Professional Documents
Culture Documents
BUILDDINGS
05/04/2011
Tarik Al-Shemmeri
Energy Audits
Is about the What, Where, and
When energy is used
And
suggesting how this consumption
can be reduced
05/04/2011
Tarik Al-Shemmeri
Energy Audits
Energy Audit will provide:
! financial,
! operational and
! Environmental
benefits
05/04/2011
Tarik Al-Shemmeri
Energy Audits
! Financial Benefits ! Reduced fuel and electricity bills.
! Reduced operation and maintenance costs .
! Reduced capital expenditure.
05/04/2011
Tarik Al-Shemmeri
Energy Audits
! Operational Benefits ! Improved comfort levels
! Improved efficiency
! Better informed workers on global issues.
05/04/2011
Tarik Al-Shemmeri
Energy Audits
! Environmental benefits
! Reduced consumption of finite resources.
! Reduced Pollution levels.
! Improved public image.
05/04/2011
Tarik Al-Shemmeri
05/04/2011
Tarik Al-Shemmeri
05/04/2011
Tarik Al-Shemmeri
05/04/2011
Tarik Al-Shemmeri
Regression Degree
Day Figure
Energy Consumed
(GJ)
January
376
185.67
February
359
166.51
March
322
157.56
April
243
124.33
May
162
98.22
June
83
72.6
July
44
56.65
August
48
54.89
September
90
71.66
October
178
103.49
November
275
140.78
December
343
171.62
Month
05/04/2011
Tarik Al-Shemmeri
10
150
(kWh)
Energy Consumed
Regression Method
100
50
0
0
05/04/2011
100
200
Degree Day
Tarik Al-Shemmeri
300
400
11
NPI Method
The Normalised Performance Indicator
(NPI)
comparing the building s energy
consumption with similar type buildings.
05/04/2011
Tarik Al-Shemmeri
12
05/04/2011
Tarik Al-Shemmeri
13
05/04/2011
Tarik Al-Shemmeri
14
05/04/2011
Tarik Al-Shemmeri
15
05/04/2011
Tarik Al-Shemmeri
16
05/04/2011
Tarik Al-Shemmeri
17
05/04/2011
Tarik Al-Shemmeri
18
05/04/2011
Tarik Al-Shemmeri
19
05/04/2011
Tarik Al-Shemmeri
20
05/04/2011
Tarik Al-Shemmeri
21
05/04/2011
Tarik Al-Shemmeri
22
Comparisons of
performance indicators
! Good - generally have good controls and energy
management procedures, but further energy savings
are often still possible.
! Fair - reasonable controls and energy management
procedures, but significant energy savings should
achievable.
! Poor - unnecessarily high consumption and urgent
action should be taken to remedy the situation.
Substantial energy savings should result from the
introduction of energy efficiency measures.
05/04/2011
Tarik Al-Shemmeri
23
Performance Yardsticks
For Buildings
Good
Fair
Poor
Pub
<339
339 470
>470
<570
570 840
>840
Theatre
<600
600 - 900
>900
Type of Facility
05/04/2011
Tarik Al-Shemmeri
24
Savings
1. By altering the physical
construction of a building to
reduce its heat loss
eg double glazing, cavity
insulation and loft insulation.
05/04/2011
Tarik Al-Shemmeri
25
Savings
2. Replacing/upgrading the
equipment and controls
to make it more efficient.
Time switches, occupancy
switches, and Thermostat
controls.
05/04/2011
Tarik Al-Shemmeri
26
Savings
3. Shop around
for the cheapest tariff.
05/04/2011
Tarik Al-Shemmeri
27
Savings
4. Continuous monitoring
of Energy consumption.
05/04/2011
Tarik Al-Shemmeri
28
Savings
5. Using combined heat and power
(CHP) plant to provide electricity
and space heating/hot water.
