning redispatch or conditional firm options. proposed in the NOPR. The Commission
redispatch and conditional firm option 984. Contrary to the assertion of is persuaded by commenters that such
sroberts on PROD1PC70 with RULES

after the first two years of service, and several commenters, we believe that an estimate is of limited use to potential
every two years thereafter. The transmission providers would take customers and is difficult, expensive
transmission provider shall reassess (1) greater risk in committing to conditions and time consuming for transmission
the redispatch required to keep the for the entire term of a 10-year
service firm or (2) the conditions or conditional option than they take today 619 See pro forma OATT section 19.3.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00128 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12393

providers to calculate with any proposed requiring the transmission transmission service,623 it argues that
accuracy. provider to identify additional the Commission’s proposed expanded
987. Finally, the Commission generators in other control areas that planning redispatch service would slow
disagrees that the study of planning could relieve the constraint. The its batch processing of transmission
redispatch options must necessarily go Commission also requested comment on service, require significant investment
hand in hand with the study of the costs whether the planning redispatch of time to evaluate the options given the
and construction requirements of obligation should be expanded to scope of an RTO, and create speculative
facility upgrades. Again, the obligation require the use of network customer redispatch estimates at best. SPP adds
to study planning redispatch in the resources in addition to transmission that RTOs should simply assist the
system impact study is not new. Our provider resources or expanded to customer with identification of planning
action in reinforcing this existing redispatch options so that the customer
require that transmission providers
obligation cannot violate comparability can bilaterally contract with the
contract to purchase off-system
or, in itself, cause the slowing of study generation owners of its choice.
processes. We have moved to a later resources to facilitate the planning
991. MISO adds that conditional firm
study of conditional firm options so that redispatch.
is inconsistent with RTO market
both options can be studied in tandem. (i) Application to RTOs and ISOs mechanisms, requires burdensome
Furthermore, we note that the structure changes to curtailment protocols and
of the reassessment product requires the Comments
reliability coordinator’s procedures, and
study of both options at the system 989. RTOs state that reforms regarding would impact every tool used in real
impact study phase, since by definition time for congestion management in
planning redispatch and conditional
customers opting for the reassessment RTOs. In its reply comments, MISO
firm services are unnecessary in RTO
product are not likely to enter into a adds that adoption of conditional firm
markets with financial congestion
facilities study agreement. We service would require revisions to seams
acknowledge that the few changes that management because these markets
already provide sufficient redispatch agreement protocols. California
we are making to the planning Commission states on reply that the
redispatch obligation may increase inside RTOs and sufficient
added administrative complexity of
requests for study of the option and interconnection service for generators
conditional firm service is unnecessary
certainly the new conditional firm located at RTO boundaries to address
in the CAISO because the ISO’s
option will need more study than in the the Commission’s point-to-point service
transmission service model makes no
past. While we recognize the tension concerns.621 Ameren and MISO add that
distinction between firm and non-firm
between the adoption of requirements to the options could disrupt the service and provides prospective new
speed study completion and the distribution of financial transmission customers with information to
increase in studies’ complexity caused rights in RTO markets. Others disagree objectively estimate curtailments.
by the conditional firm option,620 we and argue that planning redispatch FirstEnergy and MISO express concern
will not forego a beneficial new option should be used by RTOs to define the regarding disruption of existing RTO
for customers because of this tension. current and future operational communication protocols if these
We expect that transmission providers environment to ensure that systems are services are required in RTOs.
will be diligent in completing the not overbuilt.622 AWEA contends that,
system impact studies and in bringing to since RTOs and ISOs vary considerably Commission Determination
our attention any difficulties in meeting in the services they offer, RTOs and 992. Notwithstanding the
deadlines caused by the study of the ISOs should be required to demonstrate requirements of section IV.C of this
two options. that their services are consistent with or Final Rule, the Commission finds that it
(B) Who Must Provide Planning superior to planning redispatch and would be inappropriate to require RTOs
Redispatch and Conditional Firm conditional firm services. In particular, and ISOs with real-time energy markets
AWEA argues that RTOs that do not to adopt the provisions for conditional
NOPR Proposal provide financial rights should be firm point-to-point service. Customers
988. In the NOPR, the Commission required to provide both of these transacting in RTOs and ISOs are able
requested comment on the applicability services. Exelon states on reply that the to buy through transmission congestion
of these two options to transmission Commission has proposed minor in the RTOs’ real-time energy markets
providers who operate as RTOs and changes to the existing planning and need no prior reservation in order
ISOs. The Commission also requested redispatch requirement that should not to access transmission. Voluntary
comment on which resources should be be impractical or too burdensome for curtailment in order to access
required in the provision of planning RTOs to administer. transmission is thus not an attractive
redispatch. First, the Commission option given the range of options
proposed that the planning redispatch 990. In its reply comments, California available for customers transacting in
requirement apply to the redispatch of Commission adds that capping the RTOs and ISOs. Further, in RTOs and
the transmission provider’s own frequency or costs of redispatch in an ISOs with financial transmission rights,
generation resources, but not to obligate RTO market would inappropriately shift conditional firm service may disrupt the
transmission providers to purchase new the costs of congestion to others. distribution of these rights. We therefore
resources to provide the service. If a Although SPP has successfully used believe that there is no need to reform
transmission provider cannot planning redispatch to facilitate short- existing RTO and ISO procedures to
accommodate a long-term firm point-to- term firm transmission service and to satisfy concerns underlying the
point transmission request through address interim circumstances adoption of the conditional firm option.
planning redispatch, the Commission associated with long-term firm 993. The Commission directs,
sroberts on PROD1PC70 with RULES

however, RTOs and ISOs that already


620 In section V.D.5.a, we adopt a requirement 621 E.g., MISO, PJM, California Commission, and

that transmission providers post metrics on their ISO New England. 623 Citing Attachment AC of the SPP OATT

performance in processing system impact studies 622 E.g., AWEA, Indianapolis Power Reply, and (Optimal Reservation Processing Method for Short
and facilities studies. Exelon Reply. Term Firm Transmission Services).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00129 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12394 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

provide planning redispatch pursuant to system constraints, including not only adoption of such a market would raise
section 13.5 of the pro forma OATT to the transmission provider’s own significant political opposition and be
modify the relevant provisions of their resources and those of its network contrary to the Commission’s
tariffs consistent with our directives in customers, but also all non-affiliated commitment in the NOPR to avoid such
this Final Rule.624 RTOs and ISOs need resources both within and outside its restructuring.
not amend their tariffs if the footprint that choose to be included.627 999. EPSA, AWEA and PJM support
Commission has previously found that EPSA explains that this redispatch such market development. When a
these tariffs were just and reasonable would: Require transmission providers generator in another control area is
without the inclusion of pro forma to solicit offers from resources to called upon to relieve a constraint in
section 13.5 planning redispatch provide energy and perhaps ancillary regions not administered by an RTO,
provisions. We will not require services; be based on a resource’s offer PJM states that the Commission must
incorporation of the more limited of service and take into account direct the development of an alternate
planning redispatch obligations adopted generating resource and transmission LMP pricing scheme to establish
in this Final Rule if RTOs and ISOs have operating limits; include performance ‘‘system marginal costs’’ that are
already been excused from the planning assurance terms, unit commitment consistent with transparent generator
redispatch obligations of the existing procedures, billing, compensation and pricing in RTO markets. EPSA and PJM
pro forma OATT. bidding protocols, confidentiality argue that vertically integrated utilities
(ii) Generation Resources Required for protections, and information-sharing in non-RTO areas should turn over
Planning Redispatch protocols; and dispute resolution functional control of their dispatch
procedures to avoid disputes rising to function to a disinterested entity or
Comments the level that would require judicial or replicate the transparency by publishing
994. Most commenters agree that regulatory intervention. AWEA supports generation dispatch. EPSA suggests that
resources in addition to the Deseret’s OATT provisions that require the Commission require this
transmission provider’s resources can the transmission provider to relieve transparency to ensure
and should participate in the provision constraints by the least cost means, nondiscriminatory redispatch.
of planning redispatch. Commenters whether by seeking a change in 1000. A few commenters state that
differ as to whether this participation generation output from the transmission any requirement for the transmission
should be mandatory or voluntary. A provider’s merchant function or from provider to purchase generation from
few commenters maintain that any other feasible generator. Williams outside the control area to facilitate
participation by resources outside the suggests that independent generators planning redispatch is functionally
transmission provider’s control area must be allowed to participate in the unworkable and would adversely
could have adverse impacts on provision of planning redispatch service impact reliability.628 EEI supports the
reliability in the control area.625 through submission of a formulary rate Commission’s proposal to have
995. In arguing for mandatory to the transmission provider. If the transmission providers identify off-
participation, EEI and others contend Commission intends to have non- system resources that could provide
that all generation resources owned or affiliated generators participate in planning redispatch but requests
operated by all jurisdictional planning redispatch, PPL states that the clarification that no additional
transmission customers in the control Commission should require investigations or studies are required to
area or balancing authority area should transmission providers to negotiate identify these additional options.
be obligated to redispatch to agreements with generators on their MidAmerican adds that the coordinated,
accommodate new requests for service systems. open and transparent planning
in order to avoid undue 997. TranServ, MidAmerican, and provisions of the NOPR should provide
discrimination.626 Exelon argues that Nevada Companies support a planning customers with the ability to identify
transmission providers should redispatch service similar to that off-system resources. EEI and Southern
redispatch resources of its network employed by the Mid-Continent Area state that any redispatch on adjacent
customers, subject to appropriate Power Pool, whereby customers arrange systems should be arranged by
compensation. SPP contends that for their own redispatch through transmission customers and the service
generation affiliated with transmission bilateral or centralized energy markets should be curtailed prior to other firm
owners that have transferred functional and submit plans for approval to their uses of the system if the off-system
control of their transmission assets to an transmission provider and reliability generator fails to perform. WAPA and
RTO should not have any greater coordinator. Bonneville argue against the use of off-
planning redispatch obligation than 998. Several commenters discuss the system redispatch, stating that lack of
unaffiliated generation. In its reply need for market development in control over these resources could cause
comments, Entergy states that the conjunction with the planning reliability problems on the originating
Commission at a minimum should redispatch obligation. TranServ and transmission system. WAPA also
continue to allow network customers to Xcel state that the planning redispatch believes that off-system redispatch
request that transmission providers option may force transmission providers would not provide the price certainty
redispatch network customer resources without generation assets to develop needed by customers because the
in order for the customer to designate a some form of energy market to arrive at redispatched megawatts will differ
new network resource. the costs of redispatch. Southern and based on the transmission system
996. Others argue for a least-cost Progress Energy add that forced parameters, and customers would be
economic dispatch to relieve real-time required to pay for any loop flow
627 E.g., AWEA, Project for Sustainable FERC resulting from the off-system redispatch.
624 This includes the transmission provider’s Energy Policy, Exelon, Powerex, Constellation, 1001. In its reply comments, EEI adds
sroberts on PROD1PC70 with RULES

obligation to post monthly redispatch costs for each Williams, Sempra Global, PJM, EPSA, and Entegra
transmission facility over which planning and that a requirement for transmission
Reply. Sempra Global contends that the
reliability redispatch are provided. Commission should require transmission providers providers to solicit planning redispatch
625 E.g., Ameren, PNM–TNMP, Xcel, and WAPA.
to offer redispatch of non-affiliated resources both
626 E.g., Southern, FirstEnergy, MidAmerican, and within and outside its footprint, subject to pre- 628 E.g., Xcel, PNM–TNMP, and Public Power

Community Power Alliance. existing contractual commitments. Council Reply.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00130 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12395

proposals from generators inside and in order to accommodate long-term firm with the transmission provider to
outside their control areas would point-to-point service. We note that this ensure that reliability is maintained.
require that transmission personnel information is readily accessible by the 1007. We therefore direct in this Final
become involved in generation and transmission provider, as it is the same Rule that transmission providers work
power sales matters in violation of the information used to determine pro rata with customers to facilitate the use of
Commission’s Standards of Conduct. curtailments of firm resources in
third party generation, where available,
Duke argues on reply that such an contingency situations.
approach would require that third party 1004. In addition to identifying in provision of planning redispatch.
generators reveal their costs to the generation resources within the control This entails review of redispatch plans
transmission provider and that a means area, the Commission also requires submitted by customers, coordination
of estimating costs for all generators identification of resources outside the between the transmission provider and
subject to planning redispatch would control area that may be able to relieve reliability coordinator, and signaling
need to be set forth in the pro forma congested transmission facilities. To the third party generators when the
OATT. extent the transmission provider is redispatch is needed. These
1002. LPPC, APPA and TAPS oppose aware of generation resources outside of arrangements will require close
any requirement that transmission its control area that can relieve the coordination between the transmission
providers redispatch their network constraint, the transmission provider provider, third party generators and
customer’s resources as well as their must inform the customer of these transmission customers. The
own to provide planning redispatch, resources. To be clear, this does not arrangements must be sufficiently
stating that this action would require the transmission provider to detailed to allow the transmission
appropriate resources beyond the undertake any additional investigation provider to maintain reliability.
Commission’s jurisdiction, result in or study to identify generation options Although we will not allow
endless conflict between transmission located outside of the control area. To transmission providers to unreasonably
providers and resource owners, and the extent the transmission provider has deny customers the use of third-party
interfere with network customer’s use of such information, however, it must resources to provide planning
their limited resources. provide it to the customer. redispatch, it is the customers’ ultimate
Commission Determination 1005. The Commission will not responsibility to ensure that all the
mandate the use of network customer necessary contractual and technical
1003. Order No. 888 compelled resources or other third party resources
transmission providers to provide arrangements are in place to maintain
in the provision of planning
planning redispatch from their own reliability. We clarify for Entergy that
redispatch.630 If they choose, network
resources.629 The Commission declines this would allow transmission providers
customers and third parties may
to expand that obligation to require to continue to provide planning
voluntarily provide planning redispatch
transmission providers to solicit third redispatch for network customers from
services. A seller is free to post its price
party resources in order to provide the network customers’ resources. We
to relieve a specific congested
planning redispatch. We will, however, also clarify that transmission providers
transmission facility and its ability to
require transmission providers to may curtail transmission customers if a
relieve the congestion. To facilitate
identify in the system impact study (1) third-party resource fails to perform its
provision of such service by third
generation resources located within the contractual redispatch obligation. This
parties, we direct transmission
transmission provider’s control area, or any other remedy for non-
providers to modify their OASIS sites to
including its own resources, that can performance must be specified in
allow for posting of these third party
relieve the congested transmission
offers. Accordingly, we direct writing between the parties prior to
facility at issue, and (2) the impact of
transmission providers to work in commencement of the service.
each identified resource on the
congested facilities, e.g., the generator conjunction with NAESB to develop 1008. For the reasons discussed below
shift factor. The resources identified in this new OASIS functionality and any regarding the TDA proposal, we decline
the system impact study need not be necessary business practice standards. to adopt the bid-based redispatch model
available to provide the redispatch. Transmission providers need not suggested by EPSA. In section V.C.1 of
Customers must simply be provided implement this new OASIS
this Final Rule, we similarly reject
with the set of generators that could, if functionality and any related business
proposals to impose LMP and
available, make a significant practices until NAESB develops
independent control of the dispatch
contribution toward relieving the appropriate standards.
1006. Customers may then contract in function. We believe that a bid-based
constrained facility at issue. This generation market design is not
information, in addition to the advance with these third parties or use
their own resources to secure planning necessary to remedy undue
information provided through discrimination in the provision of
congestion planning studies, will redispatch services in lieu of or in
addition to service from the transmission service. We also believe
provide the necessary information to that our modifications to the planning
customers wishing to solicit third party transmission provider. In this way,
customers can arrange for their own redispatch requirement, including the
resources to relieve congested facilities
planning redispatch through bilateral OASIS changes directed herein and the
629 See pro forma OATT section 13.5. With markets and submit plans for approval requirement that transmission providers
respect to SPP’s assertion that transmission owners’ to their transmission provider and make available information on
affiliated generation should have no greater reliability coordinator. The generators capable of providing
redispatch obligations than unaffiliated generation arrangements must, however, be planning redispatch, will provide
in RTOs, we find that relevant redispatch
sufficiently detailed and coordinated
sroberts on PROD1PC70 with RULES

obligations in the RTO tariff and transmission potential customers with greater
owners’ tariffs govern this issue. See Southwest information about redispatch choices
Power Pool, Inc., 110 FERC ¶ 61,133 at P 17 (2005) 630 Network customers will continue, however, to
and enable greater opportunities for
(rejecting proposed provisions that would have be obligated to make their network resources
removed the obligation for transmission owners to available to the transmission provider for reliability planning redispatch and comparable
provide planning redispatch). redispatch in real time. service.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00131 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12396 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

(C) Pricing of Planning Redispatch providing customers a practical way to or fixed rate contracts for actual
NOPR Proposal verify that claimed redispatch costs redispatch agreed to at the time of
have actually been incurred. PGP states contracting; and redispatch costs
1009. In the NOPR, the Commission that the Commission should allow for provided from a third-party provider.
sought comment on which type of regional differences in planning Morgan Stanley opposes ‘‘higher of’’
redispatch pricing would ensure redispatch pricing. APPA does not pricing that would allow for monthly
effective use of the planning redispatch support a departure from the current charges for redispatch costs or long-term
option. The Commission described one redispatch pricing approach, while firm transmission service rate.
type of pricing, a formula rate, to Seattle states that the existing section 1015. In contrast, many transmission
include a MW quantity, the incremental 13.5 is unworkable because the cost of providers and EEI ask the Commission
cost of fuel at the point of delivery, and planning redispatch is difficult to to allow for recovery of actual costs of
the decremental cost of fuel at the point calculate for both historical and near- redispatch, rather than the estimated
of receipt capped at the price of fuel. term operating horizons, much less over costs, with the customer obligated to
The Commission sought further a multi-year planning horizon. pay all costs.635 Since providing
comment on whether it would facilitate 1013. EPSA and AWEA believe that accurate estimates of redispatch costs
planning redispatch to base calculations the pricing mechanisms suggested in the and hours are difficult, especially with
of the various costs for input into the NOPR would be open-ended and highly respect to longer-term service requests
formula on the difference between the variable over the duration of the given the variability of fuel costs,
cost of ramping up a generator at the reservation and, thus, not meet the transmission providers contend that
point of delivery and ramping down a needs of customers. EPSA and AWEA they should not bear the risks of
generator at the point of receipt. The assert that, consistent with Commission inaccurate cost estimates for a service
Commission also described a redispatch precedent,633 a utility must identify and that benefits only the point-to-point
pricing proposal to calculate redispatch justify its costs in excess of average customer.636 Indianapolis Power adds
charges monthly and charge the higher system costs before service commences that planning redispatch should be
of actual redispatch costs or the OATT in a manner that meets the customer’s priced to discourage inefficient dispatch
rate each month made by PacifiCorp in needs to charge a rate in excess of of generation. In its reply comments,
response to the NOI. average system costs, i.e., some PPM agrees that planning redispatch is
Comments customers may require a firm estimate unworkable without certainty of cost
upfront to obtain financing while others recovery for the transmission provider,
1010. While many specific comments may be willing to negotiate a rate based but believes that with enough
were received on the pricing of planning on estimates.634 EEI states on reply that information customers can evaluate the
redispatch service, there is little the policy in American Electric Power risks and gain certainty required for a
consensus on this subject. Several related to an expansion cost rate, which workable product.
commenters state that pricing is inapposite to redispatch costs because 1016. Southern argues that the current
challenges associated with planning the costs of new construction are easier pro forma OATT language unreasonably
redispatch are difficult if not to estimate in advance than are the costs places the risk of uncertainty in
insurmountable.631 of planning redispatch. EEI contends estimating redispatch costs on the
1011. MidAmerican and EEI argue transmission provider and its native
that the planning redispatch customer’s
that the current cap on planning load customers, contrary to basic cost
interest in price certainty is not a
redispatch at the costs of upgrades causation principles and native load
sufficient basis for shifting costs to other
should be removed because a customer protections in Order No. 888. Southern
customers or to the transmission
will always choose planning redispatch suggests that the Commission follow the
and the risks that redispatch costs provider.
1014. EPSA and AWEA suggest that, approach in the Deseret and SPP tariffs,
exceed construction costs falls to the which allow for the transmission
when the cost of planning redispatch is
transmission provider and is either provider to recover its actual costs of
estimated to exceed the transmission
unrecoverable or passed on to other redispatch. Ameren states that a
rate, the transmission provider should
customers. standard per kWh fee is simpler to
1012. According to several offer either: a formula rate for
incremental redispatch costs with the administer, but should be structured to
commenters, requiring the transmission recover all of the costs of planning
provider to establish a standard fee for number of hours of redispatch, the
resources to be redispatched and the redispatch, including opportunity costs.
planning redispatch, either on the 1017. Various commenters argue that
overall system or on a path-by-path conditions under which redispatch
would occur defined in advance or, an the Commission should allow the
basis, would accomplish cost certainty following redispatch costs to be
for the customer and hold the incremental cost rate determined at the
time of the reservation to cover the recovered: Fuel; variable operations and
transmission provider accountable for maintenance; increased maintenance
the accuracy of the studies used to reservation period that may include a
risk adder for the transmission provider. costs due to cycling; start-up and ramp-
assess redispatch requirements.632 down costs; emergency purchases; costs
These commenters support a Morgan Stanley argues that planning
redispatch options should include the of additional operating reserves;
standardized formula-rate for planning environmental costs; and lost
redispatch or a capped amount at, or following: Redispatch priced at a market
index; where market prices are not opportunity costs.637 MidAmerican also
close to, the embedded cost rate. Entegra argues that a transmission provider
and TransAlta state that the redispatch available, the price should be the
incremental costs; full cost pricing should be able to recover the costs of
pricing proposal may allow
transmission providers discretion to should be allowed for ‘‘life of service’’
635 E.g., Southern, MidAmerican, Entergy,
charge redispatch costs without (total dollar cost for unlimited
sroberts on PROD1PC70 with RULES

FirstEnergy, Ameren, Nevada Companies, E.ON,


redispatch over the term of a contract) and South Carolina E&G.
631 E.g., Powerex, Manitoba Hydro, Seattle, 636 E.g., EEI, Entergy, LPPC, NRECA,

NRECA, Ameren, and E.ON. 633 American Electric Power Service Corp, 64 MidAmerican, Ameren, and FirstEnergy.
632 E.g., Utah Municipals, Public Power Council, FERC ¶ 61,279 (1993) (American Electric Power). 637 E.g., LDWP, EEI, Ameren, MidAmerican, and

PPM, Entegra, Constellation, TransAlta and TAPS. 634 Id. at 62,976. Southern.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00132 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12397

redispatch energy purchased in Commission Determination cap does not serve as an incentive for
response to a pre-schedule by a 1021. Although there is no consensus expansion because the transmission
planning redispatch customer regardless regarding which form of pricing provider already will have started the
of schedule changes by the customer methodology is most appropriate for process of building transmission
and regardless of any pro rata planning redispatch service, there is facilities for the customer who opts for
curtailments affecting such customers general agreement among the the bridge product. If planning
due to system reliability. commenters that the current pricing redispatch is provided as part of a
rules fail to meet the needs of either reassessment product, the customer has
1018. EEI and Southern argue that
customers or transmission providers chosen not to pay for upgrades and thus,
customers that choose planning
and consequently fail to make planning the expansion cost cap cannot provide
redispatch should pay the cost of an incentive for transmission expansion.
transmission service and the cost of redispatch an attractive means for
customers to obtain access to the grid. 1024. We will therefore adopt a new
redispatch. EEI asserts that allowing pricing methodology. We believe that
recovery of both costs is not prohibited Transmission providers and customers
both express concern regarding the the PacifiCorp proposal described in the
‘‘and’’ pricing because the services NOPR is the one that balances the
differ, as one is provided by the variability of redispatch costs.
Customers worry that actual redispatch competing concerns of transmission
transmission system and one is customers and transmission providers.
costs may greatly exceed estimates and
provided by generators, and native load Under this pricing methodology,
thus seek cost certainty over the term of
and network customers pay pro rata customers will have the option of
the service. Conversely, transmission
shares of reliability redispatch costs to paying (1) the higher of (a) actual
providers claim that accurately
relieve constraints on the system as well estimating future redispatch costs for incremental costs of redispatch or (b)
as the basic costs of transmission long duration service is extremely the applicable embedded cost
service. TAPS and TDU Systems take difficult. In fact, transmission providers transmission rate on file with the
the opposite view and state that the state that the uncertainty in forecasting Commission or (2) a fixed rate for
Commission should require planning long-term redispatch costs is much redispatch to be negotiated by the
redispatch pricing consistent with the greater than any uncertainty inherent in transmission provider and customer and
Commission’s ‘‘higher of’’ or ‘‘or determining the costs of transmission subject to a cap representing the total
pricing’’ policy. In addition, they state upgrades. fixed and variable costs of the resources
that the redispatch charges must be 1022. The Commission has carefully expected to provide the service. If the
capped up front at fixed dollars and considered these comments and agrees customer selects the higher of
hours at or close to the embedded cost that the current method for pricing incremental cost or the embedded-cost
rate. planning redispatch service is no longer rate, the transmission provider shall
just, reasonable or not unduly calculate the costs of redispatch
1019. Arkansas Commission agrees monthly and charge the higher of
with the PacifiCorp pricing method in discriminatory. The Commission takes
three principal actions to address the redispatch or the embedded cost rate
which redispatch costs are recalculated each month.
monthly and customers are charged the concerns of customers and transmission
providers. 1025. We have selected a monthly
higher of the redispatch cost rate or the comparison of embedded costs and
1023. The Commission therefore
monthly OATT transmission rate. TAPS redispatch costs on the basis of a
adopts a new pricing method for
states that this method avoids ‘‘and’’ number of factors. The Commission has
planning redispatch service. We will no
pricing, but does not address the longer require the capping of redispatch rejected basing the comparison on the
complexity or risks associated with costs over the term of the service at the life of a long-term firm transmission
determining redispatch costs over a long costs of expansion. This change is contract.639 For administrative
period. APPA argues that the PacifiCorp inextricably linked with the change in efficiency, a transmission provider
proposal, if applied after the fact, could the obligation to provide planning should be allowed to close its books and
lead to uncertainty and disruption of redispatch, i.e., the removal of the open- not be subject to possible refunds or
market transactions. Southern opposes ended requirement to provide planning surcharges at the end of its billing cycle.
any pricing method that caps the total redispatch as long as it is more The standard billing cycle in the
costs that a planning redispatch economical than transmission upgrades. industry is one month. Allowing
customer would bear, including the We have shortened the planning transmission providers to finalize
PacifiCorp proposal, stating that caps redispatch obligation to apply before accounting entries will provide
allow the planning redispatch customer upgrades are built as a bridge product or certainty to both the transmission
to shift costs to the transmission to apply as part of a reassessment provider with regard to revenue
provider and its native load customers. product. In prior cases, the Commission recovery and to the transmission
expressed the view that capping cost customer with regard to cost exposure.
1020. E.ON points to an inherent We therefore find that a monthly
problem in planning redispatch pricing: recovery for long-term transmission
service at the costs of expanding the comparison of embedded and
Transmission providers should be kept incremental cost is appropriate. This
whole with regard to actual real-time transmission system provides an
incentive for transmission providers to method retains ‘‘higher of’’ pricing for
redispatch costs but customers may not customers, but does not subject
know until after the fact that the undertake expansion when it is
warranted.638 The expansion cost cap transmission providers to open-ended
planning redispatch was not economic liability for refunds and otherwise
should not be applied to the bridge
for their purposes. E.ON foresees should make planning redispatch
product because (1) upgrades will in
difficulty in allocating redispatch costs service more attractive for transmission
fact be constructed and should be paid
sroberts on PROD1PC70 with RULES

among multiple planning redispatch for by the customer under the ‘‘higher providers to provide. Further, given that
service customers and requests that the of’’ policy, and (2) an expansion cost redispatch often occurs only in selected
Commission adopt a specific time periods within a year (e.g., during
methodology for calculating each 638 See, e.g., Florida Power & Light Co., 70 FERC

request’s impact on the system. ¶ 61,158 at 61,484 (1995). 639 Id. at 61,483.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00133 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12398 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

the peak season, shoulder months, etc.), reject EEI’s assertion that we should can be gained by funding the upgrades
it is just and reasonable to allow the adopt such pricing because native load to remove the constraint that is causing
transmission provider to perform the and network customers pay a load ratio the transmission provider to incur
higher of calculation in each month share of redispatch costs and the redispatch costs.
when the service is provided, not spread embedded cost transmission rate. (D) Standards of Conduct and Planning
those costs over the entire year. Planning redispatch differs from the
1026. For purposes of calculating Redispatch
reliability redispatch for which
planning redispatch charges, transmission providers are only NOPR Proposal
incremental costs shall include fuel or obligated to provide network customers 1030. In the NOPR, the Commission
purchase power costs caused by with ability to avoid real-time requested comment on the interaction of
ramping up generator(s) at the point of curtailments. Rather, planning planning redispatch requirements with
delivery and ramping down generator(s) redispatch is a means of creating the Commission’s Standards of Conduct.
at the point of receipt. Additionally, additional transmission capacity,642 not
where applicable, transmission a generation service, and thus planning Comments
providers may specify in customer redispatch is appropriately priced by 1031. Commenters generally argue
service agreements other incremental applying the Commission’s ‘‘or’’ pricing that the independent functioning
costs for inclusion in the monthly actual policy. We decline to revisit that requirement and the information
incremental costs, including longstanding policy in this rulemaking. sharing prohibitions under the
opportunity costs. Identification and 1029. With respect to concerns that Standards of Conduct are irreconcilable
derivation of these costs must be the expansion cost cap was adopted to with the expanded planning redispatch
included in the service agreement. We provide rate certainty to customers over proposal in the NOPR.644 Southern,
reiterate our existing requirement that the term of the service,643 we believe TranServ and Progress Energy contend
all information necessary to calculate that the modified pricing policy adopted that the planning redispatch option
and verify opportunity costs must be here will continue to provide would require close coordination and
made available to the transmission appropriate certainty to customers, communication with market
customer.640 We clarify that the actual while also allowing transmission participants including the marketing or
costs of redispatch need not be providers to recover just and reasonable energy affiliate, which may create
determined annually or at the time that costs. For customers purchasing the confidentiality and Standards of
the service agreement is executed; bridge product, the cost of redispatch Conduct problems. For instance, they
rather, actual redispatch cost should be will be incurred only during the initial state that close coordination and sharing
determined on a monthly basis. term of the service agreement while new of non-public transmission and
1027. With respect to MidAmerican’s facilities are being constructed. During customer information would be required
request to be able to recover the this term, the cost of redispatch service to determine the generating units that
purchase power costs for a customer represents a legitimate cost of providing can be redispatched, the impact that
requiring planning redispatch, we the service and therefore should be fully planned and forced outages of
reiterate that transmission providers are recoverable under the higher of policy. redispatched generators will have on the
under no obligation to purchase power Although it is true that redispatch costs availability of transmission service and
to provide planning redispatch services. are difficult to project, and hence create the transmission line loadings, and the
Should the transmission provider take uncertainty for customers, this does not costs of redispatch. Some commenters
on the obligation to contract with a third mean that the transmission provider request that the Commission adopt an
party to provide planning redispatch at should not be allowed to recover the exception to the Standards of Conduct
the customer’s request, however, the legitimate and verifiable costs of to permit communication between
customer should be obligated to pay the providing the service. Moreover, if the transmission providers and marketing
purchase power costs, including any customer desires greater certainty and energy affiliates, acting as
reservation charge for the power. The regarding redispatch costs during this generation operators, for the
flow-through of purchase power costs period, it can elect the fixed rate option transmission provider to instruct the
must be negotiated between customers discussed above and negotiate a fixed generation operator to vary its
and transmission providers in a stand- redispatch charge with the transmission generator’s output.645
alone agreement if the transmission provider. Once upgrades are 1032. MidAmerican suggests that it is
provider agrees to make purchases on constructed, however, the customer will unlikely that any communication
the customer’s behalf. receive the certainty of paying a fixed protocols could be established that
1028. The Commission will not adopt rate for transmission costs and, would both comply with the
proposals suggested by several importantly, any expansion cost will be Commission’s current Standards of
transmission providers to allow for fixed at the time the initial service Conduct and permit a transmission
recovery of the embedded cost agreement is signed. Finally, for provider to coordinate with its
transmission rate and the full costs of customers who do not select the bridge marketing affiliate employees to arrange
redispatch. The Commission’s ‘‘higher product because they do not want to planning redispatch. Rather,
of’’ pricing policy prohibits the fund upgrades, it would be MidAmerican argues that the
transmission provider from charging unreasonable to cap the cost of transmission customer would have to
both embedded costs and incremental redispatch at the cost of upgrades. In waive the Standards of Conduct to
costs such as redispatch costs.641 We such an instance, the customer has enable the transmission function
elected to forego the price certainty that employees to share the necessary
640 See Order No. 888 at 31,740. information with their marketing
641 See Pennsylvania Electric Company, 58 FERC
affiliate counterparts.
sroberts on PROD1PC70 with RULES

¶ 61,278, 62,871–75, reh’g denied, 60 FERC ¶ 61,034 the Commission will not authorize ‘‘and’’ pricing,
(1992), aff’d sub nom. Pennsylvania Electric Co. v. i.e., embedded cost pricing plus opportunity
FERC, 11 F.3d 207 (D.C. Cir. 1993); see also Entergy (incremental) cost pricing.’’). 644 E.g., Nevada Companies, Community Power
642 Order No. 888A at 30,267. Alliance, Progress Energy, LPPC, Southern, WAPA,
Services, Inc., 71 FERC ¶ 61,139, 61,452 (1995)
(regarding the pricing of redispatch service, the 643 Florida Power & Light Co., 70 FERC ¶ 61,158 and APPA.
Commission stated ‘‘[i]t is a well-settled matter that at 61,483 (1995). 645 E.g., E.ON, Ameren, and APPA.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00134 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12399

1033. Other commenters argue that providers to evaluate the future as firm. The curtailment priority during
violations of the Standards of Conduct availability of redispatch and estimate the conditional period was proposed as
can be avoided by various means. PPM the costs of redispatch, they need only the same as secondary network service.
suggests that publication of redispatch tell the marketing affiliate which of its The Commission proposed that
costs similar to ancillary service costs generators would be suitable for customers using the conditional firm
and elimination of case-by-case sharing redispatch, thus identifying those that option would pay the long-term firm
of information between the transmission require study. This sharing of point-to-point rate. The Commission
provider and the generation operators information relating to the marketing also proposed that conditional firm
would avoid Standards of Conduct affiliate’s generation is not prohibited by service qualify for rollover rights,
issues. MidAmerican states that sole the Commission’s Standards of Conduct. provided that it meets the other rollover
reliance upon bilateral agreements with 1036. In addition, the transmission right conditions proposed in the Final
third parties to provide planning provider may also need to provide its Rule.
redispatch would resolve the need to marketing affiliate with transmission-
modify the Standards of Conduct. In related information from the (i) General Terms and Conditions
their reply comments, Utah Municipals transmission customer’s service request, Comments
state that they do not believe the such as service quantity and term, to
1038. Most commenters support
Standards of Conduct pose a barrier to determine the required duration and
pricing conditional firm service at the
provision of planning redispatch since amount of the redispatch required. We
long-term firm OATT rate and no
transmission providers redispatch to find that such information provided
commenter suggested a different pricing
serve their own loads currently, but that from the transmission provider to the
method. Nevada Companies and
if so the Commission should make small marketing affiliate is not a prohibited
Bonneville state that the customer
modifications to the standards. transfer of non-public information
because such details of the transmission seeking conditional firm service should
Commission Determination customer’s service request are available pay the actual costs of the study
1034. The Commission does not via OASIS. The only customer required to provide the number of
believe that any changes to its Standards transmission request information not conditional curtailment hours.
of Conduct are required for transmission readily available via OASIS is the 1039. EPSA and AWEA support the
providers to implement the planning source and sink information.647 We see following components of the
redispatch provisions adopted in this no need for the transmission provider to Commission’s conditional firm
Final Rule. The information at issue, provide such masked source and sink proposal: Conditional firm is available
e.g., generation redispatch cost, is held transmission information to its only to customers that first request long-
by the marketing affiliate and there is no marketing affiliate as part of this term service; it would provide a year
prohibition under our Standards of redispatch evaluation process. We do round, long-term product that is firm
Conduct on the marketing affiliate not believe that any further information during all hours of the year except at
transferring such information to the need be provided by the transmission well-defined periods when the
transmission provider. The information provider to their marketing affiliates to transmission provider is unable to
sharing prohibitions under the evaluate the generators available for provide the service; and, in all hours
Standards of Conduct are ‘‘one way,’’ planning redispatch and their costs. that are not conditional, conditional
i.e., they restrict only communications Accordingly, we find there is no need to firm service would be treated as any
of non-public transmission information create an exception to the Standards of other firm service with the same
from the transmission provider to the Conduct for the sharing of this curtailment priority as long-term firm
marketing affiliate, not vice versa. generation-related information and network and point-to-point rights.
Therefore, the flow of information from 1040. EEI proposes that conditional
publicly available transmission
marketing affiliates to transmission firm service be firm in periods when
customer request information.
providers relating to the costs and firm service is available according to
availability of generation resources for (E) Attributes of Conditional Firm ATC calculations and non-firm, with a
planning redispatch is not prohibited NOPR Proposal monthly non-firm curtailment priority,
under the Commission’s Standards of for periods when firm ATC is not
1037. In the NOPR, the Commission available. CREPC, Exelon and
Conduct.646
1035. We next turn to the flow of described conditional firm service as a MidAmerican argue that the
information from the transmission modified form of point-to-point service Commission should not require
provider to the marketing affiliate. that includes non-firm service in a conditional firm service until all
Initially, in order for transmission defined number of hours of the year attributes of the service are clearly
providers to evaluate planning when firm point-to-point service is not defined and key implementation issues
redispatch options, they must identify available. The Commission proposed are resolved, including modification of
the impacted transmission facilities, that the conditional firm service NAESB and NERC processes. NAESB
e.g., flowgates, and determine the agreement would identify the states that the Commission can reduce
marketing affiliate’s generators that conditional curtailment hours and the amount of time required to develop
could provide redispatch over those include an annual or monthly cap on OASIS and transmission loading relief
facilities. Transmission providers those hours. The Commission further protocols by clearly defining the
already have this information to enable proposed that conditional firm service conditional firm service.
them to provide least cost reliability would be curtailed before firm uses 1041. In its supplemental comments,
redispatch. However, transmission until such times as the conditional EEI states that the Commission should
providers need not provide information curtailment hours were exceeded, after not require all transmission providers to
which time the service would be treated
sroberts on PROD1PC70 with RULES

regarding the impacted transmission adopt terms and conditions for


facilities to its marketing affiliates. 647 See Open-Access Same-Time Information
conditional firm service that are only
Rather, in order for transmission System and Standards of Conduct, 83 FERC
workable for some systems, e.g.,
¶ 61,360 at 62,456 (1998), reh’g denied, 86 FERC transmission providers in the Western
646 18 CFR 358.5. ¶ 61,139, reh’g denied, 87 FERC ¶ 61,382 (1999). Interconnection using the rated path

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00135 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12400 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

methodology compared to many in the they would be voluntarily developed,650 direct transmission providers located in
Eastern Interconnection using a flow- no individual transmission provider the same region to coordinate such
based methodology; rather, the developed new services in response to development among themselves. We
Commission should allow flexibility in the workshop. In fact, seemingly, only also encourage participation of non-
the offer of conditional firm service so one transmission provider in the Eastern public utility transmission providers in
that transmission providers are not or Western Interconnection offers a the region and interested transmission
foreclosed from offering the service. service that is similar to the conditional customers in the development of these
1042. Several commenters state that firm service adopted in this Final business practices. Public utility
transmission providers and customers Rule.651 transmission providers should make
1045. Since the issuance of the NOPR, efforts to include these interested
collectively should design the
the Commission has provided the parties in their regional coordination
conditional firm service that best
industry with three formal opportunities efforts. We direct transmission
accommodates their respective needs.648
to provide comments on providers to implement these
In supplemental comments, Bonneville
implementation of the conditional firm mechanisms and business practices
states that the transmission provider,
option. The Commission held a within 180 days after the publication of
not the customer, must determine the
technical conference on implementation this Final Rule in the Federal Register.
conditions to offer in response to a 1047. The Commission adopts the
issues after issuance of the NOPR and
given request. Bonneville also requests proposal in the NOPR that customers
held many informal technical
that the Commission clarify that there using the conditional firm service pay
discussions with industry
would be no separate queue for the long-term firm point-to-point rate.
representatives. We have taken these
conditional firm service. We will not allow complete flexibility
steps in order to make the most
Commission Determination reasoned decision concerning the in defining the conditional firm option
minimum attributes of the conditional as suggested by EEI because such an
1043. The Commission adopts the firm option. These conferences and option could provide a substantially
conditional firm option as a modified workshops have been helpful and have lower quality service for which
form of long-term firm point-to-point informed our decision on the minimum transmission providers would be able to
service that includes less-than-firm attributes of conditional firm service. As recover the long-term firm rate. We also
service in a defined number of hours of noted herein, although we are reject EEI’s proposal that the service be
the year or during defined system establishing certain minimum attributes, a mix of firm and non-firm periods. We
conditions when firm point-to-point we also allow for some measure of envision the conditional firm option as
service is not available. The service can flexibility in provision of the service. one in which firm service is available
be curtailed solely for reliability reasons We will not, however, approve most of the period of a year. EEI seems
during the defined system conditions or conditional firm as a concept only. concerned about tailoring the product to
defined number of hours. We reject Given our past experience, this would situations where congestion is so acute
EEI’s suggestion to use a monthly non- provide little benefit to customers that the ‘‘conditions’’ require frequent
firm curtailment because it would allow seeking to use the service and no interruptions. We do not believe this
for curtailment of the conditional certainty to transmission providers concern is well founded. Because a
service for economic reasons. seeking to comply with our regulations. conditional firm customer is obligated
1044. In this Final Rule, we define the 1046. Further, as discussed in more to pay the long-term firm point-to-point
minimum attributes of the conditional detail below, we disagree that NERC rate, we assume that few, if any,
firm option rather than allow individual must modify its processes in order to customers would accept the service in
transmission providers to develop any allow transmission providers to circumstances where the interruptions
form of service that could conceivably implement this product. However, we (or ‘‘conditions’’) are so frequent or
be labeled conditional firm service. The will allow for a sufficient period of time pervasive to make the service
Commission has been considering a for development of business practices unattractive.
and tracking mechanisms to implement 1048. Finally, we clarify for
conditional firm product and has been
the product. We recognize that there Bonneville that customers seeking the
discussing it with the industry for some
may be some regional variation in the conditional firm option must first
time. In early 2005, the Commission
way transmission providers approach request long-term firm service. When
held a technical workshop to:
the provision of conditional firm service ATC is unavailable, the transmission
Work with market participants to develop provider must study the conditional
clear definitions for additional wholesale beyond the minimum attributes that we
establish in this Final Rule. Thus, we do firm option at the customer’s request.
electric transmission services, e.g., There is no separate queue for the
conditional firm transmission service, not direct that transmission providers
work with NAESB to develop business conditional firm option.
develop applicable pro forma tariff language
that could be included in public utilities’ practices for implementation of the (ii) Specified System Conditions and
open access transmission tariffs and address conditional firm service. Rather, we Conditional Hours
attendant issues.649
Comments
Although commenters in that 650 E.g., Bonneville Workshop Comments at 1–2

proceeding stated that the Commission (April 13, 2005) (stating that Bonneville believes the 1049. Several transmission providers
result of the workshop ‘‘will be the development of state that they cannot accurately predict
need not require new services in one or more new transmission products.’’), TAPS
transmission providers’ OATTs because Workshop Comments at 2 (April 13, 2005)
the conditional curtailment hours
(suggesting that the Commission should invite and because there are too many variables to
648 E.g., LPPC Supplemental, PPL Supplemental, consider proposals by individual utilities rather consider and ATC analysis does not
than act by rulemaking). provide this level of granularity.652
Williams Supplemental, Community Power
sroberts on PROD1PC70 with RULES

651 In the NOPR, the Commission noted


Alliance Supplemental, Entergy Supplemental, and These commenters contend that load
Southern Supplemental. PacifiCorp’s 2002 modifications to partial interim
service. See NOPR at P 319 n.298. PacifiCorp’s flow modeling for a wide range of
649 Potential New Wholesale Transmission service is similar to that proposed by EEI with the
Services, Notice of Final Agenda for Technical exception that customers are charged a pro rated 652 E.g., Imperial, Duke, Progress Energy,

Workshop, 70 FR 12865 (Mar. 16, 2005). long-term firm rate. MidAmerican, PNM–TNMP, Southern, and EEI.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00136 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12401

possible system conditions required to transmission provider is actually conditions, with non-binding estimates
estimate the conditional curtailment required to curtail transactions to meet of hours of curtailment, would lead to
hours would be complex, time- reliability requirements and all non-firm more effective and reliable operation of
consuming and costly. Given this transactions have been curtailed. Once the transmission system that is
concern, Southern, PNM–TNMP, and the transmission provider has reached consistent with regional requirements.
MidAmerican state that any conditional the annual cap on curtailable hours, 1056. In supplemental comments,
firm service should be subject to a AWEA argues the customer’s service Bonneville asserts that the transmission
‘‘reasonable efforts’’ standard and not should convert to traditional firm provider should have the option of
represent a guarantee of service or a service for the remainder of that annual offering conditional curtailment hours
binding estimate of conditional period. or specified system conditions in order
curtailment hours from the transmission 1053. Utah Municipals reply that that the transmission provider can make
provider. Progress Energy states that it transmission providers should be bound a prudent choice based on available
would be difficult to determine a by their calculations of the availability historical system data.
specific number of hours that firm of firm service, even if the firm service 1057. In supplemental comments,
service is available, given that the is not available year-round. TAPS argues that conditional firm
industry uses seasonal models. Ameren 1054. FirstEnergy and Nevada service should be limited to 100 hours
states that the conditional curtailment Companies state that monthly caps, as per year of conditional curtailment,
hours should be spelled out in the opposed to annual caps of curtailment subject to curtailment on the same basis
transmission service agreement. hours, would be preferable because they as firm service beyond those hours, and
1050. Several commenters state that provide more information to the made available to and integrated with
the transmission provider should customer and are more appropriate for network customers. In TAPS view, this
provide customers a choice between transmission systems with mostly would result in a more efficient use of
defined system conditions and seasonal constraints. According to the grid, provide customers sufficient
conditional curtailment hours.653 In Nevada Companies, a curtailment based certainty to sign long-term power
supplemental comments, EPSA and upon the maximum number of hours purchase contracts and promote
AWEA state that neither option should per year, without taking into account transmission construction. TAPS also
be arbitrarily excluded; rather, they the specific times or conditions for believes that the customer should have
argue that transmission providers those curtailments, would be the option of expressing the curtailment
should consult with each customer in unworkable in the context of a seasonal restriction on the basis of specified
determining the defined conditions that peak system, such as exists with Nevada system conditions in the 100-hour
could form the basis of the conditional Companies. range.
firm service. EPSA and AWEA propose 1058. In its supplemental comments,
1055. Several commenters support a
that conditional firm should be firm Entergy suggests that the Commission
variation on conditional firm service
during all hours of the year except in allow more flexibility between the
that would allow a transmission
those hours in which a defined contracting parties to identify the
provider to specify either the conditional nature of the service, i.e.,
contingency occurs, and the transmission facilities/elements that
transmission provider is actually unable the Commission should not prescribe
may become constrained or the parameters of the conditional period
to provide service. EPSA and AWEA operating conditions that will result in
also propose that the system impact that may ignore real-time conditions on
curtailments of a particular conditional the transmission provider’s system that
study should describe the reliability firm service.654 Many of these
contingency and the transmission require a curtailment.
commenters propose a defined system 1059. EEI, Duke, and PNM–TNMP
service agreement should clearly define condition as the trigger for non-firm object, in their supplemental comments,
the contingency. curtailment of the service rather than
1051. EPSA and AWEA state that to specifying system conditions or the
the use of conditional curtailment maximum number of curtailment hours
conditional firm should only be hours.655 Entergy and LPPC propose per year, stating that requiring either
curtailed after all non-firm services are that such curtailments have the same would be incompatible with current
curtailed on the same constrained path priority as secondary network service. curtailment procedures and unfairly
during the period of the defined Entergy contends that this service shift risks of curtailment to other firm
contingency. Finally, AWEA and EPSA would be superior to the conditional customers. EEI, Progress Energy and
state that transmission providers must firm service described in the NOPR Duke argue that the service should be
maintain the committed capacity subject because it would be more comparable curtailable during a particular season,
to the defined contingency only, reflect with the service transmission providers month or other defined period to
capacity commitments for conditional make available to network customers provide more certainty to the
firm service in their ATC calculations, and would minimize the risk to other transmission customer and the
and be prevented from further curtailing customers who might otherwise bear the transmission provider as to when the
conditional firm service due to load cost of inaccurate conditional service is subject to curtailment.
growth after the execution of the initial curtailment hours, as well as disputes 1060. With regard to modeling
service agreement. between the transmission provider and methods for estimating the conditional
1052. AWEA proposes that if a service the transmission customer regarding the curtailment hours, EEI asks the
agreement specifies conditional number of conditional curtailment Commission not to require the
curtailment hours, the transmission hours. Seattle and Santee Cooper transmission provider to use a specific
provider must provide firm service suggest that defining the limitations on methodology to evaluate whether it can
except in the curtailable hours defined the service based on operating provide conditional firm service.
in the service agreement and the service
sroberts on PROD1PC70 with RULES

Bonneville argues that transmission


must be treated as firm unless the 654 E.g., AWEA, EPSA, Project for Sustainable
providers need flexibility to modify
FERC Energy Policy, Santee Cooper, Seattle,
653 E.g., Barrick Supplemental, Bonneville Entergy, and LPPC. their ATC methodologies to
Supplemental, BP Energy Supplemental, and EPSA 655 E.g., Santee Cooper, Seattle, Entergy, LPPC, appropriately model the new service
and AWEA Supplemental. and Nevada Supplemental. and avoid planning obligations to firm

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00137 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12402 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

up the conditional curtailment hours of several reasons. Specified system Commission’s examination of modeling
a conditional firm reservation. Nevada conditions give certainty to the methods in the NOPR was not meant to
Companies suggest that the transmission customer that it will only be propose one method over another;
provider use the appropriate seasonal conditionally curtailed when forecasted rather, it was meant to examine possible
operating case with updated projections reliability problems actually occur. ways to determine a number of
to determine the amount of requested Transmission providers benefit from conditional curtailment hours to
service that can be provided without this option because they can point to encourage dialog on the issue.
violating reliability criteria. specific constraints on their system and Additionally, we will allow
1061. Ameren argues that when a implement a curtailment plan when transmission providers to add a risk
transmission provider models system those transmission elements are factor to their calculation of annual
contingency events, the events are not constrained. Additionally, designation curtailment hours to account for
interchangeable with a number of hours. of specific system conditions may allow forecasting risks. Further, we note that
According to Ameren, the two for a better fit of the conditional firm our adoption of the conditional bridge
measurements will produce different service to a specific transmission and reassessment products, detailed
impacts for the transmission system, provider’s system. Consider the example above, address modeling difficulties by
and the transmission provider should of firm service that is not available on limiting the number of years that a
not be required to make both options a specific system because a transmission transmission provider must model in
available at the customer’s option. LPPC line is taken out of service for determining both the number of hours
and Public Power Council state that maintenance about two weeks a year. and future system conditions. Moreover,
transmission providers should not be The designation of this line as the we clarify that if the customer selects
required to limit the number of specific condition for conditional firm the annual hourly cap option, the
curtailments on a monthly or yearly service would allow the transmission transmission provider has the flexibility
basis because of the inherent provider to provide firm service without to conditionally curtail the customer for
unpredictability of future transmission having to worry if the maintenance on any reliability reason during those
constraints. APPA states that using the line takes an extra week. The hours, including but not limited to, the
curtailment based on a specified conditional firm customer has fewer system condition(s) identified in the
number of hours will cause the concerns about undue discrimination by system impact study. Without this
transmission provider to overestimate the transmission provider and could flexibility the hourly cap option and the
the number of curtailment hours. benefit from maintenance on the line specific system condition option would
1062. NRECA believes that the that was finished one week early. be indistinguishable with a cap on the
Commission should allow for regional Additionally, we note that many number of hours that the system
flexibility in the determination of the commenters representing transmission conditions interruption could occur.
parameters of the service and providers and customers support this 1068. We will require annual caps on
transmission providers should have approach. the number of hours because calculating
maximum flexibility to set conditions 1066. We will require specificity of an annual cap entails less risk for the
that use conservative assumptions (e.g., system conditions. Acceptable system transmission provider and its existing
based on the driest weeks of the year, conditions include, but are not limited firm customers than monthly or
summer or winter peak period to, designation of limiting transmission seasonal caps. While we will not require
constraints). NRECA believes such elements, such as a transmission line, monthly or seasonal caps, we encourage
service should be conditioned on substation or flowgate. We do not transmission providers to offer them if
operating conditions as well as with believe, however, that designation of they can overcome modeling barriers
reference to a number of times of system load levels, standing alone, because monthly or seasonal caps give
interruption. In contrast, MISO supports would qualify as an acceptable system more certainty to customers about the
the election of a consistent method of condition. Rather, load levels would particular aspects of their service.
curtailment applied to all customers, in have to be linked to a specific constraint Though we allow for flexibility in
order to make the service easier to or transmission element that is modeling and determining the number
implement. associated with the request for service, of conditional curtailment hours for a
1063. Powerex states that conditional e.g., load levels in a constrained load particular service request, we believe
firm service should be offered only on pocket. Otherwise, the system load level that this will have a minimal impact on
paths where curtailment to existing would not be specific to the part of the conditional firm customers.
long-term customers is not expected to system over which service is requested Transmission providers will be allowed
occur. and, hence, have no necessary relation to curtail only for reliability purposes
to the problems, if any, created by the and conditional firm customers during
Commission Determination service being requested. Furthermore, conditional curtailment hours will be
1064. The Commission requires that, because most system loads experience curtailed only after all point-to-point
when conducting the system impact load growth every year, conditional non-firm customers have been curtailed.
study for the conditional firm option, curtailments would necessarily increase
the transmission provider shall identify: (iii) Conditional Curtailment Priority
over a multi-year conditional firm
(1) The specific system condition(s) service term. Comments
when conditional curtailment may 1067. We recognize that modeling of 1069. Some commenters agree with
apply; and (2) the annual number of the conditional curtailment hours the Commission’s proposal that
hours when conditional curtailment entails difficulties beyond those conditional firm service should have
may apply. A customer must select encountered in modeling ATC. To secondary network curtailment priority
either conditions or hours for address these difficulties we are during conditional curtailment hours,656
sroberts on PROD1PC70 with RULES

incorporation into its conditional firm allowing flexibility in determining the while others disagree. Bonneville
service agreement. number of hours. We clarify that we will supports the use of the secondary
1065. We require the offer of specific not require a standardized method of
system conditions during which modeling the conditional curtailment 656 E.g., Bonneville, AWEA Reply, and EPSA

conditional curtailment may apply for hours. We also note that the Reply.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00138 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12403

network curtailment priority arguing transmission loading relief, including curtailment with all other firm uses of
that customers will value the service the NERC’s Interchange Distribution the system once conditional curtailment
more with the secondary network Calculator (IDC), would need hours, if that is the option selected, are
priority, thus increasing the viability of modification to allow for curtailment. exhausted.
conditional firm service as an Specifically, Entergy contends that the 1075. The secondary network
alternative to transmission upgrades. Commission should allow time for the curtailment priority is appropriate
EPSA and AWEA argue that conditional IDC to be modified to specify a different because the customer is paying the long-
firm service during conditional curtailment priority for the same term firm point-to-point rate and thus
curtailment hours should be curtailed transaction depending on the identity of should receive the highest non-firm
after all non-firm uses. In their reply the constraining element. Imperial states curtailment priority during the
comments, TDU Systems oppose EPSA that it may take over a year to develop conditional curtailment hours or during
and AWEA’s position, arguing that computer software to correctly handle specified system conditions. Adoption
secondary network service should have new curtailment priorities during an of this curtailment priority overcomes
at least as high a priority as conditional emergency. Bonneville disagrees and what could otherwise be significant
firm service. In contrast, EEI argues that states that conditional firm service does implementation hurdles. It allows for
setting the curtailment priority equal to not present unique issues with respect implementation of the service without
secondary network service would to curtailment and that it would be changes to existing NERC TLR practices.
adversely impact the reliability of firm curtailable during real time like NERC and members of the industry
service by reducing real-time redispatch secondary network service. need not undertake the time-consuming
options and contradict Order No. 888 1072. EEI states that the conditional and expensive process of establishing a
precedent that provides priority non- firm service as currently proposed new curtailment priority that is between
firm service only for network customers would conflict with tagging protocols firm and non-firm service as some
that pay a load ratio share of system and NERC criteria because there is commenters requested. Use of this
costs.657 If conditional firm service is currently no way to tag service as both curtailment priority also avoids
implemented, Powerex states that firm and non-firm. EEI states that, if attendant decisions relating to the
transmission providers should provide conditional firm service is subject to method of curtailment that should
data and evidence demonstrating that curtailment during a specific period, the apply, i.e., pro rata or transactional
the rights of existing long-term firm tag can identify those periods and curtailment, for a quasi-firm curtailment
customers will be protected. EEI takes curtailments will be implemented in priority. It is also consistent with
issue with the Commission’s proposal to conditional periods and non-conditional existing interruption provisions of the
grant conditional firm customers periods in accordance with those tags. pro forma OATT which provide that
priority non-firm service during However, if conditional service is secondary service cannot be interrupted
conditional curtailment hours because curtailable in a certain number of hours, for economic reasons.659 This is
they would pay for long-term use of the or when specific conditions occur, the
consistent with our determination that
grid, stating that all long-term point-to- tag cannot be rewritten in a way that
conditional firm service when it is
point customers pay for service on a will provide for curtailment without
conditional is curtailable only to
long-term basis but, unlike network personal involvement of balancing
maintain reliable operation of the
customers, they do not get priority non- authority operators, which could lead to
transmission system.
firm service. increased curtailments of firm
transmission customers. 1076. We reject EEI’s argument that
1070. Commenters address
1073. Xcel states that limiting the curtailment priority for conditional
implementation issues related to the
curtailments to a specified number of firm service is inconsistent with
Commission’s right of first refusal,
hours per year could result in Commission precedent regarding
tagging, tracking, and curtailment
conditional firm service having greater priority non-firm service only for
priority proposals, as well as other
value than firm, while strictly adhering network customers. EEI’s argument is
implementation issues implicated in the
to a maximum number of curtailment inapposite. Long-term firm point-to-
conditional firm service. Manitoba
hours could potentially conflict with the point customers taking fully firm service
Hydro, Bonneville and Seattle support
reliability standards in section 215 of without the conditional firm option do
the Commission’s proposal that
the FPA. NRECA argues that conditional not need access to priority non-firm
conditional firm service would qualify
firm service should be subject to pro service as EEI suggests. They have
for right of first refusal when firm
rata curtailment with all other firm assurance that their service will not be
service becomes available. Several
users during non-conditional times. interrupted for economic reasons and
commenters believe that the
will only be curtailed on a comparable
Commission’s proposal with regard to Commission Determination basis with network service. This would
right of first refusal should be refined to
1074. We adopt a secondary network not be the case for conditional firm
allow automatic assignment to
curtailment priority to apply for the customers. We also find that EEI has
conditional firm customers of firm
hours or specific system conditions failed to explain the connection
capacity as it becomes available in the
when conditional firm service is between the conditional firm
short term.658 Bonneville asserts that
conditional. During non-conditional transmission service and the availability
prior to implementation of the new
periods, conditional firm service is of reliability redispatch options, i.e.,
service the industry must work with
subject to pro rata curtailment generators on its system that can ramp
NAESB to develop a communications
consistent with curtailment of other up or down in response to a
protocol to either employ automatic
long-term firm service. Thus, secondary curtailment. We reject Powerex’s
assignment or right of first refusal.
network service and conditional firm request that transmission providers be
1071. Entergy and Exelon state that
sroberts on PROD1PC70 with RULES

service when it is conditional will share required to show that existing long-term
the standards for implementing
the same curtailment priority. Also, rights are protected. Each addition of a
657 CitingOrder No. 888 at 31,750. there is no conflict with reliability new long-term firm transaction impacts
658 E.g.,
EEI, EPSA, TranServ, Bonneville, standards because conditional firm
Constellation and Seattle Reply. service will be subject to pro rata 659 See pro forma OATT section 14.7.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00139 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12404 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

the rights of existing firm customers to this attribute of conditional firm service. load growth and changes in load for
some extent. Transmission providers need not prior services.
1077. We disagree with commenters’ implement this requirement until
suggestion that the NERC IDC must be Commission Determination
NAESB develops appropriate
changed to accommodate conditional communications protocols. 1081. The Commission finds that
firm service. We reiterate that we are not rollover rights are appropriate for point-
creating a new curtailment priority in (iv) Rollover Rights
to-point service that is provided using
this Final Rule. We also disagree that Comments planning redispatch or conditional firm
new tags that combine a firm and non- options and would otherwise be eligible
firm priority must be developed in order 1079. Several commenters support the for rollover rights. The following
to implement the conditional firm Commission’s proposal that conditional discussion addresses only rollover
option. The curtailment priority in a tag firm service would qualify for rollover rights for service that is paired with a
can be changed ahead of the operating rights.661 Manitoba Hydro, Bonneville transmission provider’s biennial
hour based on a near-term forecast of and Seattle state that rollover rights are reassessment right. While the
system conditions.660 We are cognizant appropriate where the transmission Commission agrees with commenters
that daily and hourly operations to provider does not have an obligation to that subsequent firm transmission
change the tags for conditional firm plan for service to the conditional firm service requests should not be placed
customers likely involve the need for customer during the conditional ahead of the conditional firm service,
control room coordination and curtailment hours. Bonneville adds that, we note above our concerns with the
development of an appropriate tracking in rolling over conditional firm service, modeling requirements and reliability
process. As the Commission described the transmission service agreement impacts of an ongoing service that relies
in the NOPR, new tracking and tagging should allow for no more than the same upon unchanging curtailment
business practices for this service must number of conditional curtailment conditions or redispatch requirements.
be developed by each transmission hours than in the original service The biennial assessment right,
provider. Thus, we are allowing a agreement and provide for fewer hours discussed above, addresses the concern
sufficient period for the development of of curtailment if system conditions expressed by EEI that transmission
these business practices, i.e., 180 days provide for more firm service. If providers cannot accurately determine
from the date of publication of this Final conditional firm service is used as an conditional curtailment hours or
Rule in the Federal Register. As interim product until transmission is estimate redispatch costs for a ten-year
directed above, transmission providers built, APPA contends that rollover service. The biennial review in
must coordinate with other transmission rights would be appropriate. conjunction with rollover rights allows
providers in their regions to develop 1080. Others argue that rollover rights the transmission provider to update the
these tracking and tagging business for conditional firm service are parameters of the service in order to
practices. inappropriate.662 These commenters do maintain reliable operations and allows
1078. Finally, we address requests to not support the granting of rollover customers to keep their place in the
allow for automatic assignment of short- rights, nor do they support the queue ahead of other customers seeking
term firm point-to-point service to designation of conditional firm service conditional firm, planning redispatch
conditional firm customers. We agree as long-term service. In order to options, or other firm services.
that transmission providers must take accommodate conditional firm rollover
into account the conditional firm 1082. Rollover rights for the
rights, FirstEnergy contends that the reassessment product can provide
service in evaluating the availability of transmission provider would be
short-term firm service. Because significant value to the conditional firm
required to model a number of off-peak customer. A conditional firm customer
conditional firm is a long-term firm use load flow cases and provide system
of the system, it should not be opting to roll over will retain priority
reinforcements. Ameren states that the claim to the portion of its service that
interrupted prior to short-term firm number of hours that the service will be
service. However, short-term firm is firm. For example, if a five-year
available at some future date after the conditional firm service initially has a
service reserved prior to the reservation contract expires will not be known at
of conditional firm service should 100-hour annual cap on curtailments,
the time the initial contract is executed. but the cap is later reassessed at 150
maintain priority over conditional firm EEI adds that estimating conditional
service in the periods when conditional hours, the rollover right would continue
curtailment hours for 10 years of service to give the customer first call on all but
firm service is conditional, i.e., when is an impossible task. MISO states that
specified system conditions exist or the 150 hours as against all other
rollover rights would add more subsequent requests for firm service.
conditional curtailment hours apply. complexity to the AFC/ATC calculation
Because the assignment proposal meets 1083. We note that a customer taking
process and competition queues. conditional firm or planning redispatch
both of these objectives, we direct Entergy and EEI state that, while
transmission providers to assign short- options as part of a five-year point-to-
subsequent firm transmission service point service must declare its intent to
term firm service to conditional firm should not be placed ahead of the
customers as the service becomes roll the service over in the fourth year
conditional firm service, it is of service, coincident with the second
available. Accordingly, we direct appropriate at the time of a rollover
transmission providers to work with biennial review. Thus, we task
request, and perhaps more frequently, to transmission providers and customers,
NAESB to develop the appropriate allow the transmission provider to
communications protocols to implement in negotiating their service agreement,
update the conditional firm service with coordinating the timing of the
660 For example, in the Eastern Interconnection,
parameters in order to take into account biennial review with the deadline for
sroberts on PROD1PC70 with RULES

tags can be changed up to 35 minutes before the declaring rollover intent. Specifically,
661 E.g., AWEA, EPSA, Manitoba Hydro,
hour in which a TLR event is scheduled. See NERC customers deciding whether to renew
Standard IRO–006–3, Transmission Loading Relief Bonneville, TranServ, Seattle, and Utah Municipals
Procedures—Eastern Interconnection, section 6.2 Reply. their service should have information
(Communications and Timing Requirements) at 23– 662 E.g., EEI, FirstEnergy, Ameren, SPP, and TDU on additional conditions on the service
25 (August 2, 2006). Systems Reply. or additional estimated redispatch costs

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00140 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12405

at least 30 days prior to the relevant resource is undeliverable due to implementation challenges of creating a
rollover deadline. curtailment of conditional firm service. conditional firm service for network
1084. Additionally, because the 1086. Other commenters assert that customers can be overcome. Bonneville
biennial review provides the the Commission should create an also states that other options such as
exception to allow designation of seasonal firm and long-term reservation
transmission provider with the ability to
network resources that use conditional of secondary network service should be
plan for and maintain system reliability,
firm service.665 AWEA adds that explored in order to allow network
we will not allow the rollover right to
resources should not lose their customers similar access to monthly
infringe upon this review. Thus, we
designation when transactions are ATC.
direct that the transmission provider has
curtailed pursuant to conditional firm 1089. Nevada Companies state that
a right to review the conditions or service because this is not the way network customers have load service
redispatch requirements at the end of similar resources with special obligations and should always have
the first year of a service that has been protection systems are treated. Several unconditional firm service, without
rolled over, i.e., year six of service, as commenters state that conditional firm exception. However, Nevada Companies
consistent with a biennial review of service should qualify as a network state that network customers could
service.663 resource when the associated resource is benefit from a service similar to
(v) Use of Conditional Firm Options in imported by a network customer.666 BP conditional firm service. According to
Designating Network Resources Energy adds that more coordination Nevada Companies, if a network
between the two systems with respect to customer desires to deliver its resources
Comments specifying the set of conditions or to a point of receipt that is not available
specific set of hours is required. all seasons of the year, it could procure
1085. Several commenters state that
1087. Some commenters state that firm transmission capacity that is
the Commission should not modify conditional firm service should be made available on a seasonal basis for the
current OATT requirements for available to network customers because delivery of a network resource.
designating network resources to conditional firm service may trump the 1090. Some commenters state that
include resources delivered using provision or scheduling of secondary network customers should be permitted
conditional firm service; otherwise, network service and because network to designate as network resources third
reliability would be threatened because customers should have service that is at party power supplies that are supported
network customers could lean on the a minimum equivalent with point-to- by the supplier’s conditional firm
system during conditional periods.664 point service.667 These commenters reservation.668 In supplemental
They oppose allowing a resource taking suggest that the Commission could comments, Xcel states that it does not
conditional firm service to qualify as a permit network customers to designate oppose allowing conditional firm to
network resource when the associated a conditional network resource that qualify as a network resource, but it
resource is imported by a network would be a firm resource for the hours should be clear that the service is an
customer from an adjacent system. EEI when a comparable conditional firm exception to the otherwise ‘‘firm is
and Duke agree with the Commission’s point-to-point service is firm. In firm’’ policy that requires all firm users
NOPR proposal that conditional firm supplemental comments, NRECA and to be curtailed pro-rata.
service should not be available to TAPS argue that ‘‘on-system’’ LSEs
network customers and further assert Commission Determination
should be allowed to designate a
that a product that includes a non-firm network resource where transmission is 1091. The Commission will allow
portion is inappropriate for a load- fully firm for all but the limited time conditional firm point-to-point service
following service like network service. each year, e.g., to 100 hours or less, and to qualify as firm service that supports
EEI asserts that because the Commission ‘‘off-system’’ LSEs should be allowed to the designation of network resources
requires that network resources be treat a network resource supported by imported from other control areas. As
deliverable on a non-curtailable basis, conditional firm service as a resource on we explain in more detail in section
resources using conditional firm service the host system where it takes network V.D.6, the Commission has longstanding
cannot be designated as a network service. NRECA believes that if the limitations on network resources.
resource until the maximum conditional criteria for both network service Network resources cannot be
curtailment hours have been reached. resource designations and for the interrupted for economic reasons and
EEI and Duke contend that establishing proposed conditional firm service are third-party transmission arrangements
a defined period of curtailment for based on the physical, engineering to deliver the resource to the network
conditional firm service, either seasonal, characteristics of the transmission must be non-interruptible.669 EEI is
monthly, or specific dates, eliminates system, the network customer should be incorrect that, under our precedent, a
issues with respect to the designation of able to designate the resource as resource must be ‘‘noncurtailable’’ to
network resources because a resource deliverable to load on a non-curtailable qualify as a network resource under the
using conditional firm service would be basis, except for the specified OATT. All resources are ‘‘curtailable’’—
eligible for designation for the part of conditions. e.g., if a unit trips off line, the resource
the year when the service was defined 1088. In its reply comments, is, by definition, curtailed. Network
as firm. In its reply comments, Duke Bonneville states that since secondary resources may also be unavailable due
states that it cannot reliably operate its network service cannot be purchased on to other reasons besides an unplanned
system if it is required to serve a long-term basis, the Commission unit outage, such as unplanned
unplanned load when a network should evaluate whether the design and transmission outages or environmental
restrictions. It is appropriate to allow
663 Such a review would occur in the first year 665 E.g., AWEA, EPSA, TAPS, APPA, Utah conditional firm service to support the
sroberts on PROD1PC70 with RULES

of a rolled over service if the initial service term Municipals Reply, and Barrick Reply.
was for five years. 666 E.g., Bonneville Supplemental, TDU Systems 668 E.g., APPA Supplemental, EPSA and AWEA
664 E.g., Entergy Supplemental, Southern Supplemental, PPL Supplemental, and BP Energy Supplemental.
Supplemental, MISO Supplemental, Community Supplemental. 669 Wisconsin Public Power Inc. v. Wisconsin

Power Alliance Supplemental, and Powerex 667 E.g., NRECA, TDU Systems, TAPS, and Utah Public Service Corp., 84 FERC ¶ 61,120 at 61,660
Supplemental. Municipals Reply. (1998) (WPPI).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00141 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12406 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

designation of network resources 1094. Finally, in light of our participation in redispatch would
because the conditional firm option conclusions above that conditional firm require market mechanisms.
only affects the transmission of the service satisfies the Commission’s
Commission Determination
resource to the network, not the requirements for designating network
interruptibility of the generating resources because the delivery of the 1098. The Commission addresses
resource itself. Conditional firm service resource to the network is not below two distinct parts of the TDA
satisfies the Commission’s requirement interruptible for economic reasons, we proposal: (1) Expansion of transmission
for the delivery of the resource to the do not need to adopt a seasonal, provider’s real-time reliability
network to be non-interruptible because monthly or periodic method for redispatch obligation as well as
such transmission service is curtailable determining the conditions under which inclusion of third-party resources in
only for specific reliability reasons, not conditional service may be curtailed as provision of redispatch and (2) posting
economic reasons. suggested by EEI and others. of real-time redispatch costs or
1092. We decline, however, to adopt prices.671 The Commission has carefully
b. Proposals for Transparent Redispatch considered both the TDA proposal and
the conditional firm option for network
service. Commenters argue that NOPR Proposal the comments respecting it. We agree
conditional firm network service should with many of the public policy goals
1095. In the NOPR, the Commission articulated by Transparent Dispatch
be made available to prevent explained that the major focus of this
conditional firm point-to-point service Advocates, such as increasing the
rulemaking was to strengthen the pro transparency of information and
from ‘‘trumping’’ the scheduling of forma OATT in order to remedy undue increasing the efficient use of existing
secondary network service and to discrimination rather than create new infrastructure. However, we also agree
ensure that network service is at a market structures. The Commission with many of the commenters that
minimum equivalent to point-to-point stated its intention to retain the use of certain aspects of the TDA proposal are
service. Concerns regarding conditional an OATT to facilitate the development unclear and, depending on its
firm point-to-point service ‘‘trumping’’ of competitive wholesale markets by interpretation, may require the creation
secondary network service would not be reducing barriers to entry through the of new services under the pro forma
resolved by creating conditional firm control of transmission assets, not OATT or new market structures. We are
network service. The ‘‘as available’’ impose any particular market structure particularly cognizant of the arguments
nature of secondary network service on the industry. of customer groups such as APPA,
will still permit all firm uses of the NRECA and TAPS that the TDA
system, including conditional firm Comments
proposal may be difficult to implement,
service, to have a higher reservation 1096. Several commenters argue that contentious, and may not provide
priority than secondary network service. the Commission should expand the significant benefits to customers. These
Creating a conditional firm network planning redispatch requirements of the customers also are concerned that it
service would not change that pro forma OATT to incorporate third may detract from other reforms
reservation priority. party provision of redispatch and considered in this proceeding that they
1093. Others argue that conditional bidding protocols.670 In reply believe provide greater benefits, such as
firm network service should be required comments, Transparent Dispatch transmission planning reform.
in order to ensure that network service Advocates submitted a proposal that, 1099. After considering the views of
is equivalent to point-to-point service. among other things, would require all the parties, the Commission has
As noted above, however, the two transmission providers to (1) post the sought to strike a reasonable balance
services are not precisely the same, nor real-time cost estimate of providing between the positions of the
were they intended to be identical. In redispatch service from their resources commenters. On the one hand, we adopt
Order No. 888, the Commission at congested locations, (2) accept offers certain reforms that will provide
attempted to strike a balance between from third parties to provide redispatch additional information regarding
competing interests in designing service, and (3) provide real-time redispatch costs in a manner that
network and point-to-point transmission redispatch to resolve transmission benefits consumers. On the other hand,
services, each service with its own costs constraints. Transparent Dispatch we will not adopt the portions of the
and benefits. It is therefore appropriate Advocates argue that their proposal is TDA proposal that would require the
that we consider the need for consistent with the scope of the creation of new services under the pro
conditional firm service in each context. rulemaking because it would not require forma OATT or new market structures.
While we conclude that implementation the adoption of LMP markets or other We do not believe that such
of conditional firm network service is standardization; rather, it would simply fundamental changes are necessary or
not necessary to remedy undue provide cost visibility and proper cost appropriate at this time, nor do we have
discrimination at this time, we note that assignment of the dispatch decisions an adequate record upon which to adopt
allowing conditional firm point-to-point made by transmission providers. them.
service will nonetheless provide 1097. In a notice issued on November 1100. Specifically, the Commission
substantial benefits to network 15, 2006, the Commission sought further declines to adopt the TDA proposal to
customers by allowing the designation comment on the TDA proposal. The expand transmission providers’ real-
of network resources delivered to the Commission asked, inter alia, about time reliability redispatch obligations
network from other control areas using implementation impediments and and incorporate third party bids into
conditional firm point-to-point service. confidentiality issues related to posting redispatch. As discussed in detail
Conditional firm point-to-point service redispatch costs, whether the TDA above, transmission providers will
will thereby allow network customers to proposal was required to remedy undue continue to have an obligation to
sroberts on PROD1PC70 with RULES

access new alternative power sources. discrimination, and whether third party 671 Transparent Dispatch Advocates’ proposal for
Transmission providers are free to make
mandatory coordination agreements between
a filing under FPA section 205 670 See section V.C.1 of this Final Rule for a transmission providers for provision of redispatch
proposing conditional firm network discussion of comments regarding independent service is addressed in section V.C.1 of this Final
service. dispatch and spot market development. Rule.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00142 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12407

perform reliability redispatch for account for independent, third party Advocates propose that the Commission
network customers and provide the resources in its control area in impose upon transmission providers an
planning redispatch described above for establishing redispatch costs, or allow obligation to do the following: Provide
point-to-point customers. Transmission independent resources to post real-time, reliability redispatch to point-to-point
providers will not be required, as cost-based price and quantity bids for customers in real-time for comparable
Transparent Dispatch Advocates redispatch plus the resource’s impact on treatment to that currently provided to
request, to incorporate third party the constraint on the transmission network customers and native load;
resources when providing reliability provider’s OASIS. Transparent Dispatch consider their own resources, network
redispatch or evaluating planning Advocates state that the published resources, and offers from non-network
redispatch options for point-to-point or redispatch values would be cost-based resources in providing least cost
network transmission service. We will, in non-market environments. redispatch in real-time; and, publish
however, institute a posting requirement 1103. On November 3, 2006, a real-time information about the cost of
so that the actual costs of redispatch summary of, and frequently asked redispatch (including the prices
under existing and future redispatch questions regarding, the TDA proposal submitted by non-network resources) on
agreements is made transparent to (TDA Summary) was attached to its OASIS site on a frequent and timely
potential customers. While we will not comments filed by San Diego G&E in basis. In their supplemental comments,
require posting of a real-time estimate of response to the October 12 Technical Transparent Dispatch Advocates
redispatch prices as proposed by Conference and in support of the TDA propose a different method for
Transparent Dispatch Advocates, the proposal. In the TDA Summary, calculating redispatch prices using the
Commission concludes that the posting Transparent Dispatch Advocates assert difference between the cost of the
requirement required herein will that the Commission need only revise
generation raised and the pre-redispatch
provide important information the existing redispatch provisions of the
transmission provider’s system-wide
regarding the costs of redispatch pro forma OATT to require posting by
marginal cost (e.g., system lambda).
without revealing confidential the transmission providers of the nature
Transparent Dispatch Advocates further
information that might harm existing of congestion at pre-designated
flowgates and data concerning the propose that point-to-point redispatch
markets. customers taking this service would not
response required to relieve congestion.
(1) Expansion of Reliability Redispatch Additionally, the TDA Summary states be subject to curtailment along with
Obligation and Inclusion of Third Party that the transmission provider would other firm customers in accordance with
Resources have no obligation to provide for real- the current OATT curtailment rules.
time redispatch from its own or Transparent Dispatch Advocates argue
Comments that their modified proposal would
affiliated generation; rather, all
1101. In reply comments filed generators wishing to provide facilitate comparable access to
September 20, 2006, Transparent redispatch could volunteer to submit redispatch service and ensure that the
Dispatch Advocates argue that the bids. Transparent Dispatch Advocates existing redispatch provisions of the
Commission must bring transparency to state that these bids could be either OATT can be made effective.
the dispatch function to make market or cost based depending on 1105. Several parties offer comments
redispatch effective and fair and to whether the bidder has market-based in support of the TDA redispatch
thereby remedy the potential for rates within the control area. The proposal.673 Constellation encourages
discriminatory provision of transmission provider would be the Commission to fully consider the
transmission service. Transparent obligated to evaluate the bids, publish TDA proposal in the appropriate
Dispatch Advocates assert that the the price for redispatch, and call on context, whether in this docket or in a
Commission should require each generators to provide the requested separate proceeding. California
transmission provider to publish a redispatch in real time. Transparent Commission states that a movement of
‘‘dynamic real-time value of what it Dispatch Advocates suggest that OATT policy in the direction implied
would charge to provide redispatch transmission providers calculate the by the TDA proposal is necessary to
service at specified congestion locations price for redispatch by taking the improve efficiency of generation and
within the transmission provider’s difference between bids received by transmission investment. BP Energy
system and at specified flowgates at the those generators that the transmission believes that a redispatch mechanism is
border of the transmission provider’s provider would call upon to increase necessary to minimize aggregate
system.’’ 672 Transparent Dispatch output (i.e., to redispatch) and the costs consumer costs and make redispatch
Advocates contend that the publication the transmission provider otherwise equally available to all participants.
of this data would: Allow customers to would have paid the generator whose PPM supports the TDA proposal noting
assess available real-time redispatch output is lowered to relieve the that it would provide sufficient cost
options; allow customers to access constraint. Transparent Dispatch certainty for both the transmission
redispatch at actual costs; allow Advocates contend that their proposal provider and the customer and make
customers to predict with reasonable differs from LMP markets because, more efficient use of the existing grid
certainty the costs of redispatch; allow while LMP sets system-wide clearing without impacting reliability. Although
all resource owners to voluntarily offer prices, their transparent redispatch it opposed the proposal initially, MISO
redispatch solutions and be properly proposal would apply only at selected states that it now cautiously supports
compensated for their efforts; and over flowgates and only with respect to those the TDA redispatch proposal, provided
time, support long-term transmission transacting at those flowgates. that RTOs do not bear an inappropriate
service. 1104. On December 15, 2006, in
share of costs to modify information
1102. In reply comments, Transparent supplemental comments filed in
technology systems.
sroberts on PROD1PC70 with RULES

Dispatch Advocates further request response to the Commission’s November


adoption of rules that would either 15 Notice asking for comment on the 673 E.g., EPSA and AWEA Supplemental,
require the transmission provider to TDA proposal, Transparent Dispatch Constellation Supplemental, California Commission
Advocates sought to clarify their Supplemental, PPL Supplemental, BP Energy
672 Transparent Dispatch Advocates Reply at 5. proposal. Transparent Dispatch Supplemental, PPM, and San Diego G&E.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00143 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12408 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

1106. Many commenters oppose the or organization that has not been advanced in the SMD proceeding and
TDA proposal stating that the record in approved by state regulators as cost thus conflict with state commission
this proceeding does not warrant effective for retail customers. SEARUC jurisdiction in much the same manner
implementing such a complex and opposes the mandatory use of LMP or as the SMD proposal. Georgia
uncertain proposal which imposes LMP-like pricing, congestion Commission and others assert that the
significant risks, costs and burdens on management approach or organized only difference between the SMD
transmission providers and their native wholesale market structure without proposal and TDA proposal is that the
load customers.674 Public Power prior state endorsement; and the TDA proposal would require
Council, Southern, and NRECA do not mandatory posting of competitively transmission providers, but not third
believe that the Commission should sensitive, generation plant-specific costs party merchants, to make their costs
adopt the TDA proposal without an or price information. transparent.677 NRECA believes that a
analysis of costs and benefits and note 1108. Georgia Commission states that real-time pricing scheme based on some
that no party has provided any such radical restructuring is not necessary to value other than actual costs constitutes
analysis. OG&E and Public Power achieve the goals stated by the
the creation of a new product and an
Council state that the costs of Commission in the NOPR. Alabama
organized, bid-based market in regions
congestion likely vary greatly by region Commission, Georgia Commission and
that have not adopted such market
and argue that Transparent Dispatch South Carolina Regulatory Staff state
that analyses associated with potential structures. NRECA contends that it
Advocates have provided no evidence
implementation of new market would be politically unacceptable to
that their industry-wide solution solves
structures in the Southeast have reform the OATT in a manner that
potential regional redispatch problems.
1107. Several state commissions demonstrated that the implementation necessitates the formation of regional
oppose adoption of the TDA proposal or costs associated with such structures bid-based markets in non-RTO areas.
urge the Commission to impose vastly outweigh the benefits. North 1111. In contrast, California
significant conditions on the proposal to Carolina Commission argues that the Commission supports the TDA proposal
protect retail customers.675 SEARUC, TDA proposal fails to comply with the to the effect that transmission providers
Alabama Commission, Florida Commission’s directive in the NOI. In should be required to post redispatch
Commission, Georgia Commission, its view, the Commission intended to cost information and to provide real-
North Carolina Commission and South focus in this proceeding on specific time redispatch. In supplemental
Carolina Regulatory Staff express problems that continue to exist and comments, California Commission
concern that the TDA proposal would targeted remedies. asserts that this effort is needed to
make competitively sensitive 1109. North Carolina Commission prevent undue discrimination, for
information available to the public on states that the Transparent Dispatch improved efficiency of generation and
an inconsistent basis, compel the Advocates’ reply comments incorrectly transmission investment and to improve
provision of additional services that risk equate the use of redispatch for the efficiency, transparency and
increasing retail costs, harm reliable economic purposes pursuant to 13.5 of openness of redispatch, and
service to retail ratepayers that state the pro forma OATT with its use for transmission access generally.
commissions are obligated by state laws reliability purposes. North Carolina
to protect, impose administrative Commission maintains that these 1112. Some commenters argue that
difficulties and excessive services are not comparable, and thus the TDA proposal is necessary to
implementation costs, and compel states the use of redispatch for reliability remedy undue discrimination.678 Others
or regions to change current practices or purposes does not justify requiring a disagree.679 Transparent Dispatch
market structures in contradiction of transmission provider to provide it for Advocates contend that making real-
EPAct 2005. SEARUC asks the economic purposes. North Carolina time economic dispatch available to
Commission to make clear that Commission asserts that ‘‘non-network transmission customers’’
implementation of a proposal targeted at implementation of the TDA proposal is necessary to remedy undue
enhancing transparency will not result would result in substantial benefits discrimination against those customers
in a federally imposed change in accruing to PJM without commensurate as compared with network customers. In
economic dispatch practices or lessen benefits to non-RTO areas. North their supplemental comments, EPSA
the amount of firm capacity available for Carolina Commission, Southwest and AWEA state that the TDA proposal
service to native load customers. Utilities and Southern argue that the is necessary to remedy the same undue
SEARUC also expresses concern costs of implementing the proposal are discrimination targeted by the NOPR
regarding the imposition of incremental not justified by any potential efficiency proposal pertaining to planning
costs upon retail ratepayers without benefits and thus there is a compelling redispatch service. PPL suggests that the
prior state approval or the reason to reject the TDA proposal. TDA proposal may permit transmission
implementation of any type of process 1110. Several parties argue that the customers to benefit from redispatch,
TDA proposal represents a move toward which transmission owners in non-RTO
674 E.g., LPPC Supplemental, Community Power
Standard Market Design (SMD).676
Alliance Supplemental, Public Power Council Alabama Commission, Georgia 677 E.g., Community Power Alliance
Supplemental, Pacific Coast Parties Supplemental,
EEI Supplemental, Duke Supplemental, Southern Commission and North Carolina Supplemental, and Entergy Supplemental.
678 EPSA and AWEA Supplemental, BP Energy
Supplemental, Southwest Utilities Supplemental, Commission submit that the TDA
South Carolina E&G Supplemental, Ameren Supplemental, California Commission
proposal shares characteristics with the Supplemental.
Supplemental, Alabama Commission
Supplemental, Florida Commission Supplemental, centralized dispatch and LMP proposals 679 E.g., LPPC Supplemental, Community Power

Georgia Commission Supplemental, North Carolina Alliance Supplemental, Public Power Council
Commission Supplemental, South Carolina 676 Commenters reference a proposal in a Supplemental, Pacific Coast Parties Supplemental,
sroberts on PROD1PC70 with RULES

Regulatory Staff, and SEARUC Supplemental. proceeding terminated by the Commission. See EEI Supplemental, Duke Supplemental, South
675 E.g., Alabama Commission Supplemental, Remedying Undue Discrimination through Open Carolina E&G Supplemental, Ameren
Florida Commission Supplemental, Georgia Access Transmission Service and Standard Supplemental, North Carolina Commission
Commission Supplemental, North Carolina Electricity Market Design, 67 FR 55454 (Aug. 29, Supplemental, South Carolina Regulatory Staff
Commission Supplemental, South Carolina 2002), FERC Stats. & Regs. ¶ 32,563 (2003), Supplemental, and North Carolina Commission
Regulatory Staff, and SEARUC Supplemental. terminated by, 112 FERC ¶ 61, 073 (2005). Supplemental.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00144 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12409

areas now employ to benefit themselves 1115. Many commenters contend that area. If the Commission adopts the TDA
or their native load customers. the TDA proposal is ambiguous, proposal, APPA asserts that the
1113. A number of commenters assert insufficiently developed or marked by Commission should limit all sellers of
that neither the record nor Transparent inconsistencies.682 Pacific Coast Parties generation used for redispatch service to
Dispatch Advocates present evidence of argue that the TDA proposal is too cost-based bids and require all parties to
discriminatory treatment of sweeping and contains too many provide cost information.
transmission customers with regard to uncertainties to allow for meaningful 1117. In supplemental comments, EEI
transparent redispatch.680 South comment. Southwest Utilities believe and Public Power Council assert that the
Carolina E&G asserts that that it would be premature for the Commission in seeking comment on the
implementation of the TDA proposal Commission to adopt the TDA proposal TDA proposal has not proposed a rule
should not be unjustifiably forced onto without further development, comment, with sufficient clarity to allow
individual transmission providers given discussion and input from affected meaningful comment and, therefore, it
that there is no demonstration that there electric industry stakeholders. PPL and would be inappropriate to adopt the
is a problem. MidAmerican and Xcel believes that the Commission TDA proposal based on this
Progress Energy and others argue that needs to better define the proposed new proceeding’s record. Pacific Coast
unsupported assertions of undue service and allow comment on the Parties add that the Commission cannot
discrimination are insufficient to service before detailed tariff language is adopt the TDA proposal based on the
support the TDA proposal. These developed to implement this proposed sparse record in this proceeding.
commenters argue that pursuant to the new service. Public Power Council MidAmerican and Progress Energy
contends that, although the proposal contend that the Commission’s notice
recent National Fuel decision, the
appears to seek only the posting of here does not satisfy Administrative
courts would likely require the
information, in reality, Transparent Procedure Act requirements for public
Commission to overcome substantial
Dispatch Advocates ask that the notice and comments on the TDA
hurdles in order to adopt the TDA
Commission require reciprocal proposal. In their view, the Commission
proposal based on theoretical assertions
redispatch coordination. Public Power must initiate a separate rulemaking
of undue discrimination.681 These
Council also argues that the TDA proceeding to evaluate the TDA
commenters contend that the National
proposal is silent or ambiguous proposal.
Fuel case would likely require the 1118. Progress Energy and
concerning critical issues associated
Commission to demonstrate how MidAmerican assert that, under the
with implementation; the proposal fails
potential undue discrimination justifies current pro forma OATT, redispatch is
to explain the ‘‘cost’’ at which
a costly redispatch proposal, why based on a ‘‘careful’’ evaluation of the
transmission providers would offer
section 206 rights are insufficient to reliability and cost impacts of using
redispatch or the price, terms, and
ensure redispatch is comparably redispatch on a long-term basis and thus
conditions of such a transaction.
provided, and why the comparability 1116. Several parties refer to seeming the transmission provider is able to
findings of Order No. 888 are no longer discrepancies between Transparent serve transmission customers and
sufficient. Dispatch Advocates’ explanations of the wholesale load-serving obligations at
1114. In response to assertions that proposal and question whether the TDA least cost. In their view, the
utilities routinely redispatch to meet proposal entails cost-based or market- transmission provider’s retail and
electric load, LPPC argues that there is based bidding.683 APPA notes that wholesale customers would absorb the
nothing discriminatory about a Transparent Dispatch Advocates state in costs to serve transmission customers
vertically integrated utility’s use of its reply comments that effective that obtain the forced real-time
own nonjurisdictional generation to redispatch service must reflect actual redispatch under the TDA proposal.
support bundled sales service. LPPC costs. APPA adds that the TDA 1119. Community Power Alliance,
states that the use of generation first to Summary, in contrast, provides that any North Carolina Commission, Progress
serve native load has been the generator with market-based rate Energy and MidAmerican contend that
fundamental operating principal for authority in the transmission provider’s native load customers would be harmed
jurisdictional and nonjurisdictional control area could charge a market- by a requirement that transmission
utilities for decades, and certainly under based price for generation offered for providers sell their excess generation to
Order No. 888. LPPC concludes that this redispatch service. LPPC, TDU Systems, redispatch customers. They state that
is not a problem calling for Commission TAPS, APPA and NRECA express such a requirement would prevent or
attention. In response to assertions that concern about allowing redispatch reduce the sale of generation in
TLRs are discriminatory, Duke notes providers to bid under market-based competitive markets and that these
that neither the Transparent Dispatch rate authority. These commenters argue market sales would otherwise reduce
Advocates nor any other commenter has that reliance on existing market-based costs to native load customers.
provided an analysis of the scope, rate authority to support redispatch Moreover, where the transmission
location and magnitude of the TLR offers no protection against the exercise provider is required to redispatch its
problem. of market power, given the high own generation, Progress Energy and
concentration of transmission provider- MidAmerican argue that Transparent
680 E.g., LPPC Supplemental, Community Power owned generation within its control Dispatch Advocates’ proposed
Alliance Supplemental, Public Power Council redispatch would either use more
Supplemental, Pacific Coast Parties Supplemental, 682 E.g., Pacific Coast Parties Supplemental, expensive units or cause the
EEI Supplemental, Duke Supplemental, Southwest Utilities Supplemental, Entergy
MidAmerican and Progress Energy Supplemental,
transmission providers to lose the
Supplemental, EEI Supplemental, PPL
South Carolina E&G Supplemental, Ameren Supplemental, Public Power Council Supplemental,
opportunity to make higher valued
Supplemental, North Carolina Commission Florida Commission Supplemental, SEARUC sales, which also increases costs for
sroberts on PROD1PC70 with RULES

Supplemental, North Carolina Commission Staff Supplemental, Progress Energy and MidAmerican native load customers.
Supplemental, and North Carolina Commission Supplemental, APPA Supplemental, NRECA 1120. In supplemental comments,
Supplemental. Supplemental, and TAPS Supplemental.
681 E.g., Entergy Supplemental, LPPC 683 E.g., Progress Energy and MidAmerican
E.ON, Progress Energy and
Supplemental, Public Power Council Supplemental, Supplemental, APPA Supplemental, NRECA MidAmerican assert that some
and OG&E Supplemental. Supplemental, and TAPS Supplemental. generators face limits with regard to the

