Professional Documents
Culture Documents
NAME
Ajay
REG. No.
214-08-11-12287-2161
Course No.
PGCM 11
Course Title
Assignment No.
Date of Dispatch
ASSIGNMENT
ON
SUBMITTED BY:
Ajay,
PGCM,
REG NO: 214-08-11-12287-2161
ASSIGNMENT:
2
ii.
ABSTRACT:
from the raw form to semi-finished and then finally in to finished state
must be planned and managed in such a way that no wastage or misuse
comes in to scene. The introduction of supply chain management in
construction is intended to integrate processes, manage interfaces
between companies in projects, reduce uncertainties and weed out
inefficiency as much as possible. The elimination of waste and in
efficiency from the supply chain builds in value in the process.
All the authorities guiding personnel at different level of construction
project should be in a perfect sync and well-coordinated. Flow of
information from the top level of management to bottom and vice-versa
must be smooth, lucid and clear avoiding any conflict and misguidance.
Manpower should be as lean as possible avoiding any over numbered
people situation at project site.
For planning, managing and executing a construction project following
key areas are the axis around which a Project manager emphasis and
concern should revolve:
Committed leadership.
Determining bottlenecks and then methods to get rid from it.
Framing guideline easy to follow.
Quality driven agenda.
Making a task schedule clearly indicating start and finish
date of project along with time taken to complete different
individual tasks at different levels and stages of project.
5
SCOPE OF WORK
The project is about construction of a housing colony for an industrial
group in Western Maharashtra along a coastal belt. Following points
must be strictly considered and followed during the start of project: Maintaining as less no. of people as possible on company rollup to
junior level.
This will cut down the cost involved in arranging and
maintaining man power.
Avoid over crowded situation on construction site.
Easy and less hectic management system.
Less controlling and monitoring required.
Supervisors below junior level will be on temporary job basis and
to be recruited locally from 100 km radius.
No accommodation is must for local workers.
Only travel arrangements can be made on demand as the
people are around 100 km radius from the work site.
6
AREA
(sq.m.)
PERSONNEL
NOS
REMARKS
120/BLOCK
Senior Executives
10
10 Bungalows
100
White Collared
Workers
100
Individual
House
80
Blue Collared
Workers
300
Individual
House
FUNCTIONS
The key function of construction Project:
PROJECT COORDINATOR
The function of a project control manager is to regularize the
work flow in the project.
He forms a planning department under which all the
essentials of the project are been maintained and recorded.
The project control manager being the head of the planning
department has to keep up the above mentioned functions. He
is assisted by:
SCHEDULERS: prepares the work flow for a project.
DOCUMENT CONTROLLERS: maintains all the records
of the project.
COST SPECIALISTS: analysis the day to day change in
field of construction financially and run the project
economically.
10
ii.
DESIGN CONSULTANT:
The design manager makes the plan and does the design of
every single member of a structure that has to come in the
project.
As for the residential project, he does prepare the layout of the
entire colony with specification of the every single
apartment and bungalow allocated as per the specification
proposed by the clients.
He prepares the drawings which provide all the essentials for
the structure.
QC INSPECTOR: He takes care in examining the quality of
the all the products from reinforcement, concrete to a completed
building.
SAFETY INSPECTORS: He assures the safe working
condition prevails in the site to all the people working in the site.
Thus he assures that the risk factors in the site are minimized and a
safe working environment is provided.
2. CONSTRUCTION MANAGER
He is the head of the execution department.
The main function of the execution department is to execute the
orders received from the planning department.
The most active post in the organization is the construction
manager since he decides upon the plans proposed on assumed
working conditions and executes them under the actual working
conditions.
11
12
SR.NO
DESIGNATION
QUALIFICATION &
EXPERIENCE
NO
Project In-Charge
Account Manager
Construction Manager
Engineers
REMARKS
From the head
of the project
nominated via
board of
members in
company
Recommended
by the project
in charge
Takes sole
responsibility
for maintain the
cash flow
control for the
entire project
Makes the
entire work
flow operations
in the project
Ensures the
project works
are done with
quality
20
13
A coordinative effort between these two divisions will ensure that the
product is ready for the execution team to deliver.
FINANCE AND MARKETING DEPARTMENT:
The team will work around the year to ensure that the required cash
flow is maintained and also to ensure that the work doesnt get
affected due to the inherent issues of managing the project.
Employees in the Manager level will ensure that the required books
are to do the book keeping and also execute the plans of the General
Managers.
The General Managers are to ensure that the plans are made keeping
in mind the vision and direction set by the project manager.
QUALITY DEPARTMENT
The Quality Team will have a structure as follows: Quality Control
Plays a very vital role in a project. Hence, it would be critical to have
a Quality Team member involved in every critical aspect of the
project.
A team member would be involved in the Planning and
Infrastructure, one team member in Architecture and one in
Execution.
15
Client
Consultant
Constructor
Needs
Design and
Management
Subcontractor
Suppliers
Fabrication
Parts production
Capacity
Material
Studies
Use
Site
Construction
Production
Thus it is very clear from the flow chart that in the field of construction
there is no unidirectional flow of orders or communication it is a must
that a for an efficient project there is a must that all should be knowing
the happenings around them so as that the problems can be discussed
18
and hurdles are overcome. So as a result the client is pleased and at the
same time the work progress is also maintained at the same ratio. As a
result for the company time efficiency is gained which at the days end
earns a lot of profit and fame for the concern.
CONCLUSIONS
The structure proposed for the organization of the knowledge based on the
Document, Processes, Elements and Basic Materials trees for a small building
company has enabled the relation to be made among Materials, services and
Suppliers. A real example was used based on the quality document obtained from
one company. Later, other documents used by the company may be included.
This will allow for the registration of the experiences. The Organized and
integrated knowledge originated from a classification structure can work as a
professional habilitation/updating tool, capable of integrating the knowledge of
the area under consideration. Moreover it can contribute to the strengthening of
the technical history of the company and work as a channel to disseminate this
knowledge of its collaborations.
The Recommendations include:
Ensuring the early involvement of the key project team member that have
expert knowledge so that an appropriate level of client satisfaction and
value can be defined.
Establishing of subcontractor a supplier relationship by selecting teams
based on value rather than lowest price.
19
BIBLOGRAPHY:
Chapter on Organization Management Koontz Odoneal McGraw Hill
Publications
Report of the Committee on the Placing and Management of Contracts
for Building and Civil Engineering Works - Banwell, H.
Modeling the Construction Process Using Plans of Work - Hughes, W
20
21