05/04/2011
Tarik Al-Shemmeri
29
Case study
Tarik Al-Shemmeri
05/04/2011
30
Natural Gas
(Therm)
Electricity (kWh)
January
1578
5325
February
1400
5220
March
1309
5400
April
1000
5225
May
750
5300
June
503
5425
July
355
5330
August
350
4990
September
500
5250
October
800
5300
November
1150
5400
December
1460
4880
11,155
63,045
Month
TOTALS
Tarik Al-Shemmeri
05/04/2011
31
Gas Data
Month
Gas (Therm)
Gas (GJ)
Cost
% Cost
January
1578
166.5
760.44
14.1
February
1400
147.72
675
12.6
March
1309
138.12
631.32
11.7
April
1000
105.52
483
May
750
79.14
363
6.7
June
503
53.07
244.44
4.5
July
355
37.46
173.4
3.2
August
350
36.93
171
3.1
September
500
52.76
243
4.5
October
800
84.41
387
7.2
November
1150
121.34
555
10.3
December
1460
154.05
703.8
13.1
11,155
1177.03
5390.4
100
Totals
Tarik Al-Shemmeri
05/04/2011
32
Electricity Data
Month
Elec. (kWh)
Cost
% Cost
January
5325
429.17
8.4
February
5220
420.77
8.3
March
5400
435.77
8.6
April
5225
42.17
8.3
May
5300
427.17
8.4
June
5425
437.17
8.6
July
5330
429.57
8.5
August
4990
402.37
7.9
September
5250
423.17
8.3
October
5300
427.17
8.4
November
5400
435.17
8.6
December
4880
393.57
7.7
Totals
63,045
5081.6
100
Tarik Al-Shemmeri
05/04/2011
33
16%
N atural
G as
Electricity
84%
Tarik Al-Shemmeri
05/04/2011
34
Energy C ost
49%
51%
Tarik Al-Shemmeri
05/04/2011
N atural
G as
Electricity
35
100
50
0
J an Feb Mar Apr May J un
Tarik Al-Shemmeri
05/04/2011
36
Energy
C ost
1000
800
600
G as
()
Electricity
()
400
200
0
J an Feb Mar Apr May J un
Tarik Al-Shemmeri
05/04/2011
37
Regression Degree
Day Figure
Energy Consumed
(GJ)
January
376
185.67
February
359
166.51
March
322
157.56
April
243
124.33
May
162
98.22
June
83
72.6
July
44
56.65
August
48
54.89
September
90
71.66
October
178
103.49
November
275
140.78
December
343
171.62
1403.99
1228.83
Month
Regression data
Totals
Tarik Al-Shemmeri
05/04/2011
38
Energy Consumed
(GJ)
100
50
0
0
100
200
300
400
Tarik Al-Shemmeri
05/04/2011
39
1.
Add your quarterly or monthly use over one year for each fuel and enter below
Natural gas
Electricity
Total energy use for the year
{ Therms x 29.31
kWh x 1
= 11155 x 29.31
=326953
= 63045
=389998
kWh
kWh
kWh
kWh
kWh
kWh
kWh
C
D
E
If you cannot identify these then choose one of the following factors applied to the total energy used.
For light industrial factory building
Annual space heating energy
Annual non-space heating energy
Find the Degree Days for the energy data year = 2523
The weather correction factor = 2462/2523 = 0.976
Adjust the space heating energy to standard conditions
kWh
F
G
H
= D x G =311998x0.976=304455
Obtain the exposure factor from this chapter to suit the location of the building = 1
304455 x 1
304455
J
kWh
kWh
M / N =2000/2160
=
=
2160
0.926
Tarik Al-Shemmeri
05/04/2011
N
P
kWh
m2
kWh/m2
POOR
40
height
depth
Tarik Al-Shemmeri
05/04/2011
41
Element
U-value
W/m2K
Area
m2
Temp.
Difference (oC)
Heat loss
W
Door
18
12.5
450
Windows
5.3
42
12.5
2782
Walls
2.3
360
12.5
10350
Roof
2.6
900
12.5
29250
Floor
0.26
900
12.5
2925
Fabric heat loss = TOTAL ( Doors, Windows, Walls, Roof & Floor) 45757
Ventilation Heat Loss
= 0.335 N V T 15600
N=1.2
0
Tarik Al-Shemmeri
05/04/2011
42
Energy Efficiency
Measures
Tarik Al-Shemmeri
05/04/2011
43
Wall Insulation
Area
cost of liner board
Cost
= 2952
= 360 m2
= 8.20/m
= 360 * 8.2
Roriginal = 1/Uoriginal
= 1/2.3 = 0.4348
Rinsulation = x /k = 0.025/0.04
= 0.625
Rnew = Roriginal + Rinsulation
Unew
AUwall original = 828 W/K
AUwall new
= 0.9436 * 360
AUwall
= AU * 12.5
Saving
= 6.104 * 65.32
= 2950/398.71
= 339.7 W/K
= 6.104 kW
= 3908.71/annum
Tarik Al-Shemmeri
05/04/2011
= 7.4 years
44
Roof Insulation
Area
Cost of Rockwool
= 900 m2
= 6.40 / m2
Rnew
Unew
= 1 / 2.8846 = 0.3467
AUroof original
AUroof new
AU
Qf
Saving
= 900 x 2.6
= 900 x 0.3467
= 2340 - 312
= AU * 12.5
= 25.35 * 65.32
= 2340 W/K
= 312 W/K
= 2028 W/K
= 25.35 kW
= 1655.84/annum
= 5760/1655.84
Tarik Al-Shemmeri
05/04/2011
= 3.48 years
45