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00145 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12410 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

amount of time that they are allowed to alleviate constraints in order that other Congress’ focus on protecting native
operate due to air emissions caps and customers’ transactions could flow load and ensuring reliability in EPAct
maintenance schedules. They contend would violate Standards of Conduct. 2005.
that the TDA proposal could cause 1123. TAPS argues that accurately 1128. APPA argues that the
allowable run time to be ‘‘used up’’ forecasting the price of long-term firm implementation of the TDA proposal
prior to the time that the generator has service may be difficult and thus the would require the following:
fulfilled its planned native load TDA proposal would not provide designation and posting by the
obligation, thus requiring that the adequate levels of certainty to facilitate transmission provider of chosen
transmission provider resort to long-term service. flowgates; posting by the transmission
alternative, likely more expensive, 1124. Mark Lively asserts that the
provider of the desired characteristics of
power supplies for these obligations. TDA proposal fails to address other
generation or demand-side responses
1121. Several parties assert that types of redispatch, including loop flow,
that could alleviate such constraints;
Transparent Dispatch Advocates’ reactive power, Inadvertent Interchange
posting by the transmission provider of
proposal to substitute redispatch for and intra-hour interchange, and as such
historical redispatch costs; resolution of
transmission upgrades will depress will result in suboptimal operation of
whether public utility transmission
transmission investment.684 LPPC the network.
1125. OG&E questions whether the providers can be required to provide
argues that Transparent Dispatch
TDA proposal would apply to RTOs but generation resources for redispatch;
Advocates’ proposal conflicts with the
if so, OG&E argues that the proposal resolution of whether transmission
Commission’s policy of promoting
should be rejected. OG&E contends that providers would be discriminated
transmission infrastructure
the Commission explained in Order No. against if they were not permitted to
development. NRECA states that, to the
2000 that congestion management is a charge market-based rates;
extent that redispatch is required to
regional function and that the TDA administration by the transmission
fulfill long-term point-to-point service
proposal should not apply to a provider of short-term (daily or hourly)
on a particular transmission provider’s
transmission provider located within an market for redispatch, notwithstanding
system, such providers have failed to
meet their obligations under the existing RTO. a conflict of interest between the
OATT to plan and expand the system 1126. In supplemental comments, transmission provider’s market-making
for those transmission customers’ long- Transparent Dispatch Advocates and market-participant roles and
term needs. NRECA envisions contend that the transparent dispatch possibly third-party monitoring of
redispatch customers potentially proposal would not involve the market administration.
requesting ‘‘ever more convoluted’’ establishment of organized markets of 1129. APPA, Xcel, North Carolina
dispatch rules in order to avoid any sort; rather, it simply would require Commission, and NRECA raise concerns
transmission upgrades. NRECA prefers the posting of redispatch costs. over the costs of establishing and
better enforcement of section 15.4 of the Transparent Dispatch Advocates state administering redispatch markets and
OATT in conjunction with a more open that the proposal only requires the systems, including the costs of
and inclusive planning process. TAPS consideration by the transmission hardware, software, communication
argues that transmission providers will provider of additional price data from systems, billing and reporting systems.
profit from market-based prices for non-network resources and minimal North Carolina Commission submits
redispatch and will be discouraged from adjustments in transmission provider’s that the costs of implementing the TDA
transmission expansion. TAPS contends reporting systems. proposal would be substantial because
that PJM has conceded that LMP signals 1127. Several parties disagree with there are no current practices or rules on
have proven insufficient to create a Transparent Dispatch Advocates and which to model structures for the TDA
robust grid. In TAPS view, this counters argue that the proposal would require proposal. Other commenters similarly
Transparent Dispatch Advocates’ claims the establishment and operation of assert that the TDA proposal would
that their proposal will reveal the value markets by transmission providers.686 impose significant administrative
of transmission upgrades and encourage APPA and TDU Systems assert that burdens and expenses on transmission
investment. under the TDA proposal transmission providers, especially if an independent
1122. Several commenters submit that providers would select bids, from entity were required for
the TDA proposal raises Standards of among a variety of affiliated and implementation, and that most of these
Conduct issues.685 They argue that unaffiliated resources, that most costs would be shifted to native load
requiring the TDA proposal would effectively relieve constraints. customers.687 Xcel argues that
complicate if not undermine the Community Power Alliance, Georgia redispatch cannot be cost-effectively
functional separation and information Commission, Southern and Entergy managed unless done within the context
sharing policies of the Standards of assert that the TDA proposal would of a regional Day 2 energy market.
Conduct because the transmission result in the establishment of formal 1130. NRECA asserts that
function would be performing LMP markets in non-RTO/ISO areas, or transmission providers would need an
merchant, or at least merchant-related, at least start down the ‘‘slippery slope’’ enormous amount of data, including
functions. According to Community to LMP markets. Community Power resource status, marginal generation
Power Alliance, the requirement that Alliance and Entergy contend that costs, start up costs, ramp rates, and
transmission providers allow merchant adoption of the TDA proposal is in environmental costs of operation, to
generators to offer to sell generation to conflict with the purpose of the redispatch resources. NRECA asserts
rulemaking as stated in the NOPR and that the allocation of redispatch costs
684 E.g., LPPC Supplemental, TAPS
for multiple customers taking redispatch
Supplemental, NRECA Supplemental, Southern 686 E.g., APPA Supplemental, LPPC
may be difficult.
sroberts on PROD1PC70 with RULES

Supplemental, South Carolina E&G Supplemental, Supplemental, TDU Systems Supplemental, NRECA
and E.ON Supplemental. Supplemental, Progress Energy and MidAmerican
685 E.g., Nevada Companies Supplemental, Supplemental, Southern Supplemental, Duke 687 E.g., Community Power Alliance

Community Power Alliance Supplemental, Supplemental, OG&E Supplemental, Georgia Supplemental, Southwest Utilities Supplemental,
Southwest Utilities Supplemental, and Southern Commission Supplemental, and North Carolina Florida Commission Supplemental, Ameren
Supplemental. Commission Supplemental. Supplemental, and Entergy Supplemental.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00146 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12411

1131. Xcel, APPA, and TDU Systems transmission function into a generation the TDA proposal could not be justified
assert that the TDA proposal would not procurement function, violating the under these provisions of the FPA.
address concerns about subjective scope of the Commission’s jurisdiction. Commission Determination
redispatch decisions by transmission Southern, LPPC and North Carolina
providers. TDU Systems argue that the Commission add that the TDA proposal 1136. The Commission agrees with
proposal would allow for the functional would be in violation of section 201 of the Transparent Dispatch Advocates
equivalent of an RTO market, without a the FPA that expressly limits the proponents that greater transparency of
market administrator that satisfies the Commission’s jurisdiction to matters reliability redispatch information can
independence criteria of Order No. 2000 which are not subject to regulation by provide benefits to consumers, as well
or Order No. 888. APPA asserts that the States. Southern further asserts that as increase efficient use of the existing
posting of information concerning the this is made clearer by the exclusion in transmission grid. We are therefore
nature of congestion at designated section 201 of ‘‘facilities used for the adopting certain reforms, as explained
flowgates would be followed by generation of electric energy’’ from the in the section below, that will increase
differences of opinion as to how the Commission’s jurisdiction. Southern the availability and transparency of
dispatch entity is exercising its contends that mandated cost-based sales redispatch costs. However, we are
judgment in calculating the costs and in would also constitute an unlawful adopting these reforms in the context of
redispatching resources. taking of private property under the the existing obligation to provide
1132. Southwest Utilities and Fifth Amendment of the Constitution. network and point-to-point transmission
Southern assert that the proposal raises service under the pro forma OATT. We
significant questions regarding 1134. LPPC states that Transparent will not adopt the portion of TDA
commercial, operational, economic, and Dispatch Advocates seek to reason proposal that would require the creation
compliance issues that remain around section 201 of the FPA in of new services or any broader market
unanswered. For example, Southwest arguing that redispatch ‘‘does not reforms.
Utilities argues that it would appear that involve the sale of electricity for re-sale 1137. The TDA proposal has
under the TDA proposal a transmission or consumption; it involves the generated controversy for several
provider accepting a third party bid provision of a service to support reasons, including the lack of clarity in
would be required to assume the transmission service.’’ 689 LPPC the proposal, certain inconsistencies
commercial obligation, including credit counters that, in redispatch, generation that appear in Transparent Dispatch
risk associated with the bid and the is used instead of transmission service Advocates’ various submissions, and
posting of collateral, and would execute rather than in support of transmission concerns that Transparent Dispatch
the contract with the third party bidder service. North Carolina Commission, Advocates’ true intent is to restructure
under currently unspecified terms and LPPC and APPA argue that the courts bilateral markets. We believe that many
conditions. Southwest Utilities and have previously rejected Commission of the concerns regarding the TDA
Southern further argue that the proposal attempts to extend regulation to matters proposal are overstated, but we do agree
fails to resolve how operational and specifically excluded, statutorily, from that it lacks clarity and consistency in
economic liability to the redispatch regulation on the grounds that they are many important respects. For example,
customer would be impacted in the the functional equivalent of a it is not clear whether the proposed
event of non-performance by a third jurisdictional service.690 LPPC also service would be available to all
party supplier. Southwest Utilities also asserts that section 217 of the FPA customers, any point-to-point customer
asserts that it is unclear whether the specifies that utilities have a right to use including those taking non-firm service,
TDA proposal could function within the their transmission facilities on a priority or solely to long-term firm point-to-
rated path/contract path model of much basis in order to meet their core service point customers.692 Additionally, while
of the Western Interconnection. obligations. Transparent Dispatch Advocates
1133. Many parties argue that 1135. North Carolina Commission contend that ‘‘the one step’’ required of
implementation of the TDA proposal asserts that in Order No. 888 the the Commission is to implement a
would raise jurisdictional issues.688 Commission interpreted its authority redispatch cost posting requirement,693
Community Power Alliance, South under sections 205 and 206 of the FPA the TDA proposal also would require
Carolina E&G, Progress Energy, to include the effect the Rule may have the Commission to expand the current
MidAmerican and Southern assert that over generation facilities because redispatch obligations under the pro
the TDA proposal conflicts with state preventing undue discrimination is one forma OATT and adopt complex
and federal laws in that it forces of the matters specifically provided for settlement mechanisms to account for
transmission providers to use generation in Part II. North Carolina Commission third party redispatch. The different
(that was built, dedicated and argues that California Independent TDA proposals also vary as compared
dispatched to serve retail and wholesale System Operator v. FERC,691 however, with each other. For instance, the TDA
customers at least cost) to serve other establishes limits on how broadly Summary states that transmission
wholesale suppliers and customers. sections 205 and 206 can be interpreted. providers would not be obligated to
Community Power Alliance argues that North Carolina Commission contends provide their resources for real-time
states, not the Commission, have that sections 205 and 206 historically redispatch, but the Transparent
authority to regulate how utilities have been interpreted to apply to the
dispatch generation and procure rates for wholesale sales and purchases,
692 Compare Transparent Dispatch Advocates

resources. Further, Community Power Supplemental at 2 n.4 (stating that the proposed
rather than to the underlying generating service would supplement the existing OATT
Alliance asserts that requiring utilities facilities. As a result, North Carolina requirement to provide redispatch to long-term firm
to establish platforms for third-party point-to-point customers) and Transparent Dispatch
Commission argues that the adoption of
generators’ offers would convert the Advocates Supplemental at 5 (discussing the
sroberts on PROD1PC70 with RULES

proposal as a remedy for undue discrimination


689 Transparent Dispatch Advocates Reply at 17.
688 E.g., APPA Supplemental, LPPC against firm point-to-point customers) with
690 CitingNorthwest Pipeline Corp. v. FERC, 905 Transparent Dispatch Advocates Supplemental at
Supplemental, Community Power Alliance
Supplemental, South Carolina E&G Supplemental, F.2d 1403, 1410–11 (10th Cir. 1990); Detroit Edison 14–15 (demonstrating the redispatch pricing
Progress Energy and MidAmerican Supplemental, Co. v. FERC, 334 F.3d 48, 54–55 (D.C. Cir. 2003). mechanism for a non-firm transaction).
and Southern Supplemental. 691 372 F.3d 395 (D.C. Cir. 2004). 693 Transparent Dispatch Advocates Reply at 18.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00147 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12412 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Dispatch Advocates Supplemental Commission has found that this of the planning redispatch service.
Comments make clear that the treatment meets the comparability Transmission providers therefore would
transmission provider would be requirements enunciated in Order No. only be able to evaluate the availability
obligated to use its own (or affiliated) 888.696 of their own resource as they do today.
resources to provide this redispatch. 1139. Next, we also decline to adopt Thus, Transparent Dispatch Advocates
1138. We first address the contention a requirement for transmission have failed to show how its proposal
of Transparent Dispatch Advocates that providers to incorporate offers to would supplement provision of long-
the real-time reliability redispatch redispatch from third parties into their term rights.
obligation of transmission providers reliability redispatch or planning 1141. Because we find that the TDA
must be extended to ‘‘non-network redispatch. Mandatory inclusion of proposal for real-time redispatch and
transmission customers’’ to remedy third party offers is not necessary to third party participation is unnecessary
undue discrimination. We disagree. In remedy undue discrimination. The pro to remedy undue discrimination or
order to remedy undue discrimination, forma OATT obligates transmission comparability issues, we need not
we have made changes to the pro forma providers to use their resources to address the issue of the scope of the
OATT to implement a new conditional provide, where available consistent with Commission’s jurisdiction as it relates to
firm option for point-to-point service reliability, redispatch service because the TDA proposal.
and we make changes to the existing they do so when serving their native (2) Redispatch Rate Transparency
planning redispatch obligation. load customers. Third party generators
However, Transparent Dispatch do not have this obligation, nor do the Comments
Advocates have failed to show that the Transparent Dispatch Advocates 1142. PJM argues that if the
unavailability of reliability redispatch propose to create such an obligation. Commission does not provide for
for point-to-point transmission Rather, under the TDA proposal, independently administered real-time
customers amounts to undue transmission providers would remain spot markets, it should require
discrimination. Order No. 888 provided obligated to provide redispatch service, transmission providers to ‘‘make public
for reliability redispatch for network but third party generators would have their dispatch sequence and the real-
customers but not for firm point-to- only the option of doing so. Transparent time marginal costs of electricity.’’ 697 In
point customers.694 There is a good Dispatch Advocates are therefore not reply comments, Transparent Dispatch
reason for this distinction. The pro proposing comparable treatment and we Advocates request that the Commission
forma OATT requires network decline to adopt the proposal. This require publication of ‘‘dynamic real-
customers to make their generation notwithstanding, we believe that time value of what [each transmission
resources available to the transmission redispatch offers by third party provider] would charge to provide
provider to provide reliability generators can increase system redispatch service at specified
redispatch to maintain the reliability of reliability and reduce costs to customers congestion locations within the
service to both native load and network by increasing the planning redispatch transmission provider’s system and at
customers. There is no corresponding options available to transmission specified flowgates at the border of the
obligation on point-to-point customers providers. We therefore are adopting, as transmission provider’s system.’’ 698 In
to make their generation resources explained above, a requirement that supplemental comments, Transparent
available to provide reliability transmission providers modify their Dispatch Advocates state that ‘‘[t]he
redispatch. Therefore, the two services OASIS to allow for the posting of third essence of the TDA proposal is to
are not comparable in this respect, party offers to supply planning require transmission providers to make
which is why reliability redispatch redispatch. This OASIS posting real-time information about the cost of
service was not required for point-to- requirement does not obligate redispatch available on their OASIS in
point customers. However, if a transmission providers to incorporate order to allow more efficient use of the
reliability problem does arise, any bids from third parties into their transmission system.’’ 699 Transparent
curtailment of firm point-to-point redispatch; rather, posting of third party Dispatch Advocates, EPSA and AWEA
transmission service must be on a offers to provide redispatch may be used state that the posting requirement
nondiscriminatory and pro rata basis by transmission customers to secure should be limited to pre-determined
with the treatment of network service planning redispatch provided the flowgates and that the estimated price
and native load customers.695 The appropriate agreements are reached for redispatch should be posted
between the customer, third party frequently and sufficiently in advance of
694 See pro forma OATT section 33.2; see also
redispatch provider, transmission the hour in which the price would be
Midwest Independent Transmission System
Operator, Inc., 84 FERC ¶ 61,231 at 62,168 (1998) provider and reliability coordinator. effective in order to allow the
(‘‘redispatch will be utilized to avoid the 1140. We disagree with Transparent transmission customer to change its
curtailment of firm point-to-point services, a Dispatch Advocates and their schedule and avoid redispatch charges.
requirement that is not imposed under the pro supporters that their proposal for real- 1143. EPSA, AWEA and Transparent
forma tariff.’’); Mid-Continent Area Power Pool, 87
FERC ¶ 61,190 at 61,726–27 (1999) (finding no time redispatch and third party Dispatch Advocates state that since this
obligation to offer reliability redispatch to point-to- generation participation would allow for information is available today and
point customers and no obligation for point-to-point additional long-term rights through considered by transmission providers in
customers to participate in reliability redispatch). planning redispatch. If third party serving their own native load, there are
695 See, e.g., North American Electric Reliability
participation in the offer of redispatch is no impediments to implementing their
Council, 88 FERC ¶ 61,046 at 61,123–24 (1999)
(explaining that pro rata curtailment is consistent voluntary, transmission providers proposed posting requirement.
with comparability even if network/native load would not be able to depend upon third Transparent Dispatch Advocates argue
reduction is accomplished by redispatch and point- party resources in evaluating the that concerns about release of
to-point customer reduction is not); Northern States confidential data can be addressed by
availability of resources during the term
sroberts on PROD1PC70 with RULES

Power Co., 83 FERC ¶ 61,338 at 62,369 (1998) (the


existence of redispatch options is not a criterion
697 PJM at 6.
under the pro forma OATT for disproportionate FERC, 176 F.3d 1090 (8th Cir. 1999) (Northern
curtailments), reh’g, clarification and stay denied, States Power). 698 TransparentDispatch Advocates Reply at 5.
84 FERC ¶ 61,128 (1998), remanded on other 696 Northern States Power, 83 FERC ¶ 61,338 at 699 TransparentDispatch Advocates
grounds sub nom. Northern States Power Co. v. 62,369. Supplemental at 7.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00148 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12413

using system costs instead of unit- market certainty of least cost redispatch undue discrimination. Williams
specific cost data to calculate the posted and appropriate bid selection. proposes that affiliate and third-party
redispatch price. EPSA and AWEA state 1145. PGP states that the redispatch generators submit either a pre-
that there are not confidentiality issues option should be available irrespective established rate structure or formulary
with the Transparent Dispatch of time frame, but must recognize the pricing methodology prior to the
Advocates’ posting proposal because limited ability of the transmission provision of redispatch service.
redispatch costs are not the costs that provider to identify likely redispatch Williams states the primary
the transmission provider is incurring to costs further out in time. Thus, PGP implementation impediment to greater
sell energy into the market: they argues, posting redispatch costs in areas transparency of redispatch cost
contend that redispatch costs are the net without organized markets should focus information is the accuracy and
cost incurred by the transmission initially on real-time reliability availability of redispatch costs.
provider, e.g., the difference between redispatch, later expanding to longer 1148. BP Energy submits that posting
the costs of ramping up and ramping time frames. PGP asserts that redispatch the costs of redispatch is not the same
down resources. EPSA and AWEA also should be undertaken only when firm as posting operational cost curves of
state that there would be no competitive bids are available and the transmission specific generating units. BP Energy
concerns over the posting of this customer has accepted responsibility for adds that, given the availability of
information from third party suppliers redispatch costs, which should be based redispatch costs, there is no reason to
because the suppliers names need not on just and reasonable prices and must post the differential in unit-specific
be used. be known with a degree of certainty. costs as a supplement to marginal prices
1144. Some commenters do not PGP adds that the transmission provider posted at significant locations
believe that making certain information should establish protocols that support throughout the control area. PGP states
publicly available will result in firm bids, which would be published that there is no need to establish
confidential information disclosure.700 and, if accepted, result in binding markets to provide real-time redispatch.
PPL states that while confidentiality obligations on the part of the bidders. Rather, PGP asserts that limited
concerns must be considered, the nature PGP argues that it is reasonable for protocols can be established for specific
and type of information that is publicly transmission providers to post real-time locations or types of congestion that
provided may be structured so as to bids on constrained paths that are may be directly relieved via redispatch.
alleviate or minimize such concerns. otherwise subject to curtailments to PGP believes that the Commission
PPL argues that rather than posting ensure compliance with reliability should avoid establishing detailed rules
specific generator cost information the criteria. PGP contends that postings governing redispatch protocols, but
all-in price for redispatch may be posted should take place on the transmission rather should permit regional practices
instead. BP Energy argues that posting providers’ OASIS and that all to be developed that result in ‘‘just and
redispatch prices at specified locations information should be retained by the reasonable’’ charges for redispatch
reveals the economic value of adding transmission provider. PGP submits that service.
transmission/generation at those redispatch bids should be explicitly 1149. In its reply comments, Southern
locations, but does not reveal the added to the Commission’s Electric states that requiring vertically integrated
production cost associated with specific Quarterly Reports filing requirements if utilities to post their real-time marginal
generation resources. BP Energy states not already required. costs of electricity would be
that hourly redispatch costs should be 1146. Constellation argues that the
discriminatory and violate the Trade
posted for all ‘‘significant congested Commission should require each
Secrets Act.702 Southern states that
interfaces’’ within a transmission transmission provider to post two
values to the market on its OASIS site, RTOs do not make public the marginal
provider’s control area and for all
in order to enhance transparency: costs of the utilities participating in
interfaces at control area boundaries.
historical costs of redispatch at certain their markets, thus requiring other
PGP asserts that transmission providers
specified flowgates (perhaps those most transmission providers to do so would
with OATTs should post any available
congested historically) and real-time be discriminatory. Southern states that
information on hourly redispatch
redispatch costs at the same flowgates. marginal costs information is
costs.701 PGP and PPL argue, however,
Constellation submits that each commercial or financial information
that there should be an appropriate lag
transmission provider engages in protected by federal statute that if
in the disclosure of actual redispatch
costs in order to address confidentiality redispatch and thus can readily released would put it at a competitive
concerns. Williams states that increased ascertain the cost of redispatch at disadvantage and harm its customers by
transparency and proper monitoring are various locations. Constellation argues allowing competing generators to price
immediate, real solutions to ‘‘issues’’ that posting such costs will enable their power just below the published
with the posting of the cost of transmission customers to more marginal costs.
redispatch. Williams asserts that those accurately assess the potential costs of 1150. Several parties assert that the
customers requesting redispatch should redispatch prior to deciding to incur TDA proposal would require the posting
be provided the cost differential redispatch costs. Constellation adds that of vertically integrated utilities’
between the original dispatch and the the customer receiving redispatch generation costs and thus would
redispatch and that post audit should be obligated to pay the actual provide competitors and buyers with
redispatch data and system models can costs of redispatch, regardless of the commercially-sensitive information.703
be made available (after the expiration costs reflected in the postings, which, 702 18U.S.C. 1905.
of a non-disclosure period) to provide Constellation contends, should reflect 703 E.g.,
Entergy Supplemental, Community
the transmission provider’s most Power Alliance Supplemental, Progress Energy and
700 E.g., EPSA and AWEA Supplemental, BP accurate and up-to-date information. MidAmerican Supplemental, Southern
sroberts on PROD1PC70 with RULES

Energy Supplemental, and California Commission 1147. Williams believes that Supplemental, Southwest Utilities Supplemental,
Supplemental. Transparent Dispatch Advocates’ Nevada Companies Supplemental, OG&E
701 PGP asserts that the transmission provider Supplemental, Florida Commission Supplemental,
should be required to post redispatch information
redispatch proposal offers a partial PPL Supplemental, Ameren Supplemental, North
by event and by entity to address concerns about remedy to transmission congestion Carolina Commission Supplemental, and SEARUC
anticompetitive behavior. caused by insufficient infrastructure and Supplemental.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00149 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12414 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Many of these parties assert that posting neighboring transmission providers will Commission Determination
a utility’s incremental costs publicizes not run afoul of anti-trust and collusion 1156. After careful consideration of
the price at which the utility elects to concerns that they are colluding in price the comments of the parties, we adopt
operate resources rather than purchase setting; and how to verify providers are a posting obligation that balances
from a third-party.704 EEI and South selecting the lowest bid unless they are several competing considerations. First,
Carolina E&G assert that making this required to post all third party generator we agree with Transparent Dispatch
information public may adversely affect bids as well as their own or their Advocates and supporting parties that
competition and markets. Duke argues affiliates’ cost of providing the service. the increased availability of information
that having the transmission provider 1153. Ameren asserts that the existing
regarding redispatch costs can benefit
post daily and hourly generator costs OATT contains requirements for
consumers and increase the efficient use
assigns it responsibilities that are information to be posted by
of the grid. Second, we are cognizant,
beyond the typical transmission transmission providers, and does not
however, that increased posting and
function. Duke urges the Commission to believe that additional posting ought to
reporting can impose cost burdens on
consider voluntary alternatives to be required. Ameren provides several
transmission providers or otherwise
resource-specific cost information that recommendations were the Commission
harm market participants. For example,
would divulge competitively-sensitive to adopt some or the entire TDA
proposal. First, Ameren asserts that the reporting obligations can reveal
data. SEARUC argues that any
there are many different ways to confidential information that could
incremental transparency improvements
estimate this cost and, in order to avoid harm market participants or increase the
not be implemented in such a manner
the creation of competing methods for cost of serving native load customers.
as to make competitively sensitive
estimating redispatch costs, the We also recognize that the posting or
information available to the public on
Commission must consider and provide reporting obligation should be
an inconsistent basis. Nevada
guidance on several questions.706 reasonably tailored to provide useful
Companies assert that the requirement
to make such information publicly Second, so that transmission providers information to consumers without, at
available to the transmission provider are not disadvantaged by this new the same time, imposing unnecessary
would have to be imposed upon all obligation, Ameren urges the burdens on transmission providers,
generators, including independent Commission to develop detailed either in the frequency of the posting
power producers, so that such requirements, including uniform obligation or the scope of information
information would lose the value it timelines for posting, guidelines for provided.
estimating cost, and inclusion of all 1157. In balancing these
derives from not being publicly known.
1151. Entergy argues that the dispatchable generation in the relevant considerations, we will, as explained
Commission is statutorily prohibited footprint. Ameren further argues that further below, adopt a requirement that
from requiring the disclosure of posting only the difference in costs transmission providers post certain
information that undermines fair would not address the potential for redispatch cost information associated
competition under the electric market anticompetitive impacts. Finally, with the existing redispatch services
transparency provisions in sections Ameren contends that the Commission that must be provided under the pro
220(b)(1) and (2) of the FPA.705 South may wish to consider implementing the forma OATT. We find that providing
Carolina E&G submits that the TDA changes only on an interim basis, then customers with additional transparency
proposal is inconsistent with this to observe whether there is any market and greater information regarding the
provision of the FPA. Southern further benefit or any competitive harm as a cost of congestion, will facilitate their
contends that mandating that result of the new requirements. consideration of planning redispatch
transmission providers post and offer 1154. Duke believes that the posting options which in turn will provide for
their generation on an at-cost basis, of hourly redispatch costs would create more efficient use of the grid. We stress,
while allowing third party generators to near-constant off-OASIS however, that this posting requirement
submit bid prices would also be communications between the relates only to the existing redispatch
discriminatory. TAPS asserts that the transmission provider and merchant services required under the pro forma
proposed real-time disclosure of bid and function employees, which, Duke OATT; it does not expand those service
cost information runs contrary to the asserts, would raise Standards of obligations. The primary purpose of the
Commission’s policy of a 6-month delay Conduct concerns. posting requirement is to ensure that all
for release of bid information. 1155. NRECA argues that allocated customers have access to this
1152. NRECA asserts that the costs may vary significantly regardless information, not only the customer
Transparent Dispatch Advocates fail to of methodology, which devalues the receiving the redispatch service.
explain why transmission providers posting of costs. North Carolina 1158. Moreover, the costs of the
coordinating with third parties or Commission argues that publishing dynamic posting requirement proposed
indicative redispatch costs in real time by Transparent Dispatch Advocates
704 E.g., Entergy Supplemental, Community would require a determination as to outweigh the benefits of such a
Power Alliance Supplemental, Southern how such costs are determined and requirement. Transparent Dispatch
Supplemental, Duke Supplemental and South Advocates propose that the posting
Carolina E&G Supplemental.
whether each component of such costs
705 Entergy refers to the following language: are appropriately charged to customers. requirement be limited to specified
(1) The Commission shall exempt from disclosure congestion locations within and at the
information the Commission determines would, if 706 Ameren raises several questions to this effect: border of each transmission provider’s
disclosed, be detrimental to the operation of an Does the transmission provider estimate cost effect system. Transparent Dispatch Advocates
effective market * * *; and (2) [i]n determining the across all market LMPs or just the congested points?
information to be made available under this section Should the analysis take into account credits and
have not proposed ex ante criteria to
and the time to make the information available, the adjustments to which some participants may be determine which flowgates would
sroberts on PROD1PC70 with RULES

Commission shall seek to ensure that consumers entitled? For what period should the transmission require posting. In fact, some members
and competitive markets are protected from adverse provider provide this estimate? For those of the Transparent Dispatch Advocates
effects of potential collusion and other transmission providers within a centralized market,
anticompetitive behaviors that can be facilitated by how should they treat market costs such as losses
coalition would have the posting
untimely public disclosure of transaction-specific or RSG (Revenue Sufficiency Guarantee in MISO) requirement apply to all transmission
information. in calculating the redispatch cost? facilities, whether or not they were

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00150 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12415

congested and whether or not customers all potential third party providers. This reliability redispatch is provided during
were seeking service over those OASIS modification, described above, the month, regardless of whether the
facilities. Such an open-ended will provide third parties seeking to transmission customer is required to
obligation to post costs for all facilities provide redispatch with the opportunity reimburse the transmission provider for
on a transmission provider’s system to frequently update the price of their those exact costs. Thus, if the
would unnecessarily impose offers as suggested by Transparent transmission customer pays for
uncertainties and unbounded Dispatch Advocates. redispatch pursuant to a negotiated
administrative costs on transmission 1161. We do believe, however, that fixed rate, the transmission provider is
providers. Additionally, depending on information regarding actual redispatch required to post and calculate the
the frequency of publication and the costs should be made more widely monthly average redispatch costs and
method used to calculate the estimates, available. Currently, when a the high and low costs in the month
the publication of these estimates could transmission provider provides even though the transmission provider
reveal sensitive confidential information reliability or planning redispatch, the will bill the customer the fixed rate. The
about transmission providers’ associated cost information is provided same posting requirement applies if the
generation costs that would likely harm only to the customer receiving the customer is paying a monthly ‘‘higher
existing markets and native loads. There service through its invoices. This of’’ rate.709 The transmission provider
is no simple formula for estimating the ignores the fact that information shall post this data on OASIS as soon as
costs that would fully mask this regarding the cost of redispatch can practical after the end of each month,
confidential information and at the benefit all customers and increase the but no later than when it sends invoices
same time provide practical information efficient use of the grid. We therefore
to transmission customers for
about the costs of redispatch. find that it is no longer just, reasonable
redispatch-related services. We direct
1159. While we agree that and not unduly discriminatory to limit
transmission providers to work in
transparency can benefit customers, the provision of this information only to
conjunction with NAESB to develop
Transparent Dispatch Advocates have the individual customers receiving the
this new OASIS functionality and any
not demonstrated the benefits of its service.
posting requirement to customers 1162. Accordingly, to provide greater necessary business practice standards.
seeking reliability or planning availability of redispatch information, 1163. There are several benefits to this
redispatch. Transparent Dispatch the Commission adopts certain posting requirement. First and foremost,
Advocates would have transmission additional posting requirements for it will give customers fairly current
providers frequently post an estimate of transmission providers. Specifically, we information regarding the cost of
the cost of the next increment of direct each transmission provider to redispatch of the congested
redispatch. Customers seeking post on OASIS its monthly average cost transmission facilities over which
redispatch would not know the actual of redispatch for each internal congested redispatch is provided, presumably
costs customers paid for redispatch. Nor transmission facility or interface over some of the most congested facilities on
would they be able to apply the estimate which it provides redispatch service transmission providers’ systems.
of cost to their transactions since most using planning redispatch or reliability Second, it will limit posting only to
transactions would involve more than a redispatch under the pro forma those congested transmission facilities
single increment of redispatch service OATT.707 Additionally, to demonstrate over which redispatch has actually been
and there might be multiple redispatch the range of redispatch costs each sought and granted and for which
transactions over a single transmission month, the Commission directs redispatch charges have been billed to
facility. Thus the estimate would only transmission providers to post a high customers. This addresses commenters’
be of value to the marginal customer and low redispatch cost for the month concerns about the posting of
taking a small amount of redispatch for each of these same transmission information that is valuable only
service. Transmission providers would constraints. The transmission provider hypothetically. Third, because we
expend time and money determining shall calculate the monthly average cost require the posting of average redispatch
the correct formula to use to estimate in $/MWh for each congested costs, not real-time redispatch costs or
costs, collecting data for the inputs to transmission facility by dividing real-time system lambda or system
the calculation and frequently posting monthly total redispatch costs (at the incremental costs, it will not be harmful
estimates throughout each day that facility) by the total MWhs that would to native load or reveal otherwise
could have little or no correlation to the otherwise be curtailed (at the facility) in competitively sensitive information.
actual costs a transmission customer the month absent the redispatch.708
1164. Finally, in addition to the above
would pay for the redispatch service. Transmission providers shall post
1160. Third party participation in posting requirement, we note that, as
internal constraint or interface data for
redispatch is one of the benefits part of the transmission planning
the month if any planning redispatch or
Transparent Dispatch Advocates point provisions adopted in this Final Rule,
to in support of its proposed posting 707 The relevant reliability redispatch costs for we are providing customers with a right
requirement. Transparent Dispatch posting purposes are those costs the transmission to request a study of a defined number
Advocates would have transmission provider invoices network customers based on a of congested transmission facilities on
load ratio share pursuant to section 33.3 of the pro an annual basis. This will provide
providers act as the conduit for service forma OATT. The transmission provider need not
from third party redispatch providers, perform new calculations of out-of-merit dispatch
customers an additional opportunity to
collecting from customers and paying costs; rather the reliability redispatch invoices evaluate redispatch costs, including
third party providers. As described should form the basis of information from which costs for those congested transmission
the transmission provider determines monthly facilities for which redispatch service
above, we are allowing third party average reliability redispatch costs.
participation in planning redispatch 708 For example, if reliability redispatch is used
has not been granted.
sroberts on PROD1PC70 with RULES

without requiring transmission by the transmission provider to prevent curtailment


providers to act as bill collectors for of 10 MW of transmission provider or network 709 This is not a new calculation for the

customer load for 5 hours during the month across transmission provider because the transmission
third party redispatch providers or flowgate A, the transmission provider would use 50 provider must determine the redispatch costs to
requiring coordination agreements MWh as the divisor to determine the monthly know whether to charge higher of the embedded
among each transmission provider and average cost of redispatch for flowgate A. rate or the redispatch costs.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00151 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12416 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

c. Other Requested Service 1168. MidAmerican urges the conditional firm service. However,
Modifications Commission to allow for dynamic requestors have not adequately
NOPR Proposal scheduling service between control addressed concerns about the service,
areas on a case-by-case basis, by including the potential for hoarding
1165. In the NOPR, the Commission including and pricing the service in the transmission and the reliability issues
summarized requests for various new service agreement. MidAmerican states related to evaluating the availability of
services made in response to the NOI. that this service would be similar to the service or granting the service over
The Commission’s proposed solutions point-to-point service, but would allow many years. A seasonally shaped service
evaluated solely the planning redispatch the transmission customer to could exacerbate the lumpiness of
and conditional firm options. dynamically monitor its loads in transmission investment by preventing
Comments neighboring control areas and dispatch customers willing to pay for
its own remote resource to meet the load transmission upgrades from obtaining
1166. Commenters make several fluctuations in load pockets served by all twelve months of service. While we
suggestions with regard to additional other transmission providers. will not reduce the number of services
services or modifications to existing MidAmerican further states that this required as suggested by TranServ, the
services. Most popular among the new service is necessary in the Western Commission must limit the number of
suggested new services is long-term, Interconnection because neither point- new services adopted and modifications
seasonally-shaped firm point-to-point to-point nor network service meets the to existing services to a reasonable
service. Several commenters support needs of loads that are not confined to number that transmission providers can
this service for circumstances in which a single geographic area served by a reliably implement. For these reasons,
the transmission provider determines single transmission provider. we decline to adopt any additional
that the requested service is available 1169. Barrick states that the proposals or modifications to firm
during some, but not all, months of each Commission should require point-to-point service beyond those
year of a single or multiyear request.710 transmission providers to confirm the directed above in this Final Rule. Of
Commenters suggest that the long-term, availability of secondary service for course, transmission providers remain
seasonally-shaped service would network customers on a monthly or free to voluntarily propose additional
provide an option for the transmission quarterly basis so that network services that are consistent with or
customer in lieu of costly upgrades customers can plan ahead for the use of superior to the pro forma OATT, as
without the operational difficulties of secondary service. In its reply modified by this Final Rule.
conditional firm service. In its reply comments, Seattle supports the 1171. The Commission rejects the
comments, Powerex states that this development of short-term redispatch request to adopt long-term non-firm
product would have less of an adverse service, currently under discussion for service because there is no indication
impact on existing firm rights holders. provision in the Pacific Northwest. that customers would find such a
Northwest IOUs propose that the TranServ requests that the Commission service useful and it would be
transmission customer pay the long- clarify whether sequential reservation of inconsistent with the policy in the pro
term point-to-point transmission service 12 consecutive months of monthly firm forma OATT that values firm service
rate prorated for the portion of the year service is long-term service. TranServ over non-firm service.
for which it receives the service. Public requests that the Commission direct the 1172. MidAmerican requests that the
Power Council states that the development of business practices by Commission allow a point-to-point
transmission customer would be free to NAESB to allow customers to designate service that would let a transmission
purchase non-firm or secondary service minimum term and capacity for partial customer monitor its load and dispatch
for the periods when firm service interim service, similar to the practice its remote resources to meet load
through the seasonally-shaped service employed by Bonneville. fluctuations. In Order No. 888–A, the
was unavailable. Northwest IOUs argue Commission clarified that this type of
Commission Determination dynamic scheduling was not mandated
that ‘‘cream-skimming’’ is avoided by
processing only requests for long-term 1170. The Commission rejects the Order No. 888, but that nothing in Order
service and having the transmission requests to order new services or No. 888 precludes a transmission
provider determine the availability of modifications to existing services provider from offering it as a separate
the service. suggested by commenters. We believe service.711 Thus, MidAmerican may
1167. Powerex supports the that the modifications to point-to-point propose such a service pursuant to an
implementation of a long-term non-firm transmission service adopted herein FPA section 205 filing with the
best address the issues raised by these Commission, and we will consider it, as
point-to-point service. Tacoma believes
requests. The planning redispatch and we would any new service proposal, on
priority non-firm or partial firm
conditional firm options provide a a fact-specific, case-by-case basis.
transmission services are alternatives to
means of remedying undue 1173. Barrick requests that the
planning redispatch. Entegra proposes
discrimination, and increasing Commission require the confirmation of
an additional service that would allow
transparency and access to the grid by the availability of secondary service for
the customer, in the event of a
point-to-point customers. We note that network customers on a monthly or
constraint, to agree to either pay for
there is considerable overlap between quarterly basis so that network
redispatch or have its service curtailed.
these options and the new services customers can plan ahead for the use of
In contrast to these request for new
suggested by commenters. However, we secondary service. As we stated in the
services, TranServ states that simplified
find that the introduction of the NOPR, secondary network service refers
services and a reduction in the number
requested new services may create to transmission service for network
of services would increase the
greater complexities than those present customers from resources other than
transparency and fluidity of electricity
sroberts on PROD1PC70 with RULES

in the planning redispatch and designated network resources and is


trading.
conditional firm options. For example, provided on an ‘‘as available’’ basis.
710 E.g., MidAmerican, Public Power Council, several commenters propose a long-term Since the secondary service is provided
Northwest IOUs, Xcel, Powerex Reply, PPL, and seasonally shaped firm point-to-point
Seattle Reply. service as a superior option to the 711 Order No. 888–A at 30,235–36.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00152 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12417

on an as available basis, Barrick’s OATT services or new services, they transmission facilities and market
request seeks to allow secondary may submit an FPA section 205 filing to efficiencies. Chief among the arguments
network service to pre-empt firm uses of propose such modifications and the cited by those objecting to the required
the system, such as short-term firm Commission will evaluate such service is the potential adverse effect on
point-to-point service, for what is a less proposals on a case-by-case basis. those serving native load or taking
than firm service. Barrick has not clearly longer term service due to increased
2. Hourly Firm Service
articulated why this proposal is frequency of curtailments. Other
necessary to prevent the exercise of NOPR Proposal objections to the required service
undue discrimination or why service 1177. In the NOPR, the Commission include reliability concerns and the
from designated network resources proposed to add point-to-point hourly unjustified curtailment priority that
would not meet its need for firmer firm service to the pro forma OATT. The would be afforded to short-term
secondary service. Thus, we reject Commission stated its belief that adding customers that have not financially
Barrick’s request. this service would eliminate a barrier to committed to long-term grid service. To
1174. With regard to Seattle’s support the development of markets and thereby the extent hourly firm service is
for redispatch being developed in the decrease opportunities for undue required, commenters generally support
Pacific Northwest, we believe that this discrimination. The Commission further use of the IES Method for pricing,
type of redispatch shares many of the stated that the concerns expressed in although some commenters ask the
attributes of the Transparent Dispatch Order No. 888 regarding the unduly Commission to allow pricing to vary
Advocates proposal rejected above. discriminatory effects of hourly firm according to regional practice. As for
Although we acknowledge that market service have proven unfounded. batching and scheduling, many parties
mechanisms that provide hour-ahead or Consistent with our precedent, the request that the Commission clarify
real-time redispatch for all transmission Commission proposed to use the ‘‘IES specific details of each of these
customers can provide benefits to Method’’ to price hourly firm service proposals to prevent future disputes.
customers and efficient use of the and apply different pricing based on Mandatory Hourly Firm
transmission grid, for the reasons stated whether the service is taken during peak
in the prior section, we will not require or off-peak hours.713 The Commission 1180. Various commenters state their
in this Final Rule that all transmission explained that this pricing method general support of, or non-opposition to,
providers implement such market would ensure that hourly firm the proposal to require hourly firm
mechanisms. We note that nothing customers pay a fair share of the costs service.714 Among those who support it,
prevents the Commission from of the transmission system. several state that they already supply
reviewing proposals for such market 1178. The Commission proposed the service themselves.715 Such
mechanisms on a case-by-case basis. We allowing transmission customers to commenters argue that hourly firm
note that the conditional firm and batch requests and schedules for hourly service would decrease opportunities
planning redispatch options adopted in firm service that will be provided for undue discrimination, enhance the
this Final Rule will provide some of the within the same calendar day. customer’s ability to participate in the
flexibility Entegra seeks. Customers Schedules for firm hourly service, like real-time energy markets, encourage
taking service under these options will all other firm schedules, would be due trade and marketing liquidity, increase
be able to choose, when executing the by 10 a.m. the day before the service is firm uses of the grid, allow greater
service agreement, between curtailment to commence. The Commission also customer choice, increase efficiencies in
and redispatch. proposed that, consistent with other wholesale markets, and help maximize
1175. Also, the Commission clarifies durations of service, the confirmation use of existing transmission facilities.716
for TransServ that twelve months of period for hourly firm service specified WAPA states that its experience
consecutive monthly firm service, in section 13.2 of the pro forma OATT indicates that the current provisions for
where the term of any particular would allow longer term requests for preempting shorter-term transmission
monthly service agreement is for less service to preempt shorter hourly firm service with longer-term service, as
than a year, is not long-term service.712 requests for service until one hour codified in OATT section 13.2,
The Commission rejects TranServ’s before the commencement of hourly adequately serve to discourage
request that NAESB develop particular firm service. speculative hoarding of hourly capacity.
business practices regarding partial 1181. Numerous commenters
Comments objecting to the proposed service cite
interim service as TranServ has not
shown a need for such a requirement. 1179. Commenters are split on the effect of curtailment on customers
1176. The Commission continues to whether to require hourly firm service. taking network or longer term service,
encourage transmission providers to Varied interests express some support of especially in the service of native
propose other services that are the requirement, while mostly IOUs, load.717 Specifically, they argue that the
consistent with or superior to the pro cooperatives, and public power inclusion of an additional short-term
forma OATT that meet customers’ needs providers oppose the requirement. firm service would increase the
and make more efficient use of the Supporters, which include several
transmission system. We will not entities that currently offer hourly firm 714 E.g., Ameren, Arkansas Commission,

mandate that transmission providers service, foresee increased use of Bonneville, BP Energy, Constellation, FirstEnergy,
MidAmerican, MISO/PJM States, Morgan Stanley,
provide any service other than the Nevada Companies, Newmont Mining,
713 See IES Utilities, Inc., 81 FERC ¶ 61,187 at
services set forth in the pro forma OATT NorthWestern, Pinnacle, PPL, CREPC, and Suez
61,833–34 (1997), reh’g denied, 82 FERC ¶ 61,089,
since they may not be applicable in all Energy NA.
aff’d on other grounds sub nom. Wisconsin Public 715 E.g., Bonneville, Pinnacle (noting Arizona
circumstances. However, if transmission Power Inc. v. FERC, No. 98–61,089, 1999 U.S. App.
LEXIS 3998 (Feb. 23, 1999) (unpublished opinion) Public Service Company’s adoption of the service),
providers seek to provide any
sroberts on PROD1PC70 with RULES

(adopting peak and off-peak pricing to hourly non- PNM–TNMP, and WAPA (in its Desert-Southwest
modifications to the required pro forma firm transmission service); see also New York State region).
716 E.g., Arkansas Commission, BP Energy,
Electric & Gas Corp., 92 FERC ¶ 61,169 at 61,593–
712 See pro forma OATT section 1.18 (defining 94 (2000) (approving application of the IES Method FirstEnergy, Morgan Stanley, Pinnacle, PNM-
long-term firm point-to-point transmission service for time-differentiated hourly non-firm rate design), TNMP, and PPL.
as service with a term of one year or more). order on reh’g, 100 FERC ¶ 61,021 (2002). 717 e.g., APPA, Duke, EEI, MISO, and Southern.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00153 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12418 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

likelihood that longer-term service of transactions on a very short-term 13.2(iii)) and adopt the proposal to
would be curtailed and degrade the notice. require that hourly firm service be
reliability of service to native load, since 1184. Many argue that the scheduled the day before service is to
all firm service (point-to-point and justifications provided in Order No. 888 commence.
network), regardless of duration, would for not requiring this service remain 1187. Duke explains that the current
be curtailed pro rata. Objecting valid, such as the argument that the 10 a.m. deadline for firm schedules
commenters argue that such a result is service will invite cream skimming.721 need not be enforced in the absence of
unfair to customers that have made a MISO sees a likelihood that an ‘‘hourly hourly firm service and often is not
long-term commitment to taking service, priority war’’ would ensue on enforced (with transmission providers
including expanding the system;718 constrained interfaces between firm and acting on a comparable basis in waiving
inconsistent with FPA section 217(b)(4), non-firm requests and that resolving the deadline). Thus Duke identifies as a
which requires the Commission to these conflicts would be time drawback to the addition of hourly firm
promote the availability of transmission consuming and stretch its resources. service the likelihood that transmission
for native load service;719 and MISO argues that an hourly firm providers will enforce the 10 a.m.
inconsistent with the Commission’s product would degrade the value of deadline and thereby reduce existing
commitment in the NOPR to maintain non-firm service and that the flexibility.
existing native load protections.720 introduction of this new, logistically 1188. Some commenters objecting to
1182. Although transmission challenging service, further compounds the new service requirement argue that,
providers plan for their native load the task of rooting out undue if the Commission retains this service,
needs when calculating ATC, Imperial discrimination. MISO argues that the certain modifications should be
argues that they cannot always proposed mandatory introduction of made.723 These modifications include:
accurately predict these needs. Imperial this service will have serious adverse giving the service a lower curtailment
states that transmission providers have implications for many functioning priority, pricing it at a premium above
been able to rely on the release of RTOs. MISO contends that hourly firm the IES methodology, requiring that the
unscheduled capacity when balancing service should remain strictly optional firm hourly postings be based upon the
their schedules to meet fluctuating for RTOs arguing that weighing the pros daily firm ATC (with the additional
needs (such as during heat waves). In and cons of this new service can best be capacity that might be available in
view of the decline in transmission addressed within each RTO’s ‘‘shoulder’’ hours of the day being made
infrastructure relative to load stakeholder process. available only as hourly non-firm), and
throughout the country, NRECA objects 1185. TVA argues that hourly firm giving secondary network service a
to the reduction in ATC that would reservations would likely end up being higher priority over hourly firm. Duke
result from dedicating transmission bumped by requests for longer service argues on reply that, if the Commission
capacity to hourly firm service. NRECA (such as daily firm), consuming valuable determines that hourly firm service
argues that designated network transmission provider staff time and should be required, a technical
resources may no longer be regarded as resources on administrative tasks with conference should be held to develop
such because firm transmission to no real benefit and potentially appropriate, workable tariff language in
support them is not available on significant costs. Similarly, Southern light of the implementation issues
constrained transmission systems (i.e., argues that hourly firm service would raised by commenters.
most transmission systems). If hourly likely result in the transmission
provider receiving less revenues Voluntary Hourly Firm Service
firm service is to be required, Imperial
proposes also requiring transmission (because fewer customers would take 1189. Various commenters ask that
providers to make available all but 20 daily firm service) while incurring hourly firm service not be required and,
percent of non-reserved transmission as higher costs (due to implementation instead, continue to be allowed on a
firm so that non-firm service will be complexities), the net effect of which voluntary basis by willing transmission
available for the use of network would raise OATT charges. providers.724 These commenters
customers and native load providers. 1186. Among commenters offering generally argue that the service’s effect
qualified support for mandatory hourly on reliability, curtailment priority,
1183. Southern argues that the firm service,722 ELCON and FirstEnergy longer term service, transmission
provision of hourly firm service would
ask the Commission to monitor the use expansion, and the ability to serve
require the transmission provider to
of this service and to reconsider its native load counsels against mandating
predict the exact hour on which
continued need if it impairs the quality the service. NRECA argues that hourly
expected peak conditions will occur in
or availability of long-term firm firm service would unduly interfere
order to be able to post the amount of
services. Powerex argues that hourly with the ability of network customers
hourly firm service that will be available
firm point-to-point service could (and the transmission provider on
for each hour of a given day. If system
increase opportunities for undue behalf of its native load customers) to
conditions then change, Southern
discrimination unless the conditions use secondary network service, which is
continues, reliability could be placed in
under which the non-firm transmission offered only on an ‘‘as available’’ basis
jeopardy, which would result in long-
service can be interrupted are clarified. and therefore would have a lower
term service being curtailed. Southern
South Carolina E&G argues that the reservation and curtailment priority
also argues that the provision of this
Commission should give the service a than hourly firm service.
hourly firm service would complicate
lower curtailment priority than any 1190. NRECA notes that the Western
real-time operations and negatively
longer term firm service (citing as Interconnection, where hourly firm
impact reliability since, if curtailments
support the lower reservation priority service has proven to be a useful
on a specific path prove necessary, it is
for short term firm service in section product, differs from the Eastern
sroberts on PROD1PC70 with RULES

more difficult to curtail a large number


721 e.g., LDWP, MISO, Southern, TAPS, TDU 723 e.g.,
APPA, NRECA, Southern, and TAPS.
718 e.g., MISO and Southern. Systems. 724 E.g.,
APPA, Duke, East Texas Cooperatives,
719 e.g., APPA, NRECA, and Southern. 722 E.g., ELCON, FirstEnergy, Powerex, and South EEI, Imperial, LDWP, LPPC, Northwest IOUs,
720 e.g., Southern. Carolina E&G. NRECA, PJM, Southern, and TDU Systems.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00154 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12419

Interconnection in a number of respects, service is not interruptible during the ensure that capacity is utilized to meet
in particular, by virtue of extensive hour due to other non-reliability driven a real market need.
reliance on point-to-point service by requests, but rather at the start of the 1197. SPP urges the Commission to
LSEs to serve native load. For this next hour, provided sufficient apply the same reservation deadline to
reason, NRECA continues, public utility scheduling notice is given. Xcel hourly firm as used for daily firm
transmission providers should only be continues that this clarification would service in order to make the service
allowed to voluntarily offer hourly firm also stipulate that non-firm service (and easier to administer (and limit the
transmission service if the service is all other types of service) may be impact on non-firm service). Bonneville
available equally to all transmission curtailed without notice at any time for also suggests that reservation timing
customers and the new service does not reliability reasons. requirements be the same as those for
undermine the quality of, and flexibility hourly non-firm service and, with
of, the transmission provider’s existing Pricing respect to competing reservations,
network service (including secondary 1194. Many commenters support the hourly firm service be classified as
network service) and point-to-point Commission’s proposal to use the IES Short-Term Firm. TVA notes that
transmission service. NRECA also Method to price hourly firm service.725 although the scheduling deadline for
requests that the Commission clarify Several commenters suggest that the service is 10 a.m. the day before service
that the only circumstance in which Commission allow transmission is to commence, the NOPR also states
hourly firm service could be offered providers to define their own peak and that longer-term requests may preempt
would be if daily service were not being off-peak hours under the IES shorter requests until one hour before
fully used. methodology, with some suggesting that the commencement of service. TVA sees
1191. Northwest IOUs suggest that the it should be allowed as a regional an inconsistency in that it appears firm
Commission develop standardized variation to account for the different service can be reserved and scheduled
point-to-point hourly firm service peak times in regions such as the after 10 a.m. on the day prior all the way
provisions for the voluntary provision of WECC.726 East Texas Cooperatives asks up until one hour before the service is
this service by those transmission the Commission to require that revenue to commence. TVA argues that no
providers that determine such service from hourly firm service be applied as service that could preempt the hourly
would be appropriate to offer on their a credit to network service revenue service should be sold after the 10 a.m.
systems. TDU Systems argue that the requirements like other point-to-point day-ahead deadline, and requests that
Commission should condition approval services. PGP supports the IES Method, the Commission clarify this ambiguity.
of an hourly service on requirements but recommends that the Commission 1198. If the Commission requires
that a lower curtailment priority is be open to other approaches. hourly firm service, Progress Energy
established for hourly firm service than requests that it be offered on a day-
other firm services, including secondary Reservations, Scheduling, Preemption ahead basis only, as proposed in the
network service; and, it may only be and Right of First Refusal, Batching NOPR, to allow transmission providers
sold in the hour preceding the start of sufficient time to analyze the reliability
1195. Some commenters support the
service to ensure that hourly service impacts of the requested hourly firm
proposed reservation or scheduling
would not impede the provision of service. Nevada Companies recommend
requirements for hourly firm service.727
service to other firm services, including that any hourly firm service have the
Others commenters express concerns
secondary network service. In light of same scheduling deadlines as daily firm
regarding, or object to, this aspect of the
comments, Powerex abandoned its and that customers not be permitted to
hourly firm proposal.728 As discussed
initial conditional support for the submit hourly firm schedules
below, several commenters suggest
proposal to support voluntary provision throughout the day. In Nevada
modifications to different components
of the service. Companies’ view, this would enable
of the proposal.
transmission customers to schedule firm
Alternative Proposals 1196. Some commenters state that transmission only for the part of the day
1192. PJM recommends adding a hourly firm should be a means of selling that it is needed while, at the same time,
service similar to PJM’s non-firm willing unused capacity in hours not purchased transmission providers would not be
to pay congestion (NF–WPC) service for longer-term transactions and, as a overwhelmed with the task of
which may serve the same purpose as, result, it will be important to establish administering the reservation process.
and be an alternative to, hourly firm a sequencing for sales that accomplishes 1199. Some recommend that
service. NF–WPC service would be this so that cream skimming does not scheduling conform to the existing
evaluated for ATC and curtailed by occur.729 Tacoma recommends that the scheduling practices in each region,
transmission customers if the effective Commission establish hourly firm such as in the WECC.730 For its part,
price of congestion were too high. Thus, service as the lowest priority in the MISO argues that the proposed
NF–WPC service will result in a service request queue. Tacoma also scheduling deadline for hourly firm
reduction in all TLR curtailments. To suggests that the Commission limit the service is before the deadline for the
add this service to the OATT, PJM purchase of hourly firm in such a way submittal of the MISO daily firm
explains, all transmission providers as to assure that the purchase is not an service, which would require a
with control over dispatch would have attempt to manipulate a market, such as substantial change to its Energy Markets
to provide a transparent means for making the service available only to Tariff, firm service evaluation process,
redispatch to clear congestion and LSEs, which Tacoma states would and other firm and non-firm timing
maintain reliability on either side of a requirements. MISO argues that this
border. 725 E.g., Ameren, EEI, NorthWestern, PGP, and
could adversely affect the current Joint
1193. Xcel argues that it is possible PNM–TNMP.
and Common Market Alignment of
sroberts on PROD1PC70 with RULES

726 E.g., Northwest IOUs, Public Power Council,


that hourly firm service would not be Business Practices initiative with PJM.
and CREPC.
needed if the existing OATT were 727 E.g., Ameren, Duke, NorthWestern, PNM– Public Power Council offers
clarified as it relates to priority of non- TNMP, and WAPA.
firm service. Xcel proposes that the 728 E.g., Bonneville, Southern, and TVA. 730 E.g., MidAmerican, Northwest IOUs, Public

Commission could clarify that non-firm 729 E.g., Public Power Council and Tacoma. Power Council, and CREPC.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00155 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12420 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Bonneville’s scheduling timeline as an since they will know they will not be withdrawing an hourly firm request in
example in which longer blocks get bumped by other customers using the order to avoid potential ‘‘gaming’’ issues
priority over the shorter blocks within service. that may arise from entities requesting
the 10 a.m. to 2 p.m. preschedule-day 1203. Duke requests guidance on how transmission on a pre-scheduled basis
reservation period, and hourly firm is long the hourly firm customer has to and then asking for the request to be
bought within the day at the same times respond to a competing request. Since withdrawn during real-time. To simplify
as hourly non-firm transmission (i.e., up hourly firm could be preempted up to real-time administration of hourly firm
to 20 minutes prior to the delivery an hour before the schedule starts, Duke service, WAPA suggests that the
hour). argues that in many cases there will not Commission explicitly include in the
1200. Occidental requests that the be 24 hours available and the revised pro forma OATT a statement
Commission change the 10 a.m. day- scheduling deadline (of 10 a.m. of the waiving the Order No. 638 displacement
before scheduling timeline to be as close day prior to commencement of such rules for hourly requests during the
to real-time as possible. It contends that service) may have passed. For example, hour before the service is to commence.
under the pro forma OATT, merchant if a pre-confirmed, longer-term, 1208. Several commenters support the
generators still will be relegated to competing request is received just prior Commission’s batching proposal.731
making non-firm reservations and sales, to the deadline (one-hour prior to WAPA argues that the proposed
because the 10 a.m. prior day firm service commencing), Duke questions limitation on batching hourly firm
service scheduling timeline would whether the transmission provider is requests and schedules to within the
cause them to incur expensive required to offer the right of first refusal same day would alleviate the workload
reservations to the sales point, but not at all. issues associated with evaluating
be able to have the transaction tagged 1204. Joined by TranServ, Duke also individual hourly firm reservations in
with source and sink (as required under requests that the Commission provide order to identify conflicting schedules
the NERC tagging procedure), before guidance on how to administer the right across congested paths.
consummation of the firm hourly of first refusal when, for example, three 1209. MidAmerican objects to the
transaction. Occidental further contends different hourly customers have batching proposal, arguing that
that the change in scheduling timeline confirmed reservations on a constrained transmission requests should be
will not be problematic to the interface for different hours in a day and evaluated in queue order and schedules
transmission providers, particularly if the transmission provider then receives linked to a specific OASIS request.
the transaction takes place in a single a pre-confirmed request for daily service MISO argues that the batching proposal
control area. Occidental also argues that on the same path for the same day. may interfere with the established
the OATT benefits the transmission Alternatives solutions for this scenario protocols for transmission service
provider, which can favor its own or offered by Duke include offering the request processing. In MISO, for
affiliated generation when balancing shorter-term customers simultaneous or example, there is no interface for
with other control areas and dispatching consecutive opportunities to exercise Available Share of Total Flowgate
in real time. the right of first refusal, prohibiting the Capability, which would seem to
1201. Bonneville, which has provided preemption of multiple overlapping suggest that batch processing could
hourly firm service since 2002, takes requests, or denying shorter term infringe on the various Commission-
issue with the fact that the Commission customers a right of first refusal. Duke approved seams agreements.
proposes that the service would become recommends NAESB develop 1210. Some commenters offer
unconditional only one hour before the appropriate business practice standards modifications or request clarifications.
commencement of delivery. Bonneville after the Commission’s decision on this Bonneville proposes that NAESB
argues that its own timeline, under issue. develop industry standards for defining
which hourly firm service becomes 1205. With the NOPR’s potential for and processing batched reservations and
unconditional at the close of the adding more complexity with hourly schedules. EEI argues that transmission
preschedule window for the day of firm service under similar conditions as providers who offer hourly firm service
delivery (currently, at 2 p.m. of the other short-term firm services, TranServ should permit their customers to batch
preschedule day or as soon as requests that the Commission either multiple requests for service that have
practicable thereafter), is superior and eliminate the conditional nature of the same points of receipt and delivery;
should be adopted by the Commission. short-term firm point-to-point service are for the same quantity of service, and
Bonneville explains that, in its under the OATT (and the reservation are for the same day. Otherwise, EEI
experience, customers place great value window would be set to not interfere explains, batching will complicate the
on having unconditional firm rights with requests for daily firm service) or ability of the transmission provider to
before they reach the real-time allow hourly firm service to be study requests for hourly service.
scheduling window, and an hour leaves preempted without a right of first NorthWestern explains that it cannot
little or no time to make alternative refusal. fully support the Commission’s
arrangements if the hourly firm 1206. Duke requests that, whether or recommendation to allow ‘‘batching’’ of
reservation is preempted. Finally, not the Commission requires hourly requests without a more clear definition
Bonneville foresees potential reliability firm service, the Commission clarify of what may be batched and a
effects if a customer using hourly firm how the ‘‘short-term rights of first determination that requests of a longer
transmission for operating reserves is refusal’’ should be implemented in increment preempt shorter increment
preempted the hour before delivery, and section 13.2(iii) of the OATT, since requests (e.g., a request for daily service
is unable to make transmission there already is some lack of clarity with preempts a request for hourly service)
arrangements elsewhere. regard to this right for daily, weekly, regardless of how many hours are
1202. Ameren argues that a later and monthly service. batched together.
sroberts on PROD1PC70 with RULES

request for hourly firm service should 1207. Based on its experience, WAPA 1211. TranServ states support for the
not be able to preempt an earlier suggests that the Commission institute ability to batch requests and schedules
request, even if it is for a greater number limits on the allowable time period in for multiple hours of firm service with
of hours. According to Ameren, this will which customers may contact the
provide certainty to users of this service transmission provider for the purpose of 731 E.g., PGP, PNM–TNMP, and WAPA.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00156 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12421

varying capacity over the hours. 3. Rollover Rights impact on its system of serving a long-
However, with respect to competing 1214. Section 2.2 of the pro forma term firm transmission customer and
requests and the right of first refusal, OATT allows existing firm transmission grants the transmission customer
TranServ suggests that the preempting service customers—wholesale existing capacity, the transmission
request must be for a fixed capacity over requirements and transmission-only provider must plan and operate its
the term of the request to be considered customers with contracts of one year or system with the expectation that it will
a competing request. According to more—the right to continue to take continue to provide service to the
TranServ, this would prevent potential transmission service from the transmission customer should the
gaming by a customer submitting a transmission provider when the transmission customer exercise the right
request for one extra hour at 1 MW to customer’s contract expires. The pro of first refusal. If constraints arise after
gain priority over another reservation. forma OATT provides that the a transmission provider enters into a
transmission reservation priority is long-term agreement with the
Commission Determination independent of whether the existing transmission customer (and that
customer continues to purchase agreement does not contain an allowed
1212. In light of the potential for restriction on the transmission
market disruption and the scheduling capacity and energy from the
transmission provider or elects to customer’s right of first refusal), the
complications that would arise from obligation is on the transmission
purchase capacity from another
providing hourly firm service, we provider to either curtail service to all
supplier. This transmission reservation
decline to adopt in the Final Rule the priority for existing firm transmission affected customers or build more
proposal to require transmission service customers, which is also referred capacity to relieve the constraint.735 A
providers to offer hourly firm service. to as a right of first refusal or a rollover transmission provider is obligated to
While there is some industry support for right, is an ongoing right that currently curtail service pursuant to its OATT or
hourly firm service, we conclude that may be exercised at the end of all firm expand its system when its system
the downsides associated with requiring contract terms of one year or longer. A becomes constrained such that it cannot
transmission providers to offer hourly transmission customer must give notice satisfy existing transmission customers,
firm service outweigh the benefits of the of whether it will exercise its right of including the exercise of their rollover
proposal due to the significant issues first refusal 60 days before the rights, because it should have planned
raised by commenters. Commenters expiration of its service agreement. and operated its system with the
opposing mandatory hourly service 1215. In Order No. 888, the expectation that each long-term firm
raise a number of legitimate concerns Commission provided that, if a transmission customer will exercise its
with respect to the service’s potential to transmission customer subject to the rollover rights.736
adversely affect reliability and create rollover right selects a new power 1216. If a transmission provider’s
additional complexity and inefficiency supplier that substantially changes the transmission system cannot
in scheduling and administering the location or direction of its power flows, accommodate all of the requests for
right of first refusal. We do not believe the customer’s right to continue taking transmission service at the end of the
that the modifications suggested by service from the transmission provider contract term, the existing long-term
commenters supporting the service may be affected by transmission transmission customer must agree to
adequately resolve these concerns. constraints associated with the match the rate offered by the potential
change.732 The Commission also customer, up to the transmission
Given regional differences and varying
provided that a transmission provider provider’s maximum rate, and to accept
system constraints, a solution that may
may reserve existing capacity for retail a contract term at least as long as that
be appropriate for resolving scheduling,
native load and network load growth offered by the potential customer.
reservation or other issues resulting reasonably forecasted within the However, a competitor’s offer does not
from hourly firm service on one transmission provider’s current have to be ‘‘substantially similar in all
transmission system may not be planning horizon, but that any capacity respects’’ to the existing transmission
appropriate for another transmission so reserved must be posted on the customer’s.737
system. Moreover, even the commenters transmission provider’s OASIS and
supporting the proposal do not NOPR Proposal
made available to others until the
demonstrate a clear need for an hourly capacity is needed for the anticipated 1217. In the NOPR, the Commission
firm service product. The Commission network or retail native load use.733 The proposed to revise the right of first
therefore concludes that requiring Commission also has held that a refusal provision in the pro forma
hourly firm service is not needed to transmission provider may restrict a OATT to apply to firm wholesale
address undue discrimination, the goal right of first refusal based on pre- requirements and transmission-only
of this rulemaking. existing contracts that commence in the contracts that have a minimum term of
1213. To the extent they deem it future if the transmission provider five years, rather than the current
appropriate, transmission providers will knows at the time of the execution of minimum term of one year. In addition,
continue to have the option to propose the original service agreement that ATC a transmission customer under a
offering hourly firm service in an FPA used to serve a customer will be rollover agreement would be required to
section 205 filing with the Commission. available for only a particular time provide notice of whether it intended to
Because we are not adopting the period, after which time it is already exercise its right of first refusal no less
mandatory hourly firm service proposal, committed to another transmission than one year prior to the expiration of
we believe that the most serious customer under a previously confirmed its contract, rather than the current 60
concerns regarding scheduling short- transmission request.734 Once a days. The Commission proposed to
transmission provider evaluates the maintain the requirement that an
sroberts on PROD1PC70 with RULES

term service and administering the right


of first refusal are alleviated. We address 732 Order No. 888 at 31,665 n.176. 735 Id. at P 9.
scheduling and right of first refusal 733 Id.at 31,694. 736 Id.
issues relating to existing services in 734 E.g., Southwest Power Pool, Inc., 109 FERC ¶ 737 Idaho Power Co. v. FERC, 312 F.3d 454, 462

section V.D.5.b. 61,041 at P 6 (2004). (D.C. Cir. 2002).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00157 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12422 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

existing transmission customer match resources to accommodate a service permitted to the five-year minimum
competing offers as to term and rate. guaranteed for only one year, and Xcel term and matching exposure for small
The Commission discussed whether and TVA note that the increase in term embedded transmission-dependent
native load restrictions should be should encourage investment and utilities and full or near-full
reevaluated with each rollover and, if expansion of the grid by providing requirements customers to ensure a
so, whether native load should then be improved certainty of cost recovery. EEI continued right to service. Additionally,
required to compete with rollover stresses that there is no single minimum TAPS asserts that the minimum rollover
customers for the capacity. The rollover term that works for all parties, in the absence of a competing request
Commission also asked for comment on as power purchase contract terms vary should be one year, rather than five.
whether there is a sufficiently clear, and some state planning obligations 1222. TDU Systems, which generally
consistent, and transparent method that require purchases for longer or fewer opposes the increase to five years,
could be implemented on a generic than five years, but that five years believes that the Commission should
basis to address the need for a represents a reasonable balance. clarify that rollover customers retain
transmission provider to demonstrate its Southern emphasizes that the reforms their rights to transmission capacity in
forecast of native load growth and its should also improve reliability, promote the event of competing bids from either
effect on capacity reserved by rollover the provision of service to native load the transmission provider or another
customers. The rollover reforms were transmission customers, and increase transmission customer if the rollover
proposed to be effective as to new market efficiencies by releasing customer matches up to a five-year
transmission contracts upon transmission capacity to the market. In contract term. Lastly, Seattle is
Commission acceptance of the its reply, Southern expresses its belief concerned that with a five-year
transmission provider’s coordinated and that the current policy of requiring minimum, the risk in multi-segmented
regional planning process required by transmission planners to assume that all transmission transactions of one
the Final Rule, with existing rollover agreements having a minimum term of segment being undone by refusal of
contracts becoming subject to the new one year will continue taking service in another is increased. Seattle suggests
rules on the first rollover date after the perpetuity threatens reliability. In that acceptance and confirmation of one
effective date of the revisions. Southern’s view, this policy results in segment be made contingent on
planning that is based on speculation coordinated acceptance and
a. Five-Year Minimum Contract Term and guesswork that can signal a need for confirmation on all other required
Comments inappropriate and expensive segments.
transmission upgrades and mask the 1223. In its reply to the arguments
1218. Many commenters support the that rollover rights should be extended
increase in the contract term eligible for need for appropriate expansion.
1220. However, several modifications to accommodate service at new receipt
a rollover right.738 These commenters or delivery points, EEI argues that this
and clarifications were sought by some
support the increase to five years based would allow a rollover customer to have
commenters before they could agree to
largely on the Commission’s rationale priority over higher-queued customers
an increase in the minimum term to five
for proposing it, i.e., an increase to five on transmission paths other than the
years. APPA, Sacramento, and TAPS
years would encourage longer-term use path over which the rollover customer
contend that transmission customers
of the grid and assist in long-term is currently taking service, even if the
making this long-term commitment
planning. Many also point out that a new service would have different
should be permitted to change their
longer minimum term reduces the impacts on the transmission system. EEI
designated resources and receipt points
universe of contracts transmission argues that such service would be new
as their power supply needs change.739
providers must assume will exist in service and not a rollover of existing
APPA also asserts that transmission
perpetuity, thereby increasing certainty service. EEI also urges the Commission
customers that agree to a five-year
and reducing speculation. These to reject TAPS’s assertion that it should
contract term should not be forced to
commenters also argue that rollover require the transmission provider to
compete with other transmission
reform will improve reliability and accept rollover customers’ designations
customers for firm capacity whenever
provide increased revenues to perform of any network resources that are
their contracts come up for renewal.
upgrades. Some also argue that this is reasonably foreseeable and to redispatch
Without such assurances of continued
consistent with the native load its system if necessary to accommodate
service, APPA argues that the
protections in new section 217 of the that resource, because among other
Commission’s proposals would not
FPA. things this would require providers to
comport with section 217 of the FPA.740
1219. E.ON, for example, notes that build the transmission system with
1221. In order to further ensure
system expansions may have been sufficient redundancy to permit any
continued service, TAPS seeks the
limited in the past because transmission customer to take service from any
following modifications: Transmission
providers did not want to commit resource. Moreover, EEI argues that
providers should be required to
redispatch if necessary to accept a TAPS does not provide any suggestion
738 E.g., APPA, Barrick Reply, Bonneville,
as to what should be considered a
Community Power Alliance, Constellation, ‘‘reasonably foreseeable’’ and timely
reasonably foreseeable resource and that
Dominion, Duke, EEI, Entegra, Entergy, E.ON, designated network resource with costs
FirstEnergy, Great Northern, Imperial, Indianapolis sharing costs on a load ratio basis would
shared on a load ratio basis;
Power Reply, LPPC, LDWP, MidAmerican, MISO, result in eighty to ninety percent of the
transmission providers should be
MISO Transmission Owners, Nevada Commission, redispatch costs being borne by the
Nevada Companies, North Carolina Commission required to offer cost-based sales to
transmission provider’s native load
Reply, Northwest IOUs, NorthWestern, NPPD, PGP, embedded transmission-dependent
Pinnacle, PNM–TNMP, Progress Energy, Public customers.
utilities that cannot reach alternative 1224. EEI also argues in its reply that
Power Council, Sacramento, Salt River, Santa Clara,
suppliers; and exceptions should be
sroberts on PROD1PC70 with RULES

Seattle, South Carolina E&G, Southern, SPP, TAPS’s proposal to exempt all small
Tacoma, TAPS, TransServ, TVA, Utah Municipals, customers from the five-year minimum
739 Seealso TDU Systems Reply.
and Xcel. The Commission notes that several of
these commenters have conditioned or qualified 740 Seealso NCEMC and Arkansas Municipal
term would interfere with transmission
their support on the adoption of a number of (opposing the increase in the minimum term to five providers’ ability to plan their systems
modifications, which will be discussed below. years). to meet their customers’ needs, as the

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00158 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12423

aggregated loads of several small agreements to three years.744 AWEA and effective one-year power supply
customers can have a substantial impact PPM suggest that the Commission contracts be grandfathered because, in
on the system. EEI contends that TAPS’s increase the minimum term to three EEI’s view, it would interfere with good
proposal to exempt all full and near-full years, because five years is beyond the utility planning. EEI also argues that
requirements customers is also term for many shorter-term power sales extending the minimum term to five
unreasonable, as the transmission transactions and it would be cost years does not abrogate a customer’s
provider would be forced to provide prohibitive to lock up service for five power supply contract because
preferential service to certain groups of years. Manitoba Hydro suggests a two- transmission and supply are unbundled
customers. As for the proposal to allow to three-year minimum term and that and, therefore, changing the terms of
customers to exercise rollover rights guaranteed redirects be permitted. transmission service does not interfere
with only one-year contracts if there is Constellation, while generally with contract rights under power sales
no competing request, EEI contends supportive of a five-year minimum term, agreements.
there is no need for a rollover if there would prefer a three-year minimum 1229. Exelon argues that limiting
is no competing request, since there is term because it says three years is more rollover rights to contracts that are five
enough capacity for all and the closely aligned with much of the years or greater will discriminate against
transmission provider will grant the commercial activity in the energy merchant generators that do not have
customer’s new request for service for commodity markets. Wisconsin Electric load linked to generation, lead to
one year.741 supports the current one-year term, but stranded generation investments that
1225. The increase in the minimum proposes three years as an alternative. In were based on the current rules, and
contract term eligible for a rollover right its reply, Duke indicates that it would unfairly advantage local utilities
was opposed outright by several support a three-year minimum term for wanting to build their own generation as
commenters for a variety of reasons.742 rollover, but only if the notice period is opposed to seeking competitive
Many of these commenters oppose the required to match project lead time. alternatives. Exelon suggests that an
increase to five years because they claim 1227. In their replies, several approach similar to that utilized in PJM
it is difficult under current market commenters dispute the assertion that be adopted, in which PJM evaluates new
conditions to secure a five-year power customers may not be able to obtain requests for service that cannot be
supply agreement to underpin a five- generation supplies for five-year granted without utilizing an existing
year transmission contract, particularly periods. They contend that generators in customer’s service by notifying the
in organized markets where the focus is a competitive market will have to offer existing customer and requiring it to
on spot transactions or where the grid five-year contracts or risk losing their match the new request within thirty
is very weak.743 They also argue that sales if LSEs begin requesting five-year days or release the service. PJM explains
changes in the market (e.g., fuel costs) contract terms in order to obtain further that its approach would allow
could significantly change the options rollover rights.745 SPP states on reply transmission customers two rollover
available to customers within a five-year that it has not been its experience that options: long-term service for less than
period and that a service extension of suppliers have refused to enter into five years with no rollover right, or
less than five years may be needed to power supply agreements in excess of service for one year with indefinite
manage delays in generation three years. EEI also argues that, even if rollover rights conditioned on either
construction or some other a transmission customer has to accept future limitations or an agreement to
unforeseeable event. TDU Systems urge the risk that its term of service exceeds pay for necessary upgrades to maintain
the Commission to require any the term of its power purchase in order the rollover. In its reply, TAPS opposes
transmission provider seeking an to obtain rollover rights, the cost of the the PJM approach stating that it would
increase in the minimum contract term transmission service that is at risk is invite discrimination by transmission
to demonstrate that sufficient economic small in comparison to the cost of the owners.
power because the cost of transmission 1230. Other commenters that oppose
power supplies are available under
service is only a small portion of the the increase to five years assert that they
longer-term contracts. EEI replies that
delivered price of energy. EEI and are already long-term customers that
such an approach would be inconsistent
Bonneville also note in their replies that simply take service year-to-year and
with the separation of functions
unneeded transmission service can be should therefore already be included in
between generation and transmission.
sold in the secondary market. planning, based on the fact that they are
1226. Some commenters also argue 1228. NCEMC opposes the increase in either a generator or load and cannot
that five years is incompatible with contract term because it would inhibit simply pick up and leave the system.746
retail procurement processes in some the ability to pursue its prudent Several other commenters likewise
states, such as Illinois and New Jersey, portfolio approach to mitigate price oppose the increase to five years
which they assert limit power supply risks by providing for a mix of shorter because they do not believe that it will
and longer-term power supply contracts. result in an increase in long-term
741 In their replies, Entergy, MidAmerican, and

Progress Energy note many of these same concerns.


If the Commission increases the contracting and planning as suggested
742 E.g., Alberta Intervenors, Alcoa, Ameren, minimum term, NCEMC argues that all by the Commission.747 For example,
AMP-Ohio, Arkansas Municipal, AWEA, Dynegy existing rollover contracts should be Williams notes that it currently has a
Reply, Eastern North Carolina, EPSA, Exelon, grandfathered. EPSA also believes that ten-year transmission contract and
Fayetteville, Manitoba Hydro, Morgan Stanley, existing one-year contracts should be argues that its transmission provider has
NCEMC, NRECA, MISO/PJM States, PJM, Powerex,
PPM, Reliant, TDU Systems, TransAlta, Williams, grandfathered, otherwise it argues that done nothing to improve the grid in its
and Wisconsin Electric. market participants that relied on the area. TransAlta believes that a five-year
743 E.g., Alcoa, AMP-Ohio, Arkansas Municipal, current policy will be harmed. In its minimum contract term will limit
AWEA, Eastern North Carolina, EPSA, Exelon, reply, EEI urges the Commission to market participation to deep-pocketed
sroberts on PROD1PC70 with RULES

Fayetteville, Manitoba Hydro, NCEMC, NRECA,


MISO/PJM States, Reliant, TDU Systems, and
reject EPSA’s proposal that all currently market participants who can afford long
Wisconsin Electric. TAPS also notes the difficulties,
744 E.g., EPSA, Exelon, Reliant, and MISO/PJM 746 e.g., Morgan Stanley and Manitoba Hydro.
particularly for small transmission-dependent
utilities, of locking in a five-year supply contract a States. 747 e.g., Alberta Intervenors, TransAlta, and
year in advance of rollover. 745 E.g., EEI Reply and Southern Reply. Williams.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00159 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12424 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

contracts. TransAlta also believes that order to be eligible for a subsequent rights in the OATT to the varying
the current option to contract for just rollover. commercial practices across the
one year and obtain a rollover right is 1232. Our decision to adopt a five- country.
often the benefit that prompts market year minimum term will remedy many 1235. We also do not believe that
participants to buy yearly service of the problems associated with the adopting a five-year minimum term will
instead of shorter-term products and, current policy. Under our current have an adverse effect on participation
therefore, is an incentive to purchase policy, a customer can secure in retail auctions that use three-year
longer-term service. Alberta Intervenors transmission service for one year and, in solicitations. At the outset, we note that
believe that a longer minimum term will so doing, require the transmission retail auctions use solicitations of
provide a disincentive for long-term provider to plan and upgrade its system varying length and, hence, the fact that
trading since the increased time on the assumption the rollover right will some states may use three-year auctions
commitment of five years will be continually renewed. For example, if does not provide a basis to establish a
significantly increase the trading party’s a transmission provider’s planning generic standard for rollover rights
risk.748 The Organizations of MISO and horizon is 10 years, a one-year under the OATT. Some states use
PJM States believe that the current reservation would require the shorter term auctions (e.g., one year)
rollover policy generally results in an transmission provider to plan and and, as indicated, we cannot reasonably
increase in investment in transmission upgrade the system as if the customer tailor an OATT rollover obligation to the
and is only detrimental if service is had purchased 10 years’ service (i.e., varying commercial practices across the
terminated and the capacity goes would exercise its rollover right every country. We also do not believe that our
unused. year during that 10-year period). policy will have an adverse effect on
Because of this, the customer receives a any such auctions. The winners in a
Commission Determination guarantee of service beyond what it has retail solicitation are determined anew
1231. The Commission finds that the contracted to pay for and the in each auction, based on the bids
current rollover policy is no longer just, transmission provider must plan for submitted in that auction. A prospective
reasonable, and not unduly service that may not actually be used. bidder therefore does not need a
discriminatory. The rights and 1233. By failing to link the customer’s ‘‘rollover right’’ to compete in an
obligations of a rollover customer rights and obligations with those of the auction. It only needs transmission
should bear a rational relationship to transmission provider, the current service over the term of the solicitation
the planning and construction policy can have several detrimental (e.g., three years). The fact that it may
obligations imposed on the transmission effects. For example, it requires the not have an automatic right to
provider by the rollover rights. We find, transmission provider to plan and transmission capacity in the next
for the reasons explained below, that the construct facilities that may not be auction simply places it on the same
current policy no longer meets this necessary to serve load. Given the footing as any other bidder.
standard and that a five-year term will difficulty of siting new transmission, it 1236. In response to those
ensure greater consistency between the is inappropriate to require transmission commenters who argue that
rights and obligations of customers and providers to use finite resources to transmission customers making this
the corresponding planning and finance and construct facilities that may long-term commitment must also be
construction obligations of transmission not be necessary. Additionally, the permitted to change their designated
providers. We also believe that an current policy harms OATT customers resources and receipt points as their
increase to a five-year term is consistent by allowing rollover customers to tie up power supply needs change, we believe
with the native load protections capacity that may be needed by other that such an approach is unworkable.
contained in new section 217 of the customers. This is because the current Allowing rollover customers to change
FPA, primarily because requiring policy allows a rollover customer to their designated resources and receipt
longer-term agreements ensures that the lock up existing capacity, regardless of points in this manner would
rollover right is used by transmission whether the rollover customer intends inappropriately result in rollover
customers with long-term obligations to to use that capacity. This reduces the customers having priority over other
purchase capacity.749 Accordingly, the availability of existing capacity for other transmission customers in the queue
Commission adopts a five-year customers and, in turn, reduces
that may have already requested service
minimum contract term in order for a competitive alternatives for customers.
over a given transmission path. This
1234. Some commenters have argued
customer to be eligible for a rollover could result in substantial disruptions
that the Commission should use a
right. At the end of its initial five-year to transmission service to higher-queued
shorter period, such as three years, that
contract term, a transmission customer customers requesting long-term service
is more aligned with auctions in retail
must, within the one-year notice period over these paths.750 Moreover,
access markets or existing commercial
(discussed more fully below), agree to transmission customers are not
practices. We disagree. The purpose of
another five-year contract term or match currently guaranteed the ability to turn
our reform of the rollover rights policy
any longer-term competing request in to other suppliers at other designated
is to ensure that the rights and
obligations of the customer are better resources and receipt points and,
748 See also Morgan Stanley.
aligned with the planning and therefore, we do not understand how
749 See EPAct 2005 sec. 1233(a) (to be codified at
construction obligations of the simply increasing the minimum
section 217(b)(4) of the FPA, 16 U.S.C. 824q), which
provides that ‘‘[t]he Commission shall exercise the transmission provider. It is not to link contract term to five years should
authority of the Commission under [the FPA] in a the term of the rollover right to any
manner that facilitates the planning and expansion 750 We agree with EEI that requiring transmission

of transmission facilities to meet the reasonable


particular commercial practice in any providers to ensure rollover customers the ability to
needs of load-serving entities to satisfy the service particular region. We do not believe that change their designated resources and receipt
sroberts on PROD1PC70 with RULES

obligations of the load-serving entities, and enables such a policy could be fairly points without disrupting service to other
load-serving entities to secure firm transmission implemented in any event. Commercial customers would, taken to its logical conclusion,
rights (or equivalent tradable or financial rights) on require transmission providers to construct the
a long term basis for long term power supply
practices vary between the regions and transmission system with sufficient redundancy to
arrangements made, or planned, to meet such change over time, and it would therefore permit any customer to take service from any
needs.’’ be impractical to tailor the rollover resource.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00160 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12425

necessarily result in allowing This also would detract from one of the Most support the increase based on the
transmission customers this increased primary goals of rollover reform, which argument that the current 60-day notice
flexibility. Likewise, we do not is to improve transmission planning and period makes it very difficult to plan the
understand why an increase in the encourage longer-term contracting. As system, because transmission providers
minimum contract term should result, discussed below, existing transmission often do not know until 60 days before
as argued by APPA, TAPS, and others, contracts will be permitted to roll over the end of a contract whether a
in a transmission customer not having under their existing terms until the first transmission customer will roll over its
to compete with other transmission such rollover opportunity following the service, resulting in potential
customers for firm capacity whenever effectiveness of the reforms required by overbuilding of the system (e.g., because
its contract comes up for renewal. As this Final Rule. a transmission provider must plan its
discussed below, we will continue to 1239. Lastly, we note that many of the system assuming a transmission
require transmission customers to match reforms adopted elsewhere in this Final customer will roll over but sometimes it
competing requests for service as to Rule will be beneficial to customers that does not). They also argue that it is
term and rate, ensuring that no longer receive rollover rights, as well difficult to re-market capacity in only 60
transmission customers that value the as to customers with rollover rights that days if rollover is not sought and that
service the most receive it. wish to use their rollover rights to turn potential transmission customers are
1237. We reject TAPS’ proposal to to alternative suppliers using different often unnecessarily turned away
exempt all small customers from the transmission paths. First, greater because transmission providers are
five-year minimum, since this would consistency and transparency in ATC unaware of the availability of capacity
interfere with transmission providers’ calculations will provide greater until 60 days before the end of a
ability to plan their systems to meet assurance of nondiscriminatory access contract subject to a rollover right. In
their customers’ needs. As EEI points to existing transmission capacity. general, these commenters view a one-
out, the aggregated loads of several Second, our reforms relating to year notice period as an improvement.
small customers can have a substantial conditional firm and redispatch service However, many of these same
impact on the system. We therefore will help to maximize the use of commenters do not believe one-year
believe it would be inappropriate to existing capacity, consistent with notice is appropriate if the transmission
categorically exempt small customers. reliability, thereby providing customers provider must construct facilities to
We also reject TAPS’ proposal to without rollover rights greater flexibility accommodate a rollover and, therefore,
exempt all full and near-full to purchase existing transmission the notice should instead be tied to the
requirements customers, because it capacity. Third, our clarifications start date for any necessary upgrades.752
would force transmission providers to regarding our policy on redirects should 1241. EEI, for example, believes that
provide preferential service to certain improve the ability of transmission notice should be tied to the start date of
groups of customers. Additionally, we customers to redirect their service to any necessary transmission upgrades,
reject TAPS’ proposal to allow new receipt or delivery points. Fourth, because the transmission provider may
customers to exercise rollover rights lifting the price cap on reassigned be left with stranded transmission
with only one-year contracts if there is transmission capacity should assist capacity if it must begin construction on
no competing request. Without a transmission customers in reassigning upgrades necessary to accommodate a
competing request, a rollover right is not any capacity that may not be needed on rollover before the transmission
necessary in order to continue service as a given path because of a change in customer has even indicated whether it
long as capacity remains available. suppliers that requires service over new will in fact seek a rollover. EEI also
Additionally, allowing a rollover for a transmission paths. This will also argues that a competing customer could
one-year contract would continue to necessarily result in the unneeded be required to pay an incremental rate
impose planning and construction capacity being freed up for use by other for network upgrades that could have
obligations on the transmission provider transmission customers, thereby further been avoided if the rollover customer
that bear no reasonable relation to the assisting them in obtaining capacity that had provided earlier notice of its
rights and obligations of the rollover they need to access alternative intention not to seek a rollover. EEI
rights customer. We further reject TDU suppliers. Lastly, and most importantly, further contends that some state
Systems’ proposal that transmission greater openness and coordination in commissions will not allow upgrades
providers demonstrate the availability of transmission planning should provide where there is only the potential for a
long-term supplies before moving to a all customers better information rollover. Finally, EEI states that a one-
five-year term. To do so would regarding future resource options and year notice period does not ensure that
effectively require transmission access to competitive alternatives. We the transmission provider will be able to
providers to engage in the business of also believe that improved transmission re-market the capacity, forcing other
procuring supplies for their planning should help to address
transmission customers, which is allegations made by certain E.ON, Entegra, Entergy, FirstEnergy, Great
clearly outside the scope of their transmission customers (e.g., Williams) Northern, Imperial, LDWP, LPPC, MidAmerican,
obligation to provide transmission MISO, MISO Transmission Owners, Nevada
that even though they have signed up Commission, Nevada Companies, North Carolina
service, and could implicate Standards for ten years of service, they have not Commission Reply, NorthWestern, Northwest IOUs,
of Conduct issues. seen their needs planned for adequately. NRECA, PGP, Pinnacle, PNM–TNMP, Progress
1238. We also reject the proposal of Energy, Public Power Council, Salt River, Santa
EPSA and others that all currently b. One-Year Notice Provision Clara, Southern, South Carolina E&G, SPP, Tacoma,
TranServ, TVA, Utah Municipals, and Xcel. Both
effective one-year power supply Comments APPA and TAPS support a one-year notice
contracts be grandfathered because this provision, but only on the condition that the
1240. Many commenters support an
would disrupt transmission planning. clarifications and modifications they suggest are
increase in the notice period to one year
sroberts on PROD1PC70 with RULES

For example, such an approach would made.


or some other greater time period.751 752 E.g., Barrick Reply, Duke, EEI, Entergy,
require that a large portion of existing
Indianapolis Power Reply, LPPC, Nevada
capacity be planned for on a 751 E.g., Ameren, Barrick Reply, Bonneville, Commission, Nevada Companies, Pinnacle,
significantly different timeline than that Community Power Alliance, Constellation, Progress Energy, South Carolina E&G Reply,
subject to the reformed rollover right. Dominion, Duke, East Texas Cooperatives, EEI, Southern, and TVA.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00161 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12426 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

transmission customers to bear the times. They argue, among other things, capacity. This 60-day period was
increased costs associated with the that LSE transmission customers need a reasonable for a rollover right of short
newly constructed transmission reasonable amount of certainty so that duration (one year), but it is no longer
facilities. EEI proposes that a date be they may plan their power supply reasonable for a rollover right with a
included in the initial service agreement arrangements without fear that they may minimum five-year term.
by which the transmission customer become unraveled due to unforeseeable 1246. In selecting a new notice
must exercise its rollover rights if circumstances. Utah Municipals also period, the Commission has attempted
upgrades are needed to accommodate assert that the proffered justification for to balance the circumstances faced by
the rollover. If there is a pre-confirmed the proposal—to prevent overbuilding— customers in renewing power supply
competing request or newly projected is questionable at best as even the contracts and the interests of
growth in native load, EEI suggests that current policy which requires only a transmission providers in attempting to
the rollover customer must exercise its one-year contract minimum for rollover plan their system. The Commission
rollover and match by the later of the and 60-days notice has not resulted in recognizes that no single notice period
project start date for any new wasteful overbuilding of the system. can perfectly balance these
transmission facilities needed or 60 TDU Systems also point out that under considerations, but chooses the one-year
days after the transmission provider section 28.2 of the pro forma OATT, notice period as most appropriate under
notifies the transmission customer of transmission providers should be the circumstances. Given that the
the competing request.753 Additionally, planning and expanding their systems minimum rollover term has been
if more than one-year notice is required to accommodate their network lengthened to five years, it is reasonable
because of the need for upgrades, EEI customers’ current and future needs. to expect that customers will consider
proposes that the transmission provider 1244. The one-year notice provision is renewing such long term obligations in
be required to notify the transmission opposed by several commenters, who advance of 60 days prior to the
customer if subsequent events delay the argue that having to give one-year notice expiration of their current obligation.
project start date, in which case the constitutes an undue burden.754 In We do not believe it is reasonable to
notice period would be revised. EEI general, these commenters argue that fashion our notice period for customers
asserts that any disputes can be dealt under current market conditions, that wait until the last minute to
with by protesting the filing of an transmission customers do not typically evaluate whether to extend their long-
unexecuted agreement. EEI stresses that renew supply contracts one year in term contracts.
better, more inclusive planning, and advance of expiration.755 Alberta 1247. Many transmission providers
more transparent ATC calculations, will Intervenors argue that a one-year notice argue that a one-year notice period is
provide transmission customers with provision does not aid in re-marketing too short because it is not consistent
greater assurances that project start capacity, as any unused long-term firm with the transmission provider’s
dates are accurate. service is already re-marketed as short- planning horizon. We disagree. The
1242. Southern suggests that partial term firm or non-firm service. Alberta Commission is extending the minimum
rollover be permitted if notice is not Intervenors also argue that the increased term for rollover rights to five years to
given in time for construction of an lead time increases risk and creates ensure greater consistency between the
upgrade needed to provide full service. uncertainty making it less likely that customer’s rights and obligations and
Duke, Nevada Commission, and customers will enter into long-term the planning and construction
Southern suggest that providing for one- contracts. EPSA and Exelon suggest a obligations of the transmission provider.
year notice without a link to the start flexible notice rule that depends on the We believe that this modification
date for any upgrades falls short of the length of the underlying contract or satisfies the principal concerns of
native load protections found in section requiring more than 60-days notice if transmission providers regarding the
217 of the FPA. As an alternative, the there is insufficient capacity for a new current policy on rollover rights. We
Nevada Commission suggests tying the long-term firm transmission service recognize that a one-year notice period
notice requirement to the amount of request, as is done in PJM. They also is shorter than the typical planning
capacity subject to rollover, i.e., below suggest PJM’s approach whereby a horizon, but we decline to extend the
a certain threshold, one year would be transmission customer must inform PJM
notice period to a time that coincides
deemed per se sufficient. whether it will roll over within thirty
with the typical planning horizon or the
1243. APPA argues in reply that many days of being notified of a competing
customers may not know even one year time it takes to construct new facilities.
request. PPM and Wisconsin Electric
in advance if they will have firm power Doing so would effectively eliminate
suggest a six-month notice period,
supplies under contract that would rollover rights altogether, given that the
which complements their alternative
enable them to roll over their resulting notice period could be three-
suggestion of a three-year minimum
corresponding firm transmission to-five years. We do not believe it is
contract term.
agreement and, therefore, requiring reasonable to expect customers to have
them to exercise their rollover rights Commission Determination decided on new sources of supply three
even earlier in the contract term would 1245. The Commission finds that the years in advance of the expiration of
only exacerbate an already impossible current 60-day notice period should be their current contracts. We therefore
situation. In their replies, NRECA, modified to reflect the longer term (five find that a one-year notice period most
TAPS, TDU Systems, and Utah years) of the rollover rights. Currently, appropriately balances the interests of
Municipals urge the Commission to a customer with a one-year rollover customers and transmission providers.
reject the recommendation that notice right has 60 days to provide notice of c. Matching and Rollover Restrictions
periods be expanded to be whether it intends to rollover its Based On Native and Network Load
commensurate with construction lead Growth
sroberts on PROD1PC70 with RULES

754 E.g., Alberta Intervenors, Alcoa, Arkansas

753 Ameren, Pinnacle, Southern, and TranServ Municipal, EPSA, Exelon, Manitoba Hydro, Morgan Comments
agree that the submission of a competing request Stanley, PPM, TransAlta, Williams, and Wisconsin
should trigger an accelerated timeline for the Electric. 1248. As noted above, the
original customer to exercise or release its rollover 755 E.g., Arkansas Municipal, Williams, and Commission proposed to maintain the
rights. Wisconsin Electric. requirement that an existing rollover

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00162 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12427

transmission customer match competing right to recall capacity based on revised compute the Existing Transmission
offers as to term and rate. Some forecasts of native load growth. Capacity component of ATC to develop
commenters argue that a competing 1250. APPA contends on reply that native load growth reservations that
customer be required to execute a transmission customers could find it support rollover restrictions. AWEA,
contingent service agreement that very difficult to line up a new firm NorthWestern, and TAPS suggest
becomes effective if the rollover power supply of a term long enough to posting forecast information on the
customer does not match.756 Given the match the power supply arrangements OASIS, and TAPS goes on to stress that
increase in the minimum contract term of its vertically-integrated investor- this information should be included in
to five years in order to be eligible for owned transmission provider (which is state planning documents as well as the
a rollover right, TAPS argues that likely to have owned, rate-based transmission provider’s coordinated and
matching must be structured to generation in its power supply portfolio regional planning process. EPSA
recognize that a network customer must and, therefore, could agree to a very stresses that native load capacity must
extend its power supply by at lease five long-term transmission agreement). TDU follow native load and not only be made
years as well, in order to match a Systems argue that transmission available for the transmission provider
competing point-to-point customer that providers should be forced to compete and its affiliates. EPSA believes this is
can simply extend its reservation. To for capacity and that this is, in fact, required by the native load protections
ensure that network customers are not required by section 217 of the FPA, as found in FPA section 217.
disadvantaged by matching, TAPS the native load preference does not 1252. Duke asks the Commission to
suggests that the Commission restrict distinguish between the retail native address the possibility that capacity
reservations qualified to compete loads of transmission providers and the subject to a rollover right might be
native loads of other LSEs dependent on needed to serve native load outside of
against a network customer’s reservation
their systems. Powerex and PPM also the ten-year planning horizon. The
to customers with long-term power
support requiring transmission Nevada Commission and Southern
contracts, so they are on more equal
providers to compete. NorthWestern suggest that the Commission give
footing with network customers. TAPS
and Southern support requiring deference to state resource planning
also proposes a cut-off for requests with processes in attempting to verify native
which the network customer will need transmission providers to compete, but
only when a restriction is not included load growth forecasts. Southern also
to compete, such as three months prior asks that the Commission clarify that
to when the network customer exercises in the original agreement. APPA also
notes in its reply comments that, if rollover rights can be restricted based on
its rollover right, so that the network rollover rights belonging to higher-
customer can structure its power supply Southern included LSEs’ loads in its
transmission planning and construction queued transmission customers. If
commitments with some degree of transmission studies show no problems
advance knowledge of the competing program along with its own native load,
there would be no need to reclaim the without the presence of a rollover, but
requests. In its reply, Bonneville then problems are identified with the
suggests allowing network transmission LSEs’ capacity at the close of the initial
contract term or the renewal terms. rollover included, Southern contends
customers to compete based on the that placing a corresponding limitation
duration of their network transmission 1251. Several commenters also
addressed the Commission’s request for in the service agreement would be
service request rather than on the appropriate. Pinnacle requests
duration of their resource commitments. comment on whether there is a
sufficiently clear, consistent, and clarification that when rollover rights
As such, the transmission provider are restricted based on native load
would assume that existing designated transparent method that could be
implemented on a generic basis to growth, the transmission customer must
resources would continue to be used pay for upgrades to continue its service.
after the rollover unless informed address the need for a transmission
1253. Several commenters also
otherwise. provider to demonstrate its forecast of
suggest that transmission providers
native load growth and its effect on
1249. The Commission also discussed should be permitted to evaluate rollover
capacity reserved by rollover customers.
in the NOPR whether native load restrictions at the time of each
Many of these commenters support the
restrictions should be reevaluated with rollover.760 These commenters argue
development of a clear and transparent
each rollover and, if so, whether native that it is impossible to identify all
method for demonstrating native load
load should then be required to compete potential limitations upfront as system
growth.758 Some commenters point to
with rollover customers for the capacity. conditions change in unforeseeable
the need for accurate and transparent
Several commenters argue that a ways (e.g., fluctuations in fuel prices
ATC calculations to aid in this
transmission provider’s native and can change dispatch decisions). They
process.759 If the transmission
network loads should not be forced to also argue that allowing a re-evaluation
provider’s calculation of ATC is
compete with other transmission is consistent with the native load
consistent with the requirements the
customers, as opposed to allowing the protections in FPA section 217.
Commission adopts in this proceeding 1254. In its reply, TAPS argues that a
transmission provider to continue to yet there is insufficient capacity to
reserve capacity for its native and transmission provider should not be
accommodate the customer’s rollover, permitted to avoid its planning and
network load at the time of granting a EEI recommends that the provider may
rollover.757 Most also stress that expansion obligations by treating load
include in the service agreement a growth not anticipated and documented
requiring a transmission provider to limitation of rollover rights. AWEA
compete would violate the native load in the original service agreement as a
recommends that transmission competing request to be matched. TAPS
protections in section 217 of the FPA. providers adopt the same transparent
LDWP contends that there should be no points out that section 217 of the FPA
and consistent methods used to treats all LSEs—whether they are
limitation on a transmission provider’s
sroberts on PROD1PC70 with RULES

758 E.g., AWEA, Duke, EEI, Entergy, EPSA,


transmission providers or transmission-
756 E.g., MidAmerican and Powerex. Imperial, Nevada Commission, Powerex, Salt River, dependent utilities—the same, without
757 E.g., Allegheny, Entergy, FirstEnergy, Seattle, South Carolina E&G, Southern, SPP Reply,
Imperial, Nevada Companies, Progress Energy, Salt and TAPS. 760 E.g., Nevada Companies, South Carolina E&G,

River, Santa Clara, and Seattle. 759 E.g., AWEA, EEI, EPSA, and MISO. and Southern.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00163 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12428 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

distinction, and therefore provides no restrictions to be included in the initial Organization of MISO and PJM States
basis to allow one LSE to claim transmission service agreement, we assert that any changes for RTOs should
transmission rights currently used by necessarily reject the suggestion that be made through the stakeholder
another LSE.761 Lastly, TAPS argues transmission providers be permitted to process. In its reply, Williams opposes
that when a provider is reclaiming restudy for rollover restrictions at the permitting RTO stakeholders to
capacity for load growth reserved in the time of each rollover. Accordingly, it is determine changes in rollover rights
initial service agreement, rollover unnecessary for us to address whether it policy in RTO regions, as it would result
customers should be allowed to match would be appropriate for a transmission in disparate rules and practices and
the request, thereby imposing an provider’s native or network load to increased opportunities for
additional requirement on the provider. compete with a rollover customer if a discrimination, and therefore, the
new study at the time of the rollover Commission should adopt a single
Commission Determination
indicated a native or network need for policy applicable to all rollover rights.
1255. The Commission will not adopt the capacity. 1259. Other commenters raise
any changes to its matching policies at 1257. In response to the suggestions of different discrete issues. Morgan Stanley
this time. At the time of rollover of their some commenters, we believe that asks the Commission to amend pro
contracts, transmission customers will consideration should be given in our forma OATT section 2.2 to include
continue to be required to match case-by-case evaluations of native load existing policy determinations with
competing requests for service as to growth forecasts to state-approved respect to the manner in which a
term and rate in order to roll over their integrated resource plans that show a transmission provider can curtail or,
service. This preserves the current native load need for the capacity.765 alternatively, must honor and
policy goal of providing a mechanism Moreover, we believe that the ATC and accommodate rollover requests. Duke
for awarding capacity to those who planning reforms that we are adopting asks the Commission to abandon its
value it most, as well as providing for in this Final Rule will provide greater existing policy prohibiting the
a tie-breaking mechanism when needed transparency and assurance that restriction of rollover rights based on
that gives priority to existing customers transmission providers’ forecasts of the potential exercise of other
so that they may continue to receive native load growth are accurate. We customers’ rollover rights. Salt River
transmission service.762 Absent the emphasize that we expect the forecasts asks the Commission to clarify that the
requirement that the customer match utilized in transmission planning to be proposal to extend the minimum term to
the contract term of a competing consistent with the forecasts utilized to five years does not change the definition
request, transmission providers could be support a rollover restriction. Lastly, the in section 1.20 of the pro forma OATT
forced to enter into shorter-term coordinated and regional planning that one year constitutes a long-term
arrangements that could be detrimental process required by this Final Rule is contract. AWEA, Constellation, and
from both an operational standpoint designed to improve the availability of EPSA ask the Commission to allow
(i.e., system planning) and a financial transmission service by, among other transmission customers to waive their
standpoint.763 We clarify, however, that things, increasing transparency and rollover rights.
transmission customers must also enter providing customers a meaningful
into a transmission contract of at least Commission Determination
opportunity to participate in the
five years in order to obtain a planning process. Accordingly, we 1260. As we explain in section IV.C
subsequent rollover right in the absence believe that improved planning should above, RTOs and ISOs must submit a
of a competing request for a longer term. help to reduce the need to restrict filing showing that their practices are
1256. The Commission will continue rollovers in the future. consistent with or superior to the
to require rollover restrictions based on modifications made in the Final Rule.
reasonable forecasts of native load d. Other Issues This does not necessarily mean that
growth or preexisting contracts that Comments entities such as CAISO must create
commence in the future to be included 1258. A number of comments relate to rollover rights if they do not have them
in the initial transmission service the applicability of the rollover-related already. Arguments regarding the
agreement. This will remain the only reforms to RTOs and ISOs. CAISO asks applicability of rollover reform may be
appropriate way to restrict a rollover the Commission to confirm that the raised pursuant to the process described
right. We also will continue to evaluate rollover reforms do not apply to CAISO in section IV.C. We also clarify that our
a transmission provider’s native load as its current tariff does not have such decision to extend the minimum term to
growth forecasts on a case-by-case basis, a provision and rollover is, in fact, five years does not change the definition
as no commenter has provided us with incompatible with CAISO’s in section 1.20 of the pro forma OATT
a sufficiently clear, consistent, and transmission service model. that one year constitutes a long-term
transparent method that could be Sacramento, however, asks the contract. Commenters have not offered
implemented on a generic basis that Commission to clarify that rollover sufficient justification for further
ensures that the demonstration of native rights apply to long-term firm service clarifications to our rollover policies or
load growth is accurate and is tied to a provided by RTOs and ISOs under amendments to section 2.2 at this time.
need for the specific capacity reserved Order No. 681 under what it terms the
by a rollover customer.764 Because we e. Effectiveness Upon Acceptance of
‘‘as good as or superior to’’ standard.766 Coordinated and Regional Planning
will continue to require rollover
Process and Transition
765 We note that this is consistent with the
761 See also APPA Reply and TDU Systems Reply. Commission’s evaluation of rollover restrictions Comments
762 See Order No. 888–A at 30,197. proposed by transmission providers in the past.
763 Id. See, e.g., Nevada Power Co., 97 FERC ¶ 61,324 at
1261. Several transmission customers
and other commenters support a linkage
sroberts on PROD1PC70 with RULES

764 While the Commission has not to date 62,493 n.17 (2001).
accepted any native load growth showing made by 766 In its reply, CAISO argues that this request to

a transmission provider, it has recently set for expand the requirements of Order No. 681 is like CAISO that do not offer traditional Order No.
hearing several such showings. See, e.g., Southern inappropriate both because the Commission and 888 network and point-to-point transmission
Co. Servs., Inc., 116 FERC ¶ 61,050 (2006); Nevada courts have already recognized that rollover rights services and because the Commission has already
Power Co., 116 FERC ¶ 61,093 (2006). under the pro forma OATT do not apply to entities rejected such a requirement in Order No. 681 itself.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00164 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12429

between rollover reform and planning, 1264. As for the transition period transmission provider’s coordinated and
but do not support making rollover proposed in the NOPR, a variety of regional planning process. We believe
reforms effective upon acceptance of a commenters point out that, depending that utilizing a subjective deadline, such
transmission provider’s coordinated and on the status of any given contract, as the successful implementation of the
regional planning process, but rather on making the one-year notice provision planning process, could result in
successful implementation of that effective on acceptance of a significant confusion in the industry as
process.767 While both TAPS and TDU transmission provider’s planning to when rollover reforms should be
Systems support the link to planning process could leave some transmission effective. Furthermore, an existing filed
generally, TAPS goes further and customers unable to provide one-year and accepted transmission planning
advocates holding transmission notice if there is less than one year process, such as those that may be on
providers accountable for failing to plan remaining on their contracts.770 file for RTOs and ISOs, does not trigger
and construct facilities needed to meet FirstEnergy, Exelon, Great Northern, the effectiveness of rollover reform for
transmission customer needs. TDU and TAPS emphasize that existing transmission providers using the
Systems point out that the linkage to transmission customers should be process. Such RTOs and ISOs and their
planning does not remedy concerns that permitted one more rollover under the transmission-owning members must, as
the current market does not generally current rules, because the parties to discussed elsewhere in this Final Rule,
provide for five-year supply contracts. such agreements have relied on the comply with the planning reforms
1262. Some commenters, however, current rules in meeting their required by the Final Rule through the
oppose linking the effectiveness of transmission needs. APPA and TAPS compliance filing procedures identified
rollover reform to planning, arguing that point out that transmission customers in section IV.C. It is Commission
rollover reform is needed as quickly as will need a sufficient amount of time to acceptance of these compliance filings
possible.768 For example, Duke, Progress secure five-year power agreements to that will trigger effectiveness of rollover
Energy, and Southern argue that FPA meet the new requirements. AWEA reform for these transmission providers,
section 217 provides no indication that argues generally for a transition period assuming rollover reform is applicable
the native and network load protections during which existing customers can to their tariff services in the first
inherent in rollover reform should be maintain or relinquish their existing instance.
rollover rights under current rules and 1267. In response to commenters’
subject to conditions such as waiting for
become subject to new requirements concerns that, depending on the
the Commission to accept a planning
only at the end of the transition period. effective date of rollover reform, certain
process. Moreover, Duke argues that
customers may not have a year or more
developing a planning process will be Commission Determination left on their contracts such that they can
time-consuming and that holding 1265. The Commission adopts the comply with the one-year notice
rollover reform hostage to it could NOPR proposal to make rollover reform provision, we emphasize that existing
motivate stakeholders with contracts effective at the time of acceptance by the contracts with a rollover right at the
shorter than five years to endlessly try Commission of a transmission time of effectiveness of rollover reform
to convince the Commission to delay provider’s coordinated and regional may exercise their next rollover based
acceptance of a transmission provider’s planning process also required by this on the existing notice rules. It is only a
planning process. Final Rule. We believe that rollover rollover contract entered into or
1263. Some commenters contend that reform and transmission planning are renewed after the effectiveness of
linking planning and rollover reform closely related, because according to our rollover reform that must comply with
will create differences in tariffs, with longstanding policy, transmission the new rollover provisions, including
each transmission provider having a service eligible for a rollover right must the one-year notice requirement.
different effective date for rollover be set aside for rollover customers and
reforms.769 MISO argues in its reply that 4. Modification of Receipt or Delivery
included in transmission planning. We
the Commission should clarify in the Points
believe that it is necessary that reforms
Final Rule that its requirement that the in both areas proceed together, and 1268. Section 22 of the pro forma
new policy becomes effective upon therefore, we reject the suggestion of OATT provides that a transmission
acceptance of the transmission some commenters that rollover reform customer taking firm point-to-point
provider’s coordinated and regional proceed independent of transmission service may modify its receipt and
planning process is already met in planning reform. We understand that delivery points, i.e., redirect its service,
regions where RTOs or ISOs provide our approach may result in differences on either a non-firm or a firm basis.
service, as they already have in transmission providers’ OATTs, with Section 22.1 (Modifications on a Non-
Commission-approved regional some having a different effective date Firm Basis) provides that, subject to
transmission planning mechanisms in for rollover reforms. However, because certain conditions, a firm point-to-point
place. Bonneville argues in its reply for the effectiveness of rollover reform will customer may request transmission
a consistent implementation date across be tied to acceptance of a transmission service on a non-firm basis over receipt
all transmission providers so as to avoid provider’s coordinated and regional and delivery points other than those
another degree of complexity for transmission planning process, rollover specified in its service agreement
customers requiring rollover capacity reforms in any given region generally (known as secondary receipt and
across multiple transmission providers’ should be effective within the same time delivery points) in amounts not to
systems. period. exceed its firm capacity reservation,
1266. We reject the arguments by without incurring an additional non-
767 E.g., AWEA, Constellation, EPSA, Exelon,
some commenters that rollover reform firm point-to-point service charge or
PGP, and PPM. be made effective upon the ‘‘successful’’ executing a new service agreement.
sroberts on PROD1PC70 with RULES

768 E.g., Bonneville, Duke, EEI Reply, North


implementation, as opposed to Section 22.2 (Modifications on a Firm
Carolina Commission Reply, Northwest IOUs, Basis) provides that any request to
PNM–TNMP Reply, Progress Energy, Public Power acceptance by the Commission, of a
Council, South Carolina E&G Reply, and Southern. modify receipt and delivery points on a
769 E.g., Northwest IOUs, Duke Reply and EEI 770 E.g., APPA, FirstEnergy, Northwest IOUs, PGP, firm basis shall be treated as a new
Reply. and Public Power Council. request for service in accordance with

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00165 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12430 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

section 17 of the pro forma OATT customers complained of difficulties a customer’s original path. The
(Procedures for Arranging Firm Point-to- obtaining redirected service, while Commission stated its belief that other
Point Transmission Service), except that transmission providers complained of a proposed reforms in the areas of
the transmission customer shall not be lack of clarity in the rules governing process, transmission planning, and
obligated to pay any additional deposit redirects. In the NOPR, the Commission ATC calculation should address
if the capacity reservation does not stated its belief that a number of these transmission customer concerns
exceed the amount reserved in the concerns appeared to have been regarding redirects. The Commission
existing service agreement. While such resolved by the adoption of the WEQ encouraged interested parties to submit
new request is pending, the Standards in Order No. 676, which was a specific proposal, along with proposed
transmission customer retains its issued after the NOI. The Commission revised pro forma OATT language, to
priority for service at the existing firm sought comment on whether parties the extent they believe the proposed
receipt and delivery points specified in believed the WEQ Standards in fact reforms will not adequately address
its service agreement. addressed those concerns adequately. their concerns.
1269. In Order No. 676, the 1271. The Commission also stated its 1273. The Commission also noted in
Commission adopted the ‘‘Standards for expectation that a number of other the NOPR that several transmission
Business Practices and Communication concerns raised in response to the NOI, providers had posted business practices
Protocols for Public Utilities’’ developed while perhaps not yet addressed (or that allow network customers either to
by the NAESB’s Wholesale Electric addressed fully) by a WEQ Standard, are substitute an off-system non-designated
Quadrant (WEQ).771 Order No. 676 nevertheless the types of issues that are resource for a designated resource or to
incorporated the aforementioned appropriate for the WEQ process. The redirect the point of receipt associated
standards by reference into the Commission therefore proposed that with an existing network resource. The
Commission’s regulations, required each commenter that continued to Commission proposed that network
public utilities to implement the believe additional reform is necessary customers not be permitted to redirect
standards by July 1, 2006, and required with regard to redirects evaluate network transmission service because
public utilities to file revisions to their whether its concerns would more network service involves no identified
OATTs to include these standards.772 appropriately be addressed by the WEQ contract path and therefore should not
The WEQ Standards include a number as it considers its next version of its be treated as a directable service.
of standards addressing requirements standards.776 The Commission noted a. Proposed Reliance on WEQ Process
for dealing with redirects on both a firm that WEQ was in the process of and Other OATT Reforms
and non-firm basis.773 All of the WEQ reevaluating WEQ Standard 001–9.7,
dealing with redirects and rollovers, so Comments
Standards dealing with redirects were
adopted by the Commission in Order that it is consistent with the 1274. Commenters generally agree
No. 676, except for WEQ Standard 001– Commission’s guidance given in Order with the Commission that issues with
9.7, which addresses the impact of a No. 676. The Commission requested respect to redirects of firm and non-firm
firm redirect on a long-term firm comment on whether the WEQ process, transmission service are best addressed
transmission customer’s rollover rights along with the guidance provided by the through the WEQ as established by
under section 2.2 of the pro forma Commission in Order No. 676, is NAESB, in accordance with Order No.
OATT. The Commission directed the sufficient to address the concerns of 676 and the WEQ process for creating
WEQ to reconsider WEQ Standard 001– commenters that seek clarification on new standards.777 Seattle argues that the
9.7 and to adopt a revised standard the interplay between redirects and NAESB standard setting process has
consistent with the Commission’s rollovers. worked well thus far and, as a result,
policies.774 The Commission also 1272. In the NOPR, the Commission other redirect issues should be first
offered guidance to assist the WEQ in acknowledged that there were referred to NAESB as a standard-setting
developing a standard that is consistent additional, more fundamental concerns request. MISO states that it has serious
with Commission policy.775 with regard to section 22 raised in concerns with the WEQ process and the
response to the NOI. Customers Commission’s unwarranted deference to
NOPR Proposal generally argued that their ability to NAESB to develop what will become
1270. In response to the NOI, redirect to new points is stymied by a binding business standards and
commenters raised various concerns lack of ATC at the new points or the practices.
regarding redirects. Among other things, need for major upgrades, or that 1275. Nevada Companies recommend
transmission providers take too long to the following improvements for the
771 The WEQ was established by NAESB in
process the redirect request. NAESB process: use of a professional
response to a Commission order requesting the Transmission providers, on the other facilitator to keep discussions focused
wholesale electric power industry to develop and moving; and mandatory surveys
business practice standards and communication hand, complained of the administrative
burdens and complexity (particularly breaking down the sections on proposed
protocols by establishing a single consensus,
industry-wide standards organization for the with regard to reliability) of processing NAESB standards after the first round of
wholesale electric industry. See Order No. 676 at transmission customers’ short-term comments are received to determine if
P 3–4.
changes in service and that there is consensus exists on the proposed
772 The standards will hereinafter be referred to
often not enough time for the market to standards, since it appears that there are
as the WEQ Standards. The Commission adds a
reference to the WEQ Standards in section 4 of the respond to capacity made available on relatively few participants at NAESB
pro forma OATT, which identifies the meetings where standards are being
Commission’s regulations containing the terms and 776 The Commission noted in this regard that the drafted and relatively few commenters
conditions relevant to the OASIS and standards of WEQ’s procedures ensure that all industry members on those draft standards.
conduct. can have input into the development of a business 1276. Several commenters state that
sroberts on PROD1PC70 with RULES

773 The requirements for dealing with redirects on


practice standard, whether or not they are members they agree with the Commission’s
a firm basis are found at WEQ Standard 001–9, et of NAESB, and each standard it adopts is supported
seq., and the requirements for dealing with redirects by a consensus of the five industry segments: proposal to rely on other proposed
on a non-firm basis are found at 001–10, et seq. transmission, generation, marketers/brokers,
774 Order No. 676 at P 52.
distribution/load-serving entities, and end-users. 777 E.g., EEI, Imperial, NorthWestern, Southern,
775 Id. at P 53–61. See Order No. 676 at P 5 & n.5. and Suez Energy NA.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00166 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12431

reforms in the NOPR to resolve the is an acceptable standards development the redirect, regardless of the duration
remaining redirect issues.778 Seattle process, representing a cooperative of the redirect. Contrary to the
generally agrees that the reforms effort by industry participants to comments of Bonneville, MISO, and
proposed in the NOPR should improve develop business practices that enhance Southern, the Commission did not
the ability to assign and use the efficiency of the electric grid.780 impose this requirement for the first
transmission on a firm basis. EEI and Where necessary, NAESB participants time in Order No. 676, but merely
NorthWestern state that the NOPR may seek clarification of Commission provided guidance to the industry by
proposal to increase transparency in the policy so that NAESB may develop the restating Commission policy on this
calculation of ATC should assist appropriate standards. matter. The Commission has explained
transmission customers in both b. Redirects and Rollovers Rights in prior orders that a transmission
selecting transmission paths that may be customer making a firm redirect request
available for redirect and understanding Comments
does not convert its original long-term
why certain paths cannot accommodate 1279. Regarding the interaction firm transmission service to short-term
redirect transactions. between redirects and rollovers, some service, nor does it lose its rollover
Commission Determination commenters request that the rights under its long-term firm
Commission clarify what they view as transmission service agreement. The
1277. The Commission concludes that an inconsistency between Order No.
the proposed method for addressing Commission’s concern underlying this
676, the Commission’s existing pro
remaining concerns with redirects—i.e., policy is that long-term customers
forma OATT, and the rollover proposal
relying on other reforms adopted in this should not need to choose between
in the NOPR. Specifically, Bonneville,
Final Rule and in the Order No. 676 redirecting on a firm basis and
MISO, and Southern argue that, contrary
proceeding—is adequate to ensure that to the pro forma OATT and NOPR, maintaining rollover rights, rather their
transmission providers do not engage in Order No. 676 improperly suggested in rollover rights should be retained
undue discrimination when a customer an example that a short-term redirect of consistent with the long-term nature of
seeks to modify its receipt and delivery a long-term service agreement gives the their service.
points on a firm basis. As explained customer rollover rights for the new 1281. In Commonwealth Edison Co.,
throughout this Final Rule, the reforms path. TranServ supports placing the the Commission explained that a
adopted herein address the remaining following two conditions on the receipt ‘‘request to change a delivery point on
opportunities for undue discrimination. of rollover rights for redirects: a redirect a firm basis for one month and then to
Planning and ATC reforms will give on a firm basis must be for one year or revert to its original delivery point does
transmission customers more accurate longer, and the redirect must be for the not convert its existing long-term firm
and complete ATC information when entire remaining term of the parent transmission service agreement into two
evaluating their redirect options. (original) request.781 If these conditions separate short-term transmission service
Increased transparency will give are met, TranServ contends that the agreements.’’ 782 The Commission stated
transmission customers the information customer will be granted rollover rights that section 22.2 was intended to
they need to evaluate a transmission on the redirect path and lose the provide flexibility to transmission
provider’s denial of a request to redirect. rollover rights held on the original path. customers to permit them to react in a
Modifications to the process for If the customer wishes to retain rollover competitive market and that some
requesting and securing firm point-to- rights on the original path, TranServ amount of this flexibility would be lost
point service will improve the ability to continues, it will have the option to if a long-term firm transmission
redirect transmission service to new submit multiple redirect requests of less customer seeking to modify its delivery
points pursuant to section 22 and than one year in duration for the term points would lose its rollover rights.783
ensure complete and timely responses desired. With respect to WEQ Standard
from transmission providers. The 001.9.7, MISO incorporates by reference 1282. The Commission affirmed this
Commission therefore concludes that no its opposition to the Commission’s policy in American Electric Power
further reforms specific to redirects are adoption of the proposed transfer of Service Corp.784 In that case, a long-term
necessary at this time. rollover rights on the redirected path in transmission customer (Exelon) had
1278. The Commission also concludes its request for rehearing of Order No. been granted a short-term redirect, but
that the NAESB WEQ is the appropriate 676. There MISO argued that there denied rollover rights on the redirected
standard-setting body for developing should be no rollover rights on a path. The Commission found the denial
business practices and implementing redirect path and that the guidance in of rollover rights was improper, since
the Commission’s redirect policy. The Order No. 676 requiring the the ‘‘redirect request made by Exelon
Commission will refrain from transmission provider ‘‘to offer rollover did not convert Exelon’s long-term firm
commenting here on the NAESB process rights to a customer requesting a firm transmission service to short-term
itself because we believe that the redirect if rollover rights are available service, and, therefore, did not affect
industry is best situated to determine on the redirect path’’ was inconsistent Exelon’s rollover rights under its long-
how to structure the standard-setting with the pro forma OATT. term firm transmission service
process to provide for the widest agreement.’’ 785 Thus, there is no
possible participation and consensus. Commission Determination
inconsistency between the
We nevertheless clarify that, consistent 1280. Commission policy allows a Commission’s redirect policy and Order
with precedent, NAESB is charged with redirect of firm, long-term service to No. 676.
implementing Commission policy retain rollover rights, even if the redirect
through business practices.779 The is requested for a shorter period. In 782 95 FERC ¶ 61,027 at 61,083 (2001).
Commission finds that the NAESB WEQ other words, the rollover right follows
sroberts on PROD1PC70 with RULES

783 The Commission, however, recognized that


this flexibility was not unlimited—any change to a
778 E.g.,EEI, NorthWestern, and Seattle. 780 See Order No. 676 at P 12. delivery point is treated as a new request for service
779 See Standards for Business Practices of 781 TranServ explains that these are two primary for purposes of the availability of capacity.
784 97 FERC ¶ 61,207 at 61,905–06 (2001).
Interstate Natural Gas Pipelines, Order No. 587–N, features in a revised WEQ 001–9.7 standard that
FERC Stats. & Regs. ¶ 31,125 at P 23 (2002). was open for public comment. 785 Id.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00167 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12432 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

c. Redirects as New Requests for Service customer access to system capacity or As a result, a uniform pricing method
Comments queue position different from other for redirects is beyond the scope of this
customers submitting new requests for proceeding. Nevertheless, we note that
1283. With respect to the provision in service. A redirect request must be the Commission explained in a recent
section 22.2 of the pro forma OATT evaluated in accordance with section 17 order that its policy does not allow
specifying that requests to redirect on a using the same system assumptions and transmission providers to collect
firm basis be considered new requests analysis applicable to any other new additional charges when a firm point-to-
for service, LPPC and NPPD ask that this request for service, including whether point customer redirects on a non-firm
provision be modified to ensure that a sufficient ATC exists to accommodate basis.786 The Commission concluded
customer redirecting its service will the request. The Commission concludes that it would not subject non-firm
retain a higher priority for service in the it would be inappropriate, and contrary redirects to the Appalachian Method of
transmission provider’s queue than new to the pro forma OATT, to grant pricing,787 which is premised on the
customers. LPPC argues that it is redirects special queue treatment. assumption that a customer using the
inequitable to require customers to 1286. Regarding Imperial’s request transmission system for the 16 peak
compete for capacity as though their that transmission providers be given hours of the day should pay the same
loads were incremental to the system additional time to determine whether contribution to fixed costs as a customer
when they are simply changing their native load growth will prevent rollover who has reserved capacity on a daily
receipt points as a matter of necessity rights for the redirects, we find that basis. This is because the redirecting
(since suppliers may commence serving redirects should be studied like any customer already would have paid for
other loads or cease doing business). EEI
other new request for firm point-to- firm service over all on-peak and off-
argues on reply that, if LPPC’s proposal
point service. Transmission providers peak hours during the reservation
would give customers priority at new
must examine whether any request, a period of its service, therefore, there is
points of receipt and delivery regardless
firm redirect request or a new service no need to ensure that the customer
of whether the redirected service creates
request, would be affected by future pays a premium for the opportunity to
system impacts different from the old
native load growth resulting in possible cherry pick the best hours each day.
service, the proposal would replace
rollover rights restrictions, so we see no Furthermore, because the Commission
‘‘first-come, first-served’’ priority with a
need to provide additional time for is not requiring the provision of hourly
system in which customers would never
transmission provider analysis of firm firm service, Southern’s argument
know for sure whether their own
redirect request. regarding redirected hourly firm service
requests for service would be displaced
is now moot.
by subsequent requests for redirected d. Pricing for Redirects
service. EEI cautions that the Comments e. Other Issues
transmission system simply cannot be Comments
planned and constructed with enough 1287. TranServ requests that the
spare capacity to allow any customer to Commission resolve a disagreement 1290. EEI agrees with the
redirect service to any point that it among WEQ participants regarding the Commission’s proposal to clarify that
chooses at any time. pricing of redirects as requests for new network customers may not redirect
1284. Bonneville similarly argues that service. TranServ asks whether the network transmission service. Alberta
a redirect request should meet the same failure to charge an incremental uplift Intervenors contend that undue
term and notice requirements as a new between the original and redirected rate discrimination remains because the
request given that the transmission (e.g., respectively, the monthly rate and flexibility to modify points of receipt
provider’s planning horizon and the daily on-peak rate) would constitute the and delivery that the network customer
amount of time needed to remarket offering of a discount for daily service enjoys through ‘‘parking’’ and
unused capacity is no different for a that in turn must be posted for all other ‘‘hubbing’’ is not likewise granted to a
redirect and a new transmission service paths to the same point of delivery. point-to-point customer. Alberta
request. APPA argues on reply that it is TranServ argues that it is reasonable to Intervenors recommends that the pro
unclear how Bonneville’s request would charge an incremental uplift such that forma OATT either make a common
affect load-serving transmission the rate paid by the redirect customer service available to all participants (not
customers that cannot obtain power would be on par with that paid by any just network customers) or prohibit
supply agreements of a term sufficient other transmission customer reserving network customers from using point-to-
to dovetail with the term requirements (daily) short-term firm service of like point services for parking and hubbing.
for a new request. Imperial recommends duration (i.e., a ‘‘new request for 1291. Imperial asks the Commission
that redirects be evaluated using ATC at service’’), and the customer would pay to clarify that a transmission customer
the time of the redirect request, like any the difference between the daily on- should not be able to make multiple
other new request for service, but that peak rate and 1/30th of the monthly redirects. Imperial explains that this
the transmission provider be given rate. clarification would address two
additional time to determine whether 1288. Southern argues that, with concerns: multiple short-term changes
native load growth will prevent rollover respect to the price for redirects, if raise reliability concerns and often there
rights for the redirects. redirected hourly firm service is more is insufficient time for the released
valuable than firm service, economic capacity to be used by another
Commission Determination theory would dictate that customers customer; and the burden on properly
1285. Section 22.2 of the pro forma should be required to pay for that added scheduling for reliability increases
OATT provides that redirects ‘‘shall be value. exponentially when there are redirects
treated as a new request for service in of redirects.
Commission Determination
sroberts on PROD1PC70 with RULES

accordance with section 17,’’ except that


the transmission customer may not be 1289. The Commission has not 786 Midwest Independent Transmission System
required to pay an additional deposit in established a single, industry-wide Operator, Inc., 118 FERC ¶ 61,095 at P 79–85(2007).
certain circumstances. Therefore, a pricing policy for redirects and did not 787 See Appalachian Power Co., 39 FERC ¶ 61,296

redirect right does not grant the propose a pricing policy in the NOPR. (1987).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00168 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12433

1292. MISO/PJM States argue that As long as the customer meets these processing system impact studies and
because RTOs are not likely to engage in requirements, the Commission believes facilities studies associated with
discrimination with respect to redirects, that the ability to redirect service does requests for transmission service. The
the Commission should not modify RTO not present an unreasonable burden to Commission proposed that transmission
redirect policies in the instant transmission providers. As for providers calculate the proposed
rulemaking proceeding. applicability to RTOs and ISOs, we performance metrics separately for
explain our compliance requirements in affiliates and non-affiliates and for
Commission Determination
section IV.C of this Final Rule. To the requests for short-term and long-term
1293. The Commission adopts the extent an RTO’s or ISO’s redirect policy transmission service.
NOPR proposal and finds that network does not conform to the pro forma 1299. In addition, the Commission
customers may not redirect network OATT, as amended by this Final Rule, proposed to require a notification filing
service in a manner comparable to the the RTO or ISO must demonstrate that and the posting of additional metrics if
way customers redirect point-to-point its policy is consistent with or superior a transmission provider completes more
service. Unlike point-to-point service, to the pro forma provisions in than 20 percent of non-affiliates’ studies
network service involves no identified accordance with the compliance outside of the 60-day due diligence
contract path and thus is not a procedures set forth in that section. deadline in the pro forma OATT for two
directable service. A network customer consecutive quarters. Starting the
seeking to substitute one resource for 5. Acquisition of Transmission Service
quarter after a notification filing, the
another already has the ability under the a. Processing of Service Requests transmission provider would be
pro forma OATT to terminate its required to post the following
1296. The pro forma OATT includes
existing designation and designate a information on OASIS: (1) The average,
requirements that transmission
new resource on an as-available basis. If across completed system impact studies,
providers process requests for
necessary, the network customer may of the employee-hours expended per
transmission service in a timely fashion.
then request to redesignate its original completed system impact study, (2) the
Section 17.5 (Response to a Completed
network resource by making a request to average, across completed facilities
Application) and section 18.4
designate a new network resource. studies, of employee-hours expended
(Determination of Available
Alternatively, the network customer per completed facilities study, (3) the
Transmission Capability) of the pro
could use secondary network service if number of employees devoted to
forma OATT provide that following the
it wants to substitute a non-designated processing system impact studies, and
network resource for a designated receipt of a completed application for
service, the transmission provider must (4) the number of employees devoted to
network resource on an as-available processing facilities studies. The
basis. respond to transmission customer
requests for determinations of the Commission proposed that transmission
1294. For similar reasons, the
availability of firm and non-firm providers post these additional
Commission denies Alberta Intervenors’
transmission capacity on a timely basis. performance metrics until they process
request. The Commission has explained
The transmission provider must make at least 90 percent of all system impact
that customers must choose between
the determination as soon as reasonably and facilities studies within 60 days
point-to-point and network services,
practicable after receipt but no later after the study agreement has been
each of which has its own advantages
than certain specified time periods (or executed. The additional performance
and risks.788 The Commission declined
such time periods generally accepted in metrics also would be calculated
to implement a single form of
transmission service in Order No. 888, the region). separately for affiliates’ and non-
concluding that point-to-point and 1297. Section 19 (Additional Study affiliates’ requests for transmission
network services are the appropriate Procedures for Firm Point-to-Point service and for short-term and long-term
base-line services under the pro forma Transmission Service Requests) of the transmission service.
OATT, and Alberta Intervenors offer no pro forma OATT provides deadlines Comments
justification for departing from that that transmission providers must adhere
to in issuing system impact study Standard Performance Metrics
approach now. Alberta Intervenors
parking and hubbing related arguments agreements and facilities studies 1300. Transmission customers and a
alleging that network service is agreements and that transmission number of other commenters generally
commonly used to purchase power customers must abide by in responding support or do not oppose the
intended for sales to third parties is to these study agreements. Section 19 Commission’s proposal to require
addressed in section V.D.7 of this Final requires transmission providers to use transmission providers to post
Rule. Although we deny Alberta due diligence to complete system performance metrics.789
Intervenors’ request, we expect that the impact studies and facilities studies 1301. Southern and Salt River oppose
reforms adopted in this Final Rule will within 60 days. Section 32 of the pro the proposal, arguing that most of the
provide point-to-point customers with forma OATT (Additional Study data needed to compute the metrics is
increased service options and flexibility. Procedures for Network Integration already available on OASIS. Southern
1295. Implementing Imperial’s Transmission Service Requests) asserts that the NOPR does not explain
proposal would prevent customers from contains similar due diligence deadlines why the currently available information
redirecting for a short period or periods for completing system impact studies is inadequate or how the proposed
of time and then redirecting back to and facilities studies associated with metrics would not be duplicative and,
their original points, making redirects a requests for network service. thus, does not fully justify the need for
less valuable option for customers. (1) Posting Performance Metrics reform. Southern also argues that the
Multiple redirects are allowed only if Commission’s proposal will impose
NOPR Proposal
sroberts on PROD1PC70 with RULES

the customer can meet the scheduling


789 E.g., ELCON, Suez Energy NA, Powerex,
and other requirements for new requests 1298. In the NOPR, the Commission
Seattle, TAPS, Constellation, Entegra, NRECA, TDU
for service under the pro forma OATT. proposed to require transmission Systems, Regional Electricity Committee, MISO,
providers to post on their OASIS sites MidAmerican, FirstEnergy, Tacoma, EEI, Nevada
788 Order No. 888–A at 30,260. metrics that track their performance in Companies, and TranServ.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00169 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12434 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

costs and burdens on transmission to be performed on a short-term basis, Commission’s proposal as a punishment
providers, and ultimately those who use so any metrics required as part of OATT for delays in processing request studies.
their services, that do not correspond reform should not include short-term 1307. Several other commenters
with the limited benefits that might be requests. CREPC suggests that suggest changes to the Commission’s
gained. Salt River believes that performance metrics be calculated proposal. Southern believes the
performance tracking requirements separately for renewable resources. submission of a notification of
should be established on a case-by-case 1304. Several commenters suggest extenuating circumstances should
basis in response to complaints. that transmission providers post suspend the obligation to post the
NorthWestern believes the 60 days additional metrics proposed in the
additional information to further
should be a target, but not a deadline, NOPR. EEI and Southern argue that the
enhance transparency. A number of
and, as such, transmission providers Commission should be certain that it is
commenters suggest that the
should not be required to report collecting such information only from
Commission require the posting of the
performance metrics that summarize the those transmission providers that, for no
time they take to perform the studies. disposition of all transmission service
other reason except themselves, fail to
1302. Several commenters requested requests, including those not requiring
consistently evaluate studies within the
clarification on certain features of the studies.790 TDU Systems suggest that
60-day due diligence period. Therefore,
Commission’s proposal. Nevada the Commission require transmission
if a transmission provider demonstrates
Companies asks the Commission to be providers to post the parameters of each
that delays in completing studies are
very specific as to what statistical data denied request. MISO suggests that
due to extenuating circumstances, then
items are to be reported on the OASIS transmission providers provide a
EEI and Southern believe the
so that transmission providers do not narrative to explain any anomalous Commission should not require the
inadvertently violate the confidentiality study costs that may affect the posted transmission provider to post the
of their transmission customers. PNM- average cost. If a transmission provider additional metrics. MISO believes the
TNMP requests clarification that the anticipates that it will miss the study Commission should exempt RTOs from
standards set out in the NOPR are solely deadline date, NRECA suggests that it the additional employee performance
applicable to processing of transmission should post that information, the metrics proposed in the NOPR for the
delivery service requests, and not to expected finish date, and a reason for same reason that the Commission
interconnection service requests. Insofar not being able to meet the deadline. proposed to exempt RTOs from
as the Commission determines that 1305. EEI recommends that the operational penalties for untimely
performance metrics should be posted, Commission delegate to NAESB the completion of studies, as MISO claims
Southern asks the Commission to clarify responsibility for developing the the additional posting requirements are
that the proposed posting of Standard and Communications in the nature of penalty. Bonneville
performance metrics also would be Protocols, business practices and OASIS believes the proposed metrics will be
required of RTOs and ISOs. modifications that will be necessary to misleading whenever a transmission
1303. A number of commenters provide the metrics. provider employs outside consultants to
suggest that the Commission modify the perform or assist with studies.
performance metrics that transmission Additional Performance Metrics (After Therefore, Bonneville suggests that the
providers are required to post. EEI Two Quarters of Late Studies) Commission add two other metrics, the
suggests that NAESB develop the
1306. EEI and Southern oppose the number of studies performed entirely by
metrics that transmission providers are
Commission’s proposal to require consultants and, in the case of studies
required to post, using the metrics
transmission providers that fail to performed by a combination of
contained in the NOPR as guidance. EEI
complete studies in a timely manner to employees and consultants, the average
and MidAmerican suggest that the
post additional performance metrics percentage of the study performed by
performance metrics include
that measure the labor input used to consultants.
information about the degree to which
transmission customers delay the study complete studies. EEI asserts that there Commission Determination
process. MISO suggests that is little value to be gained from posting
Standard Performance Metrics
transmission providers post metrics the additional information that the
related to the time transmission Commission proposes. EEI believes the 1308. The Commission will require
customers take to respond to the results information concerning the number of transmission providers to post the
of completed system impact studies and employees who perform studies will not performance metrics proposed in the
facilities studies. Southern asserts that be determinative of responsibility for NOPR, as modified by this Final Rule.
fewer metrics should be required and the delay because the significant issue is The proposed metrics will enhance the
that they should relate directly to the whether the number of studies that the transparency of the study process and
study-timing concerns raised in the transmission provider is required to shed light on whether transmission
NOPR. Bonneville and MISO argue that perform or the total amount of time providers are processing request studies
transmission providers should not have needed to perform studies has increased in a non-discriminatory manner. We
to post information about the cost of significantly or whether customers also agree with comments by
transmission system upgrades caused the delays. Southern questions MidAmerican and EEI that transmission
recommended in the request studies. the Commission’s legal authority to providers should be able to track delays
Bonneville believes that the average cost require transmission providers that do in the study process caused by
of recommended upgrades is misleading not complete studies in a timely manner transmission customers. Doing so will
because it will mask the wide variation to post additional performance metrics, allow the Commission and market
in such costs. MISO suggests that citing Cal. Ind. Sys. Operator Corp. v. participants to determine the extent to
sroberts on PROD1PC70 with RULES

transmission providers also report the FERC.791 Southern characterizes the which delays by transmission customers
standard deviation for study completion are causing transmission providers to
times. Southern asserts further that the 790 E.g., CREPC, MISO, Constellation, and TDU process request studies on an untimely
OATT does not specifically provide for Systems. basis, which will add needed
a system impact study or facilities study 791 372 F.3d 395, 404 (D.C. Cir. 2004). transparency to the study process.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00170 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12435

Therefore, we will revise the • System impact study processing transmission customer
performance metrics transmission time pursuant to sections 19.3 and 32.3 Æ Average cost of facilities studies
providers are required to post to include of the pro forma OATT completed during the period
metrics that track delays by Æ Number of system impact studies Æ Average cost of recommended
transmission customers. completed upgrades for facilities studies
1309. Transmission providers will be Æ Number of system impact studies completed during the period
required to post the performance completed more than 60 days after • Service requests withdrawn from
metrics, outlined below, for each receipt of executed system impact facilities study queue
calendar quarter. Transmission study agreement Æ Number of requests withdrawn
providers will be required to begin Æ Average time (days) from receipt of from the facilities study queue
tracking their performance upon the executed system impact study Æ Number of facilities studies
effective date of this Final Rule and agreement to date when completed withdrawn more than 60 days after
keep the quarterly performance metrics system impact study made available receipt of executed facilities study
posted on their OASIS sites for three to the transmission customer agreement
calendar years. The transmission Æ Average cost of system impact Æ Average time (days) from receipt of
provider will be required to post the studies completed during the executed facilities study agreement
quarterly performance metrics within 15 period to date when request was
days of the end of the quarter. The withdrawn from the facilities study
• Service requests withdrawn from
performance metrics outlined below queue
system impact study queue
must be calculated separately for
Æ Number of requests withdrawn • For all facilities studies completed
affiliates’ and non-affiliates’ requests, in
from the system impact study queue more than 60 days after receipt of
order to identify potential instances
Æ Number of system impact studies executed facilities study agreement,
when the transmission provider is
withdrawn more than 60 days after average number of days study was
processing requests on a discriminatory
receipt of executed system impact delayed due to transmission customer’s
basis. The transmission provider is
study agreement actions (e.g., delays in providing needed
required to aggregate studies associated
Æ Average time (days) from receipt of data).
with requests for short-term and long-
executed system impact study 1311. In response to Nevada
term transmission service when
agreement to date when request was Companies request that we clarify the
calculating the metrics defined below.
withdrawn from the system impact statistical data items that are to be
While a transmission provider could
study queue reported on OASIS pursuant to the
offer to study a request for short-term
firm point-to-point transmission service, • For all system impact studies Commission’s proposal, we reiterate
completed more than 60 days after that transmission providers are required
we acknowledge that the transmission
receipt of executed system impact study to provide summary data as defined
customer often is unwilling to pay for
agreement, average number of days above. We do not believe these data will
such a study. Therefore, to ease the
study was delayed due to transmission violate the confidentiality of any
reporting burden, the transmission
customer’s actions (e.g., delays in transmission customer, even in the
provider is not required to report the
providing needed data) event the transmission provider has
performance metrics defined below
separately for requests for short-term • Process time from completed worked on a limited number of studies.
system impact study to offer of facilities We clarify that the performance metrics
and long-term firm point-to-point
study pursuant to sections 19.4 and 32.4 posting requirement discussed above is
transmission service. A transmission
of the pro forma OATT solely applicable to processing of
provider is also required to post
Æ Number of new facilities study transmission delivery service requests,
performance metrics for studies that it
agreements delivered to and not to interconnection service
conducts for RTOs.
transmission customers requests. Finally, we clarify that RTOs
1310. A transmission provider is
Æ Number of new facilities study and ISOs also are required to post the
required to post the following set of
agreements delivered to performance metrics described above.
performance metrics on a quarterly
transmission customers more than As we discuss below, we believe all
basis:
transmission providers should be
• Process time from initial service 30 days after the completion of the
system impact study subject to the same reporting
request to offer of system impact study
Æ Average time (days) from requirements.
agreement pursuant to sections 17.5,
completion of system impact study 1312. We disagree with Southern and
19.1 and 32.1 of the pro forma OATT
to delivery of facilities study Salt River which argue that the data
Æ Number of new system impact already on OASIS is sufficient to
study agreements delivered to agreement
Æ Number of new facilities study accomplish our goal to enhance
transmission customers transparency of the transmission
Æ Number of new system impact agreements executed
provider’s request study processing.
study agreements delivered to the • Facilities study processing time
First, the data available on the OASIS
transmission customer more than pursuant to sections 19.4 and 32.4
template transstatusaudit does not
30 days after the transmission Æ Number of facilities studies contain the information necessary to
customer submitted its request completed calculate all of the performance metrics
Æ Average time (days) from request Æ Number of facilities studies proposed in the NOPR.792 For instance,
submittal to change in request completed more than 60 days after
status receipt of executed facilities study 792 The OASIS template transstatusaudit is
sroberts on PROD1PC70 with RULES

Æ Average time (days) from request agreement defined in the Standards and Communications
submittal to delivery of system Æ Average time (days) from receipt of Protocols section of NAESB’s WEQ Business
Practice Standards. The template transstatusaudit is
impact study agreement executed facilities study agreement the audit component to OASIS template transstatus
Æ Number of new system impact to date when completed facilities and, as such, contains information regarding the
study agreements executed study made available to the Continued

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00171 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12436 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

transstatusaudit allows one to transmission provider is between rate determine the specific performance
determine when a request was moved cases. We therefore believe that there metrics that will achieve our policy
from ‘‘received’’ to ‘‘study’’ and then to are several reasons that greater goals and thus we will not request that
‘‘accepted’’ or ‘‘counteroffer’’. transparency is required to provide the NAESB develop the metrics to be
Depending on when the transmission correct incentives to comply with the posted.795 We believe the set of
provider moves the request into pro forma OATT provisions respecting performance metrics we have chosen
‘‘study,’’ this information does not allow studies. strike the appropriate balance between
one to determine either whether the 1314. We also note that virtually all requiring information that will enhance
transmission provider provided a commenters agree with our proposal to transparency and help ensure that the
system impact study agreement within require transmission providers to transmission provider is processing
30 days or whether the transmission calculate the above performance request studies in a timely and non-
provider completed the system impact metrics. This support stems, in part, discriminatory fashion while limiting
study within 60 days. In addition, the from transmission customers’ the burden the transmission provider
transmission provider is required to perception that transmission providers faces. For instance, we believe the
make the data in transstatusaudit do not exert sufficient effort to complete performance metrics that address the
available on OASIS for only 90 days and requests in a timely manner.794 Delays cost of system impact studies and
available by request for three years.793 in processing study requests can cause facilities studies as well as the cost of
As a result, market participants would customers to incur material financial any proposed transmission upgrades
be required to calculate the performance damage. Moreover, the data needed to can be calculated with relatively little
metrics they desire on a quarterly basis calculate the required performance effort by the transmission provider and
if they want to use just the data posted statistics is readily available to the should provide meaningful benefits to
on OASIS. Finally, downloading transmission provider and, therefore, transmission customers. The
transstatusaudit data for specific OASIS the cost to the transmission provider transmission provider readily knows the
requests that required a system impact will be small relative to the benefits of cost of studies it completes and the
study or feasibility study can be enhanced transparency and assurance costs of proposed system upgrades and
cumbersome due to the manual nature that the transmission provider is summaries of this information should
of the download process. The processing request studies in a timely enhance the transmission customer’s
transmission provider has the data and non-discriminatory fashion. ability to decide whether to submit a
necessary to calculate the proposed 1315. Based on our experience and request for service that may result in a
performance metrics readily available. the comments received in response to study offer.
We believe it is more efficient for a the NOI and NOPR, the Commission 1317. We do not believe the relative
single transmission provider to calculate believes the steps we take here are benefits and burdens justify requiring
the performance metrics for its system necessary to increase transparency for
the transmission provider to post
rather than have multiple interested the processing of service requests by all
performance metrics beyond those
parties calculate the performance transmission providers. It would be
adopted in this Final Rule. For instance,
statistics for each transmission provider inappropriate, as some commenters
requiring the transmission provider to
of interest. suggest, to wait for specific complaints
calculate additional summary
1313. We also disagree with about specific transmission providers
information or post long narratives to
Southern’s assertion that the costs and before requiring the transmission
explain anomalous upgrade costs do not
burdens to transmission providers are provider to calculate the performance
appear necessary at this time to achieve
not justified by the benefits that might metrics defined above. We conclude
our stated policy goals, particularly
be gained. We are concerned that, under that the reporting requirements adopted
since transmission customers can
the existing pro forma OATT, in this Final Rule must be applied to all
request data associated with completed
transmission providers do not have transmission providers in order to
system impact studies and facilities
adequate incentives to conduct studies enhance the transparency of the study
studies pursuant to section
on a timely and nondiscriminatory process and ensure that transmission
37.6(b)(2)(iii) of the Commission’s
basis. First, transmission providers have provider processes study requests in a
regulations.796 In addition, we do not
incentives to discriminate against third timely and non-discriminatory fashion
believe transmission customers, beyond
parties and in favor of their affiliates for all transmission customers. The fact
(i.e., to delay the study requests of the transmission customer directly
that the 60-day timeframe in the pro
nonaffiliates, but act more quickly on affected, would benefit from the
forma OATT is a target and not a
those of its affiliates). Second, information NRECA suggests the
deadline does not change the fact that
transmission providers also can lack transmission provider should be
requiring all transmission providers to
incentives to provide sufficient staff required to post when it anticipates that
post the performance metrics defined
resources to support increasing it will not complete a study within the
above will enhance the transparency of
demands in the study process. Given 60-day due diligence timeframe. Section
the study process.
that most of the costs associated with 1316. We will not adopt any of the 19.3 of the pro forma tariff already
the study process are operational, changes to the proposed performance requires the transmission provider to
transmission providers, at most, will metrics requested by commenters, other notify the affected transmission
recover those costs without profit (i.e., than adding metrics to track delays by customer when it will not be able to
a return) and, if the demands of the customers as discussed above. The complete a study within the 60-day due
study process are increasing, fail to Commission is in a better position to diligence timeframe, provide an
recover such cost increases if the expected completion date, and explain
794 E.g., Constellation, EPSA NOI Comments, why additional time is needed. We do
sroberts on PROD1PC70 with RULES

type of transmission service requested, affiliate Arkansas Cities NOI Comments, APPA NOI Reply
795 As noted in P 1318, we direct public utilities
status, date and time the transmission service was Comments, and Powerex NOI Reply Comments 795
requested, and the date and time of all changes in As noted in P 1318, we direct public utilities working through NAESB to develop protocols for
request status (e.g., place in study mode, confirmed working through NAESB to develop protocols for posting the performance metrics required here so
or withdrawn). posting the performance metrics required here so they will be posted in a consistent fashion.
793 18 CFR 37.7(b). they will be posted in a consistent fashion. 796 18 CFR 37.6(b)(2)(iii).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00172 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12437

not believe other transmission facilities studies, of employee-hours increase the transmission provider’s
customers would benefit enough from expended per completed facilities incentive to staff its study function
this information to justify requiring the study; (3) the number of employees appropriately.
transmission provider to post it. devoted to processing system impact 1322. The additional posting
Similarly, we do not believe the benefit studies; and (4) the number of requirement is not a penalty or a
to market participants justifies the employees devoted to processing punishment. We opted not to require
burden of requiring transmission facilities studies. The transmission the transmission provider to post these
providers to calculate performance provider is not required to post these additional performance metrics on a
metrics separately for renewable additional performance metrics regular basis out of a desire to limit the
resources. separately for affiliates’ and non- transmission provider’s reporting
1318. We agree, however, with EEI’s affiliates’ requests for transmission burden. However, once the transmission
recommendation that the Commission service and for short-term and long-term provider has stopped completing
delegate to NAESB the responsibility for transmission service. The transmission studies on a timely basis, we believe the
developing the Standard and provider is instead required to aggregate enhanced transparency justifies the
Communications Protocols, business studies associated with requests for additional reporting burden. As a result,
practices and OASIS modifications that short-term and long-term transmission ISOs and RTOs also will be required to
will be necessary to provide the service when calculating these post the additional performance metrics
performance metrics adopted above. additional metrics. The transmission described above. We disagree with
NAESB is in the best position to provider is not required to post the Southern’s argument that we lack
develop the standards and the processes additional metrics if the Commission jurisdiction to require additional
by which the performance metrics are concludes that delays in completing posting. The posting requirements are
posted. studies are due to extenuating directly related to pro forma OATT
Additional Performance Metrics (after circumstances. However, the obligations that are necessary to remedy
two quarters of late studies) transmission provider is required to undue discrimination and, hence,
post the additional metrics while the necessarily derive from our broad
1319. The Commission also adopts Commission considers the transmission discretion in fashioning remedies to
the NOPR proposal to require provider’s notification filing arguing undue discrimination. We are not
transmission providers to submit a that extenuating circumstances attempting to dictate a transmission
notification filing with the Commission prevented it from processing request provider’s internal staffing decisions;
in the event the transmission provider studies on a timely basis. Based on the rather, we illuminate the transmission
processes more than 20 percent of non- timing described in this Final Rule, the provider’s compliance with its pro
affiliates’ studies outside of the 60-day transmission provider will be required forma OATT obligations to perform
due diligence deadlines in the pro to post the additional performance studies within certain deadlines and on
forma OATT for two consecutive metrics approximately two months after a nondiscriminatory basis.
quarters. This filing must be filed within the provider makes its notification 1323. We will not add the two other
30 days of the end of the second quarter filing. The Commission will have this metrics suggested by Bonneville
during which the transmission provider time to evaluate the transmission regarding the number of studies
processes more than 20 percent of non- provider’s contention that it was unable performed entirely by consultants and,
affiliates’ studies outside of the 60-day to complete request studies due to
due diligence deadlines in the pro in the case of studies performed by a
extenuating circumstances. As a result, combination of employees and
forma OATT. For the purposes of we expect the transmission provider
calculating this notification trigger, the consultants, the average percentage of
with legitimate extenuating the study performed by consultants.
transmission provider is required to circumstances typically will not have to
aggregate all system impact studies and Rather, transmission providers should
post any additional metrics. include the time spent by consultants
facilities studies that it completes 1321. We disagree with those arguing
during the quarter for non-affiliates.797 on studies in the performance metrics
that information concerning the number defined above.
The transmission provider may explain of employees who perform studies will
in its notification filing that it believes not be determinative of responsibility (2) Operational Penalties for Late
there are extenuating circumstances that for the delay. The transmission provider Studies
prevented it from meeting the deadlines will have the right to establish that it is NOPR Proposal
in the pro forma OATT. unable to perform studies in a timely
1320. As the Commission proposed in 1324. The Commission proposed to
manner because of factors outside its
the NOPR, starting the quarter following impose operational penalties when
control. We received a number of
a notification filing, the transmission transmission providers routinely fail to
comments to the NOPR and NOI that
provider will be required to post: (1) meet the 60-day due diligence deadlines
suggest that transmission customers
The average, across completed system prescribed in sections 19.3, 19.4, 32.3
believe transmission providers fail to
impact studies, of the employee-hours and 32.4 of the pro forma OATT. Under
complete studies on a timely basis
expended per completed system impact the proposal, a transmission provider
because they do not have sufficient staff
study; (2) the average, across completed who processes more than 20 percent of
to perform the studies.798 As explained
non-affiliates’ studies outside of the 60-
above, this is one of the concerns that
797 For instance, if the transmission provider day due diligence deadlines in the pro
completes 4 non-affiliates’ system impact studies has led us to adopt these reforms. The
forma OATT for two consecutive
during the quarter with 2 completed more than 60 additional metrics will serve to shed
quarters would be required to notify the
days after the system impact study agreement was light on the transmission provider’s
executed and completes 2 non-affiliates’ facilities Commission. In this notification filing,
resource commitment, enhance the
sroberts on PROD1PC70 with RULES

studies during the quarter with none completed the transmission provider may explain
more than 60 days after the facilities study transparency of the study process, and
that it believes there are extenuating
agreement was executed, then the transmission
provider will be deemed to have completed 2 out 798 E.g., Constellation, EPSA NOI Comments, circumstances that prevented it from
of 6 (33 percent) studies outside of the deadlines Arkansas Cities NOI Comments, APPA NOI Reply meeting the deadlines in the pro forma
in the pro forma OATT. Comments, and Powerex NOI Reply Comments. OATT. The transmission provider

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00173 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12438 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

would be subject to an operational in practice.803 Several opponents argue circumstances. Tacoma asks the
penalty if it continues to be out of that the Commission’s proposed penalty Commission to ensure that the
compliance 799 with the deadlines regime is inconsistent with the new processing time is measured from the
prescribed in the pro forma OATT for requirements the Commission has point that the customer provides
each of the two quarters following its proposed for regional planning and complete information.
notification filing. requirements to consider redispatch in 1329. EEI recommends that the
1325. The Commission proposed that the system impact study.804 In its reply Commission hold a technical conference
the operational penalty be assessed on comments, EEI argues that due process to determine the extent to which studies
a quarterly basis, starting with the requires that the Commission not are not being completed within 60 days,
quarter following the notification filing impose penalties on transmission the principal causes of delays in
and continuing until the transmission providers for study delays because, in completing studies within 60 days and
provider completes at least 90 percent of EEI’s view, it is highly likely that the whether the increased planning and
all studies within 60 days after the delays will have been caused by factors coordination requirements proposed by
study agreement has been executed. For or events that were beyond the the Commission will result in additional
any system impact study or facilities transmission provider’s control. time being needed to complete the
study completed during that quarter and Southern asserts that any scheme of studies. EEI believes the Commission is
more than 60 days after the study operational penalties associated with far more likely to arrive at a reasonable
agreement was executed, the the processing of studies cannot be conclusion concerning these issues after
Commission proposed a penalty equal implemented fairly unless and until the a technical conference than if it simply
to $500 for each day the transmission problem surrounding the submission of imposes penalties for failures to
provider takes to complete the study multiple requests is addressed. complete all studies within 60 days.
beyond 60 days. For any system impact Southern argues that the Commission Seattle believes the proposed penalties
study or facilities study that is still would violate a transmission provider’s should not be implemented until
pending at the end of the quarter and due process rights if it were to impose providers and customers have had at
that has been in the study queue for penalties for delays caused by least one year of experience working
more than 60 days, the Commission transmission customers. CREPC with the performance metrics.
proposed a penalty equal to $500 for proposes that transmission projects that
1330. Transmission customers
each day the study has been in the study cross seams not be subject to penalties,
generally support the Commission’s
queue beyond 60 days. arguing that such an exception will
proposal to impose operational
1326. In addition to the proposed create a level playing field for those
penalties when a transmission provider
operational penalties, the Commission transmission providers in the West
routinely fails to meet the 60-day due
indicated that it would order other working with the CAISO and foreign
diligence deadlines.807 In its reply
remedial actions, consistent with the transmission owners to resolve
comments, Entegra argues that the
Policy Statement on Enforcement, to be transmission service requests.
question is not whether a transmission
determined on a case-by-case basis. The 1328. A number of commenters ask
provider has sufficient margins of
Commission proposed that RTOs not be the Commission to clarify specific
flexibility, but whether the transmission
subject to this penalty regime because of elements of the proposed operational
provider has any stake in meeting the
the RTOs’ independence. penalty regime. Several commenters
deadlines. Occidental argues that
argue that the proposal does not clearly
Comments transmission providers may have little
provide for an exemption from
1327. Transmission providers incentive to meaningfully address
operational penalties if the failure to
generally oppose the Commission’s customers’ issues without the prospect
meet the timeliness criteria is a result of
proposal.800 Some opponents argue that, of a prospective remedy. Responding to
extenuating circumstances or customer
to the extent the Commission is going to EEI’s due process argument, TDU
caused delays, thereby denying
impose penalties, it should do so on a Systems in reply assert that imposition
transmission providers due process.805
case-by-case basis.801 Opponents cite a of penalties in this instance raises no
Several commenters ask the
number of reasons the Commission more due process concerns than those
Commission to clarify that a
should not impose the proposed operational penalties that transmission
transmission provider is not subject to
operational penalty regime. Several customers are routinely subjected to
operational penalties if the transmission
opponents caution that imposing a under the OATT. TDU Systems argue
provider’s failure to meet the
penalty may lead transmission that, should the Commission determine
compliance threshold following its
providers to either prematurely deny a that transmission providers are entitled
notification filing is due to extenuating
request or accept a request to the to challenge any operational penalty for
circumstances.806 Southern asks that the
detriment of system reliability.802 failure to process service requests in a
Commission clarify that the submission
Several opponents argue that many timely manner, then those challenges
of a notification of extenuating
transmission requests introduce unique must be on terms and conditions that
circumstances would suspend the
complexities into the study process, so are comparable to those available to
obligation of a transmission provider to
a firm 60-day deadline is not workable transmission customers—a complaint
process at least 90 percent of the study
pursuant to FPA section 206. TDU
requests within the proposed deadlines,
Systems believe that the proposed
799 The transmission provider would be deemed
until such time as the Commission
to be out of compliance if it completes 10 percent ‘‘explanatory statement’’
issues a final determination on the
or more of non-affiliates’ system impact studies and contemporaneous with any notification
facilities studies outside of the deadlines prescribed notification of extenuating
filing is a form of expedited review that
in the pro forma OATT.
is clearly not comparable to the
sroberts on PROD1PC70 with RULES

800 E.g., EEI, MidAmerican, Entergy, Southern, 803 E.g., MidAmerican, Southern, NorthWestern,

Imperial, NorthWestern, PNM–TNMP, Salt River, Northwest IOUs, and PNM–TNMP Reply. treatment of customers under the tariff.
and Bonneville Reply. 804 E.g., MidAmerican, Southern, and EEI Reply.
801 E.g., EEI, Southern, and PNM–TNMP Reply. 805 E.g., EEI, Southern, Northwest IOUs, and 807 E.g., Suez Energy NA, TAPS, Constellation,
802 E.g., MidAmerican, Southern, Imperial, and MidAmerican. Entegra, TDU Systems, CREPC, and Nevada
EEI Reply. 806 E.g., EEI and MidAmerican. Companies.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00174 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12439

1331. Several transmission customers with any amount in excess of the study met regardless of the type of provider
question whether the proposed penalty costs payable to the transmission conducting the study. Xcel notes that,
level is sufficient to ensure customer, in recognition of the harm to historically, transmission owners need
compliance.808 Constellation transmission customers when required to complete facility studies in concert
recommends a penalty of up to $10,000 studies are not completed expeditiously. with RTOs, thereby giving the customer
per day per violation. Entegra suggests CREPC asks the Commission to clarify the most up-to-date and coordinated
the Commission set the penalty equal to how it plans to determine which analysis. Consequently, Xcel believes it
the higher of the lost opportunity cost unaffiliated transmission customers will is imperative that both transmission
to the customer resulting from the delay, receive operational penalty payments. owners and RTOs operate under the
if any, or $1,000 for each day. Entegra CREPC also asks the Commission same rules, reporting obligations, and
also suggests that penalties should be whether the $500 per day penalty is a performance metrics in the OATT.
assessed automatically, without a flat rate that would be pro-rated among 1337. In its reply comments, WPS
notification filing to the Commission. In eligible non-offending, unaffiliated disagrees with the Commission’s
its reply comments, EEI argues that the transmission customers or if the $500 is proposal to exempt RTOs from penalties
total penalty for delayed studies will be a rate paid to each eligible transmission for their repeated failure to meet the 60-
far higher than $500 per day if the customer. day due diligence requirements. WPS
transmission provider is processing 1335. Commenters affiliated with asserts that the Commission should
more than five requests per 60-day RTOs and one transmission customer impose penalties and prohibit the
period, which EEI asserts is extremely support the Commission’s proposal to recovery of associated revenue where
likely. exempt RTOs from penalties for late appropriate. WPS argues that RTO
1332. Constellation asks the studies.810 MISO asserts that RTOs do independence does not guarantee RTO
Commission to consider whether to not have incentives to delay the competence or compliance in every
require the transmission provider to processing of transmission service instance. WPS believes imposing
engage an independent transmission requests, as they have no affiliates to reporting obligations and penalties for
administrator to the extent a favor and because their Commission- failure to comply with tariff
transmission provider’s posted approved design and internal requirements, particularly tariff
performance metrics are not accurate or procedures ensure their independence. deadlines, will help to motivate
the transmission provider persistently MISO argues further that all compliance by ensuring that RTOs
fails to adhere to the relevant timelines. transmission service requests benefit devote resources to tariff compliance.
1333. Several commenters suggest some RTO member and, as a result, WPS acknowledges that a non-profit
that the Commission extend the study RTOs have no disincentive to approve RTO has no dividends to cancel and
completion deadlines, such as to 120 or service so long as reliability is likely no property to liquidate to cover
180 days, at least for the purposes of maintained. MISO/PJM States asserts these shortfalls, yet believes that such
assessing penalties.809 Bonneville that the NOPR proposal to exempt RTOs organizations can exercise cost-cutting
suggests that the Commission change from operational penalties for late measures, especially regarding rewards
the service request study process to studies is appropriate because a penalty for employee performance, and thereby
match the interconnection study process does not serve a useful purpose with bear some financial responsibility and
as articulated in the Large Generator respect to RTOs. TDU Systems state that accountability for their operational
Interconnection Procedures. Imperial an RTO should not be financially violations. In the event of a penalty,
recommends that instead of mandating penalized for late studies because RTO WPS believes the Commission could
a nationwide study schedule, each of independence should minimize require an RTO to take steps to cover its
the NERC regions should establish a incentives for affiliate preference and penalty-related revenue shortfall by
schedule taking into account the various RTO members indirectly pay for all RTO cutting its budget, eliminating
needs of the region. Southern suggests incurred costs in any event. management bonuses and
restarting the 60-day due diligence 1336. Most of those commenters not demonstrating that it has taken
period for any study that experiences a affiliated with an RTO oppose the reasonable corrective steps before the
delay that cannot properly be attributed proposal to exempt RTOs from penalties Commission permits recovery of the
to the transmission provider. In contrast for late studies.811 Southern argues that remaining penalty revenue from its
to the suggestions to increase the study given that the Commission is seeking to members and customers. To the extent
time, Entegra suggests that the increase transparency in the system, the some portion of an RTO’s penalties are
Commission consider changing the due Commission would undercut that goal passed through to its market
diligence deadlines to 30 days to further by omitting a significant segment of the participants, including transmission
the goal of encouraging timeliness in industry. TAPS argues that RTOs may owners, WPS argues that those market
completing required studies. still fail to complete studies on a timely participants would be in a position to
1334. Several commenters suggest basis due to competing internal take actions similar to the actions taken
methods for distributing the operational priorities or bureaucratic indifference. by shareholders of a publicly traded
penalties the transmission provider pays Progress notes that the Commission has company to motivate the RTO either by
for late studies. TAPS believes that found that RTOs and ISOs should be changing the RTO’s processes or its
penalty revenues should go to victims of subject to penalties for failure to meet Board of Directors.
1338. TAPS states that some
study delay. Similarly, Entegra believes reliability standards. Salt River argues
adaptation of the penalties may be
the penalty should take the form of a that RTOs should be subject to
necessary to make them appropriate and
credit against the transmission operational penalties because the
effective in the non-profit RTO/ISO
customer’s obligation to reimburse the impact on the customer is identical if
context, for example, by requiring a
transmission provider for study costs, the request processing deadline is not
sroberts on PROD1PC70 with RULES

reduction in management
808 E.g.,
compensation. TDU Systems
TAPS, Constellation, and Entegra. 810 E.g., MISO, MISO/PJM States, TDU Systems,
809 E.g.,
Bonneville, MidAmerican, Progress and Indianapolis Power Reply. recommend that RTOs be subject to the
Energy, NorthWestern, Northwest IOUs, and EEI 811 E.g., Southern, TAPS, Progress Energy, Salt notification filing requirement that is
Reply. River, and Xcel. part of the Commission’s penalty

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00175 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12440 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

proposal, regardless of whether RTOs OATT. The operational penalty will be customer. We will not, however, exempt
are subject to pay penalties. TDU assessed on a quarterly basis, starting all transmission projects that cross
Systems believe this reporting with the quarter following the seams from operational penalties, as
requirement would provide an objective notification filing and continuing until CREPC urges. We will consider the
measure of RTO efficiency. APPA the transmission provider completes at specific facts surrounding studies of
believes steps should be taken to least 90 percent of all studies within 60 such projects based on a transmission
remedy tardy RTO processing of service days after the study agreement has been provider’s notification filing. In
requests, suggesting that performance executed. For any system impact study response to TDU Systems, we
incentives for RTO employees, if or facilities study completed during that acknowledge that the procedures for
carefully designed, could be useful. In quarter and more than 60 days after the addressing a transmission provider’s
its reply comments, Duke argues that study agreement was executed, the failure to conform to the 60-day time
although transmission owners in RTOs penalty will equal $500 for each day the frame are not the same as the
should not pay the price for RTOs transmission provider takes to complete procedures applicable to a transmission
failures to abide by the tariff, RTOs lack the study beyond 60 days. For any customer that is assessed an operational
of performance should be addressed by system impact study or facilities study penalty under the pro forma OATT. We
the Commission, perhaps in a separate that is still pending at the end of the believe such different procedures are
proceeding. quarter and that has been in the study justified in this instance. The other
1339. Transmission providers that queue for more than 60 days, the operational penalties in the pro forma
have retained an independent tariff penalty will equal $500 for each day the OATT are assessed for failure to remain
administrator suggest that these study has been in the study queue in compliance with strict requirements,
independent entities should also be beyond 60 days. while the study time frame is based on
exempt from operational penalties 1341. The late study penalty regime the transmission provider using its due
related to study completion times.812 In described in this Final Rule will become diligence to complete studies within 60
their view, these independent entities effective at the same time as the rest of days. The Commission recognizes that
also have no incentive to discriminate the new pro forma OATT. The penalty the transmission provider must have
when completing service request regime is designed so that the flexibility, within reason, to complete
studies. Similarly, NorthWestern argues transmission provider has to be out of studies outside of this time frame. At
that a transmission provider without an compliance for at least three quarters the same time, the notification and
affiliate that could benefit from a delay before it is subject to late study penalty procedures we adopt in this
in completing service request studies penalties. We believe nine months is Final Rule will ensure that this
also should be exempt from paying the sufficient time for the transmission flexibility is not abused.
proposed operational penalties. provider to adjust its operations to the 1344. We do not find the remaining
new requirements in this Final Rule, comments in opposition to the
Commission Determination
including penalties for late studies. That operational penalty for late studies to be
1340. The Commission adopts the is, we believe transmission providers compelling, particularly given the
NOPR proposal to subject transmission should be able to reallocate employees flexibility built into our penalty regime.
providers to operational penalties when to study requests for service and hire We would not expect a transmission
they routinely fail to meet the 60-day new staff, to the extent these steps are provider to prematurely deny a request
due diligence deadlines prescribed in necessary, by the time the transmission for service simply to avoid an
sections 19.3, 19.4, 32.3 and 32.4 of the provider will be subject to civil operational penalty. According to
pro forma OATT. Transmission penalties. section 17.5 of the pro forma OATT, a
providers must have a meaningful stake 1342. The procedures underlying the transmission provider must either grant
in meeting study time frames. As operational penalty regime adopted in service or offer the transmission
discussed above, a transmission this Final Rule ensure that the due customer a system impact study. The
provider will be required to make a process rights of transmission providers transmission provider does not have the
notification filing with the Commission are protected. In their notification filing, option to simply deny the request for
indicating that it has not completed transmission providers will have the service. We therefore interpret
request studies on a timely basis and right to document and describe any comments that the transmission
may present evidence that extenuating unique complexities that particular provider may prematurely deny a
circumstances prevented it from requests introduce into the study request to mean that the transmission
completing studies on a timely basis. process and that prevent the provider will not explore all possible
The transmission provider then will be transmission provider from completing system upgrades or redispatch options
subject to an operational penalty if the the study within a the 60-day due as required by section 19.3 of the pro
transmission provider continues to be diligence time frame. Thus the 60-day forma OATT or any conditional firm
out of compliance with the deadlines time frame will continue to be a flexible options discussed in section V.D.1.
prescribed in the pro forma OATT for deadline, especially given that the Such behavior would be a tariff
each of the two quarters following its transmission provider is not required to violation that should be brought to our
notification filing and the Commission complete all studies within 60 days. attention. The transmission provider is
determines that no extenuating These due process rights provide a de required under the pro forma OATT to
circumstances exist to excuse the facto case-by-case review of the provide a complete study and
transmission provider’s non- transmission provider’s efforts to corresponding work papers to the
compliance. The transmission provider complete studies on a timely basis. transmission customer. If a transmission
will be deemed to be out of compliance 1343. On review of a notification customer feels a system impact study is
if it completes 10 percent or more of filing, we will waive operational incomplete, it has recourse to call the
sroberts on PROD1PC70 with RULES

non-affiliates’ system impact studies penalties if a transmission provider Commission’s Enforcement Hotline or
and facilities studies outside of the establishes that its non-compliance is file a formal complaint with the
deadlines prescribed in the pro forma the result of factors or events that are Commission.
truly beyond its control, including 1345. We also do not expect a
812 E.g., Duke, MidAmerican, and TranServ. delays caused by the transmission transmission provider to accept a

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00176 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12441

transmission service request to the study processing deadlines in the pro determination on the notification of
detriment of system reliability simply to forma OATT, while not being extenuating circumstances. At the same
meet the study time frame. First, the unnecessarily punitive. We believe that time, we will not require the
transmission provider is not required to a penalty in the range of $10,000 per transmission provider to distribute its
complete every request study within 60 day per late study would be operational penalty while we are still
days. Second, to the extent our new unnecessarily punitive. The proposal to considering the transmission provider’s
requirements that the transmission set the penalty equal to the higher of the notification filing. The transmission
provider consider conditional firm lost opportunity cost to the customer provider nonetheless remains liable for
options and participate in regional resulting from the delay, if any, or paying the operational penalty for all
planning cause study delays, the $1,000 for each day is administratively request studies completed or
transmission provider can document cumbersome and could result in outstanding after the notification filing
and describe such delays in its administrative costs that are not and not completed within 60 days. This
notification filing. Finally, the justified. Finally, we believe the due timing will balance the transmission
transmission provider has been required process afforded the transmission provider’s due process rights with the
to consider redispatch in the system provider is an important element of the need to provide an incentive to the
impact study since Order No. 888 was penalty regime, so we decline to impose transmission provider to complete
issued, so the 60-day due diligence time penalties automatically, without a studies on a timely basis.
frame should continue to be consistent notification filing to the Commission. 1350. We clarify that the processing
with the long standing requirement to 1348. As indicated in the NOPR, we time is measured from the point that the
consider redispatch in the system may order other remedial actions in customer returns its executed study
impact study. addition to the operational penalties agreement to the transmission provider.
1346. As we discuss below, we described above, consistent with the By the time the transmission provider
believe NAESB’s queue hoarding and Policy Statement on Enforcement. We offers a system impact study agreement,
queue flooding business practices, as will determine any other remedial it should have all the information it
well as additional reforms adopted in action on a case-by-case basis. The needs to complete the study. Pursuant
this Final Rule, will address the decision to order other remedial actions to section 17.4 of the pro forma OATT,
problem surrounding the submission of will be based, among other things, on the transmission provider can deem a
multiple requests. With regard to whether we believe the transmission transmission service request deficient if
requests for a technical conference or provider is using the same due diligence the transmission customer does not
further procedures to consider the effect to complete studies for non-affiliated provide all information the transmission
of our operational penalty regime, we customers as it uses to complete studies provider needs to evaluate the request
believe the commenters’ proposals for itself. We do not believe it would be for service. We expect the transmission
would largely provide anecdotal appropriate, as a general matter, to provider to use informal means to
information and speculation on the require a transmission provider to communicate the information it needs
impacts of the new planning and engage an independent transmission from the transmission customer before it
coordination requirements. Our administrator to the extent its posted deems a transmission service request
experience from the last ten years, and performance metrics are not accurate. deficient.
the comments provided in response to As a threshold matter, Commission 1351. We adopt the NOPR proposal to
the NOI and NOPR, provide a sufficient audit staff may audit the accuracy of a have the transmission provider
basis to develop a penalty regime. In transmission provider’s posted metrics. distribute the operational penalty for
addition, the very requirement that If we are concerned about the accuracy late studies to all non-affiliated
transmission customers post of a transmission provider’s metrics, we transmission customers, as discussed in
performance metrics and submit will evaluate the use of third-party section V.C.5.b of this Final Rule. We
notification filings prior to assessment audits at that time. We will not prejudge believe that a transmission provider that
of operational penalties will provide which remedial actions we will is not processing studies on a timely
actual experience with the new regime. consider if a transmission provider basis potentially harms all transmission
As explained above, the notification persistently fails to adhere to the customers, not just those with requests
procedures adopted today will ensure relevant timelines. Rather, we will in the study queue. For instance, a
that we will not assess a penalty for late review each such instance on a case-by- transmission customer may decide
studies unless justified by the case basis and determine the against requesting service that it
circumstances. We can propose appropriate remedial action consistent believes will require a system impact
additional changes to the study process with the Commission’s Policy Statement study if the transmission provider is not
or penalty regime based on the actual on Enforcement. processing transmission service requests
experience under this Final Rule if our 1349. We clarify that a transmission on a timely basis. Therefore, we will not
experience warrants it. provider is not subject to operational adopt suggestions to distribute penalty
1347. As described above, we adopt penalties if it can make a showing that revenue only to transmission customers
the proposal to set the operational its failure to meet the compliance that have request studies that are not
penalty for late studies equal to $500 threshold following its notification completed within 60 days. We clarify
per day per late study. We believe $500 filing is due to extenuating that the penalty is $500 per day per late
per day per late study is in line with the circumstances, as we agree that the study, with the resulting total penalty
cost the transmission provider would transmission provider should not be revenue distributed to unaffiliated
incur to focus additional resources on penalized for factors out of its control. transmission customers as discussed in
processing requests studies. In addition, The submission of a notification of section V.C.5.b of this Final Rule. We
the penalty for being one month late, extenuating circumstances will not, clarify that the transmission provider
sroberts on PROD1PC70 with RULES

$15,000, is in line with the overall cost however, suspend the obligation of a will propose a method to determine
of the study. We conclude that the $500 transmission provider to process at least how unaffiliated transmission
per day per late study penalty is high 90 percent of the study requests within customers will receive operational
enough to provide the incentive to the proposed deadlines, until such time penalty payments, as discussed in
transmission providers to comply with as the Commission issues a final section V.C.5.b of this Final Rule.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00177 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12442 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

1352. We will not alter the 60-day unique characteristics when we (4) Fee for Multiple Self-Competing
study completion timeframe currently consider whether penalties would be Transactions
embodied in sections 19.3, 19.4, 32.3 appropriate. We agree that RTOs do not NOPR Proposal
and 32.4 of the pro forma OATT. We have an incentive to discriminate
continue to believe, absent concrete (which is one of the bases for this 1358. In the NOPR, the Commission
evidence to the contrary, that the policy) and we agree that imposing a sought comment on a fee structure that
existing timeframe adequately balances penalty raises the issue of cost recovery, could provide a disincentive for
the need for expeditious resolution of as most RTOs are not-for-profit entities. transmission customers to submit
request studies and the need to ensure We will therefore consider these and all duplicative requests without penalizing
that the transmission provider can other relevant factors in exercising our transmission customers that have
reliably accommodate the transmission discretion whether to impose a penalty legitimate requests for transmission
service reserved. Moreover, we believe in a given circumstance. service. The Commission asked for
the penalty regime defined in this Final 1354. Consistent with the treatment of detailed recommendations, including
Rule protects the transmission provider RTOs, we will not exempt independent any proposed tariff language, regarding
in the event studies take longer to entities that provide tariff the standards it should use to identify
complete due to the new planning administration from penalties for late requests that would be subject to a fee.
requirements defined in section V.B of completion of studies. As with RTOs, The Commission also sought
this Final Rule or the new requirement independence does not guarantee recommendations on the level of a fee
to consider conditional firm options as competence or compliance in every that balances its policy goals to
defined in section V.D.1 of this Final instance. Independent entities have a discourage requests for transmission
Rule. We will not adopt the suggestion similar incentive to limit the personnel service that the transmission customer
to restart the 60-day due diligence committed to processing request studies does not intend to confirm while not
period for any study that experiences a in an effort to reduce overhead costs. discouraging legitimate requests for
delay that can not properly be attributed We believe that all entities transmission service. Finally, the
to the transmission provider. We administering the tariff should operate Commission sought comment regarding
reiterate that the transmission provider under the same rules, reporting the circumstances, if any, under which
is not subject to penalties for late obligations, and performance metrics in the processing fee would be refunded to
studies if it can establish that delays are the pro forma OATT. or credited to the transmission
due to factors the transmission provider customer.
cannot control. (3) Recovery Through Rates
1353. The Commission declines to NOPR Proposal Comments
adopt the NOPR proposal to exempt 1359. A number of commenters
1355. The Commission proposed that
RTOs from operational penalties for express support for a fee for duplicative
a transmission provider cannot recover
completing studies on an untimely requests.814 CREPC believes that queue
for ratemaking purposes any operational
basis. We agree with those commenters
penalty it pays for failing to process blocking behavior should be
that argue that RTO independence does
transmission service studies on a timely discouraged so that legitimate requests
not guarantee RTO competence or
basis. lower in the queue are not
compliance in every instance and that
disadvantaged. MISO believes the
RTOs may fail to complete studies on a Comments transmission provider should be
timely basis due to competing internal 1356. CREPC noted that, while it may allowed to charge a fee that is small
priorities or staffing issues. Imposing be reasonable for an investor-owned enough to not create a barrier to entry
penalties for failure to comply with the utility to pay penalties without being yet high enough to ‘‘add up’’ for anyone
due diligence timeframe for completing allowed to recover the penalties in rates, wishing to flood the queue. MISO and
studies will provide RTOs an this approach will be problematic for Seattle suggest that the fee be based on
appropriate incentive to comply with utilities that do not have shareholders. the transmission provider’s cost to
the pro forma OATT requirements and
review a request and handle the initial
ensure that they devote adequate Commission Determination
processing. MISO also believes the
resources to tariff compliance. Finally, 1357. We will prohibit all transmission provider should be able to
we note that subjecting RTOs to jurisdictional transmission providers charge a fixed dollar amount for any
operational penalties for late studies is from recovering penalties for late accepted requests that the customer
consistent with the Commission’s studies from transmission customers. wants to retract. Southern suggests that
decision to subject RTOs and ISOs to We believe that all entities the Commission consider a procedure
penalties for failure to meet reliability administering the tariff should operate whereby transmission customers place a
standards.813 We believe that all under the same rules, reporting deposit with transmission providers to
transmission providers, including RTOs, obligations, and performance metrics in cover a certain number of requests that
should operate under the same rules, the pro forma OATT. Non-profit is forfeited once the requests reach a
reporting obligations, and performance transmission providers have other certain threshold and are deemed self-
metrics in the OATT. We will sources of money to pay penalties competing. TranServ suggests that the
nonetheless keep in mind the nature of beyond the revenue they collect for fee apply to requests for long-term firm
an RTO’s operations and the RTO’s sales of transmission service. Therefore, transmission service and be based on
813 Rules Concerning Certification of the Electric
we require non-profit transmission duration of the request and not capacity
Reliability Organization; and Procedures for the
providers to pay operational penalties requested as an incentive to the
Establishment, Approval, and Enforcement of for late studies from their other sources transmission customer to submit fewer
sroberts on PROD1PC70 with RULES

Electric Reliability Standards, Order No. 672–A, 71 of money. This notwithstanding, we combined requests where possible.
FR 19814 (Apr. 18, 2006), FERC Stats. & Regs. may consider factors such as an entity’s TranServ suggests this fee could be
¶ 31,212 at P 56 (2006) (‘‘It is not arbitrary and
capricious to treat all operators alike, including
financial ability to absorb a penalty in
RTOs and ISOs, in terms of their liability for determining whether to impose 814 E.g., MidAmerican, MISO, Seattle, Southern,

violation of a Reliability Standard.’’). penalties in the first instance. TranServ, TAPS, and CREPC.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00178 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12443

waived if the service request is Santa Clara disagrees with Powerex. customer retracts or withdraws a
submitted pre-confirmed. Santa Clara urges the Commission to request, the transmission provider is
1360. Most of the transmission examine the practice of queue hoarding allowed to deduct from the transmission
customers and some transmission and punish those entities that are acting customer’s deposit the costs the
providers oppose the creation of a fee in an anticompetitive and manipulative transmission provider incurred to
structure for duplicative requests for manner. Further, Santa Clara urges the process the request. As a result, we do
transmission service.815 Several Commission to refrain from being too not believe any other fee structure is
commenters argue that the Commission specific in its ruling, as a more general necessary to make the transmission
should determine whether the newly- explanation of the behavior to be provider whole when a transmission
adopted NAESB business practices and avoided would go a long way in customer submits a transmission service
other reforms proposed in the NOPR can preventing entities from making an end- request it does not expect to confirm.
reduce the number of requests that the run around a ruling against queue 1366. A transmission provider that
transmission customer does not intend hoarding. continues to experience problems
to confirm.816 Nevada Companies and 1364. MidAmerican believes that if a related to submission of multiple
Great Northern assert that the current fee is imposed, the fee should not be duplicative requests for transmission
deposit requirement serves to refunded as the administrative costs and service is free to file a tariff modification
discourage multiple self-competing difficulty of administering the refunds that includes a fee to combat the
requests. Constellation asserts that the would be an unreasonable burden on problem. This filing should explain why
Commission should focus on narrowly- the transmission provider. CREPC the transmission provider is unable to
tailored penalties to deter market believes refunding or crediting the handle the submission of multiple
participants from intentionally jamming processing fee would defeat the purpose duplicative requests for transmission
the queue. of having one in the first place, although service through NAESB’s queue
1361. Several commenters suggest the processing fee could be refunded if hoarding and queue flooding business
that a transmission provider that makes the duplicative service request attached practices.
a showing that it is experiencing a to it actually comes to fruition. Suez
(5) Clustering Transmission Service
significant problem with respect to Energy NA suggests that the processing
Request Studies
customers’ submission of multiple fee be refunded whenever the
transmission provider exceeds the 60- NOPR Proposal
competing requests should be allowed
to propose a fee to combat the day request study due diligence 1367. In the NOPR, the Commission
problem.817 MISO notes that the deadline. TAPS suggests that the fee be sought comment regarding whether a
Commission has rejected a fee for structured to provide for exceptions transmission provider should be
unconfirmed requests in the past.818 where the failure to confirm reflects a required to study requests for
1362. TAPS believes the fee revenue legitimate purpose, not jamming. TAPS transmission service in a group if the
should be shared with network cites as examples transmission requests transmission provider fails to complete
customers on a load-ratio share basis. associated with requests for proposals, studies on a timely basis. If so, the
TAPS also suggests that the fee apply to alternative sites for planned generation, Commission sought comment on the
the transmission provider’s merchant and the inability to secure timely circumstances that should trigger such a
arm in a meaningful way. confirmation of all legs of a multi- requirement and the appropriate
system path. TAPS notes that the method of implementing the
1363. CREPC urges the Commission to
current pro forma OATT accommodates requirement. The Commission sought
adopt a simple, straightforward standard
multiple submissions in relation to the further comment regarding whether
for determining duplicative requests,
same competitive solicitation in transmission providers should be
such as the same points of receipt and
sections 19.2(ii) and 32.2(ii). required to study requests for
delivery, same source and sink, same
time frame, and same firmness, as well Commission Determination transmission service in a group if all the
as the same project at multiple transmission customers in the group
1365. The Commission will not agree to cluster their requests. Finally,
locations. Powerex recommends that the require transmission providers to charge
Commission be very specific in the Commission sought comment
a fee for duplicative requests for regarding how to select the requests that
describing the types of multiple transmission service. We will instead
transmission requests it believes to be a belong to a cluster so that transmission
first consider whether the newly customers cannot ‘‘cherry-pick’’ clusters
problem and the fee structure that adopted NAESB queue flooding and
would be applied to such problematic to avoid transmission system upgrade
queue hoarding business practices costs.
requests. For example, Powerex believes reduce the number of requests that the
the Commission should clarify that transmission customer does not intend Comments
requests subject to the fee must be to confirm. We are concerned that 1368. A few commenters, primarily
multiple, not pre-confirmed, and with benefits to market participants would transmission customers, believe
identical quantity, point of receipt, not justify the administrative costs of a transmission providers should be
point of delivery, start time, end time, new fee if the NAESB business practices required to study requests for
and firmness. In its reply comments, can effectively discourage transmission transmission service in a group.819
service requests the transmission CREPC believes transmission providers
815 E.g., EEI, Nevada Companies, Powerex, and
customer does not intend to confirm. should have the discretion to develop
Suez Energy NA.
816 E.g., EEI, Powerex, Suez Energy NA, and We also believe that the current deposit the criteria for clustering so that
Entegra. mechanism in section 17.3 of the pro transmission customers do not have the
817 E.g., EEI and TAPS. forma OATT should have the same opportunity to ‘‘cherry pick’’ study
sroberts on PROD1PC70 with RULES

818 See Midwest Independent Transmission effect as a fee based on the transmission clusters. If transmission providers are
System Operator, Inc., 97 FERC ¶ 61,269 (2001) provider’s cost to process the request for required to study requests in a group,
(rejecting a proposal to include a fee for non-
confirmed transmission service requests for firm
transmission service, like the fee MISO Powerex believes customers should be
point-to-point transmission service of one week or and CREPC propose. Pursuant to section
longer). 17.3, in the event a transmission 819 E.g., CREPC, Powerex, and Suez Energy NA.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00179 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12444 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

given the option of paying the transmission provider to include, to the should permit coordination and
transmission provider to perform an extent it is consistent with good utility implementation of these requirements
individual study. Suez Energy NA practice, the potential counterflows by a third party such as wesTTrans.net
believes studying requests that are created by the clustered requests. We do and sub-regional planning
clustered voluntarily will partially not agree, as suggested by commenters, organizations. At a minimum, these
incorporate the value of counterflows in that clustering necessarily leads to one commenters ask the Commission to
the study process. PGP believes set of transmission customers develop business practices to protect a
transmission customers should have the subsidizing another set of transmission transmission customer caught between
opportunity to join a cluster, but only if customers. two systems with uncoordinated
the customer is bound to accept the 1371. We therefore require each deadlines.
study results. transmission provider to include tariff
1369. A number of commenters, language in its compliance filing that 1374. Exelon states that the
primarily transmission providers, state describes how it will process a request Commission should require all
that transmission providers should be to cluster request studies and how it transmission providers to allow
allowed, but not required, to study will structure the transmission transmission customers to link
requests for transmission service in a customers’ obligations when they have consecutive requests for service (e.g.,
group.820 Bonneville argues that the joined a cluster. We will give the monthly firm service requests for
transmission provider is in the best transmission provider discretion to December, January and February) and to
position to determine whether requests determine whether a transmission evaluate such request as a single
should be studied individually or in customer can opt out of a cluster and request. Exelon argues that this service,
groups. EEI asserts that clustering does request an individual study. We are which is currently provided by some
not necessarily ensure timely giving each transmission provider transmission providers, would increase
completion of transmission studies. discretion to develop the clustering uniformity and use of the transmission
FirstEnergy believes each transmission procedures it will use because we system, and enhance competitiveness
service request should stand on its own believe the transmission provider is in without burdening transmission
merits and be directly assigned costs the best position to determine the providers or adding administrative
associated with its own request so that clustering procedures that it can complexity.
requests in one part of the request queue accommodate. We also believe that the 1375. TDU Systems indicate that
do not end up subsidizing requests in transmission provider is in the best several of its members have experienced
another part of the request queue. MISO position to develop a clustering difficulty related to the lack of
believes giving the transmission procedure that prevents a transmission standardized business practices,
provider discretion to cluster requests customer from strategically selecting the particularly in practices related to
will address the Commission’s concerns clusters in which it participates in an timing, application requirements, and
with respect to transmission customers attempt to avoid responsibility for requirements relating to methods of
cherry-picking clusters to avoid paying needed transmission system upgrades. proving that a network customer has
upgrade costs. Arkansas Commission (6) Standardization of Business executed a power purchase agreement
and East Texas Cooperatives suggest Practices for Study Queue Processing prior to designating the power purchase
that the Commission allow clustering agreement as a network resource.
through an open season procedure NOPR Proposal
1376. PNM–TNMP does not believe
similar to the procedure SPP currently 1372. In the NOPR, the Commission that additional clarity or business
uses pursuant to Attachment Z of SPP’s sought comment on whether additional practices are necessary beyond those
OATT. standardization of request queue
already provided in Order No. 676.
Commission Determination processing is necessary. If so, the
However, to the extent additional issues
Commission sought comment on the
1370. The Commission will not arise, PNM–TNMP believes NAESB’s
specific issues commenters believe are
require transmission providers to study WEQ forum is the appropriate place to
not clearly prescribed in Order No. 676
transmission requests in a cluster, address them. Similarly, NorthWestern
or the NOPR and that require additional
although we encourage transmission recommends that transmission
mandatory queue processing business
providers to cluster request studies providers work together within regional
practices.
when it is reasonable. We do, however, groups to develop a common set of
require transmission providers to Comments business practices that will be followed
consider clustering studies if the 1373. Several commenters identified by all transmission providers within
customers involved request the cluster issues where a transmission customer each region, instead of the Commission
and the transmission provider can needs coordinated responses across using the NOPR comments it receives to
reasonably accommodate the request. several transmission systems in order to develop a prescriptive set of business
We believe clustering request studies serve its load.821 Seattle and NRECA practices by which all transmission
offers potential benefits as the needed suggest that the Commission amend the providers must abide. In its reply
transmission upgrades are frequently pro forma OATT so that a customer’s comments, Powerex argues that either
large enough that the upgrade can applications for service across multiple the entire transmission process has to be
accommodate more than one systems that are intended to serve a integrated via an RTO, or coordination
transmission service request. In single sink from an identified resource of requests across multiple control areas
addition, jointly modeling transmission will be considered a single application has to be done transmission provider by
service requests can allow the for purposes of establishing the transmission provider. Powerex suggests
transmission provider to more deadlines for rendering an agreement for that NorthWestern’s suggestion for
sroberts on PROD1PC70 with RULES

efficiently design transmission system service, revising queue status, eliciting regional development of business
upgrades. Clustering also allows the deposits and finally commencing practices may be a more pragmatic
service. Seattle believes the Commission approach to address concerns about
820 E.g., Bonneville, EEI, MISO, Nevada coordination of requests across multiple
Companies, Southern, Entegra, and PNM–TNMP. 821 E.g., NRECA, TDU Systems, and Seattle. systems.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00180 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12445

Commission Determination required to take the same quantity of suggests that confirmation time periods
1377. The Commission agrees that service across consecutive transmission be shortened for short-term firm point-
transmission requests across multiple service requests, it should simply have to-point service requests to discourage
transmission systems should be the option to do so. On the second issue, behaviors that have the effect of
coordinated by the relevant we reiterate that, according to existing delaying queue processing. In its reply
transmission providers. We will not, NAESB business practice standard 001– comments, Powerex asserts that
however, amend the pro forma OATT to 4.16, the transmission provider is requiring transmission provider
require such coordination. Rather, we required to consider the full duration of responses to be based on posted ATC, as
require transmission providers working the linked requests when determining well as increasing standardization in
through NAESB to develop business reservation priority pursuant to section transmission provider response time for
practice standards related to 13.2 of the pro forma OATT. short-term transmission requests, would
coordination of requests across multiple 1379. We believe most of the enhance a transmission customer’s
transmission systems. In order to standardization issues TDU Systems ability to manage multiple transmission
provide guidance to NAESB, we will raise (application requirements, provider requests within the context of
articulate the principles that should requirements relating to methods of the pro forma tariff.
proving that a network customer has 1382. Occidental suggests in reply
govern processing across multiple
executed a power purchase agreement that the Commission should introduce
systems. All the transmission providers
prior to designating the power purchase meaningful tariff-based sanctions for
involved in a request across multiple
agreement as a network resource, and unauthorized deviations from the
systems should consider a request that
timing) have been addressed in this standards and modeling assumptions it
requires studies across multiple systems proposes to include in Attachment C of
to be a single application for purposes Final Rule. In particular, we describe
the information a network customer is the pro forma OATT, the transmission
of establishing the deadlines for provider’s description of its ATC
rendering an agreement for service, required to provide when designating a
new network resource in section V.D.6.b calculation methodology.
revising queue status, eliciting deposits 1383. Several commenters make
and commencing service. In order to of this Final Rule. We also indicate in
section V.D.6.b that the transmission suggestions to allow the transmission
preserve the rights of other transmission provider to terminate idle transmission
customers with studies in the queue, the provider is not allowed to require a
network customer to provide contract service requests. TDU Systems
priority for the single application recommends that the Commission
should be based on the latest priority terms and conditions when it designates
a power purchase agreement as a provide a sunset date by which all
across the transmission providers requests not pursued by the
involved in the multiple system request. network resource. The network
customer is required to provide a transmission customer would be
We note that regional entities like terminated. MidAmerican and
wesTTrans are already coordinating statement that attests, among other
things, that it has executed a power Northwest IOUs ask the Commission to
requests across multiple transmission clarify in the Final Rule that the
systems and we believe such purchase agreement prior to confirming
its request to designate a new network transmission provider may deem a
coordination is an acceptable solution to transmission service application
this issue. resource. We will continue to give
transmission providers discretion in withdrawn and terminated if a customer
1378. We interpret Exelon’s request revises its application or if such
that we require all transmission determining whether to impose
restrictions on the earliest time at which customer fails to timely pay the annual
providers to allow transmission reservation fee pursuant to section 17.7
customers to link consecutive requests it will accept a request for transmission
service. We believe the transmission of the pro forma OATT.
for firm point-to-point transmission 1384. Constellation asks the
service and to evaluate such requests as provider is in the best position to
Commission to require transmission
a single request as asking us to (1) allow determine whether it needs to restrict
providers to release study results as
transmission customers to require the the time at which it will accept requests
soon as a study is completed, rather
transmission provider to either grant for transmission service in order to
than holding them until the end of the
service for the entire period, deny process transmission service requests in
60 days.
service for the entire period, or offer the an orderly fashion consistent with the 1385. NorthWestern believes an
same partial quantity for the entire requirements in the pro forma OATT. appropriate modification to the study
period and (2) require the transmission (7) Additional Processing Proposals process would be to allow the
provider to consider the full duration of transmission provider to have an
the linked requests when determining Comments
opportunity to verify and correct the
reservation priority pursuant to sections 1380. A number of commenters system impact study results at the
13.2 of the pro forma OATT (short-term propose changes to queue processing beginning of the facilities study and
firm point-to-point transmission requirements that were not addressed in again before construction begins.
service). We require transmission the NOPR. 1386. With the exception of very
providers working through NAESB to 1381. Powerex believes that OASIS short-term transmission service (for
develop business practice standards to practices should be modified to ensure which a bid-based system is impractical
allow a transmission customer to rebid that short-term firm and non-firm point- to manage), LDWP suggests that the
a counteroffer of partial service so the to-point service requests are processed queue process be transformed into a
transmission customer is allowed to based on the ATC posted at the time the competitive process in which awards of
take the same quantity of service across requests were queued. Powerex argues transmission service are allocated in a
all linked transmission service requests. that a transmission provider should not manner similar to the provisions in
sroberts on PROD1PC70 with RULES

Transmission providers need not be permitted to grant transmission section 4.4 of Order No. 638.
implement these business practice service requests at a time when its 1387. TranServ notes that OASIS
standards until NAESB develops OASIS indicates there is no ATC. In its standards allow the customer to turn a
appropriate standards. We note that the view, any such requests should be request into a pre-confirmed request,
transmission customer should not be automatically denied. Powerex also but not vice versa. If the Commission’s

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00181 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12446 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

proposal on granting priority to pre- 001–4.11 allows the transmission (2) transform the queue process into
confirmed requests is adopted, TranServ provider to retract a request if the competitive process, (3) shorten the
believes this capability should be transmission customer does not respond confirmation time periods for short-term
removed from OASIS as it would seem to an acceptance within the time firm point-to-point service requests and
to invite gaming and confuse established in NAESB business practice (4) introduce penalties when the
transmission providers attempting to standard 001–4.13. Therefore, we transmission provider deviates from the
process requests in proper queue order. interpret TDU Systems comments to ATC calculation procedures detailed in
1388. PGP states that OASIS platforms refer to circumstances when a Attachment C of the pro forma OATT.
should be accessible from different transmission customer fails to respond We believe the pro forma tariff is just
computer platforms using a variety of to the transmission provider’s request and reasonable without such
browsers, not just one operating system/ for additional information during the modifications and the commenters have
browser combination (Windows/ course of a request study. As discussed not demonstrated that reforms in these
Explorer), which is currently the case. above, by the time the transmission areas are required at this time to prevent
Commission Determination provider offers a system impact study the exercise of undue discrimination.
agreement, it should have all of the
1389. We will not adopt Powerex’s information that it needs to complete b. Reservation Priority
proposal to require the transmission the study. Pursuant to section 17.4 of
provider to accept or deny in all cases the pro forma OATT, the transmission 1394. Section 13.2 of the pro forma
non-firm and short-term firm point-to- provider can deem a transmission OATT requires transmission providers
point transmission service requests service request deficient if the to process requests for long-term firm
solely based on posted ATC. The issue transmission customer does not provide point-to-point service on a first-come,
Powerex raises is ultimately a question all of the information the transmission first-served basis and to process requests
of how the transmission provider is provider needs to evaluate the request for short-term firm point-to-point
going to exercise its discretion under the for service. We will revise section 17.7 service on a first-come, first-served basis
tariff. Under the pro forma OATT, the of the pro forma OATT so that the conditional on the duration of the
transmission provider can use its transmission provider is able to request. Section 14.2 of the pro forma
knowledge of the system to exercise its terminate a request for transmission OATT requires transmission providers
discretion to offer transmission service service if a transmission customer that to process requests for non-firm point-
even if posted ATC is not sufficient to is extending the commencement of to-point service on a first-come, first-
accommodate the requested service. service does not pay the required annual served basis conditional on the duration
Alternatively, the transmission provider reservation fee within 15 days of of the request to the extent transmission
can use its discretion to update posted notifying the transmission provider that capacity beyond that needed by native
ATC in response to a transmission it would like to extend the load customers, network customers and
customer’s verbal request to update commencement of service. We will not firm point-to-point transmission
ATC.822 In both situations, the change the pro forma OATT to allow the customers is available. In the NOPR, the
transmission provider may provide transmission provider to terminate a Commission made a number of
transmission service in instances when transmission service request if the proposals and requested comment
posted ATC is not sufficient to transmission customer changes its regarding various aspects of the
accommodate a transmission service application for service. We believe the reservation priority rules.
request at the time the transmission existing pro forma OATT is sufficient to
customer requests service. We do not allow a transmission provider to manage (1) Priority for Pre-confirmed Requests
wish to discourage transmission situations where the transmission NOPR Proposal
providers from making transmission customer modifies its application for
service available at times when posted service to the point that the customer is 1395. In the NOPR, the Commission
ATC is not accurate. Therefore, we will requesting transmission service that is proposed to change the priority rules to
continue to allow the transmission meaningfully different than its initial give priority to pre-confirmed requests
provider to accept transmission service request. for firm point-to-point transmission
requests in instances when posted ATC 1391. We clarify that sections 19.3 service. Specifically, the Commission
is not sufficient but the transmission and 32.3 of the pro forma OATT require proposed that a pre-confirmed short-
provider believes it can accommodate the transmission provider to release term request for firm transmission
the service. The transmission provider study results as soon as a study is service would preempt any non-pre-
must use its discretion to grant service completed, rather than holding them confirmed short-term requests,
when posted ATC is not sufficient on a until the end of the 60 days. regardless of duration. Similarly, the
non-discriminatory basis. In order to 1392. Commenters also suggest Commission proposed that a pre-
ensure that it does so, we expect the changes to the OASIS protocols, confirmed request for long-term firm
transmission provider to log such including prohibiting transmission transmission service would preempt a
instances as an act of discretion and customers from changing a request into request for long-term transmission
post the log as required in section a pre-confirmed request and requiring service that is not pre-confirmed. Under
37.6(g)(4) of the Commission’s OASIS platforms to be accessible on the Commission’s proposal, a pre-
regulations.823 non-Windows/Explorer computers. We confirmed request for short-term
1390. We will not modify the pro believe these issues are best addressed transmission service would not pre-
forma OATT to address requests to by NAESB. empt a non-pre-confirmed request for
allow the transmission provider to 1393. Commenters proposed a
long-term transmission service.
terminate idle transmission service number of additional modifications to
sroberts on PROD1PC70 with RULES

requests. NAESB’s business practice the pro forma OATT that we do not Comments
believe are necessary. These proposals
822 See, e.g., Florida Power Corp., 111 FERC ¶ would (1) allow the transmission 1396. A number of commenters
61,243 at P 5 (2005). provider to verify and correct studies generally support the Commission’s
823 18 CFR 37.6(g)(4). between each step in the study process, proposal to give priority to pre-

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00182 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12447

confirmed requests.824 Commenters who withdraw a pre-confirmed request for include a time window between
support the proposal note that giving transmission service at any time prior to acceptance of a request and
reservation priority to pre-confirmed acceptance by a transmission provider. confirmation of the request, during
requests for transmission service could Opponents also argue that giving which a request can not be preempted
help alleviate the problems that arise priority to pre-confirmed requests by a pre-confirmed request for
when a transmission customer submits would disrupt the study process.830 transmission service.
multiple identical requests for service This disruption would occur when a
with no intention of confirming all transmission provider receives a pre- Commission Determination
accepted requests.825 Supporters of the confirmed request for transmission 1401. The Commission generally
proposal also note that the proposal service while it is actively studying a agrees with those commenters that argue
would allow the transmission provider request for service that has not been pre- that giving a priority to pre-confirmed
to focus its attention on those requests confirmed. Under these circumstances, requests can increase the efficient
that appear most likely to result in an the transmission provider would be utilization of the system by giving
actual reservation of transmission required to suspend the study of one priority to customers who are
service.826 Although Nevada Companies request in order to study a request with committed to purchase service over
do not oppose the proposal, they note a higher reservation priority. In its reply those who have not so committed,
that concerns regarding withdrawal of comments, Indianapolis Power asks the including customers that submit
pre-confirmed requests might otherwise Commission to clarify if this multiple requests without any intent to
be alleviated by requiring a non- interpretation of the NOPR proposal is take service if each request is granted.
refundable deposit on requests. accurate. TranServ, suggesting that the However, we are mindful of concerns
1397. Several commenters suggest Commission has not proposed to give a that doing so could undermine the
that establishing reservation priority priority to pre-confirmed requests for Commission’s desire to promote longer-
first based on pre-confirmation status non-firm transmission service, asserts term uses of the transmission system,
and then based on duration would that having different priority rules for disrupt the study process, or
ultimately result in transmission firm and non-firm transmission service disadvantage transmission customers
customers with relatively shorter term introduces unnecessary complexity. that are not in the position to pre-
requests getting transmission service Finally, Southern believes that a pre- confirm their requests. As a result, we
instead of transmission customers with confirmed service request submitted will modify the NOPR proposal and give
relatively longer term requests.827 EEI within close proximity to the actual priority only to pre-confirmed non-firm
asserts that this result would be commencement of service should not point-to-point transmission service
inconsistent with the Commission’s preempt an existing non-pre-confirmed requests and short-term firm point-to-
desire to promote longer-term uses of request, if doing so would be disruptive point transmission service requests. In
the transmission system. Several to the operations of the transmission addition, longer duration requests for
transmission providers suggest that the provider or to the reliability of the transmission service will continue to
Commission modify its proposal to system itself. have priority over shorter duration
ensure that longer duration requests 1399. Opponents also argue that requests for transmission service, with
continue to have a priority over shorter giving a priority to pre-confirmed pre-confirmation serving as a tie-breaker
duration requests.828 EEI suggests that requests would unfairly disadvantage for requests of equal duration. This
the Commission should use pre- transmission customers who are not in policy will still give an advantage to
confirmation as a tie-breaker for short- a position to pre-confirm their requests, pre-confirmed requests without
term requests for transmission service such as those requesting service in imposing substantial implementation
with the same duration. Southern argues response to a request for proposals.831 difficulties or undermining the
further that a pre-confirmed daily or EEI notes that the Commission Commission’s goals to encourage longer-
hourly request should not preempt a addressed this issue when it issued term uses of the transmission system.
weekly request that has not been pre- Order No. 638 and decided that giving
Our revised policy on priority for pre-
confirmed. priority to pre-confirmed requests
confirmed requests thus addresses the
1398. Opponents of the proposal would disadvantage customers who are
identify a number of operational comments that we should preserve the
requesting service from multiple
difficulties in implementing a system priority of longer duration requests for
transmission providers.832 In the event
that gives priority to pre-confirmed transmission service over shorter
the Commission decides to proceed
requests. Several commenters note that duration requests for transmission
with its proposal, TAPS suggests that
transmission customers are not bound to service. For instance, a pre-confirmed
the Commission limit the priority for
take service because they pre-confirm a daily or hourly request will not preempt
pre-confirmed requests to non-firm and
request for transmission service.829 a weekly request that has not been pre-
short-term firm requests for
They argue, for instance, a transmission confirmed. Pre-confirmed short-term
transmission service.
customer is not bound to take service in 1400. Several commenters question service requests therefore will not have
the event the transmission provider whether a request that has been a priority superior to that of long-term
offers a study or counteroffers the accepted but not confirmed would be service requests that have not been pre-
request with a partial quantity of pre-empted by a new pre-confirmed confirmed.
service. Similarly, MidAmerican notes request.833 In a similar vein, TDU 1402. We acknowledge that our
that a transmission customer may Systems suggests that the Commission revised policy on priority for pre-
confirmed requests may be less effective
824 E.g., Nevada Companies, Seattle, LDWP, PGP, 830 E.g., Bonneville, EEI, and MidAmerican. than the NOPR proposal in alleviating
PNM–TNMP, Salt River, and Suez Energy NA. 831 E.g., EEI, MISO, TAPS, Constellation, and the problems that arise when
sroberts on PROD1PC70 with RULES

825 E.g., Ameren, Santa Clara, Entegra, Entergy,


TDU Systems. transmission customers submit multiple
and TVA.
826 E.g., Ameren and NorthWestern.
832 Open Access Same-Time Information System
identical requests for service. However,
and Standards of Conduct, Order No. 638, 65 FR we have taken other steps—notably
827 E.g., CREPC and EEI.
17370, FERC Stats. & Regs., ¶ 1996–2000 ¶ 31,093
828 E.g., Entergy, Southern, and NorthWestern. at 31,439 (2000). accepting the NAESB business practices
829 E.g., Bonneville and EEI. 833 E.g., MidAmerican and TranServ. on queue flooding and queue

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00183 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12448 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

hoarding 834—that we believe will effects of the priority for pre-confirmed another transmission customer that is
substantially reduce the instances of requests will be resolved prior to the willing to commit to take the same
multiple identical requests for service. time when the transmission provider service. Moreover, this policy is
1403. The Commission also would require an accepted request to be consistent with NAESB business
acknowledges the concerns expressed confirmed. Handling priority for pre- standard 001–4.25, which allows a pre-
regarding operational difficulties caused confirmed requests should be no more confirmed request for non-firm point-to-
by giving priority to pre-confirmed disruptive than giving a transmission point transmission service to preempt a
requests and clarify our policy as customer time to confirm an accepted request of equal duration and lower
follows. First, we will prohibit request. price that has been accepted but not
transmission customers from 1406. Excluding long-term requests confirmed.835
withdrawing pre-confirmed non-firm for transmission service will mitigate
and short-term firm point-to-point many of the concerns expressed by (2) Price as a Tie-Breaker
transmission service requests prior to commenters who argued that giving a NOPR Proposal
when the transmission customer is priority to pre-confirmed requests will 1408. The NOPR also proposed to add
offered service or a system impact unfairly disadvantage transmission price as a tie-breaker in determining
study. This policy will address customers who are requesting service in reservation queue priority when the
MidAmerican’s concern that a response to a request for proposals and transmission provider is willing to
transmission customer may withdraw a are therefore not in a position to pre- discount transmission service. Under
pre-confirmed request for transmission confirm their requests. Such requests for the Commission’s proposal, price would
service at any time prior to acceptance proposals typically involve long-term serve as a tie-breaker after pre-
by a transmission provider. We believe contracts for energy and/or generating confirmation for those requests that are
prohibiting withdrawal of a pre- capacity and, therefore, would be linked not yet confirmed.
confirmed request is less most likely to long-term transmission
administratively burdensome than the service requests. We disagree, however, Comments
non-refundable deposit on requests with EEI’s characterization of the 1409. All of the commenters who
proposed by Nevada Companies and Commission’s decision in Order No. 638 address the Commission’s proposal to
achieves the same goals. The to give a priority to pre-confirmed add price as a tie-breaker support the
Commission will allow transmission requests for non-firm service only if the proposal, although some request that it
providers to invalidate a pre-confirmed request offers a higher price. The be modified or clarified. Several
request at the request of the Commission’s decision in that commenters ask the Commission to
transmission customer in the very near proceeding was driven by its clarify that an otherwise higher queued
term following submittal of the request, interpretation that the proposed request has a right to match the price
in the event the transmission customer business practice addressed in the part offer of a request with a higher price.836
makes an inadvertent error in of Order No. 638 cited by Southern was With regard to short-term service,
submitting its request. We expect the not consistent with the relevant section WAPA believes that the Commission’s
transmission provider to log such of the pro forma tariff. In addition, the proposal to add price as a tie-breaker
occurrences as an act of discretion so we Commission’s experience since Order would overly complicate matters after
can verify that transmission customers No. 638 and the comments received to taking into account the many complex
are not abusing this flexibility. the NOPR proposal indicate the value of timing restrictions on short-term
1404. Second, while the Commission giving a priority to pre-confirmed service. As a result, WAPA proposes
recognizes that a customer submitting a requests, despite concerns that some that the Commission limit application of
pre-confirmed request is not bound to transmission customers are not in a its proposal to requests for long-term
take service when the transmission position to pre-confirm their requests transmission service. MISO/PJM States
provider counteroffers the transmission for transmission service. suggest that the Commission consider
customer’s initial request, we do not 1407. In response to requests for requiring point-to-point transmission
believe this fact alone warrants clarification from MidAmerican and customers to offer a reservation price at
reversing our proposal to give a priority TranServ, we clarify that a new pre- which they would be willing to sell
to pre-confirmed requests. We are confirmed request for transmission their transmission service.
satisfied that a transmission customer service would preempt a request of
that pre-confirms its request is obligated equal duration that has been accepted Commission Determination
to take full service in the event the by the transmission provider but not yet 1410. The Commission adopts the
transmission provider offers the service confirmed by the transmission NOPR proposal to add price as a tie-
requested. customer. Thus, we decline to adopt breaker in determining reservation
1405. The Commission also believes TDU Systems’ suggestion that the queue priority when the transmission
the revised priority policy will address Commission include a time window provider is willing to discount
Southern’s comment that a pre- between acceptance of a request and transmission service. As a result, price
confirmed service request submitted confirmation of the request, during will serve as a tie-breaker after pre-
within close proximity to the actual which a request can not be preempted confirmation for those requests that
commencement of service should not by a pre-confirmed request for have not yet been confirmed by the
preempt an existing non-pre-confirmed transmission service. This is consistent transmission customer or have not yet
request if doing so would be disruptive with our desire to give transmission been evaluated by the transmission
to the operations of the transmission service first to those customers that are provider. Consistent with the principles
provider or to the reliability of the committed to taking the transmission currently embodied in the pro forma
system itself. A pre-confirmed request service if it is granted. In the case of OATT and articulated in Order No. 638,
sroberts on PROD1PC70 with RULES

for transmission service will not pre- monthly firm point-to-point we clarify that, in the event a later
empt an equal duration request that has transmission service, the transmission queued short-term request for
already been confirmed. Therefore, the customer has up to four days to confirm
an accepted request. This is a 835 See Order No. 676.
834 See Order No. 676 at P 19. potentially long delay when there is 836 E.g., EEI and MidAmerican.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00184 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12449

transmission service preempts a requests of equal duration, in the event conducted like a blind auction, so that
conditional confirmed short-term a five minute equivalent priority requests are not visible on OASIS until
request for transmission service based standard is adopted. the window closes.
on price, then the conditional confirmed 1416. Many of the large power
Comments
request has a right to match the price marketers and transmission providers in
offer of the later queued request.837 1414. Many of the commenters in the the East oppose the notion of a
1411. We disagree with WAPA’s West support the proposal to treat submittal window. Opponents of a time
proposal to limit application of the transmission requests submitted within window within which all requests
NOPR proposal to requests for long-term some specified period of time as would be deemed to have been
transmission service. We believe the submitted simultaneously. Supporters submitted simultaneously suggest that
addition of price as a tie-breaker for of a time window within which all the proposal is an unnecessary
discounted firm point-to-point requests would be deemed to have been complication and may actually be
transmission service is an economically submitted simultaneously argue that the counterproductive to the Commission’s
efficient policy for both short-term and proposal would give transmission ultimate goal due to issues regarding
long-term firm point-to-point customers who are less sophisticated how transmission service would be
transmission service. We recognize that and have fewer financial resources allocated among simultaneous
adding another element to the equal access to transmission service.838 requests.843 EEI notes that there is no
reservation priority criteria adds Other supporters argue that such a time limit on how far in advance a
additional complexity. However, we window would be particularly transmission customer may submit
believe that the efficiency gains warrant appropriate in circumstances when a requests for firm transmission service,
any additional complexity in the few tariff calls for requests to be submitted so the likelihood that any two requests
cases in which transmission customers ‘‘no earlier than’’ a specific deadline.839 are submitted within the same five
bid for transmission service. In its reply comments, NRECA argues minute period is low. Powerex argues
1412. We do not agree with MISO/ that a customer attempting to plan a that the simplicity of the first-come, first
PJM States’ suggestion that the request under such circumstances may served approach limits the number of
Commission require point-to-point miss being the first in time by a matter disputes. In its reply comments,
transmission customers to offer a of seconds because its computer is Powerex argues that none of the
reservation price at which they would slower than another customer’s commenters that favor a five-minute
be willing to sell their transmission computer. window addressed the operational
service. The transmission provider may 1415. Supporters of the proposal problems that such a proposal would
already make unscheduled firm suggest a number of modifications to the generate.
transmission service available to other Commission’s suggested five-minute 1417. Some commenters argue that a
customers on a non-firm basis and we window. A number of commenters pro rata allocation of simultaneous
have adopted proposals that we believe suggest a window longer than five requests of equal duration will result in
will encourage transmission customers minutes.840 For instance, Bonneville all transmission customers acquiring
to voluntarily offer to sell firm point-to- proposes a system similar to PJM’s 30 less transmission service than they need
point transmission service on the minute window for monthly service. On to complete their wholesale
secondary market as described in the other hand, Manitoba Hydro transactions.844 As a result, these
section V.C.4 of this Final Rule. As a suggests a shorter window and a limit commenters suggest that the need to
result, we see no reason to require a firm on the number and size of requests, provide transmission customers with
point-to-point customer to offer its claiming this would reduce the usable quantities of transmission service
reserved capacity for sale. potential for gaming and/or anti- will necessarily lead to developing an
competitive behavior. A number of allocation protocol in addition to
(3) Five-Minute Window for Requests commenters also suggest that such a allocating based on time submitted and
NOPR Proposal system should be limited to short-term duration of request.845 Powerex argues
transmission service 841 and/or should that any system that creates a time
1413. In the NOPR, the Commission not apply to requests for transmission
responded to comments that window within which all requests
service submitted close to the hour that would be deemed to have been
transmission customers that have the service commences.842 In its reply
financial resources to purchase software submitted simultaneously will lead
comments, PNM–TNMP asserts that, if transmission customers to inflate the
and employ staff to continually monitor the Commission implements a five-
OASIS sites have an unfair advantage quantity of service they request in order
minute window policy, then the policy to get quantity of service they actually
under a first-come, first-served approach should not be limited to long-term
by seeking comment on whether any desire. Other commenters make
transactions. In its reply comments, suggestions regarding the manner by
such advantage would be mitigated if all NRECA argues that requests submitted
requests submitted within a five-minute which transmission service should be
within a five-minute window should allocated among simultaneously
window were deemed to have been not be publicly available until the
submitted simultaneously. The submitted requests. Bonneville believes
window has closed in order to prevent that each transmission provider should
Commission also sought comment on competitors from requesting the same
whether transmission customers could develop an allocation method
service simply to disrupt the appropriate to its system. CREPC
game a five minute equivalent priority transmission service procurement
standard to request transmission service suggests that price be used as a
process. Similarly, Bonneville suggests secondary tie-breaker after duration.
only after another transmission that the reservation process should be
customer has made a request. The TDU Systems argue that using duration
sroberts on PROD1PC70 with RULES

Commission further sought comment on 838 E.g., Bonneville and Santa Clara. 843 E.g., EEI, MidAmerican, Ameren,
how to allocate limited transmission 839 E.g., TDU Systems and NRECA. Constellation, Entergy, NorthWestern, PNM-TNMP,
capacity among equivalent priority 840 E.g., Bonneville and CREPC. WAPA, Powerex, and Indianapolis Power Reply.
841 E.g., Bonneville and Nevada Companies. 844 E.g., Powerex and TranServ.
837 See Order No. 638 at 31,442. 842 E.g., Bonneville and NRECA. 845 Id.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00185 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12450 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

as a tie-breaker for simultaneous their tariffs or adopted business cannot be gamed in the manner
requests could discriminate against practices that mandate that requests can suggested by Powerex and TranServ. We
purchased power contracts that are be submitted no earlier than a specific believe that transmission providers will
designated as network resources. deadline.847 In these instances, multiple be able to develop allocation methods,
requests for transmission service can be like the method PJM uses to allocate
Commission Determination
submitted at approximately the same monthly firm point-to-point
1418. Based on the comments time. We generally agree with Powerex’s transmission service, that address the
received, it appears that the desire for a assertion that the simplicity of the operational issues Powerex and
time window within which all requests current first-come, first served approach TranServ raise.
would be deemed to have been limits the number of disputes. However,
submitted simultaneously is largely (4) Right of First Refusal and
when a transmission provider
limited to market participants in the Preemption
establishes a ‘‘no earlier than’’ deadline,
Western Interconnection. With one submittals that are received by the 1423. While not specifically
exception, we will not mandate a transmission provider within a matter of addressed in the NOPR, a few
change to our current first-come, first- seconds cannot be meaningfully commenters use the Commission’s
served policy to address an issue that differentiated. A transmission provider proposed introduction of hourly firm
appears to be regional in nature. Rather, with such a business practice or tariff service, discussed above, to argue that
we will allow transmission providers to provision will be required to modify its the Commission should take the
propose a window within which all tariff to include its proposed specified opportunity to clarify or revise the right
transmission service requests the period of time. We will evaluate each of first refusal for short-term
transmission provider receives will be proposal on a case-by-case basis, as transmission service requests.
deemed to have been submitted described below. 1424. To understand commenter
simultaneously. Transmission providers 1420. We will allow transmission concerns, it is useful to note the relevant
will have discretion to determine which providers to propose the period of time components of the reservation and
transmission services will be subject to within which all requests would be scheduling process in the pro forma
a submittal window policy. We believe deemed to have been submitted OATT. Reservations for short-term firm
the transmission provider is in the best simultaneously. We believe the point-to-point transmission service are
position to determine whether it can transmission provider is in the best available on a first-come, first-served
accommodate a submittal window for a position to identify the window it can basis and are conditional based upon
specific transmission service and the operationally accommodate. We expect the length of the requested transaction
need for such a window. the submittal window to be open for at as explained further below. If the
1419. In order to ensure that least five minutes unless the transmission system becomes
transmission service is not awarded in transmission provider can present a oversubscribed, longer-term service may
an arbitrary fashion and to ensure that compelling rationale to justify a shorter preempt shorter-term service, up to a
transmission customers who are less submittal window. specified period. The shorter-term
sophisticated and have fewer financial 1421. We agree with NRECA and reservation holder has a right of first
resources have equal access to Bonneville’s suggestion that requests refusal to match the longer-term
transmission service, we will require submitted within a specified window reservation, but such right must be
transmission provider who set a ‘‘no should not be publicly available until exercised within 24 hours of being
earlier than’’ time for request submittal the window has closed in order to notified of the competing reservation, or
to treat all transmission service requests prevent competitors from requesting the earlier to comply with the scheduling
received within a specified period of same service simply to disrupt the deadline.
time as having been received transmission service procurement Comments
simultaneously. We agree with those process.
commenters that argue that a time 1422. We will require each 1425. Salt River argues that the time
window within which all requests transmission provider that is required required to administer the right of first
would be deemed to have been to, or decides to, deem all requests refusal—which includes contacting
submitted simultaneously is particularly submitted within a specified period as customers and allowing time to exercise
appropriate in circumstances when a having been submitted simultaneously the right of first refusal—is
tariff or business practice calls for to propose a method for allocating overwhelming. Salt River argues that the
requests to be submitted no earlier than transmission capacity if sufficient current OASIS business practices do not
a specific deadline. As NRECA argues, capacity is not available to meet all permit adequate time to implement
there is no meaningful difference requests submitted within the specified these rules, and the industry lacks the
between requests for transmission time period. We agree with Bonneville software to either streamline the effort
service that are identical in all respects that the transmission provider is in the or ensure quality control. Salt River
except that one request is received by best position to determine an allocation contends that for hourly, daily, and
the transmission provider seconds that is appropriate to its system and that weekly requests, the complexity and
ahead of another request because one potentially unjust results of
customer’s computer is slower than 847 For instance, Idaho Power Company has administering preemption and the right
another customer’s computer. EEI is adopted a business practice that requests for of first refusal rules outweighs any
correct that NAESB’s uniform business monthly firm transmission service cannot be potential benefits. Accordingly, Salt
submitted earlier than 11 months prior to operation. River recommends revisions to the pro
practices do not limit how far in Portland General Electric has adopted a business
advance a transmission customer may practice that Daily Firm ATC on the California- forma OATT that make the right of first
submit requests for firm transmission Oregon Intertie will be posted at or about 7:11 a.m. refusal available only to monthly
sroberts on PROD1PC70 with RULES

service.846 However, a number of Pacific on the day prior to operation and that requests for service.
requests that are submitted prior to ATC being 1426. To address the complications
transmission providers have modified posted will be refused. SPP has modified its tariff
so that requests for monthly firm transmission
arising from preemption and the right of
846 See NAESB Business Practice Standard 001– service cannot be submitted more than 90 days first refusal, Duke proposes several
4.13. prior to the first day of operation. revisions to the pro forma OATT: only

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00186 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12451

pre-confirmed requests would trigger of the ‘‘reservation’’ references to customer can appropriately designate as
preemption; confirmed requests could ‘‘request.’’ a network resource. Section 30.1 of the
not be displaced by longer-term pro forma OATT describes network
Commission Determination
requests; only monthly customers resources as all generation owned or
subject to preemption would be given a 1429. Based on the issues raised in purchased by the network customer
right of first refusal (Salt River proposes comments, we find that changing the designated to serve network load under
a similar OATT revision); and, profiled ‘‘first come, first served’’ nature of the the tariff. Section 30.1 also indicates
requests (i.e., requests for transmission reservation process and right of first that network resources may not include
that may have different MW values for refusal process is not warranted at this resources that are committed for sale to
each hour of the day, and may even time. The ‘‘first-come, first-served’’ non-designated third-party load or
include some hours where the MW principle facilitates the administration otherwise cannot be called upon to meet
value is zero) would not be granted of the reservation process and benefits the network customer’s network load on
priority over confirmed reservations. customers because there can be little a noninterruptible basis. Pursuant to
TranServ also asks the Commission to confusion about how to comply with it. section 30.7 of the pro forma OATT, the
provide guidance establishing the 1430. The remaining concerns network customer must demonstrate
earliest and latest submission times and regarding administering the right of first that it owns or has committed to
maximum successive or consecutive refusal are addressed below. First, when purchase generation pursuant to an
terms of service required. TranServ a longer-term request seeks capacity executed contract in order to designate
contends it is unreasonable that a allocated to multiple shorter-term a generating resource as a network
request for daily firm service could be requests, the shorter-term customers resource. Alternatively, the network
submitted years in advance and then should have simultaneous opportunities customer may establish that execution
have a right of first refusal to match any to exercise the right of first refusal. of a contract is contingent upon the
longer-term request for service. Duration, pre-confirmation status, price, availability of network service. Section
1427. To eliminate the potential for and time of response would then be 29.2 requires the network customer to
more complexity, TranServ requests that used to determine which of the shorter- provide the following information about
the Commission eliminate the term requests will be able to exercise the a power purchase agreement that is to
conditional nature of short-term point- right of first refusal, consistent with the serve as a new designated network
to-point service under the OATT. Commission’s tie breaking provision in resource: source of supply, control area
Whether the Commission adopts this section 13.2(ii). Second, to minimize the location, transmission arrangements and
recommendation, TranServ further potential for gaming, a preempting delivery point(s) to the transmission
recommends that the Commission revise longer request must be for a fixed provider’s transmission system.
the timing provisions for requesting capacity over the term of the request. 1433. As the Commission noted in the
short-term point-to-point service to 1431. We agree with NorthWestern’s NOPR, a number of orders address what
reduce overlap for submission of assertion that the sentence in section types of resources meet the criteria set
requests that would trigger the need for 13.2(iii) of the pro forma OATT that out in sections 30.1 and 30.7 of the pro
preemption. TranServ and Duke includes the two uses of ‘‘reservation’’ forma OATT. In MSCG, the Commission
recommend a reservation or bidding creates confusion. Therefore, we clarify stated that network resources must be
process in which one increment of that the terms ‘‘reservation’’ and generating resources owned by the
service (monthly, weekly, daily, and ‘‘request’’ are not used interchangeably;
hourly) is available at a time, with each network customer or purchases of
‘‘reservation’’ is meant to be a confirmed noninterruptible power under executed
successive shorter increment of service request, while ‘‘request’’ is a queued
becoming available after the reservation contracts that require the network
request that has not been confirmed. To customer to pay for the purchase.848 In
or bidding window for the preceding clarify the distinction between use of
longer increment has closed. WPPI, the Commission found that a
the terms ‘‘request’’ and ‘‘reservation’’ network customer can designate as a
1428. NorthWestern requests that the
in section 13.2(iii), we will revise that network resource a system purchase that
Commission clarify whether the terms
section so that the sentence ‘‘Before the is not backed by a specific generator.849
‘‘reservation’’ and ‘‘request’’ used in
conditional reservation deadline, if The Commission found that Wisconsin
section 13.2 (Reservation Priority) are
available transfer capability is Public Service Corporation (WPS) had
used interchangeably. If they are not
insufficient to satisfy all Applications, appropriately designated a power
used interchangeably, and ‘‘reservation’’
an Eligible Customer with a reservation purchase as a network resource, even
is meant to be a confirmed request,
for shorter-term service has the right of though the power purchase agreement
while ‘‘request’’ is a queued request that
has not been confirmed, NorthWestern first refusal to match any longer-term did not require WPS to take energy
suggests that the sentence that includes reservation before losing its reservation around the clock and allowed WPS to
the two uses of ‘‘reservation’’ creates priority’’ is replaced by the sentence convert its energy purchase to a
confusion because, if both requests are ‘‘Before the conditional reservation discounted product that could be
confirmed, then either sufficient deadline, if available transfer capability interrupted.850 In addition, the
capacity exists to accept both requests, is insufficient to satisfy all Applications, Commission stated that, because the pro
or the transmission provider accepted an Eligible Customer with a reservation forma OATT requires a power purchase
requests that exceed the ATC. To avoid for shorter-term service has the right of to be noninterruptible, third-party
confusion, then NorthWestern first refusal to match any longer-term transmission arrangements to deliver
recommends that the second use of request before losing its reservation the resource to the network have to be
‘‘reservation’’ should be changed to priority.’’
‘‘request.’’ If so, to avoid the suggestion 6. Designation of Network Resources 848 Morgan Stanley Capital Group v. Illinois
sroberts on PROD1PC70 with RULES

that the section is attempting to Power Co., 83 FERC ¶ 61,204 at 61,911–12 (1998),
distinguish between requests that have a. Qualification as a Network Resource order on reh’g, 93 FERC ¶ 61,081 (2000) (MSCG).
849 Wisconsin Public Power Inc. v. Wisconsin
been confirmed from those simply 1432. Taken together, the following Public Service Corp., 84 FERC ¶ 61,120 at 61,650–
queued, NorthWestern recommends that sections of the pro forma OATT 51 (1998) (WPPI).
the Commission consider changing all describe the resources a network 850 Id.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00187 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12452 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

noninterruptible as well.851 In Illinois interrupt sales under the purchase Dynegy 856 that the inclusion of an LD
Power, the Commission found that a agreement for reasons other than provision in EEI’s Master Power
firm purchase need not be backed by a reliability, but allows the buyer to force Purchase and Sale Agreement’s Firm LD
capacity purchase to qualify as a delivery at a higher price. In addition, product (EEI’s Firm LD Product) does
network resource.852 the Commission proposed that a not inherently make that product less
network customer may not designate as firm.
NOPR Proposal 1440. Several commenters argue that,
a network resource a purchase
1434. In the NOPR, the Commission agreement that requires a seller to pay when the Commission in Dynegy
proposed to maintain its current policy the buyer’s cost of replacement power considered the acceptability of EEI’s
regarding the power purchase when the seller chooses not to deliver Firm LD Product as a designated
agreements that network customers may energy for economic reasons. network resource, it neglected to
designate as network resources. In consider the presence of a provision
particular, the Commission proposed Comments Overview which appears to contradict its
that a network customer would continue decision.857 They point to the
to be able to designate resources from 1437. Most commenters argue that the Commission’s statement in Dynegy that
system purchases not linked to a Commission must provide further EEI’s Firm LD Product ‘‘does not permit
specific generating unit, provided the clarification than given in the NOPR, the power to be interrupted for
power purchase agreement is not particularly with regard to the eligibility economic reasons, or at the discretion of
interruptible for economic reasons, does of firm LD power products and the either party, but only if a force majeure
not allow the seller to fail to perform information required by section 29.2(v) occurs.’’ 858 Some contend that the
under the contract for economic of the pro forma OATT for seller’s Commission’s conclusion ignored the
reasons, and requires the network choice contracts. Various commenters fact that EEI’s Firm LD Product actually
customer to pay for the purchase. In also argue that the Commission’s allows power to be interrupted for any
addition, the Commission reiterated that precedent on this issue is contradictory reason, including economic reasons,
third-party transmission arrangements and that the Commission’s policy with after which the agreement then provides
to deliver the purchase to the network respect to designation of network LDs as a remedy if the interruption was
must be noninterruptible. resources may violate section 217 of the not due to a force majeure event.859
1435. Regarding seller’s choice FPA and conflict with state jurisdiction. Duke and EEI note that contracts under
contracts, the Commission explained EEI’s Firm LD Product agreement or
(1) LD Contracts similar agreements have become
that a power purchase agreement that is
structured so that a network customer Comments commonplace since the Commission’s
cannot specify all of the information Dynegy decision and that clarification
required by section 29.2(v) of the pro 1438. Many commenters express regarding their use as network resources
forma OATT cannot be designated as a general support for some or all of the is required to address industry
network resource. Specifically, the Commission’s clarifications in the confusion.
Commission reiterated that a request to NOPR with regard to ineligibility of 1441. Several commenters disagree
designate a new network resource must resources which are interruptible for that the EEI Firm LD Product gives
provide the information including the economic reasons and/or that allow the parties the right to interrupt for any
source of supply, control area location, seller to compensate the buyer instead reason, including economic reasons,
transmission arrangements, and delivery of delivering power even if the seller is provided that LDs are paid by the non-
point(s) to the transmission provider’s able to deliver power.853 However, performing party.860 Hoosier argues on
transmission system. The Commission many commenters express concern reply that EEI and Southern have
proposed that, when designating a about the clarity of the policy.854 misunderstood the Commission’s intent
system purchase as a new network in Dynegy. Hoosier contends that the
1439. In particular, several parties
resource, a network customer must Commission correctly found in Dynegy
contend that it is in fact the firmness of
identify the resource as a system that the EEI Firm LD Product does not
the contract and not the mere existence
purchase as well as the control area permit power to be interrupted for
of an LD provision describing the economic reasons, or at the discretion of
from which the power will originate. remedies in case of a failure to perform
1436. In response to suggestions that either party, but only if a force majeure
that determines the eligibility of a event occurs. Thus, Hoosier argues, the
liquidated damages (LD) products power purchase agreement to be
should not be designated network EEI Firm LD Product does not give the
designated as a network resource.855 seller a right to interrupt for any reason
resources because they are interruptible TAPS argues that, in order to determine
for economic reasons, the Commission other than force majeure, and any seller
the firmness of a purchase, one must that interrupts for economic reasons is
proposed to clarify that network look at the criteria for excusing a failure
customers may not designate as network clearly in breach of its obligations to
to supply. AMP-Ohio, MISO, and NCPA perform under the contract and must
resources those power purchase also express support for this position,
agreements that give the seller a pointing to the Commission’s finding in 856 Dynegy Midwest Generation, 101 FERC
contractual right to compensate the ¶ 61,295 (2002), reh’g dismissed, 108 FERC ¶ 61,175
buyer instead of delivering power even 853 E.g., Ameren, BART, Constellation, Duke, (2004) (Dynegy).
if the seller is able to deliver power. For Entegra, Entergy, Morgan Stanley, MISO, 857 E.g., Duke, Dynegy Reply, EEI, and Southern.

instance, the Commission proposed that NorthWestern, Progress Energy, Sempra Global, 858 Dynegy at P 21.

a network customer may not designate Southern, Suez Energy NA, and TranServ. 859 E.g., Duke, EEI and Southern. EEI notes that
854 E.g., AMP-Ohio, APPA, Duke, EEI, Entergy, its Firm LD Product is distinct from its ‘‘System
as a network resource a purchase
Fayetteville, Morgan Stanley, NCPA, Northwest Firm’’ and ‘‘Unit Firm’’ products in its Master
agreement that allows the seller to
sroberts on PROD1PC70 with RULES

IOUs, Northwest Parties, MISO/PJM States, PGP, Power Purchase and Sale Agreement, each of which
Pinnacle, PNM–TNMP, Salt River, Sempra Global, excuses a failure to perform only for force majeure
851 Id. at 61,660. Southern, TAPS, Utah Municipals, and WSPP. and neither of which permits a party to fail to
852 Illinois Power Co., 102 FERC ¶ 61,257 at P 14 855 E.g., AMP-Ohio, Northwest IOUs, NRECA perform and pay liquidated damages.
(2003), reh’g denied, 108 FERC ¶ 61,175 (2004) Reply, PGP, Pinnacle, Sempra Global, Strategic 860 E.g., Hoosier Reply, Strategic Energy Reply,

(Illinois Power). Energy Reply, and TAPS. and Utah Municipals.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00188 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12453

pay damages. Hoosier acknowledges contingent and system firm contracts Southern’s assumption that a failure to
that a seller always has the choice of not require delivery if the unit or group of deliver under a firm LD contract would
performing its obligations and paying units performs and excuses delivery if result in substantial non-delivery
damages, but that is not peculiar to the they do not, while a Firm LD obligation penalties, one would expect a supplier
EEI Firm LD Product. Hoosier maintains requires delivery so long as it is afforded the option to divert power to a
that any party to any contract has the physically possible to achieve delivery, higher priced market that produces a net
ability, but not the right, to breach its regardless of the cost of doing so. Thus, financial gain would elect to interrupt
obligations under the contract and pay according to Morgan Stanley, firm LD service under the power sales contract
damages. According to Hoosier, the only products can enhance supply security and pay the LDs. Detroit Edison
difference in the case of the EEI Firm LD because they are not dependent upon contends that purchasers would be left
Product is that the parties have the performance of an individual unit or hanging during periods of supply
stipulated beforehand as to the measure units, but rather put the burden and shortage when firm physical supply is
of the damages required of a seller in opportunity on the supplier to use most critical.
breach, in order to minimize litigation multiple physical resources to meet its 1447. In its reply comments, Duke
over damages. This stipulation, Hoosier obligations. asserts that allowing firm LD products
argues, conveys no additional 1444. APPA also requests to be designated as network resources
substantive rights on either party. reconsideration of this issue, arguing would result in network customers
1442. Several parties note that firm that its members are often presented leaning on its system. Although it has
LD contracts account for a significant with power purchase agreements based doubts about whether the EEI Firm LD
number of currently utilized products on EEI’s Firm LD Product and that they Product actually contains language that
and that disallowing these product to be are not always successful in negotiating prohibits interruptions for economic
designated as network resources may amendments to such agreements with reasons, Duke would find the inclusion
create significant disruption.861 suppliers. APPA argues that an LSE can of such language in purchased power
Commenters supporting continued use use a diverse resource portfolio, agreements to provide sufficient
of firm LD contracts as designated including firm LD power purchase firmness to allow the contract to be
network resources argue that allowing agreements, to serve its load designated as a network resource. In its
products structured on EEI’s Firm LD economically, while meeting reliability reply comments, Dynegy argues that
Product has not created reliability requirements and advancing other allowing designation of firm LD
problems.862 Southern argues that the important policy objectives (diverse fuel products is simply inconsistent with the
Commission should not set criteria that mix, use of renewable energy, etc.). existing OATT requirements that a
would place in jeopardy an array of APPA urges the Commission to allow transmission customer either own,
products that have a firm LD dimension. such use if it is consistent with the purchase or have rights to generation.
Southern further states that such commercial practices in a region.863 1448. Northwest IOUs request that the
products are among the most reliable in 1445. NCPA also opposes forbidding Commission clarify whether the
instances where market prices are very firm LD products without looking more limitations for qualification of a network
high (where LDs could be quite fully into their merits and the potential resource, such as the presence or
substantial) and that just about any safeguards that could be built into them. absence of an LD clause, would prevent
power purchase/sale contract can be NCPA recognizes that firm LD contracts a transmission provider from using such
financially settled in real-time or for a raise certain issues under the pro forma a resource for service to its bundled
given period in lieu of physical delivery OATT and also pose issues for planning native load customers. Northwest IOUs
during that period. The fact that some where a specific resource is not state that, if the non-rate terms and
contracts set out in advance the terms of designated, but these problems are not conditions do not apply directly by
such settlement (so to render commerce significantly different from the problems requirement of the Final Rule, but only
more efficient and liquid) does not, of a large transmission owner under a comparability test where there
Southern argues, render those contracts designating its entire fleet as network is a comparison to network customers,
any less qualified for designation as resources for its entire load. Rather than then that position should be made clear.
network resources. Thus, Southern ban LD contracts from an important They further note that some
encourages the Commission to segment of the market, several transmission providers have no
reconsider its revised guidance commenters suggest that the comparable network service, or no
regarding the ineligibility of contracts Commission convene a separate service involving generating units
structured after EEI’s Firm LD Product. proceeding or conference to further within the transmission provider’s
Utah Municipals agrees, and similarly investigate the issue.864 control area. Accordingly, Northwest
requests that contracts under EEI’s Firm 1446. Other commenters argue against IOUs request that the Commission
LD Product be allowed to qualify as allowing the designation as network clarify whether, in those instances, the
network resources. resources of contracts that permit the limitations for qualification of a network
1443. Morgan Stanley argues that the interruption of power sales for reasons resource would apply.
notion that firm LD contracts do not other than reliability as long as LDs are 1449. Many commenters also argue
contribute as much to resource paid.865 Detroit Edison argues in its for the eligibility of service provided
adequacy as contracts tied to individual reply comments that a seller’s decision under the WSPP Service Schedule C
physical resources is inaccurate. Morgan to pay the ‘‘costs of ‘cover’ ’’ under these (Schedule C) agreement.866 In
Stanley contends that the incentive to contracts is of no value to an LSE that particular, WSPP argues that its
ensure performance is far greater with a lacks deliverable alternatives. Detroit Schedule C product satisfies the
firm LD obligation than with unit Edison further claims that, contrary to Commission’s requirements for
contingent and system firm contracts. designation as a network resource
sroberts on PROD1PC70 with RULES

863 MISO/PJM States similarly argue that whether


Morgan Stanley explains that unit a particular contract with LD provisions can serve
because it requires the seller to deliver
as a designated resource should be decided within power except under very limited
861 E.g., APPA, Hoosier Reply, NCPA, Southern, the RTO stakeholder process.
Strategic Energy Reply, and Utah Municipals. 864 E.g., APPA Reply, Morgan Stanley, and NCPA. 866 E.g., APPA, EEI, Entergy, Northwest Parties,
862 E.g., EEI, Hoosier Reply, Southern and NCPA. 865 E.g., Duke, Dynegy, and Detroit Edison Reply. Salt River, Utah Municipals, and WSPP.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00189 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12454 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

circumstances, such as force majeure, interruptible for reasons other than violate the terms of the contract, but
and that the agreement itself clearly reliability is not eligible for designation rather merely specifies the damages that
provides that it is a firm product. as a network resource) and the guidance must be paid if the seller fails to
However, WSPP notes that its product, given in WPPI 867 (that a power perform under the contract. As noted by
like most if not all wholesale power purchase agreement which permits many commenters, it is the firmness of
sales contracts, contains a damages curtailment to serve the seller’s native a power purchase contract, and not
provision which could be characterized load is eligible for designation as a simply the presence or absence of an LD
as an LD provision. WSPP contends that network resource). Duke argues that, provision, that determines the eligibility
such provision is used simply to avoid since the type of contracts contemplated of that power purchase to be designated
the need to litigate damages and not to in WPPI are clearly interruptible for as a network resource.
permit a seller to ignore its delivery reasons other than reliability, WPPI 1453. We conclude, however, that the
obligations by financially settling a firm should no longer be deemed valid case firmness of an obligation to provide
power sale. WSPP states that it is not law in light of the Commission’s under a contract with an LD provision
intended that sellers be allowed to proposed clarifications in the NOPR. is informed by the particular terms of
refuse to deliver for economic reasons. Duke argues that allowing such the LD provision. The type of LD
Therefore, WSPP requests clarification contracts to be designated as network provision commonly seen in firm LD
that its Schedule C product is eligible resources creates reliability risks and products, such as the EEI Firm LD
for designation as a network resource, likely permits two entities to designate Product, obligates the supplier, in the
and notes the potential for significant the same generation as network case of interruption for reasons other
disruptions in the market and WSPP resources. While Duke acknowledges than force majeure, to make the
member sales of firm products if its that exceptions to this rule may be aggrieved buyer financially whole by
Schedule C product is not considered necessary in the Western reimbursing them for the additional
eligible for designation as a network Interconnection, it does not support an costs, if any, of replacement power. In
resource. exception for the Eastern contrast to this ‘‘make whole’’ type of
1450. EEI and Northwest Parties note Interconnection. EEI argues that the LD provision, other types of LD
that, in some instances, both the sellers conflict between the Dynegy and WPPI provisions establish penalties at a fixed-
and buyers of the Schedule C product standards has resulted in different dollar amount, cap penalties at some
designate that product as a network transmission providers and customers level, or are otherwise not equivalent to
resource, since it appears to meet the using different standards for designation a general ‘‘make whole’’ type provision.
pro forma OATT definition of a network of network resources. EEI therefore asks Under these other types of LD
resource for both parties because the the Commission to clarify precisely provisions, suppliers only need to
agreement allows interruptions to serve what contracts qualify as a network compare their savings from interrupting
native loads. If only one party is found resource before it implements its with the specified LD penalty when
to be able to designate the Schedule C proposed attestation requirement. deciding whether to interrupt power
product as a network resource, EEI
Commission Determination sales. Because such a consideration may
argues that the other party would run
1452. Many commenters seek not take into account the cost of
the risk of civil penalties for making an
clarification of the eligibility of power replacement power, such LD provisions
incorrect attestation and may also lose
purchase agreements with LD provision could lead to inefficient supplier
the transmission rights that it needs to
serve its native load or network load. to be designated as network resources. interruption and economic harm to the
Northwest Parties request specific In clarifying our policy concerning firm buyer.
clarification as to whether power LD products, we turn first to the 1454. We find that a ‘‘make whole’’
purchased under Schedule C from a apparent confusion surrounding the LD provision, such as that found in the
seller with public utility or statutory Commission’s findings in Dynegy. Duke, EEI Firm LD Product and in the WSPP
obligations to its customers is to be Dynegy, EEI, and Southern argue that Schedule C agreement, does not create
considered power available to meet the the Commission incorrectly found in incentives that are incompatible with
purchaser’s network load on a non- Dynegy that the EEI Firm LD Product the firmness of the overall product.
interruptible basis, given that the seller could not be interrupted for economic ‘‘Make whole’’ LDs require the seller to
may interrupt service under the power reasons. These parties argue that the EEI consider the price of the replacement
sales contract to meet its public utility Firm LD product actually allows power power, if it is available, to its original
or statutory obligations. If the to be interrupted for any reason, buyer if the seller fails to perform under
Commission decides that the Schedule including economic reasons, after which the contract. There could, of course, be
C transactions cannot be designated as LDs are assessed if the interruption was situations where the supplier is still
network resources, Northwest Parties not due to a force majeure event. We presented with a net financial gain and
asks the Commission to state whether disagree. As Hoosier points out, the EEI has an incentive to interrupt, but those
such transactions would be eligible if Firm LD Product does not permit power incentives would seem to be the same
the WSPP service agreement requires to be interrupted for economic reasons. incentives faced by a designated
the seller to give the purchaser advance While any party to any contract can network resource that is a specific
notice of an interruption. Salt River also choose to fail to perform, that does not generating plant owned by the network
asks that, if Schedule C is found to be convey a contractual right to fail to customer. In such an instance, the
ineligible, the Commission identify the perform. The EEI contract clearly network customer may determine, from
specific changes needed to that contract obligates the supplier to provide power, time to time, that it is more economic
to allow for designation. except in cases of force majeure. Thus, to substitute power from an alternate
1451. Beyond the eligibility of the contract does not allow interruption source in order to allow the originally
sroberts on PROD1PC70 with RULES

contracts with LDs to be designated as for economic reasons. The presence of designated resource to either shut down
network resources, EEI and Duke also an LD provision in the EEI Firm LD or to sell its output into the wholesale
argue that there is a conflict between the Product does not permit the seller to market. We find no reason to create
policy guidance given in Dynegy (that a financial incentives that make
power purchase agreement which is 867 WPPI, 84 FERC at 61,652. purchased power designated as a

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00190 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12455

network resource financially ‘‘more chose to interrupt power sales to the statutory obligations to its customers.’’
firm’’ than owned generation. buyer for reasons other than force Thus, the WSPP Schedule C agreement
1455. Accordingly, we find that the majeure. We disagree. Detroit Edison is appears to allow interruptions for
inclusion of a ‘‘make whole’’ LD addressing the fairly unusual reasons other than reliability and, as a
provision in a power purchase circumstance where a power supply is result, would not be eligible for
agreement does not disqualify that interrupted, there are no available designation as a network resource under
agreement from being designated as a alternatives in the market, and firm load the Dynegy or WPPI precedent. We find
network resource. However, other types therefore must be interrupted. We fail to that the provision in the WSPP
of LD provisions may create incentives see why this circumstance, and the Schedule C agreement allowing for
that are incompatible with the firmness difficulty of calculating damages for lost interruption of generation service in
of a power purchase agreement. Thus, as load when it occurs, provides a reason order to serve native load would need
of the effective date of this Final Rule, why a particular network resource (an to be revised to explicitly prohibit
power purchase agreements designated LD contract) should not qualify under interruptions for reasons other than
as network resources may only contain the pro forma OATT as a network reliability of service to native load in
LD provisions that are of the ‘‘make resource. order for that provision to meet the
whole’’ type. Conversely, power 1457. We also disagree with Dynegy’s requirements established under Dynegy
purchase agreements containing LD argument that allowing the designation and WPPI.
provisions that provide penalties of a of firm LD products is inconsistent with 1461. Maintaining the standard for
fixed amount, that are capped at a fixed the existing OATT requirement that a eligibility established in Dynegy and
amount, or that otherwise do not require transmission customer own, purchase or WPPI will further the Commission’s
the seller to pay an aggrieved buyer the have rights to generation. As discussed, goals of preventing undue
full cost of replacing interrupted power, firm LD contracts that meet the discrimination, promoting comparable
are not acceptable. Any contract which Commission’s requirements for treatment of customers, and increasing
contains an unacceptable LD provision, designation do create for the buyer a the accuracy of ATC calculations.
but otherwise qualifies for designation contractual right to generation and do However, we acknowledge that some
as a network resource and has been not contain damage provisions which may currently be relying on the WSPP
properly designated as a network make the actual incentives under such Schedule C agreement in designating
resource prior to the effective date of contracts incompatible with those network resources and that there may be
this Final Rule, will be grandfathered present in owned generation. disruption if we were to invalidate the
only until the earlier of (1) the 1458. In response to Northwest IOUs’
designations of the existing WSPP
expiration of the current term of the request, we also clarify that the presence
Schedule C resources. Thus, we exercise
power purchase agreement or (2) an or absence of an LD provision does not
prevent a transmission provider from our discretion not to invalidate existing
indefinite termination 868 of the power
using such a resource to serve its designations of the WSPP Schedule C
purchase agreement as a designated
bundled native load customers. Rather, agreements as a result of noncompliance
network resource pursuant to section
as we explain above, it is the type of LD with this particular requirement until
30.3 of the pro forma OATT. In response
provision that is controlling. A power the earlier of the following: (1) The
to the many comments received, we
purchase contract with a ‘‘make whole’’ expiration of the current term of a
confirm that the LD provisions in both
remedy could be used to serve native power purchase agreement or (2)
the EEI Firm LD Product and the WSPP
Schedule C agreement are acceptable.869 load customers. redesignation of a previously designated
1456. Detroit Edison argues that a 1459. We disagree with Duke and WSPP Schedule C resource following a
seller’s obligation to pay the cost of EEI’s argument that there is a conflict period of temporary or indefinite
replacement power under firm LD between the policy guidance given in termination pursuant to sections 30.2
contracts is of no value to an LSE that Dynegy (that a power purchase and 30.3 of the pro forma OATT.
lacks deliverable alternatives. Detroit agreement which is interruptible for Alternatively, parties may voluntarily
Edison appears to assume that, as long reasons other than reliability is not reform the offending contract terms in
as an LSE purchasing power had no eligible for designation as a network order to preserve their eligibility for
deliverable alternatives from which to resource) and the guidance given in network service.
procure power, a designated supplier WPPI (that a power purchase agreement (2) Off-System Resources
would not be liable for damages if it which permits curtailment to serve the
seller’s native load is eligible for Comments
868 As discussed below, in section V.D.6.c, designation as a network resource). We 1462. Many commenters request
termination of network resource status may either reiterate the Commission’s finding in
be temporary or indefinite. A firm LD contract that
clarification or reconsideration of the
does not have a ‘‘make whole’’ LD provision and
WPPI that a power purchase agreement information that is required to be
which is grandfathered here may continue to be properly designated as a network specified in section 29.2(v) of the pro
temporarily terminated in order to make third-party resource may permit curtailment to forma OATT in order to designate a
sales without jeopardizing its eligibility to be serve the seller’s native load. Consistent
redesignated after a third-party sale. However, once
seller’s choice contract or system sale as
a network resource is indefinitely terminated, it
with the long-standing definition in a network resource. Northwest Parties
must comport with the requirements for LD Order No. 888, ‘‘curtailment’’ agree with the proposal in the NOPR
provisions, and all other requirements for contemplates a reduction in service as a that system sales may be designated by
designation of network resources, before it can be result of system reliability conditions,
redesignated.
providing the control area from which
869 As discussed below, however, we otherwise
not economic reasons. the sale is made, transmission
find that the WSPP Schedule C agreement does not
1460. Although we find that the LD arrangements, and delivery points to the
comply with the requirements for designation as a provision contained in the WSPP transmission provider’s transmission
sroberts on PROD1PC70 with RULES

network resource because it allows for interruption Schedule C agreement does not impair system.870 For system sales, Northwest
for reasons other than reliability. We therefore do the firmness of that agreement, we note
not need to address requests to clarify that both the
buying and selling party to a WSPP Schedule C
that the agreement otherwise allows 870 Northwest Parties request similar clarification

contract can designate network resources associated interruptions in generation service ‘‘to for designation of purchase contracts from one or
with the contract. meet [the] Seller’s public utility or more specified, individual resources.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00191 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12456 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Parties argue that unit-specific of that resource. TDU Systems also 1469. Because some regions of the
information is not needed because such argue that, for competitive reasons, an country determine ATC using a flow-
sales are, by definition, from a variety of LSE should never be required to identify based methodology and other regions
resources and, in any event, the the generator or the transmission zone use a rated path methodology, EEI
resource-specific information is where the generator is located. argues that section 29.2(v) should be
typically not available to the purchaser. 1466. In contrast, EEI requests that the modified to permit transmission
This is particularly true, they argue, for Commission modify section 29.2(v) to providers to require a network customer
sales from large hydroelectric systems, clearly state that the transmission to designate the point to which the
which are operated as one provider has the discretion to require energy is delivered and from which the
interconnected unit. For purchase the network customer to identify the transmission provider will provide
contracts, they argue that unit-specific location of the generator with more network service if it is not delivered at
information is not needed because it is specificity than simply specifying the the generator bus.
provided in the generation control area in which the network 1470. Duke requests that the
interconnection agreement to the resource is located, since the location Commission resolve an inconsistency
control area where the resource is will affect the flowgate over which the between the NOPR’s statement at P 408
located. Northwest Parties contend that energy will be transmitted. EEI argues that ‘‘when a network customer is
not requiring unit-specific information that it is necessary to narrow the designating a system purchase as a new
for purchase of power, including location of the source of a power network resource, the source
purchases of system power, is consistent purchase to the system of a particular information required in section 29.2(v)
with the Commission’s description in transmission owner, rather than a should identify that the resource is a
the NOPR of the requirements to control area. PNM-TNMP and Duke also system purchase and should identify the
designate a network resource. support requirements that network control area from which the power will
1463. Pinnacle argues that the Final customers provide more information originate,’’ and the statement in the very
Rule should recognize that the level of concerning the location of off-system next sentence that a ‘‘power purchase
detail required by section 29.2(v) may network resources and purchase agreement that is structured so that a
vary depending on circumstances and agreements so that the transmission network customer cannot specify all of
permit the transmission provider to provider can properly evaluate the the information required by section
determine the level of information impact on its system. Duke states that 29.2(v) cannot be designated as a
necessary for the evaluation of the Duke Carolinas are now receiving network resource.’’ Duke notes that
network resource. In some cases, a requests to designate as network significantly more information is
power purchase agreement may, they resources power purchase agreements required by section 29.2(v) (unit size,
argue, appropriately refer to more that list the point of delivery as ‘‘the
VAR capability, operating restrictions,
general information than a specific variable generating cost for redispatch
PJM control area’’ or ‘‘into Southern.’’
single control area or single source of computations, etc.) than the ‘‘control
1467. Dynegy argues in its reply
supply. area from which the power will
1464. In cases where a power comments that the Commission has originate.’’
purchase agreement is being sourced by never explained how a transmission 1471. Morgan Stanley contends that
generating units from an external customer designating a firm LD contract the information required in section
control area, Entergy contends on reply as a network resource could ever 29.2(v) must not disallow designation of
that simply identifying the control area comply with section 29.2 of the pro seller’s choice contracts as network
is sufficient for purposes of studying the forma OATT, which requires specific resources. They assert that transmission
deliverability of that resource. However, information about the generation providers use security constrained
in cases where the power is sourced by resource being designated. Dynegy economic dispatch under which the
generating units internal to the contends that, just like a seller’s choice source of supply in a contract is
transmission provider’s control area, contract, a customer is not entitled to generally irrelevant from a planning or
Entergy argues that identifying only the any information about particular operational perspective and is therefore
control area does not provide sufficient generating assets when entering a firm not needed. Morgan Stanley also argues
information to study deliverability. In LD purchase contract such as the EEI that, if the underlying network
that case, Entergy argues that the Firm LD Product. As a result, Dynegy customer’s contract permits the seller to
customer must provide the specific states that it is unclear how a network curtail its dispatch and substitute a
information required by section 29.2(v) customer would ever be able to source from the market, the
of the pro forma OATT, including the legitimately designate such contracts as transmission provider would never
location of the specific generating units. a network resource. actually know the location where a
If such information is not available at 1468. In order to help ensure that all network customer’s power is coming
the time of the network resource network resources are in fact backed by from and, thus, it is unclear why the
designation, Entergy argues that the capacity, Dynegy argues that the specification of that source should be a
customer should still be able to Commission should require requirement. Therefore, Morgan Stanley
designate the agreement as a network identification of more than just the requests that the Commission consider
resource, but that the customer would control area when designating a network revising 29.2(v) to eliminate the
have to confirm resource deliverability resource. Dynegy argues that the inclusion of information that is not
prior to actually scheduling the service. Commission should require the necessary or make the provision of such
1465. TDU Systems argue in their generation owner or trading agent for information required ‘‘to the extent
reply comments that specifying the the generation to positively verify that practicable.’’
control area and the interface over capacity was sold to the entity 1472. Duke replies that Morgan
sroberts on PROD1PC70 with RULES

which power will enter the transmission designating that particular generator as Stanley accurately portrays what
provider’s transmission system from a a network resource, and that the typically happens under seller’s choice
designated network resource in an designation is appropriate pursuant to contracts, but reaches the wrong
external control area is sufficient for the parties’ agreement, as is currently conclusion about a remedy. Duke argues
purposes of studying the deliverability required in PJM. that, if network customers are permitted

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00192 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12457

to designate as network resources control area(s) from which the power very next sentence that a ‘‘power
contracts that may be relatively long- will originate; (4) delivery point(s) to purchase agreement that is structured so
term, but under which the seller has no the transmission provider’s that a network customer cannot specify
obligation to identify the source of the transmission system; and (5) all of the information required by
power any sooner than on a day-ahead transmission arrangements on the section 29.2(v) cannot be designated as
basis, then ATC may be reserved even external transmission system(s). a network resource.’’ We disagree. The
though there is no intent to use it. Duke Additionally, section 29.2(v) is revised first statement only provided guidance
also argues that allowing seller’s choice to require that the following information on what could be provided in lieu of the
contracts would hamper the be provided with such designation, but source of supply information (as
transmission provider’s ability to plan such information must be masked on required in the last bullet of section
its system. In Duke’s view, it would be OASIS to prevent the release of 29.2(v) of the existing pro forma OATT)
appropriate to permit a seller’s choice commercially sensitive information and was not intended to excuse
contract to be a designated network including (1) any operating restrictions customers from providing all of the
resource at the time transmission (periods of restricted operation, relevant information for an off-system
service is granted for the period such maintenance schedules, minimum purchase other than the specific source
transmission service lasts, as at that loading level of resource, normal of supply. However, the revisions to
point the customer will have designated operating level of resource); and, (2) section 29.2(v) we adopt in this Final
a source and sink. approximate variable generating cost Rule remove any confusion.
1473. Fayetteville recognizes that ($/MWH) for redispatch computations. 1479. We disagree with Dynegy’s
there are problems related to modeling Requests to designate off-system argument that no firm LD contracts
and reliability in contracts for energy network resources submitted on or after would be able to meet the requirements
which do not specify particular units as the effective date of this Final Rule must for designation. We note that all of the
sources, but argues that these problems include all of the information listed information required for off-system
are exactly the same as those that exist above. resources should be available for a
within any vertically integrated utility 1477. We direct transmission seller’s choice contract. Even firm LD
which names its generation fleet as providers to develop OASIS contracts have variable generating costs
network resources for its native load. functionality to (1) allow all of the (energy cost) and may have maintenance
information required for a request to and other operating constraints. If no
Commission Determination
designate network resources to be such constraints are contractually
1474. Many comments were received provided electronically, (2) mask specified, or if no such constraints are
with respect to seller’s choice and information about operating restrictions relevant to an owned generation
system purchases. Some comments refer and generating cost on OASIS, and (3) resource being designated, then that
not only to seller’s choice and system allow for queries of all information should be reflected in the information
purchases, but also to other possible off- provided with designation requests in posted on OASIS.
system transactions, including sourcing accordance with section 37.6 of the 1480. We reject Dynegy’s request that
from owned generation located off- Commission’s regulations.871 As the Commission require additional
system. We therefore use the term ‘‘off- provided in paragraph 385, we also verification by sellers that capacity was
system resources’’ here to refer to all direct transmission providers to work in in fact sold to an entity designating that
such resources. conjunction with NAESB to develop particular generator as a network
1475. The existing requirements in business practice standards describing resource and that the network resource
section 29.2(v) are intended to ensure procedural requirements for submitting designation is appropriate pursuant to
that the network customer designating designations over any new OASIS the parties’ agreement. As the
resources on other transmission systems functionality. Transmission providers Commission explained in Illinois
provides sufficient information to allow need not implement this new OASIS Power,872 a firm energy purchase need
the local transmission provider to functionality and any related business not be backed by capacity to qualify as
determine the effect on ATC. practices until NAESB develops a designated network resource.
Conversely, network customers should appropriate standards. Prior to 1481. We disagree with commenters
not be permitted to designate off-system implementation of this new OASIS who argue that more specific
resources which are so vaguely defined functionality, any information that information than the control area must
that the effects on ATC cannot be cannot be provided electronically may be provided with each request to
determined. In light of the requests that be submitted by transmitting the designate system purchases or seller’s
the Commission clarify exactly what information to the transmission choice contracts as network resources.
information must be provided in order provider by telefax or providing the In particular, we disagree with EEI’s and
to designate network resources located information by telephone over the Duke’s argument that customers
off-system, and what information transmission provider’s time recorded designating seller’s choice contracts as
required by section 29.2(v) must be telephone line. network resources must be required, on
posted on OASIS, we will revise section 1478. Duke argues that there is an a generic basis, to identify the specific
29.2(v) of the pro forma OATT to inconsistency between the following transmission system, rather than the
specify exactly what information is statements in P 408 of the NOPR: (1) more general control area, in which the
required. ‘‘when a network customer is physical resources are located. EEI
1476. As revised by the Final Rule, designating a system purchase as a new argues that such specificity is required
section 29.2(v) of the pro forma OATT network resource, the source for transmission providers to identify
will require the following information to information required in section 29.2(v) the individual flowgates over which the
be provided with the request and posted should identify that the resource is a power will flow into their system. The
sroberts on PROD1PC70 with RULES

on OASIS when designating an off- system purchase and should identify the existing section 29.2(v) of the pro forma
system resource: (1) Identification of the control area from which the power will OATT requires that customers
resource as an off-system resource; (2) originate’’; and (2) the statement in the designating network resources identify
amount of power to which the customer
has rights; (3) identification of the 871 18 CFR 37.6. 872 102 FERC ¶ 61,257 at P 14.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00193 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12458 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

the ‘‘delivery point(s) to the the particular transmission provider’s are for the purpose of meeting a service
transmission provider’s transmission control area from which to dispatch obligation.
system.’’ We agree with Entergy and power, it must designate each of the 1487. Newmont Mining disagrees that
TDU Systems that providing both the resources as network resources. the Commission’s requirements for
control area in which off-system 1484. We disagree with Morgan designation of network resources are
resources are located as well as the Stanley’s unsupported comments that contrary to the new FPA section
delivery point(s) to the transmission the source of supply in a contract is 217(b)(2). Newmont Mining argues the
provider’s transmission system is irrelevant. We find that location of legislative history of section 217(b)(2)
usually sufficiently specific to allow a resources is a critical factor to the shows that it was intended essentially to
transaction to be evaluated for its effect transmission provider’s ATC codify Order No. 888 873 and that the
on the ATC of the local transmission calculations and its ability to model and resource designation requirements do
system. However, we acknowledge evaluate the proposed network resource, not deny LSEs any right to use their
Duke’s concern about receiving requests regardless of whether the transmission transmission, but rather prescribe how
to designate as network resources providers use security constrained they are to implement that right.
purchase agreements that list the point economic dispatch. 1488. EEI, Nevada Companies, PNM-
of delivery as only vague statements TNMP and South Carolina E&G on reply
such as ‘‘the PJM control area’’ or ‘‘into (3) Ability To Serve Native Load also argue that the Commission’s
Southern.’’ If any transmission provider Comments requirements for eligibility for
believes that it faces unique designation as a network resource may
1485. Many parties contend that the impermissibly conflict with state-
circumstances that require deviations Commission’s policy with regard to the
from the pro forma OATT in order to mandated procurement plans. EEI and
qualification of network resources South Carolina E&G contend that, by
allow them to determine the effects of affects their ability to serve native load.
designations of network resources on imposing restrictions on the ability of
EEI argues that energy purchases are an LSEs to serve their native load, the
ATC, it can, in a filing pursuant to FPA
integral part of the resources many Commission is indirectly asserting
section 205, propose terms and
utilities use to serve their loads, yet jurisdiction over state-regulated
conditions that it demonstrates are
often such projected energy purchases procurement practices, which they
consistent with or superior to the pro
are not under contract until shortly further argue is prohibited under
forma OATT.
1482. Because some regions of the before the power is needed. According Northern States Power Co. v. FERC.874
country determine ATC using a flow- to EEI, the requirement that a purchase 1489. Nevada Companies argue that
based methodology and other regions contract be executed to qualify as a the type of contracts that the
use a rated path methodology, EEI network resource jeopardizes the ability Commission has determined to be
argues that section 29.2(v) should be of such utilities to serve their native eligible for qualification as network
modified to permit transmission loads because they will not be able to resources tend to be the most expensive.
providers to require a network customer reserve transmission capacity and other They point out that state regulatory
to designate the point to which the users may receive all of the ATC before agencies might determine that other
energy is delivered and from which the their contracts are executed. types of contracts are more cost-effective
transmission provider will provide 1486. APPA, EEI and Nevada without unnecessarily jeopardizing
network service if it is not delivered at Companies argue that restrictions on the reliability. Even more troubling, they
the generator bus. It is unclear what types of generation and power supply argue, is the problem created when
specific changes EEI is requesting. We arrangements that qualify for network transmission providers have peak loads
note that, with respect to off-system service may violate section 217 of the that can more effectively be served by
purchases, section 29.2(v) of the pro FPA. EEI notes that section 217 provides purchasing power on a short-term
forma OATT already requires that the that LSEs are entitled to use firm period (i.e., less than one year). To
delivery point(s) to the transmission transmission rights to deliver the output reserve the transmission required to
provider’s transmission system be of their generators or purchased energy serve a needle peak that can occur
included in the description of the to meet their service obligations to their anytime within a four month period
network resource. loads. In EEI’s view, section 217 would require the purchase of
1483. In response to Entergy’s request, requires the Commission to exercise its thousands of megawatt hours of power
we clarify that a customer may not authority in a manner that enables LSEs that Nevada Power knows it will not
designate as a network resource a to secure firm transmission rights on a need, resulting in a disallowance by the
seller’s choice power purchase long term basis for long term power Public Utility Commission of Nevada,
agreement which is sourced by supply arrangements made, or which approves all open positions,
generating units internal to the ‘planned,’ to meet such needs and, options and hedges for Nevada Power.
transmission provider’s control area, therefore, a requirement that network 1490. Nevada Companies contend that
since evaluating the effect on ATC customers and transmission providers the network designation process should
would be problematic. We disagree with not reserve transmission capacity to not be changed on systems where the
Entergy that a customer should be able serve their network loads and native process works reasonably well,
to designate such a resource, even loads unless they either own generation
without specifying the location of the or have executed contracts that specify 873 In its reply comments, Newmont Mining cites

specific generating units, provided that the source of the energy is inconsistent (through reference to its own NOI reply comments)
with section 217. APPA notes that the statement in H.R. Rep No. 108–65 at 171 (2003)
the customer’s network service from that ‘‘[t]his section is intended to be consistent with
those units is contingent upon section 217 does not distinguish among the Commission’s Order No. 888,’’ as well as the
confirming resource deliverability prior the types of power supply arrangements statement in S. Rep. No. 109–78 at 50 (2005) that
sroberts on PROD1PC70 with RULES

to actually scheduling the service, that an LSE must enter into to be section 217 ‘‘does not affect the Commission’s
because such a policy would still protected and that section 217(b)(1)(A) authority under sections 205 and 206 [of the FPA]
to ensure that rates are just and reasonable and not
significantly obscure the evaluation of refers to a broad universe of owned or unduly discriminatory or preferential.’’
ATC. If a customer wishes to have a contracted generation that would 874 176 F.3d 1090, 1096 (8th Cir. 1999), cert.

choice of resources that are internal to suffice, so long as the power supplies denied, 528 U.S. 1182 (2000).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00194 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12459

particularly on systems where nothing in section 217 suggests that (4) General
transmission providers are required to LSEs should not be required to comply Comments
make significant purchases of power to with reasonable requirements that are
meet their retail loads. Nevada necessary to prevent undue 1496. A number of commenters raised
Companies argue that the Commission other general concerns regarding the
discrimination and maintain a reliable
should therefore give transmission designation of network resources. TAPS
transmission system. The conditions
providers the option of instituting a requests that the Commission clarify
that have been established for taking that conditional firm transmission
reservation-based contract demand network transmission service are
service similar to that previously service is sufficiently firm to meet the
reasonable and support these goals, and requirement that third-party
approved in Florida Power.875 we therefore disagree that such
1491. Newmont Mining replies that transmission arrangements to deliver a
Nevada Companies proposal is not conditions are inconsistent with the designated purchase to the network be
similar to the Florida Power proposal or requirements of section 217. noninterruptible. TAPS also requests
other approved contract demand Furthermore, as Newmont Mining that the Commission provide for
network service arrangements, as those points out, the legislative history of designation of network resources within
services were offered at the request of a section 217(b)(2) supports the the control area on a conditional firm
network customer; designed to deal interpretation that section 217 was basis.
with a particular circumstance of the intended to be consistent with the 1497. In its reply comments, South
network customer; and offered as an Commission’s authority under sections Carolina E&G request clarification of the
option to, not as a replacement for, 205 and 206 of the FPA to ensure that content and process of making
standard network integration services. rates are just and reasonable and not information postings in accordance with
Utah Municipals in their reply unduly discriminatory or preferential, section 29.2 of the pro forma OATT.
comments agree that utilities should not under which the designation South Carolina E&G argues that, taken
be permitted to unilaterally impose a requirements in Order No. 888 were literally, section 29.2 requires that
contract demand ‘‘reservation based’’ everything in an application for network
adopted.
methodology on its network customers. service be posted. South Carolina E&G
1492. Newmont Mining argues that 1494. We also disagree with contends, however, that the contents of
Nevada Companies’ request to maintain commenter arguments that the an application do not fit on OASIS as
an open position for a portion of their Commission’s requirements for currently configured, and that making
resource portfolio, in accordance with eligibility for designation as a network such information available on OASIS is
their required resource planning resource impermissibly conflicts with not necessary for the Commission’s
process, does have some basis, but that state-mandated procurement plans. We purposes, particularly given the
Nevada Companies’ proposal is not the point out that, with the exception of Commission’s representations in favor
right solution. If the Commission is some clarifications on the types of LD of preserving the integrity of customer
inclined to provide some relief to provisions that are acceptable in confidential information. South
Nevada Companies, Newmont Mining designated firm LD products and what Carolina E&G suggests the Commission
argues that such relief should come, if information a customer designating a require only the following information
at all, only after an investigation of how system purchase or a seller’s choice to be posted on OASIS: identification of
similar problems are handled on other contract must provide, the requirements the service type as ‘‘network’’;
systems and that such relief should be identification of the source by name of
for designation of network resources are
limited. The limitations Newmont the generator or system; identification of
not new. Order No. 888 has long
Mining suggests include, among other the sink by name of the network
required that contracts be executed and customer’s load; identification of the
things, excusing Nevada Companies imposed reasonable restrictions on the
from the requirement, if at all, only to point of receipt by specification of the
types of resources that may be interface at which the network customer
the extent that a specific open portfolio designated as network resources.
position is contained in a resource plan intends to deliver to the resource into
approved in accordance with applicable 1495. To the extent that individual the transmission provider’s
law; requiring that the reservation be transmission providers have unique transmission area; and identification of
posted on OASIS; not granting a circumstances or needs that justify a the point of delivery and sink.
reservation to Nevada Companies over a variation from the pro forma OATT, 1498. South Carolina E&G also
competing application for network those parties can request such a requests clarification on how designated
service by a potential network customer variation and explain why their network resources are to be posted.
that actually has a designated network proposed variation is consistent with or South Carolina E&G asks, for instance,
resource; and permitting other network superior to the requirements of the pro whether the Commission expects
customers to hold similar open forma OATT in a section 205 filing. In transmission providers to develop an
positions. particular, Nevada Companies’ request OASIS template that network customers
can update, as necessary, for network
Commission Determination for approval of a contract demand
resources to simply be posted in PDF
service in order to address certain issues
1493. We generally disagree with format, or be accomplished via the
presented by their unique situation comment section of an OASIS
arguments that the Commission’s would properly be made in the context
restrictions on the designation of reservation. South Carolina E&G argues
of a section 205 filing requesting a that posting via the comment section of
network resources may violate section deviation from the pro forma OATT. We
217 of the FPA. Congress did not require OASIS allows for operational ease, but
agree with Newmont Mining and Utah provides limited transparency and
that LSEs be able to take transmission
sroberts on PROD1PC70 with RULES

Municipals that approved variations, if includes administrative challenges due


service without limitations of any kind
in order to serve their native load, and any, must be applied on a comparable to character limitations and formatting
basis to both the transmission provider’s constraints. Alternatively, South
875 Florida Power Corp, 81 FERC ¶ 61,247 (1997) merchant function and the other Carolina E&G argues, new functionality
(Florida Power). network customers. on OASIS that allows customers to post,

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00195 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12460 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

modify and update network resources 1502. In its reply comments, Dynegy transmission provider and approved by
would satisfy the Commission’s disagrees with request to grandfather the Commission.877
requirements, but would involve added existing designated network resources, 1506. In response to TDU Systems’
costs and time. and argues that the Commission’s request for clarification that the process
1499. TranServ seeks clarification as holding in Dynegy was erroneous and of network resource designation should
to the minimum term, if any, that the should be remedied in its entirety, be the same for all users, we note that
transmission provider must honor for without the creation of yet another class section 28.2 of the pro forma OATT
designation of new network resources. of grandfathered entities. already provides that ‘‘[t]he
TranServ requests that network Transmission Provider, on behalf of its
resources be allowed to be designated Commission Determination Native Load Customers, shall be
for the same minimum time periods required to designate resources and
1503. The Commission agrees with
used for firm point-to-point service, i.e., loads in the same manner as any
TAPS that firm point-to-point Network Customer under Part III of this
daily or hourly service. Conversely, transmission service provided on a
South Carolina E&G argues in its reply Tariff.’’ We encourage parties to utilize
conditional firm basis is sufficiently the Commission’s Enforcement Hotline
comments that requiring transmission firm to be used for transmission to
providers to update their list of to report suspected abused of this
import a designated network resource. process.
designated network resources on an Firm point-to-point transmission service
hourly basis is too burdensome. South provided on a conditional firm basis b. Documentation for Network
Carolina E&G requests that the meets the existing requirement that Resources
Commission allow alternative methods transmission arrangements in other
of designating network resources on a NOPR Proposal
control areas delivering power
short-term basis, such as adding 1507. In the NOPR, the Commission
purchases designated as network
comments to the appropriate comment noted that transmission providers are
resources to the network customer’s
field on either eTags or OASIS responsible for verifying that the
transmission provider must not be
reservations. network customer has provided all the
interruptible for economic reasons, as information required in section 29.2, but
1500. TDU Systems argue that the explained further in section III.F of this
designation of network resources that transmission providers are not
Final Rule. With respect to TAPS’ responsible for verifying that the
(explicit or implicit) by some second request for clarification to allow
transmission providers is automatic, generating units and power purchase
for designation of network resources agreements network customers
while network customers are required to within the control area on a conditional-
pay for elaborate studies of every designate as network resources satisfy
firm basis, we note that such the requirements in sections 30.1 and
conceivable path affected by the designation of network resources within
addition of the resource. TDU Systems 30.7 of the pro forma OATT. However,
the control area will not be allowed, as the Commission also explained that the
request that the Commission clarify that discussed further in section III.F.
the process of network resource transmission provider continues to have
designation should be the same for all 1504. In response to South Carolina the responsibility to verify that third-
network users. E&G’s request, we reiterate that not all party transmission arrangements to
1501. APPA, Fayetteville, NCPA, of the information required by section deliver the purchase to the transmission
Northwest Parties, TAPS, and 29.2 of the pro forma OATT for provider’s system are firm.
designation of a network resource will 1508. The Commission proposed to
Wolverine request that clarifications
be made publicly available on OASIS. require the transmission provider’s
made to the Commission’s policy for
As discussed above, information about merchant function as well as network
qualification as a network resource
operating restrictions and generating customers to include a statement with
apply prospectively and/or that
cost will be masked to protect each application for network service or
sufficient time be allowed after the
commercially sensitive information. to designate a new network resource
adoption of the Final Rule such that the
South Carolina E&G has also requested that attests that, for each network
necessary products, information systems
clarification of the Commission’s intent resource identified in the application for
and business practices can be
with respect to how designated network service, (1) the transmission customer
developed. Such commenters contend
resource information is posted. Our owns or has committed to purchase the
that the designated network resources
existing regulations specify the view, designated network resource, and (2) the
they currently rely upon were acquired
download, and query requirements for designated network resource comports
and designated consistent with prior
information posted regarding network with the requirements for designated
Commission precedent, so that changes
resource designations.876 The details of network resources.
to the network resource criteria
how those informational postings are 1509. If the network customer does
established in this proceeding should
accomplished are best left to be not include an attestation when it
not invalidate the continued use of such
determined as part of the NAESB confirms its request, the Commission
resources. Because there may be many
standards development process. proposed that the transmission provider
existing designated network resources
will notify the network customer within
that do not meet the standards that the 1505. TranServ requests that the
15 days of confirmation that its request
Commission eventually sets, Duke Commission clarify the minimum term,
is deficient and that, wherever possible,
suggests on reply that the Commission if any, that a transmission provider must
the transmission provider will attempt
may need to permit existing contractual honor for designations of new network
to remedy deficiencies in the request
designated network resources that do resources. We agree with TranServ that
through informal communications with
not qualify under the new standard to the minimum term should be the same
the network customer. If such efforts are
sroberts on PROD1PC70 with RULES

retain their designated status until the as the minimum time period used for
unsuccessful, the Commission further
earlier of the expiration data of the firm point-to-point service (i.e., daily),
transaction or the expiration date of any unless otherwise demonstrated by the 877 See, e.g., Entergy Services, Inc., 105 FERC
necessary transmission service ¶ 61,318 (2003), reh’g denied in relevant part, 109
supporting that network resource. 876 See 18 CFR 37.6(a). FERC ¶ 61,216 (2004).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00196 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12461

proposed that the status of the request rate authority. APPA and TAPS argue contend that the gap between the
on OASIS will be changed to that the new attestation requirements Commission’s interpretation of the
‘‘retracted’’ and the network customer’s should be consistently applied to all qualifications of network resources and
request will be terminated without network customers, including the current procurement practices creates a
prejudice to the network customer transmission provider’s merchant significant possibility that, if the
submitting a new request that includes function and affiliates. Commission enforces its policies, it
the required attestation, after which the 1513. Several commenters support the could cause substantial disruptions of
network customer will be assigned a Commission’s determination that service to network and native loads,
new priority consistent with the date of transmission providers are not required reduce supply options, or expose
the new request. to independently verify the accuracy of network customers and transmission
1510. In the event that the an application for network service.880 providers to increased liability.882 EEI
transmission provider or any network Some commenters request that the asserts that this is because a significant
customer designates a network resource Commission clarify that transmission number of network customers and
that it does not own or has not providers or transmission owners can transmission providers are serving their
committed to purchase, or that does not voluntarily seek information which network loads and native loads using
otherwise comport with the verifies that contractual terms meet the resources, particularly power purchase
requirements for designated network requirements in section 30.1 and 30.7 of contracts, that may not meet the
resources, the Commission proposed the pro forma OATT.881 In its reply Commission’s requirement for
that it will deem the network customer comments, Duke argues that, without designation as network resources. Some
to be in violation of the pro forma the ability to request the contracts commenters request that the
OATT and will consider assessing civil supporting the compliance with the Commission engage in a comprehensive
penalties on a case-by-case basis requirement that the designated network review of power purchase practices
consistent with the Commission’s Policy resources are firm enough, the before implementing its proposed
Statement on Enforcement. The Commission may not have authority to attestation requirement, and apply any
Commission encouraged the require that the network customer change in policies only to power
transmission provider and other market support its designation in situations purchases entered into after the effective
participants to use the Commission’s where the network customer is date of the Final Rule and after the
Enforcement Hotline to report instances nonjurisdictional. industry has had time to develop new
when they believe a network customer 1514. Pinnacle disagrees with the products that meet the Commission’s
has designated as a network resource a NOPR proposal that transmission requirements.883
resource that does not meet the criteria providers should continue to be 1517. Entegra replies that the
for network resources. responsible for verifying the firmness of expressed concern about the attestation
Comments the network customers’ transmission requirement by EEI is puzzling and
arrangements on other systems. Instead, troubling, because the NOPR did not
1511. Several commenters support the Pinnacle contends that the transmission propose to change the current
overall proposed changes involving requirements of the pro forma OATT
customer should have the obligation to
attestation requirements, claiming the regarding the qualification of network
ensure that their transmission
proposal should help to eliminate resources. Entegra argues that the
arrangements meet the requirements
abuse, including the practice of some widespread non-compliance alleged by
needed to ensure that their resources
utilities denying transmission requests EEI makes adoption of an attestation
qualify as designated network resources.
in order to accommodate its merchant requirement more important and that
In its reply comments, Detroit Edison
function’s plans to engage in future EEI’s allegations may, at most, suggest
also requests that the Commission
short-term purchases to serve native that the Commission consider some sort
require proof that network customers
load.878 Entegra explicitly supports the of amnesty for network customers and
have obtained the requisite transmission
Commission’s proposal to treat failures transmission providers willing to self-
to comply as violations of the pro forma service on external systems.
1515. Dynegy, in its reply comments, report and commit to full compliance
OATT subject to enforcement. Pinnacle with the network resource rules going
requests that network resource
notes that customers should make such forward.
information and validity of designation
attestations in good faith, such that an 1518. To ensure that network
be verified not only by the designating
inadvertent error or omission would not customers can submit requests for new
customer, but also by the seller or owner
automatically result in recourse to a network service without a final,
legal remedy if it can be corrected of the generation, in order to help
ensure that all network resources are in executed contract, Entergy requests that
without adverse impacts. an attestation to designate a new
1512. Dynegy argues in its reply fact backed by capacity. Entegra
similarly suggests that the Commission network resource should not be required
comments that transmission customers
require that entities designating network until the service request is confirmed. If
who knowingly provide false or
resources make periodic OASIS postings the request is pre-confirmed, Entergy
inaccurate information in their network
that will permit verification that the suggests that the attestation should be
resource designations not only
entity designating a generating facility provided at the time the request is
jeopardize reliability, but are essentially
as a network resource actually has rights submitted.
engaging in theft. Dynegy argues that 1519. SPP requests that the
such parties should be subject to the to power from that facility.
1516. EEI and Entergy allege that the Commission not require it to police the
sanctions and penalties under the
Commission’s NOPR attestation additional restrictions on the
Market Behavior Rule,879 including
proposal may have unintended designation of network resources
revocation of the violator’s market-based
consequences. Some commenters proposed in the NOPR. SPP states that
sroberts on PROD1PC70 with RULES

878 E.g., Ameren, Entegra, Pinnacle, Public Power


it has neither the data nor the personnel
880 E.g., Ameren, EEI, Suez Energy NA, Nevada
Council, and Southern.
879 See Investigation of Terms and Conditions of Companies, and Utah Municipals. 882 E.g., EEI, TDU Systems, Indianapolis Power

Public Utility Market-Based Rate Authorizations, 881 E.g., Ameren, Duke Reply, Entergy, and Reply, and South Carolina E&G Reply.
105 FERC ¶ 61,218 (2003). Pinnacle. 883 E.g., EEI and Indianapolis Power Reply.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00197 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12462 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

necessary to perform this function and resource comports with the is whether the violation is willful.887 At
that the Commission should rely on requirements for designated network the same time, consideration is
network customer verification, subject resources. The network customer should provided for other factors that may
to Commission audits. TranServ include this attestation in the weigh for assessing civil penalties, even
suggests that the exact nature of how the customer’s comment section of the in circumstances of inadvertent
customer would make the newly request when it confirms the request on violations. For instance, the
required attestation, as well as the OASIS. Commission considers whether the
treatment of OASIS requests failing to 1522. If the network customer does violator has a history of violations and
provide the required attestation, should not include the attestation when it whether the actions were recklessly or
be determined in the NAESB forum at confirms the request, the transmission deliberately indifferent to the results.888
the time when the technical provider must notify the network While enforcement actions will not be
requirements for processing network customer within 15 days of automatic, and the inadvertence of a
service requests on OASIS are confirmation that its request is deficient, violation would be a consideration
established. in accordance with the procedures in when determining what, if any, penalty
1520. Several commenters request section 29.2 of the pro forma OATT. to impose, there may be some instances
that the Commission amend section 30.2 Whenever possible, the transmission where inadvertent violations would be
of the pro forma OATT to require provider shall attempt to remedy found, after consideration as established
network customers that designate deficiencies in the request through in the Policy Statement on Enforcement,
network resources in an external control informal communications with the to warrant a penalty.
area also provide a certification from network customer. If such efforts are 1525. Dynegy also requests that
that control area’s administrator that the unsuccessful, the transmission provider transmission customers who knowingly
resource being designated is not shall terminate the network customer’s provide false or inaccurate information
counted as a designated resource for request and change the status of the in their network resource designations
another load on or off of the system.884 request on OASIS to ‘‘retracted.’’ This be subject to the sanctions and penalties
TDU Systems disagree, arguing on reply termination shall be without prejudice under the Market Behavior Rules,889
that the Commission should not require to the network customer submitting a including revocation of the violator’s
these types of certifications. TDU new request that includes the required market-based rate authority. We
Systems recommend, in the alternative, attestation. The network customer shall reiterate that violations will be dealt
that LSEs on multiple systems should be assigned a new priority consistent with on a case-by-case basis in
not have to undesignate network with the date of the new request. accordance with the Policy Statement
resources to serve off-system load, on Enforcement.
1523. In the event that the
which would eliminate the need for 1526. We reject requests to allow the
transmission provider or any other
such control area certification for such transmission provider to voluntarily
network customer designates a network
transactions. TDU Systems also argues seek information which verifies that
resource that it does not own or has not
that, in the absence of any evidence of contractual terms meet the requirements
committed to purchase or that does not
abuse, the Commission should not in sections 30.1 and 30.7 of the pro
comport with the requirements for
further complicate a process that most forma OATT. Allowing transmission
designated network resources, we will
market participants would agree is providers to verify terms and conditions
deem the network customer to be in
already overly complicated and of power purchase agreements would
violation of the pro forma OATT and
burdensome. put transmission providers in the
will consider assessing civil penalties
Commission Determination on a case-by-case basis, consistent with position of interpreting contracts and
the Commission’s Policy Statement on accepting or rejecting designations
1521. The Commission adopts the based on their interpretations. We
NOPR proposal that transmission Enforcement.885 We encourage the
transmission provider and other market believe such authority is unnecessary in
providers continue to be responsible for light of the new attestation requirements
verifying that third-party transmission participants to use the Commission’s
Enforcement Hotline to report instances and that instances of non-compliance
arrangements to deliver the purchase to are better handled by the Commission’s
the transmission provider’s system are where they believe a network resource
has been designated that does not meet enforcement staff in the context of
firm, but that transmission providers are audits and Enforcement Hotline reports.
not responsible for verifying that the the Commission’s requirements.
1524. In response to Pinnacle’s This applies equally to jurisdictional
generating units and power purchase and nonjurisdictional customers. Every
agreements network customers request that an inadvertent error or
omission should not automatically transmission customer must satisfy the
designate as network resources satisfy requirements of the transmission
the requirements in sections 30.1 and result in a penalty if it can be corrected
without adverse impacts, we reiterate provider’s OATT in order to take
30.7 of the pro forma OATT. We also service. The Commission thus has
adopt the proposal to require both the the policy established in the
Commission’s Policy Statement on authority to require that all network
transmission provider’s merchant customers support their designations.
function and network customers to Enforcement that enforcement actions
will not be imposed ‘‘automatically.’’ 1527. We disagree with Pinnacle’s
include a statement with each argument that transmission providers
application for network service or to Enforcement actions are instead
considered on a case-by-case basis after should not be responsible for verifying
designate a new network resource that the firmness of the network customer’s
attests, for each network resource consideration of a number of factors
which may result in penalties being transmission arrangements on other
identified, that (1) the transmission systems. We find that having
customer owns or has committed to reduced or eliminated.886 Among the
sroberts on PROD1PC70 with RULES

purchase the designated network many factors to be considered pursuant 887 Id. at P 20.
resource and (2) the designated network to the Policy Statement on Enforcement 888 Id.
889 Investigation of Terms and Conditions of
884 E.g., 885 See supra note 75.
MISO, Indianapolis Power Reply, and Public Utility Market-Based Rate Authorizations,
Detroit Edison Reply. 886 Policy Statement on Enforcement at P 13. 105 FERC ¶ 61,218 (2003).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00198 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12463

transmission providers verify firmness of these questions above, we believe that provider, on behalf of its native load
of such transmission arrangements many of the concerns about the customers, to designate resources and
provides a significant benefit to the attestation requirement are resolved. loads in the same manner as any
system and is not unduly burdensome. Commenters have not supported claims network customer under Part III of the
The confirmation or lack thereof of that the attestation requirement will be pro forma OATT (Network Integration
service on the third-party’s system either burdensome or that the Transmission Service). The information
should be readily available on OASIS. If requirement will require substantial provided by the transmission provider
firm third-party service is not confirmed time to comply. As noted above, the must be consistent with the information
in OASIS, the transmission provider minimal additional network resource it uses to calculate ATC. Section 30.3 of
should attempt to remedy any designation requirements impose in this the pro forma OATT previously allowed
information deficiency in the request Final Rule beyond the existing the network customer to terminate the
through informal communications with requirements are not expected to be designation of all or part of a generating
the network customer. If such efforts are unduly burdensome. While exceptions resource as a network resource at any
unsuccessful, the transmission provider may be appropriate in cases of time, but stated that the network
should find the request to designate the legitimate emergencies, we disagree customer should provide notification to
network resource deficient. Because this with the implication that a customer the transmission provider as soon as
information is available on OASIS, we should be granted general flexibility to reasonably practicable.
disagree with Detroit Edison’s request designate a network resource that 1535. In Order No. 888–B, the
that the Commission require proof that otherwise may not be eligible. Commission clarified that the pro forma
customers have obtained requisite 1531. In response to Entergy’s request, OATT allows network customers to
transmission service on external we agree that attestations will not be designate network resources over
systems. required to be submitted until the shorter time periods. The Commission
1528. We also disagree with SPP’s service request is confirmed. However, indicated that a network customer that
argument that it should not be required if the request is pre-confirmed, we agree seeks to engage in firm sales from its
to police the additional restrictions on that the attestation must be provided at currently designated network resources
the designation of network resources, the time the request is submitted. may terminate the generating resource
since it has neither the data nor the 1532. In response to TranServ’s (or a portion of it) as a network resource
personnel necessary to perform this request that the exact nature of how the pursuant to section 30.3 of the pro
function. The only ‘‘additional’’ customer would make an attestation forma OATT and request that, as set
restrictions that the transmission should be determined in the NAESB forth in section 29 of the pro forma
provider is called upon to police is that forum, we note that the contents and the OATT, the same generation resource be
network customers submit the specific information that is required to designated as a network resource
appropriate attestations when be provided with the attestation are
effective with the end of its power
requesting designation of a network specified in the pro forma OATT, and
sale.890
resource, which places a particularly we are requiring that the attestation be
small burden on the transmission submitted through OASIS with each NOPR Proposal
provider. We also do not expect the request to designate a new network 1536. In the NOPR the Commission
requirement that transmission providers resource. The appropriate subject for proposed to continue to allow network
verify the firmness of the network transmission providers to coordinate customers to ‘‘undesignate’’ 891 a portion
customer’s transmission arrangements with NAESB to resolve is limited to the of their network resources on a short-
on other transmission systems to require appropriate formatting of such term basis to make off-system sales. The
any additional data or personnel. information to be provided in OASIS. In Commission reiterated that a network
1529. We reject Dynegy’s request that response to TranServ’s request that customer may redesignate the resource
the validity of network resource NAESB should also determine the by making a request to designate a new
designations be verified not only by the treatment of OASIS requests where the network resource. Additionally, the
designating customer, but also by the customer fails to provide the necessary Commission reiterated that the
seller or owner of the generation, in attestation, we point out that we have transmission provider and all network
order to help ensure that all network already directed that such requests are customers must designate their network
resources are in fact backed by capacity. to be found deficient by the resources and are prohibited from
Similarly, we deny Entegra’s request transmission provider and treated in making firm third-party sales from
that the customer be required to make accordance with the procedures in designated network resources. The
additional, periodic OASIS postings to section 29.2 of the pro forma OATT.
demonstrate that it has rights to the Commission stated that, to the extent
1533. We reject requests to require
power from a designated resource. We the transmission provider or a network
network customers designating network
find that such additional verifications customer wants to make a firm sale from
resources in an external control area to
are unnecessary in light of the new a network resource, it must undesignate
provide certification from that control
attestation requirements. the resource pursuant to section 30.3 of
area’s administrator that the resource
1530. With regard to arguments that the pro forma OATT. The network
being designated is not counted as a
requiring an attestation may disrupt customer, including the transmission
designated resource for another load on
service, the alleged confusion over the provider itself, could request to
or off the system. We find that, in
Commission’s requirements for redesignate the resource by making a
absence of any evidence that the
designation of network resources seems request to designate a new network
Commission’s new attestation
primarily concerned with whether the resource pursuant to section 30.2 of the
requirements will be insufficient, this
EEI Firm LD Product and similar pro forma OATT.
requested verification appears
sroberts on PROD1PC70 with RULES

products were eligible to be designated unnecessary. 890 Order No. 888–B at 62,093.
as network resources and whether
certain resources can be designated both c. Undesignation of Network Resources 891 The general term ‘‘undesignation’’ refers to
both temporary terminations and indefinite
to serve native load and other network 1534. Section 28.2 of the pro forma terminations of network resource status, as
customers. As we have addressed both OATT requires the transmission discussed below.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00199 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12464 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

1537. The Commission also sought considered a request for indefinite by the publicly available information
comment on the amount of time prior to termination of those network resources. posted on OASIS.
operation that the transmission provider 1541. We direct transmission 1543. Transmission providers need
and other network customers should be providers to develop OASIS not implement this new OASIS
required to terminate a network functionality and, working through functionality and any related business
resource to ensure that the appropriate NAESB, business practice standards practices until NAESB develops
set of network resources are included in describing the procedural requirements appropriate standards. Prior to
the ATC calculation. for submitting both temporary and implementation of this new OASIS
indefinite terminations of network functionality, requests for temporary or
(1) Overview indefinite terminations of network
resources, to allow network customers
Comments to provide all required information for resources may be submitted by
such terminations. Such OASIS transmitting the required information to
1538. Most commenters appear to functionality should allow for electronic the transmission provider by telefax or
support the Commission’s proposal to submittal of the type of termination providing the information by telephone
continue to allow network customers to (temporary or indefinite), the effective over the transmission provider’s time
undesignate a portion of their network date and time of the termination, and recorded telephone line.
resources on a short-term basis to make identification and capacity of
off-system sales. However, many (2) Risk to ATC Rights
resource(s) or portions thereof to be
commenters request clarification that a terminated. For temporary terminations, Comments
temporary undesignation will not cause such OASIS functionality should also
them to forfeit their rights to 1544. Most commenters request
allow for electronic submittal of (1) clarification that a temporary
transmission priority or ATC for any effective date and time of redesignation,
other time period. Several commenters undesignation of a network resource
following the period of temporary does not constitute a forfeiture of
also request that formal undesignations termination; (2) information and
not be required or that the process not priority followed by a new request to
attestation for redesignating the network designate the network resource, or
be burdensome. A wide range of resource following the temporary
comments were received in response to otherwise put in jeopardy the ATC
termination, in accordance with section associated with the designation of that
the Commission’s request for comments 30.2 of the pro forma OATT; and (3)
on the amount of time prior to operation resource for any period other than the
identification of any related period of undesignation.893 Several
that the transmission provider and other transmission service requests to be
network customers should be required commenters argue that virtually no
evaluated concomitantly with the network customers will ever make a
to terminate a network resource to request for temporary termination. In
ensure that the appropriate set of firm third-party sale if they are forced to
response to TranServ’s request, we reapply for transmission service after a
network resources are included in the clarify that the request for temporary
ATC calculation. period of undesignation of their
termination of the resource and the resource, since they would run the risk
Commission Determination requests for the related transmission of losing the ATC associated with the
service identified in item (3), if any, resource.894 EEI and Entergy contend
1539. The Commission generally should be evaluated as a single request, that the result of such a policy would be
adopts the NOPR proposal to continue and approved or disapproved as such. that the industry would no longer be
to require network customers and the We specifically direct transmission able to take advantage of the diversity of
transmission provider’s merchant providers, working through NAESB, to peak loads to make firm sales and
function to undesignate network develop business standards describing purchases, and an almost immediate
resources or portions thereof in order to the procedures for submitting and shortage of firm energy sources to serve
make certain firm, third-party sales from processing requests for concomitant network and native loads. Duke argues
those resources. In particular, network evaluations of transmission requests and that the approach of not compelling
customers and the transmission temporary terminations. When network customers to risk losing the
provider’s merchant function may only processing such requests, the evaluation ATC associated with their designated
enter into a third-party power sale from of the transmission service requests resources beyond the period that the
a designated network resource if the identified in item (3) should take into resource is designated would be the
third-party power purchase agreement account the undesignation of the comparable approach vis-à-vis point-to-
allows the seller to interrupt power network resources identified in the point customers seeking to temporarily
sales to the third party in order to serve request for termination. However, the redirect their service.
the designated network load. Such evaluation of the transmission service 1545. Southern argues that to treat a
interruption must be permitted without requests in item (3) should be processed redesignation as an entirely new
penalty, to avoid imposing financial taking proper account of all competing application for network resource
incentives that compete with the transmission service requests of higher designation would appear to depart
network resource’s obligation to serve priority. from existing tariff requirements and
its network load. 1542. Consistent with the unnecessarily limit the reliability of
1540. We clarify that requests to requirements for requests for network customers’ service. It also
undesignate network resources that are designation of new network resources, argues that such an approach would be
submitted concurrently with a request the new OASIS functionality should in contravention with section 217(b)(4)
to redesignate those network resources also allow for queries of requests to of the FPA, which directs the
at a specific point in time shall be undesignate and redesignate network
sroberts on PROD1PC70 with RULES

considered temporary terminations. resources. In accordance with section 893 E.g., Duke, EEI, Entergy, Exelon, MDEA Reply,

Conversely, requests to undesignate 37.6 of the Commission’s regulations,892 Northwest Parties, Pinnacle, Progress Energy, South
Carolina E&G Reply, Southern, TDU Systems Reply,
network resources submitted without such requests must be able to be queried TranServ, and WSPP Reply.
any concurrent request to redesignate 894 E.g., Duke, EEI, Entergy, Progress Energy,

those network resources shall be 892 18 CFR 37.6. South Carolina E&G Reply, and TranServ.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00200 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12465

Commission to act in a manner that Commission Determination resource for a specific amount of time
facilitates the planning and expansion 1549. In response to the many prior to the commencement of an off-
of facilities to meet the reasonable needs requests and comments, we clarify that system sale. In many instances, EEI
of LSEs to satisfy the service obligations a request for termination of a network argues, short-term firm power sales are
of the LSEs. Southern contends that the resource that is concurrently paired made with relatively little lead time,
NOPR proposal would create with a request to redesignate that particularly after events such as forced
administrative burdens on transmission resource at a specific point in time will outages or unusual weather conditions.
providers, potentially treat network not result in the network customer EEI and PNM–TNMP argue that
service as an inferior product to long permanently forfeiting rights to use that requiring transmission providers or
term point-to-point transmission resource as a designated network network customers to undesignate a
service, and introduce a substantial resource. Any change in ATC that is specific amount of time prior to an off-
deterrent against optimization of determined by the transmission system sale would foreclose the
network resources by network provider to have resulted from the possibility that firm sales could be made
customers. temporary termination shall be posted with short lead times. That, EEI argues,
1546. On the other hand, Great on OASIS during this temporary period. would adversely affect the sales market,
Northern initially requests that ATC not We agree that requiring network without having any impact on ATC on
be set aside for a former network customers making temporary the path used by the network resource
resource in anticipation that it might be terminations to permanently forfeit because the network resource would not
designated as a network resource at rights to use this ATC would be undesignated. In EEI’s view,
some time in the future. In order to significantly reduce or eliminate firm imposing lead times on undesignations
ensure comparable treatment for all third-party power sales. We emphasize, of network resources would also result
transmission service customers, Great however, that a request to terminate a in treating network and native load
Northern argues, the Commission network resource that is not customers less favorably than point-to-
should place new requests to designate accompanied with a request to point customers. EEI points out that the
network resources at the end of the pro forma OATT does not impose any
redesignate that resource at a specific
transmission queue, regardless of the minimum lead times on firm redirects of
point in time is to be considered an
prior designation of those resources. point-to-point transmission service
indefinite termination. After an
Great Northern clarifies on reply that, pursuant to section 22 of the pro forma
indefinite termination of a resource, the
while ATC should not be set aside for OATT or reassignment of transmission
network customer has no continuing
former network resources in service pursuant to section 23 of the
rights to the use of such resource and
anticipation that it might be designated OATT, despite the fact that advance
future requests to designate that
as a network resource at some notice of redirects might make the
resource would be processed consistent
unspecified time in the future, it has no resultant ATC more marketable.
with section 30.2 as a designation of
objection to setting aside ATC to be 1552. Most commenters, however,
used by a formerly designated network new network resource. appear to support the establishment of
1550. We disagree with
resource after a temporary, specified a minimum amount of time prior to
NorthWestern’s argument that, once
period of undesignation such as one operation that the transmission provider
upgrades specified through the
month or one season. and other network customers should be
1547. NorthWestern, in its reply interconnection process have been
required to terminate a network
comments, disagrees with Great installed, the generator can be specified
resource to ensure that the appropriate
Northern’s initial comments that new as a network resource by any customer,
set of network resources are included in
designations be placed at the end of at the time of commercial operation of
the ATC calculation, although they
transmission service queue regardless of the generator or at any time in the express widely varying opinions on
the prior designation of those resources. future. The Commission has long noted what period of time would be
NorthWestern argues that such a policy that the generator interconnection appropriate.
would unduly discriminate against the process is separate and independent of 1553. Ameren and Pinnacle contend
network customer who is paying for the the acquisition of transmission service that the amount of time prior to
use of the entire transmission system for the same generator.895 The fact that operation that the transmission provider
and grant an undue preference to the system upgrades may be required to and other network customers should be
point-to-point customer. NorthWestern interconnect a generator does not mean required to terminate a network
also argues that the proposal that ATC any network customer is entitled to the resource should be linked to the
not be set aside for an undesignated use of that generator at all times, even frequency of the calculation that gets
network resource appears to conflict in the event that the network customer standardized in the ATC process.
with the Commission’s standard indefinitely terminates the designation Pinnacle contends that, if the
interconnection procedures for large of that resource. The integration of undesignation and redesignation are
and small generators. Once all upgrades network resources with different performed on OASIS as they propose,
specified through the interconnection network customers presents different ATC could be recalculated and posted
process have been installed, effects and flows on the transmission immediately following the
NorthWestern contends that the system that must be evaluated by the undesignation or redesignation. Ameren
generator can be specified as a network transmission provider. contends that it cannot comment further
resource by any customer, at the time of (3) Minimum Lead-Time until the parameters of the ATC process
commercial operation for the generator are defined. FirstEnergy states that the
or at any time in the future. Comments amount of time should be consistent
1548. TAPS appears to support a 1551. EEI and Entergy argue that the with the time periods required in
sroberts on PROD1PC70 with RULES

requirement that transmission Commission should not require markets, and that outside of markets,
customers get back in the queue when transmission providers or network times should be established that
re-designating resources, so long as the customers to undesignate a network coincide with such markets. Southern
rules apply to transmission providers as argues that the current practice, under
well as network customers. 895 See, e.g., Order No. 2003 at P 118, 744. which a resource is undesignated when

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00201 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12466 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

it schedules point-to-point transmission 1558. We find it unnecessary to network customer. EEI and NRECA
service for an off-system sale, provides incorporate into the pro forma OATT contend that requiring formal
adequate time to ensure that the provisions relaxed rules for changing undesignations is substantially more
appropriate set of network resources is the undesignation of network resources cumbersome for network customers and
included in the ATC calculation. at any time to handle system transmission providers making off-
1554. PJM notes that, under its emergencies, force majeure events, system sales.
system, a generator resource with excess forced outages or unusual weather 1561. Progress Energy and TranServ
capacity can undesignate the excess conditions, as suggested by some argue that network customers should
resource on a ‘‘day ahead’’ basis. PJM commenters. Other procedures such as not have to go through the process of
believes that this is the proper amount those in NERC’s standard for Capacity & redesignating a network resource as new
of time needed to ensure resource Energy Emergencies, EOP–002–2, or the when the network customer once again
adequacy. PJM argues that a generator possible use of capacity benefit margin, needs to use this resource to serve
should not, under any circumstance, are more appropriate to deal with network load. TranServ argues that such
change the designation of its resource legitimate system emergencies. Outside a transaction is exactly analogous to a
‘‘same day.’’ the context of legitimate system redirect of firm point-to-point service on
1555. TranServ argues that, at a emergencies, network customers should a firm basis and requests clarification of
minimum, a request for undesignation rely on appropriate planning and whether the provider should evaluate a
should be supplied no later than the operation, rather than relaxed rules for request to undesignate a network
firm scheduling deadline so that designation of network resources. resource concomitantly with the
released capacity may be acquired on a 1559. We disagree with EEI’s assessment of that same customer’s
non-firm basis. If that data were argument that requiring a minimum point-to-point request, as is done with
required to be submitted earlier than the lead-time will result in treating network redirects on a firm basis.
and native load customers less favorably 1562. NRECA states that the
scheduled deadline, TranServ suggests
than point-to-point customers. In undesignation requirement is too
the transmission provider may be able
particular, EEI is incorrect in its burdensome and, therefore, the
to offer incremental capacity for firm
statement that the OATT does not Commission should adopt a
sales. TranServ requests that the comparability requirement that would
impose any minimum lead times on
Commission establish in the pro forma allow network customers to utilize the
firm redirects of point-to-point
OATT some nominal timeframe for practice that many public utility
transmission service or reassignments of
network customers to provide to the transmission providers use today: i.e.,
transmission service. Firm point-to-
transmission provider their planned use use designated resources for firm off-
point customers are also subject to
of designated resources to serve loads. system transactions or third party uses
deadlines for scheduling redirects
1556. Nevada Companies requests pursuant to section 22.2 of the pro without having to go through the
that, due to some system emergencies, forma OATT. Furthermore, we find that designation, undesignation and
force majeure events, and hourly EEI has provided no compelling redesignation process. NRECA argues
scheduling of tie-line changes, they be evidence to support its argument that that existing scheduling procedures
allowed to change undesignation of the adverse impacts on the market for have allowed transmission providers to
network resources at any time to handle firm energy with short lead times deliver power from their designated
these types of events. justifies having no minimum lead time. network resources for off-system
Commission Determination merchant purposes reliably and should
(4) General perform equally well for network
1557. Commenters presented many Comments customers, provided they still pay a
alternative views in response to the point-to-point charge for the
1560. Several commenters argue that
Commission’s request in the NOPR for ‘‘outbound’’ leg of a delivery to a
the Commission should not require
comments on the appropriate minimum neighboring network to serve the
network customers or the transmission
lead-time prior to operation that the customer’s network load on the
provider to make formal modifications
transmission provider and other neighboring network. NRECA argues in
to their designations of network
network customers should be required its reply comments that, whatever the
resources when they make firm sales to
to terminate a network resource to Commission decides to do,
third parties from those resources.896
ensure that the appropriate set of comparability is the most important
EEI and Southern argue that the practice
network resources are included in the principle when considering the
of most network customers and
ATC calculation. In consideration of transmission providers in the ten years undesignation policy and that
these comments, the Commission finds since the Commission issued Order No. ‘‘grandfathering’’ agreements which
that the appropriate requirement is that 888 has been that a network resource is would allow transmission providers to
network customers not be permitted to undesignated for any period for which essentially get around this requirement
make firm third-party sales from any the customer requests firm point-to- would allow undue discrimination to
designated network resource without (1) point transmission service from the continue. EEI disagrees in its reply
undesignating that resource for the generator or a third party. This practice, comments with NRECA’s assertion that
period of the third-party sale pursuant EEI argues, has not resulted in any transmission providers currently have
to pro forma OATT section 30.3 and (2) adverse impacts on reliability or on the an advantage over network customers,
providing notice of such undesignation availability of transmission service and arguing that the same standards apply to
before the firm scheduling deadline (10 that, to the contrary, selling energy from the transmission provider’s merchant
a.m. the day before service commences). network resources on a firm basis function and network customers when
We find that this requirement strikes the instead of a non-firm basis frees up firm they seek to make off-system sales from
sroberts on PROD1PC70 with RULES

appropriate balance, allowing transmission capacity that otherwise network resources.


undesignated capacity to be acquired on would have to be reserved for the 1563. PNM–TNMP contends that the
a non-firm basis but not creating an Commission has held that formal
undue adverse effect on third-party 896 E.g., EEI, NRECA Reply, PNM–TNMP, and undesignation and redesignation are not
sales. Southern. required, so long as the transmission

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00202 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12467

provider treats its own resources and revised network service agreements resources have low capacity factors and,
the network resources of network reflecting the changes. therefore, their transmission
customers comparably. PNM–TNMP 1567. South Carolina E&G argues in reservations are frequently
and Pinnacle further argue that to its reply comments that off-system sales underutilized. They request that
require formal undesignation and of firm power are typically in the form network customers be given the ability
redesignation would appear to do of a slice-of-system sale. South Carolina to optimize their transmission
nothing more than impose an extra layer E&G requests that the Commission purchases by bringing energy into the
of administration to the management of provide guidance for how to treat such host transmission provider’s system
network resources, making power sales a sale of power, suggesting that the from other designated network
more difficult and potentially reducing transmission provider be permitted to resources in times when they are not
financial benefits to end use customers. undesignate a slice of a system using their peaking designated
Bonneville argues that the sufficient to support the firm power sale resources.
Commission’s proposals regarding the and then, at the conclusion of the sale, 1570. MDEA, Progress Energy, and
use of network resources for surplus redesignate that slice of the system as a Entergy request that, for reliability and
sales are likely to raise the cost to network resource. economic reasons, network customers
consumers. 1568. While generally supporting the be given the flexibility to substitute new
Commission’s proposal to continue to designated network resources without
1564. Duke requests that the allow network customers and the abandoning the original transmission
Commission clarify that any product transmission provider, with respect to queue position of an existing designated
that is not ‘‘designatable’’ as a network its native load, to undesignate network network resource.899 If the Commission
resource by a buyer may be sold by a resources to allow them to make sales to does not change its proposal in order to
seller that happens to be a network third parties, some commenters seek provide network customers with this
customer, without having to certain changes, consideration, or flexibility, Progress Energy contends
undesignate any network resources. clarification by the Commission.898 EEI, that point-to-point service will be a
1565. Suez Energy NA requests that joined by TDU Systems on reply, argue superior service to network service.
the Commission ensure that a utility that the Commission should modify its 1571. Entergy states that it is
cannot use redesignation to hoard statement that network customers important for the Commission to
transmission capacity in order to should be permitted to undesignate recognize that the undesignation of
deprive independent power producers network resources ‘‘on a short-term network resources can be used by
of access to the grid. It contends that a basis to make off system sales.’’ They network customers as a means of
utility could consistently hold argue that nothing in Order No. 888, the allowing merchant generators the
transmission to serve generation that Commission’s decisions, or the public opportunity to displace existing
never runs for economic reasons and, interest requires that network resources resources in serving network and native
the day before power flows, redesignate be undesignated only for short-term load. It argues that the Commission
that transmission to accommodate a sales. They further argue that such sales should be wary of limiting the ability of
third-party purchase, effectively using need not be ‘‘off-system.’’ Progress a network customer to undesignate
Energy argues that the Commission network resources, as any such
its ability to redesignate network
should only allow transmission restriction will have broader
transmission capacity to hoard scarce
customers to undesignate network implications than just the ability of
ATC. In order to prevent potential
resources to make firm off-system sales network customers, including the
abuse, Suez Energy NA agrees with the
for a term which the transmission
NOPR proposal to require transmission transmission provider’s wholesale
customer has adequate generation
providers to use the same OASIS merchant function, to sell that resource
reserves to serve its network load. In its
procedures to designate and terminate off-system with point-to-point service.
view, the transmission provider also 1572. Entergy also requests that the
network status for themselves that they must have the authority to deny the
apply to network customers. Commission clarify that, while network
designation or undesignation of the
customers cannot redirect network
1566. If the Commission requires network resources if the transmission
service, nothing in this prohibition
formal designations and undesignations, provider determines that it needs the
prevents transmission providers from
EEI asks the Commission to clarify network resources to preserve the
studying requests to designate new
whether it is changing its policy that it reliability of its transmission system or
network resources as displacements of
is not necessary to modify service to ensure that there is sufficient
existing network resources. It argues
agreements in such circumstances in transmission capability to support the
that preventing network customers from
order to avoid requiring transmission requested changes. NRECA disagrees on
using automated study functions would
providers to make numerous filings reply, arguing that granting transmission
significantly hinder the ability of these
amending service agreements.897 If providers the authority to deny
customers to substitute their existing
formal undesignations are required, EEI undesignation requests would give them
long-term resources with short-term
argues on reply that each transmission too much discretion and the perfect
purchases of energy and capacity from
provider would be required to submit a opportunity to discriminate.
1569. Progress Energy agrees with the merchant generators when it is
revised application for network service economical to do so.
under section 29.2 of the pro forma Commission that network service
involves the entire transmission 1573. TDU Systems argue that
OATT both at the time the resource was network customers (and transmission
undesignated and at the time that provider’s system and does not involve
a contract path like point-to-point providers to the extent they serve native
resource was redesignated. EEI also load on other systems) should be able to
argues that formal undesignation would service. It also agrees that the delivery
schedule output on a firm basis from
sroberts on PROD1PC70 with RULES

require the execution and filing of of a network resource once inside the
system does not need to be redirected. 899 In its reply comments, MDEA requests that
897 See Virginia Electric and Power Co., 81 FERC Progress Energy notes that peaking any such flexibility afforded to transmission
¶ 61,125 at 61,111–12 (1997), reh’g denied, 82 FERC providers also be available to network customers on
¶ 61,034 (1998). 898 E.g., EEI, Pinnacle, and Progress Energy. a non-discriminatory basis.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00203 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12468 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

network resources on one system to submitting undesignations and/or transmission providers serving their
serve their network loads on redesignations entails. We disagree with native loads, are subject to these
neighboring systems without having to Xcel’s argument that most economy requirements for designation and
designate and redesignate network energy purchases that benefit its native undesignation of network resources.
resources among the various load customers likely will not take place Section 28.2 of the pro forma OATT
transmission providers’ control areas. if undesignation of network resources is clearly provides that transmission
TDU Systems state this would permit required prior to firm, third-party sales. providers are required to designate
LSEs that serve across multiple systems First, the requirement to undesignate resources and loads in the same manner
to come closer to replicating the network resources only applies to firm as any network customer. We encourage
economic dispatch of control area sales, while typical non-firm economy parties suspecting that transmission
operators, significantly reducing the energy transactions would not require providers or other network customers
cost of discharging their service undesignation. Second, undesignating a are not conforming to the requirements
obligations to the customers they serve. network resource is not unduly for designating or undesignating
1574. Xcel opposes requiring a burdensome, consisting only of network resources to report their
transmission customer to undesignate a electronically submitting several items concerns using the Commission’s
network resource even in a situation of information, as described above. Enforcement Hotline.
where the resource is used only Therefore, we do not believe that a 1581. EEI has requested clarification
transiently to provide off-system sales, transaction prevented purely as a result of whether the Commission is changing
arguing that such policy would have of the requirement to undesignate its policy that transmission providers do
significant adverse consequences for network resources would have provided not need to modify network service
customers across the country. It points any significant economic value had it agreements when network resources are
out that it is native load customers that taken place. undesignated and redesignated. We
frequently benefit from purchase of 1577. We find that requests to allow have not proposed and do not intend to
economy energy and that, if an ‘‘informal undesignations’’ appear to be begin requiring that network customers
undesignation was required to deliver simply requests to not require file modified service agreements when
economy energy, most such transactions undesignations at all. Since the salient network resources are designated or
likely would not occur. Xcel also argues feature of requiring an undesignation is undesignated. As we explained in
the NOPR concepts relating to that the proper account is taken of the Dayton Power and Light Co.,900
designation of network resources and effects on ATC, informal ‘‘changes in network resources may
justification of economy energy undesignations, which do not take require the customer to file a request
purchases are irrelevant in the context proper account of the fact that a under OASIS, but a change to the
of an RTO where energy is procured and resource is no longer a designated information recorded initially in the
dispatched throughout the RTO on a network resource, appear to serve no network service agreement is not a
security constrained economic basis. purpose. requirement.’’ EEI also argues that, if
1575. EEI, joined by TDU Systems on 1578. With regard to PNM-TNMP’s formal undesignations are required,
reply, requests that the Commission argument that the Commission has held then each transmission provider would
clarify that any changes to the that formal undesignation and be required to submit a revised
procedures for designating and redesignation are not required, so long application for network service under
undesignating network resources apply as the transmission provider treats its section 29.2 of the pro forma OATT,
only to designations made after the own resources and the network both at the time the resource was
Final Rule becomes effective, in order to customer’s resources comparably, we undesignated and the time that resource
avoid substantial adverse impacts on the believe PNM-TNMP misunderstands our was redesignated. We disagree. There is
reliability of service to network and policies. We note that PNM-TNMP no requirement that a transmission
native loads. Duke and Pinnacle request provides no citation to Commission provider submit a revised application
that the Commission require NAESB to precedent to support its statement. for network service every time a
develop standards that address 1579. Duke requests clarification as to resource is designated or undesignated.
undesignation and redesignation and whether a network customer must 1582. In response to a request by
allow sufficient time for the NAESB undesignate a network resource in order South Carolina E&G, we clarify that firm
process and for OASIS tools to be to make a third-party sale from that third-party sales may be made from an
developed and approved, prior to the resource if the third-party sale would undesignated portion of a network
implementation of a new policy. not itself qualify to be designated as a customer’s network resources (i.e., a
TranServ asks that the undesignation of network resource. We reiterate the ‘‘slice-of-system sale’’), so long as all of
network resources be supported on existing requirement that designated the applicable requirements are met. In
OASIS. network resources must not be particular, the network customer must
committed for sale to non-designated submit undesignations for each portion
Commission Determination third-party load or include resources of each resource supporting the third-
1576. We disagree with commenters that otherwise cannot be called upon to party sale. If the undesignation is
arguing that formal undesignations and/ meet the network customer’s network temporary, then the request must be
or redesignations of resources used to load on a noninterruptible basis. We accompanied by a request to redesignate
make firm third-party sales should not find that a resource is ‘‘committed for the resource(s) on a specific date. When
be required. The undesignation and sale to a non-designated third party the undesignation takes effect, the
redesignation requirements exists not load’’ if a power purchase agreement for network customer must update the
only to promote reliability, but also to the sale from that resource provides for capacities specified in its list of
prevent undue discrimination, promote penalties if service to the third party is designated network resources posted on
sroberts on PROD1PC70 with RULES

comparable treatment of customers, and interrupted in order to serve the OASIS.


increase the accuracy of ATC designated network load. 1583. We agree with EEI and TDU
calculations. We find that the interest in 1580. In response to comments by Systems’ comments that there should be
advancing these policy goals overrides EEI, NRECA, and Suez Energy NA, we
the minimal burden and cost that reiterate that all parties, including 900 93 FERC ¶ 61,331 at 62,128 (2000).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00204 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12469

no minimum term for undesignations. network resource, as long as the dispatched throughout the RTO on a
We also agree with EEI and TDU network customer uses that ATC to security constrained economic basis. We
Systems’ arguments that network designate an alternate resource. We agree that Day 2 RTOs do not use the
customers should not be restricted to disagree. Granting this request would, physical rights model contemplated
temporarily undesignating network without any apparent justification, put under the pro forma OATT and, hence,
resources only for use in off-system point-to-point customers seeking ATC not all the provisions discussed here are
sales, and clarify that network freed up by an undesignation at a directly applicable to Day 2 markets.
customers are not so restricted. disadvantage. We also disagree that, if However, as we explain in section
1584. We agree with Progress Energy the Commission does not allow network IV.C.2, RTOs and ISOs must make the
that network customers should only customers this flexibility, point-to-point necessary filings to comply with the
make firm third-party sales when they service will be a superior service to Final Rule, or demonstrate that their
have sufficient generation reserves to network service. Progress Energy seems existing tariff provisions are consistent
serve their loads. However, the purpose to be arguing that the point-to-point with or superior to the terms of the
of the pro forma OATT is to provide customer’s ability to engage in a redirect revised pro forma OATT.
nondiscriminatory transmission access, affords that customer more flexibility 1591. We agree with parties arguing
not to enforce generation adequacy than the network customer. We point that network customers should not be
requirements. out that redirects of point-to-point required to use the new NAESB
1585. With regard to Progress Energy’s service on a firm basis are only on an processes and OASIS tools to be
request for flexibility to evaluate ‘‘as-available’’ basis. Firm point-to-point developed in response to this section
potential impacts to the transmission customers cannot redirect unless ATC is until such time as the NAESB standards
system related to the undesignation and available to support such a redirect after and OASIS functionality have been
redesignation of network resources, we all higher-priority requests have been developed and implemented. However,
find that situations where accommodated. once the new standards and
undesignations cannot be 1588. Entergy has requested functionality are in place, network
accommodated due to transmission clarification that, while network customers must use these new
constraints should be extremely rare, customers cannot redirect network procedures to undesignate (whether
such as highly-extraordinary service, nothing in this prohibition temporarily or as part of an indefinite
counterflow situations. In such rare prevents transmission providers from termination) any network resources,
situations, the transmission provider studying requests to designate new regardless of the date that those
should attempt to remedy the situation network resources as displacements of resources were originally designated.
without denying the undesignation. If it existing network resources. Although
is determined that the resource cannot 7. Clarifications Related to Network
Entergy’s request is unclear, we reiterate
be undesignated without jeopardizing Service
that redirects are not allowed within the
reliability, then the transmission context of network service and that a. Secondary Network Service
provider may deny the request for network customers are not ‘‘first in line’’ 1592. Section 28.4 of the existing pro
undesignation. to use ATC freed up by their forma OATT allows a network customer
1586. We share NRECA’s concern that undesignation of another network to deliver energy to its network load
allowing transmission providers to deny resource. Such requests must be from non-designated network resources
undesignations for reliability reasons processed taking proper account of all on an as-available basis without
could give a direct market competitor a competing transmission service requests additional charge, referred to as
significant opportunity to discriminate, of higher priority. secondary network service. In Order No.
but must weigh this concern against our 1589. We disagree with TDU System’s 888, the Commission described such
significant interest in preserving argument that network customers energy as non-firm economy energy
reliability. We point out that should be able to schedule output on a purchases used to displace firm network
transmission providers denying requests firm basis from network resources on resources.902
for service or changes to service because one system to serve their network loads 1593. The use of secondary network
of reliability concerns must post a on neighboring systems without having service to deliver purchased power
description of such denials in to designate and redesignate network when a network customer is making off-
accordance with section 37.6(e)(2) of the resources among the various system sales has been raised in several
Commission’s regulations.901 Again, we transmission providers’ control areas. Commission investigations and audits.
encourage any parties with concerns Allowing network customers to not In Idaho Power, the Commission
about denials of service or changes to formally undesignate and redesignate accepted a settlement with Idaho Power
service by a transmission provider for network resources, even only when related to Idaho Power’s incorrect use of
reasons of reliability to report their using those resources to serve their the native load priority to access its
concerns to the Commission’s network loads on neighboring systems, transmission system.903 In Idaho Power,
Enforcement Hotline. will necessarily result in inaccurate the utility’s wholesale merchant
1587. We deny requests by MDEA, evaluations of ATC. We reiterate that function purchased power outside of
Progress Energy, and Entergy that the burden associated with Idaho Power’s control area to facilitate
network customers be given the undesignating and redesignating the an off-system sale and used secondary
flexibility to substitute new designated resources is particularly light and find network service to bring the purchases
network resources without abandoning that requiring network customers to into Idaho Power’s control area.904 In
the original transmission queue position make temporary undesignations when accepting the settlement, the
of an existing designated network making third-party firm sales is thus Commission stated that ‘‘[i]t is
resource. These parties seem to be justified in light of the ATC-related axiomatic that the native load priority
sroberts on PROD1PC70 with RULES

requesting that a network customer be benefits.


allowed to be ‘‘first in line’’ to use the 1590. Xcel argues that the concepts 902 Order No. 888 at 31,751.
ATC freed up by an undesignation of a relating to designation of network 903 Idaho Power Co., 103 FERC ¶ 61,182 at P 2
resources are irrelevant in the context of (2003) (Idaho Power).
901 18 CFR 37.6(e)(2). an RTO where energy is procured and 904 Id. at P 4.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00205 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12470 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

cannot be used to complete sales that secondary service for this non-economy 1599. Although Powerex supports the
are not necessary to serve native energy, thereby interfering with its Commission’s restriction on the proper
load.’’ 905 In MidAmerican, the service obligations. To avoid such cases, use of secondary service, it also states
Commission issued an audit report that EEI, Pinnacle, and PGP recommend that that determining whether or not an
contained a finding that MidAmerican’s secondary service not be limited to import would qualify as ‘‘economy
wholesale merchant function used economy energy only. NRECA states energy’’ would be difficult. Powerex
network service instead of point-to- that the Commission’s proposed requests that the Commission
point service to deliver short-term limitation on the use of secondary implement specific rules in advance of
energy purchases to its control area that service would prevent network such transactions to resolve uncertainty.
were not used to serve MidAmerican’s customers from meeting their native It suggests a capacity test to prevent
native load.906 load obligations in cases of extreme preferential acquisition of generation
weather and power outages. NRECA capacity, a tariff prohibition on the use
NOPR Proposal asks the Commission to state explicitly by the network customer or its energy
1594. In the NOPR, the Commission in section 28.4 of the pro forma OATT affiliates of any export transmission
proposed to clarify that a network that secondary service may not be used capacity made available on another
customer may not use secondary to facilitate off-system third party sales, intertie, and the modification of
network service to import energy onto but rather must be used to import power business practices governing
its system to support an off-system sale needed to serve network load curtailment. In reply, Alberta
if the purchased power does not economically and efficiently. Entergy Intervenors agree with Powerex’s
displace the customer’s own higher cost suggests the Commission abandon the proposed changes to curtailment
generation. The Commission therefore limitation and specify simply that practices, but disagree with the other
proposed to modify section 28.4 of the secondary service cannot be used to two elements. Alberta Intervenors assert
pro forma OATT to state that a network serve loads other than the network or that the tariff prohibition causes
customer may use secondary network native load. inefficient use of ATC and that the
service only to deliver economy energy 1597. Others argue that the restriction capacity test is not a stand-alone test
and to define ‘‘economy energy’’ as of secondary service to only economy and, as a result, would only be helpful
energy purchased by a network energy would have unintended as a supplement to the ‘‘economy
customer that displaces the customer’s consequences regarding the purchase of energy’’ test.
own higher cost generation for the renewable resources. Emerald, Flathead, 1600. Some participants raise other
purpose of serving the customer’s and the Northwest Parties state that, for issues not addressed in the NOPR.
designated network loads. The reasons of customer demand or South Carolina E&G asks that the
Commission further explained that all contractual obligation, network Commission clarify its policy on
participants engaging in purchases for customers may be required to purchase purchases of economy energy, as well as
resale must compete on a comparable renewable power that generally is more provide a clear definition of the
basis and use point-to-point service to expensive than traditional thermal or acceptable trading practices—notably
complete all segments of a purchase for hydro electric generation. These parking, hubbing, and lending—under
resale off-system. purchases could displace less expensive the current pro forma OATT. Emerald
non-renewable resources, resulting in and Flathead request the Commission to
(1) Overview the need for the network customer to revise the definition of ‘‘network load’’
Comments make off-system sales of the non- in section 1.24 of the pro forma OATT
renewable resources. Emerald, Flathead, to allow point-to-point and network
1595. Several commenters agree with and Northwest Parties suggest that the
the Commission and support the service to the same discrete point of
Commission revise the definition of delivery. Morgan Stanley asks that the
proposed clarification regarding the use ‘‘economy energy’’ to include an
of secondary network service.907 Alberta Commission explain why using
exception for renewable energy. TAPS secondary service to make an off-system
Intervenors state that such a restriction raises a similar issue, asking the
ensures fair competition among network purchase while there is any off-system
Commission to clarify that economy sale during the same interval is
customers and preserves the entitlement purchases as well as substitute
of native load customers. improper and whether the Commission
resources qualify for use of secondary will prohibit such activity only if the
1596. Other participants oppose the service.
proposal, arguing that it is too broad and off-system purchase and sale are part of
1598. EEI argues that the proposed
would interfere with legitimate activity a single transaction. Finally, Xcel argues
limitation on secondary service would
by network customers.908 EEI points out require all network customers to engage that the concepts relating to designation
that, if a network customer is using all in a specific form of Commission- of network resources are irrelevant in
available network resources but is still regulated economic dispatch, while the context of an RTO where energy is
purchasing energy from non-designated requiring transmission providers to procured and dispatched throughout the
network resources to meet its peak evaluate each resource and become RTO on a security constrained economic
native load, the network customer ‘‘dispatch police.’’ Entergy, SPP, and basis.
would need to rely on secondary service PGP agree. They assert that calculating Commission Determination
to transmit this purchase. In EEI’s view, the ‘‘cost’’ of power is problematic, 1601. In general, the Commission
the Commission’s proposal would inherently subjective and burdensome agrees with parties that favor an
prevent this customer from using because transmission providers lack the expansion of the proper use of
necessary knowledge to perform this
secondary network service. Although
905 Id.
analysis. EEI, Entergy, SPP, and PGP
we affirm our finding in
sroberts on PROD1PC70 with RULES

906 MidAmerican Energy Co., 112 FERC ¶ 61,346


instead suggest that the Commission
at P 6 (2005). MidAmerican,909 the Commission
907 E.g., Alberta Intervenors, Southern, Suez
conduct periodic audits of secondary
Energy NA, and TAPS. service to ensure compliance with the 909 MidAmerican Energy Co., 112 FERC ¶ 61,346
908 E.g., EEI, Entergy, Northwest Parties, NRECA, requirements of OATT section 28.4 at P 6 (2005) (MidAmerican). Following an audit,
Pinnacle, PGP, Southern, and Xcel. rather than transmission providers. the Commission found that MidAmerican’s

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00206 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12471

recognizes that there are instances point-to-point service shall not be made customer could also request to
outside the proposed definition of before certain specified periods (more redesignate its original network resource
economy energy that warrant the use of than 60 days in advance for monthly by making a request to designate a new
secondary service in order to serve service, more than 14 days in advance network resource. Alternatively, a
network loads reliably. The Commission for weekly service, etc.). TDU Systems network customer could use secondary
therefore declines to adopt the states that some of its members network service when it wants to
definition of economy energy proposed currently use secondary service to substitute a non-designated network
in the NOPR and, instead, will retain access economy off-system purchases resource for a designated network
the existing section 28.4 that permits where intervening transmission resource on an as-available basis.
use of secondary network service ‘‘to constraints preclude the designation of
Comments
deliver energy to its Network Loads.’’ those resources as network resources for
1602. With respect to Powerex’s long periods of time. Application of the 1609. MISO strongly supports the
comments, we reject the requested non-firm point-to-point service request Commission’s clarification stating that
clarifications as Powerex has not fully deadlines would impair TDU Systems’ network service is not a directable
supported the use of its proposed ability to rely on secondary service in service and believes that the proposal
capacity test or other measures and has those instances since they would extend appropriately clarifies the Commission’s
not demonstrated that such test would beyond the timing requirements set policy on redirect service. TDU Systems
not preclude legitimate uses of this forth in section 18.3. and NRECA, however, believe that the
priority as noted in the NOPR. If parties Commission should allow redirects of
suspect inappropriate use of secondary Commission Determination network service to deliver an LSE’s
network service, they may report the 1606. The Commission clarifies that resources. TDU Systems assert that
suspected activity to the Commission’s secondary service must be requested in redirect of network service is critical to
Enforcement Hotline or file a compliant accordance with section 18, including LSEs serving native load across multiple
with the Commission pursuant to FPA the timing restrictions set forth in transmission systems because it allows
section 206. Furthermore, the section 18.3, of the pro forma OATT. the amount of flexibility necessary to
Commission’s staff will continue to Secondary service is on an as-available manage power supply costs. In addition,
provide oversight of all tariff-related basis, and network customers should in TDU Systems’ view, redirects have no
activities through its enforcement not be permitted to lock in such service effect on system reliability.
program. in advance of other non-firm uses of 1610. EEI argues on reply that it is
available transmission. Allowing lower- unclear why redirects of network
(2) ‘‘On an as-available basis’’ service should be allowed. The
priority secondary service to have a
1603. Section 28.4 of the existing pro scheduling advantage over non-firm advantage of redirecting firm point-to-
forma OATT allows a network customer transmission would be inappropriate point service is that the customer does
to use secondary network service to and would discourage the use of non- not have to pay an additional charge for
deliver energy purchases to its network firm transmission service, thereby transmission service. However, both
load from non-designated resources ‘‘on minimizing the revenue credits from TDU Systems and NRECA agree that
an as-available basis.’’ However, the non-firm transmission service that network customers should pay an
current pro forma OATT does not benefit all firm transmission customers. additional charge for transmission
specify how a network customer must service from network resources to off-
arrange for secondary network service. (3) Redirect of Network Service system loads.
1607. The current pro forma OATT 1611. Sacramento alternatively
NOPR Proposal
does not include any provision to recommends that the Commission
1604. In the NOPR, the Commission change the point of receipt for an off- remove the ban on off-system sales in
proposed to modify section 28.4 of the system designated network resource in order to maximize efficiency in
pro forma OATT to clarify that a a manner similar to redirect of point-to- allocating transmission capacity.
network customer does not need to file point service. We are aware, however, Occidental requests that the
an application for network service to that several transmission providers have Commission place all transmission,
receive secondary service. Instead, the posted business practices that allow including on behalf of native load,
customer must merely request such network customers either to substitute under the OATT guidelines to ensure
service on OASIS in a manner an off-system non-designated network that service is provided in a non-
consistent with pro forma OATT resource for a designated network discriminatory fashion.
sections 18.1 and 18.2 (Procedures for resource or to redirect the point of
Arranging Non-Firm Point-to-Point Commission Determination
receipt associated with an existing
Transmission Service). network resource. 1612. The Commission clarifies that
Comments network customers may not redirect
NOPR Proposal network service in a manner comparable
1605. TDU Systems requests that the 1608. The Commission proposed to to the way customers redirect point-to-
Commission clarify that time constraints clarify that network customers may not point service. Point-to-point service
located in OATT section 18.3 are not redirect network service in a manner consists of a contract-path with a
applicable to secondary service. Section comparable to redirect of point-to-point designated point of receipt and point of
18.3 provides that requests for non-firm service, as network service involves no delivery. Network service has no
identified contract path and is, identified contract-path and is therefore
wholesale merchant function used network service
instead of point-to-point service to deliver short-
therefore, not a directable service. not a directable service. Network service
term energy purchases to its control area that were Should a network customer wish to instead provides for the integration of
sroberts on PROD1PC70 with RULES

not used to serve MidAmerican’s native load. The substitute one designated network new network resources and permits
Commission stressed that the use of secondary resource for another, the Commission designation of another network
network service is not for the purpose of serving off-
system sales. Id. at P 6. The modifications to section
stated that it must terminate the existing resource, which has the same practical
28.4 adopted in this Final Rule do not alter that resource and designate a new one. The effect as redirecting network service. If
limitation. Commission explained that the network the customer wants to permanently

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00207 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12472 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

substitute one designated network from network service and serve such use of the transmission system at the
resource for another, it should terminate load with the customer’s behind the customer’s meter would be appropriate
the designation of the existing network meter generation and/or through any as it would demonstrate that, if no
resource and designate a new network point-to-point transmission service.912 power flows to the customer from the
resource. The customer could then 1615. The Commission did not grid occur, that customer has not used
simply request to redesignate its original address the subject of behind the meter nor caused costs to be incurred by the
network resource, if it so desires, by generation in the NOPR. A few grid for the delivery of its energy
making a request to designate a new commenters nonetheless proposed requirements.
network resource. The ability of a revisions to the pro forma OATT to 1617. Some commenters note that the
network customer to also temporarily require netting of a network customer’s Commission has approved PJM netting
substitute one designated network behind the meter generation against provisions that apply to behind the
resource for another is addressed in their network load as described in more meter generation used by non-retail and
section V.D.6. detail below. wholesale customers to serve load.917
1613. The Commission rejects These same commenters further observe
Sacramento’s proposal to remove the Comments that PJM has filed with the Commission
ban on off-system sales. Network service 1616. Some commenters argue that, in to expand participation in its behind the
is not based upon making off-system order to meet the objective of meter generation netting program to
sales, but rather on integrating a eliminating discrimination in the include municipal, electric
network customer’s resources with its provision of open access transmission cooperatives, and electric distribution
load. Transmission providers must take service, the Commission must require transmission customers who take
point-to-point transmission service for comparable treatment between retail network service on the PJM system
off-system sales and network customers native load and network customers by pursuant to a settlement agreement filed
should be treated comparably. The allowing network customers to net by PJM on October 24, 2005 in Docket
Commission also rejects Occidental’s behind the meter generation against No. EL05–127–000.918
request to place all transmission, their network load.913 Specifically, such 1618. Further, both TAPS and AMP-
including on behalf of native load, commenters argue that the Commission Ohio argue that behind the meter
under the pro forma OATT. In Order should modify the current pricing rules generation provides benefits to the
No. 888–A the Commission clarified for network service to allow an LSE’s transmission provider that should be
that a ‘‘transmission provider is not load ratio share to reflect the reduction taken into account as part of system
required to ‘take service’ under its own in load caused by behind the meter planning obligations. For instance,
tariff for the transmission of power that generation serving retail load.914 In AMP-Ohio asserts that utility planning
is purchased on behalf of bundled retail support of this position, these can and should be able to take into
customers.’’ 910 However, the commenters argue that assigning account the ability of customers to
Commission required that transmission transmission-related costs to customers reduce their load on the system with
providers, pursuant to section 28.2 of that do not rely on the transmission behind the meter generation. TDU
the pro forma OATT, must designate provider’s system to serve load is Systems also notes PJM’s representation
network resources and network loads in inconsistent with the Commission’s that allowing municipal and electric
the same manner as any network cost-causation principles.915 For cooperative system participation in
customer. Occidental offers no example, CAC/EPUC contends that behind the meter generation netting
explanation why the existing customer generation does not cause the programs increased reliability and
requirement of section 28.2 is not transmission provider to incur costs demand response opportunities on
sufficient to address its concerns. when power is not being sold to or PJM’s system.919 Similarly, TAPS
b. Behind the Meter Generation taken off the grid. Similarly, AMP-Ohio observes that PJM’s rules reserve the
argues that it is inappropriate to assign right to call upon non-retail behind the
1614. In Order No. 888, in response to
a full load ratio share of transmission- meter generation under certain
customers with load served by ‘‘behind
related costs to behind the meter conditions.
the meter’’ generation that sought to
generation customers that do not use the Commission Determination
eliminate such load from their network
network to the full extent of their load
calculation, the Commission found that 1619. The Commission is not
ratio shares.916 Further, CAC/EPUC
a customer may exclude a particular persuaded to require transmission
load at discrete points of delivery from asserts that measuring the customer’s
providers to allow netting of behind the
its load ratio share of the allocated cost 912 Order No. 888–A at 30,258–61. meter generation against transmission
of the transmission provider’s integrated 913 E.g., TAPS, TDU Systems, AMP-Ohio, and service charges to the extent customers
system. The Commission determined, CAC/EPUC. do not rely on the transmission system
however, that customers electing to do 914 TDU Systems and TAPS also cite Consumers
to meet their energy needs. Commenters
so must seek alternative transmission Energy, 98 FERC ¶ 61,333 at 62,410 (2002)
(requiring that a transmission provider’s retail load in this proceeding have not provided
service, such as point-to-point associated with behind the meter generation be any different arguments that were not
transmission service, for any load that included in the transmission provider’s load ratio fully considered and addressed in Order
has not been designated as network load share to ensure comparability between transmission No. 888, et al. The existing pro forma
for network service.911 In Order No. providers and network customers in the calculation
of load ratio share). OATT already permits transmission
888–A, the Commission stated that it 915 E.g., AMP-Ohio, CAC/EPUC, and TAPS.
would permit a network customer to 916 Citing Occidental Chemical Corporation v. 917 E.g., AMP-Ohio, TAPS, and TDU Systems

either designate all of a discrete load as PJM Interconnection, L.L.C., and Delmarva Power & (citing PJM Interconnection, L.L.C., 107 FERC
network load under the network Light Company, 102 FERC ¶ 61,275 at P 14 (2003) ¶ 61,113 (2004), reh’g denied, 108 FERC ¶ 61,032
sroberts on PROD1PC70 with RULES

(‘‘Access charges for use of PJM’s transmission (2004) (PJM)).


integration transmission service or to 918 This settlement agreement was accepted in
system should be allocated to network customers
exclude the entirety of a discrete load based on a network customer’s actual use of PJM’s PJM Interconnection, L.L.C., 113 FERC ¶ 61,279
system, consistent with the principle of cost- (2005).
910 Order No. 888–A at 30,216. causation.’’); PJM Interconnection, L.L.C., 107 FERC 919 PJM Interconnection, L.L.C., 113 FERC
911 Order No. 888 at 31,736. ¶ 61,113, at P 28 (2004). ¶ 63,024 (2005).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00208 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12473

customers to exclude the entirety of a circumstances and events contributing urge the Commission to reject the
discrete load from network service and to the need for such firm service proposals to require transmission
serve such load with the customer’s curtailments, specific services and providers to refund transmission service
behind the meter generation and customers curtailed (including the charges to curtailed customers. They
through any needed point-to-point transmission provider’s own retail state that transmission providers are
transmission service, thereby reducing loads), and the duration of all such following ATC calculation procedures,
the network customer’s load ratio share. curtailments. TAPS also urges the but the planning process is not
Therefore, the Commission’s existing Commission to move toward maximum structured to overbuild the system to
policy already provides customers with transparency and require that sufficient ensure that no curtailments occur. They
the opportunity to reduce network information be provided for a customer also argue that the rate of return
service costs to the extent a customer is to evaluate whether it has been treated permitted in existing cost of service
not relying on the transmission system fairly as compared to other users of the regulation does not account for the risk
to meet its energy needs.920 As the system including the transmission of loss of curtailment-related revenues.
Commission concluded in Order No. provider. TDU Systems suggests that the Northwest IOUs request the
888–A, transmission customers Commission require investigations into Commission examine whether pro rata
ultimately must evaluate the financial the need for network upgrades when curtailments of transactions to relieve
advantages and risks and choose to use Level 5 Transmission Loading Relief transmission constraints unnecessarily
either network integration or firm point- (TLR) procedures are repeatedly impose burdens on transmission
to-point transmission service to serve employed. It also suggests that all Level customers, because different
load.921 We believe it is most 5 TLRs be posted on OASIS and filed curtailments on different paths have
appropriate to continue to review with the Commission. EEI agrees that different effectiveness in relieving a
alternative transmission provider providing customers with information given transmission constraint.
proposals for behind the meter on transmission curtailments may help
generation treatment on a case-by-case to reduce confusion and suspicion 1624. Manitoba Hydro notes that
basis, as the Commission did in the PJM concerning curtailments and suggests MISO is the only RTO in the Eastern
proceeding cited by the commenters. the Commission request WEQ (NAESB) Interconnection that does not redispatch
to develop a more detailed template for when constraints occur on non-market
8. Transmission Curtailments to market flows. Manitoba Hydro
posting information on curtailments that
1620. In the NOPR, the Commission will be more useful to customers. therefore urges the Commission to
proposed no changes to the pro forma 1622. Southern and other encourage implementation of redispatch
OATT with respect to curtailment commenters 922 state that sufficient to the fullest extent before resorting to
provisions for point-to-point service (set information regarding curtailments of curtailment. Seattle also supports
forth in sections 13.6 and 14.7) and transmission service is already available modifying the pro forma OATT to
network service (set forth in section 33). on OASIS and believe that the existing require reliability redispatch. Seattle
These provisions establish the terms rules requiring transmission providers proposes that redispatch costs should be
and conditions under which a to make curtailment data available on allocated to all classes of customers, and
transmission provider may curtail OASIS are adequate. Nevada Companies transmission providers’ cost recovery
service to maintain reliable operation of request the Commission be very specific should be allowed through automatic
the system. Though several commenters if it decides to mandate additional adjustment clause-type formulas to
claimed in response to the NOI that the reporting requirements in order to ensure all such costs are recovered. It
reasons for transmission curtailments remove the burden of potential suggests that routine maintenance
are difficult to discern, they did not confidentiality problems from the outages are resulting in curtailments,
provide sufficient detail to indicate reporting entity. which is an indication that transmission
whether that difficulty is a result of 1623. Powerex is concerned about service is oversold. Seattle further
inadequate disclosure regulations, inconsistent communication and suggests that transmission providers
inadequate compliance with those curtailment procedures. It recommends prepare a quarterly incident report for
regulations, or some other reason. that the Commission require three redispatch events detailing
Therefore, the Commission sought additional measures including: Early circumstances resulting in the
further comment on whether requiring notice of curtailment through the use of redispatch, system status information,
transmission providers to post the ‘‘recall’’ function on OASIS; a power transfer distribution factors,
additional information would improve requirement to provide credits for generator offers for redispatch and other
transparency and the ability of curtailed service when non-firm point-
information supporting redispatch
customers to make use of that to-point transmission service is
determinations, including the basis for
information. The Commission also interrupted; and requiring pro rata
selecting generators called for
declined in the NOPR to propose curtailments made prior to the energy
generic penalties for improper redispatch.
scheduling and tagging deadline (e.g.,
transmission curtailments. 20 minutes before the operating hour) to 1625. APPA, EEI and others comment
be based on reservation rather than that the Commission should not impose
Comments generic penalties for improper
schedule. In its reply comments, Seattle
1621. APPA suggests that the states support of pro rata curtailments curtailments, but treat violations on a
Commission require transmission based on reservations. TDU Systems case-by-case basis. To ensure
providers to produce additional recommend that the Commission compliance with curtailment posting
information regarding firm transmission require transmission providers to refund information, Southwestern Coop
service curtailments, including all transmission charges to curtailed suggests that the Commission adopt
sroberts on PROD1PC70 with RULES

customers, to discourage transmission generic penalties for curtailment


920 We note that EEI responds to allegations of
providers from overselling their violations, claiming that penalties for
undue discrimination in the calculation of load
ratio share costs in the OATT Definitions section of systems. On reply, EEI and PNM–TNMP transmission provider curtailment
this Final Rule. discrimination would provide
921 Order No. 888–A at 30,260–61. 922 PNM–TNMP and TranServ. incentives for compliance.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00209 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12474 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Commission Determination transmission customers at the same required to relieve the overloaded
1626. The Commission concludes that time. facility.
the posting of additional curtailment 1628. The Commission rejects TDU
1630. The Commission also rejects
information is necessary to provide Systems’ proposal to require reports
TDU Systems’ recommendation to
transparency and allow customers to filed with the Commission regarding
Level 5 TLRs or to require transmission refund transmission charges to curtailed
determine whether they have been customers as a means of disciplining
treated in the same manner as other providers to conduct investigations into
the need for network upgrades when instances of improper curtailments or
transmission system users, including transmission providers’ overselling their
customers of the transmission provider. TLR 5 procedures are repeatedly
employed. TDU Systems’ proposal is systems. We also reject proposals to
A primary goal of this rulemaking is to remedy improper curtailments through
unnecessary at this time in light of our
remove opportunities for transmission refunds of transmission charges to
requirement that OASIS templates for
providers to unduly discriminate in curtailed customers or imposing generic
curtailment information be developed
favor of their own or their affiliates’ use
that will report occurrences of all levels penalties. Rather, the Commission
of the transmission system. Making
of TLRs. This will enable the believes that addressing allegations of
transparent details concerning
Commission and customers to monitor inappropriate curtailment practices or
transmission curtailments so that
TLR patterns and frequency. transmission providers overselling their
regulators and customers can verify that
Furthermore, the requirements imposed transmission system are more effectively
the transmission provider curtailed
in this Final Rule for congestion studies administered by the Commission on a
services in accordance with its OATT is
as part of the coordinated, open and case-by-case basis.
entirely consistent with this goal. transparent planning requirement will
Commenters who oppose greater allow stakeholders in the transmission 1631. With respect to the proposal to
curtailment transparency offer no provider’s planning process to request require redispatch to be performed to
convincing evidence to suggest that any studies of those portions of the the fullest extent prior to curtailments,
harm or hardship of doing so outweigh transmission system where they have Manitoba Hydro itself notes that the
the benefits. encountered transmission problems due proposal is intended to address
1627. We agree with suggestions for curtailment and redispatch practices
to frequent and recurring constraints.
the posting of additional curtailment 1629. The Commission rejects the unique to MISO. Therefore we conclude
information on OASIS and, therefore, three proposals suggested by Powerex. that Manitoba Hydro’s concerns are best
require transmission providers, working First, it is not necessary to provide early addressed on a case specific basis.
through NAESB, to develop a detailed curtailment notification through the
template for the posting of additional 1632. Regarding Seattle’s proposal to
OASIS ‘‘recall’’ function since the
information on OASIS regarding firm require what it characterizes as
OASIS currently provides a curtailment
transmission curtailments. ‘‘reliability redispatch’’ to benefit and be
notification function. Transmission
Transmission providers need not providers should continue to use the paid by all customer classes, we note
implement this new OASIS OASIS Schedule Details template to that this proposal would require
functionality and any related business post information on the scheduled uses expansion of the network service
practices until NAESB develops of the transmission system and any ‘‘reliability redispatch’’ provisions to
appropriate standards. These postings curtailments and interruption thereof. apply to point-to-point service as well.
must include all circumstances and Second, with respect to Powerex’s The network service ‘‘reliability
events contributing to the need for a request to credit customers when their redispatch’’ provisions in pro forma
firm service curtailment, specific non-firm point-to-point transmission OATT sections 33.2 and 33.3 were
services and customers curtailed service is interrupted, we find it established in Order No. 888 to ensure
(including the transmission provider’s unnecessary to modify the pro forma comparable reliable service to network
own retail loads), and the duration of OATT to adopt such crediting customers as the service that the
the curtailment. This information is in procedures, consistent with our finding transmission provider provides to its
addition to the Commission’s existing in Order No. 888–A that proper bundled retail load. These redispatch
requirements: (1) When any crediting would vary depending on the procedures further provide for
transmission is curtailed or interrupted, specific rate design a company uses.923 redispatch of not just the transmission
the transmission provider must post Third, we believe that pro-rating provider’s own resources, but all
notice of the curtailment or interruption curtailments based on reservations network resources, including those of
on OASIS, and the transmission would have the potential to impair
provider must state on OASIS the network customers, when required to
reliability since the amount of capacity
reason why the transaction could not be maintain the reliability of the system
actually curtailed using this approach
continued or completed; (2) information and avoid the need for curtailments.
would not address actual power flows
to support any such curtailment or and, therefore, may be less than Seattle has not demonstrated that its
interruption, including the operating proposal to extend ‘‘reliability
status of facilities involved in the 923 See Order No 888–A at 30,276. In Allegheny redispatch’’ for point-to-point service is
constraint or interruption, must be Power System, Inc., 80 FERC ¶ 61,143 at 61,549 required to ensure comparable, not
(1997), the Commission clarified that where a unduly discriminatory transmission
maintained for three years and made transmission provider has not proposed an express
available upon request to the curtailed crediting provision for the interruption of non-firm service and has not addressed why
or interrupted customer, the point-to-point customers, the transmission provider network customer resources should be
Commission’s Staff, and any other must compute its bill to an interrupted non-firm redispatched for the benefit of point-to-
customer as if the term of service actually rendered
person who requests it; and, (3) any were the term of service reserved. In other words, point customer. Accordingly, we
sroberts on PROD1PC70 with RULES

offer to adjust the operation of the if a customer with a weekly reservation was decline to adopt Seattle’s proposal. We
transmission provider’s system to interrupted after one day, its bill must be computed discuss redispatch issues more broadly
as if it had a daily reservation, and if a customer
restore a curtailed or interrupted with a daily reservation was interrupted after ten in section V.D.1 of this Final Rule.
transaction must be posted and made hours, its bill must be computed using the hourly
available to all curtailed and interrupted rate applied to ten hours of service.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00210 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12475

9. Standardization of Rules and facilitate a consistent interpretation and limiting access to transmission services,
Practices to minimize discretion on what rules, including rates and charges for service,
a. Business Practices practice and standards should be posted should be included in the OATT and
on OASIS. should be subject to Commission
1633. In Order No. 888, the 1636. On the particular issue of scrutiny. Examples given include all
Commission required each public utility creditworthiness and security rules and practices affecting calculation
that owns, controls, or operates facilities requirements, the Commission of ATC, creditworthiness criteria, and
used for transmitting electricity in preliminarily concluded that the mere rules or practices affecting the
interstate commerce to file, pursuant to posting of information on OASIS was transmission provider’s regional
section 205 of the FPA, a pro forma insufficient. The Commission proposed planning process. Commenters argue
OATT under which it would provide that each transmission provider’s OATT that Commission oversight is necessary
open access transmission services. contain sufficient information about its to ensure that these rates, charges, rules,
However, certain rules, standards, and credit process and requirements to practices, terms or conditions of
practices governing the provision of enable customers to understand the transmission service are reasonable and
transmission service (e.g., public utility information required to demonstrate afford comparable treatment for
business practices) are not reflected in creditworthiness and to determine for wholesale customers.
the pro forma OATT. Only when a themselves the general amount and type 1638. Other commenters advocate
public utility adopts a rule, standard, or of security they may need to provide in further inclusion of rules, standards and
practice that significantly affects its order to receive service. The practices in the transmission provider’s
rates and services has the Commission Commission therefore proposed to OATT. Morgan Stanley believes that
required it to make a filing pursuant to amend section 11 of the pro forma business practices manuals should be
FPA section 205 to amend its OATT.924 OATT on creditworthiness to require incorporated into each OATT and filed
The Commission has applied this policy each transmission provider to include with the Commission for approval.
using a ‘‘rule of reason’’ test.925 its creditworthiness and security Morgan Stanley states that if this is not
NOPR Proposal requirements in a new Attachment L to required then, at a minimum, each
its OATT. Consistent with the OATT should provide for a process to
1634. In the NOPR, the Commission Creditworthiness Policy Statement,926
proposed not to modify its existing use when the transmission provider
the Commission proposed to require the wishes to amend its business practices
policy regarding the inclusion of rules, new Attachment L to include such
standards and practices in a manuals. For example, transmission
qualitative and quantitative criteria providers should provide notice to all
transmission provider’s OATTs. The necessary to determine the level of
Commission expressed concern that affected parties of an intent to make a
secured and unsecured credit required, change, a mechanism to receive
requiring transmission providers to with supplementation in a credit guide
include all of their rules, standards, and stakeholder feedback on the proposed
or manual to be posted on OASIS.927 change, and a minimum period of time
practices in their OATTs could decrease The Commission sought comment on
a transmission provider’s flexibility to between the final implementation
whether the proposal is unduly decision and the effective date of the
change business practices and respond
burdensome. proposed change (e.g., 30–60 days after
to the requests of its customers. The
Commission also expressed a belief that Comments final decision). Southwestern Coop,
requiring transmission providers to file however, maintains that transmission
Included in Open Access Transmission providers should not be allowed to
all of their rules, standards, and Tariffs
practices in their OATTs would be change their rules, standards and
impractical and potentially 1637. Many commenters express practices that affect the justness and
administratively burdensome. support for the continuation of the reasonableness of OATTs without prior
1635. The NOPR further noted that current Commission policy which Commission review. Southwestern Coop
there is broad consensus that rules, requires the inclusion in the states that the Commission should
standards, and practices not required to transmission provider’s OATT of only require all rules, standards and practices
be included in a transmission provider’s those rules, standards and practices that relating to transmission services to be
pro forma OATT should be posted on significantly affect transmission rates included in the OATT filed with the
the transmission provider’s OASIS. The and services.928 These commenters Commission, because otherwise it
Commission agreed and proposed to generally state that any rule, practice, cannot ensure that jurisdictional rates
require transmission providers to post term or condition that could result in are just and reasonable.
on OASIS all of their rules, standards, Posted on OASIS
926 Policy Statement on Electric Creditworthiness,
and practices that relate to transmission
services. The Commission sought 109 FERC ¶ 61,186 (2004) (Creditworthiness Policy 1639. Many commenters also express
Statement). support for the proposed requirement
comment on how best to determine 927 The Commission proposed to require the new
what ‘‘relates’’ to transmission service to Attachment L to include the following elements: (1)
that all rules, standards and practices
A summary of the procedure for determining the that are not required to be included in
924 E.g., Cleveland v. FERC, 773 F.2d 1368, 1376 level of secured and unsecured credit; (2) a list of a transmission provider’s OATT and
(D.C. Cir. 1985). the acceptable types of collateral/security; (3) a that affect a transmission provider’s
procedure for providing customers with reasonable
925 See, e.g., Public Serv. Comm’n of N.Y. v.
notice of changes in credit levels and collateral
provision of transmission service be
FERC, 813 F.2d 448, 454 (D.C. Cir. 1987) (holding posted on OASIS.929 Commenters
that the Commission properly excused utilities from requirements; (4) a procedure for providing
filing policies or practices that dealt with only customers, upon request, a written explanation for generally state that these postings will
matters of ‘‘practical insignificance’’ to serving any change in credit levels or collateral allow for increased transparency, while
customers); Midwest Independent Transmission requirements; (5) a reasonable opportunity to
affording the transmission provider
sroberts on PROD1PC70 with RULES

System Operator, Inc., 98 FERC ¶ 61,137 at 61,401 contest determinations of credit levels or collateral
(‘‘It appears that the proposed Operating protocols requirements; and (6) a reasonable opportunity to flexibility to make revisions rather than
could significantly affect certain rates and service post additional collateral, including curing any
and as such are required to be filed pursuant to non-creditworthy determination. 929 E.g., CAISO, EEI, MidAmerican, MISO/PJM

section 205.’’), order granting clarification, 100 928 E.g., ISO/RTO Council, CAISO, LDWP, MISO/ States, Nevada Companies, PJM, Powerex, Santa
FERC ¶ 61,262 (2002). PJM States, PGP, and PNM–TNMP. Clara, Suez Energy NA, TDU Systems, and TAPS.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00211 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12476 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

having to amend the OATT each time a apply an existing requirement in a non- example, those greater than 25 percent
change occurs. discriminatory manner. within a one-month period) be subject
1640. Powerex argues that the 1644. Other commenters propose to an active notification requirement.
transmission provider also should be modifications to the credit-related 1646. TVA recommends the
required to post data used to calculate proposals set forth in the NOPR. TAPS Commission consider two fundamental
ATC, any metrics the Commission urges the Commission to require the principles as it standardizes
adopts regarding the transmission transmission provider to adopt a two- creditworthiness terms and conditions.
provider’s performance of system part creditworthiness assessment in First, as long as qualitative factors are
impact and facilities studies, order to facilitate non-burdensome and part of the equation (and TVA agrees
information concerning both planned fair assessment of creditworthiness. that they should be), TVA states that
and unplanned transmission outages, TAPS recommends that a standard certain subjective judgments by the
and a transmission provider’s business similar to the Florida Power Corp. transmission provider will be required.
practices, tariff, organizational charts OATT be applied, which provides that TVA encourages the Commission to
and job descriptions of its employees. customers with ‘‘satisfactory long-term provide guidance on appropriate criteria
1641. Southern takes issue with the payment history’’ and a minimum credit to consider in making these judgments,
use in the NOPR of the phrase ‘‘all of rating of Baa2 (Moody’s) or BBB (S&P) but not to remove entirely from the
their rules, standards and practices,’’ would not have to post any credit process the flexibility necessary for
stating that language suggests that a security. If a customer fails to meet the individual assessments of customer
transmission provider might be required threshold test, TAPS states that the creditworthiness. Second, TVA states
to reduce each detail of its business transmission provider would perform a that transmission providers may have to
practices to writing, which could be transparent credit assessment that is impose different security requirements
overly burdensome. In addition, consistent with the Commission’s as a result of differences in statutes,
Southern believes that any rule relating Creditworthiness Policy Statement and regulations, or other legal requirements.
to posting requirements on OASIS the credit policies developed for use in For example, TVA states that its ability
should have certain mechanisms to regional transmission organizations
to incur debt is limited by section 15d(a)
allow the transmission provider to such as MISO and SPP. According to
of the Tennessee Valley Authority
deviate from posted practices when TAPS, since quantitative measures
Act 932 and, therefore, it may need to
necessary. In contrast, ELCON states sometimes understate public power
impose security requirements that are
that any rule, standard or practice used creditworthiness, transmission
stricter than those of a public utility, as
by the transmission provider and any of providers will need to weigh qualitative
the Commission has previously
its employees to approve or disapprove factors more heavily than quantitative
recognized.933 TVA requests that the
a request for service should be factors in assessing public power
final rule respect these differing legal
committed to writing and posted. creditworthiness. For public entities
that fail the threshold test, TAPS states obligations and provide corresponding
Similarly, TranServ argues that flexibility in credit decisions among
transmission providers should be that transmission providers should use
outstanding bond indebtedness as a transmission providers.
required to post on OASIS any criteria 1647. A number of commenters
applied by the transmission provider to proxy for tangible net worth for those
entities whose energy and transmission oppose the Commission’s proposed
any attribute of a transmission or creditworthiness policy.934 In general,
ancillary service request for the purpose service payments receive priority over
bond payments. these commenters believe that each
of determining whether the service transmission provider should have the
1645. PJM generally agrees with the
request should be approved or denied. flexibility to make and change
creditworthiness proposals, except for
1642. Northwest IOUs suggests that inclusion in the OATT of the actual creditworthiness procedures without
the Commission should adopt a ‘‘rule of detailed algorithms used to calculate the delay of obtaining Commission
reason’’ test for matters required to be credit scores, stating that those approval. They also argue that the
posted on the OASIS similar to the test algorithms, as the Commission Commission’s goal of transparency
applied to matters required to be recognized,931 may change over time. In could be better achieved by requiring
included in the OATT. PJM’s view, requiring all such changes the posting of a transmission provider’s
Creditworthiness to be approved by the Commission creditworthiness policy on OASIS.935
would be unnecessarily burdensome to Xcel and MidAmerican assert that the
1643. Several commenters support the Commission’s proposal would decrease
both the Commission and the
inclusion of a separate Attachment L to a transmission provider’s ability to
transmission provider. PJM
the pro forma OATT outlining recommends that the overall framework timely respond to changing market and
creditworthiness requirements, asserting of the credit determinations be included financial conditions and, therefore,
that Attachment L will standardize in the OATT, while the detailed creditworthiness and security
credit procedures and security algorithms be posted on OASIS to meet requirements should simply be posted
requirements and increase transparency goals. PJM also on OASIS. Southern believes that the
transparency.930 Suez Energy NA states recommends that the Commission Commission should permit but not
that the proposal is not unduly accept, as an option, a regularly-updated require transmission providers to file
burdensome, that the procedures posting on the transmission provider’s their creditworthiness and security
proposed are not different from the Web site of each customer’s available procedures as part of their OATTs.936
Creditworthiness Policy Statement or credit and collateral requirement as
the procedures already imposed in sufficient notification for most changes 932 16 U.S.C. 831n–4.
individual cases, and that the in credit available and credit 933 Citing East Ky. Power Coop., Inc., 114 FERC
Commission is merely proposing to
sroberts on PROD1PC70 with RULES

¶ 61,035 at P 56 (2006).
requirements. PJM further recommends 934 E.g., MidAmerican, Southern, PNM–TNMP,

930 E.g., APPA, East Texas Cooperatives, Lassen,


that only significant and sudden NorthWestern, and Xcel.
MISO/PJM States, Nevada Companies, NRECA, reductions in credit available (for 935 E.g., PNM–TNMP, EEI, and MidAmerican.

PGP, Powerex, Southern, Suez Energy NA, TANC, 936 Southern states that it already includes

and TAPS. 931 See NOPR at P 456. creditworthiness and security requirements in its

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00212 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12477

Southern also asks that the Commission rule, standard or practice. For example, on OASIS.938 We find that it is now
allow a transmission provider, in its CAISO proposed to post certain necessary to also require that all rules,
compliance filing, to request a technical, operational and business standards or business practices that
determination that its current standards related to dynamic scheduling relate to the terms and conditions of
creditworthiness policies and practices on its Web site and include only the transmission service, and how that
are acceptable under the new rates under its OATT. In that instance, transmission service is provided to
Commission policies. Similarly, ISO- the Commission found that the details customers, to be detailed, clearly stated
New England states that this rulemaking contained in the standards were on the transmission provider’s public
should not modify the ISO-New practices that could significantly affect Web site, with a link to this information
England Financial Assurance and the terms and conditions of service and, on OASIS.939 We emphasize that this
Billing Policies, which are already on therefore, under the Commission’s ‘‘rule requirement applies to all such rules,
file with the Commission. of reason’’ must be filed under section standards, and practices, currently
1648. CAISO states that although the 205 of the FPA.937 written or otherwise.940 While we
NOPR requirements concerning credit acknowledge this requirement will
1651. Comments received in response
and security requirements do not appear result in some burden to transmission
to the NOPR confirm that there is broad
unduly burdensome, it is concerned that providers, we find that this approach is
support for the Commission’s existing
the Commission may apply these necessary to provide greater
practice, requiring only those rules,
requirements in a manner that will transparency and mitigate the potential
standards, and practices that
impose an undue burden on for undue discrimination against
transmission providers and effectively significantly affect transmission service,
customers taking service under the
eliminate the ability of transmission and the use of the ‘‘rule of reason’’ test
transmission provider’s OATT. Further,
providers to supplement basic elements to identify those rules, standards, and
our holding is not intended to eliminate
with a credit guide or manual. CAISO practices. The Commission disagrees
all discretion under the pro forma
and MidAmerican further state that with parties arguing that all of a
OATT; rather, we recognize that certain
there is no legitimate reason to treat transmission provider’s rules, standards,
tariff provisions require consideration of
credit policies and procedures any and practices should be incorporated
the specific facts and circumstances
differently than the other rules, into its OATT. We believe that requiring related to particular service requests.941
practices and standards that the transmission providers to file all of their We merely require that, if the
Commission permits to be included on rules, standards and practices in their transmission provider uses standards,
OASIS and does not require to be filed OATTs would be impractical and rules or business practices to administer
as part of the tariff. Santa Clara potentially administratively its OATT, such standards, rules or
recommends that if the Commission burdensome. business practices must be available for
decides to require creditworthiness and 1652. The Commission instead public inspection. Moreover, we note
security policies to be posted on OASIS requires transmission providers to post that our actions here are consistent with
rather than included in the OATT, then on their public Web sites all rules, actions we have taken in recent
it should require at least a 30-day notice standards, and practices that relate to proceedings. For example, the
period for changes in the credit policies. transmission service and provide a link Commission has required that certain
to those rules, standards, and practices business practices manuals be posted
Commission Determination on OASIS. We conclude that it would
1649. The Commission adopts the not be appropriate to place the rules, 938 See, e.g., Order No. 889 at 31,588–89; Open

NOPR proposal to continue to require standards, and practices only on OASIS Access Same-Time Information Systems, Order No.
605, 64 FR 34117 (Jun. 25, 1999), FERC Stats. and
only those rules, standards, and as some transmission providers use Regs. ¶ 31,075 (1999); Order No. 676 at P 79.
practices that significantly affect certificates to restrict access to their 939 If a particular rule, standard or practice

transmission service be incorporated OASIS sites. By providing a link on conflicts with an OATT provision, the OATT of
into a transmission provider’s OATT. OASIS to the rules, standards, and course shall govern in all circumstances. Moreover,
as noted in the NOPR, we emphasize that posting
The Commission further affirms the use practices that are otherwise publicly rules, practices and standards—in lieu of filing such
of a ‘‘rule of reason’’ to determine what posted, the Commission ensures that all practices with the Commission as part of the
rules, standards, and practices potential customers will have access to transmission provider’s pro forma OATT—neither
significantly affect transmission service the information necessary for them to insulates a transmission provider from complaints
nor confers a just and reasonable presumption. We
and, as a result, must be included in the understand the terms and conditions of encourage customers to call the Commission’s
transmission provider’s OATT. service. We amend section 4 of the pro Enforcement Hotline with complaints about the
1650. The ‘‘rule of reason’’ test has forma OATT to expressly establish this application of such rules, standards and practices
arisen primarily with respect to should they experience problems with their
posting requirement. transmission providers. To the extent customers are
protocols or operating procedures used 1653. We note that we already require not satisfied with responses from their transmission
by RTOs and ISOs. For example, the certain rules and practices to be posted provider, they should contact the Commission’s
Commission has held that, while Enforcement Hotline via telephone (202) 502–8390,
MISO’s business practices manuals toll-free 1–888–889–8030, fax (202) 208–0057, or at
937 California Independent System Operator http://www.ferc.gov/cust-protect/enforce-hot.asp.
implicate the Commission’s jurisdiction Corp., 107 FERC ¶ 61,329 at P 21–22 (2004); see 940 With respect to the business practices
because they generally involve ‘‘the also Southwest Power Pool, Inc., 112 FERC ¶ 61,303 developed by NAESB, there may be certain
installation, operation, or use of at P 25 (requiring that the SPP OATT provide copyright restrictions that limit the transmission
facilities for the transmission or delivery sufficient information for market participants to provider’s ability to post those practices on its own
fully understand SPP’s implementation of an Web site. In such instances, we expect that the
of power in interstate commerce,’’ they imbalance market), reh’g denied, 113 FERC ¶ 61,115 transmission provider will reference any NAESB
do not require an FPA section 205 filing (2005); PJM Interconnection, L.L.C., 104 FERC practices it uses and provide a link on its public
because ‘‘they mostly involve general ¶ 61,124 at P 61 (requiring PJM to place all Web site to the NAESB Web site in order to provide
sroberts on PROD1PC70 with RULES

operating procedures.’’ In other cases, procedures, standards and requirements for interested parties with a means to access the
proposing that a transmission owner construct a copyrighted material.
the facts have required the filing of the specific upgrade, and all procedures for charging 941 The circumstances and manner in which a

customers, in its tariff, not in its manuals), order on transmission provider exercises its discretion under
OATT since the Commission issued its reh’g, PJM Interconnection, L.L.C., 105 FERC its OATT must be posted in accordance with 18
Creditworthiness Policy Statement. ¶ 61,123 (2003). CFR 37.6(4).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00213 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12478 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

and made available for public view on pro forma OATT to formalize this 1658. We disagree with commenters
a permanent basis.942 As in those cases, posting requirement and obligate that claim requiring this information in
we find that making rules, standards, transmission providers to follow the an attachment to each transmission
and practices readily accessible will amendment procedures specified by the provider’s OATT will hinder the
serve as a tool to supplement each transmission provider. As with the transmission provider’s ability to timely
transmission provider’s OATT and requirement to post the underlying respond to changing market and
facilitate fair and open access to the standards, rules and practices, we financial conditions. Because
transmission grid. believe the amendment procedures Attachment L requires only a summary
1654. To provide guidance to the required here will increase transparency of credit requirements and other
transmission providers as to whether a and help minimize opportunities for information, we expect the need to
particular rule, standard, or practice undue discrimination. revise Attachment L will occur
‘‘relates to’’ transmission service, and 1656. The Commission also adopts infrequently. As suggested by PJM,
therefore warrants posting, the the NOPR proposal and amend the pro detailed information, such as the
Commission believes the MAPP Policies forma OATT to include a new algorithms used by the transmission
and Procedures for Transmission Attachment L.944 We find that the provider to determine credit scores, can
Operations manual is a good example of transmission provider’s basic credit be posted on OASIS along with other
the type of information that relates to standards significantly affect information that relates to the provision
the terms and conditions of transmission service and, therefore, of transmission service. Thus, the
transmission service. For example, the must be included in the pro forma requirement we are imposing should not
MAPP manual sets forth information OATT. This will ensure that all be overly burdensome.
supplementing its OATT pertaining to customers have clear information as to 1659. At the same time, we agree that
(1) transmission service requests on the the credit process and standards used by transmission providers need flexibility
MAPP OASIS site, (2) the retraction of a transmission provider to grant or deny in determining credit requirements in
an accepted or counteroffer transmission service and, in turn, will light of qualitative and quantitative
transmission request, (3) timing serve to prevent undue discrimination factors, as we recognized in the NOPR
requirements for transmission service and eliminate a potentially significant and the Creditworthiness Policy
requests, (4) methods to accommodate a barrier to entry in the provision of Statement. We believe the requirements
firm transmission request with service. Most importantly, by making adopted in this Final Rule allow for
redispatch, and (5) transmission service Attachment L a part of the pro forma such flexibility. By requiring
charge implementation procedures. OATT, customers will have an transmission providers to consider both
Other examples include detailed opportunity to comment on any changes quantitative and qualitative factors, the
information regarding tagging, to the standards proposed by a particular circumstances surrounding
scheduling, billing and other matters transmission provider in a rate filing public power entities can be recognized.
provided in other RTO manuals. This is with the Commission. We agree, moreover, with TVA that the
the type of information that clearly 1657. To that end, each transmission transmission provider’s credit policies
relates to transmission service and provider’s Attachment L must specify must be consistent with its legal
therefore must be reduced to writing the qualitative and quantitative criteria obligations and expect that interested
and publicly posted. that the transmission provider uses to parties will bring any legal conflicts to
1655. We also agree with requests to determine the level of secured and our attention on review of the
require a transparent process for unsecured credit required. Attachment transmission provider’s compliance
amending rules, standards, and L must also contain the following filing.
practices previously posted by a elements: (1) A summary of the 1660. With regard to requests to find
transmission provider. We therefore procedure for determining the level of existing credit policies consistent with
require each transmission provider also secured and unsecured credit; (2) a list the requirements of the Final Rule, all
post on its public Web site (with a of the acceptable types of collateral/ transmission providers will be required
corresponding link on OASIS) a security; (3) a procedure for providing to demonstrate compliance with all
statement of the process by which the customers with reasonable notice of aspects of the Final Rule either by
transmission provider will amend these changes in credit levels and collateral implementing the reforms adopted
rules, standards, and practices that are requirements; (4) a procedure for today or showing that departures are
accessible via OASIS. As part of this providing customers, upon request, a consistent with or superior to the terms
process, the transmission provider must written explanation for any change in and conditions of the pro forma OATT,
specify a mechanism to provide credit levels or collateral requirements; as modified by this Final Rule. The
reasonable notice of any proposed (5) a reasonable opportunity to contest procedural mechanisms for making such
changes to a posted business practice determinations of credit levels or a showing provided for in section IV.C
and the respective effective date of such collateral requirements; and (6) a above give transmission providers the
change.943 We amend section 4 of the reasonable opportunity to post opportunity to demonstrate that
additional collateral, including curing retention of their existing credit
942 See, e.g., Midwest Independent Transmission
any non-creditworthy determination. practices is appropriate.
System Operator, Inc., 108 FERC ¶ 61,163 at P 658, 1661. Finally, with regard to Santa
order on reh’g, 109 FERC ¶ 61,157 (2004), order on We will allow the transmission provider
reh’g, 111 FERC ¶ 61,043, order on reh’g, 112 FERC to supplement Attachment L with a Clara’s request to require the
¶ 61,086 (2005); see also PJM Interconnection, credit guide or manual to be posted on transmission provider to provide at least
L.L.C., 81 FERC ¶ 61,257 at 62,267 (1997) (finding
OASIS. a 30-day notice period for changes in
no reason to require filing of the PJM Manuals but creditworthiness and security policies
requiring that such manuals be available for public
inspection on a permanent basis), order on reh’g, 92 944 As with new Attachment K to the pro forma that are posted on OASIS, we explain
sroberts on PROD1PC70 with RULES

FERC ¶ 61,282 (2000). OATT, regarding transmission planning, we above that each transmission provider
943 As part of their business practice amendment acknowledge that some transmission providers may must identify and incorporate a specific
procedures, transmission providers may adopt such already have attachments to their OATTs labeled
additional procedures they deem appropriate, such with the letter ‘‘L,’’ in which case transmission
process in its OATT for amending
as opportunities for comment to proposed changes providers are free to label their credit procedures business practices that are posted on
to rules, standards, and practices. OATT attachment with the next available letter. OASIS. Such practices include those

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00214 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12479

that describe and implement its (2) Indemnification/Limitation of 1667. EEI contends that the addition
creditworthiness and security policies. Liability of the Commission’s new EPAct 2005
Comments authority to establish mandatory
b. Liability and Indemnification reliability standards to provide open
1662. In Order No. 888, the only 1665. Several commenters 946 urge the access transmission service to all
liability provisions included in the pro Commission to change the customers, regardless of their risk
indemnification provision to protect profile, makes it an appropriate time to
forma OATT related to force majeure
transmission providers from liability revisit the liability provisions in the
and indemnification.945 Section 10.1 of
except in the case of gross negligence or OATT. According to EEI, a limitation on
the pro forma OATT provides that liability in the pro forma OATT should
intentional misconduct, thereby
neither the transmission provider nor exempting the transmission provider be viewed as a necessary element of the
the transmission customer will be from liability for acts of ordinary implementation of the Commission’s
considered in default as to any negligence. These commenters also reliability authority. Because
obligation under the tariff if prevented request that the Commission add to the transmission providers cannot deny
from fulfilling the obligation due to an pro forma OATT a new provision service to particular customers based on
event of force majeure. A party whose clarifying that the transmission provider the risk of potential damages, EEI and
performance under the tariff is hindered would not be liable to any transmission Southern assert that all transmission
by an event of force majeure, however, customer or third party for direct, providers should be protected from
is required to make all reasonable efforts incidental, consequential, indirect, or certain risks associated with this
to perform its obligations under the punitive damages arising from services obligation to serve. EEI argues that
tariff. With respect to indemnification, provided under the tariff, except in increased protection from liability
under section 10.2 of the pro forma cases of gross negligence or intentional would lower the cost of capital for new
OATT, the transmission customer misconduct (in which case, EEI, and transmission projects and promote the
indemnifies the transmission provider Northwest IOUs propose, liability expansion of transmission
against third party claims arising from would be limited to direct damages). infrastructure. EEI further argues that
the transmission provider’s performance These commenters note that the the technological complexity of modern
of its obligations under tariff on behalf Commission has allowed transmission utility systems and the potential for
of the transmission customer, except in providers this protection in the tariffs of service interruptions unrelated to
MISO, PJM, ISO New England, SPP, and human errors justify liability
cases of negligence or intentional
their member transmission owners and limitations. According to EEI, a
wrongdoing by the transmission
generators, but it has not fully explained limitation on liability to direct damages
provider. puts the risk on those customers with
its basis for treating non-RTO member
(1) Force Majeure transmission providers differently from special reliability needs, rather than
RTOs and ISOs. EEI further notes that spreading the risk among all customers.
Comments 1668. EEI notes that the Commission
the Commission accepted similar
1663. Santa Clara queries whether the liability protection in the Large has denied requests for exemptions from
Generator Interconnection Agreement liability for ordinary negligence in the
Commission intended to make the
(‘‘LGIA’’) and in natural gas pipeline indemnification provision on the
transmission provider’s performance of
tariffs.947 EEI requests that this liability grounds that liability and
its obligations less burdensome by using indemnification were ‘‘separate
the phrase ‘‘all reasonable efforts’’ limitation be added to the pro forma
transmission service agreement that issue[s]’’ and that transmission
instead of ‘‘due diligence’’ in the force providers seeking liability protections
majeure provision in section 10.1 of the would apply to transmission customers
acting in good faith to carry out the could rely on state laws.949 EEI argues,
pro forma OATT is. In either case, Santa however, that an OATT and the
Clara requests the Commission to directives of a transmission provider.
accompanying service agreement
consider the use of the most stringent 1666. With respect to third party constitute a contract between the
term when addressing a transmission indemnification, EEI notes that the transmission provider and the customer
provider’s obligation to perform under Commission reasoned in SPP that, even that is established pursuant to federal
its tariff. though a broader liability limitation law and, as a result, it is not at all clear
would relieve a transmission provider that a state law limitation on liability
Commission Determination from liability for ordinary negligence, would apply. Southern asserts that
that provision only applies to adopting liability limits would provide
1664. The Final Rule retains the transmission customers under the tariff.
current ‘‘all reasonable efforts’’ standard uniformity, certainty, and reduce risk
EEI states that there are many other since reliance on state law is an issue
in the force majeure provision. Santa entities that could initiate legal action
Clara does not explain how the ‘‘all not free from doubt.
against the transmission provider in 1669. Entegra argues on reply that the
reasonable efforts’’ standard may be connection with the provision of NOPR did not contemplate any
more or less stringent than the ‘‘due transmission service, thereby making an modification to these provisions of the
diligence’’ standard. Further, as the adequate indemnification provision in pro forma OATT and neither EEI nor
Commission explained in Order No. the pro forma OATT necessary for the Southern has established a nexus
888, this protection against unexpected same reasons as the limited liability between such a modification and the
and unpredictable events is provision.948 goals set forth in the NOPR. TDU
appropriately made available to both the Systems on reply similarly argue that
transmission provider and transmission 946 E.g.,Southern, EEI, and Northwest IOUs. EEI’s request is outside the scope of the
sroberts on PROD1PC70 with RULES

customer. We therefore find that the 947 Citing Article 18, Large Generator rulemaking and neither EEI nor
clarification requested by Santa Clara is Interconnection Agreement; ANR Pipeline Co., 98
FERC ¶ 61,218, order on tariff filing, 100 FERC
Southern show a change in
unnecessary. ¶ 61,132 (2002). circumstance justifying a new limitation
948 Citing Southwest Power Pool, Inc., 112 FERC
945 Order No. 888–B at 62,081 ¶ 61,100 at P 39 (2005). 949 Citing Order No. 888–A at 30,301.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00215 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12480 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

on liability. Immunizing transmission through force majeure and to third parties arising under the LGIA
providers from these liability risks, TDU indemnification provisions from from conduct on behalf of the
Systems contend, would simply transfer damages or liability when service is indemnifying party, except in cases of
risk to customers that have no control provided by the transmission provider gross negligence. Given that the
over the transmission provider’s without negligence, it would leave the indemnification provision in the pro
negligence. Entegra and TDU Systems determination of liability in other forma LGIA is bilateral, in contrast to
further argue that Southern previously instances to other proceedings.953 the pro forma OATT, it is reasonable to
sought the same relief in a tariff filing 1672. On the issue of a negligence permit a gross negligence standard in
rejected by the Commission less than a standard for the indemnification the case of an interconnection.
year ago, stating that the Commission provision, we decline to depart from our
1675. We also reject commenters’
thus already rejected the notion that policy set forth in Order No. 888, as
assertions that the liability standard the
Southern was similarly situated to the affirmed in Order No. 888–A and
Commission has approved for RTOs/
RTOs and ISOs that have this subsequent orders.954 In Order No. 888,
ISOs and gas pipelines is appropriate for
protection.950 Entegra notes that the Commission stated:
other transmission providers. In the
Southern did not seek rehearing of that We have limited the indemnification Reliability Policy Statement,957 the
order and its comments here are portion of the provision so that it is now only Commission stated that it would
therefore an impermissible collateral the transmission customer who indemnifies
the transmission provider from the claims of
consider, on a case-by-case basis,
attack on a final Commission order. As
third parties. The customer is taking service proposals by public utilities to amend
for the argument regarding EPAct 2005,
from the transmission provider and may their OATTs to include limitations on
TDU Systems note that the Commission
appropriately be asked to bear the risks of liability. The Commission further noted
presumably was aware of its new third-party suits arising from the provision of that while this issue has not been
reliability authorities when it issued the service to the customer under the tariff. We resolved on a standardized basis, the
Southern order four months after EPAct find that this new indemnification provision Commission has entertained RTO
was enacted. would be too strict if it required customers
1670. TDU Systems also point out that to indemnify transmission providers even in
transmission providers’ specific
the tariff language proposed by EEI cases where the transmission provider is proposals to amend their OATTs to
would not protect a transmission negligent. Accordingly, the revised provision include provisions addressing
customer from being sued by a third provides that the customer will not be limitations on liability.958
party for the negligence or willful required to indemnify the transmission 1676. In subsequent orders, the
provider in the case of negligence or
misconduct of the transmission intentional wrongdoing by the transmission Commission found that the gross
provider. In such lawsuits, TDU provider.955 negligence and intentional wrongdoing
Systems claim, a third party would not indemnification and liability standard is
be limited to direct damages. According 1673. The Commission subsequently appropriate for RTOs and ISOs.
to TDU systems, any indemnification as addressed this issue in Northeast However, the Commission has declined
between the transmission provider and Utilities. There, the Commission found to extend this protection to all
the transmission customer that is that a broader customer indemnification transmission providers. In Southwest
limited to direct damages would leave obligation that would include ordinary Power Pool, Inc., the Commission
the customer holding the bag for the negligence would not give any incentive explicitly stated ‘‘that our acceptance
indirect damages caused by the to the transmission provider to avoid
here of the gross negligence and
transmission provider’s negligence or negligent actions. In Northeast Utilities,
intentional wrongdoing indemnity
willful misconduct. the Commission explained again why it
standard is limited to SPP, in its role as
permitted a gross negligence exception
Commission Determination an RTO, and its TOs; we do not intend
in the pro forma LGIA section 18.1 in
to extend such protection to all
1671. We will retain the current order to further limit the transmission
transmission providers.’’ 959 In Southern
liability protections in the pro forma provider’s liability. As the Commission
Company Services, Inc., the
OATT for the same reasons that the explained in Order No. 2003,
Commission stated that:
Commission has rejected similar past interconnection warrants a different
proposals. While the Commission standard because it presents a greater Having considered Southern Companies’
explained in Order Nos. 888–A and risk of liability than exists for the proposed limitation on liability and
provision of transmission service. The indemnification provisions pursuant to our
888–B that the pro forma tariff was not
Commission further found that because Reliability Policy Statement cited above, we
intended to address liability issues, as
risk exposure can increase find that Southern Companies have not
EEI notes, the Commission stated that shown that they are similarly situated to the
liability was a separate issue from interconnection costs, a broader
RTOs/ISOs they cite in support. While
indemnification.951 The Commission indemnity standard is appropriate in the
Southern Companies claim that they ‘‘may
further explained that transmission interconnection context.956 not be protected by any State-regulated
providers were not precluded from 1674. Further, unlike Order No. 888 limitations on liability,’’ Southern
relying on state laws that protected in which the transmission customer Companies offer no evidence to support this
utilities or others from claims founded indemnifies the transmission provider, concern. The Commission has provided such
in ordinary negligence.952 The in Order No. 2003 the indemnity liability protection to RTOs/ISOs because
Commission declined to adopt a provision is expressly bilateral. In Order they were created by and solely regulated by
uniform federal liability standard and No. 2003 the interconnecting generator the Commission, and otherwise would be
decided that, while it was appropriate to and the transmission provider each without limitations on liability. Southern
protect the transmission provider indemnifies the other from all damages Companies have proffered no evidence of any
sroberts on PROD1PC70 with RULES

950 See Entegra Reply (citing Southern Company 953 Order No. 888–B at 62,081. 957 Policy Statement on Matters Related to Bulk
954 See, e.g., Northeast Utilities Services Co., 111 Power System Reliability, 107 FERC ¶ 61,052 (2004)
Services, Inc., 113 FERC ¶61,239 (2005)).
951 See Order No. 888–A at 30,301 and Order No. FERC ¶ 61,333 (2005) (Northeast Utilities). (Reliability Policy Statement).
888–B at 62,081 (section 10.2 of the pro forma 955 Order No. 888 at 31,765. 958 Reliability Policy Statement at P 40 (citations

OATT). 956 Order No. 2003 at P 636; Order No. 2003–A omitted).
952 Order No. 888–A at 30,301. at 31,162. 959 112 FERC ¶ 61,100 at P 39 (2005).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00216 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12481

change in circumstances vis-à-vis their OATT and Standards of Conduct expanded or clarified to encompass
liability exposure post-Order No. 888.960 purposes because recent pleadings divisions of an entity that operate as a
1677. Commenters offer no new reveal that there continues to be functional unit, we note that PNM–
arguments that demonstrate that they confusion about this definition. TNMP’s concern appears to have been
are unable to rely on state laws, i.e., the TranServ asks for clarification of the raised in the context of lifting the price
state laws provide inadequate application of the definition of cap for capacity reassignment, initially
protection. While EEI and Southern ‘‘affiliate’’ with respect to a merchant proposed only for non–affiliated
assert that there is uncertainty in affiliate of a transmission provider that transmission customers. We believe we
whether state law on liability would has turned over tariff administration have addressed PNM–TNMP’s concerns
apply to a service agreement between a functions to an ISO, RTO, or other by lifting the price cap for capacity
transmission provider and a independent entity. PNM–TNMP reassignment for all customers,
transmission customer, we note that suggests that the definition of Affiliate including affiliates of the transmission
neither provide any evidence that be expanded or clarified to encompass provider and the transmission
transmission providers are actually divisions of an entity that operate as a provider’s merchant function.
precluded from relying on state law for functional unit. PNM–TNMP asserts
b. Good Utility Practice
liability protection. EEI and Southern that such a change would make clear
that an Affiliate includes not only NOPR Proposal
thus fail to show that the potential for
a legal and regulatory gap is so great as separate legal entities, but also may 1685. In the NOPR, the Commission
to warrant inclusion of liability apply to divisions and functional units proposed to incorporate the definition
protections in the pro forma OATT for within the entity. of reliable operation from FPA section
all transmission providers. In this Commission Determination 215 in the definition of Good Utility
regard, the Commission also finds Practice in the pro forma OATT.
1681. As discussed in section V.C.4,
without merit assertions that increased the Commission lifts the price cap on Comments
liability protections in the pro forma reassigned transmission capacity for all
OATT should be viewed as a necessary 1686. No commenters oppose the
transmission customers, regardless of Commission’s proposal to modify the
element of the implementation of the affiliation with the transmission
Commission’s reliability authority. As definition of Good Utility Practice to
provider. It is therefore no longer reference the reliable operation standard
none of the arguments proffered by necessary to define an affiliate for
commenters persuade us to change our of FPA section 215.
purposes of that provision. The
policy regarding liability protections Commission nonetheless adopts the Commission Determination
applicable to non-RTO and non-ISO proposed definition of Affiliate to 1687. The Commission adopts the
transmission providers, we decline to implement the reforms associated with NOPR proposal to incorporate the
modify the liability protections in the distribution of operational penalties definition of reliable operation from
pro forma OATT. discussed in section V.C.5.b. FPA section 215 in the definition of
10. OATT Definitions 1682. With regard to the request that Good Utility Practice in the pro forma
we clarify that an Affiliate does not OATT. FPA section 215(b) obligates all
1678. In order to support the reforms apply to transmission-only cooperatives, users, owners and operators of the bulk
adopted in this Final Rule and we agree with NRECA that the power system to comply with reliability
otherwise clarify the requirements of the Commission made clear in Order No. standards that will take effect under that
pro forma OATT, the Commission adds 888–A that there was no corporate section. Referencing section 215 in the
and amends various definitions in the affiliation between G&T cooperatives definition of Good Utility Practice is
pro forma OATT, as set forth below. and their member distribution appropriate to ensure that the reliability
a. Affiliate cooperatives.961 standards ultimately developed by the
1683. TranServ requests clarification ERO and approved by the Commission
NOPR Proposal regarding the use of the term ‘‘affiliate’’ are reflected in the pro forma OATT.
1679. In the NOPR, the Commission in the context of a transmission owner
that has turned over operational control c. Non-Firm Sales
proposed a new definition of Affiliate
incident to the proposed change to the of its transmission facilities to an RTO, NOPR Proposal
pricing of reassigned capacity. ISO, or to an independent entity. We 1688. The Commission proposed to
clarify that, for purposes of the add a definition for Non-Firm Sales to
Comments distribution of penalties, if such clarify the treatment of such sales under
1680. Some commenters request transmission owner is not required to be section 30.4 of the pro forma OATT.962
clarification that the proposed a transmission provider under a The Commission proposed defining a
definition of Affiliate would not apply Commission-approved tariff, the Non-Firm Sale as ‘‘an energy sale for
to transmission-only cooperatives or merchant affiliate of such transmission which delivery or receipt of the energy
independent entities such as RTOs. owner would not be considered to be an may be interrupted for any reason or for
NRECA asserts that in Order No. 2004– ‘‘affiliate’’ of the RTO, ISO, or no reason, without liability on the part
A, the Commission concluded that independent entity under the definition of either the buyer or seller.’’ The
‘‘[g]eneration and transmission adopted in this Final Rule. The Commission also proposed to clarify
cooperatives (G&T) are not subject to the affiliation of a merchant to a that, for the purposes of applying
Standards of Conduct consistent with transmission owner does not establish
the policies established under Order No. an affiliation between such merchant 962 Section 30.4 as proposed in the NOPR
888.’’ NRECA asks for confirmation that and the RTO, ISO, or independent entity provides, in relevant part, that ‘‘[t]he Network
sroberts on PROD1PC70 with RULES

distribution and generation and transmission provider. Customer shall not operate its designated Network
transmission cooperatives will not be 1684. As to PNM–TNMP’s request Resources located in the Network Customer’s or the
Transmission Customer’s Control Area such that the
considered affiliates of each other for that the definition of ‘‘affiliate’’ be output of those facilities exceeds its designated
Network Load, plus Non-Firm Sales delivered
960 113 FERC ¶ 61,239 at P 7 (2005). 961 Order No. 888–A at 30,286 and 30,366. pursuant to Part II of the Tariff, plus losses.’’

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00217 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12482 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

section 30.4, energy sales that can only firm, provided that the sale cannot be service. As discussed in section V.D.7,
be interrupted to maintain system curtailed only for economic reasons. the Commission retains the existing
reliability would be considered firm requirement in section 28.4 that permits
Commission Determination
sales. use of secondary network service ‘‘to
1692. The Commission adopts the deliver energy to its Network Loads.’’
Comments proposed definition of a Non-Firm Sale The proposed definition of ‘‘economy
1689. Several commenters argue that and incorporates that defined term in energy’’ is therefore unnecessary.
the proposed definition of Non-Firm section 30.4 of the pro forma OATT.
Network customers may use network f. Commenter Proposals
Sales could impede a network
customer’s ability to obtain transmission resources for third party sales only if the 1697. Several commenters request
service for certain types of energy sale is on a non-firm basis. This ensures that the Commission amend or add
products. In particular, Duke, EEI, and that the network resource is available to other definitions in the pro forma
Southern question the treatment of serve the network load on an OATT.
power purchase agreements with LD uninterruptible basis. We conclude that
(1) Network Transmission Service
provisions under the proposed it would be inappropriate, as some
definition. Duke contends that a commenters suggest, to relax the Comments
contract with an LD provision might be definition of a Non-Firm Sale to include 1698. TDU Systems and Northwest
interruptible for any reason, but it any sale that is not otherwise firm Parties contend that, to help eliminate
would still provide for liability in the enough to be designated as a network undue discrimination, the Commission
form of LD payments. As a result, the resource. We address the requirements should modify the definitions of
LD contract might not fall within the for designation of network resources in ‘‘network load’’ and ‘‘network operating
definition of a Non-Firm Sale. At the section V.D.6, concluding that not all committee’’ in the pro forma OATT.
same time, network customers can only contracts with LD provisions are Although the pro forma OATT already
designate resources from system sufficiently firm to be eligible for defines ‘‘network load’’ to include
purchases not linked to a specific designation. There we explain that only wholesale native load, TDU Systems
generating unit if the purchase power LD provisions that provide for ‘‘make contend that transmission providers
agreement is not interruptible for whole’’ remedies are sufficiently firm to frequently either give preference to their
economic reasons, does not excuse be designated as network resources. It own retail native load or ignore
seller performance for economic does not follow, however, that all wholesale customer native load in
reasons, and requires the network remaining contracts with LD provisions planning and expansion of the system
customer to pay for the purchase. are non-firm. The very existence of an and in ATC calculations for processing
1690. Commenters are thus concerned LD provision indicates that interruption transmission service requests. TDU
that some contracts with LD provisions of service will result in liability and, Systems argue that comparable
may be too firm to be a Non-Firm Sale, thus, such contracts cannot treatment of wholesale native load and
but not firm enough to be designated as automatically be considered Non-Firm retail native load is required in all
a network resource. Duke argues that Sales for purposes of section 30.4. To respects in light of the definition of
network customers should be allowed to allow otherwise would create ‘‘network load.’’ At the same time, TDU
operate their Network Resources to both conflicting incentives for the network Systems argue that the definition of
serve load and sell a firm LD product. customer. ‘‘network load’’ unreasonably restricts a
EEI is concerned that the proposed d. Pre-Confirmed Application transmission customer from serving a
definition of Non-Firm Sales would part of its load at a given delivery point
prohibit a network customer from NOPR Proposal with non-network resources since it
making an off-system sale of a firm LD 1693. Incident to the proposal to give provides that a customer ‘‘may not
product or any other product that does priority to requests that are pre- designate only part of the load at a
not result in undesignation of a Network confirmed, the NOPR proposed a new discrete Point of Delivery.’’
Resource, given the restrictions set forth definition of Pre-Confirmed 1699. Northwest Parties also assert
in section 30.4. Duke and EEI therefore Application. that the Commission should revise the
propose that a Non-Firm Sale should be definition of ‘‘network load’’ to permit
defined as any sale that is not Comments
point-to-point service and network
sufficiently firm to be designated a 1694. No commenters oppose the service to the same network load if the
Network Resource of the purchasing Commission’s proposed definition of a point-to-point service is ignored in
entity. Raising concerns similar to those Pre-Confirmed Application. calculating load ratio share. Northwest
raised by Duke and EEI, Southern Commission Determination Parties also argue that the Commission
proposes to define Non-Firm Sales as should allow point-to-point and
any sale that does not commit the 1695. The Commission adopts the network service to the same network
associated resource to a third party and proposed definition of Pre-Confirmed load if the point-to-point service is
otherwise keeps the resource available Application in order to implement the purchased as non-firm.
for network service on a non- reforms adopted above regarding the 1700. EEI replies in opposition to
interruptible basis. priority of transmission service requests TDU Systems’ proposal to eliminate the
1691. NRECA, however, argues that under the pro forma OATT. requirement that a network customer
contracts with LD provisions are e. NOPR Proposals Not Adopted may designate only part of its load
typically considered firm products, so delivery as a network load. EEI argues
long as they cannot be curtailed for Economy Energy that TDU Systems are incorrect in
sroberts on PROD1PC70 with RULES

economic reasons alone. NRECA 1696. The Commission also proposed asserting that the definition of ‘‘network
requests that the Commission confirm in the NOPR to adopt a definition of load’’ prohibits a network customer
its understanding that the mere ‘‘economy energy’’ incident to its from serving part of its load with non-
inclusion of an LD provision in a proposed changes to section 28.4 network resources and secondary
contract does not make the sale non- regarding the use of secondary network network service to serve part, or even

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00218 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12483

all, of its network load. EEI contends Commission could require that firm as a result, requiring system impact
that adoption of TDU Systems’ proposal transmission service be available at least studies for short-term requests often
would eliminate one of the fundamental 95 percent of the time (excluding force creates unnecessary burdens for
principles on which network service is majeure curtailments) in order for transmission providers by mandating
founded: That the network customer transmission to be defined as ‘‘firm.’’ them to use limited resources to perform
must pay for network service based on 1704. Powerex also contends that studies that do not offer significant
its entire load, including load served by ‘‘non-firm transmission service’’ is benefits to customers. Powerex contends
behind the meter generation, since the interpreted differently in different that the 60-day study period is
transmission provider must plan its regions. In the Pacific Northwest, particularly ill-suited for short-term
transmission system to serve the Powerex asserts that non-firm service transmission requests, most of which
customer’s entire load. implies a lower curtailment priority but are for service that must commence
1701. PNM–TNMP agree on reply that only as a result of actual transmission within the study period.
Commission should reject a change to system constraints (i.e., once the
the definition in the pro forma OATT Commission Determination
operating hour has begun, higher
regarding network load. PNM-TNMP priority firm reservations cannot 1707. The Commission declines to
state that the proposal presupposes that implement schedules over lower modify the definition of ‘‘system impact
transmission providers discriminate priority non-firm reservation). In study’’ or otherwise modify section 17.5
against transmission customers and contrast, Powerex argues that, for some to restrict system impact studies only to
provides preferential treatment to their transmission providers located in the exclude reference to short-term point-to-
own retail native load in terms of Desert Southwest, transmission capacity point service. Regardless of the length of
planning and expansion of the system associated with firm service reservations a service request, a transmission
and in ATC calculations for processing that have capacity schedules attached to provider must assess whether a system
transmission service requests. PNM– them (e.g., to deliver operating reserves) impact study is required to evaluate the
TNMP contend that they treat retail can also be sold as non-firm service that request for transmission service. Only
native load comparably with other could be interrupted in the operating upon the completion of such an
network customers in all aspects and hour by the firm reservation. Powerex assessment will the transmission
believe that any problems encountered believes that these two types of service provider be able to identify the impact
by a transmission customer regarding could be described as non-firm, non- a particular request will have on the
undue discrimination should be interruptible (for the Pacific Northwest) grid. We conclude that eliminating or
addressed through the enforcement or and non-firm, interruptible (for the shortening the system impact study
complaint process, and that a change to Desert Southwest). period could jeopardize system
the pro forma OATT is not warranted. reliability and therefore reject the
Commission Determination modifications proposed by Powerex.
Commission Determination
1705. The Commission finds that the
1702. The Commission declines to (4) Definitions for RTOs, ISOs and ITCs
clarifications proposed by Powerex are
modify the definitions of ‘‘network Comments
unnecessary to remedy undue
load’’ and ‘‘network operating
discrimination in the provision of open 1708. Wisconsin Electric and
committee.’’ The reforms related to ATC
access transmission service. In section International Transmission argue that
calculation and transmission planning
V.D.8 of this Final Rule, the the terms used in the pro forma OATT
adopted in this Final Rule adequately
Commission requires transmission are inadequate when applied to RTO
address the concerns regarding undue
providers to post additional information regions, especially in MISO.
preference of native load in those areas.
With regard to the request to allow regarding curtailments in order to International Transmission and
network customers to serve part of their provide transparency and allow Wisconsin Electric assert that, in an
load with non-firm point-to-point customers to determine whether they RTO, the transmission provider and
service and part with network service, have been treated in the same manner transmission owner are separate entities
the Commission already determined in as other transmission system users. We with separate functions, thus creating a
Order Nos. 888 and 888–A that a conclude that existing compliance and need for separate definitions. They also
transmission customer is not allowed to enforcement procedures, coupled with contend that additional definitions may
take a combination of both network and these new posting requirements, are be needed when the transmission owner
point-to-point transmission service to sufficient to address improper is an independent stand-alone
serve the same discrete load.963 We are curtailments of service. transmission company operating within
not persuaded to modify that policy (3) System Impact Study the RTO.
here. 1709. Wisconsin Electric requests that
Comments the Commission define the term
(2) Firm and Non-Firm Transmission 1706. Powerex urges the Commission ‘‘transmission owner’’ in the pro forma
Service to modify sections 1.47 and 17.5 of the OATT and specify which of its
Comments pro forma OATT to clarify that provisions are applicable to the
1703. Powerex contends that ‘‘firm transmission providers are not required transmission provider and which apply
transmission service’’ is not adequately to perform system impact studies for to the ‘‘transmission owner.’’
defined or sufficiently described in the short-term service requests. Specifically, Additionally, Wisconsin Electric states
pro forma OATT to ensure that a Powerex requests that the Commission that the pro forma OATT includes a
transmission customer is not being amend the definition of a ‘‘system definition for ‘‘control area’’ and the
required to pay for firm service that is impact study’’ to refer only to requests NOPR refers to the geographic area
sroberts on PROD1PC70 with RULES

curtailed on a regular basis. For for long-term firm point-to-point service served by transmission providers as its
example, Powerex states the or network service. Powerex argues that control area, which in Wisconsin
short-term firm point-to-point service Electric’s view is inaccurate in the case
963 See Order No. 888 at 31,736; Order No. requests do not require transmission of MISO. Wisconsin Electric explains
888–A at 30,259. providers to upgrade their systems and, MISO has shifted to the use of the NERC

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00219 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12484 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

functional model and uses terms such as revenue credit instead. In addition, manner, pursuant to the principles set
‘‘balancing authorities,’’ ‘‘generator Ameren believes that the current forth in the Policy Statement on
operators,’’ ‘‘reliability authorities,’’ and definition of long-term firm point-to- Enforcement.
the like. Wisconsin Electric therefore point service in section 1.18 of the pro
1. General Policy
requests that the Commission supplant forma OATT makes calculation of load
the term ‘‘control area’’ in the pro forma ratio share very difficult in the modern a. Compliance Review Regime
OATT with a term that is predicated on RTO/Seams Elimination Cost Allocation NOPR Proposal
the performance of a particular function, (SECA) environment.
1715. The Commission proposed to
not the type of entity performing the Commission Determination maintain a strong program to audit
function.
1713. The Commission is not compliance with the new pro forma
1710. International Transmission does
persuaded to adopt the revisions OATT. The audit program would
not object to the Commission’s proposal
proposed by Ameren. We believe that include operational audits similar to
to largely retain the existing definitions
what constitutes source and sink is past OATT compliance audits, during
set forth in the pro forma OATT, but
sufficiently addressed in Order No. 888 which staff may collect information on
asserts that the Commission should
and OASIS related proceedings and we implementation of a transmission
explicitly recognize in the Final Rule
will not expand the discussion here.964 provider’s OATT. The Commission
that such definitions may be inadequate stated that it would issue public reports
when applied to RTOs. International Order No. 888 also made clear that there
are no ‘‘load ratio’’ limitations on the of audit results and noted that contested
Transmission also asks the Commission audits would be subject to the
not to require RTOs with additional use of interfaces under section 30.8 of
the pro forma OATT.965 Otherwise, Commission’s Final Rule on contested
definitions in their tariffs to remove operational audits.966
those definitions when complying with requests for interface capacity are
the Final Rule and, instead, expressly subject to the pro forma OATT Comments
allow RTOs to propose additional procedures. Moreover, Ameren has
failed to justify revising the definition of 1716. Most initial commenters
definitions that may be necessary. support a strong staff audit program.967
‘‘transmission peak.’’ While peak load
Commission Determination data ultimately resides with the RTO or Other commenters counter that staff
ISO, each transmission provider audits will not be needed if the
1711. As explained in section IV.C, all Commission issues a corrected pro
transmission providers—including ISOs coordinates this type of data with RTO
or ISO. Finally, we reaffirm that long- forma OATT, especially with respect to
and RTOs—will have an opportunity to RTOs and ISOs.968 These commenters
demonstrate that departures from the term firm service is service with a term
of one year or more. Modifying the term argue that formal complaints,
pro forma OATT, as modified by this Enforcement Hotline calls and random
Final Rule, are consistent with or of long-term service to reduce the
number of contracts used in the audits sufficiently inform staff of OATT
superior to the terms and conditions of compliance issues as to make additional
the pro forma OATT. Proposals to denominator for purposes of calculating
the load ratio share and for ratemaking staff audits unnecessary. Southern
amend terms such as ‘‘control area’’ or asserts that, under the separation of
‘‘transmission owner’’ based on a purposes may affect how the
function policy, Commission audit staff
particular set of facts are best left for transmission provider plans its system
should be separated from investigative
case-by-case review. to service customers and has not been
and enforcement staff. Particular
justified.
(5) Other Definitions commenters contend that the
E. Enforcement Commission should focus compliance
Comments efforts on specific OATT provisions,
1714. The Commission attaches
1712. Ameren advocates the substantial importance to strengthening such as those concerning network
modification of a number of other pro compliance with the OATT, on service (Arkansas Cities), or on
forma OATT definitions. Ameren monitoring and auditing OATT structural issues such as independent
proposes definitions for ‘‘source’’ and compliance, including its staff’s efforts planning and operation of transmission
‘‘sink,’’ as well as additional provisions to resolve disputes about compliance facilities (Reliant). Nevada Companies
in section 22.2 governing source and through the Enforcement Hotline and suggests that the Commission set up
sink of transmission. Ameren also other dispute resolution mechanisms, regional audit teams to foster strong
requests clarification of the word ‘‘use’’ and on investigating potential and working relationships with transmission
in section 30.8, arguing that some alleged OATT violations. The expansion providers. EPSA asks the Commission to
entities have assumed that ‘‘use’’ means of the Commission’s enforcement adopt stronger measures than a staff
scheduled amounts. Ameren argues for powers pursuant to EPAct 2005 directly audit program to monitor compliance.
an improved definition of ‘‘transmission augmented its ability to enforce the EPSA’s proposed measures include
peak’’ because the data necessary no OATT by, among other things, requiring transmission providers to:
longer resides with the transmission providing authority to assess civil designate compliance officers to report
owner in an RTO or ISO. Finally, penalties of up to $1 million for each OATT violations to company boards;
Ameren suggests a revised definition of day that an OATT violation continues. undergo compliance audits by an
‘‘long-term firm,’’ which would include The Commission intends to use its
966 See Procedures for Disposition of Contested
only contracts that are longer than one enforcement powers with respect to the Audit Matters, Order No. 675, 71 FR 9698 (Feb. 27,
year, not just one year or longer, arguing OATT in a fair and even-handed 2006), FERC Stats. & Regs. ¶ 31,209 (2006)
it would reduce the number of contracts (Contested Audit Matters), order on rehearing and
that are only one-year in length that are 964 Redirect-related issues are addressed in clarification, Order No. 675–A, 71 FR 29779 (May
sroberts on PROD1PC70 with RULES

used in the denominator for purposes of section V.D.4. 24, 2006), FERC Stats. & Regs. ¶ 31,217 (2006).
965 See Order No. 888 at 31,753–54; Order No. 967 E.g., APPA, AWEA, EEI, Morgan Stanley,
calculating the load ratio share and for
888–A at 30,304–5; see also Sierra Pacific Power NRG, Southern, TAPS, and Williams.
ratemaking purposes. On this latter Co., 81 FERC ¶ 61,136 at 61,139–40 (1997); New 968 E.g., Ameren, PNM–TNMP, and South
point, Ameren asserts that such England Power Pool, 83 FERC ¶ 61,045 at 61,248 Carolina E&G. In reply comments, TDU Systems
contracts should be reflected as a (1998). urge the Commission to reject this contention.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00220 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12485

independent auditor in response to designated an OATT compliance officer, their inquiries.971 Southern has not
material violations; and hire an engaged a third-party auditor, or cited any justification for restricting
independent administrator to oversee transferred transmission functions to an communications among these staff
OATT compliance and regional independent transmission coordinator. members or from them to the
planning efforts if a transmission We decline EPSA’s proposal to require Commission. To the contrary, a free
provider has not complied with its new such actions, except on a case-by-case flow of communications among auditors
OATT within a specified period of time. basis when warranted. and investigators, consistent with the
In reply comments, MISO opposes 1719. We disagree with PJM’s request Commission’s rule on staff separation of
EPSA’s proposal for a third-party that the Commission require third-party functions, should increase the efficiency
compliance administrator for RTOs and market monitoring to ascertain market of the Commission staff’s compliance
ISOs if they do not timely comply with abuses occurring with respect to program and enforcement efforts.972
new OATT provisions, arguing that transmission providers outside RTOs
these entities already are independent and ISOs, subject to Commission b. Use of Independent Third Party
administrators of transmission grids and oversight. In a number of instances Audits
planning processes. MISO asserts that since 2000, the Commission has
inserting an ‘‘independent’’ authority NOPR Proposal
established third-party monitoring of a
over OATT compliance by RTOs and 1721. The Commission proposed not
transmission provider located outside
ISO would create a superfluous to mandate the use of third party
an RTO or ISO.969 These monitors were
bureaucratic layer. NRECA opposes
established on a case-specific basis to auditors and, instead, proposed that
EPSA’s proposal because a third-party
address concerns related to the Commission staff conduct audits of
compliance administrator or auditor
transmission provider at issue. We have compliance with the pro forma OATT.
would be too expensive and the
no evidence to support requiring The Commission stated that it may
Commission cannot delegate its
monitors for every transmission require third party compliance audits as
compliance authority.
1717. Noting that the Commission provider in the Nation. Further, the part of a compliance plan following a
required RTOs to undertake extensive Commission has access to substantial Commission staff audit report. In
market monitoring in Order No. 2000, information on OATT compliance by response to situations such as
PJM states that the Commission should transmission providers that are not systematic OATT violations, a pattern of
require in the pro forma OATT a similar RTOs or ISOs through their postings on repeated violations, or violations that
degree of market monitoring in non- OASIS, informal and formal complaints require ongoing monitoring, the
RTO areas to make available to by customers, and reports by market Commission could require an audited
Commission staff information needed to monitors for such transmission
party to hire a third party to continue
ascertain market abuses in these areas. providers. Indeed, the revised pro forma
compliance audits.
PJM asserts that any such market OATT will greatly enhance our
monitoring should be performed by oversight and enforcement capabilities Comments
entities independent of the non-RTO by increasing the transparency of many
utilities, with Commission oversight. critical functions under the pro forma 1722. Most initial commenters agree
Indicated Parties reply that RTOs’ OATT, such as ATC calculation and with the Commission’s proposal to
market monitors should examine market transmission planning. PJM has not require third-party audits only as part of
power in transmission planning because provided any evidence that the an individual post-audit compliance
RTOs delegate transmission operations enhanced transparency under the plan.973 EEI and Southwestern Coop
and planning duties to constituent OATT, coupled with the Commission’s submit that selection of third-party
transmission owners that retain own monitoring and audits of OATT auditors should be subject to
incentives to benefit affiliates or compliance and its enhanced Commission review and approval, while
vertically-integrated divisions. enforcement authority, will be South Carolina E&G cautions that the
insufficient to ascertain and deter OATT Commission should carefully weigh the
Commission Determination violations. We do not object to the costs and benefits of independent
1718. The Commission adopts the suggestion of Indicated Parties that RTO auditors before requiring their use.
NOPR proposal to emphasize a strong and ISO market monitors examine Southern suggests that third-party
staff audit program for compliance with market power in transmission planning, audits be required only for systematic,
OATT requirements, including so long as the market monitors’ egregious OATT violations. Entegra
operational audits. Staff audits of OATT activities in this respect are consistent doubts that third-party auditors can
compliance may be random or targeted with these roles as set forth in the remedy patterns of discrimination by
with respect to the entities being applicable RTO and ISO tariffs. transmission providers against
audited or particular provisions of the 1720. We do not agree with independent merchant generators.
OATT that are scrutinized. Because its Southern’s assertion that the
responsibility is to assess and ensure Commission’s audit staff should be 971 Statement of Administrative Policy on
compliance with the OATT, staff will separated from its investigative and Separation of Functions, 101 FERC ¶ 61,340 at P
maintain discretion as to the entities it enforcement staff. The Commission’s 24–26 (2002).
audits and the subject matter of these separation of functions regulation 970
972 See also Order No. 675–A at P 25–29 (the

audits. The Commission encourages generally permits Commission auditors,


Commission’s regulation and policy statement on
transmission providers to designate separation of functions remain applicable following
investigators and enforcement staff to EPAct 2005, and efficiency and sound
employees as compliance officers for the speak freely to persons inside the administrative practice continue to favor the
OATT or to conduct third-party audits Commission as to the subject matter of sharing of information between the Commission’s
sroberts on PROD1PC70 with RULES

relating to OATT compliance when audit staff and investigative staff).


973 E.g., Alberta Intervenors, Arkansas
appropriate. However, we do not believe 969 See, e.g., Duke Power, 113 FERC ¶ 61,288
Commission, Constellation, EEI, EPSA, MISO/PJM
that staff should forego an audit of an (2005); MidAmerican Energy Holdings Co., 113 States, Nevada Companies, PNM–TNMP, South
entity’s OATT compliance solely FERC ¶ 61,298 (2005). Carolina E&G, Southwestern Coop, and Suez Energy
because a transmission provider has 970 18 CFR 385.2202. NA.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00221 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12486 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Commission Determination instead support incorporation in the pro violations involving reasonable
1723. The Commission adopts the forma OATT of a schedule of significant interpretations of tariff provisions or for
NOPR proposal not to require generally remedies and sanctions for specific actions taken for reliability purposes
the use of third party auditors to assess violations to assure transparency and that are consistent with good utility
compliance with the OATT. We believe certainty as to situations in which practice. PNM–TNMP and Southern ask
that a requirement for the use of third- penalties would be assessed and to deter the Commission to clarify that LSEs will
party audits in compliance plans should anticompetitive behavior. 977 EPSA not be penalized for OATT violations
depend on particular facts, including advises that the Commission refrain for taking actions necessary to meet
the egregiousness and extent of from setting pre-determined limits on their native load obligations since,
violations found during a staff audit or penalty amounts because each violation pursuant to new FPA section 217, 981
investigation and the appropriate scope of a specific pro forma OATT provision LSEs should not be considered to have
or cost of a third-party audit. As stated may present different facts that may engaged in ‘‘undue discrimination or
above, we encourage transmission warrant different outcomes. Nevada preference’’ for certain actions required
providers to use third-party compliance Companies suggest that the Commission to serve native load customers. TDU
audits when appropriate to supplement provide incentives to construct new Systems argue in reply comments that a
our staff’s audit efforts. transmission infrastructure rather than ‘‘safe harbor’’ approach could permit
implement an overbearing penalty unduly discriminatory or preferential
2. Civil Penalties regime because additional transmission behavior that would be penalized under
1724. In the NOI, the Commission capacity itself will resolve many a case-by-case approach. Entegra replies
asked for comment as to whether it complaints. that safe harbors for ‘‘reasonable’’ tariff
should address imposing remedies or 1727. Wisconsin Electric concludes interpretations would give vertically-
penalties against transmission providers that OATT violations by non-profit integrated utilities license to
as part of OATT reform. After the NOI, RTOs and ISOs should not be subject to discriminate against competitors, and
the Commission issued its Policy civil penalties because they would be suggests that the Commission ensure
Statement on Enforcement and, in passed through to customers and not act that the OATT operates as a sword for
response to specific authority granted it as an effective deterrent. 978 Rather than attacking undue discrimination, not as a
in EPAct 2005, issued Order No. 670, assess a penalty in response to an RTO’s shield for defending it. Occidental
the Anti-manipulation Rule. 974 or ISO’s OATT violation, Wisconsin replies that transmission providers with
Electric suggests that the Commission a Commission-approved independent
a. Whether Civil Penalties Should Be could intensify oversight of an RTO’s or transmission coordinator should not be
Specified in the OATT ISO’s OATT compliance. NorthWestern insulated from tariff-based civil
NOPR Proposal comments, in contrast, that RTOs and penalties and other sanctions.
1725. Aside from operational ISOs should not be exempted from civil
penalty assessments for their OATT Commission Determination
penalties proposed in the NOPR, 975 the
Commission proposed not to establish a violations, because these violations 1730. Following enactment in EPAct
schedule of enforcement remedies and could have as much or more adverse 2005 of enhanced authority for the
sanctions in the pro forma OATT. effects on transmission access or system Commission to assess civil penalties for
Rather, the Commission stated that it reliability as would OATT violations by violations of statutes it administers and
would address OATT violations and other transmission providers. of regulations and orders under these
appropriate responses on a case-by-case 1728. Several commenters support the statutes, the Commission issued the
basis, consistent with the Policy Commission’s proposal to consider Policy Statement on Enforcement to set
Statement on Enforcement. The mitigating factors listed in the Policy forth how it intends to use this authority
Commission explained that it may Statement on Enforcement in assessing consistent with the statute. 982
impose civil penalties when warranted, civil penalties for OATT violations. 979 Underlying this policy is the recognition
after consideration of applicable factors In this regard, EEI states that the that the appropriate basis for assessment
listed in the Policy Statement on Commission should clarify that when a of a civil penalty for a violation is an
Enforcement; OATT violators also will party engages in self-reporting, examination of the facts and
be expected to disgorge unjust profits compliance programs or cooperation circumstances relating to that violation,
when they can be determined or with Commission staff, the Commission and the use of discretion and flexibility
reasonably estimated. will recognize the party’s attorney-client to address it on its merits. This
privilege. 980 examination includes a review of all
Comments 1729. EEI suggests that the applicable mitigating factors set forth in
1726. The majority of parties filing Commission establish ‘‘safe harbors’’ the Policy Statement on Enforcement.
comments on this issue agree that the against civil penalties for OATT While we understand that establishing a
Commission should assess civil schedule of civil penalties for violations
penalties on a case-by-case basis under discriminatory behavior in its transmission
planning process. of particular provisions of the pro forma
the guidance of the Policy Statement on 977 E.g., Arkansas Commission and ELCON. OATT would establish greater
Enforcement. 976 Other commenters 978 Wisconsin Electric asserts that the specificity with respect to civil
Commission has recognized this principle in other penalties, the Commission already
974 Prohibition of Energy Market Manipulation, III contexts, citing Financial Reporting and Cost concluded in the Policy Statement on
FERC Stats. & Regs. ¶ 31,202 (2006), order denying Accounting, Oversight and Recovery Practices for
rehearing, 114 FERC ¶ 61,300 (2006). Regional Transmission Organizations and Enforcement that it would ‘‘not
975 NOPR at P 384. Independent System Operators, FERC Stats. & Regs. prescribe specific penalties or develop
976 E.g., APPA, EEI, EPSA, Nevada Companies, ¶ 35,546 at P 9 (2004). formulas for different violations.’’ 983
sroberts on PROD1PC70 with RULES

979 E.g., Nevada Companies and PNM–TNMP.


PNM–TNMP, Southern, and Southwestern Coop. We see no justification to depart from
Southwestern Coop also urges speedy review of 980 EEI observes that the Commission held in its

violations and swift assessment of penalties. In final rule on contested audit procedures that ‘‘an
981 16 U.S.C. 824q(k).
reply comments, Sacramento adds that the audited person who appropriately interposes the
982 Policy Statement on Enforcement at P 1.
Commission may assess civil penalties against a attorney-client privilege will not be considered non-
transmission provider that engages in unduly cooperative.’’ Contested Audit Matters at P 35. 983 Id. at P 13.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00222 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12487

that decision with respect to violations 1733. We agree with commenters who b. Whether Transmission Providers
of OATT provisions. state that the Commission and its staff Should Be Subject to Revocation of
1731. Several commenters ask that we should recognize the valid assertion of Market-Based Rates for OATT
establish specific ‘‘safe harbors’’ or the attorney-client privilege in the Violations
exemptions from assessment of civil context of investigations, audits and NOPR Proposal
penalties for OATT violations in other fact-finding activities. As EEI
specific circumstances or with respect 1735. The Commission observed in
points out, we recently stated with
to specific types of entities that may the NOPR that some OATT violations,
respect to audits that we would not after applying the factors in the Policy
engage in OATT violations. We decline consider an entity to be uncooperative
to create automatic safe harbors for Statement on Enforcement to all facts
with audit staff if the entity and circumstances, may merit
specific circumstances or specific types appropriately asserts that a
of OATT violations. The creation of revocation of market-based rate
communication or document is covered authority. Before considering revoking
such exemptions would require us to
by that privilege.987 We take the same an entity’s market-based rate authority
forego the examination of the specific
position with respect to investigations for an OATT violation, the Commission
circumstances of particular violations
that we described in the Policy or other fact-finding undertakings with proposed that it must find a nexus
Statement on Enforcement as the respect to possible OATT violations. between the specific facts relating to the
touchstone of our policy in assessing 1734. In the Policy Statement on OATT violation and the entity’s market-
civil penalties. Instead, we will decide Enforcement, however, the Commission based rate authority. The Commission
requests for leniency in particular cases drew a distinction between cooperation, also proposed that if it determines, as a
by using the principles set forth in the which we expect from entities subject to result of a significant OATT violation, to
Policy Statement on Enforcement and the Commission’s jurisdiction given revoke the market-based rate authority
considering all applicable mitigating their statutory obligation to provide of a transmission provider within a
factors listed therein.984 particular market, each affiliate of the
information to us, and ‘‘exemplary’’
1732. Likewise, we will not establish transmission provider that possesses
cooperation, which ‘‘quickly ends
an automatic exemption from civil market-based rate authority would have
wrongful conduct, determines the facts,
penalty assessments for OATT that authority revoked in that market,
and corrects a problem.’’ 988 The effective on the date of revocation of the
violations committed by particular types Commission explained that we will give
of entities such as non-profit RTOs and transmission provider’s market-based
some consideration to exemplary rate authority.
ISOs. The Commission decided last year cooperation and indicated that one
that it would not automatically exempt example of such cooperation is a Comments
RTOs and ISOs from penalties assessed
situation in which an entity being 1736. Most parties that submitted
by the Electric Reliability Organization
investigated provides to staff internal initial comments on this issue support
or Regional Entities for reliability
investigations or audit reports relating the Commission’s conclusion that, in
violations pursuant to new FPA section
to misconduct. These investigations and certain circumstances, it may be
215. In Order No. 672, the Commission
reports may include information that an appropriate to revoke the market-based
stated, ‘‘[w]hile we recognize that RTOs
entity could properly shield from rate authority of an entity that engages
and ISOs have some unique
disclosure pursuant to the attorney- in an OATT violation.990 The majority
characteristics, we do not believe that a
client privilege. We observe that an of these commenters support the
generic exemption from any type of
entity that is in a position to assert this Commission’s proposal to do so only if
penalty is appropriate for any entity,
privilege validly also has the option to it finds a nexus between the OATT
including an RTO or ISO.’’ 985 We
waive it. If a waiver of attorney-client violation and the entity’s market-based
believe the same principle applies to
privilege, whether related to an internal rate authority.991
civil penalties for OATT violations. 1737. Some commenters oppose the
However, in assessing civil penalties for investigation or audit or not, assists staff
requirement for a nexus between the
OATT violations, we will consider all in ascertaining the facts relating to OATT violation and the entity’s market-
applicable facts relating to the violator, alleged or apparent misconduct, ends based rate authority because the
including the effect of potential misconduct quickly or otherwise Commission has not stated what facts
penalties on the financial viability of the substantially advances an investigation would be sufficient to show such a
violator.986 or inquiry, that waiver may be an nexus.992 EPSA and NRECA (in reply
element in finding ‘‘exemplary comments) contend that if the
984 We have also provided clarification on the
cooperation’’ as described in the Policy Commission does not remove the
procedures that would apply to the assessment in
formal proceedings of civil penalties relating to Statement on Enforcement.989 ‘‘nexus’’ condition, it should clarify
OATT violations in our recent Statement of what constitutes a ‘‘nexus’’ between an
Administrative Policy Regarding the Process for OATT violation and an entity’s market-
Assessing Civil Penalties, 117 FERC ¶ 61,317 (2006).
985 Rules Concerning Certification of the Electric
based rate authority. Similarly, PNM–
Reliability Organization; and Procedures for the TNMP argues that such a nexus must be
Establishment, Approval, and Enforcement of
987 Citing Contested Audit Matters at P 35. clear and fact-specific, consistent with
Electric Reliability Standards, Order No. 672, 71 FR 988 Policy Statement on Enforcement at P 26. the Policy Statement on Enforcement.
8662 (Feb. 17, 2006), FERC Stats. & Regs. ¶ 31,204 989 See In re PacifiCorp, 118 FERC ¶ 61,026 at P
at P 634 (2006), order on reh’g, Order No. 672–A,
TDU Systems contend in reply
3, 8 and attached stipulation and consent agreement
FERC Stats. & Regs. ¶ 31,212 (2006). at P 24 (2007) (referring to transmission provider’s
986 Policy Statement on Enforcement at P 20. Cf. 990 E.g., EEI, ELCON, Morgan Stanley, Nevada
waivers of attorney-client privilege as an element in Companies, Northwest IOUs, Progress Energy,
Order No. 672–A at P 56–57 (holding that for
sroberts on PROD1PC70 with RULES

making finding of exemplary cooperation with PNM–TNMP, Sempra Global, Southern, and TDU
determining a penalty pursuant to the FPA section
215 reliability program, circumstances such as investigation when approving settlement assessing Systems.
organization structure or non-for-profit status will civil penalty that resolved a transmission provider’s 991 E.g., EEI, Nevada Companies, Northwest IOUs,

be considered, but that there should not be an violations of its OATT, among other matters); In re Progress Energy, PNM–TNMP, Sempra Global, and
automatic exemption from monetary penalties for Entergy Services, Inc., 118 FERC ¶ 61,027 at P 15, Southern.
RTOs and ISOs). 18 (2007) (same). 992 E.g., APPA.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00223 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12488 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

comments that, at a minimum, a unlawful activities should not lose their substantial OATT violation has
transmission provider or its affiliate that market-based rate authority as a result of occurred and that the violation either
has market-based rate authority must the transmission provider’s OATT related to the exercise of the violator’s
overcome a rebuttable presumption that violation. NRECA replies that market- market-based rate authority or violated
its OATT violation has the requisite based rate authority is a privilege, not a a specific condition of that authority.
‘‘nexus’’ to support revocation of such right, and asserts that the Commission 1745. The Commission emphasizes
authority. should revoke market-based rate that we have discretion to fashion
1738. Other commenters argue that a authority in response to an OATT remedies for OATT violations that relate
serious OATT violation removes the violation that indicates that a public to the violator’s market-based rate
mitigation of transmission market power utility possesses market power. authority in instances in which we do
provided by adherence to an OATT, 1742. APPA also suggests that, short not find a factual nexus justifying
thereby eviscerating one of the essential of revocation of a transmission revocation of that authority. For
requirements for market-based rate provider’s market-based rate authority example, in appropriate circumstances,
authority.993 EEI and PNM–TNMP reply in response to an OATT violation, the we may modify or add additional
that not every OATT violation Commission could condition that conditions to the violator’s market-
diminishes the availability of authority, or the market-based rate based rate authority or impose other
transmission service so as to establish authority of the transmission provider’s requirements to help ensure that the
vertical market power. affiliates. APPA provides the following violator does not commit future, similar
1739. APPA and TDU Systems suggest examples of such conditions: A misconduct. Nor is revocation of
in reply comments that the proposed requirement to participate in joint market-based rate authority the only
nexus condition would unduly limit planning of transmission facilities with action we may take to respond to an
any sanctions, because the shareholders the transmission provider’s network OATT violation that meets the nexus
of the violator could still reap the customers and offer these customers condition. We will consider whether to
benefits of such a violation if an affiliate appropriate credits under OATT section impose sanctions such as assessment of
that did not have any knowledge of the 30.9; an offer of joint transmission civil penalties for particularly serious
OATT violation could continue to ownership opportunities to LSEs for OATT violations in addition to
engage in transactions under market- new transmission facilities on revocation of the violator’s market-based
based rate authority. According to reasonable terms and conditions; and an rate authority.
APPA, this possibility could lessen the offer to network service customers to 1746. We do not adopt our proposal
incentive for senior management over a participate in the ownership of the from the NOPR to revoke the market-
transmission provider and affiliates to transmission provider’s existing based rate authority of each affiliate of
make OATT compliance a high priority. transmission system on a load ratio a transmission provider that loses its
As such, APPA and TAPS suggest that share basis. market-based rate authority within a
the Commission consider revoking a Commission Determination particular market as a result of an OATT
transmission provider’s market-based violation. Rather, we will create a
1743. We adopt the NOPR proposal to
rate authority for a ‘‘material’’ OATT rebuttable presumption that all affiliates
revoke an entity’s market-based rate
violation that effectively denies, delays, of a transmission provider should lose
authority in response to an OATT
or diminishes a customer’s access to their market-based rate authority in each
violation only upon a finding of a
transmission service essential to market in which their affiliated
specific factual nexus between the
mitigating transmission market power. transmission provider loses its market-
1740. TDU Systems caution that violation and the entity’s market-based
rate authority. We believe that the based rate authority as a result of an
revocation of market-based rate OATT violation. We will allow an
‘‘nexus condition’’ is required in order
authority may not be sufficient to deter affiliate of a transmission provider to
to ensure that our actions are not
OATT violations if reversion to cost- retain its market-based rate authority in
arbitrary or capricious or based on an
based rates may provide a transmission a market area if the affiliate overcomes
inadequate factual record. We note that
provider with the ability to recover all the rebuttable presumption with respect
in this context the Commission has the
costs and receive higher revenues than to that market area.
burden to show a factual nexus. We do
competitive markets might otherwise 1747. We expect that the issue of
not assign a burden on the violator to
produce. Therefore, TDU Systems ask potential revocation of market-based
show the lack of this nexus.
that the Commission consider 1744. Determining what would be a rate authority will arise as a result of an
assessment of civil penalties in addition sufficient factual nexus between an OATT violation in a market in which
to revocation of market-based rate OATT violation and revocation of the the transmission provider possesses
authority. violator’s market-based rate authority is transmission market power through the
1741. The majority of commenters ownership of transmission facilities in
best left to a case-by-case consideration.
disagree, however, with the that market. For these markets, we have
The wide range of positions among
Commission’s proposal to revoke the evaluated whether a transmission
commenters on how to define a
market-based rate authority of all provider should receive authority to
sufficient factual nexus itself suggests
affiliates of a transmission provider to make sales of electric power for resale
that this finding is best made after
the same extent that we revoke that at market-based rates using a four-prong
review of a specific factual situation.
transmission provider’s market-based analysis. In this analysis we consider
Some commenters assert that a finding
rate authority.994 These commenters whether the transmission provider and
of a ‘‘serious’’ or ‘‘material’’ violation of
assert that affiliates that have no the OATT would be sufficient. We its affiliates have adequately mitigated
knowledge of, or involvement in, their disagree. While an entity’s market power in generation and
affiliated transmission provider’s
sroberts on PROD1PC70 with RULES

inconsequential OATT violation would transmission, whether the transmission


not serve as a basis for revoking that provider or its affiliates can erect other
993 E.g.,
APPA, EPSA, and TAPS.
994 E.g., entity’s market-based rate authority, our barriers to entry, and whether there is
EEI, Nevada Companies, Northwest IOUs,
Progress Energy, PNM–TNMP, Sempra Global, and view is that the nexus condition evidence that the transmission provider
Southern. requires us to find both that a and its affiliates have engaged in

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00224 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12489

affiliate abuse or reciprocal dealing.995 we believe that it is appropriate to Comments


In particular, we have long held that the establish a presumption in this 1750. All commenters on this issue
existence of an OATT is deemed to circumstance that if we find that a concur with a case-by-case approach to
mitigate vertical market power and transmission provider should lose its it.997 Southwestern Coop suggests that,
transmission market power held by a market-based rate authority in a market as the Commission gains sufficient
transmission provider and its affiliates in which it possesses transmission experience to describe particular
in a particular market. An OATT market power, we will revoke the misconduct as market manipulation per
violation by a transmission provider in market-based rate authority in that se, it should identify such misconduct
a market in which it possesses market of all affiliates of the in the OATT. While contending that the
transmission market power that merits transmission provider. Commission should act with caution in
revocation of the transmission listing behaviors that constitute per se
1748. We are mindful, however, that
provider’s market-based rate authority market manipulation in view of the
the circumstances of a particular
may call into question whether the dynamic nature of markets, TDU
transmission provider’s affiliates affiliate may not always justify the
imposition of a remedy so severe as Systems urge the Commission to specify
continue to qualify for market-based in the OATT that transmission planning
rates in that market under the standards revocation of market-based rate
authority in a particular market when its misconduct could constitute a form of
that we have established.996 As a result, market manipulation or abuse.
affiliated transmission provider loses its
995 In our recent NOPR on market-based rates for market-based rate authority in that Commission Determination
wholesale sales of electricity, the Commission market as a result of an OATT violation.
1751. We adopt the NOPR proposal
proposed to discontinue referring to affiliate abuse To afford due process to a transmission
among a transmission provider and its affiliates as for a case-by case approach to
a separate ‘‘prong’’ of our analysis of whether to
provider’s affiliates in that situation, considering whether OATT violations
grant market-base rate authority. The Commission and to ensure that a determination to may constitute market manipulation.
instead proposed to address affiliate abuse by revoke market-based rate authority in a Without reference to a specific factual
requiring that transmission providers and their particular market for a transmission
affiliates comply with restrictions and conditions pattern developed in an investigation or
set forth in the regulations we propose in that provider and all of its affiliates that on-the-record proceeding, the
proceeding. Market-Based Rates for Wholesale possess such authority is adequately Commission is not in a position to
Sales of Electric Energy, Capacity and Ancillary based upon record evidence and not identify market manipulation relating to
Services by Public Utilities, 71 FR 33102 (Jun. 7, arbitrary or capricious, we will allow an
2006), FERC Stats. & Regs. ¶ 32,602 at P 13 (2006). OATT violations.998
996 We observe that specific situations in which opportunity for each such affiliate to
transmission providers have agreed to resolve staff make a showing that it should retain its VI. Information Collection Statement
allegations that they engaged in OATT violations market-based rate authority or that 1752. The Office of Management and
have involved transactions with affiliates. See enforcement action against it should be
Idaho Power (settlement of, among other issues, an
Budget (OMB) regulations require that
Enforcement staff allegation that a transmission less severe than revocation. The OMB approve certain reporting, record
provider permitted its merchant function to request determination whether an affiliate has keeping, and public disclosure
non-firm transmission to enable the merchant overcome the rebuttable presumption (collections of information) imposed by
function to make off-system sales that by definition
were not used to serve native load, so that the
depends on an analysis of specific facts an agency.999 Pursuant to OMB
transmission did not qualify for the ‘‘native load’’ in the record. Relevant facts would regulations, the Commission is
priority specified in section 28.4 of the transmission include, but are not limited to, whether: providing notice of its proposed
provider’s OATT); Cleco Corp., 104 FERC ¶ 61,125 (1) The transmission provider and the information collections to OMB for
(2003) (settlement between Enforcement staff and a
utility holding company and its subsidiaries affiliate were under the same control; (2) review under section 3507(d) of the
relating, in part, to the provision by a transmission the affiliate knew of, participated in or Paperwork Reduction Act of 1995.1000
provider of a unique type of transmission service was an accomplice to the OATT 1753. The Commission identifies the
that was neither made available to non-affiliates nor violation; (3) the affiliate assisted the information provided under Part 35
included in its FERC tariff); Tucson Electric Power subpart C as contained in FERC–516
Co., 109 FERC ¶ 61,272 (2004) (operational audit in transmission provider in exercising
which staff found that, among other matters, a market power; or (4) the affiliate and Part 37 as contained in FERC–717.
transmission provider permitted its wholesale benefited from the violation. The Commission solicited comments on
merchant function to purchase hourly non-firm and the need for this information, whether
monthly firm point-to-point transmission service c. Whether Certain OATT Violations the information will have practical
using an off-OASIS scheduling procedure while the Should Be Considered Market
transmission provider did not post on its OASIS the
utility, ways to enhance the quality,
availability of capacity on these paths); South Manipulation Under Section 222 of the utility, and clarity of the information to
Carolina Electric & Gas Co., 111 FERC ¶ 61,217 FPA be collected, and any suggested methods
(2005) (settlement of Enforcement staff allegation for minimizing respondents’ burden,
that a transmission provider made available firm NOPR Proposal
point-to-point transmission service to its affiliated
including the use of automated
merchant function that did not submit transmission 1749. The Commission proposed in information exchanges. The
schedules with specific receipt points for the the NOPR to decline to identify in the Commission did not receive any specific
service as required by section 13.8 of the pro forma OATT specific conduct that comments regarding its burden
transmission provider’s OATT); and MidAmerican
Energy Co., 112 FERC ¶ 61,346 (2005) (operational constitutes per se market manipulation. estimates. Where commenters raised
audit in which staff found, among other things, that The Commission proposed to consider concerns that specific information
a transmission provider permitted its wholesale on a case-by-case basis, if and when collection requirements would be
merchant function to (a) use network transmission they arise, whether specific burdensome to implement, the
service to bring short-term energy purchases onto
its system while it simultaneously made off-system circumstances relating to OATT
997 APPA, Nevada Companies, PNM–TNMP,
sales, inconsistently with the preamble to Part III violations constitute market
Southwestern Coop, and TDU Systems.
of the transmission provider’s OATT and section manipulation under the standards set
sroberts on PROD1PC70 with RULES

998 Similarly, in issuing the Anti-manipulation


28.6 of its OATT; and (b) confirm firm network forth in Order No. 670.
transmission service requests without identifying a Rule, we declined to provide specific examples of
designated network resource or acquiring an what would constitute market manipulation. Order
associated network resource, in some instances inconsistent with section 29.2 or section 30.6 of the No. 670 at P 64–67.
999 5 CFR 1320.11.
using this service to deliver short-term energy transmission provider’s OATT). See also
purchases used to facilitate off-system sales, Commission orders cited in note 989 supra. 1000 44 U.S.C. 3507(d).

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00225 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12490 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Commission has address those concerns 1754. The Commission estimates the
elsewhere in the rule. burden for complying with the Final
Rule is as follows: 1001

Number of Number of Hours per Total annual


Data collection respondents responses response hours

Part 35 (FERC–516)

Conforming tariff changes ............................................................................... 116 1 25 2,900


Revision of Imbalance Charges ....................................................................... 116 1 5 580
ATC revisions .................................................................................................. 116 1 40 4,640
Planning (Attachment K) .................................................................................. 116 1 200 23,200
Congestion studies .......................................................................................... 116 1 300 34,800
Attestation of network resource commitment .................................................. 116 1 1 116
Capacity reassignment .................................................................................... 116 1 100 11,600
Operational Penalty annual filing ..................................................................... 116 1 10 1,160
Creditworthiness—include criteria in the tariff ................................................. 116 1 40 4,640

Sub Total Part 35 ..................................................................................... ........................ ........................ ........................ 83,636

Part 37 (FERC–717)

ATC-related standards:
NERC/NAESB Team to develop .............................................................. 1 1 1,920 1,920
Review and comment by utility ................................................................. 116 1 20 2,320
Implementation by each utility .................................................................. 116 1 40 4,640
Mandatory data exchanges ............................................................................. 116 1 80 9,280
Explanation of change of ATC values ............................................................. 116 1 100 11,600
Reevaluate CBM and post quarterly ............................................................... 116 1 20 2,320
Post OASIS metrics; requests accepted/denied ............................................. 116 1 90 10,440
Post planning redispatch offers and reliability redispatch data ....................... 116 1 20 2,320
Post curtailment data ....................................................................................... 116 1 10 11,160
Post Planning and System Impact Studies ..................................................... 116 1 5 580
Posting of metrics for System Impact Studies ................................................ 116 1 100 11,600
Post all rules to OASIS .................................................................................... 116 1 5 580
Sub Total (Part 37) ................................................................................... ........................ ........................ ........................ 68,760

Total (Part 35 + Part 37) ................................................................... ........................ ........................ ........................ 140,476

Recordkeeping ................................................................................................. 116 1 40 4,640

1755. Information Collection Costs: Title: FERC–516, Electric Rate achieve this goal by increasing the
No comments were received regarding Schedules and Tariff Filings; FERC–717 clarity and transparency of the rules
the Commission’s estimate of costs to Standards for Business Practices and applicable to the planning and use of
comply with these requirements. The Communication Protocols for Public the transmission system and by
Commission has projected costs of Utilities. addressing ambiguities and the lack of
compliance as follows: Action: Proposed Collections. sufficient detail in several important
Total Annual Hours for Collection: OMB Control Nos. 1902–0096 and areas of the pro forma OATT. The lack
Reporting + recordkeeping hours = 1902–0173. of specificity in the pro forma OATT
152,396 + 4,640 = 157,036 hours. Respondents: Business or other for
creates opportunities for undue
Cost to Comply: profit.
Frequency of responses: On occasion. discrimination as well as making the
Reporting = $17,373,144 undue discrimination that does occur
152,396 hours @ $114 an hour Necessity of the Information: The
Federal Energy Regulatory Commission more difficult to detect. To accomplish
(average cost of attorney ($200 per
adopts these amendments to its this we are proposing five objectives: (1)
hour), consultant ($150), technical
regulations adopted in Order Nos. 888 To improve transparency and
($80), and administrative support
and 889, and to the pro forma open consistency in several critical areas, by
($25))
Recordkeeping = $7,478,888 access transmission tariff, to ensure that providing for greater consistency in the
Labor (file/record clerk @ $17 an transmission services are provided on a calculation of ATC, (2) to reform the
hour) 4,640 hours @ $17/hour = basis that is just, reasonable and not transmission planning requirements of
$78,880 unduly discriminatory or preferential. the pro forma OATT to eliminate
Storage 8,000 sq. ft. × $925 (off site The purpose of this rulemaking is to potential undue discrimination and
storage) = $7,400,000 strengthen the pro forma OATT to support the construction of adequate
Total costs = $24,852,024 ensure that it achieves its original transmission facilities to meet the needs
Labor $ ($17,373,144 + $78,880) + purpose—remedying undue of all LSEs, (3) to remedy certain
Recordkeeping Storage Costs discrimination—not to create new portions of the pro forma OATT that
sroberts on PROD1PC70 with RULES

($7,400,000) market structures. We propose to may have permitted utilities to

1001 These burden estimates applied only to the

Final Rule and do not reflect upon all of FERC–516


or FERC–717.

VerDate Aug<31>2005 19:40 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00226 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12491

discriminate against new merchant regulations, which provides a impact on a substantial number of small
generation, including intermittent categorical exemption for approval of entities.
generation, (4) to provide for greater actions under sections 205 and 206 of
IX. Document Availability
transparency in the provision of the FPA relating to the filing of
transmission service to allow schedules containing all rates and 1760. In addition to publishing the
transmission customers better access to charges for the transmission or sale full text of this document in the Federal
information to make their resource subject to the Commission’s Register, the Commission provides all
procurement and investment decisions, jurisdiction, plus the classification, interested persons an opportunity to
as well as to increase the Commission’s practices, contracts and regulations that view and/or print the contents of this
ability to detect any remaining incidents affect rates, charges, classifications and document via the Internet through the
of undue discrimination; and (5) to services.1003 Commission’s Home Page (http://
reform and provide greater clarity in www.ferc.gov) and in the Commission’s
areas that have generated recurring VIII. Regulatory Flexibility Act Public Reference Room during normal
disputes over the past 10 years, such as Analysis business hours (8:30 a.m. to 5 p.m.
rollover rights, ‘‘redirects,’’ and 1759. The Regulatory Flexibility Act Eastern time) at 888 First Street, NE.,
generation redispatch. The reforms of 1980 (RFA) 1004 generally requires a Room 2A, Washington DC 20426.
proposed in this Final Rule are intended description and analysis of final rules 1761. From the Commission’s Home
to address deficiencies in the pro forma that will have significant economic Page on the Internet, this information is
OATT that have become apparent since impact on a substantial number of small available in the Commission’s document
the implementation of Order No. 888 in entities. This rule applies to public management system, eLibrary. The full
1996 and to facilitate improved utilities that own, control or operate text of this document is available on
planning and operation of transmission interstate transmission facilities other eLibrary in PDF and Microsoft Word
facilities. than those that have received waiver of format for viewing, printing, and/or
1756. Interested persons may obtain the obligation to comply with Order downloading. To access this document
information on the reporting Nos. 888 and 889. The total number of in eLibrary, type ‘‘RM05–25’’ or
requirements by contacting the public utilities that, absent waiver, ‘‘RM05–17’’ in the docket number field.
following: Federal Energy Regulatory would have to modify their current 1762. User assistance is available for
Commission, 888 First Street, NE., OATTs by filing the revised pro forma eLibrary and the Commission’s website
Washington, DC 20426, Attention: OATT is 116.1005 Of these only six during normal business hours. For
Michael Miller, Office of the Executive public utilities, or less than two percent, assistance, please contact the
Director, Phone: (202) 502–8415, fax: have output of four million MWh or less Commission’s Online Support at 1–866–
(202) 273–0873, e-mail: per year.1006 The Commission does not 208–3676 (toll free) or 202–502–6652 (e-
michael.miller@ferc.gov. consider this a substantial number and, mail at FERCOnlineSupport@FERC.gov),
1757. For submitting comments in any event, each of these entities or the Public Reference Room at 202–
concerning the collections of retains its rights to waiver of these 502–8371, TTY 202–502–8659 (e-mail at
information and the associated burden requirements.1007 The criteria for waiver public.referenceroom@ferc.gov).
estimate(s), please send your comments that would be applied under this X. Effective Date and Congressional
to the contact listed above and to the rulemaking for small entities is Notification
Office of Information and Regulatory unchanged from that used to evaluate
Affairs, Office of Management and requests for waiver under Order Nos. 1763. These regulations are effective
Budget, 725 17th Street, NW., 888 and 889. Accordingly, the May 14, 2007. The Commission has
Washington, DC 20503 Attention: Desk Commission certifies that the Final Rule determined, with the concurrence of the
Officer for the Federal Energy will not have a significant economic Administrator of the Office of
Regulatory Commission, phone (202) Information and Regulatory Affairs of
395–3122, fax: (202) 395–7285. Due to 1003 18 CFR 380.4(a)(15).
OMB, that this rule is not a ‘‘major rule’’
security concerns, comments should be 1004 5 U.S.C. 601–612. as defined in section 351 of the Small
sent electronically to the following e- 1005 The Commission has identified 116 Business Regulatory Enforcement
mail address: transmission providers with tariffs on file. We note Fairness Act of 1996. The Commission
oira_submission@omb.eop.gov. Please that this figure is lower than our initial estimate in will submit the Final Rule to both
the NOPR, based on FERC Form No. 1 and FERC
reference the docket number of this Form No. 1–F data.
houses of Congress and to the General
rulemaking in your submission. 1006 Id. Accounting Office.
1007 The Regulatory Flexibility Act defines a
VII. Environmental Analysis List of Subjects
‘‘small entity’’ as ‘‘one which is independently
1758. The Commission is required to owned and operated and which is not dominant in 18 CFR Part 35
prepare an Environmental Assessment its field of operation.’’ See 5 U.S.C. 601(3) and
601(6); 15 U.S.C. 632(a)(1). In Mid-Tex Elec. Coop. Electric power rates, Electric utilities,
or an Environmental Impact Statement v. FERC, 773 F.2d 327, 340–43 (D.C. Cir. 1985), the Reporting and recordkeeping
for any action that may have a court accepted the Commission’s conclusion that,
requirements.
significant adverse effect on the human since virtually all of the public utilities that it
environment.1002 The Commission regulates do not fall within the meaning of the term 18 CFR Part 37
‘‘small entities’’ as defined in the Regulatory
concludes that neither an Flexibility Act, the Commission did not need to Conflict of interests, Electric power
Environmental Assessment nor an prepare a regulatory flexibility analysis in
plants, Electric utilities, Reporting and
Environmental Impact Statement is connection with its proposed rule governing the
allocation of costs for construction work in progress recordkeeping requirements.
required for this Final Rule under
(CWIP). The CWIP rules applied to all public By the Commission.
section 380.4(a)(15) of the Commission’s
sroberts on PROD1PC70 with RULES

utilities. The revised pro forma OATT will apply


only to those public utilities that own, control or Magalie R. Salas,
1002 Regulations Implementing the National operate interstate transmission facilities. These Secretary.
Environmental Policy Act, Order No. 486, 52 FR entities are a subset of the group of public utilities
47897 (Dec. 17, 1987), FERC Stats. & Regs. ¶ 30,783 found not to require preparation of a regulatory ■In consideration of the foregoing, the
(1987). flexibility analysis for the CWIP rule. Commission amends parts 35 and 37,

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00227 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12492 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Chapter I, Title 18 of the Code of 205 of the FPA in accordance with the effective on December 31, 1996. For
Federal Regulations, as follows: procedures set forth in Order No. 890, sales of electric energy pursuant to a
FERC Stats. & Regs ¶ 31,241. bilateral non-economy energy
PART 35—FILING OF RATE (iii) If a public utility owns, controls, coordination agreement executed on or
SCHEDULES AND TARIFFS or operates transmission facilities used before July 9, 1996, this requirement
for the transmission of electric energy in will not apply unless separately ordered
■ 1. The authority citation for part 35
interstate commerce as of May 14, 2007, by the Commission.
continues to read as follows:
such facilities are jointly owned with a (ii) [Reserved.]
Authority: 16 U.S.C. 791a–825r, 2601– non-public utility, and the joint (3) Every public utility that owns,
2645; 31 U.S.C. 9701; 42 U.S.C. 71–7352. ownership contract prohibits controls, or operates facilities used for
■ 2. Amend § 35.28 as follows: transmission service over the facilities the transmission of electric energy in
■ a. Paragraph (c) is revised. to third parties, the public utility with interstate commerce, and that is a
■ b. Paragraphs (d)(i) and (d)(ii) are respect to access over the public utility’s member of a power pool, public utility
redesignated as paragraphs (d)(1) and share of the jointly owned facilities holding company, or other multi-lateral
(d)(2). must file no later than May 14, 2007 the trading arrangement or agreement that
■ c. Newly redesignated paragraph revisions to the pro forma tariff contains transmission rates, terms or
(d)(1) is revised. contained in Order No. 890, FERC Stats. conditions, must have on file a joint
■ d. Paragraph (e)(1) introductory text is & Regs. ¶ 31,241, pursuant to section pool-wide or system-wide open access
revised. 206 of the FPA and accompanying rates transmission tariff, which tariff must be
■ e. Paragraph (e)(1)(ii) is revised. pursuant to section 205 of the FPA. the pro forma tariff contained in Order
(iv) Any public utility whose No. 888, FERC Stats. & Regs. ¶ 31,036,
§ 35.28 Non-discriminatory open access transmission facilities are under the as revised by the pro forma tariff
transmission tariff.
independent control of a Commission- contained in Order No. 890, FERC Stats.
* * * * * approved ISO or RTO may satisfy its & Regs. ¶ 31,241, or such other open
(c) Non-discriminatory open access obligation under paragraph (c)(1) of this access tariff as may be approved by the
transmission tariffs. (1) Every public section, with respect to such facilities, Commission consistent with Order No.
utility that owns, controls, or operates through the open access transmission 888, FERC Stats. & Regs. ¶ 31,036 and
facilities used for the transmission of tariff filed by the ISO or RTO. Order No. 890, FERC Stats. & Regs.
electric energy in interstate commerce (v) If a public utility obtains a waiver ¶ 31,241.
must have on file with the Commission of the tariff requirement pursuant to (i) For any power pool, public utility
a tariff of general applicability for paragraph (d) of this section, it does not holding company or other multi-lateral
transmission services, including need to file the pro forma tariff required arrangement or agreement that contains
ancillary services, over such facilities. by this section. transmission rates, terms or conditions
Such tariff must be the open access pro (vi) Any public utility that seeks a and that is executed after May 14, 2007,
forma tariff contained in Order No. 888, deviation from the pro forma tariff this requirement is effective on the date
FERC Stats. & Regs. ¶ 31,036 (Final Rule contained in Order No. 888, FERC Stats. that transactions begin under the
on Open Access and Stranded Costs), as & Regs. ¶ 31,036, as revised in Order No. arrangement or agreement.
revised by the open access pro forma 890, FERC Stats. & Regs. ¶ 31,241, must (ii) For any power pool, public utility
tariff contained in Order No. 890, FERC demonstrate that the deviation is holding company or other multi-lateral
Stats. & Regs. ¶ 31,241 (Final Rule on consistent with the principles of Order arrangement or agreement that contains
Open Access Reforms), or such other No. 888, FERC Stats. & Regs ¶ 31,036 transmission rates, terms or conditions
open access tariff as may be approved and Order No. 890, FERC Stats. & Regs. and that is executed on or before May
by the Commission consistent with ¶ 31,241. 14, 2007, a public utility member of
Order No. 888, FERC Stats. & Regs (vii) Each public utility’s open access such power pool, public utility holding
¶ 31,306 and Order No. 890, FERC Stats. transmission tariff must include the company or other multi-lateral
& Regs. ¶ 31,241. standards incorporated by reference in arrangement or agreement that owns,
(i) Subject to the exceptions in part 38 of this chapter. controls, or operates facilities used for
paragraphs (c)(1)(ii), (c)(1)(iii), (c)(1)(iv) (2) Subject to the exceptions in the transmission of electric energy in
and (c)(1)(v) of this section, the pro paragraphs (c)(2)(i) and (c)(3)(iii) of this interstate commerce must file the
forma tariff contained in Order No. 888, section, every public utility that owns, revisions to its joint pool-wide or
FERC Stats. & Regs. ¶ 31,036, as revised controls, or operates facilities used for system-wide contained in Order No.
by the open access pro forma tariff the transmission of electric energy in 890, FERC Stats. & Regs. ¶ 31,241,
contained in Order No. 890, FERC Stats. interstate commerce, and that uses those pursuant to section 206 of the FPA and
& Regs. ¶ 31,241, and accompanying facilities to engage in wholesale sales accompanying rates pursuant to section
rates, must be filed no later than 60 days and/or purchases of electric energy, or 205 of the FPA in accordance with the
prior to the date on which a public unbundled retail sales of electric energy, procedures set forth in Order No. 890,
utility would engage in a sale of electric must take transmission service for such FERC Stats. & Regs ¶ 31,241.
energy at wholesale in interstate sales and/or purchases under the open (iii) A public utility member of a
commerce or in the transmission of access transmission tariff filed pursuant power pool, public utility holding
electric energy in interstate commerce. to this section. company or other multi-lateral
(ii) If a public utility owns, controls, (i) For sales of electric energy arrangement or agreement that contains
or operates facilities used for the pursuant to a requirements service transmission rates, terms or conditions
transmission of electric energy in agreement executed on or before July 9, and that is executed on or before July 9,
interstate commerce as of May 14, 2007, 1996, this requirement will not apply 1996 must take transmission service
sroberts on PROD1PC70 with RULES

it must file the revisions to the pro unless separately ordered by the under a joint pool-wide or system-wide
forma tariff contained in Order No. 890, Commission. For sales of electric energy open access transmission tariff filed
FERC Stats. & Regs. ¶ 31,241, pursuant pursuant to a bilateral economy energy pursuant to this section for wholesale
to section 206 of the FPA and coordination agreement executed on or trades among the pool or system
accompanying rates pursuant to section before July 9, 1996, this requirement is members.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00228 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12493

(4) Consistent with paragraph (c)(1) of Authority: 16 U.S.C. 791–825r, 2601–2645; necessary to provide reasonable
this section, every Commission- 31 U.S.C. 9701; 42 U.S.C. 7101–7352. assurance that the interconnected
approved ISO or RTO must have on file ■ 4. Amend § 37.6 as follows: transmission network will be secure, or
with the Commission a tariff of general ■ a. Paragraph (a)(1) is revised. such definition as contained in
applicability for transmission services, ■ b. Paragraph (b) introductory text is Commission-approved Reliability
including ancillary services, over such revised. Standards.
facilities. Such tariff must be the pro ■ c. Paragraphs (b)(1)(v) through (2) * * *
forma tariff contained in Order No. 888, (b)(1)(viii) are added. (i) Information used to calculate any
FERC Stats. & Regs. ¶ 31,036, as revised ■ d. Paragraphs (b)(2)(i) through posting of ATC and TTC must be dated
by the pro forma tariff contained in (b)(2)(iii) are revised. and time-stamped and all calculations
Order No. 890, FERC Stats. & Regs. ■ e. Paragraph (b)(3) is revised. shall be performed according to
¶ 31,241, or such other open access tariff ■ f. Paragraphs (c)(2) and (c)(5) are consistently applied methodologies
as may be approved by the Commission revised. referenced in the Transmission
consistent with Order No. 888, FERC ■ g. Paragraphs (e)(1) and (e)(2)(ii) are Provider’s transmission tariff and shall
Stats. & Reg. ¶ 31,036 and Order No. revised. be based on Commission-approved
890, FERC Stats. & Regs. ¶ 31,241. ■ h. Paragraph (e)(3)(ii) is revised. Reliability Standards as well as current
(i) Subject to paragraph (c)(4)(ii) of ■ i. Paragraphs (h), (i) and (j) are added. industry practices, standards and
this section, a Commission-approved criteria.
ISO or RTO must file the revisions to § 37.6 Information to be posted on the
OASIS. (ii) On request, the Responsible Party
the pro forma tariff contained in Order must make all data used to calculate
No. 890, FERC Stats. & Regs. ¶ 31,241, (a) * * *
(1) Make requests for transmission ATC, TTC, CBM, and TRM for any
pursuant to section 206 of the FPA and constrained posted paths publicly
accompanying rates pursuant to section services offered by Transmission
Providers, Resellers and other providers available (including the limiting
205 of the FPA in accordance with the element(s) and the cause of the limit
procedures set forth in Order No. 890, of ancillary services, request the
designation of a network resource, and (e.g., thermal, voltage, stability), as well
FERC Stats. & Regs ¶ 31,241. as load forecast assumptions) in
(ii) If a Commission-approved ISO or request the termination of the
designation of a network resource; electronic form within one week of the
RTO can demonstrate that its existing
posting. The information is required to
open access tariff is consistent with or * * * * *
(b) Posting transfer capability. The be provided only in the electronic
superior to the revisions to the pro
available transfer capability on the format in which it was created, along
forma tariff contained in Order No. 888,
Transmission Provider’s system (ATC) with any necessary decoding
FERC Stats. & Regs. ¶ 31,036, as revised
and the total transfer capability (TTC) of instructions, at a cost limited to the cost
by the pro forma tariff in Order No. 890,
FERC Stats. & Regs. ¶ 31,241, or any that system shall be calculated and of reproducing the material. This
portions thereof, the Commission- posted for each Posted Path as set out information is to be retained for six
approved ISO or RTO may instead set in this section. months after the applicable posting
forth such demonstration in its filing (1) * * * period.
pursuant to section 206 in accordance (v) Available transfer capability or (iii) System planning studies,
with the procedures set forth in Order ATC means the transfer capability facilities studies, and specific network
No. 890, FERC Stats. & Regs ¶ 31,241. remaining in the physical transmission impact studies performed for customers
(d) Waivers. * * * network for further commercial activity or the Transmission Provider’s own
(1) No later than May 14, 2007, or over and above already committed uses, network resources are to be made
* * * * * or such definition as contained in publicly available in electronic form on
(e) Non-public utility procedures for Commission-approved Reliability request and a list of such studies shall
tariff reciprocity compliance. (1) A non- Standards. be posted on the OASIS. A study is
public utility may submit a transmission (vi) Total transfer capability or TTC required to be provided only in the
tariff and a request for declaratory order means the amount of electric power that electronic format in which it was
that its voluntary transmission tariff can be moved or transferred reliably created, along with any necessary
meets the requirements of Order No. from one area to another area of the decoding instructions, at a cost limited
888, FERC Stats. & Regs. ¶ 31,036 and interconnected transmission systems by to the cost of reproducing the material.
Order No. 890, FERC Stats. & Regs. way of all transmission lines (or paths) These studies are to be retained for five
¶ 31,241. between those areas under specified years.
system conditions, or such definition as (3) Posting. The ATC, TTC, CBM, and
* * * * *
(ii) If the submittal is found to be an contained in Commission-approved TRM for all Posted Paths must be posted
acceptable transmission tariff, an Reliability Standards. in megawatts by specific direction and
applicant in a Federal Power Act (FPA) (vii) Capacity Benefit Margin or CBM in the manner prescribed in this
section 211 or 211A proceeding against means the amount of TTC preserved by subsection.
the non-public utility shall have the the Transmission Provider for load- (i) Constrained posted paths.—(A) For
burden of proof to show why service serving entities, whose loads are located firm ATC and TTC.
under the open access tariff is not on that Transmission Provider’s system, (1) The posting shall show ATC, TTC,
sufficient and why a section 211 or to enable access by the load-serving CBM, and TRM for a 30-day period. For
211A order should be granted. entities to generation from this period postings shall be: by the
interconnected systems to meet hour, for the current hour and the 168
* * * * *
generation reliability requirements, or hours next following; and thereafter, by
sroberts on PROD1PC70 with RULES

PART 37—OPEN ACCESS SAME-TIME such definition as contained in the day. If the Transmission Provider
INFORMATION SYSTEMS Commission-approved Reliability charges separately for on-peak and off-
Standards. peak periods in its tariff, ATC, TTC,
■ 3. The authority citation for part 37 (viii) Transmission Reliability Margin CBM, and TRM will be posted daily for
continues to read as follows: or TRM means the amount of TTC each period.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00229 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12494 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

(2) Postings shall also be made by the the current day and the next six days comparably. Requests for transmission
month, showing for the current month following for each period. These service, ancillary service, and to
and the 12 months next following. postings are to be updated whenever the designate and terminate a network
(3) If planning and specific requested ATC changes by more than 20 percent resource, as well as the responses to
transmission studies have been done, of the Path’s TTC. such requests, must be conducted in
seasonal capability shall be posted for (B) If planning and specific requested accordance with the Transmission
the year following the current year and transmission studies have been done, Provider’s tariff, the Federal Power Act,
for each year following to the end of the seasonal capability shall be posted for and Commission regulations.
planning horizon but not to exceed 10 the year following the current year and (ii) The requirement in paragraph
years. for each year following until the end of (e)(1)(i) of this section, to post requests
(B) For non-firm ATC and TTC. The the planning horizon but not to exceed for transmission and ancillary service
posting shall show ATC, TTC, CBM and 10 years. offered by Transmission Providers
TRM for a 30-day period by the hour (iii) Calculation of CBM. under the pro forma tariff, including
and days prescribed under paragraph (A) The Transmission Provider must requests for discounts, prior to the
(b)(3)(i)(A)(1) of this section and, if so reevaluate its CBM needs at least every Transmission Provider responding to
requested, by the month and year as year. the request, does not apply to requests
prescribed under paragraph (b)(3)(i)(A) (B) The Transmission Provider must for next-hour service made during Phase
(2) and (3) of this section. The posting post its practices for reevaluating its I.
of non-firm ATC and TTC shall show CBM needs. (iii) In the event that a discount is
CBM as zero. (iv) Daily load. The Transmission being requested for ancillary services
(C) Updating posted information for Provider must post on a daily basis, its that are not in support of basic
constrained paths. actual daily peak load for the prior day. transmission service provided by the
(1) The capability posted under (c) * * * Transmission Provider, such request
paragraphs (b)(3)(i)(A) and (B) of this (2) Transmission Providers must need not be posted on the OASIS.
section must be updated when provide a downloadable file of their (iv) In processing a request for
transactions are reserved or service ends complete tariffs in the same electronic transmission or ancillary service, the
or whenever the estimate for the path format as the tariff that is filed with the Responsible Party shall post the same
changes by more than 10 percent. Commission. Transmission Providers
(2) All updating of hourly information information as required in paragraphs
also must provide a link to all of the (c)(4) and (d)(3) of this section, and the
shall be made on the hour. rules, standards and practices that relate
(3) When the monthly and yearly following information: the date and time
to transmission services posted on the when the request is made, its place in
capability posted under paragraphs Transmission Providers’ public Web
(b)(3)(i)(A) and (B) of this section are any queue, the status of that request,
sites. and the result (accepted, denied,
updated because of a change in TTC by
more than 10 percent, the Transmission * * * * * withdrawn). In processing a request to
Provider shall post a brief, but specific, (5) Customers choosing to use the designate or terminate the designation
narrative explanation of the reason for OASIS to offer for resale transmission of a network resource, the Responsible
the update. This narrative should capacity they have purchased must post Party shall post the date and time when
include, the specific events which gave relevant information to the same OASIS the request is made.
rise to the update (e.g., scheduling of as used by the Transmission Provider (v) For any request to designate or
planned outages and occurrence of from whom the Reseller purchased the terminate a network resource, the
forced transmission outages, de-ratings transmission capacity. This information Transmission Provider (at the time
of transmission facilities, scheduling of must be posted on the same display when the request is received), must post
planned generation outages and page, using the same tables, as similar on the OASIS (and make available for
occurrence of forced generation outages, capability being sold by the download) information describing the
changes in load forecast, changes in new Transmission Provider, and the request (including: name of requestor,
facilities’ in-service dates, or other information must be contained in the identification of the resource, effective
events or assumption changes) and new same downloadable files as the time for the designation or termination,
values for ATC on the path (as opposed Transmission Provider’s own available identification of whether the transaction
to all points on the network). capability. involves the Transmission Provider’s
(4) When the monthly and yearly * * * * * wholesale merchant function or any
capability posted under paragraphs (e) Posting specific transmission and affiliate; and any other relevant terms
(b)(3)(i)(A) and (B) of this section ancillary service requests and responses. and conditions) and shall keep such
remain unchanged at a value of zero for (1) General rules. information posted on the OASIS for at
a period of six months, the (i) All requests for transmission and least 30 days. A record of the
Transmission Provider shall post a brief, ancillary service offered by transaction must be retained and kept
but specific, narrative explanation of the Transmission Providers under the pro available as part of the audit log
reason for the unavailability of ATC. forma tariff, including requests for required in § 37.7.
(ii) Unconstrained posted paths. discounts, and all requests to designate (vi) The Transmission Provider shall
(A) Postings of firm and nonfirm ATC, or terminate a network resource, must post a list of its current designated
TTC, CBM, and TRM shall be posted be made on the OASIS and posted prior network resources and all network
separately by the day, showing for the to the Transmission Provider customers’ current designated network
current day and the next six days responding to the request, except as resources on OASIS. The list of network
following and thereafter, by the month discussed in paragraphs (e)(1)(ii) and resources should include the name of
sroberts on PROD1PC70 with RULES

for the 12 months next following. If the (iii) of this section. The Transmission the resource, its geographic and
Transmission Provider charges Provider must post all requests for electrical location, its total installed
separately for on-peak and off-peak transmission service, for ancillary capacity, and the amount of capacity to
periods in its tariff, ATC, TTC, CBM, service, and for the designation or be designated as a network resource.
and TRM will be posted separately for termination of a network resource (2) * * *

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00230 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12495

(ii) Information to support the reason received the request for transmission Responsible Party received the executed
for the denial, including the operating service to when the Responsible Party system impact study agreement to date
status of relevant facilities, must be changed the transmission service when request was withdrawn from the
maintained for five years and provided, request status to indicate that the Responsible Party’s system impact study
upon request, to the potential Responsible Party could offer queue.
Transmission Customer and the transmission service or needed to (iv) Process time from completed
Commission’s Staff. perform a system impact study, system impact study to offer of facilities
* * * * * (D) Mean time (in days), for all system study.
(3) * * * impact study agreements delivered by (A) Number of new facilities study
(ii) Information to support any such the Responsible Party during the agreements delivered during the
curtailment or interruption, including reporting quarter, from the date when reporting quarter to entities that request
the operating status of the facilities the Responsible Party received the transmission service,
involved in the constraint or request for transmission service to the (B) Number of new facilities study
interruption, must be maintained and date when the Responsible Party agreements delivered during the
made available upon request, to the delivered a system impact study reporting quarter to entities that request
curtailed or interrupted customer, the agreement, and transmission service more than thirty
Commission’s Staff, and any other (E) Number of new system impact (30) days after the Responsible Party
person who requests it, for five years. study agreements executed during the completed the system impact study,
reporting quarter. (C) Mean time (in days), for all
* * * * * (ii) System impact study processing facilities study agreements delivered by
(h) Posting information summarizing the Responsible Party during the
time.
the time to complete transmission (A) Number of system impact studies reporting quarter, from the date when
service request studies. (1) For each completed by the Responsible Party the Responsible Party completed the
calendar quarter, the Responsible Party during the reporting quarter, system impact study to the date when
must post the set of measures detailed (B) Number of system impact studies the Responsible Party delivered a
in paragraph (h)(1)(i) through paragraph completed by the Responsible Party facilities study agreement, and
(h)(1)(vi) of this section related to the during the reporting quarter more than (D) Number of new facilities study
Responsible Party’s processing of 60 days after the Responsible Party agreements executed during the
transmission service request system received an executed system impact reporting quarter.
impact studies and facilities studies. study agreement, (v) Facilities study processing time.
The Responsible Party must calculate (C) For all system impact studies (A) Number of facilities studies
and post the measures in paragraph completed more than 60 days after completed by the Responsible Party
(h)(1)(i) through paragraph (h)(1)(vi) of receipt of an executed system impact during the reporting quarter,
this section separately for requests for study agreement, average number of (B) Number of facilities studies
short-term firm point-to-point days study was delayed due to completed by the Responsible Party
transmission service, long-term firm transmission customer’s actions (e.g., during the reporting quarter more than
point-to-point transmission service, and delays in providing needed data), 60 days after the Responsible Party
requests to designate a new network (D) Mean time (in days), for all system received an executed facilities study
resource and must be calculated and impact studies completed by the agreement,
posted separately for transmission Responsible Party during the reporting (C) For all facilities studies completed
service requests from Affiliates and quarter, from the date when the more than 60 days after receipt of an
transmission service requests from Responsible Party received the executed executed facilities study agreement,
Transmission Customers who are not system impact study agreement to the average number of days study was
Affiliates. The Responsible Party is date when the Responsible Party delayed due to transmission customer’s
required to include in the calculations provided the system impact study to the actions (e.g., delays in providing needed
of the measures in paragraph (h)(1)(i) entity who executed the system impact data),
through paragraph (h)(1)(vi) of this study agreement, and (D) Mean time (in days), for all
section all studies the Responsible Party (E) Mean cost of system impact facilities studies completed by the
conducts of transmission service studies completed by the Responsible Responsible Party during the reporting
requests on another Transmission Party during the reporting quarter. quarter, from the date when the
Provider’s OASIS. (iii) Transmission service requests Responsible Party received the executed
(i) Process time from initial service withdrawn from the system impact facilities study agreement to the date
request to offer of system impact study study queue. when the Responsible Party provided
agreement. (A) Number of transmission service the facilities study to the entity who
(A) Number of new system impact requests withdrawn from the executed the facilities study agreement,
study agreements delivered during the Responsible Party’s system impact study (E) Mean cost of facilities studies
reporting quarter to entities that request queue during the reporting quarter, completed by the Responsible Party
transmission service, (B) Number of transmission service during the reporting quarter, and
(B) Number of new system impact requests withdrawn from the (F) Mean cost of upgrades
study agreements delivered during the Responsible Party’s system impact study recommended in facilities studies
reporting quarter to entities that request queue during the reporting quarter more completed during the reporting quarter.
transmission service more than thirty than 60 days after the Responsible Party (vi) Service requests withdrawn from
(30) days after the Responsible Party received the executed system impact facilities study queue.
received the request for transmission study agreement, and (A) Number of transmission service
sroberts on PROD1PC70 with RULES

service, (C) Mean time (in days), for all requests withdrawn from the
(C) Mean time (in days), for all transmission service requests Responsible Party’s facilities study
requests acted on by the Responsible withdrawn from the Responsible Party’s queue during the reporting quarter,
Party during the reporting quarter, from system impact study queue during the (B) Number of transmission service
the date when the Responsible Party reporting quarter, from the date the requests withdrawn from the

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00231 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12496 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Responsible Party’s facilities study posted separately for transmission (j) Posting redispatch data.
queue during the reporting quarter more service requests from Affiliates and (1) The Transmission Provider must
than 60 days after the Responsible Party transmission service requests from allow the posting on OASIS of any third
received the executed facilities study Transmission Customers who are not party offer to relieve a specified
agreement, and Affiliates. congested transmission facility.
(C) Mean time (in days), for all (i) Mean, across all system impact (2) The Transmission Provider must
transmission service requests studies the Responsible Party completes post on OASIS (i) its monthly average
withdrawn from the Responsible Party’s during the reporting quarter, of the cost of planning and reliability
facilities study queue during the employee-hours expended per system redispatch, for which it invoices
reporting quarter, from the date the impact study the Responsible Party customers, at each internal transmission
Responsible Party received the executed completes during reporting period; facility or interface over which it
facilities study agreement to date when (ii) Mean, across all facilities studies provides redispatch service and (ii) a
request was withdrawn from the the Responsible Party completes during high and low redispatch cost for the
Responsible Party’s facilities study the reporting quarter, of the employee-
queue. month for each of these same
hours expended per facilities study the transmission facilities. The transmission
(2) The Responsible Party is required Responsible Party completes during
to post the measures in paragraph provider must post this data on OASIS
reporting period; as soon as practical after the end of each
(h)(1)(i) through paragraph (h)(1)(vi) of (iii) The number of employees the
this section for each calendar quarter month, but no later than when it sends
Responsible Party has assigned to
within 15 days of the end of the invoices to transmission customers for
process system impact studies;
calendar quarter. The Responsible Party redispatch-related services.
(iv) The number of employees the
will keep the quarterly measures posted Responsible Party has assigned to ■ 5. In § 37.7, paragraph (b) is revised to
on OASIS for three calendar years. process facilities studies.
(3) The Responsible Party will be read as follows:
(4) The Responsible Party is required
required to post on OASIS the measures to post the measures in paragraph § 37.7 Auditing Transmission Service
in paragraph (h)(3)(i) through paragraph (h)(3)(i) through paragraph (h)(3)(iv) of Information.
(h)(3)(iv) of this section in the event the this section for each calendar quarter * * * * *
Responsible Party, for two consecutive within 15 days of the end of the (b) Audit data must remain available
calendar quarters, completes more than calendar quarter. The Responsible Party for download on the OASIS for 90 days,
twenty (20) percent of the studies will keep the quarterly measures posted except ATC/TTC postings that must
associated with requests for on OASIS for five calendar years. remain available for download on the
transmission service from entities that (i) Posting data related to grants and OASIS for 20 days. The audit data are
are not Affiliates of the Responsible denials of service. The Responsible to be retained and made available upon
Party more than sixty (60) days after the Party is required to post data each request for download for five years from
Responsible Party delivers the month listing, by path or flowgate, the the date when they are first posted in
appropriate study agreement. The number of transmission service requests the same electronic form as used when
Responsible Party will have to post the that have been accepted and the number they originally were posted on the
measures in paragraph (h)(3)(i) through of transmission service requests that OASIS.
paragraph (h)(3)(iv) of this section until have been denied during the prior
it processes at least ninety (90) percent Note: The following appendices will not be
month. This posting must distinguish
of all studies within 60 days after it has published in the Code of Federal
between the length of the service Regulations.
received the appropriate executed study request (e.g., short-term or long-term
agreement. For the purposes of requests) and between the type of Appendix A: Summary of Compliance
calculating the percent of studies service requested (e.g., firm point-to- Filing Requirements
completed more than sixty (60) days point, non-firm point-to-point or
after the Responsible Party delivers the network service). The posted data must For a more detailed description of
appropriate study agreement, the show: compliance obligations please refer to
Responsible Party should aggregate all (1) The number of non-Affiliate the Final Rule paragraph number. For
system impact studies and facilities requests for transmission service that further information related to the Final
studies that it completes during the have been rejected, Rule, such as electronic versions of the
reporting quarter. The Responsible Party (2) The total number of non-Affiliate pro forma OATT showing tariff changes
must calculate and post the measures in requests for transmission service that adopted in the Final Rule in redline/
paragraph (h)(3)(i) through paragraph have been made, strikeout format, and further
(h)(3)(iv) of this section separately for (3) The number of Affiliate requests information regarding docketing of
requests for short-term firm point-to- for transmission service that have been compliance filings and specific filing
point transmission service, long-term rejected, and instructions, please visit our Web site at
firm point-to-point transmission service, (4) The total number of Affiliate the following location http://
and requests to designate a new network requests for transmission service that www.ferc.gov/industries/electric/indus-
resource and must be calculated and have been made. act/oatt-reform.asp.

Deadline (days after publication Final rule


Compliance action
in Federal Register) paragraph No.

30 .............................................. Optional Implementation FPA section 205 filings allowing transmission providers to propose P 139
sroberts on PROD1PC70 with RULES

previously approved variations from the pro forma OATT that have been affected by pro
forma OATT Final Rule reforms to remain in effect subject to a demonstration that such
variations continue to be consistent with or superior to the revised Final Rule pro forma
OATT (non RTO/ISO transmission providers). Such optional filings must request a 90 day
effective date to facilitate Commission review under section 205.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00232 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12497

Deadline (days after publication Final rule


Compliance action
in Federal Register) paragraph No.

60 .............................................. Non-ISO/RTO transmission providers submit FPA section 206 filings that contain the non-rate P 135
terms and conditions set forth in Final Rule. These filings need only contain the revised
provisions adopted in the Final Rule. Transmission providers utilizing the optional Imple-
mentation FPA section 205 filing described above, need only submit tariff sheets necessary
to implement the remaining modifications required under the Final Rule, i.e., modifications
related to tariff provisions that did not implicate previously-approved variations.
75 .............................................. Transmission Providers must post a ‘‘strawman’’ proposal for compliance with each of the P 443
nine planning principles adopted in the Final Rule. This may be posted on the Trans-
mission Providers Web site or its OASIS site.
90 .............................................. NERC/NAESB status report and work plan for completion of ATC related business practices P 223
and standards.
NAESB status report and work plan for completion of OASIS functionality or uniform business P 141
practices (other than those related to ATC).
120 ............................................ Transmission Providers must submit redesigned transmission charges that reflect the Capac- P 263
ity Benefit Margin set-aside through a limited issue section 205 rate filing as part of their
initial ATC related compliance filings.
180 ............................................ Submit compliance filings with Attachment C (ATC) of the pro forma OATT ............................. P 140
210 ............................................ ISOs and RTOs, and transmission providers located within an ISO/RTO footprint, submit FPA P 157, P 161
section 206 filings that contain the non-rate terms and conditions set forth in the Final Rule.
These filings need only contain the revised provisions adopted in the Final Rule or a dem-
onstration that previously approved variations continue to be consistent with or superior to
the revised pro forma OATT.
210 ............................................ Submit compliance filings with Attachment K (Planning) of the pro forma OATT or RTOs and P 140, P 442
ISOs file a demonstration that their planning processes are consistent with or superior to
the planning principles in the Final Rule.
N/A ............................................ Transmission Providers must file a revised Attachment C to incorporate any changes to P 325
NERC’s and NAESB’s reliability and business practice standards to achieve consistency in
ATC within 60 days of completion of the NERC and NAESB processes.
N/A ............................................ After the submission of FPA section 206 compliance filings, transmission providers may sub- P 135
mit FPA section 205 filings proposing rates for the services provided for in the tariff, as well
as non-rate terms and conditions that differ from those set forth in the Final Rule if those
provisions are ‘‘consistent with or superior to’’ the pro forma OATT.

Appendix B: Commenting Party


Acronyms

INITIAL COMMENTERS
Abbreviation Initial commenters

Alberta Intervenors ............................................................. Alberta Intervenors (TransCanada Energy Ltd., ENMAX Energy Marketing, Inc.;
EPCOR Merchant and Capital, LP; and TransAlta Corporation).
Alcoa .................................................................................. Alcoa Inc. and Alcoa Power Generating Inc.
Allegheny ............................................................................ Allegheny Power and Allegheny Energy Supply Company, LLC.
Ameren ............................................................................... Ameren Services Company.
American Transmission ...................................................... American Transmission Company LLC.
AMP-Ohio ........................................................................... American Municipal Power-Ohio, Inc.
Anaheim ............................................................................. Cities of Anaheim, Azusa, Banning, Colton, Pasadena, and Riverside, California.
APPA .................................................................................. American Public Power Association.
ARC .................................................................................... Alliance for Retail Choice.
Arkansas Commission ....................................................... Arkansas Public Service Commission.
Arkansas Municipal ............................................................ Arkansas Municipal Power Association.
AWEA ................................................................................. American Wind Energy Association.
Barrick ................................................................................ Barrick Goldstrike Mines Inc.
BART .................................................................................. San Francisco Bay Area Rapid Transit District.
Bonneville ........................................................................... Bonneville Power Administration.
BP Energy .......................................................................... BP Energy Company.
Bureau of Reclamation ...................................................... U.S. Bureau of Reclamation.
CAC/EPUC ......................................................................... Cogeneration Association of California (Coalinga Cogeneration Co., Mid-Set Cogen-
eration Co., Kern River Cogeneration Co., Sycamore Cogeneration Co., Sargent
Canyon Cogeneration Co., Salinas River Cogeneration Co., Midwest Sunset Co-
generation Co. and Watson Cogeneration Co.) and Energy Producers and Users
Coalition (Aera Energy LLC, BP American, Inc., Chevron USA, Inc., ConocoPhilips
Co., ExxonMobil Power and Gas Services, Inc., Shell Oil Products, US, THUMS
sroberts on PROD1PC70 with RULES

Long Beach Co., Occidental Elk Hills, Inc., and Valero Refining Co.—California).
CAISO ................................................................................ California Independent System Operator Corporation.
California Commission ....................................................... Public Utilities Commission of the State of California.
Calpine ............................................................................... Calpine Corporation.
Chandley-Hogan ................................................................ John D. Chandley and William W. Hogan.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00233 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12498 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

INITIAL COMMENTERS—Continued
Abbreviation Initial commenters

ColumbiaGrid ..................................................................... ColumbiaGrid Members (Bonneville Power Administration; Avista Corp.; Public Utility
District No. 1 of Chelan County, Washington; Public Utility District No. 2 of Grant
County, Washington; Puget Sound Energy, Inc.; Seattle City Light; and Tacoma
Power.
Community Power Alliance ................................................ Community Power Alliance Members (Entergy, Progress Energy, Salt River Project
Agricultural Improvement and Power District, and Southern Co.).
Constellation ....................................................................... Constellation Energy Group, Inc.
CREPC ............................................................................... Committee on Regional Electric Power Corp.
Dominion ............................................................................ Dominion Resources Services, Inc. (Armstrong Energy Limited Partnership, LLLP;
Dominion Energy Marketing, Inc.; Elwood Energy, LLC; Fairless Energy, LLC;
Pleasants Energy, LLC and Virginia Electric and Power Co. d/b/a Dominion Vir-
ginia Power).
Dow .................................................................................... Dow Chemical Corp.
Duke ................................................................................... Duke Energy Corp.
E.ON ................................................................................... E.ON U.S. LLC.
East Texas Cooperatives ................................................... East Texas Electric Cooperative, Inc.; Northeast Texas Electric Cooperative, Inc.;
Sam Rayburn Generation and Electric Cooperative, Inc. and Tex-La Electric Coop-
erative of Texas, Inc.
Eastern North Carolina ...................................................... Eastern NC Towns (Towns of Black Creek, NC; Lucama, NC; Stantonsburg, NC).
EEI ...................................................................................... Edison Electric Institute.
ELCON ............................................................................... Electricity Consumers Resource Council, American Iron and Steel Institute, and
American Forest & Paper Institute.
Emerald .............................................................................. Emerald People’s Utility District.
Entegra ............................................................................... Entegra Power Group LLC and LS Power Associates, L.P.
Entergy ............................................................................... Entergy Services, Inc.
EPSA .................................................................................. Electric Power Supply Association.
Exelon ................................................................................ Exelon Corporation.
Fayetteville ......................................................................... Public Works Commission of the City of Fayetteville, North Carolina.
Fertilizer Institute ................................................................ Fertilizer Institute.
FirstEnergy ......................................................................... FirstEnergy Service Company (First Energy Solutions; American Transmission Sys-
tems, Inc.; Jersey Central Power and Light Co.; Metropolitan Edison Co.; and
Pennsylvania Electric Co.).
Flathead ............................................................................. Flathead Electric Cooperative.
Florida Commission ........................................................... Florida Public Service Commission.
Florida Industrial Cogeneration Association ...................... Florida Industrial Cogeneration Association.
FMPA ................................................................................. Florida Municipal Power Agency and Midwest Municipal Transmission Group.
Geothermal Producers ....................................................... CE Generation, LLC; Ormat Technologies, Inc.; Caithness Energy, LLC; and Geo-
thermal Energy Association.
Grant .................................................................................. Grant County PUD, Chelan County PUD and Pend Oreille County PUD.
Great Northern ................................................................... Great Northern Power Development, L.P.
Imperial ............................................................................... Imperial Irrigation District.
Indianapolis Power ............................................................. Indianapolis Power & Light Co.
Indicated New York Transmission Owners ........................ Central Hudson Gas & Electric Corp.; Consolidated Edison Co. of New York, Inc.;
LIPA; New York Power Authority; New York State Electric & Gas Corp.; Orange
and Rockland Utilities, Inc.; and Rochester Gas and Electric Corp.
International Transmission ................................................. International Transmission Co. d/b/a ITCTransmission and Michigan Electric Trans-
mission Co., LLC.
IRH Management ............................................................... IRH Management Committee and the Schedule 20A Service Providers.
ISO New England .............................................................. ISO New England, Inc. and New England Power Pool.
ISO/RTO Council ............................................................... ISO/RTO Council.
Lassen ................................................................................ Lassen Municipal Utility District.
LDWP ................................................................................. City of Los Angeles Department of Water and Power.
LPPC .................................................................................. Large Public Power Council.
Manitoba Hydro .................................................................. Manitoba Hydro.
MDEA ................................................................................. Mississippi Delta Energy Agency, Clarksdale Public Utilities Commission, and Public
Service Commission of Yazoo City.
MidAmerican ...................................................................... MidAmerican Energy Company and PacifiCorp.
MISO .................................................................................. Midwest Independent Transmission System Operator, Inc.
MISO Transmission Owners .............................................. Midwest ISO Transmission Owners.
MISO/PJM States ............................................................... Organization of MISO States and Organization of PJM States, Inc.
Morgan Stanley .................................................................. Morgan Stanley Capital Group Inc.
NAESB ............................................................................... North American Energy Standards Board.
NARUC ............................................................................... National Association of Regulatory Utility Commissioners.
National Grid ...................................................................... National Grid USA.
NCEMC .............................................................................. North Carolina Electric Membership Corporation.
NCPA ................................................................................. Northern California Power Agency.
NERC ................................................................................. North American Electric Reliability Corporation.
sroberts on PROD1PC70 with RULES

Nevada Commission .......................................................... Public Utilities Commission of Nevada.


Nevada Companies ............................................................ Nevada Power Company and Sierra Pacific Power Company.
New Jersey Board .............................................................. New Jersey Board of Public Utilities.
New Mexico Attorney General ........................................... New Mexico Attorney General.
New York Commission ....................................................... New York State Public Service Commission.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00234 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12499

INITIAL COMMENTERS—Continued
Abbreviation Initial commenters

Newfoundland .................................................................... Newfoundland and Labrador Hydro.


Newmont Mining ................................................................ Newmont USA Limited, dba Newmont Mining Corp.
Northeast Utilities ............................................................... Northeast Utilities Service Company (Connecticut Light and Power Co.; Western
Massachusetts Electric Co.; Public Service Co. of New Hampshire; Holyoke Water
Power Co.; and Holyoke Power and Electric Co.).
Northwest IOUs .................................................................. Northwest Investor-Owned Utilities (Avista Corp., Portland General Electric Co., and
Puget Sound Energy, Inc.).
Northwest Parties ............................................................... Northwest Parties (Avista Corp., Bonneville Power Administration, PacifiCorp, PNGC
Power, Portland General Electric Co., Public Power Council, Public Utility Commis-
sion of Oregon and Puget Sound Energy, Inc.).
NorthWestern ..................................................................... NorthWestern Corporation.
NPPD ................................................................................. Nebraska Public Power District.
NRECA ............................................................................... National Rural Electric Cooperative Association.
NRG ................................................................................... NRG Energy, Inc.
NYAPP ............................................................................... New York Association of Public Power.
Occidental .......................................................................... Occidental Chemical Corporation.
Oklahoma Commission ...................................................... Oklahoma Corporation Commission.
Old Dominion ..................................................................... Old Dominion Electric Cooperative.
Oversight Resources .......................................................... Oversight Resources, LLC.
PGP .................................................................................... Public Generating Pool and Chelan County PUD.
Pinnacle .............................................................................. Pinnacle West Capital Corporation; Arizona Public Service Company; and APS En-
ergy Services Company, Inc.
PJM .................................................................................... PJM Interconnection, LLC.
PNM–TNMP ....................................................................... Public Service Company of New Mexico and Texas-New Mexico Power Company.
Powerex ............................................................................. Powerex Corp.
PPL ..................................................................................... PPL Companies.
PPM .................................................................................... PPM Energy, Inc.
Progress Energy ................................................................ Progress Energy, Inc. (Carolina Power & Light Co. d/b/a Progress Energy Carolinas
and Florida Power Corp., d/b/a Progress Energy Florida; and Progress Ventures,
Inc.).
Project for Sustainable FERC Energy Policy .................... Project for Sustainable FERC Energy Policy (American Wind Energy Association,
Delaware Division of the Public Advocate, Environmental Law & Policy Center, Illi-
nois Citizens Utility Board, Natural Resources Defense Council, Northwest Energy
Coalition, Office of the Ohio Consumers’ Counsel, Pace Energy Project, Project for
Sustainable FERC Energy Policy, Renewable Northwest Project, West Wind
Wires, and Wind on the Wires).
PSEG ................................................................................. Public Service Electric and Gas Company; PSEG Power LLC; and PSEC Energy Re-
sources & Trade LLC (PSEG Companies).
Public Power Council ......................................................... Public Power Council.
Reliant ................................................................................ Reliant Energy, Inc.
Sacramento ........................................................................ Sacramento Municipal Utility District.
Salt River ............................................................................ Salt River Project Agricultural Improvement and Power District.
San Diego G&E .................................................................. San Diego Gas & Electric Company.
Santa Clara ........................................................................ City of Santa Clara, California d/b/a Silicon Valley Power.
Santee Cooper ................................................................... South Carolina Public Service Authority.
SCE .................................................................................... Southern California Edison.
Seattle ................................................................................ City of Seattle—City Light Department.
Sempra Global ................................................................... Sempra Global.
South Carolina E&G ........................................................... South Carolina Electric & Gas Company.
South Carolina Regulatory Staff ........................................ South Carolina Office of Regulatory Staff.
Southern ............................................................................. Southern Company Services, Inc.
Southwest Transmission .................................................... Southwest Area Transmission Sub-Regional Planning Group.
Southwestern Coop ............................................................ Southwestern Electric Cooperative, Inc.
SPP .................................................................................... Southwest Power Pool, Inc.
Steel Manufacturers Association ....................................... Steel Manufacturers Association.
Suez Energy NA ................................................................ Suez Energy North America, Inc.
Tacoma .............................................................................. Tacoma Power.
TANC .................................................................................. Transmission Agency of Northern California.
TAPS .................................................................................. Transmission Access Policy Study Group.
TDU Systems ..................................................................... Transmission Dependent Utilities Systems.
TransAlta ............................................................................ TransAlta Energy Marketing (US) Inc.
TranServ ............................................................................. TranServ International, Inc.
Tucson ................................................................................ Tucson Electric Power Company.
TVA .................................................................................... Tennessee Valley Authority.
Utah Municipals .................................................................. Utah Associated Municipal Power Systems.
WAPA ................................................................................. Western Area Power Administration.
WECC ................................................................................ Western Electricity Coordinating Council.
sroberts on PROD1PC70 with RULES

WestConnect ...................................................................... WestConnect Companies.


Western Governors ............................................................ Western Governors’ Association.
Williams .............................................................................. Williams Power Company, Inc.
Wisconsin Electric .............................................................. Wisconsin Electric Power Company.
WSPP ................................................................................. Western Systems Power Pool, Inc.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00235 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12500 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

INITIAL COMMENTERS—Continued
Abbreviation Initial commenters

Xcel .................................................................................... Xcel Energy Services, Inc.

REPLY COMMENTERS
Abbreviation Reply commenters

Alberta Intervenors ............................................................. Alberta Intervenors (TransCanada Energy Ltd., ENMAX Energy Marketing, Inc.;
EPCOR Merchant and Capital, LP; and TransAlta Corporation).
Anaheim ............................................................................. Cities of Anaheim, Azusa, Banning, Colton, Pasadena, and Riverside, California.
APPA .................................................................................. American Public Power Association.
Barrick ................................................................................ Barrick Goldstrike Mines Inc.
Bonneville ........................................................................... Bonneville Power Administration.
CAISO ................................................................................ California Independent System Operator Corporation.
California Commission ....................................................... Public Utilities Commission of the State of California.
Canadian Electricity Association ........................................ Canadian Electricity Association.
Chandley-Hogan ................................................................ John D. Chandley and William W. Hogan.
CMUA ................................................................................. California Municipal Utilities Association.
ColumbiaGrid ..................................................................... ColumbiaGrid Members (Bonneville Power Administration; Avista Corp.; Public Utility
District No. 1 of Chelan County, Washington; Public Utility District No. 2 of Grant
County, Washington; Puget Sound Energy, Inc.; Seattle City Light; and Tacoma
Power.
Community Power Alliance ................................................ Community Power Alliance Members (Entergy, Progress Energy, Salt River Project
Agricultural Improvement and Power District, and Southern Co.).
Detroit Edison ..................................................................... Detroit Edison Co.
Duke ................................................................................... Duke Energy Corp.
Dynegy ............................................................................... Dynegy Power Marketing, Inc.
East Texas Cooperatives ................................................... East Texas Electric Cooperative, Inc.; Northeast Texas Electric Cooperative, Inc.;
Sam Rayburn Generation and Electric Cooperative, Inc. and Tex-La Electric Coop-
erative of Texas, Inc.
EEI ...................................................................................... Edison Electric Institute.
ElectriCities ........................................................................ ElectriCities of North Carolina, Inc.
Entegra ............................................................................... Entegra Power Group LLC and LS Power Associates, L.P.
Entergy ............................................................................... Entergy Services, Inc.
EPSA .................................................................................. Electric Power Supply Association.
Exelon ................................................................................ Exelon Corporation.
Fayetteville ......................................................................... Public Works Commission of the City of Fayetteville, North Carolina.
Fertilizer Institute ................................................................ Fertilizer Institute.
FMPA ................................................................................. Florida Municipal Power Agency and Midwest Municipal Transmission Group.
Great Northern ................................................................... Great Northern Power Development, L.P.
Hoosier ............................................................................... Hoosier Energy Rural Electric Cooperative, Inc.
H.Q. Energy ....................................................................... H.Q. Energy Services (U.S.), Inc.
Indianapolis Power ............................................................. Indianapolis Power & Light Co.
Industrial Customers of Northwest Utilities ........................ Industrial Customers of Northwest Utilities (Air Liquide; Air Products; BPB Gypsum,
Inc.; Blue Heron Paper Company; Boeing; Boise Cascade; CNC Containers,
Northwest; Chemi-Con Materials Corporation; Dyno Nobel, Inc.; ConAgra Foods;
Eka Chemicals, Inc.; Evanite Fiber; Georgia-Pacific; Grays Harbor Paper, L.P.;
Hewlett-Packard; Inland Empire Paper Co.; Intel; J.R. Simplot; Kimberly-Clark Cor-
poration; Longview Fibre; Microsoft Corporation; Norpac Foods; Noveon Kalama,
Inc.; Oregon Steel Mills; PCC Structurals, Inc.; Ponderay Newsprint Co; Shell Oil
Products US; Simpson Paper; Simpson Timber; Solar Grade Silicon LLC; SP
Newsprint Co.; Tesoro Refining and Marketing Co.; Wah Chang; West Linn Paper
Company; Weyerhaeuser).
International Transmission ................................................. International Transmission Co. d/b/a ITCTransmission and Michigan Electric Trans-
mission Co., LLC.
ISO/RTO Council ............................................................... ISO/RTO Council.
Lassen ................................................................................ Lassen Municipal Utility District.
LPPC .................................................................................. Large Public Power Council.
MAPP ................................................................................. Mid-Continent Area Power Pool.
Mark Lively ......................................................................... Mark B. Lively.
MDEA ................................................................................. Mississippi Delta Energy Agency, Clarksdale Public Utilities Commission, Public
Service Commission of Yazoo City, Arkansas Electric Cooperative Corporation,
Municipal Energy Agency of Mississippi, and Lafayette Utilities System*.1008
MidAmerican ...................................................................... MidAmerican Energy Company and PacifiCorp.
MISO .................................................................................. Midwest Independent Transmission System Operator, Inc.
Morgan Stanley .................................................................. Morgan Stanley Capital Group Inc.
NARUC ............................................................................... National Association of Regulatory Utility Commissioners.
sroberts on PROD1PC70 with RULES

NC Transmission Planning Participants ............................ North Carolina Transmission Planning Collaborative Participants.
NCPA ................................................................................. Northern California Power Agency.
Newmont Mining ................................................................ Newmont USA Limited, dba Newmont Mining Corp.
North Carolina Commission ............................................... North Carolina Utilities Commission; Public Staff of the North Carolina Utilities Com-
mission; and the Attorney General of the State of North Carolina.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00236 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12501

REPLY COMMENTERS—Continued
Abbreviation Reply commenters

Northwest IOUs .................................................................. Northwest Investor-Owned Utilities (Avista Corp., Portland General Electric Co., and
Puget Sound Energy, Inc.).
NorthWestern ..................................................................... NorthWestern Corporation.
NRECA ............................................................................... National Rural Electric Cooperative Association.
Occidental .......................................................................... Occidental Chemical Corporation.
OG&E ................................................................................. Oklahoma Gas and Electric Company.
Ohio Power Siting Board ................................................... Ohio Power Siting Board, American Municipal Power-Ohio, Inc. and Buckeye Power,
Inc.
Old Dominion ..................................................................... Old Dominion Electric Cooperative; Southern Maryland Electric Cooperative, Inc.; Al-
legheny Electric Cooperative, Inc.; and North Carolina Electric Membership Cor-
poration.
Omaha Public Power ......................................................... Omaha Public Power District.
Pennsylvania Commission ................................................. Pennsylvania Public Utility Commission.
PJM .................................................................................... PJM Interconnection, LLC.
PNM-TNMP ........................................................................ Public Service Company of New Mexico and Texas-New Mexico Power Company.
Powerex ............................................................................. Powerex Corp.
PPM .................................................................................... PPM Energy, Inc.
Progress Energy ................................................................ Progress Energy, Inc. (Carolina Power & Light Co. d/b/a Progress Energy Carolinas
and Florida Power Corp., d/b/a Progress Energy Florida; and Progress Ventures,
Inc.).
Project for Sustainable FERC Energy Policy .................... Project for Sustainable FERC Energy Policy (Delaware Division of the Public Advo-
cate, Environmental Law & Policy Center, Fresh Energy, Natural Resources De-
fense Council, Northwest Energy Coalition, Pace Energy Project, Project for Sus-
tainable FERC Energy Policy, Renewable Northwest Project, West Wind Wires,
and Wind on the Wires).*
Public Power Council ......................................................... Public Power Council.
Sacramento ........................................................................ Sacramento Municipal Utility District.
Salt River ............................................................................ Salt River Project Agricultural Improvement and Power District.
Santa Clara ........................................................................ City of Santa Clara, California d/b/a Silicon Valley Power.
Seattle ................................................................................ City of Seattle—City Light Department.
Seminole ............................................................................ Seminole Electric Cooperative, Inc.
South Carolina E&G ........................................................... South Carolina Electric & Gas Company.
Southern ............................................................................. Southern Company Services, Inc.
SPP .................................................................................... Southwest Power Pool, Inc.
Steel Manufacturers Association ....................................... Steel Manufacturers Association.
Strategic Energy ................................................................. Strategic Energy, L.L.C.
TANC .................................................................................. Transmission Agency of Northern California.
TAPS .................................................................................. Transmission Access Policy Study Group.
TDU Systems ..................................................................... Transmission Dependent Utilities Systems.
Transparent Dispatch Advocates ....................................... PJM Interconnection, LLC; Electric Consumers Resource Council; Electric Power
Supply Association; Natural Resources Defense Council; Renewable Northwest
Project; Project for Sustainable FERC Energy Policy; Center for Energy Efficiency
& Renewable Technologies; Shell Trading Gas and Power Company; American
Wind Energy Association; and Exelon.
Utah Municipals .................................................................. Utah Associated Municipal Power Systems.
WestConnect ...................................................................... WestConnect Companies.
Williams .............................................................................. Williams Power Company, Inc.
Wolverine ........................................................................... Wolverine Power Supply Cooperative, Inc.
WPS Companies ................................................................ WPS Companies (Wisconsin Public Service Corporation and Upper Peninsula Power
Company).
WSPP ................................................................................. Western Systems Power Pool, Inc.
Xcel .................................................................................... Xcel Energy Services, Inc.

TECHNICAL CONFERENCE COMMENTERS


Abbreviation Technical conference commenters

APPA* ................................................................................ American Public Power Association.


APS* ................................................................................... Arizona Public Service Company.
Bonneville* ......................................................................... Bonneville Power Administration.
Constellation* ..................................................................... Constellation Energy Group, Inc.
EEI* .................................................................................... Exelon Corporation on behalf of Edison Electric Institute (EEI).
EPSA*1009 .......................................................................... Electric Power Supply Association.
Exelon* ............................................................................... Exelon.
NAESB* .............................................................................. North American Energy Standards Board.
sroberts on PROD1PC70 with RULES

NARUC* ............................................................................. National Association of Regulatory Utility Commissioners.


National Grid* ..................................................................... National Grid USA.
National Grid/Central Hudson ............................................ National Grid USA, Central Hudson Gas & Electric Corporation, and American Wind
Energy.
NERC* ................................................................................ Prague Power, LLC, on behalf of the North American Electric Reliability Corporation.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00237 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12502 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

TECHNICAL CONFERENCE COMMENTERS—Continued


Abbreviation Technical conference commenters

New York Parties ............................................................... Consolidated Edison Co. of New York, Inc., Orange and Rockland Utilities, Inc., New
York Power Authority, and Independent Power Producers of New York, Inc.
NRECA* ............................................................................. Great River Energy on behalf of National Rural Electric Cooperative Association
(NRECA).
NRG on behalf of EPSA* ................................................... NRG Energy, Inc. on behalf of Electric Power Supply Association (EPSA).
PacifiCorp ........................................................................... PacifiCorp.
PJM* ................................................................................... PJM Interconnection, LLC.
AWEA* ............................................................................... PPM Energy, Inc. on behalf of American Wind Energy Association
Progress Energy* ............................................................... Progress Energy, Inc. (Carolina Power & Light Company, d/b/a. Progress Energy
Carolinas, Inc. and Florida Power Corporation, d/b/a Progress Energy Florida,
Inc.).
Renewable Northwest Project* .......................................... Renewable Northwest Project.
San Diego G&E .................................................................. San Diego Gas & Electric Company.
TAPS* ................................................................................. Southern Minnesota Municipal Power Agency and Transmission Access Policy Study
Group.
TDU Systems ..................................................................... Transmission Dependent Utilities Systems.
South Carolina Regulatory Staff ........................................ South Carolina Office of Regulatory Staff.
Southern* ........................................................................... Southern Company Services, Inc.
WECC* ............................................................................... Western Electricity Coordinating Council.
Williams* ............................................................................. Williams Power.
Williams* ............................................................................. Williams Power Company, Inc.
Xcel* ................................................................................... Xcel Energy Services, Inc.

SUPPLEMENTAL COMMENTERS
Abbreviation Supplemental commenters

Alabama Commission ........................................................ Alabama Public Service Commission.


Ameren ............................................................................... Ameren Services Company.
APPA .................................................................................. American Public Power Association.
Barrick ................................................................................ Barrick Goldstrike Mines Inc.
Bonneville ........................................................................... Bonneville Power Administration.
BP Energy .......................................................................... BP Energy Company.
California Commission ....................................................... Public Utilities Commission of the State of California.
Community Power Alliance ................................................ Community Power Alliance Members (Entergy, Progress Energy, Salt River Project
Agricultural Improvement and Power District, and Southern Co.).
Constellation ....................................................................... Constellation Energy Group, Inc.
Duke ................................................................................... Duke Energy Corp.
E.ON ................................................................................... E.ON U.S. LLC.
EEI ...................................................................................... Edison Electric Institute.
Entergy ............................................................................... Entergy Services, Inc.
EPSA and AWEA ............................................................... Electric Power Supply Association and American Wind Energy Association.
Florida Commission ........................................................... Florida Public Service Commission.
Georgia Commission .......................................................... Georgia Public Service Commission.
LPPC .................................................................................. Large Public Power Council.
Mark Lively ......................................................................... Mark B. Lively.
MISO .................................................................................. Midwest Independent Transmission System Operator, Inc.
Nevada Companies ............................................................ Nevada Power Company and Sierra Pacific Power Company.
North Carolina Commission ............................................... North Carolina Utilities Commission; Public Staff of the North Carolina Utilities Com-
mission; and the Attorney General of the State of North Carolina.
NRECA ............................................................................... National Rural Electric Cooperative Association.
OG&E ................................................................................. Oklahoma Gas and Electric Company.
Pacific Coast Parties .......................................................... Pacific Coast Parties (Avista Corporation, Bonneville Power Administration,
PacifiCorp, Portland General Electric Company, Puget Sound Energy, Inc., the
Sacramento Municipal Utility District and the Transmission Agency of Northern
California).
PGP .................................................................................... Public Generating Pool.
Southwest Utilities .............................................................. Pinnacle West Companies, Public Service Company of New Mexico, Texas-New
Mexico Power Company, and UniSource Energy Corporation.
PNM-TNMP ........................................................................ Public Service Company of New Mexico and Texas-New Mexico Power Company.
Powerex ............................................................................. Powerex Corp.
PPL ..................................................................................... PPL Companies.
PPM .................................................................................... PPM Energy, Inc.
Progress Energy ................................................................ Progress Energy, Inc. (Carolina Power & Light Company, d/b/a. Progress Energy
Carolinas, Inc. and Florida Power Corporation, d/b/a Progress Energy Florida,
Inc.).
sroberts on PROD1PC70 with RULES

Progress Energy and MidAmerican ................................... Progress Energy, Inc. and MidAmerican Energy Company.
Public Power Council ......................................................... Public Power Council.
SEARUC ............................................................................ Southeastern Association of Regulatory Utility Commissioners.
South Carolina E&G ........................................................... South Carolina Electric & Gas Company.
South Carolina Regulatory Staff ........................................ South Carolina Office of Regulatory Staff.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00238 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12503

SUPPLEMENTAL COMMENTERS—Continued
Abbreviation Supplemental commenters

Southern ............................................................................. Southern Company Services, Inc.


Tacoma .............................................................................. Tacoma Power.
TAPS .................................................................................. Transmission Access Policy Study Group.
TDU Systems ..................................................................... Transmission Dependent Utilities Systems.
Transparent Dispatch Advocates ....................................... Transparent Dispatch Advocates (American Wind Energy Association; Center for En-
ergy Efficiency & Renewable Technologies; Electric Consumers Resource Council;
Electric Power Supply Association; Exelon Corporation; Natural Resources De-
fense Council; PJM Interconnection, LLC; PPM Energy; Project for Sustainable
FERC Energy Policy; Renewable Northwest Project; and Shell Trading Gas and
Power Company)*1010
Western Governors ............................................................ Western Governors’ Association.
Williams .............................................................................. Williams Power Company, Inc.
WIRES ................................................................................ WIRES.
Xcel .................................................................................... Xcel Energy Services, Inc.

Appendix C: Pro Forma Open Access 1.37 Point-To-Point Transmission Service 8.2 Study Costs and Revenues
Transmission Tariff 1.38 Power Purchaser 9 Regulatory Filings
1.39 Pre-Confirmed Application 10 Force Majeure and Indemnification
Table of Contents 1.40 Receiving Party 10.1 Force Majeure
I. Common Service Provisions 1.41 Regional Transmission Group (RTG) 10.2 Indemnification
1 Definitions 1.42 Reserved Capacity 11 Creditworthiness
1.1 Affiliate 1.43 Service Agreement 12 Dispute Resolution Procedures
1.2 Ancillary Services 1.44 Service Commencement Date 12.1 Internal Dispute Resolution
1.3 Annual Transmission Costs 1.45 Short-Term Firm Point-To-Point Procedures
1.4 Application Transmission Service 12.2 External Arbitration Procedures
1.5 Commission 1.46 System Condition 12.3 Arbitration Decisions
1.6 Completed Application 1.47 System Impact Study 12.4 Costs
1.7 Control Area 1.48 Third-Party Sale 12.5 Rights Under the Federal Power Act
1.8 Curtailment 1.49 Transmission Customer II. Point-to-Point Transmission Service
1.9 Delivering Party 1.50 Transmission Provider 13 Nature of Firm Point-to-Point
1.10 Designated Agent 1.51 Transmission Provider’s Monthly Transmission Service
1.11 Direct Assignment Facilities Transmission System Peak 13.1 Term
1.12 Eligible Customer 1.52 Transmission Service 13.2 Reservation Priority
1.13 Facilities Study 1.53 Transmission System 13.3 Use of Firm Transmission Service by
1.14 Firm Point-To-Point Transmission 2 Initial Allocation and Renewal the Transmission Provider
Service Procedures 13.4 Service Agreements
1.15 Good Utility Practice 2.1 Initial Allocation of Available 13.5 Transmission Customer Obligations
1.16 Interruption Transfer Capability for Facility Additions or Redispatch
1.17 Load Ratio Share 2.2 Reservation Priority for Existing Firm Costs
1.18 Load Shedding Service Customers 13.6 Curtailment of Firm Transmission
1.19 Long-Term Firm Point-To-Point 3 Ancillary Services Service
Transmission Service 3.1 Scheduling, System Control and 13.7 Classification of Firm Transmission
1.20 Native Load Customers Dispatch Service Service
1.21 Network Customer 3.2 Reactive Supply and Voltage Control 13.8 Scheduling of Firm Point-To-Point
1.22 Network Integration Transmission From Generation or Other Sources Transmission Service
Service Service 14 Nature of Non-Firm Point-to-Point
1.23 Network Load 3.3 Regulation and Frequency Response Transmission Service
1.24 Network Operating Agreement Service 14.1 Term
1.25 Network Operating Committee 3.4 Energy Imbalance Service 14.2 Reservation Priority
1.26 Network Resource 3.5 Operating Reserve—Spinning Reserve 14.3 Use of Non-Firm Point-To-Point
1.27 Network Upgrades Service Transmission Service by the
1.28 Non-Firm Point-To-Point 3.6 Operating Reserve—Supplemental Transmission Provider
Transmission Service Reserve Service 14.4 Service Agreements
1.29 Non-Firm Sale 3.7 Generator Imbalance Service 14.5 Classification of Non-Firm Point-To-
1.30 Open Access Same-Time 4 Open Access Same-Time Information Point Transmission Service
Information System (OASIS) System (OASIS) 14.6 Scheduling of Non-Firm Point-To-
1.31 Part I 5 Local Furnishing Bonds Point Transmission Service
1.32 Part II 5.1 Transmission Providers That Own 14.7 Curtailment or Interruption of
1.33 Part III Facilities Financed by Local Furnishing Service
1.34 Parties Bonds 15 Service Availability
1.35 Point(s) of Delivery 5.2 Alternative Procedures for Requesting 15.1 General Conditions
1.36 Point(s) of Receipt Transmission Service 15.2 Determination of Available Transfer
6 Reciprocity Capability
1008 A ‘‘*’’ indicates that the composition of this 7 Billing and Payment 15.3 Initiating Service in the Absence of
7.1 Billing Procedure: an Executed Service Agreement
sroberts on PROD1PC70 with RULES

group has altered in the reply comment filing.


1009 A ‘‘*’’ indicates that this party submitted 7.2 Interest on Unpaid Balances 15.4 Obligation to Provide Transmission
speaker materials at the October 12 Technical 7.3 Customer Default Service that Requires Expansion or
Conference. 8 Accounting for the Transmission Modification of the Transmission
1010 A ‘‘*’’ indicates that the composition of this Provider’s Use of the Tariff System, Redispatch or Conditional
group has altered in this filing. 8.1 Transmission Revenues Curtailment

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00239 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12504 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

15.5 Deferral of Service 24.1 Transmission Customer Obligations 33.5 Allocation of Curtailments
15.6 Other Transmission Service 24.2 Transmission Provider Access to 33.6 Load Shedding
Schedules Metering Data 33.7 System Reliability
15.7 Real Power Losses 24.3 Power Factor 34 Rates and Charges
16 Transmission Customer 25 Compensation for Transmission 34.1 Monthly Demand Charge
Responsibilities Service 34.2 Determination of Network
16.1 Conditions Required of 26 Stranded Cost Recovery Customer’s Monthly Network Load
Transmission Customers 27 Compensation for New Facilities and 34.3 Determination of Transmission
16.2 Transmission Customer Redispatch Costs Provider’s Monthly Transmission System
Responsibility for Third-Party III. Network Integration Transmission Service Load
Arrangements 28 Nature of Network Integration 34.4 Redispatch Charge
17 Procedures For Arranging Firm Point- Transmission Service 34.5 Stranded Cost Recovery
to-Point Transmission Service 28.1 Scope of Service 35 Operating Arrangements
17.1 Application 28.2 Transmission Provider 35.1 Operation Under The Network
17.2 Completed Application Responsibilities Operating Agreement
17.3 Deposit 28.3 Network Integration Transmission 35.2 Network Operating Agreement
17.4 Notice of Deficient Application Service 35.3 Network Operating Committee
17.5 Response to a Completed 28.4 Secondary Service
Application 28.5 Real Power Losses Schedule 1
17.6 Execution of Service Agreement 28.6 Restrictions on Use of Service Scheduling, System Control and Dispatch
17.7 Extensions for Commencement of 29 Initiating Service Service
Service 29.1 Condition Precedent for Receiving
18 Procedures for Arranging Non-Firm Schedule 2
Service
Point-to-Point Transmission Service 29.2 Application Procedures Reactive Supply and Voltage Control From
18.1 Application 29.3 Technical Arrangements to be Generation Sources Service
18.2 Completed Application Completed Prior to Commencement of Schedule 3
18.3 Reservation of Non-Firm Point-to- Service
Point Transmission Service Regulation and Frequency Response
29.4 Network Customer Facilities Service
18.4 Determination of Available Transfer 29.5 Filing of Service Agreement
Capability 30 Network Resources Schedule 4
19 Additional Study Procedures For Firm 30.1 Designation of Network Resources Energy Imbalance Service
Point-to-Point Transmission Service
30.2 Designation of New Network Schedule 5
Requests
Resources
19.1 Notice of Need for System Impact Operating Reserve—Spinning Reserve
30.3 Termination of Network Resources
Study Service
30.4 Operation of Network Resources
19.2 System Impact Study Agreement and
30.5 Network Customer Redispatch Schedule 6
Cost Reimbursement
19.3 System Impact Study Procedures Obligation Operating Reserve—Supplemental Reserve
19.4 Facilities Study Procedures 30.6 Transmission Arrangements for Service
19.5 Facilities Study Modifications Network Resources Not Physically
Interconnected With the Transmission Schedule 7
19.6 Due Diligence in Completing New
Facilities Provider Long-Term Firm and Short-Term Firm
19.7 Partial Interim Service 30.7 Limitation on Designation of Point-to-Point
19.8 Expedited Procedures for New Network Resources Schedule 8
Facilities 30.8 Use of Interface Capacity by the
Network Customer Non-Firm Point-to-Point Transmission
19.9 Penalties for Failure to Meet Study Service
Deadlines 30.9 Network Customer Owned
20 Procedures if the Transmission Transmission Facilities Schedule 9
Provider is Unable to Complete New 31 Designation of Network Load Generator Imbalance Service
Transmission Facilities for Firm Point- 31.1 Network Load
31.2 New Network Loads Connected With Attachment A
to-Point Transmission Service
20.1 Delays in Construction of New the Transmission Provider Form of Service Agreement for Firm Point-
Facilities: 31.3 Network Load Not Physically to-Point Transmission Service
20.2 Alternatives to the Original Facility Interconnected With the Transmission Attachment A–1
Additions Provider
31.4 New Interconnection Points Form of Service Agreement for the Resale,
20.3 Refund Obligation for Unfinished Reassignment or Transfer of Long-Term
Facility Additions 31.5 Changes in Service Requests
31.6 Annual Load and Resource Firm Point-to-Point Transmission
21 Provisions Relating to Transmission
Information Updates Service
Construction and Services on the
Systems of Other Utilities 32 Additional Study Procedures for Attachment B
21.1 Responsibility for Third-Party Network Integration Transmission Form of Service Agreement for Non-Firm
System Additions Service Requests Point-to-Point Transmission Service
21.2 Coordination of Third-Party System 32.1 Notice of Need for System Impact
Study Attachment C
Additions
22 Changes in Service Specifications 32.2 System Impact Study Agreement and Methodology to Assess Available Transfer
22.1 Modifications On a Non-Firm Basis Cost Reimbursement Capability
22.2 Modification On a Firm Basis 32.3 System Impact Study Procedures Attachment D
23 Sale or Assignment of Transmission 32.4 Facilities Study Procedures
Service 32.5 Penalties for Failure to Meet Study Methodology for Completing a System
23.1 Procedures for Assignment or Deadlines Impact Study
Transfer of Service 33 Load Shedding and Curtailments Attachment E
23.2 Limitations on Assignment or 33.1 Procedures
sroberts on PROD1PC70 with RULES

Index of Point-to-Point Transmission


Transfer of Service 33.2 Transmission Constraints Service Customers
23.3 Information on Assignment or 33.3 Cost Responsibility for Relieving
Transfer of Service Transmission Constraints Attachment F
24 Metering and Power Factor Correction 33.4 Curtailments of Scheduled Service Agreement for Network Integration
at Receipt and Delivery Points(s) Deliveries Transmission Service

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00240 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12505

Attachment G 1. Match, at all times, the power voluntary offer of such service by the
Network Operating Agreement output of the generators within the Transmission Provider.
Attachment H electric power system(s) and capacity ii. Any retail customer taking
Annual Transmission Revenue
and energy purchased from entities unbundled transmission service
Requirement for Network Integration outside the electric power system(s), pursuant to a state requirement that the
Transmission Service with the load within the electric power Transmission Provider offer the
Attachment I system(s); transmission service, or pursuant to a
2. Maintain scheduled interchange voluntary offer of such service by the
Index of Network Integration Transmission
Service Customers with other Control Areas, within the Transmission Provider, is an Eligible
limits of Good Utility Practice; Customer under the Tariff.
Attachment J
3. Maintain the frequency of the
Procedures for Addressing Parallel Flows electric power system(s) within 1.13 Facilities Study
Attachment K reasonable limits in accordance with
An engineering study conducted by
Transmission Planning Process Good Utility Practice; and
the Transmission Provider to determine
Attachment L 4. Provide sufficient generating the required modifications to the
Creditworthiness Procedures capacity to maintain operating reserves
Transmission Provider’s Transmission
in accordance with Good Utility
I. Common Service Provisions System, including the cost and
Practice.
scheduled completion date for such
1 Definitions 1.8 Curtailment modifications, that will be required to
1.1 Affiliate provide the requested transmission
A reduction in firm or non-firm
service.
With respect to a corporation, transmission service in response to a
partnership or other entity, each such transfer capability shortage as a result of 1.14 Firm Point-To-Point
other corporation, partnership or other system reliability conditions. Transmission Service
entity that directly or indirectly, 1.9 Delivering Party
through one or more intermediaries, Transmission Service under this
controls, is controlled by, or is under The entity supplying capacity and Tariff that is reserved and/or scheduled
common control with, such corporation, energy to be transmitted at Point(s) of between specified Points of Receipt and
partnership or other entity. Receipt. Delivery pursuant to Part II of this
Tariff.
1.2 Ancillary Services 1.10 Designated Agent
Those services that are necessary to 1.15 Good Utility Practice
Any entity that performs actions or
support the transmission of capacity functions on behalf of the Transmission Any of the practices, methods and
and energy from resources to loads Provider, an Eligible Customer, or the acts engaged in or approved by a
while maintaining reliable operation of Transmission Customer required under significant portion of the electric utility
the Transmission Provider’s the Tariff. industry during the relevant time
Transmission System in accordance period, or any of the practices, methods
with Good Utility Practice. 1.11 Direct Assignment Facilities
and acts which, in the exercise of
1.3 Annual Transmission Costs Facilities or portions of facilities that reasonable judgment in light of the facts
are constructed by the Transmission known at the time the decision was
The total annual cost of the Provider for the sole use/benefit of a made, could have been expected to
Transmission System for purposes of particular Transmission Customer
Network Integration Transmission accomplish the desired result at a
requesting service under the Tariff. reasonable cost consistent with good
Service shall be the amount specified in Direct Assignment Facilities shall be
Attachment H until amended by the business practices, reliability, safety and
specified in the Service Agreement that expedition. Good Utility Practice is not
Transmission Provider or modified by governs service to the Transmission
the Commission. intended to be limited to the optimum
Customer and shall be subject to practice, method, or act to the exclusion
1.4 Application Commission approval. of all others, but rather to be acceptable
A request by an Eligible Customer for 1.12 Eligible Customer practices, methods, or acts generally
transmission service pursuant to the accepted in the region, including those
i. Any electric utility (including the practices required by Federal Power Act
provisions of the Tariff. Transmission Provider and any power section 215(a)(4).
1.5 Commission marketer), Federal power marketing
The Federal Energy Regulatory agency, or any person generating 1.16 Interruption
Commission. electric energy for sale for resale is an
Eligible Customer under the Tariff. A reduction in non-firm transmission
1.6 Completed Application Electric energy sold or produced by service due to economic reasons
such entity may be electric energy pursuant to Section 14.7.
An Application that satisfies all of the
information and other requirements of produced in the United States, Canada 1.17 Load Ratio Share
the Tariff, including any required or Mexico. However, with respect to
deposit. transmission service that the Ratio of a Transmission Customer’s
Commission is prohibited from ordering Network Load to the Transmission
1.7 Control Area by Section 212(h) of the Federal Power Provider’s total load computed in
sroberts on PROD1PC70 with RULES

An electric power system or Act, such entity is eligible only if the accordance with Sections 34.2 and 34.3
combination of electric power systems service is provided pursuant to a state of the Network Integration Transmission
to which a common automatic requirement that the Transmission Service under Part III of the Tariff and
generation control scheme is applied in Provider offer the unbundled calculated on a rolling twelve month
order to: transmission service, or pursuant to a basis.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00241 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12506 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

1.18 Load Shedding 1.25 Network Operating Committee Provisions of Part I and appropriate
The systematic reduction of system Schedules and Attachments.
A group made up of representatives
demand by temporarily decreasing load from the Network Customer(s) and the 1.33 Part III
in response to transmission system or Transmission Provider established to Tariff Sections 28 through 35
area capacity shortages, system coordinate operating criteria and other pertaining to Network Integration
instability, or voltage control technical considerations required for Transmission Service in conjunction
considerations under Part III of the implementation of Network Integration with the applicable Common Service
Tariff. Transmission Service under Part III of Provisions of Part I and appropriate
1.19 Long-Term Firm Point-To-Point this Tariff. Schedules and Attachments.
Transmission Service 1.26 Network Resource 1.34 Parties
Firm Point-To-Point Transmission Any designated generating resource The Transmission Provider and the
Service under Part II of the Tariff with owned, purchased or leased by a Transmission Customer receiving
a term of one year or more. Network Customer under the Network service under the Tariff.
1.20 Native Load Customers Integration Transmission Service Tariff.
Network Resources do not include any 1.35 Point(s) of Delivery
The wholesale and retail power
resource, or any portion thereof, that is Point(s) on the Transmission
customers of the Transmission Provider
committed for sale to third parties or Provider’s Transmission System where
on whose behalf the Transmission
otherwise cannot be called upon to meet capacity and energy transmitted by the
Provider, by statute, franchise,
the Network Customer’s Network Load Transmission Provider will be made
regulatory requirement, or contract, has
on a non-interruptible basis. available to the Receiving Party under
undertaken an obligation to construct
Part II of the Tariff. The Point(s) of
and operate the Transmission Provider’s 1.27 Network Upgrades
Delivery shall be specified in the
system to meet the reliable electric
Modifications or additions to Service Agreement for Long-Term Firm
needs of such customers.
transmission-related facilities that are Point-To-Point Transmission Service.
1.21 Network Customer integrated with and support the
1.36 Point(s) of Receipt
An entity receiving transmission Transmission Provider’s overall
Transmission System for the general Point(s) of interconnection on the
service pursuant to the terms of the Transmission Provider’s Transmission
Transmission Provider’s Network benefit of all users of such Transmission
System. System where capacity and energy will
Integration Transmission Service under be made available to the Transmission
Part III of the Tariff. 1.28 Non-Firm Point-To-Point Provider by the Delivering Party under
1.22 Network Integration Transmission Transmission Service Part II of the Tariff. The Point(s) of
Service Point-To-Point Transmission Service Receipt shall be specified in the Service
The transmission service provided under the Tariff that is reserved and Agreement for Long-Term Firm Point-
under Part III of the Tariff. scheduled on an as-available basis and To-Point Transmission Service.
is subject to Curtailment or Interruption 1.37 Point-To-Point Transmission
1.23 Network Load as set forth in Section 14.7 under Part Service
The load that a Network Customer II of this Tariff. Non-Firm Point-To-
designates for Network Integration Point Transmission Service is available The reservation and transmission of
Transmission Service under Part III of on a stand-alone basis for periods capacity and energy on either a firm or
the Tariff. The Network Customer’s ranging from one hour to one month. non-firm basis from the Point(s) of
Network Load shall include all load Receipt to the Point(s) of Delivery under
1.29 Non-Firm Sale Part II of the Tariff.
served by the output of any Network
Resources designated by the Network An energy sale for which receipt or 1.38 Power Purchaser
Customer. A Network Customer may delivery may be interrupted for any
The entity that is purchasing the
elect to designate less than its total load reason or no reason, without liability on
capacity and energy to be transmitted
as Network Load but may not designate the part of either the buyer or seller.
under the Tariff.
only part of the load at a discrete Point 1.30 Open Access Same-Time
of Delivery. Where a Eligible Customer 1.39 Pre-Confirmed Application
Information System (OASIS)
has elected not to designate a particular An Application that commits the
load at discrete points of delivery as The information system and standards Transmission Customer to execute a
Network Load, the Eligible Customer is of conduct contained in Part 37 of the Service Agreement upon receipt of
responsible for making separate Commission’s regulations and all notification that the Transmission
arrangements under Part II of the Tariff additional requirements implemented Provider can provide the requested
for any Point-To-Point Transmission by subsequent Commission orders Transmission Service.
Service that may be necessary for such dealing with OASIS.
non-designated load. 1.40 Receiving Party
1.31 Part I
The entity receiving the capacity and
1.24 Network Operating Agreement Tariff Definitions and Common energy transmitted by the Transmission
An executed agreement that contains Service Provisions contained in Provider to Point(s) of Delivery.
the terms and conditions under which Sections 2 through 12.
the Network Customer shall operate its 1.41 Regional Transmission Group
1.32 Part II (RTG)
sroberts on PROD1PC70 with RULES

facilities and the technical and


operational matters associated with the Tariff Sections 13 through 27 A voluntary organization of
implementation of Network Integration pertaining to Point-To-Point transmission owners, transmission users
Transmission Service under Part III of Transmission Service in conjunction and other entities approved by the
the Tariff. with the applicable Common Service Commission to efficiently coordinate

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00242 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12507

transmission planning (and expansion), 1.49 Transmission Customer transmission-only, with a contract term
operation and use on a regional (and Any Eligible Customer (or its of five years or more), have the right to
interregional) basis. Designated Agent) that (i) executes a continue to take transmission service
Service Agreement, or (ii) requests in from the Transmission Provider when
1.42 Reserved Capacity
writing that the Transmission Provider the contract expires, rolls over or is
The maximum amount of capacity renewed. This transmission reservation
and energy that the Transmission file with the Commission, a proposed
unexecuted Service Agreement to priority is independent of whether the
Provider agrees to transmit for the existing customer continues to purchase
Transmission Customer over the receive transmission service under Part
capacity and energy from the
Transmission Provider’s Transmission II of the Tariff. This term is used in the
Transmission Provider or elects to
System between the Point(s) of Receipt Part I Common Service Provisions to
purchase capacity and energy from
and the Point(s) of Delivery under Part include customers receiving
another supplier. If at the end of the
II of the Tariff. Reserved Capacity shall transmission service under Part II and
contract term, the Transmission
be expressed in terms of whole Part III of this Tariff.
Provider’s Transmission System cannot
megawatts on a sixty (60) minute 1.50 Transmission Provider accommodate all of the requests for
interval (commencing on the clock transmission service, the existing firm
hour) basis. The public utility (or its Designated
Agent) that owns, controls, or operates service customer must agree to accept a
1.43 Service Agreement facilities used for the transmission of contract term at least equal to the longer
electric energy in interstate commerce of a competing request by any new
The initial agreement and any Eligible Customer or five years and to
amendments or supplements thereto and provides transmission service under
pay the current just and reasonable rate,
entered into by the Transmission the Tariff.
as approved by the Commission, for
Customer and the Transmission 1.51 Transmission Provider’s Monthly such service. The existing firm service
Provider for service under the Tariff. Transmission System Peak customer must provide notice to the
1.44 Service Commencement Date The maximum firm usage of the Transmission Provider whether it will
Transmission Provider’s Transmission exercise its right of first refusal no less
The date the Transmission Provider
System in a calendar month. than one year prior to the expiration
begins to provide service pursuant to
date of its transmission service
the terms of an executed Service 1.52 Transmission Service agreement. This transmission
Agreement, or the date the Transmission
Point-To-Point Transmission Service reservation priority for existing firm
Provider begins to provide service in
provided under Part II of the Tariff on service customers is an ongoing right
accordance with Section 15.3 or Section
a firm and non-firm basis. that may be exercised at the end of all
29.1 under the Tariff.
firm contract terms of five years or
1.45 Short-Term Firm Point-To-Point 1.53 Transmission System longer. Service agreements subject to a
Transmission Service The facilities owned, controlled or right of first refusal entered into prior to
Firm Point-To-Point Transmission operated by the Transmission Provider [the acceptance by the Commission of
Service under Part II of the Tariff with that are used to provide transmission the Transmission Provider’s Attachment
a term of less than one year. service under Part II and Part III of the K], unless terminated, will become
Tariff. subject to the five year/one year
1.46 System Condition requirement on the first rollover date
A specified condition on the 2 Initial Allocation and Renewal after [the acceptance by the Commission
Transmission Provider’s system or on a Procedures of the Transmission Provider’s
neighboring system, such as a 2.1 Initial Allocation of Available Attachment K].
constrained transmission element or Transfer Capability 3 Ancillary Services
flowgate, that may trigger Curtailment of
Long-Term Firm Point-to-Point For purposes of determining whether Ancillary Services are needed with
Transmission Service using the existing capability on the Transmission transmission service to maintain
curtailment priority pursuant to Section Provider’s Transmission System is reliability within and among the Control
13.6. Such conditions must be identified adequate to accommodate a request for Areas affected by the transmission
in the Transmission Customer’s Service firm service under this Tariff, all service. The Transmission Provider is
Agreement. Completed Applications for new firm required to provide (or offer to arrange
transmission service received during the with the local Control Area operator as
1.47 System Impact Study initial sixty (60) day period discussed below), and the Transmission
An assessment by the Transmission commencing with the effective date of Customer is required to purchase, the
Provider of (i) the adequacy of the the Tariff will be deemed to have been following Ancillary Services (i)
Transmission System to accommodate a filed simultaneously. A lottery system Scheduling, System Control and
request for either Firm Point-To-Point conducted by an independent party Dispatch, and (ii) Reactive Supply and
Transmission Service or Network shall be used to assign priorities for Voltage Control from Generation or
Integration Transmission Service and Completed Applications filed Other Sources.
(ii) whether any additional costs may be simultaneously. All Completed The Transmission Provider is
incurred in order to provide Applications for firm transmission required to offer to provide (or offer to
transmission service. service received after the initial sixty arrange with the local Control Area
(60) day period shall be assigned a operator as discussed below) the
1.48 Third-Party Sale priority pursuant to Section 13.2. following Ancillary Services only to the
sroberts on PROD1PC70 with RULES

Any sale for resale in interstate Transmission Customer serving load


commerce to a Power Purchaser that is 2.2 Reservation Priority For Existing within the Transmission Provider’s
not designated as part of Network Load Firm Service Customers Control Area (i) Regulation and
under the Network Integration Existing firm service customers Frequency Response, (ii) Energy
Transmission Service. (wholesale requirements and Imbalance, (iii) Operating Reserve—

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00243 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12508 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Spinning, (iv) Operating Reserve— Customers solely by posting on the insufficient to accommodate a request
Supplemental, and (v) Generator OASIS, (2) any customer-initiated for firm transmission service, additional
Imbalance. The Transmission Customer requests for discounts (including studies may be required as provided by
serving load within the Transmission requests for use by one’s wholesale this Tariff pursuant to Sections 19 and
Provider’s Control Area is required to merchant or an affiliate’s use) must 32.
acquire these Ancillary Services, occur solely by posting on the OASIS, The Transmission Provider shall post
whether from the Transmission and (3) once a discount is negotiated, on its public Web site all rules,
Provider, from a third party, or by self- details must be immediately posted on standards and practices that (i) relate to
supply. The Transmission Customer the OASIS. A discount agreed upon for the terms and conditions of
may not decline the Transmission an Ancillary Service must be offered for transmission service, (ii) are not subject
Provider’s offer of Ancillary Services the same period to all Eligible to a North American Energy Standards
unless it demonstrates that it has Customers on the Transmission Board (NAESB) copyright restriction,
acquired the Ancillary Services from Provider’s system. Sections 3.1 through and (iii) are not otherwise included in
another source. The Transmission 3.7 below list the seven Ancillary this Tariff. The Transmission Provider
Customer must list in its Application Services. shall post on OASIS an electronic link
which Ancillary Services it will to these rules, standards and practices,
purchase from the Transmission 3.1 Scheduling, System Control and
and shall post on its public Web site an
Provider. A Transmission Customer that Dispatch Service
electronic link to the NAESB Web site
exceeds its firm reserved capacity at any The rates and/or methodology are where any rules, standards and
Point of Receipt or Point of Delivery or described in Schedule 1. practices that are protected by copyright
an Eligible Customer that uses may be obtained. The Transmission
Transmission Service at a Point of 3.2 Reactive Supply and Voltage
Control from Generation or Other Provider shall also make available on its
Receipt or Point of Delivery that it has public Web site a statement of the
not reserved is required to pay for all of Sources Service
process by which the Transmission
the Ancillary Services identified in this The rates and/or methodology are Provider shall add, delete or otherwise
section that were provided by the described in Schedule 2. modify the rules, standards and
Transmission Provider associated with practices that are posted on its website.
the unreserved service. The 3.3 Regulation and Frequency
Response Service Such process shall set forth the means
Transmission Customer or Eligible by which the Transmission Provider
Customer will pay for Ancillary Where applicable the rates and/or shall provide reasonable advance notice
Services based on the amount of methodology are described in Schedule to Transmission Customers and Eligible
transmission service it used but did not 3. Customers of any such additions,
reserve. deletions or modifications, the
If the Transmission Provider is a 3.4 Energy Imbalance Service
associated effective date, and any
public utility providing transmission Where applicable the rates and/or additional implementation procedures
service but is not a Control Area methodology are described in Schedule that the Transmission Provider deems
operator, it may be unable to provide 4. appropriate.
some or all of the Ancillary Services. In
3.5 Operating Reserve—Spinning 5 Local Furnishing Bonds
this case, the Transmission Provider can
fulfill its obligation to provide Ancillary Reserve Service
5.1 Transmission Providers That Own
Services by acting as the Transmission Where applicable the rates and/or
Facilities Financed by Local Furnishing
Customer’s agent to secure these methodology are described in Schedule
Bonds
Ancillary Services from the Control 5.
Area operator. The Transmission This provision is applicable only to
3.6 Operating Reserve—Supplemental Transmission Providers that have
Customer may elect to (i) have the
Reserve Service financed facilities for the local
Transmission Provider act as its agent,
(ii) secure the Ancillary Services Where applicable the rates and/or furnishing of electric energy with tax-
directly from the Control Area operator, methodology are described in Schedule exempt bonds, as described in Section
or (iii) secure the Ancillary Services 6. 142(f) of the Internal Revenue Code
(discussed in Schedules 3, 4, 5, 6 and (‘‘local furnishing bonds’’).
3.7 Generator Imbalance Service Notwithstanding any other provision of
9) from a third party or by self-supply
when technically feasible. Where applicable the rates and/or this Tariff, the Transmission Provider
The Transmission Provider shall methodology are described in Schedule shall not be required to provide
specify the rate treatment and all related 9. transmission service to any Eligible
terms and conditions in the event of an Customer pursuant to this Tariff if the
4 Open Access Same-Time
unauthorized use of Ancillary Services provision of such transmission service
Information System (OASIS)
by the Transmission Customer. would jeopardize the tax-exempt status
The specific Ancillary Services, prices Terms and conditions regarding Open of any local furnishing bond(s) used to
and/or compensation methods are Access Same-Time Information System finance the Transmission Provider’s
described on the Schedules that are and standards of conduct are set forth in facilities that would be used in
attached to and made a part of the 18 CFR part 37 of the Commission’s providing such transmission service.
Tariff. Three principal requirements regulations (Open Access Same-Time
apply to discounts for Ancillary Information System and Standards of 5.2 Alternative Procedures for
Services provided by the Transmission Conduct for Public Utilities) and 18 CFR Requesting Transmission Service
sroberts on PROD1PC70 with RULES

Provider in conjunction with its part 38 of the Commission’s regulations (i) If the Transmission Provider
provision of transmission service as (Business Practice Standards and determines that the provision of
follows: (1) Any offer of a discount Communication Protocols for Public transmission service requested by an
made by the Transmission Provider Utilities). In the event available transfer Eligible Customer would jeopardize the
must be announced to all Eligible capability as posted on the OASIS is tax-exempt status of any local

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00244 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12509

furnishing bond(s) used to finance its This reciprocity requirement applies Upon the occurrence of a default, the
facilities that would be used in not only to the Transmission Customer Transmission Provider may initiate a
providing such transmission service, it that obtains transmission service under proceeding with the Commission to
shall advise the Eligible Customer the Tariff, but also to all parties to a terminate service but shall not terminate
within thirty (30) days of receipt of the transaction that involves the use of service until the Commission so
Completed Application. transmission service under the Tariff, approves any such request. In the event
(ii) If the Eligible Customer thereafter including the power seller, buyer and of a billing dispute between the
renews its request for the same any intermediary, such as a power Transmission Provider and the
transmission service referred to in (i) by marketer. This reciprocity requirement Transmission Customer, the
tendering an application under Section also applies to any Eligible Customer Transmission Provider will continue to
211 of the Federal Power Act, the that owns, controls or operates provide service under the Service
Transmission Provider, within ten (10) transmission facilities that uses an Agreement as long as the Transmission
days of receiving a copy of the Section intermediary, such as a power marketer, Customer (i) continues to make all
211 application, will waive its rights to to request transmission service under payments not in dispute, and (ii) pays
a request for service under Section the Tariff. If the Transmission Customer into an independent escrow account the
213(a) of the Federal Power Act and to does not own, control or operate portion of the invoice in dispute,
the issuance of a proposed order under transmission facilities, it must include pending resolution of such dispute. If
Section 212(c) of the Federal Power Act. in its Application a sworn statement of the Transmission Customer fails to meet
The Commission, upon receipt of the one of its duly authorized officers or these two requirements for continuation
Transmission Provider’s waiver of its other representatives that the purpose of of service, then the Transmission
rights to a request for service under its Application is not to assist an Provider may provide notice to the
Section 213(a) of the Federal Power Act Eligible Customer to avoid the Transmission Customer of its intention
and to the issuance of a proposed order requirements of this provision. to suspend service in sixty (60) days, in
under Section 212(c) of the Federal accordance with Commission policy.
Power Act, shall issue an order under 7 Billing and Payment
Section 211 of the Federal Power Act. 8 Accounting for the Transmission
7.1 Billing Procedure
Upon issuance of the order under Provider’s Use of the Tariff
Section 211 of the Federal Power Act, Within a reasonable time after the first The Transmission Provider shall
the Transmission Provider shall be day of each month, the Transmission record the following amounts, as
required to provide the requested Provider shall submit an invoice to the outlined below.
transmission service in accordance with Transmission Customer for the charges
the terms and conditions of this Tariff. for all services furnished under the 8.1 Transmission Revenues
Tariff during the preceding month. The Include in a separate operating
6 Reciprocity invoice shall be paid by the revenue account or subaccount the
A Transmission Customer receiving Transmission Customer within twenty revenues it receives from Transmission
transmission service under this Tariff (20) days of receipt. All payments shall Service when making Third-Party Sales
agrees to provide comparable be made in immediately available funds under Part II of the Tariff.
transmission service that it is capable of payable to the Transmission Provider, or
providing to the Transmission Provider by wire transfer to a bank named by the 8.2 Study Costs and Revenues
on similar terms and conditions over Transmission Provider. Include in a separate transmission
facilities used for the transmission of operating expense account or
7.2 Interest on Unpaid Balances
electric energy owned, controlled or subaccount, costs properly chargeable to
operated by the Transmission Customer Interest on any unpaid amounts expense that are incurred to perform
and over facilities used for the (including amounts placed in escrow) any System Impact Studies or Facilities
transmission of electric energy owned, shall be calculated in accordance with Studies which the Transmission
controlled or operated by the the methodology specified for interest Provider conducts to determine if it
Transmission Customer’s corporate on refunds in the Commission’s must construct new transmission
affiliates. A Transmission Customer that regulations at 18 CFR 35.19a(a)(2)(iii). facilities or upgrades necessary for its
is a member of, or takes transmission Interest on delinquent amounts shall be own uses, including making Third-Party
service from, a power pool, Regional calculated from the due date of the bill Sales under the Tariff; and include in a
Transmission Group, Regional to the date of payment. When payments separate operating revenue account or
Transmission Organization (RTO), are made by mail, bills shall be subaccount the revenues received for
Independent System Operator (ISO) or considered as having been paid on the System Impact Studies or Facilities
other transmission organization date of receipt by the Transmission Studies performed when such amounts
approved by the Commission for the Provider. are separately stated and identified in
operation of transmission facilities also the Transmission Customer’s billing
agrees to provide comparable 7.3 Customer Default
under the Tariff.
transmission service to the members of In the event the Transmission
such power pool and Regional Customer fails, for any reason other than 9 Regulatory Filings
Transmission Group, RTO, ISO or other a billing dispute as described below, to Nothing contained in the Tariff or any
transmission organization on similar make payment to the Transmission Service Agreement shall be construed as
terms and conditions over facilities used Provider on or before the due date as affecting in any way the right of the
for the transmission of electric energy described above, and such failure of Transmission Provider to unilaterally
owned, controlled or operated by the payment is not corrected within thirty make application to the Commission for
sroberts on PROD1PC70 with RULES

Transmission Customer and over (30) calendar days after the a change in rates, terms and conditions,
facilities used for the transmission of Transmission Provider notifies the charges, classification of service, Service
electric energy owned, controlled or Transmission Customer to cure such Agreement, rule or regulation under
operated by the Transmission failure, a default by the Transmission Section 205 of the Federal Power Act
Customer’s corporate affiliates. Customer shall be deemed to exist. and pursuant to the Commission’s rules

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00245 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12510 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

and regulations promulgated for rate changes or other changes to the conduct of the arbitrator(s), or the
thereunder. Tariff, or to any Service Agreement decision itself, violated the standards
Nothing contained in the Tariff or any entered into under the Tariff, which set forth in the Federal Arbitration Act
Service Agreement shall be construed as shall be presented directly to the and/or the Administrative Dispute
affecting in any way the ability of any Commission for resolution) shall be Resolution Act. The final decision of the
Party receiving service under the Tariff referred to a designated senior arbitrator must also be filed with the
to exercise its rights under the Federal representative of the Transmission Commission if it affects jurisdictional
Power Act and pursuant to the Provider and a senior representative of rates, terms and conditions of service or
Commission’s rules and regulations the Transmission Customer for facilities.
promulgated thereunder. resolution on an informal basis as
promptly as practicable. In the event the 12.4 Costs
10 Force Majeure and Indemnification Each Party shall be responsible for its
designated representatives are unable to
10.1 Force Majeure resolve the dispute within thirty (30) own costs incurred during the
An event of Force Majeure means any days [or such other period as the Parties arbitration process and for the following
act of God, labor disturbance, act of the may agree upon] by mutual agreement, costs, if applicable:
public enemy, war, insurrection, riot, such dispute may be submitted to 1. The cost of the arbitrator chosen by
fire, storm or flood, explosion, breakage arbitration and resolved in accordance the Party to sit on the three member
or accident to machinery or equipment, with the arbitration procedures set forth panel and one half of the cost of the
any Curtailment, order, regulation or below. third arbitrator chosen; or
2. One half the cost of the single
restriction imposed by governmental 12.2 External Arbitration Procedures
arbitrator jointly chosen by the Parties.
military or lawfully established civilian Any arbitration initiated under the
authorities, or any other cause beyond a Tariff shall be conducted before a single 12.5 Rights Under the Federal Power
Party’s control. A Force Majeure event neutral arbitrator appointed by the Act
does not include an act of negligence or Parties. If the Parties fail to agree upon Nothing in this section shall restrict
intentional wrongdoing. a single arbitrator within ten (10) days the rights of any party to file a
Neither the Transmission Provider of the referral of the dispute to Complaint with the Commission under
nor the Transmission Customer will be arbitration, each Party shall choose one relevant provisions of the Federal Power
considered in default as to any arbitrator who shall sit on a three- Act.
obligation under this Tariff if prevented member arbitration panel. The two
from fulfilling the obligation due to an arbitrators so chosen shall within II. Point-To-Point Transmission Service
event of Force Majeure. However, a twenty (20) days select a third arbitrator Preamble
Party whose performance under this to chair the arbitration panel. In either
Tariff is hindered by an event of Force The Transmission Provider will
case, the arbitrators shall be
Majeure shall make all reasonable provide Firm and Non-Firm Point-To-
knowledgeable in electric utility
efforts to perform its obligations under Point Transmission Service pursuant to
matters, including electric transmission
this Tariff. the applicable terms and conditions of
and bulk power issues, and shall not
this Tariff. Point-To-Point Transmission
10.2 Indemnification have any current or past substantial
Service is for the receipt of capacity and
business or financial relationships with
The Transmission Customer shall at any party to the arbitration (except prior energy at designated Point(s) of Receipt
all times indemnify, defend, and save arbitration). The arbitrator(s) shall and the transfer of such capacity and
the Transmission Provider harmless provide each of the Parties an energy to designated Point(s) of
from, any and all damages, losses, opportunity to be heard and, except as Delivery.
claims, including claims and actions otherwise provided herein, shall 13 Nature of Firm Point-To-Point
relating to injury to or death of any generally conduct the arbitration in Transmission Service
person or damage to property, demands, accordance with the Commercial
suits, recoveries, costs and expenses, Arbitration Rules of the American 13.1 Term
court costs, attorney fees, and all other Arbitration Association and any The minimum term of Firm Point-To-
obligations by or to third parties, arising applicable Commission regulations or Point Transmission Service shall be one
out of or resulting from the Regional Transmission Group rules. day and the maximum term shall be
Transmission Provider’s performance of specified in the Service Agreement.
its obligations under this Tariff on 12.3 Arbitration Decisions
behalf of the Transmission Customer, Unless otherwise agreed, the 13.2 Reservation Priority
except in cases of negligence or arbitrator(s) shall render a decision (i) Long-Term Firm Point-To-Point
intentional wrongdoing by the within ninety (90) days of appointment Transmission Service shall be available
Transmission Provider. and shall notify the Parties in writing of on a first-come, first-served basis, i.e., in
11 Creditworthiness such decision and the reasons therefor. the chronological sequence in which
The arbitrator(s) shall be authorized each Transmission Customer has
The Transmission Provider will only to interpret and apply the requested service.
specify its Creditworthiness procedures provisions of the Tariff and any Service (ii) Reservations for Short-Term Firm
in Attachment L. Agreement entered into under the Tariff Point-To-Point Transmission Service
12 Dispute Resolution Procedures and shall have no power to modify or will be conditional based upon the
change any of the above in any manner. length of the requested transaction.
12.1 Internal Dispute Resolution The decision of the arbitrator(s) shall be However, Pre-Confirmed Applications
Procedures
sroberts on PROD1PC70 with RULES

final and binding upon the Parties, and for Short-Term Point-to-Point
Any dispute between a Transmission judgment on the award may be entered Transmission Service will receive
Customer and the Transmission in any court having jurisdiction. The priority over earlier-submitted requests
Provider involving transmission service decision of the arbitrator(s) may be that are not Pre-Confirmed and that
under the Tariff (excluding applications appealed solely on the grounds that the have equal or shorter duration. Among

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00246 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12511

requests with the same duration and date sixty (60) days after publication in Transmission Service without (1)
pre-confirmation status (Pre-Confirmed Federal Register] or (ii) agreements degrading or impairing the reliability of
or not confirmed), priority will be given executed prior to the aforementioned service to Native Load Customers,
to an Eligible Customer’s request that date that the Commission requires to be Network Customers and other
offers the highest price, followed by the unbundled, by the date specified by the Transmission Customers taking Firm
date and time of the request. Commission. The Transmission Point-To-Point Transmission Service, or
(iii) If the Transmission System Provider will maintain separate (2) interfering with the Transmission
becomes oversubscribed, requests for accounting, pursuant to Section 8, for Provider’s ability to meet prior firm
longer term service may preempt any use of the Point-To-Point contractual commitments to others, the
requests for shorter term service up to Transmission Service to make Third- Transmission Provider will be obligated
the following deadlines: one day before Party Sales. to expand or upgrade its Transmission
the commencement of daily service, one System pursuant to the terms of Section
week before the commencement of 13.4 Service Agreements
15.4. The Transmission Customer must
weekly service, and one month before The Transmission Provider shall offer agree to compensate the Transmission
the commencement of monthly service. a standard form Firm Point-To-Point Provider for any necessary transmission
Before the conditional reservation Transmission Service Agreement facility additions pursuant to the terms
deadline, if available transfer capability (Attachment A) to an Eligible Customer of Section 27. To the extent the
is insufficient to satisfy all Applications, when it submits a Completed Transmission Provider can relieve any
an Eligible Customer with a reservation Application for Long-Term Firm Point- system constraint by redispatching the
for shorter term service or equal To-Point Transmission Service. The Transmission Provider’s resources, it
duration service and lower price has the Transmission Provider shall offer a shall do so, provided that the Eligible
right of first refusal to match any longer standard form Firm Point-To-Point Customer agrees to compensate the
term request or equal duration service Transmission Service Agreement Transmission Provider pursuant to the
with a higher price before losing its (Attachment A) to an Eligible Customer terms of Section 27 and agrees to either
reservation priority. A longer term when it first submits a Completed (i) compensate the Transmission
competing request for Short-Term Firm Application for Short-Term Firm Point- Provider for any necessary transmission
Point-To-Point Transmission Service To-Point Transmission Service pursuant facility additions or (ii) accept the
will be granted if the Eligible Customer to the Tariff. Executed Service service subject to a biennial
with the right of first refusal does not Agreements that contain the information reassessment by the Transmission
agree to match the competing request required under the Tariff shall be filed Provider of redispatch requirements as
within 24 hours (or earlier if necessary with the Commission in compliance described in Section 15.4. Any
to comply with the scheduling with applicable Commission redispatch, Network Upgrade or Direct
deadlines provided in section 13.8) from regulations. An Eligible Customer that Assignment Facilities costs to be
being notified by the Transmission uses Transmission Service at a Point of charged to the Transmission Customer
Provider of a longer-term competing Receipt or Point of Delivery that it has on an incremental basis under the Tariff
request for Short-Term Firm Point-To- not reserved and that has not executed will be specified in the Service
Point Transmission Service. When a a Service Agreement will be deemed, for Agreement prior to initiating service.
longer duration request preempts purposes of assessing any appropriate
multiple shorter duration requests, the charges and penalties, to have executed 13.6 Curtailment of Firm Transmission
shorter duration requests shall have the appropriate Service Agreement. The Service
simultaneous opportunities to exercise Service Agreement shall, when In the event that a Curtailment on the
the right of first refusal. Duration, pre- applicable, specify any conditional Transmission Provider’s Transmission
confirmation status, price and time of curtailment options selected by the System, or a portion thereof, is required
response will be used to determine the Transmission Customer. Where the to maintain reliable operation of such
order by which the multiple shorter Service Agreement contains conditional system and the system directly and
duration requests will be able to curtailment options and is subject to a indirectly interconnected with
exercise the right of first refusal. After biennial reassessment as described in Transmission Provider’s Transmission
the conditional reservation deadline, Section 15.4, the Transmission Provider System, Curtailments will be made on a
service will commence pursuant to the shall provide the Transmission non-discriminatory basis to the
terms of Part II of the Tariff. Customer notice of any changes to the transaction(s) that effectively relieve the
(iv) Firm Point-To-Point Transmission curtailment conditions no less than 90 constraint. Transmission Provider may
Service will always have a reservation days prior to the date for imposition of elect to implement such Curtailments
priority over Non-Firm Point-To-Point new curtailment conditions. Concurrent pursuant to the Transmission Loading
Transmission Service under the Tariff. with such notice, the Transmission Relief procedures specified in
All Long-Term Firm Point-To-Point Provider shall provide the Transmission Attachment J. If multiple transactions
Transmission Service will have equal Customer with the reassessment study require Curtailment, to the extent
reservation priority with Native Load and a narrative description of the study, practicable and consistent with Good
Customers and Network Customers. including the reasons for changes to the Utility Practice, the Transmission
Reservation priorities for existing firm number of hours per year or System Provider will curtail service to Network
service customers are provided in Conditions under which conditional Customers and Transmission Customers
Section 2.2. curtailment may occur. taking Firm Point-To-Point
Transmission Service on a basis
13.3 Use of Firm Transmission Service 13.5 Transmission Customer comparable to the curtailment of service
by the Transmission Provider Obligations for Facility Additions or to the Transmission Provider’s Native
Redispatch Costs
sroberts on PROD1PC70 with RULES

The Transmission Provider will be Load Customers. All Curtailments will


subject to the rates, terms and In cases where the Transmission be made on a non-discriminatory basis,
conditions of Part II of the Tariff when Provider determines that the however, Non-Firm Point-To-Point
making Third-Party Sales under (i) Transmission System is not capable of Transmission Service shall be
agreements executed on or after [insert providing Firm Point-To-Point subordinate to Firm Transmission

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00247 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12512 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Service. Long-Term Firm Point-to-Point Point Service Agreement for Long-Term The Transmission Provider will furnish
Service subject to conditions described Firm Transmission Service along with a to the Delivering Party’s system
in Section 15.4 shall be curtailed with corresponding capacity reservation operator, hour-to-hour schedules equal
secondary service in cases where the associated with each Point of Delivery. to those furnished by the Receiving
conditions apply, but otherwise will be Points of Delivery and corresponding Party (unless reduced for losses) and
curtailed on a pro rata basis with other capacity reservations shall be as shall deliver the capacity and energy
Firm Transmission Service. When the mutually agreed upon by the Parties for provided by such schedules. Should the
Transmission Provider determines that Short-Term Firm Transmission. The Transmission Customer, Delivering
an electrical emergency exists on its greater of either (1) the sum of the Party or Receiving Party revise or
Transmission System and implements capacity reservations at the Point(s) of terminate any schedule, such party shall
emergency procedures to Curtail Firm Receipt, or (2) the sum of the capacity immediately notify the Transmission
Transmission Service, the Transmission reservations at the Point(s) of Delivery Provider, and the Transmission Provider
Customer shall make the required shall be the Transmission Customer’s shall have the right to adjust
reductions upon request of the Reserved Capacity. The Transmission accordingly the schedule for capacity
Transmission Provider. However, the Customer will be billed for its Reserved and energy to be received and to be
Transmission Provider reserves the right Capacity under the terms of Schedule 7. delivered.
to Curtail, in whole or in part, any Firm The Transmission Customer may not
Transmission Service provided under exceed its firm capacity reserved at each 14 Nature of Non-Firm Point-To-Point
the Tariff when, in the Transmission Point of Receipt and each Point of Transmission Service
Provider’s sole discretion, an emergency Delivery except as otherwise specified 14.1 Term
or other unforeseen condition impairs or in Section 22. The Transmission
degrades the reliability of its Provider shall specify the rate treatment Non-Firm Point-To-Point
Transmission System. The Transmission and all related terms and conditions Transmission Service will be available
Provider will notify all affected applicable in the event that a for periods ranging from one (1) hour to
Transmission Customers in a timely Transmission Customer (including one (1) month. However, a Purchaser of
manner of any scheduled Curtailments. Third-Party Sales by the Transmission Non-Firm Point-To-Point Transmission
Provider) exceeds its firm reserved Service will be entitled to reserve a
13.7 Classification of Firm sequential term of service (such as a
capacity at any Point of Receipt or Point
Transmission Service sequential monthly term without having
of Delivery or uses Transmission
(a) The Transmission Customer taking Service at a Point of Receipt or Point of to wait for the initial term to expire
Firm Point-To-Point Transmission Delivery that it has not reserved. before requesting another monthly term)
Service may (1) change its Receipt and so that the total time period for which
Delivery Points to obtain service on a 13.8 Scheduling of Firm Point-To- the reservation applies is greater than
non-firm basis consistent with the terms Point Transmission Service one month, subject to the requirements
of Section 22.1 or (2) request a Schedules for the Transmission of Section 18.3.
modification of the Points of Receipt or Customer’s Firm Point-To-Point 14.2 Reservation Priority
Delivery on a firm basis pursuant to the Transmission Service must be submitted
terms of Section 22.2. to the Transmission Provider no later Non-Firm Point-To-Point
(b) The Transmission Customer may than 10 a.m. [or a reasonable time that Transmission Service shall be available
purchase transmission service to make is generally accepted in the region and from transfer capability in excess of that
sales of capacity and energy from is consistently adhered to by the needed for reliable service to Native
multiple generating units that are on the Transmission Provider] of the day prior Load Customers, Network Customers
Transmission Provider’s Transmission to commencement of such service. and other Transmission Customers
System. For such a purchase of Schedules submitted after 10 a.m. will taking Long-Term and Short-Term Firm
transmission service, the resources will be accommodated, if practicable. Hour- Point-To-Point Transmission Service. A
be designated as multiple Points of to-hour schedules of any capacity and higher priority will be assigned first to
Receipt, unless the multiple generating energy that is to be delivered must be reservations with a longer duration of
units are at the same generating plant in stated in increments of 1,000 kW per service and second to Pre-Confirmed
which case the units would be treated hour [or a reasonable increment that is Applications. In the event the
as a single Point of Receipt. generally accepted in the region and is Transmission System is constrained,
(c) The Transmission Provider shall consistently adhered to by the competing requests of the same Pre-
provide firm deliveries of capacity and Transmission Provider]. Transmission Confirmation status and equal duration
energy from the Point(s) of Receipt to Customers within the Transmission will be prioritized based on the highest
the Point(s) of Delivery. Each Point of Provider’s service area with multiple price offered by the Eligible Customer
Receipt at which firm transmission requests for Transmission Service at a for the Transmission Service. Eligible
capacity is reserved by the Transmission Point of Receipt, each of which is under Customers that have already reserved
Customer shall be set forth in the Firm 1,000 kW per hour, may consolidate shorter term service have the right of
Point-To-Point Service Agreement for their service requests at a common point first refusal to match any longer term
Long-Term Firm Transmission Service of receipt into units of 1,000 kW per reservation before being preempted. A
along with a corresponding capacity hour for scheduling and billing longer term competing request for Non-
reservation associated with each Point purposes. Scheduling changes will be Firm Point-To-Point Transmission
of Receipt. Points of Receipt and permitted up to twenty (20) minutes [or Service will be granted if the Eligible
corresponding capacity reservations a reasonable time that is generally Customer with the right of first refusal
shall be as mutually agreed upon by the accepted in the region and is does not agree to match the competing
sroberts on PROD1PC70 with RULES

Parties for Short-Term Firm consistently adhered to by the request: (a) Immediately for hourly Non-
Transmission. Each Point of Delivery at Transmission Provider] before the start Firm Point-To-Point Transmission
which firm transfer capability is of the next clock hour provided that the Service after notification by the
reserved by the Transmission Customer Delivering Party and Receiving Party Transmission Provider; and, (b) within
shall be set forth in the Firm Point-To- also agree to the schedule modification. 24 hours (or earlier if necessary to

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00248 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12513

comply with the scheduling deadlines event that a Transmission Customer Service provided under the Tariff for
provided in section 14.6) for Non-Firm (including Third-Party Sales by the reliability reasons when an emergency
Point-To-Point Transmission Service Transmission Provider) exceeds its non- or other unforeseen condition threatens
other than hourly transactions after firm capacity reservation. Non-Firm to impair or degrade the reliability of its
notification by the Transmission Point-To-Point Transmission Service Transmission System or the systems
Provider. Transmission service for shall include transmission of energy on directly and indirectly interconnected
Network Customers from resources an hourly basis and transmission of with Transmission Provider’s
other than designated Network scheduled short-term capacity and Transmission System. Transmission
Resources will have a higher priority energy on a daily, weekly or monthly Provider may elect to implement such
than any Non-Firm Point-To-Point basis, but not to exceed one month’s Curtailments pursuant to the
Transmission Service. Non-Firm Point- reservation for any one Application, Transmission Loading Relief procedures
To-Point Transmission Service over under Schedule 8. specified in Attachment J. The
secondary Point(s) of Receipt and Transmission Provider reserves the right
14.6 Scheduling of Non-Firm Point-
Point(s) of Delivery will have the lowest to Interrupt, in whole or in part, Non-
To-Point Transmission Service
reservation priority under the Tariff. Firm Point-To-Point Transmission
Schedules for Non-Firm Point-To-
14.3 Use of Non-Firm Point-To-Point Service provided under the Tariff for
Point Transmission Service must be
Transmission Service by the economic reasons in order to
submitted to the Transmission Provider
Transmission Provider accommodate (1) a request for Firm
no later than 2 p.m. [or a reasonable
Transmission Service, (2) a request for
The Transmission Provider will be time that is generally accepted in the
subject to the rates, terms and region and is consistently adhered to by Non-Firm Point-To-Point Transmission
conditions of Part II of the Tariff when the Transmission Provider] of the day Service of greater duration, (3) a request
making Third-Party Sales under (i) prior to commencement of such service. for Non-Firm Point-To-Point
agreements executed on or after May 14, Schedules submitted after 2 p.m. will be Transmission Service of equal duration
2007 or (ii) agreements executed prior to accommodated, if practicable. Hour-to- with a higher price, (4) transmission
the aforementioned date that the hour schedules of energy that is to be service for Network Customers from
Commission requires to be unbundled, delivered must be stated in increments non-designated resources, or (5)
by the date specified by the of 1,000 kW per hour [or a reasonable transmission service for Firm Point-to-
Commission. The Transmission increment that is generally accepted in Point Transmission Service during
Provider will maintain separate the region and is consistently adhered to conditional curtailment periods as
accounting, pursuant to Section 8, for by the Transmission Provider]. described in Section 15.4. The
any use of Non-Firm Point-To-Point Transmission Customers within the Transmission Provider also will
Transmission Service to make Third- Transmission Provider’s service area discontinue or reduce service to the
Party Sales. with multiple requests for Transmission Transmission Customer to the extent
Service at a Point of Receipt, each of that deliveries for transmission are
14.4 Service Agreements which is under 1,000 kW per hour, may discontinued or reduced at the Point(s)
The Transmission Provider shall offer consolidate their schedules at a of Receipt. Where required,
a standard form Non-Firm Point-To- common Point of Receipt into units of Curtailments or Interruptions will be
Point Transmission Service Agreement 1,000 kW per hour. Scheduling changes made on a non-discriminatory basis to
(Attachment B) to an Eligible Customer will be permitted up to twenty (20) the transaction(s) that effectively relieve
when it first submits a Completed minutes [or a reasonable time that is the constraint, however, Non-Firm
Application for Non-Firm Point-To- generally accepted in the region and is Point-To-Point Transmission Service
Point Transmission Service pursuant to consistently adhered to by the shall be subordinate to Firm
the Tariff. Executed Service Agreements Transmission Provider] before the start Transmission Service. If multiple
that contain the information required of the next clock hour provided that the transactions require Curtailment or
under the Tariff shall be filed with the Delivering Party and Receiving Party Interruption, to the extent practicable
Commission in compliance with also agree to the schedule modification. and consistent with Good Utility
applicable Commission regulations. The Transmission Provider will furnish Practice, Curtailments or Interruptions
to the Delivering Party’s system will be made to transactions of the
14.5 Classification of Non-Firm Point- shortest term (e.g., hourly non-firm
operator, hour-to-hour schedules equal
To-Point Transmission Service transactions will be Curtailed or
to those furnished by the Receiving
Non-Firm Point-To-Point Party (unless reduced for losses) and Interrupted before daily non-firm
Transmission Service shall be offered shall deliver the capacity and energy transactions and daily non-firm
under terms and conditions contained provided by such schedules. Should the transactions will be Curtailed or
in Part II of the Tariff. The Transmission Transmission Customer, Delivering Interrupted before weekly non-firm
Provider undertakes no obligation under Party or Receiving Party revise or transactions). Transmission service for
the Tariff to plan its Transmission terminate any schedule, such party shall Network Customers from resources
System in order to have sufficient immediately notify the Transmission other than designated Network
capacity for Non-Firm Point-To-Point Provider, and the Transmission Provider Resources will have a higher priority
Transmission Service. Parties requesting shall have the right to adjust than any Non-Firm Point-To-Point
Non-Firm Point-To-Point Transmission accordingly the schedule for capacity Transmission Service under the Tariff.
Service for the transmission of firm and energy to be received and to be Non-Firm Point-To-Point Transmission
power do so with the full realization delivered. Service over secondary Point(s) of
that such service is subject to Receipt and Point(s) of Delivery will
14.7 Curtailment or Interruption of
sroberts on PROD1PC70 with RULES

availability and to Curtailment or have a lower priority than any Non-Firm


Interruption under the terms of the Service Point-To-Point Transmission Service
Tariff. The Transmission Provider shall The Transmission Provider reserves under the Tariff. The Transmission
specify the rate treatment and all related the right to Curtail, in whole or in part, Provider will provide advance notice of
terms and conditions applicable in the Non-Firm Point-To-Point Transmission Curtailment or Interruption where such

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00249 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12514 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

notice can be provided consistent with Transmission Service, consistent with facilities or upgrades needed to provide
Good Utility Practice. its planning obligations in Attachment Firm Point-To-Point Transmission
K, provided the Transmission Customer Service whenever the Transmission
15 Service Availability
agrees to compensate the Transmission Provider determines that providing the
15.1 General Conditions Provider for such costs pursuant to the requested service would, without such
The Transmission Provider will terms of Section 27. The Transmission new facilities or upgrades, impair or
provide Firm and Non-Firm Point-To- Provider will conform to Good Utility degrade reliability to any existing firm
Point Transmission Service over, on or Practice and its planning obligations in services.
across its Transmission System to any Attachment K, in determining the need
for new facilities and in the design and 15.6 Other Transmission Service
Transmission Customer that has met the Schedules
requirements of Section 16. construction of such facilities. The
obligation applies only to those facilities Eligible Customers receiving
15.2 Determination of Available that the Transmission Provider has the transmission service under other
Transfer Capability right to expand or modify. agreements on file with the Commission
A description of the Transmission (b) If the Transmission Provider may continue to receive transmission
Provider’s specific methodology for determines that it cannot accommodate service under those agreements until
assessing available transfer capability a Completed Application for Firm Point- such time as those agreements may be
posted on the Transmission Provider’s To-Point Transmission Service because modified by the Commission.
OASIS (Section 4) is contained in of insufficient capability on its
Transmission System, the Transmission 15.7 Real Power Losses
Attachment C of the Tariff. In the event
sufficient transfer capability may not Provider will use due diligence to Real Power Losses are associated with
exist to accommodate a service request, provide redispatch from its own all transmission service. The
the Transmission Provider will respond resources until (i) Network Upgrades are Transmission Provider is not obligated
by performing a System Impact Study. completed for the Transmission to provide Real Power Losses. The
Customer, (ii) the Transmission Transmission Customer is responsible
15.3 Initiating Service in the Absence Provider determines through a biennial for replacing losses associated with all
of an Executed Service Agreement reassessment that it can no longer transmission service as calculated by
If the Transmission Provider and the reliably provide the redispatch, or (iii) the Transmission Provider. The
Transmission Customer requesting Firm the Transmission Customer terminates applicable Real Power Loss factors are
or Non-Firm Point-To-Point the service because of redispatch as follows: [To be completed by the
Transmission Service cannot agree on changes resulting from the Transmission Provider].
all the terms and conditions of the reassessment. A Transmission Provider
Point-To-Point Service Agreement, the shall not unreasonably deny self- 16 Transmission Customer
Transmission Provider shall file with provided redispatch or redispatch Responsibilities
the Commission, within thirty (30) days arranged by the Transmission Customer 16.1 Conditions Required of
after the date the Transmission from a third party resource. Transmission Customers
Customer provides written notification (c) If the Transmission Provider
directing the Transmission Provider to determines that it cannot accommodate Point-To-Point Transmission Service
file, an unexecuted Point-To-Point a Completed Application for Firm Point- shall be provided by the Transmission
Service Agreement containing terms and To-Point Transmission Service because Provider only if the following
conditions deemed appropriate by the of insufficient capability on its conditions are satisfied by the
Transmission Provider for such Transmission System, the Transmission Transmission Customer:
requested Transmission Service. The Provider will offer the Firm (a) The Transmission Customer has
Transmission Provider shall commence Transmission Service with the pending a Completed Application for
providing Transmission Service subject condition that the Transmission service;
to the Transmission Customer agreeing Provider may curtail the service prior to (b) The Transmission Customer meets
to (i) compensate the Transmission the curtailment of other Firm the creditworthiness criteria set forth in
Provider at whatever rate the Transmission Service for a specified Section 11;
Commission ultimately determines to be number of hours per year or during (c) The Transmission Customer will
just and reasonable, and (ii) comply System Condition(s). If the have arrangements in place for any
with the terms and conditions of the Transmission Customer accepts the other transmission service necessary to
Tariff including posting appropriate service, the Transmission Provider will effect the delivery from the generating
security deposits in accordance with the use due diligence to provide the service source to the Transmission Provider
terms of Section 17.3. until (i) Network Upgrades are prior to the time service under Part II of
completed for the Transmission the Tariff commences;
15.4 Obligation To Provide (d) The Transmission Customer agrees
Customer, (ii) the Transmission
Transmission Service That Requires to pay for any facilities constructed and
Provider determines through a biennial
Expansion or Modification of the chargeable to such Transmission
reassessment that it can no longer
Transmission System, Redispatch or Customer under Part II of the Tariff,
reliably provide such service, or (iii) the
Conditional Curtailment whether or not the Transmission
Transmission Customer terminates the
(a) If the Transmission Provider service because the reassessment Customer takes service for the full term
determines that it cannot accommodate increased the number of hours per year of its reservation;
a Completed Application for Firm Point- of conditional curtailment or changed (e) The Transmission Customer
To-Point Transmission Service because the System Conditions. provides the information required by
sroberts on PROD1PC70 with RULES

of insufficient capability on its the Transmission Provider’s planning


Transmission System, the Transmission 15.5 Deferral of Service process established in Attachment K;
Provider will use due diligence to The Transmission Provider may defer and
expand or modify its Transmission providing service until it completes (f) The Transmission Customer has
System to provide the requested Firm construction of new transmission executed a Point-To-Point Service

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00250 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12515

Agreement or has agreed to receive in 18 CFR 2.20 including but not limited service requests of less than one month.
service pursuant to Section 15.3. to the following: If the Application is rejected by the
(i) The identity, address, telephone Transmission Provider because it does
16.2 Transmission Customer number and facsimile number of the not meet the conditions for service as
Responsibility for Third-Party entity requesting service; set forth herein, or in the case of
Arrangements (ii) A statement that the entity requests for service arising in
Any scheduling arrangements that requesting service is, or will be upon connection with losing bidders in a
may be required by other electric commencement of service, an Eligible Request For Proposals (RFP), said
systems shall be the responsibility of the Customer under the Tariff; deposit shall be returned with interest
Transmission Customer requesting (iii) The location of the Point(s) of less any reasonable costs incurred by
service. The Transmission Customer Receipt and Point(s) of Delivery and the the Transmission Provider in
shall provide, unless waived by the identities of the Delivering Parties and connection with the review of the losing
Transmission Provider, notification to the Receiving Parties; bidder’s Application. The deposit also
the Transmission Provider identifying (iv) The location of the generating will be returned with interest less any
such systems and authorizing them to facility(ies) supplying the capacity and reasonable costs incurred by the
schedule the capacity and energy to be energy and the location of the load Transmission Provider if the
transmitted by the Transmission ultimately served by the capacity and Transmission Provider is unable to
Provider pursuant to Part II of the Tariff energy transmitted. The Transmission complete new facilities needed to
on behalf of the Receiving Party at the Provider will treat this information as provide the service. If an Application is
Point of Delivery or the Delivering Party confidential except to the extent that withdrawn or the Eligible Customer
at the Point of Receipt. However, the disclosure of this information is decides not to enter into a Service
Transmission Provider will undertake required by this Tariff, by regulatory or Agreement for Firm Point-To-Point
reasonable efforts to assist the judicial order, for reliability purposes Transmission Service, the deposit shall
Transmission Customer in making such pursuant to Good Utility Practice or be refunded in full, with interest, less
arrangements, including without pursuant to RTG transmission reasonable costs incurred by the
limitation, providing any information or information sharing agreements. The Transmission Provider to the extent
data required by such other electric Transmission Provider shall treat this such costs have not already been
system pursuant to Good Utility information consistent with the recovered by the Transmission Provider
Practice. standards of conduct contained in Part from the Eligible Customer. The
37 of the Commission’s regulations; Transmission Provider will provide to
17 Procedures for Arranging Firm (v) A description of the supply the Eligible Customer a complete
Point-To-Point Transmission Service characteristics of the capacity and accounting of all costs deducted from
17.1 Application energy to be delivered; the refunded deposit, which the Eligible
(vi) An estimate of the capacity and Customer may contest if there is a
A request for Firm Point-To-Point energy expected to be delivered to the dispute concerning the deducted costs.
Transmission Service for periods of one Receiving Party; Deposits associated with construction of
year or longer must contain a written (vii) The Service Commencement Date new facilities are subject to the
Application to: [Transmission Provider and the term of the requested provisions of Section 19. If a Service
Name and Address], at least sixty (60) Transmission Service; Agreement for Firm Point-To-Point
days in advance of the calendar month (viii) The transmission capacity Transmission Service is executed, the
in which service is to commence. The requested for each Point of Receipt and deposit, with interest, will be returned
Transmission Provider will consider each Point of Delivery on the to the Transmission Customer upon
requests for such firm service on shorter Transmission Provider’s Transmission expiration or termination of the Service
notice when feasible. Requests for firm System; customers may combine their Agreement for Firm Point-To-Point
service for periods of less than one year requests for service in order to satisfy Transmission Service. Applicable
shall be subject to expedited procedures the minimum transmission capacity interest shall be computed in
that shall be negotiated between the requirement; accordance with the Commission’s
Parties within the time constraints (ix) A statement indicating whether regulations at 18 CFR 35.19a(a)(2)(iii),
provided in Section 17.5. All Firm the Transmission Customer commits to and shall be calculated from the day the
Point-To-Point Transmission Service a Pre-Confirmed Request, i.e., will deposit check is credited to the
requests should be submitted by execute a Service Agreement upon Transmission Provider’s account.
entering the information listed below on receipt of notification that the
the Transmission Provider’s OASIS. 17.4 Notice of Deficient Application
Transmission Provider can provide the
Prior to implementation of the requested Transmission Service; and If an Application fails to meet the
Transmission Provider’s OASIS, a (x) Any additional information requirements of the Tariff, the
Completed Application may be required by the Transmission Provider’s Transmission Provider shall notify the
submitted by (i) transmitting the planning process established in entity requesting service within fifteen
required information to the Attachment K. (15) days of receipt of the reasons for
Transmission Provider by telefax, or (ii) The Transmission Provider shall treat such failure. The Transmission Provider
providing the information by telephone this information consistent with the will attempt to remedy minor
over the Transmission Provider’s time standards of conduct contained in Part deficiencies in the Application through
recorded telephone line. Each of these 37 of the Commission’s regulations. informal communications with the
methods will provide a time-stamped Eligible Customer. If such efforts are
17.3 Deposit unsuccessful, the Transmission Provider
record for establishing the priority of the
sroberts on PROD1PC70 with RULES

Application. A Completed Application for Firm shall return the Application, along with
Point-To-Point Transmission Service any deposit, with interest. Upon receipt
17.2 Completed Application also shall include a deposit of either one of a new or revised Application that
A Completed Application shall month’s charge for Reserved Capacity or fully complies with the requirements of
provide all of the information included the full charge for Reserved Capacity for Part II of the Tariff, the Eligible

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00251 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12516 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Customer shall be assigned a new then the Eligible Customer’s application properly evaluate system conditions, the
priority consistent with the date of the shall be deemed withdrawn and its Transmission Provider also may ask the
new or revised Application. deposit, pursuant to Section 17.3, shall Transmission Customer to provide the
be returned with interest. If during any following:
17.5 Response to a Completed (vi) The electrical location of the
extension for the commencement of
Application initial source of the power to be
service an Eligible Customer submits a
Following receipt of a Completed Completed Application for Firm transmitted pursuant to the
Application for Firm Point-To-Point Transmission Service, and such request Transmission Customer’s request for
Transmission Service, the Transmission can be satisfied only by releasing all or service; and
Provider shall make a determination of part of the Transmission Customer’s (vii) The electrical location of the
available transfer capability as required Reserved Capacity, the original ultimate load.
in Section 15.2. The Transmission Reserved Capacity will be released The Transmission Provider will treat
Provider shall notify the Eligible unless the following condition is this information in (vi) and (vii) as
Customer as soon as practicable, but not satisfied. Within thirty (30) days, the confidential at the request of the
later than thirty (30) days after the date original Transmission Customer agrees Transmission Customer except to the
of receipt of a Completed Application to pay the Firm Point-To-Point extent that disclosure of this
either (i) if it will be able to provide transmission rate for its Reserved information is required by this Tariff, by
service without performing a System Capacity concurrent with the new regulatory or judicial order, for
Impact Study or (ii) if such a study is Service Commencement Date. In the reliability purposes pursuant to Good
needed to evaluate the impact of the event the Transmission Customer elects Utility Practice, or pursuant to RTG
Application pursuant to Section 19.1. to release the Reserved Capacity, the transmission information sharing
Responses by the Transmission Provider reservation fees or portions thereof agreements. The Transmission Provider
must be made as soon as practicable to previously paid will be forfeited. shall treat this information consistent
all completed applications (including with the standards of conduct contained
applications by its own merchant 18 Procedures for Arranging Non-Firm in Part 37 of the Commission’s
function) and the timing of such Point-To-Point Transmission Service regulations.
responses must be made on a non- 18.1 Application (viii) A statement indicating whether
discriminatory basis. Eligible Customers seeking Non-Firm the Transmission Customer commits to
Point-To-Point Transmission Service a Pre-Confirmed Request, i.e., will
17.6 Execution of Service Agreement
must submit a Completed Application execute a Service Agreement upon
Whenever the Transmission Provider receipt of notification that the
to the Transmission Provider.
determines that a System Impact Study Transmission Provider can provide the
Applications should be submitted by
is not required and that the service can requested Transmission Service.
entering the information listed below on
be provided, it shall notify the Eligible
the Transmission Provider’s OASIS. 18.3 Reservation of Non-Firm Point-to-
Customer as soon as practicable but no
Prior to implementation of the Point Transmission Service
later than thirty (30) days after receipt
Transmission Provider’s OASIS, a
of the Completed Application. Where a Requests for monthly service shall be
Completed Application may be
System Impact Study is required, the submitted no earlier than sixty (60) days
submitted by (i) transmitting the
provisions of Section 19 will govern the before service is to commence; requests
required information to the
execution of a Service Agreement. for weekly service shall be submitted no
Transmission Provider by telefax, or (ii)
Failure of an Eligible Customer to earlier than fourteen (14) days before
providing the information by telephone
execute and return the Service service is to commence, requests for
over the Transmission Provider’s time
Agreement or request the filing of an daily service shall be submitted no
recorded telephone line. Each of these
unexecuted service agreement pursuant earlier than two (2) days before service
methods will provide a time-stamped
to Section 15.3, within fifteen (15) days is to commence, and requests for hourly
record for establishing the service
after it is tendered by the Transmission service shall be submitted no earlier
priority of the Application.
Provider will be deemed a withdrawal than noon the day before service is to
and termination of the Application and 18.2 Completed Application commence. Requests for service
any deposit submitted shall be refunded A Completed Application shall received later than 2 p.m. prior to the
with interest. Nothing herein limits the provide all of the information included day service is scheduled to commence
right of an Eligible Customer to file in 18 CFR 2.20 including but not limited will be accommodated if practicable [or
another Application after such to the following: such reasonable times that are generally
withdrawal and termination. (i) The identity, address, telephone accepted in the region and are
number and facsimile number of the consistently adhered to by the
17.7 Extensions for Commencement of
entity requesting service; Transmission Provider].
Service
(ii) A statement that the entity 18.4 Determination of Available
The Transmission Customer can requesting service is, or will be upon
obtain up to five (5) one-year extensions Transfer Capability
commencement of service, an Eligible
for the commencement of service. The Customer under the Tariff; Following receipt of a tendered
Transmission Customer may postpone (iii) The Point(s) of Receipt and the schedule the Transmission Provider will
service by paying a non-refundable Point(s) of Delivery; make a determination on a non-
annual reservation fee equal to one- (iv) The maximum amount of capacity discriminatory basis of available transfer
month’s charge for Firm Transmission requested at each Point of Receipt and capability pursuant to Section 15.2.
Service for each year or fraction thereof. Point of Delivery; and Such determination shall be made as
sroberts on PROD1PC70 with RULES

If the Eligible Customer does not pay (v) The proposed dates and hours for soon as reasonably practicable after
this non-refundable reservation fee initiating and terminating transmission receipt, but not later than the following
within 15 days of notifying the service hereunder. time periods for the following terms of
Transmission Provider it intends to In addition to the information service (i) thirty (30) minutes for hourly
extend the commencement of service, specified above, when required to service, (ii) thirty (30) minutes for daily

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00252 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12517

service, (iii) four (4) hours for weekly existing studies; however, the Eligible available to the Eligible Customer as
service, and (iv) two (2) days for Customer will be responsible for charges soon as the System Impact Study is
monthly service. [Or such reasonable associated with any modifications to complete. The Transmission Provider
times that are generally accepted in the existing planning studies that are will use the same due diligence in
region and are consistently adhered to reasonably necessary to evaluate the completing the System Impact Study for
by the Transmission Provider]. impact of the Eligible Customer’s an Eligible Customer as it uses when
request for service on the Transmission completing studies for itself. The
19 Additional Study Procedures for System. Transmission Provider shall notify the
Firm Point-to-Point Transmission (ii) If in response to multiple Eligible Eligible Customer immediately upon
Service Requests Customers requesting service in relation completion of the System Impact Study
19.1 Notice of Need for System Impact to the same competitive solicitation, a if the Transmission System will be
Study single System Impact Study is sufficient adequate to accommodate all or part of
for the Transmission Provider to a request for service or that no costs are
After receiving a request for service, accommodate the requests for service, likely to be incurred for new
the Transmission Provider shall the costs of that study shall be pro-rated transmission facilities or upgrades. In
determine on a non-discriminatory basis among the Eligible Customers. order for a request to remain a
whether a System Impact Study is (iii) For System Impact Studies that Completed Application, within fifteen
needed. A description of the the Transmission Provider conducts on (15) days of completion of the System
Transmission Provider’s methodology its own behalf, the Transmission Impact Study the Eligible Customer
for completing a System Impact Study is Provider shall record the cost of the must execute a Service Agreement or
provided in Attachment D. If the System Impact Studies pursuant to request the filing of an unexecuted
Transmission Provider determines that a Section 20. Service Agreement pursuant to Section
System Impact Study is necessary to 15.3, or the Application shall be deemed
accommodate the requested service, it 19.3 System Impact Study Procedures
terminated and withdrawn.
shall so inform the Eligible Customer, as Upon receipt of an executed System
soon as practicable. Once informed, the Impact Study Agreement, the 19.4 Facilities Study Procedures
Eligible Customer shall timely notify the Transmission Provider will use due If a System Impact Study indicates
Transmission Provider if it elects not to diligence to complete the required that additions or upgrades to the
have the Transmission Provider study System Impact Study within a sixty (60) Transmission System are needed to
redispatch or conditional curtailment as day period. The System Impact Study supply the Eligible Customer’s service
part of the System Impact Study. If shall identify (1) any system constraints, request, the Transmission Provider,
notification is provided prior to tender identified with specificity by within thirty (30) days of the
of the System Impact Study Agreement, transmission element or flowgate, (2) completion of the System Impact Study,
the Eligible Customer can avoid the redispatch options (when requested by shall tender to the Eligible Customer a
costs associated with the study of these a Transmission Customer) including an Facilities Study Agreement pursuant to
options. The Transmission Provider estimate of the cost of redispatch, (3) which the Eligible Customer shall agree
shall within thirty (30) days of receipt conditional curtailment options (when to reimburse the Transmission Provider
of a Completed Application, tender a requested by a Transmission Customer) for performing the required Facilities
System Impact Study Agreement including the number of hours per year Study. For a service request to remain
pursuant to which the Eligible Customer and the System Conditions during a Completed Application, the Eligible
shall agree to reimburse the which conditional curtailment may Customer shall execute the Facilities
Transmission Provider for performing occur, and (4) additional Direct Study Agreement and return it to the
the required System Impact Study. For Assignment Facilities or Network Transmission Provider within fifteen
a service request to remain a Completed Upgrades required to provide the (15) days. If the Eligible Customer elects
Application, the Eligible Customer shall requested service. For customers not to execute the Facilities Study
execute the System Impact Study requesting the study of redispatch Agreement, its application shall be
Agreement and return it to the options, the System Impact Study shall deemed withdrawn and its deposit,
Transmission Provider within fifteen (1) identify all resources located within pursuant to Section 17.3, shall be
(15) days. If the Eligible Customer elects the Transmission Provider’s Control returned with interest. Upon receipt of
not to execute the System Impact Study Area that can significantly contribute an executed Facilities Study Agreement,
Agreement, its application shall be toward relieving the system constraint the Transmission Provider will use due
deemed withdrawn and its deposit, and (2) provide a measurement of each diligence to complete the required
pursuant to Section 17.3, shall be resource’s impact on the system Facilities Study within a sixty (60) day
returned with interest. constraint. If the Transmission Provider period. If the Transmission Provider is
possesses information indicating that unable to complete the Facilities Study
19.2 System Impact Study Agreement any resource outside its Control Area in the allotted time period, the
and Cost Reimbursement could relieve the constraint, it shall Transmission Provider shall notify the
(i) The System Impact Study identify each such resource in the Transmission Customer and provide an
Agreement will clearly specify the System Impact Study. In the event that estimate of the time needed to reach a
Transmission Provider’s estimate of the the Transmission Provider is unable to final determination along with an
actual cost, and time for completion of complete the required System Impact explanation of the reasons that
the System Impact Study. The charge Study within such time period, it shall additional time is required to complete
shall not exceed the actual cost of the so notify the Eligible Customer and the study. When completed, the
study. In performing the System Impact provide an estimated completion date Facilities Study will include a good
sroberts on PROD1PC70 with RULES

Study, the Transmission Provider shall along with an explanation of the reasons faith estimate of (i) the cost of Direct
rely, to the extent reasonably why additional time is required to Assignment Facilities to be charged to
practicable, on existing transmission complete the required studies. A copy of the Transmission Customer, (ii) the
planning studies. The Eligible Customer the completed System Impact Study and Transmission Customer’s appropriate
will not be assessed a charge for such related work papers shall be made share of the cost of any required

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00253 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12518 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Network Upgrades as determined Point-To-Point Transmission Service deadlines, the Transmission Provider
pursuant to the provisions of Part II of that requires the addition of facilities or shall consider all System Impact Studies
the Tariff, and (iii) the time required to upgrades to the Transmission System and Facilities Studies that it completes
complete such construction and initiate until such facilities or upgrades have for non-Affiliates during the calendar
the requested service. The Transmission been placed in service. quarter. The percentage should be
Customer shall provide the calculated by dividing the number of
19.8 Expedited Procedures for New
Transmission Provider with a letter of those studies which are completed on
Facilities
credit or other reasonable form of time by the total number of completed
security acceptable to the Transmission In lieu of the procedures set forth studies. The Transmission Provider may
Provider equivalent to the costs of new above, the Eligible Customer shall have provide an explanation in its
facilities or upgrades consistent with the option to expedite the process by notification filing to the Commission if
commercial practices as established by requesting the Transmission Provider to it believes there are extenuating
the Uniform Commercial Code. The tender at one time, together with the circumstances that prevented it from
Transmission Customer shall have thirty results of required studies, an meeting the 60-day study completion
(30) days to execute a Service ‘‘Expedited Service Agreement’’ deadlines.
Agreement or request the filing of an pursuant to which the Eligible Customer (iii) The Transmission Provider is
unexecuted Service Agreement and would agree to compensate the subject to an operational penalty if it
provide the required letter of credit or Transmission Provider for all costs completes ten (10) percent or more of
other form of security or the request will incurred pursuant to the terms of the non-Affiliates’ System Impact Studies
no longer be a Completed Application Tariff. In order to exercise this option, and Facilities Studies outside of the 60-
and shall be deemed terminated and the Eligible Customer shall request in day study completion deadlines for each
withdrawn. writing an expedited Service Agreement of the two calendar quarters
covering all of the above-specified items immediately following the quarter that
19.5 Facilities Study Modifications within thirty (30) days of receiving the triggered its notification filing to the
Any change in design arising from results of the System Impact Study Commission. The operational penalty
inability to site or construct facilities as identifying needed facility additions or will be assessed for each calendar
proposed will require development of a upgrades or costs incurred in providing quarter for which an operational penalty
revised good faith estimate. New good the requested service. While the applies, starting with the calendar
faith estimates also will be required in Transmission Provider agrees to provide quarter immediately following the
the event of new statutory or regulatory the Eligible Customer with its best quarter that triggered the Transmission
requirements that are effective before estimate of the new facility costs and Provider’s notification filing to the
the completion of construction or other other charges that may be incurred, such Commission. The operational penalty
circumstances beyond the control of the estimate shall not be binding and the will continue to be assessed each
Transmission Provider that significantly Eligible Customer must agree in writing quarter until the Transmission Provider
affect the final cost of new facilities or to compensate the Transmission completes at least ninety (90) percent of
upgrades to be charged to the Provider for all costs incurred pursuant all non-Affiliates’ System Impact
Transmission Customer pursuant to the to the provisions of the Tariff. The Studies and Facilities Studies within
provisions of Part II of the Tariff. Eligible Customer shall execute and the 60-day deadline.
return such an Expedited Service (iv) For penalties assessed in
19.6 Due Diligence in Completing New
Agreement within fifteen (15) days of its accordance with subsection (iii) above,
Facilities
receipt or the Eligible Customer’s the penalty amount for each System
The Transmission Provider shall use request for service will cease to be a Impact Study or Facilities Study shall
due diligence to add necessary facilities Completed Application and will be be equal to $500 for each day the
or upgrade its Transmission System deemed terminated and withdrawn. Transmission Provider takes to
within a reasonable time. The
19.9 Penalties for Failure To Meet complete that study beyond the 60-day
Transmission Provider will not upgrade
Study Deadlines deadline.
its existing or planned Transmission
System in order to provide the Sections 19.3 and 19.4 require a 20 Procedures if the Transmission
requested Firm Point-To-Point Transmission Provider to use due Provider Is Unable To Complete New
Transmission Service if doing so would diligence to meet 60-day study Transmission Facilities for Firm Point-
impair system reliability or otherwise completion deadlines for System Impact to-Point Transmission Service
impair or degrade existing firm service. Studies and Facilities Studies.
(i) The Transmission Provider is 20.1 Delays in Construction of New
19.7 Partial Interim Service required to file a notice with the Facilities
If the Transmission Provider Commission in the event that more than If any event occurs that will
determines that it will not have twenty (20) percent of non-Affiliates’ materially affect the time for completion
adequate transfer capability to satisfy System Impact Studies and Facilities of new facilities, or the ability to
the full amount of a Completed Studies completed by the Transmission complete them, the Transmission
Application for Firm Point-To-Point Provider in any two consecutive Provider shall promptly notify the
Transmission Service, the Transmission calendar quarters are not completed Transmission Customer. In such
Provider nonetheless shall be obligated within the 60-day study completion circumstances, the Transmission
to offer and provide the portion of the deadlines. Such notice must be filed Provider shall within thirty (30) days of
requested Firm Point-To-Point within thirty (30) days of the end of the notifying the Transmission Customer of
Transmission Service that can be calendar quarter triggering the notice such delays, convene a technical
sroberts on PROD1PC70 with RULES

accommodated without addition of any requirement. meeting with the Transmission


facilities and through redispatch. (ii) For the purposes of calculating the Customer to evaluate the alternatives
However, the Transmission Provider percent of non-Affiliates’ System Impact available to the Transmission Customer.
shall not be obligated to provide the Studies and Facilities Studies processed The Transmission Provider also shall
incremental amount of requested Firm outside of the 60-day study completion make available to the Transmission

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00254 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12519

Customer studies and work papers for any necessary engineering, (a) Service provided over Secondary
related to the delay, including all permitting, and construction of Receipt and Delivery Points will be non-
information that is in the possession of transmission or distribution facilities on firm only, on an as-available basis and
the Transmission Provider that is the system(s) of any other entity or for will not displace any firm or non-firm
reasonably needed by the Transmission obtaining any regulatory approval for service reserved or scheduled by third-
Customer to evaluate any alternatives. such facilities. The Transmission parties under the Tariff or by the
Provider will undertake reasonable Transmission Provider on behalf of its
20.2 Alternatives to the Original
efforts to assist the Transmission Native Load Customers.
Facility Additions
Customer in obtaining such (b) The sum of all Firm and non-firm
When the review process of Section arrangements, including without Point-To-Point Transmission Service
20.1 determines that one or more limitation, providing any information or provided to the Transmission Customer
alternatives exist to the originally data required by such other electric at any time pursuant to this section
planned construction project, the system pursuant to Good Utility shall not exceed the Reserved Capacity
Transmission Provider shall present Practice. in the relevant Service Agreement under
such alternatives for consideration by which such services are provided.
the Transmission Customer. If, upon 21.2 Coordination of Third-Party
(c) The Transmission Customer shall
review of any alternatives, the System Additions
retain its right to schedule Firm Point-
Transmission Customer desires to In circumstances where the need for To-Point Transmission Service at the
maintain its Completed Application transmission facilities or upgrades is Receipt and Delivery Points specified in
subject to construction of the alternative identified pursuant to the provisions of the relevant Service Agreement in the
facilities, it may request the Part II of the Tariff, and if such upgrades amount of its original capacity
Transmission Provider to submit a further require the addition of reservation.
revised Service Agreement for Firm transmission facilities on other systems, (d) Service over Secondary Receipt
Point-To-Point Transmission Service. If the Transmission Provider shall have and Delivery Points on a non-firm basis
the alternative approach solely involves the right to coordinate construction on shall not require the filing of an
Non-Firm Point-To-Point Transmission its own system with the construction Application for Non-Firm Point-To-
Service, the Transmission Provider shall required by others. The Transmission Point Transmission Service under the
promptly tender a Service Agreement Provider, after consultation with the Tariff. However, all other requirements
for Non-Firm Point-To-Point Transmission Customer and of Part II of the Tariff (except as to
Transmission Service providing for the representatives of such other systems, transmission rates) shall apply to
service. In the event the Transmission may defer construction of its new transmission service on a non-firm basis
Provider concludes that no reasonable transmission facilities, if the new over Secondary Receipt and Delivery
alternative exists and the Transmission transmission facilities on another Points.
Customer disagrees, the Transmission system cannot be completed in a timely
manner. The Transmission Provider 22.2 Modification On a Firm Basis
Customer may seek relief under the
dispute resolution procedures pursuant shall notify the Transmission Customer Any request by a Transmission
to Section 12 or it may refer the dispute in writing of the basis for any decision Customer to modify Receipt and
to the Commission for resolution. to defer construction and the specific Delivery Points on a firm basis shall be
problems which must be resolved before treated as a new request for service in
20.3 Refund Obligation for Unfinished it will initiate or resume construction of accordance with Section 17 hereof,
Facility Additions new facilities. Within sixty (60) days of except that such Transmission Customer
If the Transmission Provider and the receiving written notification by the shall not be obligated to pay any
Transmission Customer mutually agree Transmission Provider of its intent to additional deposit if the capacity
that no other reasonable alternatives defer construction pursuant to this reservation does not exceed the amount
exist and the requested service cannot section, the Transmission Customer may reserved in the existing Service
be provided out of existing capability challenge the decision in accordance Agreement. While such new request is
under the conditions of Part II of the with the dispute resolution procedures pending, the Transmission Customer
Tariff, the obligation to provide the pursuant to Section 12 or it may refer shall retain its priority for service at the
requested Firm Point-To-Point the dispute to the Commission for existing firm Receipt and Delivery
Transmission Service shall terminate resolution. Points specified in its Service
and any deposit made by the Agreement.
22 Changes in Service Specifications
Transmission Customer shall be
23 Sale or Assignment of Transmission
returned with interest pursuant to 22.1 Modifications On a Non-Firm
Service
Commission regulations Basis
35.19a(a)(2)(iii). However, the The Transmission Customer taking 23.1 Procedures for Assignment or
Transmission Customer shall be Firm Point-To-Point Transmission Transfer of Service
responsible for all prudently incurred Service may request the Transmission Subject to Commission approval of
costs by the Transmission Provider Provider to provide transmission service any necessary filings, a Transmission
through the time construction was on a non-firm basis over Receipt and Customer may sell, assign, or transfer all
suspended. Delivery Points other than those or a portion of its rights under its
21 Provisions Relating to Transmission specified in the Service Agreement Service Agreement, but only to another
Construction and Services on the (‘‘Secondary Receipt and Delivery Eligible Customer (the Assignee). The
Systems of Other Utilities Points’’), in amounts not to exceed its Transmission Customer that sells,
sroberts on PROD1PC70 with RULES

firm capacity reservation, without assigns or transfers its rights under its
21.1 Responsibility for Third-Party incurring an additional Non-Firm Point- Service Agreement is hereafter referred
System Additions To-Point Transmission Service charge or to as the Reseller. Compensation to
The Transmission Provider shall not executing a new Service Agreement, Resellers shall be at rates established by
be responsible for making arrangements subject to the following conditions. agreement with the Assignee. The

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00255 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12520 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Assignee must execute a service 24 Metering and Power Factor Firm Point-To-Point Transmission
agreement with the Transmission Correction at Receipt and Delivery Service identifies the need for new
Provider prior to the date on which the Points(s) facilities, the Transmission Customer
reassigned service commences that will shall be responsible for such costs to the
24.1 Transmission Customer
govern the provision of reassigned extent consistent with Commission
Obligations policy. Whenever a System Impact
service. The Transmission Provider
shall credit or charge the Reseller, as Unless otherwise agreed, the Study performed by the Transmission
appropriate, for any differences between Transmission Customer shall be Provider identifies capacity constraints
the price reflected in the Assignee’s responsible for installing and that may be relieved by redispatching
Service Agreement and the Reseller’s maintaining compatible metering and the Transmission Provider’s resources to
Service Agreement with the communications equipment to eliminate such constraints, the
Transmission Provider. If the Assignee accurately account for the capacity and Transmission Customer shall be
does not request any change in the energy being transmitted under Part II of responsible for the redispatch costs to
Point(s) of Receipt or the Point(s) of the Tariff and to communicate the the extent consistent with Commission
Delivery, or a change in any other term information to the Transmission policy.
or condition set forth in the original Provider. Such equipment shall remain
III. Network Integration Transmission
Service Agreement, the Assignee will the property of the Transmission
Service
receive the same services as did the Customer.
Reseller and the priority of service for Preamble
24.2 Transmission Provider Access to
the Assignee will be the same as that of Metering Data The Transmission Provider will
the Reseller. The Assignee will be provide Network Integration
subject to all terms and conditions of The Transmission Provider shall have Transmission Service pursuant to the
this Tariff. If the Assignee requests a access to metering data, which may applicable terms and conditions
change in service, the reservation reasonably be required to facilitate contained in the Tariff and Service
priority of service will be determined by measurements and billing under the Agreement. Network Integration
the Transmission Provider pursuant to Service Agreement. Transmission Service allows the
Section 13.2. 24.3 Power Factor Network Customer to integrate,
23.2 Limitations on Assignment or economically dispatch and regulate its
Unless otherwise agreed, the
Transfer of Service current and planned Network Resources
Transmission Customer is required to
to serve its Network Load in a manner
maintain a power factor within the same
If the Assignee requests a change in comparable to that in which the
range as the Transmission Provider
the Point(s) of Receipt or Point(s) of Transmission Provider utilizes its
pursuant to Good Utility Practices. The
Delivery, or a change in any other Transmission System to serve its Native
power factor requirements are specified
specifications set forth in the original Load Customers. Network Integration
in the Service Agreement where
Service Agreement, the Transmission Transmission Service also may be used
applicable.
Provider will consent to such change by the Network Customer to deliver
subject to the provisions of the Tariff, 25 Compensation for Transmission economy energy purchases to its
provided that the change will not impair Service Network Load from non-designated
the operation and reliability of the Rates for Firm and Non-Firm Point- resources on an as-available basis
Transmission Provider’s generation, To-Point Transmission Service are without additional charge. Transmission
transmission, or distribution systems. provided in the Schedules appended to service for sales to non-designated loads
The Assignee shall compensate the the Tariff: Firm Point-To-Point will be provided pursuant to the
Transmission Provider for performing Transmission Service (Schedule 7); and applicable terms and conditions of Part
any System Impact Study needed to Non-Firm Point-To-Point Transmission II of the Tariff.
evaluate the capability of the Service (Schedule 8). The Transmission 28 Nature of Network Integration
Transmission System to accommodate Provider shall use Part II of the Tariff to Transmission Service
the proposed change and any additional make its Third-Party Sales. The
costs resulting from such change. The Transmission Provider shall account for 28.1 Scope of Service
Reseller shall remain liable for the such use at the applicable Tariff rates, Network Integration Transmission
performance of all obligations under the pursuant to Section 8. Service is a transmission service that
Service Agreement, except as allows Network Customers to efficiently
specifically agreed to by the 26 Stranded Cost Recovery and economically utilize their Network
Transmission Provider and the Reseller The Transmission Provider may seek Resources (as well as other non-
through an amendment to the Service to recover stranded costs from the designated generation resources) to
Agreement. Transmission Customer pursuant to this serve their Network Load located in the
23.3 Information on Assignment or Tariff in accordance with the terms, Transmission Provider’s Control Area
Transfer of Service conditions and procedures set forth in and any additional load that may be
FERC Order No. 888. However, the designated pursuant to Section 31.3 of
In accordance with Section 4, all sales Transmission Provider must separately the Tariff. The Network Customer taking
or assignments of capacity must be file any specific proposed stranded cost Network Integration Transmission
conducted through or otherwise posted charge under Section 205 of the Federal Service must obtain or provide
on the Transmission Provider’s OASIS Power Act. Ancillary Services pursuant to Section
on or before the date the reassigned 3.
27 Compensation for New Facilities
sroberts on PROD1PC70 with RULES

service commences and are subject to


Section 23.1. Resellers may also use the and Redispatch Costs 28.2 Transmission Provider
Transmission Provider’s OASIS to post Whenever a System Impact Study Responsibilities
transmission capacity available for performed by the Transmission Provider The Transmission Provider will plan,
resale. in connection with the provision of construct, operate and maintain its

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00256 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12521

Transmission System in accordance Network Customer is responsible for month in which service is to commence.
with Good Utility Practice and its replacing losses associated with all Unless subject to the procedures in
planning obligations in Attachment K in transmission service as calculated by Section 2, Completed Applications for
order to provide the Network Customer the Transmission Provider. The Network Integration Transmission
with Network Integration Transmission applicable Real Power Loss factors are Service will be assigned a priority
Service over the Transmission as follows: [To be completed by the according to the date and time the
Provider’s Transmission System. The Transmission Provider]. Application is received, with the
Transmission Provider, on behalf of its earliest Application receiving the
Native Load Customers, shall be 28.6 Restrictions on Use of Service highest priority. Applications should be
required to designate resources and The Network Customer shall not use submitted by entering the information
loads in the same manner as any Network Integration Transmission listed below on the Transmission
Network Customer under Part III of this Service for (i) sales of capacity and Provider’s OASIS. Prior to
Tariff. This information must be energy to non-designated loads, or (ii) implementation of the Transmission
consistent with the information used by direct or indirect provision of Provider’s OASIS, a Completed
the Transmission Provider to calculate transmission service by the Network Application may be submitted by (i)
available transfer capability. The Customer to third parties. All Network transmitting the required information to
Transmission Provider shall include the Customers taking Network Integration the Transmission Provider by telefax, or
Network Customer’s Network Load in Transmission Service shall use Point- (ii) providing the information by
its Transmission System planning and To-Point Transmission Service under telephone over the Transmission
shall, consistent with Good Utility Part II of the Tariff for any Third-Party Provider’s time recorded telephone line.
Practice and Attachment K, endeavor to Sale which requires use of the Each of these methods will provide a
construct and place into service Transmission Provider’s Transmission time-stamped record for establishing the
sufficient transfer capability to deliver System. The Transmission Provider service priority of the Application. A
the Network Customer’s Network shall specify any appropriate charges Completed Application shall provide all
Resources to serve its Network Load on and penalties and all related terms and of the information included in 18 CFR
a basis comparable to the Transmission conditions applicable in the event that 2.20 including but not limited to the
Provider’s delivery of its own generating a Network Customer uses Network following:
and purchased resources to its Native Integration Transmission Service or (i) The identity, address, telephone
Load Customers. secondary service pursuant to Section number and facsimile number of the
28.4 to facilitate a wholesale sale that party requesting service;
28.3 Network Integration Transmission (ii) A statement that the party
Service does not serve a Network Load.
requesting service is, or will be upon
The Transmission Provider will 29 Initiating Service commencement of service, an Eligible
provide firm transmission service over 29.1 Condition Precedent for Customer under the Tariff;
its Transmission System to the Network (iii) A description of the Network
Receiving Service
Customer for the delivery of capacity Load at each delivery point. This
and energy from its designated Network Subject to the terms and conditions of description should separately identify
Resources to service its Network Loads Part III of the Tariff, the Transmission and provide the Eligible Customer’s best
on a basis that is comparable to the Provider will provide Network estimate of the total loads to be served
Transmission Provider’s use of the Integration Transmission Service to any at each transmission voltage level, and
Transmission System to reliably serve Eligible Customer, provided that (i) the the loads to be served from each
its Native Load Customers. Eligible Customer completes an Transmission Provider substation at the
Application for service as provided same transmission voltage level. The
28.4 Secondary Service under Part III of the Tariff, (ii) the description should include a ten (10)
The Network Customer may use the Eligible Customer and the Transmission year forecast of summer and winter load
Transmission Provider’s Transmission Provider complete the technical and resource requirements beginning
System to deliver energy to its Network arrangements set forth in Sections 29.3 with the first year after the service is
Loads from resources that have not been and 29.4, (iii) the Eligible Customer scheduled to commence;
designated as Network Resources. Such executes a Service Agreement pursuant (iv) The amount and location of any
energy shall be transmitted, on an as- to Attachment F for service under Part interruptible loads included in the
available basis, at no additional charge. III of the Tariff or requests in writing Network Load. This shall include the
Secondary service shall not require the that the Transmission Provider file a summer and winter capacity
filing of an Application for Network proposed unexecuted Service requirements for each interruptible load
Integration Transmission Service under Agreement with the Commission, and (had such load not been interruptible),
the Tariff. However, all other (iv) the Eligible Customer executes a that portion of the load subject to
requirements of Part III of the Tariff Network Operating Agreement with the interruption, the conditions under
(except for transmission rates) shall Transmission Provider pursuant to which an interruption can be
apply to secondary service. Deliveries Attachment G, or requests in writing implemented and any limitations on the
from resources other than Network that the Transmission Provider file a amount and frequency of interruptions.
Resources will have a higher priority proposed unexecuted Network An Eligible Customer should identify
than any Non-Firm Point-To-Point Operating Agreement. the amount of interruptible customer
Transmission Service under Part II of load (if any) included in the 10 year
29.2 Application Procedures
the Tariff. load forecast provided in response to
An Eligible Customer requesting (iii) above;
28.5 Real Power Losses
sroberts on PROD1PC70 with RULES

service under Part III of the Tariff must (v) A description of Network
Real Power Losses are associated with submit an Application, with a deposit Resources (current and 10-year
all transmission service. The approximating the charge for one month projection). For each on-system Network
Transmission Provider is not obligated of service, to the Transmission Provider Resource, such description shall
to provide Real Power Losses. The as far as possible in advance of the include:

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00257 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12522 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

• Unit size and amount of capacity • Location of Network Resources in Part 37 of the Commission’s
from that unit to be designated as described in subsection (v) above regulations.
Network Resource • 10 year projection of system
29.3 Technical Arrangements to be
• VAR capability (both leading and expansions or upgrades
• Transmission System maps that Completed Prior to Commencement of
lagging) of all generators
• Operating restrictions include any proposed expansions or Service
—Any periods of restricted operations upgrades Network Integration Transmission
throughout the year • Thermal ratings of Eligible Service shall not commence until the
—Maintenance schedules Customer’s Control Area ties with other Transmission Provider and the Network
—Minimum loading level of unit Control Areas; Customer, or a third party, have
—Normal operating level of unit (vii) Service Commencement Date and completed installation of all equipment
—Any must-run unit designations the term of the requested Network specified under the Network Operating
required for system reliability or Integration Transmission Service. The Agreement consistent with Good Utility
contract reasons minimum term for Network Integration Practice and any additional
Transmission Service is one year; requirements reasonably and
• Approximate variable generating (viii) A statement signed by an
cost ($/MWH) for redispatch consistently imposed to ensure the
authorized officer from or agent of the reliable operation of the Transmission
computations Network Customer attesting that all of
• Arrangements governing sale and System. The Transmission Provider
the network resources listed pursuant to
delivery of power to third parties from shall exercise reasonable efforts, in
Section 29.2(v) satisfy the following
generating facilities located in the coordination with the Network
conditions:
Transmission Provider Control Area, (1) The Network Customer owns the Customer, to complete such
where only a portion of unit output is resource, has committed to purchase arrangements as soon as practicable
designated as a Network Resource; generation pursuant to an executed taking into consideration the Service
For each off-system Network contract, or has committed to purchase Commencement Date.
Resource, such description shall generation where execution of a contract 29.4 Network Customer Facilities
include: is contingent upon the availability of
• Identification of the Network The provision of Network Integration
transmission service under Part III of the
Resource as an off-system resource Transmission Service shall be
Tariff; and (2) the Network Resources do
• Amount of power to which the conditioned upon the Network
not include any resources, or any
customer has rights Customer’s constructing, maintaining
portion thereof, that are committed for
• Identification of the control area(s) and operating the facilities on its side of
sale to non-designated third party load
from which the power will originate each delivery point or interconnection
or otherwise cannot be called upon to
• Delivery point(s) to the necessary to reliably deliver capacity
meet the Network Customer’s Network
Transmission Provider’s Transmission and energy from the Transmission
Load on a non-interruptible basis; and
System (ix) Any additional information Provider’s Transmission System to the
• Transmission arrangements on the required of the Transmission Customer Network Customer. The Network
external transmission system(s) as specified in the Transmission Customer shall be solely responsible for
• Operating restrictions, if any Provider’s planning process established constructing or installing all facilities on
—Any periods of restricted operations in Attachment K. the Network Customer’s side of each
throughout the year Unless the Parties agree to a different such delivery point or interconnection.
—Maintenance schedules time frame, the Transmission Provider 29.5 Filing of Service Agreement
—Minimum loading level of unit must acknowledge the request within
—Normal operating level of unit ten (10) days of receipt. The The Transmission Provider will file
—Any must-run unit designations acknowledgement must include a date Service Agreements with the
required for system reliability or by which a response, including a Commission in compliance with
contract reasons Service Agreement, will be sent to the applicable Commission regulations.
• Approximate variable generating Eligible Customer. If an Application 30 Network Resources
cost ($/MWH) for redispatch fails to meet the requirements of this
section, the Transmission Provider shall 30.1 Designation of Network Resources
computations;
(vi) Description of Eligible Customer’s notify the Eligible Customer requesting Network Resources shall include all
transmission system: service within fifteen (15) days of generation owned, purchased or leased
• Load flow and stability data, such receipt and specify the reasons for such by the Network Customer designated to
as real and reactive parts of the load, failure. Wherever possible, the serve Network Load under the Tariff.
lines, transformers, reactive devices and Transmission Provider will attempt to Network Resources may not include
load type, including normal and remedy deficiencies in the Application resources, or any portion thereof, that
emergency ratings of all transmission through informal communications with are committed for sale to non-
equipment in a load flow format the Eligible Customer. If such efforts are designated third party load or otherwise
compatible with that used by the unsuccessful, the Transmission Provider cannot be called upon to meet the
Transmission Provider shall return the Application without Network Customer’s Network Load on a
• Operating restrictions needed for prejudice to the Eligible Customer filing non-interruptible basis. Any owned or
reliability a new or revised Application that fully purchased resources that were serving
• Operating guides employed by complies with the requirements of this the Network Customer’s loads under
system operators section. The Eligible Customer will be firm agreements entered into on or
sroberts on PROD1PC70 with RULES

• Contractual restrictions or assigned a new priority consistent with before the Service Commencement Date
committed uses of the Eligible the date of the new or revised shall initially be designated as Network
Customer’s transmission system, other Application. The Transmission Provider Resources until the Network Customer
than the Eligible Customer’s Network shall treat this information consistent terminates the designation of such
Loads and Resources with the standards of conduct contained resources.

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00258 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12523

30.2 Designation of New Network resource following the temporary the Network Resource’s designated
Resources termination, in accordance with Section capacity, excluding energy delivered
The Network Customer may designate 30.2; and using secondary service or Point-to-
a new Network Resource by providing (v) Identification of any related Point Transmission Service.
the Transmission Provider with as much transmission service requests to be
evaluated concomitantly with the 30.5 Network Customer Redispatch
advance notice as practicable. A Obligation
designation of a new Network Resource request for temporary termination, such
must be made through the Transmission that the requests for undesignation and As a condition to receiving Network
Provider’s OASIS by a request for the request for these related Integration Transmission Service, the
modification of service pursuant to an transmission service requests must be Network Customer agrees to redispatch
Application under Section 29. This approved or denied as a single request. its Network Resources as requested by
request must include a statement that The evaluation of these related the Transmission Provider pursuant to
the new network resource satisfies the transmission service requests must take Section 33.2. To the extent practical, the
following conditions: (1) the Network into account the termination of the redispatch of resources pursuant to this
Customer owns the resource, has network resources identified in (iii) section shall be on a least cost, non-
committed to purchase generation above, as well as all competing discriminatory basis between all
pursuant to an executed contract, or has transmission service requests of higher Network Customers, and the
committed to purchase generation priority. Transmission Provider.
As part of a temporary termination, a
where execution of a contract is 30.6 Transmission Arrangements for
Network Customer may only redesignate
contingent upon the availability of Network Resources Not Physically
the same resource that was originally
transmission service under Part III of the Interconnected With The Transmission
designated, or a portion thereof.
Tariff; and (2) The Network Resources Provider
Requests to redesignate a different
do not include any resources, or any
resource and/or a resource with The Network Customer shall be
portion thereof, that are committed for
increased capacity will be deemed responsible for any arrangements
sale to non-designated third party load
deficient and the Transmission Provider necessary to deliver capacity and energy
or otherwise cannot be called upon to
will follow the procedures for a from a Network Resource not physically
meet the Network Customer’s Network
deficient application as described in interconnected with the Transmission
Load on a non-interruptible basis. The
Section 29.2 of the Tariff. Provider’s Transmission System. The
Network Customer’s request will be
deemed deficient if it does not include 30.4 Operation of Network Resources Transmission Provider will undertake
this statement and the Transmission reasonable efforts to assist the Network
The Network Customer shall not Customer in obtaining such
Provider will follow the procedures for operate its designated Network
a deficient application as described in arrangements, including without
Resources located in the Network limitation, providing any information or
Section 29.2 of the Tariff. Customer’s or Transmission Provider’s data required by such other entity
30.3 Termination of Network Control Area such that the output of pursuant to Good Utility Practice.
Resources those facilities exceeds its designated
Network Load, plus Non-Firm Sales 30.7 Limitation on Designation of
The Network Customer may terminate Network Resources
delivered pursuant to Part II of the
the designation of all or part of a
Tariff, plus losses. This limitation shall The Network Customer must
generating resource as a Network
not apply to changes in the operation of demonstrate that it owns or has
Resource by providing notification to
a Transmission Customer’s Network committed to purchase generation
the Transmission Provider through
Resources at the request of the pursuant to an executed contract in
OASIS as soon as reasonably
Transmission Provider to respond to an order to designate a generating resource
practicable, but not later than the firm
emergency or other unforeseen as a Network Resource. Alternatively,
scheduling deadline for the period of
condition which may impair or degrade the Network Customer may establish
termination. Any request for
the reliability of the Transmission that execution of a contract is
termination of Network Resource status
System. For all Network Resources not contingent upon the availability of
must be submitted on OASIS, and
physically connected with the transmission service under Part III of the
should indicate whether the request is
Transmission Provider’s Transmission Tariff.
for indefinite or temporary termination.
System, the Network Customer may not
A request for indefinite termination of 30.8 Use of Interface Capacity by the
schedule delivery of energy in excess of
Network Resource status must indicate Network Customer
the date and time that the termination the Network Resource’s capacity, as
is to be effective, and the identification specified in the Network Customer’s There is no limitation upon a Network
and capacity of the resource(s) or Application pursuant to Section 29, Customer’s use of the Transmission
portions thereof to be indefinitely unless the Network Customer supports Provider’s Transmission System at any
terminated. A request for temporary such delivery within the Transmission particular interface to integrate the
termination of Network Resource status Provider’s Transmission System by Network Customer’s Network Resources
must include the following: either obtaining Point-to-Point (or substitute economy purchases) with
(i) Effective date and time of Transmission Service or utilizing its Network Loads. However, a Network
temporary termination; secondary service pursuant to Section Customer’s use of the Transmission
(ii) Effective date and time of 28.4. The Transmission Provider shall Provider’s total interface capacity with
redesignation, following period of specify the rate treatment and all related other transmission systems may not
temporary termination; terms and conditions applicable in the exceed the Network Customer’s Load.
sroberts on PROD1PC70 with RULES

(iii) Identification and capacity of event that a Network Customer’s


resource(s) or portions thereof to be schedule at the delivery point for a 30.9 Network Customer Owned
temporarily terminated; Network Resource not physically Transmission Facilities
(iv) Resource description and interconnected with the Transmission The Network Customer that owns
attestation for redesignating the network Provider’s Transmission System exceeds existing transmission facilities that are

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00259 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12524 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

integrated with the Transmission 31.3 Network Load Not Physically limited to, any information provided
Provider’s Transmission System may be Interconnected With the Transmission under section 29.2(ix) pursuant to the
eligible to receive consideration either Provider Transmission Provider’s planning
through a billing credit or some other This section applies to both initial process in Attachment K. The Network
mechanism. In order to receive such designation pursuant to Section 31.1 Customer also shall provide the
consideration the Network Customer and the subsequent addition of new Transmission Provider with timely
must demonstrate that its transmission Network Load not physically written notice of material changes in
facilities are integrated into the plans or interconnected with the Transmission any other information provided in its
operations of the Transmission Provider. To the extent that the Network Application relating to the Network
Provider, to serve its power and Customer desires to obtain transmission Customer’s Network Load, Network
transmission customers. For facilities service for a load outside the Resources, its transmission system or
added by the Network Customer Transmission Provider’s Transmission other aspects of its facilities or
System, the Network Customer shall operations affecting the Transmission
subsequent to the [the effective date of
have the option of (1) electing to include Provider’s ability to provide reliable
a Final Rule in RM05–25–000], the
the entire load as Network Load for all service.
Network Customer shall receive credit
for such transmission facilities added if purposes under Part III of the Tariff and 32 Additional Study Procedures for
designating Network Resources in Network Integration Transmission
such facilities are integrated into the
connection with such additional Service Requests
operations of the Transmission
Network Load, or (2) excluding that
Provider’s facilities; provided however, entire load from its Network Load and 32.1 Notice of Need for System Impact
the Network Customer’s transmission purchasing Point-To-Point Transmission Study
facilities shall be presumed to be Service under Part II of the Tariff. To the After receiving a request for service,
integrated if such transmission facilities, extent that the Network Customer gives the Transmission Provider shall
if owned by the Transmission Provider, notice of its intent to add a new determine on a non-discriminatory basis
would be eligible for inclusion in the Network Load as part of its Network whether a System Impact Study is
Transmission Provider’s annual Load pursuant to this section the needed. A description of the
transmission revenue requirement as request must be made through a Transmission Provider’s methodology
specified in Attachment H. Calculation modification of service pursuant to a for completing a System Impact Study is
of any credit under this subsection shall new Application. provided in Attachment D. If the
be addressed in either the Network 31.4 New Interconnection Points Transmission Provider determines that a
Customer’s Service Agreement or any System Impact Study is necessary to
other agreement between the Parties. To the extent the Network Customer
accommodate the requested service, it
desires to add a new Delivery Point or
31 Designation of Network Load shall so inform the Eligible Customer, as
interconnection point between the
soon as practicable. In such cases, the
Transmission Provider’s Transmission
31.1 Network Load Transmission Provider shall within
System and a Network Load, the
thirty (30) days of receipt of a
The Network Customer must Network Customer shall provide the
Transmission Provider with as much Completed Application, tender a System
designate the individual Network Loads Impact Study Agreement pursuant to
on whose behalf the Transmission advance notice as reasonably
practicable. which the Eligible Customer shall agree
Provider will provide Network to reimburse the Transmission Provider
Integration Transmission Service. The 31.5 Changes in Service Requests for performing the required System
Network Loads shall be specified in the Under no circumstances shall the Impact Study. For a service request to
Service Agreement. Network Customer’s decision to cancel remain a Completed Application, the
or delay a requested change in Network Eligible Customer shall execute the
31.2 New Network Loads Connected
Integration Transmission Service (e.g. System Impact Study Agreement and
With the Transmission Provider return it to the Transmission Provider
the addition of a new Network Resource
The Network Customer shall provide or designation of a new Network Load) within fifteen (15) days. If the Eligible
the Transmission Provider with as much in any way relieve the Network Customer elects not to execute the
advance notice as reasonably practicable Customer of its obligation to pay the System Impact Study Agreement, its
of the designation of new Network Load costs of transmission facilities Application shall be deemed withdrawn
constructed by the Transmission and its deposit shall be returned with
that will be added to its Transmission
Provider and charged to the Network interest.
System. A designation of new Network
Load must be made through a Customer as reflected in the Service 32.2 System Impact Study Agreement
Agreement. However, the Transmission and Cost Reimbursement
modification of service pursuant to a
Provider must treat any requested
new Application. The Transmission (i) The System Impact Study
change in Network Integration
Provider will use due diligence to Transmission Service in a non- Agreement will clearly specify the
install any transmission facilities discriminatory manner. Transmission Provider’s estimate of the
required to interconnect a new Network actual cost, and time for completion of
Load designated by the Network 31.6 Annual Load and Resource the System Impact Study. The charge
Customer. The costs of new facilities Information Updates shall not exceed the actual cost of the
required to interconnect a new Network The Network Customer shall provide study. In performing the System Impact
Load shall be determined in accordance the Transmission Provider with annual Study, the Transmission Provider shall
sroberts on PROD1PC70 with RULES

with the procedures provided in Section updates of Network Load and Network rely, to the extent reasonably
32.4 and shall be charged to the Resource forecasts consistent with those practicable, on existing transmission
Network Customer in accordance with included in its Application for Network planning studies. The Eligible Customer
Commission policies. Integration Transmission Service under will not be assessed a charge for such
Part III of the Tariff including, but not existing studies; however, the Eligible

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00260 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12525

Customer will be responsible for charges 32.4 Facilities Study Procedures deadlines for System Impact Studies
associated with any modifications to If a System Impact Study indicates and Facilities Studies under Part II of
existing planning studies that are that additions or upgrades to the the Tariff. These same requirements and
reasonably necessary to evaluate the Transmission System are needed to penalties apply to service under Part III
impact of the Eligible Customer’s supply the Eligible Customer’s service of the Tariff.
request for service on the Transmission request, the Transmission Provider, 33 Load Shedding and Curtailments
System. within thirty (30) days of the
(ii) If in response to multiple Eligible completion of the System Impact Study, 33.1 Procedures
Customers requesting service in relation shall tender to the Eligible Customer a Prior to the Service Commencement
to the same competitive solicitation, a Facilities Study Agreement pursuant to Date, the Transmission Provider and the
single System Impact Study is sufficient which the Eligible Customer shall agree Network Customer shall establish Load
for the Transmission Provider to to reimburse the Transmission Provider Shedding and Curtailment procedures
accommodate the service requests, the for performing the required Facilities pursuant to the Network Operating
costs of that study shall be pro-rated Study. For a service request to remain Agreement with the objective of
among the Eligible Customers. a Completed Application, the Eligible responding to contingencies on the
(iii) For System Impact Studies that Customer shall execute the Facilities Transmission System and on systems
the Transmission Provider conducts on Study Agreement and return it to the directly and indirectly interconnected
its own behalf, the Transmission Transmission Provider within fifteen with Transmission Provider’s
Provider shall record the cost of the (15) days. If the Eligible Customer elects Transmission System. The Parties will
System Impact Studies pursuant to not to execute the Facilities Study implement such programs during any
Section 8. Agreement, its Application shall be period when the Transmission Provider
32.3 System Impact Study Procedures deemed withdrawn and its deposit shall determines that a system contingency
be returned with interest. Upon receipt exists and such procedures are
Upon receipt of an executed System of an executed Facilities Study necessary to alleviate such contingency.
Impact Study Agreement, the Agreement, the Transmission Provider The Transmission Provider will notify
Transmission Provider will use due will use due diligence to complete the all affected Network Customers in a
diligence to complete the required required Facilities Study within a sixty timely manner of any scheduled
System Impact Study within a sixty (60) (60) day period. If the Transmission Curtailment.
day period. The System Impact Study Provider is unable to complete the
shall identify any system constraints 33.2 Transmission Constraints
Facilities Study in the allotted time
and redispatch options, additional period, the Transmission Provider shall During any period when the
Direct Assignment Facilities or Network notify the Eligible Customer and Transmission Provider determines that a
Upgrades required to provide the provide an estimate of the time needed transmission constraint exists on the
requested service. In the event that the to reach a final determination along Transmission System, and such
Transmission Provider is unable to with an explanation of the reasons that constraint may impair the reliability of
complete the required System Impact additional time is required to complete the Transmission Provider’s system, the
Study within such time period, it shall the study. When completed, the Transmission Provider will take
so notify the Eligible Customer and Facilities Study will include a good whatever actions, consistent with Good
provide an estimated completion date faith estimate of (i) the cost of Direct Utility Practice, that are reasonably
along with an explanation of the reasons Assignment Facilities to be charged to necessary to maintain the reliability of
why additional time is required to the Eligible Customer, (ii) the Eligible the Transmission Provider’s system. To
complete the required studies. A copy of Customer’s appropriate share of the cost the extent the Transmission Provider
the completed System Impact Study and of any required Network Upgrades, and determines that the reliability of the
related work papers shall be made (iii) the time required to complete such Transmission System can be maintained
available to the Eligible Customer as construction and initiate the requested by redispatching resources, the
soon as the System Impact Study is service. The Eligible Customer shall Transmission Provider will initiate
complete. The Transmission Provider provide the Transmission Provider with procedures pursuant to the Network
will use the same due diligence in a letter of credit or other reasonable Operating Agreement to redispatch all
completing the System Impact Study for form of security acceptable to the Network Resources and the
an Eligible Customer as it uses when Transmission Provider equivalent to the Transmission Provider’s own resources
completing studies for itself. The costs of new facilities or upgrades on a least-cost basis without regard to
Transmission Provider shall notify the consistent with commercial practices as the ownership of such resources. Any
Eligible Customer immediately upon established by the Uniform Commercial redispatch under this section may not
completion of the System Impact Study Code. The Eligible Customer shall have unduly discriminate between the
if the Transmission System will be thirty (30) days to execute a Service Transmission Provider’s use of the
adequate to accommodate all or part of Agreement or request the filing of an Transmission System on behalf of its
a request for service or that no costs are unexecuted Service Agreement and Native Load Customers and any
likely to be incurred for new provide the required letter of credit or Network Customer’s use of the
transmission facilities or upgrades. In other form of security or the request no Transmission System to serve its
order for a request to remain a longer will be a Completed Application designated Network Load.
Completed Application, within fifteen and shall be deemed terminated and
(15) days of completion of the System 33.3 Cost Responsibility for Relieving
withdrawn. Transmission Constraints
Impact Study the Eligible Customer
32.5 Penalties for Failure To Meet
sroberts on PROD1PC70 with RULES

must execute a Service Agreement or Whenever the Transmission Provider


request the filing of an unexecuted Study Deadlines implements least-cost redispatch
Service Agreement, or the Application Section 19.9 defines penalties that procedures in response to a
shall be deemed terminated and apply for failure to meet the 60-day transmission constraint, the
withdrawn. study completion due diligence Transmission Provider and Network

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00261 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12526 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

Customers will each bear a Transmission Provider’s Transmission 34.4 Redispatch Charge
proportionate share of the total System, the Transmission Provider, The Network Customer shall pay a
redispatch cost based on their respective consistent with Good Utility Practice, Load Ratio Share of any redispatch costs
Load Ratio Shares. also may Curtail Network Integration allocated between the Network
Transmission Service in order to (i) Customer and the Transmission
33.4 Curtailments of Scheduled
limit the extent or damage of the Provider pursuant to Section 33. To the
Deliveries
adverse condition(s) or disturbance(s), extent that the Transmission Provider
If a transmission constraint on the (ii) prevent damage to generating or incurs an obligation to the Network
Transmission Provider’s Transmission transmission facilities, or (iii) expedite Customer for redispatch costs in
System cannot be relieved through the restoration of service. The Transmission accordance with Section 33, such
implementation of least-cost redispatch Provider will give the Network amounts shall be credited against the
procedures and the Transmission Customer as much advance notice as is Network Customer’s bill for the
Provider determines that it is necessary practicable in the event of such applicable month.
to Curtail scheduled deliveries, the Curtailment. Any Curtailment of
Parties shall Curtail such schedules in Network Integration Transmission 34.5 Stranded Cost Recovery
accordance with the Network Operating Service will be not unduly The Transmission Provider may seek
Agreement or pursuant to the discriminatory relative to the to recover stranded costs from the
Transmission Loading Relief procedures Transmission Provider’s use of the Network Customer pursuant to this
specified in Attachment J. Transmission System on behalf of its Tariff in accordance with the terms,
33.5 Allocation of Curtailments Native Load Customers. The conditions and procedures set forth in
Transmission Provider shall specify the FERC Order No. 888. However, the
The Transmission Provider shall, on a rate treatment and all related terms and Transmission Provider must separately
non-discriminatory basis, Curtail the conditions applicable in the event that file any proposal to recover stranded
transaction(s) that effectively relieve the the Network Customer fails to respond costs under Section 205 of the Federal
constraint. However, to the extent to established Load Shedding and Power Act.
practicable and consistent with Good Curtailment procedures.
Utility Practice, any Curtailment will be 35 Operating Arrangements
shared by the Transmission Provider 34 Rates and Charges
35.1 Operation Under the Network
and Network Customer in proportion to The Network Customer shall pay the Operating Agreement
their respective Load Ratio Shares. The Transmission Provider for any Direct
Transmission Provider shall not direct The Network Customer shall plan,
Assignment Facilities, Ancillary construct, operate and maintain its
the Network Customer to Curtail Services, and applicable study costs,
schedules to an extent greater than the facilities in accordance with Good
consistent with Commission policy, Utility Practice and in conformance
Transmission Provider would Curtail along with the following:
the Transmission Provider’s schedules with the Network Operating Agreement.
under similar circumstances. 34.1 Monthly Demand Charge 35.2 Network Operating Agreement
33.6 Load Shedding The Network Customer shall pay a The terms and conditions under
To the extent that a system monthly Demand Charge, which shall which the Network Customer shall
contingency exists on the Transmission be determined by multiplying its Load operate its facilities and the technical
Provider’s Transmission System and the Ratio Share times one twelfth (1⁄12) of and operational matters associated with
Transmission Provider determines that the Transmission Provider’s Annual the implementation of Part III of the
it is necessary for the Transmission Transmission Revenue Requirement Tariff shall be specified in the Network
Provider and the Network Customer to specified in Schedule H. Operating Agreement. The Network
shed load, the Parties shall shed load in 34.2 Determination of Network Operating Agreement shall provide for
accordance with previously established Customer’s Monthly Network Load the Parties to (i) operate and maintain
procedures under the Network equipment necessary for integrating the
Operating Agreement. The Network Customer’s monthly Network Customer within the
Network Load is its hourly load Transmission Provider’s Transmission
33.7 System Reliability (including its designated Network Load System (including, but not limited to,
Notwithstanding any other provisions not physically interconnected with the remote terminal units, metering,
of this Tariff, the Transmission Provider Transmission Provider under Section communications equipment and
reserves the right, consistent with Good 31.3) coincident with the Transmission relaying equipment), (ii) transfer data
Utility Practice and on a not unduly Provider’s Monthly Transmission between the Transmission Provider and
discriminatory basis, to Curtail Network System Peak. the Network Customer (including, but
Integration Transmission Service not limited to, heat rates and
34.3 Determination of Transmission
without liability on the Transmission operational characteristics of Network
Provider’s Monthly Transmission
Provider’s part for the purpose of Resources, generation schedules for
System Load
making necessary adjustments to, units outside the Transmission
changes in, or repairs on its lines, The Transmission Provider’s monthly Provider’s Transmission System,
substations and facilities, and in cases Transmission System load is the interchange schedules, unit outputs for
where the continuance of Network Transmission Provider’s Monthly redispatch required under Section 33,
Integration Transmission Service would Transmission System Peak minus the voltage schedules, loss factors and other
endanger persons or property. In the coincident peak usage of all Firm Point- real time data), (iii) use software
sroberts on PROD1PC70 with RULES

event of any adverse condition(s) or To-Point Transmission Service programs required for data links and
disturbance(s) on the Transmission customers pursuant to Part II of this constraint dispatching, (iv) exchange
Provider’s Transmission System or on Tariff plus the Reserved Capacity of all data on forecasted loads and resources
any other system(s) directly or Firm Point-To-Point Transmission necessary for long-term planning, and
indirectly interconnected with the Service customers. (v) address any other technical and

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00262 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12527

operational considerations required for Schedule 2—Reactive Supply and The obligation to maintain this balance
implementation of Part III of the Tariff, Voltage Control From Generation or between resources and load lies with
including scheduling protocols. The Other Sources Service the Transmission Provider (or the
Network Operating Agreement will In order to maintain transmission Control Area operator that performs this
recognize that the Network Customer voltages on the Transmission Provider’s function for the Transmission Provider).
shall either (i) operate as a Control Area transmission facilities within acceptable The Transmission Provider must offer
under applicable guidelines of the limits, generation facilities and non- this service when the transmission
Electric Reliability Organization (ERO) generation resources capable of service is used to serve load within its
as defined in 18 CFR 39.1, (ii) satisfy its providing this service that are under the Control Area. The Transmission
Control Area requirements, including all Customer must either purchase this
control of the control area operator are
necessary Ancillary Services, by service from the Transmission Provider
operated to produce (or absorb) reactive
contracting with the Transmission or make alternative comparable
power. Thus, Reactive Supply and
Provider, or (iii) satisfy its Control Area arrangements to satisfy its Regulation
Voltage Control from Generation or
requirements, including all necessary and Frequency Response Service
Other Sources Service must be provided
Ancillary Services, by contracting with obligation. The amount of and charges
for each transaction on the
another entity, consistent with Good for Regulation and Frequency Response
Transmission Provider’s transmission
Utility Practice, which satisfies the Service are set forth below. To the
facilities. The amount of Reactive
applicable reliability guidelines of the extent the Control Area operator
Supply and Voltage Control from
ERO. The Transmission Provider shall performs this service for the
Generation or Other Sources Service Transmission Provider, charges to the
not unreasonably refuse to accept that must be supplied with respect to
contractual arrangements with another Transmission Customer are to reflect
the Transmission Customer’s only a pass-through of the costs charged
entity for Ancillary Services. The transaction will be determined based on
Network Operating Agreement is to the Transmission Provider by that
the reactive power support necessary to Control Area operator.
included in Attachment G. maintain transmission voltages within
35.3 Network Operating Committee limits that are generally accepted in the Schedule 4—Energy Imbalance Service
region and consistently adhered to by Energy Imbalance Service is provided
A Network Operating Committee the Transmission Provider. when a difference occurs between the
(Committee) shall be established to Reactive Supply and Voltage Control scheduled and the actual delivery of
coordinate operating criteria for the from Generation or Other Sources energy to a load located within a
Parties’ respective responsibilities under Service is to be provided directly by the Control Area over a single hour. The
the Network Operating Agreement. Each Transmission Provider (if the Transmission Provider must offer this
Network Customer shall be entitled to Transmission Provider is the Control service when the transmission service is
have at least one representative on the Area operator) or indirectly by the used to serve load within its Control
Committee. The Committee shall meet Transmission Provider making Area. The Transmission Customer must
from time to time as need requires, but arrangements with the Control Area either purchase this service from the
no less than once each calendar year. operator that performs this service for Transmission Provider or make
Schedule 1—Scheduling, System the Transmission Provider’s alternative comparable arrangements,
Control and Dispatch Service Transmission System. The Transmission which may include use of non-
Customer must purchase this service generation resources capable of
This service is required to schedule from the Transmission Provider or the providing this service, to satisfy its
the movement of power through, out of, Control Area operator. The charges for Energy Imbalance Service obligation. To
within, or into a Control Area. This such service will be based on the rates the extent the Control Area operator
service can be provided only by the set forth below. To the extent the performs this service for the
operator of the Control Area in which Control Area operator performs this Transmission Provider, charges to the
the transmission facilities used for service for the Transmission Provider, Transmission Customer are to reflect
transmission service are located. charges to the Transmission Customer only a pass-through of the costs charged
Scheduling, System Control and are to reflect only a pass-through of the to the Transmission Provider by that
Dispatch Service is to be provided costs charged to the Transmission Control Area operator. The
directly by the Transmission Provider (if Provider by the Control Area operator. Transmission Provider may charge a
the Transmission Provider is the Control Transmission Customer a penalty for
Area operator) or indirectly by the Schedule 3—Regulation and Frequency
either hourly generator imbalances
Transmission Provider making Response Service
under Schedule 9 or hourly energy
arrangements with the Control Area Regulation and Frequency Response imbalances under this Schedule for the
operator that performs this service for Service is necessary to provide for the same imbalance, but not both.
the Transmission Provider’s continuous balancing of resources The Transmission Provider shall
Transmission System. The Transmission (generation and interchange) with load establish charges for energy imbalance
Customer must purchase this service and for maintaining scheduled based on the deviation bands as follows:
from the Transmission Provider or the Interconnection frequency at sixty (i) Deviations within +/¥1.5 percent
Control Area operator. The charges for cycles per second (60 Hz). Regulation (with a minimum of 2 MW) of the
Scheduling, System Control and and Frequency Response Service is scheduled transaction to be applied
Dispatch Service are to be based on the accomplished by committing on-line hourly to any energy imbalance that
rates set forth below. To the extent the generation whose output is raised or occurs as a result of the Transmission
Control Area operator performs this lowered (predominantly through the use Customer’s scheduled transaction(s)
sroberts on PROD1PC70 with RULES

service for the Transmission Provider, of automatic generating control will be netted on a monthly basis and
charges to the Transmission Customer equipment) and by other non-generation settled financially, at the end of the
are to reflect only a pass-through of the resources capable of providing this month, at 100 percent of incremental or
costs charged to the Transmission service as necessary to follow the decremental cost; (ii) deviations greater
Provider by that Control Area operator. moment-by-moment changes in load. than +/¥1.5 percent up to 7.5 percent

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00263 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12528 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

(or greater than 2 MW up to 10 MW) of other non-generation resources capable Schedule 8—Non-Firm Point-To-Point
the scheduled transaction to be applied of providing this service. The Transmission Service
hourly to any energy imbalance that Transmission Provider must offer this The Transmission Customer shall
occurs as a result of the Transmission service when the transmission service is compensate the Transmission Provider
Customer’s scheduled transaction(s) used to serve load within its Control for Non-Firm Point-To-Point
will be settled financially, at the end of Area. The Transmission Customer must Transmission Service up to the sum of
each month, at 110 percent of either purchase this service from the the applicable charges set forth below:
incremental cost or 90 percent of Transmission Provider or make (1) Monthly delivery: $ll/KW of
decremental cost, and (iii) deviations alternative comparable arrangements to Reserved Capacity per month.
greater than +/¥7.5 percent (or 10 MW) satisfy its Supplemental Reserve Service (2) Weekly delivery: $ll/KW of
of the scheduled transaction to be obligation. The amount of and charges Reserved Capacity per week.
applied hourly to any energy imbalance for Supplemental Reserve Service are (3) Daily delivery: $ll/KW of
that occurs as a result of the set forth below. To the extent the Reserved Capacity per day.
Transmission Customer’s scheduled Control Area operator performs this The total demand charge in any week,
transaction(s) will be settled financially, service for the Transmission Provider, pursuant to a reservation for Daily
at the end of each month, at 125 percent charges to the Transmission Customer delivery, shall not exceed the rate
of incremental cost or 75 percent of are to reflect only a pass-through of the specified in section (2) above times the
decremental cost. costs charged to the Transmission highest amount in kilowatts of Reserved
For purposes of this Schedule, incremental Provider by that Control Area operator. Capacity in any day during such week.
cost and decremental cost represent the (4) Hourly delivery: The basic charge
Transmission Provider’s actual average Schedule 7—Long-Term Firm and
hourly cost of the last 10 MW dispatched to Short-Term Firm Point-To-Point shall be that agreed upon by the Parties
supply the Transmission Provider’s Native Transmission Service at the time this service is reserved and
Load Customers, based on the replacement in no event shall exceed $ll/MWH.
cost of fuel, unit heat rates, start-up costs The Transmission Customer shall The total demand charge in any day,
(including any commitment and redispatch compensate the Transmission Provider pursuant to a reservation for Hourly
costs), incremental operation and each month for Reserved Capacity at the delivery, shall not exceed the rate
maintenance costs, and purchased and sum of the applicable charges set forth specified in section (3) above times the
interchange power costs and taxes, as below: highest amount in kilowatts of Reserved
applicable.
(1) Yearly delivery: one-twelfth of the Capacity in any hour during such day.
Schedule 5—Operating Reserve— demand charge of $ll/KW of In addition, the total demand charge in
Spinning Reserve Service Reserved Capacity per year. any week, pursuant to a reservation for
Spinning Reserve Service is needed to Hourly or Daily delivery, shall not
(2) Monthly delivery: $ll/KW of exceed the rate specified in section (2)
serve load immediately in the event of Reserved Capacity per month.
a system contingency. Spinning Reserve above times the highest amount in
Service may be provided by generating (3) Weekly delivery: $ll/KW of kilowatts of Reserved Capacity in any
units that are on-line and loaded at less Reserved Capacity per week. hour during such week.
than maximum output and by non- (4) Daily delivery: $ll/KW of (5) Discounts: Three principal
generation resources capable of Reserved Capacity per day. requirements apply to discounts for
providing this service. The transmission service as follows (1) any
The total demand charge in any week, offer of a discount made by the
Transmission Provider must offer this pursuant to a reservation for Daily
service when the transmission service is Transmission Provider must be
delivery, shall not exceed the rate announced to all Eligible Customers
used to serve load within its Control specified in section (3) above times the
Area. The Transmission Customer must solely by posting on the OASIS, (2) any
highest amount in kilowatts of Reserved customer-initiated requests for
either purchase this service from the Capacity in any day during such week.
Transmission Provider or make discounts (including requests for use by
alternative comparable arrangements to (5) Discounts: Three principal one’s wholesale merchant or an
satisfy its Spinning Reserve Service requirements apply to discounts for affiliate’s use) must occur solely by
obligation. The amount of and charges transmission service as follows (1) any posting on the OASIS, and (3) once a
for Spinning Reserve Service are set offer of a discount made by the discount is negotiated, details must be
forth below. To the extent the Control Transmission Provider must be immediately posted on the OASIS. For
Area operator performs this service for announced to all Eligible Customers any discount agreed upon for service on
the Transmission Provider, charges to solely by posting on the OASIS, (2) any a path, from point(s) of receipt to
the Transmission Customer are to reflect customer-initiated requests for point(s) of delivery, the Transmission
only a pass-through of the costs charged discounts (including requests for use by Provider must offer the same discounted
to the Transmission Provider by that one’s wholesale merchant or an transmission service rate for the same
Control Area operator. affiliate’s use) must occur solely by time period to all Eligible Customers on
posting on the OASIS, and (3) once a all unconstrained transmission paths
Schedule 6—Operating Reserve— discount is negotiated, details must be that go to the same point(s) of delivery
Supplemental Reserve Service immediately posted on the OASIS. For on the Transmission System.
Supplemental Reserve Service is any discount agreed upon for service on
needed to serve load in the event of a a path, from point(s) of receipt to Schedule 9—Generator Imbalance
system contingency; however, it is not point(s) of delivery, the Transmission Service
available immediately to serve load but Provider must offer the same discounted Generator Imbalance Service is
sroberts on PROD1PC70 with RULES

rather within a short period of time. transmission service rate for the same provided when a difference occurs
Supplemental Reserve Service may be time period to all Eligible Customers on between the output of a generator
provided by generating units that are all unconstrained transmission paths located in the Transmission Provider’s
on-line but unloaded, by quick-start that go to the same point(s) of delivery Control Area and a delivery schedule
generation or by interruptible load or on the Transmission System. from that generator to (1) another

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00264 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12529

Control Area or (2) a load within the or respond to transmission security Date
Transmission Provider’s Control Area constraints. Transmission Customer:
over a single hour. The Transmission For purposes of this Schedule, By:
Provider must offer this service when incremental cost and decremental cost lllllllllllllllllllll
Transmission Service is used to deliver represent the Transmission Provider’s Name
energy from a generator located within actual average hourly cost of the last 10
lllllllllllllllllllll
its Control Area. The Transmission MW dispatched to supply the
Transmission Provider’s Native Load Title
Customer must either purchase this
service from the Transmission Provider Customers, based on the replacement lllllllllllllllllllll
or make alternative comparable cost of fuel, unit heat rates, start-up Date
arrangements, which may include use of costs (including any commitment and
Specifications for Long-Term Firm Point-to-
non-generation resources capable of redispatch costs), incremental operation Point Transmission Service
providing this service, to satisfy its and maintenance costs, and purchased
1.0 Term of Transaction: llllllll
Generator Imbalance Service obligation. and interchange power costs and taxes,
To the extent the Control Area operator as applicable. Start Date: lllllllllllllll
performs this service for the Termination Date: llllllllllll
Attachment A—Form Of Service Agreement
Transmission Provider, charges to the 2.0 Description of capacity and energy to be
For Firm Point-To-Point Transmission
Transmission Customer are to reflect transmitted by Transmission Provider
Service
only a pass-through of the costs charged including the electric Control Area in which
1.0 This Service Agreement, dated as of the transaction originates.
to the Transmission Provider by that llll, is entered into, by and between
lllllllllllllllllllll
Control Area Operator. The llll (the Transmission Provider), and
Transmission Provider may charge a llll (‘‘Transmission Customer’’). 3.0 Point(s) of Receipt: lllllllll
Transmission Customer a penalty for 2.0 The Transmission Customer has been Delivering Party: lllllllllllll
either hourly generator imbalances determined by the Transmission Provider to 4.0 Point(s) of Delivery: lllllllll
have a Completed Application for Firm
under this Schedule or hourly energy Receiving Party: lllllllllllll
Point-To-Point Transmission Service under
imbalances under Schedule 4 for the the Tariff. 5.0 Maximum amount of capacity and en-
same imbalance, but not both. 3.0 The Transmission Customer has ergy to be transmitted (Reserved Capacity): l
The Transmission Provider shall provided to the Transmission Provider an 6.0 Designation of party(ies) subject to re-
establish charges for generator Application deposit in accordance with the ciprocal service obligation: llllllll
imbalance based on the deviation bands provisions of Section 17.3 of the Tariff. lllllllllllllllllllll
4.0 Service under this agreement shall
as follows: (i) Deviations within +/¥1.5 lllllllllllllllllllll
commence on the later of (l) the requested
percent (with a minimum of 2 MW) of service commencement date, or (2) the date lllllllllllllllllllll
the scheduled transaction to be applied on which construction of any Direct 7.0 Name(s) of any Intervening Systems
hourly to any generator imbalance that Assignment Facilities and/or Network providing transmission service: llllll
occurs as a result of the Transmission Upgrades are completed, or (3) such other lllllllllllllllllllll
Customer’s scheduled transaction(s) date as it is permitted to become effective by
8.0 Service under this Agreement may be
will be netted on a monthly basis and the Commission. Service under this
subject to some combination of the charges
settled financially, at the end of each agreement shall terminate on such date as
detailed below. (The appropriate charges for
mutually agreed upon by the parties.
month, at 100 percent of incremental or 5.0 The Transmission Provider agrees to individual transactions will be determined in
decremental cost, (ii) deviations greater provide and the Transmission Customer accordance with the terms and conditions of
than +/¥1.5 percent up to 7.5 percent agrees to take and pay for Firm Point-To- the Tariff.)
(or greater than 2 MW up to 10 MW) of Point Transmission Service in accordance 8.1 Transmission Charge: llllllll
the scheduled transaction to be applied with the provisions of Part II of the Tariff and lllllllllllllllllllll
hourly to any generator imbalance that this Service Agreement. 8.2 System Impact and/or Facilities Study
occurs as a result of the Transmission 6.0 Any notice or request made to or by Charge(s):
Customer’s scheduled transaction(s) either Party regarding this Service Agreement
lllllllllllllllllllll
shall be made to the representative of the
will be settled financially, at the end of other Party as indicated below. lllllllllllllllllllll
each month, at 110 percent of Transmission Provider: 8.3 Direct Assignment Facilities Charge: l
incremental cost or 90 percent of lllllllllllllllllllll lllllllllllllllllllll
decremental cost, and (iii) deviations
lllllllllllllllllllll 8.4 Ancillary Services Charges: lllll
greater than +/¥7.5 percent (or 10 MW)
lllllllllllllllllllll lllllllllllllllllllll
of the scheduled transaction to be
applied hourly to any generator Transmission Customer: lllllllllllllllllllll
imbalance that occurs as a result of the lllllllllllllllllllll lllllllllllllllllllll
Transmission Customer’s scheduled lllllllllllllllllllll lllllllllllllllllllll
transaction(s) will be settled at 125 lllllllllllllllllllll lllllllllllllllllllll
percent of incremental cost or 75 7.0 The Tariff is incorporated herein and lllllllllllllllllllll
percent of decremental cost, except that made a part hereof.
an intermittent resource will be exempt IN WITNESS WHEREOF, the Parties have Attachment A–1—Form of Service
from this deviation band and will pay caused this Service Agreement to be executed Agreement for the Resale, Reassignment or
by their respective authorized officials. Transfer of Long-Term Firm Point-to-Point
the deviation band charges for all Transmission Service
Transmission Provider:
deviations greater than the larger of 1.5
By: 1.0 This Service Agreement, dated as of
percent or 2 MW. An intermittent
lllllllllllllllllllll llll, is entered into, by and between
sroberts on PROD1PC70 with RULES

resource, for the limited purpose of this llll (the Transmission Provider), and
Schedule is an electric generator that is Name
llll (the Assignee).
not dispatchable and cannot store its lllllllllllllllllllll 2.0 The Assignee has been determined by
fuel source and therefore cannot Title the Transmission Provider to be an Eligible
respond to changes in system demand lllllllllllllllllllll Customer under the Tariff pursuant to which

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00265 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
12530 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations

the transmission service rights to be 3.0 Point(s) of Receipt: lllllllll shall be made to the representative of the
transferred were originally obtained. Delivering Party: lllllllllllll other Party as indicated below.
3.0 The terms and conditions for the Transmission Provider:
4.0 Point(s) of Delivery: lllllllll
transaction entered into under this Service lllllllllllllllllllll
Agreement shall be subject to the terms and Receiving Party: lllllllllllll
5.0 Maximum amount of reassigned capac- lllllllllllllllllllll
conditions of Part II of the Transmission
Provider’s Tariff, except for those terms and ity: lllllllllllllllllll lllllllllllllllllllll
conditions negotiated by the Reseller, as 6.0 Designation of party(ies) subject to re- Transmission Customer:
identified below, of the reassigned ciprocal service obligation: llllllll lllllllllllllllllllll
transmission capacity (pursuant to Section lllllllllllllllllllll
lllllllllllllllllllll
23.1 of this Tariff) and the Assignee and
appropriately specified in this Service lllllllllllllllllllll lllllllllllllllllllll
Agreement. Such negotiated terms and lllllllllllllllllllll 7.0 The Tariff is incorporated herein and
conditions include: contract effective and 7.0 Name(s) of any Intervening Systems made a part hereof.
termination dates, the amount of reassigned providing transmission service: llllll IN WITNESS WHEREOF, the Parties have
capacity or energy, point(s) of receipt and caused this Service Agreement to be executed
lllllllllllllllllllll
delivery. Changes by the Assignee to the by their respective authorized officials.
Reseller’s Points of Receipt and Points of 8.0 Service under this Agreement may be Transmission Provider:
Delivery will be subject to the provisions of subject to some combination of the charges
By:
Section 23.2 of this Tariff. detailed below. (The appropriate charges for
individual transactions will be determined in lllllllllllllllllllll
4.0 The Transmission Provider shall
credit or charge the Reseller, as appropriate, accordance with the terms and conditions of Name
for any difference between the price reflected the Tariff.) lllllllllllllllllllll
in the Assignee’s Service Agreement and the 8.1 Transmission Charge: llllllll Title
Reseller’s Service Agreement with the lllllllllllllllllllll lllllllllllllllllllll
Transmission Provider.
5.0 Any notice or request made to or by 8.2 System Impact and/or Facilities Study Date
either Party regarding this Service Agreement Charge(s): Transmission Customer:
shall be made to the representative of the lllllllllllllllllllll By:
other Party as indicated below. lllllllllllllllllllll lllllllllllllllllllll
Transmission Provider: 8.3 Direct Assignment Facilities Charge: l Name
lllllllllllllllllllll lllllllllllllllllllll lllllllllllllllllllll
lllllllllllllllllllll 8.4 Ancillary Services Charges: lllll Title
lllllllllllllllllllll lllllllllllllllllllll lllllllllllllllllllll
Assignee: lllllllllllllllllllll Date
lllllllllllllllllllll lllllllllllllllllllll
lllllllllllllllllllll Attachment C—Methodology To Assess
lllllllllllllllllllll
lllllllllllllllllllll Available Transfer Capability
lllllllllllllllllllll
6.0 The Tariff is incorporated herein and The Transmission Provider must include,
lllllllllllllllllllll at a minimum, the following information
made a part hereof.
IN WITNESS WHEREOF, the Parties have 9.0 Name of Reseller of the reassigned concerning its ATC calculation methodology:
caused this Service Agreement to be executed transmission capacity: (1) A detailed description of the specific
by their respective authorized officials. lllllllllllllllllllll mathematical algorithm used to calculate
Transmission Provider: firm and non-firm ATC (and AFC, if
Attachment B—Form of Service Agreement applicable) for its scheduling horizon (same
By: for Non-Firm Point-to-Point Transmission day and real-time), operating horizon (day
lllllllllllllllllllll Service ahead and pre-schedule) and planning
Name 1.0 This Service Agreement, dated as of horizon (beyond the operating horizon);
lllllllllllllllllllll llll, is entered into, by and between (2) A process flow diagram that illustrates
Title llll (the Transmission Provider), and the various steps through which ATC/AFC is
lllllllllllllllllllll llll (Transmission Customer). calculated; and
2.0 The Transmission Customer has been (3) A detailed explanation of how each of
Date determined by the Transmission Provider to the ATC components is calculated for both
Assignee: be a Transmission Customer under Part II of the operating and planning horizons.
By: the Tariff and has filed a Completed (a) For TTC, a Transmission Provider shall:
lllllllllllllllllllll Application for Non-Firm Point-To-Point (i) explain its definition of TTC; (ii) explain
Name Transmission Service in accordance with its TTC calculation methodology; (iii) list the
lllllllllllllllllllll Section 18.2 of the Tariff. databases used in its TTC assessments; and
3.0 Service under this Agreement shall be (iv) explain the assumptions used in its TTC
Title provided by the Transmission Provider upon assessments regarding load levels, generation
lllllllllllllllllllll request by an authorized representative of the dispatch, and modeling of planned and
Date Transmission Customer. contingency outages.
4.0 The Transmission Customer agrees to (b) For ETC, a transmission provider shall
Specifications for the Resale, Reassignment supply information the Transmission explain: (i) its definition of ETC; (ii) the
or Transfer of Long-Term Firm Point-to-Point Provider deems reasonably necessary in calculation methodology used to determine
Transmission Service accordance with Good Utility Practice in the transmission capacity to be set aside for
1.0 Term of Transaction: llllllll order for it to provide the requested service. native load (including network load), and
Start Date: lllllllllllllll 5.0 The Transmission Provider agrees to non-OATT customers (including, if
provide and the Transmission Customer applicable, an explanation of assumptions on
Termination Date: llllllllllll agrees to take and pay for Non-Firm Point- the selection of generators that are modeled
sroberts on PROD1PC70 with RULES

2.0 Description of capacity and energy to be To-Point Transmission Service in accordance in service); (iii) how point-to-point
transmitted by Transmission Provider includ- with the provisions of Part II of the Tariff and transmission service requests are
ing the electric Control Area in which the this Service Agreement. incorporated; (iv) how rollover rights are
transaction originates. llllllllll 6.0 Any notice or request made to or by accounted for; and (v) its processes for
lllllllllllllllllllll either Party regarding this Service Agreement ensuring that non-firm capacity is released

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00266 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Rules and Regulations 12531

properly (e.g., when real time schedules Attachment F—Service Agreement for (iii) The methodology, criteria, and
replace the associated transmission service Network Integration Transmission Service processes used to develop transmission
requests in its real-time calculations). To be filed by the Transmission Provider plans;
(c) If a Transmission Provider uses an AFC (iv) The method of disclosure of criteria,
methodology to calculate ATC, it shall: Attachment G—Network Operating assumptions and data underlying
(i) explain its definition of AFC; (ii) Agreement transmission system plans;
explain its AFC calculation methodology; To be filed by the Transmission Provider (v) The obligations of and methods for
(iii) explain its process for converting AFC customers to submit data to the transmission
into ATC for OASIS posting; (iv) list the Attachment H—Annual Transmission provider;
databases used in its AFC assessments; and Revenue Requirement for Network (vi) The dispute resolution process;
(v) explain the assumptions used in its AFC Integration Transmission Service (vii) The transmission provider’s study
assessments regarding load levels, generation 1. The Annual Transmission Revenue procedures for economic upgrades to address
dispatch, and modeling of planned and Requirement for purposes of the Network congestion or the integration of new
contingency outages. Integration Transmission Service shall be resources; and
(d) For TRM, a Transmission Provider shall llll. (viii) The relevant cost allocation
explain: (i) its definition of TRM; (ii) its TRM 2. The amount in (1) shall be effective until procedures or principles.
calculation methodology (e.g., its amended by the Transmission Provider or
assumptions on load forecast errors, forecast modified by the Commission. Attachment L—Creditworthiness Procedures
errors in system topology or distribution Attachment I—Index of Network Integration For the purpose of determining the ability
factors and loop flow sources); (iii) the Transmission Service Customers of the Transmission Customer to meet its
databases used in its TRM assessments; (iv) obligations related to service hereunder, the
the conditions under which the transmission Customer Transmission Provider may require
provider uses TRM. A Transmission Provider Date of Service Agreement reasonable credit review procedures. This
that does not set aside transfer capability for Attachment J—Procedures for Addressing review shall be made in accordance with
TRM must so state. Parallel Flows standard commercial practices and must
(e) For CBM, the Transmission Provider To be filed by the Transmission Provider specify quantitative and qualitative criteria to
shall state include a specific and self- determine the level of secured and unsecured
contained narrative explanation of its CBM Attachment K—Transmission Planning credit.
practice, including: (i) an identification of the Process The Transmission Provider may require the
entity who performs the resource adequacy The Transmission Provider shall establish Transmission Customer to provide and
analysis for CBM determination; (ii) the a coordinated, open and transparent planning maintain in effect during the term of the
methodology used to perform generation process with its Network and Firm Point-to- Service Agreement, an unconditional and
reliability assessments (e.g., probabilistic or Point Transmission Customers and other irrevocable letter of credit as security to meet
deterministic); (iii) an explanation of whether interested parties, including the coordination its responsibilities and obligations under the
the assessment method reflects a specific of such planning with interconnected Tariff, or an alternative form of security
regional practice; (iv) the assumptions used systems within its region, to ensure that the proposed by the Transmission Customer and
in this assessment; and (v) the basis for the Transmission System is planned to meet the acceptable to the Transmission Provider and
selection of paths on which CBM is set aside. needs of both the Transmission Provider and consistent with commercial practices
(f) In addition, for CBM, a Transmission its Network and Firm Point-to-Point established by the Uniform Commercial Code
Provider shall: (i) explain its definition of Transmission Customers on a comparable that protects the Transmission Provider
CBM; (ii) list the databases used in its CBM and nondiscriminatory basis. The against the risk of non-payment.
calculations; and (iii) demonstrate that there Transmission Provider’s coordinated, open Additionally, the Transmission Provider
is no double-counting of contingency outages and transparent planning process shall be must include, at a minimum, the following
when performing CBM, TTC, and TRM provided as an attachment to the information concerning its creditworthiness
calculations. Transmission Provider’s Tariff. procedures:
(g) The Transmission Provider shall The Transmission Provider’s planning (1) a summary of the procedure for
explain its procedures for allowing the use of process shall satisfy the following nine determining the level of secured and
CBM during emergencies (with an principles, as defined in the Final Rule in unsecured credit;
explanation of what constitutes an Docket No. RM05–25–000: coordination, (2) a list of the acceptable types of
emergency, the entities that are permitted to openness, transparency, information collateral/security;
use CBM during emergencies and the exchange, comparability, dispute resolution, (3) a procedure for providing customers
procedures which must be followed by the regional participation, economic planning with reasonable notice of changes in credit
transmission providers’ merchant function studies, and cost allocation for new projects. levels and collateral requirements;
and other load-serving entities when they The planning process shall also provide a (4) a procedure for providing customers,
need to access CBM). If the Transmission mechanism for the recovery and allocation of upon request, a written explanation for any
Provider’s practice is not to set aside transfer planning costs consistent with the Final Rule change in credit levels or collateral
capability for CBM, it shall so state. in Docket No. RM05–25–000. requirements;
The Transmission Provider’s planning (5) a reasonable opportunity to contest
Attachment D—Methodology for Completing process must include sufficient detail to determinations of credit levels or collateral
a System Impact Study enable Transmission Customers to requirements; and
To be filed by the Transmission Provider understand: (6) a reasonable opportunity to post
(i) The process for consulting with additional collateral, including curing any
Attachment E—Index of Point-To-Point customers and neighboring transmission non-creditworthy determination.
Transmission Service Customers providers;
Customer (ii) The notice procedures and anticipated [FR Doc. E7–3636 Filed 3–14–07; 8:45 am]
Date of Service Agreement frequency of meetings; BILLING CODE 6717–01–P
sroberts on PROD1PC70 with RULES

VerDate Aug<31>2005 18:17 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00267 Fmt 4701 Sfmt 4700 E:\FR\FM\15MRR2.SGM 15MRR2

You might also like